JP2958717B2 - Guide pipe for compacted pile - Google Patents
Guide pipe for compacted pileInfo
- Publication number
- JP2958717B2 JP2958717B2 JP6652191A JP6652191A JP2958717B2 JP 2958717 B2 JP2958717 B2 JP 2958717B2 JP 6652191 A JP6652191 A JP 6652191A JP 6652191 A JP6652191 A JP 6652191A JP 2958717 B2 JP2958717 B2 JP 2958717B2
- Authority
- JP
- Japan
- Prior art keywords
- pile
- guide pipe
- tip
- return plate
- compacted
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired - Fee Related
Links
Landscapes
- Placing Or Removing Of Piles Or Sheet Piles, Or Accessories Thereof (AREA)
- Piles And Underground Anchors (AREA)
Description
【0001】[0001]
【産業上の利用分野】この発明は、場所打ちコンクリー
ト杭や連続地中壁又は既製コンクリート杭を使用した埋
込み杭等の構築において、その先端支持力を増強する締
め固め杭を先端地盤(孔底地盤)の中へ貫入するために
使用されるガイドパイプに関する。BACKGROUND OF THE INVENTION The present invention relates to a cast-in-place concrete pile, a continuous underground wall, or an embedded pile using a ready-made concrete pile. And a guide pipe used to penetrate into the ground.
【0002】[0002]
【従来の技術】従来、場所打ちコンクリート杭などの構
築においては、掘削によって先端地盤が緩み先端支持力
が低下することが問題とされ、特開昭63−61241
9号公報に記載された施工法では、打設コンクリートが
強度を発現した後に先端地盤中へ締め固め杭を貫入し、
先端地盤を締め固めて支持力を増強する工法が提案され
ている。2. Description of the Related Art Conventionally, in the construction of cast-in-place concrete piles and the like, there has been a problem that excavation loosens the tip ground and lowers the tip supporting force.
In the construction method described in Japanese Patent Publication No. 9, after the cast concrete has developed strength, the compacted pile penetrates into the tip ground,
A construction method has been proposed in which the tip ground is compacted to increase the bearing capacity.
【0003】[0003]
【本発明が解決しようとする課題】上記した公知の施工
法は、躯体コンクリートが強度を発現するのを待って締
め固め杭を先端地盤中へ貫入する方法であるため、躯体
コンクリートの養生期間だけ工期が長びく欠点がある。
一方、打設した躯体コンクリート等がガイドパイプ内へ
逆流して固まることのないように、ガイドパイプの先端
開口部を締め固め杭によって破断できる程度の強度を持
つ蓋板で水密的に密閉した構成のガイドパイプが開発さ
れている(特願平2−341238号)。しかし、蓋板
の加工が面倒で製作費用が高くつく。のみならず、先端
を密閉された中空のガイドパイプを掘削孔中に挿入し沈
設しようとすると、泥水による浮力が抵抗力として働
く。特に、既製コンクリート杭を使った埋め込み杭の施
工においては、掘削孔中の泥水等を既製コンクリート杭
がまるでピストンの如くに圧縮しながら建て込まれるた
め、浮力以上に大きな水圧等が抵抗力として働き、作業
を困難ならしめる問題がある。The above-mentioned known construction method is a method in which the compacted pile penetrates into the tip ground after the stiffness of the skeletal concrete has developed, so that only the curing period of the stiffened concrete is required. There is a disadvantage that the construction period is long.
On the other hand, in order to prevent the poured concrete from flowing back into the guide pipe and solidifying, the opening at the tip of the guide pipe is tightly sealed with a lid plate that is strong enough to be broken by a pile. (Japanese Patent Application No. 2-341238) has been developed. However, the processing of the cover plate is troublesome and the production cost is high. In addition, when a hollow guide pipe with a closed end is inserted into a borehole to attempt to sink it, buoyancy due to muddy water acts as resistance. In particular, in the construction of embedded piles using ready-made concrete piles, since the pre-made concrete piles are built while compressing muddy water etc. in the drilling hole like a piston, water pressure etc. greater than buoyancy acts as resistance. There is a problem that makes the work difficult.
【0004】そこで、図6のように既製杭aに取り付け
たガイドパイプbの先端開口が全面開放されたものも開
発されている(特願平2−407579号)。しかし、
この構成だと締め固め杭dを貫入した際に生ずる排土c
がガイドパイプb内に侵入する(図6参照)。この排土
cは後でガイドパイプb内に中詰めされるセメントミル
クの品質を劣化させ、本体杭に許容限度の荷重が負荷さ
れたときは許容限度荷重のはるか手前で前記劣化したセ
メントミルクが破壊され支持力の低下をきたすという問
題があり、解決すべき課題になっている。[0004] Therefore, a guide pipe b attached to a ready-made stake a, as shown in FIG. 6, has been developed in which the front end opening is entirely open (Japanese Patent Application No. 2-407579). But,
With this configuration, the earth removal c generated when the compaction pile d penetrates
Enter the guide pipe b (see FIG. 6). This earth removal c deteriorates the quality of the cement milk which is later packed in the guide pipe b, and when the load of the allowable limit is applied to the main body pile, the deteriorated cement milk becomes far before the allowable load. There is a problem of being destroyed and lowering the bearing capacity, which is a problem to be solved.
