JP2858205B2 - Reinforcing bar mounting method and rebar mounting device used for the same - Google Patents

Reinforcing bar mounting method and rebar mounting device used for the same

Info

Publication number
JP2858205B2
JP2858205B2 JP6024841A JP2484194A JP2858205B2 JP 2858205 B2 JP2858205 B2 JP 2858205B2 JP 6024841 A JP6024841 A JP 6024841A JP 2484194 A JP2484194 A JP 2484194A JP 2858205 B2 JP2858205 B2 JP 2858205B2
Authority
JP
Japan
Prior art keywords
main
bar
reinforcing
reinforcing bar
bars
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
JP6024841A
Other languages
Japanese (ja)
Other versions
JPH07216877A (en
Inventor
栄 中井
雅孝 魚住
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Mitsui Construction Co Ltd
Original Assignee
Mitsui Construction Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Mitsui Construction Co Ltd filed Critical Mitsui Construction Co Ltd
Priority to JP6024841A priority Critical patent/JP2858205B2/en
Publication of JPH07216877A publication Critical patent/JPH07216877A/en
Application granted granted Critical
Publication of JP2858205B2 publication Critical patent/JP2858205B2/en
Anticipated expiration legal-status Critical
Expired - Fee Related legal-status Critical Current

Links

Landscapes

  • Piles And Underground Anchors (AREA)
  • Load-Engaging Elements For Cranes (AREA)

Description

【発明の詳細な説明】DETAILED DESCRIPTION OF THE INVENTION

【0001】[0001]

【産業上の利用分野】本発明は、現場打設コンクリート
によって深礎杭を構築する際に適用するに好適な鉄筋建
て込み方法及びこれに用いる鉄筋建て込み装置に関す
る。
BACKGROUND OF THE INVENTION 1. Field of the Invention The present invention relates to a method for building a reinforcing bar suitable for use when constructing a deep foundation pile using cast-in-place concrete, and a reinforcing bar building apparatus used therefor.

【0002】[0002]

【従来の技術】従来、コンクリート杭を補強するための
鉄筋を縦穴中に建て込む際には、縦穴内に鉄筋部材を搬
入し、該縦穴坑内において作業員が鉄筋部材を1本づつ
組み立てていく方法がある。しかし、この方法は、深く
狭い坑内での作業となるため作業環境が悪く、また、作
業者が居る縦穴坑内にクレーン等によって鉄筋材料を供
給する必要があるため、吊り荷の落下の危険性もあっ
て、安全性の問題がある。そこで、工場や現場付近にお
いて、あらかじめ鉄筋籠を製作して、現地に運搬を行
い、クレーン等によって、該鉄筋籠を吊り下げる形で、
縦穴中に建て込む方法も知られている。こうした鉄筋籠
方式は、工期が早く、また、坑内人力作業がいらないこ
とによって、安全性が高い。
2. Description of the Related Art Conventionally, when a reinforcing bar for reinforcing a concrete pile is built in a vertical hole, a reinforcing member is carried into the vertical hole, and an operator assembles the reinforcing members one by one in the vertical hole. There is a way. However, this method has a poor working environment because it requires work in a deep and narrow mine.In addition, since it is necessary to supply reinforced material by a crane or the like into a vertical pit where workers are located, there is also a danger of falling suspended loads. There is a safety issue. Therefore, in the vicinity of a factory or site, a reinforcing rod cage is manufactured in advance, transported to the site, and the reinforcing rod cage is suspended by a crane or the like.
It is also known to build it in a vertical hole. Such a rebar cage system has high safety because the construction period is short and no manual work is required in the mine.

【0003】[0003]

【発明が解決しようとする課題】しかし、このような鉄
筋籠は、深礎杭のように、深さがあり、大口径のコンク
リート杭に適用しようとすると、予め組み立てられた状
態の鉄筋籠が非常に大型になってしまう。従って、大口
径深礎杭を構築したい場合、特にこれが山岳部における
橋脚用のものであるときには、組み立てられた鉄筋籠を
現地に運搬することが非常に困難になる。また、たと
え、運搬が出来たとしても、組立て済みの大型鉄筋籠の
運搬には、大型の運搬車が必要になるので、運搬コスト
が過大になる。さらに、縦穴内に建て込む際にも、組立
て済鉄筋籠の重量に見合った大型のクレーンが必要にな
るが、こうした山岳の現場は、施工ヤードが極めて限定
されているので、大型のクレーンの搬入及びその設置が
出来ない場合がある。従って、こうした鉄筋籠は、経済
性や、施工制約によって制限を受ける形で、大口径の深
礎杭の施工に適用されることは稀であった。そこで本発
明は、上記事情に鑑み、大型のクレーンや運搬車を必要
とすることなく、小スペースで、経済的に、坑外組立て
を可能にした、安全な鉄筋建て込み方法及び鉄筋建て込
み装置を提供するものである。
However, when such a reinforcing cage is applied to a large-diameter concrete pile having a depth such as a deep foundation pile, the reinforcing cage in a pre-assembled state is required. It becomes very large. Therefore, when it is desired to construct a large-diameter deep foundation pile, particularly when the pile is used for a pier in a mountainous area, it is extremely difficult to transport the assembled reinforcing cage to the site. Further, even if the transportation is possible, the transportation of the assembled large reinforced cage requires a large-sized transportation vehicle, so that the transportation cost becomes excessive. In addition, a large crane that matches the weight of the pre-assembled reinforced cage is required when building in a vertical hole.However, at such mountainous sites, construction yards are extremely limited, And its installation may not be possible. Therefore, such reinforced cages are rarely applied to the construction of large-diameter deep foundation piles in a form that is limited by economy and construction restrictions. In view of the above circumstances, the present invention has been made in consideration of the above circumstances, and does not require a large crane or a transport vehicle. Is provided.

【0004】[0004]

【課題を解決するための手段】即ち本発明は、地面(2
a)から掘り下げられた縦穴(3)に、複数の主筋(3
7a)と複数の配力筋(37b)によるコンクリート補
強用の鉄筋組立体(37)を建て込む際に、前記縦穴
(3)に、主筋保持手段(9)を、前記縦穴の坑外から
昇降装置により該縦穴内で下降自在に設置し、複数の主
筋(37a)を、該複数の主筋(37a)の各々の配筋
位置に対応させた形で前記主筋保持手段(9)に縦に保
持させ、前記縦穴(3)の口元(3a)付近で前記複数
の配力筋(37b)の各々を、前記主筋保持手段(9)
に保持された複数の主筋(37a)に交差するよう該主
筋(37a)に接続しながら、前記主筋保持手段(9)
、前記縦穴の坑外から前記昇降装置を介して該縦穴内
下方に移動させることによって、前記複数の配力筋
(37b)が接続された複数の主筋(37a)を、前記
鉄筋組立体(37)として、該鉄筋組立体を前記主筋保
持手段上に搭載保持した形で、前記縦穴(3)中に降ろ
していくようにして、構成される。また、本発明は、フ
レーム(6)を有し、前記フレーム(6)に主筋配筋手
段(7)を設け、前記主筋配筋手段(7)に複数の主筋
配置部(71)を、該主筋配置部(71)に対して主筋
(37a)を上下に移動自在にそれぞれ保持し得るよう
に設け、前記主筋配筋手段(7)の下方に主筋保持手段
(9)を、上下に移動自在に設け、前記フレーム(6)
に、前記主筋保持手段(9)を上下に移動駆動位置決め
自在な昇降装置(10)を設け、前記主筋配筋手段
(7)の主筋配置部(71)と前記主筋保持手段(9)
の間に主筋(37a)をセットし得るようにしたことを
特徴として、鉄筋建て込み装置(5)が構成される。ま
た、本発明において、前記主筋配置部(71)は、建て
込むべき主筋(37a)の配筋ピッチに対応した形で形
成して、構成される。また、本発明において、前記主筋
配筋手段(7)には主筋固定具(72)を、前記複数の
主筋配置部(71)の各々に主筋(37a)を水平方向
に入れ込み自在に設けて、構成される。また、本発明に
おいて、前記主筋配筋手段(7)と前記主筋保持手段
(9)の間に鉄筋建て込み位置決め具(8)を、前記主
筋配筋手段(7)と整合した位置に配置する形で上下方
向に並べて設けて、構成される。また、本発明におい
て、配力筋保持手段(17)を、配力筋建て込み位置の
内方から外側に向けて移動自在に設け、該配力筋保持手
段(17)には複数の配力筋保持部(191)を、上下
方向に所定の間隔をなすよう複数設けて、構成される。
なお、()内の番号等は、図面における対応する要素を
示す、便宜的なものであり、従って、本記述は図面上の
記載に限定拘束されるものではない。以下の作用の欄に
ついても同様である。
In other words, the present invention relates to a method for controlling the ground (2)
In the vertical hole (3) dug from a), several main reinforcements (3
7a) and a reinforcing bar assembly (37) for reinforcing concrete with a plurality of distributing bars (37b), the main bar holding means (9) is inserted into the vertical hole (3) from outside of the vertical hole.
A plurality of main bars (37a) are vertically installed in the main bar holding means (9) in a form corresponding to each bar arrangement position of the plurality of main bars (37a). And holding each of the plurality of force-feeding muscles (37b) near the mouth (3a) of the vertical hole (3) with the main muscle holding means (9).
The main muscle holding means (9) is connected to the main muscles (37a) so as to intersect with the plurality of main muscles (37a) held by the main muscles (37a).
From the outside of the vertical hole through the lifting device to the inside of the vertical hole.
By moving the plurality of main reinforcing bars (37a) to which the plurality of force bars (37b) are connected as the reinforcing bar assemblies (37), the reinforcing bar assemblies are connected to the main reinforcing bars.
It is configured so as to be lowered into the vertical hole (3) while being mounted and held on the holding means . Further, the present invention has a frame (6), a main bar arrangement means (7) is provided on the frame (6), and the main bar arrangement means (7) is provided with a plurality of main reinforcement arrangement portions (71). The main bar (37a) is provided so as to be vertically movable with respect to the main bar arranging portion (71), and the main bar holding means (9) is vertically movable below the main bar arranging means (7). The frame (6)
The main bar holding means (9) is provided with a vertically movable device (10) capable of vertically moving and driving the main bar holding means (9), and the main bar arranging portion (71) of the main bar arranging means (7) and the main bar holding means (9).
A main reinforcing bar (37a) can be set between the reinforcing bars, thereby constituting a reinforcing bar setting device (5). Further, in the present invention, the main bar arrangement portion (71) is formed and formed in a shape corresponding to the bar arrangement pitch of the main bar (37a) to be erected. In the present invention, the main bar arrangement means (7) is provided with a main bar fixing device (72), and the main bar (37a) is provided in each of the plurality of main bar arrangement portions (71) so as to be freely inserted in a horizontal direction, Be composed. Further, in the present invention, a reinforcing bar locating tool (8) is arranged between the main reinforcing bar arrangement means (7) and the main reinforcing bar holding means (9) at a position aligned with the main reinforcing bar arrangement means (7). It is configured by being arranged in the vertical direction in the form. In the present invention, the distribution muscle holding means (17) is movably provided from the inside to the outside of the distribution muscle building position, and the distribution muscle holding means (17) includes a plurality of distribution muscles. A plurality of streak holders (191) are provided at predetermined intervals in the vertical direction.
It should be noted that the numbers and the like in parentheses are for convenience and indicate the corresponding elements in the drawings, and therefore, the present description is not limited to the descriptions on the drawings. The same applies to the following operation columns.

【0005】[0005]

【作用】上記した構成により、本発明は、縦穴(3)の
口元(3a)付近において、主筋保持手段(9)によっ
て所定の配筋状態に保持された複数の主筋(37a)に
複数の配力筋(37b)を接続していく作業により鉄筋
組立を行い、また、主筋保持手段(9)を下方に移動さ
せることによって、該組み立てられた鉄筋組立体(3
7)の建て込み作業を行うように作用する。また、本発
明は、主筋配筋手段(7)の主筋配置部(71)と主筋
保持手段(9)の間にセットした主筋(37a)は、昇
降装置(10)を介しての主筋保持手段(9)の上下移
動によって上下に移動し、この際、主筋配置部(71)
に対して上下に相対移動するように作用する。また、本
発明において、主筋配筋手段(7)の主筋配置部(7
1)と主筋保持手段(9)の間に複数の主筋(37a)
が、該主筋(37a)の配筋ピッチに対応した形でセッ
トされるように作用する。また、本発明において、主筋
(37a)を主筋配置部(71)に入れ込む形でセット
したとき、主筋固定具(72)は、該セットされた主筋
(37a)が主筋配置部(71)から水平方向に外れる
のを防止するように作用する。また、本発明において、
主筋保持手段(9)が鉄筋建て込み位置決め具(8)に
整合配置したときに、該主筋保持手段(9)は主筋配筋
手段(7)と整合位置に配置するように作用する。ま
た、本発明において、主筋配筋手段(7)の主筋配置部
(71)と主筋保持手段(9)間にセットした複数の主
筋(37a)の内方側から外側に向けて、配力筋保持手
段(17)の配力筋保持部(191)をそれぞれ突出配
置出来るように作用する。
With the above construction, the present invention provides a plurality of main bars (37a) held in a predetermined bar arrangement state by the main bar holding means (9) near the mouth (3a) of the vertical hole (3). The rebar is assembled by connecting the rebars (37b), and the main rebar holding means (9) is moved downward, so that the rebar assembly (3) is assembled.
It works so as to perform the setting work of 7). Further, according to the present invention, the main muscle (37a) set between the main muscle arranging portion (71) of the main muscle arrangement means (7) and the main muscle holding means (9) is connected to the main muscle holding means via the elevating device (10). It moves up and down by the up and down movement of (9), and at this time, the main bar arrangement section (71)
Acts to move up and down relative to. Further, in the present invention, the main muscle arrangement section (7) of the main muscle arrangement means (7).
A plurality of main bars (37a) between 1) and the main bar holding means (9);
Acts so as to be set in a form corresponding to the bar arrangement pitch of the main bar (37a). In the present invention, when the main bar (37a) is set so as to be inserted into the main bar arranging portion (71), the main bar fixing device (72) moves the set main bar (37a) from the main bar arranging portion (71). Acts to prevent horizontal disengagement. In the present invention,
When the main-bar holding means (9) is aligned with the reinforcing-bar locating tool (8), the main-bar holding means (9) acts so as to be positioned at an alignment position with the main-bar reinforcing means (7). Further, in the present invention, a plurality of main muscles (37a) set between the main muscle arranging portion (71) of the main muscle arrangement means (7) and the main muscle holding means (9) extend from the inner side to the outer side. The distribution force holding portions (191) of the holding means (17) function so as to be protrudingly arranged.

【0006】[0006]

【実施例】図1は本発明による鉄筋建て込み装置の一実
施例を用いて鉄筋建て込み作業を行っている杭施工現場
の様子を示す一部破断斜視図、図2は図1に示す杭施工
現場の坑口付近を示す拡大図、図3は図1に示す鉄筋建
て込み装置のゲージディスクを部分を示す平面図、図4
は図3に示すゲージディスクのIV矢視部分の拡大図、図
5は図1に示す鉄筋建て込み装置のスライドガイド部分
を示す平面図、図6は図1に示す鉄筋建て込み装置の下
部フレーム枠におけるVI矢視部分の断側面図、図7は図
1に示す鉄筋建て込み装置に鉄筋吊り下げ治具を用いて
主筋を装着している様子を示す図、図8(a)乃至
(c)は図1に示す杭施工現場において主筋に配力筋を
溶接する様子を示す図である。
1 is a partially cutaway perspective view showing a state of a pile construction site in which a reinforcing bar is erected using an embodiment of a reinforcing bar embedding device according to the present invention. FIG. 2 is a perspective view showing a pile shown in FIG. FIG. 3 is an enlarged view showing the vicinity of a wellhead at a construction site, FIG. 3 is a plan view showing a part of a gauge disk of the reinforcing bar erection device shown in FIG. 1, and FIG.
FIG. 5 is an enlarged view of a portion of the gauge disk shown in FIG. 3 as viewed in the direction of arrow IV. FIG. 5 is a plan view showing a slide guide portion of the reinforcing bar erection device shown in FIG. FIG. 7 is a cross-sectional side view of a portion of the frame as viewed in the direction of arrow VI. FIG. 7 is a view showing a state in which main reinforcing bars are attached to the reinforcing bar building apparatus shown in FIG. 1 using a reinforcing bar hanging jig, and FIGS. 2) is a diagram showing a manner in which the distribution bars are welded to the main bars at the pile construction site shown in FIG. 1.

【0007】杭施工を行っている現場1には、図1に示
すように、後に杭30になるための縦穴3が、地面2a
から地中2に掘り下げられた形で、所定の径D1をなす
円柱状に形成されており、縦穴3の側壁3cには仮支保
用のモルタル36が、該縦穴3の口元部分である坑口3
aと穴底3bを接続する形で、円環状に吹き付け打設さ
れている。また、現場1には、鉄筋建て込み装置5が、
上記杭30のため、即ちコンクリート補強用の鉄筋を鉄
筋組立体である鉄筋籠37として、縦穴3中に建て込み
するために設けられており、鉄筋籠37は、その全体外
観形状が円筒状をなすように形成されている。鉄筋籠3
7は、その各々が上下方向即ち縦に伸延する形で縦穴3
の側壁3cに沿って並ぶ複数の主筋37aと、その各々
が該複数の主筋37aに交差する形で横に伸延するよ
う、これ等複数の主筋37aに溶接接続された複数の配
力筋37bによって構成されており、いま、鉄筋籠37
は、鉄筋建て込み装置5を介して、主筋37aと配力筋
37bの接続作業を行いながら、縦穴3中に建て込みさ
れつつある。なお、配力筋37bは、図2右部に示すよ
うに、その現場1への搬入形状がそれぞれ半円状をなす
形に形成されており、該半円状の配力筋37bを2本1
対にして円形状にラップ溶接することによって、1本の
配力筋37bが構成されるものである。
[0007] At the site 1 where the pile is being constructed, as shown in FIG.
The hole 3 is formed into a columnar shape having a predetermined diameter D1 in a shape dug into the ground 2 from below, and a mortar 36 for temporary support is provided on a side wall 3c of the vertical hole 3 in a wellhead 3 serving as a mouth portion of the vertical hole 3.
a and is connected to the hole bottom 3b by being sprayed in an annular shape. In addition, on the site 1, a reinforcing bar building device 5 is provided.
It is provided for the above-mentioned pile 30, that is, a reinforcing bar for concrete reinforcement is built in the vertical hole 3 as a reinforcing bar cage 37 which is a reinforcing bar assembly. It is formed so as to form. Reinforcing basket 3
7 are vertical holes 3 each extending vertically.
And a plurality of force distribution bars 37b welded to the plurality of main bars 37a so that each of the main bars 37a extends along the side walls 3c so as to intersect with the plurality of main bars 37a. It is now composed of reinforced cage 37
Is being built into the vertical hole 3 while connecting the main reinforcing bar 37a and the force distribution bar 37b via the reinforcing bar mounting device 5. As shown in the right part of FIG. 2, each of the force distribution bars 37b is formed into a semicircular shape to be carried into the site 1, and two of the semicircular force distribution bars 37b are formed. 1
One pair of force distribution bars 37b is formed by lap welding in a pair in a circular shape.

【0008】鉄筋建て込み装置5は、図1に示すよう
に、フレーム6を有しており、フレーム6は、その4本
の支柱61の脚部61aによって、地面2a上に立設支
持されている。フレーム6の上端部には、中抜け円盤状
に形成されたゲージディスクが、4本の梁62を介し
て4本の支柱61に接続された形で、該4本の支柱の真
中部分に、主筋配筋手段として設けられており、ゲージ
ディスクには、図3に示すように、複数の主筋配置部
71が、該ゲージディスク7の外周に沿って所定のピッ
チP1毎に形成されている。ゲージディスク7に形成さ
れた複数の主筋配置部71は、建て込むべき主筋37a
の配筋ピッチに対応した形で形成されており、実施例に
おいては、主筋配置部71の形成ピッチが5cm程度に
形成されていることによって、主筋37aの配筋ピッチ
を10、15、20cm等の5の整数倍ピッチから選択
し得るようになっている。
As shown in FIG. 1, the reinforcing bar embedding device 5 has a frame 6. The frame 6 is supported upright on the ground 2 a by the legs 61 a of the four columns 61. I have. At the upper end of the frame 6, a gauge disk 7 formed in a hollow disk shape is connected to four pillars 61 via four beams 62, and is provided in the middle part of the four pillars. is provided as a main reinforcement reinforcement means, the gauge disk 7, as shown in FIG. 3, a plurality of main reinforcement placement portion 71, are formed at predetermined pitch P1 along the periphery of the gauge disk 7 I have. The plurality of main bar arrangement portions 71 formed on the gauge disk 7 are provided with main bars 37a to be built.
In the example, the formation pitch of the main reinforcement arrangement portion 71 is formed to be about 5 cm, so that the reinforcement arrangement pitch of the main reinforcement 37a is set to 10, 15, 20 cm or the like. The pitch can be selected from a pitch of an integral multiple of 5.

【0009】ゲージディスク7の各主筋配置部71に
は、図4に示すように、杭30の配筋主筋径に対応した
径の主筋37aが、それぞれ1本づつ収容自在になって
おり、また主筋配置部71は、主筋37aを図4紙面と
交差方向である上下方向に移動自在にそれぞれ保持し得
るようになっている。さらに、ゲージディスク7には板
バネ等からなるストッパ72が、主筋固定具として主筋
配置部71の形成数量だけそれぞれの主筋配置部71に
設けられており、ストッパ72は、プレート73によっ
てその一端側をゲージディスク7に固着された形で設け
られている。そして、各ストッパ72は、図4一点鎖線
で示すように、内方側即ち該主筋配置部71側に向かっ
てのみ自在に撓むことが出来るようになっており、これ
によって、ストッパ72は、複数の主筋配置部71の各
々に前記主筋37aを水平方向に入れ込み自在(即ち図
4矢印A方向に向けて嵌入させ得るよう)になってい
る。
As shown in FIG. 4, a main bar 37a having a diameter corresponding to the bar main bar diameter of the pile 30 can be accommodated in each main bar arranging portion 71 of the gauge disk 7, one by one. The main bar arranging portion 71 can hold the main bar 37a so as to be movable in a vertical direction which is a direction intersecting with the plane of FIG. Further, the gauge disk 7 is provided with stoppers 72 made of a leaf spring or the like as main bar fixing members in the respective main bar arranging portions 71 by the number of the main bar arranging portions 71 formed. Is fixed to the gauge disk 7. Each of the stoppers 72 can freely bend only toward the inner side, that is, toward the main bar placement portion 71, as shown by the one-dot chain line in FIG. The main bar 37a can be freely inserted in each of the plurality of main bar arranging portions 71 in the horizontal direction (that is, can be fitted in the direction of arrow A in FIG. 4).

【0010】また、フレーム6の下部には、図1に示す
ように、円環状に形成されたスライドガイド8が、4本
の梁63を介して前記4本の支柱61に接続支持された
形で鉄筋建て込み位置決め具として設けられており、ス
ライドガイド8は、図2に示すように、前記地面2aよ
り若干上の坑口3a上に配置する形、即ち作業員39の
足元付近の高さ位置に配置する形になっている。また、
スライドガイド8は、前記ゲージディスク7と後述する
下部フレーム枠9の間において、該ゲージディスク7と
整合した位置に配置するよう、該ゲージディスク7と上
下方向に並べて設けられており、スライドガイド8の真
中部分には、図5に示すように、鉄筋挿通空間8sが、
前記鉄筋籠37の外径より若干大きな径D2をなす形で
円形状に形成されている。即ち、スライドガイド8の鉄
筋挿通空間8sは、組立て済み状態の鉄筋籠37を、図
5紙面と交差方向に示す上下方向に通過させ得るように
なっている。
At the lower part of the frame 6, as shown in FIG. 1, a slide guide 8 formed in an annular shape is connected to and supported by the four columns 61 via four beams 63. As shown in FIG. 2, the slide guide 8 is disposed on the wellhead 3a slightly above the ground 2a, that is, a height position near the foot of the worker 39. It is shaped to be placed in. Also,
The slide guide 8 is provided between the gauge disc 7 and a lower frame 9 to be described later, and is arranged vertically with the gauge disc 7 so as to be arranged at a position aligned with the gauge disc 7. As shown in FIG. 5, a reinforcing bar insertion space 8s
The rebar cage 37 is formed in a circular shape with a diameter D2 slightly larger than the outer diameter. That is, the reinforcing-bar insertion space 8s of the slide guide 8 allows the assembled reinforcing-bar cage 37 to pass in the up-down direction shown in a direction intersecting the paper surface of FIG.

【0011】また、フレーム6の上部には、図1又は図
2に示すように、実施例においては3ヶの電動式のチェ
ーンブロック10が、前記ゲージディスク7の底面部分
から垂下するようこれに装着された形で設けられてお
り、3ヶのチェーンブロック10の下方(即ちゲージデ
ィスク7の下方)には、鉄筋建て込み装置5の主筋保持
手段である下部フレーム枠9が、牽引用の何本かのワイ
ヤ11によって該3ヶのチェーンブロック10に吊下さ
れて、縦穴3中を上下に移動自在な形で設けられてい
る。即ち、チェーンブロック10は、下部フレーム枠9
を上下に移動駆動位置決め自在な昇降装置として、フレ
ーム6に設けられており、通常の状態(即ち鉄筋建て込
み作業を行っている間)では、該チェーンブロック10
の操作によって、下部フレーム枠9が、上方側から下方
側に向けて下降移動のみをし得るようになっている。
As shown in FIG. 1 or FIG. 2, in the embodiment, three electric chain blocks 10 are provided on the upper portion of the frame 6 so as to hang from the bottom of the gauge disk 7. Below the three chain blocks 10 (that is, below the gauge discs 7), the lower frame 9 serving as the main reinforcement holding means of the reinforcing bar embedding device 5 is provided in a mounted state. It is suspended from the three chain blocks 10 by a wire 11 and is provided so as to be movable up and down in the vertical hole 3. That is, the chain block 10 is attached to the lower frame 9
Is provided on the frame 6 as a vertically movable device which can be moved and moved up and down, and the chain block 10 is provided in a normal state (that is, while the reinforcing bar is being built).
By this operation, the lower frame 9 can only move downward from the upper side to the lower side.

【0012】下部フレーム枠9は、図1に示すように、
前記モルタル36が吹き付けされた状態の縦穴3の内径
より若干小さな径の円環状に形成されており、下部フレ
ーム枠9の下端部には、図6に示すように、支持部9a
が、該下部フレーム枠9の上端部側に形成された上フラ
ンジ部9bと対向する形で設けられている。下部フレー
ム枠9には、先に述べたように縦穴3の側壁3cに沿っ
て並ぶ複数の主筋37aが、上フランジ部9bに形成さ
れた挿通穴9sを介して支持部9a上に搭載されてお
り、従って、複数の主筋37aに接続された複数の前記
配力筋37bからなる鉄筋籠37は、下部フレーム枠9
に搭載支持されている。また、下部フレーム枠9の支持
部9aの底面側には、図6に示すように、前記縦穴3の
穴底3bに支持され得る形で、支持面9aが円周状に形
成されている。
The lower frame 9 is, as shown in FIG.
The mortar 36 is formed in an annular shape having a diameter slightly smaller than the inner diameter of the vertical hole 3 in a state where the mortar 36 is sprayed, and a lower end of the lower frame 9 has a support portion 9a as shown in FIG.
Are provided so as to face an upper flange portion 9b formed on the upper end side of the lower frame 9. As described above, the plurality of main bars 37a arranged along the side wall 3c of the vertical hole 3 are mounted on the lower frame 9 on the support portion 9a through the insertion holes 9s formed in the upper flange portion 9b. Therefore, the reinforcing bar cage 37 composed of the plurality of force distribution bars 37b connected to the plurality of main bars 37a is connected to the lower frame 9
It is mounted and supported. As shown in FIG. 6, a support surface 9a is formed on the bottom surface side of the support portion 9a of the lower frame 9 so as to be supported by the hole bottom 3b of the vertical hole 3.

【0013】また、下部フレーム枠9には、図1に示す
ように、いくつかのフック保持具12が装着されてお
り、各フック保持具12には、図6に示すように、フッ
ク係合突起12aが、下部フレーム枠9の放射方向内方
において、下側に突する形でそれぞれ設けられている。
そして、フック保持具12は、下部フレーム枠9に接続
された部分とフック係合突起12aとの間にフック配置
溝12bが形成されており、フック保持具12には、フ
ック配置溝12bの下側からフック係合突起12aに引
掛けられた形で、前記ワイヤ11の下端部に接続された
吊輪13が係合保持されている。従って、前述したよう
に下部フレーム枠37が支持している前記鉄筋籠37
は、フック保持具12に係合保持されたワイヤ11を介
して、前記3ヶのチェーンブロック10に吊下支持され
ており、これによって鉄筋籠37は、該チェーンブロッ
ク10が装着されたフレーム6に支持された形になって
いる。なお、ワイヤ11と吊輪13の間には、図6に示
すように、レベル調整ジャッキ15が、該ワイヤ11の
図6矢印B、C方向の長さを調整し得るように設けられ
ており、該レベル調整ジャッキ15を介して、下部フレ
ーム枠9の平衡状態、即ち該下部フレーム枠9に搭載支
持された鉄筋籠37の平衡状態が調整保持され得るよう
になっている。
As shown in FIG. 1, several hook holders 12 are mounted on the lower frame 9, and each hook holder 12 has a hook engaging member as shown in FIG. The protrusions 12a are provided inward in the radial direction of the lower frame 9 so as to protrude downward.
The hook holder 12 has a hook arrangement groove 12b formed between a portion connected to the lower frame 9 and the hook engaging projection 12a. A hanging ring 13 connected to the lower end of the wire 11 is engaged and held by being hooked on the hook engaging projection 12a from the side. Accordingly, as described above, the reinforcing bar cage 37 supported by the lower frame
Are suspended from and supported by the three chain blocks 10 via wires 11 which are engaged and held by hook holders 12, whereby the reinforcing bar cage 37 is attached to the frame 6 on which the chain blocks 10 are mounted. The shape is supported by. As shown in FIG. 6, a level adjusting jack 15 is provided between the wire 11 and the suspension ring 13 so as to adjust the length of the wire 11 in the directions of arrows B and C in FIG. The equilibrium state of the lower frame 9, that is, the equilibrium state of the rebar cage 37 mounted and supported on the lower frame 9 can be adjusted and held through the level adjusting jack 15.

【0014】さらに、鉄筋建て込み装置5のフレーム6
には、図2に示すように、前記ゲージディスク7に装着
された形で4ケの油圧ジャッキ16が設けられており、
それぞれの油圧ジャッキ16には、配力筋保持手段であ
る配力筋受け治具17が、チェーン20を介してそれぞ
れ吊下されている。各配力筋受け治具17は、油圧ジャ
ッキ16を介して図2矢印D、E方向に示す上下方向に
所定長さ分だけ移動自在な形になっており、また、配力
筋受け治具17は、該配力筋受け治具17が吊下されて
いる油圧ジャッキ16の配設位置が、配力筋37bの配
筋時に該配力筋受け治具17を配置させるべき位置より
若干放射方向内方側に寄った形で、配力筋37bを建て
込みするべき位置の内方から外方に向けて移動自在な形
になっている。そして、配力筋受け治具17には、図8
(a)乃至(c)に示すように、複数の配力筋保持部で
ある掛け具191が、前記配力筋37bの配筋ピッチに
対応したピッチで上下方向に所定の間隔をなすよう複数
設けられており、各配力筋受け治具17の上下方向に並
ぶ複数の掛け具191は、ガイド9を介して連結され
た形で、該ガイド9の操作によって、図8矢印F、G
方向に示す放射方向内外方向に所定ストローク分だけ突
出後退自在な形になっている。そして、配力筋受け治具
17は、複数の掛け具191のそれぞれに1本づつの配
力筋37bが搭載保持され得るようになっている。
Further, the frame 6 of the reinforcing-bar building device 5
As shown in FIG. 2, four hydraulic jacks 16 are provided in a form mounted on the gauge disc 7.
Each hydraulic jack 16 has a distribution line receiving jig 17 as a distribution line holding means suspended from a chain 20 . Each distributing muscle receiving jig 17 is movable via a hydraulic jack 16 by a predetermined length in the vertical direction shown by arrows D and E in FIG. Reference numeral 17 denotes a position at which the hydraulic jack 16 on which the power distribution muscle receiving jig 17 is suspended is slightly radiated from a position at which the power distribution muscle receiving jig 17 is to be arranged when the power distribution muscle 37b is arranged. In a form shifted toward the inside in the direction, the force distribution bar 37b is movable from the inside to the outside at the position where the power distribution bar 37b is to be built. 8 is provided in the power distribution muscle receiving jig 17.
As shown in (a) to (c), a plurality of hooks 191 serving as a plurality of force distribution muscle holding portions are arranged at predetermined intervals in the vertical direction at a pitch corresponding to the muscle arrangement pitch of the force distribution muscles 37b. provided, a plurality of hanger 191 arranged in the vertical direction of the distribution force muscle receiving jig 17, in a form linked via a guide 1 9, by the operation of the guide 1 9, 8 arrows F, G
In the radially inward and outward directions shown in FIG. The distributing muscle receiving jig 17 is configured such that one distributing muscle 37b can be mounted and held on each of the plurality of hooks 191.

【0015】ところで、現場1には、図1に示すよう
に、クレーン車40が、縦穴40付近に位置する形で配
置されており、クレーン車40のフックブロック41に
は、鉄筋吊り下げ治具である主筋吊り具21が装着吊下
されている。主筋吊り具21は、図7に示すように、実
施例においては3ヶの鞘管22を有しており、各鞘管2
2の内部には、鉄筋挿通空間である主筋挿通空間22s
が、前記主筋37aを該主筋37aの材軸方向に沿って
(即ち上下に)移動自在に挿通させ得る形で形成されて
いる。3ヶの鞘管22は、連結部材23を介して、前記
主筋37aの配筋ピッチに対応したピッチで水平方向に
並ぶように連結されており、主筋吊り具21の3ヶの鞘
管22は、連結部材23に装着された牽引ワイヤ25、
束ね治具26を介して、前記フックブロック41に吊下
されている。従って、これ等、連結部材23、牽引ワイ
ヤ25、束ね治具26は、3ヶの鞘管22に設けられた
吊下係合手段を構成する形になっており、該吊下係合手
段によって、主筋吊り具21がフックブロック41に吊
下支持されている。
As shown in FIG. 1, a crane truck 40 is disposed at the site 1 so as to be positioned near the vertical hole 40. Is attached and suspended. As shown in FIG. 7, the main bar suspension 21 has three sheath tubes 22 in the embodiment, and each sheath tube 2
2 has a main bar insertion space 22s, which is a reinforcing bar insertion space.
However, the main bar 37a is formed so as to be freely movable along the material axis direction of the main bar 37a (that is, up and down). The three sheath tubes 22 are connected via a connecting member 23 so as to be arranged in a horizontal direction at a pitch corresponding to the bar arrangement pitch of the main bar 37a. A pulling wire 25 attached to the connecting member 23,
It is suspended by the hook block 41 via a bundling jig 26. Accordingly, the connecting member 23, the pulling wire 25, and the bundling jig 26 constitute suspension engaging means provided on the three sheath tubes 22, and the suspension engaging means The main bar suspension 21 is suspended from the hook block 41.

【0016】また、主筋吊り具21には、図7に示すよ
うに、前記主筋37aを把持自在な鉄筋クランプである
クランプ27が、3ヶの鞘管22の下方において、該鞘
管22と1対1をなすように、前記連結部材23、牽引
ワイヤ25、束ね治具26が形成している吊下係合手段
に3ヶ設けられており、各クランプ27は長さL1をな
す接続ワイヤ29を介して前記連結部材23に吊下され
た形で、それぞれの鞘管22と連結接続されている。即
ち、主筋吊り具21は、これが前記吊下係合手段によっ
て、クレーン車40のフックブロック41に吊下されて
いる状態下において、各鞘管22と各クランプ27が、
該クランプ27の重量によって、所定の間隔L1を鉛直
方向に保持し得る形になっており、このとき、3ヶの鞘
管22は、クレーンの牽引力内に介在配置する形で、該
3ヶの鞘管22と3ヶのクランプ27が鉛直方向に並ぶ
ように配置し、これによって、主筋吊り具21は図1に
示すように、主筋37aをその材軸方向を鉛直方向に向
けた形で保持し得るようになっている。
As shown in FIG. 7, a clamp 27, which is a rebar clamp capable of gripping the main bar 37a, is attached to the main bar suspension 21 below the three sheath tubes 22 and one of them. Three pairs are provided on the suspension engaging means formed by the connecting member 23, the pulling wire 25, and the bundling jig 26 so as to form a pair, and each clamp 27 has a connecting wire 29 having a length L1. Are connected to and connected to the respective sheath tubes 22 in a form suspended from the connection member 23 via the connection member. That is, in a state where the main bar suspension tool 21 is suspended by the hook block 41 of the crane truck 40 by the suspension engagement means, each sheath tube 22 and each clamp 27 are
Due to the weight of the clamp 27, a predetermined distance L1 can be held in the vertical direction. At this time, the three sheath tubes 22 are arranged so as to be interposed within the traction force of the crane. The sheath tube 22 and the three clamps 27 are arranged so as to be arranged in the vertical direction, whereby the main bar suspension 21 holds the main bar 37a with the material axis direction of the main bar 37a directed vertically as shown in FIG. It is possible to do.

【0017】現場1は以上のような構成を有しているの
で、該現場1において杭30を構築する際には、縦穴3
を地面2aの所定の位置から所定の径D1をなすように
所定深さ分だけ掘り下げ形成し、その側壁3cにモルタ
ル36を所定厚さに吹き付け施工したところで、鉄筋建
て込み装置5を用いて、該縦穴3に複数の主筋37aと
複数の配力筋37bによる鉄筋籠37を鉄筋組立体とし
て建て込む作業を行う。そこで、まず、鉄筋籠5を建て
込みすべき縦穴3の坑口3aを包囲するように、即ち、
図1に示すように下部フレーム枠9が該縦穴3中を下降
自在な形で、鉄筋建て込み装置5を設置する。この際、
鉄筋建て込み装置5は、フレーム6の中心CL1が、縦
穴3の中心CL1に一致した形になるように設置する。
Since the site 1 has the above configuration, when constructing the pile 30 at the site 1, the vertical holes 3
Is dug down by a predetermined depth so as to form a predetermined diameter D1 from a predetermined position on the ground 2a, and a mortar 36 is sprayed to a predetermined thickness on the side wall 3c. An operation of building the reinforcing bar cage 37 into the vertical hole 3 with the plurality of main bars 37a and the plurality of distribution bars 37b as a reinforcing bar assembly is performed. Therefore, first, the surrounding of the wellhead 3a of the vertical hole 3 where the reinforcing bar 5 is to be built,
As shown in FIG. 1, the reinforcing-bar-building device 5 is installed so that the lower frame 9 can descend in the vertical hole 3. On this occasion,
The reinforcing bar setting device 5 is installed such that the center CL1 of the frame 6 matches the center CL1 of the vertical hole 3.

【0018】そこで、第1に、所定配筋本数の主筋37
aを、その各々の配筋位置に対応させた形で下部フレー
ム枠9に縦に保持させる作業を行う。そこでまず、主筋
吊り具21の3ヶの鞘管22の各々の主筋挿通空間22
sに、図1右奥部に示すように寝かせた状態の主筋37
aを挿通させると共に、該主筋37aの所定の位置(即
ち該主筋37aを縦にしたときに下部になる位置)にク
ランプ27を取り付ける。こうして、3ヶのクランプ2
7に3本の主筋37aを把持させた形にしておいて、束
ね治具26をクレーン車40のフックブロック41に係
合させてから、クレーン操作によって、該フックブロッ
ク41を上方に移動させる。すると、主筋吊り具21
は、主筋37aを把持している各クランプ27が、3ヶ
の鞘管23に設けられた連結部材23、牽引ワイヤ2
7、束ね治具26を吊り下げ係合手段としてクレーン4
0に吊下された形で、縦になる。このように、主筋37
aを寝かせた状態から縦に起こすとき、3本の主筋37
aは、3本の鞘管22によって、水平方向の移動を拘束
された形で起き上がり、また、縦になった主筋37a
は、当該3本の鞘管22による水平方向の拘束力と3本
の主筋37aの自重によってその材軸方向を鉛直方向に
向けるよう保持された形で、3ヶのクランプ27を介し
て主筋吊り具21に吊下された形になる。これによっ
て、3本の主筋37aは、図1に示すように、各主筋3
7aの材軸が撓むことなく、安定的に、主筋吊り具21
を介してフックブロック41に吊下保持される。
Therefore, first, the main bars 37 having a predetermined number of bars are arranged.
a is vertically held by the lower frame 9 in a form corresponding to the respective bar arrangement positions. Therefore, first, the main muscle insertion space 22 of each of the three sheath tubes 22 of the main muscle suspender 21.
In FIG. 1, the main bar 37 in a state of being laid down as shown in the right back of FIG.
a, and the clamp 27 is attached to a predetermined position of the main bar 37a (that is, a position that becomes lower when the main bar 37a is vertically extended). Thus, three clamps 2
After the three main bars 37a are gripped in the shape 7 and the binding jig 26 is engaged with the hook block 41 of the crane truck 40, the hook block 41 is moved upward by the crane operation. Then, the main bar suspension 21
Each of the clamps 27 holding the main bar 37a is connected to the connecting member 23 provided on the three sheath tubes 23,
7. The crane 4 is used as a hanging engagement means with the binding jig 26 suspended.
It hangs at 0 and becomes vertical. Thus, the main line 37
When a is raised vertically from a laid state, the three main bars 37
a rises in a state where horizontal movement is restrained by the three sheath tubes 22, and a vertical main bar 37a
The main reinforcement is suspended via three clamps 27 in a form held by the horizontal restraining force of the three sheath tubes 22 and the own weight of the three main reinforcements 37a so that the axial direction of the material is oriented in the vertical direction. It is in the form suspended by the tool 21. Thereby, as shown in FIG. 1, the three main bars 37a
The main bar suspension 21 is stably provided without bending the material axis of 7a.
And is suspended from the hook block 41 via.

【0019】この状態で、さらにクレーン操作を介して
フックブロック41を適宜移動させ、該3本の主筋37
aを、ゲージディスク7、下部フレーム枠9間にそれぞ
れセットする。これには、まず、各主筋37aの下端部
を下部フレーム枠9に、挿通穴9sを挿通させて支持部
9aに搭載する形にしてから、該主筋37aの上端部
を、ゲージディスク7の所定位置の主筋配置部71に入
り込み配置させる。この際、各主筋配置部71にはスト
ッパ72が設けられているので、該ストッパ72を主筋
37aによって図4矢印A方向に押す形で、該主筋37
aを主筋配置部71に水平方向から入り込みさせる。す
ると、ストッパ72は、該ストッパ72が保有している
バネ力によって図4実線で示すようにプレート73側に
復元する形で、主筋37aが入り込み配置された主筋配
置部71を直ちに塞ぐ。即ち、該主筋配置部71から主
筋37aが放射方向外側に外れるのを防止する。これに
よって、主筋配置部71には、主筋37aが、該主筋配
置部71に対して上下に移動自在に保持された形にな
る。なお、ゲージディスク7には、所定のピッチP1
(実施例においては5cmピッチで)主筋配置部71が
複数形成されているので、該複数の主筋配置部71のう
ち、必要なもののみを選択的に用いることが出来る。即
ち、配筋が不要な位置にある主筋配置部71は用いない
で残す。
In this state, the hook block 41 is further appropriately moved through a crane operation, and the three main bars 37 are moved.
a is set between the gauge disk 7 and the lower frame 9. First, the lower end of each main bar 37a is inserted into the lower frame 9 through the insertion hole 9s and is mounted on the support 9a. It enters the main bar arrangement portion 71 at the position and arranges it. At this time, since the stopper 72 is provided in each main bar arrangement portion 71, the stopper 72 is pushed by the main bar 37a in the direction of arrow A in FIG.
a is made to enter the main bar arrangement portion 71 from the horizontal direction. Then, the stopper 72 restores to the plate 73 side by the spring force held by the stopper 72 as shown by the solid line in FIG. That is, the main bar 37a is prevented from coming off from the main bar arranging portion 71 outward in the radial direction. As a result, the main bar 37a is held in the main bar arranging portion 71 so as to be vertically movable with respect to the main bar arranging portion 71. The gauge disk 7 has a predetermined pitch P1.
Since a plurality of main bar arrangement portions 71 are formed (at a pitch of 5 cm in the embodiment), only necessary ones of the plurality of main bar arrangement portions 71 can be selectively used. That is, the main bar placement unit 71 at a position where bar arrangement is unnecessary is left without being used.

【0020】こうして、主筋32aを順次3本づつ、下
部フレーム枠9の支持部9aに搭載し、ゲージディスク
7の主筋配置部71に配置させながら、クレーン操作に
よって、主筋吊り具21を下降させると、該主筋吊り具
21による吊下支持状態が解除された3本の主筋37a
は、その自重によって、下部フレーム枠7に縦に保持さ
れた形になる。そこで、主筋吊り具21の3ヶのクラン
プ27を順次主筋37aから取り外す。さらに、クレー
ン操作によってフックブロック41を上昇させる。する
と、クランプ27が主筋37aから取り外された状態の
主筋吊り具21は、3ヶの鞘管22が、各主筋挿通空間
22sを介して主筋37aに対して相対的に上方に移動
する形で、該主筋37aからその上側に抜けるように外
れる。従って、主筋吊り具21を用いれば、寝かせた状
態の主筋37aにクランプ27を取付けてクレーンを操
作するだけで、簡単に該主筋37aを縦にすることが出
来る。また、該クランプ27を縦になった主筋37aか
ら取り外すだけで、簡単に主筋吊り具21を主筋37a
から取り外すことが出来、これらの作業に高所作業や作
業の煩雑さが伴わない。
In this way, three main bars 32a are successively mounted on the support portion 9a of the lower frame 9 and the main bar suspension 21 is lowered by crane operation while being placed on the main bar placement portion 71 of the gauge disk 7. , The three main bars 37a released from the suspended support state by the main bar suspenders 21
Is vertically held by the lower frame 7 due to its own weight. Then, the three clamps 27 of the main bar suspension 21 are sequentially removed from the main bar 37a. Further, the hook block 41 is raised by the crane operation. Then, the main muscle suspender 21 in a state where the clamp 27 is removed from the main muscle 37a is in a form in which the three sheath tubes 22 move relatively upward with respect to the main muscle 37a via the respective main muscle insertion spaces 22s. It is detached from the main bar 37a so as to escape upward. Therefore, if the main bar suspension 21 is used, the main bar 37a can be easily made vertical only by attaching the clamp 27 to the main bar 37a in a laid state and operating the crane. Also, by simply removing the clamp 27 from the vertical main bar 37a, the main bar suspension 21 can be easily removed from the main bar 37a.
, And these operations do not involve complicated work at a high place or work.

【0021】こうして、上述した主筋37aをゲージデ
ィスク7、下部フレーム枠9間にセットする作業を繰返
すことによって、所定配筋本数の主筋37aを、その各
々の配筋位置に対応させた形で、下部フレーム枠9に縦
に搭載保持したところで、レベル調整ジャッキ15を駆
動操作して、各ワイヤ11の長さを調整する形で、下部
フレーム枠9のレベル調整を行う。これによって、該下
部フレーム枠9に搭載保持された所定本数の主筋37a
は、その各々が材軸方向を鉛直方向に向けた形になるよ
うに平衡保持される。そこで次に、該所定本数の主筋3
7aに配力筋37bを接続する作業を行う。
By repeating the operation of setting the main reinforcing bars 37a between the gauge disk 7 and the lower frame 9 in this manner, the main reinforcing bars 37a of a predetermined number are arranged in a form corresponding to each of the reinforcing bar positions. When vertically mounted and held on the lower frame 9, the level of the lower frame 9 is adjusted by driving the level adjustment jack 15 to adjust the length of each wire 11. Thus, a predetermined number of main bars 37a mounted and held on the lower frame 9 are provided.
Are balanced so that each of them has a shape in which the axial direction of the material is oriented vertically. Then, next, the predetermined number of main bars 3
The work of connecting the force distribution muscle 37b to 7a is performed.

【0022】当該配力筋37bの主筋37aへの接続作
業時には、配力筋受け治具1を用いるが、鉄筋籠37
における最下部部分に位置する配力筋37bを主筋37
aに接続する際には、該主筋37aの下端に配力筋受け
治具1の下端部を合わせてセットする。そして、これ
より上側位置の配力筋37bを主筋37aに接続する際
には、図8(a)に示すように、既に主筋37aに接続
された配力筋37bの上方に各配力筋受け治具1を位
置決めセットする。なお、配力筋受け治具1の位置決
めは、最下端部の掛け具191を、既に主筋37aに接
続済みの配力筋37b等に係合保持させた形にしておい
て、4ヶの油圧ジャッキ16をそれぞれ駆動操作するこ
とによって行う。
At the time of connecting the distribution bars 37b to the main reinforcement 37a, the distribution rod receiving jig 17 is used.
The main muscle 37b is connected to the distribution muscle 37b located at the lowermost part of
when connecting to a sets together lower end of the jig 1 7 receives Hairyoku muscle at the lower end of the main muscle 37a. When connecting the force-supplying muscle 37b at a position higher than this to the main muscle 37a, as shown in FIG. The jig 17 is positioned and set. The positioning of the distribution muscle receiving jig 17 is performed by setting the hook 191 at the lowermost end to be engaged with the distribution muscle 37b already connected to the main reinforcement 37a and holding the jig 17 in four positions. The operation is performed by operating the hydraulic jacks 16 respectively.

【0023】こうして位置決めした4ヶの配力筋受け治
具1のそれぞれは、下部フレーム枠9上に保持された
ことによって輪状になっている複数の主筋37aの内側
に配置する形になっている。そこで次に、図8(b)に
示すように、配力筋受け治具1を放射方向外側に若干
移動させると共に、ガイド19を介して複数の掛け具1
91を図8矢印G方向に突出させる形にして、主筋37
aの外側に該複数の掛け具191を突出配置させる。こ
の際、配力筋受け治具1の複数の掛け具191のうち
最下部に位置する掛け具191を、既に主筋37aに接
続済で最上部に位置していた配力筋37bに引掛けるよ
うにすると、配力筋受け治具1は、主筋37aの内方
側に的確に保持される。このとき配力筋受け治具1
は掛け具191が、配力筋37bの配筋ピッチに対応し
た形で設けられているので、配力筋37bを配筋すべき
位置が、複数の掛け具191の配置位置によって直ちに
検出される。
Each of the four force receiving muscle receiving jigs 17 positioned in this manner is arranged inside a plurality of annular main muscles 37a held by the lower frame 9 to form a ring. I have. Therefore, next, as shown in FIG. 8 (b), the jig 1 7 receives distribution force muscle causes slightly moved radially outward, via a guide 19 more hanger 1
9 is projected in the direction of arrow G in FIG.
The plurality of hooks 191 are arranged so as to protrude outside a. At this time, the lowermost hook 191 of the plurality of hooks 191 of the power distribution bar receiving jig 17 is hooked on the power distribution bar 37b already connected to the main bar 37a and located at the uppermost position. By doing so, the distribution muscle receiving jig 17 is accurately held inside the main muscle 37a. At this time, since the hanging tool 191 is provided on the force-receiving muscle receiving jig 17 in a form corresponding to the muscle-arrangement pitch of the force-distributing muscle 37b, a plurality of positions where the force-irradiating muscle 37b is to be arranged are determined. It is immediately detected by the arrangement position of the hanging tool 191.

【0024】そこで、4ヶの配力筋受け治具1を図2
に示すように、その各々の掛け具191が主筋37aの
外側に突出する形になるようにセットしたところで、図
2右部に示すように半円状になっている配力筋37b
を、引き続き図8(b)に示すように、配力筋受け治具
の各掛け具191上に引掛ける形で係合保持させ
る。そして、該配力筋37bを、その1本1本が円周状
になるように、2本の半円状の配力筋37b、37bの
各両端部をラップさせながら、主筋37aに該主筋37
aと交差する形になるようそれぞれ溶接接続していく。
すると、当該複数の主筋37aへの配力筋37bの接続
作業を繰返すことによって、鉄筋組立体である鉄筋籠1
0を形成することが出来、このための鉄筋組立作業は、
図2に示すように、坑口3a付近の地面2a上におい
て、坑外作業で行うことが出来る。
Then, the four force receiving jigs 17 are connected to each other in FIG.
As shown in FIG. 2, when each hook 191 is set so as to protrude outside the main bar 37a, the distribution bar 37b having a semicircular shape as shown in the right part of FIG.
Then, as shown in FIG. 8 (b), it is engaged and held in such a manner that it is hooked on each hook 191 of the distribution force receiving jig 17 . Then, the main muscle 37a is attached to the main muscle 37a by wrapping the two ends of the two semicircular force muscles 37b so that each of the muscles 37b becomes circumferential. 37
Each is welded and connected so as to intersect with a.
Then, the connecting operation of the force distribution bars 37b to the plurality of main reinforcements 37a is repeated, so that the rebar cage 1 as the rebar assembly is
0 can be formed, and the rebar assembling work for this
As shown in FIG. 2, it can be carried out outside the mine on the ground 2 a near the wellhead 3 a.

【0025】こうして、先にセットした配力筋受け治具
18の全ての段の掛け具191に係合させた配力筋37
bを主筋37aに溶接接続して、1サイクル分の配力筋
接続作業を終えたなら、次に図8(c)に示すように、
配力筋受け治具18を主筋37a(即ち組立中の鉄筋籠
37)と切り離す。これには、各油圧ジャッキ16を解
放して、それぞれの配力筋受け治具18を若干づつ下方
に移動させる。すると、該配力筋受け治具18は直ち
に、チェーン20を介して該油圧ジャッキ16に吊下さ
れた形になって、これにより主筋37aより放射方向内
方側に戻る形で配力筋受け治具18が、図8(c)に示
すように、主筋37aの内側に復元配置する。
In this manner, the power distribution bars 37 engaged with the hooks 191 of all the steps of the power distribution line receiving jig 18 set in advance.
b is welded and connected to the main bar 37a, and after completing one cycle of the connecting work of the distribution bars, as shown in FIG. 8 (c),
The distribution bar receiving jig 18 is separated from the main bar 37a (that is, the reinforcing bar cage 37 being assembled). For this purpose, the hydraulic jacks 16 are released, and the respective force-distributing-bar receiving jigs 18 are slightly moved downward. Then, the distributing muscle receiving jig 18 is immediately suspended by the hydraulic jack 16 via the chain 20, whereby the distributing muscle receiving jig 18 returns radially inward from the main reinforcement 37 a. As shown in FIG. 8C, the jig 18 is restored and arranged inside the main bar 37a.

【0026】このようにして、配力筋受け治具18の全
ての段の掛け具191の分だけ配力筋37bを主筋37
aに接続する作業を行うと、該配力筋受け治具18の長
さに対応した分だけの鉄筋籠組立作業が進行したことに
なる。そこで、このように配力筋受け治具18を用いて
鉄筋籠37を組み立てる作業を行いながら、所定のサイ
クルで、各チェーンブロック10を駆動し、各ワイヤ1
1を伸長させていく形で、下部フレーム枠9を縦穴3中
に少しづつ下降させていく。すると、下部フレーム枠9
上に搭載保持された形で、該下部フレーム枠9とゲージ
ディスク7の主筋配置部71間にセットされている所定
本数の主筋37aは、先に述べたように、該主筋37a
に接続された配力筋37bと共に、鉄筋籠37の組立済
部分として、縦穴3内に降ろされていく。従って、坑口
3a付近の地面2a上で作業員39が各チェーンブロッ
ク10を駆動操作することによって、主筋37aと配力
筋37bを、鉄筋籠37にした状態で、縦穴3内に建て
込む作業を行うことが出来る。なお、こうして鉄筋籠3
7の組立済部分を、縦穴3内に降ろしていく際に、該鉄
筋籠37を形成している各主筋37aは、ゲージディス
ク7の各主筋配置部71に対して相対的に下降移動する
形になり、このときに、該それぞれの主筋配置部71に
はストッパ72が設けられていることによって、それぞ
れの主筋37aは主筋配置部71から放射方向外側に外
れることなく、円滑にゲージディスク7に対して下降移
動することが出来る。
In this manner, the main muscles 37b are connected to the main muscles 37b by the hooks 191 of all the stages of the jigs 18 for receiving the main muscles.
When the work for connecting to the a is performed, the rebar cage assembling work corresponding to the length of the distributing muscle receiving jig 18 has progressed. Thus, while performing the work of assembling the reinforcing bar cage 37 by using the distributing bar receiving jig 18 in this manner, each chain block 10 is driven in a predetermined cycle, and each wire 1
The lower frame 9 is gradually lowered into the vertical hole 3 in such a manner that 1 is extended. Then, the lower frame 9
A predetermined number of the main bars 37a set between the lower frame 9 and the main bar arranging portion 71 of the gauge disc 7 while being mounted and held on the main frame 37a as described above.
Together with the force distribution bars 37b connected to the vertical bar 3 as an assembled part of the reinforcing bar cage 37. Therefore, when the operator 39 drives and operates each chain block 10 on the ground 2a near the wellhead 3a, the main bars 37a and the force distribution bars 37b are laid in the vertical holes 3 in a state where the reinforcing bars 37 are formed. You can do it. In addition, in this way, steel cage 3
When the assembled portion 7 is lowered into the vertical hole 3, the main bars 37 a forming the reinforcing bar cage 37 move downward relative to the main bar placement portions 71 of the gauge disk 7. At this time, the stopper 72 is provided in each of the main bar arrangement portions 71, so that each of the main bars 37a does not come off radially outward from the main bar arrangement portion 71, and is smoothly attached to the gauge disk 7. On the other hand, it can move downward.

【0027】ところで、上述したように縦穴3内に降ろ
されていく組立済部分の鉄筋籠37は、配力筋37bが
主筋37aに接続された位置より下方側にある坑口3a
付近において、スライドガイド8の鉄筋挿通空間8sを
通過する形で、下降移動する。この際、スライドガイド
8はゲージディスク7と整合した位置に設けられてお
り、該ゲージディスク7及びスライドガイド8が設けら
れているフレーム6の中心CL1は、縦穴3の中心CT
1と一致した形になっている。すると、該スライドガイ
ド8は、その内径即ち鉄筋挿通空間8sの径D2が、鉄
筋籠37の外径より若干大きな形で円環状に形成されて
いることによって、該鉄筋挿通空間8sを通過する組立
済部分の鉄筋籠37は、スライドガイド8の内側面に案
内される形で、常に該鉄筋籠37の部材中心を縦穴3の
中心CT1に一致させた形で、縦穴3中に降りることが
出来る。
By the way, as described above, the reinforcing bar cage 37 of the assembled portion which is lowered into the vertical hole 3 is provided with the wellhead 3a located below the position where the force distribution bar 37b is connected to the main bar 37a.
In the vicinity, it descends while passing through the reinforcing bar insertion space 8s of the slide guide 8. At this time, the slide guide 8 is provided at a position aligned with the gauge disk 7, and the center CL 1 of the frame 6 provided with the gauge disk 7 and the slide guide 8 is located at the center CT of the vertical hole 3.
It has a shape that matches 1. Then, since the slide guide 8 is formed in an annular shape in which the inner diameter, that is, the diameter D2 of the reinforcing bar insertion space 8s is slightly larger than the outer diameter of the reinforcing bar cage 37, the slide guide 8 passes through the reinforcing bar insertion space 8s. The reinforced basket 37 of the finished portion is guided into the inner surface of the slide guide 8 and can descend into the longitudinal hole 3 with the center of the member of the rebar cage 37 always coincident with the center CT1 of the longitudinal hole 3. .

【0028】このようにして、先に述べたように所定配
筋本数の主筋37aを、その各々の配筋位置に対応させ
た形で、下部フレーム枠9とゲージディスク7の主筋配
置部71間にセットし、該所定本数の主筋37aに配力
筋37bを接続して、鉄筋籠37を組み立てながら、チ
ェーンブロック10の駆動操作によって下部フレーム枠
9を鉄筋籠37を組み立てた長さ分づつ下降させていく
作業を、所定のサイクルで繰り返していく作業を繰返す
ことによって、縦穴3に主筋37aと配力筋37bを、
これ等を接続した鉄筋籠37の状態で建て込むことが出
来る。すると、当該鉄筋籠組立及び建て込み作業を坑口
3a付近の地面2a上で行うことが出来、鉄筋組立のた
めに縦穴3の坑内に作業員39が降りたり、縦穴3上に
足場を仮設して高所作業を行う必要がない。なお、形成
構築すべき杭30の長さ、即ち縦穴3の深さが1本の主
筋37aの長さより大なるときには、主筋37aを上下
方向に順次ラップさせながら順次継ぎ足していく形で、
主筋37aを所定長さにすることが出来るので、縦穴3
に鉄筋建て込み装置5を設置したままの状態で、杭30
全長分の鉄筋籠37を建て込んでしまうことが出来、段
取り替えの必要がない。
In this manner, as described above, the main reinforcing bars 37a having the predetermined number of bars are arranged between the lower frame 9 and the main bar arranging portion 71 of the gauge disk 7 in such a manner as to correspond to the respective bar arranging positions. The lower frame 9 is driven down by the drive operation of the chain block 10 by the length of the rebar cage 37 by assembling the rebar cage 37 while connecting the force distribution bars 37b to the predetermined number of main rebars 37a. By repeating the work of repeating the work in a predetermined cycle, the main bar 37a and the force distribution bar 37b are
These can be built in the state of the reinforcing bar cage 37 connected thereto. Then, the rebar cage assembling and erection work can be performed on the ground 2a near the wellhead 3a, and the worker 39 descends in the pit of the vertical hole 3 for rebar assembly, or temporarily sets a scaffold on the vertical hole 3. No need to work at height. In addition, when the length of the pile 30 to be formed and constructed, that is, the depth of the vertical hole 3 is larger than the length of one main bar 37a, the main bars 37a are sequentially wrapped in the vertical direction while being sequentially added,
Since the main bar 37a can be set to a predetermined length, the vertical hole 3
In the state where the reinforcing bar embedding device 5 is installed in
Reinforcing cages 37 for the entire length can be built in, and there is no need to change the setup.

【0029】さらに、このようにして、所定長さ分の鉄
筋籠37を、組立済状態で、縦穴37に建て込み設置す
ると、該鉄筋建て込みのために縦穴3を下降させた下部
フレーム枠9は、穴底3bに到達する。これによって、
下部フレーム枠9の支持部9aを介して、鉄筋籠37が
穴底3bに支持された形になる。すると、下部フレーム
枠9を吊下する形で、該下部フレーム枠9上の鉄筋籠3
7を支持していたワイヤ11は、それまで、下向きに突
出しているフック係合突起12aに吊輪13が引掛けら
れてフック配置溝12bに配置する形で、フック保持具
12に保持されていたので、当該下部フレーム枠9の穴
底3bへの到達によって、吊輪13がフック配置溝12
bに対して下方に移動する形で、フック係合突起12a
から抜ける。これによって、下部フレーム枠9(即ちこ
れが支持する鉄筋籠37)とワイヤ11(即ち該ワイヤ
11が接続しているチェーンブロック10)の係合状態
が解除される。即ち、下部フレーム枠9は、鉄筋建て込
み装置5における消耗部品として、穴底3bに置き去り
にし、該下部フレーム枠9以外の構成部分を鉄筋籠37
と切り離して回収し、他の杭30の施工位置に転用する
が、当該部品回収作業のために、作業員が縦穴30に入
る必要はなく、チェーンブロック10の操作によって、
これを行うことが出来る。即ち、安全性が高い。
Further, in this manner, when the reinforcing bar cage 37 of a predetermined length is erected and installed in the vertical hole 37 in an assembled state, the lower frame 9 in which the vertical hole 3 is lowered for mounting the reinforcing bar. Reaches the hole bottom 3b. by this,
The reinforcing rod cage 37 is supported by the hole bottom 3b via the support portion 9a of the lower frame 9. Then, the reinforcing cage 3 on the lower frame 9 is suspended from the lower frame 9.
The wire 11 supporting the wire 7 is held by the hook holder 12 so that the hanging ring 13 is hooked on the hook engaging projection 12a projecting downward and is arranged in the hook arrangement groove 12b. Therefore, when the lower frame 9 reaches the hole bottom 3b, the suspension ring 13
b, the hook engaging protrusion 12a
Get out of. Thereby, the engagement state between the lower frame 9 (ie, the reinforcing bar cage 37 supported by the lower frame 9) and the wire 11 (ie, the chain block 10 to which the wire 11 is connected) is released. That is, the lower frame 9 is left behind on the hole bottom 3b as a consumable part in the reinforcing bar setting device 5, and the components other than the lower frame 9 are reinforced cages 37.
It is separated and collected, and is diverted to the construction position of another pile 30. However, the worker does not need to enter the vertical hole 30 for the part collection work, and by operating the chain block 10,
You can do this. That is, safety is high.

【0030】そこで、上述したように吊輪13を介して
ワイヤ11を下部フレーム枠9と切離したところで、各
チェーンブロック10の駆動操作によってワイヤ11を
引上げ、鉄筋建て込み装置5を縦穴3から撤去すれば、
直ちに該縦穴3にコンクリートを打設する作業を行うこ
とが出来る。また、撤去した鉄筋建て込み装置を、未だ
鉄筋籠37が建て込みされていない縦穴3に転用し、新
たな鉄筋建て込み作業を開始することが出来る。従っ
て、施工効率が良く、杭施工を行うことが出来る。な
お、こうした鉄筋建て込み装置5の移設や、先に述べた
主筋37aの鉄筋建て込み装置5へのセットには、クレ
ーン車40を使用するが、鉄筋建て込み装置5は、鉄筋
籠37を保持していない状態で設置或いは移設され、ま
た、主筋37aのセットは3本づつ行われるので、該ク
レーン車40は小型のもので十分である。また、鉄筋籠
37は、坑口3a付近で組み立てられる形で、その組立
以前には、主筋37aと半円形の配力筋37bを、寝か
せた状態で重ねて保管しておくことが出来る。よって、
こうしたクレーン車40の設置や主筋37a、配力筋3
7b等の鉄筋の保管のために、広範な場所が占有される
ことはない。
Therefore, when the wire 11 is separated from the lower frame 9 via the suspension ring 13 as described above, the wire 11 is pulled up by the driving operation of each chain block 10, and the reinforcing bar erection device 5 is removed from the vertical hole 3. if,
Immediately, an operation of placing concrete in the vertical hole 3 can be performed. In addition, the removed reinforcing-bar building device can be diverted to the vertical hole 3 in which the reinforcing bar cage 37 has not yet been built, and a new reinforcing-bar building operation can be started. Therefore, pile construction can be performed with good construction efficiency. The crane truck 40 is used for the transfer of the reinforcing bar embedding device 5 and the setting of the main reinforcing bar 37a to the reinforcing bar embedding device 5 described above, but the reinforcing bar embedding device 5 holds the reinforcing bar cage 37. The crane truck 40 is installed or moved in a state where it is not mounted, and the main bars 37a are set three by three. The reinforcing bar cage 37 can be assembled near the wellhead 3a. Before the assembling, the main bar 37a and the semicircular force bar 37b can be stored in an overlaid state. Therefore,
The installation of such a crane truck 40, the main reinforcement 37a, and the distribution muscle 3
Extensive space is not occupied for storage of rebar such as 7b.

【0031】なお、上述した実施例においては、円柱形
状の縦穴3にその側壁3cに沿った円筒状の鉄筋籠37
を建て込みする例を述べたが、縦穴3及び鉄筋籠37の
形状は、これに限定されるものではない。従って、縦穴
3の真中部分にも鉄筋籠37等の鉄筋組立体を建て込み
しても構わない。また、その全体形状が板状をなす鉄筋
組立体を壁状の縦穴に建て込みしても構わない。また、
実施例においては、鉄筋建て込み装置5の下部フレーム
9は電動式のチェーンブロック10によって上下に移動
駆動される例を述べたが、下部フレーム9は縦穴3中を
下降することが出来れば、その他の昇降装置によって上
下に移動駆動位置決めされても構わない。
In the above-described embodiment, the cylindrical reinforcing bar 37 is formed in the cylindrical vertical hole 3 along the side wall 3c.
Has been described, but the shapes of the vertical hole 3 and the reinforcing bar cage 37 are not limited thereto. Therefore, a reinforcing bar assembly such as the reinforcing bar cage 37 may be built in the middle of the vertical hole 3. Further, a reinforcing bar assembly having a plate-like overall shape may be built in a wall-shaped vertical hole. Also,
In the embodiment, the example has been described in which the lower frame 9 of the reinforcing bar erection device 5 is driven to move up and down by the electric chain block 10. However, if the lower frame 9 can be lowered in the vertical hole 3, May be vertically moved and positioned by the lifting device.

【0032】[0032]

【発明の効果】以上説明したように本発明によれば、地
面2aから掘り下げられた縦穴3に、複数の主筋37a
と複数の配力筋37bによるコンクリート補強用の鉄筋
籠37等の鉄筋組立体を建て込む際に、前記縦穴3に、
下部フレーム枠9等の主筋保持手段を、前記縦穴の坑外
からチェーンブロック10等の昇降装置により該縦穴内
下降自在に設置し、複数の主筋37aを、該複数の主
筋37aの各々の配筋位置に対応させた形で前記主筋保
持手段に縦に保持させ、前記縦穴3の坑口3a等の口元
付近で前記複数の配力筋37bの各々を、前記主筋保持
手段に保持された複数の主筋37aに交差するよう該主
筋37aに接続しながら、前記主筋保持手段を、前記縦
穴の坑外から前記昇降装置を介して前記縦穴内で下方に
移動させることによって、前記複数の配力筋37bが接
続された複数の主筋37aを、前記鉄筋組立体として、
該鉄筋組立体を前記主筋保持手段上に搭載保持した形
で、前記縦穴3中に降ろしていくようにして構成したの
で、縦穴3の口元付近において、主筋保持手段によって
所定の配筋状態に保持された複数の主筋37aに複数の
配力筋37bを接続していく作業により鉄筋組立を行
い、また、主筋保持手段を昇降装置を介して縦穴内で
方に移動させることによって該組み立てられた鉄筋組立
体の建て込み作業を行うことが出来る。従って、鉄筋組
立作業と鉄筋建て込み作業を縦穴3の口元付近の坑外で
行うことが出来るので、坑内作業を避けることが出来、
安全である。また、主筋37aと配力筋37bは、縦穴
37の口元付近で組み立てるので、組み立てられる以前
には、それぞれの主筋37aと配力筋37bをそれぞれ
重ねた状態で現場に搬入し、これを保管しておくことが
出来る。従って、スペースを要さない。また、鉄筋組立
体は、主筋保持手段に搭載保持させた形で、組み立てな
がら、該主筋保持手段を昇降装置を介して縦穴内で下降
移動させることによって、縦穴3内に建て込み出来るの
で、予め組み上げた状態のものを吊り上げする作業がな
い。この結果、大型のクレーンや運搬車は必要ないの
で、経済施工が可能である。このように、本発明は、施
工制約を受けることが少ないので、特に山岳部において
橋脚用の大口径深礎杭を構築するための鉄筋組立体を立
坑に設置するとき等に、有効である。
As described above, according to the present invention, a plurality of main bars 37a are formed in the vertical hole 3 dug from the ground 2a.
When a reinforcing bar assembly such as a reinforcing bar cage 37 for reinforcing concrete with a plurality of distributing bars 37b is built,
The main-bar holding means such as the lower frame 9 is placed outside the vertical hole.
From the vertical hole by a lifting device such as a chain block 10
In descending freely installed, a plurality of main reinforcements 37a, is held vertically to the main reinforcement holding means in a form to correspond to reinforcement position of each of the plurality of main reinforcements 37a, near the mouth of the wellhead 3a etc. of the vertical hole 3 While connecting each of the plurality of distribution muscles 37b to the main muscle 37a so as to intersect with the plurality of main muscles 37a held by the main muscle holding means, the main muscle holding means is connected to the vertical
By moving the plurality of main reinforcing bars 37a to which the plurality of force distribution bars 37b are connected, by moving the main reinforcing bars 37b downward from the outside of the hole in the vertical hole via the lifting device ,
A form in which the reinforcing bar assembly is mounted and held on the main reinforcing bar holding means.
In, since it is configured as go down into the vertical hole 3, in the vicinity of the mouth of the vertical hole 3, connecting a plurality of distribution power muscle 37b into a plurality of main reinforcements 37a held in a predetermined reinforcement conditions by the main reinforcement holding means The rebar assembly can be performed by moving the main rebar holding means down in the vertical hole via the elevating device to perform the rebar assembly operation of the assembled rebar assembly. I can do it. Therefore, since the rebar assembling work and the rebar building work can be performed outside the pit near the mouth of the vertical hole 3, the pit work can be avoided,
It is safe. Also, since the main reinforcement 37a and the distribution muscle 37b are assembled near the mouth of the vertical hole 37, before assembly, the main reinforcement 37a and the distribution muscle 37b are carried to the site in a state where the respective main reinforcement 37a and the distribution muscle 37b are overlapped, and stored. Can be kept. Therefore, no space is required. In addition, the rebar assembly can be built in the vertical hole 3 by moving the main reinforcement holding means down in the vertical hole via the elevating device while assembling the reinforcing bar assembly while being mounted and held on the main reinforcement holding means. There is no work to lift the assembled one. As a result, a large-sized crane and a truck are not required, and economic construction is possible. As described above, the present invention is less subject to construction restrictions, and is particularly effective when a rebar assembly for constructing a large-diameter deep foundation pile for a bridge pier is installed in a shaft in mountainous areas.

【0033】また、本発明によれば、フレーム6を有
し、前記フレーム6にゲージディスク7等の主筋配筋手
段を設け、前記主筋配筋手段に複数の主筋配置部71
を、該主筋配置部71に対して主筋37aを上下に移動
自在にそれぞれ保持し得るように設け、前記主筋配筋手
段の下方に下部フレーム枠9等の主筋保持手段を、上下
に移動自在に設け、前記フレーム6に、前記主筋保持手
段を上下に移動駆動位置決め自在なチェーンブロック1
0等の昇降装置を設け、前記主筋配筋手段の主筋配置部
71と前記主筋保持手段の間に主筋37aをセットし得
るようにしたことを特徴として、鉄筋建て込み装置5を
構成したので、主筋配筋手段の主筋配置部71と主筋保
持手段の間にセットした主筋37aは、昇降装置を介し
ての主筋保持手段の上下移動によって上下に移動し、こ
の際、主筋配置部71に対して上下に相対移動すること
が出来る。従って、地面から掘り下げ形成した縦穴3上
に鉄筋建て込み装置5を、その主筋保持手段が該縦穴3
中を下降し得るように設置し、主筋配筋手段の主筋配置
部と該主筋保持手段の間に所定配筋本数の主筋37aを
セットすれば、該主筋37aに配力筋37bを接続しな
がら、主筋保持手段を下方に移動させるだけで、該配力
筋37bを接続した主筋37aを縦穴3中に降ろしてい
くことが出来る。この際、配力筋37bを主筋37aに
接続する作業は、該主筋37aを主筋配筋手段の主筋配
置部71と主筋保持手段の間にセットした状態で行うこ
とが出来、また、該主筋配筋手段は上下に移動自在であ
るため、当該配力筋37bを主筋37aに接続する作業
を、坑口3a等の口元付近の地上即ち坑外の、作業に適
した高さ位置で行うことが出来る。また、配力筋37b
を接続した主筋37aによる鉄筋組立済部分を縦穴3内
に降ろすには、地上で昇降装置を操作して、主筋保持手
段を下降移動させる形で簡単に出来る。そして、上記鉄
筋組立と当該主筋保持手段の下降移動によって、縦穴3
内に鉄筋組立体を建て込む作業を完了することが出来
る。即ち、所定配筋本数の主筋37aと配力筋37bを
接続組み立てする作業と、該主筋37aと配力筋37b
による鉄筋籠37等の鉄筋組立体を縦穴3中に建て込む
作業を、地上作業のみで行うことが出来る。従って、鉄
筋組立のために作業員が坑内に入ったり或いは縦穴3上
に足場を組み上げたりする必要がなく、安全性が高い。
また、鉄筋組立体を支持する主筋保持手段は、フレーム
6に設けられた昇降装置によって縦穴3内に下降され得
るので、鉄筋建て込みのために大型のクレーンが必要と
されない。よって経済的である。また、鉄筋建て込み装
置5は、縦穴3位置に設置して用いるものであり、ま
た、主筋37aや配力筋37bはこれが組み立てられる
迄の間は、それぞれを重ねた状態で、搬入保管されて良
いので、鉄筋建て込みに必要なスペースが小さくてす
む。従って、施工ヤードが限定されているような現場へ
の適用も可能であり、汎用性が高い。
Further, according to the present invention, the frame 6 is provided with main bar arrangement means such as a gauge disk 7 on the frame 6, and the main bar arrangement means is provided with a plurality of main bar arrangement portions 71.
Are provided so as to be capable of vertically holding the main bar 37a with respect to the main bar arranging portion 71, respectively. The main bar holding means such as the lower frame 9 below the main bar arranging unit is vertically movable. A chain block 1 provided on the frame 6 and capable of moving and positioning the main bar holding means up and down.
Since the main reinforcing bar 37a can be set between the main bar arranging portion 71 of the main bar arranging device and the main bar holding device, the reinforcing bar laying device 5 is configured. The main bar 37a set between the main bar arranging unit 71 of the main bar arranging unit and the main bar holding unit is moved up and down by the vertical movement of the main bar holding unit via the elevating device. Can move up and down relatively. Therefore, the reinforcing bar embedding device 5 is placed on the vertical hole 3 dug down from the ground, and the main reinforcement holding means is provided with the vertical hole 3.
It is installed so as to be able to descend inside, and if the main bars 37a of a predetermined number of bars are set between the main bar arranging portion of the main bar arranging unit and the main bar holding unit, the main bar 37a is connected to the main bar 37b. By simply moving the main bar holding means downward, the main bar 37a to which the force distribution bar 37b is connected can be lowered into the vertical hole 3. At this time, the work of connecting the force bars 37b to the main bars 37a can be performed in a state where the main bars 37a are set between the main bar arranging portion 71 of the main bar arranging means and the main bar holding means. Since the streak means can be moved up and down, the work of connecting the distribution muscle 37b to the main streaks 37a can be performed at a height suitable for the work, that is, on the ground near the mouth of the wellhead 3a or the like, that is, outside the pit. . In addition, the distribution muscle 37b
In order to lower the rebar-assembled portion by the main bar 37a connected to the inside of the vertical hole 3, it is easy to operate the lifting device on the ground and move the main bar holding means downward. Then, the vertical hole 3 is formed by the rebar assembly and the downward movement of the main bar holding means.
The work of laying the reinforcing bar assembly can be completed. That is, the work of connecting and assembling the main bars 37a and the force bars 37b of a predetermined number of bars, and the operation of connecting the main bars 37a and the force bars 37b.
Of the reinforcing bar assembly such as the reinforcing bar cage 37 in the vertical hole 3 can be performed only by ground work. Therefore, there is no need for an operator to enter the mine or assemble a scaffold on the vertical hole 3 for assembling the rebar, and the safety is high.
In addition, the main bar holding means for supporting the reinforcing bar assembly can be lowered into the vertical hole 3 by the lifting / lowering device provided on the frame 6, so that a large crane is not required for building the reinforcing bar. Therefore, it is economical. The reinforcing bar embedding device 5 is installed and used at the position of the vertical hole 3, and the main bar 37a and the distribution bar 37b are carried in a stacked state until they are assembled, and are carried in and stored. Because it is good, the space required for building reinforcement is small. Therefore, application to the site where the construction yard is limited is also possible, and the versatility is high.

【0034】また、本発明において、前記主筋配置部7
1は、建て込むべき主筋37aの配筋ピッチに対応した
形で形成すると、前記主筋配筋手段の主筋配置部71と
前記主筋保持手段の間に複数の主筋37aが、該主筋3
7aの配筋ピッチに対応した形でセットされることが出
来る。従って、該配筋ピッチに対応した形でセットされ
た主筋37aに配力筋37bを、該配力筋37bの配筋
ピッチに対応した形で接続するだけで、鉄筋籠37等の
鉄筋組立体を組み立てる作業を行うことが出来るので、
非常に便利である。これによって、一層効率的に鉄筋建
て込み作業を進行させることが可能になる。
Further, in the present invention, the main bar arrangement portion 7
1 is formed in a shape corresponding to the bar arrangement pitch of the main bar 37a to be erected, a plurality of main bars 37a are provided between the main bar placement section 71 of the main bar arrangement means and the main bar holding means.
7a can be set in a form corresponding to the bar arrangement pitch. Therefore, the rebar assembly such as the rebar cage 37 is simply connected to the main rebar 37b to the main rebar 37a set in a form corresponding to the rebar pitch in a form corresponding to the rebar pitch of the rebar 37b. Can work to assemble
Very convenient. This makes it possible to proceed with the work of building the reinforcing bar more efficiently.

【0035】また、本発明において、前記主筋配筋手段
にはストッパ72等の主筋固定具を、前記複数の主筋配
置部71の各々に主筋37aを水平方向に入れ込み自在
に設けて構成すると、主筋37aを主筋配置部71に入
れ込む形でセットしたとき、主筋固定具は、該セットさ
れた主筋37aが主筋配置部から水平方向に外れるのを
防止することが出来る。従って、主筋37aは、これを
各主筋配置部71に水平方向に入れ込む形で、主筋配筋
手段の主筋配置部と主筋保持手段間にセットすることが
簡単に出来て、さらに、該主筋配置部から水平方向に外
れるのを主筋固定具によって防止された形で、当該主筋
セット状態が安定的に保持される。従って、主筋37a
をセットする作業及び該主筋37aに配力筋37bを接
続する作業を、一層円滑に進めることが出来る。
In the present invention, when the main bar arrangement means such as a main bar fixing means such as a stopper 72 is provided in each of the plurality of main bar arranging portions 71 so as to be freely inserted in the horizontal direction, When the main bar 37a is set so as to be inserted into the main bar placement section 71, the main bar fixing device can prevent the set main bar 37a from coming off in the horizontal direction from the main bar placement section. Therefore, the main bar 37a can be easily set between the main bar arranging portion of the main bar arranging device and the main bar holding device by inserting the main bar 37a into each main bar arranging portion 71 in the horizontal direction. The main muscle set state is stably held in such a manner that the main muscle fixing device prevents the main muscle from being horizontally disengaged from the part. Therefore, the main line 37a
And the operation of connecting the force distribution muscle 37b to the main muscle 37a can be performed more smoothly.

【0036】また、本発明において、前記主筋配筋手段
と前記主筋保持手段の間にはスライドガイド8等の鉄筋
建て込み位置決め具を、前記主筋配筋手段と整合した位
置に配置する形で上下方向に並べて設けて構成すると、
主筋保持手段が鉄筋建て込み位置決め具に整合配置した
ときに、該主筋保持手段は主筋配筋手段と整合位置に配
置することが出来る。すると、鉄筋建て込み作業時に
は、上述したように組み立てられる鉄筋組立体を縦穴3
に降ろすために、主筋保持手段を縦穴3内に下降移動さ
せなければならないので、該主筋保持手段の配置位置、
即ちこれに保持される鉄筋組立体の配置位置が把握し辛
いが、こうして主筋配筋手段を鉄筋建て込み位置決め具
に整合させておけば、該鉄筋建て込み位置決め具を介し
て、鉄筋組立体の配置位置を主筋配筋手段の配置位置に
合わせて、上下に並べることが出来る。すると、主筋配
筋手段はフレーム6に設けられた形になっているので、
先に述べたように鉄筋建て込み装置5を縦穴3上に設置
する際に、例えばフレーム6の中心CL1が縦穴3の中
心CT1に一致した形になるように、フレーム6の位置
を合わせておけば、鉄筋建て込み時に、鉄筋建て込み位
置決め具を介して、組み立てられた鉄筋組立体を、縦穴
3の正確な位置に配置させることが出来る。これによっ
て、簡単に均等な被り厚さを得ることが出来る。
Further, in the present invention, a reinforcing bar locating tool such as a slide guide 8 is vertically arranged between the main reinforcing bar arrangement means and the main reinforcing rod holding means at a position aligned with the main reinforcing bar arrangement means. When arranged and arranged in the direction,
When the main bar holding means is aligned with the reinforcing bar locating tool, the main bar holding means can be positioned at a position aligned with the main bar arranging means. Then, at the time of rebar building work, the rebar assembly assembled as described above is inserted into the vertical hole 3.
In order to lower the main bar holding means, it is necessary to lower the main bar holding means into the vertical hole 3, so that the arrangement position of the main bar holding means,
In other words, it is difficult to grasp the arrangement position of the reinforcing bar assembly held by the reinforcing bar assembly. However, if the main reinforcing bar arranging means is aligned with the reinforcing bar locating tool, the reinforcing bar assembly can be moved through the reinforcing bar locating tool. The arrangement position can be arranged vertically according to the arrangement position of the main bar arrangement means. Then, since the main bar arrangement means is provided in the frame 6,
As described above, when installing the reinforcing bar embedding device 5 on the vertical hole 3, the position of the frame 6 is adjusted so that, for example, the center CL1 of the frame 6 coincides with the center CT1 of the vertical hole 3. For example, at the time of rebar installation, the assembled rebar assembly can be arranged at an accurate position of the vertical hole 3 via the rebar installation positioning tool. This makes it possible to easily obtain a uniform covering thickness.

【0037】また、本発明において、前記配力筋受け治
具17等の配力筋保持手段を、配力筋建て込み位置の内
方から外側に向けて移動自在に設け、該配力筋保持手段
には複数の掛け具191等の配力筋保持部を、上下方向
に所定の間隔をなすよう複数設けて、構成すると、主筋
配筋手段の主筋配置部71と主筋保持手段間にセットし
た複数の主筋の内方側から外側に向けて、配力筋保持手
段の配力筋保持部をそれぞれ突出配置させることが出来
る。すると、先に述べたように、複数の主筋37aに複
数の配力筋37bを接続する際に、このように主筋37
aの外側に突出配置させた配力筋保持部に配力筋37b
を保持させておいて、この状態で、該配力筋37bの主
筋37aへの溶接作業を行うことが出来る。従って、配
力筋37bを主筋37aに接続するための溶接作業を行
っている間に、何等かの他の手段によって該配力筋37
bを横向きに保持しておく必要がない。また、配力筋3
7の配筋ピッチに対応したピッチで配力筋保持部が設け
られた配力筋保持手段を用いれば、該配力筋37bの配
筋位置をいちいち割り出す必要がない。従って、一層効
率的に鉄筋組立を行うことが可能となる。なお、配力筋
保持手段は、これを使う必要がないときには、鉄筋建て
込み位置(即ち後にコンクリートが打設される領域の)
の内方側に配置させておくことが出来るので、先に述べ
たように昇降装置を介して主筋37aを下降移動させる
際に、該配力筋保持手段が該主筋37aの下降移動を邪
魔することはない。
In the present invention, the distribution muscle holding means such as the distribution muscle receiving jig 17 is movably provided from the inside to the outside of the distribution muscle building position, and the distribution muscle holding means is provided. When the means is provided with a plurality of force distribution muscle holding portions such as a plurality of hooks 191 and the like at predetermined intervals in the vertical direction, and is configured, it is set between the main muscle placement portion 71 of the main muscle reinforcement means and the main muscle holding device. Distributing muscle holding portions of the distributing muscle holding means can be respectively arranged so as to protrude from the inside to the outside of the plurality of main muscles. Then, as described above, when connecting the plurality of force distribution bars 37b to the plurality of main bars 37a, the main bars 37
The force-feeding muscle 37b is provided on the force-feeding muscle holding portion protruding outside of FIG.
In this state, the welding operation of the force distribution bars 37b to the main bars 37a can be performed. Therefore, while performing the welding operation for connecting the power distribution bars 37b to the main reinforcement 37a, the power distribution bars 37b are connected by some other means.
There is no need to hold b sideways. In addition, distributing muscle 3
By using a force-strength muscle holding unit provided with a force-strength muscle holding unit at a pitch corresponding to the muscle-arrangement pitch of No. 7, it is not necessary to determine the muscle-arrangement position of the force-strength muscle 37b one by one. Therefore, it is possible to more efficiently assemble the reinforcing bar. When it is not necessary to use the reinforcing bars, it is necessary to use the reinforcing bars at the position where the reinforcing bars are erected (that is, in the area where concrete is to be cast later).
As described above, when the main muscle 37a is moved downward via the elevating device, the force distribution muscle holding means hinders the downward movement of the main muscle 37a. Never.

【図面の簡単な説明】[Brief description of the drawings]

【図1】本発明による鉄筋建て込み装置の一実施例を用
いて鉄筋建て込み作業を行っている杭施工現場の様子を
示す一部破断斜視図である。
FIG. 1 is a partially broken perspective view showing a state of a pile construction site where a reinforcing bar is being built using an embodiment of a reinforcing bar building device according to the present invention.

【図2】図1に示す杭施工現場の坑口付近を示す拡大図
である。
FIG. 2 is an enlarged view showing the vicinity of a wellhead of the pile construction site shown in FIG.

【図3】図1に示す鉄筋建て込み装置のゲージディスク
を部分を示す平面図である。
FIG. 3 is a plan view showing a part of a gauge disk of the reinforcing-bar laying device shown in FIG. 1;

【図4】図3に示すゲージディスクのIV矢視部分の拡大
図である。
FIG. 4 is an enlarged view of a portion of the gauge disc shown in FIG.

【図5】図1に示す鉄筋建て込み装置のスライドガイド
部分を示す平面図である。
FIG. 5 is a plan view showing a slide guide portion of the reinforcing-bar laying device shown in FIG.

【図6】図1に示す鉄筋建て込み装置の下部フレーム枠
におけるVI矢視部分の断側面図である。
6 is a cross-sectional side view of a portion of the lower frame of the reinforcing bar erection device shown in FIG.

【図7】図1に示す鉄筋建て込み装置に鉄筋吊り下げ治
具を用いて主筋を装着している様子を示す図である。
FIG. 7 is a view showing a state in which a main reinforcing bar is attached to the reinforcing bar building device shown in FIG. 1 using a reinforcing bar hanging jig.

【図8】図1に示す杭施工現場において主筋に配力筋を
溶接する様子を示す一連の図である。
FIG. 8 is a series of diagrams showing a manner in which a distribution bar is welded to a main bar at the pile construction site shown in FIG.

【符号の説明】[Explanation of symbols]

2a……地面 3……縦穴 3a……口元(坑口) 5……鉄筋建て込み装置 6……フレーム 7……主筋配筋手段(ゲージディスク) 71……主筋配置部 72……主筋固定具(ストッパ) 8……鉄筋建て込み位置決め具(スライドガイド) 9……主筋保持手段(下部フレーム枠) 10……昇降装置(チェーンブロック) 17……配力筋保持手段(配力筋受け治具) 191……配力筋保持部(掛け具) 37……鉄筋組立体(鉄筋籠) 37a……主筋 37b……配力筋 2a ... ground 3 ... vertical hole 3a ... mouth (headhole) 5 ... reinforcement reinforcing device 6 ... frame 7 ... main reinforcement arrangement means (gauge disk) 71 ... main reinforcement arrangement part 72 ... main reinforcement fixture ( Stopper) 8 Reinforcing bar positioning tool (slide guide) 9 Main bar holding means (lower frame) 10 Lifting device (chain block) 17 Power distribution holding means (distribution jig) 191: distribution muscle holding part (hanging tool) 37: reinforcing bar assembly (rebar cage) 37a: main reinforcement 37b: distribution muscle

フロントページの続き (58)調査した分野(Int.Cl.6,DB名) E02D 5/34 B66C 1/62 E04G 21/16Continuation of the front page (58) Field surveyed (Int.Cl. 6 , DB name) E02D 5/34 B66C 1/62 E04G 21/16

Claims (6)

(57)【特許請求の範囲】(57) [Claims] 【請求項1】地面から掘り下げられた縦穴に、複数の主
筋と複数の配力筋によるコンクリート補強用の鉄筋組立
体を建て込む際に、 前記縦穴に、主筋保持手段を、前記縦穴の坑外から昇降
装置により該縦穴内で下降自在に設置し、 複数の主筋を、該複数の主筋の各々の配筋位置に対応さ
せた形で前記主筋保持手段に縦に保持させ、 前記縦穴の口元付近で前記複数の配力筋の各々を、前記
主筋保持手段に保持された複数の主筋に交差するよう該
主筋に接続しながら、 前記主筋保持手段を、前記縦穴の坑外から前記昇降装置
を介して該縦穴内で下方に移動させることによって、前
記複数の配力筋が接続された複数の主筋を、前記鉄筋組
立体として、該鉄筋組立体を前記主筋保持手段上に搭載
保持した形で、前記縦穴中に降ろしていくようにして構
成した、鉄筋建て込み方法。
When a reinforcing bar assembly for reinforcing concrete with a plurality of main bars and a plurality of distribution bars is erected in a vertical hole dug from the ground, a main reinforcement holding means is provided in the vertical hole, outside the vertical hole. Going up and down
It is installed in the vertical hole by the device so as to be able to descend freely, a plurality of main bars are vertically held by the main bar holding means in a form corresponding to each bar arrangement position of the plurality of main bars, and the vicinity of the mouth of the vertical hole is While connecting each of the plurality of distribution bars to the main bar so as to intersect with the plurality of main bars held by the main bar holding unit, the lifting / lowering device is connected to the main bar holding unit from outside the pit of the vertical hole.
By moving the plurality of main reinforcing bars connected to the plurality of force bars as the reinforcing bar assembly , the reinforcing bar assembly is mounted on the main reinforcing bar holding means by moving downwardly in the vertical hole through
A method of building a reinforcing bar, wherein the reinforcing bar is lowered into the vertical hole while being held .
【請求項2】フレームを有し、 前記フレームに主筋配筋手段を設け、 前記主筋配筋手段に複数の主筋配置部を、該主筋配置部
に対して主筋を上下に移動自在にそれぞれ保持し得るよ
うに設け、 前記主筋配筋手段の下方に主筋保持手段を、上下に移動
自在に設け、 前記フレームに、前記主筋保持手段を上下に移動駆動位
置決め自在な昇降装置を設け、 前記主筋配筋手段の主筋配置部と前記主筋保持手段の間
に主筋をセットし得るようにして構成したことを特徴と
する、鉄筋建て込み装置。
2. A main bar arrangement means is provided on said frame, and said main reinforcement arrangement means holds a plurality of main reinforcement arrangement portions, and holds the main reinforcements up and down with respect to said main reinforcement arrangement portions. A main bar holding means is provided below the main bar arrangement means so as to be movable up and down; and the frame is provided with an elevating device which can move and position the main bar holding means up and down and is positioned. A reinforcing bar setting device, wherein a main bar is set between a main bar arranging portion of the device and the main bar holding device.
【請求項3】前記主筋配置部は、建て込むべき主筋の配
筋ピッチに対応した形で形成して構成した、請求項2記
載の鉄筋建て込み装置。
3. The reinforcing bar laying device according to claim 2, wherein said main reinforcing bar arranging portion is formed in a form corresponding to a reinforcing bar pitch of a main reinforcing bar to be erected.
【請求項4】前記主筋配筋手段に主筋固定具を、前記複
数の主筋配置部の各々に主筋を水平方向に入れ込み自在
に設けて構成した、請求項2記載の鉄筋建て込み装置。
4. The reinforcing-bar laying device according to claim 2, wherein a main-bar fixing means is provided in said main-bar arrangement means so that a main bar can be freely inserted in each of said plurality of main-bar arrangement portions in a horizontal direction.
【請求項5】前記主筋配筋手段と前記主筋保持手段の間
に鉄筋建て込み位置決め具を、前記主筋配筋手段と整合
した位置に配置する形で上下方向に並べて設けて構成し
た、請求項2記載の鉄筋建て込み装置。
5. A reinforcing bar built-in positioning tool is provided between said main reinforcing bar arrangement means and said main reinforcing bar holding means so as to be arranged at a position aligned with said main reinforcing bar arrangement means in a vertical direction. 2. The reinforcing bar installation device according to 2.
【請求項6】配力筋保持手段を、配力筋建て込み位置の
内方から外側に向けて移動自在に設け、該配力筋保持手
段には複数の配力筋保持部を、上下方向に所定の間隔を
なすよう複数設けて構成した、請求項2記載の鉄筋建て
込み装置。
6. A distributing muscle holding means is provided movably from inside to outside of the distributing muscle building position, and the distributing muscle holding means includes a plurality of distributing muscle holding portions in a vertical direction. 3. The reinforcing-bar laying device according to claim 2, wherein a plurality of the reinforcing bars are provided at predetermined intervals.
JP6024841A 1994-01-27 1994-01-27 Reinforcing bar mounting method and rebar mounting device used for the same Expired - Fee Related JP2858205B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP6024841A JP2858205B2 (en) 1994-01-27 1994-01-27 Reinforcing bar mounting method and rebar mounting device used for the same

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP6024841A JP2858205B2 (en) 1994-01-27 1994-01-27 Reinforcing bar mounting method and rebar mounting device used for the same

Publications (2)

Publication Number Publication Date
JPH07216877A JPH07216877A (en) 1995-08-15
JP2858205B2 true JP2858205B2 (en) 1999-02-17

Family

ID=12149445

Family Applications (1)

Application Number Title Priority Date Filing Date
JP6024841A Expired - Fee Related JP2858205B2 (en) 1994-01-27 1994-01-27 Reinforcing bar mounting method and rebar mounting device used for the same

Country Status (1)

Country Link
JP (1) JP2858205B2 (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102295225A (en) * 2011-08-26 2011-12-28 中天建设集团有限公司 Steel reinforcement cage lifting structure

Families Citing this family (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP6261290B2 (en) * 2013-01-23 2018-01-17 辻 八郎 Vertical pile construction method
JP6431232B1 (en) * 2018-04-25 2018-11-28 辻 ふうな Rebar assembly method
CN113086848B (en) * 2021-03-31 2022-06-17 华中科技大学 Intelligent guiding method and system for double-machine hoisting pose of underground continuous wall reinforcement cage
CN113291974B (en) * 2021-05-24 2023-06-02 中建三局集团华南有限公司 Safe and convenient vertical and sliding hoisting device for supporting pile cage
CN116122268B (en) * 2023-02-07 2024-07-26 中交二航局第一工程有限公司 Pile head reinforcing steel bar cage and construction method

Family Cites Families (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS5980817A (en) * 1982-10-30 1984-05-10 Hisaichi Tekkin:Kk Connection work of iron bars in deep foundation work

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102295225A (en) * 2011-08-26 2011-12-28 中天建设集团有限公司 Steel reinforcement cage lifting structure

Also Published As

Publication number Publication date
JPH07216877A (en) 1995-08-15

Similar Documents

Publication Publication Date Title
JP4385236B1 (en) Reinforcement construction method for deep pile and its reinforcing bar unit
CN108203981B (en) System and method for installing steel support in cover and excavation method
JP2858205B2 (en) Reinforcing bar mounting method and rebar mounting device used for the same
JP5075398B2 (en) Construction method of tower-like PC structure and tension system device
JP3070657B2 (en) Reinforcing equipment
JP2858206B2 (en) Rebar hanging jig
JP3841499B2 (en) Slope working scaffold and method of constructing slope working scaffold
JP3068781B2 (en) Reinforcing equipment
JP3220397B2 (en) Elevating scaffold
JP6431232B1 (en) Rebar assembly method
JPH09177070A (en) Method and device for placing of steel bar cage for deep foundation
JP2001055733A (en) Construction method for underground wall and underground wall structure thereof
JPH09125370A (en) Reinforcing steel installation device
JP2681219B2 (en) Working scaffolding in the deep foundation method
KR102503595B1 (en) Energy reduction underground retaining wall demolition method
JP5597952B2 (en) How to build the connection between the column and foundation, and how to place the ring reinforcement
JP2681218B2 (en) Working scaffolding in the deep foundation method
JPH05263531A (en) Automatic construction method and lifting-up device of structure
JP3538806B2 (en) Rebar assembling method for deep foundation and circular work table used for it
JP3021199B2 (en) Construction method of chimney inner cylinder and pull jack up device for the construction
JP3753821B2 (en) 押 し Pipe construction push-up device
JPH08284418A (en) Method for installing elevator for construction
JPS6152305B2 (en)
JPS61229017A (en) Deep foundation pile reinforcement assembling method and scaffold additionally functioning as jig for assembling reinforcement
JPH08218638A (en) Suspending jig, method of building reinforcement with the use of suspended jig, and reinforcement swing preventing jig used for suspended jig

Legal Events

Date Code Title Description
R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

LAPS Cancellation because of no payment of annual fees