CN114809772B - Construction method of assembled column connecting joint and connecting joint - Google Patents

Construction method of assembled column connecting joint and connecting joint Download PDF

Info

Publication number
CN114809772B
CN114809772B CN202210625463.1A CN202210625463A CN114809772B CN 114809772 B CN114809772 B CN 114809772B CN 202210625463 A CN202210625463 A CN 202210625463A CN 114809772 B CN114809772 B CN 114809772B
Authority
CN
China
Prior art keywords
cast
prefabricated column
column
node area
concrete mortar
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN202210625463.1A
Other languages
Chinese (zh)
Other versions
CN114809772A (en
Inventor
季静
苏家杰
陈熹俊
韩小雷
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
South China University of Technology SCUT
Original Assignee
South China University of Technology SCUT
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by South China University of Technology SCUT filed Critical South China University of Technology SCUT
Priority to CN202210625463.1A priority Critical patent/CN114809772B/en
Publication of CN114809772A publication Critical patent/CN114809772A/en
Application granted granted Critical
Publication of CN114809772B publication Critical patent/CN114809772B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04HBUILDINGS OR LIKE STRUCTURES FOR PARTICULAR PURPOSES; SWIMMING OR SPLASH BATHS OR POOLS; MASTS; FENCING; TENTS OR CANOPIES, IN GENERAL
    • E04H9/00Buildings, groups of buildings or shelters adapted to withstand or provide protection against abnormal external influences, e.g. war-like action, earthquake or extreme climate
    • E04H9/02Buildings, groups of buildings or shelters adapted to withstand or provide protection against abnormal external influences, e.g. war-like action, earthquake or extreme climate withstanding earthquake or sinking of ground
    • E04H9/021Bearing, supporting or connecting constructions specially adapted for such buildings
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04BGENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
    • E04B1/00Constructions in general; Structures which are not restricted either to walls, e.g. partitions, or floors or ceilings or roofs
    • E04B1/62Insulation or other protection; Elements or use of specified material therefor
    • E04B1/92Protection against other undesired influences or dangers
    • E04B1/98Protection against other undesired influences or dangers against vibrations or shocks; against mechanical destruction, e.g. by air-raids

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Environmental & Geological Engineering (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Business, Economics & Management (AREA)
  • Emergency Management (AREA)
  • Physics & Mathematics (AREA)
  • Electromagnetism (AREA)
  • Conveying And Assembling Of Building Elements In Situ (AREA)
  • Joining Of Building Structures In Genera (AREA)

Abstract

The invention provides a construction method of an assembly type column connecting node and the connecting node, comprising the following steps: pouring and maintaining a cast-in-place node area at the top of the lower-layer prefabricated column; a template is sleeved on the top of the cast-in-place node area and surrounds the part, extending out of the top of the cast-in-place node area, of the lower-layer precast column longitudinal bar, and the template and the top surface of the cast-in-place node area form an accommodating space with an upward opening and capable of pouring concrete mortar; pouring concrete mortar into the accommodating space through the opening; aligning and inserting the positioning component extending out of the bottom of the upper-layer prefabricated column into the concrete mortar through the opening, and supporting the bottom of the upper-layer prefabricated column on the top of the template; and curing the concrete mortar. The invention can solve the problems of poor construction quality and low construction precision of the connecting joint of the prefabricated column.

Description

一种装配式柱连接节点施工方法及连接节点Construction method and connection node of assembled column connection node

技术领域technical field

本发明涉及装配式结构技术领域,更具体地,涉及一种装配式柱连接节点施工方法。The invention relates to the technical field of prefabricated structures, and more particularly, relates to a construction method of prefabricated column connection nodes.

背景技术Background technique

目前我国装配式结构的广泛应用是推进装配式建筑发展和实现建筑行业工业化的重要一行,与原有现浇混凝土结构具有质量稳定、施工效率高、较少项目总建设成本、减少对环境的污染的有点。目前现有的预制柱中,装配式混凝土柱之间的连接方式主要采用灌浆套筒连接和锚浆搭接连接,又或者在节点中增加型钢连接件以实现连接,上述几种连接方式建设成本增加、施工工序复杂,且施工精度难以保证,施工后节点质量检测困难。At present, the wide application of prefabricated structures in my country is an important line to promote the development of prefabricated buildings and realize the industrialization of the construction industry. Compared with the original cast-in-place concrete structure, it has stable quality, high construction efficiency, less total project construction cost, and reduced environmental pollution. a bit. Among the existing prefabricated columns, the connection methods between prefabricated concrete columns mainly adopt grouting sleeve connection and anchor grout lap connection, or add section steel connectors to the nodes to realize the connection. The construction cost of the above several connection methods increase, the construction process is complicated, and the construction accuracy is difficult to guarantee, and the node quality inspection after construction is difficult.

发明内容Contents of the invention

本发明旨在克服上述现有技术的至少一种缺陷(不足),提供一种装配式柱连接节点施工方法及连接节点,用于解决装配式预制柱连接节点施工质量差、施工精度低的问题。The present invention aims to overcome at least one defect (deficiency) of the above-mentioned prior art, and provides a construction method and connection node of a prefabricated column connection, which are used to solve the problems of poor construction quality and low construction accuracy of the connection node of an assembled prefabricated column .

本发明采取的技术方案是:The technical scheme that the present invention takes is:

第一方面,本发明提供一种装配式柱连接节点施工方法,包括:In the first aspect, the present invention provides a construction method for a prefabricated column connection node, including:

在下层预制柱的顶部浇筑和养护现浇节点区;Pour and maintain the cast-in-place node area on the top of the lower prefabricated column;

在所述现浇节点区的顶部,并围绕所述下层预制柱纵筋伸出现浇节点区顶部的部分套设模板,所述模板与所述现浇节点区的顶面形成敞口向上的可浇灌混凝土砂浆的容纳空间;On the top of the cast-in-place node area, a formwork is set around the part of the lower precast column longitudinal reinforcement protruding from the top of the cast-in-place node area, and the formwork and the top surface of the cast-in-place node area form an open and upward The accommodation space for pourable concrete mortar;

通过所述敞口向所述容纳空间浇灌混凝土砂浆;pouring concrete mortar into the accommodation space through the opening;

通过所述敞口将伸出上层预制柱底部的定位部件对准插入所述混凝土砂浆,将上层预制柱底部支承在所述模板的顶部;Align and insert the positioning parts protruding from the bottom of the upper prefabricated column through the opening into the concrete mortar, and support the bottom of the upper prefabricated column on the top of the template;

养护所述混凝土砂浆。The concrete mortar is cured.

