JP2962931B2 - Dam Inflow Prediction Method - Google Patents

Dam Inflow Prediction Method

Info

Publication number
JP2962931B2
JP2962931B2 JP12994792A JP12994792A JP2962931B2 JP 2962931 B2 JP2962931 B2 JP 2962931B2 JP 12994792 A JP12994792 A JP 12994792A JP 12994792 A JP12994792 A JP 12994792A JP 2962931 B2 JP2962931 B2 JP 2962931B2
Authority
JP
Japan
Prior art keywords
inflow
dam
predicted
rainfall
actual
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
JP12994792A
Other languages
Japanese (ja)
Other versions
JPH05297909A (en
Inventor
真和 窪田
憲一 黒谷
秀明 桐野
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Efu Efu Shii Kk
Fuji Electric Co Ltd
Original Assignee
Efu Efu Shii Kk
Fuji Electric Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Efu Efu Shii Kk, Fuji Electric Co Ltd filed Critical Efu Efu Shii Kk
Priority to JP12994792A priority Critical patent/JP2962931B2/en
Publication of JPH05297909A publication Critical patent/JPH05297909A/en
Application granted granted Critical
Publication of JP2962931B2 publication Critical patent/JP2962931B2/en
Anticipated expiration legal-status Critical
Expired - Fee Related legal-status Critical Current

Links

Landscapes

  • Flow Control (AREA)
  • Feedback Control In General (AREA)

Description

【発明の詳細な説明】DETAILED DESCRIPTION OF THE INVENTION

【0001】[0001]

【産業上の利用分野】本発明は、ダム流入量予測方法に
関し、詳しくは、上流ダムから計画的に放流されている
河川において、降雨による流量の増加も含めて下流ダム
への流入量を予測すると共に、必要に応じて降雨による
予測流入量の補正も可能にしたダム流入量予測方法に関
する。
BACKGROUND OF THE INVENTION 1. Field of the Invention The present invention relates to a method for predicting the inflow of a dam, and more particularly, to the prediction of the inflow to a downstream dam, including an increase in flow due to rainfall, in a river that is systematically discharged from an upstream dam. In addition, the present invention relates to a dam inflow prediction method capable of correcting a predicted inflow due to rainfall as necessary.

【0002】[0002]

【従来の技術及び発明が解決しようとする課題】従来、
ダムの放流量から下流河川での流量を計算する方法はい
くつか提案されているが、一般に上流ダムの放流点から
予測地点である下流ダムの流入点までの河川を水路とし
て表現し、これを水路底勾配・水深などを用いてモデル
化して非定常不等流方程式を解くことにより水流を求め
る方法が用いられている。しかしながら、通常、河川の
モデル化は容易ではなく、また、この方法では計算に多
くの時間を要するという問題がある。更に、降雨流出の
計算方法ないし予測誤差の修正方法には、予測精度をあ
げるためにカルマンフィルタを用い、逐次最適推定する
方法等があるが、一般に計算が複雑であるという欠点が
ある。
2. Description of the Related Art
Several methods have been proposed to calculate the discharge in the downstream river from the discharge of the dam.In general, the river from the discharge point of the upstream dam to the inflow point of the downstream dam, which is the predicted point, is expressed as a waterway, and this is expressed as a waterway. A method of obtaining a water flow by solving an unsteady non-uniform flow equation by modeling using a channel bottom gradient, water depth, and the like is used. However, there is a problem that the modeling of a river is usually not easy, and that this method requires much time for calculation. Further, as a method of calculating rainfall runoff or a method of correcting a prediction error, there is a method of sequentially and optimally using a Kalman filter in order to improve prediction accuracy, but generally has a drawback that the calculation is complicated.

【0003】本発明は上記問題点を解決するためになさ
れたもので、その目的とするところは、簡単かつ短時間
の計算により下流ダムの流入量を高精度で予測し、下流
ダムでの利用計画を有効に策定可能とすると共に上流ダ
ムにおける放水も有効に活用できるようにしたダム流入
量予測方法を提供することにある。また、本発明は、降
雨による予測流入量を逐次、補正して予測誤差を修正可
能としたダム流入量予測方法を提供することも目的とし
ている。
[0003] The present invention has been made to solve the above problems, and an object of the present invention is to predict the inflow of a downstream dam with high accuracy by a simple and short-time calculation, and to utilize the downstream dam. It is an object of the present invention to provide a method for predicting a dam inflow which enables a plan to be formulated effectively and makes effective use of water discharge at an upstream dam. Another object of the present invention is to provide a dam inflow prediction method capable of correcting a prediction error by sequentially correcting a predicted inflow due to rainfall.

