JP2980793B2 - Column / beam joining method - Google Patents

Column / beam joining method

Info

Publication number
JP2980793B2
JP2980793B2 JP5166768A JP16676893A JP2980793B2 JP 2980793 B2 JP2980793 B2 JP 2980793B2 JP 5166768 A JP5166768 A JP 5166768A JP 16676893 A JP16676893 A JP 16676893A JP 2980793 B2 JP2980793 B2 JP 2980793B2
Authority
JP
Japan
Prior art keywords
column
bar
precast
hollow precast
hollow
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
JP5166768A
Other languages
Japanese (ja)
Other versions
JPH0726623A (en
Inventor
和久 末岡
俊久 清水
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Okumuragumi KK
Original Assignee
Okumuragumi KK
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Okumuragumi KK filed Critical Okumuragumi KK
Priority to JP5166768A priority Critical patent/JP2980793B2/en
Publication of JPH0726623A publication Critical patent/JPH0726623A/en
Application granted granted Critical
Publication of JP2980793B2 publication Critical patent/JP2980793B2/en
Anticipated expiration legal-status Critical
Expired - Fee Related legal-status Critical Current

Links

Description

【発明の詳細な説明】DETAILED DESCRIPTION OF THE INVENTION

【0001】[0001]

【産業上の利用分野】この発明は、鉄筋コンクリート製
の柱と梁との接合工法に関する。
BACKGROUND OF THE INVENTION 1. Field of the Invention The present invention relates to a method for joining reinforced concrete columns and beams.

【0002】[0002]

【従来の技術】従来、コンクリート構造物は、現場で構
造物全体を構築する現場打コンクリート打設工法が採ら
れている。しかしながら、この工法は、型枠や鉄筋組立
て作業が繁雑なうえに、作業者の技量によって施工精度
にばらつきが生じやすいという欠点を有する。そこで、
繰り返し作業の多い高層建築物等の場合には、柱,梁お
よびスラブ等の構造部材を工場等の他の場所で分割して
製造し、この製造された各構造部材を現場で接合して組
立てるプレキャスト工法が採られている。
2. Description of the Related Art Conventionally, for a concrete structure, a cast-in-place concrete casting method for constructing the entire structure on site has been adopted. However, this construction method has the drawbacks that the assembling work of the formwork and the reinforcing bar is complicated, and that the construction accuracy tends to vary depending on the skill of the operator. Therefore,
In the case of a high-rise building or the like in which repetitive work is frequently performed, structural members such as columns, beams, and slabs are divided and manufactured in another place such as a factory, and the manufactured structural members are joined and assembled on site. Precast method is adopted.

【0003】上記プレキャスト工法によれば、各構造部
材を予め工場等で製造するので品質の信頼性は高いとい
う利点がある。ところが、各構造部材の重量が大きい場
合には、現場への搬入時や組立て施工時に高能力の揚重
機を使用しなければならなくなる。そこで、各構造部材
の寸法を小さくして重量が軽くなるように考慮する必要
がある。
According to the precast method, since each structural member is manufactured in advance at a factory or the like, there is an advantage that the reliability of quality is high. However, when the weight of each structural member is large, it is necessary to use a high-capacity lifting machine at the time of carrying into the site or at the time of assembling. Therefore, it is necessary to reduce the weight of each structural member so as to reduce the weight.

【0004】ところで、上記プレキャスト工法において
梁と上下階のプレキャスト柱とを接合する際には、プレ
キャスト柱の底部にスリーブを埋設しておき、このスリ
ーブ内に下階のプレキャスト柱の柱主筋を挿入して接合
するのが一般的である。その際に、柱全体をプレキャス
トコンクリートとすると重量が大きくなり、大容量の重
機が必要となる。それを避けるために、柱の外郭に当た
る部分のみをプレキャスト化して中空プレキャスト柱型
枠(以下、単に中空プレキャスト柱と言う)を形成し、現
場で組み立てた後に残りのコンクリートを打設する方法
が取られる。
By the way, in joining the beams and the precast columns on the upper and lower floors in the above precast method, a sleeve is buried at the bottom of the precast column, and the main reinforcement of the lower precast column is inserted into the sleeve. It is common to join them together. At this time, if the entire column is made of precast concrete, the weight increases, and a heavy-capacity heavy machine is required. In order to avoid this, a method of precasting only the portion corresponding to the outer shell of the column to form a hollow precast column formwork (hereinafter simply referred to as a hollow precast column) and assembling it on site and then casting the remaining concrete is adopted. Can be

【0005】その際における上下階のプレキャスト柱の
接合は、次のような2つの重ね継ぎ手によって実施され
る。
[0005] At this time, the joining of the precast columns on the upper and lower floors is performed by the following two lap joints.

【0006】(1) 柱主筋と帯筋を内蔵すると共に、柱
主筋を柱頭から上階のスラブ面以上に突出させた中空プ
レキャスト柱を立設する。そして、この中空プレキャス
ト柱上にプレキャスト梁の端部を載架して柱・梁接合部
(以下、パネルゾーンと言う)に梁下端主筋,柱主筋およ
び梁上端主筋を配筋し、コンクリートを打設して柱・梁
を一体に接合する。次に、上記スラブ面以上に突出した
柱主筋に上階の中空プレキャスト柱が挿入されて重ね継
ぎ手を構成する。
(1) A hollow precast column having a column main bar and a stirrup built therein and having a column main bar protruding from the column capital beyond the slab surface of the upper floor is erected. Then, place the end of the precast beam on this hollow precast column, and
(Hereinafter referred to as the panel zone) The main bar at the bottom of the beam, the main bar at the column and the main bar at the top of the beam are arranged, concrete is cast, and the column and beam are joined together. Next, a hollow precast pillar on the upper floor is inserted into a pillar main bar projecting above the slab surface to form a lap joint.

【0007】(2) 図6に示すように、柱主筋1aと帯
筋2aを内蔵する中空プレキャスト柱A上にプレキャス
ト梁Bを載架する。そして、パネルゾーンを高さ方向に
貫通する長さを有する縦筋1cとその中間部に巻き付け
られた帯筋2cとから成る上下柱接合用の先組鉄筋C
を、その帯筋2cが上記パネルゾーンに位置するように
してその縦筋1cを中空プレキャスト柱Aの中空部に挿
入させて配筋し、コンクリートを打設する。こうして、
柱・梁を一体に接合した後に、スラブ面上に突出した先
組鉄筋Cに上階の中空プレキャスト柱(図示せず)が挿入
されて重ね継ぎ手を形成する。
(2) As shown in FIG. 6, a precast beam B is mounted on a hollow precast column A containing a column main bar 1a and a band bar 2a. Then, a pre-assembled reinforcing bar C for joining the upper and lower columns, which is composed of a vertical bar 1c having a length penetrating the panel zone in the height direction and a band 2c wound around an intermediate portion thereof.
The longitudinal bar 1c is inserted into the hollow part of the hollow precast column A so that the stirrup 2c is positioned in the panel zone, and the reinforcing bars are arranged, and concrete is poured. Thus,
After joining the columns and beams together, a hollow precast column (not shown) on the upper floor is inserted into a pre-assembled reinforcing bar C protruding on the slab surface to form a lap joint.

【0008】[0008]

【発明が解決しようとする課題】しかしながら、上記従
来のプレキャスト工法における重ね継ぎ手には、以下の
ような問題点がある。 (イ) 上記(1)の重ね継ぎ手の場合 下階の中空プレキャスト柱から突出した柱主筋は上
階の中空プレキャスト柱とかち合う。そのために、下階
の中空プレキャスト柱の柱主筋を、上階の中空プレキャ
スト柱の中空部に容易に挿入できるように内側に曲げ加
工する必要がある。 上述のように柱主筋を内側に曲げ加工しているため
に、パネルゾーンの柱帯筋を取り付ける際には取り付け
位置に応じて帯筋の外径を変える必要がある。 柱頭から突出している柱主筋の長さを、上階の中空
プレキャスト柱との重ね継ぎ手を形成するための長さ分
に加えて、梁の高さ分の長さだけ長く形成する必要があ
る。そのため、中空プレキャスト柱の柱主筋の突出部が
長大となって、中空プレキャスト柱を運搬する際やプレ
キャスト梁や床等の配設の際における作業性が悪い。
However, the lap joint in the above-mentioned conventional precast method has the following problems. (A) In the case of the lap joint of (1) above, the pillar main bar projecting from the hollow precast column on the lower floor is in contact with the hollow precast column on the upper floor. For this purpose, it is necessary to bend inward so that the main bar of the hollow precast column on the lower floor can be easily inserted into the hollow portion of the hollow precast column on the upper floor. As described above, since the column main reinforcement is bent inward, when attaching the column reinforcement in the panel zone, it is necessary to change the outer diameter of the reinforcement according to the mounting position. It is necessary to make the length of the pillar main bar projecting from the column capital longer by the length of the beam in addition to the length for forming the lap joint with the hollow precast pillar on the upper floor. For this reason, the protruding portion of the column main reinforcement of the hollow precast column becomes long, and workability is poor when transporting the hollow precast column or arranging the precast beam, the floor, and the like.

【0009】(ロ) 上記(2)の重ね継ぎ手の場合 一本の中空プレキャスト柱Aは、上側から挿入され
る上側の先組鉄筋Cの縦筋1cと下側から挿入される下
側の先組鉄筋(図示せず)の縦筋とによって重ね継ぎ手を
形成する。そのために、中空プレキャスト柱Aは少なく
とも重ね継ぎ手長さの2倍の長さを必要とする。この重
ね継ぎ手の長さは、鉄筋径“d"を25mmとすると40
d以上必要とし、その結果、階高は2m以上となる。 意匠的な面から、結合された中空プレキャスト柱A
の外面とプレキャスト梁Bの外面とを同一面にする場合
がある。その際には、プレキャスト梁Bの梁主筋の被り
厚さおよびパネルゾーンにおける先組鉄筋Cの縦筋1c
の被り厚さが厚くなるので、剥落の危険性を防止するた
めに補強筋を設ける必要がある。
(B) In the case of the lap joint of the above (2), one hollow precast column A is composed of the vertical bar 1c of the upper pre-assembled reinforcing bar C inserted from the upper side and the lower bar 1c inserted from the lower side. A lap joint is formed with a vertical bar of a braided reinforcing bar (not shown). For that purpose, the hollow precast column A needs at least twice the length of the lap joint. The length of the lap joint is 40 when the rebar diameter “d” is 25 mm.
d or more, and as a result, the floor height becomes 2 m or more. Hollow precast pillar A joined from the design point of view
And the outer surface of the precast beam B may be the same. In this case, the thickness of the main reinforcing bar of the precast beam B and the longitudinal reinforcing bar 1c of the pre-assembled reinforcing bar C in the panel zone were measured.
Therefore, it is necessary to provide reinforcing bars in order to prevent the risk of peeling.

【0010】そこで、この発明の目的は、中空プレキャ
スト柱から突出する柱主筋の長さを短くでき、階高を低
くでき、結合された中空プレキャスト柱の外面と梁の外
面とを補強筋なしで同一面にできる柱・梁の接合工法を
提供することにある。
Accordingly, an object of the present invention is to reduce the length of a main bar projecting from a hollow precast column, reduce the floor height, and connect the outer surface of a joined hollow precast column and the outer surface of a beam without reinforcing bars. It is an object of the present invention to provide a method for joining columns and beams on the same surface.

【0011】[0011]

【課題を解決するための手段】上記目的を達成するため
に、請求項1に係る発明の柱・梁の接合工法は、柱頭か
ら長くとも上階のスラブ面まで突出した柱主筋及び帯筋
を内蔵した中空プレキャスト柱をスラブ上に建て込み、
下端主筋及びスターラップ筋が埋設された半プレキャス
トコンクリート梁の端部を上記中空プレキャスト柱上に
載置した後、上記中空プレキャスト柱に内蔵された上記
柱主筋における上記柱頭から突出した箇所に帯筋を所定
間隔で設置し、柱・梁接合部を水平方向に貫通させて上
記半プレキャストコンクリート梁間に下端連結筋を架け
渡し、上記柱・梁接合部を高さ方向に貫通する長さを有
する縦筋およびこの縦筋をその両端部で筒状に固定する
繋筋から成る先組鉄筋を上記柱・梁接合部内に在る上記
中空プレキャスト柱の柱主筋内に挿入して配筋し、上記
半プレキャストコンクリート梁に沿って上記柱・梁接合
部を貫通させて上記スターラップ筋の上辺内側に上端主
筋を配筋し、上記中空プレキャスト柱内,半プレキャス
トコンクリート梁内および柱・梁接合部内にコンクリー
トを打設して、柱と梁とを一体化することを特徴として
いる。
In order to achieve the above-mentioned object, according to the first aspect of the present invention, there is provided a method for connecting a column and a beam, wherein a column main bar and a band bar projecting from a capital to a slab surface of an upper floor at the longest. The built-in hollow precast pillar is built on the slab,
After placing the end of the semi-precast concrete beam in which the lower main bar and the stirrup bar are buried, on the hollow precast column, a band bar is provided at a portion of the column main bar built into the hollow precast column projecting from the stigma. Are installed at predetermined intervals, the column / beam joint is pierced in the horizontal direction, the lower end connecting bar is bridged between the semi-precast concrete beams, and a length having a length penetrating the column / beam joint in the height direction. A pre-assembled reinforcing bar consisting of a reinforcing bar and a connecting bar for fixing the vertical bar at both ends thereof in a tubular shape is inserted into the column main bar of the hollow precast column located in the column / beam joint, and the bars are arranged. Penetrate the column / beam joint along the precast concrete beam, arrange the upper main bar inside the upper side of the stirrup streak, and inside the hollow precast column and semi-precast concrete beam. Also, concrete is poured into the column / beam joint to integrate the column and beam.

