JP3006389B2 - Centralized monitoring and control device - Google Patents
Centralized monitoring and control deviceInfo
- Publication number
- JP3006389B2 JP3006389B2 JP6000067A JP6794A JP3006389B2 JP 3006389 B2 JP3006389 B2 JP 3006389B2 JP 6000067 A JP6000067 A JP 6000067A JP 6794 A JP6794 A JP 6794A JP 3006389 B2 JP3006389 B2 JP 3006389B2
- Authority
- JP
- Japan
- Prior art keywords
- monitoring
- control device
- power supply
- turned
- business
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired - Fee Related
Links
Landscapes
- Debugging And Monitoring (AREA)
Description
【0001】[0001]
【産業上の利用分野】本発明は、分散配置された自動機
等を監視センタで集中監視する集中監視制御装置の改良
に関する。BACKGROUND OF THE INVENTION 1. Field of the Invention The present invention relates to an improvement in a centralized monitoring and control device for centrally monitoring a distributed automatic machine at a monitoring center.
【0002】近年、入金,出金等の取引を行う自動取引
装置(以下自動機と称する)の普及に伴い、営業時間を
延長して無人で現金の取扱を行う金融機関が増大してき
た。しかし、時間を延長しても、営業時間の終了間際に
は、通常よりも利用者が増え、慌てて取引を行うため取
引上のトラブルが発生しやすくなっている。In recent years, with the spread of automatic transaction apparatuses (hereinafter, referred to as automatic machines) for performing transactions such as deposits and withdrawals, financial institutions that extend business hours and handle cash unattended have increased. However, even if the hours are extended, the number of users is increased more than usual just before the end of business hours, and transactions are performed in a hurry, so that transaction troubles are likely to occur.
【0003】一方、これらの自動機は、回線を通じて監
視センタで集中監視されており、前述の終了間際におけ
る現状から、自動機の営業時間終了時点での監視強化が
必要とされる。On the other hand, these automatic machines are centrally monitored by a monitoring center via a line, and it is necessary to strengthen monitoring at the end of business hours of the automatic machines from the current situation immediately before the end.
【0004】[0004]
【従来の技術】図8は従来例の集中監視制御装置構成図
である。各営業店に設置されている自動機9は、図8に
示すように、ISDN網 10 などの交換網を通じて、監
視センタに設けられた集中監視制御装置1により監視制
御されている。2. Description of the Related Art FIG. 8 is a block diagram of a conventional centralized monitoring and control device. As shown in FIG. 8, the automatic machines 9 installed in each sales office are monitored and controlled by a centralized monitoring and control device 1 provided in a monitoring center through an exchange network such as an ISDN network 10.
【0005】この監視センタに設置されている集中監視
制御装置1は、監視画面を表示したり、各自動機9に指
令を与える複数のワークステーションWS2と、各WS
2を制御し、且つ営業店側装置7との間で通信を行うシ
ステムコントローラSC3から構成されており、端末ア
ダプタTA4,図示省略した網終端装置により、ISD
N網 10 に接続されている。[0005] The centralized monitoring and control device 1 installed in the monitoring center includes a plurality of workstations WS2 for displaying a monitoring screen and giving commands to the automatic machines 9;
2 and a system controller SC3 that communicates with the branch office device 7. The terminal controller TA4, a network termination device (not shown)
It is connected to the N network 10.
【0006】また、各営業店の自動機9は、端末アダプ
タTA8(以下、自動機9とTA8等を営業店側装置7
と総称する)、図示省略した網終端装置を介してISD
N網10 に接続されている。[0006] The automatic machine 9 of each business office is connected to a terminal adapter TA8 (hereinafter, the automatic machines 9 and TA8 and the like are connected to the business office side device 7).
, ISD via a network termination device not shown.
It is connected to the N network 10.
【0007】このような監視システムにおいて、業務開
始時に、監視センタでは、SC3の電源5,TA4の電
源6,およびWS2の電源がそれぞれ監視員によって投
入され、営業店では、TA8および自動機9の電源が営
業店の係員によって投入されて、営業が開始される。In such a monitoring system, at the start of business, the monitoring center turns on the power supply of SC3 5, the power supply 6 of TA4, and the power supply of WS2 at the monitoring center. The power is turned on by a staff member of the sales office, and business is started.
【0008】ここで、監視センタ側の電源が投入される
と、TA4は各営業店に対して一斉発呼し、営業店側装
置7の電源が投入されていれば回線接続が行われる。以
後、自動機9が正常か否かの問い合わせ等が行われてそ
の結果がWS2の監視画面に表示される。Here, when the power supply of the monitoring center is turned on, the TA 4 calls all the business offices at once, and if the power supply of the business office equipment 7 is turned on, the line connection is made. Thereafter, an inquiry is made as to whether or not the automatic machine 9 is normal, and the result is displayed on the monitoring screen of the WS 2.
【0009】ここで、自動機9に障害が発生すると、T
A8は集中監視制御装置1に障害状況を通知し、その内
容がWS2に表示される。この障害状態は保守員に通報
され、処置される。Here, if a failure occurs in the automatic machine 9, T
A8 notifies the centralized supervisory control device 1 of the failure status, and the content is displayed on the WS2. This fault condition is reported to a maintenance person and taken care of.
【0010】なお、前述の一斉発呼時に営業店側装置7
の電源が投入されていない場合は、営業店側装置7の電
源が投入された時点で、営業店側から発呼して回線接続
が行われる。つまり、電源投入時に、双方から回線接続
が行われる。[0010] At the time of the above-mentioned simultaneous call, the branch office device 7
Is not turned on, a call is made from the office side to establish a line connection when the office apparatus 7 is turned on. In other words, when the power is turned on, the lines are connected from both sides.
【0011】業務終了時には、監視センタでは、切断順
序は任意ではあるが、係員が、WS2の電源を切断し、
SC3の電源5を切断し、TA4の電源6を切断して監
視業務を終了する。[0011] At the end of the work, at the monitoring center, the disconnection order is arbitrary, but a staff member turns off the power supply of WS2,
The power supply 5 of the SC 3 is turned off, and the power supply 6 of the TA 4 is turned off to end the monitoring operation.
【0012】また、営業店側では、営業終了時間にな
り、且つ顧客が操作中でなければ、TA8の電源、自動
機9の電源をそれぞれ切断する。On the business side, when the business close time is reached and the customer is not operating, the power supply of the TA 8 and the power supply of the automatic machine 9 are turned off.
【0013】[0013]
【発明が解決しようとする課題】監視業務を終了する場
合、係員が監視センタ内の各装置の電源を切断するが、
TA4の電源が切断されるまでは回線は接続状態であ
り、自動機9に異常が発生した場合は、異常通知が送信
されてくる。このとき、WS2,SC3の電源が切断さ
れているとこの通知は受付けられず、監視目的が達成さ
れないとか、回線費用が無駄になるといった課題とな
る。When ending the monitoring work, a staff member turns off the power of each device in the monitoring center.
The line is in a connected state until the power of the TA4 is turned off, and when an abnormality occurs in the automatic machine 9, an abnormality notification is transmitted. At this time, if the power of the WS2 and the SC3 is turned off, this notification is not accepted, and the problem is that the monitoring purpose is not achieved or the line cost is wasted.
【0014】また、TA4の電源が切断されると回線切
断状態となり、営業店側装置7の電源が切断されていな
いと、営業店側装置7から回線接続が試みられ、回線接
続のための発呼が集中してISDN網 10 が輻輳する原
因となる。When the power supply of the TA 4 is cut off, the line is cut off. If the power supply of the branch office side device 7 is not cut off, a line connection is attempted from the branch office side device 7 and a call for line connection is made. Calls are concentrated and the ISDN network 10 becomes congested.
【0015】さらに、集中監視制御装置1の電源が切断
された時点において、駆け込みの顧客により自動機9が
使用されている場合があり、且つ顧客操作にトラブルが
発生した場合、障害電話(自動機9に併設されている電
話と監視センタとの間の電話で、係員はWS2の監視画
面を見ながら顧客に対応する。)等による問い合わせに
対処することができず、サービスが低下する。Further, when the central monitoring and control device 1 is turned off, the automatic machine 9 may be used by a rush customer, and if a trouble occurs in the customer operation, a trouble telephone (automatic machine) 9 cannot respond to inquiries by the telephone between the telephone attached to the monitoring center and the monitoring center while looking at the monitoring screen of the WS2), and the service is deteriorated.
【0016】本発明は、上記課題に鑑み、業務終了時点
での被監視装置の状態に基づいて適切な終了処理を行う
集中監視制御装置を提供することを目的とする。The present invention has been made in view of the above problems, and has as its object to provide a centralized supervisory control device that performs appropriate termination processing based on the state of a monitored device at the end of a job.
【0017】[0017]
【課題を解決するための手段】上記課題を解決するた
め、本発明の集中監視制御装置は、図1の本発明の原理
図に示すように、被監視装置32を監視制御する集中監視
制御装置であって、業務終了操作が行われたとき、被監
視装置32の使用状況を検索する使用状況検索部30と、前
記検索の結果、該被監視装置32が使用状態のときは監視
業務を継続させ、不使用状態のときは該被監視装置32に
発呼不要を通知した後自装置の電源33を切断する業務終
了処理部31とを備えるように構成する。In order to solve the above-mentioned problems, a centralized monitoring and control device according to the present invention comprises a centralized monitoring and control device for monitoring and controlling a monitored device 32 as shown in the principle diagram of the present invention in FIG. And a usage status search unit 30 for searching the usage status of the monitored device 32 when the operation of ending the operation is performed, and continuing the monitoring operation when the monitored device 32 is in the usage status as a result of the search. To the monitored device 32 when not in use.
The system is configured to include a business end processing unit 31 that turns off the power supply 33 of the own device after notifying that the call is unnecessary .
【0018】[0018]
【0019】[0019]
【作用】集中監視制御装置において業務終了操作が成さ
れたとき、使用状況検索部30は、被監視装置32が使用状
態か不使用状態かを検索し、使用状態のときは監視業務
を継続させ、不使用状態のときは、自装置の電源33を切
断する。When the service termination operation is performed in the centralized monitoring and control device, the use state search unit 30 searches whether the monitored device 32 is in the use state or the non-use state, and when it is in the use state, the monitoring operation is continued. When not in use, the power supply 33 of the own device is turned off.
【0020】以上の処置により、業務終了後も被監視装
置が使用状態であれば監視を継続させることができ、被
監視装置のトラブルに対処できる。また、被監視装置32
が不使用状態で電源33を切断する場合、被監視装置32に
発呼不要通知を行うことにより、電源33が切断された後
に、被監視装置32からの無駄な発呼、および異常通知が
防止できる。With the above measures, if the monitored device is in use even after the work is completed, the monitoring can be continued, and the trouble of the monitored device can be dealt with. The monitored device 32
When the power supply 33 is turned off when the power supply 33 is not in use, the unnecessary notification of the call to the monitored device 32 is performed, thereby preventing unnecessary calls from the monitored device 32 and abnormal notification after the power supply 33 is turned off. it can.
【0021】[0021]
【実施例】図2は一実施例の構成図、図3は業務終了時
の処理フローチャート図、図4は監視画面例(その1)
を表す図、図5は監視画面例(その2)を表す図、図6
は監視画面例(その3)を表す図、図7は監視画面例
(その4)を表す図である。FIG. 2 is a block diagram of one embodiment, FIG. 3 is a processing flowchart at the end of a job, and FIG. 4 is an example of a monitoring screen (part 1).
FIG. 5 is a diagram showing an example of a monitoring screen (No. 2), and FIG.
FIG. 7 is a diagram illustrating an example of a monitoring screen (No. 3), and FIG. 7 is a diagram illustrating an example of a monitoring screen (No. 4).
【0022】図2の集中監視制御装置1において、2は
複数のワークステーションWSで、例えば地域別に区分
した複数の営業店装置7の監視画面をそれぞれ表示し、
且つ制御指令が入力される。なお、WS2の電源は、こ
こではSC 20 からの電源切断指令で切断されるものと
する。In the centralized monitoring and control apparatus 1 shown in FIG. 2, reference numeral 2 denotes a plurality of workstations WS, for example, each displaying a monitoring screen of a plurality of branch office apparatuses 7 divided by region,
In addition, a control command is input. It is assumed that the power of WS2 is turned off by a power-off command from SC20.
【0023】20はシステムコントローラSCで、複数の
WS2を制御し、各WS2において入力された制御指令
を指定された営業店側装置7に通知し、また営業店側装
置7からの状態通知を対応するWS2に表示させる等の
監視制御を行う。Reference numeral 20 denotes a system controller SC for controlling a plurality of WSs 2, notifying control instructions inputted in each WS 2 to a designated office apparatus 7, and corresponding to a state notification from the office apparatus 7. The monitoring control is performed such as displaying the information on the WS2.
【0024】ここで、21は使用状況検索部21で、複数の
WS2のうちのいずれかのWS2から業務終了入力が通
知されたとき、すべての営業店側装置7に対して、使用
状況要求電文を送信し、その応答電文を受け取って業務
終了処理部22に渡す。22は業務終了処理部で、この応答
電文を受取り、そき内容を分析して、後述する終了処理
を行う。5は切断対象の電源である。Here, reference numeral 21 denotes a use state search unit 21 which sends a use state request message to all the branch office apparatuses 7 when a work end input is notified from any one of the plurality of WSs 2. Is transmitted, and the response message is received and passed to the business end processing unit 22. Reference numeral 22 denotes an operation termination processing unit which receives the response message, analyzes the contents of the response message, and performs termination processing described later. Reference numeral 5 denotes a power source to be disconnected.
【0025】4は回線制御を行う端末アダプタTAで、
業務開始時の電源投入時に営業店側装置7に一斉発呼し
て回線接続を行うとともに、図示省略した網終端装置と
の間でデータのやりとりを行い、ISDN網 10 を介
し、営業店側装置7との間で通信を行う。6はTA4の
電源で、SC 20 の電源5とは別系統で切断される。こ
の切断により、ISDN網 10 はSC 20 とすべての営
業店側装置7との間の回線接続を切断する。Reference numeral 4 denotes a terminal adapter TA for performing line control.
When the power is turned on at the start of the business, the call is simultaneously sent to the branch office device 7 to make a line connection, and data is exchanged with a network terminating device (not shown) via the ISDN network 10. 7 is communicated. Reference numeral 6 denotes a power supply of TA4, which is cut off in a different system from the power supply 5 of SC20. With this disconnection, the ISDN network 10 disconnects the line connection between the SC 20 and all the branch office devices 7.
【0026】また、営業店側装置7において、9は自動
機で、図示省略したが障害電話が併設されている。この
障害電話はフックオフされたとき、監視センタに通知さ
れ、係員がWS2の画面上に表示された監視センタ側電
話番号を指定することにより、その障害電話と監視セン
タの電話とが接続される。In the branch office apparatus 7, reference numeral 9 denotes an automatic machine, which is provided with a trouble telephone (not shown). When the troubled telephone is hooked off, it is notified to the monitoring center, and the clerk specifies the monitoring center side telephone number displayed on the screen of WS2, so that the troubled telephone and the telephone of the monitoring center are connected.
【0027】8は端末アダプタで、その営業店に設置さ
れている自動機9を制御するとともに、ISDN網 10
を介して、集中監視制御装置1との間でISDN網 10
を介して通信を行う。Reference numeral 8 denotes a terminal adapter for controlling the automatic machine 9 installed in the branch office and for controlling the ISDN network.
Through the ISDN network with the centralized monitoring and control device 1
Communication via.
【0028】その他、図8と同一符号は同一対象物を表
す。なお、自動機9,TA8等の営業店側装置7の電源
は、本実施例では、営業店の係員によって切断されるも
のとし、電源投入時に集中監視制御装置1および営業店
側装置7の双方から発呼して回線接続動作が行われるも
のとし、また、回線が無断で切断された場合は、再発呼
するものとする。The same reference numerals as those in FIG. 8 denote the same objects. In this embodiment, it is assumed that the power supply of the office equipment 7 such as the automatic machine 9 and the TA8 is cut off by a staff member of the office. , And the line connection operation is performed. If the line is disconnected without permission, the call is re-issued.
【0029】図4は、全自動機の監視画面を示したもの
で、自動機9の識別番号ID対応で、設置支店名、状態
(○は正常)が表示されている。この監視画面上に表示
されている項目に対応するキー(例えば、障害状況を表
示させる場合はキーH)を押下するか、その表示位置に
マウス2aでクリック(矢印を合わせる)することによ
り、その項目に対応する監視画面に切り替わるか、また
は指令が入力される) 以上の構成の監視システムにより、次のような業務終了
処理が行われる。図3〜図7参照 (1) 業務終了時、監視員はWS2の監視画面上で業務
終了を選択し、確認を選択する。FIG. 4 shows a monitoring screen of the fully automatic machine, in which the name of the installed branch and the state (circle is normal) are displayed corresponding to the identification number ID of the automatic machine 9. By pressing a key corresponding to the item displayed on the monitoring screen (for example, key H for displaying a failure status) or clicking (adjusting an arrow) to the displayed position with the mouse 2a, (The screen is switched to the monitoring screen corresponding to the item, or a command is input.) The following business termination processing is performed by the monitoring system configured as described above. See FIG. 3 to FIG. 7 (1) At the end of the work, the monitor selects the work end on the monitoring screen of WS2, and selects the confirmation.
【0030】例えば、図4の監視画面の場合、「O/そ
の他」をマウス2aでクリックする(またはキーOを押下
する、以下同様) と、図5に示すように、「その他のキ
ー」23が、表示されるから、このうちよりG/業務終了
をクリックする。これにより、図6に示したようなメッ
セージがメッセージボックス24に表示されるから、この
メッセージボックス24内の「確認」25をマウス2aでクリ
ックする。なお、「取消」26は業務終了操作の取消しで
ある。 (2) これにより業務終了操作入力がSC 20 に通知さ
れ、SC20の使用状況検索部22は、回線接続されている
すべての営業店装置7に対して使用状況要求電文を送信
する。 (3) この電文を受け取った営業店側装置7の端末アダ
プタTA8は、各自動機9の使用状況を検索し、 (4) 自動機9の使用状況をSC20に応答する。 (5) この応答電文により、業務終了処理部23は、全営業
店の自動機9について使用中のものがあるか否かを判別
し、 (6) 1台もなければ、すべての営業店側装置7に対して
発呼不要電文を送信した後、WS2に電源切断指令を送
出し、電源5を切断する。 (7) 1台でも使用中の自動機9があれば、業務終了操作
を行ったWS2の監視画面上にメッセージボックス27
(図7)を表示し、監視業務継続の確認入力を要求す
る。 (8) ここで、「確認」28が指示されると、監視業務を
継続し、 (9) 「取消」29が指示されると、電源5, WS2の電源
を強制切断する。この切断時にも発呼不要電文を送信す
る。なお、この「取消」29による強制切断は、図5の
「その他のキー」23のうちの「X/終了」と同様に、何
らかの理由で営業店側装置7の状態如何に係わらず切断
できるようにしたものである。For example, in the case of the monitoring screen of FIG. 4, if "O / other" is clicked with the mouse 2a (or the key O is pressed, the same applies hereinafter), the "other key" 23 is displayed as shown in FIG. Is displayed, G / End of business is clicked. As a result, a message as shown in FIG. 6 is displayed in the message box 24, and the "confirmation" 25 in the message box 24 is clicked with the mouse 2a. Note that "cancel" 26 is a cancellation of the operation end operation. (2) As a result, the business end operation input is notified to the SC 20, and the use state search unit 22 of the SC 20 transmits a use state request message to all the branch office apparatuses 7 connected to the line. (3) The terminal adapter TA8 of the branch office apparatus 7 that has received the message searches for the use status of each automatic machine 9, and (4) responds the use status of the automatic machine 9 to the SC20. (5) Based on this response message, the business end processing unit 23 determines whether or not the automatic machines 9 of all the branch offices are in use. (6) If there is no machine, all the branch offices After transmitting the call-unnecessary message to the device 7, a power-off command is sent to the WS 2 to turn off the power source 5. (7) If there is at least one automatic machine 9 in use, a message box 27 is displayed on the monitoring screen of the WS 2 where the operation end operation was performed.
(FIG. 7) is displayed, and a confirmation input for monitoring business continuation is requested. (8) Here, when "Confirm" 28 is instructed, the monitoring operation is continued, and (9) When "Cancel" 29 is instructed, the power of the power supply 5 and WS2 is forcibly turned off. Even at the time of this disconnection, a callless message is transmitted. Note that the forced disconnection by the "cancel" 29 can be cut off for any reason regardless of the state of the branch-side device 7 in the same manner as "X / End" of the "other keys" 23 in FIG. It was made.
【0031】一方、SC 20 の電源が切断されたとき、
営業店側装置7は発呼不要電文を受信するから、TA4
の電源6が投入されていて回線接続状態であっても、異
常通知は行わない。また、続いてTA4の電源6が切断
されて回線が切断されても発呼しない。On the other hand, when the power of the SC 20 is turned off,
Since the office device 7 receives the call-free message, TA4
Even if the power supply 6 is turned on and the line is connected, the abnormality notification is not performed. Then, even if the power supply 6 of the TA 4 is cut off and the line is cut off, no call is made.
【0032】以上のごとく、業務終了指示により、自動
機9の使用状態を検索し、使用状態ならば監視を継続
し、不使用状態ならば、発呼不要を通知して電源を切断
するため、業務終了間際の監視が正常に行われ、また、
電源切断による被監視装置からの無駄な発呼、異常通知
を無くすことができる効果を奏する。As described above, the use state of the automatic machine 9 is searched according to the work end instruction, and if it is in use state, the monitoring is continued. Monitoring just before the end of work is performed normally,
This has the effect of eliminating useless calls and abnormal notifications from the monitored device due to power-off.
【0033】[0033]
【発明の効果】以上説明したように、本発明の集中監視
制御装置は、業務終了操作により、被監視装置の使用状
態を検索し、使用状態ならば監視を継続し、不使用状態
ならば、発呼不要を通知して電源を切断するようにした
ため、業務終了間際の監視が正常に行われ、また、集中
監視制御装置の電源切断による被監視装置からの無駄な
発呼、異常通知を無くすことができる効果を奏する。As described above, the centralized monitoring and control device of the present invention searches for the use status of the monitored device by the operation end operation, and if the use status, the monitoring is continued. Since the power is turned off by notifying that no call is required, monitoring immediately before the end of work is performed normally, and unnecessary calls and abnormal notifications from the monitored device due to the power cut off of the centralized monitoring and control device are eliminated. The effect that can be achieved.
【図1】 本発明の原理図FIG. 1 is a principle diagram of the present invention.
【図2】 一実施例の構成図FIG. 2 is a configuration diagram of an embodiment.
【図3】 業務終了時の処理フローチャート図FIG. 3 is a processing flowchart at the end of work.
【図4】 監視画面例(その1)を表す図FIG. 4 is a diagram showing an example of a monitoring screen (1).
【図5】 監視画面例(その2)を表す図FIG. 5 is a diagram showing an example of a monitoring screen (2).
【図6】 監視画面例(その3)を表す図FIG. 6 is a diagram illustrating an example of a monitoring screen (part 3).
【図7】 監視画面例(その4)を表す図FIG. 7 is a diagram illustrating an example of a monitoring screen (part 4).
【図8】 従来例の集中監視制御装置構成図FIG. 8 is a block diagram of a conventional centralized monitoring and control device.
1 集中監視制御装置 2 ワークス
テーションWS 2a マウス 3 システム
コントローラSC 4 端末アダプタTA 5,6 電源 7 営業店側装置 8 端末アダ
プタTA 9 自動機 10 ISDN
網 20 システムコントローラSC 21 使用状況
検索部 22 業務終了処理部 23 その他の
キー 24, 27 メッセージボックス 25, 28 確認 26, 29 取消 30 使用状況
検索部 31 業務終了処理部 32 被監視装
置 33 電源DESCRIPTION OF SYMBOLS 1 Central monitoring and control apparatus 2 Workstation WS 2a Mouse 3 System controller SC 4 Terminal adapter TA 5,6 Power supply 7 Branch office apparatus 8 Terminal adapter TA 9 Automatic machine 10 ISDN
Network 20 System controller SC 21 Usage status search section 22 Business termination processing section 23 Other keys 24, 27 Message box 25, 28 Confirmation 26, 29 Cancel 30 Usage status search section 31 Business termination processing section 32 Monitored device 33 Power supply
───────────────────────────────────────────────────── フロントページの続き (56)参考文献 特開 平5−165552(JP,A) 特開 平5−197453(JP,A) 特開 平6−119532(JP,A) 特開 昭63−68939(JP,A) 特開 平4−323751(JP,A) 特開 平5−28004(JP,A) 実開 昭63−143962(JP,U) (58)調査した分野(Int.Cl.7,DB名) G06F 11/28 ──────────────────────────────────────────────────続 き Continuation of the front page (56) References JP-A-5-165552 (JP, A) JP-A-5-197453 (JP, A) JP-A-6-119532 (JP, A) JP-A-63-1988 68939 (JP, A) JP-A-4-323375 (JP, A) JP-A-5-28004 (JP, A) JP-A-63-143962 (JP, U) (58) Fields investigated (Int. Cl. 7 , DB name) G06F 11/28
Claims (1)
御装置であって、 業務終了指示により該被監視装置の使用状況を検索する
使用状況検索部と、 前記検索結果に基づき、該被監視装置が使用状態のとき
は監視業務を継続させ、不使用状態のときは該被監視装
置に発呼不要を通知した後自装置の電源を切断する業務
終了処理部とを備えることを特徴とする集中監視制御装
置。1. A centralized monitoring and control device for monitoring and controlling a monitored device, comprising: a use status search unit for searching for a usage status of the monitored device in response to an operation end instruction; and a monitoring device based on the search result. There when the use state is continued monitoring operations, 該被monitoring instrumentation when the unused state
A centralized monitoring and control device, comprising: a service termination processing unit for turning off the power of the device after notifying the device that the call is unnecessary .
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP6000067A JP3006389B2 (en) | 1994-01-05 | 1994-01-05 | Centralized monitoring and control device |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP6000067A JP3006389B2 (en) | 1994-01-05 | 1994-01-05 | Centralized monitoring and control device |
Publications (2)
Publication Number | Publication Date |
---|---|
JPH07200359A JPH07200359A (en) | 1995-08-04 |
JP3006389B2 true JP3006389B2 (en) | 2000-02-07 |
Family
ID=11463849
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
JP6000067A Expired - Fee Related JP3006389B2 (en) | 1994-01-05 | 1994-01-05 | Centralized monitoring and control device |
Country Status (1)
Country | Link |
---|---|
JP (1) | JP3006389B2 (en) |
-
1994
- 1994-01-05 JP JP6000067A patent/JP3006389B2/en not_active Expired - Fee Related
Also Published As
Publication number | Publication date |
---|---|
JPH07200359A (en) | 1995-08-04 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
JP3437176B2 (en) | Power management device and power management system | |
JP3006389B2 (en) | Centralized monitoring and control device | |
JPH0530103A (en) | Password setting system by remote control | |
JP3981349B2 (en) | Remote control system | |
JP2009015785A (en) | Automatic machine monitoring system | |
JPS62169266A (en) | Data transmission and reception terminal equipment | |
JP2833969B2 (en) | User fault monitoring control method | |
JPS62197836A (en) | Remote supervisory and controlling equipment | |
JPH11312204A (en) | Automatic machine monitoring device | |
JPH06103194A (en) | Automatic host transmission method for off-line transaction data | |
JPH0495160A (en) | Monitoring system for centralized monitoring and control system | |
JP3716360B2 (en) | Automatic machine monitoring system | |
JP2000029968A (en) | Method for monitoring automatic transaction device and system therefor and recording medium for recording the same method | |
JPH067384B2 (en) | Monitoring method for automated transaction equipment | |
KR20000008416A (en) | Finance network managing method and device | |
JPS636660A (en) | Automatic transaction processing system | |
JPH0795304A (en) | Alarm telephone set | |
JP2001168993A (en) | Call center system | |
JP2000013503A (en) | Exchange operation system | |
JPH09190590A (en) | Remote monitoring device | |
JPH01263768A (en) | Automatic centralized supervisory system | |
JPH11120416A (en) | Customer guide system | |
JP2000115288A (en) | Operation management tool and information processing system | |
JPH0355647A (en) | Computer system | |
JPH0247782B2 (en) |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
A01 | Written decision to grant a patent or to grant a registration (utility model) |
Free format text: JAPANESE INTERMEDIATE CODE: A01 Effective date: 19991026 |
|
LAPS | Cancellation because of no payment of annual fees |