【0004】[0004]

【課題を解決するための手段】上記目的を達成するた
め、第1の発明は、上流ダムから計画的に放流されてい
る河川の下流ダムにおける流入量を予測するダム流入量
予測方法において、一定時間前の実績放流量及び以後の
計画放流量と、予測計算時間間隔と、一次遅れ時定数及
び無駄時間とを用いて求めた上流ダムの放流による予測
流入量と、実績降雨量及び予測降雨量に基づきタンクモ
デルを用いて求めた降雨による予測流入量と、一定時間
前の実績流入量及び予測流入量の差に基づく基底流量と
の和により下流ダム予測流入量を求めるものである。
According to a first aspect of the present invention, there is provided a dam predicting method for predicting an inflow into a downstream dam of a river which is intentionally discharged from an upstream dam. Predicted inflows from upstream dams, using actual discharges before and after planned discharges, estimated calculation time intervals, first-order lag time constants and dead time, actual rainfall and predicted rainfall Is calculated based on the sum of the predicted inflow due to rainfall obtained by using the tank model based on the above and the base flow based on the difference between the actual inflow and the predicted inflow before a certain period of time.

【0005】第2の発明は、上記第1の発明において、
予測時点における実績流入量と予測流入量との差に応
じ、タンクモデルを用いて求めた降雨による予測流入量
を補正するものである。
According to a second aspect, in the first aspect,
In accordance with the difference between the actual inflow amount and the predicted inflow amount at the time of the prediction, the predicted inflow amount due to rainfall obtained using the tank model is corrected.

【0006】[0006]

【作用】第1の発明においては、まず、(1)上流ダム
における、予測時点から一定時間前の実績放流量及びこ
れから放流しようとする計画放流量を含むq(t)を用い
て、上流ダムからの放流により生じる下流ダムの予測流
入量U(t)を、一次遅れ+無駄時間に近似し、数式1を
用いて計算時間間隔Δt毎に計算する。
According to the first aspect of the present invention, first, (1) the upstream dam is determined by using q (t) including the actual discharge amount and the planned discharge amount to be discharged from the upstream dam at a certain time before the predicted time. The estimated inflow amount U (t) of the downstream dam caused by the discharge from the water is approximated to the first-order lag + dead time, and is calculated for each calculation time interval Δt using Expression 1.

【0007】[0007]

【数1】 U(t+Δt)=U(t)+(Δt/T){q(t−L)−U(t)}U (t + Δt) = U (t) + (Δt / T) {q (t−L) −U (t)}

【0008】ここで、Tは一次遅れ時定数、Lは上流ダ
ムからの水流が下流ダムに影響するまでの無駄時間であ
る。これらを下流ダムの予測流入量U(t)の関数として
過去の実績データから近似曲線を作成し、それらのデー
タを記憶装置に記憶させておく。なお、計算時間間隔Δ
tは一次遅れ時定数Tよりも十分小さくとる。
Here, T is a first-order lag time constant, and L is a dead time until the water flow from the upstream dam affects the downstream dam. An approximate curve is created from these past data as a function of the predicted inflow amount U (t) of the downstream dam, and the data is stored in a storage device. The calculation time interval Δ
t is set sufficiently smaller than the first-order lag time constant T.

【0009】(2)過去の実績降雨量とこれからの予
測降雨量により、タンクモデルを用いて降雨による下流
ダムの予測流入量S(t)を計算時間間隔Δt毎に計算す
る。ここで、タンクモデルとは図3のように直列に配置
された複数段のタンクにより表わされ、時間毎の降雨量
が最上段のタンクの上方から入力される。1段目のタン
クに入力された降雨量はこのタンクに貯留し、貯留して
いる高さ(流出高)と各孔の高さとの差に各孔毎の流出
係数を乗じて側面の孔から流出する。これらの側面の孔
からの流出量は、1段目のタンクによる下流への流出量
である。また、底面の孔から流出した水は、更に下段
(2段目)のタンクへ浸透する。
(2) A predicted inflow amount S (t) of the downstream dam due to rainfall is calculated for each calculation time interval Δt by using a tank model based on the past actual rainfall amount and the predicted rainfall amount. Here, the tank model is represented by a plurality of tanks arranged in series as shown in FIG. 3, and a rainfall amount for each time is input from above the uppermost tank. The rainfall input to the first tank is stored in this tank, and the difference between the stored height (outflow height) and the height of each hole is multiplied by the outflow coefficient of each hole, and the rainfall amount from the side hole is used. leak. The outflow from these side holes is the outflow downstream by the first tank. In addition, the water flowing out from the hole at the bottom permeates into the lower (second) tank.

