CN109139056A - The telescoping steel form of tunnel side wall concrete lining cutting - Google Patents

The telescoping steel form of tunnel side wall concrete lining cutting Download PDF

Info

Publication number
CN109139056A
CN109139056A CN201811269244.4A CN201811269244A CN109139056A CN 109139056 A CN109139056 A CN 109139056A CN 201811269244 A CN201811269244 A CN 201811269244A CN 109139056 A CN109139056 A CN 109139056A
Authority
CN
China
Prior art keywords
truss
side wall
trolley
jack
lining cutting
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201811269244.4A
Other languages
Chinese (zh)
Inventor
陈育权
王涛
吴世然
任强
侯彬
李进军
宋求明
熊德政
王江
杜思存
朱小春
章琦云
李学凯
赵博
刘永年
孙旭生
胡清林
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Zhengzhou Meiyu Construction Engineering Co Ltd
China Water And Electric Power Foreign Co Ltd
Sinohydro Bureau 3 Co Ltd
Original Assignee
Zhengzhou Meiyu Construction Engineering Co Ltd
China Water And Electric Power Foreign Co Ltd
Sinohydro Bureau 3 Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Zhengzhou Meiyu Construction Engineering Co Ltd, China Water And Electric Power Foreign Co Ltd, Sinohydro Bureau 3 Co Ltd filed Critical Zhengzhou Meiyu Construction Engineering Co Ltd
Priority to CN201811269244.4A priority Critical patent/CN109139056A/en
Publication of CN109139056A publication Critical patent/CN109139056A/en
Pending legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D11/00Lining tunnels, galleries or other underground cavities, e.g. large underground chambers; Linings therefor; Making such linings in situ, e.g. by assembling
    • E21D11/04Lining with building materials
    • E21D11/10Lining with building materials with concrete cast in situ; Shuttering also lost shutterings, e.g. made of blocks, of metal plates or other equipment adapted therefor
    • E21D11/102Removable shuttering; Bearing or supporting devices therefor

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Structural Engineering (AREA)
  • Mining & Mineral Resources (AREA)
  • Civil Engineering (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Geochemistry & Mineralogy (AREA)
  • Geology (AREA)
  • Lining And Supports For Tunnels (AREA)

Abstract

The present invention provides a kind of telescoping steel form of tunnel side wall concrete lining cutting, can be realized the full face quick lining cutting of tunnel concrete.Its structure trolley two sides is equipped with hoisting frame, hoisting frame is connected to trolley two sides by sliding-rail sliding, template and jack are equipped with above hoisting frame, template requires merogenesis manufacture installation, power source of the jack as hoisting frame, hoisting frame is slowly promoted, achievees the effect that synovial membrane, this structure is simple, it is convenient to assemble and disassemble, low in cost, adaptable, work progress and in time a kind of sleiding form of maintenance and the tunnel side wall concrete rapid construction of repairing construction mass defect can be monitored at any time.

Description

The telescoping steel form of tunnel side wall concrete lining cutting
Technical field
The invention patent technology is related to the construction method of tunnel concrete liner, in particular to a kind of tunnel side wall concrete The sleiding form of lining cutting.
Background technique
Currently, tunnel side wall concrete lining cutting generallys use telescoping steel form, it is full face to can be realized tunnel concrete Quick lining cutting.But in the prior art the lining cutting of tunneling boring telescoping steel form it is more outstanding the disadvantage is that: telescoping steel form volume is big, weight Greatly, it installs, is mobile, removing inconvenience;Manufacture, installation cost are high, and short tunnel is difficult to amortize its cost, section is bigger, abutment wall more Height, amortization charge are higher;Adaptability is relatively poor, and telescoping steel form at all can not for the turning of small curvature in hole inside turn difficulty It realizes;Intuitively work progress cannot be monitored, cannot find constructional deficiency in time, cannot in time to concrete curing, It can only could be demoulded after strong, concrete construction defect can not be effectively addressed and conserve in time;Versatility is bad, for Bending section, transition and peripheral wall height variation portion of tunnel etc. are not available, and also need to be influenced with other modes lining cutting is taken Speed of application increases construction cost.
Summary of the invention
The purpose of the invention patent technology be in order to solve critical issue present in tunnel side wall concrete work progress, Design a kind of structure is simple, convenient to assemble and disassemble, low in cost, adaptable, versatility is wide, it is quality controllable, can continuously construct, can be with When monitoring work progress and in time maintenance and repairing construction mass defect tunnel side wall concrete rapid construction a kind of punching block Trolley.
In order to solve the above technical problems, the technical scheme adopted by the invention is that: a kind of tunnel side wall concrete lining cutting Telescoping steel form, including trolley are equipped with truss in trolley two sides, and trolley two sides are equipped with sliding rail, and truss and installation are on the slide rail Sliding block connection, is fixedly connected with template in truss one end, is equipped with hoisting mechanism in trolley, moves down on hoisting mechanism driving truss It is dynamic.
In preferred embodiment, the hoisting mechanism is pressure lever type mechanism, including support rod and jack, support rod are embedded in coagulation In soil, truss is equipped with hoisting frame, and hoisting frame is mounted on jack, and the tracks of jack are support rod.
In preferred embodiment, the hoisting mechanism is rod-pulling type mechanism, including support rod, jack and anchor pole, the support Bar installs anchor pole outside concrete at the top of trolley, and support rod is connect with anchor pole, and support rod is the tracks of jack, Jack is mounted on truss.
In preferred embodiment, the hoisting mechanism is cable wire hoisting mechanism, including cable wire and hoist engine, cable wire one end and truss Connection, the cable wire other end are connect by pulley with hoist engine.
In preferred embodiment, truss is connect by demoulding lead screw with sliding block.
In preferred embodiment, bracket panel is equipped with below truss, bracket panel is connect by more lifting ropes with truss, on bracket panel It is managed equipped with maintenance.
In preferred embodiment, bracket panel is equipped with below truss, bracket panel is connect by more lifting ropes with truss, on bracket panel It is managed equipped with maintenance.
In preferred embodiment, jack is controlled by YKT-36 type hydraulic control panel.
In preferred embodiment, it is provided with charging mechanism on trolley, the charging mechanism includes hopper, multiple material-dividing grooves and more A movable joint chute, each movable joint chute are separately positioned on trolley two sides, and each material-dividing groove one end is connected to each movable joint chute, other end It is connected to the hopper being arranged at the top of trolley.
The present invention solves the disadvantage that not being available in tunnel peripheral wall height variation portion, can intuitive monitored concrete Lining cutting process can demould in advance tunnel concrete and can conserve in time and the tunnel abutment wall of mending concrete constructional deficiency is mixed Solidifying soil lining cutting rapid construction, design structure is simple, convenient to assemble and disassemble, low in cost, adaptable, versatility is wide, quality controllable, energy It continuously constructs, work progress can be monitored at any time and the tunnel side wall concrete of maintenance and repairing construction mass defect is quickly applied in time A kind of sleiding form of work.
Detailed description of the invention
Fig. 1 is telescoping steel form floor map of the invention
Fig. 2 is telescoping steel form cross-sectional configuration schematic diagram of the invention
Fig. 3 is that telescoping steel form vertical section pressure lever type of the invention promotes structural schematic diagram
Fig. 4 is telescoping steel form vertical section rod-pulling type lift structure schematic diagram of the invention
Fig. 5 is telescoping steel form vertical section cable wire lift structure schematic diagram of the invention
Meaning label is as follows in attached drawing:
Jack 1;Plank 2;Material-dividing groove 3;Hopper 4;Bridging 5;Movable joint chute 6;Sliding rail 7;Hoist engine 8;Pump line 9;Trolley 10;Support rod 11;Anchor pole 12;Template 13;Truss 14;Bracket panel 15;Conserve pipe 16;Track 17;Demould lead screw 18;Sliding block 19; Hoisting frame 20;Cable wire 21;Pulley 22.
Specific embodiment
Embodiment 1:
In Fig. 1 ~ 5, a kind of telescoping steel form of tunnel side wall concrete lining cutting, including trolley 10, it is equipped in 10 two sides of trolley Truss 14,10 two sides of trolley are equipped with sliding rail 7, and truss 14 connect with the sliding block 19 being mounted on sliding rail 7, fixes in 14 one end of truss It is connected with template 13, is equipped with hoisting mechanism in trolley 10, hoisting mechanism driving truss 14 moves up and down, thus structure, Ke Yishi Existing tunnel side wall lining, the place for being difficult to lining cutting of tunnel high-wall are resolved, lifting system also side's final result synovial membrane well.
In preferred embodiment, the hoisting mechanism is pressure lever type mechanism, including support rod 11 and jack 1, support rod 11 bury In concrete, truss 14 is equipped with hoisting frame 20, and hoisting frame 20 is mounted on jack 1, and the tracks of jack 1 are branch Strut 11, the most simply, conveniently, support rod 11 also can replace the reinforcing bar inside concrete to this hoisting way, and use is such Mode, it is necessary to be that reinforcement installation and concrete synchronous are constructed.
In preferred embodiment, the hoisting mechanism is rod-pulling type mechanism, including support rod 11, jack 1 and anchor pole 12 are described Support rod 11 installs anchor pole 12 outside concrete at the top of trolley 10, and support rod 11 is connect with anchor pole 12, and support rod 11 is thousand The tracks on jin top 1, jack 1 is mounted on truss 14, and such method may be implemented tension and compression combination, and support rod 11 can also be with Recycling is reused.
In preferred embodiment, the hoisting mechanism is cable wire hoisting mechanism, including cable wire 21 and hoist engine 8,21 one end of cable wire and purlin Frame 14 connects, and 21 other end of cable wire is connect by pulley 22 with hoist engine 8, thus structure, and truss 14 is provided dynamic by hoist engine 8 Power, cable wire 21 lift the truss 14 on both sides simultaneously, can make 8 uniform force of hoist engine in this way, also can achieve the effect of synovial membrane Fruit.
In preferred embodiment, truss 14 is connect by demoulding lead screw 18 with sliding block 19, demoulding lead screw 18 by template 13 slowly It is separated with concrete, keeps metope injury-free, then carry out synovial membrane again.
In preferred embodiment, bracket panel 15 is equipped with below truss 14, bracket panel 15 is connect by more lifting ropes with truss 14, Bracket panel 15 is equipped with maintenance pipe 16, bracket panel 15 is suspended in midair in 13 lower part of template, after convenience is manually on bracket panel 15 to demoulding Quality defect of concrete repaired in time, built-in fitting is handled;And arrange that a sprinkle water and spray fills on the downside of template 13 It sets, guarantee in time sprinkles water to the concrete for reaching initial setting strength, conserves.
In preferred embodiment, jack 11 is controlled by YKT-36 type hydraulic control panel, and console is in the commander of sliding mode system The heart is that jack 1 provides power by oil pipe, control valve etc., and automatic leveling device is the synchronizing device of jack 1, is fixed on branch It supports on thick stick, control is synchronized to jack 1 in due course, it is ensured that sliding formwork is horizontal, uniformly rises.
In preferred embodiment, 13 merogenesis of template is manufactured, and is bolted between section, and 13 length of template considers tunnel design point as a whole Seam, reinforcing bar length, construction speed require etc. factors, be generally advisable with 10-20 meters, in order to pacify tear open, convenient transportation, can merogenesis system It makes, is bolted between section.
In preferred embodiment, charging mechanism is provided on trolley 10, the charging mechanism includes hopper 4, multiple material-dividing grooves 3 With multiple movable joint chutes 6, each movable joint chute 6 is separately positioned on 10 two sides of trolley, and each 3 one end of material-dividing groove and each movable joint chute 6 connect Logical, other end is connected to the hopper 4 that 10 top of trolley is arranged in, and concrete is directly sent to hopper 4 by concrete pump, By material-dividing groove 3, movable joint chute 6 to 13 two sides uniform distributing of template, close a position, vibrate, mouth internal vibration over the pattern 13 Device effectively vibrates to concrete implementation.
Embodiment 2:
Template 13 makes: manufacturing in manufacturing shop by design requirement merogenesis, carries out an acceptance inspection after pre-assembled, merogenesis is numbered after qualification.
Reinforcement installation: can install in advance, can also with slding form operation while installation, while sliding formwork;Recommend first to pacify using reinforcing bar Dress mode, in favor of rapid concrete construction.
Die body installation: merogenesis installation after all systems are installed, carries out no-load test.
The installation of concrete conveying system: after template 13 is in place, installing concrete hopper 4, material-dividing groove 3, movable joint chute 6, Concrete pump, erection concrete pump pipe are installed in suitable position.
Concrete construction: concrete is transported using tank car, and concrete pumping to aggregate bin utilizes material-dividing groove 3, movable joint chute It 6 symmetrically puts in storage, uniform point storehouse;It is important to guarantee that two sides side wall concrete is uniformly synchronized and put in storage, to ensure that side does not occur for template 13 It moves, and is uniformly vibrated using the layering of flexible axle shock club.Strict implement sequence put in storage, be layered close a position, uniformly vibrate, synchronize it is sliding Principle.
Sliding formwork is sliding: concrete pour for the first time it is first sliding with sliding formwork, strictly by following six step carry out: for the first time Pour the concrete or mortar of 10cm thickness, half aggregate;Then the second layer concrete is poured no more than 30cm by lift height;Thickness When reaching 70cm, start sliding 3~6cm, checks whether demoulding concrete intensity is suitable.4th layer pours rear sliding 6cm, continues Layer 5 sliding 12cm~15cm again is poured, layer 6 pours rear sliding 20cm, if phenomenon without exception, can normally be poured With it is sliding.Concreting is symmetrically poured using layering, and lift height is not more than 30cm.Sliding formwork it is first it is sliding will slowly into Row, and in the process, to hydraulic device, 13 structure of template and related facility, in load conditions, comprehensive system inspection, It finds the problem, handles in time, can be carried out after all going well normal sliding.When construction is transferred to normal sliding, it should keep as far as possible It works continuously, demoulding concrete surface quality is observed by special messenger, with the suitable sliding time of determination and sliding speed.Normal day is sliding 4-6m or so is risen, this needs is determined according to compbined tests such as concrete property, feeding strength, environment temperature, demoulding strengths.
Concrete should be done before concreting and consolidates body setting test, should control it solid body setting time 4~6 hours.To protect Card concrete smoothly puts in storage, it is desirable that concrete workability, good fluidity, the slump meet pumping requirements.The concrete surface of demoulding Trowel troweling should can be used by having hard feeling and the finger mark of 1mm or so can be extruded without trickling and drawing crack phenomenon, hand.If demoulding is mixed Solidifying soil face is smooth, can not do troweling processing.If demoulding concrete face is defective, concrete surface repairing should be carried out immediately, generally It is flattened in concrete surface with magma with trowel.In order to which sliding formwork can be gone on smoothly, concrete supply is continuous.When concrete initial set Between requirement to choose the Fresh Concrete with Admixtures presetting period and climate temperature etc. can be adjusted in time depending on the site environment.
The maintenance of concrete defect elimination: magma reparation is carried out to concrete using bracket panel 15 in time after demoulding, it is desirable that light, It is even, smooth.To make demoulding concrete surface that there is suitable curing condition, prevents crack, be arranged on bracket panel 15 Curing agent can also be used in sprinkler pipe, is conserved in time to demoulding concrete face.
Die body decentralization, translation: after sliding formwork slides into design position, first by die body it is fixed using the suspention of roll bolt 12 or Trolley 10 suspends pole-climbing in midair, installs jack 1;Or suspended in midair using guide chain, demoulding lead screw 18 is unclamped, keeps template 13 and concrete de- From;Thereafter using console control jack die body is slowly transferred on the moving track of tunnel bottom plate or using jack, The modes such as hoist engine 8 are transferred.It recycles that elevator is led or other power draw die body moving to next storehouse number, starts next storehouse The construction of number concrete slip-form.
It is so round-trip in proper order, gradually complete tunnel side wall concrete lining construction.It, can for needing the tunnel of vault lining cutting It is realized using vault trolley 10;For abutment wall transition, arc section etc., implement again after simply transformation can be carried out.
The above embodiments are only the preferred technical solution of the present invention, and are not construed as limitation of the invention, this hair Bright protection scope should be with the technical solution of claim record, technical characteristic in the technical solution recorded including claim Equivalents are protection scope.Equivalent replacement i.e. within this range is improved, also within protection scope of the present invention.

Claims (8)

1. a kind of telescoping steel form of tunnel side wall concrete lining cutting, including trolley (10) are equipped with truss in trolley (10) two sides (14), it is characterized in that: trolley (10) two sides are equipped with sliding rail (7), truss (14) connects with the sliding block (19) being mounted on sliding rail (7) It connects, is fixedly connected with template (13) in truss (14) one end, be equipped with hoisting mechanism in trolley (10), hoisting mechanism drives truss (14) it moves up and down.
2. the telescoping steel form of a kind of tunnel side wall concrete lining cutting according to claim 1, it is characterized in that: the elevator Structure is pressure lever type mechanism, including support rod (11) and jack (1), support rod (11) are embedded in concrete, and truss is set on (14) Have hoisting frame (20), hoisting frame (20) is mounted on jack (1), and the tracks of jack (1) are support rod (11).
3. the telescoping steel form of a kind of tunnel side wall concrete lining cutting according to claim 1, it is characterized in that: the elevator Structure is rod-pulling type mechanism, including support rod (11), jack (1) and anchor pole (12), the support rod (11) outside concrete, Anchor pole (12) are installed at the top of trolley (10), support rod (11) is connect with anchor pole (12), and support rod (11) is the fortune of jack (1) Dynamic rail road, jack (1) are mounted on truss (14).
4. the telescoping steel form of a kind of tunnel side wall concrete lining cutting according to claim 1, it is characterized in that: the elevator Structure is cable wire hoisting mechanism, including cable wire (21) and hoist engine (8), cable wire (21) one end are connect with truss (14), cable wire (21) The other end is connect by pulley (22) with hoist engine (8).
5. the telescoping steel form of a kind of tunnel side wall concrete lining cutting according to claim 1, it is characterized in that: truss (14) is logical Demoulding lead screw (18) is crossed to connect with sliding block (19).
6. the telescoping steel form of a kind of tunnel side wall concrete lining cutting according to claim 1, it is characterized in that: in truss (14) Lower section is equipped with bracket panel (15), and bracket panel (15) is connect by more lifting ropes with truss (14), and bracket panel (15) is equipped with maintenance It manages (16).
7. the telescoping steel form of a kind of tunnel side wall concrete lining cutting according to claim 2 or 3, it is characterized in that: jack (1) it is controlled by YKT-36 type hydraulic control panel.
8. according to claim 1 to a kind of 6 described in any item telescoping steel forms of tunnel side wall concrete lining cutting, it is characterized in that: Charging mechanism is provided on trolley (10), the charging mechanism includes that hopper (4), multiple material-dividing grooves (3) and multiple movable joints slip Cylinder (6), each movable joint chute (6) are separately positioned on trolley (10) two sides, and each material-dividing groove (3) one end is connected to each movable joint chute (6), Other end is connected to the hopper (4) being arranged at the top of trolley (10).
CN201811269244.4A 2018-10-29 2018-10-29 The telescoping steel form of tunnel side wall concrete lining cutting Pending CN109139056A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201811269244.4A CN109139056A (en) 2018-10-29 2018-10-29 The telescoping steel form of tunnel side wall concrete lining cutting

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201811269244.4A CN109139056A (en) 2018-10-29 2018-10-29 The telescoping steel form of tunnel side wall concrete lining cutting

Publications (1)

Publication Number Publication Date
CN109139056A true CN109139056A (en) 2019-01-04

Family

ID=64806670

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201811269244.4A Pending CN109139056A (en) 2018-10-29 2018-10-29 The telescoping steel form of tunnel side wall concrete lining cutting

Country Status (1)

Country Link
CN (1) CN109139056A (en)

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110043287A (en) * 2019-05-06 2019-07-23 中国水利电力对外有限公司 The circumferential slip form construction device and method of wholecircle tunnel concrete liner
CN111140258A (en) * 2020-01-13 2020-05-12 成都锐龙机械制造有限公司 Culvert lining trolley and lining method
CN113719148A (en) * 2021-08-13 2021-11-30 上海建工二建集团有限公司 Sliding formwork supporting device for brick wall reinforcement and construction method
WO2024021388A1 (en) * 2022-07-25 2024-02-01 中国水利电力对外有限公司 Comprehensive operation trolley for construction of air-cushion surge chamber of hydropower station, and using method thereof

Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH04176997A (en) * 1990-11-09 1992-06-24 Sato Kogyo Co Ltd Continuously placing method for tunnel lining concrete
CN2270807Y (en) * 1996-08-16 1997-12-17 北京市第二水利工程处 Advancing tunnel sliding shuttering
CN201963317U (en) * 2011-03-08 2011-09-07 湖北安联建设工程有限公司 Single-side steel mould trolley
CN103711491A (en) * 2013-12-19 2014-04-09 中国长江三峡集团公司 Equipment used for vertical shaft concrete lining construction and construction method thereof
CN205329640U (en) * 2016-01-12 2016-06-22 中国水利水电第七工程局有限公司 " T " supports symmetrical sliding formwork construction structures
CN207538841U (en) * 2017-12-08 2018-06-26 中国水利水电第七工程局有限公司 A kind of hydraulic tunnel inverted arch cambered surface slip form construction device
CN208934709U (en) * 2018-10-29 2019-06-04 中国水利电力对外有限公司 The telescoping steel form of tunnel side wall concrete lining cutting

Patent Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH04176997A (en) * 1990-11-09 1992-06-24 Sato Kogyo Co Ltd Continuously placing method for tunnel lining concrete
CN2270807Y (en) * 1996-08-16 1997-12-17 北京市第二水利工程处 Advancing tunnel sliding shuttering
CN201963317U (en) * 2011-03-08 2011-09-07 湖北安联建设工程有限公司 Single-side steel mould trolley
CN103711491A (en) * 2013-12-19 2014-04-09 中国长江三峡集团公司 Equipment used for vertical shaft concrete lining construction and construction method thereof
CN205329640U (en) * 2016-01-12 2016-06-22 中国水利水电第七工程局有限公司 " T " supports symmetrical sliding formwork construction structures
CN207538841U (en) * 2017-12-08 2018-06-26 中国水利水电第七工程局有限公司 A kind of hydraulic tunnel inverted arch cambered surface slip form construction device
CN208934709U (en) * 2018-10-29 2019-06-04 中国水利电力对外有限公司 The telescoping steel form of tunnel side wall concrete lining cutting

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
《煤矿冻结法凿井经验》编写组: "《煤矿冻结法凿井经验》", 30 June 1976, 煤炭工业出版社, pages: 117 - 118 *

Cited By (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110043287A (en) * 2019-05-06 2019-07-23 中国水利电力对外有限公司 The circumferential slip form construction device and method of wholecircle tunnel concrete liner
CN111140258A (en) * 2020-01-13 2020-05-12 成都锐龙机械制造有限公司 Culvert lining trolley and lining method
CN111140258B (en) * 2020-01-13 2024-05-31 成都锐龙机械制造有限公司 Culvert lining trolley and lining method
CN113719148A (en) * 2021-08-13 2021-11-30 上海建工二建集团有限公司 Sliding formwork supporting device for brick wall reinforcement and construction method
WO2024021388A1 (en) * 2022-07-25 2024-02-01 中国水利电力对外有限公司 Comprehensive operation trolley for construction of air-cushion surge chamber of hydropower station, and using method thereof

Similar Documents

Publication Publication Date Title
CN109139056A (en) The telescoping steel form of tunnel side wall concrete lining cutting
CN106894639B (en) The hanging reverse construction method of installation of steel construction under a kind of
CN111946124B (en) Method for manufacturing silo with vertical shaft structure by using section bar combined frame for silo
CN103939114B (en) A kind of outstanding rail chassis lining construction method
CN108505645B (en) CL composite concrete shear wall cast-in-place construction method
CN104533456A (en) Super-large section chamber reinforced concrete modelling construction method
CN107542268A (en) The reverse construction method of installation of stage steel construction in a kind of grand theater room
CN108687950A (en) A kind of prefabricated trolley of pipe gallery and piping lane method for prefabricating
CN104278841A (en) Method for pouring concrete in steel pipe column
KR101573369B1 (en) Slabs railway track repair equipment and slabs railway track repair method using the same
CN105133754A (en) Prefabricated concrete shear wallboard counterbore guide type mounting device and method
CN110682416A (en) Template system for prefabricating comprehensive pipe gallery and construction method thereof
CN104452591A (en) Cast-in-place box beam construction technology applied to bridge constructions
CN205223976U (en) Irrigation gallery concrete slipform device
CN208934709U (en) The telescoping steel form of tunnel side wall concrete lining cutting
CN103669872B (en) A kind of walling method and walling equipment
CN106223960B (en) High-speed rail major long tunnel inverted arch moves integrally mould bases construction
CN114876515A (en) Two lining platform trucks in tunnel are pour fast
CN114438896A (en) Assembling construction method for assembled segmental beam of 100t span-pier gantry crane
CN108277908B (en) Energy-saving environment-friendly CL wall engineering construction method
CN205224332U (en) Prefabricated wall body and prefabricated wallboard
CN110043287A (en) The circumferential slip form construction device and method of wholecircle tunnel concrete liner
CN205445633U (en) Tunnel ditch cable groove built -up plate hangs commentaries on classics formula erection equipment
CN112609584A (en) Prefabricated small box girder installation construction method for intelligent express way
CN202401753U (en) Sliding die device

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination