JP3224503B2 - Road construction method - Google Patents
Road construction methodInfo
- Publication number
- JP3224503B2 JP3224503B2 JP30429995A JP30429995A JP3224503B2 JP 3224503 B2 JP3224503 B2 JP 3224503B2 JP 30429995 A JP30429995 A JP 30429995A JP 30429995 A JP30429995 A JP 30429995A JP 3224503 B2 JP3224503 B2 JP 3224503B2
- Authority
- JP
- Japan
- Prior art keywords
- road
- soil cement
- soil
- height
- underground structure
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired - Lifetime
Links
Landscapes
- Road Paving Structures (AREA)
- Consolidation Of Soil By Introduction Of Solidifying Substances Into Soil (AREA)
Description
【0001】[0001]
【発明の属する技術分野】本発明は、軟弱地盤上に盛土
により道路を構築する際の構築工法に関する。BACKGROUND OF THE INVENTION 1. Field of the Invention The present invention relates to a construction method for constructing a road by embankment on soft ground.
【0002】[0002]
【従来の技術】埋土層や沖積層の層厚が厚い軟弱地盤上
に盛土により道路を構築する場合は、図4に示すように
浅層地盤改良を施して剛性を高めた改良地盤を路床と
し、その上に盛土により各種砕石などからなる路盤を設
け、その上を舗装する工法が一般的である。(本明細書
では、路盤と舗装とを分離せず、両者を合わせて道路舗
装という。)そして、時には改良地盤の下層に更に摩擦
杭を設けて圧密による沈下を抑制している。2. Description of the Related Art As shown in FIG. 4, when a road is constructed by embankment on a soft ground where the thickness of a buried layer or an alluvial layer is thick, a ground improved in rigidity by performing a shallow ground improvement as shown in FIG. It is a common practice to provide a floor, a subgrade made of various crushed stones and the like by embankment, and paving the floor. (In the present specification, the roadbed and the pavement are not separated, and the two are collectively referred to as road pavement.) In some cases, a friction pile is further provided below the improved ground to suppress settlement due to consolidation.
【0003】[0003]
【発明が解決しようとする課題】道路の路床には盛土に
よる静的荷重とともに交通による動的荷重が負荷され、
これらが合成されて路床に伝達される。そのため、改良
の程度が十分でない場合には静的荷重による圧密沈下に
は十分耐えられても、その数倍の動的荷重には耐えられ
ず、道路が動的荷重により圧密沈下し続けることとな
る。一方、地盤を十分に改良すれば、動的荷重による圧
密沈下を抑制することは勿論可能であるが、地盤改良の
程度と動的荷重による圧密沈下の抑制効果との関連が十
分に把握されていないため、圧密沈下を抑制しようとす
るあまり、過剰に地盤改良をして無用な工期の長さ、無
駄な工費の支出を招くことが多かった。On the roadbed of a road, a dynamic load due to traffic is applied together with a static load due to embankment.
These are combined and transmitted to the subgrade. Therefore, if the degree of improvement is not sufficient, the road will not be able to withstand the dynamic load several times as large as it can withstand the consolidation settlement due to the static load, and the road will continue to consolidate due to the dynamic load. Become. On the other hand, if the ground is sufficiently improved, it is of course possible to suppress consolidation settlement due to dynamic loads, but the relationship between the degree of ground improvement and the effect of suppressing consolidation settlement due to dynamic loads has been well understood. Because of the lack of consolidation settlement, excessive ground improvement often resulted in useless construction periods and wasteful expenditures.
【0004】[0004]
【課題を解決するための手段】本発明は、その上に構築
される道路の動的荷重による圧密沈下を実質的になくす
るための効率的な地盤改良工法について検討した結果な
された発明である。SUMMARY OF THE INVENTION The present invention was made as a result of studying an efficient ground improvement method for substantially eliminating consolidation settlement due to dynamic load of a road constructed thereon. .
【0005】即ち、本発明は、道路基礎の軟弱地盤に、
平面配置を格子状配置または非接触形千鳥配置として平
面視改良率20〜60%でソイルセメント柱状体を構築
し、その上に固結材を混合して固結した改良土壌を敷設
し、さらにその上に道路舗装を構築して、ソイルセメン
ト柱状体の先端から道路舗装面までの高さを4m以上と
することを特徴とする道路の構築工法である。そして、
平面配置が格子状配置の場合は格子間隔がソイルセメン
ト柱状体の上端から道路舗装面までの高さの2倍以下に
設定され、平面配置が非接触形千鳥配置の場合は隣接す
る2本のソイルセメント柱状体の間隔がソイルセメント
柱状体の上端から道路舗装面までの高さの2倍以下に設
定される。[0005] That is, the present invention is applied to soft ground on a road foundation.
A soil cement columnar body is constructed at a planar view improvement rate of 20 to 60% as a lattice arrangement or a non-contact staggered arrangement as a planar arrangement, and a consolidated soil is mixed therewith to lay an improved consolidated soil, and This is a road construction method characterized in that a road pavement is constructed thereon, and the height from the tip of the soil cement column to the road pavement surface is 4 m or more. And
When the plane arrangement is a grid arrangement, the grid spacing is set to less than twice the height from the upper end of the soil cement column to the road pavement surface, and when the plane arrangement is a non-contact staggered arrangement, two adjacent The interval between the soil cement pillars is set to not more than twice the height from the upper end of the soil cement pillars to the road pavement surface.
【0006】深層地盤の改良にソイルセメント柱状体の
形成、浅層地盤の改良に固結材で固結した改良土壌の敷
設という組み合わせを採用する際には、ソイルセメント
柱状体の長さ+浅層改良土壌(路床)の厚さ+道路舗装
の厚さ、が動的荷重による圧密沈下抑制のための大きな
条件であり、この値が4m以上となると動的荷重による
圧密沈下を実質的になくすることができる。更に、ソイ
ルセメント柱状体は平面視改良率20〜60%の範囲で
形成すれば十分であり、改良率を殊更高める必要はな
い。When a combination of forming a soil cement column for improving the deep ground and laying an improved soil consolidated with a consolidating material for improving the shallow ground is adopted, the length of the soil cement column plus the shallow length is used. The thickness of the layer-improved soil (roadbed) + the thickness of the road pavement is a large condition for suppressing consolidation settlement due to dynamic load. When this value exceeds 4 m, consolidation settlement due to dynamic load is substantially reduced. Can be eliminated. Furthermore, it is sufficient that the soil cement columnar body is formed in an improvement ratio in plan view of 20 to 60%, and there is no need to particularly increase the improvement ratio.
【0007】本発明においては上記のソイルセメント柱
状体の長さ+浅層改良土壌(路床)の厚さ+道路舗装の
厚さ、の値は4m以上である必要はあるが、大きくして
もさほど動的圧密沈下の抑制効果は大きくならない。し
かし、大きくなればそれだけ静的圧密沈下の抑制効果は
大きくなる。通常、ソイルセメント柱状体の長さは3〜
5mに、浅層改良土壌の厚さは0.5〜1mに、道路舗
装の厚さは10〜50cmに設定され、ソイルセメント
柱状体の先端から道路舗装面までの高さが4〜7mに設
定される。In the present invention, the value of the above-mentioned length of the soil cement column + thickness of the improved shallow soil (roadbed) + thickness of the road pavement needs to be at least 4 m, but it is necessary to increase the value. The effect of suppressing dynamic consolidation settlement is not so large. However, the larger the size, the greater the effect of suppressing static consolidation settlement. Usually, the length of soil cement column is 3 ~
5 m, the thickness of the shallow layer improved soil is set to 0.5-1 m, the thickness of the road pavement is set to 10-50 cm, and the height from the tip of the soil cement column to the road pavement surface is set to 4-7 m. Is set.
【0008】本発明で深層地盤改良のために構築するソ
イルセメント柱状体は動的荷重による地盤の側方流動を
防止することも目的としているが、平面配置を格子状配
置もしくは非接触形千鳥配置として、平面視改良率をで
きるだけ低く抑える。平面視改良率20〜60%の範囲
においては格子状配置を採用した場合、格子間隔がソイ
ルセメント柱状体の上端から道路舗装面までの高さの2
倍以下であれば、静的荷重、動的荷重はソイルセメント
柱状体の確実に伝達され、十分地盤の側方流動を防止す
ることが可能である。[0008] The purpose of the present invention is to prevent the lateral flow of the ground due to the dynamic load in the soil cement columnar body constructed for deep ground improvement, but the planar arrangement is a lattice-like arrangement or a non-contact staggered arrangement. The improvement rate in plan view is kept as low as possible. In the case where the grid-like arrangement is employed in the range of the planar view improvement rate of 20 to 60%, the grid interval is 2 times the height from the upper end of the soil cement column to the road pavement surface.
If it is less than twice, the static load and the dynamic load can be reliably transmitted to the soil cement columnar body, and the lateral flow of the ground can be sufficiently prevented.
【0009】非接触形千鳥配置を採用した場合も同様に
道路軸方向およびそれに直交する方向に隣接する2本の
ソイルセメント柱状体の間隔がソイルセメント柱状体の
上端から道路舗装面までの高さの2倍以下であれば、静
的荷重、動的荷重はソイルセメント柱状体の確実に伝達
され、十分地盤の側方流動を防止することが可能であ
る。Similarly, when the non-contact staggered arrangement is adopted, the distance between two soil cement pillars adjacent in the direction of the road axis and the direction perpendicular thereto is also the height from the upper end of the soil cement pillar to the road pavement surface. If it is less than twice the static load and the dynamic load can be reliably transmitted to the soil cement columnar body, and it is possible to sufficiently prevent lateral flow of the ground.