【0012】また、請求項2に係る発明は、上記請求項
1に係る発明の柱・梁接合工法において、上記中空プレ
キャスト柱に内蔵された柱主筋における上記柱頭から突
出した箇所に設置される帯筋は、一本の鉄筋によってス
パイラル状に形成されていることを特徴としている。
According to a second aspect of the present invention, there is provided the column-beam joining method according to the first aspect of the present invention, wherein the belt is installed at a location protruding from the top of the column in the main bar of the column built in the hollow precast column. The muscle is characterized in that it is formed in a spiral shape by a single reinforcing bar.

【0013】また、請求項3に係る発明は、上記請求項
1に係る発明の柱・梁接合工法において、上記中空プレ
キャスト柱に内蔵された上記柱主筋における上記柱頭か
ら突出した箇所に設置される帯筋は、繋材によって連結
されていることを特徴としている。
According to a third aspect of the present invention, in the column-beam joining method according to the first aspect of the present invention, the column-beam joining method is installed at a location protruding from the column capital in the column main reinforcement built in the hollow precast column. The stirrups are characterized in that they are connected by connecting members.

【0014】また、請求項4に係る発明は、上記請求項
1乃至請求項3の何れか一つに記載の柱・梁の接合工法
において、上記柱・梁接合部内に在る上記中空プレキャ
スト柱の柱主筋内に挿入される上記先組鉄筋は、上記縦
筋における上記繋筋より先端部を内側に折り曲げられて
且つ上記縦筋の先端にフックが設けられていることを特
徴としている。
According to a fourth aspect of the present invention, there is provided the column / beam joining method according to any one of the first to third aspects, wherein the hollow precast column located in the column / beam joint is provided. The front reinforcing bar inserted into the column main reinforcing bar is characterized in that a tip portion is bent inward from the connecting bar in the vertical bar and a hook is provided at a distal end of the vertical bar.

【0015】[0015]

【実施例】以下、この発明を図示の実施例により詳細に
説明する。本実施例における柱・梁の接合工法は、下側
の中空プレキャスト柱と上側の中空プレキャスト柱とを
先組鉄筋で接合する柱・梁の接合工法である。
DETAILED DESCRIPTION OF THE PREFERRED EMBODIMENTS Hereinafter, the present invention will be described in detail with reference to the illustrated embodiments. The column / beam joining method in this embodiment is a column / beam joining method in which a lower hollow precast column and an upper hollow precast column are joined by a pre-assembled reinforcing bar.

【0016】図1および図2は、本実施例における柱・
梁の接合工法によって形成された柱・梁の接合構造の説
明図である。図1および図2に示すように、中空プレキ
ャスト柱11の柱主筋11aは、柱頭11bから長くとも
上階のスラブ面まで突出している。また、上記中空プレ
キャスト柱11の柱頭11b上に一端部が載置されてパ
ネルゾーンを形成する2本の梁12,13は、下端主筋
とスターラップ筋12b,13bが埋設された半プレキャ
ストコンクリート梁である。そして、上記中空プレキャ
スト柱の柱主筋11aにおけるパネルゾーン内に在る突
出部に外接させて、矩形の帯筋11cが所定間隔で設置
されている。
FIGS. 1 and 2 show the pillars in this embodiment.
It is explanatory drawing of the joining structure of the column and the beam formed by the joining method of the beam. As shown in FIG. 1 and FIG. 2, the column main bar 11a of the hollow precast column 11 projects from the column capital 11b to the slab surface on the upper floor at the longest. The two beams 12, 13 having one end placed on the capital 11b of the hollow precast column 11 to form a panel zone are semi-precast concrete beams in which a lower main bar and stirrup bars 12b, 13b are embedded. It is. Then, rectangular strip bars 11c are provided at predetermined intervals so as to circumscribe the protrusions located in the panel zone in the pillar main bars 11a of the hollow precast columns.

【0017】図2に示すように、縦筋14aを上下端部
の繋筋14b,14bによって四角筒に固定して成る先組
鉄筋14の下側半分を上記パネルゾーンにおける中空プ
レキャスト柱11の柱主筋11a内に挿入して、柱主筋
11aの突出部と先組鉄筋14の縦筋14aの下側半分と
で重ね継ぎ手を形成する。一方、上階のスラブ面から上
方に突出している先組鉄筋14の上側半分には上階の中
空プレキャスト柱(図示せず)の下部中空部をかぶせて重
ね継ぎ手を形成する。こうして、上記上下階の中空プレ
キャスト柱と2本の梁を接合するのである。
As shown in FIG. 2, the lower half of the pre-assembled reinforcing bar 14 having the longitudinal bars 14a fixed to the square tube by the connecting bars 14b at the upper and lower ends is used as the column of the hollow precast column 11 in the panel zone. It is inserted into the main reinforcing bar 11a, and a lap joint is formed by the protruding portion of the column main reinforcing bar 11a and the lower half of the longitudinal bar 14a of the pre-assembled reinforcing bar 14. On the other hand, the lower half of a hollow precast pillar (not shown) on the upper floor is covered on the upper half of the pre-assembled reinforcing bar 14 projecting upward from the slab surface on the upper floor to form an overlapping joint. In this way, the hollow precast columns on the upper and lower floors and the two beams are joined.

【0018】上記先組鉄筋14の縦筋14aは、繋筋1
4b,14bより先端部分が内側に折り曲げられてその先
端にはフック14cが設けられている。こうして、先組
鉄筋14を中空プレキャスト柱11の柱主筋11a内に
挿入する際における作業性の向上を図っている。
The longitudinal bar 14a of the pre-assembled reinforcing bar 14 is
A tip portion is bent inward from 4b and 14b, and a hook 14c is provided at the tip. In this way, the workability at the time of inserting the pre-assembled reinforcing bar 14 into the column main bar 11a of the hollow precast column 11 is improved.