可选地,在通过所述敞口将伸出上层预制柱底部的定位部件对准插入所述混凝土砂浆之前,还包括:Optionally, before aligning and inserting the positioning part protruding from the bottom of the upper prefabricated column through the opening into the concrete mortar, it further includes:

在伸出上层预制柱底部的定位部件箍设抗剪钢筋;Set shear reinforcement hoops on the positioning parts protruding from the bottom of the upper prefabricated column;

或者,在所述现浇节点区的顶部,并围绕所述下层预制柱纵筋伸出现浇节点区顶部的部分套设模板之前,还包括:Or, before setting the formwork on the top of the cast-in-place node area and around the part of the lower precast column longitudinal reinforcement protruding from the top of the cast-in-place node area, it also includes:

在下层预制柱的纵筋伸出现浇节点区顶部的部分箍设抗剪钢筋。The shear reinforcement is hooped at the top of the cast-in-place node area where the longitudinal reinforcement of the lower prefabricated column extends.

可选地,在下层预制柱的顶部浇筑和养护现浇节点区,包括:Optionally, a cast-in-place node area is poured and cured on top of the lower precast columns, including:

对下层预制柱纵筋伸出所述下层预制柱的顶部且伸入现浇节点区的部分箍设箍筋;Stirrups are set on the part where the longitudinal reinforcement of the lower prefabricated column protrudes from the top of the lower prefabricated column and extends into the cast-in-place node area;

浇筑所述现浇节点区;Pouring the cast-in-place node area;

养护所述现浇节点区。The cast-in-place node area is maintained.

可选地,通过所述敞口向所述容纳空间浇灌混凝土砂浆,包括:Optionally, pouring concrete mortar into the accommodation space through the opening includes:

通过所述敞口向所述容纳空间浇灌混凝土砂浆,使所述容纳空间至少一半浇灌有所述混凝土砂浆。Concrete mortar is poured into the accommodation space through the opening, so that at least half of the accommodation space is poured with the concrete mortar.

可选地,通过所述敞口向所述容纳空间浇灌混凝土砂浆,包括:Optionally, pouring concrete mortar into the accommodation space through the opening includes:

通过所述敞口向所述容纳空间浇灌混凝土砂浆,使所述容纳空间的混凝土砂浆在所述定位部件插入时会溢出。Concrete mortar is poured into the accommodation space through the opening, so that the concrete mortar in the accommodation space will overflow when the positioning component is inserted.

可选地,所述定位部件包括所述上层预制柱纵筋向内弯折后伸出所述上层预制柱底部的部分,所述定位部件插入所述混凝土砂浆的深度大于或等于满足所述上层预制柱纵筋的锚固要求的最小长度。Optionally, the positioning component includes a part that protrudes from the bottom of the upper precast column after the longitudinal reinforcement of the upper prefabricated column is bent inward, and the depth of the positioning component inserted into the concrete mortar is greater than or equal to satisfy the requirements of the upper layer. The minimum length required for the anchorage of longitudinal reinforcement of precast columns.

可选地,所述模板的高度大于或等于定位部件的高度与保护所述定位部件的保护层厚度之和。Optionally, the height of the template is greater than or equal to the sum of the height of the positioning component and the thickness of the protective layer protecting the positioning component.

可选地,在所述现浇节点区的顶部,并围绕所述下层预制柱伸出现浇节点区顶部的纵筋套设模板之后,通过所述敞口向所述容纳空间浇灌混凝土砂浆之前,还包括:Optionally, at the top of the cast-in-place node area and around the lower prefabricated column extending the longitudinal reinforcement at the top of the cast-in-place node area to set the template, before pouring concrete mortar into the accommodation space through the opening ,Also includes:

通过支撑固定所述模板的位置;fixing the position of the formwork by supports;

在养护所述混凝土砂浆之后,还包括:After curing the concrete mortar, also include:

撤走所述支撑,并在所述模板为可拆卸时,拆卸所述模板。The supports are removed and, when the formwork is detachable, the formwork is disassembled.

可选地,在下层预制柱的顶部浇筑和养护现浇节点区之后,通过所述敞口向所述容纳空间浇灌混凝土砂浆之前,还包括:Optionally, after pouring and curing the cast-in-situ node area on the top of the lower prefabricated column, before pouring concrete mortar into the accommodation space through the opening, the method further includes:

对所述现浇节点区的顶面进行拉毛。The top surface of the cast-in-place node area is roughened.

第二方面,本发明提供一种装配式柱连接节点,包括上层预制柱、下层预制柱,所述上层预制柱和所述下层预制柱分别设有纵筋和箍筋,所述上层预制柱与所述下层预制柱之间设有现浇节点区,所述上层预制柱设有定位部件,所述的定位部件伸出所述上层预制柱的底部;所述下层预制柱纵筋的上部伸入所述现浇节点区并伸出所述现浇节点区的顶部,所述连接节点采用如权利要求1至5任一项所述的装配式柱连接节点施工方法进行施工。In a second aspect, the present invention provides an assembled column connection node, comprising an upper prefabricated column and a lower prefabricated column, the upper prefabricated column and the lower prefabricated column are respectively provided with longitudinal reinforcement and stirrup, and the upper prefabricated column and the lower prefabricated column are respectively provided with There are cast-in-place node areas between the lower precast columns, and the upper precast columns are provided with positioning parts, and the positioning parts extend out from the bottom of the upper precast columns; the upper part of the longitudinal reinforcement of the lower precast columns extends into The cast-in-place node area protrudes from the top of the cast-in-place node area, and the connection node is constructed by using the construction method of the fabricated column connection node according to any one of claims 1 to 5.

