JP2691473B2 - Tunnel lining Concrete continuous pouring method - Google Patents

Tunnel lining Concrete continuous pouring method

Info

Publication number
JP2691473B2
JP2691473B2 JP2305737A JP30573790A JP2691473B2 JP 2691473 B2 JP2691473 B2 JP 2691473B2 JP 2305737 A JP2305737 A JP 2305737A JP 30573790 A JP30573790 A JP 30573790A JP 2691473 B2 JP2691473 B2 JP 2691473B2
Authority
JP
Japan
Prior art keywords
concrete
frame
lining concrete
tunnel
lining
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
JP2305737A
Other languages
Japanese (ja)
Other versions
JPH04176997A (en
Inventor
睦彦 木村
義昭 石田
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Sato Kogyo Co Ltd
Original Assignee
Sato Kogyo Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Sato Kogyo Co Ltd filed Critical Sato Kogyo Co Ltd
Priority to JP2305737A priority Critical patent/JP2691473B2/en
Publication of JPH04176997A publication Critical patent/JPH04176997A/en
Application granted granted Critical
Publication of JP2691473B2 publication Critical patent/JP2691473B2/en
Anticipated expiration legal-status Critical
Expired - Fee Related legal-status Critical Current

Links

Description

【発明の詳細な説明】 〔産業上の利用分野〕 本発明は、機械掘削によるトンネル施工において、そ
の掘削と覆工コンクリート打設を、同時併行的に行い得
る覆工コンクリートの連続打設装置に関する。
Description: TECHNICAL FIELD The present invention relates to a continuous lining concrete pouring device capable of simultaneously excavating and lining concrete in a tunnel construction by mechanical excavation. .

〔従来の技術〕[Conventional technology]

従来、トンネル施工における覆工コンクリートの打設
は、トンネル掘削機などにより掘削完了後に、または掘
削切羽よりかなり後方位置で、ノンテレスコピック型ス
チールフォーム、ニールドビーム型スチールフォーム、
テレスコピック型スチールフォーム、バラセントルなど
の移動式、もしくは分割式型枠を用い、順次1ブロック
ごとにコンクリートを打設する方法が採用されていた。
Conventionally, when placing lining concrete in tunnel construction, after completion of excavation with a tunnel excavator or at a position considerably behind the excavation face, non-telescopic type steel foam, kneaded beam type steel foam,
A method of placing concrete in blocks one by one using a movable or split form such as telescopic steel foam or Baracentre was adopted.

しかし、これらの覆工方法は、1回の打設長が6〜12
m程度であり、コンクリートの養生および打設サイクル
上の理由により、1日1回の打設が限度であり、到底施
工の迅速化は望めず、また立坑なども多くなることによ
り道路障害等の問題を誘発し、さらに掘削からコンクリ
ート打設まで長時間放置するため、トンネルの支保を確
実に行い地山の安定を図らねばならないなどの問題点を
有していた。
However, in these lining methods, one casting length is 6 to 12
It is about m, and due to reasons such as concrete curing and placing cycle, the placing is limited to once a day, it is not possible to speed up the construction at all, and due to the increase in vertical shafts, road obstacles etc. Since it causes a problem and is left unattended for a long time from excavation to concrete placement, it has problems such as ensuring the support of the tunnel and stabilizing the ground.

一方、近年施工の迅速化・省力化の要請の下、セグメ
ント工法が多用されているが、本工法は地表沈下を避け
ることが難しく、またセグメント自体が高価なため、そ
の組立費および裏込注入費などを含めると全体工事費の
半分を占める場合もあり、工事費が割高となるため経済
的でないなどの問題点を有する。
On the other hand, in recent years, the segment construction method has been widely used due to the demand for faster construction and labor saving, but this construction method makes it difficult to avoid subsidence and the segment itself is expensive. Including the cost, it may occupy half of the total construction cost, and the construction cost becomes expensive, which is not economical.

近年、上述した問題点を解決すべく、ELC工法(Extru
ded Concrete Lining工法)が注目を浴びている。前記E
LC工法は、我が国では「直打ちコンクリート工法」など
とも呼ばれ、その工法は、シールド機により掘削する後
方で、この掘削と併行して内型枠を組立て、フレッシュ
コンクリートに圧縮力を与えながら打設し、地山に密着
した覆工コンクリートを構築するものである。
In recent years, the ELC method (Extru
ded Concrete Lining method) is attracting attention. The E
In Japan, the LC method is also called the "direct-casting concrete method". In this method, the inner formwork is assembled in parallel with this excavation behind the excavation by the shield machine, and it is applied while applying compressive force to the fresh concrete. It is intended to build lining concrete that is closely attached to the ground.

〔発明が解決しようとする課題〕[Problems to be solved by the invention]

しかしながら、前記ELC工法は、前述したような掘削
完了後等において順次1ブロックごとにコンクリートを
打設する方法や、セグメント工法に比べ、地表沈下を抑
え、施工速度の向上および工費節減を図り得るものの、
1ストロークの掘削後、最後列のコンクリート打設完了
地点の内型枠を解体し、最前列まで移動して組立て、前
記1ストリーク分のコンクリート打設を行うため、この
解体・移動・組立ての一連の作業を1ストローク掘削毎
に行わねばならず、その作業に手間を要するとともに、
その施工速度にも一定の限界がある。
However, the ELC method can suppress the surface subsidence, improve the construction speed, and reduce the construction cost compared to the method of placing concrete one by one block after the completion of excavation as described above or the segment construction method. ,
After excavating one stroke, dismantle the inner formwork at the final row of concrete pouring completion point, move to the front row and assemble, and perform concrete pouring for one streak, so this sequence of dismantling, moving and assembling Must be performed for each stroke excavation, which requires time and effort,
There is a certain limit to the construction speed.

そこで本発明の主たる目的は、トンネル掘削と同時併
行的に地山に密着した覆工コンクリートを連続的に打設
し得るとともに、その際の型枠作業に要する手間と時間
を簡略化し、施工の迅速化並びに省力化を図った覆工コ
ンクリートの連続打設工法を提供するものである。
Therefore, the main object of the present invention is to be able to continuously pour lining concrete in close contact with the ground in parallel with tunnel excavation, simplify the time and effort required for the formwork at that time, and implement the construction. It is intended to provide a continuous pouring method for lining concrete which is speedy and labor-saving.

〔課題を解決するための手段〕[Means for solving the problem]

前記課題は、トンネル掘削機の坑口側に、覆工コンク
リート打設・加圧装置、スライド型枠装置、および反力
受グリップ装置を、この順に有し、 前記覆工コンクリート打設・加圧装置は、 掘削面の支保のための外周面枠と、この外周面枠の一
部または全部を掘削面に押圧させて自身を掘削面に対し
て固定する固定支持手段と、覆工コンクリート打設時の
側型枠として機能し、打設された覆工コンクリートをそ
の打継端面から加圧するためにトンネル方向に進退自在
に駆動され、かつ掘削断面形状と実質的に同一の外径お
よび打設覆工コンクリート厚に相当する部材幅を有する
環状枠材と、この環状枠材のトンネル坑口側面およびそ
の反対側面に連通するコンクリート打設口とを備え、 前記スライド型枠装置は、 前記覆工コンクリート打設・加圧装置に連行して、前
記環状枠材の枠材内面に内接し得る外径を有し、覆工コ
ンクリート打設時には前記環状枠材とともに覆工コンク
リート打設用型枠となる内型枠用外周面枠と、この外周
面枠の一部または全部を既設の巻立コンクリート内面に
押圧させて自身を既設の巻立コンクリート内面に固定す
るための固定支持手段とを備え、 前記反力受グリップ装置は、 前記スライド型枠装置に対してスライド用ジャッキに
より連結され、前記スライド型枠装置の外周面枠と実質
的に同一外径の外周面枠を有するとともに、この外周面
枠の一部または全部を既設の巻立コンクリート内面に押
圧させて自身を既設の巻立コンクリート内面に固定する
ための固定支持手段とを備えており、 前記トンネル掘削機と前記覆工コンクリート打設・加
圧装置とを、別体としたトンネル覆工コンクリートの連
続打設装置を用い、 シールド機によるトンネル掘削に続き、前記覆工コン
クリート打設・加圧装置、スライド型枠装置および反力
受グリップ装置の順に連行させ、前記シールド機による
1ストローク掘削毎に、 前記覆工コンクリート打設・加圧装置を掘削面に対し
固定支持し、その環状枠材をトンネル切羽方向へ移動さ
せるとともに、これに追従して、前記環状枠材に前記ス
ライド型枠装置の内型枠用外周面枠が嵌挿状態となるよ
うに移動し、これにより前記環状枠材と内型枠用外周面
枠とによって閉塞される空間を形成し、この空間に前記
環状枠材の打設口より覆工コンクリートを供給するとと
もに、硬化までの間これを加圧状態に保持しつつ、覆工
コンクリートを連続的に形成するようにすることで解決
できる。
The subject has a lining concrete pouring / pressurizing device, a slide form device, and a reaction force receiving grip device in this order on the pit side of a tunnel excavator. Is an outer peripheral surface frame for supporting the excavation surface, fixed support means for pressing a part or all of the outer peripheral surface frame against the excavation surface to fix itself to the excavation surface, and when placing lining concrete Functioning as a side formwork of the concrete, driven to move forward and backward in the tunnel direction in order to press the poured lining concrete from its connecting end face, and the outer diameter and casting cover that are substantially the same as the excavated cross-sectional shape. An annular frame member having a member width corresponding to the thickness of the worked concrete, and a concrete pouring port communicating with the tunnel pit side surface and the opposite side surface of the annular frame material, wherein the slide formwork device comprises the lining concrete pouring Installation An inner formwork that is entrained by a pressurizing device and has an outer diameter capable of being inscribed in the inner surface of the frame material of the annular frame material, and becomes the formwork for the lining concrete pouring together with the annular frame material when the lining concrete is placed And a fixing support means for fixing a part or all of the outer peripheral surface frame to the existing inner surface of the rolled concrete by fixing the inner peripheral surface of the outer peripheral frame to the existing inner surface of the rolled concrete. The grip device is connected to the slide form frame device by a sliding jack, has an outer peripheral face frame having substantially the same outer diameter as the outer peripheral face frame of the slide form frame device, and a part of the outer peripheral face frame. Or a fixed support means for pressing the whole to the existing inner surface of the rolled concrete to fix itself to the inner surface of the existing rolled concrete, the tunnel excavator and the lining concrete pouring / pressurizing device. Using a continuous tunnel lining concrete pouring device as a separate unit, following tunnel excavation by a shield machine, the lining concrete pouring / pressurizing device, slide formwork device, and reaction force receiving grip device are carried in this order. Then, the lining concrete placing / pressurizing device is fixedly supported on the excavation surface every one stroke excavation by the shield machine, and the annular frame material is moved in the tunnel face direction, and following this, The inner frame outer peripheral surface frame of the slide mold device is moved so as to be fitted into the annular frame member, thereby forming a space closed by the annular frame member and the inner mold outer peripheral surface frame. Forming and supplying the lining concrete from the casting opening of the annular frame material to this space, while maintaining it under pressure until hardening, to form the lining concrete continuously You can solve it by doing.

〔作用〕[Action]

本発明においては、覆工コンクリート連続打設装置を
構成する各装置は、全て、トンネル掘削面もしくは覆工
コンクリート内壁に内接する外径形状を有する。したが
って、各装置が地山安定に資するとともに、各装置自体
も安定化する。
In the present invention, all the devices constituting the lining concrete continuous casting device have an outer diameter shape that is inscribed in the tunnel excavation surface or the lining concrete inner wall. Therefore, each device contributes to stable ground and each device itself is also stabilized.

