JP2704826B2 - Construction method of asphalt road with buried heating pipe - Google Patents

Construction method of asphalt road with buried heating pipe

Info

Publication number
JP2704826B2
JP2704826B2 JP16831793A JP16831793A JP2704826B2 JP 2704826 B2 JP2704826 B2 JP 2704826B2 JP 16831793 A JP16831793 A JP 16831793A JP 16831793 A JP16831793 A JP 16831793A JP 2704826 B2 JP2704826 B2 JP 2704826B2
Authority
JP
Japan
Prior art keywords
asphalt concrete
lower layer
plastic pipe
roadbed
asphalt
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
JP16831793A
Other languages
Japanese (ja)
Other versions
JPH06341107A (en
Inventor
武夫 福田
Original Assignee
三菱化学産資株式会社
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by 三菱化学産資株式会社 filed Critical 三菱化学産資株式会社
Priority to JP16831793A priority Critical patent/JP2704826B2/en
Publication of JPH06341107A publication Critical patent/JPH06341107A/en
Application granted granted Critical
Publication of JP2704826B2 publication Critical patent/JP2704826B2/en
Anticipated expiration legal-status Critical
Expired - Fee Related legal-status Critical Current

Links

Landscapes

  • Road Paving Structures (AREA)

Description

【発明の詳細な説明】DETAILED DESCRIPTION OF THE INVENTION

【0001】[0001]

【産業上の利用分野】本発明は融雪や凍結防止のための
加熱用プラスチックパイプを埋設したアスファルト道路
の施工方法の改良に関する。
BACKGROUND OF THE INVENTION 1. Field of the Invention The present invention relates to an improvement of an asphalt road construction method in which a heating plastic pipe for preventing snow melting and freezing is embedded.

【0002】[0002]

【従来の技術】路盤上に積雪や凍結の防止に用いられる
加熱用のプラスチックパイプが敷設されているアスファ
ルト道路の施工には、先ず、路盤上に金網を敷設し、こ
の金網上にプラスチックパイプを配管して固定した後、
路盤上に粗粒度のアスファルトコンクリートを供給し
て、プラスチックパイプを埋め込むようにしてアスファ
ルトコンクリートを敷き均し、これを輾圧してアスファ
ルトコンクリート下層を形成する。
2. Description of the Related Art When constructing an asphalt road on which a plastic pipe for heating used to prevent snow and freezing is laid on a roadbed, first, a wire mesh is laid on the roadbed, and a plastic pipe is placed on the wire mesh. After piping and fixing,
Coarse-grained asphalt concrete is supplied on a roadbed, and asphalt concrete is spread and leveled so as to embed a plastic pipe, and is compacted to form a lower layer of asphalt concrete.

【0003】次いで、アスファルトコンクリート下層上
に密粒度或いは細粒度のアスファルトコンクリートを供
給して敷き均した後、このアスファルトコンクリート上
層を輾圧するようにした方法が知られている(特開平4
−289301号公報参照)。ここで、粒度とは2.5
mm篩を通過した割合(%)で表わされ、粗粒度は20
〜35、密粒度は35〜50、細粒度は50〜80であ
る。
Next, a method is known in which dense or fine asphalt concrete is supplied and spread on the lower layer of asphalt concrete, and then the upper layer of asphalt concrete is compacted (Japanese Patent Laid-Open No. Hei 4 (1994)).
-289301). Here, the particle size is 2.5
mm, expressed as a percentage (%) that passed through a sieve.
35, the fine particle size is 35 to 50, and the fine particle size is 50 to 80.

