JP2891431B2 - Subway reinforced concrete wall construction method - Google Patents

Subway reinforced concrete wall construction method

Info

Publication number
JP2891431B2
JP2891431B2 JP23791690A JP23791690A JP2891431B2 JP 2891431 B2 JP2891431 B2 JP 2891431B2 JP 23791690 A JP23791690 A JP 23791690A JP 23791690 A JP23791690 A JP 23791690A JP 2891431 B2 JP2891431 B2 JP 2891431B2
Authority
JP
Japan
Prior art keywords
concrete wall
shield machine
concrete
formwork
wall
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Lifetime
Application number
JP23791690A
Other languages
Japanese (ja)
Other versions
JPH04118497A (en
Inventor
進 那須
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Konoike Construction Co Ltd
Original Assignee
Konoike Construction Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Konoike Construction Co Ltd filed Critical Konoike Construction Co Ltd
Priority to JP23791690A priority Critical patent/JP2891431B2/en
Publication of JPH04118497A publication Critical patent/JPH04118497A/en
Application granted granted Critical
Publication of JP2891431B2 publication Critical patent/JP2891431B2/en
Anticipated expiration legal-status Critical
Expired - Lifetime legal-status Critical Current

Links

Description

【発明の詳細な説明】 〔産業上の利用分野〕 本発明はシールド機発進・到達立坑の土留め壁等とし
て使用される地下鉄筋コンクリート連続壁工法に関する
ものである。
DETAILED DESCRIPTION OF THE INVENTION [Industrial Application Field] The present invention relates to a subway reinforced concrete continuous wall construction method used as a retaining wall or the like of a shield machine start / reach shaft.

〔発明の背景〕[Background of the Invention]

この種の地下鉄筋コンクリート連続壁は掘削機にて地
盤を掘削して立溝を形成し、該立溝内に鉄筋籠を建込
み、この後該立溝内下部よりコンクリートを打設するこ
とにより形成される。該立溝を掘削機で掘削する際に
は、該立溝に安定液を注入して立溝周壁の土圧や地下水
圧と該安定液の液圧とをバランスさせて立溝周壁の崩壊
を防止する。
This type of subway reinforced concrete continuous wall is formed by excavating the ground with an excavator to form a ditch, laying a steel cage in the ditch, and then pouring concrete from the lower part of the ditch. Is done. When excavating the vertical ditch with an excavator, a stabilizing liquid is injected into the vertical ditch to balance the earth pressure or groundwater pressure of the vertical ditch peripheral wall with the liquid pressure of the stable liquid, thereby causing collapse of the vertical ditch peripheral wall. To prevent.

このようにして形成された地下鉄筋コンクリート連続
壁の内側の地山を掘削して立坑を形成し、該立坑に地下
洞道を接続する場合があるが、その際には該地下鉄筋コ
ンクリート連続壁の坑口からシールド機を発進させて地
下洞道を掘設したり、該坑口へ地下洞道を掘設して来た
シールド機を到達させたりする。
The ground inside the subway reinforced concrete continuous wall thus formed may be excavated to form a shaft, and an underground cave may be connected to the shaft. Then, a shield machine is started to dig an underground cave, or a shield machine that has digged an underground cave to reach the entrance.

〔従来の技術〕[Conventional technology]

従来は上記鉄筋コンクリート連続壁の鉄筋籠を切断し
かつコンクリートを切削する鏡切り工を行なって坑口を
開設し、該坑口からシールド機を発進させあるいは該坑
口へシールド機を到達させていた。この際、坑口開設時
に地山側からの土砂の崩壊や地下水の侵入を防ぐため、
坑口開設に先立って該鉄筋コンクリート連続壁の坑口相
当部の周辺の地山側に凍結処理、あるいは薬液注入処理
を施して地盤安定を行なっていた。
Conventionally, a pit was opened by cutting the reinforced cage of the reinforced concrete continuous wall and cutting the concrete to perform a mirror-cutting work, and a shield machine was started from the pit or reached to the pit. At this time, at the time of opening of the pit, to prevent the collapse of soil and groundwater from the ground side,
Prior to the opening of the pit, the ground was stabilized by applying a freezing treatment or a chemical injection treatment to the ground near the portion corresponding to the pit of the reinforced concrete continuous wall.

〔発明が解決しようとする課題〕[Problems to be solved by the invention]

しかしながら、上記凍結処理にあっては地山側の地盤
の安定化は図れるものの、施工日数が長くかゝり、凍結
のための費用も相当高価なものになる。また薬液注入処
理では地盤の安定化が均一でなく、信頼性が低く、出水
や地盤崩壊の危険性がある。更に上記鏡切り工では、作
業能率の低下、作業環境の悪化が伴い、安全施工管理上
にも問題点が多く、このような問題点は高深度、大口径
のシールド工法になればますます深刻なものとなってい
る。
However, in the above-mentioned freezing process, although the ground on the ground side can be stabilized, the construction days are long, and the cost for freezing is considerably high. Also, in the chemical solution injection process, the ground stabilization is not uniform, the reliability is low, and there is a risk of flooding and ground collapse. Furthermore, the above-mentioned mirror-cutting work involves a decrease in work efficiency and a deterioration in the work environment, and there are many problems in safe construction management. These problems become more serious with the use of a shield method with a large depth and a large diameter. It has become something.