【0010】以上は、道路を構築する基礎地盤中に埋設
構造物がない場合であるが、道路の構築に際しては、暗
渠などの既設地下構造物の上を横断する場合や道路の構
築に先行して暗渠などの既設地下構造物を敷設し、その
後、その上を横断して道路を構築する場合が多い。そし
て、この地下構造物は通常は支持層に到達する支持杭に
よって支持されており、沈下することはなく、沈下して
もごく少ない。この殆ど沈下しない地下構造物の上を横
断して構築した道路に動的荷重による圧密沈下が発生す
ると、地下構造物の上の部分とそれに隣接する部分とで
道路上に段差を生ずることとなり、交通上危険である。The above is a case where there is no buried structure in the foundation ground on which a road is constructed. However, when constructing a road, it is necessary to cross over an existing underground structure such as a culvert or to construct a road. In many cases, existing underground structures such as culverts are laid, and then roads are built across them. The underground structure is usually supported by a support pile reaching the support layer, and does not sink, and the sink is very small. If consolidation subsidence due to dynamic load occurs on a road constructed over an underground structure that hardly sinks, a step will occur on the road between the upper part of the underground structure and the part adjacent to it. Dangerous on traffic.
【0011】本発明はかかる段差の発生の解消にも利用
される。即ち、地下構造物の近傍にはソイルセメント柱
状体の先端から路盤舗装面までの高さを4m以上とした
長いソイルセメント柱状体を構築し、この地下構造物か
ら離れるに従って段々に短いソイルセメント柱状体を構
築することによって、地下構造物の近傍では圧密沈下を
極力抑制し、離れるに従って徐々にある程度の圧密沈下
を許容するという対策を採る。この場合でも、段差解消
工法は効率的で経済的である必要があるので、地下構造
物近傍の地盤改良の諸条件、即ち、構築されるソイルセ
メント柱状体の平面配置、格子状配置の場合の格子間
隔、非接触形千鳥配置の場合の隣接するソイルセメント
柱状体の間隔、平面視改良率、浅層改良土壌の配合条件
などは上記の道路全長にわたって改良する場合と同じ条
件が適用され、ただ、地下構造物から離れるに従って段
々ソイルセメント柱状体の長さが短くなる点が異なる。The present invention is also used for eliminating such a step. That is, in the vicinity of the underground structure, a long soil cement column having a height from the tip of the soil cement column to the roadbed pavement surface of 4 m or more is constructed, and the longer the distance from the underground structure, the shorter the soil cement column becomes. By constructing the body, measures will be taken to minimize consolidation settlement near the underground structure and to allow some degree of consolidation settlement gradually as it moves away. Even in this case, the step-elimination method needs to be efficient and economical.Therefore, various conditions for ground improvement near the underground structure, that is, in the case of the planar arrangement of the soil cement pillars to be constructed and the lattice arrangement The grid spacing, the spacing between adjacent soil cement columns in the case of non-contact staggered arrangement, the improvement rate in plan view, the mixing conditions of shallow-layer improved soil, etc. apply the same conditions as when improving over the entire length of the road described above. The difference is that the length of the soil cement column gradually decreases as the distance from the underground structure increases.
【0012】[0012]
【発明の実施の形態】以下、図面を参照しながら、本発
明を詳細に説明する。DETAILED DESCRIPTION OF THE PREFERRED EMBODIMENTS Hereinafter, the present invention will be described in detail with reference to the drawings.
【0013】図1は本発明で構築した道路の断面図であ
り、(a)は一般部の道路軸に直交する方向の断面図、
(b)は地下構造物横断部の道路軸方向の断面図であ
る。図2は本発明および従来工法などで構築した道路の
圧密沈下量と時間との関係を示すグラフである。図3は
ソイルセメント柱状体の平面配置の例を示し、(a)は
格子状配置の1例、(b)は非接触形千鳥配置の1例で
ある。図4は若干異なった2つの従来工法で構築した道
路の道路軸に直交する方向の断面図である。FIG. 1 is a cross-sectional view of a road constructed according to the present invention. FIG. 1A is a cross-sectional view of a general portion in a direction perpendicular to a road axis.
(B) is a cross-sectional view of a cross section of the underground structure in the direction of the road axis. FIG. 2 is a graph showing the relationship between the amount of consolidation settlement of a road constructed according to the present invention and the conventional method, and time. 3A and 3B show an example of a planar arrangement of the soil cement pillars, wherein FIG. 3A shows an example of a lattice arrangement, and FIG. 3B shows an example of a non-contact staggered arrangement. FIG. 4 is a cross-sectional view in a direction perpendicular to the road axis of a road constructed by two slightly different conventional methods.
【0014】図1(a)を参照して、施工手順を交えな
がら、本発明による一般部道路の構築工法の例を説明す
る。Referring to FIG. 1 (a), an example of a general road construction method according to the present invention will be described along with construction procedures.
