JP3753821B2 - 押 し Pipe construction push-up device - Google Patents

押 し Pipe construction push-up device Download PDF

Info

Publication number
JP3753821B2
JP3753821B2 JP35483296A JP35483296A JP3753821B2 JP 3753821 B2 JP3753821 B2 JP 3753821B2 JP 35483296 A JP35483296 A JP 35483296A JP 35483296 A JP35483296 A JP 35483296A JP 3753821 B2 JP3753821 B2 JP 3753821B2
Authority
JP
Japan
Prior art keywords
gantry
pipe
dredging
push
pipe material
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Lifetime
Application number
JP35483296A
Other languages
Japanese (ja)
Other versions
JPH10184021A (en
Inventor
康博 泉
昭三 松井
勲 松本
良太 鬼頭
光久 西村
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Takasago Thermal Engineering Co Ltd
Obayashi Corp
Takenaka Corp
Original Assignee
Takasago Thermal Engineering Co Ltd
Obayashi Corp
Takenaka Corp
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Takasago Thermal Engineering Co Ltd, Obayashi Corp, Takenaka Corp filed Critical Takasago Thermal Engineering Co Ltd
Priority to JP35483296A priority Critical patent/JP3753821B2/en
Publication of JPH10184021A publication Critical patent/JPH10184021A/en
Application granted granted Critical
Publication of JP3753821B2 publication Critical patent/JP3753821B2/en
Anticipated expiration legal-status Critical
Expired - Lifetime legal-status Critical Current

Links

Images

Landscapes

  • Conveying And Assembling Of Building Elements In Situ (AREA)

Description

【0001】
【発明の属する技術分野】
本発明は、建物の竪配管を構築する際に用いられる竪配管用押し上げ装置に関するものである。
【0002】
【従来の技術】
従来、配管用の管材を高所にリフトアップしたり、揚重するための装置としては、タワークレーンのように管材の頂部にフック等を係止して、これを吊り上げるように構成されたものや、その他特開平6−286990号公報に開示された「配管リフトアップ装置」がある。後者は、走行可能なリフターに配管を水平に支持させるようにしたものである。
【0003】
ところで建物に竪配管する場合、従来はタワークレーン等のロングリフトで管材を1本、1本吊り上げ、順次管材の上に継ぎ足していったり、あるいは下に継ぎ足して、その分タワークレーンのワイヤを巻き上げていく方法が行われている。また複数の管材を同時に施工する方法として、複数本の管材をフレームや固定部材などを用いて竪管ユニットとしてユニット化し、これをタワークレーンなどで垂直状態で順次上側に揚重する工法が実施されている。
【0004】
【発明が解決しようとする課題】
しかしながらタワークレーンを用いる従来の方法によれば、タワークレーンを占有している時間が長く、建物における他の使用者との調整が必要であり、独自に工事を進めることができないなど問題がある。そこで発明者らは、タワークレーン等のロングリフトを用いることなく、垂直状態の管材を下から順次継ぎ足し、さらにこれを押し上げて竪配管を施工する方法を開発したが、前記した既存の配管リフトアップ装置では、管材を垂直に支持することができず、このような竪配管の施工方法に用いることができない。
【0005】
本発明はかかる点に鑑みてなされたものであり、タワークレーン等のロングリフトを用いることなく、竪配管を構成する管材を垂直状態で下から押し上げることのできる装置を提供して、垂直状態の管材を下から順次継ぎ足して施工する方法を好適に実施できるようにすることをその目的としている。
【0006】
【課題を解決するための手段】
前記第1の目的を達成するため,請求項1によれば,管材を下から順次継ぎ足して建物に竪配管を施工する際に用いる押し上げ装置であって,適宜の駆動手段によって垂直に上下動する架台と,前記架台の長手方向に沿って当該架台の上面に設けられ,竪配管を構成する管材を垂直に支持する複数の支持部材とを備えたことを特徴とする,竪配管施工用押し上げ装置が提供される。
【0007】
駆動手段としては、油圧ジャッキやモータを用いることができる。支持部材としては、例えば管材の下部が挿入されるソケット状の部材や、管材の下部に対して挿入する挿入部材を用いることができる。このような支持部材に垂直に支持された管材は、架台を上昇させることで垂直に押し上げられる。従って、押し上げられた管材を建物側に仮固定し、次いで架台を下降させて次の管材を架台の支持部材に支持させ、再び架台を上昇させて、先の管材の下端部と次の管材の上端部とを接続し、その後仮固定を解除してさらにそのまま次の管材を架台で押し上げることによって、先の管材ごと上昇する。それゆえ垂直状態の管材を下から順次継ぎ足して竪配管を施工することが可能になる。
【0008】
かかる竪配管施工用押し上げ装置において,請求項2に記載したように,架台における支持部材の位置を架台の長手方向に沿って変更自在に構成すれば,複数の管材を同時に押し上げて配管を同時に施工する場合,個々の配管の芯出しに対処することができる。
【0009】
さらに請求項3に記載したように、架台に複数の支持部材を設けた場合、少なくとも一部の支持部材による管材の支持高さを、他の支持部材による管材の支持高さと異なるように構成すればさらに好ましい作用効果が得られる。即ち同時に複数の管材を押し上げると、通常管材の長さは同一であるから、各管材とも同じタイミングで先の管材と当接することになる。そうすると各管材とも一斉に芯合わせと接続作業を実施しなければならない。しかしながら請求項3に記載したように、少なくとも一部の支持部材による管材の支持高さを、他の支持部材による管材の支持高さと異なるように構成すれば、当該異なった高さの分だけ、タイミングがずれて各管材が先の管材と順に当接することになる。従って、芯合わせや接続が順次個別に行えることになる。
【0010】
さらに請求項4のように、架台を、垂直に配置されたガイド部材に沿って上下動させるようにすれば、架台を安定した状態で上下動させることができる。ガイド部材としては、例えば架台の両端に配置するガイドレールや、架台を挿通する適宜のシャフト部材等が提案できる。
【0011】
そして架台によって押し上げた管材を仮固定するための仮固定装置を,架台の上方に設ける上部架台に設置すれば,一旦管材を押し上げ,この押し上げた管材をそのまま当該仮固定装置で仮固定できるので,架台を下げて次に接続すべき管材を架台に支持させ,再び架台を上昇させて先の管材の下に芯合わせして接続することが容易になる。なおこの上部架台は建物側に固定させる。仮固定装置は,かかる作用に鑑み,少なくとも管材が落下しないようにできるものであればよく,管材を把持する構成に限らず,例えば吊下したり,係止できるものであればよい。
【0012】
このように上部架台を備えた竪配管施工用押し上げ装置において,さらに請求項に記載したように,架台と上部架台との間にはネジ軸が渡され,適宜の駆動手段による回転駆動でウォームギヤ機構を介してこのネジ軸を上下動させることで,この架台を上下動させるように構成したり,請求項に記載したように,架台側だけを上下動させたり,さらには請求項に記載したように,ネジ軸を上下動させると同時に,当該ネジ軸に沿って架台を上下動させるようにしてもよい。駆動手段としてはモータが適しており,このモータを例えばインバータ制御することにより,架台の上下動の速度を調節することが容易になる。さらにエンコーダを併用することにより,上昇量の微調整や所定の上昇量の設定が容易になり,管相互の芯合わせや接続作業を行いやすい。なおネジ軸を渡すとは,1本のネジ軸を渡すものに限らず,複数のネジ軸を適宜接続して渡すようにした場合も含む。
【0013】
請求項の場合には,例えばウォームギヤ装置におけるウォームホイルの内周にネジを切ってネジ軸と螺合させ,このウォームホイルの外周にネジを切ってウォームと螺合させ,当該ウォームをモータ等で回転させれば,ウォームギヤ装置を備えた上部架台側は固定されているので,ネジ軸を上下動させることができ,しかも大きい力で上下動させることができる。
【0014】
請求項の場合には,例えばウォームギヤ装置におけるウォームホイルの内周にネジを切ってネジ軸と螺合させ,このウォームホイルの外周にネジを切ってウォームと螺合させ,当該ウォームをモータ等で回転させれば,架台側の方をネジ軸に沿ってを上下動させることができる。
【0015】
請求項の場合は,いわば前記請求項5,6の双方の構成を採用したものであり,ネジ軸が上下動すると同時にこのネジ軸に沿って架台が上下動する。従って極めて大きい力で架台を上下動させることができると共に,ネジ軸の上下動量,架台自体がネジ軸に対して移動する移動量を,前記請求項5,6よりも少なくすることができ,架台の上下動速度を高くすることができる。
【0016】
【発明の実施の形態】
以下、図面に基づいて本発明の実施の形態を説明する。図1は本実施形態にかかる竪配管施工用の押し上げ装置10を用いて実施する竪管の施工方法の準備段階を示しており、まず竪配管を実施する建物の一階の床面1から二階の階床部2、三階の階床部3に渡って、本実施形態にかかる押し上げ装置10を設置する。この押し上げ装置10は、1階の床面1から2階の階床部2にかけて垂直に立設させた2本の対向するガイドレール11、12と、これらガイドレール11、12間に装着され、これらガイドレール11、12に沿って上下に摺動自在な架台13とを有している。この架台13は、竪配管、即ちシャフト配管の全重量を受けるものであり、例えばH鋼などの鋼材を利用して構成されている。
【0017】
この架台13の上面には、支持部材となる6本の芯出し治具14、15、16、17、18、19が設けられている。もちろんその数は任意である。これら各芯出し治具14、15、16、17、18、19は、架台13の長手方向(図中のX方向)に移動自在であり、また任意の位置にて固定自在である。このような芯出し治具14〜19の移動自在性、固定自在性は、例えば架台13の上面に長孔や複数のボルト孔を形成し、配管位置に合ったボルト孔にて固定することによって実現される。
【0018】
例えば図2に示したように、芯出し治具14の下面にプレート14xを設け、このプレート14xに適宜弧状の長孔14yを複数環状に形成する。一方架台13には、長手方向に沿って2本の長孔13a、13aを形成する。そして所定の配管位置に、芯出し治具14のプレート14xをあてがい、適宜の固定手段、例えばボルト81を、長孔14y及び長孔13挿通させて、その突出部にナット82を締め付けて固定する。かかる構成により、芯出し治具14〜19の移動自在性、固定自在性は容易に実現でき、配管位置に合わせて芯出し治具14〜19を自由に固定させることができる。
【0019】
各芯出し治具14、15、16、17、18、19は、竪配管する管材の径に対応する大きさの支持柱14a、15a、16a、17a、18a、19aと、各支持柱14a、15a、16a、17a、18a、19aの上部に設けられたソケット状の受容部14b、15b、16b、17b、18b、19bとを有している。これら各受容部14b、15b、16b、17b、18b、19bの内径は、竪配管する管材の径に適合した大きさである。
【0020】
また各受容部14b、15b、16b、17b、18b、19bの底面の位置は、全て異なった高さとなるように設定してある。例えば受容部14b、15bについていえば、受容部14bの底面14cの位置は、受容部15bの底面15cの位置よりも、高さdだけ高いところに位置するように設定してある。この場合、高さdは、10mm前後が適当である。他の受容部16b、17b、18b、19bについても同様であり、図3に示したように、本実施形態に用いた芯出し治具14、15、16、17、18、19における各受容部14b、15b、16b、17b、18b、19bにおいては、受容部14bの底面14cが最も高く、以下順次高さd分だけ低くなるように各底面の位置を設定し、受容部19bの底面19cが最も低い位置となるようにしてある。これによって各芯出し治具14、15、16、17、18、19は、各々管材の支持高さを異なったものとしている。
【0021】
この場合、そのように各受容部14b、15b、16b、17b、18b、19bの底面の位置を各々変えて支持高さを異なったものとする構成に代えて、図4に示したように、例えば受容部17b、18b、19bに基づいて説明すると、各受容部17b、18b、19bの底面17d、18d、19dは全て同一の高さとしておき、その上に必要に応じて高さがdの、専用の単位スペーサS1、S2を用い、必要な高さ分に応じた枚数のこの単位スペーサを、受容部17b、18b内に納入するようにしてもよい。例えば、受容部17bに対しては、単位スペーサS1を2枚、受容部17bには単位スペーサS2を1枚納入しておけば、高さdだけ各々異なった支持高さを実現することができる。なおこのような単位スペーサは、ある程度弾性を有する材質で構成すれば、管材挿入時に当該管材の下端を衝撃から保護することができる。
【0022】
三階の階床部3には、押し上げ装置10における上部架台21が設置固定される。この上部架台21は、2本の鋼材、例えばH鋼材を所定の間隔をあけて平行に配した構成を採っている。そしてこの上部架台21の両端近傍には、外周にネジを切った、ネジ軸となる2本のネジ棒22、22が貫通し、後述のウォームギヤ装置27内のウォームホイルの内周と螺合している。そしてこのネジ棒22はさらに三階の階床部3のスリーブ3aや3bを遊貫している。
【0023】
これら各ネジ棒22、22の下端部には、図5に示したように、接続部材23、23を介してネジ棒接続治具24、24の上端部が、ピン83、割ピン84等で接続されている。このネジ棒接続治具24、24は、二階の階床部2に形成された対応する適宜のスリーブ2a、2bを遊貫している。さらに各ネジ棒接続治具24、24の下端部には、接続部材25、25を介して、外周にネジを切った2本のネジ棒26、26の上端部がピン83、割ピン84等で取り付けられ、これらネジ棒26、26の下端部は、各々前記架台13の両端部近傍を貫通し、後述のウォームギヤ装置29内のウォームホイルの内周と螺合している。
【0024】
上部架台21の上面には、ネジ棒22、22と螺合するウォームギヤ装置27、27が取り付けられており、さらに各ウォームギヤ装置27はモータ28によって駆動されるようになっている。従って、各モータ28を作動させると、ウォームギヤ装置27内のウォーム(図示せず)が回転し、これによってウォームギヤ装置27内のウォームホイル(図示せず)が回転し、このウォームホイルの内周と螺合しているネジ棒22、22は上昇又は下降する。従って、それに伴ってネジ棒接続治具24、24及びネジ棒26、26も上下動する。
【0025】
架台13の下面には、ネジ棒26、26と螺合するウォームギヤ装置29、29が取り付けられており、さらに各ウォームギヤ装置29はモータ30によって駆動されるようになっている。従って、各モータ30を作動させると、ウォームギヤ装置29内のウォーム(図示せず)が回転し、これによってウォームギヤ装置29内のウォームホイル(図示せず)が回転し、それに伴ってガイドレール11、12に対して摺動自在な架台13は、前記ウォームホイルの内周と螺合しているネジ棒26、26に対して上昇又は下降する。
【0026】
前記したモータ28、30は、別設の制御装置31によって制御され、モータ28、30に付設されているエンコーダの機能と相俟って、架台13を上昇、下降させるときの速度、移動量等は、全てこの制御装置31によって制御されるようになっている。
【0027】
即ち、図6に示したように、制御装置31は、操作タッチパネル32、シーケンサ33、インバータ34を有しており、操作タッチパネル32から必要な情報、例えば架台13が上下動する際の速度設定、移動量設定、水平出しのための偏差設定をシーケンサ33に入力すると、それに応じてモータ28、30の回転を制御するインバータ34に対して必要な信号が入力され、それに基づいてインバータ34はモータ28、30を制御するようになっている。他方、各モータ28、30には、対応するエンコーダ35、36が付設されており、積算回転数に応じた位置信号をシーケンサ33にフィードバックするようになっている。これによって架台13の位置を正確に制御することが可能であり、所定の位置での停止も正確に行える。
【0028】
上部架台21には、三階の階床部3の配管用のスリーブ3c、3d、3e、3f、3g、3hの上方に位置するように、夫々対応する6つの仮固定装置41、72、73、74、75、76が固定されている。各仮固定装置41、72、73、74、75、76は、大きさが異なるのみで基本的には同一構成であるから、いま仮固定装置41を図7に基づいて説明する。これらの仮固定装置の材質としては、例えば板厚20mm以上の鋼板を用いることが好ましい。
【0029】
この仮固定装置41は、上部支持台14を構成している2本の鋼材21a、21bに跨って略箱体形状の本体42が固定され、この本体42の上面開口部周縁に、2つの係止体43、44が上方に回動自在となるように取り付けられた構成を有している。これら係止体43、44は左右対称形状をなし、各々内側が突き合わさるように対向して配置され、各外側辺43a、44aの両端近傍と、本体42との間に、蝶番等の回動部材45を取り付けて、水平状態から上方にのみ回動自在となるように構成されている。
【0030】
また係止体43、44の突き合わせ側内側辺には、半円形の切欠部43b、44bが形成されている。そして図5に示したように、係止体43、44が水平状態で各内側辺が突き合わさっている状態では、これら2つの切欠部43b、44bによって円形の開口部Hが形成される。この開口部Hの内径は、スリーブ3cに配管される管材P11やP21の外径よりも僅かに大きい程度に設定され、後述のつば部pfの外径よりも小さくなるように設定されている。即ちスリーブ3cに配管される管材の本体のみを通過させる大きさに設定されている。
【0031】
本実施形態にかかる押し上げ装置10は以上のように構成されており、さらにこの押し上げ装置10を用いて竪管の施工方法を好適に実施するために、三階の階床部3の下面には、管材を吊り込むための吊り込み装置として、往復牽引ウインチ(摩擦巻胴式のエンドレスウインチ)51が設けられている。この往復牽引ウインチ51は、少なくとも配管用のスリーブ3c〜3hまでの範囲をカバーできるように、左右に移動自在である。この往復牽引ウインチ51は、一階の床面1で組み立てられたネジ棒22やネジ棒接続治具24を引き上げる際にも使用される。なおこの往復牽引ウインチ51に代えて、他の吊り込み装置、例えばチェーンブロックを用いてもよい。
【0032】
さらに四階の階床部4の上面には、最上部に配管されることになる管材P11〜P16を引き上げるための他の往復牽引ウインチ52が、階床部4上を移動自在な支持体53に設けられている。この往復牽引ウインチ52についても、他の公知の吊り込み装置を用いることができる。
【0033】
押し上げ装置10や、その仮固定装置41、及び往復牽引ウインチ51、52は以上のようにして予め所定の位置にセットされる。また架台13の芯出し治具14〜19も、予め配管位置に合わせて架台13上の所定の位置にて、例えば図2に示した方法で固定される。
【0034】
これから実施しようとする竪管の施工方法においては、図8に示したように、各管材Pの上端部近傍の外周に、つば部pfを、例えば溶接等によって固着した管材Pを用いている。このようなつば部pfに限らず、外周に突出する形態の適宜の突部を形成した管材であれば、本実施形態にかかる竪管の施工方法に使用することが可能である。なおつば部pfの固着位置は、管径の大小に係わらず、全て同一位置に設定してある。即ち図6中の管材Pの上端部からつば部pfまでの距離Mは、後述の全ての管材とも同一である。なおつば部pfには、公知の接続ソケットで兼用することができる。
【0035】
次に施工手順について説明すると、まず最上部に配管される管材P11、P12、P13、P14、P15、P16は、四階の階床部4の上面に設けられた往復牽引ウインチ52で、図9に示したように吊り込まれる。なおこれら最上部に配管される管材P11、P12、P13、P14、P15、P16の各頂上部には、吊り込みに供するための係止具pkを予め固着しておけば、往復牽引ウインチ52のワイヤ52aでの吊り込みに便利である。
【0036】
例えば端に配管される管材P11を吊り込む手順について説明すると、往復牽引ウインチ52のワイヤ52aを、四階の階床部4のスリーブ4c、仮固定装置41、三階の階床部3のスリーブ3c、二階の階床部2のスリーブ2cを通じて階下に降ろし、一階に置かれている管材P11の頂上部に設けられた係止具pkに、往復牽引ウインチ52のワイヤ52aの先端部にあるフック52bを係止する。
【0037】
次にこのワイヤ52aを巻き上げていくと共に管材P11を立ち上げ、垂直状態で吊り上げてスリーブ2cを通過させ、図10の状態からさらにスリーブ3cを通過させる。そしてなおもそのまま吊り上げていくと、仮固定装置41に形成されている開口部Hは管材P11の本体のみを通過させる形状であるから、やがて管材P11のつば部pfが開口部Hの周縁部、即ち各係止体43、44の切欠部43b、44bに引っかかり、管材P11の吊り上げにより、図11に示したように、各係止体43、44は開いて持ち上げられる。
【0038】
なおもそのまま吊り上げていくと、各係止体43、44の切欠部43b、44bに対する管材P11のつば部pfの前記引っかかりは解除され、図12に示したように、各係止体43、44は、自重によって下方に回動して水平状態になる。ここで管材P11の吊り上げを停止し、逆に管材P11を徐々に降ろしていくと、図13に示したように、管材P11のつば部pfが開口部Hの周縁部、即ち各係止体43、44の切欠部43b、44bに係止され、管材P11はその時点で仮固定装置41に吊下された状態、即ち仮固定状態となる。
【0039】
他の最上部に配管される管材P12、P13、P14、P15、P16も、全く同じ要領で吊り込んで、図9、図14に示したように、上部架台21の対応する各仮固定装置72、73、74、75、76で仮固定させる。そのようにして最上部に配管される管材P11、P12、P13、P14、P15、P16を全て仮固定した段階で、四階の階床部4に設置していた往復牽引ウインチ52は撤去する。
【0040】
次に前記管材P11、P12、P13、P14、P15、P16の下に配管される管材P21、P22、P23、P24、P25、P26を往復牽引ウインチ51で吊り込み、その上端部を二階の階床部2の対応する各スリーブ2c、2d、2e、2f、2g、2h内に挿入すると共に、各下端部を架台13上に設けてある各芯出し治具14、15、16、17、18、19の各受容部14b、15b、16b、17b、18b、19b内に挿入し、管材P21、P22、P23、P24、P25、P26を自立させる。
【0041】
この場合、前出図8に示したように、各管材Pには、その上端部近傍外周につば部pfが形成してあるので、図14に示したように、往復牽引ウインチ51のワイヤ51aによって吊り込む際、ワイヤ51aをこのつば部pfに係止させて取り付けることができ、作業しやすく、しかも安定して吊り込むことができる。また往復牽引ウインチ51は、適宜図中のX方向に移動自在であるから、全ての管材P21、P22、P23、P24、P25、P26を吊り込むことが可能である。
【0042】
そのようにして各管材P21、P22、P23、P24、P25、P26のセットが完了すると、制御装置31の操作タッチパネル32に上昇高さ等を入力し、各モータ28、30を作動させる。モータ28が作動すると、ネジ棒22の回転によって当該ネジ棒22自体が上昇し、それに伴ってネジ棒接続治具24、24が上昇する。一方モータ30の作動によりネジ棒26が回転し、それに伴って架台13がガイドレール11、12に沿って上昇する。従って架台13は、ネジ棒26自体の上昇と、このネジ棒26に沿っての架台13自体の上昇とによって上昇し、それによって架台13の芯出し治具14、15、16、17、18、19の各受容部14b、15b、16b、17b、18b、19b内にその下端部が挿入されている各管材P21、P22、P23、P24、P25、P26が上方に押し上げられる。
【0043】
各管材P21、P22、P23、P24、P25、P26が上方に押し上げられると、その上端部が、先の管材P11、P12、P13、P14、P15、P16の下端部に接近する。ここで図15に示したように、各芯出し治具14、15、16、17、18、19の各受容部14b、15b、16b、17b、18b、19における各底面の位置は、受容部14bのそれが最も高く、受容部19bのそれが最も低くなるように順次に高さが異なっている。従って、架台13を上昇させて各管材P21、P22、P23、P24、P25、P26を同時に同一速度で押し上げても、図16に示したように、受容部14b内にその下端部が挿入されている管材P21の上端面が最も速く、先の管材P11の下端部に到達して接触する。かかる接触は、二階の階床部2上の空間にて行われる。
【0044】
その時点で、適宜芯合わせをしながら、架台13の押し上げを停止し、管材P11の下端部と管材P21の上端部との接続、例えば仮溶接を実施する。この場合、モータ28、30の回転速度等によって架台13の上昇速度は微調整が容易であるから、芯合わせ作業が非常に実施しやすい。そしてそのようにして管材P11の下端部と管材P21との仮溶接が終了すると、再びモータ28、30を上昇側に作動させて架台13を上昇させる。
【0045】
そうすると次は図17に示したように、管材P22の上端部が管材12の下端部と当接する。ここで適宜芯合わせをしながら、架台13の押し上げを停止し、管材P11の下端部と管材P21の上端部とを仮溶接する。次いで再びモータ28、30を上昇側に作動させて架台13を上昇させると、今度は図18に示したように、管材P23の上端部が管材13の下端部と当接する。後は全く同様な手順で仮溶接を実施し、以下他の管材P24、P25、P26についても同様にして、夫々対応する管材P14、P15、P16と順次仮溶接していく。
【0046】
このように次々と時期を違えて各管材P21、P22、P23、P24、P25、P26の上端部が、先の管材P11、P12、P13、P14、P15、P16の下端部との仮溶接位置に到達するので、少ない作業員でも効率よくかつ正確に管材P21、P22、P23、P24、P25、P26の上端部と、管材P11、P12、P13、P14、P15、P16との接続作業が行える。また既述したように、そのときに必要な芯合わせ作業も非常に容易である。またかかる仮溶接による接続作業は全て、二階の階床部2上の空間の低所で行えるから、この点でも作業環境は良好である。なおここでねじ込み配管は、本締め、フランジ、コア等も本締めを行う。
【0047】
管材P21、P22、P23、P24、P25、P26の上端部と、先の管材P11、P12、P13、P14、P15、P16の下端部との仮溶接が完了すると、モータ28、30を上昇側に作動させて架台13を上昇させ、管材P21、P22、P23、P24、P25、P26を、先の管材P11、P12、P13、P14、P15、P16ごと押し上げていく。そうすると、まず図19に示したように、管材P21のつば部pfが仮固定装置41に接近する。そしてそのまま架台13を上昇させていくと、既述の先の管材P11、P12、P13、P14、P15、P16の仮固定と全く同じ要領で、管材P21、P22、P23、P24、P25、P26は、対応する仮固定装置41、72、73、74、75、76に仮固定されるのである。例えば管材P21についていえば、仮固定装置41に形成されている開口部Hは管材P21の本体のみを通過させる形状であるから、図20に示したように、管材P21のつば部pfが開口部Hの周縁部、即ち各係止体43、44の切欠部43b、44bに引っかかり、管材P21の押し上げにより、図20に示したように、各係止体43、44は開いて持ち上げられる。
【0048】
なおもそのまま押し上げると、各係止体43、44の切欠部43b、44bに対する管材P21のつば部pfの前記引っかかりは解除され、図21に示したように、各係止体43、44は、自重によって下方に回動して水平状態になる。既述したように、架台13による押し上げの際には、各管材P21、P22、P23、P24、P25、P26の上端部の位置、即ち各つば部pfの高さは、管材P21が最も高い位置にあり、管材P26のつば部pfの高さは最も低い位置にある。従って、図19〜図21に至るプロセスは、管材P21が最も速く、管材P26が最も遅く達成される。
【0049】
そして最も遅い管材P26が、図21の状態になった時点、即ち仮固定装置46の係止体が水平状態に復帰した時点で、モータ28、30を下降側に作動させ、架台13を下降させていく。そうすると、各管材P21、P22、P23、P24、P25、P26も下降していき、やがて今度は管材P26の方から順に、対応する仮固定装置76、75、74、73、72、41に各々各つば部pfが係止され、仮固定されていく。例えば最も遅く仮固定される管材P21についていえば、図22に示したように、管材P21のつば部pfが仮固定装置41における開口部Hの周縁部、即ち各係止体43、44の切欠部43b、44bに係止され、管材P21はその時点で仮固定装置41に吊下された状態、即ち仮固定状態となるのである。
【0050】
全ての管材P21、P22、P23、P24、P25、P26が、対応する仮固定装置41、72、73、74、75、76に仮固定された状態を図23に示した。なお架台13はそのまま下降させ、再び次の管材を設置する位置、即ち図9の状態で停止させ、往復牽引ウインチ51によって次の管材、例えば管材21の下に接続配管される管材31の吊り込み作業を実施する。
【0051】
この間仮固定されている管材P21、P22、P23、P24、P25、P26については、仮溶接してある先の管材P11、P12、P13、P14、P15、P16との接続部に対して、本溶接を実施し、例えば溶接部の防錆塗装まで実施する。かかる作業は三階の階床部3上の空間内で行え、作業がしやすい。接続部分が図23に示したように、当該空間の低所にくるように予め管材Pのつば部pfの位置を設定しておけば、さらに作業が容易である。また管材P21、P22、P23、P24、P25、P26はそのように仮固定されている状態であるから、この点でも作業しやすくなっている。
【0052】
以上のようにして順次管材Pを往復牽引ウインチ51で吊り込んで架台13にセットし、その後押し上げて二階部分で仮溶接し、次いで先の管材ごと押し上げて仮固定して本溶接を実施する作業を繰り返して行けば、所定の竪配管が施工される。
【0053】
そして図24に示したように、管材P21、P22、P23、P24、P25、P26に、管材P31、P32、P33、P34、P35、P36、管材P41、P42、P43、P44、P45、P46を接続し、例えば次に接続する管材P51、P52、P53、P54、P55、P56が最下部の配管、最後に接続する管材であった場合、管材P41、P42、P43、P44、P45、P46との仮溶接が終了し、最後に所定の配管箇所に押し上げる前の段階で、同図に示したように、先の管材P31、P32、P33、P34、P35、P36における配管後に高所に位置する部分に対して、断熱材61を取り付ける作業を実施する。もちろん他の管材P41、P42、P43、P44、P45、P46における配管後に高所に位置する部分A、管材P51、P52、P53、P54、P55、P56における配管後に高所に位置する部分Bに対しても必要な処理、例えば断熱処理、スリーブ貫通部の穴埋め処理、防火処理、その他必要な処理をこの段階で行う。
【0054】
図24に示した段階では、未だ管材が所定の配管位置に達しておらず、配管後に天井部など高所に位置する部分は、階床部のやや上方、即ち低所に位置している状態である。従って、前記した各作業はきわめて容易に実施することができる。また架台13の位置(高さ)によって、配管後に高所に位置する部分の位置を調整できるから、最も作業しやすい位置となったところで架台13を停止させればよい。
【0055】
以上のようにして、各管材に対して配管後に高所に位置する部分に必要な処理を行った後、モータ28、30を上昇側に作動させて架台13を上昇させて、最後の管材P51、P52、P53、P54、P55、P56を所定位置まで押し上げたうえ、押し上げ代の断熱を施し、各階にて所定の支持金物等の取り付け作業を実施すれば、竪配管の施工が完了する。
【0056】
以上の作業手順でもわかるように、本実施形態にかかる押し上げ装置10を用いれば、タワークレーン等のロングリフトを使用することなく竪配管の施工ができる。従ってこれまで面倒であったタワークレーンの使用についての他の工事方との調整が不要であり、設計段階の早期に工事日程等を決定する必要もない。またその分、タワークレーンを使用する他の工事方の工事期間も短縮できる。
【0057】
しかも下方からの押し上げによって上側の管材の下端部と下側の管材の上端部との接続を行うことができるので、管相互の芯合わせが容易であり、接続作業が従来より簡易、迅速かつ精度よく行える。また架台13の芯出し治具14〜19の各受容部14b〜19bに管材Pの下端部を挿入することで、管材Pを垂直に支持し、この架台13を上昇させて管材Pを押し上げるようにしているから、安定した押し上げ作業が行える。しかも架台13の両端部は、ガイドレール11、12に沿って摺動自在であるから、さらに安定した押し上げ作業を可能にしている。
【0058】
そして架台13に設けられた各芯出し治具14、15、16、17、18、19の各受容部14b、15b、16b、17b、18b、19bにおける各底面の位置(高さ)が各々異なっており、管材の支持高さが違っているため、上側の6本の管材の下端部と下側の6本の管材の上端部とを接続する場合、下側の6本の管材の上端部が、上側の6本の管材の下端部との接続位置には順次時期を違えて到達するため、個別に芯合わせや接続作業を実施することができる。それゆえ、少ない作業員でかかる接続作業を効率よく行うことができる。また6本同時に芯合わせする必要がないので、芯合わせ自体を正確に行うことができる。
【0059】
さらに、上部架台21には、仮固定装置41、72〜76が設けられているので、架台13によって押し上げられた管材は、これら仮固定装置41、72〜76によってそのまま仮固定することができ、後の作業がしやすい。また架台13の上下動は、モータ28、30によるネジ軸22、26の回転によって実現しており、上下動の際の速度や上下の移動量の制御が容易である。
【0060】
【発明の効果】
請求項1〜に記載の竪配管用押し上げ装置によれば,架台を上昇させることで,架台の支持部材に垂直に支持した管材を,垂直に押し上げることができる。従って,タワークレーン等のロングリフトを用いることなく,垂直状態の管材を下から順次継ぎ足して施工する竪管の施工方法を好適に実施することができる。即ち。従来のようにロングリフトで吊り上げる工法に比べて工事スペースをとらず,市街地の再開発事業などで好適に実施することができる。
【0061】
特に請求項の場合には,複数の管材を同時に押し上げて配管を同時に施工する場合,個々の配管の芯出しに対処することができる。さらに請求項3の場合には,同時に複数の管材を押し上げても,タイミングをずらせて各管材を先の管材と当接させることができ,管相互の芯合わせや接続が順次個別に行える。そして請求項4によれば,さらに架台を安定した状態で上下動させることができるという効果が得られる。
【0062】
そして請求項5〜7の各押し上げ装置によれば,架台の上下動の速度調節や上昇量の微調整や所定の上昇量の設定が容易になり,管相互の芯合わせや接続作業を行いやすいという効果がさらに得られる。また大きい力で架台を上下動させることが容易である。特に請求項8の場合には架台の上下動速度を高くすることができ,迅速な作業を行える。
【図面の簡単な説明】
【図1】 本発明の実施の形態にかかる押し上げ装置を所定の位置にセットした状態を示す説明図である。
【図2】図1の押し上げ装置における架台に芯出し治具を取り付ける様子を示す斜視図である。
【図3】図1の押し上げ装置における架台の芯出し治具の断面説明図である。
【図4】他の芯出し治具の断面説明図である。
【図5】図1の押し上げ装置におけるネジ棒とネジ棒接続治具の取り付ける様子を示す斜視図である。
【図6】図1の押し上げ装置における制御装置の説明図である。
【図7】図1の押し上げ装置における上部架台の仮固定装置の斜視図である。
【図8】図1の押し上げ装置を用いて竪管の施工方法を実施する際に用いた管材の上部の正面図である。
【図9】図1の押し上げ装置を用いて実施する竪管の施工方法において、最上部の管材を仮固定した状態を示す説明図である。
【図10】図7の仮固定装置に最上部の管材が接近した状態を示す説明図である。
【図11】図7の仮固定装置における係止体を最上部の管材のつば部が持ち上げた状態を示す説明図である。
【図12】図7の仮固定装置における係止体が水平状態に復帰した状態を示す説明図である。
【図13】図7の仮固定装置における係止体に最上部の管材のつば部が係止されて仮固定された状態を示す説明図である。
【図14】図1の押し上げ装置を用いて実施する竪管の施工方法において、最上部に配管される管材を仮固定した後、架台を次の管材のセット位置まで下降させて次の管材を吊り込んでいる様子を示す説明図である。
【図15】図1の押し上げ装置を用いて実施する竪管の施工方法において、次の管材を押し上げて最上部の管材に接近させた状態を示す説明図である。
【図16】図1の押し上げ装置を用いて実施する竪管の施工方法において、次の管材を押し上げて最初の管材の上端部が対応する最上部の管材の下端部と接触した状態を示す説明図である。
【図17】図1の押し上げ装置を用いて実施する竪管の施工方法において、次の管材を押し上げて2番目の管材の上端部が対応する最上部の管材の下端部と接触した状態を示す説明図である。
【図18】図1の押し上げ装置を用いて実施する竪管の施工方法において、次の管材を押し上げて3番目の管材の上端部が対応する最上部の管材の下端部と接触した状態を示す説明図である。
【図19】図7の仮固定装置に次の管材が接近した状態を示す説明図である。
【図20】図7の仮固定装置における係止体を次の管材のつば部が持ち上げた状態を示す説明図である。
【図21】図7の仮固定装置における係止体が水平状態に復帰した状態を示す説明図である。
【図22】図7の仮固定装置における係止体に次の管材のつば部が係止されて仮固定された状態を示す説明図である。
【図23】図1の押し上げ装置を用いて実施する竪管の施工方法において、架台が上昇して全ての次の管材が仮固定された状態を示す説明図である。
【図24】図1の押し上げ装置を用いて実施する竪管の施工方法において、最後に接続する管材の最終押し上げ前に、先の管材に対して断熱処理を行っている様子を示す説明図である。
【符号の説明】
1 一階の床面
2 二階の階床部
3 三階の階床部
4 四階の階床部
10 押し上げ装置
11、12 ガイドレール
13 架台
14、15、16、17、18、19 芯出し治具
14b、15b、16b、17b、18b、19b 受容部
21 上部架台
22、26 ネジ棒
24 ネジ棒接続治具
27、29 ウォームギヤ装置
28、30 モータ
31 制御装置
41、72、73、74、75、76 仮固定装置
P 管材
pf つば部
[0001]
BACKGROUND OF THE INVENTION
The present invention relates to a lifting device for a fence pipe used when building a fence pipe for a building.
[0002]
[Prior art]
Conventionally, as a device for lifting and lifting pipe material for piping to a high place, like a tower crane, it is configured to hook a hook etc. on the top of the pipe material and lift it up In addition, there is a “pipe lift-up device” disclosed in JP-A-6-286990. In the latter, the pipe is horizontally supported by a lifter capable of traveling.
[0003]
By the way, when piped to a building, conventionally, one pipe and one pipe are lifted with a long lift such as a tower crane, and the pipes are added to the pipes one after another, or are added below, and the tower crane wire is wound up accordingly. There is a way to go. In addition, as a method of constructing multiple pipe materials at the same time, a method has been implemented in which multiple pipe materials are unitized as a dredging pipe unit using a frame or a fixed member, and this is sequentially lifted upward in a vertical state using a tower crane or the like. ing.
[0004]
[Problems to be solved by the invention]
However, according to the conventional method using a tower crane, there is a problem that it takes a long time to occupy the tower crane, adjustment with other users in the building is required, and the construction cannot be independently performed. Therefore, the inventors have developed a method of constructing a vertical pipe by sequentially adding vertical pipe materials from the bottom without using a long lift such as a tower crane, and further raising the pipe. In the apparatus, the pipe material cannot be supported vertically, and cannot be used in the construction method of such dredging pipes.
[0005]
The present invention has been made in view of the above points, and provides a device that can push up the pipe material constituting the vertical pipe from below without using a long lift such as a tower crane, The purpose is to allow the pipe material to be added from the bottom in order to be able to carry out the construction.
[0006]
[Means for Solving the Problems]
In order to achieve the first object, according to claim 1, Add pipes sequentially from the bottom A push-up device used when constructing dredging pipes in a building, the frame vertically moving by appropriate driving means, and the frame along the longitudinal direction of the frame Top surface of And a plurality of support members that vertically support the pipe material that constitutes the dredging pipe.
[0007]
As the driving means, a hydraulic jack or a motor can be used. As the support member, for example, a socket-like member into which the lower part of the pipe material is inserted, or an insertion member to be inserted into the lower part of the pipe material can be used. The pipe material vertically supported by such a support member is pushed up vertically by raising the gantry. Therefore, the pushed-up pipe material is temporarily fixed to the building side, then the gantry is lowered to support the next pipe material on the support member of the gantry, the gantry is raised again, and the lower end of the previous pipe material and the next pipe material The upper end is connected, and then the temporary fixing is released, and the next pipe is lifted as it is with the gantry. Therefore, it is possible to construct a vertical pipe by sequentially adding vertical pipe materials from the bottom.
[0008]
In such a push-up device for pipe construction, as described in claim 2, the position of the support member on the gantry is determined. Along the length of the gantry If it is configured to be changeable, it is possible to cope with centering of individual pipes when pipes are constructed by simultaneously pushing up a plurality of pipe materials.
[0009]
Further, when a plurality of support members are provided on the gantry, the support height of the tube material by at least some of the support members is configured to be different from the support height of the tube material by the other support members. More preferable effects can be obtained. That is, when a plurality of pipe materials are pushed up at the same time, the length of the normal pipe material is the same, so that each pipe material comes into contact with the previous pipe material at the same timing. Then, it is necessary to carry out centering and connection work for each pipe material at the same time. However, as described in claim 3, if the support height of the tube material by at least a part of the support member is configured to be different from the support height of the tube material by the other support member, the amount corresponding to the different height, The timing is shifted and each pipe material comes into contact with the previous pipe material in order. Accordingly, the centering and connection can be sequentially performed individually.
[0010]
Furthermore, if the gantry is moved up and down along the guide members arranged vertically as in claim 4, the gantry can be moved up and down in a stable state. As the guide member, for example, guide rails arranged at both ends of the gantry, an appropriate shaft member through which the gantry is inserted, and the like can be proposed.
[0011]
And If a temporary fixing device for temporarily fixing the pipe material pushed up by the gantry is installed on the upper gantry provided above the gantry, the pipe material can be pushed up once and the pushed up pipe material can be temporarily fixed by the temporary fixing device. The pipe to be connected next is supported on the gantry by lowering, and the gantry is raised again, and it becomes easy to align and connect under the previous pipe. This upper frame is fixed to the building side. In view of this action, the temporary fixing device is not limited to a configuration that grips the tube material, and may be any device that can be suspended or locked.
[0012]
In such an uplifting device for pipe construction having an upper frame, further claim 5 As described above, a screw shaft is passed between the gantry and the upper gantry, and the gantry is moved up and down by rotating the screw shaft up and down via a worm gear mechanism by rotational driving by an appropriate driving means. Or claim 6 As described in, only the gantry side is moved up and down, and further 7 As described above, the gantry may be moved up and down along the screw shaft at the same time as moving the screw shaft up and down. A motor is suitable as the driving means. By controlling the motor with, for example, an inverter, it becomes easy to adjust the vertical movement speed of the gantry. In addition, by using the encoder together, it is easy to finely adjust the amount of increase and set the predetermined amount of increase, making it easy to align and connect pipes. The passing of the screw shaft is not limited to passing one screw shaft, but includes a case where a plurality of screw shafts are connected as appropriate.
[0013]
Claim 5 In this case, for example, a screw is cut on the inner periphery of the worm wheel in the worm gear device and screwed with the screw shaft, a screw is cut on the outer periphery of the worm wheel and screwed with the worm, and the worm is rotated by a motor or the like. In this case, since the upper frame side provided with the worm gear device is fixed, the screw shaft can be moved up and down and moved up and down with a large force.
[0014]
Claim 6 In this case, for example, a screw is cut on the inner periphery of the worm wheel in the worm gear device and screwed with the screw shaft, a screw is cut on the outer periphery of the worm wheel and screwed with the worm, and the worm is rotated by a motor or the like. If so, the frame side can be moved up and down along the screw shaft.
[0015]
Claim 7 In the case of 5, 6 Both of these configurations are adopted, and at the same time as the screw shaft moves up and down, the gantry moves up and down along the screw shaft. Therefore, the gantry can be moved up and down with a very large force, and the vertical movement amount of the screw shaft and the movement amount of the gantry itself with respect to the screw shaft can be determined. 5, 6 And the vertical movement speed of the gantry can be increased.
[0016]
DETAILED DESCRIPTION OF THE INVENTION
Hereinafter, embodiments of the present invention will be described with reference to the drawings. FIG. 1 shows the preparatory stage of the construction method of the soot pipe implemented using the push-up device 10 for soot piping construction according to the present embodiment. The push-up device 10 according to the present embodiment is installed across the floor portion 2 and the floor portion 3 on the third floor. The push-up device 10 is mounted between two guide rails 11 and 12 which are vertically opposed from the floor surface 1 on the first floor to the floor portion 2 on the second floor, and the guide rails 11 and 12. A gantry 13 that can slide up and down along the guide rails 11 and 12 is provided. The gantry 13 receives the total weight of the saddle pipe, that is, the shaft pipe, and is configured by using a steel material such as H steel.
[0017]
On the upper surface of the gantry 13, six centering jigs 14, 15, 16, 17, 18, 19 serving as support members are provided. Of course, the number is arbitrary. These centering jigs 14, 15, 16, 17, 18, 19 are movable in the longitudinal direction of the gantry 13 (X direction in the drawing) and can be fixed at an arbitrary position. Such centering jigs 14 to 19 can be moved and fixed by, for example, forming a long hole or a plurality of bolt holes on the top surface of the gantry 13 and fixing them with bolt holes suitable for the piping position. Realized.
[0018]
For example, as shown in FIG. 2, a plate 14x is provided on the lower surface of the centering jig 14, and a plurality of arc-shaped elongated holes 14y are appropriately formed in the plate 14x in an annular shape. On the other hand, two long holes 13a and 13a are formed in the gantry 13 along the longitudinal direction. Then, a plate 14x of the centering jig 14 is assigned to a predetermined piping position, and an appropriate fixing means, for example, a bolt 81 is inserted through the long hole 14y and the long hole 13, and a nut 82 is fastened and fixed to the protruding portion. . With this configuration, the centering jigs 14 to 19 can be easily moved and fixed, and the centering jigs 14 to 19 can be freely fixed according to the piping position.
[0019]
Each of the centering jigs 14, 15, 16, 17, 18, 19 includes support columns 14a, 15a, 16a, 17a, 18a, 19a having a size corresponding to the diameter of the pipe material to be piped, and the support columns 14a, Socket-like receiving portions 14b, 15b, 16b, 17b, 18b, and 19b provided on the upper portions of 15a, 16a, 17a, 18a, and 19a. The inner diameter of each of the receiving portions 14b, 15b, 16b, 17b, 18b, 19b is a size suitable for the diameter of the pipe material to be piped.
[0020]
Further, the positions of the bottom surfaces of the receiving portions 14b, 15b, 16b, 17b, 18b, and 19b are all set to have different heights. For example, regarding the receiving portions 14b and 15b, the position of the bottom surface 14c of the receiving portion 14b is set to be higher than the position of the bottom surface 15c of the receiving portion 15b by a height d. In this case, the height d is suitably around 10 mm. The same applies to the other receiving portions 16b, 17b, 18b, and 19b. As shown in FIG. 3, each receiving portion in the centering jigs 14, 15, 16, 17, 18, and 19 used in this embodiment is used. 14b, 15b, 16b, 17b, 18b, and 19b, the bottom surface 14c of the receiving portion 14b is the highest, and the position of each bottom surface is set so as to be sequentially lowered by the height d. The lowest position is set. As a result, the centering jigs 14, 15, 16, 17, 18, 19 each have a different support height of the pipe material.
[0021]
In this case, instead of the configuration in which the support height is changed by changing the position of the bottom surface of each receiving portion 14b, 15b, 16b, 17b, 18b, 19b, as shown in FIG. For example, based on the receiving portions 17b, 18b, and 19b, the bottom surfaces 17d, 18d, and 19d of the receiving portions 17b, 18b, and 19b are all set to the same height, and a height of d is set as necessary. Alternatively, dedicated unit spacers S1 and S2 may be used, and the number of unit spacers corresponding to the required height may be delivered into the receiving portions 17b and 18b. For example, if two unit spacers S1 are supplied to the receiving portion 17b and one unit spacer S2 is supplied to the receiving portion 17b, different support heights can be realized by the height d. . In addition, if such a unit spacer is comprised with the material which has elasticity to some extent, the lower end of the said pipe material can be protected from an impact at the time of pipe material insertion.
[0022]
The upper frame 21 in the push-up device 10 is installed and fixed on the floor portion 3 on the third floor. The upper frame 21 has a configuration in which two steel materials, for example, H steel materials are arranged in parallel at a predetermined interval. In the vicinity of both ends of the upper pedestal 21, two screw rods 22, 22 serving as screw shafts, which are threaded on the outer periphery, pass through and are screwed into the inner periphery of a worm wheel in a worm gear device 27 described later. ing. The screw rod 22 further penetrates the sleeves 3a and 3b of the floor portion 3 on the third floor.
[0023]
As shown in FIG. 5, the upper ends of the threaded rod connecting jigs 24, 24 are connected to the lower ends of the threaded rods 22, 22 by pins 83, split pins 84, etc. It is connected. The screw rod connecting jigs 24, 24 pass through corresponding appropriate sleeves 2a, 2b formed in the second floor portion 2. Further, at the lower end of each screw rod connecting jig 24, 24, the upper ends of the two screw rods 26, 26, which are threaded on the outer periphery via connecting members 25, 25, are pin 83, split pin 84, etc. The lower ends of the screw rods 26, 26 pass through the vicinity of both ends of the gantry 13 and are screwed into the inner periphery of a worm wheel in a worm gear device 29 described later.
[0024]
Worm gear devices 27 and 27 screwed with the screw rods 22 and 22 are attached to the upper surface of the upper frame 21, and each worm gear device 27 is driven by a motor 28. Accordingly, when each motor 28 is operated, a worm (not shown) in the worm gear device 27 is rotated, and thereby a worm wheel (not shown) in the worm gear device 27 is rotated. The threaded rods 22, 22 are raised or lowered. Accordingly, the screw rod connecting jigs 24 and 24 and the screw rods 26 and 26 also move up and down accordingly.
[0025]
Worm gear devices 29 and 29 screwed with the screw rods 26 and 26 are attached to the lower surface of the gantry 13, and each worm gear device 29 is driven by a motor 30. Accordingly, when each motor 30 is operated, a worm (not shown) in the worm gear device 29 is rotated, and thereby a worm wheel (not shown) in the worm gear device 29 is rotated. The slidable base 13 is raised or lowered with respect to the screw rods 26 and 26 that are screwed with the inner periphery of the worm wheel.
[0026]
The motors 28 and 30 described above are controlled by a separate control device 31, coupled with the function of the encoder attached to the motors 28 and 30, the speed and amount of movement when the gantry 13 is raised and lowered. Are all controlled by the control device 31.
[0027]
That is, as shown in FIG. 6, the control device 31 includes an operation touch panel 32, a sequencer 33, and an inverter 34, and necessary information from the operation touch panel 32, for example, speed setting when the gantry 13 moves up and down, When the movement amount setting and the deviation setting for leveling are input to the sequencer 33, a necessary signal is input to the inverter 34 for controlling the rotation of the motors 28 and 30, and the inverter 34 is based on the signals. , 30 are controlled. On the other hand, corresponding encoders 35 and 36 are attached to the motors 28 and 30, respectively, and position signals corresponding to the accumulated rotational speed are fed back to the sequencer 33. As a result, the position of the gantry 13 can be accurately controlled, and the stop at the predetermined position can also be accurately performed.
[0028]
The upper frame 21 has six temporary fixing devices 41, 72, 73 corresponding to the upper floor 21 so as to be positioned above the piping sleeves 3c, 3d, 3e, 3f, 3g, 3h of the third floor portion 3, respectively. 74, 75 and 76 are fixed. The temporary fixing devices 41, 72, 73, 74, 75, and 76 have basically the same configuration except for the size, so the temporary fixing device 41 will now be described with reference to FIG. As a material of these temporary fixing devices, for example, a steel plate having a thickness of 20 mm or more is preferably used.
[0029]
In the temporary fixing device 41, a substantially box-shaped main body 42 is fixed across the two steel materials 21a and 21b constituting the upper support base 14, and two engagement members are provided on the periphery of the upper surface opening of the main body 42. It has the structure attached so that the stop bodies 43 and 44 could rotate upwards. These locking bodies 43 and 44 have a symmetrical shape and are arranged so as to face each other so that the insides of the locking bodies 43 and 44 face each other. Between the vicinity of both ends of each of the outer sides 43a and 44a and the main body 42, a hinge or the like can be rotated. A member 45 is attached and configured to be rotatable only upward from a horizontal state.
[0030]
In addition, semicircular cutouts 43b and 44b are formed on the inner sides of the engaging bodies 43 and 44 on the abutting side. As shown in FIG. 5, when the locking bodies 43 and 44 are in a horizontal state and the respective inner sides are abutted with each other, a circular opening H is formed by the two cutouts 43 b and 44 b. The inner diameter of the opening H is set to be slightly larger than the outer diameter of the pipe materials P11 and P21 piped to the sleeve 3c, and is set to be smaller than the outer diameter of the collar pf described later. That is, the size is set such that only the main body of the pipe material piped to the sleeve 3c is allowed to pass.
[0031]
The push-up device 10 according to the present embodiment is configured as described above. Further, in order to suitably carry out the construction method of the soot pipe using the push-up device 10, the lower surface of the floor portion 3 on the third floor is used. A reciprocating towing winch (friction winding type endless winch) 51 is provided as a hoisting device for hoisting the pipe material. The reciprocating towing winch 51 is movable to the left and right so as to cover at least the range from the sleeves 3c to 3h for piping. The reciprocating towing winch 51 is also used when the screw rod 22 and the screw rod connecting jig 24 assembled on the floor surface 1 on the first floor are pulled up. Instead of the reciprocating towing winch 51, another hanging device such as a chain block may be used.
[0032]
Further, another reciprocating towing winch 52 for pulling up the pipe materials P11 to P16 to be piped at the uppermost portion is provided on the upper surface of the floor portion 4 on the fourth floor. Is provided. For the reciprocating towing winch 52, other known suspension devices can be used.
[0033]
The push-up device 10, the temporary fixing device 41, and the reciprocating tow winches 51 and 52 are set in advance in a predetermined position as described above. The centering jigs 14 to 19 of the gantry 13 are also fixed in advance at a predetermined position on the gantry 13 in accordance with, for example, the method shown in FIG.
[0034]
In the construction method of the soot pipe to be implemented from now on, as shown in FIG. 8, the pipe material P in which the collar portion pf is fixed to the outer periphery in the vicinity of the upper end portion of each pipe material P by, for example, welding or the like is used. It is possible to use for the construction method of the soot pipe concerning this embodiment if it is not only such a collar part pf but the pipe material which formed the suitable protrusion of the form which protrudes on an outer periphery. The fixing positions of the collar portions pf are all set to the same position regardless of the pipe diameter. That is, the distance M from the upper end of the pipe P in FIG. 6 to the collar pf is the same for all the pipes described later. The collar portion pf can also be used as a known connection socket.
[0035]
Next, the construction procedure will be described. First, pipes P11, P12, P13, P14, P15, and P16 piped at the top are reciprocating towing winches 52 provided on the upper surface of the floor 4 of the fourth floor. Suspended as shown in. It should be noted that if a locking tool pk for suspension is attached in advance to the top of each of the pipe materials P11, P12, P13, P14, P15, and P16 piped at the top, the reciprocating towing winch 52 Convenient for hanging with the wire 52a.
[0036]
For example, the procedure for suspending the pipe material P11 piped at the end will be described. The wire 52a of the reciprocating tow winch 52 is connected to the sleeve 4c of the floor 4 of the fourth floor, the temporary fixing device 41, and the sleeve of the floor 3 of the third floor. 3c, it is lowered down through the sleeve 2c of the floor 2 of the second floor, and is located at the tip of the wire 52a of the reciprocating tow winch 52 on the locking tool pk provided on the top of the pipe P11 placed on the first floor. The hook 52b is locked.
[0037]
Next, the wire 52a is rolled up, and the pipe material P11 is raised, lifted in a vertical state, passed through the sleeve 2c, and further passed through the sleeve 3c from the state of FIG. And if it is still lifted as it is, since the opening H formed in the temporary fixing device 41 has a shape that allows only the main body of the pipe P11 to pass through, the flange pf of the pipe P11 eventually becomes the peripheral portion of the opening H, That is, it catches on the notch parts 43b and 44b of each latching body 43 and 44, and as shown in FIG. 11, each latching body 43 and 44 is opened and lifted by lifting of the pipe material P11.
[0038]
If it is still lifted as it is, the hooking of the flange portion pf of the pipe material P11 with respect to the cutout portions 43b, 44b of the locking bodies 43, 44 is released, and as shown in FIG. Is turned downward by its own weight and becomes horizontal. Here, when the lifting of the pipe material P11 is stopped and the pipe material P11 is gradually lowered, the flange portion pf of the pipe material P11 is a peripheral portion of the opening H, that is, each locking body 43 as shown in FIG. 44, the pipe member P11 is suspended by the temporary fixing device 41 at that time, that is, temporarily fixed.
[0039]
The pipe materials P12, P13, P14, P15, and P16 piped on the other uppermost part are also suspended in exactly the same manner, and as shown in FIGS. , 73, 74, 75, 76. The reciprocating towing winch 52 installed on the floor 4 of the fourth floor is removed at the stage where all the pipes P11, P12, P13, P14, P15, and P16 are temporarily fixed.
[0040]
Next, the pipe materials P21, P22, P23, P24, P25, and P26 piped under the pipe materials P11, P12, P13, P14, P15, and P16 are suspended by the reciprocating towing winch 51, and the upper end of the pipe material is placed on the second floor. The centering jigs 14, 15, 16, 17, 18, which are inserted into the corresponding sleeves 2 c, 2 d, 2 e, 2 f, 2 g, 2 h of the part 2 and whose lower ends are provided on the mount 13, It inserts in each 19 receiving part 14b, 15b, 16b, 17b, 18b, 19b, and makes the pipe materials P21, P22, P23, P24, P25, P26 self-supporting.
[0041]
In this case, as shown in FIG. 8, each pipe P has a flange pf formed on the outer periphery in the vicinity of the upper end, so that the wire 51a of the reciprocating towing winch 51 is shown in FIG. , The wire 51a can be locked and attached to the collar portion pf, so that it is easy to work and can be suspended stably. Since the reciprocating towing winch 51 is movable in the X direction in the drawing as appropriate, it is possible to suspend all the pipe materials P21, P22, P23, P24, P25 and P26.
[0042]
When the setting of the pipe materials P21, P22, P23, P24, P25, and P26 is completed in this way, the rising height or the like is input to the operation touch panel 32 of the control device 31, and the motors 28 and 30 are operated. When the motor 28 is operated, the screw rod 22 itself is raised by the rotation of the screw rod 22, and the screw rod connecting jigs 24, 24 are raised accordingly. On the other hand, the screw rod 26 is rotated by the operation of the motor 30, and the gantry 13 is raised along the guide rails 11, 12 accordingly. Accordingly, the gantry 13 is raised by the raising of the screw rod 26 itself and the raising of the gantry 13 itself along the screw rod 26, whereby the centering jigs 14, 15, 16, 17, 18, The pipe members P21, P22, P23, P24, P25, and P26, whose lower end portions are inserted into the 19 receiving portions 14b, 15b, 16b, 17b, 18b, and 19b, are pushed upward.
[0043]
When the pipe materials P21, P22, P23, P24, P25, and P26 are pushed upward, the upper ends thereof approach the lower ends of the previous pipe materials P11, P12, P13, P14, P15, and P16. Here, as shown in FIG. 15, the positions of the bottom surfaces of the receiving portions 14b, 15b, 16b, 17b, 18b, and 19 of the centering jigs 14, 15, 16, 17, 18, and 19 are the receiving portions. The heights are sequentially different so that 14b is the highest and the receiving part 19b is the lowest. Therefore, even if the pedestal 13 is raised and the pipe materials P21, P22, P23, P24, P25, and P26 are simultaneously pushed up at the same speed, the lower end portion is inserted into the receiving portion 14b as shown in FIG. The upper end surface of the pipe material P21 is the fastest and reaches the lower end portion of the previous pipe material P11 and comes into contact therewith. Such contact is made in a space on the second floor 2.
[0044]
At that time, while properly aligning the core 13, the push-up of the gantry 13 is stopped, and the lower end portion of the pipe material P11 and the upper end portion of the pipe material P21 are connected, for example, temporary welding. In this case, since the ascending speed of the gantry 13 can be easily finely adjusted based on the rotational speeds of the motors 28 and 30, the centering operation is very easy to perform. And when temporary welding of the lower end part of the pipe material P11 and the pipe material P21 is complete | finished in that way, the motors 28 and 30 will be actuated to the raising side again and the mount 13 will be raised.
[0045]
Then, next, as shown in FIG. 17, the upper end portion of the pipe material P22 comes into contact with the lower end portion of the pipe material 12. Here, while appropriately aligning the core, the push-up of the gantry 13 is stopped, and the lower end portion of the pipe material P11 and the upper end portion of the pipe material P21 are temporarily welded. Next, when the motors 28 and 30 are actuated again to raise the gantry 13, the upper end portion of the tube material P23 comes into contact with the lower end portion of the tube material 13 as shown in FIG. After that, temporary welding is performed in exactly the same procedure, and the other pipe materials P24, P25, and P26 are similarly temporarily welded to the corresponding pipe materials P14, P15, and P16, respectively.
[0046]
In this way, the upper ends of the pipe materials P21, P22, P23, P24, P25, and P26 are placed at the temporary welding positions with the lower ends of the previous pipe materials P11, P12, P13, P14, P15, and P16 at different times. Therefore, even a small number of workers can efficiently and accurately connect the upper ends of the pipe materials P21, P22, P23, P24, P25, and P26 to the pipe materials P11, P12, P13, P14, P15, and P16. Further, as already described, the centering operation required at that time is very easy. Moreover, since all the connection work by such temporary welding can be performed in the low place of the space on the floor part 2 on the second floor, the working environment is good also in this respect. It should be noted that here, the screw-in pipes are finally tightened, and the flange, the core, etc. are also finally tightened.
[0047]
When the temporary welding of the upper ends of the pipe materials P21, P22, P23, P24, P25, P26 and the lower ends of the previous pipe materials P11, P12, P13, P14, P15, P16 is completed, the motors 28, 30 are moved upward. The base 13 is raised by operating, and the pipe materials P21, P22, P23, P24, P25 and P26 are pushed up together with the previous pipe materials P11, P12, P13, P14, P15 and P16. Then, first, as shown in FIG. 19, the collar portion pf of the pipe material P21 approaches the temporary fixing device 41. When the gantry 13 is raised as it is, the pipe materials P21, P22, P23, P24, P25, and P26 are exactly the same as the temporary fixing of the pipe materials P11, P12, P13, P14, P15, and P16 described above. Are temporarily fixed to the corresponding temporary fixing devices 41, 72, 73, 74, 75, 76. For example, regarding the pipe material P21, the opening H formed in the temporary fixing device 41 has a shape that allows only the main body of the pipe material P21 to pass through. Therefore, as shown in FIG. 20, the collar pf of the pipe material P21 is the opening. As shown in FIG. 20, each of the locking bodies 43 and 44 is opened and lifted by being caught by the peripheral edge portion of H, that is, the notches 43b and 44b of the locking bodies 43 and 44, and pushing up the pipe P21.
[0048]
If pushed up as it is, the hooking of the flange portion pf of the pipe material P21 with respect to the cutout portions 43b, 44b of the locking bodies 43, 44 is released, and as shown in FIG. It turns downward by its own weight and becomes horizontal. As described above, when pushing up by the gantry 13, the positions of the upper ends of the pipe materials P21, P22, P23, P24, P25, and P26, that is, the height of each collar pf is the position where the pipe material P21 is the highest. The height of the flange portion pf of the pipe material P26 is at the lowest position. Accordingly, the process leading to FIGS. 19 to 21 is achieved with the pipe P21 being the fastest and the pipe P26 being the slowest.
[0049]
Then, when the slowest pipe P26 reaches the state shown in FIG. 21, that is, when the locking body of the temporary fixing device 46 returns to the horizontal state, the motors 28 and 30 are actuated downward to lower the gantry 13. To go. As a result, the pipe materials P21, P22, P23, P24, P25, and P26 also descend, and eventually each of the temporary fixing devices 76, 75, 74, 73, 72, and 41 corresponding to the pipe material P26 sequentially. The collar portion pf is locked and temporarily fixed. For example, regarding the pipe material P21 that is temporarily fixed most recently, as shown in FIG. 22, the flange portion pf of the pipe material P21 is the peripheral edge portion of the opening H in the temporary fixing device 41, that is, the notches of the locking bodies 43 and 44. The pipe member P21 is engaged with the parts 43b and 44b, and the pipe member P21 is suspended from the temporary fixing device 41 at that time, that is, temporarily fixed.
[0050]
FIG. 23 shows a state in which all the pipe materials P21, P22, P23, P24, P25, and P26 are temporarily fixed to the corresponding temporary fixing devices 41, 72, 73, 74, 75, and 76. The gantry 13 is lowered as it is, and is stopped again at the position where the next pipe material is installed, that is, in the state of FIG. 9, and the next pipe material, for example, the pipe material 31 connected to the pipe 21 is suspended by the reciprocating towing winch 51. Perform the work.
[0051]
For the pipe materials P21, P22, P23, P24, P25, and P26 that are temporarily fixed during this period, the main welding is performed on the connection portions of the pipe materials P11, P12, P13, P14, P15, and P16 that have been temporarily welded. For example, it carries out even to the rust prevention coating of a welding part. Such work can be performed in the space on the floor 3 of the third floor, and the work is easy. As shown in FIG. 23, if the position of the collar portion pf of the pipe material P is set in advance so that the connection portion is located in the lower part of the space, the operation is further facilitated. Moreover, since the pipe materials P21, P22, P23, P24, P25, and P26 are temporarily fixed in this manner, the work is easy in this respect as well.
[0052]
As described above, the pipe material P is sequentially suspended by the reciprocating towing winch 51 and set on the gantry 13 and then pushed up and temporarily welded on the second floor, and then the whole pipe material is pushed up and temporarily fixed to perform the main welding. If it repeats, predetermined dredging piping will be constructed.
[0053]
Then, as shown in FIG. 24, pipe materials P31, P32, P33, P34, P35, P36 and pipe materials P41, P42, P43, P44, P45, and P46 are connected to the pipe materials P21, P22, P23, P24, P25, and P26. For example, when the pipe materials P51, P52, P53, P54, P55, and P56 to be connected next are the lowermost pipes and the pipe materials to be connected last, provisional connection with the pipe materials P41, P42, P43, P44, P45, and P46 At the stage before welding is finished and finally pushed up to a predetermined pipe location, as shown in the figure, the pipes P31, P32, P33, P34, P35, On the other hand, an operation of attaching the heat insulating material 61 is performed. Of course, with respect to the part A located at a high place after piping in the other pipe materials P41, P42, P43, P44, P45, P46, and the part B located at a high place after piping in the pipe materials P51, P52, P53, P54, P55, P56 However, necessary processing such as heat insulation processing, hole filling processing of the sleeve penetration portion, fire prevention processing, and other necessary processing are performed at this stage.
[0054]
In the stage shown in FIG. 24, the pipe material has not yet reached the predetermined piping position, and the portion located at a high place such as the ceiling after the pipe is located slightly above the floor, that is, at a low place. It is. Therefore, each operation described above can be performed very easily. Moreover, since the position of the part located at a high place after piping can be adjusted by the position (height) of the gantry 13, the gantry 13 may be stopped at the position where it is most easy to work.
[0055]
As described above, after the pipes are subjected to the necessary processing at a high position after piping, the motors 28 and 30 are operated to the ascending side to raise the pedestal 13, and the final pipe P51 , P52, P53, P54, P55, P56 are pushed up to a predetermined position, heat insulation for the push-up allowance is performed, and installation work of predetermined support hardware etc. is performed on each floor, so that the construction of the dredging pipe is completed.
[0056]
As can be seen from the above work procedure, when the push-up device 10 according to the present embodiment is used, construction of the dredging pipe can be performed without using a long lift such as a tower crane. Therefore, there is no need for adjustment with other construction methods for the use of the tower crane, which has been troublesome until now, and it is not necessary to determine the construction schedule and the like early in the design stage. In addition, the construction period of other construction methods using tower cranes can be shortened accordingly.
[0057]
Moreover, since the lower end of the upper pipe and the upper end of the lower pipe can be connected by pushing up from below, the pipes can be easily aligned with each other, making the connection work easier, faster and more accurate than before. Well done. Further, by inserting the lower end portion of the tube material P into the receiving portions 14b to 19b of the centering jigs 14 to 19 of the gantry 13, the tube material P is supported vertically, and the gantry 13 is raised to push up the tube material P. Therefore, stable push-up work can be performed. Moreover, since both end portions of the gantry 13 are slidable along the guide rails 11 and 12, a more stable push-up operation is possible.
[0058]
The positions (heights) of the bottom surfaces of the receiving portions 14b, 15b, 16b, 17b, 18b, 19b of the centering jigs 14, 15, 16, 17, 18, 19 provided on the mount 13 are different. Since the support height of the pipes is different, when connecting the lower ends of the upper six pipes and the upper ends of the lower six pipes, the upper ends of the lower six pipes However, since it arrives at the connection position with the lower end part of the upper six pipe materials at different times in sequence, the centering and connection work can be performed individually. Therefore, the connecting work can be efficiently performed with a small number of workers. Further, since it is not necessary to align the six cores at the same time, the centering itself can be accurately performed.
[0059]
Furthermore, since the upper frame 21 is provided with temporary fixing devices 41, 72 to 76, the pipe material pushed up by the frame 13 can be temporarily fixed as it is with these temporary fixing devices 41, 72 to 76, Easy to do later work. The vertical movement of the gantry 13 is realized by the rotation of the screw shafts 22 and 26 by the motors 28 and 30, and the speed and the vertical movement amount during the vertical movement can be easily controlled.
[0060]
【The invention's effect】
Claims 1 to 7 According to the vertical piping push-up device described in 1), the pipe supported vertically on the support member of the gantry can be pushed up vertically by raising the gantry. Therefore, it is possible to suitably carry out the construction method of the vertical pipe in which vertical pipe materials are sequentially added from below without using a long lift such as a tower crane. That is. Compared to the conventional method of lifting with a long lift, it does not take up construction space, and can be suitably implemented in urban redevelopment projects.
[0061]
Especially claims 1 In this case, when a plurality of pipes are pushed up at the same time and pipes are constructed at the same time, it is possible to cope with centering of individual pipes. Further, in the case of claim 3, even if a plurality of pipes are pushed up at the same time, the pipes can be brought into contact with the previous pipes at different timings, and the pipes can be individually aligned and connected sequentially. According to the fourth aspect of the present invention, it is possible to obtain an effect that the gantry can be moved up and down in a stable state.
[0062]
And claims 5-7 According to each of the push-up devices, it is possible to easily adjust the speed of vertical movement of the pedestal, finely adjust the amount of increase, and set a predetermined amount of increase, thereby further obtaining the effect of facilitating the alignment and connection of pipes. . Moreover, it is easy to move the gantry up and down with a large force. In particular, in the case of claim 8, the vertical movement speed of the gantry can be increased, and a quick operation can be performed.
[Brief description of the drawings]
FIG. 1 is an explanatory diagram showing a state where a push-up device according to an embodiment of the present invention is set at a predetermined position.
FIG. 2 is a perspective view showing a state in which a centering jig is attached to a gantry in the push-up device shown in FIG.
3 is a cross-sectional explanatory view of a centering jig for a gantry in the push-up device of FIG. 1. FIG.
FIG. 4 is a cross-sectional explanatory view of another centering jig.
5 is a perspective view showing a state in which a screw rod and a screw rod connecting jig are attached in the push-up device of FIG. 1. FIG.
6 is an explanatory diagram of a control device in the push-up device of FIG. 1;
7 is a perspective view of an upper frame temporary fixing device in the push-up device of FIG. 1. FIG.
FIG. 8 is a front view of the upper part of the pipe material used when implementing the construction method of the soot pipe using the push-up device of FIG.
FIG. 9 is an explanatory view showing a state where the uppermost pipe material is temporarily fixed in the construction method of the soot pipe carried out using the push-up device shown in FIG. 1;
10 is an explanatory view showing a state in which the uppermost pipe member approaches the temporary fixing device of FIG. 7; FIG.
11 is an explanatory view showing a state in which a collar portion of the uppermost pipe member lifts a locking body in the temporary fixing device of FIG. 7; FIG.
12 is an explanatory view showing a state in which a locking body in the temporary fixing device of FIG. 7 has returned to a horizontal state.
13 is an explanatory view showing a state where a collar portion of the uppermost tube member is locked and temporarily fixed to a locking body in the temporary fixing device of FIG. 7; FIG.
FIG. 14 is a construction method of a dredge pipe implemented using the push-up device of FIG. 1, after temporarily fixing the pipe material piped on the uppermost part, lowering the mount to the set position of the next pipe material, It is explanatory drawing which shows a mode that it is hanging.
15 is an explanatory view showing a state in which the next pipe material is pushed up and brought close to the uppermost pipe material in the construction method of the soot pipe carried out using the push-up device of FIG.
FIG. 16 is a diagram illustrating a state in which the next pipe member is pushed up and the upper end portion of the first pipe member is in contact with the lower end portion of the corresponding uppermost pipe member in the construction method of the soot pipe performed using the push-up device of FIG. FIG.
FIG. 17 shows a state in which the next pipe is pushed up and the upper end of the second pipe is in contact with the lower end of the corresponding uppermost pipe in the construction method of the soot pipe carried out using the push-up device of FIG. It is explanatory drawing.
18 shows a state in which the next pipe is pushed up and the upper end of the third pipe is in contact with the lower end of the corresponding uppermost pipe in the construction method of the soot pipe implemented using the push-up device of FIG. It is explanatory drawing.
19 is an explanatory view showing a state in which the next pipe material approaches the temporary fixing device of FIG. 7;
20 is an explanatory view showing a state in which a collar portion of the next pipe member lifts the locking body in the temporary fixing device of FIG. 7; FIG.
21 is an explanatory view showing a state in which the locking body in the temporary fixing device of FIG. 7 has returned to the horizontal state.
22 is an explanatory view showing a state in which a collar portion of the next pipe member is locked and temporarily fixed to the locking body in the temporary fixing device of FIG. 7;
FIG. 23 is an explanatory view showing a state in which all the next pipe members are temporarily fixed by raising the gantry in the method for constructing the culvert pipe implemented using the push-up device of FIG. 1;
FIG. 24 is an explanatory diagram showing a state in which heat insulation treatment is performed on the previous pipe material before the final push-up of the pipe material to be finally connected in the construction method of the soot pipe performed using the push-up device of FIG. is there.
[Explanation of symbols]
1 Floor on the first floor
2 Second floor
3 The third floor
4 Floors on the 4th floor
10 Push-up device
11, 12 Guide rail
13 frame
14, 15, 16, 17, 18, 19 Centering jig
14b, 15b, 16b, 17b, 18b, 19b
21 Upper frame
22, 26 Screw rod
24 Screw rod connection jig
27, 29 Worm gear device
28, 30 Motor
31 Control device
41, 72, 73, 74, 75, 76 Temporary fixing device
P pipe material
pf collar

Claims (7)

管材を下から順次継ぎ足して建物に竪配管を施工する際に用いる押し上げ装置であって,適宜の駆動手段によって垂直に上下動する架台と,前記架台の長手方向に沿って当該架台の上面に設けられ,竪配管を構成する管材を垂直に支持する複数の支持部材とを備えたことを特徴とする,竪配管施工用押し上げ装置。 A push-up device used when constructing pipes in a building by sequentially adding pipe materials from the bottom, and is provided on the upper surface of the frame along the longitudinal direction of the frame and vertically moving vertically by appropriate driving means. And a plurality of supporting members for vertically supporting the pipe material constituting the dredging pipe. 架台における支持部材の位置は,架台の長手方向に沿って変更自在であることを特徴とする,請求項1に記載の竪配管施工用押し上げ装置。  2. The lifting device for dredging construction according to claim 1, wherein the position of the support member on the gantry can be changed along the longitudinal direction of the gantry. 管材を下から順次継ぎ足して建物に竪配管を施工する際に用いる押し上げ装置であって,適宜の駆動手段によって垂直に上下動する架台と,前記架台の上面に設けられ,竪配管を構成する管材を垂直に支持する複数の支持部材とを備え,
少なくとも一部の支持部材による管材の支持高さは,他の支持部材による管材の支持高さとは異なっていることを特徴とする,竪配管施工用押し上げ装置。
A push-up device used when constructing dredging pipes in a building by sequentially adding pipe materials from the bottom, and a stand that moves vertically up and down by appropriate driving means, and a pipe material that is provided on the top face of the stand and constitutes dredging pipes A plurality of support members that vertically support the
An uplifting device for dredging pipe construction, characterized in that the support height of the pipe material by at least some of the support members is different from the support height of the pipe material by other support members.
建物に竪配管を施工する際に用いる押し上げ装置であって,適宜の駆動手段によって垂直に上下動する架台と,前記架台に設けられ,竪配管を構成する管材を垂直に支持する支持部材とを備え,
前記架台は,垂直に配置されたガイド部材に沿って上下動することを特徴とする,竪配管施工用押し上げ装置。
A push-up device used when constructing dredging pipes in a building, comprising a gantry that moves up and down vertically by appropriate driving means, and a support member that is provided on the gantry and supports the pipe material that constitutes the dredging pipe vertically. Prepared,
The lifting device for dredging piping construction, wherein the gantry moves up and down along a guide member arranged vertically.
建物に竪配管を施工する際に用いる押し上げ装置であって,適宜の駆動手段によって垂直に上下動する架台と,前記架台に設けられ,竪配管を構成する管材を垂直に支持する支持部材とを備え,
前記架台の上方には建物側に固定される上部架台を有し,
前記架台と上部架台との間にはネジ軸が渡されると共に,当該ネジ軸と螺合するウォームギヤ装置をこの上部架台に設け,適宜の駆動手段による回転駆動により当該ウォームギヤ装置を介してこのネジ軸を上下動させることで,前記架台が上下動するように構成されたことを特徴とする,竪配管施工用押し上げ装置。
A push-up device used when constructing dredging pipes in a building, comprising a gantry that moves up and down vertically by appropriate driving means, and a support member that is provided on the gantry and supports the pipe material that constitutes the dredging pipe vertically. Prepared,
An upper frame fixed to the building side is provided above the frame,
A screw shaft is passed between the gantry and the upper gantry, and a worm gear device that is screwed to the screw shaft is provided in the upper gantry, and the screw shaft is rotated via the worm gear device by rotation driving by an appropriate driving means. An uplifting device for dredging piping construction, wherein the frame is configured to move up and down by moving up and down.
建物に竪配管を施工する際に用いる押し上げ装置であって,適宜の駆動手段によって垂直に上下動する架台と,前記架台に設けられ,竪配管を構成する管材を垂直に支持する支持部材とを備え,
前記架台の上方には建物側に固定される上部架台を有し,
前記架台と上部架台との間にはネジ軸が渡されると共に,当該ネジ軸と螺合するウォームギヤ装置を前記架台に設け,適宜の駆動手段による回転駆動によって当該ウォームギヤ装置を介してこのネジ軸に沿って前記架台を上下動させるように構成されたことを特徴とする,竪配管施工用押し上げ装置。
A push-up device used when constructing dredging pipes in a building, comprising a gantry that moves up and down vertically by appropriate driving means, and a support member that is provided on the gantry and supports the pipe material that constitutes the dredging pipe vertically. Prepared,
An upper frame fixed to the building side is provided above the frame,
A screw shaft is passed between the gantry and the upper gantry, and a worm gear device that is screwed to the screw shaft is provided on the gantry, and the screw shaft is connected to the screw shaft via the worm gear device by rotational driving by appropriate driving means. A push-up device for dredging pipe construction, characterized in that it is configured to move the gantry up and down along.
建物に竪配管を施工する際に用いる押し上げ装置であって,適宜の駆動手段によって垂直に上下動する架台と,前記架台に設けられ,竪配管を構成する管材を垂直に支持する支持部材とを備え,
前記架台の上方には建物側に固定される上部架台を有し,
前記架台と上部架台との間にはネジ軸が渡されると共に,当該ネジ軸と螺合するウォームギヤ装置をこれら架台及び上部架台の双方に設け,適宜の駆動手段による回転駆動により上部架台側のウォームギヤ装置を介してこのネジ軸を上下動させると共に,架台側のウォームギヤ装置を介してこのネジ軸に沿って前記架台を上下動させるように構成されたことを特徴とする,竪配管施工用押し上げ装置。
A push-up device used when constructing dredging pipes in a building, comprising a gantry that moves up and down vertically by appropriate driving means, and a support member that is provided on the gantry and supports the pipe material that constitutes the dredging pipe vertically. Prepared,
An upper frame fixed to the building side is provided above the frame,
A screw shaft is passed between the gantry and the upper gantry, and a worm gear device that is screwed to the screw shaft is provided on both the gantry and the upper gantry, and the worm gear on the upper gantry side is rotated by appropriate driving means. A push-up device for dredging pipe construction, wherein the screw shaft is moved up and down through a device, and the frame is moved up and down along the screw shaft through a worm gear device on the frame side .
JP35483296A 1996-12-20 1996-12-20 押 し Pipe construction push-up device Expired - Lifetime JP3753821B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP35483296A JP3753821B2 (en) 1996-12-20 1996-12-20 押 し Pipe construction push-up device

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP35483296A JP3753821B2 (en) 1996-12-20 1996-12-20 押 し Pipe construction push-up device

Publications (2)

Publication Number Publication Date
JPH10184021A JPH10184021A (en) 1998-07-14
JP3753821B2 true JP3753821B2 (en) 2006-03-08

Family

ID=18440211

Family Applications (1)

Application Number Title Priority Date Filing Date
JP35483296A Expired - Lifetime JP3753821B2 (en) 1996-12-20 1996-12-20 押 し Pipe construction push-up device

Country Status (1)

Country Link
JP (1) JP3753821B2 (en)

Families Citing this family (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP6180350B2 (en) * 2014-03-20 2017-08-16 三機工業株式会社 竪 pipe installation stand, construction plant structure and 竪 pipe installation method

Also Published As

Publication number Publication date
JPH10184021A (en) 1998-07-14

Similar Documents

Publication Publication Date Title
WO2022151773A1 (en) Fabricated rapid construction platform for bridge and control method therefor
CN110371823B (en) Self-lifting hoisting equipment suitable for assembly type additional elevator construction and construction method
CN116516837B (en) Prefabricated box girder paving device and paving method
JP3658118B2 (en) Temporary fixing device for dredging construction and construction method for dredging
JP3753821B2 (en) 押 し Pipe construction push-up device
CN116588819A (en) Hoisting device for glass curtain wall plate and construction method thereof
CN110077934B (en) Construction device and construction method thereof in elevator subsection hoistway
JP3688837B2 (en) How to construct a pipe
JPH07895B2 (en) Reinforcing cage construction equipment
JP2612974B2 (en) Mounting method of outer wall PC members
JP2858205B2 (en) Reinforcing bar mounting method and rebar mounting device used for the same
JP3220397B2 (en) Elevating scaffold
JP3097010B2 (en) Elevator device for underground construction and underground construction method using it
JPH05319729A (en) Attaching work device of guide rail of elevator and attaching work method of guide rail using that device
CN219792148U (en) Full-automatic hoisting device of prefabricated structure for underground station
CN216829331U (en) Adjusting device and adjusting equipment of curved plate
CN210594968U (en) Sliding device for hoisting truss
JP2872419B2 (en) Method for assembling tower-like structure and scaffolding device for use in the method
JPS63110365A (en) Method and apparatus for rising and falling of lift stand
JP2761518B2 (en) Construction method of building
JP3347968B2 (en) Hydraulic elevator installation method
JP2003253887A (en) Construction equipment and construction method
JP3279290B2 (en) Rebar prefab vertical composition device
JP2858206B2 (en) Rebar hanging jig
JPH04277269A (en) Construction method of plant

Legal Events

Date Code Title Description
A977 Report on retrieval

Free format text: JAPANESE INTERMEDIATE CODE: A971007

Effective date: 20041005

A131 Notification of reasons for refusal

Free format text: JAPANESE INTERMEDIATE CODE: A131

Effective date: 20041116

A521 Written amendment

Free format text: JAPANESE INTERMEDIATE CODE: A523

Effective date: 20050117

A131 Notification of reasons for refusal

Free format text: JAPANESE INTERMEDIATE CODE: A131

Effective date: 20050614

A521 Written amendment

Free format text: JAPANESE INTERMEDIATE CODE: A523

Effective date: 20050812

TRDD Decision of grant or rejection written
A01 Written decision to grant a patent or to grant a registration (utility model)

Free format text: JAPANESE INTERMEDIATE CODE: A01

Effective date: 20051206

A61 First payment of annual fees (during grant procedure)

Free format text: JAPANESE INTERMEDIATE CODE: A61

Effective date: 20051214

R150 Certificate of patent or registration of utility model

Free format text: JAPANESE INTERMEDIATE CODE: R150

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20081222

Year of fee payment: 3

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20091222

Year of fee payment: 4

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20101222

Year of fee payment: 5

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20101222

Year of fee payment: 5

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20111222

Year of fee payment: 6

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20111222

Year of fee payment: 6

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20121222

Year of fee payment: 7

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20121222

Year of fee payment: 7

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20131222

Year of fee payment: 8

EXPY Cancellation because of completion of term