JP2000199214A - Civil engineering construction and construction method therefor - Google Patents

Civil engineering construction and construction method therefor

Info

Publication number
JP2000199214A
JP2000199214A JP10374463A JP37446398A JP2000199214A JP 2000199214 A JP2000199214 A JP 2000199214A JP 10374463 A JP10374463 A JP 10374463A JP 37446398 A JP37446398 A JP 37446398A JP 2000199214 A JP2000199214 A JP 2000199214A
Authority
JP
Japan
Prior art keywords
wall material
stones
concrete
slope
civil engineering
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
JP10374463A
Other languages
Japanese (ja)
Inventor
Isao Yukimoto
功 行本
Kiyonori Hasegawa
聖記 長谷川
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Kankyo Kogaku Co Ltd
Original Assignee
Kankyo Kogaku Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Kankyo Kogaku Co Ltd filed Critical Kankyo Kogaku Co Ltd
Priority to JP10374463A priority Critical patent/JP2000199214A/en
Publication of JP2000199214A publication Critical patent/JP2000199214A/en
Pending legal-status Critical Current

Links

Landscapes

  • Pit Excavations, Shoring, Fill Or Stabilisation Of Slopes (AREA)
  • Retaining Walls (AREA)
  • Revetment (AREA)

Abstract

PROBLEM TO BE SOLVED: To improve construction workability during the time when the civil engineering construction of wet masonry type is to be constructed, and shorten the construction period. SOLUTION: A foundation concrete 3 is provided frontward of the lower part of a slope 2, a wire gauze 5 is erected and held along the slope 2 on the foundation concrete 3, in the surface side of the wire netting 5, natural stones 9 are piled while an anchor 10 is directed to the side of the wire netting 5, the anchor 10 is penetrated into the wire netting 5 to be extended on the rear side of the wire netting 5, thereafter a part between the wire netting 5 and the slope 2 is filled with concrete to bury and fix the anchor. Thereby when the civil engineering construction of net masonry type is constructed, waiting of curing of the concrete is eliminated by packaging half or more of the natural stones 9 by the concrete.

Description

【発明の詳細な説明】DETAILED DESCRIPTION OF THE INVENTION

【0001】[0001]

【発明の属する技術分野】本発明は、土木構築物、土木
構築物の施工方法に関する。
BACKGROUND OF THE INVENTION 1. Field of the Invention The present invention relates to a civil engineering structure and a construction method of the civil engineering structure.

【0002】[0002]

【従来の技術】従来、土木構築物として、練石積みタイ
プの擁壁、護岸等が広く知られている。この練石積みタ
イプの護岸等は、法面にコンクリート層を設け、そのコ
ンクリート層に複数の石を積み上げ状態をもって該コン
クリート層表面から露出するように保持させることにな
っており、これにより、強固な護岸機能を発揮すること
ができることになっている。
2. Description of the Related Art Conventionally, as a civil engineering structure, a masonry type retaining wall, seawall, and the like are widely known. In this type of embankment type revetment, a concrete layer is provided on a slope, and a plurality of stones are stacked on the concrete layer and held so as to be exposed from the surface of the concrete layer. It is supposed to be able to demonstrate the revetment function.

【0003】[0003]

【発明が解決しようとする課題】しかし、上記練石積み
タイプの護岸等においては、各石を脱落させることなく
コンクリート層に保持するためには該各石の半分以上を
該コンクリート層により包み込まれていなければなら
ず、施工において、その状態を得るべく、コンクリート
(未硬化)により各石の半分以上を包み込む作業を行わ
なければならない。このため、その施工には、かなりの
熟練と労力とが必要となっている。しかも、施工におい
て、各石を脱落することなく積み上げるためには、各段
毎に各石を包み込んだコンクリートの養生を待たなけれ
ばならず、施工が完了するまでにはかなりの工期が必要
となっている。
However, in the above embankment type revetment, more than half of each stone is wrapped in the concrete layer in order to hold each stone in the concrete layer without falling off. In the construction, in order to obtain that condition, it is necessary to wrap half or more of each stone with concrete (unhardened). For this reason, the construction requires considerable skill and labor. Moreover, in order to pile up each stone without falling off during construction, it is necessary to wait for curing of the concrete wrapping each stone in each step, and a considerable construction period is required until the construction is completed. ing.

【0004】本発明は以上のような事情を勘案してなさ
れたもので、その技術的課題は、コンクリート層と複数
の石との組み合わせからなる練石積みタイプの土木構築
物を構築するに際しての施工作業性を向上させると共
に、その施工工期を短縮することにある。
SUMMARY OF THE INVENTION The present invention has been made in view of the above circumstances, and has a technical problem to be solved when constructing a masonry-type civil construction composed of a combination of a concrete layer and a plurality of stones. It is to improve the workability and shorten the construction period.

【0005】[0005]

【課題を解決するための手段】上記技術的課題を達成す
るために本発明(請求項1)の発明にあっては、法面の
下部前方に基礎材が設けられ、前記基礎材に壁材の下端
部が固定されて、該壁材が前記法面に対して所定間隔離
間しつつ沿うように配設され、前記壁材と前記法面との
間にコンクリート層が配設され、前記壁材の表面側に、
アンカーをそれぞれ備えた複数の石が、積み石状態をも
って該アンカーを前記壁材側に向けつつ配設され、前記
各石のアンカーが、前記壁材を貫通して前記コンクリー
ト層に埋設固定されている、ことを特徴とする土木構築
物とした構成としてある。また、請求項1の発明の好ま
しい態様としては、請求項3〜6、8の記載の通りとな
る。
In order to achieve the above technical object, according to the invention of the present invention (claim 1), a base material is provided in front of a lower part of a slope, and a wall material is provided on the base material. The lower end of the wall material is fixed, the wall material is disposed so as to follow a predetermined distance from the slope, and a concrete layer is disposed between the wall material and the slope, On the surface side of the material,
A plurality of stones each having an anchor are arranged with the stones facing the wall material side in a piled state, and the anchors of each stone are embedded and fixed in the concrete layer through the wall material. The structure is a civil engineering structure. Preferred embodiments of the first aspect of the invention are as described in the third to sixth and eighth aspects.

【0006】上記技術的課題を達成するために本発明
(請求項2)にあっては、法面の下部前方に基礎材が設
けられ、前記基礎材に壁材の下端部が固定されて、該壁
材が前記法面に対して所定間隔離間しつつ沿うように配
設され、前記壁材と前記法面との間にコンクリート層が
配設され、前記壁材の表面側に、アンカーをそれぞれ備
えた複数の石が、積み石状態をもって該アンカーを前記
壁材側に向けつつ配設され、前記各石のアンカーが、前
記壁材に連結されている、ことを特徴とする土木構築物
とした構成としてある。また、請求項2の発明の好まし
い態様としては、請求項3〜5、7、8の記載の通りと
なる。
In order to achieve the above technical object, according to the present invention (claim 2), a base member is provided in front of a lower part of a slope, and a lower end portion of a wall member is fixed to the base member. The wall material is disposed so as to be separated from the slope by a predetermined distance, a concrete layer is disposed between the wall material and the slope, and an anchor is provided on the surface side of the wall material. A plurality of stones respectively provided, with the anchors facing the wall material side in a piled state, and the anchor of each stone is connected to the wall material, There is a configuration. Preferred embodiments of the invention of claim 2 are as described in claims 3 to 5, 7, and 8.