〔課題を解決するための手段〕[Means for solving the problem]

本発明は上記従来の課題を解決するための手段とし
て、 安定液(2)を注入しつゝ掘削機にて地盤を掘削して
立溝(1)を形成する工程1 該立溝(1)内にシールド機(16)発進到達坑口(1
5)相当部に型枠(4)を組込んだ鉄筋籠(3)を建込
み、該型枠(4)内には比重1.0〜1.2のビーズ(9)を
分散した泥水(10)を充填する工程2 該立溝(1)内下部よりコンクリートを打設する工程
3 該型枠(4)内にセメントミルク(14)を注入し該泥
水(10)と置換してシールド機(16)発進到達坑口(1
5)相当部に間詰コンクリート壁(13)を打設する工程
4 上記のようにして地下鉄筋コンクリート連続壁(12)
を形成した後、その内側の地山(1B)を掘削して立坑
(1C)を形成する工程5 該型枠(4)を解体撤去するとともに該立坑(1C)側
から該坑口(15)相当部に隔壁(15A)を取付ける工程
6 以上の工程1,2,3,4,5,6からなる地下鉄筋コンクリー
ト連続壁工法を提供するものである。
According to the present invention, as a means for solving the above-mentioned conventional problems, a step 1 of injecting a stabilizing liquid (2) and excavating the ground with an excavator to form a vertical groove (1) 1 Inside the shield machine (16)
5) Reinforcing cage (3) with built-in formwork (4) is built in the corresponding part, and the formwork (4) is filled with muddy water (10) dispersed with beads (9) having a specific gravity of 1.0 to 1.2. Step 2 Pour concrete from the lower part of the vertical groove (1) Step 3 Inject cement milk (14) into the form (4) and replace it with the muddy water (10) to start the shield machine (16) Reach (1
5) Step 4 of placing concrete wall (13) at the corresponding part 4 Subway reinforced concrete continuous wall (12) as described above
Step 5 of excavating the ground (1B) inside and forming a shaft (1C) after forming the shaft. (5) Dismantling and removing the formwork (4), and also corresponding to the wellhead (15) from the shaft (1C) side. Step 6 of Attaching Partition Wall (15A) to Part The present invention provides a subway reinforced concrete continuous wall construction method comprising the above steps 1, 2, 3, 4, 5, and 6.

そして望ましくは該型枠(4)内には該間詰コンクリ
ート壁(13)の補強材(6)を予め上方に引抜き可能に
組込んでおく。
Desirably, a reinforcing material (6) for the filling concrete wall (13) is previously incorporated in the form (4) so as to be able to be pulled out upward.

〔作用〕[Action]

本発明において立溝(1)に鉄筋籠(3)を建込む
際、該鉄筋籠(3)のシールド機(16)発進到達坑口
(15)相当部に組込んだ型枠(4)内にビーズ(9)を
分散した泥水(10)を充填するので、該型枠(4)内に
立溝(1)内の安定液(2)が侵入しない。該ビーズ
(9)は比重1.0〜1.2であるから該泥水(10)は周囲の
安定液(2)と略同比重となり、鉄筋籠(3)建込み時
該泥水(10)は該安定液(2)と実質的に混合されな
い。そして該型枠(4)内にセメントミルク(14)を注
入すると該セメントミルク(14)が該泥水(10)と置換
されるが、この際、該泥水(10)に分散しているビーズ
(9)の濾別効果により、セメントミルク(14)のなか
のセメント粒子が濾別捕捉されて型枠(4)内から該泥
水(10)とともに外方へ逃散することを防止される。即
ち該セメントミルク(14)は該泥水(10)と実質的に混
合することなく置換される。そして該泥水(10)中のビ
ーズ(9)はセメントミルク(14)内に残存して形成さ
れる間詰コンクリート壁(13)を補強する充填材とな
る。
In the present invention, when the reinforcing bar cage (3) is built in the vertical groove (1), the reinforcing bar (3) is installed in a formwork (4) incorporated in a portion corresponding to a shield machine (16) start reaching wellhead (15). Since the muddy water (10) in which the beads (9) are dispersed is filled, the stable liquid (2) in the vertical groove (1) does not enter the mold (4). Since the specific gravity of the beads (9) is 1.0 to 1.2, the mud (10) has substantially the same specific gravity as the surrounding stable liquid (2). It is not substantially mixed with 2). When the cement milk (14) is injected into the mold (4), the cement milk (14) is replaced with the mud (10). At this time, beads (10) dispersed in the mud (10) are used. By the filtering effect of 9), the cement particles in the cement milk (14) are prevented from being trapped by filtering and escaping out of the mold (4) together with the muddy water (10). That is, the cement milk (14) is replaced without substantially mixing with the mud (10). The beads (9) in the muddy water (10) serve as a filler to reinforce the filling concrete wall (13) formed by remaining in the cement milk (14).

このようにしてシールド機(16)発進到達坑口(15)
相当部に間詰コンクリート壁(13)が形成されるが、型
枠(4)に予め該間詰コンクリート壁(13)の補強材
(6)を上方に引抜き可能に組込んでおくと、該補強材
(6)は該間詰コンクリート壁(13)を補強する。この
補強材(6)はシールド機(16)の発進到達にあたって
間詰コンクリート壁(13)から上方に引抜かれ撤去され
る。シールド機(16)は該間詰コンクリート壁(13)を
切削して坑口(15)を開設し、発進または到達するので
あるが、この際、地山(1A),(1B)側からの土砂の崩
壊や地下水の進入は隔壁(15A)により堰止められる。
In this way, the shield machine (16) launch arrival wellhead (15)
Although a concrete filling wall (13) is formed in a considerable portion, if the reinforcing material (6) of the concrete filling wall (13) is previously incorporated into the formwork (4) so as to be able to be pulled out upward, the above-mentioned structure is obtained. The reinforcing material (6) reinforces the filling concrete wall (13). The reinforcing material (6) is pulled up from the filling concrete wall (13) and removed when the shield machine (16) reaches the start. The shield machine (16) cuts the filled concrete wall (13) to open a wellhead (15), and starts or arrives. At this time, the earth and sand from the ground (1A) and (1B) sides Collapse and groundwater intrusion are blocked by a bulkhead (15A).