【0015】(1)対象軟弱地盤を若干掘削し、通常の
ソイルセメント柱工法で径80cmのソイルセメント柱
状体1を、非接触形千鳥配置で、ピッチ200cm(道
路軸方向、直交方向とも)で平面視改良率25%で構築
する。ソイルセメント柱状体1の長さは350cmとす
る。ソイルセメント柱状体を構築するが、その長さが短
い場合として、工区によりソイルセメント柱状体1の長
さを200cmとする。(1) The target soft ground is slightly excavated, and a soil cement columnar body 1 having a diameter of 80 cm is formed in a non-contact staggered manner at a pitch of 200 cm (both in the road axis direction and in the orthogonal direction) by a normal soil cement column method. Constructed with 25% improvement in plan view. The length of the soil cement column 1 is 350 cm. The length of the soil cement column 1 is set to 200 cm depending on the construction section, assuming that the length is short.
【0016】(2)掘削土および他所より搬送してきた
土砂にセメント系固結材を混合して固結した浅層改良土
壌層11を70cmの厚さに敷設する。(2) A 70-cm-thick improved shallow soil layer 11 is formed by mixing a cement-based solidifying material with excavated soil and earth and sand conveyed from another place and consolidating it.
【0017】(3)粒度調整砕石層15を10cmの厚
さに敷設し、その上を5cmの厚さのアスファルトーコ
ンクリート16で舗装する。(3) A particle size adjusting crushed stone layer 15 is laid in a thickness of 10 cm, and the crushed stone layer 15 is paved with an asphalt concrete 16 having a thickness of 5 cm.
【0018】以上で本発明による一般部道路の構築は完
了し、ソイルセメント柱状体の先端から道路舗装面まで
の高さが435cmの道路が構築される。ソイルセメン
ト柱状体を構築しても、その長さが短い200cmの場
合はソイルセメント柱状体の先端から道路舗装面までの
高さが285cmとなる。With the above, the construction of the general road according to the present invention is completed, and a road having a height of 435 cm from the tip of the soil cement pillar to the road pavement surface is constructed. Even when a soil cement column is constructed, if the length is 200 cm, the height from the tip of the soil cement column to the road pavement surface is 285 cm.
【0019】図1(b)の地下構造物横断部の場合に
は、上記(1)のソイルセメント柱状体1の長さを35
0cmから200cmまで数段階で段階的に減らす点以
外は上記と同様に施工する。In the case of the cross section of the underground structure shown in FIG. 1B, the length of the soil cement column 1 of the above (1) is set to 35.
Construction is performed in the same manner as described above except that the number of steps is reduced in several steps from 0 cm to 200 cm.
【0020】図2は各種工法で構築された道路の経過時
間と沈下量の関係を表す時間沈下曲線であり、l−本発
明の場合、m−ソイルセメント柱状体は構築するがソイ
ルセメント柱状体の先端から道路舗装面までの高さが2
85cmの場合、n−図4(b)で示す従来工法の場
合、を示す。FIG. 2 is a time subsidence curve showing the relationship between the elapsed time and the amount of subsidence of a road constructed by various methods. 1-In the case of the present invention, the m-soil cement column is constructed, but the soil cement column is constructed. The height from the tip of the road to the road pavement is 2
In the case of 85 cm, n—the case of the conventional method shown in FIG.
【0021】グラフから明らかなように、供用開始まで
の静的荷重による沈下量はいずれも小さく有意差は認め
られない程度であるが、供用開始後の動的荷重による沈
下量は大きな差を生じ、本発明で構築された道路の動的
荷重による圧密沈下抑制の効果が大きいことがわかる。
因みに、ソイルセメント柱状体を構築しても、その長さ
が短い場合は、従来の浅層地盤を十分に改良した場合と
動的荷重による圧密沈下抑制効果に大差がないことがわ
かる。As is apparent from the graph, the settlement amount due to the static load until the start of operation is small and no significant difference is recognized, but the settlement amount due to the dynamic load after the start of operation has a large difference. It can be seen that the effect of suppressing the consolidation settlement by the dynamic load of the road constructed by the present invention is great.
By the way, even if the soil cement column is constructed, when the length is short, it is understood that there is not much difference between the case where the conventional shallow ground is sufficiently improved and the effect of suppressing the consolidation settlement by the dynamic load.
【0022】図3はソイルセメント柱状体の平面配置に
関連して格子状配置の場合の格子間隔および非接触形千
鳥配置を採用した場合の隣接する2本のソイルセメント
柱状体の間隔を説明するもので、(a)に示すように格
子間隔は格子が長方形の場合は長い方の間隔dが格子間
隔である。また、(b)に示すように隣接する2本のソ
イルセメント柱状体の間隔は、非接触形千鳥配置のピッ
チが道路軸方向とそれと直交方向とで異なる場合は長い
方の間隔d′が柱状体間隔である。FIG. 3 illustrates the grid spacing in the case of a grid arrangement and the spacing between two adjacent soil cement columns in the case of employing the non-contact staggered arrangement in relation to the planar arrangement of the soil cement columns. As shown in (a), when the grid is rectangular, the longer interval d is the grid interval. In addition, as shown in (b), the interval between two adjacent soil cement pillars is such that when the pitch of the non-contact staggered arrangement is different between the road axis direction and the direction orthogonal thereto, the longer distance d 'is columnar. It is body spacing.
