JP4374535B2 - Tunnel construction method - Google Patents

Tunnel construction method Download PDF

Info

Publication number
JP4374535B2
JP4374535B2 JP2004208576A JP2004208576A JP4374535B2 JP 4374535 B2 JP4374535 B2 JP 4374535B2 JP 2004208576 A JP2004208576 A JP 2004208576A JP 2004208576 A JP2004208576 A JP 2004208576A JP 4374535 B2 JP4374535 B2 JP 4374535B2
Authority
JP
Japan
Prior art keywords
tunnel
excavated
lining
invert
construction method
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
JP2004208576A
Other languages
Japanese (ja)
Other versions
JP2006028867A (en
Inventor
勉 木内
雅之 清水
正憲 鈴木
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Shimizu Corp
Original Assignee
Shimizu Corp
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Shimizu Corp filed Critical Shimizu Corp
Priority to JP2004208576A priority Critical patent/JP4374535B2/en
Publication of JP2006028867A publication Critical patent/JP2006028867A/en
Application granted granted Critical
Publication of JP4374535B2 publication Critical patent/JP4374535B2/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Description

本発明はトンネルの築造方法、特にトンネルボーリングマシン等の全断面トンネル掘削機による効率的な施工が可能なトンネル築造方法に関する。   The present invention relates to a tunnel construction method, and more particularly to a tunnel construction method capable of efficient construction using a full-section tunnel excavator such as a tunnel boring machine.

周知のように、トンネルボーリングマシン(TBM)等の全断面トンネル掘削機によってトンネルを築造する場合、掘削壁面に対する覆工は現場にてコンクリートを打設することで行うことが一般的である。その一例としてたとえば特許文献1には、まずアーチ部に対してコンクリートを打設してアーチ部の覆工壁を先行施工し、次いで、インバート部に対してコンクリートを打設してインバート部の覆工を行うという工法が開示されている。   As is well known, when a tunnel is constructed by a full-section tunnel excavator such as a tunnel boring machine (TBM), the lining on the excavated wall surface is generally performed by placing concrete on the site. As an example, for example, in Patent Document 1, concrete is first placed on the arch part, and the lining part of the arch part is preceded, and then concrete is placed on the invert part to cover the invert part. A construction method of performing construction is disclosed.

また、この種のトンネル築造方法における掘削土の搬送手法として、たとえば特許文献2には延伸ベルトコンベアを用いるものが提案されている。
特開2001−173386号公報 特開平10−280883号公報
As a method for conveying excavated soil in this type of tunnel construction method, for example, Patent Document 2 proposes a method using a stretch belt conveyor.
JP 2001-173386 A Japanese Patent Laid-Open No. 10-280883

しかし、特許文献1に示されているようにインバート部にコンクリートを打設して覆工を行うことでは、工期が長くかかるばかりでなく複雑かつ特殊な型枠装置を必要とするので、必ずしも効率な施工が行えるものではない。なお、この種のトンネル築造方法においてもシールド工法と同様にセグメントを用いる場合があり、トンネル全周にわたってセグメントを組み立てることで覆工を行うようにすれば施工性を改善できるのであるが、その場合には施工コストの著しい増大が不可避であるので広く一般に採用できるものではない。   However, as shown in Patent Document 1, by placing concrete in the invert part and performing the lining, not only the construction period is long but also a complicated and special formwork device is required, so it is not always efficient. It is not something that can be done. In this type of tunnel construction method, there are cases where segments are used in the same way as the shield method, and workability can be improved if lining is performed by assembling the segments all around the tunnel. However, since a significant increase in construction cost is unavoidable, it cannot be widely adopted.

また、掘削土の搬送を延伸ベルトコンベアにより行う場合には、たとえばトラック搬送による場合に比較すれば効率的ではあるが、従来においては特許文献2に示されているように掘削機と延伸ベルトコンベアとの間に移動式ベルトコンベアを設置して、掘削機からの掘削土を移動式ベルトコンベアを介して延伸ベルトコンベアまで搬送するようにしており、したがって移動式ベルトコンベアを掘進に伴って盛り替えたり逐次退避させる必要があるので、必ずしも効率的な掘削土搬送を行えるものではない。   Further, when the excavated soil is transported by the stretching belt conveyor, it is more efficient than, for example, the case of truck transportation. Conventionally, as shown in Patent Document 2, the excavator and the stretching belt conveyor are used. A mobile belt conveyor is installed between them and the excavated soil from the excavator is transported to the stretching belt conveyor via the mobile belt conveyor, so the mobile belt conveyor is refilled as it digs. Therefore, it is not always possible to efficiently carry excavated soil.

上記事情に鑑み、本発明は施工コストの増大を回避しつつ特にインバート部の覆工を効率的に行うことが可能であり、しかも延伸ベルトコンベアによる掘削土のより効率的な搬送を可能とする合理的なトンネル築造方法を提供することを目的としている。   In view of the above circumstances, the present invention can efficiently cover the invert part while avoiding an increase in construction cost, and enables more efficient transport of excavated soil by a stretch belt conveyor. The purpose is to provide a reasonable tunnel construction method.