【0007】上記技術的課題を達成するために本発明
(請求項9)にあっては、法面下部前方に壁材を、該壁
材が該法面に対して所定間隔離間しつつ沿うように起立
保持させ、次に、前記壁材の表面側において、アンカー
を備えた石を、該石のアンカーを該壁材側に向けつつ順
次、積み上げると共に、該各石のアンカーを該壁材の裏
面側に向けて貫通させ、次に、前記壁材と前記法面との
間にコンクリートを充填して、前記アンカーを埋設固定
する、ことを特徴とする土木構築物の施工方法とした構
成としてある。また、請求項9の発明の好ましい態様と
しては、請求項11〜14、16、18の記載の通りと
なる。
In order to achieve the above technical object, according to the present invention (claim 9), a wall material is provided in front of a lower part of a slope so that the wall material is separated from the slope by a predetermined distance. Then, on the surface side of the wall material, stones provided with anchors are sequentially piled up with the stone anchors facing the wall material side, and the anchors of each stone are attached to the wall material. Penetrating toward the back surface side, and then filling concrete between the wall material and the slope, and burying and fixing the anchor, as a construction method of civil engineering construction, . Preferred embodiments of the invention of claim 9 are as described in claims 11 to 14, 16, and 18.

【0008】上記技術的課題を達成するために本発明
(請求項10)にあっては、法面下部に壁材を、該壁材
が該法面に対して所定間隔離間しつつ沿うように起立保
持させ、次に、前記壁材の表面側において、アンカーを
備えた石を、該石のアンカーを該壁材側に向けつつ順
次、積み上げると共に、該各石のアンカーを該壁材に対
して連結し、次に、前記壁材と前記法面との間にコンク
リートを充填する、ことを特徴とする土木構築物の施工
方法とした構成としてある。また、請求項10の発明の
好ましい態様としては、請求項11〜14、17、18
の記載の通りとなる。
In order to achieve the above technical object, according to the present invention (claim 10), a wall material is provided below the slope so that the wall material is separated from the slope by a predetermined distance. Then, on the surface side of the wall material, stones provided with anchors are successively piled up with the stone anchors facing the wall material side, and the anchors of each stone are attached to the wall material. And connecting concrete, and then filling concrete between the wall material and the slope. In a preferred embodiment of the invention of claim 10, claims 11 to 14, 17, 18
The description is as follows.

【0009】上記技術的課題を達成するために本発明
(請求項15)にあっては、法面上にコンクリート層を
形成し、次に、前記コンクリート層に壁材を固定し、次
に、アンカーを備えた複数の石を、該壁材の表面側にお
いて、該各アンカーを介して該壁材に連結しつつ積み上
げる、ことを特徴とする土木構築物の施工方法とした構
成としてある。また、請求項15の発明の好ましい態様
としては、請求項17の記載の通りとなる。
In order to achieve the above technical object, according to the present invention (claim 15), a concrete layer is formed on a slope, and a wall material is fixed to the concrete layer. A plurality of stones having anchors are stacked on the surface side of the wall material while being connected to the wall material via the respective anchors, and the stones are piled up. Further, a preferable aspect of the invention of claim 15 is as described in claim 17.

【0010】[0010]

【発明の効果】請求項1に記載された発明によれば、法
面上をコンクリート層が覆い、そのコンクリート層と、
その表面側における複数の石及び壁材とは、アンカーが
コンクリート層に埋設固定されることに基づき、コンク
リート層と各石とが壁材を挟持する関係をもって一体化
されることになる。このため、強固な練石積みタイプの
土木構築物を得ることができることになる。また、施工
時には、壁材を起立保持させて、該壁材の表面側におい
て、該壁材(斜面)を利用することにより石を安定して
積み上げることができることになり、コンクリート層を
形成することになるコンクリート(未硬化)を、各石を
半分以上包み込むことなく、また、その養生を待つこと
なく、独立して壁材と法面との間に充填することができ
ることになる。このため、強固な練石積みタイプの土木
構築物を得つつ、その施工作業性を向上させると共に、
その施工工期を短縮することができることになる。
According to the first aspect of the present invention, a concrete layer covers the slope, and the concrete layer and
The plurality of stones and the wall material on the surface side are integrated with each other in such a manner that the concrete layer and each stone sandwich the wall material based on the anchor being embedded and fixed in the concrete layer. For this reason, it is possible to obtain a strong brickwork type civil engineering structure. Further, at the time of construction, the stone can be stably piled up by using the wall material (slope) on the surface side of the wall material by standing and holding the wall material, thereby forming a concrete layer. Concrete (unhardened) can be independently filled between the wall material and the slope without wrapping each stone in more than half and waiting for its curing. For this reason, while obtaining a strong brickwork type civil engineering structure, while improving its construction workability,
The construction period can be shortened.

【0011】請求項2に記載された発明によれば、法面
上をコンクリート層が覆い、そのコンクリート層の表面
側に複数の石が存在することになり、強固な練石積みタ
イプの土木構築物を得ることができることになる。ま
た、施工時には、壁材を起立保持させて、壁材の表面側
において、該壁材(斜面)を利用することにより石を積
み上げると共に、アンカーと壁材と連結関係に基づき、
アンカーを介して各石を壁材に保持しておくことができ
ることになり、コンクリート層を形成することになるコ
ンクリート(未硬化)を、各石を半分以上包み込むこと
なく、また、養生を待つことなく、独立して壁材と法面
との間に充填することができることになる。このため、
強固な練石積みタイプの土木構築物を得つつ、その施工
作業性を向上させると共に、その施工工期を短縮するこ
とができることになる。
According to the second aspect of the present invention, the concrete layer covers the slope, and a plurality of stones are present on the surface side of the concrete layer. You can get it. Also, at the time of construction, the wall material is raised and held, and on the surface side of the wall material, stones are piled up by using the wall material (slope), and based on the connection relationship between the anchor and the wall material,
Each stone can be held on the wall material via an anchor, and concrete (unhardened), which will form a concrete layer, must not be wrapped more than half of each stone and wait for curing. Instead, it can be filled independently between the wall material and the slope. For this reason,
The construction workability can be improved and the construction period can be shortened, while obtaining a strong brickwork type civil engineering structure.

【0012】請求項3に記載された発明によれば、壁材
が複数の壁材要素を継ぎ足すことにより構成されている
ことから、法面の大きさに応じて壁材を拡張することが
できることになり、構築すべき土木構築物の規模に簡単
に対応させることができることになる。
According to the third aspect of the present invention, since the wall material is formed by adding a plurality of wall material elements, the wall material can be expanded according to the size of the slope. This makes it possible to easily adapt to the size of the civil engineering structure to be built.

【0013】請求項4に記載された発明によれば、壁材
が格子状とされていることから、各石に備えられるアン
カーを壁材に対して挿通させて該壁材に保持させること
も、各石のアンカーを壁材に連結することも容易にでき
ることになり、施工作業性を、より向上させることがで
きることになる。しかも、施工時において、積み上げら
れた石によって、コンクリート層を形成するコンクリー
トの流動分が大量に流出することを抑制しつつ、格子状
の壁材の表面側に流出してしまったコンクリートを利用
し、その硬化を待ってその硬化コンクリート部分を壁材
に係止させ、コンクリート層と壁材とを一体化できるこ
とになる。
According to the fourth aspect of the present invention, since the wall material has a lattice shape, the anchor provided on each stone can be inserted into the wall material and held by the wall material. In addition, it is possible to easily connect the anchor of each stone to the wall material, and it is possible to further improve construction workability. In addition, at the time of construction, the concrete that has flowed out to the surface side of the grid-like wall material is used while preventing the flow of concrete forming the concrete layer from flowing out in large quantities due to the piled stones. After the hardening, the hardened concrete portion is locked to the wall material, so that the concrete layer and the wall material can be integrated.

【0014】請求項5に記載された発明によれば、壁材
が鉄筋又は金網により構成されていることから、格子状
の壁材として具体的なものをもって、上記請求項4と同
様の作用効果を得ることができることになる。
According to the fifth aspect of the present invention, since the wall material is made of a reinforcing bar or a wire mesh, the same effect as in the fourth aspect can be obtained by using a concrete lattice-like wall material. Can be obtained.