【0005】[0005]
【課題を解決するための手段】上記従来技術の課題を解
決するための手段として、この発明に係る締め固め杭用
のガイドパイプは、図面に実施例を示しているように、
場所打ちコンクリート杭などの掘削孔底地盤中へ貫入さ
れる締め固め杭6を地上から孔底まで案内するガイドパ
イプであって、締め固め杭6の外径より少し大きい内径
を有し、杭用孔2等の深さと同等以上の長さを有する鉄
管等で構成され、当該パイプ4の先端開口部を遮蔽する
土返し板10が設置され、この土返し板10には中心部
に締め固め杭6の先端径と略同径の通孔11が設けられ
ていると共に中心部から放射状配置に複数本の切込み溝
9が形成されており、土返し板10は締め固め杭6によ
り前記切込み溝9に沿って破断可能に構成されているこ
とを特徴とする(図1と図2参照)。As a means for solving the above-mentioned problems of the prior art, a guide pipe for a compaction pile according to the present invention is, as shown in the drawings, an embodiment.
A guide pipe for guiding the compacted pile 6 penetrating into the bottom of the excavation hole such as a cast-in-place concrete pile from the ground to the bottom of the hole, having an inner diameter slightly larger than the outer diameter of the compacted pile 6, A soil return plate 10 that is formed of an iron pipe or the like having a length equal to or greater than the depth of the hole 2 or the like and that shields the opening at the tip of the pipe 4 is installed. 6, a plurality of cut grooves 9 are formed radially from the center, and the soil return plate 10 is formed by the compaction pile 6 to form the cut grooves 9. (See FIGS. 1 and 2).
【0006】本発明のガイドパイプはまた、中空構造の
既製杭14の先端金具13に、締め固め杭6の外径より
少し大きい内径の短いガイドパイプ4’が既製杭14の
中空部14aと同心配置に接合されており、このガイド
パイプ4’の先端部4bは前記先端金具13から若干の
長さhだけ突き出され、当該ガイドパイプ4’の先端開
口部を遮蔽する土返し板10が設置されており、この土
返し板10には中心部に締め固め杭6の先端径と略同径
の通孔11が設けられていると共に中心部から放射状配
置に複数本の切込み溝9が形成されており、土返し板1
0は締め固め杭6により前記切込み溝9に沿って破断可
能に構成されていることモ特徴とする(図4A、B参
照)。In the guide pipe of the present invention, a short guide pipe 4 ′ having an inner diameter slightly larger than the outer diameter of the compacted pile 6 is concentric with the hollow portion 14 a of the ready-made pile 14 at the end fitting 13 of the hollow pile 14. The guide pipe 4 'has a tip 4b protruding from the tip fitting 13 by a slight length h, and an earth return plate 10 for shielding the tip opening of the guide pipe 4' is installed. The soil return plate 10 has a through hole 11 having a diameter substantially equal to the diameter of the tip of the compaction pile 6 at the center and a plurality of cut grooves 9 formed radially from the center. Ori, backplate 1
No. 0 is characterized in that it can be broken along the cut groove 9 by the compaction pile 6 (see FIGS. 4A and 4B).
