JP3028156B2 - Construction method of railway viaduct - Google Patents

Construction method of railway viaduct

Info

Publication number
JP3028156B2
JP3028156B2 JP4212402A JP21240292A JP3028156B2 JP 3028156 B2 JP3028156 B2 JP 3028156B2 JP 4212402 A JP4212402 A JP 4212402A JP 21240292 A JP21240292 A JP 21240292A JP 3028156 B2 JP3028156 B2 JP 3028156B2
Authority
JP
Japan
Prior art keywords
track
construction method
rail
railway viaduct
piers
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
JP4212402A
Other languages
Japanese (ja)
Other versions
JPH0633405A (en
Inventor
真一 玉井
惇 成行
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Tokyu Construction Co Ltd
Original Assignee
Tokyu Construction Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Tokyu Construction Co Ltd filed Critical Tokyu Construction Co Ltd
Priority to JP4212402A priority Critical patent/JP3028156B2/en
Publication of JPH0633405A publication Critical patent/JPH0633405A/en
Application granted granted Critical
Publication of JP3028156B2 publication Critical patent/JP3028156B2/en
Anticipated expiration legal-status Critical
Expired - Fee Related legal-status Critical Current

Links

Landscapes

  • Railway Tracks (AREA)
  • Machines For Laying And Maintaining Railways (AREA)
  • Bridges Or Land Bridges (AREA)

Description

【発明の詳細な説明】DETAILED DESCRIPTION OF THE INVENTION

【0001】[0001]

【産業上の利用分野】本発明は、鉄道高架橋の施工方法
に関するものである。
BACKGROUND OF THE INVENTION 1. Field of the Invention The present invention relates to a method for constructing a railway viaduct.

【0002】[0002]

【従来の技術】従来の鉄道高架橋の施工方法において
は、橋脚の上部にスラブを施工したらその上に砕石道
床、あるいはスラブ道床を搭載し、道床の上にまくらぎ
を敷設し、その上に軌条を敷設する構造であった。
2. Description of the Related Art In a conventional railway viaduct construction method, when a slab is constructed on an upper part of a pier, a crushed stone slab or a slab slab is mounted thereon, a sleeper is laid on the slab, and rails are laid thereon. Was laid.

【0003】[0003]

【発明が解決しようとする問題点】前記した従来の鉄道
高架橋の施工方法にあっては、次のような問題点があ
る。 <イ>スラブの自重は0.6t/ m2 道床の自重は0.9t/ m
2 程度である。このように死荷重が大きいため、それを
支持する高架橋の各断面が大きくなり不経済である。 <ロ>スラブコンクリートの打設のためにはその下部型
枠を支保工で支持しなければならない。そのために特に
使用中の鉄道の上にさらにスラブを設ける場合には、支
保工の高さだけスラブを高く設置しなければならない。 <ハ>市街地を走行する高架橋では、騒音の発生は周辺
の住民の生活に大きな影響を与える。
Problems to be Solved by the Invention The above-mentioned conventional method of constructing a railway viaduct has the following problems. <B> The weight of the slab is 0.6t / m 2 The weight of the slab is 0.9t / m
About 2 . Since the dead load is large as described above, each section of the viaduct supporting the dead load becomes large, which is uneconomical. <B> In order to cast slab concrete, the lower formwork must be supported by shoring. Therefore, especially when further slabs are provided on the railway in use, the slabs must be installed high by the height of the shoring. <C> In a viaduct that runs in urban areas, noise generation has a great effect on the lives of the residents in the vicinity.

【0004】[0004]

【本発明の目的】本発明は上記のような従来の問題を改
善するためになされたもので、部材数が少なく、短い工
期において経済的に施工することのでき、騒音の周囲へ
の伝播を防ぐことのできる鉄道高架橋の施工方法を提供
することを目的とする。
SUMMARY OF THE INVENTION The present invention has been made to solve the above-mentioned conventional problems, and has a small number of members, can be constructed economically in a short construction period, and can reduce the propagation of noise to the surroundings. An object of the present invention is to provide a construction method of a railway viaduct that can be prevented.

【0005】[0005]

【問題点を解決するための手段】すなわち本発明は、
梁に軌条又は軌框が取り付けられるプレストレスを導入
した鉄道高架橋の施工方法において、軌道の両側に橋脚
垂直に立設し、軌道の両側の橋脚間に、軌道を横断す
る方向に横断梁を固定し、縦梁の上面を横断梁の上面と
同一の高さに合わせ、軌道と平行方向に固定し、音を遮
断、吸収する材料を縦梁及び横断梁周囲を含めた橋脚間
に配置し、下方の空間への音の伝播を阻止することを特
徴とする、鉄道高架橋の施工方法である。
[Means for Solving the Problems] That is, the present invention relates to a vertical
Introduces prestress, which allows rails or rail frames to be attached to beams
In the construction method of the railway viaduct , the piers are erected vertically on both sides of the track, the cross beam is fixed between the piers on both sides of the track in the direction crossing the track, and the upper surface of the vertical beam is connected to the upper surface of the cross beam.
At the same height , fix it parallel to the track to block sound.
Between bridge piers, including around vertical beams and cross beams
To prevent sound from propagating into the space below.
This is the construction method of the railway viaduct.

【0006】[0006]

【本発明の構成】以下図面を参照しながら本発明鉄道高
架橋の施工方法について説明する。 <イ>使用する部材 本発明の施工方法に使用する部材は、すべて工場で製造
したプレキャスト部材で構成する。したがって良好な品
質管理の下に製造された部材を使用することができる。
さらに各コンクリート部材はプレストレスを導入したも
のを使用する。したがって、小さい断面で軽量でありな
がら十分な強度を期待できる。本発明の方法に使用する
主要な部材とは、橋脚、横断粱、縦粱である。
DESCRIPTION OF THE PREFERRED EMBODIMENTS The construction method of the railway viaduct of the present invention will be described below with reference to the drawings. <A> Member used The members used in the construction method of the present invention are all precast members manufactured at the factory. Therefore, components manufactured under good quality control can be used.
Furthermore, each concrete member uses a prestressed one. Therefore, sufficient strength can be expected while being lightweight with a small cross section. The main members used in the method of the present invention are piers, cross beams, and vertical beams.

【0007】<ロ>縦粱 鉄道の軌道と平行方向に設置する粱を縦粱1と称する。
本発明の施工方法においては、特にこの縦粱1に軌条ま
たは軌框を一体に取り付けた構造のものを使用する。す
なわち軌条などを工場で一体に取り付けた、軌条付きプ
レストレス粱を使用することを特徴とする。軌条などが
縦粱1と一体化しているから、縦粱1の運搬、架設作業
によって、軌条を同時に運搬、架設されることになる。
さらに軌条などと縦粱1が一体化しているから、道床な
どを別に施工する必要がなく、縦粱1の架設の完了と同
時に、軌条の敷設も完了することになる。
<B> Longitudinal beam A beam installed in a direction parallel to the railroad track is referred to as a longitudinal beam 1.
In the construction method of the present invention, in particular, a structure in which a rail or a rail frame is integrally attached to the vertical beam 1 is used. That is, it is characterized by using a prestressed sir with a rail in which a rail or the like is integrally attached at a factory. Since the rail or the like is integrated with the vertical beam 1, the rail is simultaneously transported and erected by the transport and installation work of the vertical beam 1.
Furthermore, since the rail and the like are integrated with the vertical beam 1, it is not necessary to separately construct a track bed and the like, and the laying of the rail is completed at the same time when the installation of the vertical beam 1 is completed.

【0008】[0008]

【施工方法】次に本発明の施工方法について説明する。 <イ>橋脚の立設 現在使用中の軌道の両側の地中には基礎を設置し、その
基礎の上には橋脚2を立設する。この橋脚2も工場生産
したプレストレスの部材であり、したがって現場でコン
クリートを打設して構築する方法に比較して施工はきわ
めて迅速である。
[Construction method] Next, the construction method of the present invention will be described. <A> Erecting a pier A foundation will be installed in the ground on both sides of the track currently in use, and a pier 2 will be erected on the foundation. The pier 2 is also a pre-stressed member manufactured at the factory, and therefore, the construction is extremely quick as compared with the method of casting and constructing concrete on site.

【0009】<ロ>横断粱の架設 軌道の両側に立設した橋脚2の上部を連結する状態で、
横断粱3を架設する。この横断粱3は当然、橋脚2の上
端と一体に固定しなければならない。そのためには図2
に示すように交差する鉄筋を場所打ちコンクリートで固
定したり、横断粱3と橋脚2とを貫通したPC鋼材を橋
脚2の外側から緊張したり、橋脚2の上部に横断粱3を
搭載して橋脚2の上端から露出させたPC鋼材で横断粱
3を緊張したり、その他各種の固定方法を採用すること
ができる。
<B> Construction of crossing beam In a state where the upper parts of the piers 2 erected on both sides of the track are connected,
A traverse beam 3 is erected. Naturally, the cross beam 3 must be fixed integrally with the upper end of the pier 2. Figure 2
As shown in the above, the intersecting steel bars are fixed with cast-in-place concrete, the PC steel material penetrating the cross beam 3 and the pier 2 is tensioned from the outside of the pier 2, or the cross beam 3 is mounted on the upper portion of the pier 2. The transverse beam 3 can be tensioned with a PC steel material exposed from the upper end of the pier 2, and other various fixing methods can be adopted.

【0010】<ハ>縦粱1の架設 こうして橋脚2の上端に固定した横断粱3の上部に、縦
粱1を架設して固定する。縦粱1には前記したように直
接、軌条または軌框を固定してある。したがって横断粱
3の上部に縦粱1を架設することによって、軌条の敷設
までが一体で完了する。その後に横断粱3と縦粱1とは
一体に強固に固定する。架設に際して、1本の縦粱1に
1本の軌条を固定してあるから、2本の縦粱1を横断粱
3上に平行に架設することによって1組の軌道が完成す
る。
<C> Installation of the vertical beam 1 On the upper portion of the cross beam 3 fixed to the upper end of the pier 2, the vertical beam 1 is installed and fixed. The rails or rail frames are directly fixed to the longitudinal beams 1 as described above. Therefore, by laying the vertical beam 1 on the upper portion of the cross beam 3, the process of laying the rail is completed integrally. After that, the crossbeam 3 and the vertical beam 1 are fixed firmly together. At the time of erection, one rail is fixed to one longitudinal beam 1. Since two longitudinal beams 1 are laid in parallel on the transverse beam 3, one set of tracks is completed.

【0011】<ニ>音の伝播の阻止 架設の終了した縦粱1の下面と周囲を遮音材4によって
包囲する。そのために例えば縦粱1の下面に遮音材4を
張り付ける。さらに縦粱1と縦粱1との間、縦粱1と遮
音材4との間には発泡材などの吸音材5を充填する。以
上のような構成を採用すると縦粱1の上部を走行する車
両の発生する音は、吸音材5に吸収され、さらに周囲の
遮音材4によって反射して周囲への伝播を阻止すること
ができる。
<D> Prevention of sound propagation The lower surface and the periphery of the erected beam 1 are surrounded by a sound insulating material 4. For this purpose, for example, a sound insulating material 4 is attached to the lower surface of the longitudinal beam 1. Further, a sound absorbing material 5 such as a foam material is filled between the vertical beam 1 and the vertical beam 1 and between the vertical beam 1 and the sound insulating material 4. When the above configuration is adopted, the sound generated by the vehicle traveling above the vertical beam 1 is absorbed by the sound absorbing material 5 and further reflected by the surrounding sound insulating material 4 to prevent the sound from propagating to the surroundings. .

【0012】[0012]

【発明の効果】本発明の鉄道高架橋の施工方法は以上説
明したようになるから次のような効果を得ることができ
る。 <イ>縦粱1と軌条とがすでに一体となったものを使用
する。そのためにスラブの施工が不要であり、さらにス
ラブの上に搭載する多量の道床が不要となる。したがっ
て死荷重を大幅に減少することができ、その結果、地震
時の水平慣性力が小さくなるために、橋脚2断面、基礎
構造その他の構造、断面を小さくすることができ、きわ
めて経済的である。 <ロ>工場で製造した部材を使用して組み立てる方法で
ある。したがって現場で型枠を組んでコンクリートを打
設する方法に比較して部品、部材点数が少なく、工期を
大幅に短縮することができる。 <ハ>現場打ちのスラブを使用せず、軌条と固定した粱
を使用するから、スラブ型枠などを支持する支保工が不
要である。したがって使用中の鉄道の上部に施工する場
合にも支保工や型枠の高さだけ低くすることができ、経
済的な施工が可能である。 <ニ>縦粱1は独立して横断粱3との間を連結してい
る。そのために車両走行の騒音が、縦粱1間から周囲に
広く伝播してしまい市街地などでは不都合な場合があ
る。そのために本発明の方法では、縦粱1の周囲を音を
遮断する材料で包囲したものである。したがって高架橋
の周囲に車両走行の騒音が伝播しがたく、広い範囲で利
用できるものである。
As described above, the method for constructing a railway viaduct of the present invention has the following advantages. <B> Use the one in which the longitudinal beam 1 and the rail are already integrated. Therefore, construction of the slab is not required, and a large amount of roadbed mounted on the slab is not required. Therefore, the dead load can be greatly reduced, and as a result, the horizontal inertia force at the time of the earthquake is reduced, so that the cross section of the pier 2, the foundation structure and other structures, the cross section can be reduced, and it is extremely economical. . <B> This is a method of assembling using members manufactured at the factory. Therefore, the number of parts and members is smaller than that of a method in which concrete is cast by assembling a formwork on site, and the construction period can be greatly reduced. <C> Since a beam and a fixed beam are used without using a cast-in-place slab, there is no need to support a slab formwork or the like. Therefore, even when the construction is performed on the upper part of the railway in use, the height can be reduced by the height of the support and the formwork, and economic construction is possible. <D> The vertical beam 1 is independently connected to the cross beam 3. Therefore, the noise of the vehicle travels widely from the space between the vertical beams 1 to the surroundings, which may be inconvenient in an urban area or the like. Therefore, in the method of the present invention, the periphery of the longitudinal beam 1 is surrounded by a material that blocks sound. Therefore, the noise of the vehicle running hardly propagates around the viaduct and can be used in a wide range.

【図面の簡単な説明】[Brief description of the drawings]

【図1】本発明の鉄道高架橋の施工方法の例の説明図FIG. 1 is an explanatory view of an example of a construction method of a railway viaduct of the present invention.

【図2】完成状態の説明図FIG. 2 is an explanatory view of a completed state.

フロントページの続き (58)調査した分野(Int.Cl.7,DB名) E01B 37/00 E01B 19/00 Continuation of front page (58) Field surveyed (Int.Cl. 7 , DB name) E01B 37/00 E01B 19/00

Claims (1)

(57)【特許請求の範囲】(57) [Claims] 【請求項1】縦梁に軌条又は軌框が取り付けられるプレ
ストレスを導入した鉄道高架橋の施工方法において、 軌道の両側に橋脚を垂直に立設し、 軌道の両側の橋脚間に、軌道を横断する方向に横断梁を
固定し、縦梁の上面を横断梁の上面と同一の高さに合わせ、 軌道
と平行方向に固定し、音を遮断、吸収する材料を縦梁及び横断梁周囲を含めた
橋脚間に配置し、下方の空間への音の伝播を阻止するこ
とを特徴とする 、 鉄道高架橋の施工方法。
1. A press in which a rail or a rail frame is attached to a vertical beam.
In the construction method of the railway viaduct that introduced stress , piers were erected vertically on both sides of the track, the cross beam was fixed between the piers on both sides of the track in the direction crossing the track, and the top of the vertical beam was crossed. To the same height as the upper surface , fixed in the direction parallel to the track, and cut off and absorb the sound, including the material around the vertical and transverse beams.
Arrange between piers to prevent sound from propagating into the space below.
A method for constructing a railway viaduct.
JP4212402A 1992-07-17 1992-07-17 Construction method of railway viaduct Expired - Fee Related JP3028156B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP4212402A JP3028156B2 (en) 1992-07-17 1992-07-17 Construction method of railway viaduct

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP4212402A JP3028156B2 (en) 1992-07-17 1992-07-17 Construction method of railway viaduct

Publications (2)

Publication Number Publication Date
JPH0633405A JPH0633405A (en) 1994-02-08
JP3028156B2 true JP3028156B2 (en) 2000-04-04

Family

ID=16621996

Family Applications (1)

Application Number Title Priority Date Filing Date
JP4212402A Expired - Fee Related JP3028156B2 (en) 1992-07-17 1992-07-17 Construction method of railway viaduct

Country Status (1)

Country Link
JP (1) JP3028156B2 (en)

Families Citing this family (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN105755957B (en) * 2016-03-01 2018-03-09 共享钢构有限责任公司 A kind of across rail overpass fast hoisting method of large span
CN106592438B (en) * 2016-12-27 2018-03-30 中铁六局集团有限公司 Twin shaft pier and middle binder truss move integrally construction method
JP6975104B2 (en) * 2018-07-18 2021-12-01 公益財団法人鉄道総合技術研究所 Bridge noise reduction device
JP6975299B2 (en) * 2018-07-18 2021-12-01 公益財団法人鉄道総合技術研究所 Viaduct and noise reduction equipment

Also Published As

Publication number Publication date
JPH0633405A (en) 1994-02-08

Similar Documents

Publication Publication Date Title
CN102653931B (en) Elastic supporting vibration isolation member ballast bed
JP2020528503A (en) System and method for construction of composite U-shaped reinforced girder bridge deck
KR100603901B1 (en) Girder bridge construction make use of a part existing girder and that execution method
KR101127130B1 (en) A precast type pre-stress box girder bridge excution method
JP4540632B2 (en) Erection girder
JP3028156B2 (en) Construction method of railway viaduct
US5163614A (en) Railway roadbeds with rail slabs, and method for preparing
JP3028157B2 (en) Railroad viaduct structure
CN208328660U (en) The U-shaped girder construction of the Two bors d&#39;s oeuveres of combined bridge
JP4162291B2 (en) Railway work girder cradle and rail work girder cradle construction method
JP4685341B2 (en) Viaduct construction method
JP3087093B2 (en) The structure of the vertical bridge in the railway viaduct
JP3028155B2 (en) Construction method of railway viaduct
JP3028159B2 (en) Construction method of railway viaduct
JP3460572B2 (en) Substructure of road viaduct
JP3788774B2 (en) Railroad track structure and railroad track construction method
JP4080652B2 (en) Railway viaduct girder
JP3307867B2 (en) Track support girder elevated track structure
CN220685751U (en) Prefabricated integral bridge deck railway simply supported T beam structure with sound barrier
JP2000104220A (en) Erection of combined truss bridge
KR102670768B1 (en) Steel composite ramen bridge reinforced with section steel supports and crossing rebars and its construction method
JP2536376B2 (en) Foundation structure of shed for road protection
JP3881342B2 (en) Bubble mortar embankment structure
CA3121143C (en) System for construction of double u and single u steel concrete composite structure for bridges.
JP7438441B1 (en) How to update bridges

Legal Events

Date Code Title Description
R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20090204

Year of fee payment: 9

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20100204

Year of fee payment: 10

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20110204

Year of fee payment: 11

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20110204

Year of fee payment: 11

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20120204

Year of fee payment: 12

LAPS Cancellation because of no payment of annual fees