JP2023042845A - Lining concrete placing method - Google Patents

Lining concrete placing method Download PDF

Info

Publication number
JP2023042845A
JP2023042845A JP2021150218A JP2021150218A JP2023042845A JP 2023042845 A JP2023042845 A JP 2023042845A JP 2021150218 A JP2021150218 A JP 2021150218A JP 2021150218 A JP2021150218 A JP 2021150218A JP 2023042845 A JP2023042845 A JP 2023042845A
Authority
JP
Japan
Prior art keywords
shotcrete
tunnel
lining concrete
inner formwork
polystyrene foam
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
JP2021150218A
Other languages
Japanese (ja)
Inventor
奨士 鈴木
Shoji Suzuki
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Okumura Corp
Original Assignee
Okumura Corp
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Okumura Corp filed Critical Okumura Corp
Priority to JP2021150218A priority Critical patent/JP2023042845A/en
Publication of JP2023042845A publication Critical patent/JP2023042845A/en
Pending legal-status Critical Current

Links

Images

Abstract

To provide a lining concrete placing method capable of simply preventing outflow of concrete from a gable side of a form of tunnel lining when the lining concrete is placed between the inner form of the form of tunnel lining and shotcrete.SOLUTION: A form of tunnel lining C comprising an inner form extending in the extension direction of a tunnel and curved in the transverse direction of the tunnel and a flange Cb installed so as to protrude outward in the tunnel transverse direction on a gable side of the inner form, is installed at a position where the shotcrete 12 is placed. Between the inner form Ca and the shotcrete 12 along the flange Cb, at least one layer of extruded polystyrene foam PF, which is a long plate member having a predetermined thickness, is installed. A long air bulk AB is inflated and installed in one layer. A space between the inner form Ca on the gable side and the shotcrete 12 is closed, and the lining concrete is placed in the space 13g formed by the inner form Ca and the shotcrete 12.SELECTED DRAWING: Figure 4

Description

本発明は、覆工コンクリートの打設方法に関し、特に山岳トンネルの施工における覆工コンクリートの打設に適用して有効な技術に関するものである。 TECHNICAL FIELD The present invention relates to a method of placing lining concrete, and more particularly to a technique effectively applied to placing lining concrete in the construction of mountain tunnels.

山岳トンネルの施工において、岩盤にダイナマイトを仕掛けて爆破することでトンネルを掘削する発破方式が用いられる。この工法は、掘削部分にコンクリートを吹き付けて硬化させてロックボルトを岩盤に設置し、地山自体の保持力を利用してトンネルを保持する工法である。ロックボルトの設置後は、セントルと呼ばれる半円筒形の型枠を嵌め込み、吹付けを行ったコンクリートとセントルとの間に覆工コンクリートを打設(充填)して仕上げが行われる。 In the construction of mountain tunnels, a blasting method is used in which the tunnel is excavated by placing dynamite in the bedrock and blowing it up. In this construction method, concrete is sprayed on the excavated part and hardened, and rock bolts are installed in the bedrock, and the holding force of the ground itself is used to hold the tunnel. After the rock bolts are installed, a semi-cylindrical form called a center is fitted, and lining concrete is placed (filled) between the sprayed concrete and the center for finishing.

ここで、セントルと吹付けコンクリートとの間詰(覆工コンクリートの打設)においてセントルの妻側からコンクリートが流出することを防止するために、エアバルクが使用されている。 Here, an air bulk is used to prevent the concrete from flowing out from the gable side of the center when filling the center and the shotcrete (placing the lining concrete).

すなわち、トンネル延伸方向の断面図である図11および図11のZ-Z線に沿った断面図である図12に示すように、セントルCは、ロックボルトBが貫通して設置された吹付けコンクリート12と対向配置される内型枠Caと、内型枠Caの妻側において当該内型枠Caのトンネル横断方向外側にはみ出すように設置されたフランジCbを備えている。そして、フランジCb側の内型枠Caの上に空気を充填しない状態のエアバルクABを設置し、当該エアバルクABに空気を充填して膨張させることで吹付けコンクリート12と密着させておいて、内型枠Caと吹付けコンクリート12との空間13gに覆工コンクリートを打設している。 That is, as shown in FIG. 11, which is a cross-sectional view in the tunnel extension direction, and FIG. 12, which is a cross-sectional view along the line ZZ in FIG. It comprises an inner formwork Ca arranged to face the concrete 12, and a flange Cb installed on the gable side of the inner formwork Ca so as to protrude outside of the inner formwork Ca in the tunnel crossing direction. Then, an air bulk AB that is not filled with air is installed on the inner formwork Ca on the flange Cb side, and the air bulk AB is filled with air and expanded to be in close contact with the shotcrete 12, The lining concrete is placed in the space 13g between the formwork Ca and the shotcrete 12 .

また、内型枠Caの妻側と吹付けコンクリート12との間隔が大きくなってしまう場合には、図示するように、エアバルクABを複数重ねて使用することで、両者の間を塞いでいる。 If the gap between the gable side of the inner formwork Ca and the shotcrete 12 becomes large, as shown in the figure, a plurality of air bulks AB are used to close the gap.

なお、図11および図12において、符号Gは地山、符号Sは鋼製支保工、符号11は鋼製支保工Sを保持するための仮吹付けコンクリートである。 In FIGS. 11 and 12, the symbol G is the natural ground, the symbol S is the steel shoring, and the symbol 11 is the temporary shotcrete for holding the steel shoring S.

エアバルクを用いたトンネル施工について記載された技術としては、例えば特許文献1(特開2017-223013号公報)が知られている。 For example, Patent Document 1 (Japanese Unexamined Patent Application Publication No. 2017-223013) is known as a technique describing tunnel construction using an air bulk.

特開2017-223013号公報JP 2017-223013 A

しかしながら、前述したエアバルクABを用いた施工方法では、次のような問題がある。 However, the construction method using the air bulk AB described above has the following problems.

すなわち、エアバルクABを膨張させると、その形状は円柱状になる。すると、エアバルクABを重ねて使用する場合には、円柱状のエアバルクABの上に円柱状のエアバルクABを載せるという形態になるため、エアバルクABの断面で考えた場合、図11に示すように、曲面を曲面で支えるようになる。そのため、エアバルクAB同士の接する面積が小さくなって不安定な設置となってしまい、施工性が悪化する。 That is, when the air bulk AB is inflated, its shape becomes columnar. Then, when the air bulk AB is used in an overlapping manner, the cylindrical air bulk AB is placed on top of the cylindrical air bulk AB. Therefore, when considering the cross section of the air bulk AB, as shown in FIG. It comes to support curved surfaces with curved surfaces. As a result, the contact area between the air bulks AB becomes small, resulting in unstable installation and poor workability.

また、エアバルクABの長さは4m程度と長尺物で重量が嵩む(例えば、直径150mmのエアバルクで約6kg、直径200mmのエアバルクで約8kg)ために、セントルCの内型枠Ca上の横断方向に沿って設置する際の作業性が極めて悪い。 In addition, the length of the air bulk AB is about 4 m, which is long and heavy (for example, about 6 kg for an air bulk with a diameter of 150 mm and about 8 kg for an air bulk with a diameter of 200 mm). The workability when installing along the direction is extremely poor.