【0007】上記の各発明において、切込み溝9は土返
し板10の外側面(下面)に形成されていること、ガイ
ドパイプ4は、場所打ちコンクリート杭2又は連続地中
壁の鉄筋3に所要の配置で所要本数だけ一体的に付設さ
れていること(図3)、ガイドパイプ4’の上端部は漏
斗形状に拡径されていること(図4A,B)、もそれぞ
れ特徴とする。さらに本発明のガイドパイプは、 イ) 中空構造で大径の既製杭5の中空部5a内に、同
中空部5aの横断面内に配分された複数の位置に締め固
め杭6の外径より少し大きい内径の複数本のガイドパイ
プ4’が並列状に配置され、各々連結板8a、8bで既
製杭5と一体的構造に拘束されていると共に、各ガイド
パイプ4’の上端部は中空部内を下降してきた締め固め
杭の誘導に適切なテーパの漏斗状に形成されているこ
と、 ロ) 前記各ガイドパイプ4’の先端開口部は土返し板
で遮蔽され、同土返し板には中心部に締め固め杭6の先
端径と略同内径の通孔が設けられていると共に中心部か
ら放射状配置に複数本の切込み溝が形成されており、土
返し板は締め固め杭により前記切込み溝に沿って破断可
能に構成されていること、も特徴とする(図5参照)。In each of the above-mentioned inventions, the cut groove 9 is formed on the outer side surface (lower surface) of the earth return plate 10, and the guide pipe 4 is required for the cast-in-place concrete pile 2 or the reinforcing bar 3 of the continuous underground wall. 3 and the upper end of the guide pipe 4 'is enlarged in a funnel shape (FIGS. 4A and 4B). Further, the guide pipe according to the present invention includes: a) The hollow pipe 5 has a hollow structure, and the compacted pile 5 is provided at a plurality of positions distributed in the cross section of the hollow pile 5a. A plurality of guide pipes 4 'each having a slightly larger inner diameter are arranged in parallel, each being restrained by a connecting plate 8a, 8b in an integrated structure with the ready-made stake 5, and the upper end of each guide pipe 4' is formed in a hollow portion. Is formed in a funnel shape having a taper suitable for guiding the compacted pile that has descended. B) The opening at the tip end of each of the guide pipes 4 'is shielded by a soil return plate, and A through hole having substantially the same inner diameter as the tip diameter of the compaction pile 6 is provided in the portion, and a plurality of cut grooves are formed radially from the central portion. It is also characterized by being breakable along 5).
【0008】[0008]
【作用】ガイドパイプ4を単独で、又は鉄筋篭3と共に
掘削孔中に沈設する際、あるいは既製杭5又は14を掘
削孔中に建込む際、掘削孔中に満たされている泥水は土
返し板10の通孔11を自由に流通するのでさしたる抵
抗を生じない。締め固め杭6が先端地盤中へ貫入される
際に生ずる上方への排土は、土返し板10によって確実
に塞き止められ、ガイドパイプ4又は4’中への侵入は
防止される。When the guide pipe 4 is laid alone or together with the rebar cage 3 in the excavation hole, or when the ready-made pile 5 or 14 is built in the excavation hole, the muddy water filled in the excavation hole is returned to the soil. There is no appreciable resistance because the through-hole 11 of the plate 10 flows freely. The upward discharge that occurs when the compaction pile 6 penetrates into the tip ground is reliably blocked by the earth return plate 10 and entry into the guide pipe 4 or 4 'is prevented.
【0009】土返し板10は締め固め杭6の貫入に伴っ
て破断されるが、その破断は放射状配置の切込み溝9に
沿って言わばチューリップの花弁のように進行して、そ
のまま締め固め杭6の外周面にまとわり付く形となるた
め(図4B)、排土の侵入防止の作用は依然保持され
る。ガイドパイプ4’の先端部4bは既製杭5又は14
の先端金具13の位置から若干の長さhだけ突き出され
ているため、ガイドパイプの先端は地盤中に幾分かのめ
り込む。従って、図6に示した排土Cは杭先端直下の空
間eの方へ廻り込んで先端支持力が低下することを防
ぐ。The soil return plate 10 is broken as the compaction pile 6 penetrates, but the fracture progresses along the radially arranged cut groove 9 like a petal of a tulip, so to speak. (FIG. 4B), so that the effect of preventing the intrusion of the earth removal is still maintained. The tip 4b of the guide pipe 4 'is made of a ready-made pile 5 or 14.
Of the guide pipe 13 slightly protrudes from the position of the front end fitting 13 into the ground. Accordingly, the earth discharging C shown in FIG. 6 is prevented from sneaking into the space e immediately below the tip of the pile to lower the tip supporting force.
