JP3146926B2 - Eaves gutter - Google Patents

Eaves gutter

Info

Publication number
JP3146926B2
JP3146926B2 JP13128195A JP13128195A JP3146926B2 JP 3146926 B2 JP3146926 B2 JP 3146926B2 JP 13128195 A JP13128195 A JP 13128195A JP 13128195 A JP13128195 A JP 13128195A JP 3146926 B2 JP3146926 B2 JP 3146926B2
Authority
JP
Japan
Prior art keywords
eaves gutter
joint
eaves
main body
front wall
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
JP13128195A
Other languages
Japanese (ja)
Other versions
JPH08326239A (en
Inventor
英明 皆川
和晴 田中
敏夫 西原
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Panasonic Electric Works Co Ltd
Original Assignee
Matsushita Electric Works Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Matsushita Electric Works Ltd filed Critical Matsushita Electric Works Ltd
Priority to JP13128195A priority Critical patent/JP3146926B2/en
Publication of JPH08326239A publication Critical patent/JPH08326239A/en
Application granted granted Critical
Publication of JP3146926B2 publication Critical patent/JP3146926B2/en
Anticipated expiration legal-status Critical
Expired - Fee Related legal-status Critical Current

Links

Landscapes

  • Sewage (AREA)
  • Building Environments (AREA)

Description

【発明の詳細な説明】DETAILED DESCRIPTION OF THE INVENTION

【0001】[0001]

【産業上の利用分野】本発明は軒樋本体を軒樋継ぎ手に
よって接続して成る軒樋に関するものである。
BACKGROUND OF THE INVENTION 1. Field of the Invention The present invention relates to an eaves gutter having an eaves gutter body connected by an eaves gutter joint.

【0002】[0002]

【従来の技術】従来のこの種のものとしては、実開平3
−86933号公報に開示されている。図3はこの軒樋
本体101の断面図である。図4はこの軒樋本体101
の斜視図である。図3及び図4に示すようにこの軒樋本
体101は膨出した前壁部の中程に前上方に開口した長
手方向の凹溝102を形成しており、凹溝102の中程
の底部に一定間隔に軒樋本体101内へ貫通した水抜き
孔103を穿設しており、軒樋本体101の凹溝102
に溜まった水を凹溝102の水抜き孔103から軒樋本
体101内に流すこととしている。これにより軒樋本体
101の膨出した前壁部を流れる水を地面に落下させる
ことなく、軒樋本体101内に流すことを可能としてい
た。
2. Description of the Related Art Conventionally, this kind is disclosed in Japanese Utility Model Application Laid-Open No.
-86933. FIG. 3 is a sectional view of the eaves gutter main body 101. FIG. 4 shows this eaves gutter main body 101.
It is a perspective view of. As shown in FIG. 3 and FIG. 4, the eaves gutter main body 101 has a longitudinal concave groove 102 opened upward and forward in the middle of the bulging front wall portion. Water draining holes 103 penetrating into the eaves gutter main body 101 at regular intervals are formed in the eaves gutter main body 101.
The water collected in the eaves gutter main body 101 flows from the drain hole 103 of the concave groove 102. As a result, the water flowing through the bulging front wall portion of the eaves gutter main body 101 can flow into the eaves gutter main body 101 without dropping to the ground.

【0003】[0003]

【発明が解決しようとする課題】しかし上記従来例で
は、軒樋本体101内の水位が上昇し水抜き孔103よ
り上になると、水が一定間隔の水抜き孔103から一斉
に溢れ出すため軒樋本体101の実質的な容量が減少す
る。また軒樋本体101に一定間隔に水抜き孔103を
形成しなければならない。この場合軒樋本体101への
水抜き孔103の加工は通常は後加工によるため加工が
面倒になる。本発明はこの点に鑑みてなされたものであ
り、軒樋本体101だけでなく軒樋継ぎ手においても、
即ち軒樋全体においてその前壁部前面に降りかかった雨
水を地面に落下させることなく軒樋全体で受け、効率的
に軒樋内部へ集水することができ、しかも軒樋本体の実
質的な容量を減少させることなく、加工を削減できる軒
樋本体を提供し、前記軒樋本体を軒樋継ぎ手によって接
続して成る軒樋を提供することを目的とするものであ
る。
However, in the above prior art, when the water level in the eaves gutter main body 101 rises and becomes higher than the water drainage holes 103, the water overflows from the water drainage holes 103 at regular intervals, so that the eaves gutters. The substantial capacity of the gutter body 101 is reduced. Further, drain holes 103 must be formed in the eaves gutter main body 101 at regular intervals. In this case, the processing of the drainage holes 103 in the eaves gutter main body 101 is usually performed by post-processing, so that the processing becomes complicated. The present invention has been made in view of this point, and not only in the eaves gutter body 101 but also in the eaves gutter joint,
That is, the entire eaves gutter receives rainwater that has fallen on the front wall of the front wall without falling to the ground, and can efficiently collect water inside the eaves gutter. An object of the present invention is to provide an eaves gutter main body capable of reducing processing without reducing the capacity, and to provide an eaves gutter formed by connecting the eaves gutter main bodies with an eaves gutter joint.

【0004】[0004]

【課題を解決するための手段】本発明の請求項1記載の
軒樋は、軒樋本体を軒樋継ぎ手によって接続して成る軒
樋において、前壁部の中程に前上方に開口した長手方向
の凹溝を軒樋本体と軒樋継ぎ手とに連続させて形成し、
軒樋継ぎ手においてのみ凹溝の中程の底部に軒樋継ぎ手
内へ貫通した水抜き孔を穿設して成ることを特徴とする
ものである。
According to a first aspect of the present invention, there is provided an eaves gutter formed by connecting an eaves gutter body by an eaves gutter joint, wherein the eaves gutter is opened in the front upper portion in the middle of the front wall portion. Directional grooves are formed in the eaves gutter body and the eaves gutter joint continuously,
The drainage hole penetrating into the eaves gutter joint is formed at the bottom of the middle of the concave groove only in the eaves gutter joint.

【0005】本発明の請求項2記載の軒樋は、請求項1
記載の軒樋において、前壁部を前方へ膨出させて形成し
たことを特徴とするものである。
[0005] The eaves gutter according to claim 2 of the present invention is characterized by claim 1.
In the eaves gutter described above, the front wall portion is formed by bulging forward.

【0006】本発明の請求項3記載の軒樋は、請求項1
又は請求項2記載の軒樋において、凹溝の下側溝縁にせ
き止め凸部を長手方向の全長にわたって形成したことを
特徴とするものである。
According to a third aspect of the present invention, there is provided an eaves gutter.
Alternatively, in the eaves gutter according to the second aspect, the damming projection is formed on the lower groove edge of the concave groove over the entire length in the longitudinal direction.

【0007】本発明の請求項4記載の軒樋は、請求項3
記載の軒樋において、軒樋継ぎ手のせき止め凸部を外側
へ突出折曲した形状に形成して該せき止め凸部の内側に
形成される凹部に軒樋本体のせき止め凸部を係合させ、
軒樋本体の外側に軒樋継ぎ手を嵌合させて接続したこと
を特徴とするものである。
According to a fourth aspect of the present invention, there is provided an eaves gutter.
In the eaves gutter described above, the eaves gutter joint damming projection is formed in a shape protruding outward and bent, and the eaves gutter body damming projection is engaged with a recess formed inside the damming projection,
The eaves gutter joint is fitted and connected to the outside of the eaves gutter body.

【0008】[0008]

【作用】本発明の請求項1記載の軒樋は、その前壁部に
落下した雨水は、前壁部の中程に前上方に開口した長手
方向の凹溝に流入し、凹溝を伝わって軒樋継ぎ手の凹溝
に流れ、軒樋継ぎ手の凹溝の中程の底部に穿設された水
抜き孔から軒樋継ぎ手内に流れ、軒樋本体内に排水され
る。
In the eaves gutter according to the first aspect of the present invention, rainwater that has fallen on the front wall of the eaves flows into the longitudinal groove opened upward and forward in the middle of the front wall, and travels along the groove. The water flows into the eave gutter joint groove, flows into the eave gutter joint from a drain hole formed in the bottom of the middle of the eave gutter joint groove, and is drained into the eave gutter body.

【0009】本発明の請求項2記載の軒樋は、その前壁
部を前方へ膨出させて形成しているため、軒先との一体
感、ボリューム感があり外観良好であるが、雨水が多量
に降りかかり地面に落下するという問題がある。しかし
この場合は前壁部の中程に前上方に開口した長手方向の
凹溝を形成しているため、軒樋の前壁部に落下した雨水
が前方へ膨出した部分を伝わってスムーズに凹溝に流入
する。
The eaves gutter according to the second aspect of the present invention is formed by expanding the front wall portion forward, so that the eaves gutter has a sense of unity with the eaves and a good sense of volume, and has a good appearance. There is a problem that it falls a lot and falls to the ground. However, in this case, since a longitudinal groove that opens upward and forward is formed in the middle of the front wall, the rainwater that has fallen on the front wall of the eaves gutter smoothly propagates through the part that swells forward. It flows into the groove.

【0010】本発明の請求項3記載の軒樋は、雨水が凹
溝を流れる際に、せき止め凸部により雨水が凹溝から溢
れるのを防止する。
The eaves gutter according to the third aspect of the present invention prevents rainwater from overflowing from the groove by the damming projection when the rainwater flows through the groove.

【0011】本発明の請求項4記載の軒樋は、軒樋継ぎ
手のせき止め凸部の内側に形成される凹部に軒樋本体の
せき止め凸部を係合させ、軒樋本体の外側に軒樋継ぎ手
を嵌合させて接続する。これにより簡易かつ確実に軒樋
本体と軒樋継ぎ手とを接続できる。
According to a fourth aspect of the present invention, there is provided an eaves gutter, wherein the eaves gutter main body is engaged with the eaves gutter main body in a recess formed inside the eaves gutter joint. Fit and connect the fittings. Thereby, the eaves gutter body and the eaves gutter joint can be easily and reliably connected.

【0012】[0012]

【実施例】図1は本発明の一の実施例である軒樋の分解
斜視図である。図1に示すようにこの軒樋は軒樋本体2
と軒樋継ぎ手1とから構成され、軒樋本体2の外側に軒
樋継ぎ手1を嵌合させて接続して成るものである。
1 is an exploded perspective view of an eaves gutter according to one embodiment of the present invention. As shown in FIG. 1, the eaves gutter main body 2
And an eaves gutter joint 1. The eaves gutter joint 1 is fitted to and connected to the outside of the eaves gutter main body 2.

【0013】軒樋継ぎ手1は底面部3aと前壁部4aと
後壁部5aと前壁部4aに連続する前耳包持部6と後壁
部5aに連続する後耳包持部7とから構成され、膨出さ
せて形成した前壁部4aの中程に前上方に開口した長手
方向の凹溝8aを形成し、凹溝8aの中程の底部に軒樋
継ぎ手1内へ貫通した水抜き孔9を形成し、その内面側
に軒樋本体2の端部を嵌め込む嵌合溝10を形成してい
る。軒樋継ぎ手1は一体成形することが可能であり、こ
の場合は水抜き孔9は成形時に形成することができ、後
加工の必要がない。
The eave gutter joint 1 includes a bottom ear portion 3a, a front wall portion 4a, a rear wall portion 5a, a front ear wrapping portion 6 continuous with the front wall portion 4a, and a rear ear wrapping portion 7 continuous with the rear wall portion 5a. And formed a longitudinal concave groove 8a opened forward and upward in the middle of the front wall portion 4a formed by bulging, and penetrated into the eaves gutter joint 1 at the middle bottom of the concave groove 8a. A drain hole 9 is formed, and a fitting groove 10 into which the end of the eave gutter main body 2 is fitted is formed on the inner surface side. The eaves gutter joint 1 can be integrally formed. In this case, the drain hole 9 can be formed at the time of molding, and there is no need for post-processing.

【0014】軒樋本体2は底面部3bと前壁部4bと後
壁部5bと前壁部4bに連続する前耳13と後壁部5a
に連続する後耳14とから構成され、膨出させて形成し
た前壁部4bの中程に前上方に開口した長手方向の凹溝
8bを形成している。尚軒樋本体2は通常は押し出し成
形によるため、孔を穿設する場合は後加工が必要となり
加工が面倒になるものであるが、本発明においては軒樋
継ぎ手1に水抜き孔9を形成しているためこのようなこ
とはない。
The eaves gutter body 2 has a front ear 13 and a rear wall 5a which are continuous with the bottom 3b, the front wall 4b, the rear wall 5b, and the front wall 4b.
And a rear recess 14 which is continuous with the rear ear 14 and has a longitudinal recessed groove 8b which is opened forward and upward in the middle of the front wall portion 4b formed by swelling. Since the eaves gutter body 2 is usually formed by extrusion, when drilling holes, post-processing is required and processing becomes troublesome. In the present invention, the drainage holes 9 are formed in the eaves gutter joint 1. This is not the case.

【0015】軒樋本体2と軒樋継ぎ手1とを接続する場
合は、軒樋継ぎ手1の両側から軒樋本体2の端部を軒樋
継ぎ手1の内面側の嵌合溝10に嵌合させて接続する。
これにより軒樋2の位置決めが容易にできる。
When connecting the eaves gutter main body 2 and the eaves gutter joint 1, the ends of the eaves gutter main body 2 from both sides of the eaves gutter connection 1 are fitted into the fitting grooves 10 on the inner surface side of the eaves gutter connection 1. Connect.
Thereby, the eaves gutter 2 can be easily positioned.

【0016】以下にこの軒樋の使用方法について説明す
る。軒樋全体の前壁部4a、4bに落下した雨水は、前
壁部4a、4bの中程に前上方に開口した長手方向の凹
溝8a、8bに流入し、凹溝8a、8bを伝わって軒樋
継ぎ手1の凹溝8a中程の底部に穿設された水抜き孔9
から軒樋継ぎ手1内に流入し、軒樋本体2内へと排水さ
れる。この軒樋は前壁部4a、4bを前方へ膨出させて
形成しているため、軒先との一体感、ボリューム感があ
り外観良好であるが、雨水が多量に降りかかり地面に落
下するという問題がある。しかしこの場合は前壁部4
a、4bの中程に前上方に開口した長手方向の凹溝8
a、8bを形成しているため、このような問題がなく軒
樋の前壁部4a、4bに落下した雨水が前方へ膨出した
部分を伝わってスムーズに凹溝8a、8bに流入する。
これにより雨水が軒樋の前壁部4a、4bから地面に落
下することを防止できる。
The method of using the eaves gutter will be described below. The rainwater that has fallen on the front walls 4a and 4b of the entire eaves gutter flows into the longitudinal grooves 8a and 8b that open upward in the middle of the front walls 4a and 4b, and travels along the grooves 8a and 8b. Drain hole 9 formed in the middle of the concave groove 8a of the eaves gutter 1
Flows into the eaves gutter joint 1 and drains into the eaves gutter body 2. Since the eaves gutter is formed by swelling the front walls 4a and 4b forward, the eaves gutter has a sense of unity with the eaves and a good sense of volume, and has a good appearance. However, a large amount of rainwater falls and falls on the ground. There is. However, in this case, the front wall 4
a, a longitudinal groove 8 which is opened in the front upper part in the middle of 4b
Since the a and b are formed, there is no such a problem, and the rainwater that has fallen on the front wall portions 4a and 4b of the eaves gutter smoothly flows into the concave grooves 8a and 8b along the bulging portion forward.
This can prevent rainwater from falling from the front walls 4a and 4b of the eaves gutter to the ground.

【0017】特に前壁部4a、4bの前方へ膨出した部
分に凹溝8a、8bを形成し、凹溝8a、8bを断面略
L字形状とした場合には雨水の凹溝8a、8bへの集水
効率が高い。
In particular, when the grooves 8a, 8b are formed at the portions of the front walls 4a, 4b which bulge forward, and the grooves 8a, 8b are substantially L-shaped in cross section, the grooves 8a, 8b High water collection efficiency.

【0018】図2は本発明の別の実施例である軒樋の分
解斜視図である。この軒樋は図1の場合によく似ている
が軒樋本体2と軒樋継ぎ手1の形状が僅かに異なる。こ
の場合軒樋本体2の凹溝8bと軒樋継ぎ手1の凹溝8a
の下側溝縁にせき止め凸部11b、凸部11aをそれぞ
れ形成しており、軒樋継ぎ手1のせき止め凸部11aを
外側へ突出折曲した形状に形成して、該せき止め凸部1
1aの内側に形成される凹部12に軒樋本体2のせき止
め凸部11bを係合させる構成である点が異なる。その
他の構成は図1の場合と同様であり、図1の場合と同様
に軒樋本体2を軒樋継ぎ手1に接続する。
FIG. 2 is an exploded perspective view of an eaves gutter according to another embodiment of the present invention. The eaves gutter is very similar to the case of FIG. 1, but the shapes of the eaves gutter body 2 and the eaves gutter joint 1 are slightly different. In this case, the groove 8b of the eave gutter body 2 and the groove 8a of the eave gutter joint 1
A damming protrusion 11b and a protrusion 11a are formed on the lower groove edge, respectively, and the damming protrusion 11a of the eaves gutter joint 1 is formed in a shape protruding outward and bent, and the damming protrusion 1b is formed.
The difference is that the damming projections 11b of the eaves gutter main body 2 are engaged with the recesses 12 formed inside the eaves gutter 1a. Other configurations are the same as those in FIG. 1, and the eaves gutter main body 2 is connected to the eaves gutter joint 1 as in the case of FIG.

【0019】この場合軒樋継ぎ手1のせき止め凸部11
aの内側に形成される凹部12に軒樋本体2のせき止め
凸部11bを係合させ、軒樋本体2の外側に軒樋継ぎ手
1を嵌合させて接続することにより簡易かつ確実に軒樋
本体と軒樋継ぎ手とを接続できる。
In this case, the damming projection 11 of the eave gutter joint 1 is provided.
The eaves gutters 11b of the eaves gutter main body 2 are engaged with the recesses 12 formed on the inner side of the e. The main body and the eave gutter joint can be connected.

【0020】以下にこの軒樋の使用方法について説明す
る。この場合せき止め凸部11a、11bにより雨水が
凹溝8a、8bから溢れるのを防止しつつ軒樋継ぎ手1
の凹溝8a中程の底部に穿設された水抜き孔9から軒樋
継ぎ手1内に流入し、軒樋本体2内へと排水される。こ
れにより雨水が軒樋の前壁部4a、4bから地面に落下
することをさらに確実に防止できる以外は上記実施例と
同様の構成及び作用効果である。尚この軒樋は直線の場
合に限られず、曲がり継ぎ手により軒樋本体を接続する
場合にも適用できる。
The method of using the eaves gutter will be described below. In this case, the damming projections 11a and 11b prevent rainwater from overflowing from the grooves 8a and 8b, and the eaves gutter joint 1
Flows into the eaves gutter joint 1 through a drainage hole 9 formed in the bottom of the middle of the concave groove 8a, and is drained into the eaves gutter body 2. This has the same configuration, operation and effect as the above embodiment, except that rainwater can be more reliably prevented from falling from the front walls 4a and 4b of the eaves gutter to the ground. The eaves gutter is not limited to a straight one, and can be applied to a case where the eaves gutter body is connected by a curved joint.

【0021】上述のごとくこのような軒樋により軒樋本
体2だけでなく軒樋継ぎ手1においても、即ち軒樋全体
においてその前壁部4a、4bの前面に降りかかった雨
水を地面に落下させることなく凹溝8a、8bにて受
け、この凹溝8a、8bに受けられた雨水を軒樋継ぎ手
1において軒樋内へ集水して効率的な集排水が行われ
る。また軒樋本体2の前壁部4bに水抜き孔9を設ける
必要がないため軒樋本体2の実質的な容量を減少させる
ことなく、加工を削減できる軒樋本体2を提供でき、か
かる軒樋本体2を軒樋継ぎ手1によって接続して成る軒
樋を提供することができる。
As described above, such eaves gutter causes the rainwater falling on the front surfaces of the front walls 4a and 4b to fall not only on the eaves gutter body 2 but also on the eaves gutter joint 1, that is, on the entire eaves gutter. The rainwater received by the grooves 8a and 8b without being received by the grooves 8a and 8b without water is collected into the eaves gutter at the eaves gutter joint 1 to efficiently collect and drain water. Further, since it is not necessary to provide the drain hole 9 in the front wall portion 4b of the eaves gutter main body 2, the eaves gutter main body 2 which can reduce the processing without reducing the substantial capacity of the eaves gutter main body 2 can be provided. An eaves gutter composed of the gutter main body 2 connected by the eaves gutter joint 1 can be provided.

【0022】[0022]

【発明の効果】本発明の請求項1記載の軒樋は、軒樋全
体においてその前壁部の前面に降りかかった雨水を地面
に落下させることなく効率的な集排水が行われると共に
軒樋継ぎ手のみに水抜き孔を穿設することにより軒樋の
前壁部に落下した雨水が地面に落下することを防止でき
る。これにより軒樋の実質的な容量を減少させることな
く、加工を削減できる軒樋を提供できる。
According to the first aspect of the present invention, the eaves gutter can be efficiently collected and drained without causing rainwater falling on the front surface of the front wall of the entire eaves gutter to fall on the ground. By forming a drain hole only in the joint, it is possible to prevent rainwater that has fallen on the front wall of the eaves gutter from falling onto the ground. This makes it possible to provide an eaves gutter capable of reducing processing without reducing the substantial capacity of the eaves gutter.

【0023】本発明の請求項2記載の軒樋は、請求項1
記載の軒樋の効果に加えて、デザイン性の向上を図れる
と共に軒樋の前壁部に落下した雨水をスムーズに軒樋内
に流入でき、雨水が地面に落下することをさらに確実に
防止できる。
The eaves gutter according to the second aspect of the present invention is the first aspect.
In addition to the effects of the eaves gutter described above, the design can be improved, and the rainwater that has fallen on the front wall of the eaves gutter can flow smoothly into the eaves gutter, further preventing rainwater from falling to the ground. .

【0024】本発明の請求項3記載の軒樋は、請求項1
又は請求項2記載の軒樋の効果に加えて、雨水が凹溝か
ら溢れるのを防止でき、雨水が地面に落下することをさ
らに確実に防止できる。
The eaves gutter according to claim 3 of the present invention is characterized by claim 1
Alternatively, in addition to the effect of the eaves gutter according to claim 2, rainwater can be prevented from overflowing from the concave groove, and rainwater can be more reliably prevented from falling to the ground.

【0025】本発明の請求項4記載の軒樋は、請求項3
記載の軒樋の効果に加えて、簡易かつ確実に軒樋本体と
軒樋継ぎ手とを接続できる。
The eaves gutter according to claim 4 of the present invention is characterized by claim 3
In addition to the effects of the described eaves gutter, the eaves gutter body and the eaves gutter joint can be easily and reliably connected.

【図面の簡単な説明】[Brief description of the drawings]

【図1】本発明の一の実施例である軒樋の分解斜視図で
ある。
FIG. 1 is an exploded perspective view of an eaves gutter according to one embodiment of the present invention.

【図2】本発明の別の実施例である軒樋の分解斜視図で
ある。
FIG. 2 is an exploded perspective view of an eaves gutter according to another embodiment of the present invention.

【図3】従来例の断面図である。FIG. 3 is a sectional view of a conventional example.

【図4】従来例の斜視図である。FIG. 4 is a perspective view of a conventional example.

【符号の説明】[Explanation of symbols]

1 軒樋継ぎ手 2 軒樋本体 4 前壁部 8 凹溝 9 水抜き孔 11 せき止め凸部 12 凹部 DESCRIPTION OF REFERENCE NUMERALS 1 eave gutter 2 eave gutter main body 4 front wall 8 concave groove 9 drainage hole 11 damming convex 12 concave

フロントページの続き (56)参考文献 特開 平3−217547(JP,A) 実開 平3−86933(JP,U) (58)調査した分野(Int.Cl.7,DB名) E04D 13/064 E04D 13/068 Continuation of the front page (56) References JP-A-3-217547 (JP, A) JP-A-3-86933 (JP, U) (58) Fields investigated (Int. Cl. 7 , DB name) E04D 13 / 064 E04D 13/068

Claims (4)

(57)【特許請求の範囲】(57) [Claims] 【請求項1】 軒樋本体を軒樋継ぎ手によって接続して
成る軒樋において、前壁部の中程に前上方に開口した長
手方向の凹溝を軒樋本体と軒樋継ぎ手とに連続させて形
成し、軒樋継ぎ手においてのみ凹溝の中程の底部に軒樋
継ぎ手内へ貫通した水抜き孔を穿設して成ることを特徴
とする軒樋。
1. An eaves gutter comprising an eaves gutter body connected by an eaves gutter joint, wherein a longitudinal groove opened upward and forward in the middle of the front wall portion is connected to the eaves gutter body and the eaves gutter joint. An eaves gutter characterized in that a drainage hole penetrating into the eaves gutter joint is formed at the bottom of the middle of the groove only in the eaves gutter joint.
【請求項2】 前壁部を前方へ膨出させて形成したこと
を特徴とする請求項1記載の軒樋。
2. The eaves gutter according to claim 1, wherein the front wall portion is formed by bulging forward.
【請求項3】 凹溝の下側溝縁にせき止め凸部を長手方
向の全長にわたって形成したことを特徴とする請求項1
又は請求項2記載の軒樋。
3. A damming projection formed on the lower groove edge of the concave groove over the entire length in the longitudinal direction.
Or the eaves gutter according to claim 2.
【請求項4】 軒樋継ぎ手のせき止め凸部を外側へ突出
折曲した形状に形成して該せき止め凸部の内側に形成さ
れる凹部に軒樋本体のせき止め凸部を係合させ、軒樋本
体の外側に軒樋継ぎ手を嵌合させて接続したことを特徴
とする請求項3記載の軒樋。
4. The eaves gutter joint has a damming projection formed in a shape protruding outward and bent, and the damming projection of the eaves gutter main body is engaged with a concave portion formed inside the damming projection. The eaves gutter according to claim 3, wherein the eaves gutter joint is fitted and connected to the outside of the main body.
JP13128195A 1995-05-30 1995-05-30 Eaves gutter Expired - Fee Related JP3146926B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP13128195A JP3146926B2 (en) 1995-05-30 1995-05-30 Eaves gutter

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP13128195A JP3146926B2 (en) 1995-05-30 1995-05-30 Eaves gutter

Publications (2)

Publication Number Publication Date
JPH08326239A JPH08326239A (en) 1996-12-10
JP3146926B2 true JP3146926B2 (en) 2001-03-19

Family

ID=15054284

Family Applications (1)

Application Number Title Priority Date Filing Date
JP13128195A Expired - Fee Related JP3146926B2 (en) 1995-05-30 1995-05-30 Eaves gutter

Country Status (1)

Country Link
JP (1) JP3146926B2 (en)

Also Published As

Publication number Publication date
JPH08326239A (en) 1996-12-10

Similar Documents

Publication Publication Date Title
JP3146926B2 (en) Eaves gutter
JP4314708B2 (en) Roof drainage structure
JP3660786B2 (en) Gutter connection structure
JP3454130B2 (en) Flat roof tile
JPH08326241A (en) Eaves gutter device
JPH032573Y2 (en)
JP3578853B2 (en) Bending joint in eaves gutter
JPH0311282Y2 (en)
JP3216580B2 (en) Eave gutter coupling device
JP2502748B2 (en) Roof board connection structure
JP3342374B2 (en) Eaves gutter and eaves gutter joint
JPS597439Y2 (en) drain
JP2003096992A (en) Eaves gutter joint
JP4540367B2 (en) Eaves water collector
KR950001658Y1 (en) Drainage pipe
JPS6239242Y2 (en)
KR200200817Y1 (en) Gutter for floor drainage
JPS6123547Y2 (en)
JP3753099B2 (en) Eaves connection structure
JP3480191B2 (en) Veranda drainage structure
JP3792373B2 (en) Eaves joint
JPH0573609B2 (en)
JP2003129621A (en) Connection structure of eaves gutter and water collector
JPH09144241A (en) Eaves gutter connection structure
JP3234468B2 (en) Water stop structure at the end of the eaves gutter

Legal Events

Date Code Title Description
A01 Written decision to grant a patent or to grant a registration (utility model)

Free format text: JAPANESE INTERMEDIATE CODE: A01

Effective date: 20001205

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20080112

Year of fee payment: 7

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20090112

Year of fee payment: 8

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20090112

Year of fee payment: 8

S533 Written request for registration of change of name

Free format text: JAPANESE INTERMEDIATE CODE: R313533

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20090112

Year of fee payment: 8

R350 Written notification of registration of transfer

Free format text: JAPANESE INTERMEDIATE CODE: R350

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20100112

Year of fee payment: 9

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20100112

Year of fee payment: 9

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20110112

Year of fee payment: 10

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20120112

Year of fee payment: 11

LAPS Cancellation because of no payment of annual fees