【0015】請求項6に記載された発明によれば、各石
間に詰め材が詰め込まれていることから、施工時及び施
工後において、各石の積み上げ状態を安定化することが
できることになる。しかも、壁材が、格子状等、壁材の
表面側と裏面側とを連通させる連通部分を有している場
合には、その格子状等の壁材の表側に流出したコンクリ
ート(コンクリート層が形成される前の未硬化状態のも
の)の硬化を待ってその硬化コンクリート部分を壁材に
係止させることができる一方、積み上げられた石と共
に、詰め材によって、コンクリートの流動分が大量に壁
材の表面側に流出することを効果的に抑制できることに
なる。
According to the invention described in claim 6, since the filling material is packed between the stones, the piled state of the stones can be stabilized at the time of construction and after the construction. . In addition, when the wall material has a communication portion that connects the front side and the back surface side of the wall material, such as a grid, the concrete (concrete layer flowing out) to the front side of the grid material, etc. The hardened concrete part can be locked to the wall material after the hardening of the unhardened state (before it is formed), while the pile of stones, together with the piled stones, can cause a large amount of concrete to flow into the wall. It is possible to effectively suppress the outflow to the surface side of the material.

【0016】請求項7に記載された発明によれば、各石
と壁材との間、及び該各石間に詰め材が詰め込まれてい
ることから、施工時及び施工後において、アンカーの長
さを考慮しつつ、各石と壁材との間に充填される詰め材
層に各石を当接(支持、案内)させつつ積み上げること
ができることになり、各石間の詰め材により該各石の動
きを規制することと相まって、各石の積み上げ状態の安
定化を図ることができることになる。これに伴い、アン
カーの長さをある程度長くとって壁材に対する連結作業
性を向上させることもできることになる。しかも、各石
と壁材との間に詰められる詰め材層が、多孔空間を構成
することになることから、その多孔空間を多種生物の生
息空間等として利用できることになる。
According to the invention described in claim 7, since the padding is packed between each stone and the wall material and between the stones, the length of the anchor during and after construction is set. In consideration of the size, the stones can be stacked while being in contact with (supporting and guiding) the filling material layer filled between the stones and the wall material. Combined with regulating the movement of the stones, it is possible to stabilize the piled state of each stone. Along with this, it is also possible to increase the length of the anchor to some extent to improve the workability of connection to the wall material. In addition, since the padding layer packed between each stone and the wall material constitutes a perforated space, the perforated space can be used as a habitat for various species.

【0017】請求項8に記載された発明によれば、詰め
材が植生土嚢を含むことから、植物を生育させて緑化を
図り、自然と調和した土木構築物を得ることができるこ
とになる。
According to the eighth aspect of the present invention, since the filling material contains vegetation sandbags, plants can be grown and greened, and a civil engineering structure in harmony with nature can be obtained.

【0018】請求項9に記載された発明によれば、当該
方法により、前述の請求項1に係る土木構築物を構築す
ることができることになり、強固な練石積みタイプの土
木構築物を得つつ、その施工作業性を向上させると共
に、その施工工期を短縮することができることになる。
According to the ninth aspect of the present invention, the civil engineering structure according to the first aspect can be constructed by the method. The work efficiency can be improved and the work period can be shortened.

【0019】請求項10に記載された発明によれば、当
該方法により、前述の請求項2に係る土木構築物を構築
することができることになり、強固な練石積みタイプの
土木構築物を得つつ、その施工作業性を向上させると共
に、その施工工期を短縮することができることになる。
According to the tenth aspect of the present invention, the civil engineering structure according to the second aspect can be constructed by the method. The work efficiency can be improved and the work period can be shortened.

【0020】請求項11に記載された発明によれば、当
該方法により、前記請求項4と同様の作用効果を得るこ
とができることになる。
According to the eleventh aspect of the present invention, the same effect as that of the fourth aspect can be obtained by the method.

【0021】請求項12に記載された発明によれば、石
の積み上げを所定の複数段とすると共に、前記コンクリ
ートの充填を、該所定の複数段をなす石の積み上げ高さ
までとし、これら工程を、一部分領域の施工工程として
順次繰り返すことから、片持ち状態の壁材の重量負担を
コンクリートの支えにより軽減して該壁材を変形させる
ことなく、練石積みタイプの土木構築物を確実に構築で
きることになる。
According to the twelfth aspect of the present invention, the stones are stacked in a plurality of predetermined steps, and the concrete is filled up to the stacked height of the predetermined plurality of stones. Since it is sequentially repeated as a partial area construction process, the weight burden of the cantilevered wall material is reduced by the support of the concrete and the wall material is not deformed, and it is possible to reliably construct a masonry type civil engineering structure. Become.

【0022】請求項13に記載された発明によれば、新
たな施工工程への移行を、該新たな施工工程前に充填さ
れたコンクリートの養生を待って行うことから、養生さ
れたコンクリートが壁材を支えることになり、片持ち状
態の壁材を変形させることなく、練石積みタイプの土木
構築物をより確実に構築できることになる。
According to the thirteenth aspect of the present invention, the transition to the new construction step is performed after the concrete filled before the new construction step is cured. Since the timber is supported, it is possible to more reliably construct a masonry-type civil engineering structure without deforming the cantilevered wall material.

【0023】請求項14に記載された発明によれば、石
及びコンクリートが壁材の上端部付近に至ったとき、該
壁材の上端部に該壁材を構成するべき壁材要素を新たに
継ぎ足すことから、該壁材を確実に上方に向けて拡張す
ることができることになり、構築すべき土木構築物の規
模に対応させることができることになる。
According to the fourteenth aspect of the present invention, when the stone and the concrete reach the vicinity of the upper end of the wall material, a wall material element to constitute the wall material is newly added to the upper end of the wall material. By adding, the wall material can be reliably expanded upward, and can be adapted to the scale of the civil engineering structure to be constructed.

【0024】請求項15に記載された発明によれば、法
面上をコンクリート層が覆い、そのコンクリート層に対
して、壁材及び該壁材に連結された各石が一体化するこ
とになり、強固な練石積みタイプの土木構築物を得るこ
とができることになる。また、施工時には、コンクリー
ト層(硬化したもの)の形成、壁材の敷設固定、各石の
連結の順に、施工が行われることになり、コンクリート
層を形成することになるコンクリート(未硬化)によっ
て各石を半分以上包み込むことも、また、そのコンクリ
ートの養生を待つことも必要はなくなる。このため、当
該方法により、強固な練石積みタイプの土木構築物を得
つつ、その施工作業性を向上させると共に、その施工工
期を短縮することができることになる。しかも、硬化し
たコンクリート層に壁材を固定することから、特に、法
面下部前方における基礎材に壁材を固定する必要はなく
なる。
According to the fifteenth aspect of the present invention, the concrete layer covers the slope, and the wall material and each stone connected to the wall material are integrated with the concrete layer. As a result, it is possible to obtain a strong brickwork type civil engineering structure. In addition, at the time of construction, construction will be performed in the order of formation of concrete layer (hardened), laying and fixing of wall material, connection of each stone, and concrete (uncured) that will form concrete layer There is no need to wrap each stone more than half and wait for the concrete to cure. For this reason, by this method, while obtaining a strong brickwork type civil engineering structure, the workability of the work can be improved and the work period can be shortened. Moreover, since the wall material is fixed to the hardened concrete layer, it is not necessary to fix the wall material to the foundation material in front of the lower part of the slope.

【0025】請求項16に記載された発明によれば、石
を壁材の表面側において積み上げるに際して、各石間に
詰め材を詰め込むことから、当方法により、前記請求項
6と同様の作用効果を得ることができることになる。
According to the sixteenth aspect of the present invention, when the stones are stacked on the surface side of the wall material, the padding material is packed between the stones. Can be obtained.