【0010】[0010]
【実施例】次に、図示した本発明の実施例を説明する。
図1と図2に示したガイドパイプ4は、例えば場所打ち
コンクリート杭の構築において、地上から先端地盤(孔
底地盤)まで締め固め杭6を誘導するためのもので、例
えば締め固め杭6の外径(通例10〜60cm程度)より
数cm程度大きい内径で、杭用孔の深さと同等以上の長さ
を有する鉄管が使用されている。このガイドパイプ4の
先端開口部は、鉄板による土返し板10で遮蔽されてい
る。土返し板10の中心部には、締め固め杭6の先端径
(通例5〜30cm程度)と等しいか又は少し大きい口径
の通孔11が設けられている。また、土返し板10に
は、その中心部から放射状の配置で多数の切込み溝9が
形成されている(図2)。切込み溝9は、土返し板10
の外側面(下側面)に、同土返し板10の板厚(約4m
m)に対し、深さ、開口幅が2×2mmぐらいのVカット
溝として形成されている。従って、土返し板10は、外
側からの圧力(例えば泥水圧)に対しては強いが、内側
からの圧力(例えば締め固め杭6による圧力)には比較
的弱く、締め固め杭6による破断(所謂ノックアウト)
は容易である。杭用孔の先端地盤(孔底)へ着底された
ガイドパイプ4中に締め固め杭6を下降させてゆくと、
締め固め杭6の先端は土返し板10の略中心部に位置す
る通孔11にのぞき出す。この締め固め杭6を強力に押
し下げると、土返し板10は切込み溝9に沿ってチュー
リップ状に破断され、締め固め杭6は先端地盤の中へ進
入してゆき、先端地盤中に所望の深さまで貫入され、そ
の体積効果で先端地盤を締め固める。このとき土返し板
10は締め固め杭6の貫入に伴う上方への排土を塞き止
め、ガイドパイプ4中への侵入を防ぐ。特に土返し板1
0が放射状配置の切込み溝9に沿ってチューリップ状に
破断された際にも、各破断片は湾曲状態になりながら締
め固め杭6の外周面にぴったりまとわり付くので、前記
排土の塞き止め作用は良好に奏される。(図4B参照)
締め固め杭6の貫入方法としては、自由落下による落し
込み方法、又はハンマーによる打込み又は油圧ジャッキ
等による静的な押し込み方法のほか、ガイドパイプ4の
上端から回転軸を挿入し、締め固め杭6の上端の角孔に
回転軸先端の角軸をはめ合わせ回転機で回転して先端地
盤へねじ込む方法などを好適に実施できる。先端地盤中
へ十分に深く貫入された締め固め杭6は、その後ガイド
パイプ4内に充填した中詰モルタル16(又はセメント
ミルク,コンクリート)によってしっかりと固定される
(図4B参照)。土返し板10によって排土の侵入が防
止されているので、高品質の中詰モルタルを施工でき
る。BRIEF DESCRIPTION OF THE DRAWINGS FIG.
The guide pipe 4 shown in FIGS. 1 and 2 is for guiding the compaction pile 6 from the ground to the tip ground (hole bottom ground) in the construction of a cast-in-place concrete pile, for example. An iron tube having an inner diameter several centimeters larger than the outer diameter (usually about 10 to 60 cm) and having a length equal to or greater than the depth of the pile hole is used. The opening at the tip end of the guide pipe 4 is shielded by an earth return plate 10 made of an iron plate. A through hole 11 having a diameter equal to or slightly larger than the tip diameter (typically about 5 to 30 cm) of the compaction pile 6 is provided in the center of the earth return plate 10. In addition, a large number of cut grooves 9 are formed in the soil return plate 10 in a radial arrangement from the center thereof (FIG. 2). The cut groove 9 is a
On the outside surface (lower surface) of the same, the thickness of the same backing plate 10 (about 4m
m), it is formed as a V-cut groove having a depth and an opening width of about 2 × 2 mm. Accordingly, the soil return plate 10 is strong against an external pressure (for example, muddy water pressure), but relatively weak against an internal pressure (for example, the pressure by the compaction pile 6), and is broken by the compaction pile 6 ( So-called knockout)
Is easy. When the compacted pile 6 is lowered into the guide pipe 4 settled on the tip ground (hole bottom) of the pile hole,
The tip of the compaction pile 6 is protruded into a through-hole 11 located substantially at the center of the soil return plate 10. When the compaction pile 6 is strongly pushed down, the earth return plate 10 is broken in a tulip shape along the cut groove 9, and the compaction pile 6 penetrates into the tip ground and has a desired depth in the tip ground. It is completely penetrated, and compacts the tip ground by its volume effect. At this time, the soil return plate 10 blocks the upward discharging of the soil due to the intrusion of the compaction pile 6 and prevents the intrusion into the guide pipe 4. In particular, clay sheet 1
Even when 0 is broken in the form of a tulip along the radially arranged cut grooves 9, each broken piece adheres to the outer peripheral surface of the compaction pile 6 in a curved state, so that the soil removal is blocked. The blocking action is well performed. (See FIG. 4B)
Examples of the method of penetrating the compaction pile 6 include a method of dropping by free fall, a method of hammering or a static pushing method by a hydraulic jack, and the like. A method of fitting the square axis of the tip of the rotating shaft into the square hole at the upper end of the shaft and rotating the screw with a rotating machine and screwing it into the tip ground can be suitably implemented. The compacted pile 6 that has penetrated sufficiently deep into the tip ground is then firmly fixed by the filling mortar 16 (or cement milk, concrete) filled in the guide pipe 4 (see FIG. 4B). Since the earth return plate 10 prevents intrusion of earth removal, high-quality hollow mortar can be constructed.