【0004】[0004]

【発明が解決しようとする課題】上記のような方法によ
り形成されたアスファルト道路は、路盤上のアスファル
トコンクリート下層が多数の空隙を有する粗粒度の層で
あるため、熱伝導性に劣り、加熱道路として十分に機能
することができなくなるという問題のあることが判っ
た。そこで、本発明の目的は埋め込まれるプラスチック
パイプに変形等の不具合を生じさせないことは勿論のこ
と、路盤上に形成されるアスファルトコンクリート層の
熱伝導性が向上するように改良した加熱用パイプを埋設
したアスファルト道路の施工方法を提供することにあ
る。
The asphalt road formed by the above method is inferior in heat conductivity because the lower layer of asphalt concrete on the roadbed is a coarse-grained layer having a large number of voids. It was found that there was a problem that it could not function sufficiently. Therefore, an object of the present invention is to embed a heating pipe which is improved so as not to cause defects such as deformation in the embedded plastic pipe and to improve the thermal conductivity of the asphalt concrete layer formed on the roadbed. It is an object of the present invention to provide an asphalt road construction method.

【0005】[0005]

【課題を解決するための手段】上記目的を達成するため
に、本発明の特徴とする加熱用パイプを埋設したアスフ
ァルト道路の施工方法は、路盤上に金網を敷設し、この
金網上に加熱用のプラスチックパイプを配管して固定し
た後、そのプラスチックパイプを埋め込むようにして路
盤上に密粒度又は細粒度のアスファルトコンクリートを
供給し、これを敷き均して形成したアスファルトコンク
リート下層を1〜5屯の荷重下で予備的に輾圧した後、
10〜20屯の通常の荷重下で輾圧し、次いで、アスフ
ァルトコンクリート下層上に密粒度又は細粒度のアスフ
ァルトコンクリートを供給して敷き均した後、このアス
ファルトコンクリート上層を10〜20屯の通常の荷重
下で輾圧するものである。
In order to achieve the above object, a method of constructing an asphalt road having a heating pipe embedded therein, which is a feature of the present invention, comprises laying a wire mesh on a roadbed, and heating the wire mesh on the wire mesh. After the plastic pipe is fixed by piping, dense or fine asphalt concrete is supplied onto the roadbed so as to embed the plastic pipe, and the lower layer of asphalt concrete formed by spreading and spreading the asphalt concrete is 1 to 5 tons. After preliminarily pressing under the load of
Crushing is performed under a normal load of 10 to 20 tons, then dense or fine asphalt concrete is supplied and spread on the lower layer of asphalt concrete, and the upper layer of asphalt concrete is spread under a normal load of 10 to 20 tons. It is pressed below.

【0006】そして、上記アスファルトコンクリート下
層の予備的な輾圧の荷重を1〜5屯にした理由は、5屯
を超過すると、加熱用のプラスチックパイプは変形が著
しく大きくなり、流水抵抗の増大によって加熱媒体が流
れなくなる問題とか、パイプ物性の低下を招く等の問題
が生ずる。また、1屯未満では輾圧する効果がない。
[0006] The reason why the preliminary compaction load of the lower layer of asphalt concrete is set to 1 to 5 tons is that if it exceeds 5 tons, the plastic pipe for heating becomes significantly deformed and the resistance to flowing water increases. There are problems such as a problem that the heating medium does not flow and a deterioration in physical properties of the pipe. Also, if it is less than 1 ton, there is no effect of compaction.

【0007】[0007]

【実施例】先ず、整地した地盤の上に小石や砂等を敷き
詰めて輾圧し、その上に均しアスファルトコンクリート
(以下、この項では単にアスコンという)を流して幅が
4mの路盤を造成する。そして、図1に示すように路盤
1上に格子状の熔接金網(径3.2mm、間隔150m
m)2を敷設し、その上にプラスチックパイプ(本例で
は内径が13mm、内厚が2mmの架橋ポリエチレン製
のパイプ)3を150mm間隔で蛇行状態に配管して固
定する。
First, pebbles, sand, etc. are spread over the ground that has been leveled, compacted, and asphalt concrete (hereinafter simply referred to as ascon in this section) is poured on the ground to form a 4 m wide roadbed. . Then, as shown in FIG. 1, a grid-like welded wire mesh (diameter 3.2 mm, interval 150 m
m) 2 is laid, and a plastic pipe (in this example, a pipe made of crosslinked polyethylene having an inner diameter of 13 mm and an inner thickness of 2 mm) 3 is fixed in a meandering state at intervals of 150 mm.

