JP3194104B2 - Large roof structure and construction method - Google Patents

Large roof structure and construction method

Info

Publication number
JP3194104B2
JP3194104B2 JP05293292A JP5293292A JP3194104B2 JP 3194104 B2 JP3194104 B2 JP 3194104B2 JP 05293292 A JP05293292 A JP 05293292A JP 5293292 A JP5293292 A JP 5293292A JP 3194104 B2 JP3194104 B2 JP 3194104B2
Authority
JP
Japan
Prior art keywords
cable
roof structure
building
gantry
constructing
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
JP05293292A
Other languages
Japanese (ja)
Other versions
JPH05255974A (en
Inventor
和男 斉田
肇 中島
隆之 西谷
尚範 谷口
健司 鈴木
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Shimizu Corp
Original Assignee
Shimizu Corp
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Shimizu Corp filed Critical Shimizu Corp
Priority to JP05293292A priority Critical patent/JP3194104B2/en
Publication of JPH05255974A publication Critical patent/JPH05255974A/en
Application granted granted Critical
Publication of JP3194104B2 publication Critical patent/JP3194104B2/en
Anticipated expiration legal-status Critical
Expired - Fee Related legal-status Critical Current

Links

Landscapes

  • Rod-Shaped Construction Members (AREA)
  • Conveying And Assembling Of Building Elements In Situ (AREA)

Description

【発明の詳細な説明】DETAILED DESCRIPTION OF THE INVENTION

【0001】[0001]

【産業上の利用分野】本発明は、上方に起くれてなる大
型屋根構造物及びその施工方法に関する。
BACKGROUND OF THE INVENTION 1. Field of the Invention The present invention relates to a large roof structure rising upward and a method of constructing the same.

【0002】[0002]

【従来の技術】従来、体育館などの上部に施工される大
型の屋根構造部は、対向する建築物下部構造部の双方か
ら等しい長さに形成された直の梁材を互いの先端を屋根
構造部の長さ方向中央部で接合することにより側面視山
形に形成されている。前記屋根構造部の施工方法として
は、屋根構造部を載置すべき建築物下部構造部を先行し
て構築するとともに、対向する建築物下部構造部の双方
から直の梁材を双方の端部が当設しかつ左右対象として
立て掛ける。そして、前記状態で各建築物下部構造部の
下端部を連結するPCストランドを介してそれぞれ対向
する相手側に向かってプレストレスを導入することによ
り、安定に立設する。
2. Description of the Related Art Conventionally, a large roof structure constructed in an upper part of a gymnasium or the like is constructed by mounting straight beams of equal length from both opposing building lower structures to the roof structure. It is formed in a mountain shape in side view by joining at the center in the length direction of the portions. As a construction method of the roof structure portion, a building lower structure portion on which the roof structure portion is to be mounted is built in advance, and a beam material directly from both of the opposing building lower structure portions is attached to both ends. Is set up and leans left and right. Then, in the state described above, the prestress is introduced toward the opposing opposing sides via the PC strands connecting the lower ends of the respective building substructures, thereby stably standing the building.

【0003】[0003]

【発明が解決しようとする課題】しかしながら、前記の
ような屋根構造部及びその施工方法の場合、以下のよう
な問題が生じていた。すなわち、前記のような屋根構造
部及びその施工方法にあっては、頂点部分の応力集中が
顕著となるため棟梁及びその近傍の構造を強固に構成す
る必要があることから、屋根構造部の揚重が困難である
ほか、重量が大きくなって屋根構造部を支持する建築物
下部構造部を高い強度を有するように形成する必要があ
り、施工コストの増大や、工期の延長の原因となってい
た。
However, in the case of the above-mentioned roof structure and its construction method, the following problems have arisen. That is, in the above-described roof structure and its construction method, since the stress concentration at the apex portion becomes remarkable, it is necessary to firmly configure the ridge and the structure in the vicinity thereof. In addition to being difficult to weight, it is necessary to form the substructure of the building that supports the roof structure with high strength because of its high weight, which increases the construction cost and prolongs the construction period. Was.

【0004】また、前記問題点に鑑みて、前記建築物下
部構造部から適切長の骨材を下から順次継ぎ足すように
連結していくことによりドーム状に構成される大屋根構
造部が提案されているが、今度は、多数の骨材を継ぎ足
す必要があるため構成に手間がかかるほか、施工位置全
体にわたって作業者の移動のための足場を組む必要があ
り、施工能率が低下するといった問題が生じる。
[0004] In view of the above problems, a large dome-shaped structure has been proposed which is constructed in a dome shape by connecting aggregates of appropriate length from the lower structure of the building so as to be sequentially added from below. However, this time, it is necessary to add a large number of aggregates, it takes time to construct, and it is necessary to build a scaffold for workers to move over the entire construction position, which reduces construction efficiency. Problems arise.

【0005】本発明は、前述の課題に鑑みてなされたも
ので、軽量化して揚重を簡便かつ構成を単純として施工
能率が向上する大型屋根構造物及びその施工方法を提供
することを目的とするものである。
The present invention has been made in view of the above-mentioned problems, and an object of the present invention is to provide a large-sized roof structure which is light in weight, can be easily lifted, has a simple structure, and improves construction efficiency, and a construction method therefor. Is what you do.

【0006】[0006]