【0011】[0011]
【第2の実施例】図3は高耐力場所打ちコンクリート杭
2の施工図を示したもので、地盤に杭用孔が支持層に達
する深さまで掘削され、その杭用孔の中に鉄筋篭3と共
にガイドパイプ4が設置されている。ガイドパイプ4
は、杭用孔2の直径(約1〜4m位)とその横断面形状
に基づいて適正に配分された3箇所の位置に3本配置さ
れている(但し、位置及び本数は図示例の限りではな
い)。各ガイドパイプ4は、鉄筋篭3に結束するか又は
溶接する方法などで鉄筋篭3へ一体的に付設されてお
り、鉄筋篭3の設置を兼ねてガイドパイプ4も杭用孔内
に設置される。Second Embodiment FIG. 3 shows a construction drawing of a high-strength cast-in-place concrete pile 2 in which a hole for a pile is excavated in the ground to a depth reaching a support layer, and a reinforcing cage is inserted in the hole for the pile. A guide pipe 4 is installed together with 3. Guide pipe 4
Are arranged at three positions appropriately distributed based on the diameter of the pile hole 2 (approximately 1 to 4 m) and the cross-sectional shape thereof (however, the position and the number are limited to those in the illustrated example). is not). Each guide pipe 4 is integrally attached to the reinforced cage 3 by a method such as bundling or welding to the reinforced cage 3, and the guide pipe 4 is also installed in the pile hole for the installation of the reinforced cage 3. You.
【0012】ガイドパイプ4は、図1と図2で説明した
ように締め固め杭6の外径よりも少し大きい内径で、少
なくとも杭用孔の深さと同等以上の長さを有し、先端開
口部は土返し板10によって遮蔽されている。As described with reference to FIGS. 1 and 2, the guide pipe 4 has an inner diameter slightly larger than the outer diameter of the compaction pile 6, has a length at least equal to the depth of the pile hole, and has a tip opening. The part is shielded by the earth return plate 10.
【0013】[0013]
【第3の実施例】図4A、Bは高耐力埋込み杭の施工に
使用される既製コンクリート杭14を示している。これ
は既製コンクリート杭14の中空部14aを締め固め杭
6のガイドパイプに利用する構成であり、既製コンクリ
ート杭14の中空部14a内の下端部に、締め固め杭6
の外径より少し大きい内径の短いガイドパイプ4’が、
その取付板15を先端金具13へ溶接等して同心配置に
設置されている。ガイドパイプ4’の先端部4bは先端
金具13の位置から5〜20cm程度の寸法hだけ突き出
されている。ガイドパイプ4’の先端開口部は第1実施
例で説明した構成の土返し板10で遮蔽されている。同
ガイドパイプ4’の上端部は倒立円すい形状の誘導部4
aに形成されている。従って、既製コンクリート杭14
の中空部14a内に挿入した締め固め杭6は、必ずガイ
ドパイプ4’内に誘導され杭中心に位置せしめられる。
既製コンクリート杭14が掘削孔中に建込まれた後に締
め固め杭6が先端地盤5へ貫入される(図4B)。その
後中空部14a及びガイドパイプ4’の内外に中詰めモ
ルタル16(又はセメントミルク,コンクリート)を充
填して締め固め杭6を固定することは、前記第1実施例
の場合と同じである。Third Embodiment FIGS. 4A and 4B show a ready-made concrete pile 14 used for construction of a high-bearing embedded pile. This is a configuration in which the hollow portion 14a of the ready-made concrete pile 14 is used as a guide pipe of the compacted pile 6, and the compacted pile 6 is provided at the lower end in the hollow portion 14a of the ready-made concrete pile 14.
A short guide pipe 4 'with an inner diameter slightly larger than the outer diameter of
The mounting plate 15 is installed concentrically by welding or the like to the tip fitting 13. The tip 4b of the guide pipe 4 'protrudes from the position of the tip fitting 13 by a dimension h of about 5 to 20 cm. The opening at the tip end of the guide pipe 4 'is shielded by the earth return plate 10 having the configuration described in the first embodiment. The upper end of the guide pipe 4 ′ is an inverted conical guiding section 4.
a. Therefore, the ready-made concrete pile 14
The compacted pile 6 inserted into the hollow portion 14a is always guided into the guide pipe 4 'and positioned at the center of the pile.
After the ready-made concrete pile 14 is built in the excavation hole, the compacted pile 6 penetrates into the tip ground 5 (FIG. 4B). Thereafter, filling the inside mortar 16 (or cement milk, concrete) inside and outside the hollow portion 14a and the guide pipe 4 'and fixing the compaction pile 6 is the same as in the first embodiment.
【0014】[0014]
【第4の実施例】図5はやはり埋込み杭に使用されるも
のであるが、特に既製杭5の内径が締め固め杭6の外径
よりも数倍大きい場合の実施例を示している。大径の中
空部5aの横断面内には、締め固め杭6の外径より少し
大きい内径の3本(但し、本数はこの限りでない)のガ
イドパイプ4’を等配して並列状に配置し、上下2枚の
連結板8a、8bで既製杭14に一体化されている。ガ
イドパイプ4’の上端部は、締め固め杭6を導入する倒
立円すい形状の誘導部4aに形成され、その上端と同じ
レベルに上位の連結板8aが設置されている。ガイドパ
イプ4’の先端部4bは下方の連結板8bの位置から若
干の長さhだけ突き出されている。各ガイドパイプ4’
の先端開口部はやはり第1実施例で説明した構成の土返
し板10で遮蔽されている。図5中の符号17は連結板
8aに設けた通孔であり、この通孔17を通じて中詰モ
ルタル等が上下の連結板8a,8bの間にも充填され
る。Fourth Embodiment FIG. 5 also shows an embodiment in which the inner diameter of the ready-made pile 5 is several times larger than the outer diameter of the compacted pile 6, which is also used for embedded piles. In the cross section of the large-diameter hollow portion 5a, three (but not limited to) guide pipes 4 'having an inner diameter slightly larger than the outer diameter of the compaction pile 6 are equally arranged and arranged in parallel. Then, it is integrated with the ready-made pile 14 by two upper and lower connecting plates 8a and 8b. The upper end of the guide pipe 4 'is formed as an inverted conical guide 4a for introducing the compaction pile 6, and the upper connecting plate 8a is installed at the same level as the upper end thereof. The distal end 4b of the guide pipe 4 'protrudes from the position of the lower connecting plate 8b by a slight length h. Each guide pipe 4 '
The opening at the front end is also shielded by the earth return plate 10 having the configuration described in the first embodiment. Reference numeral 17 in FIG. 5 denotes a through hole provided in the connecting plate 8a. Through this through hole 17, a filling mortar or the like is filled between the upper and lower connecting plates 8a and 8b.
【0015】[0015]
【その他の実施例】ガイドパイプの横断面形状は図2の
円形に限らない。角パイプ又は六角形パイプなどで全く
同様に実施することができる。Other Embodiments The cross-sectional shape of the guide pipe is not limited to the circular shape shown in FIG. It can be implemented in exactly the same way with square pipes or hexagonal pipes.
【0016】[0016]
【本発明が奏する効果】本発明に係る締め固め杭用のガ
イドパイプによれば、ガイドパイプ又は既製杭の建込み
作業が孔内の泥水にじゃまされることなく楽に施工性良
く作業できる。そして、締め固め杭6の貫入時に発生す
る排土がガイドパイプや既製杭の中に侵入することを防
止でき、先端支持力が大きく信頼性の高い高耐力場所打
ちコンクリート杭等の構築に寄与し、品質と信頼性に優
れた構造物の構築に貢献するのである。According to the guide pipe for a compacted pile according to the present invention, the work for setting up the guide pipe or the ready-made pile can be easily performed with good workability without being disturbed by the muddy water in the hole. In addition, it is possible to prevent the earth discharge generated when the compacted pile 6 penetrates from penetrating into the guide pipes and the ready-made piles, and to contribute to the construction of a high-strength cast-in-place concrete pile having a large tip supporting force and high reliability. It contributes to the construction of structures with excellent quality and reliability.
【図1】A、Bはガイドパイプ先端部の構造を示した断
面図である。FIGS. 1A and 1B are cross-sectional views showing the structure of a guide pipe tip.
【図2】図1Aのガイドパイプの底面図である。FIG. 2 is a bottom view of the guide pipe of FIG. 1A.
【図3】鉄筋篭に付設されたガイドパイプによる高耐力
場所打ちコンクリート杭の施工を示した斜視図である。FIG. 3 is a perspective view showing construction of a high strength cast-in-place concrete pile using a guide pipe attached to a reinforced cage.
【図4】A、Bは既製杭下部のガイドパイプの構造を拡
大して示した断面図である。FIGS. 4A and 4B are cross-sectional views showing an enlarged structure of a guide pipe below a ready-made pile.
【図5】大径既製コンクリート杭の断面図である。FIG. 5 is a sectional view of a large-diameter ready-made concrete pile.
【図6】従来のガイドパイプを示した断面図である。FIG. 6 is a sectional view showing a conventional guide pipe.