本発明は、上述の技術的背景からなされたものであって、セントルの内型枠と吹付けコンクリートとの間に覆工コンクリートを打設する際におけるセントルの妻側からのコンクリートの流出を簡便に防止することのできる覆工コンクリートの打設方法を提供することを目的とする。 The present invention has been made in view of the above-mentioned technical background, and is intended to facilitate the outflow of concrete from the gable side of the center when lining concrete is placed between the inner formwork of the center and the shotcrete. It is an object of the present invention to provide a method of placing lining concrete that can prevent the

上記課題を解決するため、請求項1に記載の本発明の覆工コンクリートの打設方法は、山岳トンネルの施工における覆工コンクリートの打設方法であって、トンネルの延伸方向に延びてトンネルの横断方向に湾曲した内型枠および当該内型枠の妻側においてトンネル横断方向外側にはみ出すように設置されたフランジを備えたセントルを吹付けコンクリートが打設された位置に設置し、前記フランジに沿った前記内型枠と前記吹付けコンクリートとの間に、所定の厚みを有する長尺板状部材である押出発泡ポリスチレンフォームを少なくとも1層設置するとともに、長尺状のエアバルクを膨張させて1層設置し、妻側の前記内型枠と前記吹付けコンクリートとの間を閉塞し、前記内型枠と前記吹付けコンクリートとで形成された空間に覆工コンクリートを打設する、ことを特徴とする。 In order to solve the above-mentioned problems, the method for placing lining concrete according to the present invention described in claim 1 is a method for placing lining concrete in the construction of a mountain tunnel, the method extending in the direction of extension of the tunnel. A center provided with an inner formwork curved in the transverse direction and a flange installed so as to protrude outward in the tunnel transverse direction on the gable side of the inner formwork is installed at a position where the shotcrete is placed, and is attached to the flange. At least one layer of extruded polystyrene foam, which is a long plate-shaped member having a predetermined thickness, is installed between the inner formwork and the shotcrete, and the long air bulk is expanded to 1 A layer is installed, the space between the inner formwork on the gable side and the shotcrete is closed, and lining concrete is placed in the space formed by the inner formwork and the shotcrete. and

請求項2に記載の本発明の覆工コンクリートの打設方法は、上記請求項1に記載の発明において、前記押出発泡ポリスチレンフォームが前記内型枠側に設置され、前記エアバルクが前記吹付けコンクリート側に設置されている、ことを特徴とする。 According to a second aspect of the present invention, there is provided a method for placing lining concrete according to the first aspect, wherein the extruded polystyrene foam is installed on the inner formwork side, and the air bulk is the shotcrete. It is characterized by being installed on the side.

請求項3に記載の本発明の覆工コンクリートの打設方法は、上記請求項1に記載の発明において、前記押出発泡ポリスチレンフォームが前記吹付けコンクリート側に設置され、前記エアバルクが前記内型枠側に設置されている、ことを特徴とする。 According to a third aspect of the present invention, there is provided a method for placing lining concrete according to the first aspect, wherein the extruded polystyrene foam is installed on the shotcrete side, and the air bulk is placed on the inner formwork. It is characterized by being installed on the side.

上記課題を解決するため、請求項4に記載の本発明の覆工コンクリートの打設方法は、山岳トンネルの施工における覆工コンクリートの打設方法であって、トンネルの延伸方向に延びてトンネルの横断方向に湾曲した内型枠および当該内型枠の妻側においてトンネル横断方向外側にはみ出すように設置されたフランジを備えたセントルを吹付けコンクリートが打設された位置に設置し、前記フランジに沿った前記内型枠と前記吹付けコンクリートとの間に、所定の厚みを有する長尺板状部材である押出発泡ポリスチレンフォームを少なくとも1層設置して妻側の前記内型枠と前記吹付けコンクリートとの間を閉塞し、前記内型枠と前記吹付けコンクリートとで形成された空間に覆工コンクリートを打設する、ことを特徴とする。 In order to solve the above-mentioned problems, a method for placing lining concrete according to the present invention as set forth in claim 4 is a method for placing lining concrete in the construction of a mountain tunnel. A center provided with an inner formwork curved in the transverse direction and a flange installed so as to protrude outward in the tunnel transverse direction on the gable side of the inner formwork is installed at a position where the shotcrete is placed, and is attached to the flange. At least one layer of extruded polystyrene foam, which is a long plate-shaped member having a predetermined thickness, is placed between the inner formwork and the sprayed concrete along the gable side, and the inner formwork on the gable side and the sprayed concrete are placed. A space between the concrete and the concrete is closed, and lining concrete is placed in the space formed by the inner formwork and the shotcrete.

請求項5に記載の本発明の覆工コンクリートの打設方法は、上記請求項1~4の何れか一項に記載の発明において、前記押出発泡ポリスチレンフォームの片面または両面には、トンネルの延伸方向に沿った切り欠きが所定の間隔で形成されている、ことを特徴とする。 According to claim 5, there is provided a lining concrete casting method according to any one of claims 1 to 4, wherein one or both sides of the extruded polystyrene foam is provided with a tunnel extension Notches along the direction are formed at predetermined intervals.

請求項6に記載の本発明の覆工コンクリートの打設方法は、上記請求項1~5の何れか一項に記載の発明において、前記押出発泡ポリスチレンフォームには、硬化した覆工コンクリートとの剥離性を向上させる剥離処理が施されている、ことを特徴とする。 The lining concrete casting method of the present invention according to claim 6 is characterized in that, in the invention according to any one of claims 1 to 5, the extruded polystyrene foam is mixed with the hardened lining concrete. It is characterized by being subjected to a peeling treatment for improving peelability.

請求項7に記載の本発明の覆工コンクリートの打設方法は、上記請求項6に記載の発明において、前記剥離処理は、表面が剥離剤面となった粘着テープで前記押出発泡ポリスチレンフォームの短手方向に沿って全体を巻く処理、または前記押出発泡ポリスチレンフォームの全体に剥離剤を塗布する処理である、ことを特徴とする。 The method for placing lining concrete according to the present invention described in claim 7 is characterized in that, in the invention described in claim 6, the peeling treatment is performed by using an adhesive tape having a release agent surface on the surface of the extruded polystyrene foam. It is characterized by a process of winding the whole along the width direction, or a process of applying a release agent to the entire extruded polystyrene foam.

本発明によれば、押出発泡ポリスチレンフォームはトンネルの延伸方向に対して平坦な形状となるため、押出発泡ポリスチレンフォームとエアバルクとを重ねて設置する場合には、エアバルクが安定して施工性が向上する。また、押出発泡ポリスチレンフォームのみを用いた場合には、作業の軽減を図ることができる。 According to the present invention, the extruded polystyrene foam has a flat shape in the extending direction of the tunnel. Therefore, when the extruded polystyrene foam and the air bulk are stacked on top of each other, the air bulk is stable and workability is improved. do. Moreover, when only extruded polystyrene foam is used, the work can be reduced.

また、軽量で取り扱いが容易な押出発泡ポリスチレンフォームを用いることにより、設置時の作業性が向上する。 In addition, the use of extruded polystyrene foam, which is lightweight and easy to handle, improves workability during installation.

これにより、セントルの内型枠と吹付けコンクリートとの間に覆工コンクリートを打設する際におけるセントルの妻側からのコンクリートの流出を簡便に防止することが可能になる。 As a result, it is possible to easily prevent the outflow of concrete from the gable side of the center when the lining concrete is placed between the inner formwork of the center and the shotcrete.

(a)は本実施の形態に係る山岳トンネルの施工に用いられる連続ベルトコンベアシステムの平面図、(b)は(a)の連続ベルトコンベアシステムの側面図である。(a) is a plan view of a continuous belt conveyor system used for constructing a mountain tunnel according to this embodiment, and (b) is a side view of the continuous belt conveyor system of (a). 山岳トンネルの施工の概略を示すフローチャートである。It is a flowchart which shows the outline of construction of a mountain tunnel. (a)~(d)は本実施の形態に係る山岳トンネルの施工における覆工コンクリートの打設について順を追って示す説明図である。4(a) to 4(d) are explanatory diagrams showing the order of placement of lining concrete in the construction of the mountain tunnel according to the present embodiment. 山岳トンネルの施工における覆工コンクリートの打設に際して設置される本発明の一実施の形態としての流出防止部材を含めたトンネル延伸方向の断面図である。1 is a cross-sectional view in the direction of extension of a tunnel including an outflow prevention member as an embodiment of the present invention, which is installed when lining concrete is poured in construction of a mountain tunnel; FIG. 図4のW-W線に沿った断面図である。5 is a cross-sectional view taken along line WW of FIG. 4; FIG. (a)は本実施の形態の流出防止部材に用いられた押出発泡ポリスチレンフォームを示す斜視図、(b)は片面に切り欠きを形成した(a)の押出発泡ポリスチレンフォームを示す斜視図、(c)は両面に切り欠きを形成した(a)の押出発泡ポリスチレンフォームを示す斜視図である。(a) is a perspective view showing the extruded polystyrene foam used for the outflow prevention member of the present embodiment, (b) is a perspective view showing the extruded polystyrene foam of (a) with a notch formed on one side, ( Figure 3c) is a perspective view of the extruded polystyrene foam of (a) with notches formed on both sides; 山岳トンネルの施工における覆工コンクリートの打設に際して設置される本発明の他の実施の形態としての流出防止部材を含めたトンネル延伸方向の断面図である。FIG. 4 is a cross-sectional view in the direction of extension of the tunnel, including an outflow prevention member as another embodiment of the present invention, which is installed when lining concrete is poured in the construction of a mountain tunnel. 図7のX-X線に沿った断面図である。FIG. 8 is a cross-sectional view taken along line XX of FIG. 7; 山岳トンネルの施工における覆工コンクリートの打設に際して設置される本発明のさらに他の実施の形態としての流出防止部材を含めたトンネル延伸方向の断面図である。FIG. 10 is a cross-sectional view in the tunnel extending direction including an outflow prevention member as still another embodiment of the present invention, which is installed when lining concrete is poured in construction of a mountain tunnel. 図9のY-Y線に沿った断面図である。FIG. 10 is a cross-sectional view taken along line YY of FIG. 9; 山岳トンネルの施工における覆工コンクリートの打設に際して設置される従来の流出防止部材を含めたトンネル延伸方向の断面図である。FIG. 2 is a cross-sectional view in the tunnel extension direction including a conventional outflow prevention member installed when lining concrete is placed in the construction of a mountain tunnel. 図11のZ-Z線に沿った断面図である。FIG. 12 is a cross-sectional view along line ZZ of FIG. 11;

以下、本発明の一例としての実施の形態について、図面に基づいて詳細に説明する。なお、実施の形態を説明するための図面において、同一の構成要素には原則として同一の符号を付し、その繰り返しの説明は省略する。 BEST MODE FOR CARRYING OUT THE INVENTION An embodiment as an example of the present invention will be described in detail below with reference to the drawings. In the drawings for describing the embodiments, in principle, the same components are denoted by the same reference numerals, and repeated description thereof will be omitted.

本実施の形態における覆工コンクリートの打設方法は、特に山岳トンネルの施工における覆工コンクリートの打設に適用されるものである。 The method of placing lining concrete in the present embodiment is particularly applied to placing lining concrete in the construction of mountain tunnels.

山岳トンネルの施工において、岩盤にダイナマイトを仕掛けて爆破することでトンネルを掘削する発破方式が用いられる。この工法は、掘削部分にコンクリートを吹き付けて硬化させてロックボルトを岩盤に設置し、地山自体の保持力を利用してトンネルを保持する工法であり、NATM(New Austrian Tunneling Method)と呼ばれる。 In the construction of mountain tunnels, a blasting method is used in which the tunnel is excavated by placing dynamite in the bedrock and blowing it up. This method is called NATM (New Austrian Tunneling Method), in which concrete is sprayed on the excavated part and hardened, rock bolts are installed in the bedrock, and the holding force of the ground itself is used to hold the tunnel.

まず、本実施の形態に係る山岳トンネルの施工に用いられる連続ベルトコンベアシステムの構成例について図1を参照して説明する。ここで、図1(a)は本実施の形態に係る山岳トンネルの施工に用いられる連続ベルトコンベアシステムの平面図、図1(b)は図1(a)の連続ベルトコンベアシステムの側面図である。 First, a configuration example of a continuous belt conveyor system used for constructing a mountain tunnel according to the present embodiment will be described with reference to FIG. Here, FIG. 1(a) is a plan view of a continuous belt conveyor system used for construction of a mountain tunnel according to the present embodiment, and FIG. 1(b) is a side view of the continuous belt conveyor system of FIG. 1(a). be.

図示する連続ベルトコンベアシステム1は、トンネルTの切羽Kを発破により掘削した場合に生じたずり(掘削物)をトンネルTの抗口へと運ぶずり運搬用のシステムであり、クラッシャ2とテールピース台車3とベルトコンベア4とが、切羽Kから坑口に向かって順に縦列配置されている。 The illustrated continuous belt conveyor system 1 is a system for transporting debris (excavated material) generated when the face K of the tunnel T is excavated by blasting to the tunnel T mouth. A truck 3 and a belt conveyor 4 are arranged in tandem in order from the face K toward the pit.

クラッシャ2は、発破により生じたずりをベルトコンベア4で運ぶことが可能な大きさに破砕する自走式の破砕機である。テールピース台車3は、クラッシャ2で破砕されたずりをベルトコンベア4に搬送する自走式の中継運搬装置であり、ベルトコンベア4の先端(つまり、ベルトコンベア4の切羽K側)に設置されている。ベルトコンベア4は、テールピース台車3を介して運ばれたずりを長尺となった搬送用のベルト4aに搭載してトンネルTの坑口に向かって運ぶ運搬装置であり、テールピース台車3の後端部からトンネルTの坑口側まで連続して延在した状態で設置されている。さらに、連続ベルトコンベアシステム1には、余長ベルト(延伸用ベルト)を収納するとともに、ベルト4aに適切な張力を与えるためのベルトストレージ5が設置されている。 The crusher 2 is a self-propelled crusher that crushes the debris generated by blasting into a size that can be carried by the belt conveyor 4 . The tailpiece truck 3 is a self-propelled relay conveying device that conveys the scrap crushed by the crusher 2 to the belt conveyor 4, and is installed at the tip of the belt conveyor 4 (that is, on the face K side of the belt conveyor 4). there is The belt conveyor 4 is a conveying device that carries the sludge carried via the tailpiece carriage 3 toward the mouth of the tunnel T on a long conveying belt 4a. It is installed in a state of being continuously extended from the end to the tunnel T side. Further, the continuous belt conveyor system 1 is provided with a belt storage 5 for storing extra length belts (stretching belts) and applying appropriate tension to the belts 4a.

なお、連続ベルトコンベアシステム1には、これら以外に、ベルトストレージ5に収納された余長ベルトがなくなった場合にベルト4aを継ぎ足すためのベルト接合架台(図示せず)、ベルト4aを周回駆動させるための主駆動装置であるメインドライブ(図示せず)、ベルトコンベア4の昼間部においてベルト4aを駆動するブースタドライブ(図示せず)、各装置を制御するための換気・電気機器(図示せず)などが配置されている。 In addition to the above, the continuous belt conveyor system 1 also includes a belt joint stand (not shown) for adding the belt 4a when the excess belt stored in the belt storage 5 runs out, and a belt 4a circulating drive. A main drive (not shown) which is the main drive for driving, a booster drive (not shown) which drives the belt 4a in the daytime part of the belt conveyor 4, ventilation and electrical equipment (not shown) for controlling each device ) etc. are arranged.

また、連続ベルトコンベアシステム1は、トンネルTの幅方向の一方の片側に寄せられた状態となっており、トンネルTの幅方向の他方の片側は、掘削した岩盤の壁面にコンクリートを吹き付ける吹付け機(図示せず)、発破を装填するための孔(装薬孔)を切羽Kに穿孔するための切羽穿孔機(図示せず)、発破により生じたずりをクラッシャ2に積載するためのショベル7aを備えた自走式のサイドダンプ7やバックホウなどの積載用重機、岩盤の破砕や掘削や小割などの作業を行うためのブレーカ(図示せず)などのような各種の重機の通路として使用可能になっている。さらに、作業現場には、ロックボルトや鋼製支保工などをストックしておく資材置場(図示せず)が割り当てられている。 In addition, the continuous belt conveyor system 1 is in a state of being pulled to one side in the width direction of the tunnel T, and the other side in the width direction of the tunnel T is used for spraying concrete against the wall surface of the excavated bedrock. machine (not shown), a face boring machine (not shown) for boring a hole (charge hole) for loading blasting into the face K, and a shovel for loading the crusher 2 with debris generated by the blasting. As a passageway for various heavy equipment such as a self-propelled side dump 7 equipped with 7a, a heavy equipment for loading such as a backhoe, and a breaker (not shown) for performing work such as crushing, excavating, and splitting into small rocks. Enabled. Further, the work site is assigned a material storage area (not shown) for stocking rock bolts, steel shoring, and the like.

連続ベルトコンベアシステム1において、発破の際には、先頭に位置するクラッシャ2の先端部が切羽Kから飛散するずりが届かない程度の位置に配置する。これにより、発破の際に切羽Kから飛散したずりに起因してクラッシャ2、テールピース台車3およびベルトコンベア4が破損するのを防止することができる。そして、発破後のずりの運搬の際には、サイドダンプ7が切羽Kに向かって移動し、掘削物であるずりをショベル7aでクラッシャ2に投入する。 In the continuous belt conveyor system 1, at the time of blasting, the tip of the crusher 2 located at the head is arranged at a position where the shear scattered from the face K does not reach. As a result, it is possible to prevent the crusher 2, the tailpiece carriage 3, and the belt conveyor 4 from being damaged due to the shear scattered from the face K during blasting. When transporting the blasted debris, the side dump 7 moves toward the face K, and the excavated debris is dumped into the crusher 2 by the shovel 7a.

なお、図1(b)において、左右に延びる点線は、トンネルTの長さ方向における吹付けコンクリートの領域を示し、符号Bはコンクリートに設置されたロックボルトを示している。また、吹付けコンクリートおよびロックボルトBについては後述する。 In FIG. 1(b), the dotted line extending to the left and right indicates the area of the shotcrete in the longitudinal direction of the tunnel T, and the symbol B indicates the rock bolt installed in the concrete. Also, the shotcrete and the rock bolt B will be described later.

次に、山岳トンネルの施工の概略について、図2のフローチャートを用いて説明する。 Next, the outline of construction of a mountain tunnel will be described using the flow chart of FIG.

先ず、前述のように、切羽に装薬孔の穿孔を行い(ステップSt01)、爆薬の装填を行って(ステップSt02)、発破掘削を行う(ステップSt03)。そして、ずりの搬出を行う(ステップSt04)。 First, as described above, a charge hole is drilled in the face (step St01), an explosive is loaded (step St02), and blast excavation is performed (step St03). Then, the muck is carried out (step St04).

次に、岩盤の状態等から鋼製支保工S(図4,6,9)を設置するか否かを判断し(ステップSt05)、設置する場合には、コンクリートの仮吹付けを行い(ステップSt06)、鋼製支保工Sの建込みを行う(ステップSt07)。ステップSt07で鋼製支保工Sの建込みを行ったならば仮吹きつけを行ったコンクリートの表面に、あるいは、ステップSt05で鋼製支保工Sを設置しない場合には直接地山G(図4,5,7~10)の表面に、コンクリートの吹付けを行って(ステップSt08)、ロックボルトB(図4,6,9)の設置を行う(ステップSt09)。 Next, it is determined whether or not to install the steel shoring S (Figs. 4, 6, 9) based on the condition of the rock (step St05). St06), erecting the steel shoring S (step St07). If the steel shoring S is erected in step St07, it is placed on the surface of the concrete that has been temporarily sprayed, or if the steel shoring S is not installed in step St05, it is directly ground G (Fig. 4 , 5, 7 to 10) are sprayed with concrete (step St08), and rock bolts B (FIGS. 4, 6, 9) are installed (step St09).

なお、本願において、鋼製支保工Sを設置する際に吹き付けられるコンクリートを仮吹付けコンクリート11(図4,5,7~10)といい、仮吹付けコンクリート11あるいは鋼製支保工Sを設置せずに地山Gの表面に吹き付けられるコンクリートを単に吹付けコンクリート12(図4,5,7~10)という。また、本願においては、鋼製支保工Sの建込みを行っていることを前提として、吹付けコンクリート12が仮吹付けコンクリート11に吹き付けられるものとする。但し、鋼製支保工Sの建込みを行わずに、吹付けコンクリート12を地山Gに直接吹き付けることを排除するものではない。 In the present application, the concrete that is sprayed when installing the steel shoring S is referred to as temporary shotcrete 11 (Figs. 4, 5, 7 to 10), and the temporary shotcrete 11 or steel shoring S is installed. The concrete that is sprayed onto the surface of the natural ground G is simply called the shotcrete 12 (Figs. 4, 5, 7-10). Further, in the present application, it is assumed that the shotcrete 12 is sprayed onto the temporary shotcrete 11 on the premise that the steel shoring S is erected. However, it is not excluded to directly spray the shotcrete 12 onto the natural ground G without erecting the steel shoring S.

さて、ステップSt09でロックボルトBの設置を行ったならば、最後に、トンネル内への漏水を防ぐために必要に応じて防水シートを貼り、セントルを嵌め込んで、ステップSt08で施工された吹付けコンクリート12とセントルとの間に覆工コンクリートを打設して仕上げ作業を行う(ステップSt10)。なお、覆工コンクリートの打設は、例えば1日おきに実行される。そして、一連の作業が完了したか否かを判断し(ステップSt11)、完了したならばトンネルの施工を終了する。また、ステップSt11において作業が完了していない場合には、ステップSt01に戻って、以降の工程を繰り返す。 Now, once the rock bolt B has been installed in step St09, finally, to prevent water leakage into the tunnel, a waterproof sheet is affixed as necessary, the center is fitted, and the spraying that was performed in step St08 is performed. Lining concrete is placed between the concrete 12 and the center, and finishing work is performed (step St10). The lining concrete is placed, for example, every other day. Then, it is determined whether or not the series of work is completed (step St11), and if completed, the construction of the tunnel is finished. If the work is not completed in step St11, the process returns to step St01 and the subsequent steps are repeated.

ここで、図3を用いて、覆工コンクリート13の打設について説明する。図示するように、セントルCは半円筒形の型枠であり、トンネルTの吹付けコンクリート12の部分に覆工コンクリート13を打設するため、鋼製のレール(図示せず)上を移動可能になっている。図示するように、セントルCは、トンネルTの延伸方向に延びてトンネルTの横断方向に湾曲した内型枠Caと、セントルCの妻側においてトンネル横断方向外側にはみ出すように設置されたフランジCbとを備えている。そして、当該セントルCを移動させながら、セントルCと吹付けコンクリート12との空間13gに覆工コンクリート13を打設している。 Here, the placement of the lining concrete 13 will be described with reference to FIG. As shown, the center C is a semi-cylindrical formwork that can be moved on steel rails (not shown) to cast the lining 13 in the shotcrete 12 portion of the tunnel T. It has become. As shown in the figure, the center C consists of an inner formwork Ca that extends in the extension direction of the tunnel T and is curved in the transverse direction of the tunnel T, and a flange Cb that is installed on the gable side of the center C so as to protrude outward in the tunnel transverse direction. and Then, while moving the center C, the lining concrete 13 is placed in the space 13 g between the center C and the shotcrete 12 .

すなわち、図3(a)に示すように、セントルCの内型枠Caを移動させて覆工コンクリートの打設位置(つまり、吹付けコンクリート12が打設された位置)に設置したならば、図3(b)に示すように、内型枠Caの妻側にフランジCbを取り付ける。続いて、打設したコンクリートがセントルCの妻側から流出することを防止するために、図3(c)に示すように、フランジCbに沿った内型枠Caと吹付けコンクリート12との間に流出防止部材14(詳細は後述する)を設置して妻側の内型枠Caと吹付けコンクリート12との間を閉塞する。そして、図3(d)に示すように、内型枠Caと吹付けコンクリート12とで形成された空間13gに覆工コンクリート13を打設する。 That is, as shown in FIG. 3(a), when the inner formwork Ca of the center C is moved and installed at the position where the lining concrete is placed (that is, the position where the shotcrete 12 is placed), As shown in FIG. 3(b), a flange Cb is attached to the gable side of the inner formwork Ca. Subsequently, in order to prevent the placed concrete from flowing out from the gable side of the center C, as shown in FIG. An outflow prevention member 14 (details will be described later) is installed to close the space between the inner formwork Ca on the gable side and the shotcrete 12 . Then, as shown in FIG. 3(d), the lining concrete 13 is placed in the space 13g formed by the inner formwork Ca and the shotcrete 12. Then, as shown in FIG.

ここで、覆工コンクリート13を打設充填する際に、流出防止部材14が覆工コンクリート13に押されても、当該流出防止部材14の側面がフランジCbに押圧されて移動が阻止されるので、流出防止部材14がセントルCの妻側から落下することはない。このように、フランジCbは、覆工コンクリート13の打設時に、流出防止部材14がセントルCの妻側から落下しないように支える機能を果たしている。 Here, even if the outflow prevention member 14 is pushed by the lining concrete 13 when the lining concrete 13 is placed and filled, the side surface of the outflow prevention member 14 is pressed by the flange Cb and the movement is prevented. , the outflow preventing member 14 does not drop from the gable side of the center C. Thus, the flange Cb has a function of supporting the outflow prevention member 14 so that it does not fall from the gable side of the center C when the lining concrete 13 is placed.

なお、覆工コンクリート13の打設に際しては、図3(d)に示すように、下から順番にコンクリートを注入して、最後に天井の部分にコンクリートを吹き上げて注入する。また、本実施の形態において、一度に覆工コンクリート13を注入する長さは、例えば10~15m程度、覆工コンクリート13の厚さは、例えば30cm以上である。但し、本発明における覆工コンクリート13の数値は、これらに限定されるものではない。 When placing the lining concrete 13, as shown in FIG. 3(d), the concrete is poured in order from the bottom, and finally the concrete is blown up and poured into the ceiling. Further, in the present embodiment, the length of the lining concrete 13 poured at one time is, for example, about 10 to 15 m, and the thickness of the lining concrete 13 is, for example, 30 cm or more. However, the numerical values of the lining concrete 13 in the present invention are not limited to these.

また、本実施の形態では内型枠CaにフランジCbを取り付けているが、内型枠CaとフランジCbとが一体になっていて、フランジCbの取り付けが省略できるようになっていてもよい。 Moreover, although the flange Cb is attached to the inner formwork Ca in the present embodiment, the inner formwork Ca and the flange Cb may be integrated so that the attachment of the flange Cb can be omitted.

次に、覆工コンクリート13を打設する際に設置される流出防止部材14について、図4~図10を用いて説明する。 Next, the outflow prevention member 14 installed when the lining concrete 13 is placed will be described with reference to FIGS. 4 to 10. FIG.

図4は山岳トンネルの施工における覆工コンクリートの打設に際して設置される本発明の一実施の形態としての流出防止部材を含めたトンネル延伸方向の断面図、図5は図4のW-W線に沿った断面図、図6は流出防止部材に用いられた押出発泡ポリスチレンフォームを示す斜視図である。 FIG. 4 is a cross-sectional view in the tunnel extension direction including an outflow prevention member as one embodiment of the present invention installed when lining concrete is placed in the construction of a mountain tunnel, and FIG. 5 is the WW line of FIG. FIG. 6 is a perspective view showing extruded polystyrene foam used for the outflow prevention member.

図4および図5に示すように、流出防止部材14は、所定の厚みを有する長尺板状部材である押出発泡ポリスチレンフォームPFを設置するとともに、長尺状のエアバルクABを膨張させて設置したものである。また、押出発泡ポリスチレンフォームPFが内型枠Ca側に設置され、エアバルクABが吹付けコンクリート12側に設置されている。 As shown in FIGS. 4 and 5, the outflow prevention member 14 is provided by installing an extruded polystyrene foam PF, which is a long plate-shaped member having a predetermined thickness, and expanding a long air bulk AB. It is. Also, an extruded polystyrene foam PF is installed on the inner formwork Ca side, and an air bulk AB is installed on the shotcrete 12 side.

ここで、押出発泡ポリスチレンフォームPFとは、ポリスチレンを溶解し、発泡剤や難燃剤などを混ぜて板状に押出形成した板状部材である(図6(a)参照)。この押出発泡ポリスチレンフォームPFは、製造段階で所望のサイズに加工することができるのみならず、作業現場でも簡単にカットができ、さらに、断熱性能が高く、水・湿気に強く、軽量であるために取り扱いが容易である。なお、押出発泡ポリスチレンフォームPFは、長さ910mm、幅225mm、厚さ50mmとなっているが、寸法は特に限定されるものではない。 Here, the extruded polystyrene foam PF is a plate-like member obtained by dissolving polystyrene and mixing it with a foaming agent, a flame retardant, etc. and extruding it into a plate shape (see FIG. 6(a)). This extruded polystyrene foam PF not only can be processed to the desired size at the manufacturing stage, but can also be easily cut at the work site. Furthermore, it has high heat insulation performance, is resistant to water and moisture, and is lightweight. easy to handle. The extruded polystyrene foam PF has a length of 910 mm, a width of 225 mm, and a thickness of 50 mm, but the dimensions are not particularly limited.

本実施の形態では、このような押出発泡ポリスチレンフォームPFを内型枠Caに沿うようにして(つまり、押出発泡ポリスチレンフォームPFの長手方向がトンネルTの周方向となるようにして)3層設置し、その上に(つまり、吹付けコンクリート12側に)空気の入っていないエアバルクABを1層配置して膨張させることで、エアバルクABの膨張を利用して当該エアバルクABと押出発泡ポリスチレンフォームPFとで妻側の内型枠Caと吹付けコンクリート12との間を閉塞したものである。 In the present embodiment, such extruded polystyrene foam PF is arranged along the inner mold Ca (that is, so that the longitudinal direction of the extruded polystyrene foam PF is the circumferential direction of the tunnel T). Then, by placing one layer of air-free air bulk AB on it (that is, on the shotcrete 12 side) and expanding it, the air bulk AB and the extruded polystyrene foam PF are combined by using the expansion of the air bulk AB The gap between the inner formwork Ca on the gable side and the shotcrete 12 is blocked by the above.

なお、以下に説明する図7、図8を含め、押出発泡ポリスチレンフォームPFは3層設置されているが、3層である必要はない。つまり、押出発泡ポリスチレンフォームPFの設置数は、1枚の押出発泡ポリスチレンフォームPFの厚さ、膨張時のエアバルクABの径、および妻側の内型枠Caと吹付けコンクリート12との距離に応じて決定されることから、必ずしも3層となるものではなく、少なくとも1層設置されていればよい。但し、エアバルクABについては、1層のみ配置される。 In addition, three layers of the extruded polystyrene foam PF are installed including FIG. 7 and FIG. 8 described below, but it is not necessary to have three layers. That is, the number of extruded polystyrene foams PF to be installed depends on the thickness of one extruded polystyrene foam PF, the diameter of the air bulk AB when expanded, and the distance between the inner formwork Ca on the gable side and the shotcrete 12. Therefore, it is not always necessary to have three layers, and at least one layer may be installed. However, for the air bulk AB, only one layer is arranged.

なお、内型枠Caにおけるトンネル横断方向の長さと押出発泡ポリスチレンフォームPFの長さによっては、押出発泡ポリスチレンフォームPFを1層配置するのに、当該押出発泡ポリスチレンフォームPFが1枚で足りる場合もあるし、複数枚必要となる場合もある。同様に、エアバルクABについても、1層配置するのに1枚で足りる場合もあるし、複数枚必要となる場合もある。 Depending on the length of the inner formwork Ca in the transverse direction of the tunnel and the length of the extruded polystyrene foam PF, one extruded polystyrene foam PF may be sufficient for arranging one layer of the extruded polystyrene foam PF. Yes, and you may need more than one. Similarly, for the air bulk AB, one sheet may be sufficient for arranging one layer, and a plurality of sheets may be required.

このような本実施の形態によれば、押出発泡ポリスチレンフォームPFはトンネルTの延伸方向に対して平坦な形状となるため、押出発泡ポリスチレンフォームPFとエアバルクABとを重ねて設置することにより、円柱状のエアバルクABの上に円柱状のエアバルクABを載せた場合のように曲面を曲面で支える(図11参照)ことがなくなるので、エアバルクABが安定して施工性が向上する。 According to this embodiment, since the extruded polystyrene foam PF has a flat shape with respect to the extending direction of the tunnel T, by stacking the extruded polystyrene foam PF and the air bulk AB, a circular shape can be obtained. Since there is no need to support a curved surface with a curved surface (see FIG. 11) as in the case where a columnar air bulk AB is placed on top of a columnar air bulk AB, the air bulk AB is stabilized and workability is improved.

また、軽量で取り扱いが容易な押出発泡ポリスチレンフォームPFを用いることにより、重量の嵩むエアバルクABの使用が最小限で済むので、設置時の作業性が向上する。 In addition, by using the extruded polystyrene foam PF, which is lightweight and easy to handle, the use of the heavy air bulk AB can be minimized, thereby improving the workability at the time of installation.

これにより、セントルCの内型枠Caと吹付けコンクリート12との間に覆工コンクリート13を打設する際におけるセントルCの妻側からのコンクリートの流出を簡便に防止することが可能になる。 This makes it possible to easily prevent concrete from flowing out from the gable side of the center C when the lining concrete 13 is placed between the inner formwork Ca of the center C and the shotcrete 12 .

なお、図4および図5に示す場合には、押出発泡ポリスチレンフォームPFが内型枠Ca側に設置され、エアバルクABが吹付けコンクリート12側に設置されているので、膨張により吹付けコンクリート12の凹凸に対する追随性が良好となり、妻側の内型枠Caと吹付けコンクリート12との間をより強固に閉塞することが可能になる。 4 and 5, the extruded polystyrene foam PF is installed on the inner formwork Ca side, and the air bulk AB is installed on the shotcrete 12 side. The conformability to unevenness is improved, and the space between the inner formwork Ca on the gable side and the shotcrete 12 can be closed more firmly.

なお、図6(a)に示すように、押出発泡ポリスチレンフォームPFをそのまま使用することもできるが、以下に説明する図7~図10を含め、図6(b)に示すように押出発泡ポリスチレンフォームPFの片面に、あるいは図6(c)に示すように押出発泡ポリスチレンフォームPFの両面に、トンネルTの延伸方向に沿った切り欠きPFcを所定の間隔で形成してもよい。一例を挙げると、前述した本実施の形態の押出発泡ポリスチレンフォームPFの寸法(長さ910mm、幅225mm、厚さ50mm)の場合、30mm間隔で深さ10mmの切り欠きPFcを形成する。また、両面に形成する場合には、切り欠きPFcが双方の面で交互になるようにする。 As shown in FIG. 6(a), the extruded polystyrene foam PF can be used as it is. However, as shown in FIG. 6(b), including FIGS. On one side of the foam PF, or on both sides of the extruded polystyrene foam PF as shown in FIG. As an example, in the case of the dimensions of the extruded polystyrene foam PF of the present embodiment described above (length 910 mm, width 225 mm, thickness 50 mm), cutouts PFc having a depth of 10 mm are formed at intervals of 30 mm. Moreover, when forming on both sides, the cutouts PFc are arranged alternately on both sides.

このように切り欠きPFcを形成すれば、押出発泡ポリスチレンフォームPFを内型枠Caの形状(トンネルTの形状)、あるいは後述する図7、図8に示すように、押出発泡ポリスチレンフォームPFを吹付けコンクリート12側に設置した場合には当該吹付けコンクリート12の形状に沿わせることが容易になり、妻側の内型枠Caと吹付けコンクリート12との間をより一層強固に閉塞することが可能になる。 By forming the notch PFc in this way, the extruded polystyrene foam PF is blown into the shape of the inner mold Ca (the shape of the tunnel T), or as shown in FIGS. When installed on the side of the shotcrete 12, it becomes easy to follow the shape of the shotcrete 12, and the gap between the inner formwork Ca on the gable side and the shotcrete 12 can be more firmly blocked. be possible.

なお、本実施の形態において、押出発泡ポリスチレンフォームPFの長手方向に沿った切り欠きPFcの断面形状は三角形となっているが、四角形など他の形状であってもよい。 In the present embodiment, the cross-sectional shape of the notch PFc along the longitudinal direction of the extruded polystyrene foam PF is triangular, but may be other shapes such as quadrilateral.

ここで、以下に説明する図7~図10を含め、押出発泡ポリスチレンフォームPFには、硬化した覆工コンクリート13との剥離性を向上させるための剥離処理を施すことが望ましい。剥離処理の具体例を挙げると、表面が剥離剤面となった粘着テープで押出発泡ポリスチレンフォームPFの全体を巻く処理、あるいは押出発泡ポリスチレンフォームPFの全体に剥離剤を塗布する処理などが考えられる。 Here, extruded polystyrene foam PF, including FIGS. 7 to 10 described below, is desirably subjected to a peeling treatment for improving the peelability from the hardened lining concrete 13 . Specific examples of the release treatment include a process of wrapping the entire extruded polystyrene foam PF with an adhesive tape having a release agent surface, or a process of applying a release agent to the entire extruded polystyrene foam PF. .

このようにすれば、硬化後の覆工コンクリート13が押出発泡ポリスチレンフォームPFに接着して当該押出発泡ポリスチレンフォームPFの端部がちぎれたりすることを防ぐことができ、脱型時の施工性の向上および複数回の再利用が可能になって耐久性の向上を図ることができる。また、一般的に、エアバルクABとよりも押出発泡ポリスチレンフォームPFの方が安価であるため、コスト削減を図ることができる。 In this way, it is possible to prevent the lining concrete 13 after hardening from adhering to the extruded polystyrene foam PF and tearing off the ends of the extruded polystyrene foam PF, and workability at the time of demolding. The durability can be improved by improving and reusing multiple times. In addition, since the extruded polystyrene foam PF is generally cheaper than the air bulk AB, the cost can be reduced.

なお、押出発泡ポリスチレンフォームPFを粘着テープで巻く場合には、当該押出発泡ポリスチレンフォームPFの短手方向に沿って巻くようにする。短手方向に沿って巻くことにより、押出発泡ポリスチレンフォームPFの長手方向に対して曲げにくくならない(つまり、内型枠Caに沿って曲げにくくならない)とともに、押出発泡ポリスチレンフォームPFの強度が向上する。 When the extruded polystyrene foam PF is wound with an adhesive tape, it is wound along the lateral direction of the extruded polystyrene foam PF. By winding along the lateral direction, the extruded polystyrene foam PF is not difficult to bend in the longitudinal direction (that is, it is not difficult to bend along the inner mold frame Ca), and the strength of the extruded polystyrene foam PF is improved. .

ここで、図4および図5に示す場合には、押出発泡ポリスチレンフォームPFが内型枠Ca側に設置され、エアバルクABが吹付けコンクリート12側に設置されているが、図7および図8に示すように、両者の設置位置を逆にして、エアバルクABが内型枠Ca側に設置され、押出発泡ポリスチレンフォームPFが吹付けコンクリート12側に設置されていてもよい。 Here, in the case shown in FIGS. 4 and 5, the extruded polystyrene foam PF is installed on the inner formwork Ca side, and the air bulk AB is installed on the shotcrete 12 side. As shown, the installation positions of both may be reversed so that the air bulk AB is installed on the inner formwork Ca side and the extruded polystyrene foam PF is installed on the shotcrete 12 side.

このようにすれば、重量の嵩むエアバルクABを、内型枠Caに載せるようになるので、作業者がエアバルクABを高い位置(つまり、押出発泡ポリスチレンフォームPFの上面)まで持ち上げる必要がなくなり、作業の軽減を図ることができる。 In this way, the heavy air bulk AB can be placed on the inner formwork Ca, so the operator does not need to lift the air bulk AB to a high position (that is, the upper surface of the extruded polystyrene foam PF). can be reduced.

また、図9および図10に示すように、エアバルクABを用いることなく、押出発泡ポリスチレンフォームPFのみで妻側の内型枠Caと吹付けコンクリート12との間を閉塞するようにしてもよい。なお、図示する場合には、押出発泡ポリスチレンフォームPFは3層設置されているが、3層である必要はない。つまり、押出発泡ポリスチレンフォームPFの設置数は、1枚の押出発泡ポリスチレンフォームPFの厚さ、および妻側の内型枠Caと吹付けコンクリート12との距離に応じて決定されることから、必ずしも3層となるものではなく、少なくとも1層設置されていればよい。 Alternatively, as shown in FIGS. 9 and 10, the gap between the gable-side inner formwork Ca and the shotcrete 12 may be closed only by the extruded polystyrene foam PF without using the air bulk AB. In addition, although three layers of the extruded polystyrene foam PF are installed in the drawing, it is not necessary to have three layers. In other words, the number of extruded polystyrene foams PF installed is determined according to the thickness of one extruded polystyrene foam PF and the distance between the gable-side inner formwork Ca and the shotcrete 12. It suffices that at least one layer is installed instead of three layers.

このようにすれば、重量の嵩むエアバルクABは不要になり、比較的軽量な押出発泡ポリスチレンフォームPFのみで妻側の内型枠Caと吹付けコンクリート12との間を閉塞することができるので、作業の軽減を図ることができる。 In this way, the heavy air bulk AB becomes unnecessary, and the space between the gable-side inner formwork Ca and the shotcrete 12 can be closed only by the relatively lightweight extruded polystyrene foam PF. Work can be reduced.

以上本発明者によってなされた発明を実施の形態に基づき具体的に説明したが、本明細書で開示された実施の形態はすべての点で例示であって、開示された技術に限定されるものではない。すなわち、本発明の技術的な範囲は、前記の実施の形態における説明に基づいて制限的に解釈されるものでなく、あくまでも特許請求の範囲の記載に従って解釈されるべきであり、特許請求の範囲の記載技術と均等な技術および特許請求の範囲の要旨を逸脱しない限りにおけるすべての変更が含まれる。 Although the invention made by the present inventor has been specifically described based on the embodiments, the embodiments disclosed in this specification are illustrative in all respects and are limited to the disclosed technology. isn't it. That is, the technical scope of the present invention should not be construed in a restrictive manner based on the description of the above embodiments, but should be construed according to the description of the scope of claims. All modifications are included as long as they do not deviate from the description technology and equivalent technology and the gist of the claims.

以上の説明では、本発明を、覆工コンクリートを打設する際におけるセントルの妻側の内型枠と吹付けコンクリートとの間の閉塞に適用した場合が示されているが、背面平滑型トンネルライニング工法(FILM(Flat Insulated Lining Method))にも適用することができる。背面平滑型トンネルライニング工法とは、吹付けコンクリートの凹凸部と内型枠に設置した防水シートとの空隙にモルタル等の裏込め材を充填して防水シートを全面接着する工法であり、当該工法において、妻側の内型枠と吹付けコンクリートとの間の閉塞に本発明を適用することが可能である。 In the above explanation, the case where the present invention is applied to blockage between the inner formwork on the gable side of the center and the shotcrete when the lining concrete is poured is shown. It can also be applied to a lining method (FILM (Flat Insulated Lining Method)). The smooth-back tunnel lining method is a construction method in which the gap between the uneven parts of the shotcrete and the waterproof sheet installed on the inner formwork is filled with a back-filling material such as mortar, and the waterproof sheet is adhered to the entire surface. , it is possible to apply the present invention to the closure between the gable side inner formwork and the shotcrete.

11 仮吹付けコンクリート
12 吹付けコンクリート
13 覆工コンクリート
13g 空間
14 流出防止部材
AB エアバルク
B ロックボルト
C セントル
Ca 内型枠
Cb フランジ
G 地山
PF 押出発泡ポリスチレンフォーム
PFc 切り欠き
S 鋼製支保工
T トンネル
11 Temporary shotcrete 12 Shotcrete 13 Lining concrete 13g Space 14 Outflow prevention member AB Air bulk B Rock bolt C Center Ca Inner formwork Cb Flange G Ground PF Extruded polystyrene foam PFc Notch S Steel support T Tunnel

Claims (7)

山岳トンネルの施工における覆工コンクリートの打設方法であって、
トンネルの延伸方向に延びてトンネルの横断方向に湾曲した内型枠および当該内型枠の妻側においてトンネル横断方向外側にはみ出すように設置されたフランジを備えたセントルを吹付けコンクリートが打設された位置に設置し、
前記フランジに沿った前記内型枠と前記吹付けコンクリートとの間に、所定の厚みを有する長尺板状部材である押出発泡ポリスチレンフォームを少なくとも1層設置するとともに、長尺状のエアバルクを膨張させて1層設置し、妻側の前記内型枠と前記吹付けコンクリートとの間を閉塞し、
前記内型枠と前記吹付けコンクリートとで形成された空間に覆工コンクリートを打設する、
ことを特徴とする覆工コンクリートの打設方法。
A method for placing lining concrete in the construction of a mountain tunnel, comprising:
Shotcrete is poured into a center provided with an inner formwork extending in the extension direction of the tunnel and curved in the transverse direction of the tunnel and a flange installed so as to protrude outward in the tunnel transverse direction on the gable side of the inner formwork. position and
At least one layer of extruded polystyrene foam, which is a long plate-shaped member having a predetermined thickness, is installed between the inner formwork and the shotcrete along the flange, and a long air bulk is inflated. and install one layer, closing the space between the inner formwork on the gable side and the shotcrete,
placing lining concrete in the space formed by the inner formwork and the shotcrete;
A method of placing lining concrete characterized by:
前記押出発泡ポリスチレンフォームが前記内型枠側に設置され、前記エアバルクが前記吹付けコンクリート側に設置されている、
ことを特徴とする請求項1記載の覆工コンクリートの打設方法。
wherein the extruded polystyrene foam is installed on the inner formwork side and the air bulk is installed on the shotcrete side;
The method for placing lining concrete according to claim 1, characterized in that:
前記押出発泡ポリスチレンフォームが前記吹付けコンクリート側に設置され、前記エアバルクが前記内型枠側に設置されている、
ことを特徴とする請求項1記載の覆工コンクリートの打設方法。
wherein the extruded polystyrene foam is installed on the shotcrete side and the air bulk is installed on the inner formwork side;
The method for placing lining concrete according to claim 1, characterized in that:
山岳トンネルの施工における覆工コンクリートの打設方法であって、
トンネルの延伸方向に延びてトンネルの横断方向に湾曲した内型枠および当該内型枠の妻側においてトンネル横断方向外側にはみ出すように設置されたフランジを備えたセントルを吹付けコンクリートが打設された位置に設置し、
前記フランジに沿った前記内型枠と前記吹付けコンクリートとの間に、所定の厚みを有する長尺板状部材である押出発泡ポリスチレンフォームを少なくとも1層設置して妻側の前記内型枠と前記吹付けコンクリートとの間を閉塞し、
前記内型枠と前記吹付けコンクリートとで形成された空間に覆工コンクリートを打設する、
ことを特徴とする覆工コンクリートの打設方法。
A method for placing lining concrete in the construction of a mountain tunnel, comprising:
Shotcrete is poured into a center provided with an inner formwork extending in the extension direction of the tunnel and curved in the transverse direction of the tunnel and a flange installed on the gable side of the inner formwork so as to protrude outward in the tunnel transverse direction. position and
At least one layer of extruded polystyrene foam, which is a long plate-shaped member having a predetermined thickness, is placed between the inner formwork and the shotcrete along the flange, and the inner formwork on the gable side is provided. Blocking the gap with the shotcrete,
placing lining concrete in the space formed by the inner formwork and the shotcrete;
A method of placing lining concrete characterized by:
前記押出発泡ポリスチレンフォームの片面または両面には、トンネルの延伸方向に沿った切り欠きが所定の間隔で形成されている、
ことを特徴とする請求項1~4の何れか一項に記載の覆工コンクリートの打設方法。
On one or both sides of the extruded polystyrene foam, notches are formed at predetermined intervals along the extending direction of the tunnel.
The method for placing lining concrete according to any one of claims 1 to 4, characterized in that:
前記押出発泡ポリスチレンフォームには、硬化した覆工コンクリートとの剥離性を向上させる剥離処理が施されている、
ことを特徴とする請求項1~5の何れか一項に記載の覆工コンクリートの打設方法。
The extruded polystyrene foam is subjected to a release treatment to improve release from the hardened lining concrete.
The method for placing lining concrete according to any one of claims 1 to 5, characterized in that:
前記剥離処理は、
表面が剥離剤面となった粘着テープで前記押出発泡ポリスチレンフォームの短手方向に沿って全体を巻く処理、
または前記押出発泡ポリスチレンフォームの全体に剥離剤を塗布する処理である、
ことを特徴とする請求項6記載の覆工コンクリートの打設方法。
The peeling treatment is
A process of wrapping the entire extruded polystyrene foam along the width direction with an adhesive tape having a release agent surface,
Or a process of applying a release agent to the entire extruded polystyrene foam,
The method for placing lining concrete according to claim 6, characterized in that:
JP2021150218A 2021-09-15 2021-09-15 Lining concrete placing method Pending JP2023042845A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP2021150218A JP2023042845A (en) 2021-09-15 2021-09-15 Lining concrete placing method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP2021150218A JP2023042845A (en) 2021-09-15 2021-09-15 Lining concrete placing method

Publications (1)

Publication Number Publication Date
JP2023042845A true JP2023042845A (en) 2023-03-28

Family

ID=85724093

Family Applications (1)

Application Number Title Priority Date Filing Date
JP2021150218A Pending JP2023042845A (en) 2021-09-15 2021-09-15 Lining concrete placing method

Country Status (1)

Country Link
JP (1) JP2023042845A (en)

Similar Documents

Publication Publication Date Title
KR101224880B1 (en) Tunneling Method and related Apparatus for TBM Excavation and Blasting for enlargement, using the Protector and the Muck Car
JP2023113780A (en) Method and system for constructing underground tunnel
JP2020084474A (en) Widening construction method of existing tunnel
JP2023545610A (en) tunnel drilling shield
JP4181980B2 (en) Tunnel construction method
JP2008308835A (en) Construction method for sidewall pilot tunnel type tunnel and its structure
JP6527056B2 (en) EXPORT SYSTEM AND EXPORT METHOD OF EXCAVATOR
JP2023042845A (en) Lining concrete placing method
JP4471521B2 (en) Shield construction method, large section tunnel and its construction method, and shield machine
JP7178243B2 (en) Tunnel lining construction method
JP6529378B2 (en) Invert construction method, tunnel construction method and Teruha crane for tunnel
JPH07127374A (en) Method for constructing tunnel
JP3888993B2 (en) Tunnel widening method
US4396313A (en) Method of forming flooring in tunnels
JPH04213695A (en) Segment for shield tunnel
JP2899880B1 (en) Tunnel construction equipment
JP2001003677A (en) Workstation type tunnel widening device and method
JP4705467B2 (en) Construction method of underground structure
JP2022125774A (en) Tunnel construction method
JP2022125772A (en) Tunnel construction method
JP2022125773A (en) Tunnel construction method
KR101612527B1 (en) Construction method for tunneling
JPH07119866A (en) Laying construction method of underground buried pipe
JP4374535B2 (en) Tunnel construction method
JP3996597B2 (en) Open shield machine and open shield method using it

Legal Events

Date Code Title Description
A621 Written request for application examination

Free format text: JAPANESE INTERMEDIATE CODE: A621

Effective date: 20230728

A977 Report on retrieval

Free format text: JAPANESE INTERMEDIATE CODE: A971007

Effective date: 20240229

A131 Notification of reasons for refusal

Free format text: JAPANESE INTERMEDIATE CODE: A131

Effective date: 20240307