与现有技术相比,本发明的有益效果为:以伸出上层预制柱底部的定位部件插入混凝土砂浆、伸出下层预制柱顶部的纵筋也插入混凝土砂浆的方式,使得装配式柱连接节点的施工操作更加简便,施工质量更容易保证,提高了施工精度。Compared with the prior art, the beneficial effect of the present invention is: the positioning part protruding from the bottom of the upper prefabricated column is inserted into the concrete mortar, and the longitudinal reinforcement protruding from the top of the lower prefabricated column is also inserted into the concrete mortar, so that the prefabricated column is connected to the node The construction operation is more convenient, the construction quality is easier to guarantee, and the construction accuracy is improved.

附图说明Description of drawings

图1是实施例1装配式柱连接节点施工方法的流程图Fig. 1 is the flowchart of embodiment 1 assembly type column connection node construction method

图2是实施例1施工完成后的装配式柱连接节点示意图。Fig. 2 is a schematic diagram of the connection node of the assembled column after the construction of the first embodiment is completed.

图3是图2中A处放大图。Fig. 3 is an enlarged view of A in Fig. 2 .

图4是实施例1步骤S10浇筑和养护现浇节点区的流程图。Fig. 4 is a flow chart of pouring and maintaining the cast-in-place node area in Step S10 of Embodiment 1.

图5是实施例1套设模板后的装配式柱连接节点示意图。Fig. 5 is a schematic diagram of the connection node of the prefabricated column after the formwork is set in Example 1.

图6是实施例2一个施工完成后的装配式柱连接节点示意图。Fig. 6 is a schematic diagram of a prefabricated column connection node after construction in Embodiment 2.

图7是实施例3一个施工完成后的装配式柱连接节点示意图。Fig. 7 is a schematic diagram of a prefabricated column connection node after construction in Embodiment 3.

附图说明:100-上层预制柱;111-上层预制柱的纵筋;112-上层预制柱的箍筋;113-凸块;200-下层预制柱;211-下层预制柱的纵筋;212-下层预制柱的箍筋;300-现浇节点区;310-毛刺;410-模板;411-加固钢筋;420-混凝土砂浆;430-敞口;440-容纳空间。Description of drawings: 100-upper precast column; 111-longitudinal reinforcement of upper precast column; 112-stirrup of upper precast column; 113-bump; 200-lower precast column; 211-longitudinal reinforcement of lower precast column; Stirrups of lower prefabricated columns; 300-cast-in-place node area; 310-burrs; 410-formwork; 411-reinforcing reinforcement; 420-concrete mortar; 430-opening; 440-accommodating space.

具体实施方式Detailed ways

本发明附图仅用于示例性说明,不能理解为对本发明的限制。为了更好说明以下实施例,附图某些部件会有省略、放大或缩小,并不代表实际产品的尺寸;对于本领域技术人员来说,附图中某些公知结构及其说明可能省略是可以理解的。The accompanying drawings of the present invention are only for illustrative purposes, and should not be construed as limiting the present invention. In order to better illustrate the following embodiments, some components in the drawings will be omitted, enlarged or reduced, and do not represent the size of the actual product; for those skilled in the art, some known structures and their descriptions in the drawings may be omitted. understandable.

实施例1Example 1

本实施例提供一种装配式柱连接节点施工方法,用于对装配式柱连接节点进行施工。装配整体式混凝土结构是由预制混凝土构件或部件通过钢筋、连接件或施加预应力加以连接并现场浇筑混凝土而形成整体的结构,在预制构件相互连接的节点处会形成现浇节点区。This embodiment provides a construction method for a prefabricated column connection node, which is used for constructing the prefabricated column connection node. The prefabricated integral concrete structure is an integral structure formed by prefabricated concrete components or components connected by steel bars, connectors or prestressed and cast concrete on site. A cast-in-place node area will be formed at the joints where the prefabricated components are connected.

本实施例所施工的装配式柱连接节点,是上层预制柱与下层预制柱的连接节点,上层预制柱和下层预制柱均为预制的混凝土结构。图1是本实施例装配式柱连接节点施工方法的流程图,图2是本实施例施工完成后的装配式柱连接节点示意图,图3是图2中的A处放大图。如图1至图3所示,该装配式柱连接节点施工方法包括:The prefabricated column connection node constructed in this embodiment is the connection node between the upper prefabricated column and the lower prefabricated column, both of which are prefabricated concrete structures. Fig. 1 is a flowchart of the construction method of the prefabricated column connection node in this embodiment, Fig. 2 is a schematic diagram of the prefabricated column connection node after the construction of this embodiment is completed, and Fig. 3 is an enlarged view of A in Fig. 2 . As shown in Figures 1 to 3, the construction method of the prefabricated column connection node includes:

S10.在下层预制柱200的顶部浇筑和养护现浇节点区300。S10. Pour and maintain the cast-in-place node area 300 on the top of the lower prefabricated column 200 .

现浇节点区300位于上层预制柱100与下层预制柱200之间。在装配上层预制柱100之前,需要先完成现浇节点区300的浇筑和养护。The cast-in-place node area 300 is located between the upper prefabricated column 100 and the lower prefabricated column 200 . Before the upper prefabricated columns 100 are assembled, the pouring and curing of the cast-in-place node areas 300 need to be completed.

下层预制柱200要与其顶部的的结构形成固接,下层预制柱200的纵筋211需要伸入现浇节点区300。因此,如图2至图4所示,步骤S10具体包括:The lower prefabricated column 200 needs to be firmly connected to the structure on the top, and the longitudinal reinforcement 211 of the lower prefabricated column 200 needs to extend into the cast-in-place node area 300 . Therefore, as shown in FIGS. 2 to 4, step S10 specifically includes:

S11.对下层预制柱200纵筋211伸出下层预制柱200的顶部且伸入现浇节点区300的部分箍设箍筋212;S11. Set stirrups 212 on the part where the longitudinal reinforcement 211 of the lower precast column 200 protrudes from the top of the lower precast column 200 and extends into the cast-in-place node area 300;

S12.浇筑现浇节点区300;S12. Pouring the cast-in-place node area 300;

S13.养护现浇节点区300。S13. Maintain the cast-in-place node area 300.