【0026】請求項17に記載された発明によれば、石
を壁材の表面側において積み上げるに際して、各石間、
及び各石と該壁材との間に詰め材を詰めることから、当
方法により、前記請求項7と同様の作用効果を得ること
ができることになる。
According to the invention as set forth in claim 17, when the stones are stacked on the surface side of the wall material, the distance between each stone,
In addition, since the filling material is filled between each stone and the wall material, the same operation and effect as those of the seventh aspect can be obtained by this method.

【0027】請求項18に記載された発明によれば、コ
ンクリートの充填に先立ち、壁材の表面に、コンクリー
トの流動分の流動を抑制するシートを敷設することか
ら、各石によるだけでなくシートによっても、コンクリ
ートが壁材の表面側に大量に流出することを抑制できる
ことになり、コンクリート層を的確に形成できることに
なる。
According to the eighteenth aspect of the present invention, prior to the filling of the concrete, the sheet for suppressing the flow of the concrete is laid on the surface of the wall material. Accordingly, it is possible to suppress a large amount of concrete from flowing out to the surface side of the wall material, and it is possible to accurately form a concrete layer.

【0028】[0028]

【発明の実施の形態】以下、本発明の実施形態について
図面に基づいて説明する。図1は第1実施形態に係る練
石積みタイプの護岸(土木構築物)1である。この護岸
1においては、法面2の下部前方に基礎材としての基礎
コンクリート3が設けられており、その基礎コンクリー
ト3の上面は、法面2に対して略直角となるべく、該法
面2に近づくに従って下方に向かうように傾斜されてい
る。この基礎コンクリート3の上面には、溝4が形成さ
れており、その溝4は、比較的深い深さをもって護岸1
の延設方向(図1の紙面に直交方向)に延ばされてい
る。
Embodiments of the present invention will be described below with reference to the drawings. FIG. 1 shows a stonewall type seawall (civil engineering structure) 1 according to the first embodiment. In this revetment 1, a foundation concrete 3 as a base material is provided in front of a lower part of the slope 2, and the upper surface of the foundation concrete 3 is attached to the slope 2 so as to be substantially perpendicular to the slope 2. It is inclined so that it goes downward as it approaches. A groove 4 is formed on the upper surface of the foundation concrete 3, and the groove 4 has a relatively deep seawall 1
(In the direction orthogonal to the plane of FIG. 1).

【0029】前記基礎コンクリート3の溝4には、図1
に示すように、壁材としての金網5の下端部が嵌合保持
されている。この金網5は、溝4への嵌合保持に基づ
き、その網面が法面2に対して所定間隔離間しつつ、そ
の法面2に沿うように起立されており、金網5と法面2
との間には、所定長さの空間6が形成されることになっ
ている。この場合、基礎コンクリート3に対する金網5
下端部の保持は、別の固定手段により、さらに補強して
おくことが好ましい。この金網5は、既知の如く網目を
有しており、その強度としては、上下方向に複数段に亘
って自然石を積み上げても変形しない(撓まない)もの
が用いられている。
The grooves 4 of the foundation concrete 3 are
As shown in FIG. 5, the lower end of the wire mesh 5 as the wall material is fitted and held. The wire mesh 5 is erected along the slope 2 while keeping its mesh surface separated from the slope 2 by a predetermined distance based on the fitting and holding in the groove 4.
A space 6 having a predetermined length is to be formed therebetween. In this case, the wire mesh 5 for the foundation concrete 3
It is preferable that the holding of the lower end portion is further reinforced by another fixing means. The wire netting 5 has a mesh as is known, and its strength is such that it does not deform (do not bend) even when natural stones are stacked in a plurality of stages in the vertical direction.

【0030】前記金網5の表面上には、図1に示すよう
に、ネット(シート)7が敷設されている(図4におい
ては、一部のみ図示)。このネット7は、金網5の網目
よりも細かい目を有し、後述のコンクリート層8を形成
するコンクリートの流動分(コンクリート、砂等)が、
金網5の表面側に過剰に流れ込むことを抑制することを
目的とするものであり、このネット7の他に、不織布等
が用いられる。
As shown in FIG. 1, a net (sheet) 7 is laid on the surface of the wire netting 5 (only a part is shown in FIG. 4). The net 7 has a finer mesh than the mesh of the wire mesh 5, and the fluidity (concrete, sand, etc.) of the concrete forming the concrete layer 8 described later is:
The purpose is to suppress excessive flow into the surface side of the wire mesh 5, and in addition to the net 7, a nonwoven fabric or the like is used.

【0031】前記金網5の表面上には、図1に示すよう
に、ネット7を介して複数の自然石(石)9が積み上げ
られている(図1の紙面直交方向にも複数の自然石9が
配設されている(図4参照))。各自然石9は、アンカ
ー10を一体的に備えており、そのアンカー10は、自
然石9から一定長さだけ離間するように延び、その先端
部は、カール状に巻かれている。この各自然石9は、金
網5の傾斜面を利用して、アンカー10を該金網5側に
向けつつ積み上げられており、その各自然石9のアンカ
ー10は、ネット7の表面側から該各自然石9が金網5
の網面に当接することになるまで、該ネット7、金網5
の網目を貫通して、金網5の裏面側における空間6へと
延びた状態となっている。
As shown in FIG. 1, a plurality of natural stones (stones) 9 are stacked on the surface of the wire mesh 5 via a net 7 (a plurality of natural stones 9 are also arranged in a direction perpendicular to the plane of FIG. 1). 9 (see FIG. 4). Each natural stone 9 is integrally provided with an anchor 10, and the anchor 10 extends so as to be separated from the natural stone 9 by a certain length, and a tip end portion thereof is curled. The natural stones 9 are piled up using the inclined surface of the wire mesh 5 with the anchors 10 facing the wire mesh 5 side, and the anchors 10 of the natural stones 9 are stacked from the surface side of the net 7. Natural stone 9 is wire mesh 5
The net 7 and the wire mesh 5 until they come into contact with the mesh surface of
And has extended to the space 6 on the back side of the wire mesh 5.

【0032】前記ネット7の表面には、図4に示すよう
に、前記各自然石9間において、詰め材11が詰められ
ている。この詰め材11は、各自然石9の動きを規制し
て、該各自然石9を安定な積み上げ状態とするものであ
り、この詰め材11としては、割栗石、植生土嚢等が用
いられる。特に詰め材として、植生土嚢を用いた場合に
は、上記機能の他に、植物の生育を可能として、緑化を
促進することができることになる。この場合、各自然石
9間には、詰め材11を詰めても、十分な空間(間隙)
が確保されており、その空間は、植物、生物等の生育、
生息空間として利用されることになっている。
As shown in FIG. 4, a filling material 11 is packed between the natural stones 9 on the surface of the net 7. The stuffing material 11 regulates the movement of each natural stone 9 so that the natural stones 9 are stably stacked. As the stuffing material 11, cracking stone, vegetation sandbags, or the like is used. In particular, when a vegetation sandbag is used as the filling material, in addition to the above functions, it is possible to grow plants and promote greening. In this case, a sufficient space (gap) can be provided between the natural stones 9 even if the packing material 11 is packed.
Is secured, and the space is used for the growth of plants, organisms, etc.
It is to be used as a habitat.

【0033】前記金網5と前記法面2との間には、図1
に示すように、コンクリート層8が設けられている。こ
のコンクリート層8は、金網5と法面2との間にコンク
リート(未硬化コンクリート)を充填することにより形
成されており、コンクリート層8は、基礎コンクリート
3上において、金網5と法面2との間の長さに相当する
比較的厚い厚みをもって、法面2に沿って延びている。
このコンクリート層8内には、各自然石9のアンカー1
0が埋設され、そのアンカー10のカール状先端部とコ
ンクリート層8との係合関係によりアンカー10がコン
クリート層8から抜けないようになっており、これによ
り、各自然石9とコンクリート層8とが金網5を挟持
し、各自然石9、金網5及びコンクリート層8は、一体
化することになっている。図1中、符号12は、天端コ
ンクリートを示す。
As shown in FIG. 1 between the wire mesh 5 and the slope 2
As shown in FIG. 1, a concrete layer 8 is provided. The concrete layer 8 is formed by filling concrete (unhardened concrete) between the wire mesh 5 and the slope 2, and the concrete layer 8 is formed on the foundation concrete 3 by the wire mesh 5 and the slope 2. And extends along the slope 2 with a relatively large thickness corresponding to the length between them.
In this concrete layer 8, the anchor 1 of each natural stone 9
0 is buried, and the anchor 10 is prevented from falling out of the concrete layer 8 due to the engagement relationship between the curled tip of the anchor 10 and the concrete layer 8. Sandwiches the wire mesh 5, and each natural stone 9, wire mesh 5 and concrete layer 8 are to be integrated. In FIG. 1, reference numeral 12 denotes a top concrete.

