JP3061560B2 - Tent warehouse and its construction method - Google Patents

Tent warehouse and its construction method

Info

Publication number
JP3061560B2
JP3061560B2 JP7350911A JP35091195A JP3061560B2 JP 3061560 B2 JP3061560 B2 JP 3061560B2 JP 7350911 A JP7350911 A JP 7350911A JP 35091195 A JP35091195 A JP 35091195A JP 3061560 B2 JP3061560 B2 JP 3061560B2
Authority
JP
Japan
Prior art keywords
truss
block
main frame
blocks
warehouse
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Lifetime
Application number
JP7350911A
Other languages
Japanese (ja)
Other versions
JPH09177377A (en
Inventor
知明 中村
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Taiyo Kogyo Co Ltd
Original Assignee
Taiyo Kogyo Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Taiyo Kogyo Co Ltd filed Critical Taiyo Kogyo Co Ltd
Priority to JP7350911A priority Critical patent/JP3061560B2/en
Publication of JPH09177377A publication Critical patent/JPH09177377A/en
Application granted granted Critical
Publication of JP3061560B2 publication Critical patent/JP3061560B2/en
Anticipated expiration legal-status Critical
Expired - Lifetime legal-status Critical Current

Links

Landscapes

  • Tents Or Canopies (AREA)
  • Conveying And Assembling Of Building Elements In Situ (AREA)

Description

【発明の詳細な説明】DETAILED DESCRIPTION OF THE INVENTION

【0001】[0001]

【発明の属する技術分野】本発明はテント倉庫及びその
構築方法に係り、特に膜体施工等の高所作業を最小限に
でき、また骨組構造を効率よく構築できるようにしたテ
ント倉庫及びその構築方法に関する。
BACKGROUND OF THE INVENTION 1. Field of the Invention The present invention relates to a tent warehouse and a method of constructing the tent warehouse, and more particularly to a tent warehouse and a construction thereof capable of minimizing work at a high place such as membrane construction and efficiently constructing a frame structure. About the method.

【0002】[0002]

【従来の技術】いわゆるテント倉庫は、建設省制定の
「テント倉庫技術基準」において、「主要骨組に鋼材を
使用し、ロープ又は支線等を補助材としたものに、合成
繊維又は無機繊維の膜材を用いて外構を覆う工法による
テント製倉庫用構造物」と定義されている。また、その
規模は、平屋建てで軒高さ5m以下、1棟当たりの床面
積が1000m2以下のものと規定されている。このよ
うな基準のもと、種々のタイプのテント倉庫が施工され
ている。従来、この種のテント倉庫の構築方法として
は、一般に主架構材を構成するトラス構造等の柱をあら
かじめ地組みし、各柱の建方作業を行い、各柱間を水平
梁及び横継材で連結し、その後立設された柱の柱頭部に
アーチトラスを吊り込んで架設して骨組構造を完成さ
せ、最後に膜材で外構を覆う方法がとられている。
2. Description of the Related Art A so-called tent warehouse is defined in the "Tent Warehouse Technical Standards" established by the Ministry of Construction as "a steel frame is used for the main frame and a rope or branch line is used as an auxiliary material, and a synthetic fiber or inorganic fiber membrane is used. Tent warehouse structure by a method of covering the exterior with materials. " The size of the building is stipulated to be a single-story building with a height of 5 m or less and a floor area of 1000 m2 or less per building. Under these standards, various types of tent warehouses are being constructed. Conventionally, as a method of constructing this type of tent warehouse, generally, columns such as truss structures that constitute the main frame are laid in advance, construction work of each column is performed, and horizontal beams and cross-over members are used between columns. Then, an arch truss is hung on the capitals of the pillars that have been erected, and the truss is erected to complete the frame structure. Finally, the outer structure is covered with a membrane material.

【0003】[0003]

【発明が解決しようとする課題】このように、テント倉
庫では骨組構造をあらかじめ完成させておき、その後、
骨組構造全体を覆う寸法に製作された膜体を施工する。
このため、屋根部分の膜体の施工は、所定高さの移動足
場上での高所作業となる。このため、高所作業を安全に
行うために、移動足場等の仮設工費が相当かかるという
問題がある。また、膜体施工のほとんどの作業が高所で
の手間のかかる作業であるため、施工効率が悪く、合理
的な構築方法が望まれていた。さらに、従来のテント倉
庫では、主架構材間のスパンは2.0〜2.5m程度に
設定されてきたが、主架構材間に展張される膜体は、十
分な張力が保持されていれば、従来よりスパンをあけて
もテント形状が十分保形できることが経験上、知られて
いる。
As described above, in the tent warehouse, the frame structure is completed in advance, and thereafter,
A membrane made to cover the entire frame structure is installed.
For this reason, the construction of the membrane on the roof portion is a work at a high place on a moving scaffold having a predetermined height. For this reason, there is a problem that a temporary construction cost for a moving scaffold or the like is considerably required in order to safely perform work at a high place. In addition, since most of the work of constructing the membrane is troublesome work at a high place, the construction efficiency is low and a rational construction method has been desired. Further, in the conventional tent warehouse, the span between the main frame members has been set to about 2.0 to 2.5 m. However, the membrane extended between the main frame members is required to have sufficient tension. It has been empirically known that a tent shape can be sufficiently maintained even if a span is opened.