作为预制混凝土结构的下层预制柱200设有纵筋211和箍设于纵筋211的箍筋212。下层预制柱200纵筋211的上部伸出下层预制柱200的顶部以外,并伸入现浇节点区300。在下层预制柱200预制完成后,下层预制柱200纵筋211伸出下层预制柱200顶部的部分还未箍设箍筋212,在下层预制柱200安装定位后、浇筑现浇节点区300之前,要对下层预制柱200纵筋211伸出下层预制柱200的顶部且伸入现浇节点区300的部分箍设箍筋212。The lower prefabricated column 200 as a precast concrete structure is provided with longitudinal reinforcements 211 and stirrups 212 hooped to the longitudinal reinforcements 211 . The upper part of the longitudinal reinforcement 211 of the lower precast column 200 protrudes beyond the top of the lower precast column 200 and extends into the cast-in-place node area 300 . After the prefabrication of the lower precast column 200 is completed, the part where the longitudinal reinforcement 211 of the lower precast column 200 protrudes from the top of the lower precast column 200 has not yet been hooped with hoops 212. Stirrups 212 should be provided for the part where the longitudinal reinforcement 211 of the lower precast column 200 protrudes from the top of the lower precast column 200 and extends into the cast-in-place node area 300 .

在具体实施过程中,上层预制柱100和下层预制柱200之间还可以设有梁和/或板时,梁、板可以分别是预制的或现浇的。为了实现梁端部的固接,梁的纵筋也可以伸入现浇节点区300,此时在浇筑现浇节点区300之前,要将梁的纵筋先设置好。In a specific implementation process, when beams and/or slabs may be provided between the upper prefabricated column 100 and the lower prefabricated column 200, the beams and slabs may be prefabricated or cast-in-place respectively. In order to realize the fastening of the beam ends, the longitudinal reinforcement of the beam can also be extended into the cast-in-place joint area 300 . At this time, before pouring the cast-in-place joint area 300 , the longitudinal reinforcement of the beam should be set up first.

S20.在现浇节点区300的顶部,并围绕下层预制柱200纵筋211伸出现浇节点区300顶部的部分套设模板410,模板410与现浇节点区300的顶面形成敞口430向上的可浇灌混凝土砂浆420的容纳空间440。S20. Set a formwork 410 on the top of the cast-in-place node area 300 and surround the lower prefabricated column 200 longitudinal ribs 211 protruding from the top of the cast-in-place node area 300. The formwork 410 and the top surface of the cast-in-place node area 300 form an opening 430 Upward receiving space 440 for pourable concrete mortar 420 .

示例性地,图5是套设模板410后的装配式柱连接节点示意图。如图5所示,模板410形成容纳空间440的侧面围蔽,现浇节点区300的顶面形成容纳空间440的底面围蔽,容纳空间440的顶面并未围蔽而形成向上的敞口430。模板410可以直接置于现浇节点区300的顶部,方便在施工过程中完成模板410的设置。模板410也可以插入现浇节点区300的顶部,优化模板410的固定效果。模板410与现浇节点区300顶面所形成的容纳空间440可以包裹下层预制柱200纵筋211伸出现浇节点区300顶部的部分。Exemplarily, FIG. 5 is a schematic diagram of the prefabricated column connection node after the template 410 is set. As shown in Figure 5, the template 410 forms the side enclosure of the accommodation space 440, the top surface of the cast-in-place node area 300 forms the bottom enclosure of the accommodation space 440, and the top surface of the accommodation space 440 is not enclosed but forms an upward opening 430. The formwork 410 can be directly placed on the top of the cast-in-place node area 300, which facilitates the setting of the formwork 410 during construction. The formwork 410 can also be inserted on top of the cast-in-place node area 300 to optimize the fixing effect of the formwork 410 . The accommodation space 440 formed by the template 410 and the top surface of the cast-in-place node area 300 can wrap the part of the longitudinal ribs 211 of the lower prefabricated column 200 protruding from the top of the cast-in-place node area 300 .

在施工过程中,混凝土砂浆420未凝固时,模板410容易受到较大的侧向力。在连接节点的不同工况下,模板410也容易受到一定程度的侧向力。为了进一步保证在施工过程以及施工完成后模板410的稳固性和安全性,在一种可选的实施例中,模板410为混凝土结构,模板410的内部围绕容纳空间440的中心环设有加固钢筋411。During construction, when the concrete mortar 420 is not solidified, the formwork 410 is easily subjected to a relatively large lateral force. Under different working conditions of the connection nodes, the template 410 is also susceptible to a certain degree of lateral force. In order to further ensure the stability and safety of the formwork 410 during the construction process and after the construction is completed, in an optional embodiment, the formwork 410 is a concrete structure, and the inside of the formwork 410 is provided with reinforcing steel bars around the central ring of the accommodation space 440 411.

步骤S20形成敞口430向上的可浇灌混凝土砂浆420的容纳空间440之后,还可以包括:对现浇节点区300的顶面进行拉毛。After step S20 forms the accommodating space 440 where the concrete mortar 420 can be poured with the opening 430 upward, it may further include: roughening the top surface of the cast-in-place node area 300 .

将现浇节点区300的顶面进行拉毛,使得现浇节点区300的顶面形成毛刺310,可以加强现浇节点区300与后续在容纳空间440中所浇灌混凝土砂浆420之间的连接形。The top surface of the cast-in-place node area 300 is roughened so that burrs 310 are formed on the top surface of the cast-in-place node area 300 , which can strengthen the connection between the cast-in-place node area 300 and the concrete mortar 420 subsequently poured in the accommodation space 440 .

S30.通过敞口430向容纳空间440浇灌混凝土砂浆420。S30 . Pouring concrete mortar 420 into the accommodation space 440 through the opening 430 .

当模板410套设好并与现浇节点区300的顶面形成容纳空间440后,即可向容纳空间440通过敞口430浇灌混凝土。浇灌的混凝土砂浆420可以选用和易性较好的,以便后续上层预制柱100底部定位部件的对准插入。After the formwork 410 is sleeved and forms an accommodation space 440 with the top surface of the cast-in-place node area 300 , concrete can be poured into the accommodation space 440 through the opening 430 . The poured concrete mortar 420 can be selected with good workability, so as to facilitate the alignment and insertion of the positioning parts at the bottom of the upper prefabricated column 100 later.