【0034】次に、上記練石積みタイプの護岸1(擁
壁)の施工方法について説明する。先ず、法面2の下部
前方に基礎コンクリート3を形成する。自然石9の積み
上げ土台、コンクリート層8の支持土台として機能させ
ると共に、金網5の起立保持手段として用いるためであ
る。
Next, a method of constructing the above-described stone-mason type revetment 1 (retaining wall) will be described. First, the foundation concrete 3 is formed at the lower front of the slope 2. This is because it functions as a base for stacking the natural stones 9 and a support for the concrete layer 8 and as a means for holding the wire mesh 5 upright.

【0035】次に、図2に示すように、金網5の下端部
を基礎コンクリート3に嵌合保持させる。金網5を起立
保持させて、自然石9の積み上げに際しての案内面(支
持面)を確保すると共に、コンクリート充填空間6とを
確保するためである。
Next, as shown in FIG. 2, the lower end of the wire mesh 5 is fitted and held on the foundation concrete 3. This is because the wire mesh 5 is raised and held to secure a guide surface (support surface) for stacking the natural stones 9 and a concrete filling space 6.

【0036】次に、上記金網5の表面にネット7を敷い
た後、図3に示すように、そのネット7(金網5)を案
内面、支持面として、自然石9を1〜複数段(例えば3
段)積み上げる。自然石の積み上げにおいて、自然石9
を金網5全体に一挙に積み上げるのではなく1〜複数段
積み上げるのは、片持ち状態の金網5が変形するのを防
止するためである。また、ネット7(金網5)を自然石
9の積み上げのための案内面、支持面として利用するの
は、一定とされた適正な積み上げ傾斜の下である程度安
定した積み上げ状態を得るためである。この場合、該各
自然石9のアンカー10は、ネット7、金網5の網目を
貫通されて金網5の裏面側の空間6に延ばされ、各自然
石9がネット7を介して金網5に当接されることになっ
ており、これにより、各自然石9は、金網5の斜面を支
持面、案内面として、ある程度安定な積み上げ状態とさ
れるだけでなく、仮に、自然石9の積み上げ中、その積
み上げ状態が崩れたとしても、アンカー10が金網5の
線材に係合することになり、自然石9が法面2下部の法
尻まで崩れ落ちることはないようになっている。このた
め、この金網5とアンカー10との係合関係に基づいて
自然石9の積み上げ状態の安定性を高める場合には、金
網5の網目をできるだけ小さくするのが好ましい。尚、
このアンカー10を備えた自然石9は、アンカー10の
カール状の先端部を利用し、その複数がクレーン等をも
って所定の施工場所に吊り上げ搬送される。
Next, after the net 7 is laid on the surface of the wire mesh 5, as shown in FIG. 3, the net 7 (wire mesh 5) is used as a guide surface and a support surface, and one or more natural stones 9 are used. For example, 3
Stack up). In the pile of natural stone, natural stone 9
The reason that the wire meshes 5 are not stacked all at once but are stacked one to a plurality of times is to prevent the wire mesh 5 in a cantilever state from being deformed. The reason why the net 7 (wire mesh 5) is used as a guide surface and a support surface for stacking the natural stones 9 is to obtain a somewhat stable stacking state under a constant and appropriate stacking inclination. In this case, the anchor 10 of each natural stone 9 is penetrated through the mesh of the net 7 and the wire mesh 5 and extended to the space 6 on the back side of the wire mesh 5, and each natural stone 9 is connected to the wire mesh 5 through the net 7. As a result, each natural stone 9 is not only stably piled up to some extent using the slope of the wire mesh 5 as a support surface and a guide surface, but also temporarily piles up the natural stone 9. Even if the piled state collapses, the anchor 10 will engage with the wire of the wire mesh 5 and the natural stone 9 will not fall down to the bottom of the slope 2. Therefore, in order to increase the stability of the piled state of the natural stones 9 based on the engagement relationship between the wire mesh 5 and the anchor 10, it is preferable to make the mesh of the wire mesh 5 as small as possible. still,
A plurality of natural stones 9 having the anchors 10 are lifted and conveyed to a predetermined construction site by using a crane or the like by using the curled tip of the anchor 10.

【0037】次に、図1に示すように、各自然石9間に
詰め材11を詰める。各自然石9の動きを規制して、自
然石9の積み上げ状態の安定性を高めるためである。こ
の場合、前述した如く、詰め材11として、割栗石、植
生土嚢等を用いることができるが、植生土嚢を用いた場
合には、自然石9の積み上げ状態の安定化を図ることが
できるだけでなく、植物の生育を可能として、緑化を促
進することができることになる。
Next, as shown in FIG. 1, a filling material 11 is packed between the natural stones 9. This is because the movement of each natural stone 9 is regulated to enhance the stability of the stacked state of the natural stones 9. In this case, as described above, cracking stone, vegetation sandbags, and the like can be used as the filling material 11, but when vegetation sandbags are used, not only can the stuck state of the natural stones 9 be stabilized, but also Therefore, plant growth can be enabled and greening can be promoted.

【0038】次に、図3に示すように、金網5と法面2
と間の空間6にコンクリート(図3においては、コンク
リート層8をもって示す)を充填する。法面2上にコン
クリート層8を形成するためである。この場合、コンク
リートは、型枠を金網5の裏側にセットした後、充填さ
れ、その充填は、自然石9が積み上げられた高さまで行
われる。ネット7だけでなく自然石9をも利用して、コ
ンクリートが金網5の表面側に大量に流出することを抑
制するため、積み上げられた自然石9の高さに対応させ
たのである。一方、流出してしまったコンクリートにつ
いては、その硬化を待ってその硬化部分が金網5に(金
網の構成線材を包み込むようにして)係止されることに
なり、その硬化部分は、金網5とコンクリート層8とを
一体化するために利用される。勿論この場合、コンクリ
ートの充填は、コンクリートの注入後、バイブレータ等
を用いて、均一となるように打設される。
Next, as shown in FIG.
Is filled with concrete (shown by a concrete layer 8 in FIG. 3). This is because the concrete layer 8 is formed on the slope 2. In this case, the concrete is filled after setting the formwork on the back side of the wire mesh 5, and the filling is performed up to the height at which the natural stones 9 are stacked. In order to prevent a large amount of concrete from flowing out to the surface side of the wire mesh 5 using not only the net 7 but also the natural stones 9, the concrete stones 9 correspond to the height of the piled natural stones. On the other hand, as for the concrete that has flowed out, the hardened portion is locked to the wire mesh 5 (to wrap the wire material of the wire mesh) after the hardening thereof, and the hardened portion is connected to the wire mesh 5. It is used for integrating with the concrete layer 8. In this case, of course, the concrete is filled uniformly after the concrete is poured by using a vibrator or the like.