【0008】次いで、図2に示すように150℃前後に
加熱した密粒度(又は細粒度)のアスコンを路盤1上に
供給し、プラスチックパイプ3が埋め込まれるように敷
き均してアスコン下層4を形成する。このアスコン下層
4上を適当な輾圧機械により1〜5屯の輾圧荷重で輾圧
(一次予備輾圧工程)した後、マカダムローラ及び又は
タイヤローラ等により10〜20屯の輾圧荷重で輾圧す
る(一次輾圧工程)。
Next, as shown in FIG. 2, densely-grained (or fine-grained) ascon heated to about 150 ° C. is supplied onto the roadbed 1 and spread so that the plastic pipes 3 are embedded to form the ascon lower layer 4. Form. After the ascon lower layer 4 is rolled with a rolling load of 1 to 5 tons by a suitable rolling machine (primary pre-rolling process), it is rolled with a macadam roller and / or a tire roller at a rolling load of 10 to 20 tons. Rolling (primary rolling process).

【0009】上記アスコン下層4が十分に冷却された
後、図3に示すようにアスコン下層4上にアスファルト
フィニッシャーによって180℃に加熱した密粒度(又
は細粒度)のアスコンを供給して敷き均し、その後で、
このアスコン上層5をマカダムローラ及び又はタイヤロ
ーラ等により10〜20屯の輾圧荷重で輾圧し(二次輾
圧工程)、舗装工事を完了して道路を造成する(アスコ
ン下層4の厚さ40mm、アスコン上層5の厚さ30m
m)。
After the above-mentioned ascon lower layer 4 is sufficiently cooled, dense assorted (or fine-grain) ascon heated to 180 ° C. by an asphalt finisher is supplied onto the ascon lower layer 4 as shown in FIG. ,after,
The ascon upper layer 5 is rolled with a macadam roller and / or a tire roller with a rolling load of 10 to 20 tons (secondary rolling step), and the pavement is completed to form a road (thickness of the ascon lower layer 4 is 40 mm). , Thickness of Ascon upper layer 5 30m
m).

【0010】この施工方法においては、一次輾圧工程で
のプラスチックパイプ3を保護する目的で、供給された
アスコンを敷き均すにはスコップ等を用いて手作業によ
り行なうのが好ましいが、プラスチックパイプ3を損傷
させる心配がなければ、上記アスコンは適当な敷き均し
機械を用いて供給してもよい。また、この施工方法の実
施に際しては、プラスチックパイプの変形を抑制する目
的でアスコンが供給される前にプラスチックパイプ3の
中に冷却媒体(例えば、20℃の水道水)を流し、パイ
プ内を0.05〜5kg/cm好ましくは0.5〜3
kg/cmの加圧状態に保持しておくのがよい。
In this construction method, in order to protect the plastic pipe 3 in the primary pressing step, the supplied ascon is preferably spread by hand using a scoop or the like. If there is no fear of damaging 3, the ascon may be supplied using a suitable spreading machine. Further, when this construction method is carried out, a cooling medium (for example, tap water at 20 ° C.) is flowed through the plastic pipe 3 before ascon is supplied to suppress deformation of the plastic pipe, and the inside of the pipe is reduced to 0 °. 0.05-5 kg / cm 2, preferably 0.5-3
It is preferable to keep the pressurized state of kg / cm 2 .