【0004】そこで、本発明の目的は上述した従来の技
術が有する問題点を解消し、高所での膜体工事を最小限
にし、また各骨組の構築作業を効率的に行えるようにし
たテント倉庫及びその構築方法を提供することにある。
Accordingly, an object of the present invention is to solve the above-mentioned problems of the prior art, minimize the construction of the membrane at a high place, and efficiently perform the work of constructing each frame. An object of the present invention is to provide a warehouse and a method for constructing the same.

【0005】[0005]

【課題を解決するための手段】上記目的を達成するため
に、本発明は、平面トラスの合掌材トラスと該合掌材ト
ラスの両脚部に連結された上部柱トラスとからなる上部
ブロックと、該上部柱トラスの下端に回動可能に連結さ
れた下部柱トラスからなる下部ブロックとに分割して地
組みされ、前記上部ブロックを吊り上げに伴い、前記下
部ブロックが起立した状態で隣接した平面トラスが補助
継材で補剛され完成した主架構トラスブロックが、倉庫
長手方向に所定間隔をあけて一端から順次、その間隔が
横継材のみで連結され立設されることで骨組構造を構築
する一方、該骨組構造をあらかじめ覆っていた膜体が、
骨組構造が立設されるのに合わせて順次展張され、前記
主架構ブロックの他端までが立設された段階で前記膜体
の展張が完了するようにしたことを特徴とする。
In order to achieve the above object, the present invention relates to a joint truss for a flat truss and a joint truss.
Upper part consisting of an upper column truss connected to both legs of the lath
Block and pivotally connected to the lower end of the upper column truss.
And divided into lower blocks consisting of
The upper block is lifted and the lower
The adjacent plane truss assists with the section block standing
The main frame truss block stiffened with the joint material is stored in the warehouse
With a predetermined interval in the longitudinal direction, sequentially from one end, the interval is
Constructs a framed structure by being erected and connected only with cross-connects
On the other hand, the membrane body previously covering the framework structure is
The frame structure is sequentially expanded as it stands,
At the stage where the other end of the main frame is upright,
Is completed .

【0006】また、その構築方法として、あらかじめ各
主架構トラスブロックを、合掌材トラスと該合掌材トラ
スの両脚部に連結された上部柱トラスとからなる上部ブ
ロックと、該上部柱トラスの下端に回動可能に連結され
た下部柱トラスからなる下部ブロックとに分割して地組
みし、前記下部ブロック上に上部ブロックを仮置きした
状態で前記主架構トラスブロックを所定間隔をあけて配
置し、該主架構トラスブロック上にテント倉庫全体を覆
う膜体を展開して仮止めし、その後、前記下部ブロック
が前記上部ブロックの吊り上げに伴って起立するように
して、複数配置された前記主架構トラスブロックのう
ち、端に位置する主架構トラスブロックを吊り上げて、
主架構トラスブロックを完成させ、該主架構トラスブロ
ックの補剛を行うとともに膜体を展張し、次いで隣接し
た主架構トラスブロックを横方向に移動させながら吊り
上げて完成させ、完成した主架構トラスブロック同士を
横継材のみで連結し、さらに隣接した主架構トラスブロ
ックに対して同様の動作を繰り返していき、倉庫長手方
向に所定間隔をあけて配置されたすべての主架構トラス
ブロックを完成させるのとほぼ同時に膜体を展張し終え
るようにしたことを特徴とする。
[0006] As a construction method, each main frame truss block is previously provided with a joint truss and a joint truss.
An upper block consisting of an upper column truss connected to both legs of the upper column and a lower end of the upper column truss rotatably connected to the upper column truss.
The main truss block is divided into a lower block composed of a lower pillar truss, and the main truss block is arranged at a predetermined interval in a state where the upper block is temporarily placed on the lower block. Then, the membrane covering the entire tent warehouse is developed and temporarily fixed, and then the lower block stands up along with the lifting of the upper block, so that a plurality of the main frame truss blocks are arranged at one end. Lift the main frame truss block located,
Complete the main frame truss block, stiffen the main frame truss block, expand the membrane, and then lift the adjacent main frame truss block while moving it horizontally to complete the completed main frame truss block. By connecting them only with horizontal joints, the same operation is repeated for the adjacent main frame truss blocks to complete all the main frame truss blocks arranged at predetermined intervals in the longitudinal direction of the warehouse. At the same time, the film body has been expanded.

【0007】このとき前記下部ブロックは、スペーサ及
びキャスターが取り付けられた状態で基礎上に仮置きさ
れ、該下部ブロックと前記上部ブロックとの間にも中間
スペーサが介装されるようにすることが好ましい。
At this time, the lower block is temporarily placed on a foundation with the spacers and casters attached, and an intermediate spacer is interposed between the lower block and the upper block. preferable.