4、4’ ガイドパイプ 6 締め固め杭 14 既製杭 14a 中空部 10 土返し板 11 通孔 9 切込み溝 4, 4 'guide pipe 6 compacted pile 14 ready-made pile 14a hollow part 10 soil return plate 11 through hole 9 cut groove
───────────────────────────────────────────────────── フロントページの続き (72)発明者 土屋 富男 東京都江東区南砂二丁目5番14号 株式 会社竹中工務店技術研究所内 (72)発明者 栗田 佳彦 東京都江東区南砂二丁目5番14号 株式 会社竹中工務店技術研究所内 (72)発明者 幾田 悠康 大阪市中央区本町四丁目1番13号 株式 会社竹中工務店大阪本店内 (72)発明者 福原 拓平 東京都中央区銀座八丁目21番1号 株式 会社竹中土木内 (56)参考文献 特開 平4−209207(JP,A) (58)調査した分野(Int.Cl.6,DB名) E02D 13/04 ──────────────────────────────────────────────────続 き Continuing on the front page (72) Inventor Tomio Tsuchiya 2-5-1 Minamisuna, Koto-ku, Tokyo Inside the Technical Research Center, Takenaka Corporation (72) Inventor Yoshihiko Kurita 2-5-1 Minamisuna, Koto-ku, Tokyo No. Takenaka Corporation Technical Research Institute Co., Ltd. (72) Inventor Yuyasu Ikuta 4-1-1, Honcho, Chuo-ku, Osaka City Inside Takenaka Corporation, Osaka Main Store (72) Inventor Takuhei Fukuhara Ginza, Chuo-ku, Tokyo No. 21-1, Takenaka Civil Engineering Co., Ltd. (56) References JP-A-4-209207 (JP, A) (58) Fields investigated (Int. Cl. 6 , DB name) E02D 13/04
Claims (6)
地盤中へ貫入される締め固め杭を地上から孔底まで案内
するガイドパイプであって、締め固め杭の外径より少し
大きい内径を有し、杭用孔等の深さと同等以上の長さを
有する鉄管等で構成され、当該パイプの先端開口部を遮
蔽する土返し板が設置され、この土返し板には中心部に
締め固め杭の先端径と略同径の通孔が設けられていると
共に中心部から放射状配置に複数本の切込み溝が形成さ
れており、土返し板は締め固め杭により前記切込み溝に
沿って破断可能に構成されていることを特徴とする、締
め固め杭用のガイドパイプ。1. A guide pipe for guiding a compacted pile penetrating into the bottom of a drilled hole such as a cast-in-place concrete pile from the ground to the bottom of the hole, and having an inner diameter slightly larger than the outer diameter of the compacted pile. , Composed of an iron pipe or the like having a length equal to or greater than the depth of the pile hole, etc., and a soil return plate that shields the opening at the tip of the pipe is installed. A through-hole of approximately the same diameter as the tip diameter is provided, and a plurality of cut grooves are formed radially from the center, and the soil return plate is configured to be broken along the cut groove by compaction pile. A guide pipe for a compacted pile, characterized in that it is made.
め杭の外径より少し大きい内径の短いガイドパイプが当
該既製杭の中空部と同心配置に接合されており、このガ
イドパイプの先端部は前記先端金具から若干の長さ突き
出され、当該ガイドパイプの先端開口部を遮蔽する土返
し板が設置されており、この土返し板には中心部に締め
固め杭の先端径と略同径の通孔が設けられていると共
に、中心部から放射状配置に複数本の切込み溝が形成さ
れており、土返し板は締め固め杭により前記切込み溝に
沿って破断可能に構成されていることを特徴とする、締
め固め杭用のガイドパイプ。2. A short guide pipe having an inner diameter slightly larger than the outer diameter of the compaction pile is joined to a tip fitting of the hollow pile of the ready-made pile in a concentric arrangement with the hollow portion of the ready-made pile. The portion protrudes a little from the tip fitting, and is provided with a soil return plate that covers the distal end opening of the guide pipe. The soil return plate has a central portion approximately the same as the tip diameter of the compaction pile. A through hole having a diameter is provided, and a plurality of cut grooves are formed in a radial arrangement from the center, and the soil return plate is configured to be breakable along the cut groove by a compaction pile. A guide pipe for a compacted pile.
ていることを特徴とする請求項1又は請求項2に記載し
た締め固め杭用のガイドパイプ。3. The guide pipe for a compacted pile according to claim 1, wherein the cut groove is formed on an outer side surface of the earth return plate.
ちコンクリート杭又は連続地中壁の鉄筋に所要の配置で
所要本数だけ一体的に付設されていることを特徴とす
る、締め固め杭用のガイドパイプ。4. The compacted pile according to claim 1, wherein the required number of the guide pipes is integrally attached to a cast-in-place concrete pile or a reinforcing steel wall of a continuous underground wall in a required arrangement. Guide pipe.
部は漏斗形状に拡径されていることを特徴とする、締め
固め杭用のガイドパイプ。5. A guide pipe for a compaction pile, wherein the upper end of the guide pipe according to claim 2 is enlarged in a funnel shape.
に、同中空部の横断面内に配分された複数の位置に締め
固め杭の外径より少し大きい内径の複数本のガイドパイ
プ が並列状に配置され、各々連結板で既製杭と一体的
構造に拘束されていると共 に、各ガイドパイプの上端
部は中空部内を下降してきた締め固め杭の誘導に適 切
なテーパの漏斗状に形成されていること、 ロ) 前記各ガイドパイプの先端開口部は土返し板で遮
蔽され、同土返し板には中心部に締め固め杭の先端径と
略同内径の通孔が設けられていると共に、中心部から放
射状 配置に複数本の切込み溝が形成されており、土返
し板は締め固め杭により前記 切込み溝に沿って破断可
能に構成されていること、をそれぞれ特徴とする締め固
め杭用のガイドパイプ。6. A plurality of guides having an inner diameter slightly larger than the outer diameter of the compacted pile at a plurality of positions distributed in a cross section of the hollow part in a hollow part of a ready-made pile having a hollow structure and a large diameter. The pipes are arranged side by side, and are each constrained by a connecting plate to an integral structure with the ready-made pile, and the upper end of each guide pipe has a taper suitable for guiding the compacted pile descending in the hollow part. The guide pipe is formed in a funnel shape. B) The opening at the tip of each of the guide pipes is shielded by a soil return plate. And a plurality of cut grooves are formed radially from the center portion, and the soil return plate is configured to be breakable along the cut grooves by compaction piles. Guide pipe for compacting piles.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP6652191A JP2958717B2 (en) | 1991-03-29 | 1991-03-29 | Guide pipe for compacted pile |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP6652191A JP2958717B2 (en) | 1991-03-29 | 1991-03-29 | Guide pipe for compacted pile |
Publications (2)
Publication Number | Publication Date |
---|---|
JPH04302617A JPH04302617A (en) | 1992-10-26 |
JP2958717B2 true JP2958717B2 (en) | 1999-10-06 |
Family
ID=13318257
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
JP6652191A Expired - Fee Related JP2958717B2 (en) | 1991-03-29 | 1991-03-29 | Guide pipe for compacted pile |
Country Status (1)
Country | Link |
---|---|
JP (1) | JP2958717B2 (en) |
Families Citing this family (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JP2019100070A (en) * | 2017-12-01 | 2019-06-24 | 五洋建設株式会社 | Foundation structure of offshore wind power generation facility, and construction method of the same |
-
1991
- 1991-03-29 JP JP6652191A patent/JP2958717B2/en not_active Expired - Fee Related
Also Published As
Publication number | Publication date |
---|---|
JPH04302617A (en) | 1992-10-26 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
US5707180A (en) | Method and apparatus for forming piles in-situ | |
US8043028B2 (en) | Apparatus for providing a support column | |
JP2002155530A (en) | Embedding method and tip metal fitting of existing pile | |
JP3752560B2 (en) | Basic structure for constructing a new building in an existing basement and its construction method | |
JP2958717B2 (en) | Guide pipe for compacted pile | |
JP4485006B2 (en) | Construction method for underground structures | |
JP2001059219A (en) | Bored precast pile | |
KR20030028518A (en) | apparatus and method for retaining wall using ground anchor | |
JP3450774B2 (en) | Steel pipe pile and its burial method | |
JP2001098542A (en) | Soil cement composite taper pile | |
JP3005609B2 (en) | Construction method for high strength steel continuous walls | |
KR100549088B1 (en) | Method for isolated footing type under-Reamed pile and the isolated footing type under-Reamed thereof | |
JP2936353B2 (en) | Construction method of high strength embedded pile | |
JP2881501B2 (en) | Construction method for high strength cast-in-place concrete piles | |
JP2797030B2 (en) | Guide pipe for compacted pile | |
JP3514183B2 (en) | Embedded pile and its construction method | |
JP2879373B2 (en) | Guide pipe for compacted pile | |
KR100549456B1 (en) | Structure of Erecton reinforcing bar for Grouted Bored File | |
JP2884273B2 (en) | Construction method for high strength cast-in-place concrete piles | |
JP2881502B2 (en) | Construction method for high strength cast-in-place concrete piles | |
JP3827625B2 (en) | Seismic control structure that allows lifting of pile tip | |
JP2976390B2 (en) | Method for preventing liquefaction of the foundation directly under the existing structure | |
JP3519375B2 (en) | Cast-in-place pile construction method just below the existing foundation | |
KR200331520Y1 (en) | The Grouted Bored pile and Structure of Erecton reinforcing bar | |
JP3018877B2 (en) | Underground structure and method of constructing underground structure |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
LAPS | Cancellation because of no payment of annual fees |