本発明は、全断面トンネル掘削機を掘進させつつその後方において覆工装置群を掘進に追従させて前進させていくことにより掘削壁面を覆工するトンネルの築造方法において、延伸ベルトコンベアの先端部のテールプーリーを搭載した掘削土投入台車を全断面トンネル掘削機の背後に配置して、掘削土を掘削土投入台車に投入して延伸ベルトコンベアによって坑口まで連続搬送するとともに、掘進に追従させて掘削土投入台車を前進させていくことにより延伸ベルトコンベアを延伸していき、その掘削土投入台車の後方に前記覆工装置群を配置してそれら覆工装置群を掘削土投入台車とともに掘進に追従させて前進させていくことにより、インバート部に対してインバートセグメントを設置するとともに、その後方においてアーチ部に対する覆工壁としてのアーチコンクリートをインバートセグメントに連続するように打設形成していくことを基本とするものである。 The present invention relates to a tunnel construction method for lining a drilling wall surface by advancing a full-section tunnel excavator while advancing a lining device group following the excavation behind the full-section tunnel excavator. The excavated soil loading trolley equipped with the tail pulley is placed behind the full-section tunnel excavator, the excavated soil is loaded into the excavated soil throwing cart and continuously conveyed to the wellhead by the stretch belt conveyor, and the excavation is followed The stretch belt conveyor is extended by advancing the excavated soil throwing cart, the lining device group is arranged behind the excavated soil throwing cart, and the lining device group is excavated together with the excavated soil throwing cart. By moving it forward and following it, an invert segment is installed for the invert part, and behind it, It is an basic that they would Da設formed continuously arch concrete as Kokabe to invert the segment.

そして、本発明においては、覆工装置群として、インバート部にインバートセグメントを設置するエレクターと、アーチ部の掘削壁面にシート材を貼付するシート貼り台車と、貼付したシート上に鉄筋を配筋する配筋台車と、アーチ部に型枠を対向配置する移動式型枠装置とを採用し、前記エレクターによって前記掘削土砂投入台車の後方にインバートセグメントを施工するとともに、それら覆工装置群を施工済みのインバートセグメント上にその順で配列して同期させて前進させていくことを特徴とする。 In the present invention, as the lining device group, an erector that installs an invert segment in the invert part, a sheet pasting cart that affixes a sheet material on the excavation wall surface of the arch part, and a reinforcing bar is arranged on the pasted sheet. Adopting a bar arrangement and a movable formwork device with the formwork facing the arch , the invert segment is constructed behind the excavated sediment loading trolley by the erector, and these lining equipment groups have already been constructed. It is characterized in that it is arranged in that order on the invert segments of this and is advanced in synchronization .

本発明においては、インバートセグメント上に路盤を施工し、覆工装置群を路盤上に配列して前進させるようにすると良い。   In the present invention, a roadbed is preferably constructed on the invert segment, and the lining device group is arranged on the roadbed and advanced.

本発明においては、全断面トンネル掘削機と掘削土投入台車との間に、掘削土の連続積み込み機と定量フィーダーとを配置して、全断面トンネル掘削機により掘削された掘削土をそれら連続積み込み機と定量フィーダーにより一定量ずつ連続的に掘削土投入台車に投入するとともに、それら連続積み込み機と定量フィーダーを掘進に追従させて掘削土投入台車とともに前進させていくと良い。   In the present invention, an excavating soil continuous loader and a quantitative feeder are arranged between the full-section tunnel excavator and the excavated soil loading cart, and the excavated soil excavated by the full-section tunnel excavator is continuously loaded. It is preferable that a fixed amount is continuously fed into the excavated soil loading cart by the machine and the quantitative feeder, and the continuous loading machine and the quantitative feeder are moved forward along with the excavating soil loading cart.

本発明においては、全断面トンネル掘削機による掘削に先立ってその中心位置に小径のパイロットトンネルを先行掘削し、パイロットトンネルの内側からの作業により、全断面トンネル掘削機により掘削するべき掘削断面よりも外側の地山に対する止水改良を行い、しかる後に、全断面トンネル掘削機を掘進させてパイロットトンネルの周囲地山を環状に掘削してパイロットトンネルを拡径すると良い。   In the present invention, prior to excavation by the full-section tunnel excavator, a small-diameter pilot tunnel is excavated at the center of the excavation section, and the excavation cross section to be excavated by the full-section tunnel excavator is obtained by work from the inside of the pilot tunnel. It is recommended to improve the water stop for the outer ground and then expand the diameter of the pilot tunnel by excavating a full-section tunnel excavator and excavating the surrounding ground of the pilot tunnel in an annular shape.