【0039】また、上記のように、金網5と法面2との
間にコンクリートが充填されると、コンクリートは、各
自然石9から延びているアンカー10を包み込むことに
なる。これにより、そのコンクリートの硬化後、アンカ
ー10のカール状先端部とその硬化後のコンクリートと
が係止され、各自然石9は、コンクリート層8と協働し
て金網5を挟持しつつコンクリート層8に固定されるこ
とになる。
When concrete is filled between the wire mesh 5 and the slope 2 as described above, the concrete wraps the anchors 10 extending from the respective natural stones 9. As a result, after the concrete is hardened, the curled tip of the anchor 10 and the hardened concrete are locked, and each natural stone 9 cooperates with the concrete layer 8 while holding the wire mesh 5 therebetween. 8 will be fixed.

【0040】このような複数段の自然石9の積み上げか
らコンクリートの充填までの一連の工程は、部分領域の
施工工程として、繰り返され、そのような施工は、天端
に達するまで行われる。法面2全体に練石積みタイプの
施工を行うためである。この場合、新たな施工工程は、
その前の施工工程におけるコンクリートの養生(硬化)
を待って始められる。硬化コンクリートによって金網5
を支え、片持ち状態の金網5の変形(撓み)を確実に防
止するためである。尚、このような施工において、法面
2が大きいために金網5の長さが足りなくなった場合に
は、新たな金網5が溶接等により継ぎ足される。
A series of steps from the stacking of the natural stones 9 in a plurality of stages to the filling of the concrete are repeated as a partial area construction step, and such construction is performed until the top is reached. This is for performing a masonry type construction on the entire slope 2. In this case, the new construction process
Curing (hardening) of concrete in the previous construction process
I can wait and start. Wire mesh 5 by hardened concrete
To reliably prevent deformation (bending) of the wire mesh 5 in the cantilevered state. In such a construction, if the length of the wire mesh 5 becomes insufficient due to the large slope 2, a new wire mesh 5 is added by welding or the like.

【0041】上記部分領域の施工が繰り返されて、施工
が天端にまで達すると、天端コンクリート12が打設さ
れ、全工程を終える。
When the construction of the partial area is repeated and the construction reaches the top, the top concrete 12 is poured and the entire process is completed.

【0042】したがつて、上記第1実施形態において
は、最終的に強固な練石積みタイプの土木構築物を得る
ことができることは勿論、施工において、金網5(斜
面)、詰め材11、アンカー10等を利用することによ
り自然石9を安定して積み上げることができることにな
り、コンクリート(未硬化)を、各石を半分以上包み込
むことなく、また、その養生を待つことなく、独立して
金網5と法面2との間に充填することができることにな
る。このため、施工作業性を向上させると共に、その施
工工期を短縮することができることになる。
Therefore, in the first embodiment, not only can a strong brickwork type civil engineering structure be finally obtained, but also the wire mesh 5 (slope), the filling material 11, the anchor 10, etc. The natural stone 9 can be stably piled up by using the concrete, and the concrete (uncured) is independently wrapped with the wire mesh 5 without wrapping each stone more than half and waiting for its curing. It can be filled between the slope 2. For this reason, while improving workability | operativity, it will be possible to shorten the work period.

【0043】図5は第2実施形態を示すものである。こ
の第2実施形態において、前記1実施形態と同一構成要
素については同一符号を付してその説明を省略する。
FIG. 5 shows a second embodiment. In the second embodiment, the same components as those in the first embodiment are denoted by the same reference numerals, and description thereof is omitted.

【0044】この第2実施形態においては、積み上げ状
態の各自然石9におけるアンカー10が、金網5に貫通
されるのではなく、そのアンカー10の先端部が連結具
(ワイヤー等の結束具、シャックル等の連結金具)によ
り金網5に連結されている。このような各自然石9にお
いては、その各間に詰め材11として割栗石が詰め込ま
れているだけでなく、各自然石9と金網5との間に、詰
め材11として割栗石が充填されて詰め材層13が形成
されている。これは、詰め材層13の表面に各自然石9
を当接させて該各自然石9を該詰め材層13によって案
内、支持すると共に、その詰め材層13内の多孔空間を
種々の生物の生息空間として利用するためである。ま
た、本実施形態においては、金網5に係止具14が備え
られており、その係止具14はコンクリート層8内に埋
設されている。これにより、金網5は、コンクリート層
8との係止関係に基づき一体化されている。
In the second embodiment, the anchors 10 of the natural stones 9 in the piled state are not penetrated by the wire mesh 5, but the ends of the anchors 10 are connected by a connecting tool (a binding tool such as a wire, a shackle). Are connected to the wire net 5. In each of the natural stones 9, not only the split stone as the filling material 11 is packed between each of the natural stones 9, but also the split stone as the filling material 11 between each natural stone 9 and the wire mesh 5. The filling material layer 13 is formed. This is because each natural stone 9
Are brought into contact with each other to guide and support the natural stones 9 by the filler layer 13, and to use the porous space in the filler layer 13 as a habitat for various living things. In the present embodiment, the wire mesh 5 is provided with a locking tool 14, and the locking tool 14 is embedded in the concrete layer 8. Thereby, the wire mesh 5 is integrated based on the locking relationship with the concrete layer 8.

【0045】この第2実施形態における施工方法は、前
記第1実施形態と基本的に同様な内容となっており、先
ず、基礎コンクリート3に対して金網5が起立保持させ
られ、次に、金網5の表面側において、上記特有の内容
を加味した積み上げ作業等が行われ、次に、金網5と法
面2との間にコンクリートを充填されることになってい
る。
The construction method according to the second embodiment has basically the same contents as the first embodiment. First, the wire mesh 5 is erected on the foundation concrete 3, and then the wire mesh is On the surface side of 5, a stacking operation or the like taking into account the above-mentioned specific contents is performed, and then concrete is filled between the wire mesh 5 and the slope 2.

【0046】第2実施形態の変形例として、構造が第2
実施形態と同じであるが、その施工方法を異ならせても
よい。すなわち、先ず、法面2にコンクリート層8(硬
化状態))を形成し、そのコンクリート層8にアンカー
を介して金網5を敷設固定し、その金網5に各自然石9
のアンカー10を連結具を介して連結すると共に、その
各自然石9と金網5との間に詰め材11により詰め材層
13を形成してもよい。これにより、前記第2実施形態
と同様の作用効果を得ることができるばかりか、硬化し
ているコンクリート層8に金網5を固定するため、金網
5を基礎コンクリート3に起立保持させる必要はなくな
る。
As a modification of the second embodiment, the structure is the second
Although it is the same as the embodiment, the construction method may be different. That is, first, a concrete layer 8 (hardened state) is formed on the slope 2, a wire mesh 5 is laid on the concrete layer 8 via an anchor, and each natural stone 9 is attached to the wire mesh 5.
The anchor 10 may be connected via a connecting tool, and the filler layer 13 may be formed between the natural stone 9 and the wire mesh 5 by the filler 11. Thereby, not only the same operation and effect as in the second embodiment can be obtained, but also the wire mesh 5 is fixed to the hardened concrete layer 8, so that the wire mesh 5 does not need to be erected on the foundation concrete 3.

【0047】以上実施形態について説明したが本発明に
おいては、次のようなものを包含する。 (1)石として、自然石9の他に、擬石を用いること。 (2)金網5に代えて、鉄筋(鉄筋金網等)を用いるこ
と。 (3)上下方向に延びる鉄筋等を横方向に順次、並べる
等、種々の態様の構成をもって壁材を形成して、コンク
リート層と、積み上げられた石層とを区画すること。勿
論この場合において、壁材の連通性がよすぎる場合(隙
間、孔等の占める割合が大きい場合)には、硬化前のコ
ンクリートが流出することを抑制する意味から、ネット
7等のシートを壁材表面に敷設することが好ましい。 (4)壁材(線材、板体等)を樹脂製とすること。
Although the embodiments have been described above, the present invention includes the following. (1) As a stone, besides the natural stone 9, a pseudo stone is used. (2) Instead of the wire mesh 5, a reinforcing bar (such as a reinforcing wire mesh) is used. (3) The concrete layer and the stacked stone layers are formed by forming wall materials in various modes such as arranging reinforcing bars and the like extending in the vertical direction sequentially in the horizontal direction. Of course, in this case, if the continuity of the wall material is too good (when the ratio of the gaps, holes, etc. is large), the sheet such as the net 7 is wall-mounted to prevent the uncured concrete from flowing out. It is preferable to lay on the surface of the material. (4) The wall material (wire, plate, etc.) is made of resin.

【0048】尚、本発明の目的は、明記されたものに限
らず、実質的に好ましい或は利点として記載されたもの
に対応したものを提供することをも暗黙的に含むもので
ある。
It should be noted that the object of the present invention is not limited to what is explicitly stated, but also implicitly includes providing what substantially corresponds to what is described as preferred or advantageous.

【図面の簡単な説明】[Brief description of the drawings]

【図1】第1実施形態に係る護岸を示す説明図。FIG. 1 is an explanatory view showing a revetment according to a first embodiment.

【図2】第1実施形態に係る護岸の施工工程を示す図。FIG. 2 is a view showing a construction process of a revetment according to the first embodiment.

【図3】図2の続きを示す施工工程を示す図。FIG. 3 is a view showing a construction step that is continued from FIG. 2;

【図4】各自然石間に詰められる詰め材の状態を金網の
裏側から見た図。
FIG. 4 is a view of a state of a filling material packed between natural stones, as viewed from the back side of a wire mesh.

【図5】第2実施形態に係る護岸を示す説明図。FIG. 5 is an explanatory view showing a revetment according to a second embodiment.

【符号の説明】[Explanation of symbols]

1 護岸 2 法面 3 基礎コンクリート 5 金網 6 空間 7 ネット 8 コンクリート層 9 自然石 10 アンカー 11 詰め材 13 詰め材層 DESCRIPTION OF SYMBOLS 1 Revetment 2 Slope 3 Foundation concrete 5 Wire mesh 6 Space 7 Net 8 Concrete layer 9 Natural stone 10 Anchor 11 Packing material 13 Packing material layer

Claims (18)

【特許請求の範囲】[Claims] 【請求項1】 法面の下部前方に基礎材が設けられ、 前記基礎材に壁材の下端部が固定されて、該壁材が前記
法面に対して所定間隔離間しつつ沿うように配設され、 前記壁材と前記法面との間にコンクリート層が配設さ
れ、 前記壁材の表面側に、アンカーをそれぞれ備えた複数の
石が、積み石状態をもって該アンカーを前記壁材側に向
けつつ配設され、 前記各石のアンカーが、前記壁材を貫通して前記コンク
リート層に埋設固定されている、ことを特徴とする土木
構築物。
1. A base material is provided in front of a lower part of a slope, a lower end of a wall material is fixed to the base material, and the wall material is arranged so as to be separated from the slope by a predetermined distance. A concrete layer is disposed between the wall material and the slope, a plurality of stones each having an anchor are provided on the surface side of the wall material, and the anchor is stacked in a piled state and the anchor is attached to the wall material side. The civil engineering structure, wherein the anchors of the respective stones penetrate the wall material and are embedded and fixed in the concrete layer.
【請求項2】 法面の下部前方に基礎材が設けられ、 前記基礎材に壁材の下端部が固定されて、該壁材が前記
法面に対して所定間隔離間しつつ沿うように配設され、 前記壁材と前記法面との間にコンクリート層が配設さ
れ、 前記壁材の表面側に、アンカーをそれぞれ備えた複数の
石が、積み石状態をもって該アンカーを前記壁材側に向
けつつ配設され、 前記各石のアンカーが、前記壁材に連結されている、こ
とを特徴とする土木構築物。
2. A base material is provided in front of a lower part of a slope, and a lower end of a wall material is fixed to the base material, and the wall material is arranged so as to be separated from the slope by a predetermined distance. A concrete layer is disposed between the wall material and the slope, a plurality of stones each having an anchor are provided on the surface side of the wall material, and the anchor is stacked in a piled state and the anchor is attached to the wall material side. The civil engineering structure, wherein the anchor of each stone is connected to the wall material.
【請求項3】 請求項1又は2において、 前記壁材が、複数の壁材要素を継ぎ足すことにより構成
されている、ことを特徴とする土木構築物。
3. The civil engineering structure according to claim 1, wherein the wall material is formed by adding a plurality of wall material elements.
【請求項4】 請求項1又は2において、 前記壁材が格子状とされている、ことを特徴とする土木
構築物。
4. The civil engineering structure according to claim 1, wherein the wall material has a lattice shape.
【請求項5】 請求項4において、 前記壁材が鉄筋又は金網により構成されている、ことを
特徴とする土木構築物。
5. The civil engineering structure according to claim 4, wherein the wall material is made of a reinforcing bar or a wire mesh.
【請求項6】 請求項1において、 前記各石間に、詰め材が詰め込まれている、ことを特徴
とする土木構築物。
6. The civil engineering structure according to claim 1, wherein a filling material is packed between the stones.
【請求項7】 請求項2において、 前記各石と前記壁材との間、及び該各石間に詰め材が詰
め込まれている、ことを特徴とする土木構築物。
7. The civil engineering structure according to claim 2, wherein a padding material is packed between each of the stones and the wall material and between the stones.
【請求項8】 請求項6又は7において、 前記詰め材が植生土嚢を含む、ことを特徴とする土木構
築物。
8. The civil engineering structure according to claim 6, wherein the padding material includes vegetation sandbags.
【請求項9】 法面下部前方に壁材を、該壁材が該法面
に対して所定間隔離間しつつ沿うように起立保持させ、 次に、前記壁材の表面側において、アンカーを備えた石
を、該石のアンカーを該壁材側に向けつつ順次、積み上
げると共に、該各石のアンカーを該壁材の裏面側に向け
て貫通させ、 次に、前記壁材と前記法面との間にコンクリートを充填
して、前記アンカーを埋設固定する、ことを特徴とする
土木構築物の施工方法。
9. A wall material is stood upright and held in front of a lower part of the slope so that the wall material is separated from the slope by a predetermined distance, and an anchor is provided on the surface side of the wall material. The stones are sequentially piled up while the anchors of the stones are directed toward the wall material, and the anchors of the respective stones are penetrated toward the back side of the wall material. A method for constructing a civil engineering structure, wherein concrete is filled in between them and the anchor is buried and fixed.
【請求項10】 法面下部前方に壁材を、該壁材が該法
面に対して所定間隔離間しつつ沿うように起立保持さ
せ、 次に、前記壁材の表面側において、アンカーを備えた石
を、該石のアンカーを該壁材側に向けつつ順次、積み上
げると共に、該各石のアンカーを該壁材に対して連結
し、 次に、前記壁材と前記法面との間にコンクリートを充填
する、ことを特徴とする土木構築物の施工方法。
10. A wall material is stood and held in front of a lower part of a slope so that the wall material is separated from the slope by a predetermined distance, and an anchor is provided on a front surface side of the wall material. Stones are sequentially piled up with the anchors of the stones facing the wall material side, and the anchors of the respective stones are connected to the wall material, and then, between the wall material and the slope A construction method for civil engineering structures, characterized by filling concrete.
【請求項11】 請求項9又は10において、 前記壁材として、格子状のものを用いる、ことを特徴と
する土木構築物の施工方法。
11. The construction method according to claim 9, wherein a grid-like material is used as the wall material.
【請求項12】 請求項9又は10において、 前記石の積み上げを所定の複数段とすると共に、前記コ
ンクリートの充填を、該所定の複数段をなす石の積み上
げ高さまでとし、これら工程を、一部分領域の施工工程
として順次繰り返す、ことを特徴とする土木構築物の施
工方法。
12. The method according to claim 9, wherein the stones are stacked in a predetermined plurality of steps, and the concrete is filled up to a predetermined stacking height of the stones. A construction method for a civil engineering structure, which is sequentially repeated as a construction process of an area.
【請求項13】 請求項12において、 新たな施工工程への移行を、該新たな施工工程前に充填
されたコンクリートの養生を待って行う、ことを特徴と
する土木構築物の施工方法。
13. The construction method according to claim 12, wherein the transition to the new construction step is performed after the concrete filled before the new construction step is cured.
【請求項14】 請求項13において、 前記石及び前記コンクリートが前記壁材の上端部付近に
至ったとき、該壁材の上端部に該壁材を構成するべき壁
材要素を新たに継ぎ足す、ことを特徴とする土木構築物
の施工方法。
14. The wall material element according to claim 13, wherein when the stone and the concrete reach the vicinity of the upper end of the wall material, a wall material element to constitute the wall material is newly added to the upper end of the wall material. And a civil engineering construction method.
【請求項15】 法面上にコンクリート層を形成し、 次に、前記コンクリート層に壁材を固定し、 次に、アンカーを備えた複数の石を、該壁材の表面側に
おいて、該各アンカーを介して該壁材に連結しつつ積み
上げる、ことを特徴とする土木構築物の施工方法。
15. A concrete layer is formed on the slope, a wall material is fixed to the concrete layer, and a plurality of stones provided with anchors are placed on the surface side of the wall material. A method for constructing a civil engineering structure, comprising stacking while connecting to said wall material via an anchor.
【請求項16】 請求項9において、 前記石を前記壁材の表面側において積み上げるに際し
て、前記各石間に詰め材を詰め込む、ことを特徴とする
土木構築物の施工方法。
16. The construction method according to claim 9, wherein when the stones are stacked on the surface of the wall material, a filling material is packed between the stones.
【請求項17】 請求項10又は15において、 前記石を前記壁材の表面側において積み上げるに際し
て、前記各石間、及び該各石と該壁材との間に詰め材を
詰める、ことを特徴とする土木構築物の施工方法。
17. The method according to claim 10, wherein when the stones are stacked on the surface side of the wall material, a filling material is packed between the stones and between the stones and the wall material. The construction method of the civil engineering structure.
【請求項18】 請求項11において、 前記コンクリートの充填に先立ち、前記壁材の表面に、
コンクリートの流動分の流動を抑制するシートを敷設す
る、ことを特徴とする土木構築物の施工方法。
18. The method according to claim 11, wherein prior to the filling of the concrete,
A method for constructing a civil engineering structure, comprising laying a sheet for suppressing flow of concrete flow.
JP10374463A 1998-12-28 1998-12-28 Civil engineering construction and construction method therefor Pending JP2000199214A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP10374463A JP2000199214A (en) 1998-12-28 1998-12-28 Civil engineering construction and construction method therefor