【0023】[0023]
【発明の効果】本発明は深層地盤の改良にソイルセメン
ト柱状体の形成、浅層地盤の改良に固結材で固結した改
良土壌の敷設という組み合わせを採用し、かつ、平面配
置を格子状配置または非接触形千鳥配置としてソイルセ
メント柱状体の格子間隔または隣接するソイルセメント
柱状体の間隔をソイルセメント柱状体の上端から道路舗
装面の2倍以下として平面視改良率20〜60%でソイ
ルセメント柱状体を構築し、さらに、浅層改良土壌(路
床)の厚さ+道路舗装の厚さ、の値を4m以上とするこ
とにより、深層地盤の改良面積が少ないのにもかかわら
ず、動的荷重による圧密沈下の抑制が可能となる。この
結果、低工費で効率的な道路構築が可能になる。According to the present invention, a combination of forming a soil cement column for improving the deep ground and laying improved soil consolidated with a consolidating material for improving the shallow ground, and adopting a planar arrangement in a grid-like configuration. Soil at a planar view improvement rate of 20 to 60%, with the grid spacing of soil cement columns or the spacing between adjacent soil cement columns being no more than twice as large as the road pavement surface from the top of the soil cement columns as an arrangement or non-contact staggered arrangement By constructing a cement column and setting the value of the thickness of the shallow-layered improved soil (roadbed) + the thickness of the road pavement to 4 m or more, despite the fact that the improved area of the deep ground is small, It is possible to suppress the consolidation settlement due to the dynamic load. As a result, it is possible to construct an efficient road with low construction costs.
【0024】また、殆ど沈下しない既設地下構造物上を
横断して道路を構築する場合、道路基礎の軟弱地盤に埋
設されている地下構造物の近傍にはソイルセメント柱状
体の先端から路盤舗装面までの高さを4m以上とした長
いソイルセメント柱状体を構築し、この地下構造物から
離れるに従って段々に短いソイルセメント柱状体を構築
するという対策を採用し、かつ、該ソイルセメント柱状
体の平面配置を格子状配置または非接触形千鳥配置とし
格子間隔または隣接する2本のソイルセメント柱状体の
間隔をソイルセメント柱状体の上端から道路舗装面まで
の高さの2倍以下として平面視改良率20〜60%でソ
イルセメント柱状体を構築し、その上に浅層地盤の改良
に固結材を混合して固結した改良土壌を敷設し、さら
に、その上に道路舗装を構築することにより、沈下しな
い既設地下構造物上を横断する道路に発生していた段差
の発生を防止することが可能になる。即ち、既設地下構
造物の近傍では圧密沈下を極力抑制し、離れるに従って
徐々にある程度の圧密沈下を許容する。この結果、低工
費で効率的な道路構築が可能になる。When a road is constructed by crossing over an existing underground structure which hardly sinks, a pavement surface near the underground structure buried in the soft ground of the road foundation from the tip of the soil cement columnar body. To construct a long soil-cement column having a height of at least 4 m, and gradually constructing a short soil-cement column as the distance from the underground structure increases, and the plane of the soil-cement column. When the arrangement is grid-like or non-contact staggered, the grid spacing or the spacing between two adjacent soil cement pillars is less than twice the height from the top of the soil cement pillar to the road pavement surface, and the improvement rate in plan view is reduced. A soil cement column is constructed at 20 to 60%, and the improved soil laid by mixing a solidifying material to improve the shallow ground is laid on it, and a road pavement is further laid on it. By building, it is possible to prevent the generation of steps that occurred road crossing the existing underground structure Butsujo not sink. That is, in the vicinity of the existing underground structure, consolidation settlement is suppressed as much as possible, and a certain degree of consolidation settlement is allowed gradually as the distance increases. As a result, it is possible to construct an efficient road with low construction costs.
【図1】本発明で構築した道路の断面図であり、(a)
は一般部の道路軸に直交する方向の断面図、(b)は地
下構造物横断部の道路軸方向の断面図である。FIG. 1 is a sectional view of a road constructed according to the present invention;
FIG. 3 is a cross-sectional view of a general part in a direction orthogonal to a road axis, and FIG. 4B is a cross-sectional view of a crossing part of an underground structure in a road axial direction.
【図2】本発明および従来の工法で構築した道路の圧密
沈下量と時間との関係を示すグラフである。FIG. 2 is a graph showing a relationship between a consolidation settlement amount and time of a road constructed by the present invention and a conventional method.
【図3】ソイルセメント柱状体の平面配置の例を示し、
(a)は格子状配置の1例、(b)は非接触形千鳥配置
の1例である。FIG. 3 shows an example of a planar arrangement of a soil cement pillar,
(A) is an example of a lattice arrangement, and (b) is an example of a non-contact staggered arrangement.
【図4】若干異なった2つの従来工法で構築した道路の
道路軸に直交する方向の断面図である。FIG. 4 is a cross-sectional view of a road constructed by two slightly different conventional methods in a direction perpendicular to the road axis.
1・・ソイルセメント柱状体、2・・支持杭、3・・暗
渠、11・・セメント系固結材乾式混合浅層改良土壌
層、12・・生石灰乾式混合浅層改良土壌層、13・・
Fe石灰乾式混合浅層改良土壌層、14・・クラッシャ
ーラン層、15・・粒度調整砕石層、16・・アスファ
ルトーコンクリート層。1. Soil cement column, 2. Support pile, 3. Underdrain, 11. Cement-based solidified dry mixed shallow layer improved soil layer, 12. Quick lime dry mixed shallow layer improved soil layer, 13.
Fe lime dry-mixed shallow layer improved soil layer, 14. Crusher run layer, 15. Crushed stone layer, 16. Asphalt concrete layer.
───────────────────────────────────────────────────── フロントページの続き (73)特許権者 591072949 東京鋪装工業株式会社 東京都千代田区外神田2丁目4番4号 (72)発明者 三浦 哲彦 佐賀県佐賀市本庄町大字末次850−4 (72)発明者 藤川 和之 福岡県北九州市八幡西区永犬丸南町1− 7−5 (72)発明者 浜武 章 福岡県春日市弥生1丁目82番地 サンア イシティライフ春日3−311号 (72)発明者 田中 英樹 福岡県大牟田市甘木380−2 (72)発明者 福田 厚生 東京都港区赤坂6丁目13番7号 株式会 社テノックス内 (72)発明者 吉田 茂 東京都港区赤坂6丁目13番7号 株式会 社テノックス内 (56)参考文献 特開 昭50−44629(JP,A) 特開 昭60−152718(JP,A) 特開 昭51−93515(JP,A) (58)調査した分野(Int.Cl.7,DB名) E01C 3/00 - 3/04 E02D 3/00 101 E02D 3/12 101 ──────────────────────────────────────────────────続 き Continuing on the front page (73) Patent holder 591072949 Tokyo Hoso Kogyo Co., Ltd. 2-4-2-4 Sotokanda, Chiyoda-ku, Tokyo (72) Inventor Tetsuhiko Miura 850-4, Hatsujo-cho, Honjo-cho, Saga-shi, Saga ( 72) Inventor Kazuyuki Fujikawa 1-7-5, Einomaru-minami-cho, Yahata-nishi-ku, Kitakyushu-shi, Fukuoka (72) Inventor Akira Hamake 1-82, Yayoi, Kasuga-shi, Fukuoka San-ai City Life No. 3-311, Kasuga (72) Invention Person Hideki Tanaka 380-2 Amagi, Omuta-shi, Fukuoka (72) Inventor Fukuda 6-13-7 Akasaka, Minato-ku, Tokyo Inside Tenox Co., Ltd. (72) Inventor Shigeru Yoshida 6-13, Akasaka, Minato-ku, Tokyo No. 7 Inside Tenox Co., Ltd. (56) References JP-A-50-44629 (JP, A) JP-A-60-152718 (JP, A) JP-A-51-93515 (JP, A) (58) Investigated Field (Int.Cl. 7, DB name) E01C 3/00 - 3/04 E02D 3/00 101 E02D 3/12 101
Claims (4)
状配置としたソイルセメント柱状体を、格子間隔をソイ
ルセメント柱状体の上端から道路舗装面までの高さの2
倍以下として、平面視改良率20〜60%で構築し、そ
の上に固結材を混合して固結した改良土壌を敷設し、さ
らにその上に道路舗装を構築して、ソイルセメント柱状
体の先端から道路舗装面までの高さを4m以上とするこ
とを特徴とする道路の構築工法。1. A soil cement column having a lattice arrangement in a plane arrangement on a soft ground of a road foundation, and a lattice interval of 2 heights from the upper end of the soil cement column to a road pavement surface.
It is constructed at an improvement rate of 20 to 60% in plan view, and a consolidated soil is mixed with a consolidated material to lay the improved soil, and a road pavement is further constructed thereon, and the soil cement columnar body is constructed. A road construction method characterized in that the height from the tip of the road to the road pavement surface is 4 m or more.
触形千鳥配置としたソイルセメント柱状体を、隣接する
2本のソイルセメント柱状体の間隔をソイルセメント柱
状体の上端から道路舗装面までの高さの2倍以下とし
て、平面視改良率20〜60%で構築し、その上に固結
材を混合して固結した改良土壌を敷設し、さらにその上
に道路舗装を構築して、ソイルセメント柱状体の先端か
ら道路舗装面までの高さを4m以上とすることを特徴と
する道路の構築工法。2. A soil cement column having a non-contact staggered plane arrangement on a soft ground of a road foundation, and an interval between two adjacent soil cement columns arranged on a road pavement surface from an upper end of the soil cement column. Up to twice the height up to the height of 20 to 60% in plan view, laying the improved soil that has been mixed with the consolidated material and consolidated, and then the road pavement The height from the tip of the soil cement column to the road pavement surface is 4 m or more.
下の少ない地下構造物の上を横断して道路基礎の軟弱地
盤に道路を構築する工法であって、道路基礎の軟弱地盤
に埋設されている沈下の少ない地下構造物の近傍にはソ
イルセメント柱状体の先端から路盤舗装面までの高さを
4m以上とした長いソイルセメント柱状体を、該地下構
造物から離れるに従って段々に短いソイルセメント柱状
体を構築するとともに、ソイルセメント柱状体の平面配
置を格子状配置とし、格子間隔をソイルセメント柱状体
の上端から道路舗装面までの高さの2倍以下として、平
面視改良率20〜60%でソイルセメント柱状体を構築
し、その上に固結材を混合して固結した改良土壌を敷設
し、さらに、該地下構造物および改良土壌の上に道路舗
装を構築することを特徴とする道路の構築工法。3. A method of constructing a road on a soft ground of a road foundation by crossing over an underground structure with little settlement buried in the soft ground of a road foundation, wherein the road is buried in the soft ground of a road foundation. In the vicinity of an underground structure with little settlement, a long soil cement column having a height from the tip of the soil cement column to the roadbed pavement surface of 4 m or more is gradually reduced as the distance from the underground structure increases. While constructing the pillars, the planar arrangement of the soil cement pillars is set as a grid arrangement, and the grid spacing is set to be not more than twice the height from the upper end of the soil cement pillars to the road pavement surface. %, Constructing a soil cement columnar body, laying a consolidated soil mixed with a consolidating material, laying the consolidated soil, and constructing a road pavement on the underground structure and the modified soil. Characteristic road construction method.
下の少ない地下構造物の上を横断して道路基礎の軟弱地
盤に道路を構築する工法であって、道路基礎の軟弱地盤
に埋設されている沈下の少ない地下構造物の近傍にはソ
イルセメント柱状体の先端から路盤舗装面までの高さを
4m以上とした長いソイルセメント柱状体を、該地下構
造物から離れるに従って段々に短いソイルセメント柱状
体を構築するとともに、ソイルセメント柱状体の平面配
置を非接触形千鳥配置とし、隣接する2本のソイルセメ
ント柱状体の間隔をソイルセメント柱状体の上端から道
路舗装面までの高さの2倍以下として平面視改良率20
〜60%でソイルセメント柱状体を構築し、その上に固
結材を混合して固結した改良土壌を敷設し、さらに、該
地下構造物および改良土壌の上に道路舗装を構築するこ
とを特徴とする道路の構築工法。4. A method of constructing a road on soft ground of a road foundation by crossing over an underground structure with little settlement embedded in the soft ground of a road foundation, wherein the road is buried in the soft ground of a road foundation. In the vicinity of an underground structure with little settlement, a long soil cement column having a height from the tip of the soil cement column to the roadbed pavement surface of 4 m or more is gradually reduced as the distance from the underground structure increases. While constructing the pillars, the soil cement pillars are arranged in a non-contact staggered plane, and the interval between two adjacent soil cement pillars is set at the height of the height from the upper end of the soil cement pillars to the road pavement surface. 2 times or less and improvement rate in plan view 20
Constructing a soil cement column at about 60%, laying a consolidated soil mixed with a consolidating material, laying the consolidated soil, and constructing a road pavement on the underground structure and the modified soil. Characteristic road construction method.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP30429995A JP3224503B2 (en) | 1995-11-22 | 1995-11-22 | Road construction method |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP30429995A JP3224503B2 (en) | 1995-11-22 | 1995-11-22 | Road construction method |
Related Child Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
JP2000248315A Division JP3373488B2 (en) | 2000-08-18 | 2000-08-18 | Road construction |
Publications (2)
Publication Number | Publication Date |
---|---|
JPH09151409A JPH09151409A (en) | 1997-06-10 |
JP3224503B2 true JP3224503B2 (en) | 2001-10-29 |
Family
ID=17931369
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
JP30429995A Expired - Lifetime JP3224503B2 (en) | 1995-11-22 | 1995-11-22 | Road construction method |
Country Status (1)
Country | Link |
---|---|
JP (1) | JP3224503B2 (en) |
Families Citing this family (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JP2013221347A (en) * | 2012-04-18 | 2013-10-28 | Nishimatsu Constr Co Ltd | Ground structure and ground improvement method |
JP2015031119A (en) * | 2013-08-06 | 2015-02-16 | 東日本旅客鉄道株式会社 | Ground reinforcement structure |
Family Cites Families (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JPS5044629A (en) * | 1973-08-24 | 1975-04-22 | ||
JPS60152718A (en) * | 1984-01-18 | 1985-08-12 | Toyo Kiko:Kk | Method of improving railroad ground wherein hardener is poured in ground of depth |
-
1995
- 1995-11-22 JP JP30429995A patent/JP3224503B2/en not_active Expired - Lifetime
Also Published As
Publication number | Publication date |
---|---|
JPH09151409A (en) | 1997-06-10 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
JP3653083B2 (en) | Road construction method | |
CN110904823B (en) | Bridge head bump treatment construction structure and construction method in high soft soil filling area | |
JP5815360B2 (en) | Improved ground and its construction method | |
CN107938456B (en) | Construction method for filling river channel | |
CN109958018A (en) | A kind of heavy rainfall urban road water-permeable pavement structure and its construction method | |
CN106894311A (en) | A kind of sponge-type urban water-through bituminous paving | |
CN112921738A (en) | Highway pavement structure and construction method thereof | |
JP3373488B2 (en) | Road construction | |
EP0898623B1 (en) | Pavement for conveying vehicular traffic | |
JP3224503B2 (en) | Road construction method | |
RU2394959C1 (en) | Road surface structure | |
CN208884292U (en) | Soft soil roadbed and normal roadbed intersection anti-settling structure | |
CN218842755U (en) | High-strength composite geotechnical synthetic material reinforced mattress pad layer structure of karst foundation | |
JPH02504050A (en) | Method for forming road and roadbed structures | |
JP7298441B2 (en) | road structure | |
CN111501459B (en) | Roadbed structure of mountain road and construction method thereof | |
JP3583181B2 (en) | Embankment construction method | |
CN211142682U (en) | Structure for preventing urban road subgrade from non-uniform settlement | |
RU2422581C1 (en) | Method to repair and construct arterial highways | |
CN112813844A (en) | Access-protecting passage meeting rapid flood discharge requirement in river channel and construction method | |
CN207314070U (en) | Prevent highway from the insulation ground of frozen soil change occurs | |
CN218345827U (en) | Prevent roadbed structure that consolidation subsides | |
JPS6317969B2 (en) | ||
RU2762303C1 (en) | Method for constructing a heat-insulating structure | |
JPH0765315B2 (en) | Embankment structure |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
A01 | Written decision to grant a patent or to grant a registration (utility model) |
Free format text: JAPANESE INTERMEDIATE CODE: A01 Effective date: 20010814 |
|
R250 | Receipt of annual fees |
Free format text: JAPANESE INTERMEDIATE CODE: R250 |
|
S531 | Written request for registration of change of domicile |
Free format text: JAPANESE INTERMEDIATE CODE: R313531 |
|
R350 | Written notification of registration of transfer |
Free format text: JAPANESE INTERMEDIATE CODE: R350 |
|
FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20100824 Year of fee payment: 9 |
|
FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20100824 Year of fee payment: 9 |
|
S531 | Written request for registration of change of domicile |
Free format text: JAPANESE INTERMEDIATE CODE: R313531 |
|
FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20100824 Year of fee payment: 9 |
|
R350 | Written notification of registration of transfer |
Free format text: JAPANESE INTERMEDIATE CODE: R350 |
|
FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20100824 Year of fee payment: 9 |
|
FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20100824 Year of fee payment: 9 |
|
S531 | Written request for registration of change of domicile |
Free format text: JAPANESE INTERMEDIATE CODE: R313531 |
|
FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20100824 Year of fee payment: 9 |
|
R350 | Written notification of registration of transfer |
Free format text: JAPANESE INTERMEDIATE CODE: R350 |
|
FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20100824 Year of fee payment: 9 |
|
FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20130824 Year of fee payment: 12 |
|
FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20130824 Year of fee payment: 12 |
|
S111 | Request for change of ownership or part of ownership |
Free format text: JAPANESE INTERMEDIATE CODE: R313117 |
|
S531 | Written request for registration of change of domicile |
Free format text: JAPANESE INTERMEDIATE CODE: R313531 |
|
FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20130824 Year of fee payment: 12 |
|
R350 | Written notification of registration of transfer |
Free format text: JAPANESE INTERMEDIATE CODE: R350 |
|
R250 | Receipt of annual fees |
Free format text: JAPANESE INTERMEDIATE CODE: R250 |
|
EXPY | Cancellation because of completion of term | ||
S531 | Written request for registration of change of domicile |
Free format text: JAPANESE INTERMEDIATE CODE: R313531 |
|
R360 | Written notification for declining of transfer of rights |
Free format text: JAPANESE INTERMEDIATE CODE: R360 |
|
R370 | Written measure of declining of transfer procedure |
Free format text: JAPANESE INTERMEDIATE CODE: R370 |