【0008】[0008]

【発明の実施の形態】以下、本発明のテント倉庫及びそ
の構築方法の一実施の態様について、添付図面を参照し
て説明する。図1は、本発明のテント倉庫10の構成を
説明するために、その一部を切り欠いて示した全体斜視
図である。テント倉庫10は同図に示したように、横継
材35(後述する。)によって連結された主要骨組とし
ての4セットの主架構ブロック20と、主架構ブロック
20を覆う膜体1とから構成されている。なお、図中で
は膜体1を切り欠いた部分に隣接した2セットの主架構
ブロック20の一部が示されている。本実施の形態で
は、膜体には従来の膜材と同様の合成繊維が使用されて
いる。
DETAILED DESCRIPTION OF THE PREFERRED EMBODIMENTS An embodiment of a tent warehouse and a method for constructing the tent warehouse according to the present invention will be described below with reference to the accompanying drawings. FIG. 1 is an overall perspective view of a tent warehouse 10 according to the present invention, in which a part of the tent warehouse 10 is cut away to explain the configuration. As shown in the figure, the tent warehouse 10 is composed of four sets of main frame blocks 20 as main frames connected by a horizontal connecting member 35 (described later), and a membrane 1 covering the main frame blocks 20. Have been. In the drawing, a part of two sets of main frame blocks 20 adjacent to the cut-out portion of the film body 1 is shown. In the present embodiment, a synthetic fiber similar to a conventional film material is used for the film body.

【0009】ここで、主架構ブロック20の構成につい
て説明する。膜体1に覆われた主架構ブロック20は、
図3(f)にもその全体を示したように、2組の平面ト
ラスとしての主架構トラス21と、主架構トラス21間
を連結する複数の横継材23とからなる。本実施の形態
では、主架構トラス21はラチス材24で補剛された柱
材25及び合掌材26からなり、柱材25及び合掌材2
6には角形パイプが、ラチス材24には丸形パイプが使
用されている。また、棟、軒、裾の各位置の横継材23
には所定の直径からなる丸形パイプが使用されている。
また、丸鋼ブレース29によって壁面、屋根面が補剛さ
れている。補助材としての横継材23、ブレース29は
柱材25、合掌材26のサイズにあわせたサイズに設定
されている。また、柱材25の柱脚部28はコンクリー
ト基礎の所定位置に埋設されているコンクリートボルト
(図示せず)で基礎に固定されている。また、出入口開
口30が設けられている主架構ブロック20の妻面31
には間柱32及び胴縁33が取り付けられている。さら
に主架構ブロック20間は横継材35で棟、軒、裾位置
が連結されている。なお、使用するコンクリートボルト
は、公知の埋込みアンカーボルトでもよいし、後施工ア
ンカーボルトでもよい。
Here, the configuration of the main frame block 20 will be described. The main frame block 20 covered by the film body 1
As shown in FIG. 3 (f), the main frame truss 21 is composed of two sets of planar trusses, and a plurality of cross members 23 connecting the main frame trusses 21. In the present embodiment, the main frame truss 21 is composed of a column member 25 and a joint member 26 stiffened by a lattice member 24, and the column member 25 and the joint member 2
6 is a square pipe, and the lattice 24 is a round pipe. In addition, the horizontal connection material 23 at each position of the ridge, eaves, and hem
Is a round pipe having a predetermined diameter.
The wall surface and the roof surface are stiffened by the round steel braces 29. The transverse joint member 23 and the brace 29 as auxiliary members are set to have a size corresponding to the size of the column member 25 and the joint member 26. The column base 28 of the column member 25 is fixed to the foundation with concrete bolts (not shown) embedded at predetermined positions on the concrete foundation. Also, the wedge surface 31 of the main frame block 20 in which the entrance opening 30 is provided.
A stud 32 and a torso 33 are attached to. Further, between the main frame blocks 20, the ridge, the eaves, and the hem position are connected by a horizontal connection member 35. The concrete bolt to be used may be a known embedded anchor bolt or a post-installed anchor bolt.

【0010】以下、主架構ブロック20の構築方法につ
いて図2〜図6を参照して説明する。なお、テント倉庫
10を構築する場合には、後述するように途中の施工段
階で周縁部を畳んだ状態の膜体1を屋根上に取り付ける
が、図2、図3の説明では主架構ブロック20の構築手
順及びその形状の理解のために膜体1の図示を省略して
いる。図2(a)はあらかじめ地組みされた主架構トラ
ス21を示している。この主架構トラス21の柱材25
は後述するように上部柱25Aと下部柱25Bとからな
る。上部柱25Aは合掌材26の端部に接合された状態
で地組みされ、主架構トラス21を構成する。また同一
形状をした2組の主架構トラス21は、地組み位置で倒
した状態で数本の横継材23により仮止めされている。
この横継材23の各端部は主架構トラス21の所定節点
に1本のボルト(図示せず)で仮止めされている。この
ため、図2(a)に示した矢印方向に主架構トラス21
を起立させ、横継材23の端部のボルトを本締めするこ
とにより、図2(b)に示したように、起立状態を保持
した主架構上部ブロック20Aが完成する。
Hereinafter, a method of constructing the main frame block 20 will be described with reference to FIGS. When the tent warehouse 10 is to be constructed, the membrane 1 in a state in which the peripheral portion is folded at the middle of the construction stage is mounted on the roof as described later, but in the description of FIGS. The illustration of the membrane 1 is omitted for understanding the construction procedure and the shape thereof. FIG. 2 (a) shows the main frame truss 21 which has been laid in advance. Column material 25 of this main frame truss 21
Is composed of an upper column 25A and a lower column 25B as described later. The upper column 25 </ b> A is laid in a state where it is joined to the end of the joint material 26, and forms the main frame truss 21. The two sets of main frame trusses 21 having the same shape are temporarily fixed by several transverse joint members 23 in a state where the main frame trusses 21 are tilted at the ground position.
Each end of the transverse joint 23 is temporarily fixed to a predetermined node of the main frame truss 21 with one bolt (not shown). Therefore, the main frame truss 21 is moved in the direction of the arrow shown in FIG.
And the bolts at the ends of the lateral connection members 23 are fully tightened, thereby completing the main frame upper block 20A holding the upright state, as shown in FIG. 2B.