【0019】上述のような柱・梁の結合構造において
は、図3(a)に示すように、下階の中空プレキャスト柱
11の柱主筋11aにおける突出部と先組鉄筋14の下
側半分との重ね継ぎ手の大部分は、上記パネルゾーン内
に形成されている。ここで、重ね継ぎ手長さは中空プレ
キャスト柱11の柱主筋11aの太さ等によって変動す
る。したがって、先組鉄筋14の下側半分と中空プレキ
ャスト柱11の柱主筋11aとの重ね継ぎ手が、上記パ
ネルゾーン内に収まりきらずに中空プレキャスト柱11
内に延長される場合がある。しかしながら、その場合に
おいても、重ね継ぎ手の大部分はパネルゾーン内に形成
されるので、中空プレキャスト柱11内に延長される部
分の長さは全重ね継ぎ手長さよりも十分短い。したがっ
て、本実施例での中空プレキャスト柱11の長さは少な
くとも重ね継ぎ手長さの2倍からパネルゾーンの高さを
差し引いた長さ以上であればよく、従来の先組鉄筋を使
用した場合よりも階高を低くできる。尚、図3(b)は図
3(a)におけるA−A矢視断面図であり、図3(c)は図3
(a)におけるB−B矢視断面図であり、図3(d)は図3
(a)におけるC−C矢視断面図である。
In the column / beam joint structure as described above, as shown in FIG. 3 (a), the lower half of the hollow precast column 11 has a projecting portion in the column main bar 11a and a lower half of the pre-assembled reinforcing bar 14. Most of the lap joints are formed in the panel zone. Here, the length of the lap joint varies depending on the thickness of the column main bar 11a of the hollow precast column 11, and the like. Therefore, the overlapping joint between the lower half of the pre-assembled reinforcing bar 14 and the column main bar 11a of the hollow precast column 11 does not fit within the panel zone and the hollow precast column 11
May be extended within. However, even in that case, the length of the portion extended into the hollow precast column 11 is sufficiently shorter than the length of the entire lap joint, since most of the lap joint is formed in the panel zone. Therefore, the length of the hollow precast column 11 in the present embodiment may be at least a length obtained by subtracting the height of the panel zone from at least twice the length of the lap joint. Can also lower the floor height. 3 (b) is a sectional view taken along the line AA in FIG. 3 (a), and FIG.
FIG. 3A is a sectional view taken along the line BB in FIG.
It is CC sectional view taken on the line (a).

【0020】また、本実施例における上記パネルゾーン
内に配筋される帯筋11cは、先組鉄筋14とは別に単
独に中空プレキャスト柱11の柱主筋11aの突出部に
設置される。そのために、上記先組鉄筋14に帯筋を取
り付ける領域を設ける必要がなく、先組鉄筋14をその
分だけ短くして軽く形成できる。したがって、上記中空
プレキャスト柱11と梁12,13とを接合する際に、
先組鉄筋14を人力で搬送でき、接合作業を容易に実施
できる。
In the present embodiment, the stirrups 11c arranged in the panel zone are separately provided separately from the pre-assembled reinforcing bars 14 at the projecting portions of the column main reinforcing bars 11a of the hollow precast columns 11. Therefore, it is not necessary to provide a region for attaching the reinforcing bar to the pre-assembled rebar 14, and the pre-assembled rebar 14 can be made shorter and lighter. Therefore, when joining the hollow precast column 11 and the beams 12, 13,
The pre-assembled rebar 14 can be transported manually, and the joining operation can be easily performed.

【0021】また、本実施例における柱・梁の接合構造
によれば、以下のような効果が得られる。図4は上記パ
ネルゾーンにおける縦断面図である。尚、図4(a)は本
実施例に係る縦断面図であり、図4(b)は従来例におけ
る縦断面図である。
According to the joint structure of columns and beams in this embodiment, the following effects can be obtained. FIG. 4 is a longitudinal sectional view in the panel zone. 4A is a longitudinal sectional view according to the present embodiment, and FIG. 4B is a longitudinal sectional view in a conventional example.

【0022】図4(a)において、下側の中空プレキャス
ト柱22の柱主筋22bはパネルゾーン21内に突出し
ている。そして、この柱主筋22bは、先組鉄筋24の
縦筋24aよりも外方に位置している。その結果、梁2
5に架け渡された上端主筋25aおよび下端連結筋25b
のうち最外に位置する上端主筋25aおよび下端連結筋
25bも先組鉄筋24の縦筋24aよりも外方(但し、下
側の中空プレキャスト柱22の柱主筋22bより内方)に
位置している。したがって、上記梁25の外面と中空プ
レキャスト柱22,23の外面22a,23aとを同一面に
する際に、梁25における最外に位置する上端主筋25
aおよび下端連結筋25bの被り厚さ“d1"を小さくでき
る。同様に、パネルゾーン21にコンクリートを打設し
て上記パネルゾーン21のコンクリート外面21aと中
空プレキャスト柱22,23の外面22a,23aとを同一
面にする際に、パネルゾーン21内における最外に位置
する鉄筋(すなわち、柱主筋22b)の被り厚さ“d2"も
小さくなって中空プレキャスト柱22,23と同じ通常
の値となる。すなわち、本実施例によれば補強筋の挿入
は不要となるのである。
In FIG. 4A, the column main reinforcement 22b of the lower hollow precast column 22 projects into the panel zone 21. The column main bar 22b is located outside the longitudinal bar 24a of the pre-assembled reinforcing bar 24. As a result, beam 2
The upper main bar 25a and the lower connecting bar 25b spanned over 5
The outermost upper reinforcement 25a and the lowermost connection reinforcement 25b are also located outside the longitudinal reinforcement 24a of the pre-assembled rebar 24 (but inside the column main reinforcement 22b of the lower hollow precast column 22). I have. Therefore, when the outer surface of the beam 25 and the outer surfaces 22a and 23a of the hollow precast columns 22 and 23 are flush with each other, the outermost upper main reinforcement 25 of the beam 25 is formed.
The thickness “d 1 ” of “a” and the bottom connecting bar 25b can be reduced. Similarly, when concrete is poured into the panel zone 21 and the concrete outer surface 21a of the panel zone 21 and the outer surfaces 22a, 23a of the hollow precast columns 22, 23 are flush with each other, the outermost surface in the panel zone 21 The covering thickness “d 2 ” of the located reinforcing bar (that is, the column main bar 22 b) is also reduced to the same normal value as the hollow precast columns 22 and 23. That is, according to the present embodiment, the insertion of the reinforcing bar becomes unnecessary.

【0023】これに対して、図4(b)に示す従来の柱・梁
接合工法によって得られる柱・梁の接合構造によれば、
パネルゾーン31内に挿入されている鉄筋は先組鉄筋3
4の縦筋34aのみである。そして、この先組鉄筋34
は中空プレキャスト柱32の中空部に挿入され、梁35
の最外に位置する上端主筋35aおよび下端連結筋35b
は先組鉄筋34の縦筋34aよりも内方に位置してい
る。そのために、上端主筋35a,下端連結筋35bおよ
び先組鉄筋34の縦筋34aは共にパネルゾーン31の
コンクリート外面31aからはかなり離れた位置に在
る。したがって、最外に位置する上端主筋35a,下端連
結筋35bの被り厚さd1および先組鉄筋34の縦筋34
aの被り厚さd2は大きく、その値が100mmを越える場
合には剥落の危険が生ずるために補強筋36を挿入する
必要が生ずるのである。
On the other hand, according to the column / beam joining structure obtained by the conventional column / beam joining method shown in FIG.
The rebar inserted in the panel zone 31 is the pre-assembled rebar 3
4 are only the vertical streaks 34a. And this tip rebar 34
Is inserted into the hollow portion of the hollow precast column 32 and the beam 35
Upper main bar 35a and lower connecting bar 35b located at the outermost sides
Are located more inward than the vertical bars 34a of the pre-assembled reinforcing bars 34. Therefore, the upper main bar 35a, the lower connecting bar 35b, and the vertical bar 34a of the pre-assembled reinforcing bar 34 are all located far away from the concrete outer surface 31a of the panel zone 31. Therefore, the thickness d 1 of the outermost upper main bar 35 a and the lowermost connecting bar 35 b and the length of the vertical bar 34 of the pre-assembled reinforcing bar 34.
The thickness d 2 is greater wearing of a, it is necessary to produce to insert a reinforcement 36 for the risk of spalling caused when exceeding the value 100 mm.

【0024】上述のような本実施例による柱・梁の接合
構造は、次のような柱・梁の接合工法によって実現でき
る。以下、本実施例における柱・梁の接合工法につい
て、図5に従って詳細に述べる。
The column / beam joining structure according to the present embodiment as described above can be realized by the following column / beam joining method. Hereinafter, the method of joining columns and beams in this embodiment will be described in detail with reference to FIG.

【0025】図5(a)に示すように、柱頭から主筋11
a,11a'が突出した中空プレキャスト柱11,11'を建
て込む。次に、図5(b)に示すように、上記中空プレキ
ャスト柱11,11'間に半プレキャストコンクリート梁
13を架設する。次に、図5(c)に示すように、上記パ
ネルゾーン内に突出している中空プレキャスト柱11,
11'の主筋11a,11a'に、帯筋11c,11c'を所定
間隔で設置する。
As shown in FIG. 5 (a), the main streaks 11
A hollow precast pillar 11, 11 'from which a, 11a' protrudes is erected. Next, as shown in FIG. 5B, a semi-precast concrete beam 13 is erected between the hollow precast columns 11, 11 '. Next, as shown in FIG. 5 (c), the hollow precast columns 11, projecting into the panel zone,
The stirrups 11c, 11c 'are arranged at predetermined intervals on the main streaks 11a, 11a' of 11 '.

【0026】次に、図5(d)に示すように、パネルゾー
ンを貫通させて半プレキャストコンクリート梁13の間
に下端連結筋15,15'を配筋する。次に、図5(e)に
示すように、先組鉄筋14,14'の下側半分をパネルゾ
ーンにおける中空プレキャスト柱11,11'の柱主筋1
1a,11a'内に挿入する。その際に、先組鉄筋14,1
4'の縦筋14a,14a'を固定する下側の繋筋14b,1
4b'が下端連結筋15,15'に当接するために、図5
(f)に示すように、先組鉄筋14,14'は落下せずに上
側半分をパネルゾーンから上方に突出させて位置決めさ
れる。次に、図5(f)に示すように、半プレキャストコ
ンクリート梁13,13',…に沿ってパネルゾーンを貫
通させて、半プレキャストコンクリート梁13,13',
…のスターラップ筋13b,13b',…の上辺内側に上端
主筋16を配筋する。
Next, as shown in FIG. 5 (d), lower end connecting bars 15, 15 'are arranged between the semi-precast concrete beams 13 so as to penetrate the panel zone. Next, as shown in FIG. 5 (e), the lower half of the pre-assembled reinforcing bars 14, 14 'is connected to the column main reinforcing bars 1 of the hollow precast columns 11, 11' in the panel zone.
1a, 11a '. At that time, the pre-assembled rebar 14,1
The lower connecting bars 14b, 1 for fixing the 4 'vertical bars 14a, 14a'
4b 'comes into contact with the lower connecting bars 15, 15'.
As shown in (f), the pre-assembled reinforcing bars 14, 14 'are positioned so that the upper half protrudes upward from the panel zone without falling. Next, as shown in FIG. 5 (f), the semi-precast concrete beams 13, 13 ',.
Are arranged inside the upper sides of the stirrup bars 13b, 13b ',.

【0027】次に、図5(g)に示すように、上記中空プ
レキャスト柱11,11'の空間,半プレキャストコンク
リート梁13の空間およびパネルゾーンにコンクリート
17を打設して上階のスラブ面を形成する。次に、図5
(h)に示すように、上記スラブ面から上半分が上方に突
出している先組鉄筋14,14'に上階の中空プレキャス
ト柱18,18'を建て込む。こうして、上下階の中空プ
レキャスト柱11,18と半プレキャストコンクリート
梁13との接合を実施する。
Next, as shown in FIG. 5 (g), concrete 17 is poured into the space of the hollow precast columns 11, 11 ', the space of the semi-precast concrete beam 13 and the panel zone, and the upper slab surface is formed. To form Next, FIG.
As shown in (h), hollow precast columns 18, 18 'on the upper floor are erected on the pre-assembled reinforcing bars 14, 14' whose upper half protrudes upward from the slab surface. Thus, the joining of the hollow precast columns 11 and 18 on the upper and lower floors and the semi-precast concrete beam 13 is performed.

【0028】上述のように、本実施例においては、柱頭
11bから長くとも上階のスラブ面まで突出した柱主筋
11aを有する中空プレキャスト柱11をスラブ上に建
て込む。そして、この中空プレキャスト柱11,11,…
間に半プレキャストコンクリート梁12,13を架設
し、形成されたパネルゾーン内に突出している中空プレ
キャスト柱11の柱主筋11aに帯筋11cを所定間隔で
設置する。そして、この柱主筋11a内に先組鉄筋14
の下側半分を挿入して、中空プレキャスト柱11の柱主
筋11aと先組鉄筋14の縦筋14aとで重ね継ぎ手を形
成する。さらに、上記先組鉄筋14の上側半分に上階の
中空プレキャスト柱を建て込んで重ね継ぎ手を形成す
る。
As described above, in this embodiment, the hollow precast pillar 11 having the pillar main bar 11a protruding from the capital 11b to the slab surface of the upper floor at the longest is built on the slab. And this hollow precast pillar 11,11, ...
Half precast concrete beams 12 and 13 are erected between them, and strip bars 11c are installed at predetermined intervals on the column main bars 11a of the hollow precast columns 11 projecting into the formed panel zone. Then, the pre-assembled reinforcing bar 14 is provided in the column main bar 11a.
Of the hollow precast column 11 and the longitudinal bar 14a of the pre-assembled reinforcing bar 14 to form an overlapping joint. Further, a hollow precast column on the upper floor is erected in the upper half of the pre-assembled reinforcing bar 14 to form a lap joint.

【0029】このように、上記中空プレキャスト柱11
と上側の先組鉄筋14との重ね継ぎ手の大部分をパネル
ゾーン内に形成し、当該中空プレキャスト柱11と下側
の先組鉄筋14との重ね継ぎ手を当該中空プレキャスト
柱11内に形成する。そのために、中空プレキャスト柱
11の長さは少なくとも重ね継ぎ手長さの2倍からパネ
ルゾーンの高さを差し引いた長さ以上在ればよい。した
がって、本実施例によれば、中空プレキャスト柱の長さ
が少なくとも重ね継ぎ手長さの2倍以上必要である従来
の柱・梁の接合工法よりも階高を低くできるのである。
As described above, the hollow precast column 11
Most of the lap joint between the upper pre-assembled reinforcing bar 14 and the upper pre-assembled reinforcing bar 14 is formed in the panel zone, and the lap joint between the hollow precast post 11 and the lower pre-assembled reinforcing bar 14 is formed in the hollow precast post 11. For this purpose, the length of the hollow precast column 11 may be at least as long as the length obtained by subtracting the height of the panel zone from at least twice the length of the lap joint. Therefore, according to the present embodiment, the floor height can be made lower than the conventional column / beam joining method in which the length of the hollow precast column is at least twice the length of the lap joint.

【0030】その際に、上記帯筋11cは、先組鉄筋1
4とは独立してパネルゾーン内の柱主筋11aに直接設
置する。したがって、先組鉄筋14に帯筋を取り付ける
必要がなく、その分先組鉄筋14の長さを短くして軽量
にできる。
At this time, the above-mentioned stirrup 11c is
4 and installed directly on the column main bar 11a in the panel zone. Therefore, there is no need to attach a strap to the pre-assembled rebar 14, and the length of the pre-assembled rebar 14 can be shortened and the weight can be reduced.

【0031】また、上記パネルゾーン内には中空プレキ
ャスト柱11の柱主筋11aが突出しているために、半
プレキャストコンクリート梁12,13の外面とパネル
ゾーンのコンクリート外面と中空プレキャスト柱11の
外面とを同一面にする際に、半プレキャストコンクリー
ト梁12,13に架け渡された最外に位置する上端主筋
16,下端連結筋15の被り厚さおよびパネルゾーンに
おける最外に位置する鉄筋(柱主筋11a)の被り厚さが
薄くなる。したがって、剥落防止のための補強筋を配筋
する必要がない。
Since the column main reinforcement 11a of the hollow precast column 11 projects into the panel zone, the outer surfaces of the semi-precast concrete beams 12, 13 and the concrete outer surface of the panel zone and the outer surface of the hollow precast column 11 are separated. When making the same plane, the thickness of the outermost upper reinforcing bar 16 and the lowermost connecting bar 15 which are bridged over the semi-precast concrete beams 12 and 13 and the outermost reinforcing bar (column main bar 11a) in the panel zone ) Is thinner. Therefore, there is no need to arrange reinforcing bars for preventing peeling.

【0032】また、上記先組鉄筋14は、複数の縦筋1
4aを上下に配置した繋筋14b,14bによって筒状に固
定して形成されている。したがって、先組鉄筋14をパ
ネルゾーン内に挿入した際に、半プレキャストコンクリ
ート梁12,13間に配筋された下端連結鉄筋15に先
組鉄筋14の下側の繋筋14bが当接して、パネルゾー
ン内における先組鉄筋14の位置が正しく設定される。
さらに、上記先組鉄筋14の縦筋14aは、繋筋14bよ
り先端を内側に折り曲げてフック14cを形成してい
る。したがって、先組鉄筋14はパネルゾーン内に挿入
し易い。
Further, the pre-assembled rebar 14 includes a plurality of longitudinal rebars 1.
4a is fixed in a tubular shape by connecting bars 14b, 14b arranged vertically. Therefore, when the pre-assembled reinforcing bar 14 is inserted into the panel zone, the lower connecting bar 14b on the lower side of the pre-assembled reinforcing bar 14 abuts against the lower end connecting reinforcing bar 15 arranged between the semi-precast concrete beams 12, 13. The position of the pre-assembled rebar 14 in the panel zone is set correctly.
Further, the vertical bar 14a of the pre-assembled reinforcing bar 14 has a hook 14c formed by bending the tip of the bar 14b inward from the connecting bar 14b. Therefore, the pre-assembled rebar 14 is easily inserted into the panel zone.

【0033】上記実施例においては、上記パネルゾーン
内に設置する帯筋11cは矩形を有する複数の帯筋11c
を所定間隔で配列して設置しているが、これに限定され
るものではない。例えば、1本の鉄筋をスパイラル状に
中空プレキャスト柱の柱主筋に巻き付けてもよい。ま
た、矩形を有する複数の帯筋を所定間隔で繋材によって
固定したものでもよい。また、上記実施例においては、
先組鉄筋14における縦筋14aの先端部を内側に折り
曲げてその先端にフック14cを設けているが、縦筋は
直線状であっても構わない。
In the above embodiment, the streak 11c installed in the panel zone is a plurality of streaks 11c having a rectangular shape.
Are arranged at predetermined intervals, but the present invention is not limited to this. For example, one reinforcing bar may be spirally wound around the main bar of the hollow precast column. Further, a plurality of strips having a rectangular shape may be fixed at predetermined intervals by a connecting member. In the above embodiment,
The tip of the longitudinal bar 14a of the pre-assembled reinforcing bar 14 is bent inward to provide the hook 14c at the tip, but the vertical bar may be straight.

【0034】[0034]

【発明の効果】以上より明らかなように、請求項1に係
る発明の柱・梁の接合工法では、柱頭から長くとも上階
のスラブ面まで突出した柱主筋を内蔵した中空プレキャ
スト柱を建て込み、半プレキャストコンクリート梁を架
設した後、上記中空プレキャスト柱の柱主筋における突
出部に帯筋を設置し、柱・梁接合部を水平方向に貫通さ
せて上記半プレキャストコンクリート梁間に下端連結筋
を架け渡し、上記柱・梁接合部内に在る上記中空プレキ
ャスト柱の柱主筋内に先組鉄筋を挿入し、上記半プレキ
ャストコンクリート梁に沿って上記柱・梁接合部を貫通
させて上端主筋を配筋し、上記中空プレキャスト柱内,
半プレキャストコンクリート梁内および柱・梁接合部内
にコンクリートを打設して柱と梁を一体化するので、1
本の中空プレキャスト柱は、上側の先組鉄筋との重ね継
ぎ手の大部分を柱・梁接合部内において形成する一方、
下側の先組鉄筋との重ね継ぎ手を当該中空プレキャスト
柱内において形成する。
As is apparent from the above description, in the column / beam joining method according to the first aspect of the present invention, a hollow precast column having a built-in column main bar protruding from the capital to the slab surface of the upper floor at most is built. After the semi-precast concrete beam is erected, a stirrup is installed at the projecting portion of the column main bar of the hollow precast column, and the lower end connecting bar is bridged between the semi-precast concrete beams by horizontally penetrating the column / beam joint. Hand, insert a pre-assembled rebar into the column main bar of the hollow precast column located in the column / beam joint, and penetrate the column / beam joint along the semi-precast concrete beam to arrange the upper main bar. And inside the hollow precast column,
The concrete is cast into the semi-precast concrete beam and the column / beam joint to integrate the column and beam.
While the hollow precast column of the book forms most of the lap joint with the upper pre-assembled rebar in the column-beam joint,
A lap joint with the lower pre-assembled rebar is formed in the hollow precast column.

【0035】したがって、この発明によれば、用いる中
空プレキャスト柱の長さは少なくとも重ね継ぎ手長さの
2倍からパネルゾーンの高さを差し引いた長さ以上を有
しておればよく、階高を低くすることが可能となる。
Therefore, according to the present invention, the length of the hollow precast column used should be at least twice as long as the length of the lap joint minus the height of the panel zone. It is possible to lower it.

【0036】さらに、上記中空プレキャスト柱の柱主筋
の突出量は長くとも上階のスラブ面までであるから、柱
主筋の突出量を従来よりも短くできる。さらに、上記中
空プレキャスト柱の柱主筋はパネルゾーン内に突出して
いる。したがって、上記半プレキャストコンクリート梁
の外面とパネルゾーンのコンクリート外面と中空プレキ
ャスト柱の外面とを同一面にする際に、上記半プレキャ
ストコンクリート梁に沿って配筋された最外に位置する
上端主筋,下端連結筋の被り厚さ及び上記パネルゾーン
における最外に位置する鉄筋の被り厚さが薄く、補助筋
を配筋する必要がない。
Further, since the projecting amount of the column main reinforcement of the hollow precast column is at most as long as the slab surface on the upper floor, the projecting amount of the column main reinforcement can be made shorter than before. Further, the column main reinforcement of the hollow precast column projects into the panel zone. Therefore, when the outer surface of the semi-precast concrete beam and the concrete outer surface of the panel zone and the outer surface of the hollow precast column are flush with each other, the uppermost main reinforcement located at the outermost position arranged along the semi-precast concrete beam, The covering thickness of the lower end connecting bar and the covering bar of the outermost reinforcing bar in the panel zone are small, and there is no need to arrange auxiliary bars.

【0037】また、請求項2に係る発明の柱・梁の接合
工法によれば、上記中空プレキャスト柱の上記柱主筋に
おける上記突出部に設置される帯筋を1本の鉄筋でスパ
イラル状に成したので、上記帯筋を容易に設置できる。
According to the column / beam joining method according to the second aspect of the present invention, the reinforcing strip installed at the projecting portion of the main column of the hollow precast column is formed spirally with one reinforcing bar. Therefore, the stirrup can be easily installed.

【0038】また、請求項3に係る発明の柱・梁の接合
工法によれば、上記中空プレキャスト柱の上記柱主筋に
おける上記突出部に設置される帯筋を繋材によって連結
しているので、上記帯筋を容易に設置できる。
According to the column / beam joining method of the third aspect of the present invention, since the strips provided at the protruding portions of the column main bars of the hollow precast columns are connected by a link member, The stirrup can be easily installed.

【0039】また、請求項4に係る発明の柱・梁の接合
工法によれば、上記先組鉄筋の縦筋における繋筋より先
端部を内側に折り曲げると共に、上記縦筋の先端にフッ
クを設けているので、上記先組鉄筋を上記中空プレキャ
スト柱の柱主筋内に容易に挿入でき、且つ所定の位置に
配置できる。
According to the column / beam joining method according to the fourth aspect of the present invention, the tip of the longitudinal bar of the pre-assembled reinforcing bar is bent inward from the connecting bar, and a hook is provided at the distal end of the longitudinal bar. Therefore, the pre-assembled rebar can be easily inserted into the column main bar of the hollow precast column, and can be arranged at a predetermined position.

【図面の簡単な説明】[Brief description of the drawings]

【図1】この発明の柱・梁の接合工法によって形成され
る柱・梁の接合構造の説明図である。
FIG. 1 is an explanatory view of a column / beam joining structure formed by the column / beam joining method of the present invention.

【図2】図1に続く柱・梁の接合構造の説明図である。FIG. 2 is an explanatory view of a column / beam joining structure following FIG. 1;

【図3】図1および図2に示す柱・梁の接合構造の断面
図である。
FIG. 3 is a cross-sectional view of the column / beam joint structure shown in FIGS. 1 and 2;

【図4】図3とは異なる柱・梁の接合構造におけるパネ
ルゾーンの拡大断面図である。
FIG. 4 is an enlarged sectional view of a panel zone in a column / beam joint structure different from FIG.

【図5】この発明の柱・梁の接合工法を示す図である。FIG. 5 is a view showing a method for joining columns and beams according to the present invention.

【図6】従来の柱・梁の接合構造の説明図である。FIG. 6 is an explanatory view of a conventional column / beam joint structure.

【符号の説明】[Explanation of symbols]

11,22…中空プレキャスト柱、 11a,2
2b…柱主筋、11c…帯筋、12,13,25…半プレキ
ャストコンクリート梁、14,24…先組鉄筋、
14a,24a…縦筋、14b…繋筋、
14c…フック、15,25b…下端連結
筋、 16,25a…上端主筋。
11,22… Hollow precast column, 11a, 2
2b ... pillar main bar, 11c ... band bar, 12, 13, 25 ... semi-precast concrete beam, 14, 24 ... pre-assembled bar,
14a, 24a ... vertical streak, 14b ... tether,
14c: hook, 15, 25b: lower connecting bar, 16, 25a: upper main bar.

───────────────────────────────────────────────────── フロントページの続き (58)調査した分野(Int.Cl.6,DB名) E04B 1/16 E04B 1/20 - 1/21 ──────────────────────────────────────────────────続 き Continued on the front page (58) Fields surveyed (Int.Cl. 6 , DB name) E04B 1/16 E04B 1/20-1/21

Claims (4)

(57)【特許請求の範囲】(57) [Claims] 【請求項1】 柱頭から長くとも上階のスラブ面まで突
出した柱主筋および帯筋を内蔵した中空プレキャスト柱
型枠をスラブ上に建て込み、 下端主筋およびスターラップ筋が埋設された半プレキャ
ストコンクリート梁の端部を上記中空プレキャスト柱型
枠上に載置した後、 上記中空プレキャスト柱型枠に内蔵された上記柱主筋に
おける上記柱頭から突出した箇所に帯筋を所定間隔で設
置し、 柱・梁接合部を水平方向に貫通させて上記半プレキャス
トコンクリート梁間に下端連結筋を架け渡し、 上記柱・梁接合部を高さ方向に貫通する長さを有する縦
筋およびこの縦筋を両端部で筒状に固定する繋筋から成
る先組鉄筋を、上記柱・梁接合部内に在る上記中空プレ
キャスト柱型枠の柱主筋内に挿入して配筋し、 上記半プレキャストコンクリート梁に沿って上記柱・梁
接合部を貫通させて、上記スターラップ筋の上辺内側に
上端主筋を配筋し、 上記中空プレキャスト柱型枠内,半プレキャストコンク
リート梁内および柱・梁接合部内にコンクリートを打設
して、柱と梁とを一体化することを特徴とする柱・梁の
接合工法。
1. A semi-precast concrete in which a hollow precast column form having built-in column main bars and stirrups protruding from a capital to a slab surface of at least an upper floor is built on a slab, and a lower main bar and a stirrup are buried. After placing the end portion of the beam on the hollow precast column formwork, a stirrup is installed at a predetermined interval at a position protruding from the stigma in the column main bar built in the hollow precast column formwork, and A beam connecting portion is horizontally pierced to bridge a lower connecting bar between the semi-precast concrete beams, and a vertical bar having a length penetrating the column / beam connecting portion in a height direction, and the vertical bar at both ends. A pre-assembled reinforcing bar consisting of a reinforcing bar fixed in a cylindrical shape is inserted into the column main bar of the hollow precast column form located in the column / beam joint, and is laid out, and the semi-precast concrete Penetrate the column / beam joint along with the upper main bar inside the upper side of the stirrup streaks, and concrete is inserted into the hollow precast column formwork, semi-precast concrete beam and column / beam joint. A method of joining columns and beams, where the columns and beams are integrated.
【請求項2】 請求項1に記載の柱・梁接合工法におい
て、 上記中空プレキャスト柱型枠に内蔵された上記柱主筋に
おける上記柱頭から突出した箇所に設置される帯筋は、
一本の鉄筋によってスパイラル状に形成されていること
を特徴とする柱・梁接合工法。
2. The column-beam joining method according to claim 1, wherein the stirrups installed at positions protruding from the stigma in the column main bars built in the hollow precast column form are:
A column / beam joining method characterized by being formed in a spiral shape by a single reinforcing bar.
【請求項3】 請求項1に記載の柱・梁接合工法におい
て、 上記中空プレキャスト柱型枠に内蔵された上記柱主筋に
おける上記柱頭から突出した箇所に設置される帯筋は、
繋材によって連結されていることを特徴とする柱・梁接
合工法。
3. The column / beam joining method according to claim 1, wherein the stirrups installed at locations protruding from the stigma of the column main bars built in the hollow precast column formwork are:
A column / beam joining method characterized by being connected by connecting members.
【請求項4】 請求項1乃至請求項3の何れか一つに記
載の柱・梁の接合工法において、 上記柱・梁接合部内に在る上記中空プレキャスト柱型枠
の柱主筋内に挿入される上記先組鉄筋は、上記縦筋にお
ける上記繋筋より先端部を内側に折り曲げられて、且つ
上記縦筋の先端にフックが設けられていることを特徴と
する柱・梁の接合工法。
4. The column / beam joining method according to claim 1, wherein the column / beam is inserted into a column main bar of the hollow precast column form located in the column / beam joint. A method of joining columns and beams, characterized in that the leading rebar is bent inward at the tip of the longitudinal bar from the connecting bar, and a hook is provided at the tip of the longitudinal bar.
JP5166768A 1993-07-06 1993-07-06 Column / beam joining method Expired - Fee Related JP2980793B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP5166768A JP2980793B2 (en) 1993-07-06 1993-07-06 Column / beam joining method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP5166768A JP2980793B2 (en) 1993-07-06 1993-07-06 Column / beam joining method

Publications (2)

Publication Number Publication Date
JPH0726623A JPH0726623A (en) 1995-01-27
JP2980793B2 true JP2980793B2 (en) 1999-11-22

Family

ID=15837342

Family Applications (1)

Application Number Title Priority Date Filing Date
JP5166768A Expired - Fee Related JP2980793B2 (en) 1993-07-06 1993-07-06 Column / beam joining method

Country Status (1)

Country Link
JP (1) JP2980793B2 (en)

Families Citing this family (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109162352A (en) * 2018-10-25 2019-01-08 安徽建筑大学 A kind of beam-column connection assembled using high-strength bolt
CN110093980A (en) * 2019-05-30 2019-08-06 广东联城住工装备信息科技有限公司 Beam-column node structure, the construction method of beam-column node structure and assembled architecture
CN110528690A (en) * 2019-09-20 2019-12-03 西安建筑科技大学 A kind of assembled integral concrete beam and column node and its construction method
CN114809772B (en) * 2022-06-02 2023-03-28 华南理工大学 Construction method of assembled column connecting joint and connecting joint
CN115680116B (en) * 2022-11-10 2023-08-04 海南大学 Assembled frame beam column connection node and construction method thereof

Also Published As

Publication number Publication date
JPH0726623A (en) 1995-01-27

Similar Documents

Publication Publication Date Title
KR100761786B1 (en) Concrete-composite Crossbeam
JP2980793B2 (en) Column / beam joining method
JP2905052B2 (en) Column / beam joining method
JPH03132532A (en) Construction method of precast reinforced concrete column and beam
JPH0452321Y2 (en)
CA3162116C (en) Method for assembling a building using concrete columns
JPH11247288A (en) Column-beam main bar pre-assembled hollow precast concrete column unit and column constructing method using this column unit
US11808025B1 (en) Method for assembling a building using concrete columns
JP2984626B2 (en) PC pillar construction method and its PC pillar
JP2542283B2 (en) Joining Method of Beam Reinforcement in Wall-type Ramen Column
JPH01214641A (en) Construction of steel-pipe precast concrete pole
JPH05230935A (en) Precase concrete made beam frame member
JP3187618B2 (en) How to assemble beam reinforcement
JPH0478771B2 (en)
JP2566477B2 (en) Outer wall construction method
JPH0448145B2 (en)
JPS5830459B2 (en) Construction method of precast reinforced concrete structure
ITVR980012A1 (en) PREFABRICATED HELICAL LADDER
JPH0588331B2 (en)
JPH0448136B2 (en)
JPH0650010B2 (en) Precast version
JPS6039835B2 (en) Reinforced steel construction method
JPS62121249A (en) Construction of pillar/beam connection part
JPS5837464B2 (en) Wall reinforcing bar assembly method
JPH0874381A (en) Reinforcement unit and construction method of reinforced concrete-made building using the same

Legal Events

Date Code Title Description
R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

LAPS Cancellation because of no payment of annual fees