【0010】このようにして、すべてのタンクの側面の
孔からの流出量の和が流出高となり、これに流域面積を
乗じて下流ダムへの流入量とする。上段のタンクの側面
の孔からの流出ほど降雨後の時間遅れが短く、下段のタ
ンクの側面の孔からの流出ほど時間遅れが大きくなる。
タンクの段数は通常、2段〜4段にとる。なお、図3に
おいて、XA,XB,XCは各タンクの流出高、HA
1,HA2,HB,HCは各タンクの側面の孔の高さ、
A1,A2,A3,B1,C1は各タンクの側面の孔の
流出係数、A0,B0,C0は各タンク底面の孔の浸透
係数である。
In this way, the sum of the outflow amounts from the holes on the side surfaces of all the tanks becomes the outflow height, which is multiplied by the area of the basin to determine the inflow amount into the downstream dam. The time delay after rainfall is shorter as the water flows out from the hole on the side surface of the upper tank, and the time delay is larger as the water flows out from the hole on the side surface of the lower tank.
The number of tanks is usually two to four. In FIG. 3, XA, XB, XC are the outflow heights of each tank, HA
1, HA2, HB, HC are the heights of the holes on the side of each tank,
A1, A2, A3, B1, and C1 are the outflow coefficients of the holes on the side surface of each tank, and A0, B0, and C0 are the permeation coefficients of the holes on the bottom surface of each tank.

【0011】上流ダムの実績放流量及び計画放流量q
(t)から、前述した一次遅れ+無駄時間により上流ダム
の放流による下流ダムの予測流入量U(t)を計算時間間
隔Δt毎に計算する。
The actual and planned discharge q of the upstream dam
From (t), the predicted inflow amount U (t) of the downstream dam due to the discharge of the upstream dam is calculated for each calculation time interval Δt by the above-described first-order lag + dead time.

【0012】前記により計算した降雨による予測流
入量S(t)と、により計算した上流ダムの放流による
下流ダムの予測流入量U(t)とを合成して下流ダム流入
量とするが、この時、予測時点から数時間前の実績流入
量と予測流入量との差の平均値を計算し、これを基底流
量Vとする。このとき、予測時点から数時間前にタンク
モデルからの流出がなければ降雨の影響は受けていない
ものとしてここで計算した基底流量を用い、またこの基
底流量を保存する。予測時点から数時間前にタンクモデ
ルからの流出があれば降雨の影響を受けているものとし
て既に保存されている基底流量を用いる。
The predicted inflow S (t) due to rainfall calculated as described above and the predicted inflow U (t) of the downstream dam due to the discharge of the upstream dam calculated according to the above are combined to obtain the downstream dam inflow. At this time, the average value of the difference between the actual inflow amount and the predicted inflow amount several hours before the prediction time point is calculated, and this is set as the base flow rate V. At this time, if there is no outflow from the tank model several hours before the prediction point, the base flow rate calculated here is used assuming that the influence of rainfall has not been received, and this base flow rate is stored. If there is a runoff from the tank model several hours before the prediction point, the base flow already stored as being affected by rainfall is used.

【0013】次の数式2に示すように、前記の降雨
による予測流入量S(t)と、の上流ダム放流による予
測流入量U(t)と、の基底流量Vとの和により、最終
的な下流ダム予測流入量R(t)とする。
As shown in the following equation 2, the final flow rate S (t) due to the rainfall and the predicted flow rate U (t) due to the discharge of the upstream dam and the base flow rate V are used to calculate the final flow rate. And the downstream dam predicted inflow R (t).