【0011】次いで図2(c)に示したように、膜体1
(図示せず)を合掌材26上に仮止めた主架構上部ブロ
ック20Aを、隣接位置にあらかじめ地組みしておいた
主架構下部ブロック20B上に後述する仮設治具を介し
て載置する。主架構下部ブロック20Bは横倒し状態で
対向位置に配置された2組の下部柱25Bが横継材23
及びブレース29で連結されたものである。主架構下部
ブロック20Bは起立した状態で、その上端が主架構上
部ブロック20Aの上部柱25Aの下端に連結され、主
架構ブロック20の側壁面の一部を構成する。なお、主
架構上部ブロック20Aを吊持する揚重設備としては、
主架構ブロック20の構築位置に容易に接近できるトラ
ッククレーン等を使用することが好ましい。
Next, as shown in FIG.
The main frame upper block 20A, which is temporarily fixed (not shown) on the joint material 26, is placed via a temporary jig, which will be described later, on the main frame lower block 20B that has been previously grounded at an adjacent position. The main frame lower block 20B is provided with two sets of lower pillars 25B arranged at opposing positions in a state of being laid sideways, and a horizontal connecting member 23.
And a brace 29. With the main frame lower block 20B standing, the upper end thereof is connected to the lower end of the upper column 25A of the main frame upper block 20A, and constitutes a part of the side wall surface of the main frame block 20. In addition, as the lifting equipment for suspending the main frame upper block 20A,
It is preferable to use a truck crane or the like that can easily approach the construction position of the main frame block 20.

【0012】次に、図2(c)〜図3(e)のように、
主架構上部ブロック20Aと主架構下部ブロック20B
とを一体的に吊り上げるために使用する仮設治具につい
て、図4、図5を参照して説明する。図4に示したよう
に、主架構上部ブロック20Aは横倒し状態の主架構下
部ブロック20B上に載置されている。このとき、主架
構下部ブロック20Bの柱脚部には合成樹脂製キャスタ
ー40が取着され、この合成樹脂製キャスター40を介
して支持されている。一方、他端の柱連結部27は第1
の仮設治具としての下部スペーサ41上に載置されてい
る。下部スペーサ41は鋼製のブロックからなり、その
高さは主架構下部ブロック20Bが水平を保持できる程
度に設定されている。さらに、主架構下部ブロック20
Bの柱連結部27上には第2の仮設治具としての中間ス
ペーサ42が取り付けられている。中間スペーサ42は
図5に示したように、水平状態に横倒しされた主架構下
部ブロック20Bと主架構上部ブロック20Aとの間に
介装される。このように下部スペーサ41、中間スペー
サ42を用いて主架構上部ブロック20Aは主架構下部
ブロック20B上に図2(c)、図4に示したように安
定した状態で仮置きされる。
Next, as shown in FIGS. 2 (c) to 3 (e),
Main frame upper block 20A and main frame lower block 20B
A temporary jig used to integrally lift the components will be described with reference to FIGS. As shown in FIG. 4, the main frame upper block 20A is placed on the main frame lower block 20B in a sideways state. At this time, a caster 40 made of synthetic resin is attached to the column base of the lower block 20B of the main frame, and is supported via the caster 40 made of synthetic resin. On the other hand, the column connecting portion 27 at the other end is the first
Is mounted on the lower spacer 41 as a temporary jig. The lower spacer 41 is made of a steel block, and its height is set so that the main frame lower block 20B can maintain the horizontal position. Furthermore, the main frame lower block 20
An intermediate spacer 42 as a second temporary jig is mounted on the column connecting portion 27 of B. As shown in FIG. 5, the intermediate spacer 42 is interposed between the main frame lower block 20B and the main frame upper block 20A which are laid down horizontally. As described above, the main frame upper block 20A is temporarily placed on the main frame lower block 20B in a stable state as shown in FIGS. 2C and 4 by using the lower spacer 41 and the intermediate spacer 42.

【0013】この状態から主架構上部ブロック20Aと
主架構下部ブロック20Bとを同時に吊り上げるには図
5に示したように、主架構上部ブロック20Aの上部柱
25A下端と主架構下部ブロック20Bの柱連結部27
との間を掛け渡すようにリング状の鋼製ワイヤ43を取
り付ける。このように主架構上部ブロック20Aと主架
構下部ブロック20Bとがリング状の鋼製ワイヤ43で
緩くつながれているので、図3(d)のように主架構上
部ブロック20Aを吊り上げると、主架構下部ブロック
20Bも追随して徐々に起立していく。このとき、主架
構下部ブロック20Bの下端側面には合成樹脂製キャス
ター40が取り付けられている。このため、主架構下部
ブロック20Bはこの合成樹脂製キャスター40を介し
て接地する。この結果、主架構下部ブロック20Bは完
全に起立状態となるまで滑らかにその姿勢を変えること
ができる(図3(d)〜(e)参照)。
In order to simultaneously lift the main frame upper block 20A and the main frame lower block 20B from this state, as shown in FIG. Part 27
A ring-shaped steel wire 43 is attached so as to bridge the gap. Since the main frame upper block 20A and the main frame lower block 20B are loosely connected by the ring-shaped steel wire 43 in this manner, when the main frame upper block 20A is lifted as shown in FIG. The block 20B also gradually rises following the movement. At this time, casters 40 made of synthetic resin are attached to the lower end side surface of the main frame lower block 20B. For this reason, the main frame lower block 20B is grounded via the caster 40 made of synthetic resin. As a result, the posture of the main frame lower block 20B can be smoothly changed until the main frame lower block 20B is completely upright (see FIGS. 3D to 3E).

【0014】主架構上部ブロック20Aと主架構下部ブ
ロック20Bとを一体化させるには、まず主架構下部ブ
ロック20Bが合成樹脂製キャスター40で容易に移動
できるまで主架構下部ブロック20Bを吊り上げ、この
状態で基礎上の固定位置まで主架構上部ブロック20A
と主架構下部ブロック20Bとを移動し、主架構下部ブ
ロック20Bの柱脚部28をコンクリートボルトで基礎
上に固定する。次いで主架構上部ブロック20Aの上部
柱25Aの下端と主架構下部ブロック20Bの柱連結部
27とをボルト接合により連結する(図3(e)参
照)。さらに必要な横継材23、ブレース29を取り付
けて補剛し、すでに構築されている隣接主架構ブロック
20と棟、軒、裾位置を横継材35で連結し、骨組構造
としての一体化を図る(図3(f)参照)。
In order to integrate the main frame upper block 20A and the main frame lower block 20B, first, the main frame lower block 20B is lifted until the main frame lower block 20B can be easily moved by the casters 40 made of synthetic resin. To the fixed position on the foundation with the main frame upper block 20A
And the main frame lower block 20B, and the column base 28 of the main frame lower block 20B is fixed on the foundation with concrete bolts. Next, the lower end of the upper column 25A of the main frame upper block 20A and the column connecting portion 27 of the main frame lower block 20B are connected by bolting (see FIG. 3E). Further, the necessary transverse joints 23 and braces 29 are attached and stiffened, and the already constructed adjacent main frame block 20 and the ridge, eaves, and hem positions are connected by the transverse joints 35, so that integration as a frame structure is achieved. (See FIG. 3 (f)).

【0015】次に、テント倉庫としての構築方法につい
て、図6、7の(a)〜(e)に示した主架構ブロック
20の構築手順を参照して説明する。このとき、図8〜
図12は図6、7の(a)〜(e)に対応した施工状態
を示した斜視図である。以下、図6、7を参照してテン
ト倉庫の構築方法について説明する。図6(a)は前述
した主架構ブロック20を、テント倉庫10の構築位置
に所定の間隔をあけて配置した例を示している。本実施
の形態では、4セットの主架構ブロック20がほぼ主架
構ブロック20の棟方向長さに等しい離れをとって配置
されている。以下、各主架構ブロック20を区別して述
べる場合には図6(a)の右側のブロックから第1〜4
ブロック(符号201〜204)と記す。
Next, a method of constructing a tent warehouse will be described with reference to the procedure for constructing the main frame block 20 shown in FIGS. At this time, FIG.
FIG. 12 is a perspective view showing a construction state corresponding to (a) to (e) of FIGS. Hereinafter, a method of constructing a tent warehouse will be described with reference to FIGS. FIG. 6A shows an example in which the above-mentioned main frame blocks 20 are arranged at predetermined intervals in the construction position of the tent warehouse 10. In the present embodiment, four sets of main frame blocks 20 are arranged at a distance substantially equal to the length of the main frame blocks 20 in the ridge direction. Hereinafter, when the main frame blocks 20 are described separately, the first to fourth blocks from the block on the right side of FIG.
This is referred to as a block (reference numerals 201 to 204).

【0016】第1ブロック201と第2ブロック202
との間は他のブロック間に比べて接近させて配置してい
る。このとき屋根膜体1と壁面膜体1とは図6(a)、
図8に示したように4セットの主架構ブロック201〜
204を覆うように展開された状態で主架構ブロック2
01〜204に仮止めされている。また、第1ブロック
201と第2ブロック202との間には、十分な長さの
屋根膜体1の展開しろ1aが確保されている。このた
め、図6(b)に示したように、第1ブロック201を
吊り上げて完成させ、第2ブロック202との間に高低
差が生じても屋根膜体1を確実に展開することができ
る。構築手順としては、第1ブロック201の柱脚部2
8をコンクリートボルトで基礎上に固定し、主架構上部
ブロック201Aと主架構下部ブロック201Bとを接
合する。さらに第1ブロック201全体を横継材23、
ブレース29で補剛する。
First block 201 and second block 202
Is arranged closer than other blocks. At this time, the roof membrane 1 and the wall membrane 1 are shown in FIG.
As shown in FIG. 8, four sets of main frame blocks 201 to 201 are provided.
Main frame block 2 in a state where it is deployed to cover 204
It is temporarily fixed to 01-204. In addition, between the first block 201 and the second block 202, a spread 1a of the roof membrane 1 having a sufficient length is secured. Therefore, as shown in FIG. 6B, the first block 201 is lifted and completed, and the roof membrane 1 can be reliably deployed even if a height difference occurs between the first block 201 and the second block 202. . As a construction procedure, the column base 2 of the first block 201
8 is fixed on the foundation with concrete bolts, and the main frame upper block 201A and the main frame lower block 201B are joined. Further, the entire first block 201 is connected to the transverse connection member 23,
Stiffen with brace 29.

【0017】次いで、第2ブロック202を図6
(b)、図9に模式的に矢印で示したように、上方へ吊
り上げながら、第3ブロック203側に移動する。そし
て図6(c)、図10に示したように所定の固定位置ま
で移動させたら、ブロック全体を起立させるのと同時
に、下部柱25Bの柱脚部28をコンクリートボルトで
基礎上に固定し、主架構上部ブロック202Aと主架構
下部ブロック202Bとを接合する。さらに第1ブロッ
ク201と第2ブロック202との間を横継材35で連
結するとともに、第2ブロック202全体を横継材、ブ
レース29で補剛する。本実施の形態では、横継材35
は棟、両軒、両裾の5箇所に取り付けられる。これらの
うち棟、軒位置の横継材35は膜体1の保形のために利
用され、裾位置の横継材35は膜体1の裾部分の固定の
ために利用される。
Next, the second block 202 is shown in FIG.
(B), as shown by arrows in FIG. 9, move to the third block 203 side while lifting it upward. Then, as shown in FIG. 6C and FIG. 10, when the block is moved to a predetermined fixing position, the entire block is raised, and at the same time, the column base 28 of the lower column 25B is fixed on the foundation with concrete bolts. The main frame upper block 202A and the main frame lower block 202B are joined. Further, the first block 201 and the second block 202 are connected by the transverse joint 35, and the entire second block 202 is stiffened by the transverse joint and the brace 29. In the present embodiment, the transverse joint 35
Are attached to five locations: ridge, both eaves, and both hem. Of these, the horizontal joint 35 at the ridge and eave positions is used for shape preservation of the membrane 1, and the horizontal joint 35 at the bottom is used for fixing the bottom of the membrane 1.

【0018】以下、同様の手順により第3ブロック20
3を吊り上げ移動し、第4ブロック204に接近した基
礎上に所定位置で第3ブロック203を固定し、第3ブ
ロック203を完成させて第2ブロック202と連結
し、第3ブロック203までの膜体1を展張する(図6
(d)、図11参照)。そして最終的に第4ブロック2
04を移動、起立させてすべての主架構ブロック201
〜204を完成させた状態で図12に示したように、屋
根膜体1の周縁部を、壁面膜体1の上端を覆うようにし
て軒から垂らし端部処理を行う。併せて妻面の壁面膜体
1を展張する。このようにしてほとんど高所作業を行わ
ずに、テント倉庫全体を効率よく構築することができ
る。
Hereinafter, the third block 20 is operated in the same manner.
3 is lifted and moved, the third block 203 is fixed at a predetermined position on the foundation approaching the fourth block 204, the third block 203 is completed and connected to the second block 202, and the film up to the third block 203 is formed. Extend the body 1 (Fig. 6
(D), see FIG. 11). And finally the fourth block 2
04 is moved and raised, and all the main frame blocks 201 are moved.
As shown in FIG. 12 in a state where the steps # 204 to # 204 are completed, the edge of the roof membrane 1 is hung from the eaves so as to cover the upper end of the wall membrane 1. At the same time, the wall surface film body 1 on the wife's face is extended. In this way, the entire tent warehouse can be efficiently constructed with almost no work at height.

【0019】以上に述べた主架構ブロック20の数やブ
ロックの形状、ブロック間のスパンは、設計上の条件や
使用する部材の大きさにより設計者の判断で適宜変更で
きることは言うまでもない。また、膜体1の形状も屋
根、壁面を分離せずに全体を一体化した形状とすること
も可能である。また、テント倉庫を例に本発明の構成を
説明したが、施設としての用途は倉庫に限られず、集客
施設等の種々のものに適用できることは言うまでもな
い。
It goes without saying that the number of main frame blocks 20, the shape of the blocks, and the span between the blocks described above can be appropriately changed by the designer's judgment depending on the design conditions and the size of the members to be used. Also, the shape of the film body 1 can be made into an integrated shape without separating the roof and the wall surface. Further, the configuration of the present invention has been described using a tent warehouse as an example, but it goes without saying that the use as a facility is not limited to a warehouse, but can be applied to various facilities such as a customer attracting facility.

【0020】[0020]

【発明の効果】以上の説明から明らかなように、本発明
によれば、高所での膜体工事を最小限にすることがで
き、また骨組部材の省略を実現でき鉄骨工事の効率化、
材料コストの低減を図ることができるという効果を奏す
る。
As is apparent from the above description, according to the present invention, the construction of the membrane at a high place can be minimized, and the framing member can be omitted.
There is an effect that the material cost can be reduced.

【図面の簡単な説明】[Brief description of the drawings]

【図1】本発明によるテント倉庫の一実施の形態を示し
た斜視図。
FIG. 1 is a perspective view showing an embodiment of a tent warehouse according to the present invention.