【課題を解決するための手段】請求項1記載の発明の大
型屋根構造物は、上方に起くれてなる大型屋根構造物で
あって、施工すべき建物の下部構造部の上部に建て込ま
れた複数の梁構造物を備えてなり、梁構造物はアーチ状
の梁材と、この梁材の両下端部を連結するようにして張
設された下弦ケーブルとからなり、梁材と下弦ケーブル
の間には双方を連結する補助ケーブルが束材として梁構
造物の長さ方向に複数取り付けられて全体が上方に凸の
弓型または山形に形成することを特徴とする。請求項2
記載の発明の大型屋根構造物の施工方法は、屋根構造を
施工すべき下部構造部の間の床部に梁材を設置するとと
もにこの梁材の両下端部を結ぶようにして下弦ケーブル
を取り付けかつ下弦ケーブルと梁材の間に目的長さの補
助ケーブルを取り付けて束材とし、下弦ケーブルを牽引
することにより張設して双方の梁材を目的の形状に起く
って梁構造物を完成する工程を具備することを特徴とす
る。請求項3記載の大型屋根構造物の施工方法は、屋根
構造部を載置すべき建物の下部構造部を施工して建物の
中央部に構台を屋根構造部を設置する高さに形成して立
設する工程と、前記梁材を両端部を下部構造部の上部に
設置しかつ中央部を構台の上部に設置することにより建
物の上部に架設する工程と、梁材の両下端部を結ぶよう
にして下弦ケーブルを取り付けかつ下弦ケーブルと梁材
の間に目的長さの補助ケーブルを取り付けて束材とし
下弦ケーブルを牽引することにより張設して双方の梁材
を目的の形状に起くって梁構造物を完成する工程を具備
することを特徴とする。請求項4記載の発明は、上方に
起くれてなる大型屋根構造物の施工方法であって、屋根
構造部を載置すべき建物の下部構造部を施工して建物の
中央部に屋根構造部の最上部の高さに形成された構台を
立設する工程と、この構台を中心に対向する前記下部構
造部のそれぞれの上部から構台の上部に向けて梁材を構
成する梁半材を立て掛けるとともに双方の上端部を上下
に回動自在にピン接合する工程と、双方の梁半材の下端
部を結ぶようにして下弦ケーブルを取り付けかつこの下
弦ケーブルと梁半材の間に目的の長さの補助ケーブルを
取り付けて束材とし、下弦ケーブルを構台の上部または
梁半材の下端部において牽引することにより張設して双
方の梁半材を目的の高さに上昇する工程と、目的の高さ
に上昇後前記ピン接合部分を剛接合して梁構造物を完成
する工程を備えることを特徴とする。請求項5記載の発
明は、前記請求項2または4記載の大型屋根構造物の施
工方法であって、屋根構造物を載置すべき建物の下部構
造物を施工して、前記完成した梁構造物をリフトアップ
して下部構造物の上部に設置する工程を具備することを
特徴とする。
Means for Solving the Problems] claim 1 large roof structures in the embodiment described is a large roof structure made me caused upwards, is Tatekoma on top of the lower structure portion of the building to be construction The beam structure comprises an arched beam material and a lower string cable stretched so as to connect both lower ends of the beam material. Between them, a plurality of auxiliary cables for connecting the both are attached as a bundle in the length direction of the beam structure, and the whole is formed in an upwardly convex bow or chevron shape. Claim 2
The construction method of a large-sized roof structure according to the invention described above includes installing a beam on the floor between the lower structures where the roof structure is to be constructed, and attaching a lower chord cable so as to connect both lower ends of the beam. Attach an auxiliary cable of the desired length between the lower string cable and the beam to make it a bundle, stretch it by pulling the lower cable, raise both beams to the desired shape, and complete the beam structure And a step of performing The construction method of a large-sized roof structure according to claim 3 is to construct a lower structure portion of a building on which the roof structure portion is to be mounted, and form a gantry in a central portion of the building at a height at which the roof structure portion is installed. Erecting the beam, installing the beam at the upper part of the building by installing both ends at the upper part of the lower structure part, and installing the center part at the upper part of the gantry, and connecting both lower ends of the beam. In this way, attach the lower string cable and attach the auxiliary cable of the desired length between the lower string cable and the beam material to make a bundle ,
The present invention is characterized in that a step of stretching the lower string cable by pulling the lower string cable to raise both beam members into a desired shape to complete a beam structure is provided. The invention according to claim 4 is a method for constructing a large-sized roof structure rising upward, comprising constructing a lower structure portion of a building on which the roof structure portion is to be mounted and installing the roof structure portion at the center of the building. Erecting a gantry formed at the height of the uppermost part, and leaning a beam half member constituting the beam from the upper portion of each of the lower structural portions facing the gantry toward the upper portion of the gantry. the upper portion and a step of freely pin joints rotate up and down, attached the desired length of the auxiliary cable between the both and fitted with a lower chord cable so as to connect the lower end of the beam a half member of the lower chord cable and beam half material As a bundle , a step of stretching the lower string cable by pulling it at the upper part of the gantry or at the lower end of the beam half to raise both beam halves to the target height, and after rising to the target height, Rigid beam Characterized in that it comprises the step of completing the creation. Claim 5
Ming is a method for constructing a large-sized roof structure according to claim 2 or 4 , wherein a lower structure of a building on which the roof structure is to be mounted is constructed, and the completed beam structure is lifted up. A step of installing the lower structure above the lower structure.

【0007】[0007]

【作用】前記請求項1の大型屋根構造物によれば、梁材
をアーチ構造の応力状態とすることにより軸力抵抗系を
形成し、屋根構造部の荷重を能率良く支持する結果、梁
材の断面積を小さくする。また、下弦ケーブルの牽引力
を調整することにより梁材の自重時モーメントを制御す
ることができるから、応力集中を回避することができ
る。同時に、梁材と各ケーブルからなる構造部全体を釣
り合い系として構成することが可能である。
According to the large-sized roof structure of the first aspect, an axial force resistance system is formed by setting the beam material to the stress state of the arch structure, and the load of the roof structure is efficiently supported. To reduce the cross-sectional area. Also, by adjusting the pulling force of the lower chord cable, the moment of the beam material under its own weight can be controlled, so that stress concentration can be avoided. At the same time, it is possible to configure the entire structure including the beam and each cable as a balanced system.

【0008】請求項2の大型屋根構造物の施工方法によ
れば、梁材を床部に載置した状態で下弦ケーブルの張設
を行なって梁構造物の施工を行うから、その作業性が向
上する。
According to the construction method for a large-sized roof structure according to the second aspect, the beam structure is constructed by stretching the lower chord cable while the beam material is placed on the floor, thereby improving workability. improves.

【0009】請求項3の大型屋根構造物の施工方法によ
れば、前記請求項2の発明に比して、構台が不要または
より低く形成すればよいから、屋根構造部の施工の工数
が減少する。また、梁材を水平にして下部構造部の間に
架設するから、梁材の施工位置へのセットや起くりが容
易となる。
According to the construction method for a large-sized roof structure according to the third aspect, since the gantry need not be formed or can be formed lower than the invention of the second aspect, the man-hour for the construction of the roof structure portion is reduced. I do. In addition, since the beam is horizontally installed between the lower structural parts, it is easy to set and raise the beam at the construction position.

【0010】請求項4の大型屋根構造物の施工方法によ
れば、設置位置において本設の半分の長さの梁半材を剛
接合することから、移送すべき梁半材の重量が減少して
設置位置への揚重作業が容易となる。また、梁材を下部
構造部上部に設置した状態で梁構造物の施工作業を行う
から、屋根の施工と並行して建物下部の施工を進めるこ
とができる。
According to the construction method for a large-sized roof structure of the present invention, since the beam half having a half length of the main construction is rigidly joined at the installation position, the weight of the beam half to be transferred is reduced and the beam half is moved to the installation position. Lifting work becomes easier. Moreover, since the construction work of the beam structure is performed in a state where the beam material is installed on the upper part of the lower structure, the construction of the lower part of the building can be advanced in parallel with the construction of the roof.

【0011】請求項5の大型屋根構造物の施工方法によ
れば、梁構造物を設置位置下方の床部で完成した後に設
置位置にセットするから、梁材の屈曲後の長さなどと設
置位置の形状との調整を梁材をリフトアップする前に行
なうことができて、施工精度が向上する。
According to the construction method for a large-sized roof structure according to the fifth aspect, the beam structure is set at the installation position after the beam structure is completed on the floor below the installation position. Adjustment with the shape of the position can be performed before the beam material is lifted up, and construction accuracy is improved.

【0012】[0012]

【実施例】以下、図1ないし図7を参照して本発明の大
型屋根構造物を説明する。図1に示す符号10は、本実
施例の屋根構造部である。
DETAILED DESCRIPTION OF THE PREFERRED EMBODIMENTS A large-sized roof structure according to the present invention will be described below with reference to FIGS. Reference numeral 10 shown in FIG. 1 denotes a roof structure of the present embodiment.

【0013】図1及び図2に示すように、前記屋根構造
部10は、アーチ状の梁材11と、この梁材11の両下
端部を連結するようにして張設された下弦ケーブル12
と、梁材11と下弦ケーブル12の間を梁材11の長さ
方向適切位置に取り付けられた複数の補助ケーブル13
とで構成されてなる梁構造物14を下部構造物の上部に
複数立て込み、これら梁構造物14にその上面から覆う
ように屋根板材10aを取り付けることにより平面視円
型のドーム状に形成されている。
As shown in FIGS. 1 and 2, the roof structure 10 includes an arched beam 11 and a lower chord cable 12 stretched so as to connect both lower ends of the beam 11.
And a plurality of auxiliary cables 13 attached between the beam 11 and the lower string cable 12 at appropriate positions in the length direction of the beam 11
A plurality of beam structures 14 are formed on the upper part of the lower structure, and a roof dome material 10a is attached to these beam structures 14 so as to cover the upper surfaces thereof, thereby forming a circular dome shape in plan view. ing.

【0014】梁材11は、アーチ構造の応力状態を形成
することにより荷重に対して軸力抵抗系を構成するアー
チ状であって、屋根構造部10の外縁に沿って施工した
平面視円型の下部構造部15の上に直径の位置で載置し
て両下端部を固定することにより架設されている。
The beam member 11 has an arch shape that forms an axial force resistance system by forming a stress state of the arch structure, and is formed along the outer edge of the roof structure 10 in a circular shape in a plan view. Is mounted on the lower structure portion 15 at a diameter position and fixed at both lower end portions.

【0015】下弦ケーブル12は、梁材11の両下端部
の間で梁材11より大きい半径の概略梁材11に沿う円
弧もしくはそれに近い形をを形成している。補助ケーブ
ル13は、梁材11の頂部とその両翼において左右対象
となるように略等間隔で取り付けられている。図3、図
4及び図5に示すように、下弦ケーブル12と補助ケー
ブル13は、互いに固定または水平動自在として接続さ
れている。
The lower chord cable 12 is formed between the lower end portions of the beam member 11 and has an arc having a radius larger than the beam member 11 along the beam member 11 or a shape close thereto. The auxiliary cables 13 are attached at substantially equal intervals so as to be symmetrical at the top of the beam member 11 and both wings. As shown in FIGS. 3, 4, and 5, the lower string cable 12 and the auxiliary cable 13 are connected to each other so as to be fixed or horizontally movable.

【0016】図3に示すように、下弦ケーブル12と補
助ケーブル13を互いに固定して接続する方法として
は、下弦ケーブル12を構成する下弦ケーブル分体12
aをケーブル取り付けプレート16を介してその長さ方
向に接続するとともに、ケーブル取り付けプレート16
に補助ケーブル13を取り付ける。各ケーブルは、端部
に係止金具17を取り付けるとともにこの係止金具17
の中央部に形成されている止め金具挿入孔17aをケー
ブル取り付けプレート16の端部に形成された止め金具
挿入孔16aに一致させるとともに、双方の止め金具挿
入孔16a、17aに棒状の止め金具18を連通するこ
とにより接続するようになっている。この方法の場合、
各ケーブルは、ケーブル取り付けプレート16に対して
それぞれ回動自在に取り付られる。
As shown in FIG. 3, as a method of fixing and connecting the lower string cable 12 and the auxiliary cable 13 to each other, a lower string cable segment 12 forming the lower string cable 12 is used.
a in its length direction via a cable mounting plate 16 and the cable mounting plate 16
Auxiliary cable 13 is attached. Each cable is provided with a locking member 17 at an end thereof and the locking member 17.
The stopper fitting hole 17a formed at the center of the cable fitting plate 16 matches the stopper fitting hole 16a formed at the end of the cable mounting plate 16, and both stopper fitting holes 16a and 17a have rod-shaped stoppers 18 respectively. Are connected to each other. In this case,
Each cable is rotatably attached to the cable mounting plate 16.

【0017】一方、図4に示すように、互いに水平動自
在に接続する方法としては、補助ケーブル13の下端部
に第1の接続金具19を取り付け、この第1の接続金具
19の中央部に設けられたケーブル挿通孔19aに下弦
ケーブル12を挿通する。また、図5に示すように、図
4に示す方法のほか、補助ケーブル13の下端部に前記
係止金具17を取り付け、この係止金具17と第2の接
続金具20とを止め金具18を介して回動自在に連結す
ることにより補助ケーブル13と下弦ケーブル12を接
続する方法であっても良い。この方法の場合、係止金具
17が第2の接続金具20に対して上下方向に回動自在
であるから、下弦ケーブル12の取り付け時における水
平移動に対して第2の接続金具20が自由に方向を変え
ることができて下弦ケーブル12の施工及び張設作業が
容易となる。
On the other hand, as shown in FIG. 4, as a method of connecting to each other so as to be able to move horizontally, a first connection fitting 19 is attached to the lower end of the auxiliary cable 13, and the center of the first connection fitting 19 is attached to The lower string cable 12 is inserted into the provided cable insertion hole 19a. As shown in FIG. 5, in addition to the method shown in FIG. 4, the lock 17 is attached to the lower end of the auxiliary cable 13, and the lock 18 and the second connection 20 are connected to the lock 18. The auxiliary cable 13 and the lower string cable 12 may be connected by being rotatably connected via a cable. In the case of this method, since the locking fitting 17 is rotatable in the vertical direction with respect to the second connecting fitting 20, the second connecting fitting 20 is free to move horizontally when the lower string cable 12 is attached. The direction can be changed, and the construction and stretching work of the lower string cable 12 become easy.

【0018】前記屋根構造部10によれば、梁材11を
アーチ構造の応力状態とすることにより軸力抵抗系を形
成するから、屋根構造部10の荷重を能率良く支持する
ことにより梁材11の断面積を小さく形成して、重量の
低減による施工性の向上及び施工コストの低減を可能に
することができる。また、起くり時の下弦ケーブル12
の牽引力を調整することにより梁材11の自重時モーメ
ントを制御することができるから、応力集中を回避する
ことができて前記梁材11の断面積を一層小型として形
成することが可能となる。同時に、梁構造物14は、全
体を釣り合い系として構成することができるから、下端
部における水平スラストを無くすことができる。
According to the roof structure 10, since the axial force resistance system is formed by setting the beam 11 to the stress state of the arch structure, the beam 11 can be efficiently supported by supporting the load of the roof structure 10. Can be formed to have a small cross-sectional area, thereby making it possible to improve workability and reduce construction costs by reducing the weight. Also, the lower string cable 12 at the time of rising
By adjusting the traction force, the moment of the beam 11 under its own weight can be controlled, so that stress concentration can be avoided and the cross-sectional area of the beam 11 can be made smaller. At the same time, since the entire beam structure 14 can be configured as a balancing system, horizontal thrust at the lower end can be eliminated.

【0019】なお、図6に示すように、前記梁構造物1
4と梁構造物14を載置すべき下部構造部との組み合わ
せにより、建築物を蒲鉾状などに構成することも可能で
ある。
As shown in FIG. 6, the beam structure 1
It is also possible to configure the building into a kamaboko shape or the like by a combination of 4 and a lower structure on which the beam structure 14 is to be placed.

【0020】以下、本発明の第1実施例を図7及び図8
を参照して説明する。本実施例の大型屋根構造物の施工
方法により前記屋根構造部10を施工するには、以下の
ように行なう。
Hereinafter, a first embodiment of the present invention will be described with reference to FIGS.
This will be described with reference to FIG. The construction of the roof structure 10 by the construction method of the large-sized roof structure according to the present embodiment is performed as follows.