【0014】[0014]

【数2】R(t)=S(t)+U(t)+V## EQU2 ## R (t) = S (t) + U (t) + V

【0015】(3)第2の発明において、実績流入量に
より予測流入量を補正する場合には、この予測時点kで
の予測流入量R(k)、実績流入量Q(k)を用いて数式3
により補正係数αを求め、時間低減関数として数式4に
示すようにタンクモデルのみにより予測計算した降雨に
よる予測流入量S(t)のみを補正し、新たな下流ダム予
測流入量とする。なお、この場合の補正計算の間隔は先
の計算時間間隔Δtよりも長いものとする。
(3) In the second invention, when the predicted inflow is corrected based on the actual inflow, the predicted inflow R (k) and the actual inflow Q (k) at the prediction time k are used. Equation 3
, And only the predicted inflow S (t) due to rain, which is predicted and calculated using only the tank model, as shown in Equation 4, as a time reduction function, is used as a new downstream dam predicted inflow. Note that the correction calculation interval in this case is longer than the previous calculation time interval Δt.

【0016】[0016]

【数3】α={Q(k)−R(k)}/S(k)Α = {Q (k) −R (k)} / S (k)

【0017】[0017]

【数4】 R(k+i)={1+αe-t/T1}S(k+i)+U(k+i)+VR (k + i) = {1 + αe- t / T1 } S (k + i) + U (k + i) + V

【0018】[0018]

【実施例】以下、図に沿って各発明の実施例を説明す
る。図1は第1の発明の実施例を示すフローチャートで
ある。まず、実績降雨量保存ファイル11内の実績降雨
量及び予測降雨量保存ファイル12内の予測降雨量を用
いて、タンクモデルにより、降雨による予測流入量S
(t)のみを計算する(ステップS1)。このとき、タン
クモデル係数ファイル14に保存されているタンクモデ
ル係数を参照する。次に、計画放流量保存ファイル13
に保存されている上流ダムの計画放流量と、図示されて
いない記憶装置内の実績放流量とを用いて、河道モデル
を用いて数式1により放流による予測流入量U(t)を計
算する(S2)。このとき、河道モデル一次遅れ時定数
ファイル15内の一次遅れ時定数T及び河道モデル無駄
時間ファイル16内の無駄時間Lを参照する。
BRIEF DESCRIPTION OF THE DRAWINGS FIG. FIG. 1 is a flowchart showing an embodiment of the first invention. First, using the actual rainfall amount in the actual rainfall amount storage file 11 and the predicted rainfall amount in the predicted rainfall amount storage file 12, a predicted inflow amount S due to rainfall is calculated by a tank model.
Only (t) is calculated (step S1). At this time, the tank model coefficient stored in the tank model coefficient file 14 is referred to. Next, the planned discharge discharge storage file 13
Using the planned discharge amount of the upstream dam stored in the storage area and the actual discharge amount in the storage device (not shown), the predicted inflow amount U (t) due to the discharge is calculated by Equation 1 using the river channel model ( S2). At this time, the primary delay time constant T in the river channel model primary delay time constant file 15 and the dead time L in the river channel model dead time file 16 are referred to.

【0019】予測時点から数時間前にタンクモデルから
の流出があれば、降雨の影響を受けているものとして基
底流量ファイル17内に既に保存されている基底流量V
を用いるため、基底流量の計算は不要となり(S3 N
O)、後述するステップS5に移る。また、予測時点か
ら数時間前にタンクモデルからの流出がなければ、降雨
の影響がないものとし、実績流入量から降雨による流入
量と放流による流入量とを差し引き、基底流量V(S3
YES,S4)とする。なお、この基底流量Vは基底
流量ファイル17に保存される。
If there is an outflow from the tank model several hours before the forecast point, the base flow rate V already stored in the base flow rate file 17 is assumed to be affected by rainfall.
, The calculation of the base flow rate becomes unnecessary (S3N
O) The process moves to step S5 described below. If there is no outflow from the tank model several hours before the prediction time point, it is assumed that there is no influence of rainfall, and the inflow amount due to rainfall and the inflow amount due to discharge are subtracted from the actual inflow amount, and the base flow rate V (S3
YES, S4). The base flow rate V is stored in the base flow rate file 17.

【0020】河道モデルの一次遅れ時定数T、無駄時間
Lは流量の関数となるので、ここで再度,予測流入量を
用いて河道モデルの計算を行い、上流ダムでの放流によ
る予測流入量U(t)を計算する(S5)。その後、降雨
による予測流入量S(t)と上流ダム放流による予測流入
量U(t)と基底流量Vとの和により、最終的な下流ダム
予測流入量R(t)を計算する(S6)。
Since the first-order lag time constant T and the dead time L of the river channel model are functions of the discharge, the river channel model is again calculated using the predicted inflow, and the predicted inflow U due to the discharge at the upstream dam is calculated again. (t) is calculated (S5). Thereafter, a final downstream dam predicted inflow R (t) is calculated from the sum of the predicted inflow S (t) due to rainfall, the predicted inflow U (t) due to upstream dam discharge, and the base flow V (S6). .

【0021】図2は、第2の発明の実施例を示すフロー
チャートである。この実施例では、計算された降雨によ
る予測流入量S(t)と放流による予測流入量U(t)と基
底流量Vとの和から予測流入量R(t)を計算し、実績流
入量保存ファイル18内の実績流入量との差に基づき補
正の要否を判断し(S41)、必要であれば(S41Y
ES)前記数式3により補正係数αを計算し、数式4に
より補正を行なう(S42)。補正が必要なければ(S
41 NO)、補正係数及び流入量の補正計算は行わ
ず、ステップS5へ移行する。
FIG. 2 is a flowchart showing an embodiment of the second invention. In this embodiment, a predicted inflow R (t) is calculated from the sum of the calculated predicted inflow S (t) due to rainfall, the predicted inflow U (t) due to discharge, and the base flow V, and the actual inflow storage is performed. Whether correction is necessary or not is determined based on the difference from the actual inflow amount in the file 18 (S41), and if necessary (S41Y).
ES) The correction coefficient α is calculated by the above equation 3, and the correction is performed by the equation 4 (S42). If no correction is needed (S
41 NO), the flow proceeds to step S5 without performing the correction calculation of the correction coefficient and the inflow amount.

【0022】なお、図4は、第1の発明の実施例による
予測結果であり、降雨の少ない時期の降雨量、上流ダム
放流量、下流ダム流入量の実績値(実線)及び予測値
(破線)を示している。降雨があるまでの流入量は、河
道モデルの一次遅れ+無駄時間で上流ダムの放流量によ
り予測流入量が計算されている。図5は、第2の発明の
実施例による予測結果であり、降雨の多い時期の降雨
量、上流ダム放流量、下流ダム流入量の実績値及び予測
値を示している。この図から明らかなように、急激な降
雨量の増加に対して本発明の補正を行うことにより、予
測値が実績値に近くなっている。図6は図5と同じ条件
で補正を行わなかった場合の予測結果であり、図のよう
な急激な雨量の増加に対しては、予測精度が悪くなって
いるのがわかる。
FIG. 4 is a prediction result according to the first embodiment of the present invention. The actual value (solid line) and the predicted value (solid line) of the rainfall, the upstream dam discharge, and the downstream dam inflow during a period of low rainfall are shown. ). For the inflow before rainfall, the predicted inflow is calculated from the discharge of the upstream dam by the first-order delay of the river channel model + the dead time. FIG. 5 shows prediction results according to the embodiment of the second invention, and shows actual values and predicted values of rainfall, upstream dam discharge, and downstream dam inflow during heavy rainfall. As is clear from this figure, the predicted value is close to the actual value by performing the correction according to the present invention for the rapid increase in rainfall. FIG. 6 shows a prediction result when the correction is not performed under the same conditions as in FIG. 5, and it can be seen that the prediction accuracy is deteriorated for a sudden increase in the amount of rain as shown in FIG.

【0023】[0023]

【発明の効果】以上のように第1の発明によれば、簡単
な計算により求めた上流ダムの放流による予測流入量
と、タンクモデルを用いて求めた降雨による予測流入量
と、基底流量とにより下流ダムにおける予測流入量を求
めることができるため、従来のように河川モデルを作成
することなく短時間で流入量を予測することができる。
これにより、下流ダムでの有効な利用計画を策定でき、
また、上流ダムからの放水を有効に活用することができ
る。また、第2の発明によれば、上記効果に加えて、予
測流入量を逐次補正することで予測精度を大幅に高める
ことができ、しかも、従来のカルマンフィルタ等を用い
る方法に比べて計算を簡略化できる等の効果がある。
As described above, according to the first aspect of the present invention, the predicted inflow due to the discharge of the upstream dam obtained by a simple calculation, the predicted inflow due to rainfall obtained by using a tank model, and the base flow rate As a result, the predicted inflow amount at the downstream dam can be obtained, so that the inflow amount can be predicted in a short time without creating a river model as in the related art.
As a result, an effective utilization plan for downstream dams can be formulated,
In addition, water discharge from upstream dams can be used effectively. According to the second invention, in addition to the above effects, the prediction accuracy can be greatly improved by sequentially correcting the predicted inflow amount, and the calculation is simplified as compared with the conventional method using a Kalman filter or the like. There is an effect that it can be made.