〔発明の効果〕〔The invention's effect〕

したがって本発明では、立溝に建込む鉄筋籠に予め組
込んだ型枠にビーズを分散した泥水を充填するから、該
型枠にセメントミルクを注入した際に立溝内の安定液と
の混合を防止され、所定強度を持った間詰コンクリート
壁が容易に得られる。そしてシールド機は該間詰コンク
リート壁を直接切削して発進または到達するから、従来
のような鏡切り工は必要なく、騒音、作業能率の低下、
作業環境の悪化が解消される。また地山側からの土砂の
崩壊や地下水の侵入は隔壁で阻止するから、凍結処理や
薬液注入処理が不要になり、高深度、大口径の地下洞道
の接続でも安価に、しかも信頼度の高い安全性をもって
行なうことが出来る。
Therefore, in the present invention, since the formwork pre-installed in the reinforcing rod cage built in the vertical groove is filled with muddy water in which beads are dispersed, when the cement milk is injected into the formwork, it is mixed with the stable liquid in the vertical groove. Is prevented, and a concrete-filled concrete wall having a predetermined strength can be easily obtained. And since the shield machine directly cuts and starts or arrives at the filled concrete wall, there is no need for a conventional mirror cutting work, noise, reduction in work efficiency,
Deterioration of the working environment is eliminated. In addition, since the sediment collapse and groundwater intrusion from the ground side are prevented by the partition walls, freezing treatment and chemical liquid injection treatment are not required, and even when connecting to a deep and large-diameter underground tunnel, it is inexpensive and highly reliable. It can be done with safety.

〔実施例〕〔Example〕

本発明を第1図〜第12図に示す一実施例によって説明
すれば、(1)は立溝であり工程1により従来と同様に
掘削機により掘設され、内部には泥水である安定液
(2)が充たされて地山(1A),(1B)側から及ぼされ
る土圧や地下水圧に対坑している。(3)は工程2より
該立溝(1)に建込まれる鉄筋籠であり、該鉄筋籠
(3)のシールド機発進到達坑口相当部には鋼鉄製の型
枠(4)が組込まれている。該型枠(4)は円筒側壁
(4A)と、外側底板(4B)と、内側底板(4C)と、該外
側底板(4B)と内側底板(4C)との間に介在する補強リ
ブ(4D)および補強リング(4E)と、外側底板(4B)か
ら外側に向かって差出されている建込ガイド(4F)と、
円筒側壁(4A)の周縁に取付けられているセパレートブ
ラシ(4G)とからなり、該内側底板(4C)には第1図お
よび第2図に示すようにセメントミルク注入管(5)が
連絡するノズル(4H)が複数個配置されている。そして
該型枠(4)内には間詰コンクリート用補強材としての
鋼管(6)および型枠(4)の上側には該鋼管(6)を
収納する収納筒(7)が組込まれ、更に排泥管(5A)が
連絡する。該鋼管(6)は第4図および第5図に示すよ
うに内部に断面十形状のリブ(6A)が挿着され、このよ
うな構造をとることによって該鋼管(6)に及ぼされる
外力を該リブ(6A)で分散緩和させ、該鋼管(6)の変
形を防止するのである。更に該鋼管(6)の下端には空
気抜孔(6C)を設けた底蓋(6B)を取付ける。該底蓋
(6B)は鋼管(6)を間詰コンクリート壁内に建込む
時、コンクリートが該鋼管(6)内に侵入するのを防止
するものであるが、該鋼管(6)引抜き時に及ぼされる
鋼管(6)の内圧を逃すために該底蓋(6B)に空気抜孔
(6C)を設けるのである。更に該鋼管(6)の周囲は硬
質熱可塑性プラスチック層(6D)によって被覆される。
そして該熱可塑性プラスチック層(6D)の内部には溶剤
導入空間(6E)が形成されている。該熱可塑性プラスチ
ック層(6D)の材料としてはポリ塩化ビニル、ポリスチ
レン、ポリメタクリレート、アクリロニトリル−ブタジ
エン−スチレン共重合体等の硬質な熱可塑性プラスチッ
クまたは該熱可塑性プラスチックの発泡体が用いられ、
間詰コンクリート壁の強度と等しいかまたはそれ以上の
強度を有することが好ましく、該硬質熱可塑性プラスチ
ック層(6D)により地山側からの外力を間詰コンクリー
ト壁から鋼管(6)に緩衝しつゝ伝達出来るようにす
る。型枠(4)の上側に組込まれている該収納筒(7)
の径は該鋼管(6)(硬質熱可塑性プラスチック層(6
D)も含める)の径よりも若干大きめとして該鋼管
(6)と収納筒(7)との摩擦係数を出来るだけ低く
し、また該収納筒(7)の長さは該鋼管(6)の長さを
収容出来る程度のものとする。そして第6図に示すよう
に該鋼管(6)のリブ(6A)の頭部には収納筒(7)を
介して操作棒である鋼棒(8)が連絡する。該鋼棒
(8)の周囲には上記熱可塑性プラスチック層(6D)に
用いられたものと同様な熱可塑性プラスチックの発泡体
層(8A)が被覆される。該発泡体層(8A)は通常3〜4k
g/cm2程度の圧縮強度を有するもので、鋼棒(8)とコ
ンクリートとの摩擦抵抗を下げて鋼棒(8)の引抜きを
容易にするものである。
The present invention will be described with reference to an embodiment shown in FIGS. 1 to 12. (1) is a vertical groove, which is dug by an excavator in the same manner as in the prior art in step 1 and has a stable liquid of muddy water inside. (2) is filled to counter the earth pressure and groundwater pressure from the ground (1A) and (1B). (3) is a steel cage built in the vertical groove (1) from the step 2, and a steel formwork (4) is incorporated in a part of the steel cage (3) corresponding to a shield machine start reaching wellhead. I have. The formwork (4) includes a cylindrical side wall (4A), an outer bottom plate (4B), an inner bottom plate (4C), and a reinforcing rib (4D) interposed between the outer bottom plate (4B) and the inner bottom plate (4C). ) And a reinforcing ring (4E), and a mounting guide (4F) extending outward from the outer bottom plate (4B).
The inner bottom plate (4C) is connected to a cement milk injection pipe (5) as shown in FIGS. 1 and 2 by a separate brush (4G) attached to the peripheral edge of the cylindrical side wall (4A). A plurality of nozzles (4H) are arranged. A steel pipe (6) as a reinforcing material for the concrete filling and a storage tube (7) for storing the steel pipe (6) are incorporated in the formwork (4). The mud pipe (5A) contacts. As shown in FIGS. 4 and 5, the steel pipe (6) has a rib (6A) having a ten-shaped cross section inserted therein, and by adopting such a structure, an external force applied to the steel pipe (6) is reduced. The ribs (6A) alleviate dispersion and prevent deformation of the steel pipe (6). Further, a bottom cover (6B) provided with an air vent (6C) is attached to the lower end of the steel pipe (6). The bottom cover (6B) prevents concrete from entering the steel pipe (6) when the steel pipe (6) is erected in the concrete-filled concrete wall. The bottom cover (6B) is provided with an air vent (6C) to release the internal pressure of the steel pipe (6). Further, the periphery of the steel pipe (6) is covered with a hard thermoplastic layer (6D).
A solvent introduction space (6E) is formed inside the thermoplastic layer (6D). As a material of the thermoplastic layer (6D), a rigid thermoplastic such as polyvinyl chloride, polystyrene, polymethacrylate, acrylonitrile-butadiene-styrene copolymer or a foam of the thermoplastic is used.
It preferably has a strength equal to or higher than the strength of the filled concrete wall, and the hard thermoplastic layer (6D) buffers external forces from the ground side from the filled concrete wall to the steel pipe (6). Be able to communicate. The storage tube (7) installed above the formwork (4)
The diameter of the steel pipe (6) (hard thermoplastic layer (6
D) is also slightly larger than the diameter of the steel pipe (6) so that the friction coefficient between the steel pipe (6) and the storage pipe (7) is as low as possible, and the length of the storage pipe (7) is It should be of a size that can accommodate the length. Then, as shown in FIG. 6, a steel rod (8), which is an operation rod, communicates with the head of the rib (6A) of the steel pipe (6) via a storage cylinder (7). The periphery of the steel rod (8) is covered with a thermoplastic foam layer (8A) similar to that used for the thermoplastic layer (6D). The foam layer (8A) is usually 3-4k
It has a compressive strength of about g / cm 2 and reduces the frictional resistance between the steel bar (8) and the concrete to facilitate the drawing of the steel bar (8).