【0021】すなわち、図7に示すように、まず、屋根
構造部10を載置すべき建物21の下部構造部15を施
工して、かつ対向する下部構造部15の間に施工すべき
梁材11を施工位置の下方の床部上に載置する。
That is, as shown in FIG. 7, first, the lower structural part 15 of the building 21 on which the roof structural part 10 is to be mounted is constructed and the beam material to be constructed between the opposing lower structural parts 15 is constructed. 11 is placed on the floor below the construction position.

【0022】図8に示すように、前記梁材11の設置が
完了したら、梁材11の両下端部を結ぶようにして下弦
ケーブル12を取り付けかつこの下弦ケーブル12と梁
材11の間に目的の長さの補助ケーブル13を取り付け
る。補助ケーブル13の下弦ケーブル12への取り付け
は、前記ケーブル取り付けプレート16、第1の接続金
具19または第2の接続金具20を介して行なう。下弦
ケーブル12及び補助ケーブル13の取り付けが完了し
たら、梁材11の両端部で下弦ケーブル12を牽引する
ことにより梁材11を目的の形状に起くると同時に下弦
ケーブル12を梁材11の両下端部を結ぶように張設し
て梁構造物14を構成する。
As shown in FIG. 8, when the installation of the beam member 11 is completed, the lower string cable 12 is attached so as to connect both lower ends of the beam member 11, and an object is provided between the lower string cable 12 and the beam member 11. Is attached. The attachment of the auxiliary cable 13 to the lower string cable 12 is performed via the cable attachment plate 16, the first connection fitting 19 or the second connection fitting 20. When the lower string cable 12 and the auxiliary cable 13 are attached, the lower string cable 12 is pulled to the desired shape by pulling the lower string cable 12 at both ends of the beam 11, and the lower string cable 12 is connected to both lower ends of the beam 11. The beam structure 14 is formed by extending the connecting portions.

【0023】梁材11の起くりが完了したら梁構造物1
4の両端部にリフトアップ機構23、23を取り付け、
図2に示すように、梁構造物14を下部構造部15の上
部の施工位置にリフトアップして両下端部を目的位置へ
固定する。
When the raising of the beam member 11 is completed, the beam structure 1
Attach lift-up mechanisms 23, 23 to both ends of 4,
As shown in FIG. 2, the beam structure 14 is lifted up to a construction position above the lower structure portion 15 and both lower end portions are fixed to the target positions.

【0024】前記のように構成される本実施例の大型屋
根構造物の施工方法によれば、前記張設時の下弦ケーブ
ル12の張力が全体に等しく作用して梁材11の偏荷重
負荷に対する耐力が向上するから、梁材11断面積のさ
らなる小型化を可能となって梁材11が軽量化してその
施工位置への移送が容易であるほか、梁材11を形成す
る材料を節約して屋根構造部10の製造コストを低減す
ることができる。
According to the construction method of the large-sized roof structure of the present embodiment configured as described above, the tension of the lower chord cable 12 at the time of the above-mentioned stretching acts equally on the whole, so that the beam member 11 can bear the uneven load. Since the proof strength is improved, the cross-sectional area of the beam 11 can be further reduced, the beam 11 can be reduced in weight, and can be easily transferred to the construction position, and the material for forming the beam 11 can be saved. The manufacturing cost of the roof structure 10 can be reduced.

【0025】また、本実施例の大型屋根構造物の施工方
法によれば、梁材11の荷重を下弦ケーブル12の牽引
力で負担して構台22の負担する荷重が減少するから、
構台22を簡便なものとしてその施工能率を向上するこ
とができ、大型屋根構造物の工期を短縮することができ
る。
Further, according to the construction method of the large-sized roof structure of the present embodiment, the load on the beam 22 is reduced by the pulling force of the lower string cable 12 and the load on the gantry 22 is reduced.
The gantry 22 can be simplified to improve its construction efficiency, and the construction period of a large roof structure can be shortened.

【0026】一方、梁構造物14を梁材11と下弦ケー
ブル12及び補助ケーブル13を組み合わせることによ
り構成するから、施工が容易でかつ建て方精度の必要性
を低減することにより施工能率が向上するほか、梁材1
1を床部に載置した状態で下弦ケーブル12の張設を行
なうから、作業性が向上して作業能率の向上が可能とな
る。また、梁材11を設置位置垂直下方の床部で起くっ
た後に設置位置にセットするから、梁材11の屈曲後の
取り付け端部と下部構造部15に設けられた設置位置の
形状との調整を梁材11の上げ下ろしを繰り返すことな
くリフトアップする前に容易に行なうことができる。
On the other hand, since the beam structure 14 is constituted by combining the beam member 11, the lower string cable 12, and the auxiliary cable 13, the construction is easy and the necessity of the building accuracy is reduced, thereby improving the construction efficiency. In addition, beam material 1
Since the lower string cable 12 is stretched in a state where the cable 1 is placed on the floor, workability is improved and work efficiency can be improved. In addition, since the beam 11 is set at the installation position after being raised on the floor vertically below the installation position, the shape of the installation end provided after the bending of the beam 11 and the installation position provided on the lower structure portion 15 is different. Adjustment can be easily performed before lifting up without repeating raising and lowering of the beam material 11.

【0027】以下、本発明の第2実施例を図9及び図1
0を参照して説明する。本実施例の大型屋根構造物の施
工方法により前記屋根構造部10を施工するには以下の
ように行なう。
Hereinafter, a second embodiment of the present invention will be described with reference to FIGS.
0 will be described. The construction of the roof structure 10 by the construction method of the large-sized roof structure according to the present embodiment is performed as follows.

【0028】まず、図9に示すように、屋根構造部10
を載置すべき建物21の下部構造部15を施工してかつ
建物21の中央部に構台22を立設する。構台22は、
屋根構造部10の下端部が設置される下部構造部15の
高さに形成して立設する。構台22は、直の梁材11を
起くる直前まで支持するためのものであって、下部構造
部15、15間が短ければ設ける必要は無い。
First, as shown in FIG.
The lower structural part 15 of the building 21 on which is to be mounted is constructed, and the gantry 22 is erected at the center of the building 21. The gantry 22
It is formed at the height of the lower structure 15 where the lower end of the roof structure 10 is installed and stands upright. The gantry 22 is provided to support the beam member 11 up to immediately before it rises, and need not be provided if the space between the lower structural parts 15 is short.

【0029】次いで、図10に示すように、前記梁材1
1を両端部を下部構造部15の設置位置に載置しかつ中
央部を構台22の上部に設置することにより建物21の
上部に架設する。架設の完了した梁材11には、両下端
部を結ぶようにして下弦ケーブル12を取り付けかつ下
弦ケーブル12と梁材11の間に目的長さの補助ケーブ
ル13を取り付ける。そして、図10に示すように、こ
の状態で下弦ケーブル12を梁材11の下端部において
牽引して張設することにより梁材11を上方に起くって
前記梁構造物14を構成する。また、梁構造物14の完
成後は、両下端部を下部構造部15上部に固定してその
設置を完了する。
Next, as shown in FIG.
1 is placed on the upper part of the building 21 by placing both ends at the installation position of the lower structure part 15 and installing the center part on the upper part of the gantry 22. The lower string cable 12 is attached to the beam material 11 having been installed so as to connect both lower ends, and an auxiliary cable 13 having a desired length is attached between the lower string cable 12 and the beam material 11. Then, as shown in FIG. 10, in this state, the lower chord cable 12 is pulled and stretched at the lower end portion of the beam member 11, thereby raising the beam member 11 to configure the beam structure 14. After the beam structure 14 is completed, both lower ends are fixed to the upper portion of the lower structure portion 15 to complete the installation.

【0030】したがって、本実施例の大型屋根構造物の
施工方法によれば、前記第1実施例の発明と同様の効果
を奏する。また、梁材11を水平にして下部構造部15
の間に架設するから、梁材11の施工位置へのセットや
起くりが容易となるほか、梁材11を起くりの前に施工
位置にセットすることから、梁材11の施工位置への位
置調整が容易であってその施工性が向上する。
Therefore, according to the method for constructing a large-sized roof structure of the present embodiment, the same effects as those of the first embodiment can be obtained. In addition, the beam 11 is leveled and the lower structure 15
Since it is erected between the beams, it is easy to set and raise the beam 11 at the construction position, and since the beam 11 is set at the construction position before raising, the beam 11 can be moved to the construction position. Position adjustment is easy and the workability is improved.

【0031】以下、側面視山形の屋根構造部10aを施
工するための本発明の第3実施例を図11ないし図13
を参照して説明する。図11に示すように、前記屋根構
造物10aは、前記屋根構造物10の梁材11を起くる
ことなく、直のままの状態で接合することにより固定し
て、山形に形成されている。
Hereinafter, a third embodiment of the present invention for constructing a roof structure 10a having a mountain shape in side view will be described with reference to FIGS.
This will be described with reference to FIG. As shown in FIG. 11, the roof structure 10a is formed in a mountain shape by being fixed by being joined in a straight state without raising the beam material 11 of the roof structure 10.

【0032】本実施例の大型屋根構造物の施工方法によ
り前記屋根構造物10aを施工するには、図12に示す
ようにまず、構台22を中心に、対向する前記下部構造
部15のそれぞれの上部から構台22の上部に向けて前
記梁材11を形成する梁半材11aを立て掛ける。そし
て、梁半材11a、11aの互いの上端部を起くり時に
適切な角度で上下に回動自在にピン接合する。なお、梁
半材11aは、梁材11の略半分の長さに形成された梁
材11を構成する直の部材である。
In order to construct the roof structure 10a by the method for constructing a large roof structure according to this embodiment, first, as shown in FIG. A beam half 11a forming the beam 11 is leaned from the upper part toward the upper part of the gantry 22. Then, when the upper ends of the beam half members 11a, 11a are raised, they are pin-joined so as to be rotatable up and down at an appropriate angle. The beam half 11a is a straight member that constitutes the beam 11 formed to be approximately half the length of the beam 11.

【0033】前記ピン接合が完了したら、双方の梁半材
11aの下端部を結ぶようにして下弦ケーブル12を取
り付けかつこの下弦ケーブル12と梁材11aの間に目
的の長さの補助ケーブル13を取り付ける。補助ケーブ
ル13の下弦ケーブル12への取り付けは、前記ケーブ
ル取り付けプレート16、第1の接続金具19または第
2の接続金具20を介して行なう。
After the pin connection is completed, the lower string cable 12 is attached so as to connect the lower ends of both beam halves 11a, and an auxiliary cable 13 having a desired length is attached between the lower string cable 12 and the beam 11a. The attachment of the auxiliary cable 13 to the lower string cable 12 is performed via the cable attachment plate 16, the first connection fitting 19 or the second connection fitting 20.

【0034】図13に示すように、下弦ケーブル12及
び補助ケーブル13の取り付けが完了したら、下弦ケー
ブル12を牽引することにより張設して梁材11を中央
部が構台22の最上部の高さとなるまで上昇させる。な
お、上昇の際に要する下弦ケーブル12の牽引力は、揚
重すべき荷重の1.5倍程度であり、通常のケーブルへ
の張力導入用のジャッキをそのまま用いることができ
る。
As shown in FIG. 13, when the lower string cable 12 and the auxiliary cable 13 have been attached, the lower string cable 12 is pulled to stretch the beam 11 so that the center of the beam 11 is at the height of the top of the gantry 22. Raise until it becomes. Note that the traction force of the lower string cable 12 required for ascending is about 1.5 times the load to be lifted, and a normal jack for introducing tension into the cable can be used as it is.

【0035】前記梁材11の目的の高さへの上昇が完了
したら、前記ピン接合部分を剛接合した後、他の部分を
施工して、屋根構造物10aを完成する。
When the beam 11 has been raised to the desired height, the pin joint is rigidly joined, and then the other parts are constructed to complete the roof structure 10a.

【0036】前記工程の完了後、建物21内部の施工を
完了して前記構台22を撤去することにより建物21全
体の構成を完了する。
After the completion of the above steps, the construction inside the building 21 is completed and the gantry 22 is removed to complete the entire structure of the building 21.

【0037】本実施例の大型屋根構造物の施工方法によ
れば、梁材11の施工を梁半材11aを梁材11の施工
位置にセットした状態で接合して行なうから、梁材11
に比して重量が半分の梁半材11aの移送が容易で施工
能率が向上する上、梁半材11aの設置位置が高くかつ
梁材11に概略沿った上に凸の曲線を形成するように張
設するから、施工中に梁構造物14下部に形成される空
間を利用して建物21の梁材11の施工と同時に梁構造
物14の下方に位置する屋根構造部10a及び下部構造
部15などの施工作業並行することができ、屋根構造物
10aの一層の施工能率の向上が可能となる。
According to the method for constructing a large-sized roof structure according to the present embodiment, since the beam 11 is joined while the beam half 11a is set at the construction position of the beam 11, the beam 11 is joined.
The half beam 11a, which is half the weight of the beam half 11a, can be easily transported, the construction efficiency is improved, and the beam half 11a is installed at a high position and is formed so as to form an upwardly convex curve substantially along the beam member 11. From the above, at the same time as the construction of the beam material 11 of the building 21 using the space formed under the beam structure 14 during the construction, the construction of the roof structure 10a and the lower structure 15 located below the beam structure 14 The work can be performed in parallel, and the construction efficiency of the roof structure 10a can be further improved.

【0038】[0038]

【発明の効果】以上説明したように、前記請求項1記載
の本発明の大型屋根構造物では、上方に起くれてなる大
型屋根構造物であって、施工すべき建物の下部構造部の
上部に建て込まれた複数の梁構造物を備えてなり、梁構
造物はアーチ状の梁材と、この梁材の両下端部を連結す
るようにして張設された下弦ケーブルとからなり、梁材
と下弦ケーブルの間には双方を連結する補助ケーブルが
束材として梁構造物の長さ方向に複数取り付けられて全
体が上方に凸の弓型または山形に形成することを特徴と
することを特徴とするから、梁材をアーチ構造の応力状
態とすることにより軸力抵抗系を形成し、屋根構造部の
荷重を能率良く支持する結果、梁材の断面積を小さくし
て、梁材の施工性及び施工コストの低減が可能となる。
As described above, the large-sized roof structure according to the first aspect of the present invention is a large-sized roof structure rising upward, which is located above a lower structural portion of a building to be constructed. The beam structure comprises an arch-shaped beam material and a lower chord cable stretched so as to connect both lower ends of the beam material. Auxiliary cable connecting both materials and lower string cable
A plurality of beams are attached in the length direction of the beam structure as a bundle, and the whole is formed in an upwardly convex bow shape or mountain shape, so that the beam material is in a stress state of the arch structure. As a result, the axial force resistance system is formed, and the load of the roof structure is efficiently supported. As a result, the cross-sectional area of the beam is reduced, and the workability and the construction cost of the beam can be reduced.

【0039】また、下弦ケーブルの牽引力を調整するこ
とにより梁材の自重時モーメントを制御することができ
るから、応力集中を回避することができて前記梁材の断
面積を一層小型として形成することが可能となる。同時
に、梁材と各ケーブルからなる構造部全体を釣り合い系
として構成することが可能であるから、この構造部の下
端部における水平スラストを無くして、建物の構造及び
その設計を簡単にすることができる。
Further, by adjusting the pulling force of the lower string cable, the moment of the beam under its own weight can be controlled, so that stress concentration can be avoided and the cross-sectional area of the beam can be made smaller. Becomes possible. At the same time, it is possible to configure the entire structure consisting of the beam and each cable as a balanced system.Therefore, it is possible to eliminate the horizontal thrust at the lower end of this structure, thereby simplifying the structure of the building and its design. it can.

【0040】さらに、接合前に梁材を下部構造部の上部
にリフトアップしてセットするから、梁材の施工と同時
に梁構造物の下方に位置する建物の施工を進めることが
容易である上、下弦ケーブルを梁材に概略沿った上に凸
の曲線を形成するように張設して施工中に下弦ケーブル
下部に形成される空間を利用して建物の他の部分の施工
作業に有効に利用することができるから、一層の施工能
率の向上が可能である。
Furthermore, since the beam is lifted up and set on the upper part of the lower structure before joining, it is easy to proceed with the construction of the building located below the beam structure simultaneously with the construction of the beam. The lower cable is stretched so as to form an upwardly convex curve roughly along the beam material, making effective use of the space formed below the lower cable during the construction work for other parts of the building Since it can be used, construction efficiency can be further improved.

【0041】前記の結果、梁材断面積のさらなる小型化
を可能とするから、梁材が軽量化してその施工位置への
移送が容易であるほか、梁材を形成する材料を節約して
屋根構造部の製造コストを低減することができる。ま
た、前記張設時の下弦ケーブルの張力が全体に等しく作
用するから、偏荷重負荷に対する耐力が向上する。
As a result of the above, since the cross-sectional area of the beam material can be further reduced, the weight of the beam material can be reduced and the material can be easily transported to the construction position. The manufacturing cost of the structure can be reduced. In addition, since the tension of the lower string cable at the time of the stretching works equally on the whole, the strength against the uneven load is improved.

【0042】本発明の前記請求項2の大型屋根構造物の
施工方法によれば、屋根構造を施工すべき下部構造部の
間の床部に梁材を設置するとともにこの梁材の両下端部
を結ぶようにして下弦ケーブルを取り付けかつ下弦ケー
ブルと梁材の間に目的長さの補助ケーブルを取り付け
束材とし、下弦ケーブルを牽引することにより張設して
双方の梁材を目的の形状に起くって梁構造物を完成する
工程を具備することを特徴とするから、梁材を床部に載
置した状態で下弦ケーブルの張設を行なうことにより、
作業性が向上して施工能率及び施工能率の向上が可能と
なる。
According to the method for constructing a large-sized roof structure according to the second aspect of the present invention, a beam is installed on the floor between the lower structures where the roof structure is to be constructed, and both lower ends of the beam are installed. Attach the auxiliary cable object length between the mounting of the lower chord cables and lower chord cables and beam members so as to connect the
It is characterized by having a process of completing the beam structure by bundling and stretching the lower string cable by pulling the lower string cable to raise both beam materials to the desired shape, so that the beam material is put on the floor By stretching the lower string cable with it placed,
Workability is improved, and construction efficiency and construction efficiency can be improved.

【0043】本発明の請求項3の大型屋根構造物の施工
方法によれば、屋根構造部を載置すべき建物の下部構造
部を施工して建物の中央部に構台を屋根構造部を設置す
る高さに形成して立設する工程と、前記梁材を両端部を
下部構造部の上部に設置しかつ中央部を構台の上部に設
置することにより建物の上部に架設する工程と、梁材の
両下端部を結ぶようにして下弦ケーブルを取り付けかつ
下弦ケーブルと梁材の間に目的長さの補助ケーブルを取
り付けて束材とし、下弦ケーブルを牽引することにより
張設して双方の梁材を目的の形状に起くって梁構造物を
完成する工程を具備することを特徴とするから、前記請
求項2の発明と同様の効果を奏することは勿論、前記請
求項2の発明に比して、構台が不要またはより低く形成
すればよいから、屋根構造部の施工の工数が減少する。
また、梁材を水平にして下部構造部の間に架設するか
ら、梁材の施工位置へのセットや起くりが容易となっ
て、一層の施工能率の向上が可能となるほか、梁材を起
くりの前に施工位置にセットすることにより梁材の施工
位置への位置調整が容易となってその施工性が向上す
る。
According to the method for constructing a large-sized roof structure according to claim 3 of the present invention, the lower structure of the building on which the roof structure is to be mounted is constructed, and the gantry and the roof structure are installed at the center of the building. Erecting the beam at the height of the building, erecting the beam at the upper part of the building by installing both ends at the upper part of the lower structure part and installing the center part at the upper part of the gantry, Attach the lower string cable so as to connect both lower ends of the material, and attach an auxiliary cable of the desired length between the lower string cable and the beam material to form a bundle. Since the method is provided with a step of completing the beam structure by raising the material to a desired shape, the same effect as that of the invention of claim 2 can be obtained. Then, since the gantry is unnecessary or may be formed lower, Man-hours of construction of the root structure is reduced.
In addition, since the beam is installed horizontally between the lower structural parts, it is easy to set and raise the beam at the construction position, which can further improve the construction efficiency and By setting the beam material at the construction position before rising, the position adjustment of the beam material to the construction position becomes easy, and the workability is improved.

【0044】前記請求項4の大型屋根構造物の施工方法
によれば、上方に起くれてなる大型屋根構造物の施工方
法であって、屋根構造部を載置すべき建物の下部構造部
を施工して建物の中央部に屋根構造部の最上部の高さに
形成された構台を立設する工程と、この構台を中心に対
向する前記下部構造部のそれぞれの上部から構台の上部
に向けて梁材を構成する梁半材を立て掛けるとともに双
方の上端部を上下に回動自在にピン接合する工程と、双
方の梁半材の下端部を結ぶようにして下弦ケーブルを取
り付けかつこの下弦ケーブルと梁半材の間に目的の長さ
の補助ケーブルを取り付けて束材とし、下弦ケーブルを
構台の上部または梁半材の下端部において牽引すること
により張設して双方の梁半材を目的の高さに上昇する工
程と、目的の高さに上昇後前記ピン接合部分を剛接合し
て梁構造物を完成する工程を備えることを特徴とするか
ら、梁構造物を梁材と下弦ケーブル及び補助ケーブルを
組み合わせることにより簡単に構成することができ、そ
の施工が容易でかつ建て方精度の必要性を低減するほ
か、梁半材は梁材に比して軽量で移送が簡単であるから
その施工位置へのセットが容易となって屋根構造物の施
工能率が向上する。
According to the method for constructing a large-sized roof structure according to the fourth aspect of the present invention, there is provided a method for constructing a large-sized roof structure rising upward, wherein a lower structural portion of a building on which the roof structural portion is to be mounted is provided. Erecting a gantry formed at the height of the top of the roof structure in the center of the building by performing construction, and directing the gantry from the upper portion of each of the lower structures facing the center to the upper portion of the gantry. Setting the upper half of the beam half up and down and pivotally connecting the upper and lower ends of the beam half, and attaching the lower string cable so as to connect the lower ends of both the beam half and the lower string cable and the beam half. Attaching an auxiliary cable of the desired length to the bundle, and stretching the lower string cable by pulling it at the top of the gantry or the lower end of the beam half to raise both beam halves to the desired height; and Height Since the method includes a step of rigidly joining the pin joint portion after the ascending to complete the beam structure, the beam structure can be easily configured by combining the beam material, the lower string cable, and the auxiliary cable. In addition to the ease of construction and the reduction in the need for accuracy in building, the beam half is lighter and easier to transport than the beam, so it can be easily set in the construction position and the roof structure can be constructed. Efficiency is improved.

【0045】請求項5の大型屋根構造物の施工方法によ
れば、屋根構造物を載置すべき建物の下部構造物を施工
して、前記完成した梁構造物をリフトアップして下部構
造物の上部に設置する工程を具備することを特徴とする
から、梁材を設置位置垂直下方の床部で梁構造物を完成
した後に設置位置にセットすることにより、梁材の上昇
後の取り付け端部と下部構造部に設けられた設置位置の
形状との調整を梁材の上げ下ろしを繰り返すことなくリ
フトアップする前に容易に行なうことができ、施工精度
が向上する。
According to the construction method for a large-sized roof structure according to the fifth aspect, the lower structure of the building on which the roof structure is to be mounted is constructed, and the completed beam structure is lifted up. It is characterized by having a process of installing the beam on the upper part of the beam, and setting the beam at the installation position after completing the beam structure on the floor vertically below the installation position, so that the mounting end of the beam after rising Adjustment of the shape of the installation position provided in the part and the lower structure part can be easily performed before lifting up without repeatedly raising and lowering the beam material, and the construction accuracy is improved.

【図面の簡単な説明】[Brief description of the drawings]

【図1】本発明の大型屋根構造物の一実施例を示す斜視
図である。
FIG. 1 is a perspective view showing one embodiment of a large-sized roof structure according to the present invention.

【図2】前記正断面図である。FIG. 2 is the front sectional view.

【図3】前記ケーブル取り付けプレートを示す斜視図で
ある。
FIG. 3 is a perspective view showing the cable attachment plate.

【図4】前記各ケーブルを連結する第1の接続金具を示
す斜視図である。
FIG. 4 is a perspective view showing a first connection fitting for connecting the cables.

【図5】前記第2の接続金具を示す斜視図である。FIG. 5 is a perspective view showing the second connection fitting.

【図6】前記他の建物の例を示す斜視図である。FIG. 6 is a perspective view showing an example of the other building.

【図7】本発明の第1実施例の初期段階を示す施工手順
図である。
FIG. 7 is a construction procedure diagram showing an initial stage of the first embodiment of the present invention.

【図8】前記梁構造物の施工を示す施工手順図である。FIG. 8 is a construction procedure diagram showing the construction of the beam structure.

【図9】本発明の第2実施例の初期段階を示す施工手順
図である。
FIG. 9 is a construction procedure diagram showing an initial stage of the second embodiment of the present invention.

【図10】前記梁構造物の施工を示す施工手順図であ
る。
FIG. 10 is a construction procedure diagram showing construction of the beam structure.

【図11】本発明の第3実施例の施工方法により施工す
べき大屋根構造物を示す側面図である。
FIG. 11 is a side view showing a large roof structure to be constructed by the construction method of the third embodiment of the present invention.

【図12】前記梁半材の設置を示す施工手順図である。FIG. 12 is a construction procedure diagram showing installation of the beam half.

【図13】前記梁構造物の施工を示す施工手順図であ
る。
FIG. 13 is a construction procedure diagram showing the construction of the beam structure.

【符号の説明】[Explanation of symbols]

10 屋根構造部 11 梁材 11a 梁半材 12 下弦ケーブル 13 補助ケーブル 14 梁構造物 15 下部構造部 21 建物 22 構台 DESCRIPTION OF SYMBOLS 10 Roof structure part 11 Beam material 11a Beam half material 12 Lower string cable 13 Auxiliary cable 14 Beam structure 15 Lower structure part 21 Building 22 Gantry

───────────────────────────────────────────────────── フロントページの続き (72)発明者 谷口 尚範 東京都港区芝浦一丁目2番3号 清水建 設株式会社内 (72)発明者 鈴木 健司 東京都港区芝浦一丁目2番3号 清水建 設株式会社内 (56)参考文献 特開 平3−241128(JP,A) 特開 平3−90783(JP,A) 特開 平3−228983(JP,A) 特開 昭64−6429(JP,A) (58)調査した分野(Int.Cl.7,DB名) E04B 1/34 E04B 1/32 102 E04C 3/10 E04G 21/14 ────────────────────────────────────────────────── ─── Continuing on the front page (72) Inventor Naomori Taniguchi 1-3-2 Shibaura, Minato-ku, Tokyo Shimizu Corporation (72) Inventor Kenji Suzuki 1-2-3 Shibaura, Minato-ku, Tokyo Shimizu (56) References JP-A-3-241128 (JP, A) JP-A-3-90783 (JP, A) JP-A-3-228983 (JP, A) JP-A 64-6429 JP, A) (58) Field surveyed (Int. Cl. 7 , DB name) E04B 1/34 E04B 1/32 102 E04C 3/10 E04G 21/14

Claims (5)

(57)【特許請求の範囲】(57) [Claims] 【請求項1】 上方に起くれてなる大型屋根構造物であ
って、施工すべき建物の下部構造部の上部に建て込まれ
た複数の梁構造物を備えてなり、梁構造物はアーチ状の
梁材と、この梁材の両下端部を連結するようにして張設
された下弦ケーブルとからなり、梁材と下弦ケーブルの
間には双方を連結する補助ケーブルが束材として梁構造
物の長さ方向に複数取り付けられて全体が上方に凸の弓
または山形に形成することを特徴とする大型屋根構造
物。
1. A large-sized roof structure rising upward, comprising a plurality of beam structures built above a lower structure portion of a building to be constructed, wherein the beam structure has an arch shape. And a lower chord cable stretched so as to connect both lower ends of the beam material, and an auxiliary cable connecting the both is connected between the beam material and the lower chord cable as a bundle . A large-sized roof structure, wherein a plurality of roof structures are attached in the longitudinal direction of the roof, and the whole is formed in an upwardly convex bow shape or mountain shape.
【請求項2】 屋根構造を施工すべき下部構造部の間の
床部に梁材を設置するとともにこの梁材の両下端部を結
ぶようにして下弦ケーブルを取り付けかつ下弦ケーブル
と梁材の間に目的長さの補助ケーブルを取り付けて束材
とし、下弦ケーブルを牽引することにより張設して双方
の梁材を目的の形状に起くって梁構造物を完成する工程
を具備することを特徴とする大型屋根構造物の施工方
法。
2. A beam material is installed on the floor between the lower structural parts on which the roof structure is to be constructed, and a lower string cable is attached so as to connect both lower ends of the beam material. Attach an auxiliary cable of the desired length to the bundle
A method for constructing a large-sized roof structure, comprising a step of stretching the lower string cable by pulling the lower string cable to raise both beam members into a desired shape to complete the beam structure.
【請求項3】 屋根構造部を載置すべき建物の下部構造
部を施工して建物の中央部に構台を屋根構造部を設置す
る高さに形成して立設する工程と、前記梁材を両端部を
下部構造部の上部に設置しかつ中央部を構台の上部に設
置することにより建物の上部に架設する工程と、梁材の
両下端部を結ぶようにして下弦ケーブルを取り付けかつ
下弦ケーブルと梁材の間に目的長さの補助ケーブルを取
り付けて束材とし、下弦ケーブルを牽引することにより
張設して双方の梁材を目的の形状に起くって梁構造物を
完成する工程を具備することを特徴とする大型屋根構造
物の施工方法。
3. A step of constructing a lower structure portion of a building on which a roof structure portion is to be mounted, forming a gantry in a central portion of the building at a height at which the roof structure portion is to be installed, and erecting the beam material. Installing both ends on the upper part of the lower structural part and installing the center part on the upper part of the gantry at the top of the building, attaching the lower chord cable so as to connect both lower end parts of the beam material, and A process of attaching a supplementary cable of the desired length between the cable and the beam to form a bundle, stretching the lower string cable by pulling it, and raising both beams to the desired shape to complete the beam structure A method for constructing a large roof structure, comprising:
【請求項4】 上方に起くれてなる大型屋根構造物の施
工方法であって、屋根構造部を載置すべき建物の下部構
造部を施工して建物の中央部に屋根構造部の最上部の高
さに形成された構台を立設する工程と、この構台を中心
に対向する前記下部構造部のそれぞれの上部から構台の
上部に向けて梁材を構成する梁半材を立て掛けるととも
に双方の上端部を上下に回動自在にピン接合する工程
と、双方の梁半材の下端部を結ぶようにして下弦ケーブ
ルを取り付けかつこの下弦ケーブルと梁半材の間に目的
の長さの補助ケーブルを取り付けて束材とし、下弦ケー
ブルを構台の上部または梁半材の下端部において牽引す
ることにより張設して双方の梁半材を目的の高さに上昇
する工程と、目的の高さに上昇後前記ピン接合部分を剛
接合して梁構造物を完成する工程を備えることを特徴と
する大型屋根構造物の施工方法。
4. A method for constructing a large roof structure rising upward, comprising: constructing a lower structure portion of a building on which a roof structure portion is to be mounted; Erecting a gantry formed at the height of the gantry, and leaning a beam half member constituting a beam from each upper portion of the lower structure portion facing the gantry toward the upper portion of the gantry, and both upper ends thereof Connecting the lower ends of both beam halves to the lower string cable, and attaching an auxiliary cable of the desired length between the lower string cable and the beam half to form a bundle. Stretching the lower string cable by pulling it at the upper part of the gantry or at the lower end of the beam half to raise both beam halves to the desired height; and after the rise to the desired height, rigidly join the pin joints. Complete the beam structure A method for constructing a large-sized roof structure, comprising the step of:
【請求項5】 前記請求項2または4記載の大型屋根構
造物の施工方法であって、屋根構造物を載置すべき建物
の下部構造物を施工して、前記完成した梁構造物をリフ
トアップして下部構造物の上部に設置する工程を具備す
ることを特徴とする大型屋根構造物の施工方法。
5. The method for constructing a large-sized roof structure according to claim 2, wherein a lower structure of a building on which the roof structure is to be mounted is constructed, and the completed beam structure is lifted. A method for constructing a large-sized roof structure, comprising a step of raising and installing the structure on an upper part of a lower structure.
JP05293292A 1992-03-11 1992-03-11 Large roof structure and construction method Expired - Fee Related JP3194104B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP05293292A JP3194104B2 (en) 1992-03-11 1992-03-11 Large roof structure and construction method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP05293292A JP3194104B2 (en) 1992-03-11 1992-03-11 Large roof structure and construction method

Publications (2)

Publication Number Publication Date
JPH05255974A JPH05255974A (en) 1993-10-05
JP3194104B2 true JP3194104B2 (en) 2001-07-30

Family

ID=12928625

Family Applications (1)

Application Number Title Priority Date Filing Date
JP05293292A Expired - Fee Related JP3194104B2 (en) 1992-03-11 1992-03-11 Large roof structure and construction method

Country Status (1)

Country Link
JP (1) JP3194104B2 (en)

Families Citing this family (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106401042A (en) * 2016-09-12 2017-02-15 东南大学 Cable truss structure provided with steel sheet strips
CN106320519A (en) * 2016-09-12 2017-01-11 东南大学 Steel sheet strip and cable net structure
KR102115518B1 (en) * 2019-03-18 2020-05-26 주식회사 택한 Long span frame structure
CN114108947B (en) * 2021-11-30 2022-08-12 山东大学 Beam string with stress adjustment function and construction method
CN115977407B (en) * 2022-12-23 2024-01-26 中国建筑第二工程局有限公司 Prestressed large-span truss string slipping construction system and construction method thereof

Also Published As

Publication number Publication date
JPH05255974A (en) 1993-10-05

Similar Documents

Publication Publication Date Title
US5309693A (en) Frame structure
JPH0647839B2 (en) Construction method of structure
US5072555A (en) Super high-rise tower
JP3194104B2 (en) Large roof structure and construction method
RU2449093C2 (en) Frame of rapidly erected structure and method of its assembly
JP3261255B2 (en) Shell roof lift-up method
US4276733A (en) Method of constructing and erecting a dome-shaped structure
CN216787874U (en) Large-scale ring type truss hoisting structure in large-span high altitude
CN111101600B (en) Construction method of double-oblique-arch hyperbolic paraboloid cable net structure with limited construction space
JP3061560B2 (en) Tent warehouse and its construction method
CN104196221B (en) Large area is encorbelmented the construction bearing platform of building and erection method thereof
JP2946074B2 (en) Large roof erection method
JP2942761B1 (en) Construction method of large roof
JP2683682B2 (en) Yard-shaped tent
JP2869494B2 (en) Construction method of dome frame
RU2581909C1 (en) Prefabricated frame structure and method for installation thereof
JP2761792B2 (en) Construction method of large space building
JP2858891B2 (en) Construction method of large span dome roof
JPH0913505A (en) Adjustment of height of front end of cantilever roof
JP2004324214A (en) Construction method for roof frame of structure
JP2575796Y2 (en) External curing frame
JP2656440B2 (en) Construction method of pillar-free large space structure, long span beam and its manufacturing method
JP2645313B2 (en) How to build a domed shed
JP2756723B2 (en) How to set up the beam string
JP3239154B2 (en) Lift-up device for all-weather temporary roof

Legal Events

Date Code Title Description
A01 Written decision to grant a patent or to grant a registration (utility model)

Free format text: JAPANESE INTERMEDIATE CODE: A01

Effective date: 20010410

LAPS Cancellation because of no payment of annual fees