先ず、覆工コンクリート打設・加圧装置は、外周面枠
の一部または全部を掘削面に押圧させて自身を掘削面に
対して固定する固定支持手段を備えるため、覆工コンク
リートの打設時の安定および加圧時の反力点とすること
ができる。さらに、たとえばジャッキなどによりトンネ
ル出側方向に向けて進退自在に構成され、掘削断面形状
と実質的に同一の外径と打設覆工コンクリート厚に相当
する部材幅を有する環状枠材とを備える。したがって、
覆工コンクリートの打設時には側型枠として機能し、打
設後から硬化までは覆工コンクリートの打継端面より加
圧することができる。なお、前記覆工コンクリート打設
・加圧装置が前進する際には、前記環状枠材を覆工コン
クリートの打継端面に押し当て、進出操作を行うと、反
作用的に前進することができる。
First, since the lining concrete pouring / pressurizing device is provided with a fixing support means for pressing a part or all of the outer peripheral surface frame against the excavation surface to fix itself to the excavation surface, It can be used as a stable point and a reaction point at the time of pressurization. Further, it is provided with an annular frame member that is configured to be movable back and forth toward the tunnel exit side, for example, by a jack, and has an outer diameter substantially the same as the excavation cross-sectional shape and a member width corresponding to the thickness of the concrete for the cast lining. . Therefore,
It functions as a side form at the time of placing the lining concrete, and pressure can be applied from the joining end surface of the lining concrete after the placing and until hardening. In addition, when the lining concrete pouring / pressurizing device moves forward, the annular frame material is pressed against the connecting end face of the lining concrete and an advancing operation is performed, so that the lining concrete can move forward in a reactive manner.

そして、前記環状枠材のトンネル坑口側面およびその
反対側面に連通するコンクリート打設口を備えることに
よって、前記環状枠材と、この環状枠材の内壁に内接し
得る外径を有し、後述の移動操作によってトンネル方向
に移動自在に駆動される内型枠用外周面枠と、前回打設
時の覆工コンクリートの打継端面とにより順次形成され
る空間に、前記コンクリート打設口より覆工コンクリー
トを供給することができる。このため、連続的に覆工コ
ンクリートを打設できる。
Then, by providing a concrete pouring port that communicates with the tunnel pit side surface of the annular frame material and the opposite side surface thereof, the annular frame material has an outer diameter that can be inscribed in the inner wall of the annular frame material, and will be described later. A lining is made from the concrete pouring port in the space that is sequentially formed by the outer peripheral frame for the inner formwork, which is movably driven in the tunnel direction by the moving operation, and the connecting end face of the lining concrete at the time of the last pouring. Can supply concrete. Therefore, the lining concrete can be continuously poured.

前記スライド型枠装置と反力受グリップ装置とは、共
に外周面枠の一部または全部を既設の巻立コンクリート
内面に押圧させて自身を既設の巻立コンクリート内面に
固定するための固定支持手段を備えるとともに、相互に
トンネル方向にスライド用ジャッキにより連結されてい
るため、一方が前進する際には他方は固定され、他方が
前進する際には一方が固定されることによって、相互に
固定・移動を繰り返して覆工コンクリート打設位置まで
漸次移動し得る。このため、型枠作業を簡略化すること
ができる。また、前記両装置は、既設の覆工コンクリー
ト内壁に内接する外周面枠を有するため、コンクリート
硬化までの間、崩壊などがないようにこれを保持する。
The slide form frame device and the reaction force receiving grip device both have a fixing support means for fixing a part or the whole of the outer peripheral surface frame to the existing inner surface of the rolled concrete by pressing it against the inner surface of the existing rolled concrete. In addition, since they are connected to each other by a sliding jack in the tunnel direction, when one moves forward, the other is fixed, and when the other moves forward, one is fixed, thereby fixing each other. The movement can be repeated to gradually move to the lining concrete pouring position. Therefore, it is possible to simplify the formwork work. Further, both of the above devices have an outer peripheral surface frame that is inscribed in the existing inner wall of the lining concrete, so that they are held until the concrete hardens so as not to collapse.

なお、前記スライド型枠装置は、内型枠機能を有する
とともに、自身の固定保持機能とを備えるため、これを
内型枠用外周面枠部と自身を掘削面に固定するためのグ
リップ部とに分離し、相互にトンネル方向にスライドジ
ャッキにより連結してもよい。
In addition, the slide formwork device has an inner formwork function and also has a fixing and holding function of itself, so that the slide formwork device has an outer peripheral surface frame part for the inner formwork and a grip part for fixing itself to the excavation surface. And may be connected to each other by a slide jack in the tunnel direction.

トンネル覆工コンクリートの構築に際しては、先ず、
トンネル掘削機による掘削に続き、前記覆工コンクリー
ト打設・加圧装置、スライド型枠装置および反力受グリ
ップ装置の順に連行させる。
When constructing tunnel lining concrete, first
Following the excavation by the tunnel excavator, the lining concrete placing / pressurizing device, the slide formwork device and the reaction force receiving grip device are carried in this order.

そして、前記トンネル掘削機による1ストローク掘削
が終了する度に、 前記覆工コンクリート打設・加圧装置を掘削面に対し
固定支持して、打設コンクリートを加圧する際の反力点
となるようにする。
Then, each time one-stroke excavation by the tunnel excavator is completed, the lining concrete pouring / pressurizing device is fixedly supported on the excavation surface so as to become a reaction force point when pressuring the pouring concrete. To do.