上記工程2による鉄筋籠(3)を建込む際、該型枠
(4)には比重1.0〜1.2のビース(9)を分散した泥水
(10)を充填する。該ビース(9)はポリスチレン、ポ
リメタクリレート、ポリエチレン、ポリプロピレン等の
プラスチック、シラスバルーン、ガラスバルーン等の無
機質中空球体等からなり、該プラスチックには比重調節
のために炭酸カルシウム、タルク、高炉スラグ、フライ
アッシュ等の充填材が添加されてもよい。上記ビース
(9)は通常上記泥水(10)に70〜100容量%程度添加
される。該ビース(9)を分散した泥水(10)は、立溝
(1)内の安定液(2)と略同比重であり、工程2によ
る鉄筋籠(3)建込みの際に該泥水(10)は該安定液
(2)と実質的に混合されないから、該泥水(10)によ
り型枠(4)内に安定液(2)が侵入することを防止さ
れる。そして型枠(4)のセパレートブラシ(4G)によ
って、泥水(10)中のビース(9)が型枠(4)の外側
に漏洩することが防止されている。更に該型枠(4)は
立溝(1)へ建込む際に建込ガイド(4F)にガイドされ
つゝ立溝(1)内を沈降して行くが、該型枠(4)には
外側底板(4B)と内側底板(4C)との間に空間(4I)が
形成されているので、該空間(4I)にもとづく浮力が型
枠(4)に働いて鉄筋籠(3)建込みの際の重量バラン
スを取ることが出来る。更に該型枠(4)はこのような
二重底構造によって補強され形状が保持される。
When building the reinforcing rod cage (3) in the above step 2, the form (4) is filled with muddy water (10) in which beads (9) having a specific gravity of 1.0 to 1.2 are dispersed. The bead (9) is made of a plastic such as polystyrene, polymethacrylate, polyethylene, or polypropylene, or an inorganic hollow sphere such as a shirasu balloon or a glass balloon. The plastic includes calcium carbonate, talc, blast furnace slag, and fly for adjusting specific gravity. A filler such as ash may be added. The bead (9) is usually added to the muddy water (10) in an amount of about 70 to 100% by volume. The mud (10) in which the beads (9) are dispersed has substantially the same specific gravity as the stabilizing liquid (2) in the vertical groove (1), and when the rebar cage (3) is built in the step 2, the mud (10) ) Is not substantially mixed with the stabilizing solution (2), so that the muddy water (10) prevents the stabilizing solution (2) from entering the mold (4). The separate brush (4G) of the mold (4) prevents the beads (9) in the muddy water (10) from leaking to the outside of the mold (4). Further, when the formwork (4) is set in the vertical groove (1), it is guided by the building guide (4F) and sinks in the vertical groove (1). Since the space (4I) is formed between the outer bottom plate (4B) and the inner bottom plate (4C), buoyancy based on the space (4I) acts on the formwork (4) to build the reinforcing cage (3). In this case, the weight can be balanced. Further, the formwork (4) is reinforced by such a double bottom structure, and the shape is maintained.

上記鉄筋籠(3)を建込んだ後は、第7図に示すよう
に工程3において立溝(1)内下部よりコンクリート
(11)を打設して鉄筋籠(3)で補強されたコンクリー
ト連続壁(12)を形成する。該コンクリート連続壁(1
2)を形成した後は、第8図に示すように工程4におい
て注入管(5)を介して型枠(4)内にセメントミルク
(14)を注入して第9図に示すように間詰コンクリート
壁(13)を打設する。この際用いられるセメントミルク
(14)にはベントナイト、粘土等の粘性土を混入して間
詰コンクリート壁(13)の強度調節を行なう。型枠
(4)内にセメントミルク(14)を注入するとビース
(9)を分散した泥水(10)は排泥管(5A)を介して地
上へ排出され、型枠(4)内はセメントミルク(14)に
置換えられるけれども、ビース(9)によるセメントミ
ルク(14)中のセメントの濾別捕捉効果によって、セメ
ントが該泥水(10)に混合して排泥管(5A)内に流失す
ることを防止される。かくして型枠(4)内に注入され
たセメントミルク(14)は実質的に泥水(10)と混合す
ることなく泥水(10)と置換され、所定強度の間詰コン
クリート壁(13)が得られるのであるが、この際ビース
(9)はセメントミルク(14)内に残存して間詰コンク
リート壁(13)を補強する充填材となる。本実施例にお
いては、得られた間詰コンクリート壁(13)の強度は12
0〜150kg/cm2とされるが、本発明においては特に間詰コ
ンクリート壁(13)の強度を限定するものではなく、通
常70〜240kg/cm2程度とされる。次いで内側の地山(1
A)を掘削して立坑(1C)を形成した上で型枠(4)の
外側底板(4B)と内側底板(4C)とを撤去するとともに
第10図に示すように内側(掘削側)に鋼鉄製リング(15
A)を取付けて隔壁とする。
After the rebar cage (3) has been built, concrete (11) is cast from the lower portion of the vertical groove (1) in step 3 as shown in FIG. 7 to reinforce the concrete with the rebar cage (3). Form a continuous wall (12). The concrete wall (1
After the formation of 2), cement milk (14) is injected into the mold (4) via the injection pipe (5) in step 4 as shown in FIG. Cast concrete wall (13). At this time, the cement milk (14) used is mixed with a viscous soil such as bentonite or clay to control the strength of the concrete wall (13). When the cement milk (14) is injected into the formwork (4), the muddy water (10) in which the beads (9) are dispersed is discharged to the ground via a mud pipe (5A), and the inside of the formwork (4) is cement milk. Although replaced by (14), the cement is mixed with the muddy water (10) and flows into the mud drain pipe (5A) due to the filtering effect of the cement in the cement milk (14) by the beads (9). Is prevented. Thus, the cement milk (14) poured into the mold (4) is replaced with the muddy water (10) without being substantially mixed with the muddy water (10), and a concrete wall (13) with a predetermined strength is obtained. However, at this time, the beads (9) remain in the cement milk (14) and serve as a filler for reinforcing the filling concrete wall (13). In this embodiment, the strength of the obtained concrete-filled concrete wall (13) is 12
Although it is 0 to 150 kg / cm 2 , in the present invention, the strength of the concrete-filled concrete wall (13) is not particularly limited, and is usually about 70 to 240 kg / cm 2 . Then the inner ground (1
A) is excavated to form a shaft (1C), and then the outer bottom plate (4B) and the inner bottom plate (4C) of the formwork (4) are removed and, as shown in FIG. Steel ring (15
A) is attached to make a partition.

このようにしてシールド機発進到達坑口(15)が構成
されるが、該坑口(15)からシールド機を発進させるに
あたってはまず第11図に示すように立坑(1C)内におい
てシールド機(16)を坑口(15)の鋼鉄製リング(15
A)内に挿入するのであるが、第12図に示すように該鋼
鉄製リング(15A)の内面において外端部側にはエント
ランスパッキング(17A)、その内側にはエアバッグ(1
7B)が取付けられ、該エアバッグ(17B)内には外側か
らエアパイプ(17C)が連絡している。該エアバッグ(1
7B)はワッシャー(17E)を介してボルト(17D)によっ
て鋼鉄製リング(15A)に取付けられる。該エントラン
スパッキング(17A)およびエアバッグ(17B)はスチレ
ン−ブタジエンゴム、アクリロニトリル−ブタジエンゴ
ム、クロロプレンゴム、イソプレンゴム、エチレン−プ
ロピレンゴム、ウレタンゴム、シリコンゴム等の合成ゴ
ムあるいは天然ゴムを材料とする。そして該シールド機
(16)前面空間(18)には潤滑液(19)を充電してシー
ルド機(16)が間詰コンクリート壁(13)を切削する際
の減摩剤とすると同時に該空間(18)に該潤滑液(19)
によって内圧を及ぼし、シールド機(16)先端が間詰コ
ンクリート壁(13)を突破って地山(1B)に貫入する際
の地下水や地山土砂の流入を、エントランスパッキング
(17A)およびエアバッグ(17B)と協働して防ぐ。該潤
滑液は例えば粘土、ベントナイト等を水に分散させた分
散液であり、所望なれば該潤滑液には、ポリアクリル酸
塩、ポリビニルアルコール、カルボキシメチルセルロー
ズ、アルギン酸塩等の潤滑性水溶性合成樹脂が添加され
てもよい。
In this way, the shield machine start arrival wellhead (15) is configured. When the shield machine is started from the wellhead (15), the shield machine (16) is first set in the shaft (1C) as shown in FIG. The wellhead (15) of steel ring (15
A) As shown in FIG. 12, the inner surface of the steel ring (15A) has an entrance packing (17A) on the outer end side and an airbag (1) as shown in FIG.
7B) is attached, and an air pipe (17C) communicates with the inside of the airbag (17B) from the outside. The airbag (1
7B) is attached to the steel ring (15A) by bolts (17D) via washers (17E). The entrance packing (17A) and the airbag (17B) are made of synthetic rubber or natural rubber such as styrene-butadiene rubber, acrylonitrile-butadiene rubber, chloroprene rubber, isoprene rubber, ethylene-propylene rubber, urethane rubber and silicone rubber. . The space (18) in front of the shield machine (16) is charged with a lubricating liquid (19) to be used as a lubricant when the shield machine (16) cuts the filled concrete wall (13), and at the same time, the space (18) is used. 18) The lubricating liquid (19)
The inner surface of the shield machine (16) penetrates the packed concrete wall (13) and penetrates the ground (1B). (17B) to prevent. The lubricating liquid is, for example, a dispersion liquid in which clay, bentonite, or the like is dispersed in water. If desired, the lubricating liquid may include a lubricating water-soluble compound such as polyacrylate, polyvinyl alcohol, carboxymethyl cellulose, or alginate. A resin may be added.

そしてシールド機(16)の発進に先立って間詰コンク
リート壁(13)の鋼管(6)を上方へ引抜く。鋼管
(6)引抜きにあたってはまず鋼管(6)の硬質熱可塑
性プラスチック層(6D)の溶剤導入空間(6E)に該硬質
熱可塑性プラスチック層(6D)を溶解あるいは膨潤させ
る溶剤を導入する。該溶剤の導入は地上から収納筒
(7)の上端に連絡する溶剤パイプ(20)を介して行な
う。本発明に用いられる溶剤としてはメタノール、エタ
ノール、イソプロパノール、n−ブタノール等のアルコ
ール系溶剤、トルエン、キシレンの芳香族系溶剤、酢酸
エチル、酢酸n−ブチル等の酢酸エステル系溶剤、アセ
トン、メチルエチルケトン、メチルイソブチルケトン等
のケトン系溶剤、セロソルブアセテート、n−ブチルセ
ロソルブ等のセロソルブ系溶剤、ジクロルエタン、トリ
クロロエチレン、四塩化炭素等の塩素系溶剤等、好まし
くは毒性の低い有機溶剤が用いられる。該硬質熱可塑性
プラスチック層(6D)が該溶剤と接触すると該硬質熱可
塑性プラスチック層(6D)は膨潤して該鋼管(6)と該
間詰コンクリート壁(13)との間の潤滑層となり、また
溶解して該鋼管(6)と該間詰コンクリート壁(13)と
の間に隙間を形成し、あるいは該硬質熱可塑性プラスチ
ック層(6D)が低発泡体の場合には該溶剤に膨潤収縮す
ることによって該鋼管(6)と該間詰コンクリート壁
(13)との間に隙間を形成する。また鋼棒(8)は発泡
体層(8A)内を滑動する。この場合、鋼棒(8)と発泡
体層(8A)との摩擦抵抗は殆んど無視出来、実質的に引
抜き抵抗は鋼管(6)が該間詰コンクリート壁(13)か
ら引抜かれて収納筒(7)に収納される際の摩擦抵抗に
より支配されるので、鋼棒(8)の引抜き抵抗は坑口
(15)の深度に殆んど関係なくなり、しかも上記摩擦抵
抗は溶剤に膨潤もしくは溶解した硬質熱可塑性プラスチ
ック層(6D)によって極端に低下しているので本発明で
は坑口(15)が大深度に位置していても鋼管(6)の間
詰コンクリート壁(13)からの引抜きは円滑に行なわれ
るのである。
Then, prior to the start of the shield machine (16), the steel pipe (6) of the concrete wall (13) is pulled upward. In drawing out the steel pipe (6), first, a solvent for dissolving or swelling the hard thermoplastic layer (6D) is introduced into the solvent introduction space (6E) of the hard thermoplastic layer (6D) of the steel pipe (6). The introduction of the solvent is carried out from the ground via a solvent pipe (20) communicating with the upper end of the storage cylinder (7). As the solvent used in the present invention, methanol, ethanol, isopropanol, alcohol solvents such as n-butanol, toluene, aromatic solvents such as xylene, ethyl acetate, acetate solvents such as n-butyl acetate, acetone, methyl ethyl ketone, Low-toxic organic solvents such as ketone solvents such as methyl isobutyl ketone, cellosolve solvents such as cellosolve acetate and n-butyl cellosolve, and chlorine solvents such as dichloroethane, trichloroethylene and carbon tetrachloride are used. When the hard thermoplastic layer (6D) comes into contact with the solvent, the hard thermoplastic layer (6D) swells to become a lubricating layer between the steel pipe (6) and the filling concrete wall (13), It also melts to form a gap between the steel pipe (6) and the concrete filling wall (13), or swells and shrinks in the solvent when the hard thermoplastic layer (6D) is a low foam. By doing so, a gap is formed between the steel pipe (6) and the filled concrete wall (13). The steel rod (8) slides in the foam layer (8A). In this case, the frictional resistance between the steel rod (8) and the foam layer (8A) is almost negligible, and the pull-out resistance is substantially reduced when the steel pipe (6) is pulled out from the concrete wall (13). The pull-out resistance of the steel rod (8) is almost independent of the depth of the wellhead (15) because it is governed by the frictional resistance when stored in the cylinder (7), and the frictional resistance swells or dissolves in the solvent. In the present invention, even if the wellhead (15) is located at a large depth, the steel pipe (6) can be smoothly pulled out from the concrete wall (13) even if the wellhead (15) is located at a great depth. It is performed in.

鋼管(6)の鋼棒(8)を介しての引抜きは例えば地
上から油圧ジャッキ、多重式滑車、バイブロ式引抜機等
によって行なわれる。このようにして該鋼管(6)を間
詰コンクリート壁(13)から引抜き第11図点線に示すよ
うに収納筒(7)内に収納した上でシールド機(16)を
第11図矢印方向外側の地山(1B)へ向かって発進させる
のであるが、この際、エアパイプ(17C)からエアバッ
グ(17B)内に空気圧を及ぼし、シールド機(16)のス
キンプレート(16A)に圧接させる。このようにしてシ
ールド機(16)発進時の外側の地山側(1B)からの地下
水や土砂の流入を防止するものであるが、該エントラン
スパッキング(17A)も該シールド機(16)のスキンプ
レート(16A)に圧接しエアバッグ(17B)の密封性を補
助する。該エアバッグ(17B)の内圧は外側の地山側(1
B)からの水圧、土圧あるいはシールド機(16)のジャ
ッキ圧に相当する圧力とし、通常0.5〜10気圧程度とさ
れる。
The steel pipe (6) is pulled out through the steel rod (8), for example, from the ground by a hydraulic jack, a multiple pulley, a vibro puller or the like. In this manner, the steel pipe (6) is pulled out from the concrete-filled concrete wall (13) and stored in the storage cylinder (7) as shown by the dotted line in FIG. At this time, air pressure is applied from the air pipe (17C) to the inside of the airbag (17B) to be pressed against the skin plate (16A) of the shield machine (16). In this way, the ground packing (17A) prevents the inflow of groundwater and earth and sand from the outer ground side (1B) when the shield machine (16) starts, and the entrance packing (17A) also has a skin plate of the shield machine (16). (16A) is pressed against to assist the airbag (17B) in sealing. The internal pressure of the airbag (17B) is
The pressure is equivalent to the water pressure, earth pressure from B) or the jack pressure of the shield machine (16), and is usually about 0.5 to 10 atm.

上記のようにシールド機(16)は第11図矢印方向に進
み坑口(15)の間詰コンクリート壁(13)を切削し、突
破って発進して地山側(1B)に貫入するのである。
As described above, the shield machine (16) moves in the direction of the arrow in FIG. 11, cuts the concrete wall (13) of the wellhead (15), breaks through, starts, and penetrates the ground side (1B).

第13図にはシールド機(16)が鉄筋コンクリート連続
壁(12)の坑口(15)の外側の地山(1B)から到達する
状態が示される。上記シールド機(16)到達の場合には
坑口(15)の鋼鉄製リング(15A)に更に鋼製受箱(15
B)を取付けておき、該鋼製受箱(15B)内には外側の地
山(1B)から及ぼされる水圧および土圧に対坑するため
に土砂(19A)が充填せられる。
FIG. 13 shows a state in which the shield machine (16) arrives from the ground (1B) outside the wellhead (15) of the reinforced concrete continuous wall (12). When the shield machine (16) is reached, a steel ring (15A) is added to the steel ring (15A) at the wellhead (15).
B) is attached, and the steel receiving box (15B) is filled with earth and sand (19A) to counter the water pressure and earth pressure exerted from the outer ground (1B).

シールド機(16)の到達坑口(15)への到達に先立っ
てシールド機(16)発進の場合と同様に鋼棒(8)を介
して鋼管(6)を間詰コンクリート壁(13)から引抜く
のであるが、この際、鋼管(6)に電流を流すことによ
り該鋼管(6)を介して硬質熱可塑性プラスチック層
(6D)を加熱軟化させる。かくして軟化した硬質熱可塑
性プラスチック層(6D)は鋼管(6)と間詰コンクリー
ト壁(13)との潤滑層となり、あるいは該硬質熱可塑性
プラスチック層(6D)が低発泡構造を有する場合には体
積収縮して該鋼管(6)と間詰コンクリート壁(13)と
の間に隙間を生じ、該鋼管(6)を該間詰コンクリート
壁(13)から引抜く際の摩擦抵抗が極端に低下する。
Prior to the shield machine (16) reaching the arrival wellhead (15), the steel pipe (6) is pulled from the concrete wall (13) through the steel rod (8) in the same manner as when the shield machine (16) is started. At this time, the hard thermoplastic layer (6D) is heated and softened through the steel pipe (6) by passing an electric current through the steel pipe (6). The hardened thermoplastic layer (6D) thus serves as a lubricating layer between the steel pipe (6) and the concrete wall (13), or the volume if the rigid thermoplastic layer (6D) has a low foaming structure. Shrinkage causes a gap between the steel pipe (6) and the filled concrete wall (13), and the frictional resistance when the steel pipe (6) is pulled out from the filled concrete wall (13) is extremely reduced. .

このようにして鋼棒(8)を介して鋼管(6)を間詰
コンクリート壁(13)から引抜いて収納筒(7)に収納
した上で、外側の地山(1B)から第13図矢印に示すよう
に到達したシールド機(6)は間詰コンクリート壁(1
3)を切削し、突破って鋼製受箱(15B)内の土砂(19
A)を削りながら該鋼製受箱(15B)内に収納される。そ
の後収納状態のシールド機(16)の背面に止水剤の注入
硬化等の手段により止水処理を行なった上で鋼製受箱
(15B)を解体し、該シールド機(16)を埋設しあるい
は回収作業を行なう。
In this way, the steel pipe (6) is pulled out from the filling concrete wall (13) through the steel rod (8) and stored in the storage tube (7), and then the arrow shown in FIG. As shown in the figure, the shield machine (6) reached the concrete wall (1)
3) Cut and break through the soil (19B) in the steel receiving box (15B).
A) is stored in the steel receiving box (15B) while shaving. After that, after stopping the water treatment on the back surface of the shield machine (16) in the housed state by means of injection and hardening of a water stopping agent, the steel receiving box (15B) is dismantled, and the shield machine (16) is buried. Alternatively, a collection operation is performed.

【図面の簡単な説明】[Brief description of the drawings]

第1図〜第12図は本発明の一実施例を示すものであり、
第1図は鉄筋籠建込み状態の立溝部分側断面図、第2図
は型枠の外側底板切欠き正面図、第3図は型枠の縦断面
図、第4図は鋼管下端部縦断面図、第5図は鋼管横断面
図、第6図は収納筒上部分縦断面図、第7図はコンクリ
ート打設状態の立溝部分側断面図、第8図は型枠中にセ
メントミルクを注入状態の立溝部分側断面図、第9図は
間詰コンクリート壁形成状態の立溝部分側断面図、第10
図は鋼鉄製リング取付け状態の鉄筋コンクリート連続壁
部分側断面図、第11図はシールド機発進時の説明図、第
12図はシールド部分拡大断面図、第13図は本発明の他の
実施例を示すシールド機到達時の説明図である。 図中、(1)……立溝、(2)……安定液、(3)……
鉄筋籠、(4)……型枠、(6)……鋼管、(9)……
ビーズ、(10)……泥水、(13)……間詰コンクリート
壁、(14)……セメントミルク、(15)……坑口、(15
A)……鋼鉄製リング、(16)……シールド機、
1 to 12 show an embodiment of the present invention.
FIG. 1 is a side sectional view of a standing groove portion in a state in which a reinforcing cage is built, FIG. 2 is a front view of a cutout of an outer bottom plate of a formwork, FIG. 3 is a longitudinal sectional view of the formwork, and FIG. 5, FIG. 5 is a cross-sectional view of a steel pipe, FIG. 6 is a vertical cross-sectional view of an upper part of a storage tube, FIG. 7 is a side cross-sectional view of a vertical groove in a concrete casting state, and FIG. FIG. 9 is a side sectional view of a vertical groove portion in a state where a filling concrete wall is formed, FIG.
Fig. 11 is a side sectional view of a reinforced concrete continuous wall with a steel ring attached. Fig. 11 is an explanatory view when a shield machine is started.
FIG. 12 is an enlarged sectional view of a shield part, and FIG. 13 is an explanatory view of another embodiment of the present invention when the shield machine is reached. In the figure, (1) ... vertical groove, (2) ... stable liquid, (3) ...
Reinforcing cage, (4) ... formwork, (6) ... steel pipe, (9) ...
Beads, (10) ... muddy water, (13) ... concrete-filled concrete wall, (14) ... cement milk, (15) ... wellhead, (15)
A) ... steel ring, (16) ... shield machine,

Claims (2)

(57)【特許請求の範囲】(57) [Claims] 【請求項1】安定液を注入しつゝ掘削機にて地盤を掘削
して立溝を形成する工程1 該立溝内にシールド機発進到達坑口相当部に型枠を組込
んだ鉄筋籠を建込み該型枠内には比重1.0〜1.2のビーズ
を分散した泥水を充填する工程2 該立溝内下部よりコンクリートを打設する工程3 該型枠内にセメントミルクを注入し該泥水と置換してシ
ールド機発進到達坑口相当部に間詰コンクリート壁を打
設する工程4 上記のようにして地下鉄筋コンクリート連続壁を形成し
た後、その内側の地山を掘削して立坑を形成する工程5 該型枠を解体撤去するとともに該立坑側から該坑口相当
部に隔壁を取付ける工程6 以上の工程1,2,3,4,5,6からなる地下鉄筋コンクリート
連続壁工法
1. A step of forming a vertical groove by excavating the ground with an excavator by injecting a stabilizing liquid. 1. A reinforcing cage having a formwork incorporated at a portion corresponding to a wellhead for starting a shield machine in the vertical groove. Step 2: Filling the form with muddy water in which beads having a specific gravity of 1.0 to 1.2 are dispersed. Step 2: Placing concrete from the lower part of the vertical groove. Step 3: Inject cement milk into the form to replace the muddy water. Step 4 of placing a filled concrete wall at a portion corresponding to the entrance of the shield machine starting arrival and forming the continuous subway reinforced concrete wall as described above, and then excavating the ground inside to form a shaft 5 Step 6 of dismantling and removing the formwork and attaching a bulkhead from the side of the shaft to the part corresponding to the wellhead. Subway reinforced concrete continuous wall method consisting of the above steps 1, 2, 3, 4, 5, and 6
【請求項2】前記型枠内には前記間詰コンクリート壁の
補強材が予め上方に引抜き可能に組込まれている請求項
1に記載の地下鉄筋コンクリート連続壁工法
2. The subway reinforced concrete continuous wall construction method according to claim 1, wherein a reinforcing material for the filling concrete wall is incorporated in the formwork in advance so as to be able to be pulled upward.
JP23791690A 1990-09-07 1990-09-07 Subway reinforced concrete wall construction method Expired - Lifetime JP2891431B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP23791690A JP2891431B2 (en) 1990-09-07 1990-09-07 Subway reinforced concrete wall construction method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP23791690A JP2891431B2 (en) 1990-09-07 1990-09-07 Subway reinforced concrete wall construction method

Publications (2)

Publication Number Publication Date
JPH04118497A JPH04118497A (en) 1992-04-20
JP2891431B2 true JP2891431B2 (en) 1999-05-17

Family

ID=17022346

Family Applications (1)

Application Number Title Priority Date Filing Date
JP23791690A Expired - Lifetime JP2891431B2 (en) 1990-09-07 1990-09-07 Subway reinforced concrete wall construction method

Country Status (1)

Country Link
JP (1) JP2891431B2 (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN105545315A (en) * 2015-12-29 2016-05-04 上海市基础工程集团有限公司 Normal pressure tool replacing method for reinforcing excavation face soil layer in shield tunnel construction

Families Citing this family (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR100383452B1 (en) * 2000-06-01 2003-05-12 주식회사 동아지질 Wall composition structure of working hole in underground turnel
JP5840551B2 (en) * 2012-03-30 2016-01-06 大成建設株式会社 Underground wall structure and core removal method
CN107420108A (en) * 2017-08-07 2017-12-01 北京市市政四建设工程有限责任公司 A kind of shield launching sealing device

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN105545315A (en) * 2015-12-29 2016-05-04 上海市基础工程集团有限公司 Normal pressure tool replacing method for reinforcing excavation face soil layer in shield tunnel construction

Also Published As

Publication number Publication date
JPH04118497A (en) 1992-04-20

Similar Documents

Publication Publication Date Title
JP2891431B2 (en) Subway reinforced concrete wall construction method
EP2084331B1 (en) A method of constructing a pile
JP2824479B2 (en) Starting shaft structure in shield method
JPH094353A (en) Vertical hole excavating device
JP3077747B2 (en) Method and apparatus for removing concrete at pile head extra
JP3187887B2 (en) Starting shaft structure in shield method
JP4311676B2 (en) Construction method using casing
JP4872561B2 (en) Construction method of ready-made piles
JP4449532B2 (en) Rapid construction method of shaft by convex joint of deep bottom shaft
JP5282542B2 (en) Ground deformation prevention method and ground deformation prevention structure
JP3803753B2 (en) Tunnel construction method
JPH0613766B2 (en) Construction method of open-ended pile foundation
JPH01182410A (en) Method of building cast-in-place concrete pile
JP4273015B2 (en) Stabilization method of excavated soil in shield method
JP2004150070A (en) Treatment method for removed soil, and removed soil-treated construction method for foundation pile
JP4521848B2 (en) Earth removal backfill hole forming device
JP2001090060A (en) Driving method for pile and constructing method for cut- off wall using the method
JPH08209687A (en) Partial casing pile construction method
JP3074490B2 (en) Starting the shield machine
JPH05132929A (en) Development method of hollow cast-in-place pile
JPH04231593A (en) Method of constructing base of deeper depth vertical shaft constructed with vertical type shield machine
JPH10140557A (en) Construction method of cast-in-place diaphragm wall with hollow
JPH1122373A (en) Building method for arrival or starting manhole in advancing method
KR101043446B1 (en) Complex pipe pile for reinforcing ground structure
JP5526532B2 (en) Shielding machine settlement prevention method and settlement prevention structure