【図2】本発明のテント倉庫の主架構ブロックの構築方
法の作業手順の一例を示した手順説明図(その1)。
FIG. 2 is a procedure explanatory view showing an example of an operation procedure of a method of constructing a main frame block of a tent warehouse of the present invention (part 1).

【図3】本発明のテント倉庫の主架構ブロックの構築方
法の作業手順の一例を示した手順説明図(その2)。
FIG. 3 is an explanatory diagram (part 2) illustrating an example of a work procedure of a method of constructing a main frame block of a tent warehouse according to the present invention.

【図4】主架構ブロックの吊り上げ前の載置状態を示し
た状態説明図。
FIG. 4 is a state explanatory view showing a mounted state before lifting of a main frame block.

【図5】図4に示した一部を拡大して示した部分拡大
図。
FIG. 5 is a partially enlarged view showing a part shown in FIG. 4 in an enlarged manner.

【図6】テント倉庫の構築方法の作業手順の一例を示し
た手順説明図(その1)。
FIG. 6 is a procedure explanatory view showing an example of a work procedure of a tent warehouse construction method (part 1).

【図7】テント倉庫の構築方法の作業手順の一例を示し
た手順説明図(その2)。
FIG. 7 is a procedure explanatory view showing an example of a work procedure of a tent warehouse construction method (part 2).

【図8】テント倉庫の構築作業の主架構ブロック吊り上
げ状態を示した状態説明図(その1)。
FIG. 8 is a state explanatory view showing a state where a main frame block is lifted in a construction work of a tent warehouse (part 1).

【図9】テント倉庫の構築作業の主架構ブロック吊り上
げ状態を示した状態説明図(その2)。
FIG. 9 is a state explanatory view showing a state in which a main frame block is lifted in the construction work of the tent warehouse (part 2).

【図10】テント倉庫の構築作業の主架構ブロック吊り
上げ状態を示した状態説明図(その3)。
FIG. 10 is a state explanatory view showing a state in which a main frame block is lifted in the construction work of a tent warehouse (part 3).

【図11】テント倉庫の構築作業の主架構ブロック吊り
上げ状態を示した状態説明図(その4)。
FIG. 11 is a state explanatory view showing a state where a main frame block is lifted in the construction work of the tent warehouse (part 4).

【図12】テント倉庫の構築作業の主架構ブロック吊り
上げ状態を示した状態説明図(その5)。
FIG. 12 is a state explanatory view showing a state where a main frame block is lifted in a tent warehouse construction operation (part 5).

【符号の説明】[Explanation of symbols]

1 膜体 10 テント倉庫 20 主架構ブロック 23,35 横継材 25 主架構トラス 29 ブレース 40 合成樹脂製キャスター 41,42 スペーサ DESCRIPTION OF SYMBOLS 1 Membrane body 10 Tent warehouse 20 Main frame block 23,35 Crossing material 25 Main frame truss 29 Brace 40 Synthetic resin caster 41,42 Spacer

Claims (3)

(57)【特許請求の範囲】(57) [Claims] 【請求項1】平面トラスの合掌材トラスと該合掌材トラ
スの両脚部に連結された上部柱トラスとからなる上部ブ
ロックと、該上部柱トラスの下端に回動可能に連結され
た下部柱トラスからなる下部ブロックとに分割して地組
みされ、前記上部ブロックを吊り上げに伴い、前記下部
ブロックが起立した状態で隣接した平面トラスが補助継
材で補剛され完成した主架構トラスブロックが、倉庫長
手方向に所定間隔をあけて一端から順次、その間隔が横
継材のみで連結され立設されることで骨組構造を構築す
る一方、該骨組構造をあらかじめ覆っていた膜体が、骨
組構造が立設されるのに合わせて順次展張され、前記主
架構ブロックの他端までが立設された段階で前記膜体の
展張が完了するようにしたことを特徴とするテント倉
庫。
1. A truss truss for a flat truss and a truss for the truss
Upper truss consisting of an upper column truss
A lock and a pivotally connected lower end of the upper column truss.
Divided into lower blocks consisting of lower column trusses
As the upper block is lifted,
The adjacent plane truss is an auxiliary joint with the block standing
The main truss block stiffened with timber and completed is the warehouse manager
With a predetermined interval in the hand direction, sequentially from one end, the interval is horizontal
Build a frame structure by connecting and standing only with the joint
On the other hand, the membrane that previously covered the framework structure
The main structure is sequentially expanded in accordance with the standing
At the stage where the other end of the frame block is erected,
A tent warehouse characterized by the completion of the expansion .
【請求項2】あらかじめ各主架構トラスブロックを、
掌材トラスと該合掌材トラスの両脚部に連結された上部
柱トラスとからなる上部ブロックと、該上部柱トラスの
下端に回動可能に連結された下部柱トラスからなる下部
ブロックとに分割して地組みし、前記下部ブロック上に
上部ブロックを仮置きした状態で前記主架構トラスブロ
ックを所定間隔をあけて配置し、該主架構トラスブロッ
ク上にテント倉庫全体を覆う膜体を展開して仮止めし、
その後、前記下部ブロックが前記上部ブロックの吊り上
げに伴って起立するようにして、複数配置された前記主
架構トラスブロックのうち、端に位置する主架構トラス
ブロックを吊り上げて、主架構トラスブロックを完成さ
せ、該主架構トラスブロックの補剛を行うとともに膜体
を展張し、次いで隣接した主架構トラスブロックを横方
向に移動させながら吊り上げて完成させ、完成した主架
構トラスブロック同士を横継材のみで連結し、さらに隣
接した主架構トラスブロックに対して同様の動作を繰り
返していき、倉庫長手方向に所定間隔をあけて配置され
たすべての主架構トラスブロックを完成させるのとほぼ
同時に膜体を展張し終えるようにしたことを特徴とする
テント倉庫の構築方法。
Wherein the advance each main Frame truss block, if
Palm truss and upper part connected to both legs of the palm truss
An upper block consisting of a column truss and
It is divided into a lower block composed of a lower pillar truss rotatably connected to a lower end and is laid, and the main frame truss blocks are arranged at predetermined intervals in a state where an upper block is temporarily placed on the lower block. Then, on the main frame truss block, deploy a film covering the entire tent warehouse and temporarily fix it,
Thereafter, the main block truss block located at the end of the plurality of main frame truss blocks is lifted to complete the main frame truss block so that the lower block stands up with the lifting of the upper block. The main frame truss blocks are stiffened and the membrane is expanded, and then the adjacent main frame truss blocks are lifted while being moved in the horizontal direction to complete the completed main frame truss blocks. The same operation is repeated for the adjacent main frame truss blocks, and the membrane is almost simultaneously completed with all the main frame truss blocks arranged at predetermined intervals in the longitudinal direction of the warehouse. A method of constructing a tent warehouse, which has been completed.
【請求項3】前記下部ブロックは、スペーサ及びキャス
ターが取り付けられた状態で基礎上に仮置きされ、該下
部ブロックと前記上部ブロックとの間にも中間スペーサ
が介装されたことを特徴とする請求項2記載のテント倉
庫の構築方法。
3. The lower block is temporarily placed on a foundation with a spacer and a caster attached thereto, and an intermediate spacer is interposed between the lower block and the upper block. The method for constructing a tent warehouse according to claim 2.
JP7350911A 1995-12-25 1995-12-25 Tent warehouse and its construction method Expired - Lifetime JP3061560B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP7350911A JP3061560B2 (en) 1995-12-25 1995-12-25 Tent warehouse and its construction method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP7350911A JP3061560B2 (en) 1995-12-25 1995-12-25 Tent warehouse and its construction method

Publications (2)

Publication Number Publication Date
JPH09177377A JPH09177377A (en) 1997-07-08
JP3061560B2 true JP3061560B2 (en) 2000-07-10

Family

ID=18413744

Family Applications (1)

Application Number Title Priority Date Filing Date
JP7350911A Expired - Lifetime JP3061560B2 (en) 1995-12-25 1995-12-25 Tent warehouse and its construction method

Country Status (1)

Country Link
JP (1) JP3061560B2 (en)

Families Citing this family (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR100838783B1 (en) * 2007-12-14 2008-06-17 강남수 Folding type large tent
CN102179651A (en) * 2011-04-06 2011-09-14 中国建筑第八工程局有限公司 On-site plane trusses of extra-large welded ball net frame and method for splicing three-dimensional sections
JP5403722B1 (en) * 2013-04-04 2014-01-29 正博 瀧倉 Foldable mobile warehouse
CN107620428B (en) * 2017-09-29 2023-02-28 江苏沪宁钢机股份有限公司 C-shaped support column of steel structure building and installation method thereof
CN112942845B (en) * 2021-02-01 2022-10-18 中国建筑第八工程局有限公司 Method for mounting special-shaped steel structure
CN115324360A (en) * 2022-07-27 2022-11-11 成都建工第四建筑工程有限公司 Construction method of large-span suspended truss

Also Published As

Publication number Publication date
JPH09177377A (en) 1997-07-08

Similar Documents

Publication Publication Date Title
JPH04111829A (en) Method for constructing large-span roof
JP3061560B2 (en) Tent warehouse and its construction method
JPH06200625A (en) Frame method of arch truss construction
JPH0571225A (en) Temporarily set roof of complete weather type
JP2946074B2 (en) Large roof erection method
JP2723620B2 (en) Wooden construction method
JP4585672B2 (en) Roof structure of unit type building
WO1991019872A1 (en) Tent-erection method and a device for use in performing the method
JP3252675B2 (en) All-weather temporary roof
JP2001220818A (en) Steel framework structure
JPH0454016B2 (en)
JPH0529744B2 (en)
JP2888736B2 (en) Roof structure
JP3124152B2 (en) Collapse prevention frame
JP2552986Y2 (en) Lifting piece for lifting temporary tent
JP2575796Y2 (en) External curing frame
JPH0752879Y2 (en) Foldable external scaffolding unit
JPH06185120A (en) Construction method for upper structure of roof, etc.
JPH0730631B2 (en) Temporary construction of all-weather shelter for multi-storey buildings
JP2560962B2 (en) All-weather temporary structure
JPH04333775A (en) Erection method for steel framed construction of low-rise building
JPH074060A (en) Lift-up execution equipment for multistoried building
JPH04153458A (en) Deflection controlling construction for beam, and deflection controlling method
JPH0596320U (en) Rain cover for building foundation work
JPH04155034A (en) Execution method for small scale building