次に、前記覆工コンクリート打設・加圧装置の環状枠
材をトンネル切羽方向へ移動させるとともに、これに追
従して、前記環状枠材に前記スライド型枠装置の内型枠
用外周面枠が嵌挿状態となるように移動する。これによ
り前記環状枠材と内型枠用外周面枠とによって閉塞され
る空間を形成することができる。そして、この空間に前
記環状枠材の打設口より覆工コンクリートを供給し、硬
化までの間これを加圧状態に保持することによって、地
山に密着した覆工コンクリートを連続的に形成するよう
にすることができる。
Next, the annular frame material of the lining concrete pouring / pressurizing device is moved in the tunnel face direction, and following this, the annular frame material is attached to the outer peripheral surface frame for the inner formwork of the slide formwork device. Move so as to be in the inserted state. Thereby, a space closed by the annular frame member and the outer peripheral frame for the inner mold can be formed. Then, the lining concrete is supplied to this space from the pouring opening of the annular frame material and is kept under pressure until it is hardened, thereby continuously forming the lining concrete in close contact with the natural ground. You can

また、トンネル掘削機による1ストローク掘削毎の覆
工コンクリートの打設を、環状枠材と内型枠用外周面枠
の移動による閉塞空間の形成と、覆工コンクリートの供
給との繰返しにより行う分割打設とすれば、地山の緩み
を防止する上で好ましい。
In addition, division is performed by placing the lining concrete for each stroke excavation by the tunnel excavator by repeatedly forming the closed space by moving the annular frame material and the outer peripheral frame for the inner formwork and supplying the lining concrete. Placing is preferable for preventing loosening of the ground.

本発明においては、前述の如く、トンネル掘削と同時
併行的に覆工コンクリートを連続的に打設でき、また、
型枠の解体・設置作業が実質的に省かれるため、加工速
度が速く作業の効率化および省力化を図ることができ
る。
In the present invention, as described above, the lining concrete can be continuously placed in parallel with the tunnel excavation, and
Since the work of disassembling and installing the formwork is substantially omitted, the processing speed is fast and the work efficiency and labor can be reduced.

〔発明の具体的な構成〕[Specific configuration of the invention]

以下、本発明を図面に示す具体例に基づき詳説する。 Hereinafter, the present invention will be described in detail based on specific examples shown in the drawings.

本発明工法に係る覆工コンクリート連続打設装置は、
第1図に示されるように、覆工コンクリート打設・加圧
装置1(以下、単に打設装置という)と前スライド型枠
2と後スライド型枠3と反力受けグリップ装置4からな
る。前記打設装置1は他の装置と分離され、前記前スラ
イド型枠2と後スライド型枠3とは、第1スライドジャ
ッキ群5、5…で連結され、前記後スライド型枠3と反
力受けグリップ装置4とは第2スライドジャッキ群6、
6…により連結されている。
The lining concrete continuous pouring device according to the present invention method,
As shown in FIG. 1, it comprises a lining concrete pouring / pressurizing device 1 (hereinafter, simply referred to as a pouring device), a front slide mold 2, a rear slide mold 3 and a reaction force receiving grip device 4. The driving device 1 is separated from other devices, and the front slide form frame 2 and the rear slide form frame 3 are connected by a first slide jack group 5, 5, ... The receiving grip device 4 is the second slide jack group 6,
6 ... are connected.

前記打設装置1は、第2図横断面図に示されるよう
に、鋼板、角型鋼、溝型鋼などよりなる円形リング10に
対しその外周に円形面枠11が周設されており、その内方
に前記円形リング10に固設されたグリップ支持架台16が
設けられ、このグリップ支持架台16上に打設装置1の固
定支持手段たるグリップ装置13が固設されている。前記
グリップ装置13は、両側方向に伸縮するシリンダー軸13
a、13aを有し、その先端に掘削面を押圧するグリッパ1
4、14を備えている。
As shown in the transverse cross-sectional view of FIG. 2, the casting device 1 has a circular ring frame 10 made of steel plate, square steel, grooved steel, etc., and a circular surface frame 11 provided around the circular ring 10. A grip support base 16 fixed to the circular ring 10 is provided on one side, and a grip device 13 as a fixed support means of the driving device 1 is fixedly mounted on the grip support base 16. The grip device 13 includes a cylinder shaft 13 that expands and contracts in both directions.
A gripper 1 that has a and 13a and presses the excavation surface at its tip.
It has 4 and 14.

また、前記円形リング10には、円周方向に適宜の間隔
をおいて、トンネル後方側に向けて進退するプレスジャ
ッキ12、12…が設けられるとともに、そのジャッキ先端
には、コンクリート打設時の型枠側板を構成するととも
に、打設コンクリートをトンネル方向に加圧するため
の、環状枠材たるプレスリング17が設けられている。
Further, the circular ring 10 is provided with press jacks 12, 12 ... Which are moved forward and backward toward the rear side of the tunnel at appropriate intervals in the circumferential direction, and the tip of the jack is used for concrete pouring. A press ring 17, which is an annular frame material, is provided for constituting the form frame side plate and for pressing the poured concrete in the tunnel direction.

前記打設装置1の天端には、コンクリート打設のため
の打設口18を有し、図示されないコンクリートポンプに
より送給されるコンクリートがロータリーバルブなどの
コンクリート分配機を介して適切な圧力をもって、コン
クリート打設が行えるようになっている。なお、前記グ
リップ装置13の周囲に設けられたジャッキ15、15…は掘
削7と連結され、この打設装置1を牽引するためのもの
である。
A pouring port 18 for pouring concrete is provided at the top end of the pouring device 1, and concrete fed by a concrete pump (not shown) has an appropriate pressure through a concrete distributor such as a rotary valve. , Concrete can be placed. The jacks 15, 15, ... Provided around the grip device 13 are connected to the excavation 7 and are for pulling the placing device 1.

前記前スライド型枠2は、詳細には第3図横断面図に
示されるように、円形リング20、20…の外周に円形面枠
21が周設され、その内方に矩形フレーム22を有してい
る。前記円形リング21、21…の円周方向の適所をピン結
合とするとともに、上方部分を分離して、前記矩形フレ
ーム22の下方一端を前記円形リング20と固着し、その側
方をターンバックル24、24を介して前記円形リング20と
連結して、一定範囲内において円周方向に拡縮自在とな
っている。前記円形リング20の上方部分はジャーナルジ
ャッキ23、23を介して連結されており、高さ方向の調整
が可能であるとともに、折り畳める構造となっている。
なお、前記前スライド型枠2は、第1図の鎖線で示され
るように、プレスリング17に内接状態に嵌挿され、コン
クリート打設時の内型枠となるため、打設装置1のプレ
スリング17に嵌挿し得る外径形状に調整したならば、施
工中は基本的に固定とされる。
The front slide form frame 2 is, as shown in detail in the transverse sectional view of FIG. 3, a circular face frame on the outer circumference of the circular rings 20, 20.
21 is provided around and has a rectangular frame 22 inside thereof. The circular rings 21, 21 ... Are pin-coupled at appropriate places in the circumferential direction, the upper portion is separated, the lower end of the rectangular frame 22 is fixed to the circular ring 20, and the turn buckle 24 is provided on the side thereof. , 24 and is connected to the circular ring 20 via a ring 24, and is expandable and contractable in the circumferential direction within a certain range. The upper portion of the circular ring 20 is connected via journal jacks 23, 23, and the structure can be adjusted in the height direction and can be folded.
The front slide form 2 is inserted into the press ring 17 in an inscribed state as shown by the chain line in FIG. 1 and serves as an inner form at the time of placing concrete. Once adjusted to an outer diameter shape that can be fitted into the press ring 17, it is basically fixed during construction.

また、前スライド型枠2を、その前部と後部とに分割
し、たとえばこの2体を接続調整ボルトなどで接続し、
曲線部を施工する際には、前記接続調整ボルトで離間を
調整し、曲率を持たせるとともに、その隙間部分をパッ
キンなどで封止して、コンクリートの漏出防止、止水機
能を持たせるようにすれば、容易に曲線施工に対応させ
ることができる。
In addition, the front slide formwork 2 is divided into a front part and a rear part thereof, and these two bodies are connected by a connection adjusting bolt or the like,
When constructing a curved part, adjust the separation with the connection adjustment bolt to have a curvature, and seal the gap with packing etc. to prevent leakage of concrete and water stop function By doing so, it is possible to easily handle curved construction.

前記前スライド型枠2と第1スライドジャッキ群5、
5…をもって接続される後スライド型枠3は、第4図横
断面図にも示されるように、円形リング30、30…の外周
に円形面枠31が周設され、その円周方向の適所において
ピン結合とし、円形リングの端々をグリップジャッキ32
を介して連結することにより、前記グリップジャッキ32
の伸縮操作により円周方向に拡縮自在に構成し、後スラ
イド型枠3を既設のトンネル巻立コンクリート面に対し
て固定できるようにして、前記前スライド型枠2の押前
進時および反力受グリップ装置4の引前進時における反
力点となるようにしている。
The front slide mold 2 and the first slide jack group 5,
As shown in the transverse sectional view of FIG. 4, the rear slide formwork 3 connected by 5 has circular surface frames 31 around the outer circumferences of the circular rings 30, 30, ... Pin connection at each end of the circular ring with a grip jack 32
By connecting via the grip jack 32
Is configured to be expandable and contractible in the circumferential direction by the expansion and contraction operation of the rear slide form 3, so that the rear slide formwork 3 can be fixed to the existing tunnel winding concrete surface. The reaction force point is set when the grip device 4 is pulled forward.

なお、本具体例においては、前記前スライド型枠2と
後スライド型枠3とを第1スライドジャッキ5、5…に
より連結したが、これを省略し、一体として構成するこ
とも可能である。この場合には、この一体型スライド型
枠の前進時には、反力受グリップ装置4を反力点として
第2スライドジャッキ6、6…により前進し、前記反力
受グリップ装置4の前進時には、この一体型スライド型
枠を反力点とすればよい。
In this specific example, the front slide form frame 2 and the rear slide form frame 3 are connected by the first slide jacks 5, 5, ... However, it is possible to omit them and configure them integrally. In this case, when the integrated slide frame is moved forward, the reaction force receiving grip device 4 is used as a reaction force point to move forward by the second slide jacks 6, 6 ,. The body slide form may be used as the reaction force point.

第5図にも示すように、最後列の反力受グリップ装置
4は、前記後スライド型枠3とほぼ同様の構造を成し、
円形リング40、40…の外周に円形面枠41が周設され、そ
の円周方向の適所においてピン結合とし、前記円形リン
グの端々をグリップジャッキ42を介して連結することに
より、前記グリップジャッキ42の伸縮操作により円周方
向に拡縮自在として、反力受グリップ装置4を既設のト
ンネル巻立コンクリート面に対して固定できるようにな
っており、前記前後スライド型枠2、3の押前進時の際
の反力点となる。
As shown in FIG. 5, the reaction force receiving grip device 4 in the last row has substantially the same structure as the rear slide form frame 3,
A circular surface frame 41 is provided around the outer circumferences of the circular rings 40, 40 ..., and pin connection is made at appropriate positions in the circumferential direction, and the ends of the circular rings are connected via a grip jack 42, whereby the grip jack 42 is formed. The reaction force receiving grip device 4 can be fixed to the existing tunnel winding concrete surface by expanding and contracting in the circumferential direction by the expansion and contraction operation of. It becomes the reaction point of the occasion.

かかる連続打設装置を用いて、トンネル覆工コンクリ
ートの打設を行うには、先ず、第6図に示されるよう
に、トンネル切羽位置におけるトンネル掘削機7が、カ
ッターヘッドの回転およびスラストジャッキの押出しに
より地山を掘削する。以下、第7図および第8図を参照
しつつ説明する。
In order to place concrete in a tunnel lining using such a continuous placing device, first, as shown in FIG. 6, the tunnel excavator 7 at the tunnel face position rotates the cutter head and thrusts the thrust jack. The ground is excavated by extrusion. Hereinafter, description will be given with reference to FIGS. 7 and 8.

第7図(1) トンネル掘削機7によるスラストジャッキ1ストロー
クに相当する掘削(約1.5m)が完了したならば、打設装
置1のグリップ装置13によりグリッパ14を張出して打設
装置1自体を掘削面に固定する。
7 (1) When the excavation (about 1.5 m) corresponding to one stroke of the thrust jack by the tunnel excavator 7 is completed, the gripper 13 of the placing device 1 extends the gripper 14 to remove the placing device 1 itself. Fix on the excavation surface.

第7図(2) そして、打設装置1のプレスジャッキ12によりプレス
リング17を打設コンクリートの打継目より30cm程度引き
離す。これによって、前スライド型枠2の円形面枠21の
外面、プレスリング17のトンネル坑口側面、既設の巻立
コンクリートの打継目により囲まれた空間Sを形成す
る。
FIG. 7 (2) Then, the press ring 12 of the pouring device 1 separates the press ring 17 from the pouring joint of the pouring concrete by about 30 cm. As a result, a space S surrounded by the outer surface of the circular surface frame 21 of the front slide form 2, the tunnel pit side surface of the press ring 17, and the existing joints of rolled concrete is formed.

第7図(3) 打設口18を介して、前記空間SにコンクリートNを打
設する。前記空間SにコンクリートNが充填され、コン
クリートポンプの送給圧が一定値以上になったならば、
一旦コンクリートの送給を止める。
Fig. 7 (3) Concrete N is poured into the space S through the pouring port 18. If the space S is filled with concrete N and the feed pressure of the concrete pump exceeds a certain value,
Stop feeding concrete once.

なお、打設コンクリートNは前記プレスリング17によ
り常時加圧状態に保持される。
The poured concrete N is constantly kept under pressure by the press ring 17.

第7図(4) 次に、後スライド型枠3のグリップジャッキ32を張出
して、前記後スライド型枠3を巻立コンクリートR面に
固定し、第1スライドジャッキ5で前記前スライド型枠
2を30cm程前進させる。
FIG. 7 (4) Next, the grip jack 32 of the rear slide form frame 3 is extended to fix the rear slide form frame 3 to the rolled concrete R surface, and the first slide jack 5 is used for the front slide form frame 2. Advance about 30 cm.

第7図(5) その後、反力受グリップ4のグリップジャッキ42を張
出し巻立コンクリートR面に固定するとともに、前記後
スライド型枠3の固定を解き、前記後スライド型枠3を
同じく30cm程度前進させる。
7 (5) After that, while fixing the grip jack 42 of the reaction force receiving grip 4 to the overhanging concrete R surface, the rear slide formwork 3 is unfixed, and the rear slide formwork 3 is also about 30 cm. To move forward.

ここまでの工程を1サイクル打設とし、再び、前記プ
レスリング17を打設コンクリートNの打継目より30cm程
度引き離し、コンクリートNを打設する工程(第7図
(6)参照)を繰り返す。打設コンクリートN,N…の長
さが、第8図(6)および(7)に示すようにトンネル
掘削機の1ストローク掘削に相当する1.5m分になるま
で、前述のサイクルを繰り返し行って、コンクリートの
打設を完了させる。
The steps up to this point are set as one cycle, and the step of placing the concrete N again by separating the press ring 17 by about 30 cm from the joint of the cast concrete N (see FIG. 7 (6)) is repeated. Repeat the above cycle until the length of the poured concrete N, N ... becomes 1.5 m, which is equivalent to one stroke excavation of the tunnel excavator as shown in Fig. 8 (6) and (7). , Complete the concrete pouring.

第8図(8) 次に、打設装置1のグリップ装置13を緩め、プレスジ
ャッキ12、12…の伸長により、コンクリート打継端面を
プレスリング17により押して、その反作用的に前記打設
装置1を1.5m程前進させ、再度前記グリップ装置13の張
出しにより前記打設装置1を掘削面に固定し、前記プレ
スジャッキ12、12…の操作によりプレスリング17を介し
てコンクリートN,N…を所定圧で加圧し20〜30分程度保
持する。なお、前記加圧値は、地盤を破壊しない範囲
で、水圧に対し充分な止水性を有し、地盤沈下を極力少
なくする観点から適宜決定される。
FIG. 8 (8) Next, the grip device 13 of the placing device 1 is loosened, and the concrete jacking end face is pushed by the press ring 17 by the extension of the press jacks 12, 12, ... Is moved forward by about 1.5 m, the projecting device 1 is again fixed to the excavation surface by overhanging the grip device 13, and concrete N, N ... Is predetermined through the press ring 17 by operating the press jacks 12, 12. Pressurize with pressure and hold for 20 to 30 minutes. The above-mentioned pressurization value is appropriately determined from the viewpoint of having a sufficient waterproofness against water pressure and minimizing ground subsidence within a range that does not destroy the ground.

第8図(9) その間、前記後スライド型枠3を、巻立コンクリート
R面に固定し、第2スライドジャッキ6により反力受グ
リップ4を前方へ1.5m移動させて固定保持し、前記シー
ルド機7により再度掘削を開始する。
8 (9) In the meantime, the rear slide formwork 3 is fixed to the rolled concrete R surface, and the reaction force receiving grip 4 is moved forward by 1.5 m by the second slide jack 6 to be fixed and held, and the shield. The excavation is started again by the machine 7.

なお、前述具体例は、地山の緩みを極力防止する意味
で、トンネル掘削機による1ストローク掘削相当区間
(1.5m)を、30cm×5回に分割してコンクリート打設を
行ったが、施工速度を優先するならば、前記1ストロー
ク掘削相当区間を一回のコンクリート打設で行うことと
してもよい。
In addition, in the above-mentioned concrete example, in order to prevent loosening of the ground as much as possible, the section equivalent to 1-stroke excavation (1.5 m) by the tunnel excavator was divided into 30 cm × 5 times and concrete was placed, If the speed is prioritized, the section corresponding to the one-stroke excavation may be performed by placing the concrete once.

以上、詳説の本発明工法によれば、打設される覆工コ
ンクリートは、連続的に加圧状態としながら打設され、
その後も硬化まで圧力状態に保持されるため、地山に密
着する。したがって、地山は緩むことなく安定し、地表
沈下が殆どなく、またその周辺構造物に与える影響がな
い。また、掘削と同時併行的に覆工コンクリートの打設
ができ、施工の迅速化が図れる。特に、ELC工法などの
従来工法に比して、型枠作業に要する時間と手間を大幅
に低減し得る。
As described above, according to the detailed construction method of the present invention, the lining concrete to be placed is placed while continuously applying a pressure,
After that, since it is kept in a pressure state until it is cured, it adheres to the natural ground. Therefore, the ground is stable without loosening, there is almost no subsidence, and there is no effect on the surrounding structures. In addition, the lining concrete can be placed concurrently with excavation, and the construction can be speeded up. In particular, compared to conventional methods such as the ELC method, the time and labor required for formwork can be greatly reduced.

なお、本発明法にかかる打設コンクリートとしては、
フライアッシュ、およびこれにスチールファイバーおよ
び流動化材、遅延材などの混和材を配合した特殊コンク
リートなどを使用することができる。
Incidentally, as the cast concrete according to the method of the present invention,
It is possible to use fly ash, and special concrete in which steel fibers and admixtures such as fluidizers and retarders are mixed therein.

〔発明の効果〕〔The invention's effect〕

以上詳説のとおり、本発明によれば、トンネル掘削と
同時併行的に地山に密着した覆工コンクリートの打設が
できるとともに、その際の型枠作業に要する時間と手間
を簡略化し、作業の迅速化および省力化を図ることがで
きる。
As described above in detail, according to the present invention, it is possible to place lining concrete in close contact with the ground simultaneously with tunnel excavation, while simplifying the time and labor required for the formwork at that time. Speeding up and labor saving can be achieved.

【図面の簡単な説明】[Brief description of the drawings]

第1図は本発明に係る覆工コンクリート連続打設装置を
示す図、第2図は第1図のII-II線横断面図、第3図は
第1図のIII-III線横断面図、第4図は第1図のIV-IV線
横断面図、第5図は第1図のV−V線横断面図、第6図
は覆工コンクリートの打設要領を説明するための図、第
7図は覆工コンクリートの打設要領を説明するための
図、第8図は覆工コンクリートの打設要領を説明するた
めの図である。 1……覆工コンクリート打設・加圧装置、2……前スラ
イド型枠、3……後スライド型枠、4……反力受グリッ
プ装置、5……第1スライドジャッキ、6……第2スラ
イドジャッキ、7……トンネル掘削機
1 is a view showing a continuous lining concrete pouring device according to the present invention, FIG. 2 is a cross-sectional view taken along the line II-II of FIG. 1, and FIG. 3 is a cross-sectional view taken along the line III-III of FIG. 4 is a transverse sectional view taken along the line IV-IV of FIG. 1, FIG. 5 is a transverse sectional view taken along the line VV of FIG. 1, and FIG. 6 is a view for explaining the procedure for placing lining concrete. FIG. 7 is a diagram for explaining the procedure for placing lining concrete, and FIG. 8 is a diagram for explaining the procedure for placing lining concrete. 1 ... Lining concrete pouring / pressurizing device, 2 ... Front slide formwork, 3 ... Rear slide formwork, 4 ... Reaction force receiving grip device, 5 ... First slide jack, 6 ... 2 slide jacks, 7 ... Tunnel excavator

Claims (3)

(57)【特許請求の範囲】(57) [Claims] 【請求項1】トンネル掘削機の坑口側に、覆工コンクリ
ート打設・加圧装置、スライド型枠装置、および反力受
グリップ装置を、この順に有し、 前記覆工コンクリート打設・加圧装置は、 掘削面の支保のための外周面枠と、この外周面枠の一部
または全部を掘削面に押圧させて自身を掘削面に対して
固定する固定支持手段と、覆工コンクリート打設時の側
型枠として機能し、打設された覆工コンクリートをその
打継端面から加圧するためにトンネル方向に進退自在に
駆動され、かつ掘削断面形状と実質的に同一の外径およ
び打設覆工コンクリート厚に相当する部材幅を有する環
状枠材と、この環状枠材のトンネル坑口側面およびその
反対側面に連通するコンクリート打設口とを備え、 前記スライド型枠装置は、 前記覆工コンクリート打設・加圧装置に連行して、前記
環状枠材の枠材内面に内接し得る外径を有し、覆工コン
クリート打設時には前記環状枠材とともに覆工コンクリ
ート打設用型枠となる内型枠用外周面枠と、この外周面
枠の一部または全部を既設の巻立コンクリート内面に押
圧させて自身を既設の巻立コンクリート内面に固定する
ための固定支持手段とを備え、 前記反力受グリップ装置は、 前記スライド型枠装置に対してスライド用ジャッキによ
り連結され、前記スライド型枠装置の外周面枠と実質的
に同一外径の外周面枠を有するとともに、この外周面枠
の一部または全部を既設の巻立コンクリート内面に押圧
させて自身を既設の巻立コンクリート内面に固定するた
めの固定支持手段とを備えており、 前記トンネル掘削機と前記覆工コンクリート打設・加圧
装置とを、別体としたトンネル覆工コンクリートの連続
打設装置を用い、 シールド機によるトンネル掘削に続き、前記覆工コンク
リート打設・加圧装置、スライド型枠装置および反力受
グリップ装置の順に連行させ、前記シールド機による1
ストローク掘削毎に、 前記覆工コンクリート打設・加圧装置を掘削面に対し固
定支持し、その環状枠材をトンネル切羽方向へ移動させ
るとともに、これに追従して、前記環状枠材に前記スラ
イド型枠装置の内型枠用外周面枠が嵌挿状態となるよう
に移動し、これにより前記環状枠材と内型枠用外周面枠
とによって閉塞される空間を形成し、この空間に前記環
状枠材の打設口より覆工コンクリートを供給するととも
に、硬化までの間これを加圧状態に保持しつつ、覆工コ
ンクリートを連続的に形成するようにすることを特徴と
するトンネル覆工コンクリートの連続打設工法。
1. A lining concrete pouring / pressurizing device, a slide formwork device, and a reaction force receiving grip device are provided in this order on the pit side of a tunnel excavator. The equipment consists of an outer peripheral frame for supporting the excavation surface, fixed support means for pressing part or all of the outer peripheral surface frame against the excavation surface to fix itself to the excavation surface, and lining concrete pouring. It functions as a side form at the time, is driven to move forward and backward in the tunnel direction to press the placed lining concrete from its connecting end face, and has an outer diameter and placement substantially the same as the excavated cross-sectional shape. An annular frame member having a member width corresponding to the thickness of the lining concrete, and a concrete pouring port communicating with the tunnel pit side surface of the annular frame material and the opposite side surface thereof, wherein the slide formwork device is the lining concrete Casting An inner formwork that is entrained by a pressurizing device and has an outer diameter capable of being inscribed in the inner surface of the frame material of the annular frame material, and that serves as a formwork for lining concrete pouring together with the annular frame material when placing the lining concrete material. And a fixing support means for fixing a part or all of the outer peripheral surface frame to the existing inner surface of the rolled concrete by fixing the inner peripheral surface of the outer peripheral frame to the existing inner surface of the rolled concrete. The grip device is connected to the slide form frame device by a sliding jack, has an outer peripheral face frame having substantially the same outer diameter as the outer peripheral face frame of the slide form frame device, and a part of the outer peripheral face frame. Or a fixed supporting means for pressing the whole to the existing inner surface of the rolled concrete to fix itself to the inner surface of the existing rolled concrete, the tunnel excavator and the lining concrete pouring / pressurizing device. Using a continuous lining concrete pouring device as a separate unit, following the tunnel excavation by the shield machine, the lining concrete pouring / pressurizing device, slide formwork device and reaction force receiving grip device are carried in this order. Let's use the shield machine 1
For each stroke excavation, the lining concrete pouring / pressurizing device is fixedly supported on the excavation surface, the annular frame member is moved in the tunnel face direction, and following this, the annular frame member slides on the annular frame member. The outer peripheral frame for the inner mold of the mold frame device is moved so as to be in a fitted state, thereby forming a space closed by the annular frame member and the outer peripheral frame for the inner mold, and in the space, Tunnel lining characterized by supplying lining concrete from the casting opening of the annular frame material and maintaining it under pressure until hardening, while continuously forming lining concrete Continuous pouring method for concrete.
【請求項2】シールド機による1ストローク掘削毎の覆
工コンクリートの打設を分割して、環状枠材と内型枠用
外周面枠の移動による閉塞空間の形成と、覆工コンクリ
ートの供給との繰返しにより行う請求項1記載のトンネ
ル覆工コンクリートの連続打設工法。
2. Forming a closed space by moving an annular frame material and an outer peripheral frame for an inner frame by dividing the placing of the lining concrete for each stroke excavation by a shield machine, and supplying the lining concrete. The method for continuously placing concrete for tunnel lining according to claim 1, wherein the method is repeated.
【請求項3】スライド型枠装置を、内型枠用外周面枠部
と、自身を掘削面に固定するためのグリップ部とに分離
し、互いにトンネル方向にスライド用ジャッキにより連
結した装置によって行う請求項1および請求項2記載の
トンネル覆工コンクリートの連続打設工法。
3. A slide form device is performed by a device in which an outer form frame part for an inner form part and a grip part for fixing itself to an excavation surface are separated and connected to each other by a sliding jack in a tunnel direction. A method for continuously placing concrete for tunnel lining according to claim 1 or 2.
JP2305737A 1990-11-09 1990-11-09 Tunnel lining Concrete continuous pouring method Expired - Fee Related JP2691473B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP2305737A JP2691473B2 (en) 1990-11-09 1990-11-09 Tunnel lining Concrete continuous pouring method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP2305737A JP2691473B2 (en) 1990-11-09 1990-11-09 Tunnel lining Concrete continuous pouring method

Publications (2)

Publication Number Publication Date
JPH04176997A JPH04176997A (en) 1992-06-24
JP2691473B2 true JP2691473B2 (en) 1997-12-17

Family

ID=17948737

Family Applications (1)

Application Number Title Priority Date Filing Date
JP2305737A Expired - Fee Related JP2691473B2 (en) 1990-11-09 1990-11-09 Tunnel lining Concrete continuous pouring method

Country Status (1)

Country Link
JP (1) JP2691473B2 (en)

Families Citing this family (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109139056A (en) * 2018-10-29 2019-01-04 中国水利电力对外有限公司 The telescoping steel form of tunnel side wall concrete lining cutting

Family Cites Families (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS6023597A (en) * 1983-07-19 1985-02-06 株式会社熊谷組 Shield tunnel drilling method and apparatus

Also Published As

Publication number Publication date
JPH04176997A (en) 1992-06-24

Similar Documents

Publication Publication Date Title
JPH0511195B2 (en)
JP2691473B2 (en) Tunnel lining Concrete continuous pouring method
JP2691472B2 (en) Tunnel lining concrete continuous pouring equipment
JPH06248889A (en) Concrete casting device for tunnel lining
JP2501073Y2 (en) Shield machine's wife frame device
JPS6145037B2 (en)
JP2704891B2 (en) Construction method of shield excavator and tunnel lining
JPH0361000B2 (en)
JPH0610596A (en) Cast-in-place lining method of shield tunnel and lining device thereof
JPH0464398B2 (en)
JPH02132295A (en) Constructing method for tunnel lining work
JP2501072Y2 (en) Shield pressure machine for shield machine
JPH0367192B2 (en)
JP2548577B2 (en) Method and apparatus for assembling outer mold in non-segment shield method
JPH0541798B2 (en)
JPS6332960B2 (en)
JP2526312B2 (en) Shield machine and in-situ lining type shield construction method using the machine
JPH0642296A (en) Concrete placing device for tunnel lining
JPH0493498A (en) Concrete placing device for covering tunnel
JPH0791953B2 (en) Water stop device for shield machine
JPH02132297A (en) Lining work constructing method
JPH04327697A (en) Method of cast-in-place lining construction and shield excavator
JPH02171494A (en) Inner form device for directly placed concrete lining method
JPH01192998A (en) Tunnel refilling method and device therefor
JPH055039B2 (en)

Legal Events

Date Code Title Description
LAPS Cancellation because of no payment of annual fees