【0011】なお、アスコン下層側が粗粒度のものによ
り形成される比較例と、アスコン下層側が密粒度のもの
により形成される本発明方法の実施例によるプラスチッ
クパイプの変形を扁平度(%)により測定した結果は、
比較例では3.1、実施例では3.0であって差が殆ど
ない。また、道路完成後で30℃の温水を9.2リット
ル/分の流量で通水し、3時間後の路面表面温度を測定
した結果(外気温度は−2℃)は比較例では2.9℃、
実施例では3.7℃であって、本発明方法ではアスコン
層の熱伝導性を向上できることが判った。
The deformation of the plastic pipe according to the embodiment of the method of the present invention in which the lower layer of the ascon is formed of a coarse particle and the deformation of the plastic pipe according to the embodiment of the present invention in which the lower layer of the ascon is formed of a fine particle are measured by flatness (%). The result
The difference is 3.1 in the comparative example and 3.0 in the example, and there is almost no difference. After completion of the road, hot water of 30 ° C. was passed at a flow rate of 9.2 liters / minute, and the surface temperature of the road surface after 3 hours (outside air temperature was −2 ° C.) was 2.9 in the comparative example. ℃,
In Example, the temperature was 3.7 ° C., and it was found that the method of the present invention can improve the thermal conductivity of the ascon layer.

【0012】[0012]

【発明の効果】本発明は上記の如くであって、アスファ
ルトコンクリートの打ち込み作業を下層と上層の二段階
に分けて行ない、下層に対しては輾圧荷重を可能な限り
小さくした予備的な輾圧を行なっているので、プラスチ
ックパイプの不当な物性劣化や変形を防止できて、道路
完成後の加熱用パイプの使用に支障を来たす心配がな
い。また、アスファルトコンクリートの打ち込みには何
れの施工段階でも密粒度又は細粒度のアスファルトコン
クリートが用いられているので、路盤上に形成されるア
スファルトコンクリート層の熱伝導性が向上し、加熱機
能を十分に発揮できるアスファルト道路を提供できる。
The present invention is as described above, and the asphalt concrete driving operation is performed in two stages of a lower layer and an upper layer, and a preliminary piling is performed on the lower layer by minimizing the compaction load. Since the pressure is applied, the plastic pipes can be prevented from being unduly deteriorated in physical properties and deformed, and there is no fear that the use of the heating pipe after the completion of the road will be hindered. In addition, as the asphalt concrete is driven, dense or fine-grained asphalt concrete is used at any construction stage, so the thermal conductivity of the asphalt concrete layer formed on the roadbed is improved, and the heating function is sufficiently improved. Providing asphalt roads that can be used.

【図面の簡単な説明】[Brief description of the drawings]

【図1】路盤上にプラスチックパイプを配管固定した本
発明方法の初期段階を示す断面図である。
FIG. 1 is a sectional view showing an initial stage of the method of the present invention in which a plastic pipe is fixed on a roadbed.

【図2】本発明方法の中間段階を示す断面図である。FIG. 2 is a sectional view showing an intermediate stage of the method of the present invention.

【図3】本発明方法の最終段階を示す断面図である。FIG. 3 is a sectional view showing the final stage of the method of the present invention.

【符号の説明】[Explanation of symbols]

1は路盤 2は金網 3はプラスチックパイプ 4はアスファルトコンクリート下層 5はアスファルトコンクリート上層 1 is roadbed 2 is wire mesh 3 is plastic pipe 4 is asphalt concrete lower layer 5 is asphalt concrete upper layer

Claims (1)

(57)【特許請求の範囲】(57) [Claims] 【請求項1】 路盤上に金網を敷設し、この金網上に加
熱用のプラスチックパイプを配管して固定した後、その
プラスチックパイプを埋め込むようにして路盤上に密粒
度又は細粒度のアスファルトコンクリートを供給し、こ
れを敷き均して形成したアスファルトコンクリート下層
を1〜5屯の荷重下で予備的に輾圧した後、10〜20
屯の通常の荷重下で輾圧し、次いで、アスファルトコン
クリート下層上に密粒度又は細粒度のアスファルトコン
クリートを供給して敷き均した後、このアスファルトコ
ンクリート上層を10〜20屯の通常の荷重下で輾圧す
ることを特徴とする加熱用パイプを埋設したアスファル
ト道路の施工方法。
1. A wire net is laid on a roadbed, and a heating plastic pipe is laid on the wire net and fixed. Then, asphalt concrete of fine or fine grain size is laid on the roadbed so as to embed the plastic pipe. After the lower layer of asphalt concrete formed by spreading and flattening this was preliminarily pressed under a load of 1 to 5 tons,
Rolling under the normal load of ton, then supplying dense or fine-grained asphalt concrete on the lower layer of asphalt concrete and laying it down, then rolling the upper layer of asphalt concrete under the normal load of 10 to 20 tons. A method for constructing an asphalt road in which a heating pipe is buried.
JP16831793A 1993-06-01 1993-06-01 Construction method of asphalt road with buried heating pipe Expired - Fee Related JP2704826B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP16831793A JP2704826B2 (en) 1993-06-01 1993-06-01 Construction method of asphalt road with buried heating pipe

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP16831793A JP2704826B2 (en) 1993-06-01 1993-06-01 Construction method of asphalt road with buried heating pipe

Publications (2)

Publication Number Publication Date
JPH06341107A JPH06341107A (en) 1994-12-13
JP2704826B2 true JP2704826B2 (en) 1998-01-26

Family

ID=15865795

Family Applications (1)

Application Number Title Priority Date Filing Date
JP16831793A Expired - Fee Related JP2704826B2 (en) 1993-06-01 1993-06-01 Construction method of asphalt road with buried heating pipe

Country Status (1)

Country Link
JP (1) JP2704826B2 (en)

Families Citing this family (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR101241342B1 (en) * 2010-02-02 2013-03-08 롯데건설 주식회사 Snow melting road paving structure and snow melting road paving method
CN106149500B (en) * 2015-04-16 2018-06-29 王海有 A kind of construction method of cement emulsified asphalt mortar penetration type half-flexible pavement
JP5824590B1 (en) * 2015-05-02 2015-11-25 株式会社柿本商会 Road surface snow melting structure construction method

Also Published As

Publication number Publication date
JPH06341107A (en) 1994-12-13

Similar Documents

Publication Publication Date Title
EP0488305B1 (en) Method for constructing asphalted road having heating pipe laid thereunder
CN106192698A (en) Highway pavement rubblization treatment recycling paving construction structure and technology
JP2704826B2 (en) Construction method of asphalt road with buried heating pipe
US20060204332A1 (en) Method for repairing holes in pavement
JP2852980B2 (en) Construction method of asphalt road with buried heating pipe
JP3478431B2 (en) Road structure and construction method
JP2797149B2 (en) Laying method of asphalt pavement heating pipe
CN202401363U (en) Flaky or blocky stone ventilated roadbed of expressway in frozen soil region
CN115478458A (en) Integrated structure of white-to-black road surface of existing road bed block stone retaining wall and construction method
KR101986242B1 (en) Structure for Road having Smart Snow Melting Pavement, and Constructing Method thereof
JP3066411B2 (en) Non-slip pavement material and pavement method for non-slip road using the same
CN112411305A (en) Road solid waste mobile crushing and in-situ cold recycling construction method
CN111733650A (en) Cooling construction method for corrugated steel pipe of frozen soil roadbed
JPH11280010A (en) Paving method of asphalt pavement road, precast asphalt floor board and manufacture thereof
JP2004197337A (en) Road base structure
JP3209717B2 (en) Pavement road surface construction method
CN213233004U (en) Municipal works road laying structure
JP5824590B1 (en) Road surface snow melting structure construction method
JPH0551912A (en) Repairing method for paved road and structure thereof
JP2003064617A (en) Execution method of road heating and road heating apparatus
CN213538592U (en) Municipal works road laying structure
JP2014202001A (en) Concrete pavement structure
CN218478977U (en) White-to-black road surface integrated structure of existing road bed block stone retaining wall
JP2003333717A (en) Normal-temperature construction method of conduit for protecting buried cable
JP3094312U (en) Paving structures

Legal Events

Date Code Title Description
R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

FPAY Renewal fee payment (prs date is renewal date of database)

Year of fee payment: 10

Free format text: PAYMENT UNTIL: 20071009

FPAY Renewal fee payment (prs date is renewal date of database)

Year of fee payment: 11

Free format text: PAYMENT UNTIL: 20081009

LAPS Cancellation because of no payment of annual fees