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP10374463A JP2000199214A (en) 1998-12-28 1998-12-28 Civil engineering construction and construction method therefor

Publications (1)

Publication Number Publication Date
JP2000199214A true JP2000199214A (en) 2000-07-18

Family

ID=18503894

Family Applications (1)

Application Number Title Priority Date Filing Date
JP10374463A Pending JP2000199214A (en) 1998-12-28 1998-12-28 Civil engineering construction and construction method therefor

Country Status (1)

Country Link
JP (1) JP2000199214A (en)

Cited By (9)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2005171687A (en) * 2003-12-12 2005-06-30 Takuo Yukimoto Work-execution method for natural stone block
KR100509786B1 (en) * 2001-09-24 2005-08-24 가부시키가이샤 간쿄 고가쿠 겐큐쇼 Coupling member with improved feature for making lap stone used in constructing embankment, device for coupling the member with stone, and method for making lap stone
JP2009228218A (en) * 2008-03-19 2009-10-08 Sokei:Kk Stone masonry structure and stone masonry construction method
CN101806048A (en) * 2009-02-16 2010-08-18 环境工学株式会社 Civil structure and construction method thereof
JP2011006875A (en) * 2009-06-24 2011-01-13 Kankyo Kogaku Kk Civil engineering structure, method for constructing the same, and construction material for the same
JP2012021348A (en) * 2010-07-16 2012-02-02 Kiyomi Ishibashi Greening method of masonry body
JP2014133971A (en) * 2013-01-08 2014-07-24 Railway Technical Research Institute Seismic strengthening method for retaining wall
CN112655414A (en) * 2020-12-22 2021-04-16 中煤浙江生态环境发展有限公司 Ecological greening structure of high and steep rocky slope and construction method thereof
JP7510652B1 (en) 2023-04-25 2024-07-04 共和ハーモテック株式会社 Supporting member

Cited By (10)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR100509786B1 (en) * 2001-09-24 2005-08-24 가부시키가이샤 간쿄 고가쿠 겐큐쇼 Coupling member with improved feature for making lap stone used in constructing embankment, device for coupling the member with stone, and method for making lap stone
JP2005171687A (en) * 2003-12-12 2005-06-30 Takuo Yukimoto Work-execution method for natural stone block
JP2009228218A (en) * 2008-03-19 2009-10-08 Sokei:Kk Stone masonry structure and stone masonry construction method
CN101806048A (en) * 2009-02-16 2010-08-18 环境工学株式会社 Civil structure and construction method thereof
JP2011006875A (en) * 2009-06-24 2011-01-13 Kankyo Kogaku Kk Civil engineering structure, method for constructing the same, and construction material for the same
JP2012021348A (en) * 2010-07-16 2012-02-02 Kiyomi Ishibashi Greening method of masonry body
JP2014133971A (en) * 2013-01-08 2014-07-24 Railway Technical Research Institute Seismic strengthening method for retaining wall
CN112655414A (en) * 2020-12-22 2021-04-16 中煤浙江生态环境发展有限公司 Ecological greening structure of high and steep rocky slope and construction method thereof
CN112655414B (en) * 2020-12-22 2023-09-29 中煤浙江生态环境发展有限公司 Ecological greening structure of high-steep rock slope and construction method thereof
JP7510652B1 (en) 2023-04-25 2024-07-04 共和ハーモテック株式会社 Supporting member

Similar Documents

Publication Publication Date Title
KR100842802B1 (en) Hole-plate for base pile of ground concrete work and construction method using the same
KR200185875Y1 (en) Reinforced earth retaining-wall for using sand-bag
KR100679873B1 (en) Construction method of breast wall for tree planting
JP2000199214A (en) Civil engineering construction and construction method therefor
KR100752152B1 (en) Construction method of breast wall for tree planting
JP7101407B2 (en) On-site placement reinforcement top type pile foundation and its construction method
CN111119219B (en) Reinforced foundation tire membrane structure and construction method thereof
JP3271951B2 (en) Construction stone for civil engineering structures, method of manufacturing construction stone for civil engineering structures, method of using construction stone for civil engineering structures, construction stone unit for civil engineering structures and civil construction
JPH03180617A (en) Bank of sharp gradient
KR100798689B1 (en) Construction method of ground-making using assembling unit of base pile
KR100885909B1 (en) Self-supporting temporary establishment breast using public works' fiber mesh and constructing method thereof
JP2750364B2 (en) Steep embankment
JP3090642B2 (en) Construction method of foundation and foundation for wooden buildings, and structure of foundation and foundation for wooden buildings
JP3240785U (en) retaining wall
JP5851088B2 (en) Construction method of cast-in-place concrete block formwork and retaining wall
JP7075602B2 (en) Civil engineering structure and construction method of civil engineering structure
JPH0359221A (en) Steep slope banking
JP2000027186A (en) Anchor for wall surface material
JP2000319884A (en) Reinforced mud wall structure
JPH06146296A (en) Stabilizing method for cutting down of slope face
JP2002081040A (en) Construction stone for civil engineering structure
JPH0376926A (en) Steep-sloped banking
JPH05214703A (en) Method of constructing structure by foamed resin block
JPS61172921A (en) Builting method for road levee
JP2834796B2 (en) Embankment slope formation method