在一种可选的实施例中,容纳空间440中所浇灌的混凝土砂浆420不能太少,通过敞口430向容纳空间440浇灌混凝土砂浆420,使容纳空间440至少一半浇灌有混凝土砂浆420,由此使得混凝土砂浆420可以更好地包裹后续插入的上层预制柱100底部定位部件。In an optional embodiment, the concrete mortar 420 poured in the accommodation space 440 cannot be too little, and the concrete mortar 420 is poured into the accommodation space 440 through the opening 430, so that at least half of the accommodation space 440 is poured with the concrete mortar 420, by This enables the concrete mortar 420 to better wrap the positioning components at the bottom of the upper prefabricated column 100 inserted later.

在另一种可选的实施例中,通过敞口430向容纳空间440浇灌混凝土砂浆420,使容纳空间440的混凝土砂浆420在定位部件插入时会溢出,溢出的混凝土砂浆420可以使得后续插入的上层预制柱100底部定位部件得到更好的包裹。In another optional embodiment, the concrete mortar 420 is poured into the receiving space 440 through the opening 430, so that the concrete mortar 420 in the receiving space 440 will overflow when the positioning component is inserted, and the overflowing concrete mortar 420 can make the subsequently inserted The positioning parts at the bottom of the upper prefabricated column 100 are better wrapped.

S40.通过敞口430将伸出上层预制柱100底部的定位部件对准插入混凝土砂浆420,将上层预制柱100底部直接支承在模板410的顶部。S40 . Align and insert the positioning part protruding from the bottom of the upper prefabricated column 100 into the concrete mortar 420 through the opening 430 , and directly support the bottom of the upper precast column 100 on the top of the template 410 .

上层预制柱100底部的定位部件插入容纳空间440的混凝土砂浆420中,实现上层预制柱100的定位,上层预制柱100的底部可以直接支撑在模板410的顶部,待混凝土砂浆420凝固后可以实现与上层预制柱100的可靠连接。The positioning part at the bottom of the upper precast column 100 is inserted into the concrete mortar 420 in the accommodation space 440 to realize the positioning of the upper precast column 100. The bottom of the upper precast column 100 can be directly supported on the top of the formwork 410. After the concrete mortar 420 solidifies, it can realize the positioning of the upper precast column 100. Reliable connection of the upper prefabricated column 100.

当容纳空间440的混凝土砂浆420足够多时,上层预制柱100底部的定位部件插入混凝土砂浆420会让混凝土砂浆420溢出容纳空间440,上层预制柱100的底部与模板410之间也会间隙存在混凝土砂浆420,可以增强上层预制柱100与模板410之间的粘结。When the concrete mortar 420 in the accommodation space 440 is sufficient, the positioning part at the bottom of the upper prefabricated column 100 is inserted into the concrete mortar 420 to make the concrete mortar 420 overflow the accommodation space 440, and there will be concrete mortar in the gap between the bottom of the upper prefabricated column 100 and the template 410 420, the bonding between the upper prefabricated column 100 and the template 410 can be enhanced.

当上层预制柱100底部的定位部件插入容纳空间440的混凝土砂浆420时,定位部件的底部与现浇节点区300的顶面之间,可以预留一保护层厚度,用以更好地保护定义部件。因此,模板410的高度(图3中的h)大于或等于定位部件的高度(图3中的l1)与保护定位部件的保护层厚度(图3中的c)之和。When the positioning part at the bottom of the upper prefabricated column 100 is inserted into the concrete mortar 420 of the accommodation space 440, a protective layer thickness can be reserved between the bottom of the positioning part and the top surface of the cast-in-place node area 300 to better protect the defined part. Therefore, the height of the template 410 ( h in FIG. 3 ) is greater than or equal to the sum of the height of the positioning component ( l 1 in FIG. 3 ) and the thickness of the protective layer protecting the positioning component ( c in FIG. 3 ).

在一个可选的实施例中,定位部件可以包括上层预制柱100的纵筋111向内弯折后伸出上层预制柱100底部的部分。In an optional embodiment, the positioning component may include the part where the longitudinal ribs 111 of the upper precast column 100 are bent inward and protrude from the bottom of the upper precast column 100 .

由于定位部件要满足一定的锚固要求,所以定位部件插入混凝土砂浆420的深度大于或等于满足上层预制柱100的纵筋111锚固要求的最小长度。Since the positioning component must meet certain anchoring requirements, the depth of the positioning component inserted into the concrete mortar 420 is greater than or equal to the minimum length that meets the anchoring requirements of the longitudinal reinforcement 111 of the upper precast column 100 .

S50.养护混凝土砂浆420。S50. Curing concrete mortar 420.

当完成上层预制柱100的定位和安装后,即可进行混凝土砂浆420的养护。After the positioning and installation of the upper prefabricated column 100 is completed, the concrete mortar 420 can be maintained.

在一个可选的实施例中,步骤S20在现浇节点区300的顶部,并围绕下层预制柱200伸出现浇节点区300顶部的纵筋211套设模板410之后,步骤S30通过敞口430向容纳空间440浇灌混凝土砂浆420之前,还可以包括:通过支撑固定模板410的位置。步骤S50养护混凝土砂浆420之后,还可以包括:撤走支撑,并在模板410为可拆卸时,拆卸模板410。In an optional embodiment, step S20 is at the top of the cast-in-place node area 300 and after the formwork 410 is set around the lower prefabricated column 200 protruding from the top of the cast-in-place node area 300 longitudinal ribs 211, step S30 passes through the opening 430 Before pouring the concrete mortar 420 into the accommodating space 440 , it may further include: fixing the position of the template 410 by supporting. After curing the concrete mortar 420 in step S50, it may further include: removing the support, and disassembling the formwork 410 when the formwork 410 is detachable.

在混凝土砂浆420未凝固时,为了进一步保证模板410的可靠性,可以通过支撑,例如斜撑等,固定模板410,在混凝土砂浆420凝固后可以撤走支撑。When the concrete mortar 420 is not solidified, in order to further ensure the reliability of the formwork 410, the formwork 410 can be fixed by supports, such as diagonal braces, and the supports can be removed after the concrete mortar 420 is solidified.