本発明によれば、インバート部をセグメントにより早期に覆工できるばかりでなく、それを作業路床としてアーチ部の覆工に早期に着手して効率的な覆工作業を行うことができ、全体として覆工作業の施工効率を大きく向上させることができ、未覆工区間を短縮することができる。そして、トンネル全周の1/3程度のインバート部のみをセグメント覆工するに留めるので、シールド工法のように全周にわたってセグメントを設置する場合に比較すればコスト増を充分に抑制することができる。したがって本発明は、セグメント覆工による優れた施工性と、場所打ちコンクリートによる覆工の経済性という双方の利点を併せ持つものであり、特に大断面長大トンネルの施工に適用して好適である。   According to the present invention, not only can the inverted portion be lined up early by the segment, but it can be used as a work roadbed to start the arched portion at an early stage for efficient lining work. As a result, the construction efficiency of the lining work can be greatly improved, and the uncovered section can be shortened. Since only the invert part of about 1/3 of the entire circumference of the tunnel is covered with the segment, the cost increase can be sufficiently suppressed as compared with the case where the segment is installed over the entire circumference as in the shield method. . Therefore, the present invention has both the advantages of excellent workability by segment lining and economical efficiency of lining by cast-in-place concrete, and is particularly suitable for application to construction of large-section and long-sized tunnels.

また、覆工装置群としては、インバートセグメントを設置するエレクター以外は在来のアーチコンクリートの施工手段をそのまま採用可能であるし、在来の作業手順により効率的な覆工作業を実施することができる。   In addition, as the lining equipment group, conventional arch concrete construction means other than the erector for installing the invert segment can be adopted as they are, and efficient lining work can be carried out by the conventional work procedure. it can.

また、インバートセグメント上に路盤を施工して覆工装置群をその路盤上に配列して前進させることにより、路盤の早期施工が可能であるし、覆工作業のための安定な作業路床を早期に確保することが可能であり、より効率的である。   In addition, by constructing the roadbed on the invert segment and arranging the lining device group on the roadbed and moving it forward, the roadbed can be installed early, and a stable workbed for lining work can be created. It can be secured early and is more efficient.

また、掘削土の搬送を延伸ベルトコンベアで行うことにより効率的な掘削土搬送が可能であることはもとより、掘削土を連続積み込み機と定量フィーダーによって一定量ずつ掘削土投入台車に投入することにより、それらを掘進に追従して単に前進させていくことのみで、面倒な盛り替え作業等を必要とすることなく延伸ベルトコンベアを自ずと延伸させることができる。また、延伸ベルトコンベアを採用するために特殊な全断面トンネル掘削機を採用したり、そのための格別な構成を全断面トンネル掘削機に付加するような必要もない。   In addition, the excavated soil can be transported with a stretch belt conveyor, enabling efficient excavated soil transport. The stretching belt conveyor can be naturally stretched without requiring a troublesome replacement work or the like by simply moving them forward following the excavation. In addition, it is not necessary to employ a special full-section tunnel excavator in order to employ the stretch belt conveyor, or to add a special configuration for that purpose to the full-section tunnel excavator.

さらに、本設のトンネルの掘削に先立ってパイロットトンネルを先行掘削してその周囲に予め止水改良を行うことにより、全断面トンネル掘削機自体には高度の止水性能が要求されず、したがって湧水性地山に対して大断面トンネルを築造する場合にも開放型のトンネルボーリングマシン等の比較的簡便な構造の全断面トンネル掘削機の採用が可能となる。   Furthermore, prior to excavation of the main tunnel, the pilot tunnel is pre-excavated and the water stop is improved in advance around it, so that the full-section tunnel excavator itself is not required to have a high level of water stop performance. Even when constructing a large section tunnel in an aquifer, it is possible to adopt a full section tunnel excavator with a relatively simple structure such as an open tunnel boring machine.

本発明のトンネル築造方法の一実施形態を図1〜図3を参照して説明する。本実施形態のトンネル築造方法は、湧水性地山に対して大断面のトンネル1を築造するに際して、まず、そのトンネル1を築造するべき位置の中心部に小径のパイロットトンネル2を先行掘削し、そのパイロットトンネル2にはセグメント3による覆工を行う。そして、パイロットトンネル2の内側からの作業によってトンネル1の掘削予定断面よりも外側の地山を止水改良し、しかる後に、全断面トンネル掘削機4によりセグメント3を解体撤去しながらパイロットトンネル2を拡径(リーミング)する形態でその周囲を掘削して本設のトンネル1を築造する。   One embodiment of the tunnel construction method of the present invention will be described with reference to FIGS. In the tunnel construction method of this embodiment, when constructing a tunnel 1 having a large cross section with respect to a spring ground, first, a pilot tunnel 2 having a small diameter is first excavated at the center of the position where the tunnel 1 is to be constructed, The pilot tunnel 2 is covered with a segment 3. Then, the ground outside the planned excavation section of the tunnel 1 is stopped by the work from the inside of the pilot tunnel 2, and then the pilot tunnel 2 is disassembled and removed by the full-section tunnel excavator 4. The main tunnel 1 is constructed by excavating the surroundings in the form of reaming.

その際には、図1に示すように、パイロットトンネル2内に門形の搬送台車5を走行可能に設置し、それによりパイロットトンネル2の前方坑口から全断面トンネル掘削機4に対して資材を搬送する。また、搬送台車5の内側においてセグメント搬送台車6を走行可能とし、パイロットトンネル2から解体したセグメント3等の資材を前方に向けて搬送する。   In that case, as shown in FIG. 1, a portal-shaped transport cart 5 is installed in the pilot tunnel 2 so as to be able to travel, so that materials can be fed from the front entrance of the pilot tunnel 2 to the full-section tunnel excavator 4. Transport. In addition, the segment transport cart 6 can travel inside the transport cart 5, and materials such as the segment 3 disassembled from the pilot tunnel 2 are transported forward.

本実施形態において本設のトンネル1を掘削するための全断面トンネル掘削機4は、ノーズグリッパー7をパイロットトンネル2の内面に押圧せしめることでそこから反力をとって掘進する構成のトンネルボーリングマシン(TBM)であって、最前部に設けられているエレクター15によりパイロットトンネル2内のセグメント3を解体しつつ、環状のカッター8によりパイロットトンネル2を拡径するようにその周囲を環状に掘削して掘進するとともに、これに搭載されているロックボルト打設機9およびコンクリート吹き付け機10によって掘削後に直ちにトンネル内面に対してコンクリートを吹き付けるとともにロックボルトを打設して一次覆工を形成するものである。   In this embodiment, a full-section tunnel excavator 4 for excavating the main tunnel 1 is a tunnel boring machine having a structure in which a nose gripper 7 is pressed against the inner surface of the pilot tunnel 2 and a reaction force is taken from there. (TBM), while the segment 3 in the pilot tunnel 2 is disassembled by the erector 15 provided in the foremost part, the circumference of the pilot tunnel 2 is excavated in an annular shape so as to expand the diameter of the pilot tunnel 2 by the annular cutter 8 The concrete is sprayed immediately on the inner surface of the tunnel after excavation by the lock bolt driving machine 9 and the concrete spraying machine 10 mounted thereon and the lock bolt is driven to form a primary lining. is there.

また、本実施形態のトンネル築造方法では、掘削土の搬送を延伸ベルトコンベア11により行う。すなわち、図2に示すように全断面トンネル掘削機4の後方には連続積み込み機12、定量フィーダー13、掘削土投入台車14をその順で配置し、それらを全断面トンネル掘削機4の掘進に追従させて同期させて前進させていきつつ掘削土の搬送を行う。連続積み込み機12は全断面トンネル掘削機4から排出された掘削ズリを定量フィーダー13に送り込むものであり、定量フィーダー13はその掘削土を一定量ずつ掘削土投入台車14に投入するものである。   Moreover, in the tunnel construction method of this embodiment, excavation soil is conveyed by the stretch belt conveyor 11. That is, as shown in FIG. 2, a continuous loader 12, a quantitative feeder 13, and an excavating soil loading carriage 14 are arranged in this order behind the full-section tunnel excavator 4, and these are used for the excavation of the full-section tunnel excavator 4. The excavated soil is transported while following and synchronizing and moving forward. The continuous loader 12 feeds excavation gap discharged from the full-section tunnel excavator 4 to the quantitative feeder 13, and the quantitative feeder 13 inputs the excavated soil into the excavated soil input cart 14 by a certain amount.

掘削土投入台車14には延伸ベルトコンベア11の先端部のプーリーが搭載されていて、投入された掘削土はそのまま延伸ベルトコンベア11によって坑口まで連続搬送されるようになっている。その延伸ベルトコンベア11は、図3に示すように架台16ないしブラケット17により支持してトンネル1内の一方の側部に設置しておき、掘削土投入台車14の前進に伴ってベルトストレージ(図示せず)から余長ベルトが自ずと引き出されていって延伸ベルトコンベア11が自ずと前方に延伸されるようにしておく。   The excavated soil loading carriage 14 is equipped with a pulley at the tip of the stretching belt conveyor 11, and the loaded excavating soil is continuously conveyed to the wellhead as it is by the stretching belt conveyor 11. As shown in FIG. 3, the stretch belt conveyor 11 is supported by a gantry 16 or a bracket 17 and is installed on one side of the tunnel 1, and a belt storage (see FIG. (Not shown), the extra belt is naturally pulled out so that the stretch belt conveyor 11 is naturally stretched forward.

その後方では、覆工装置群20により覆工を行うが、本実施形態ではセグメントによる覆工と場所打ちの覆工壁による覆工を併用して行うこととし、図3に示すように、インバート部に対する覆工はインバートセグメント21により行い、アーチ部に対する覆工は現場においてインバートセグメント21に連続するようにアーチコンクリート22を形成することでそれを覆工壁とする。   On the rear side, lining is performed by the lining device group 20, but in this embodiment, the lining by the segment and the lining by the cast-in-place lining wall are performed in combination, and as shown in FIG. The lining for the part is performed by the invert segment 21, and the arching for the arch part is formed on the site by forming the arch concrete 22 so as to be continuous with the invert segment 21, thereby forming the lining wall.

本実施形態では、覆工装置群20としてエレクター23、シート貼り台車24、配筋台車25、移動式型枠装置26を採用し、エレクター23によってインバートセグメント23を施工していくとともに、施工済みのインバートセグメント23上にそれら覆工装置群20(エレクター23も含む)を切羽側からその順で配置して、上記の連続積み込み機12、定量フィーダー13、掘削土投入台車14と同様に、全断面トンネル掘削機4の掘進に追従させて同期させて前進させていきつつ覆工を行うものである。 In this embodiment, the erector 23, the sheet pasting cart 24, the reinforcing cart 25, and the movable formwork device 26 are adopted as the lining device group 20, and the invert segment 23 is constructed by the elector 23, and the construction has been completed. The lining device group 20 (including the erector 23) is arranged in that order from the face side on the invert segment 23 , and the entire cross section is the same as the continuous loader 12, the quantitative feeder 13, and the excavated soil throwing carriage 14. The lining is performed while the tunnel excavator 4 is moved forward in synchronization with the excavation of the tunnel excavator 4.

エレクター23はアーム23aによりインバートセグメント21を把持してインバート部に並べて設置していくものである。また、シート貼り台車24はアーチ部の掘削壁面に対してシート材を貼付するものであり、配筋台車25は貼付したシート上に鉄筋を配筋するものであり、移動式型枠装置26はアーチ部に型枠を対向配置するもの(いわゆるセントル)であり、これらシート貼り台車24、配筋台車25、移動式型枠装置26によって覆工壁としての鉄筋コンクリート造のアーチコンクリート22を効率的にかつ連続的に施工できるものとなっている。   The erector 23 is configured to hold the invert segment 21 by the arm 23a and arrange it in the invert portion. Further, the sheet pasting carriage 24 is for pasting a sheet material to the excavation wall surface of the arch part, the reinforcing bar carriage 25 is for placing a reinforcing bar on the pasted sheet, and the movable formwork device 26 is A formwork is arranged opposite to the arch (so-called centle), and the reinforced concrete arch concrete 22 as a lining wall is efficiently formed by the sheet pasting carriage 24, the reinforcing carriage 25, and the movable formwork device 26. And it can be constructed continuously.

なお、覆工装置群20の配置位置は既にエレクター23によってインバートセグメント21が設置済みであるが、そのインバートセグメント21上にはそれを設置した時点で直ちに路盤27を形成し、その路盤27上に覆工装置群20を配置する。路盤27は本設として設ければ良いが、あるいは仮設として設けることでも良い。路盤材料やその施工手法は適宜で良いが、たとえば鋼製架台やPCa部材をエレクター23を用いてインバートセグメント21上に設置することで路盤27を形成すれば施工性が良い。勿論、インバートセグメント21上にコンクリートを打設したり、あるいは掘削土を路盤材としてインバートセグメント上に撒き出することで路盤27を形成することも可能である。いずれにしても、必要であれば路盤施工用の適宜の装置をエレクター23に並設するかあるいはエレクター23とシート貼り装置24との間に配置すれば良い。   The invert segment 21 has already been installed by the erector 23 at the arrangement position of the lining device group 20, but a roadbed 27 is immediately formed on the invert segment 21 at the time of installation, and the roadbed 27 is placed on the roadbed 27. A lining device group 20 is arranged. The roadbed 27 may be provided as a permanent installation, or may be provided as a temporary installation. Although the roadbed material and its construction method may be appropriate, for example, if the roadbed 27 is formed by installing a steel mount or PCa member on the invert segment 21 using the erector 23, workability is good. Of course, it is also possible to form the roadbed 27 by placing concrete on the invert segment 21 or by rolling out the excavated soil as a roadbed material onto the invert segment. In any case, if necessary, an appropriate device for roadbed construction may be provided in parallel with the erector 23 or disposed between the erector 23 and the sheet pasting device 24.

本実施形態のトンネル築造方法によれば、インバート部のみをインバートセグメント21により覆工し、アーチ部に対してはコンクリートの場所打ちによる覆工壁としてのアーチコンクリート22を形成することで覆工を行うので、インバート部を早期に覆工できるばかりでなく、それを作業路床としてアーチ部の覆工に早期に着手して効率的な覆工作業を行うことができ、全体として覆工作業の施工効率を大きく向上させることができ、未覆工区間を短縮することができる。勿論、インバート部はトンネル全周の1/3程度に過ぎないから、シールド工法のように全周にわたってセグメントを設置する場合に比較すればコスト増を充分に抑制することができる。したがって本実施形態のトンネル築造方法は、セグメント覆工による優れた施工性と、場所打ちコンクリートによる覆工の経済性という双方の利点を併せ持つものであり、特に大断面かつ長大なトンネルの施工に適用して好適である。   According to the tunnel construction method of the present embodiment, only the invert portion is covered with the invert segment 21, and the arch portion is covered with the arch portion by forming the arch concrete 22 as the lining wall by placing the concrete in place. As a result, not only can the inverted part be lined up at an early stage, but it can also be used as a work roadbed to start the arched linen at an early stage for efficient lining work. The construction efficiency can be greatly improved, and the uncovered section can be shortened. Of course, since the invert portion is only about 1/3 of the entire circumference of the tunnel, the cost increase can be sufficiently suppressed as compared with the case where the segments are installed over the entire circumference as in the shield method. Therefore, the tunnel construction method of the present embodiment has both the advantages of excellent workability by segment lining and the economic efficiency of lining by cast-in-place concrete, and is particularly applicable to construction of large sections and long tunnels. It is preferable.

また、覆工装置群20としては、インバートセグメント21を設置するためのエレクター23以外は在来のアーチコンクリート22の施工手段であるシート貼り台車24、配筋台車25、移動式型枠装置26をそのまま採用可能であるし、その施工も在来どうり効率的に行うことができる。   Further, as the lining device group 20, a sheet pasting cart 24, a reinforcing cart 25, and a movable formwork device 26, which are construction means for conventional arch concrete 22, except for the erector 23 for installing the invert segment 21, are provided. It can be used as it is, and its construction can be done efficiently as usual.

また、インバートセグメント21を設置した後にその上部に仮設あるいは本設の路盤27を施工して、覆工装置群20をその路盤27上に配列して前進させるようにすれば、路盤27の早期施工が可能であるし、覆工作業のため安定な作業路床を早期に確保することが可能であり、より効率的である。   In addition, after the invert segment 21 is installed, a temporary or main roadbed 27 is installed on the upper portion thereof, and the lining device group 20 is arranged on the roadbed 27 to advance, so that the roadbed 27 can be installed early. It is possible to secure a stable work bed for lining work at an early stage, which is more efficient.

また、掘削土の搬送を延伸ベルトコンベア11で行うことにより効率的な掘削土搬送が可能であることはもとより、掘削土を連続積み込み機12と定量フィーダー13によって一定量ずつ掘削土投入台車14に投入するようにしたので、それらを掘進に追従して単に前進させていくことのみで、格別の盛り替え作業等を必要とすることなく延伸ベルトコンベア11を何ら面倒なく自ずと延伸させることができる。勿論、全断面トンネル掘削機4と延伸ベルトコンベア11との直接的な取り合いは考慮する必要がないから、延伸ベルトコンベア11を採用するがために全断面トンネル掘削機4に格別な構成を付加するような必要はなく、特に本実施形態のようなリーミング方式のトンネルボーリングマシンにも支障なく適用することが可能である。   In addition, the excavated soil can be efficiently conveyed by the stretching belt conveyor 11, and the excavated soil can be transferred to the excavated soil input carriage 14 by a continuous loader 12 and a quantitative feeder 13. Since they are put in, the belt conveyor 11 can be naturally stretched without any hassle by simply moving them forward following the excavation without requiring a special reordering operation. Of course, since it is not necessary to consider the direct connection between the full-section tunnel excavator 4 and the stretch belt conveyor 11, a special configuration is added to the full-section tunnel excavator 4 in order to employ the stretch belt conveyor 11. This is not necessary, and the present invention can be applied to the reaming tunnel boring machine as in this embodiment without any trouble.

さらに、本設のトンネル1の掘削に先立ってパイロットトンネル2を先行掘削してその周囲に予め止水改良を行うので、全断面トンネル掘削機4自体には高度の止水性能が要求されず、したがってその全断面トンネル掘削機4としては開放型のトンネルボーリングマシンのような比較的簡便な構造のものを採用可能である。   Furthermore, prior to excavation of the main tunnel 1, the pilot tunnel 2 is pre-excavated and the water stop is improved in advance around the pilot tunnel 2. Accordingly, the tunnel excavator 4 having a relatively simple structure such as an open-type tunnel boring machine can be adopted as the full-section tunnel excavator 4.

以上で本発明の一実施形態を説明したが、上記実施形態は好適な一例に過ぎず、本発明は上記実施形態に限定されることなく、工程の細部や使用する装置類の構成その他については、掘削するべきトンネルの規模や形態、地山状況その他の諸条件に応じて適宜の設計的変更を行えば良いことは言うまでもない。   Although one embodiment of the present invention has been described above, the above embodiment is merely a preferred example, and the present invention is not limited to the above embodiment, and details of processes, configurations of devices used, and the like are described. Needless to say, appropriate design changes may be made in accordance with the size and form of the tunnel to be excavated, the ground conditions, and other conditions.

本発明の実施形態であるトンネル築造方法を示すもので、最前部での工程を示す図である。The tunnel construction method which is embodiment of this invention is shown, and it is a figure which shows the process in the forefront part. 同、その後方での工程を示す図である。It is a figure which shows the process in the back as well. 同、図2における各部の断面図である。FIG. 3 is a cross-sectional view of each part in FIG.

符号の説明Explanation of symbols

1 トンネル
2 パイロットトンネル
3 セグメント
4 全断面トンネル掘削機
5 搬送台車
6 セグメント搬送台車
7 ノーズグリッパー
8 カッター
9 ロックボルト打設機
10 コンクリート吹き付け機
11 延伸ベルトコンベア
12 連続積み込み機
13 定量フィーダー
14 掘削土投入台車
15 エレクター
16 架台
17 ブラケット
20 覆工装置群
21 インバートセグメント
22 アーチコンクリート(覆工壁)
23 エレクター
23a アーム
24 シート貼り台車
25 配筋台車
26 移動式型枠装置
27 路盤
DESCRIPTION OF SYMBOLS 1 Tunnel 2 Pilot tunnel 3 Segment 4 Full-section tunnel excavator 5 Conveyor cart 6 Segment transport cart 7 Nose gripper 8 Cutter 9 Rock bolt placing machine 10 Concrete sprayer 11 Stretch belt conveyor 12 Continuous loader 13 Fixed feeder 14 Excavation soil input Carriage 15 Elector 16 Base 17 Bracket 20 Covering device group 21 Invert segment 22 Arch concrete (lining wall)
23 Electa 23a Arm 24 Sheet pasting cart 25 Reinforcement cart 26 Mobile formwork device 27 Roadbed

Claims (4)

全断面トンネル掘削機を掘進させつつその後方において覆工装置群を掘進に追従させて前進させていくことにより掘削壁面を覆工するトンネルの築造方法において、
延伸ベルトコンベアの先端部のテールプーリーを搭載した掘削土投入台車を全断面トンネル掘削機の背後に配置して、掘削土を掘削土投入台車に投入して延伸ベルトコンベアによって坑口まで連続搬送するとともに、掘進に追従させて掘削土投入台車を前進させていくことにより延伸ベルトコンベアを延伸していき、
その掘削土投入台車の後方に前記覆工装置群を配置してそれら覆工装置群を掘削土投入台車とともに掘進に追従させて前進させていくことにより、インバート部に対してインバートセグメントを設置するとともに、その後方においてアーチ部に対する覆工壁としてのアーチコンクリートをインバートセグメントに連続するように打設形成し、
前記覆工装置群として、インバート部にインバートセグメントを設置するエレクターと、アーチ部の掘削壁面にシート材を貼付するシート貼り台車と、貼付したシート上に鉄筋を配筋する配筋台車と、アーチ部に型枠を対向配置する移動式型枠装置とを採用し、前記エレクターによって前記掘削土砂投入台車の後方にインバートセグメントを施工するとともに、それら覆工装置群を施工済みのインバートセグメント上にその順で配列して同期させて前進させていくことを特徴とするトンネル築造方法。
In the tunnel construction method of lining the excavation wall surface by advancing the full-scale tunnel excavator while moving the lining device group following the excavation behind it,
The excavating soil loading cart equipped with the tail pulley at the tip of the stretching belt conveyor is placed behind the full-section tunnel excavator, the excavating soil is thrown into the excavating soil loading cart and continuously conveyed to the wellhead by the stretching belt conveyor By following the excavation, the excavating soil throwing carriage is moved forward to stretch the stretching belt conveyor.
The invert segment is installed in the invert portion by arranging the lining device group behind the excavated soil throwing carriage and moving the lining device group along with the excavating dirt throwing carriage to follow the excavation. with, an arch of concrete as lining wall with respect to the arch portion and Da設formed continuously to invert the segment at its rear,
As the lining device group, an erector that installs an invert segment in the invert part, a sheet affixing carriage that affixes a sheet material on the excavation wall surface of the arch part, a reinforcing bar that arranges reinforcing bars on the affixed sheet, and an arch Part formwork employs a movable mold device disposed opposite to, while applying a invert segments behind the excavating soil turned carriage by said erector, its them lining unit group on construction already invert segment A tunnel construction method characterized by arranging them in order and moving them forward in synchronization.
請求項1記載のトンネル築造方法において、
インバートセグメント上に路盤を施工し、覆工装置群を路盤上に配列して前進させることを特徴とするトンネル築造方法。
In the tunnel construction method of Claim 1 ,
A tunnel construction method comprising constructing a roadbed on an invert segment and arranging a group of lining devices on the roadbed to advance.
請求項1または2記載のトンネル築造方法において、
全断面トンネル掘削機と掘削土投入台車との間に、掘削土の連続積み込み機と定量フィーダーとを配置して、全断面トンネル掘削機により掘削された掘削土をそれら連続積み込み機と定量フィーダーにより一定量ずつ連続的に掘削土投入台車に投入するとともに、それら連続積み込み機と定量フィーダーを掘進に追従させて掘削土投入台車とともに前進させていくことを特徴とするトンネル築造方法。
In the tunnel construction method according to claim 1 or 2 ,
A continuous loader and fixed quantity feeder of excavated soil are arranged between the full section tunnel excavator and the excavated soil loading cart, and the excavated soil excavated by the full section tunnel excavator is transferred by the continuous loader and the fixed feeder. A tunnel construction method characterized in that a fixed amount is continuously fed into the excavated soil loading cart, and the continuous loader and the quantitative feeder are moved forward along with the excavating soil loading cart.
請求項1,2または3記載のトンネル築造方法において、
全断面トンネル掘削機による掘削に先立ってその中心位置に小径のパイロットトンネルを先行掘削し、
パイロットトンネルの内側からの作業により、全断面トンネル掘削機により掘削するべき掘削断面よりも外側の地山に対する止水改良を行い、
しかる後に、全断面トンネル掘削機を掘進させてパイロットトンネルの周囲地山を環状に掘削してパイロットトンネルを拡径することを特徴とするトンネル築造方法。
In the tunnel construction method according to claim 1, 2, or 3 ,
Prior to excavation with a full-section tunnel excavator, a pilot tunnel with a small diameter was excavated in the center of the tunnel,
By working from the inside of the pilot tunnel, the water stop improvement to the ground outside the excavation cross section to be excavated by the full section tunnel excavator,
Thereafter, the tunnel construction method is characterized in that a pilot tunnel is excavated and the ground around the pilot tunnel is excavated in an annular shape to expand the diameter of the pilot tunnel.
JP2004208576A 2004-07-15 2004-07-15 Tunnel construction method Active JP4374535B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP2004208576A JP4374535B2 (en) 2004-07-15 2004-07-15 Tunnel construction method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP2004208576A JP4374535B2 (en) 2004-07-15 2004-07-15 Tunnel construction method

Publications (2)

Publication Number Publication Date
JP2006028867A JP2006028867A (en) 2006-02-02
JP4374535B2 true JP4374535B2 (en) 2009-12-02

Family

ID=35895559

Family Applications (1)

Application Number Title Priority Date Filing Date
JP2004208576A Active JP4374535B2 (en) 2004-07-15 2004-07-15 Tunnel construction method

Country Status (1)

Country Link
JP (1) JP4374535B2 (en)

Families Citing this family (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP5037672B2 (en) * 2010-10-29 2012-10-03 鹿島建設株式会社 Construction equipment inside the tunnel
CN108316946B (en) * 2017-01-17 2021-07-13 中国葛洲坝集团路桥工程有限公司 Open type TBM synchronous lining method and device
CN109488322A (en) * 2018-11-28 2019-03-19 中铁工程装备集团有限公司 Tunnel inverted arch Rapid Excavation construction equipment and its construction method
KR102157220B1 (en) * 2019-11-06 2020-09-17 (주)호반산업 A method for simultaneous construction of concrete lining in tunnel excavation using TBM Boring Machine

Also Published As

Publication number Publication date
JP2006028867A (en) 2006-02-02

Similar Documents

Publication Publication Date Title
CN102787847B (en) Roadway tunneling machine
JP5444169B2 (en) Shield tunnel construction method
JP2007217911A (en) Construction method of underground cavity and tunnel construction method
CA2623698A1 (en) Method and system for mining hydrocarbon-containing materials
CN104405437A (en) Mining method employing solid filling and fully-mechanized coal mining hybrid working face
EA201270084A1 (en) UNDERGROUND MINING WORKS
TW201738454A (en) Method of constructing very large underground space and outer shield tunnel
JP4955828B1 (en) Shield type tunnel excavator
JP2014055509A (en) Construction method for shield tunnel
JP4374535B2 (en) Tunnel construction method
JP2007303155A (en) Construction method of underground cavity and tunnel construction method
JP2005171549A (en) Tunnel construction method
JP2017048588A (en) Excavated object carrying-out system and carrying-out method
CN112343613A (en) Construction method combining shield method and spray anchor support
JP2007314939A (en) Method of excavating ground
JP2017125334A (en) Lining assembling apparatus
JP6653497B2 (en) Construction method of traffic line shield tunnel and large section underground space
JP6241924B2 (en) Shield digging machine and its digging method
JP3831900B2 (en) Tunnel construction method
JP7162687B2 (en) Muddy transport system and tunnel excavation method
JP2022125773A (en) Tunnel construction method
JPH112095A (en) Method for tunnel constructing work
WO1999053173A1 (en) Tunneling device
JP2022125772A (en) Tunnel construction method
JP3689227B2 (en) Method of replacing soil removal means in tunnel excavator and tunnel excavator

Legal Events

Date Code Title Description
A621 Written request for application examination

Free format text: JAPANESE INTERMEDIATE CODE: A621

Effective date: 20070118

A977 Report on retrieval

Free format text: JAPANESE INTERMEDIATE CODE: A971007

Effective date: 20081028

A131 Notification of reasons for refusal

Free format text: JAPANESE INTERMEDIATE CODE: A131

Effective date: 20090414

A521 Written amendment

Free format text: JAPANESE INTERMEDIATE CODE: A523

Effective date: 20090526

TRDD Decision of grant or rejection written
A01 Written decision to grant a patent or to grant a registration (utility model)

Free format text: JAPANESE INTERMEDIATE CODE: A01

Effective date: 20090804

A01 Written decision to grant a patent or to grant a registration (utility model)

Free format text: JAPANESE INTERMEDIATE CODE: A01

A61 First payment of annual fees (during grant procedure)

Free format text: JAPANESE INTERMEDIATE CODE: A61

Effective date: 20090826

R150 Certificate of patent or registration of utility model

Ref document number: 4374535

Country of ref document: JP

Free format text: JAPANESE INTERMEDIATE CODE: R150

Free format text: JAPANESE INTERMEDIATE CODE: R150

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20120918

Year of fee payment: 3

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20120918

Year of fee payment: 3

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20130918

Year of fee payment: 4

S531 Written request for registration of change of domicile

Free format text: JAPANESE INTERMEDIATE CODE: R313531

R350 Written notification of registration of transfer

Free format text: JAPANESE INTERMEDIATE CODE: R350

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20140918

Year of fee payment: 5

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250