【図面の簡単な説明】[Brief description of the drawings]

【図1】第1の発明の実施例を示すフローチャートであ
る。
FIG. 1 is a flowchart showing an embodiment of the first invention.

【図2】第2の発明の実施例を示すフローチャートであ
る。
FIG. 2 is a flowchart showing an embodiment of the second invention.

【図3】タンクモデルの説明図である。FIG. 3 is an explanatory diagram of a tank model.

【図4】第1の発明の実施例による予測結果を示す図で
ある。
FIG. 4 is a diagram showing a prediction result according to the embodiment of the first invention.

【図5】第2の発明の実施例による予測結果を示す図で
ある。
FIG. 5 is a diagram showing a prediction result according to the embodiment of the second invention.

【図6】図5と同一条件で降雨による予測流入量を補正
しなかった場合の予測結果を示す図である。
FIG. 6 is a diagram illustrating a prediction result when the predicted inflow amount due to rainfall is not corrected under the same conditions as in FIG. 5;

【符号の説明】[Explanation of symbols]

11 実績降雨量保存ファイル 12 予測降雨量保存ファイル 13 計画放流量保存ファイル 14 タンクモデル係数ファイル 15 河道モデル一次遅れ時定数ファイル 16 河道モデル無駄時間ファイル 17 基底流量ファイル 18 実績流入量保存ファイル 11 Actual rainfall storage file 12 Predicted rainfall storage file 13 Planned discharge discharge storage file 14 Tank model coefficient file 15 River channel model first-order lag time constant file 16 River channel model dead time file 17 Base flow rate file 18 Actual inflow storage file

───────────────────────────────────────────────────── フロントページの続き (72)発明者 桐野 秀明 東京都日野市富士町1番地 富士ファコ ム制御株式会社内 (56)参考文献 特開 昭50−73430(JP,A) 特開 昭59−154504(JP,A) 特開 平1−191210(JP,A) 特開 平5−125713(JP,A) (58)調査した分野(Int.Cl.6,DB名) B05B 17/00 - 17/02 B05B 11/00 - 13/04 E02B 7/00 B05D 7/06 ──────────────────────────────────────────────────続 き Continuation of the front page (72) Inventor Hideaki Kirino 1 Fuji Town, Hino City, Tokyo Inside Fuji Facom Control Co., Ltd. (56) References JP-A-50-73430 (JP, A) JP-A-59- 154504 (JP, A) JP-A-1-191210 (JP, A) JP-A-5-125713 (JP, A) (58) Fields investigated (Int. Cl. 6 , DB name) B05B 17/00-17 / 02 B05B 11/00-13/04 E02B 7/00 B05D 7/06

Claims (2)

(57)【特許請求の範囲】(57) [Claims] 【請求項1】 上流ダムから計画的に放流されている河
川の下流ダムにおける流入量を予測するダム流入量予測
方法において、 一定時間前の実績放流量及び以後の計画放流量と、予測
計算時間間隔と、一次遅れ時定数及び無駄時間とを用い
て求めた上流ダムの放流による予測流入量と、 実績降雨量及び予測降雨量に基づきタンクモデルを用い
て求めた降雨による予測流入量と、 一定時間前の実績流入量及び予測流入量の差に基づく基
底流量と、 の和により下流ダム予測流入量を求めることを特徴とす
るダム流入量予測方法。
1. A dam inflow predicting method for predicting an inflow into a downstream dam of a river that is systematically discharged from an upstream dam, comprising: an actual discharge before and after a predetermined time; The estimated inflow due to the discharge of the upstream dam calculated using the interval, the first-order lag time constant and the dead time, and the estimated inflow due to the rain obtained using the tank model based on the actual rainfall and the predicted rainfall. A dam inflow predicting method, characterized in that a downstream dam predicted inflow is obtained by the sum of a base flow based on a difference between an actual inflow and a predicted inflow before time, and
【請求項2】 請求項1記載のダム流入量予測方法にお
いて、 予測時点における実績流入量と予測流入量との差に応
じ、タンクモデルを用いて求めた降雨による予測流入量
を補正することを特徴とするダム流入量予測方法。
2. The dam inflow predicting method according to claim 1, wherein the predicted inflow due to rainfall obtained by using the tank model is corrected according to a difference between the actual inflow and the predicted inflow at the time of the prediction. Characteristic dam inflow prediction method.
JP12994792A 1992-04-23 1992-04-23 Dam Inflow Prediction Method Expired - Fee Related JP2962931B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP12994792A JP2962931B2 (en) 1992-04-23 1992-04-23 Dam Inflow Prediction Method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP12994792A JP2962931B2 (en) 1992-04-23 1992-04-23 Dam Inflow Prediction Method

Publications (2)

Publication Number Publication Date
JPH05297909A JPH05297909A (en) 1993-11-12
JP2962931B2 true JP2962931B2 (en) 1999-10-12

Family

ID=15022376

Family Applications (1)

Application Number Title Priority Date Filing Date
JP12994792A Expired - Fee Related JP2962931B2 (en) 1992-04-23 1992-04-23 Dam Inflow Prediction Method

Country Status (1)

Country Link
JP (1) JP2962931B2 (en)

Families Citing this family (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2010037770A (en) * 2008-08-04 2010-02-18 Hitachi Ltd Inflow rate predicting method and dam management control system
JP5208983B2 (en) * 2010-03-02 2013-06-12 中国電力株式会社 Reservoir operation plan creation method and apparatus
CN111598354B (en) * 2020-05-26 2023-04-21 河南郑大水利科技有限公司 Method for predicting current day runoff of small reservoir

Also Published As

Publication number Publication date
JPH05297909A (en) 1993-11-12

Similar Documents

Publication Publication Date Title
CN107330274B (en) Consider that the earth and rockfill dam group control step sluicing of upstream dam bursting flood completely determines method
CN107330621A (en) A kind of multi-reservoir outlet structure escape works evaluation method for failure based on Bayesian network
US8914266B2 (en) Systems and methods for modeling floods
JP2023009541A (en) Rainwater inflow amount prediction device, rainwater inflow amount prediction method, and computer program
JP2962931B2 (en) Dam Inflow Prediction Method
CN110096670B (en) Dynamic calculation method for reducing peak flow of regulating reservoir
CN113361798B (en) Reservoir flood control scheduling method, system and storage medium based on pre-discharge index
CN114386882A (en) Over-standard flood risk regulation and control method based on mutual feedback of water engineering scheduling effects
JP3839361B2 (en) Rainwater runoff coefficient prediction method, rainwater inflow prediction method, rainwater runoff coefficient prediction program, and rainwater inflow forecast program
JP2000276235A (en) Wide area rainwater drainage system supporting device
Lindley et al. Hydraulic simulation techniques incorporated in the surface impoundment element of WEPP
JP4190788B2 (en) Inundation depth prediction system, inundation depth prediction method, inundation depth prediction program and recording medium recording inundation depth prediction program
JPH052768B2 (en)
CN114357895B (en) State machine-based volume adaptive flood simulation method for river and lake flood diversion and accumulation areas
JPH06117888A (en) Method for calculating amount of water discharged weir
Knapp et al. Effect of stratton dam operation on flood control along the Fox River and Fox chain of lakes
JP2001355222A (en) Water reservoir operating system based on discharge function
Lee et al. A post-operation audit of the Tai Hang Tung Storage Scheme
JPS58189712A (en) Method for controlling pumping-up volume of sewage pump
JPS6323391B2 (en)
JPH07138930A (en) Planed maximum dam water discharge control method device, and dam water discharge facilities using the method and device
Jones Application of mixed-integer programming for flood control in the Sacramento valley: insights & limitations
CN109298468A (en) A kind of rainfall runoff and river-level traffic forecast DSS
JP3237274B2 (en) Rainwater pump control method
Lier Modeling of ice dams in the Karasjohka River

Legal Events

Date Code Title Description
A01 Written decision to grant a patent or to grant a registration (utility model)

Free format text: JAPANESE INTERMEDIATE CODE: A01

Effective date: 19990727

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20070806

Year of fee payment: 8

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20080806

Year of fee payment: 9

LAPS Cancellation because of no payment of annual fees