JP3177016U - Reinforcing brackets for concrete cross-section repair - Google Patents

Reinforcing brackets for concrete cross-section repair Download PDF

Info

Publication number
JP3177016U
JP3177016U JP2012002628U JP2012002628U JP3177016U JP 3177016 U JP3177016 U JP 3177016U JP 2012002628 U JP2012002628 U JP 2012002628U JP 2012002628 U JP2012002628 U JP 2012002628U JP 3177016 U JP3177016 U JP 3177016U
Authority
JP
Japan
Prior art keywords
cross
concrete
anchor pin
section
repair
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Lifetime
Application number
JP2012002628U
Other languages
Japanese (ja)
Inventor
辰浩 西川
Original Assignee
株式会社ニシケン
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by 株式会社ニシケン filed Critical 株式会社ニシケン
Priority to JP2012002628U priority Critical patent/JP3177016U/en
Application granted granted Critical
Publication of JP3177016U publication Critical patent/JP3177016U/en
Anticipated expiration legal-status Critical
Expired - Lifetime legal-status Critical Current

Links

Images

Landscapes

  • Working Measures On Existing Buildindgs (AREA)

Abstract

【課題】コンクリートの断面修復の容易化と、充填した断面修復材の剥落防止を図る断面修復用補強金具を提供する。
【解決手段】コンクリートに穿孔した穴に固定されるアンカーピン2と、その基端部に設けられ、アンカーピンと一体的に形成された笠部材3と、を有し、笠部材は、放射方向に向かって複数本の骨竿7を備える。笠部材3がアンカーピン2と一体なので、元のコンクリート躯体との界面で剥落するおそれもなく、断面修復材の剥落を防止できる。また、笠部材3は放射方向に向かって複数本の骨竿7が形成されているので、アンカーピンをコンクリートに穿孔された穴に固定した状態で、断面欠損部に断面修復材を充填した場合でも、断面修復材は、笠部材3の骨竿7と骨竿の間を介して、アンカーピンの先端部側に充填することができる。
【選択図】図1
The present invention provides a reinforcing metal fitting for cross-sectional repair that facilitates cross-section repair of concrete and prevents peeling of a filled cross-section repair material.
An anchor pin 2 fixed to a hole drilled in concrete, and a cap member 3 provided at a base end portion thereof and formed integrally with the anchor pin, the cap member in a radial direction. A plurality of antiques 7 are provided. Since the cap member 3 is integral with the anchor pin 2, there is no fear of peeling off at the interface with the original concrete frame, and the cross-sectional repair material can be prevented from peeling off. In addition, since the cap member 3 is formed with a plurality of urns 7 in the radial direction, when the cross-sectional defect is filled in the cross-sectional defect with the anchor pin fixed to the hole drilled in the concrete However, the cross-sectional repair material can be filled in the tip portion side of the anchor pin through the space between the urn 7 and the urn of the shade member 3.
[Selection] Figure 1

Description

本考案は、コンクリートの剥離箇所に断面修復材を充填する断面修復工事に使用するコンクリートの断面修復用補強金具に関する。   The present invention relates to a reinforcing metal fitting for repairing a cross section of concrete used for a cross section repairing work in which a section of the concrete is filled with a cross section repair material.

従来から、コンクリートの剥離箇所に断面修復材を充填する断面修復工事に使用するコンクリートの断面修復用補強金具が知られている。   2. Description of the Related Art Conventionally, there is known a reinforcing metal fitting for repairing a cross section of a concrete used for a cross section repairing work in which a cross-section repair material is filled in a peeled portion of the concrete.

この種のコンクリートの断面修復用補強金具として、コンクリート構造物の補修金具が従来から知られている(図7参照)。ここで、図7(a)は従来のコンクリート構造物の補修金具のアンカー部品を示す図であり、図7(b)は同コンクリート構造物の補修金具の羽根部材の断面図であり、図7(c)は同羽根部材の底面図を示す図である。このコンクリート構造物の補修金具は、基端部に雄ネジを設けられたアンカー11と、アンカー11の雄ネジに結合した連結用ナット113と、連結用ナット113に取り付ける羽根部材130とからなるものであった。そして、アンカー11の連結用ナット113に結合する羽根部材130は、取付円板131に複数本の骨竿132を放射方向に向けて固着したものであり、その取付円板131は中心部にあけた取付孔133を介して皿ネジ134によりアンカー11の連結用ナット113にネジ結合されるものであった。この羽根部材130の骨竿132は、取付円板131平面直角方向に形成した取付凹部135に接合して位置決めされ、その位置に溶接して固着されている。   Conventionally, a repair bracket for a concrete structure is known as a reinforcing bracket for repairing a cross section of this type of concrete (see FIG. 7). Here, FIG. 7A is a view showing an anchor part of a conventional repair fitting for a concrete structure, and FIG. 7B is a cross-sectional view of a blade member of the repair fitting for the concrete structure. (C) is a figure which shows the bottom view of the blade member. This repair fitting for a concrete structure includes an anchor 11 provided with a male screw at a base end, a connecting nut 113 coupled to the male screw of the anchor 11, and a blade member 130 attached to the connecting nut 113. Met. The blade member 130 coupled to the connecting nut 113 of the anchor 11 is obtained by fixing a plurality of urns 132 to the mounting disc 131 in the radial direction, and the mounting disc 131 is opened at the center. The screw 11 is screwed to the connecting nut 113 of the anchor 11 by a flat head screw 134 through the mounting hole 133. The urn 132 of this blade member 130 is positioned by being joined to an attachment recess 135 formed in a direction perpendicular to the plane of the attachment disk 131, and is fixed by welding at that position.

このコンクリート構造物の補修金具を用いた補修方法として、まずコンクリート躯体にアンカー11を固着し、続いてアンカー11に連結用ナット113が取り付けられる。そして、連結用ナット113の雌ネジ内に補修材が侵入しないようにキャップを嵌め、空洞部内に補修材を連結用ナット113の高さと同程度の高さまで充填する。それから連結用ナット113からキャップを外し、その連結用ナット113に羽根部材130を結合し、さらに空洞部にはコンクリート躯体の表面と同じ高さまで補修材を充填して補修作業を完了させるものであった。   As a repair method using the repair fitting of the concrete structure, the anchor 11 is first fixed to the concrete frame, and then the connecting nut 113 is attached to the anchor 11. Then, a cap is fitted so that the repairing material does not enter the female screw of the connecting nut 113, and the repairing material is filled in the hollow portion to the same height as the connecting nut 113. Then, the cap is removed from the connecting nut 113, the blade member 130 is coupled to the connecting nut 113, and the cavity is filled with a repair material to the same height as the surface of the concrete frame to complete the repair work. It was.

特開2002−115400号公報JP 2002-115400 A

上述した従来のコンクリート構造物の補修金具では、アンカー11の雄ネジに連結用ナット113を結合し、連結用ナット113に羽根部材130を取り付ける構成であるので、コンクリート構造物の補修工程において、アンカー11に連結用ナット113を取り付ける工程、連結用ナット113の雌ネジ内にキャップを嵌め込む工程、連結用ナット113からキャップを外す工程、そして連結用ナット113に羽根部材130を結合する工程が必要となり、コンクリート躯体の空洞部といった狭い空間で、これらの作業を行うのはとても煩雑で手間が大きかった。   In the above-described conventional repair fitting for a concrete structure, the connecting nut 113 is coupled to the male screw of the anchor 11 and the blade member 130 is attached to the connecting nut 113. Therefore, in the repairing process of the concrete structure, the anchor 11, the step of attaching the connecting nut 113 to the connecting nut 113, the step of fitting the cap into the female screw of the connecting nut 113, the step of removing the cap from the connecting nut 113, and the step of connecting the blade member 130 to the connecting nut 113 are required. In a narrow space such as a hollow part of a concrete frame, these operations were very complicated and laborious.

また、連結用ナット113の雌ネジ内にキャップを嵌めて、空洞部内に補修材を連結用ナット113の高さと同程度の高さまで充填した後、連結用ナット113からキャップを外し、その連結用ナット113に羽根部材130を結合して、空洞部にコンクリート躯体の表面と同じ高さまで補修材を充填するものであったので、キャップを取り外しする工程、補充材を2回に分けて充填する工程が必要になり、作業時間が増大するものであった。   Further, a cap is fitted into the female screw of the connecting nut 113 and the cavity is filled with a repair material to a height similar to the height of the connecting nut 113, and then the cap is removed from the connecting nut 113, Since the blade member 130 is connected to the nut 113 and the cavity is filled with the repair material up to the same height as the surface of the concrete frame, the step of removing the cap and the step of filling the replenishment material in two portions Was required, and the working time was increased.

さらに、アンカー11と連結用ナット113をネジ結合するとともに、連結用ナット113と羽根部材130をネジ結合しているので、ネジ結合が不十分な場合には、充填した補修材が元のコンクリート躯体との界面で剥落するおそれがあるという問題もあった。特に、補修材を充填した後においては、ネジ結合が不十分か否かを確認することができないことから、施工の依頼主にとって不安要素となる。   Further, since the anchor 11 and the coupling nut 113 are screw-coupled and the coupling nut 113 and the blade member 130 are screw-coupled, if the screw coupling is insufficient, the filled repair material is the original concrete frame. There was also a problem that it might peel off at the interface. In particular, after filling the repair material, it cannot be confirmed whether or not the screw connection is insufficient.

本考案は、上記問題点に鑑みてなされたもので、コンクリートの断面修復の施工を容易にするとともに、充填した断面修復材が剥落しないようにするコンクリートの断面修復用補強金具を提供することを目的とする。   The present invention has been made in view of the above problems, and provides a reinforcing bracket for repairing a concrete section that facilitates the construction of a concrete section repair and prevents the filled section repair material from peeling off. Objective.

上記課題を解決し上記目的を達成するために、本考案のうち第1の態様に係るものは、コンクリートの剥離箇所に断面修復材を充填する断面修復工事に使用するコンクリートの断面修復用補強金具であって、コンクリートに穿孔した穴に固定されるアンカーピンと、アンカーピンの基端部に設けられ、アンカーピンと一体的に形成された笠部材と、を有し、笠部材は、放射方向に向かって複数本の骨竿が形成されているものである。   In order to solve the above-mentioned problems and achieve the above object, the first aspect of the present invention is a reinforcing bracket for cross-sectional repair of concrete used for cross-section repair work in which a section of concrete is filled with a cross-section repair material. An anchor pin fixed to a hole drilled in the concrete and a cap member provided at a base end portion of the anchor pin and integrally formed with the anchor pin, and the cap member is directed in the radial direction. A plurality of urns are formed.

本考案によれば、笠部材がアンカーピンと一体的に形成されているので、従来のような工程(アンカー11に連結用ナット113を取り付ける工程、連結用ナット113の雌ネジ内にキャップを嵌め込む工程、連結用ナット113からキャップを外す工程、連結用ナット113に羽根部材130を結合する工程)が不要となり、コンクリートの断面修復の施工を容易に行うことができ、作業時間も短縮することができる。また、笠部材がアンカーピンと一体的に形成されているので、笠部材とアンカーピンとがネジ結合で形成された場合のように断面修復材が元のコンクリート躯体との界面で剥落するおそれもなく、断面修復材の剥落を防止することができる。また、笠部材は放射方向に向かって複数本の骨竿が形成されているので、アンカーピンをコンクリートに穿孔された穴に固定した状態で、断面欠損部に断面修復材を充填した場合でも、断面修復材は、笠部材の骨竿と骨竿の間を介して、アンカーピンの先端部側に充填することができる。これにより、断面欠損部の全域に容易に断面修復材を充填することができる。   According to the present invention, since the cap member is integrally formed with the anchor pin, the cap is fitted into the female screw of the connecting nut 113, as in the conventional process (the step of attaching the connecting nut 113 to the anchor 11). The process, the step of removing the cap from the connecting nut 113, and the step of connecting the blade member 130 to the connecting nut 113) are not required, and the construction of the concrete cross section can be easily repaired, and the working time can be shortened. it can. In addition, since the cap member is formed integrally with the anchor pin, there is no risk that the cross-sectional repair material will be peeled off at the interface with the original concrete frame as in the case where the cap member and the anchor pin are formed by screw connection, The cross-section repair material can be prevented from peeling off. In addition, since the cap member is formed with a plurality of urns in the radial direction, even when the cross-sectional defect material is filled with a cross-sectional repair material in a state where the anchor pin is fixed to the hole drilled in the concrete, The cross-sectional repair material can be filled on the tip portion side of the anchor pin through the space between the urns of the cap member. Thereby, a cross-sectional repair material can be easily filled in the whole area of a cross-sectional defect | deletion part.

本考案のうち第2の態様に係るものは、第1の態様に係るコンクリートの断面修復用補強金具であって、前記アンカーピンは、芯棒を打設することにより該アンカーピンの先端部の拡張部を拡張することが可能な芯棒打込み式アンカーであるものである。   Of the present invention, the second aspect is a reinforcing bracket for repairing a concrete cross section according to the first aspect, wherein the anchor pin is formed by driving a core rod to form a tip of the anchor pin. This is a core rod driving type anchor capable of expanding the expansion portion.

本発明によれば、アンカーピンは、ハンマーにより芯棒を打設することによりアンカーピンの先端部の拡張部を拡張することが可能な芯棒打込み式アンカーを用いているので、本体打込み式アンカーのように別途打込み棒が必要でなく、また接着式アンカーのように別途樹脂も必要としないので、コンクリートの断面修復を容易に行うことができる。   According to the present invention, the anchor pin uses the core rod driving type anchor that can expand the extended portion of the tip portion of the anchor pin by driving the core rod with a hammer. Thus, a separate driving rod is not required, and no additional resin is required unlike an adhesive anchor, so that the cross section of the concrete can be easily repaired.

本考案のうち第3の態様に係るものは、第1の態様または第2の態様に係るコンクリートの断面修復用補強金具であって、笠部材の骨竿は、放射方向に向かうに従い、アンカーの先端部方向に湾曲するものである。   A third aspect of the present invention is the reinforcing bracket for repairing a concrete cross section according to the first aspect or the second aspect of the present invention. It curves in the direction of the tip.

本考案によれば、笠部材の骨竿は放射方向に向かうに従いアンカーピンの先端部方向に湾曲しているので、笠部材の骨竿の剛性が強くなり、コンクリートの剥離箇所に充填される断面修復材を強く押さえ込むことができる。   According to the present invention, since the curl of the cap member is curved in the direction of the tip of the anchor pin as it goes in the radial direction, the rigidity of the curl of the cap member becomes stronger, and the cross-section filled in the peeling site of the concrete We can hold down restoration material strongly.

本考案のコンクリートの断面修復用補強金具によれば、笠部材がアンカーピンと一体的に形成されているので、コンクリートの断面修復の施工を容易にすることができるとともに、断面修復材の剥落を防止することができる。   According to the reinforcing bracket for repairing a cross section of concrete according to the present invention, since the cap member is formed integrally with the anchor pin, it is possible to facilitate the construction of the cross section of the concrete and prevent the cross section repair material from peeling off. can do.

本考案の一実施形態におけるコンクリートの断面修復用補強金具の上部斜視図である。It is a top perspective view of the reinforcement metal fitting for cross-section restoration of concrete in one embodiment of the present invention. 同コンクリートの断面修復用補強金具の上面図である。It is a top view of the reinforcing metal fitting for cross-sectional repair of the concrete. 同コンクリートの断面修復用補強金具の下部斜視図である。It is a lower perspective view of the reinforcing bracket for cross-sectional repair of the same concrete. 同コンクリートの断面修復用補強金具の下面図である。It is a bottom view of the reinforcing bracket for cross-sectional repair of the concrete. 同コンクリートの断面修復用補強金具を用いて行う断面修復作業工程を示す断面工程図である。It is a cross-sectional process figure which shows the cross-section repair work process performed using the reinforcing metal fitting for cross-section repair of the concrete. 同コンクリートの断面修復用補強金具を用いて行う断面修復作業工程のフローチャートを示す図である。It is a figure which shows the flowchart of the cross-section repair work process performed using the reinforcement metal for cross-section repair of the concrete. (a)従来のコンクリート構造物の補修金具のアンカー部品を示す図である。 (b)同コンクリート構造物の補修金具の羽根部材の断面図である。 (c)同羽根部材の底面図を示す図である。(A) It is a figure which shows the anchor component of the repair metal fitting of the conventional concrete structure. (B) It is sectional drawing of the blade member of the repair metal fitting of the concrete structure. (C) It is a figure which shows the bottom view of the blade member.

以下、本考案にかかるコンクリートの断面修復用補強金具の一実施形態について図面を参照にしながら説明する。ここで、図1は本考案の一実施形態におけるコンクリートの断面修復用補強金具の上部斜視図であり、図2は同コンクリートの断面修復用補強金具の上面図であり、図3は同コンクリートの断面修復用補強金具の下部斜視図であり、図4は同コンクリートの断面修復用補強金具の下面図である。   Hereinafter, an embodiment of a reinforcing bracket for repairing a cross section of concrete according to the present invention will be described with reference to the drawings. Here, FIG. 1 is a top perspective view of a reinforcing bracket for repairing a cross section of concrete in an embodiment of the present invention, FIG. 2 is a top view of the reinforcing bracket for repairing a cross section of the concrete, and FIG. FIG. 4 is a bottom perspective view of the reinforcing bracket for cross-sectional repair, and FIG. 4 is a bottom view of the reinforcing bracket for cross-sectional repair of the same concrete.

コンクリートの断面修復用補強金具1は、コンクリートの剥離箇所に断面修復材である樹脂モルタルを充填する断面修復工事に使用されるものであって、アンカーピン2と、笠部材3とから構成されている。なお、本実施形態では、コンクリートの断面修復用補強金具1を、アンカーピン2と笠部材3とから構成させたが、他の構成部品などを備えるものであってもよい。   The concrete cross-section repair reinforcing metal fitting 1 is used for cross-section repair work in which a resin mortar that is a cross-section repair material is filled in a peeled portion of concrete, and is composed of an anchor pin 2 and a cap member 3. Yes. In addition, in this embodiment, although the reinforcement metal fitting 1 for cross-section restoration of concrete was comprised from the anchor pin 2 and the cap member 3, you may provide another component.

アンカーピン2は、先端部に軸方向に4本のスリットが形成された拡張部4を備えるアンカーピン本体5と、アンカーピン本体5内を貫通して配置された芯棒6とを有している。本実施形態のアンカーピン2は、ハンマーで芯棒6を打設することによりアンカーピン2の先端部の拡張部4が拡張する芯棒打込み式アンカーが用いられている。そして、アンカーピン本体5から出ている芯棒6の基端部をハンマー等で叩き込むことにより、アンカーピン本体4のコンクリートに埋め込まれた先端部分の拡張部4が開き、コンクリートの穴の内周壁に喰い込みアンカーピン2がコンクリートに固着される。なお、アンカーピン本体5および芯棒6の素材として、ステンレス鋼製の素材を使用している。   The anchor pin 2 has an anchor pin main body 5 having an extended portion 4 having four slits formed in the axial direction at the tip portion, and a core rod 6 disposed through the anchor pin main body 5. Yes. As the anchor pin 2 of the present embodiment, a core rod driving type anchor in which the expansion portion 4 at the tip end portion of the anchor pin 2 is expanded by driving the core rod 6 with a hammer is used. Then, by striking the base end portion of the core rod 6 protruding from the anchor pin main body 5 with a hammer or the like, the extension portion 4 at the distal end portion embedded in the concrete of the anchor pin main body 4 is opened, and the inner peripheral wall of the concrete hole The anchor pin 2 is bitten into the concrete. A stainless steel material is used as the material for the anchor pin main body 5 and the core rod 6.

笠部材3は、アンカーピン2(アンカーピン本体5)の基端部にアンカーピン2と一体的に設けられ、アンカーピン2(アンカーピン本体5)から放射方向に向かって6本の骨竿7が形成されている。なお、本実施形態では、骨竿7を6本設けたが、これに限らず、3本や9本などの複数本設けたものであってもよい。また、本実施形態では、笠部材3とアンカーピン2とを一体として製造させているが。これに限らず、アンカーピン本体5の基端部に雄ネジを設け、そのアンカーピン本体5の雄ネジと笠部材3の中央部の雌ネジに接着材を塗布して螺合させて一体化してもよい。この笠部材3の骨竿7は、アンカーピン2(アンカーピン本体5)から放射方向に向かうに従い、アンカーピン2の先端部方向に湾曲している。換言すると、笠部材3の骨竿7は、骨竿7の先端に向かうに従い、アンカーピン2の先端部方向に向かって湾曲している。   The cap member 3 is integrally provided with the anchor pin 2 at the proximal end of the anchor pin 2 (anchor pin main body 5), and six antiques 7 from the anchor pin 2 (anchor pin main body 5) in the radial direction. Is formed. In this embodiment, six antiques 7 are provided. However, the present invention is not limited to this, and a plurality of antiques such as three or nine may be provided. Further, in the present embodiment, the cap member 3 and the anchor pin 2 are manufactured as one body. Not limited to this, a male screw is provided at the base end portion of the anchor pin main body 5, and an adhesive is applied to the male screw of the anchor pin main body 5 and the female screw at the center of the cap member 3 and screwed together to be integrated. May be. The urn 7 of the shade member 3 is bent in the direction of the distal end portion of the anchor pin 2 in the radial direction from the anchor pin 2 (anchor pin main body 5). In other words, the urn 7 of the cap member 3 is curved toward the distal end portion of the anchor pin 2 as it goes toward the distal end of the urn 7.

次に、本考案の一実施形態におけるコンクリートの断面修復用補強金具1を用いたコンクリートの断面修復手順について図5および図6を用いて説明する。ここで、図5は本考案の一実施形態におけるコンクリートの断面修復用補強金具を用いて行う断面修復作業工程を示す工程断面図であり、図6は同断面修復作業工程のフローチャートを示す図である。なお、本実施形態では、学校などのコンクリート構造物のコンクリートの剥落箇所を断面修復材を用いて修復する工程について説明する。なお、本実施形態では、断面修復材として、樹脂モルタルを用いているが、これに限らず、他の断面修復材を用いてもよい。   Next, a concrete cross-section repair procedure using the concrete cross-section repair reinforcing metal fitting 1 according to an embodiment of the present invention will be described with reference to FIGS. 5 and 6. Here, FIG. 5 is a process cross-sectional view showing the cross-section repair work process performed using the reinforcing metal fitting for cross-section repair of concrete in one embodiment of the present invention, and FIG. 6 is a flowchart showing the cross-section repair work process. is there. In addition, this embodiment demonstrates the process of repairing the peeling part of the concrete of concrete structures, such as a school, using a cross-section repair material. In the present embodiment, the resin mortar is used as the cross-sectional repair material. However, the present invention is not limited to this, and other cross-sectional repair materials may be used.

まず、穿孔工程(S1)が実施される。穿孔工程では、鉄筋が腐食等してコンクリートが剥落した断面欠損部にアンカーピン2を差し込むための穴を穿孔するための工程である(図5(a)参照)。具体的には、鉄筋が腐食等してコンクリートが剥落し、露出しているコンクリート面にドリルを用いてアンカーピン2のサイズに見合った穴が穿孔される。なお、コンクリートの断面欠損部の表面に脆弱物が付着している場合は、脆弱物を落としてから、穿孔工程が実施される。   First, a drilling step (S1) is performed. The drilling step is a step for drilling a hole for inserting the anchor pin 2 into the cross-sectional defect where the reinforcing bars corroded and the concrete has fallen off (see FIG. 5A). Specifically, the reinforcing bars corrode and the concrete peels off, and a hole corresponding to the size of the anchor pin 2 is drilled on the exposed concrete surface using a drill. In addition, when a fragile material adheres to the surface of the cross-sectional defect portion of the concrete, the piercing step is performed after the fragile material is dropped.

次に、アンカーピン固定工程(S2)が実施される。アンカーピン固定工程では、穿孔工程において穿孔された穴にアンカーピン2が挿入され、アンカーピン2が固定される(図5(b)、図5(c)、図5(d)参照)。具体的には、穿孔工程において穿孔された穴にアンカーピン2を挿入した後に、ハンマーで芯棒6を打設することによりアンカーピン2の先端部の拡張部4を拡張させて穿孔された穴の内面壁に喰い込ませ、アンカーピン2が固定される。このように、本実施形態では、ハンマーにより芯棒6を打設することによりアンカーピン2の先端部の拡張部4を拡張することが可能な芯棒打込み式アンカーを用いているので、コンクリートにアンカーピン2を容易に固定することができる。   Next, an anchor pin fixing step (S2) is performed. In the anchor pin fixing step, the anchor pin 2 is inserted into the hole drilled in the drilling step, and the anchor pin 2 is fixed (see FIGS. 5B, 5C, and 5D). Specifically, after inserting the anchor pin 2 into the hole drilled in the drilling step, the core rod 6 is driven with a hammer to expand the expanded portion 4 at the tip of the anchor pin 2 and drilled. And the anchor pin 2 is fixed. Thus, in this embodiment, since the core rod driving type anchor that can expand the expansion portion 4 at the tip of the anchor pin 2 by driving the core rod 6 with a hammer is used, The anchor pin 2 can be easily fixed.

次に、プライマー塗布工程(S3)が実施される。プライマー塗布工程は、塗布する樹脂モルタルの接着を高めるために行われる下地処理工程であり、この下地処理を行うことにより、樹脂モルタルを塗布しても樹脂モルタルがめくれにくくなる。具体的には、コンクリートの断面欠損部表面に樹脂モルタルに見合ったプライマーが塗布される。なお、本実施形態では、プライマーとして、エポキシ樹脂系プライマーが用いられている。   Next, a primer application process (S3) is performed. The primer application step is a base treatment step performed to enhance the adhesion of the resin mortar to be applied. By performing this base treatment, the resin mortar is hardly turned over even if the resin mortar is applied. Specifically, a primer corresponding to the resin mortar is applied to the surface of the cross-sectional defect portion of the concrete. In this embodiment, an epoxy resin primer is used as the primer.

次に、断面修復材充填工程(S4)が実施される。断面修復材充填工程は、プライマー塗布工程により塗布されたプライマーの可使時間内に実施され、笠部材3の上部から断面修復材である樹脂モルタルが充填される。これにより、笠部材3は放射方向に向かって6本の骨竿7が形成されているので、アンカーピン2をコンクリートに穿孔された穴に固定した状態で、断面欠損部に樹脂モルタルを充填した場合でも、樹脂モルタルは、笠部材3の骨竿7と骨竿7の間を介して、アンカーピン2の先端部側に充填することができる。これにより、断面欠損部の全域に容易に樹脂モルタルを充填させることができる。また、この場合、笠部材3の骨竿7は放射方向に向かうに従いアンカーピン2の先端部方向に湾曲しているので、笠部材3の骨竿7の剛性が強くなり、コンクリートの剥離箇所に充填される樹脂モルタルを強く押さえ込むことができる。   Next, a cross-section repair material filling step (S4) is performed. The cross-section repair material filling step is performed within the working time of the primer applied by the primer application step, and the resin mortar that is the cross-section repair material is filled from the upper part of the cap member 3. As a result, the cap member 3 is formed with six urns 7 in the radial direction, so that the cross-section defect portion is filled with resin mortar while the anchor pin 2 is fixed to the hole drilled in the concrete. Even in this case, the resin mortar can be filled in the distal end side of the anchor pin 2 via the space between the urn 7 and the urn 7 of the cap member 3. Thereby, the resin mortar can be easily filled in the entire cross-sectional defect portion. Further, in this case, since the urn 7 of the cap member 3 is curved in the direction of the distal end portion of the anchor pin 2 as it goes in the radial direction, the rigidity of the urn 7 of the cap member 3 is increased and the concrete is peeled off. The filled resin mortar can be pressed down strongly.

次に、養生工程(S5)が実施される。養生工程では、断面欠損部に充填された樹脂モルタルが完全に硬化するまで養生される。   Next, a curing step (S5) is performed. In the curing process, curing is performed until the resin mortar filled in the cross-sectional defect portion is completely cured.

以上説明したように、本実施形態では、笠部材3がアンカーピン2と一体的に形成されているので、コンクリートの断面修復の施工を容易に行うことができ、作業時間も短縮することができる。また、笠部材3がアンカーピン2と一体的に形成されているので、笠部材とアンカーピンとがネジ結合で形成された場合のように断面修復材が元のコンクリート躯体との界面で剥落するおそれもなく、樹脂モルタルの剥落を防止することができる。   As described above, in this embodiment, the cap member 3 is formed integrally with the anchor pin 2, so that the construction for repairing the cross section of the concrete can be easily performed, and the working time can also be shortened. . Further, since the cap member 3 is formed integrally with the anchor pin 2, the cross-sectional repair material may be peeled off at the interface with the original concrete frame as in the case where the cap member and the anchor pin are formed by screw connection. Therefore, the resin mortar can be prevented from peeling off.

なお、今回開示された実施の形態はすべての点で例示であって制限的なものではないと考えられるべきである。さらに本考案の範囲は、上記した説明ではなく特許請求の範囲の記載によって示され、特許請求の範囲と均等の意味及び範囲内でのすべての変更が含まれることが意図される。   The embodiment disclosed this time should be considered as illustrative in all points and not restrictive. Further, the scope of the present invention is shown not by the above description but by the description of the scope of claims, and is intended to include all modifications within the meaning and scope equivalent to the scope of claims.

1 コンクリートの断面修復用補強金具
2 アンカーピン
3 笠部材
4 拡張部
5 アンカーピン本体
6 芯棒
7 骨竿

DESCRIPTION OF SYMBOLS 1 Reinforcement metal fitting for cross-section repair of concrete 2 Anchor pin 3 Cap member 4 Expansion part 5 Anchor pin main body 6 Core rod 7 Antique

Claims (3)

コンクリートの剥離箇所に断面修復材を充填する断面修復工事に使用するコンクリートの断面修復用補強金具であって、
コンクリートに穿孔した穴に固定されるアンカーピンと、
該アンカーピンの基端部に設けられ、該アンカーピンと一体的に形成された笠部材と、を有し、
該笠部材は、放射方向に向かって複数本の骨竿が形成されているコンクリートの断面修復用補強金具。
Reinforcement bracket for concrete cross-section repair used for cross-section repair work in which the section of concrete is filled with cross-section repair material,
Anchor pins fixed in holes drilled in concrete,
A cap member provided at a base end portion of the anchor pin and formed integrally with the anchor pin;
The shade member is a reinforcing metal fitting for repairing a cross section of concrete in which a plurality of urns are formed in the radial direction.
前記アンカーピンは、芯棒を打設することにより該アンカーピンの先端部の拡張部を拡張することが可能な芯棒打込み式アンカーであることを特徴とする請求項1記載のコンクリートの断面修復用補強金具。   2. The concrete cross-section repair according to claim 1, wherein the anchor pin is a core rod driving type anchor capable of expanding an extended portion of a tip portion of the anchor pin by driving the core rod. Reinforcing metal fittings. 前記笠部材の骨竿は、放射方向に向かうに従い、前記アンカーピンの先端部方向に湾曲することを特徴とする請求項1または請求項2記載のコンクリートの断面修復用補強金具

3. The reinforcing bracket for repairing a concrete cross section according to claim 1, wherein the urn of the cap member is curved toward the tip of the anchor pin as it goes in the radial direction.

JP2012002628U 2012-05-02 2012-05-02 Reinforcing brackets for concrete cross-section repair Expired - Lifetime JP3177016U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP2012002628U JP3177016U (en) 2012-05-02 2012-05-02 Reinforcing brackets for concrete cross-section repair

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP2012002628U JP3177016U (en) 2012-05-02 2012-05-02 Reinforcing brackets for concrete cross-section repair

Publications (1)

Publication Number Publication Date
JP3177016U true JP3177016U (en) 2012-07-12

Family

ID=48003900

Family Applications (1)

Application Number Title Priority Date Filing Date
JP2012002628U Expired - Lifetime JP3177016U (en) 2012-05-02 2012-05-02 Reinforcing brackets for concrete cross-section repair

Country Status (1)

Country Link
JP (1) JP3177016U (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2015092054A (en) * 2013-10-03 2015-05-14 三栄商事株式会社 Reinforcement structure of wooden building
CN107663953A (en) * 2013-06-06 2018-02-06 Sika技术股份公司 System and method for reinforcing bearing structure

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107663953A (en) * 2013-06-06 2018-02-06 Sika技术股份公司 System and method for reinforcing bearing structure
CN107663953B (en) * 2013-06-06 2020-03-10 Sika技术股份公司 System and method for reinforcing a load bearing structure
JP2015092054A (en) * 2013-10-03 2015-05-14 三栄商事株式会社 Reinforcement structure of wooden building

Similar Documents

Publication Publication Date Title
JP3177016U (en) Reinforcing brackets for concrete cross-section repair
JP2018502681A (en) Joint structure of implant abutment and crown
WO2008053542A1 (en) Anchor and its anchoring method and anchoring structure employing it
JP2015117462A (en) Pinning method
JP6345983B2 (en) Extended post-installed anchor bolt
JP4653675B2 (en) Anchor method
JP5717437B2 (en) Grout pouring hole forming form
JP4352817B2 (en) Tile peeling prevention method
JP6985717B2 (en) Pinning method
JP2009526596A (en) Footwear heel
JP6506538B2 (en) Drilling method of concrete structure
JP3958226B2 (en) Anchor pin for pinning method and pinning method using the same
JP5127945B2 (en) Repair method for floating parts such as walls and jigs used therefor
CN206438512U (en) A kind of novel slurry filling soil nailing
JP5392748B2 (en) Fixing structure and fixing method of reinforcing bar to reinforced concrete structure
US20040045245A1 (en) Wall repair clip
JP6092924B2 (en) Repair method of floating parts such as walls and fixing pin fixing method
JP3812947B2 (en) How to repair tiled outer walls
JP4386802B2 (en) Anchor member
JP5525142B2 (en) Repair structure, repair anchor and repair method
TWI604828B (en) Application of dental establishment of the fixed method
JP2005023550A (en) Outer wall repairing anchor pin
JP6350621B2 (en) Wall repair method
JP2010144381A (en) Metal fitting, structure and construction method for repairing exterior wall
KR102277664B1 (en) Coupling Method of Implant structure using press-formed metal tube structure

Legal Events

Date Code Title Description
R150 Certificate of patent or registration of utility model

Ref document number: 3177016

Country of ref document: JP

Free format text: JAPANESE INTERMEDIATE CODE: R150

Free format text: JAPANESE INTERMEDIATE CODE: R150

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20150620

Year of fee payment: 3

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

EXPY Cancellation because of completion of term