为了美观,模板410可以设计为可拆卸的,在混凝土砂浆420凝固后可以拆卸模板410,此时模板410可以是铝模板或木模板。当模板410为不可拆卸时,模板410可以是混凝土模板。For the sake of aesthetics, the formwork 410 can be designed to be detachable, and the formwork 410 can be disassembled after the concrete mortar 420 is solidified. At this time, the formwork 410 can be an aluminum formwork or a wood formwork. When the form 410 is not detachable, the form 410 may be a concrete form.

采用本实施例所提供的施工方法,以上层预制柱100的定位部件和下层预制柱200纵筋211插入混凝土砂浆420的方式,使得施工操作简单,且容易保证施工质量。Using the construction method provided in this embodiment, the positioning components of the upper precast column 100 and the longitudinal reinforcement 211 of the lower precast column 200 are inserted into the concrete mortar 420, so that the construction operation is simple and the construction quality is easy to ensure.

实施例2Example 2

本实施例提供一种装配式柱连接节点施工方法,用于对装配式柱连接节点进行施工。本实施例与实施例1的区别在于,在步骤S40之前,还包括:在伸出上层预制柱100底部的定位部件箍设抗剪钢筋412。This embodiment provides a construction method for a prefabricated column connection node, which is used for constructing the prefabricated column connection node. The difference between this embodiment and Embodiment 1 is that, before step S40 , it also includes: hooping the shear reinforcement 412 on the positioning part protruding from the bottom of the upper prefabricated column 100 .

图6是本实施例施工完成后的装配式柱连接节点示意图,如图6所示,抗剪钢筋412箍设在定位部件上。具体地,定位部件包括上层预制柱100的纵筋111向内弯折后伸出上层预制柱100底部的部分,抗剪钢筋412箍设在该部分上。Fig. 6 is a schematic diagram of the assembled column connection node after the construction of this embodiment is completed. As shown in Fig. 6, the shear reinforcement 412 is hooped on the positioning part. Specifically, the positioning component includes the part where the longitudinal reinforcement 111 of the upper precast column 100 is bent inward and protrudes from the bottom of the upper precast column 100 , and the shear steel bar 412 is hooped on this part.

实施例3Example 3

本实施例提供一种装配式柱连接节点施工方法,用于对装配式柱连接节点进行施工。本实施例与实施例1的区别在于,在步骤S20之前,还包括:在下层预制柱200的纵筋211伸出现浇节点区300顶部的部分箍设抗剪钢筋412。This embodiment provides a construction method for a prefabricated column connection node, which is used for constructing the prefabricated column connection node. The difference between this embodiment and Embodiment 1 is that before step S20, it also includes: hooping shear reinforcement 412 at the part where the longitudinal reinforcement 211 of the lower prefabricated column 200 protrudes from the top of the cast-in-place node area 300 .

如图2、图3所示,抗剪钢筋412箍设在下层预制柱200的纵筋211上。As shown in FIG. 2 and FIG. 3 , the shear reinforcement 412 is hooped on the longitudinal reinforcement 211 of the lower prefabricated column 200 .

实施例4Example 4

基于同一个发明构思,本实施例还提供一种装配式柱连接节点,如图2、图3所示,包括上层预制柱100、下层预制柱200,下层预制柱200设有纵筋211和箍筋212,上层预制柱100与下层预制柱200之间设有现浇节点区300,上层预制柱100设有定位部件,定位部件伸出上层预制柱100的底部,下层预制柱200纵筋211的上部伸入现浇节点区300并伸出现浇节点区300的顶部,连接节点采用如上所述的装配式柱连接节点施工方法进行施工。Based on the same inventive concept, this embodiment also provides a prefabricated column connection node, as shown in Figure 2 and Figure 3, which includes an upper prefabricated column 100 and a lower prefabricated column 200, and the lower prefabricated column 200 is provided with longitudinal reinforcement 211 and hoops Rib 212, a cast-in-place node area 300 is provided between the upper precast column 100 and the lower precast column 200, the upper precast column 100 is provided with a positioning component, and the positioning component protrudes from the bottom of the upper precast column 100, and the longitudinal rib 211 of the lower precast column 200 The upper part extends into the cast-in-place node area 300 and extends to the top of the cast-in-place node area 300, and the connection node is constructed by the above-mentioned prefabricated column connection node construction method.

下层预制柱200的纵筋211会伸入现浇节点区300,由此使得下层预制柱200顶部与在下层预制柱200顶部的结构形成固接;上层预制柱100底部的定位部件插入模板410与现浇节点区300顶面所形成的容纳空间440中,被容纳空间440中的混凝土砂浆420包裹连接,使得上层预制柱100的底部与下层预制柱200顶部的结构形成铰接,相比于固接而言,铰接的形式对节点施工质量的要求降低了,使得施工现场中上层预制柱100装配过程的施工质量更容易保证。而且,相比于底部和顶部都实现固接的预制柱而言,底部铰接、顶部固接的预制柱具有更好的耗能特性,可以更好地应用于抗震设计中。The longitudinal reinforcement 211 of the lower precast column 200 will extend into the cast-in-place node area 300, thereby making the top of the lower precast column 200 and the structure on the top of the lower precast column 200 form a fixed connection; the positioning part at the bottom of the upper precast column 100 is inserted into the template 410 and The accommodation space 440 formed on the top surface of the cast-in-place node area 300 is wrapped and connected by the concrete mortar 420 in the accommodation space 440, so that the bottom of the upper prefabricated column 100 and the structure at the top of the lower prefabricated column 200 form a hinge joint, compared to the fixed joint In other words, the hinged form reduces the requirements on the joint construction quality, which makes it easier to guarantee the construction quality of the middle and upper prefabricated columns 100 assembly process on the construction site. Moreover, compared with the prefabricated columns whose bottom and top are fixed, the prefabricated columns with hinged bottom and fixed top have better energy dissipation characteristics and can be better applied in seismic design.

图7是本实施例另一个施工完成后的装配式柱连接节点示意图。如图7所示,在一个可选的实施例中,上层预制柱100还设有凸块113,凸块113伸出上层预制柱100的底部,凸块113包裹伸出上层预制柱100底部的定位部件。具体地,定位部件中上层预制柱100的纵筋111向内弯折后伸出上层预制柱100底部的部分伸入凸块113内部。凸块113可以更好地保护定位部件,并且更方便插入容纳空间440中的混凝土砂浆420。Fig. 7 is a schematic diagram of another assembled column connection node after construction of this embodiment is completed. As shown in Figure 7, in an optional embodiment, the upper prefabricated column 100 is also provided with a protrusion 113, the protrusion 113 protrudes from the bottom of the upper prefabricated column 100, and the protruding protrusion 113 wraps the part protruding from the bottom of the upper prefabricated column 100. Positioning parts. Specifically, the longitudinal ribs 111 of the upper prefabricated column 100 in the positioning component are bent inwardly, and the part protruding from the bottom of the upper precast column 100 extends into the inside of the protrusion 113 . The protrusion 113 can better protect the positioning component, and it is more convenient to insert the concrete mortar 420 in the receiving space 440 .

显然,本发明的上述实施例仅仅是为清楚地说明本发明技术方案所作的举例,而并非是对本发明的具体实施方式的限定。凡在本发明权利要求书的精神和原则之内所作的任何修改、等同替换和改进等,均应包含在本发明权利要求的保护范围之内。Apparently, the above-mentioned embodiments of the present invention are only examples for clearly illustrating the technical solution of the present invention, rather than limiting the specific implementation manner of the present invention. Any modification, equivalent replacement and improvement made within the spirit and principle of the claims of the present invention shall be included in the protection scope of the claims of the present invention.

Claims (6)

1.一种装配式柱连接节点施工方法,其特征在于,包括:1. A construction method for a prefabricated column connection node, characterized in that, comprising: 在下层预制柱的顶部浇筑和养护现浇节点区;Pour and maintain the cast-in-place node area on the top of the lower prefabricated column; 在所述现浇节点区的顶部,并围绕所述下层预制柱纵筋伸出现浇节点区顶部的部分套设模板,所述模板与所述现浇节点区的顶面形成敞口向上的可浇灌混凝土砂浆的容纳空间;On the top of the cast-in-place node area, a formwork is set around the part of the lower precast column longitudinal reinforcement protruding from the top of the cast-in-place node area, and the formwork and the top surface of the cast-in-place node area form an open and upward The accommodation space for pourable concrete mortar; 通过所述敞口向所述容纳空间浇灌混凝土砂浆;pouring concrete mortar into the accommodation space through the opening; 通过所述敞口将伸出上层预制柱底部的定位部件对准插入所述混凝土砂浆,将上层预制柱底部支承在所述模板的顶部;Align and insert the positioning parts protruding from the bottom of the upper prefabricated column through the opening into the concrete mortar, and support the bottom of the upper prefabricated column on the top of the template; 养护所述混凝土砂浆;curing the concrete mortar; 在下层预制柱的顶部浇筑和养护现浇节点区,包括:Pour and maintain the cast-in-place node area on top of the lower prefabricated columns, including: 对下层预制柱纵筋伸出所述下层预制柱的顶部且伸入现浇节点区的部分箍设箍筋;Stirrups are set on the part where the longitudinal reinforcement of the lower prefabricated column protrudes from the top of the lower prefabricated column and extends into the cast-in-place node area; 浇筑所述现浇节点区;Pouring the cast-in-place node area; 养护所述现浇节点区;Maintaining the cast-in-place node area; 通过所述敞口向所述容纳空间浇灌混凝土砂浆,包括:pouring concrete mortar into the accommodation space through the opening, including: 通过所述敞口向所述容纳空间浇灌混凝土砂浆,使所述容纳空间的混凝土砂浆在所述定位部件插入时会溢出;pouring concrete mortar into the accommodation space through the opening, so that the concrete mortar in the accommodation space will overflow when the positioning component is inserted; 所述定位部件包括所述上层预制柱纵筋向内弯折后伸出所述上层预制柱底部的部分,所述定位部件插入所述混凝土砂浆的深度大于或等于满足所述上层预制柱纵筋的锚固要求的最小长度。The positioning part includes the part that protrudes from the bottom of the upper precast column after the longitudinal reinforcement of the upper precast column is bent inward, and the depth of the positioning part inserted into the concrete mortar is greater than or equal to satisfy the requirements of the longitudinal reinforcement of the upper precast column. The minimum length required for anchorage. 2.根据权利要求1所述的一种装配式柱连接节点施工方法,其特征在于,在通过所述敞口将伸出上层预制柱底部的定位部件对准插入所述混凝土砂浆之前,还包括:2. The construction method of a prefabricated column connection node according to claim 1, characterized in that, before aligning and inserting the positioning parts protruding from the bottom of the upper prefabricated column through the opening into the concrete mortar, further comprising: : 在伸出上层预制柱底部的定位部件箍设抗剪钢筋;Set shear reinforcement hoops on the positioning parts protruding from the bottom of the upper prefabricated column; 或者,在所述现浇节点区的顶部,并围绕所述下层预制柱纵筋伸出现浇节点区顶部的部分套设模板之前,还包括:Or, before setting the formwork on the top of the cast-in-place node area and around the part of the lower precast column longitudinal reinforcement protruding from the top of the cast-in-place node area, it also includes: 在下层预制柱的纵筋伸出现浇节点区顶部的部分箍设抗剪钢筋。The shear reinforcement is hooped at the top of the cast-in-place node area where the longitudinal reinforcement of the lower prefabricated column extends. 3.根据权利要求1所述的一种装配式柱连接节点施工方法,其特征在于,所述模板的高度大于或等于定位部件的高度与保护所述定位部件的保护层厚度之和。3. The construction method of a prefabricated column connection node according to claim 1, wherein the height of the template is greater than or equal to the sum of the height of the positioning part and the thickness of the protective layer protecting the positioning part. 4.根据权利要求1所述的一种装配式柱连接节点施工方法,其特征在于,在所述现浇节点区的顶部,并围绕所述下层预制柱伸出现浇节点区顶部的纵筋套设模板之后,通过所述敞口向所述容纳空间浇灌混凝土砂浆之前,还包括:4. The construction method of a prefabricated column connection node according to claim 1, characterized in that, at the top of the cast-in-place node area, and around the lower prefabricated column, extend the longitudinal reinforcement at the top of the cast-in-place node area After setting the formwork, before pouring concrete mortar into the accommodation space through the opening, it also includes: 通过支撑固定所述模板的位置;fixing the position of the formwork by supports; 在养护所述混凝土砂浆之后,还包括:After curing the concrete mortar, also include: 撤走所述支撑,并在所述模板为可拆卸时,拆卸所述模板。The supports are removed and, when the formwork is detachable, the formwork is disassembled. 5.根据权利要求1所述的一种装配式柱连接节点施工方法,其特征在于,在下层预制柱的顶部浇筑和养护现浇节点区之后,通过所述敞口向所述容纳空间浇灌混凝土砂浆之前,还包括:5. The construction method of a prefabricated column connection node according to claim 1, characterized in that, after the top of the lower prefabricated column is poured and the cast-in-situ node area is maintained, concrete is poured into the accommodation space through the opening Before the mortar, also include: 对所述现浇节点区的顶面进行拉毛。The top surface of the cast-in-place node area is roughened. 6.一种装配式柱连接节点,包括上层预制柱、下层预制柱,所述上层预制柱和所述下层预制柱分别设有纵筋和箍筋,所述上层预制柱与所述下层预制柱之间设有现浇节点区,其特征在于,所述上层预制柱设有定位部件,所述的定位部件伸出所述上层预制柱的底部;所述下层预制柱纵筋的上部伸入所述现浇节点区并伸出所述现浇节点区的顶部,所述连接节点采用如权利要求1至5任一项所述的装配式柱连接节点施工方法进行施工。6. An assembled column connection node, comprising an upper prefabricated column and a lower prefabricated column, the upper prefabricated column and the lower prefabricated column are respectively provided with longitudinal bars and stirrups, the upper prefabricated column and the lower prefabricated column There is a cast-in-place node area between them, and it is characterized in that the upper prefabricated column is provided with a positioning part, and the positioning part protrudes from the bottom of the upper precast column; the upper part of the longitudinal reinforcement of the lower prefabricated column extends into the The cast-in-place node area protrudes from the top of the cast-in-place node area, and the connection node is constructed by using the construction method of the fabricated column connection node as described in any one of claims 1 to 5.
CN202210625463.1A 2022-06-02 2022-06-02 Construction method of assembled column connecting joint and connecting joint Active CN114809772B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202210625463.1A CN114809772B (en) 2022-06-02 2022-06-02 Construction method of assembled column connecting joint and connecting joint

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202210625463.1A CN114809772B (en) 2022-06-02 2022-06-02 Construction method of assembled column connecting joint and connecting joint

Publications (2)

Publication Number Publication Date
CN114809772A CN114809772A (en) 2022-07-29
CN114809772B true CN114809772B (en) 2023-03-28

Family

ID=82521258

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202210625463.1A Active CN114809772B (en) 2022-06-02 2022-06-02 Construction method of assembled column connecting joint and connecting joint

Country Status (1)

Country Link
CN (1) CN114809772B (en)

Families Citing this family (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN116695953A (en) * 2023-05-31 2023-09-05 曹大燕 Hollow steel skeleton prefabricated column with built-in combined metal template

Family Cites Families (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2980793B2 (en) * 1993-07-06 1999-11-22 株式会社奥村組 Column / beam joining method
JPH11343665A (en) * 1998-04-03 1999-12-14 Daisue Construction Co Ltd Hollow precast concrete column and its construction method
CN108265824A (en) * 2018-01-24 2018-07-10 西安建筑科技大学 A kind of high ductility concrete beam and column node of assembled and connection method
CN112112263B (en) * 2020-07-24 2024-12-10 广东省建科建筑设计院有限公司 Prefabricated concrete beam-column joint using precast concrete pipe piles and construction method
CN113216409A (en) * 2021-04-25 2021-08-06 广东省建科建筑设计院有限公司 Connecting structure of precast concrete tubular pile column with diagonal bracing and hollow floor or flat floor
CN113638491A (en) * 2021-06-25 2021-11-12 中建五局华东建设有限公司 Assembled beam-column connection node and construction method thereof

Also Published As

Publication number Publication date
CN114809772A (en) 2022-07-29

Similar Documents

Publication Publication Date Title
CN209891048U (en) Connecting structure of precast concrete pier stud and capping beam
CN112922231A (en) Fabricated concrete beam-column joint and construction method thereof
KR101903628B1 (en) Precast Double Wall Structure with Enhanced Seismic Performance and Construction method thereof
CN108149585B (en) Splicing structure and splicing method of pier column segments of a prefabricated assembled bridge pier
CN101672007A (en) Constructing method of precast pier footing for bridge
KR100770574B1 (en) Prestressed steel reinforced concrete composite ramen bridge and construction method
CN106437031A (en) Multi-layer prefabricated column with corbels formed at one time and its preparation method and construction method
CN212358846U (en) A prefabricated concrete composite beam
KR101229263B1 (en) Slab-type box girder with a vertical connecting structure made by precast concrete and method constructing the bridge thereof
CN114809772B (en) Construction method of assembled column connecting joint and connecting joint
KR20060041078A (en) Steel casting continuous composite bridge with precast concrete deck and construction method
CN111270691A (en) Side slope prefabricated frame lattice beam structure and construction method
KR101339367B1 (en) Fabrication and reinforcing method for pre-flex girder
CN108678253A (en) A kind of method of construction of floor structure with ribbing and floor structure with ribbing
CN118601225A (en) A construction method for hollow thin-walled pier diaphragm
CN110512728A (en) A prefabricated building superimposed lotus root beam-column joint structure and its construction method
KR100203012B1 (en) Executing method of building works used a pc slab
CN212405183U (en) Prefabricated frame lattice beam structure of side slope
CN114922495B (en) Prefabricated post of rapid Assembly formula and connected node thereof
CN207812309U (en) A kind of splicing construction of the pier stud segment of precast assembly bridge pier
CN114934706B (en) An assembled prefabricated column with a convex part and its connection node
CN114086459B (en) A steel-concrete composite beam structure and construction method
JP2003041516A (en) Integral structure of upper and lower parts of continuous girder bridge and method of constructing it
KR101389819B1 (en) Continuous prestressed concrete girder structure and construction method thereof
CN119825165B (en) Assembled built-in reinforcing structure with multiple-effect connecting nodes and reinforcing method

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant