Distribution system control system

Info

Publication number
JP2807339B2
JP2807339B2 JP2328138A JP32813890A JP2807339B2 JP 2807339 B2 JP2807339 B2 JP 2807339B2 JP 2328138 A JP2328138 A JP 2328138A JP 32813890 A JP32813890 A JP 32813890A JP 2807339 B2 JP2807339 B2 JP 2807339B2
Authority
JP
Japan
Prior art keywords
accident
information
distribution
power
distribution line
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
JP2328138A
Other languages
Japanese (ja)
Other versions
JPH04197034A (en
Inventor
政泰 飛田
英治 平井
正樹 庄司
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Meidensha Corp
Toshiba Corp
Tokyo Electric Power Co Holdings Inc
Original Assignee
Meidensha Corp
Toshiba Corp
Tokyo Electric Power Co Inc
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Meidensha Corp, Toshiba Corp, Tokyo Electric Power Co Inc filed Critical Meidensha Corp
Priority to JP2328138A priority Critical patent/JP2807339B2/en
Publication of JPH04197034A publication Critical patent/JPH04197034A/en
Application granted granted Critical
Publication of JP2807339B2 publication Critical patent/JP2807339B2/en
Anticipated expiration legal-status Critical
Expired - Fee Related legal-status Critical Current

Links

Landscapes

  • Supply And Distribution Of Alternating Current (AREA)

Description

【発明の詳細な説明】 A.産業上の利用分野 本発明は配電系統を制御する配電系統制御システムに
関するものである。
The present invention relates to a distribution system control system for controlling a distribution system.

B.発明の概要 本発明の配電系統制御システムは、配電線を接続また
は切断する開閉器を備えた配電系統と、これに接続され
た上位系統と、この上位系統を監視制御する上位システ
ムとによって構成された電力系統に接続し、上位システ
ムから受け取った事故情報を各事故ごとに記憶領域を確
保して記憶する第1の記憶手段を有し、この記憶手段の
各記憶領域から読み出した事故情報にもとづいて、その
事故情報に対応する事故の復旧操作を、開閉器を制御し
て実施する配電系統制御システムにおいて、 上位システムが送信する遠方監視制御情報(上位シス
テムが遠方の各配変所等に対して監視制御を行うに必要
な“故障・異常情報SV:Supervisory,および電圧・電流
等の計測情報TM:Telemeter",以下、SV・TM情報と称す。
から推定した線路および開閉器の状態を表す状態情報を
記憶する第2の記憶手段と、配電線の停電発生時に、第
2の記憶手段から読み出した停電前の送電設備を、停電
前送電設備情報として、この配電線に対応する記憶領域
に記憶させる第3の記憶手段とを備え、事故が発生した
ときは、事故により停電となった配電線に対応する第3
の記憶手段の記憶領域から停電前送電設備情報を読み出
し、同じ事故に対応する第1の記憶手段の記憶領域に他
の事故情報と共に記憶させる構成とすることにより、 第1の記憶手段の個々の事故に対応する記憶領域から
停電前送電設備情報を読み出して復旧対象を正しく認識
し、配電系統の事故復旧操作を的確に実施することを可
能とするものである。
B. Summary of the Invention The distribution system control system of the present invention comprises a distribution system having a switch for connecting or disconnecting a distribution line, a higher system connected thereto, and a higher system for monitoring and controlling the higher system. A first storage unit connected to the configured power system and configured to store the accident information received from the upper system by securing a storage area for each accident, and reading the accident information read from each storage area of the storage unit; In the distribution system control system that controls the switch to perform the recovery operation of the accident corresponding to the accident information, the remote monitoring control information transmitted from the upper system (the upper system transmits to each remote substation, etc.) "Failure / abnormality information SV: Supervisory and measurement information TM such as voltage and current TM: Telemeter" required to perform monitoring and control on the control information are hereinafter referred to as SV / TM information.
Second storage means for storing state information indicating the state of the line and the switch estimated from the above, and the transmission equipment before the power failure read from the second storage means when the power failure of the distribution line occurs, the transmission equipment information before the power failure. And a third storage means for storing the data in a storage area corresponding to the distribution line.
By reading the power transmission equipment information before the power failure from the storage area of the storage means, and storing the information together with other accident information in the storage area of the first storage means corresponding to the same accident, The present invention is to read out power transmission facility information before a power failure from a storage area corresponding to an accident, correctly recognize a restoration target, and accurately perform an accident restoration operation of a distribution system.

C.従来の技術 近年、配電系統の操作を自動化するため配電系統制御
システムが導入されつつある。配電系統制御システムと
は、一般に配電線の各所に配置された開閉器とそれらを
監視制御する制御システムとによって構成されたものを
指すが、狭義には、制御システムのみを配電系統制御シ
ステムと呼ぶ。ここでは、制御システムのことを配電系
統制御システムということにする。
C. Prior Art In recent years, a distribution system control system has been introduced to automate the operation of the distribution system. The distribution system control system generally refers to a system configured by switches arranged in various parts of a distribution line and a control system for monitoring and controlling them, but in a narrow sense, only the control system is referred to as a distribution system control system. . Here, the control system is referred to as a distribution system control system.

この種の配電系統制御システムを備えた従来の電力系
統のブロック図を第4図に示す。この電力系統は、上位
系統3、配電系統4によって構成し、それぞれ上位シス
テム2、配電系統制御システム1が接続している。上位
系統3は配電線CB以上の配変所、変電所、および発送電
系統であり、図には例として配変所31を示した。配電系
統4は配電線立上り線路5以降の配電線群であり、この
線路によって上位系統3に接続されている。配電系統4
の配電線41にはこれを接続または切断する自動開閉器と
して、遠制機能付きの幹線開閉器42、連係開閉器43等が
設けられている。
FIG. 4 is a block diagram of a conventional power system provided with this type of distribution system control system. This power system is composed of a higher system 3 and a distribution system 4, and a higher system 2 and a distribution system control system 1 are connected to each other. The upper system 3 is a distribution substation, a substation, and a transmission power system of distribution line CB or higher, and a distribution substation 31 is shown as an example in the figure. The distribution system 4 is a group of distribution lines after the distribution line rising line 5 and is connected to the higher system 3 by this line. Distribution system 4
The distribution line 41 is provided with a main line switch 42 with a remote control function, a link switch 43, and the like as automatic switches for connecting or disconnecting the distribution line 41.

配電系統制御システム1と上位システム2、および上
位システム2と上位系統3とはそれぞれ通信線6、7に
よって接続されている。また、配電系統4の上記開閉器
と配変所31とは通信線または配電線搬送設備群(図では
省略)によって接続されている。
The distribution system control system 1 and the upper system 2, and the upper system 2 and the upper system 3 are connected by communication lines 6 and 7, respectively. The switch of the distribution system 4 and the distribution station 31 are connected by a communication line or a group of distribution line transport equipment (not shown).

幹線開閉器42、連係開閉器43等の自動開閉器は、両側
線路の充停電変化に応じて現地で自動操作される一方、
配電系統制御システム1との間で上位システム2および
上位系統3を中継して監視制御情報の送受信を行い、こ
れにより遠隔的に操作される。
The automatic switches such as the main line switch 42 and the link switch 43 are automatically operated on site in accordance with the change of charging / discharging of both sides of the track,
The upper system 2 and the upper system 3 are relayed with the distribution system control system 1 to transmit and receive monitoring control information, thereby being remotely operated.

ところで、配電系統操作を目的別に分類すると、事故
復旧操作、予定停止操作、負荷切替操作、緊急停止操作
等に分類できる。これらの操作の中で特に重要なのは事
故復旧操作である。操作の必要上、配電線を人為的に停
止させる場合には、あらかじめ停電時間や停電範囲を縮
小するようコントロールすることが可能である。しか
し、事故によって停電する場合にはこのようなコントロ
ールは不可能である。予告なしに配電線が長時間、広範
囲に亘って停電するのは、その地域の経済活動あるいは
社会生活に甚大な影響を与える。従って、事故による停
電を迅速に復旧する、いわゆる事故復旧操作が配電系統
制御システムにとって極めて重要である。
By the way, when the distribution system operation is classified by purpose, it can be classified into an accident recovery operation, a scheduled stop operation, a load switching operation, an emergency stop operation, and the like. The most important of these operations is the accident recovery operation. Due to the necessity of the operation, when the distribution line is artificially stopped, it is possible to control in advance to reduce the power outage time and the power outage range. However, such control is not possible when a power failure occurs due to an accident. Long-term, widespread blackouts of distribution lines without notice have a tremendous impact on local economic activity or social life. Therefore, a so-called accident restoration operation for quickly restoring a power failure due to an accident is extremely important for the distribution system control system.

事故復旧操作を行うにはまず事故発生時刻、事故発生
箇所、事故種別、上位系統復旧操作状況等の事故状況を
正しく把握する必要がある。事故による配電系統の停電
は、配電線41そのものに発生した事故や、上位系統3が
事故によって停電し、これが波及して生じる。具体的に
は、前者は例えば配電線事故、後者はバンク事故、電源
事故等である。
In order to perform an accident recovery operation, it is first necessary to correctly understand the accident status, such as the time at which the accident occurred, the location where the accident occurred, the type of accident, and the status of the upper system restoration operation. The power outage of the distribution system due to the accident is caused by an accident occurring in the distribution line 41 itself or a power outage of the higher system 3 due to the accident, which spreads. Specifically, the former is, for example, a distribution line accident, and the latter is a bank accident, a power supply accident, or the like.

これらの事故は上位系統を監視制御している現地自動
機器や上位システム2が検知し、まず上位系統3におい
て事故復旧操作が行われる。例えば、再閉路リレーによ
る再閉路、再々閉路あるいは上位システム2の遠方操作
による系統切替等が実施される。配電系統4の復旧操作
はこれらの操作が終了した後開始する。これに至るまで
の間、上位システム2は配変所31を始めとする上位系統
3の機器群から情報を収集し、事故情報を随時メッセー
ジ形式に編集して配電系統制御システム1へ送信する。
通常、1件の事故について、事故発生状況を第1報の事
故メッセージで通知し、上位系統3における復旧操作状
況や再事故発生状況等を第2,第3報の事故メッセージで
通知する。また、上位システム2は常時、上位系統3の
機器群の状態を収集し、それをSV・TM情報として編集し
配電系統制御システムに送信する。配電系統制御システ
ム1はこれらの情報によって事故状況を認識する。
These accidents are detected by local automatic equipment monitoring and controlling the upper system and the upper system 2, and an accident recovery operation is first performed in the upper system 3. For example, re-closing by a re-closing relay, re-closing, or system switching by remote operation of the host system 2 is performed. The operation of restoring the distribution system 4 starts after these operations are completed. Until this time, the upper system 2 collects information from the equipment group of the upper system 3 including the distribution station 31, edits the accident information into a message format as needed, and transmits it to the distribution system control system 1.
Usually, for one accident, the status of the occurrence of the accident is notified by the accident message of the first report, and the status of the recovery operation in the upper system 3 and the status of the occurrence of the re-accident are notified by the accident messages of the second and third reports. The host system 2 always collects the state of the device group of the host system 3, edits it as SV / TM information, and sends it to the distribution system control system. The distribution system control system 1 recognizes the accident situation based on the information.

D.発明が解決しようとする課題 配電系統制御システムが上位システムから事故メッセ
ージを受信し、事故情報を抽出してこれらを発生した事
故ごとに管理する。そして、上位系統の事故復旧操作の
進展状況を把握し、個々の事故に対して的確なタイミン
グで配電系統の事故復旧操作を実施する。
D. Problems to be Solved by the Invention A distribution system control system receives an accident message from a host system, extracts accident information, and manages the information for each accident that has occurred. Then, the progress of the accident restoration operation of the upper system is grasped, and the accident restoration operation of the distribution system is executed at an appropriate timing for each accident.

ところで、このような事故復旧操作を実施するために
は復旧すべき対象を認識する必要がある。すなわち、配
電系統制御システムは事故復旧操作の実施に先立ち、事
故が発生する以前の送電範囲、従って送電を行っていた
配電線の区間(以下、線路という)および入りとなって
いた開閉器を知る必要がある。
By the way, in order to perform such an accident recovery operation, it is necessary to recognize an object to be recovered. That is, the distribution system control system knows the power transmission range before the accident occurred, and therefore, the section of the distribution line (hereinafter referred to as a line) and the switch that was turned on before the accident occurred. There is a need.

本発明の目的は、このような要求を満たし、復旧対象
を正しく認識して、配電系統の事故復旧操作を的確に実
施できる配電系統制御システムを提供することにある。
An object of the present invention is to provide a distribution system control system that satisfies such a demand, correctly recognizes a restoration target, and can accurately perform an accident restoration operation of the distribution system.

E.課題を解決するための手段 本発明の配電系統制御システムは、配電線を接続また
は切断する開閉器を備えた配電系統と、これに接続され
た上位系統とによって構成された電力系統に接続し、上
記上位系統を監視制御する上位システムから受け取った
事故情報を各事故ごとに記憶領域を確保して記憶する第
1の記憶手段を有し、この記憶手段の上記記憶領域から
読み出した上記事故情報にもとづいて上記開閉器を制御
し、上記配電系統の事故復旧操作を実施する配電系統制
御システムにおいて、 上記上位システムが送信するSV・TM情報から線路およ
び開閉器の状態を推定する状態推定手段と、 上記状態推定手段が推定した上記状態情報を記憶する
第2の記憶手段と、 上記配電線に停電が生じる以前の送電設備情報を記憶
する第3の記憶手段と、 上記SV・TM情報をもとに上記配電線が停電したか否か
を判定する停電判定手段と、 この停電判定手段が上記配電線が停電したと判定した
とき、上記第2の記憶手段から停電となった配電線の停
電前の上記送電設備情報を読み出し、上記第3の記憶手
段の記憶手段の記憶領域に記憶させる第1の記憶制御手
段と、 上記上位システムからの事故情報にもとづいて事故に
より停電した配電線を特定する配電線識別手段と、 この配電線識別手段が特定する上記配電線に対応する
上記第3の記憶手段の記憶領域から停電前の上記送電設
備情報を読み出し、上記配電線を停電させた事故の事故
情報を記憶されている上記第1の記憶手段の記憶領域に
書き込む第2の記憶制御手段とを備えたことを特徴とす
る。
E. Means for Solving the Problems The distribution system control system of the present invention is connected to a power system configured by a distribution system having a switch for connecting or disconnecting a distribution line, and a higher system connected thereto. A first storage unit that secures a storage area for each accident and stores the accident information received from an upper system that monitors and controls the upper system, and stores the accident information read from the storage area of the storage unit. In a distribution system control system that controls the switch based on information and performs an accident recovery operation of the distribution system, a state estimating unit that estimates a state of a line and a switch from SV / TM information transmitted by the upper system. A second storage unit that stores the state information estimated by the state estimation unit; a third storage unit that stores power transmission facility information before a power failure occurs in the distribution line. A power outage determining means for determining whether or not the power distribution line has failed based on the SV / TM information; and when the power failure determining means determines that the power distribution line has failed, the second storage means First storage control means for reading out the power transmission facility information before the power failure of the power distribution line and storing the information in a storage area of the storage means of the third storage means, and based on the accident information from the host system Distribution line identification means for identifying a distribution line that has been powered down due to an accident; and reading out the power transmission facility information before a power failure from a storage area of the third storage means corresponding to the distribution line identified by the distribution line identification means, And a second storage control means for writing accident information of the accident in which the power distribution line was interrupted into the storage area of the first storage means.

F.作用 上記状態推定手段は、上位システムが送信するSV・TM
情報から線路および開閉器の状態を推定して出力し、第
2図の記憶手段はこれを記憶する。一方、停電判定手段
は、SV・TM情報をもとに配電線が停電したか否かを判定
する。この停電判定手段が配電線が停電したと判定した
とき、第1の記憶制御手段は、第2の記憶制御手段から
停電となった配電線の停電前の送電設備情報を読み出
し、停電となった配電線に対応する第3の記憶手段の記
憶領域に記憶させる。
F. Operation The state estimating means is the SV / TM transmitted by the host system.
The state of the line and the switch is estimated from the information and output, and the storage means in FIG. 2 stores this. On the other hand, the power failure determining means determines whether or not the power distribution line has failed based on the SV / TM information. When the power outage determining means determines that the power distribution line has failed, the first storage control means reads out the power transmission facility information before the power failure of the power outage distribution line from the second storage control means, and the power failure occurs. The information is stored in the storage area of the third storage means corresponding to the distribution line.

また、配電線識別手段は、上位システムからの事故情
報にもとづいて事故により停電となった配電線を特定
し、第2の記憶制御手段は、この配電線識別手段が特定
する配電線に対応する第3の記憶手段の記憶領域から、
この配電線の停電前の送電設備情報を読み出し、この配
電線を停電させた事故の事故情報が記憶されている第1
の記憶手段の記憶領域に書き込む。
In addition, the distribution line identification means specifies a distribution line that has lost power due to an accident based on the accident information from the host system, and the second storage control means corresponds to the distribution line specified by the distribution line identification means. From the storage area of the third storage means,
The power transmission equipment information of the distribution line before the power outage is read out, and the accident information of the accident that caused the power outage of the distribution line is stored in the first
In the storage area of the storage means.

配電系統制御システムは、第1の記憶手段の個々の事
故に対応する記憶領域から事故配電線の停電前の送電設
備情報を読み出すことによって、復旧対象を正しく認識
し、配電系統の事故復旧操作を的確に実施することがで
きる。
The distribution system control system reads the transmission facility information before the power failure of the accident distribution line from the storage area corresponding to each accident in the first storage means, thereby correctly recognizing the restoration target, and performing the accident restoration operation of the distribution system. It can be implemented accurately.

G.実施例 次に本発明の一実施例について説明する。本実施例の
配電系統制御システムを備えた電力系統のブロック図を
第1図に示す。この電力系統は、上位系統103、配電系
統104によって構成し、それぞれに上位システム102、配
電系統制御システムが接続している。配電系統制御シス
テム101と上位システム102、および上位システム102と
上位系統103とはそれぞれ通信線106、107によって接続
され、上位系統103と配電系統104とは配電線立上り線路
105によって接続されている。
G. Embodiment Next, an embodiment of the present invention will be described. FIG. 1 is a block diagram of an electric power system including the distribution system control system according to the present embodiment. This power system is composed of a higher system 103 and a distribution system 104, and a higher system 102 and a distribution system control system are connected to each other. The distribution system control system 101 and the upper system 102, and the upper system 102 and the upper system 103 are connected by communication lines 106 and 107, respectively, and the upper system 103 and the distribution system 104 are connected to a distribution line rising line.
Connected by 105.

以下では、まず上位系統103、配電系統104、および上
位システム102について説明し、その後配電系統制御シ
ステム101について詳しく説明する。上位系統103は配電
線CB以上の配変所、変電所、および発送電系統であり、
図には例として配変所131を示した。配電系統104配電線
立上り線路105以降の配電線群である。配電系統104の配
電線141にはこれを接続または切断する自動開閉器とし
て、例えば幹線開閉器142、連係開閉器143が設けられて
いる。これら開閉器と変電所131とは通信線または配電
線搬送設備群(図では省略)によって接続されている。
幹線開閉器142および連係開閉器143は、配電系統制御シ
ステム101により遠隔的に操作されて入りまたは切りと
なる。これら開閉器と配電系統制御システム101とは上
位システム102および上位系統103を中継して監視制御情
報の送受信を行う。
Hereinafter, the upper system 103, the distribution system 104, and the upper system 102 will be described first, and then the distribution system control system 101 will be described in detail. The upper system 103 is a distribution station, a substation, and a transmission power system of distribution line CB and higher,
The figure shows the distribution station 131 as an example. This is a group of distribution lines after the distribution system 104, the distribution line rising line 105. The distribution line 141 of the distribution system 104 is provided with, for example, a main line switch 142 and a link switch 143 as automatic switches for connecting or disconnecting the distribution line 141. These switches and the substation 131 are connected by a communication line or a group of distribution line transport equipment (not shown).
The main switch 142 and the link switch 143 are remotely operated by the distribution system control system 101 to be turned on or off. These switches and the distribution system control system 101 transmit and receive monitoring control information via the upper system 102 and the upper system 103.

上位システム102は通信線107を通じて上位系統103を
監視制御する。上位システム102は常時、上位系統103の
機器群の状態を収集し、それをSV・TM情報によって通信
線106を通じて配電系統制御システム101に送信する。
The host system 102 monitors and controls the host system 103 through the communication line 107. The host system 102 constantly collects the state of the device group of the host system 103 and transmits the collected state to the power distribution system control system 101 via the communication line 106 using SV / TM information.

上位系統103あるいは配電系統104においてバンク事
故、電源事故、配電線事故等が発生すると、これらは上
位系統103を監視制御している現地自動機器あるいは上
位システム102によって検知され、まず上位系統103にお
いて、例えば、再閉路リレーによる再閉路、再再閉路あ
るいは上位システム102の遠方操作による系統切替等の
事故復旧操作が行われる。配電系統104の事故復旧操作
はこれらの操作が終了した後、開始される。これに至る
までの間、上位システム102は変電所131を始めとする上
位系統103の機器群から状態情報を収集し、事故情報を
随時メッセージ形式に編集して配電系統制御システム10
1へ送信する。
When a bank accident, power supply accident, distribution line accident, or the like occurs in the upper system 103 or the distribution system 104, these are detected by local automatic equipment or the upper system 102 that monitors and controls the upper system 103, and first, in the upper system 103, For example, an accident recovery operation such as a reclosing by a reclosing relay, a reclosing, or a system switching by a remote operation of the host system 102 is performed. The accident recovery operation of the distribution system 104 is started after these operations are completed. Until this time, the upper system 102 collects status information from the equipment group of the upper system 103 including the substation 131, edits the accident information into a message format as needed, and
Send to 1.

なお、SV・TM情報は機器群の状態が変化したときただ
ちに直接的な形式で編集して送信されるが、事故メッセ
ージは状態の変化を一定時間待って編集するためSV・TM
情報に比べ若干遅れて送信される。
SV / TM information is edited and sent immediately when the status of the device group changes, but the accident message is edited after waiting for a certain period of time for the status change to be edited.
Sent slightly later than the information.

上位システム102は、通常、1件の事故について、事
故発生状況を第1報の事故メッセージで通知し、上位系
統3における復旧操作状況や再事故発生状況等を第2,第
3報の事故メッセージで通知する。具体的には、第1報
の事故メッセージで事故発生日時、事故関連設備、関連
する上位系統103の設備状態、その他の情報を伝え、第
2、第3報の事故メッセージで事故発生日時、事故関連
設備、復旧操作状況、その他の情報を伝える。配電系統
制御システム101はこれらの事故メッセージをもとに事
故情報を管理し、そして上位系統103の事故復旧状態を
把握し、上位系統103の事故復旧操作が終了した後、配
電系統104の事故復旧操作を実施する。
The host system 102 usually notifies the status of the occurrence of an accident with an accident message of the first report for one accident, and reports the status of the recovery operation and the occurrence of a re-accident in the host system 3 in the accident messages of the second and third reports. To notify. Specifically, the accident message of the first report conveys the date and time of the accident, the accident-related equipment, the equipment status of the related upper system 103, and other information. The accident message of the second and third reports reports the date and time of the accident and the accident. Communicate related equipment, restoration operation status, and other information. The distribution system control system 101 manages accident information based on these accident messages, grasps the state of accident recovery of the upper system 103, and after the accident recovery operation of the upper system 103 is completed, recovers the accident of the distribution system 104. Perform the operation.

次に、配電系統制御システム101について詳しく説明
する。配電系統制御システム101は事故情報管理部110、
状態情報管理部120、ならびに復旧制御部115によって構
成されている。
Next, the distribution system control system 101 will be described in detail. The distribution system control system 101 includes an accident information management unit 110,
It is composed of a state information management unit 120 and a recovery control unit 115.

まず、事故情報管理部110について説明する。メモリ1
11は、上位システム102から送られてくる事故情報を、
事故ごとに分けて記憶するための複数の記憶領域を持
つ。情報検索部113は後述するメモリ制御部112がメモリ
111から読み出した各事故情報と、後述する情報抽出部1
14からの事故情報とを比較し、その関係の有無を判定す
る。
First, the accident information management unit 110 will be described. Memory 1
11 is the accident information sent from the host system 102,
It has a plurality of storage areas for storing data separately for each accident. The information search unit 113 is operated by a memory control unit 112 described later.
Each accident information read from 111 and the information extraction unit 1 described later
The accident information from 14 is compared, and the presence or absence of the relationship is determined.

メモリ制御部112は、情報検索部113が関係する事故情
報を見つけたとき、情報抽出部114が抽出した事故情報
を、メモリ111の当該事故情報と同一の記憶領域に追加
して記憶させる。一方、情報検索部113が関係する事故
情報を見つけられなかったときは、メモリ制御部112は
情報抽出部114が抽出した事故情報を、メモリ111にすで
に記憶されている事故情報とは異なる記憶領域に記憶さ
せる。なお、メモリ制御部112は状態情報管理部120のメ
モリ制御部123と関連した機能をも持つが、これについ
ては後で説明する。
When the information search unit 113 finds related accident information, the memory control unit 112 adds the accident information extracted by the information extraction unit 114 to the same storage area of the memory 111 as the accident information and stores the same. On the other hand, when the information search unit 113 cannot find the relevant accident information, the memory control unit 112 stores the accident information extracted by the information extraction unit 114 in a storage area different from the accident information already stored in the memory 111. To memorize. Note that the memory control unit 112 also has a function related to the memory control unit 123 of the state information management unit 120, which will be described later.

情報抽出部114は上位システム102から送られてくる第
1〜第3報の事故メッセージから事故発生日時、事故関
連設備、関連する上位系統103の設備状態、復旧操作状
況等の事故情報を抽出し、情報検索部113に出力する。
The information extraction unit 114 extracts accident information such as the date and time of occurrence of the accident, the accident-related equipment, the equipment state of the associated higher-order system 103, the status of the recovery operation, and the like from the accident messages of the first to third reports sent from the upper system 102. Is output to the information retrieval unit 113.

次に、事故情報管理部110の動作を説明する。上位系
統103で最初の事故が発生したとすると、上位システム1
02はこれを検知し、その第1報の事故メッセージを配電
系統制御システム101に送る。情報抽出部114はこれを受
け取ると、事故発生日時に、事故関連設備等の事故情報
を抽出する。情報検索部113はこれらを受け取り、事故
発生日時および事故関連設備とメモリ制御部112を通じ
てメモリ111から読み出した各事故情報とを比較する。
この場合には、受信した事故情報に関係する事故情報は
メモリ111にはまだ記憶されていないので、情報検索部1
13は、情報は無関係であると判定する。メモリ制御部11
2はこのとき、情報抽出部114が抽出したすべての事故情
報を情報検索部113から受け取り、それらを新たに発生
した事故の情報として、その事故のために確保したメモ
リ111の記憶領域に書き込む。
Next, the operation of the accident information management unit 110 will be described. If the first accident occurs in the upper system 103, the upper system 1
02 detects this, and sends the accident message of the first report to the distribution system control system 101. Receiving this, the information extraction unit 114 extracts accident information on accident-related equipment and the like at the date and time when the accident occurred. The information retrieval unit 113 receives these, and compares the date and time of occurrence of the accident and the accident-related equipment with each accident information read from the memory 111 through the memory control unit 112.
In this case, since the accident information related to the received accident information is not yet stored in the memory 111, the information retrieval unit 1
13 determines that the information is irrelevant. Memory control unit 11
At this time, 2 receives all the accident information extracted by the information extracting unit 114 from the information retrieving unit 113, and writes them as information of a newly generated accident in the storage area of the memory 111 reserved for the accident.

上位系統103において別の事故が発生すると上位シス
テム102は同様にこれを検知し、その第1報の事故メッ
セージを配電系統制御システム101に送る。情報抽出部1
14はこれを受け取ると、事故発生日時、事故関連設備等
の事故情報を抽出する。情報検索部113はこれを受け取
り、事故発生日時および事故関連設備とメモリ制御部11
2を通じてメモリ111から読み出した事故情報とを比較す
る。この場合には、メモリ111には最初の事故の事故情
報が記憶されているので、情報検索部113にはその事故
情報が与えられる。これらは異なる事故のものであり、
関係しないため、情報検索部113は事故情報は無関係と
判定する。そのためメモリ制御部112は、情報抽出部114
が抽出した事故情報を情報検索部113から受け取り、そ
れらを新たに発生した別の事故の情報として、メモリ11
1に新たに記憶領域を確保して記憶させる。
When another accident occurs in the upper system 103, the upper system 102 similarly detects this and sends a first accident message to the distribution system control system 101. Information extraction unit 1
14 receives this, and extracts accident information such as the date and time of accident occurrence, accident-related equipment, and the like. The information retrieval unit 113 receives this, and records the date and time of the occurrence of the accident, the accident-related equipment and the memory control unit 11.
2 and the accident information read from the memory 111 is compared. In this case, since the accident information of the first accident is stored in the memory 111, the accident information is given to the information retrieval unit 113. These are from different accidents,
Since they are not related, the information search unit 113 determines that the accident information is not relevant. Therefore, the memory control unit 112
Receives the accident information extracted from the information search unit 113, and stores them as information of another newly generated accident in the memory 11
First, a new storage area is secured and stored.

次に、上位システム102が最初に発生した事故の第2
報の事故メッセージを送出すると、情報抽出部114はこ
のメッセージを受け取り、事故発生日時、事故関連設備
等の事故情報を抽出する。情報検索部113は抽出された
事故発生日時および事故関連設備と、メモリ制御部112
を通じてメモリ111から読み出した事故情報とを比較す
る。メモリ111には最初の事故の事故情報が記憶されて
いるので、その事故情報が情報検索部113に与えられた
とき、情報検索部113はこれら2つの事故の事故発生日
時および事故関連設備が関係すると判定する。メモリ制
御部112は、事故情報が関係すると判定されたため、事
故メッセージから抽出された他の事故情報を最初の事故
の情報として、メモリ111にすでに確保されている最初
の事故のための記憶領域に追加して書き込む。上位シス
テムが最初の事故の第3報の事故メッセージを送出した
場合にも同様に処理され、その事故情報は同じ記憶領域
に書き込まれる。
Next, the upper-level system 102
When an informational accident message is transmitted, the information extracting unit 114 receives this message and extracts accident information such as the date and time of occurrence of the accident and accident-related equipment. The information retrieval unit 113 includes the extracted accident occurrence date and time and accident-related equipment, and the memory control unit 112.
Is compared with the accident information read from the memory 111. Since the accident information of the first accident is stored in the memory 111, when the accident information is given to the information retrieving unit 113, the information retrieving unit 113 associates the date and time of the accident of these two accidents and the accident-related equipment. It is determined. Since it is determined that the accident information is related, the memory control unit 112 uses the other accident information extracted from the accident message as the first accident information in the storage area for the first accident already secured in the memory 111. Add and write. The same processing is performed when the host system sends the third accident message of the first accident, and the accident information is written to the same storage area.

また、上位システム102が2番目に発生した事故の第
2報の事故情報を出力した場合には、その事故情報の事
故発生日時および事故関連設備は2番目の事故のために
確保した記憶領域から読み出した事故情報と関係するた
め、その事故情報はメモリ111に2番目の事故のために
確保した記憶領域に追加して書き込まれる。
When the host system 102 outputs the accident information of the second report of the second accident, the accident date and time of the accident information and the accident-related equipment are stored in the storage area reserved for the second accident. Since the accident information is related to the read accident information, the accident information is additionally written in the memory 111 in the storage area reserved for the second accident.

一方、さらに別の事故が発生した場合には、その事故
情報の事故発生日時および事故関連設備はメモリ111に
すでに記憶されているいずれの事故情報とも関係しない
ため、これらは新たに発生した事故の情報として別の記
憶領域に記憶される。
On the other hand, if another accident has occurred, the date and time of the accident and the accident-related equipment in the accident information are not related to any accident information already stored in the memory 111. The information is stored in another storage area.

第2図は、事故メッセージから抽出した事故情報がメ
モリ111にいかに記憶されるかを概念的に示すものであ
る。最初の事故の第1報の事故情報は、そのために確保
した記憶領域である事故情報ファイルAに格納され
(a)、一方、次に発生した事故の第1報の事故情報は
別の記憶領域である事故情報ファイルBに格納される
(b)。また、2番目に発生した事故の第2、第3報の
事故情報は、上述した事故情報の関係有無の判定によっ
て関係ありとなり、事故情報ファイルBに追加される
(c)。
FIG. 2 conceptually shows how the accident information extracted from the accident message is stored in the memory 111. The accident information of the first report of the first accident is stored in the accident information file A which is a storage area reserved for that purpose (a), while the accident information of the first report of the next accident is stored in another storage area. (B). In addition, the accident information of the second and third reports of the second occurrence of the accident is related by the above-mentioned determination of the presence or absence of the relation of the accident information, and is added to the accident information file B (c).

次に、状態情報管理部120について説明する。メモリ1
21は配電系統104の配電線を構成する線路および開閉器
の状態を示す状態情報を記憶する。一方、メモリ122は
事故によって停電する以前に送電していた線路および入
りとなっていた開閉器、すなわち、停電前送電設備を記
憶する。メモリ122はこれらの情報を各配電線ごとに記
憶領域を確保し、分けて記憶する。
Next, the state information management unit 120 will be described. Memory 1
Reference numeral 21 stores state information indicating the states of the lines and switches constituting the distribution lines of the distribution system 104. On the other hand, the memory 122 stores the line that had been transmitting power before the power failure due to the accident and the switch that was on, that is, the power transmission equipment before the power failure. The memory 122 secures a storage area for each distribution line and stores the information separately.

状態推定部124は上位システム102が送出したSV・TM情
報を受信し、配電線の充停電に関する状態変化(例え
ば、CBの入り/切り、バンク2次電圧のあり/なし)を
検出する。そして、線路および開閉器の状態変化を推定
し、結果としての線路および開閉器の状態に関する状態
情報を後述するメモリ制御部123に出力する。状態推定
部124はまた、ある配電線に関して検出した状態変化が
停電方向である場合には、そのことをメモリ制御部123
に通知する。すなわち、状態推定部124は停電判定手段
としての機能を果たす。
The state estimating unit 124 receives the SV / TM information transmitted from the host system 102 and detects a state change (for example, ON / OFF of the CB and presence / absence of the bank secondary voltage) related to charging / discharging of the distribution line. Then, the state change of the line and the switch is estimated, and the resulting state information on the state of the line and the switch is output to the memory control unit 123 described later. If the state change detected for a certain distribution line is the direction of a power outage, the state estimating unit 124 also notifies the memory control unit 123 of the fact.
Notify. That is, the state estimating unit 124 functions as a power failure determination unit.

メモリ制御部123は状態推定部124からの状態情報を受
け取り、メモリ121に書き込む。また、状態推定部124か
ら停電の通知を受けたときは、停電となる直前の配電線
の送電設備をメモリ121から読み出し、停電前送電設備
の情報としてメモリ122の配電線ごとに確保した記憶領
域に書き込む。
The memory control unit 123 receives the state information from the state estimating unit 124 and writes the state information into the memory 121. When a notification of a power failure is received from the state estimating unit 124, the power transmission facility of the distribution line immediately before the power failure is read from the memory 121, and the storage area secured for each distribution line of the memory 122 as information on the power transmission facility before the power failure. Write to.

メモリ制御部123はメモリ制御部112とも接続し、必要
に応じてメモリ122の記憶内容を読み出して、メモリ制
御部112に出力する。すなわち、メモリ制御部112は、情
報検索部113が事故情報は無関係と判定し、新たに発生
した事故の事故情報をメモリ111に書き込むとき、事故
により停電した配電線の停電前送電設備の情報をメモリ
制御部123に要求する。このとき、メモリ制御部112は配
電線識別手段として機能し、メモリ111に書き込む事故
情報をもとに停電した配電線を特定し、メモリ制御部12
3に通知する。メモリ制御部123はこれを受けると、停電
した配電線の停電前送電設備の情報をメモリ122の対応
する記憶領域から読み出し、メモリ制御部112に送出す
る。メモリ制御部112はこれを受け取り、その事故のた
めに確保したメモリ111の記憶領域に関係する事故情報
と共に復旧対象の情報として格納する。上述したよう
に、事故メッセージはSV・TM情報に比べ若干遅れて上位
システム102から送信されるので、メモリ制御部112はメ
モリ122にすでに書き込まれた停電前送電設備の情報を
受け取ることができる。
The memory control unit 123 is also connected to the memory control unit 112, reads out the contents stored in the memory 122 as necessary, and outputs the read out contents to the memory control unit 112. That is, the memory control unit 112, when the information search unit 113 determines that the accident information is irrelevant and writes the accident information of the newly-occurred accident to the memory 111, the information of the power transmission equipment before the power outage of the distribution line that has failed due to the accident A request is made to the memory control unit 123. At this time, the memory control unit 112 functions as distribution line identification means, identifies the power distribution line that has lost power based on the accident information written in the memory 111, and
Notify 3. Receiving this, the memory control unit 123 reads out the information of the power transmission equipment before the power failure of the power distribution line from the corresponding storage area of the memory 122 and sends it to the memory control unit 112. The memory control unit 112 receives this, and stores it as recovery target information together with accident information relating to the storage area of the memory 111 reserved for the accident. As described above, since the accident message is transmitted from the host system 102 slightly later than the SV / TM information, the memory control unit 112 can receive the information of the power transmission equipment before the power failure already written in the memory 122.

なお、メモリ制御手段112とメモリ制御手段123とはこ
のとき、停電前送電設備の情報をメモリ122から読み出
し、メモリ111の所定の記憶領域に書き込むメモリ制御
手段として機能している。
At this time, the memory control unit 112 and the memory control unit 123 function as a memory control unit that reads information of the power transmission facilities before the power failure from the memory 122 and writes the information into a predetermined storage area of the memory 111.

次に、状態情報管理部120の動作を説明する。上位シ
ステム102は、常時上位系統103の機器群から情報を収集
し、SV・TM情報を編集して配電系統制御システム101に
送信する。状態推定部124は、これを受信し、配電線の
充停電に関する状態変化を検出する。そして、線路およ
び開閉器の状態変化を推定し、結果としての線路および
開閉器の状態に関する情報をメモリ制御部123に出力す
る。このとき、検出した状態変化が停電である場合に
は、そのことをメモリ制御部123に通知する。
Next, the operation of the state information management unit 120 will be described. The host system 102 constantly collects information from the device group of the host system 103, edits the SV / TM information, and transmits it to the distribution system control system 101. The state estimating unit 124 receives this, and detects a state change related to charging and stopping of the distribution line. Then, the state change of the line and the switch is estimated, and information on the resulting state of the line and the switch is output to the memory control unit 123. At this time, if the detected state change is a power outage, the fact is notified to the memory control unit 123.

メモリ制御部123は状態推定部124からの配電線の線路
および開閉器の状態に関する情報を受け取り、これらを
メモリ121に書き込む。また、状態推定部124から停電の
通知を受けたときは、停電となった配電線の停電前送電
設備の情報をメモリ121から読み出し、これらをメモリ1
22の配電線ごとに確保した記憶領域に書き込む。これに
よって、メモリ122には停電が発生した配電線の停電前
送電設備の情報が配電線ごとに記憶される。
The memory control unit 123 receives the information on the state of the distribution line and the switch from the state estimation unit 124 and writes them into the memory 121. Further, when receiving a notification of the power failure from the state estimating unit 124, the information of the power transmission facilities before the power failure of the distribution line having the power failure is read from the memory 121, and these are read out from the memory
Write to the storage area secured for each of the 22 distribution lines. As a result, in the memory 122, information on the power transmission facilities before the power failure of the distribution line in which the power failure has occurred is stored for each distribution line.

一方、メモリ制御部112は、情報検索部113が、情報抽
出部114により抽出された事故情報と、メモリ111に格納
されている事故情報とは関係しないと判定し、従って、
新たに発生した事故の事故情報をメモリ111に書き込む
とき、事故により停電した配電線の停電前送電設備の情
報をメモリ制御部123に、停電した配電線を通知して要
求する。メモリ制御部123はこれを受けると、要求され
た停電前送電設備の情報はすでにメモリ122に格納され
ているので、これらを読み出し、メモリ制御部112に送
る。メモリ制御部112はこれを受け取り、その事故のた
めに確保したメモリ111の記憶領域に関係する事故情報
と共に復旧対象の情報として格納する。
On the other hand, the memory control unit 112 determines that the information search unit 113 has no relation to the accident information extracted by the information extraction unit 114 and the accident information stored in the memory 111.
When writing the accident information of a newly generated accident into the memory 111, the memory control unit 123 is notified of the information of the transmission line before the interruption of the distribution line that has been interrupted due to the accident and requests the information to the memory control unit 123. Receiving this, the memory control unit 123 reads out the requested information on the power transmission equipment before the power failure since it is already stored in the memory 122, and sends it to the memory control unit 112. The memory control unit 112 receives this, and stores it as recovery target information together with accident information relating to the storage area of the memory 111 reserved for the accident.

第3図は、SV・TM情報から抽出した情報がいかにメモ
リ121、122に書き込まれ、さらにメモリ111の所定の記
憶領域に書き込まれるかを概念的に示したものである。
SV・TM情報から推定した線路および開閉器に関する状態
情報は、まずメモリ121に書き込まれる。そして、停電
のときは、停電となった配電線の停電前送電設備をメモ
リ121から読み出し、例えば、線路N0、N1、N2、N3の設
備No.、開閉器S4、S5、S6の設備No.をメモリ122の配電
線F1〜Fnごとに確保した記憶領域に書き込む。これらの
情報は、メモリ制御部112からの要求によって読み出さ
れ、対応する事故の記憶領域、事故情報ファイルAに、
事故メッセージから抽出した関係する事故情報と共に書
き込まれる。
FIG. 3 conceptually shows how the information extracted from the SVTM information is written to the memories 121 and 122 and further written to a predetermined storage area of the memory 111.
The state information on the line and the switch estimated from the SV / TM information is first written into the memory 121. Then, at the time of a power outage, the power transmission equipment before the power outage of the distribution line in which the power outage occurred is read out from the memory 121. In the storage area of the memory 122 secured for each of the distribution lines F 1 to Fn. These pieces of information are read by a request from the memory control unit 112, and are stored in a corresponding accident storage area, accident information file A.
Written with the related accident information extracted from the accident message.

復旧制御部115は、メモリ制御部112を通じてメモリ11
1から事故情報を読み出して監視しており、事故情報と
して上位系統103の事故復旧操作の終了情報が書き込ま
れた場合には、その記憶領域に対応する事故の復旧操作
を開始する。すなわち、監視制御情報を上位システム10
2および上位系統103を中継して配電系統104の例えば幹
線開閉器142および関連開閉器143に送り、これらを操作
して配電系統104の復旧を行う。この時、復旧制御部115
は、メモリ111に種々の事故情報と共に格納されている
停電前送電設備の情報を読み出して用いることができ、
復旧対象を正しく認識して、配電系統の事故復旧操作を
的確に実施できる。
The recovery control unit 115 communicates with the memory 11 through the memory control unit 112.
The accident information is read from 1 and monitored, and when the end information of the accident recovery operation of the upper system 103 is written as the accident information, the accident recovery operation corresponding to the storage area is started. That is, the monitoring control information is
2 and the upper system 103 are relayed and sent to, for example, the main switch 142 and the related switch 143 of the distribution system 104, and these are operated to restore the distribution system 104. At this time, the recovery control unit 115
Can read and use the information of the power transmission equipment before the power failure stored in the memory 111 together with various accident information,
Recognition of the restoration target is correct, and the accident restoration operation of the distribution system can be performed accurately.

H.発明の効果 以上説明したように本発明の配電系統制御システム
は、配電線を接続または切断する開閉器を備えた配電系
統と、これに接続された上位系統と、この上位系統を監
視制御する上位システムとによって構成された電力系統
に接続し、上位システムから受け取った事故情報を各事
故ごとに記憶領域を確保して記憶する第1の記憶手段を
有し、この記憶手段の各記憶領域から読み出した事故情
報にもとづいて、その事故情報に対応する事故の復旧操
作を、開閉器を制御して実施する配電系統制御システム
において、 上位システムが送信するSV・TM情報から推定した線路
および開閉器の状態を表す状態情報を記憶する第2の記
憶手段と、配電線の停電発生時に、第2の記憶手段から
読み出した停電前の線路および開閉器の設備No.を、停
電前送電設備情報として、この配電線に対応する記憶領
域に記憶させる第3の記憶手段とを備え、事故が発生し
たときは、事故により停電となった配電線に対応する第
3の記憶手段の記憶領域から停電前送電設備情報を読み
出し、同じ事故に対応する第1の記憶手段の記憶領域に
関係する事故情報と共に記憶させる構成となっている。
H. Effects of the Invention As described above, the distribution system control system of the present invention includes a distribution system including a switch for connecting or disconnecting a distribution line, a higher system connected thereto, and monitoring and controlling the higher system. A first storage unit connected to a power system constituted by a higher-level system and configured to store accident information received from the higher-level system by securing a storage area for each accident. In the distribution system control system that controls the switch based on the accident information read out from the accident information based on the accident information, the line and switching estimated from the SV / TM information transmitted by the upper system A second storage means for storing state information indicating the state of the switch, and when a power failure occurs in the distribution line, the line number and the equipment number of the switch before the power failure read out from the second storage means are stored in the power failure. A third storage unit for storing as power transmission facility information in a storage area corresponding to the distribution line, wherein when an accident occurs, the third storage unit corresponding to the distribution line that has lost power due to the accident. The power transmission facility information before the power failure is read from the area and stored together with the accident information related to the storage area of the first storage means corresponding to the same accident.

従って、本発明の配電系統制御システムは、第1の記
憶手段の個々の事故に対応する記憶領域から停電前送電
設備情報を読み出すことによって、復旧対象を正しく認
識し、配電系統の事故復旧操作を的確に実施することが
できる。
Therefore, the distribution system control system of the present invention reads out the power transmission equipment information before the power failure from the storage area corresponding to each accident in the first storage means, thereby correctly recognizing the restoration target, and performing the accident restoration operation of the distribution system. It can be implemented accurately.

【図面の簡単な説明】[Brief description of the drawings]

第1図は本発明の一実施例の配電系統制御システムを備
えた電力系統を示すブロック図、 第2図は、同実施例において事故情報がいかに記憶され
るかを説明するための概念図、 第3図は同実施例において復旧対象設備情報がいかに記
憶されるかを説明するための概念図、 第4図は従来の配電系統制御システムを備えた電力系統
を示すブロック図である。 101…配電系統制御システム、106…通信線、110…事故
情報管理部、111、121、122…メモリ、112、123…メモ
リ制御部、113…情報検索部、114…情報抽出部、115…
復旧制御部、120…設備情報管理部、124…状態推定部。
FIG. 1 is a block diagram showing an electric power system including a distribution system control system according to an embodiment of the present invention. FIG. 2 is a conceptual diagram for explaining how accident information is stored in the embodiment. FIG. 3 is a conceptual diagram for explaining how restoration target facility information is stored in the embodiment, and FIG. 4 is a block diagram showing a power system including a conventional distribution system control system. 101 ... distribution system control system, 106 ... communication line, 110 ... accident information management unit, 111, 121, 122 ... memory, 112, 123 ... memory control unit, 113 ... information search unit, 114 ... information extraction unit, 115 ...
Recovery control unit, 120: Facility information management unit, 124: State estimation unit.

───────────────────────────────────────────────────── フロントページの続き (72)発明者 平井 英治 東京都府中市東芝町1番地 株式会社東 芝府中工場内 (72)発明者 庄司 正樹 東京都品川区大崎2丁目1番17号 株式 会社明電舎内 (56)参考文献 特開 昭64−43020(JP,A) 特開 昭63−217927(JP,A) 特開 昭63−316623(JP,A) (58)調査した分野(Int.Cl.6,DB名) H02J 3/00 - 5/00──────────────────────────────────────────────────続 き Continuing from the front page (72) Eiji Hirai, 1 Toshiba-cho, Fuchu-shi, Tokyo Inside the Toshiba Fuchu Plant Co., Ltd. (72) Masaki Shoji 2-1-1, Osaki, Shinagawa-ku, Tokyo Meidensha Co., Ltd. (56) References JP-A-64-43020 (JP, A) JP-A-63-217927 (JP, A) JP-A-63-316623 (JP, A) (58) Fields investigated (Int. Cl. 6 , DB name) H02J 3/00-5/00

Claims (1)

(57)【特許請求の範囲】(57) [Claims] 【請求項1】配電線を接続または切断する開閉器を備え
た配電系統と、これに接続された上位系統とによって構
成された電力系統に接続し、上記上位系統を監視制御す
る上位システムから受け取った事故情報を各事故ごとに
記憶領域を確保して記憶する第1の記憶手段を有し、こ
の記憶手段の上記記憶領域から読み出した上記事故情報
にもとづいて上記開閉器を制御し、上記配電系統の事故
復旧操作を実施する配電系統制御システムにおいて、 上記上位システムが送信する遠方監視制御情報から線路
および開閉器の状態を推定する状態推定手段と、 上記状態推定手段が推定した上記状態情報を記憶する第
2の記憶手段と、 上記配電線に停電が生じる以前の送電設備情報を記憶す
る第3の記憶手段と、 上記遠方監視制御情報をもとに上記配電線が停電したか
否かを判定する停電判定手段と、 この停電判定手段が上記配電線が停電したと判定したと
き、上記第2の記憶手段から停電となった配電線の停電
前の上記送電設備情報を読み出し、上記第3の記憶手段
の記憶領域に記憶させる第1の記憶制御手段と、 上記上位システムからの事故情報にもとづいて事故によ
り停電した配電線を特定する配電線識別手段と、 この配電線識別手段が特定する上記配電線に対応する上
記第3の記憶手段の記憶領域から停電前の上記送電設備
情報を読み出し、上記配電線を停電させた事故の事故情
報が記憶されている上記第1の記憶手段の記憶領域に書
き込む第2の記憶制御手段とを備えたことを特徴とする
配電系統制御システム。
The present invention relates to a distribution system having a switch for connecting and disconnecting a distribution line, and a distribution system connected to the distribution system. A first storage means for storing a storage area for each of the accidents for each of the accidents, and controlling the switch based on the accident information read from the storage area of the storage means; In a distribution system control system for performing a system accident recovery operation, a state estimating means for estimating a state of a line and a switch from the remote monitoring control information transmitted by the upper system, and the state information estimated by the state estimating means. Second storage means for storing; third storage means for storing power transmission equipment information before a power failure occurs in the distribution line; and power distribution based on the remote monitoring control information. Power outage determining means for determining whether or not the line has failed; and when the power failure determining means determines that the power distribution line has failed, transmitting the power before the power failure of the distribution line having failed from the second storage means. First storage control means for reading facility information and storing the read information in a storage area of the third storage means; distribution line identification means for specifying a distribution line that has been powered down due to an accident based on accident information from the higher-level system; The power transmission facility information before the power outage is read from the storage area of the third storage means corresponding to the distribution line specified by the distribution line identification means, and accident information of the accident that caused the power outage of the distribution line is stored. And a second storage control means for writing to the storage area of the first storage means.
JP2328138A 1990-11-28 1990-11-28 Distribution system control system Expired - Fee Related JP2807339B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP2328138A JP2807339B2 (en) 1990-11-28 1990-11-28 Distribution system control system

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP2328138A JP2807339B2 (en) 1990-11-28 1990-11-28 Distribution system control system

Publications (2)

Publication Number Publication Date
JPH04197034A JPH04197034A (en) 1992-07-16
JP2807339B2 true JP2807339B2 (en) 1998-10-08

Family

ID=18206925

Family Applications (1)

Application Number Title Priority Date Filing Date
JP2328138A Expired - Fee Related JP2807339B2 (en) 1990-11-28 1990-11-28 Distribution system control system

Country Status (1)

Country Link
JP (1) JP2807339B2 (en)

Also Published As

Publication number Publication date
JPH04197034A (en) 1992-07-16

Similar Documents

Publication Publication Date Title
CN116009926B (en) Remote upgrading method, device and system for relay protection device
JPH0514975A (en) Centralized monitor system
JP2807339B2 (en) Distribution system control system
JP2825640B2 (en) Distribution system control system
JPH0622473A (en) Uninterruptible power source
JP2807338B2 (en) Distribution system control system
JP2749442B2 (en) Distribution system control system
EP3598701B1 (en) Method and system for processing critical logic state
JP2807340B2 (en) Distribution system control system
JP2599772B2 (en) Remote monitoring and control device
CN114302409A (en) Emergency communication vehicle dispatching system
JPH08149582A (en) Remote monitor and control system
CN202713338U (en) Wireless scheduling command monitoring device and wireless scheduling command transmission system
JPH09507324A (en) Method for backing up or restoring data or information processing file, and apparatus for implementing the method
JP2956601B2 (en) Fault segmentation device for distribution system
CN110970995B (en) Transmission type management and control system for key indexes of safe operation of power grid
CN106445744B (en) A kind of locomotive energy consumption information back-up and synchronous method and system
JPS609328A (en) Disconnection detecting defect zone marking system
JPS5886825A (en) Accident zone detecting system for power distribution line
CN115001133B (en) Intelligent power-off and power-on switching operation method and system in traction power supply system
CN118075323B (en) Platform door communication module monitoring and control system and method
CN106528618A (en) Method, device and system for storing and querying data of power network monitoring system
KR20220072536A (en) Voltage management method and apparatus using train driving data recording system
JP2000278858A (en) Automatic section switch for distribution line
Zhang et al. Research on Remote Operation and Maintenance Technology of Substation Fault Recorder

Legal Events

Date Code Title Description
S531 Written request for registration of change of domicile

Free format text: JAPANESE INTERMEDIATE CODE: R313531

R350 Written notification of registration of transfer

Free format text: JAPANESE INTERMEDIATE CODE: R350

S111 Request for change of ownership or part of ownership

Free format text: JAPANESE INTERMEDIATE CODE: R313115

R350 Written notification of registration of transfer

Free format text: JAPANESE INTERMEDIATE CODE: R350

LAPS Cancellation because of no payment of annual fees