JP2023019402A - Worker assignment method, worker assignment program, and worker assignment system - Google Patents

Worker assignment method, worker assignment program, and worker assignment system Download PDF

Info

Publication number
JP2023019402A
JP2023019402A JP2021124093A JP2021124093A JP2023019402A JP 2023019402 A JP2023019402 A JP 2023019402A JP 2021124093 A JP2021124093 A JP 2021124093A JP 2021124093 A JP2021124093 A JP 2021124093A JP 2023019402 A JP2023019402 A JP 2023019402A
Authority
JP
Japan
Prior art keywords
work
worker
time
production line
workers
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
JP2021124093A
Other languages
Japanese (ja)
Inventor
有希 牛尾
Yuki Ushio
公久 安間
Kimihisa Amma
聖人 内田
Masahito Uchida
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Yamaha Motor Co Ltd
Original Assignee
Yamaha Motor Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Yamaha Motor Co Ltd filed Critical Yamaha Motor Co Ltd
Priority to JP2021124093A priority Critical patent/JP2023019402A/en
Publication of JP2023019402A publication Critical patent/JP2023019402A/en
Pending legal-status Critical Current

Links

Images

Classifications

    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02PCLIMATE CHANGE MITIGATION TECHNOLOGIES IN THE PRODUCTION OR PROCESSING OF GOODS
    • Y02P90/00Enabling technologies with a potential contribution to greenhouse gas [GHG] emissions mitigation
    • Y02P90/30Computing systems specially adapted for manufacturing

Abstract

To assign workers so that all works arisen in a substrate production facility which produces substrates can be terminated for a short period of time.SOLUTION: A worker assignment method that assigns workers to works arisen in a substrate production facility 2 which produces substrates includes a creating process of, when one or more works are arisen, creating a work plan, which specifies a worker to be assigned to each work and a working sequence of each work, on the basis of the position of each worker and the proficiency of each worker on the arisen work.SELECTED DRAWING: Figure 5

Description

本明細書で開示する技術は、作業者割り当て方法、作業者割り当てプログラム及び作業者割り当て装置に関する。 The technology disclosed in this specification relates to a worker assignment method, a worker assignment program, and a worker assignment device.

従来、基板を生産する基板生産設備において、基板生産設備で発生した作業を行う作業者を管理する方法が提案されている(例えば、特許文献1参照)。具体的には、特許文献1に記載の部品実装方法では、作業計画に従って実装基板を生産した場合の部品実装ラインの生産能力を、実装基板を生産するための作業を行うオペレータ(作業者に相当)の人数に応じて推定し、推定された生産能力が所定の目標生産能力以上であると判定されるオペレータの人数を部品実装ラインに割り当てる人数と決定する。 2. Description of the Related Art Conventionally, there has been proposed a method of managing a worker who performs work in a board production facility that produces boards (see, for example, Patent Document 1). Specifically, in the component mounting method described in Patent Document 1, the production capacity of the component mounting line when mounting boards are produced according to the work plan ), and the number of operators whose estimated production capacity is determined to be equal to or greater than a predetermined target production capacity is determined as the number of operators to be assigned to the component mounting line.

特開2020-25125号公報JP 2020-25125 A

しかしながら、基板生産設備で発生した作業を行う作業者を管理する従来の方法は、発生した作業を短時間で終了させる上で改善の余地があった。
本明細書では、基板を生産する基板生産設備で発生した全ての作業が短時間で終了するように作業者を割り当てる技術を開示する。
However, the conventional method of managing the workers who perform the work in the board production equipment has room for improvement in terms of completing the work in a short period of time.
This specification discloses a technique of allocating workers so that all the work that occurs in a board production facility that produces boards can be completed in a short time.

基板を生産する基板生産設備で発生した作業に作業者を割り当てる作業者割り当て方法であって、1以上の前記作業が発生した場合に、各前記作業者の位置と、発生した前記作業についての各前記作業者の習熟度とに基づいて、各前記作業に割り当てる前記作業者と各前記作業の作業順序とを表す作業計画を作成する作成工程を含む、作業者割り当て方法。 A worker assignment method for assigning workers to works occurring in board production equipment for producing boards, wherein when one or more of the above-mentioned works occur, each worker's position and each of the above-mentioned works that have occurred A method of assigning workers, comprising a creating step of creating a work plan representing the workers to be assigned to each work and the work order of each work based on the proficiency level of the workers.

基板を生産する基板生産設備で発生した全ての作業が短時間で終了するように作業者を割り当てることができる。 Workers can be assigned so that all the work that occurs in the board production equipment that produces the boards can be completed in a short period of time.

実施形態1に係る基板生産設備の模式図Schematic diagram of substrate production equipment according to Embodiment 1 作業者割り当て装置の電気的構成を示すブロック図Block diagram showing the electrical configuration of the worker assignment device 作業計画の作成の仕方の設定を説明するための模式図Schematic diagram for explaining how to create a work plan 作成例1に係る発生した作業を示す模式図Schematic diagram showing the work that occurred according to creation example 1 作成した作業計画の模式図Schematic diagram of the created work plan 作成例2に係る発生した作業を示す模式図Schematic diagram showing the work that occurred according to creation example 2 作成した作業計画の模式図Schematic diagram of the created work plan 作成例3に係る割り込み前の作業計画の模式図Schematic diagram of work plan before interruption according to creation example 3 割り込み後の作業計画の模式図Schematic diagram of work plan after interruption 作成例4に係る割り込み前の作業計画の模式図Schematic diagram of work plan before interruption according to creation example 4 割り込み後の作業計画の模式図Schematic diagram of work plan after interruption 作成例5に係る発生した作業を示す模式図Schematic diagram showing the work that occurred according to creation example 5 作成した作業計画(教育優先)の模式図Schematic diagram of the created work plan (prioritizing education) 作成例6に係る作業計画の模式図Schematic diagram of the work plan according to creation example 6 作業計画(余剰時間教育)の模式図Schematic diagram of work plan (surplus time education) 作成例7に係る発生した作業を示す模式図Schematic diagram showing the work that occurred according to creation example 7 作業計画(作業細分化する)の模式図Schematic diagram of work plan (subdivide work) 作業計画の作成及び送信のフローチャートWork plan creation and transmission flow chart

(本実施形態の概要)
(1)本開示に係る作業者割り当て方法は、基板を生産する基板生産設備で発生した作業に作業者を割り当てる作業者割り当て方法であって、1以上の前記作業が発生した場合に、各前記作業者の位置と、発生した前記作業についての各前記作業者の習熟度とに基づいて、各前記作業に割り当てる前記作業者と各前記作業の作業順序とを表す作業計画を作成する作成工程を含む。
(Outline of this embodiment)
(1) A worker assignment method according to the present disclosure is a worker assignment method that assigns workers to work that occurs in a board production facility that produces boards, wherein when one or more of the above-mentioned works occur, each of the above-mentioned a creation step of creating a work plan representing the worker to be assigned to each work and the work order of each work based on the position of the worker and the proficiency level of each worker with respect to the work that has occurred; include.

従来、基板を生産する基板生産設備で1以上の作業が発生した場合、どの作業者がどの作業を行うか、複数の作業をどのような順序で行うかなどを作業者(あるいは作業者を管理する管理者)が判断して対応していた。しかしながら、作業者が判断していたため判断が必ずしも適切に行われず、全ての作業が終了するまでに時間がかかることがあった。 Conventionally, when one or more operations occur in a circuit board production facility that produces circuit boards, it is necessary to manage the operators (or operators), such as which operator performs which operation and in what order the multiple operations are to be carried out. (administrator) made a decision and responded. However, since the judgment was made by the worker, the judgment was not necessarily made appropriately, and it sometimes took a long time to complete all the work.

上記の作業者割り当て方法によると、各作業者の位置と発生した作業についての各作業者の習熟度とに基づいて、各作業に割り当てる作業者と各作業の作業順序とを表す作業計画を作成する。このため上記の作業者割り当て方法によると、作業者(あるいは管理者)の判断によって対応する場合に比べ、基板生産設備で発生した全ての作業が短時間で終了するように作業者を割り当てることができる。 According to the worker assignment method described above, a work plan is created that indicates the worker to be assigned to each work and the order of work for each work, based on the position of each worker and the proficiency level of each worker with respect to the work that has occurred. do. For this reason, according to the above-described worker assignment method, workers can be assigned so that all the work occurring in the board production equipment can be completed in a short time, compared to the case where the worker (or manager) decides to respond. can.

(2)前記作成工程において、前記作業に割り当てられている作業者が異なる複数の前記作業計画を作成し、当該作業者割り当て方法は、前記作成工程で作成した複数の前記作業計画のうち発生した全ての前記作業が最も早く終了する前記作業計画を所定の送信先に送信する送信工程を含んでもよい。 (2) In the creation process, a plurality of work plans with different workers assigned to the work are created, and the worker assignment method is selected from among the plurality of work plans created in the creation process. A transmitting step of transmitting the work plan that completes all the work earliest to a predetermined destination may be included.

上記の作業者割り当て方法によると、作業に割り当てられている作業者が異なる複数の作業計画を作成し、作成した複数の作業計画のうち発生した全ての作業が最も早く終了する作業計画を所定の送信先に送信するので、発生した全ての作業が短時間で終了する可能性が高くなる。 According to the worker assignment method described above, a plurality of work plans with different workers assigned to the work are created, and the work plan that completes all the work that occurred the earliest among the created work plans is specified as a predetermined work plan. Since it will be sent to the destination, it is more likely that all the work that has occurred will be completed in a short time.

(3)前記作成工程において、前記作業者が前記作業の作業位置まで移動する移動時間を短くする観点の前記作業計画と、各前記作業の作業時間を短くする観点の前記作業計画とを作成してもよい。 (3) In the creation step, the work plan is created from the viewpoint of shortening the movement time for the worker to move to the work position of the work, and the work plan is created from the viewpoint of shortening the work time of each work. may

上記の「所定の送信先」は、例えば作業者が携帯する携帯端末であってもよいし、作業者の電子メールアドレスであってもよい。作業計画の送信先は作業者の携帯端末に限定されず、作業を管理する管理者が使用している端末装置あるいは管理者の電子メールアドレスであってもよい。
上記の作業者割り当て方法によると、移動時間だけを考慮して作業計画を作成する場合や、作業時間だけを考慮して作業計画を作成する場合に比べ、全ての作業が短時間で終了する可能性が高くなる。
The above-mentioned "predetermined destination" may be, for example, a mobile terminal carried by the worker, or an e-mail address of the worker. The transmission destination of the work plan is not limited to the mobile terminal of the worker, and may be the terminal device used by the manager who manages the work or the e-mail address of the manager.
According to the above worker assignment method, all work can be completed in a short time compared to creating a work plan that considers only travel time or work time. become more sexual.

(4)前記基板生産設備は前記基板を生産する生産ラインを複数有し、各前記作業者は担当する前記生産ラインが割り当てられており、当該作業者割り当て方法は、各前記作業者に当該作業者が担当する前記生産ラインの前記作業だけを割り当てるか、又は、担当する前記生産ライン以外の前記作業も割り当てるかの設定を受け付ける第1の受付工程を含み、前記作成工程において、担当する前記生産ラインの前記作業だけを割り当てる設定がされている場合は各前記作業者に当該作業者が担当する前記生産ラインの前記作業だけを割り当て、担当する前記生産ライン以外の前記作業も割り当てる設定がされている場合は担当する前記生産ライン以外の前記作業も割り当ててもよい。 (4) The circuit board production equipment has a plurality of production lines for producing the circuit boards, and each worker is assigned the production line to be in charge of, and the worker assignment method is such that each worker is assigned the work a first receiving step for receiving a setting as to whether to assign only the work of the production line that the worker is in charge of, or to also assign the work other than the production line that the worker is in charge of; If only the work on the line is set to be assigned, each worker is assigned only the work on the production line that the worker is in charge of, and the work other than the production line that the worker is in charge of is also set to be assigned. If there is, the work other than the production line in charge may be assigned.

上記の作業者割り当て方法によると、担当する生産ラインで発生した作業だけを割り当てるか、又は、担当する生産ライン以外の作業も割り当てるかのどちらかに固定されている場合に比べ、作業を割り当てる自由度が向上する。 According to the above worker assignment method, there is more freedom in assigning work compared to the case where only the work that occurred on the production line in charge is assigned or the work other than the production line in charge is also assigned. degree improves.

(5)前記基板生産設備は前記基板を生産する生産ラインを複数有し、当該作業者割り当て方法は、複数の前記生産ラインのうちいずれかの前記生産ラインの指定を受け付ける第2の受付工程を含み、各前記作業者が前記作業計画に従って前記作業を行っているときに前記第2の受付工程で指定された前記生産ラインで新たな作業が発生した場合は、前記作成工程において、指定された前記生産ライン以外の前記作業を行っている前記作業者に当該新たな作業を割り当てた作業計画を作成し直してもよい。 (5) The circuit board production equipment has a plurality of production lines for producing the circuit boards, and the worker assignment method includes a second receiving step of receiving designation of one of the plurality of production lines. and when a new work occurs on the production line specified in the second reception process while each worker is performing the work according to the work plan, in the creation process, the specified A work plan may be recreated in which the new work is assigned to the worker performing the work outside the production line.

上記の作業者割り当て方法によると、指定された生産ラインで発生した作業を、指定された生産ライン以外の作業を行っている作業者に割り当てるので、指定された生産ラインで発生した作業を短時間で終了できる。 According to the above worker assignment method, the work that occurred on the specified production line is assigned to the worker who is doing the work other than the specified production line, so the work that occurred on the specified production line can be terminated with

(6)前記作成工程において、指定された前記生産ライン以外の前記作業を行っている前記作業者の現在の前記作業を中断させて前記新たな作業を割り込ませてもよい。 (6) In the creation process, the current work of the worker who is performing the work other than the designated production line may be interrupted and the new work interrupted.

上記の作業者割り当て方法によると、指定された生産ライン以外で発生した作業を行っている作業者の現在の作業を中断させて新たな作業を割り込ませるので、指定された生産ラインで発生した作業を短時間で終了できる。 According to the above worker allocation method, the current work of workers who are doing work outside the designated production line is interrupted and new work is interrupted. can be completed in a short time.

(7)前記作成工程において、指定された前記生産ライン以外の前記作業を行っている前記作業者の現在の前記作業の後、当該作業者の次の前記作業の前に前記新たな作業を割り込ませてもよい。 (7) In the creation process, the new work is interrupted after the current work of the worker who is performing the work other than the designated production line and before the next work of the worker. You can let

上記の作業者割り当て方法によると、指定された生産ライン以外で発生した作業を行っている作業者の現在の作業の後、当該作業者の次の作業の前に新たな作業を割り込ませるので、指定された生産ラインで発生した作業を短時間で終了できる。 According to the worker assignment method described above, after the current work of a worker who is doing work that occurred outside the designated production line, and before the next work of that worker, a new work is interrupted. The work that occurred on the designated production line can be completed in a short time.

(8)発生した前記作業の習熟度が低い前記作業者に当該作業を優先して割り当てる教育優先を行うか否かの設定を受ける第3の受付工程を含み、前記教育優先を行う設定がされている場合は、前記作成工程において、発生した前記作業に当該作業の習熟度が相対的に低い前記作業者を優先して割り当ててもよい。 (8) including a third receiving step of receiving a setting as to whether or not to give priority to training for allocating the work with priority to the worker having a low proficiency level for the work, wherein the setting is made to give priority to training; If so, in the creation process, the worker with a relatively low proficiency level for the work may be preferentially assigned to the work that has occurred.

上記の作業者割り当て方法によると、ある作業の習熟度が低い作業者がいる場合に、その作業者に当該ある作業を割り当てることにより、当該ある作業についてのその作業者の習熟度を向上させることができる。 According to the worker assignment method described above, when there is a worker whose proficiency in a certain work is low, by assigning the worker to the work, the worker's proficiency in the work can be improved. can be done.

(9)余剰時間教育を行うか否かの設定を受け付ける第4の受付工程を含み、前記余剰時間教育を行う設定がされている場合は、前記作成工程において、目標時間内に全ての前記作業が終了する範囲で、発生した前記作業に当該作業の習熟度が相対的に低い前記作業者を優先して割り当ててもよい。 (9) including a fourth receiving step of receiving a setting as to whether or not to conduct extra-time education; may be preferentially assigned to the worker with a relatively low proficiency level for the work that has occurred, within the range where is completed.

ある作業の習熟度が低い作業者がいる場合に、教育のためにその作業者に当該ある作業を割り当てた場合、作業の習熟度が低いことから、目標時間内に全ての作業が終了しなくなる可能性がある。目標時間内に全ての作業が終了しないと基板生産設備が停止し、生産性が低下する可能性がある。
上記の作業者割り当て方法によると、全ての作業が終了する時間が目標時間を超えない範囲で作業者を教育できるので、生産性の低下を抑制しつつ作業者を教育できる。
If there is a worker with a low proficiency level for a certain task, and the worker is assigned to the task for training, all the tasks will not be completed within the target time due to the low proficiency level of the task. there is a possibility. If all the work is not completed within the target time, the board production equipment may stop and the productivity may decrease.
According to the worker assignment method described above, workers can be educated within a range in which the time required to complete all tasks does not exceed the target time, so it is possible to educate workers while suppressing a decrease in productivity.

(10)発生した前記作業を細分化して複数の前記作業者に割り当てる細分化を行うか否かの設定を受け付ける第5の受付工程を含み、細分化を行う設定がされており、且つ、前記作業者の数が前記作業の数より多い場合は、前記作成工程において、1つの前記作業を細分化して複数の前記作業者を割り当ててもよい。 (10) including a fifth receiving step of receiving a setting as to whether or not to subdivide the generated work and allocate it to a plurality of workers; If the number of workers is greater than the number of works, one work may be subdivided and a plurality of workers may be assigned in the creation process.

上記の作業者割り当て方法によると、作業者の数が作業の数より多い場合は1つの作業を細分化して複数の作業者を割り当てることにより、作業が終了する時間を短縮できる。 According to the worker assignment method described above, when the number of workers is greater than the number of works, by subdividing one work and allocating a plurality of workers, it is possible to shorten the time required to complete the work.

(11)前記作業者が前記作業を行った作業時間が当該作業の標準作業時間より長かった場合に、当該作業者について当該作業の教育が必要であることを所定の通知先に通知する第1の通知工程を含んでもよい。 (11) A first method for notifying a predetermined notification destination of the necessity of training the worker for the work when the work time for the work performed by the worker is longer than the standard work time for the work. may include a notification step of

ある作業について作業者の作業時間が標準作業時間より長い場合は、その作業者はその作業の習熟度が低く、教育が必要であるといえる。
上記の作業者割り当て方法によると、例えば所定の通知先として作業者を管理する管理者の端末を設定しておけば、管理者はどの作業者にどの作業の教育が必要であるかの判断が容易になる。
If the working time of a worker for a certain work is longer than the standard working time, it can be said that the worker is low in proficiency in the work and needs training.
According to the worker assignment method described above, for example, if a terminal of a manager who manages workers is set as a predetermined notification destination, the manager can determine which worker needs training for which task. become easier.

(12)前記作業の実際の作業時間が許容作業時間を超過した場合に、前記許容作業時間を超過したことを所定の通知先に通知する第2の通知工程を含んでもよい。 (12) The method may include a second notification step of notifying a predetermined notification destination of the fact that the allowable work time has been exceeded when the actual work time of the work exceeds the allowable work time.

ある作業者の作業の実際の作業時間が許容時間を超過した場合、そのままでは作業の遅れによって基板生産設備が停止する可能性がある。
上記の作業者割り当て方法によると、例えば所定の通知先として作業者を管理する管理者の端末を設定しておけば、管理者は許容時間を超過した作業を手伝うよう他の作業者に指示することにより、作業の遅れを抑制できる。
If the actual work time of a certain worker exceeds the allowable time, there is a possibility that the board production equipment will stop due to the work delay.
According to the above worker assignment method, for example, if the terminal of the manager who manages the worker is set as a predetermined notification destination, the manager instructs other workers to help with the work that exceeds the allowable time. By doing so, delays in work can be suppressed.

(13)各前記作業者について、前記作業毎に当該作業の累積作業時間及び当該作業の累積作業回数の少なくとも一方に基づいて当該作業の習熟度を更新する更新工程を含んでもよい。 (13) For each worker, the method may include an update step of updating the proficiency level of the work based on at least one of the cumulative work time of the work and the cumulative work count of the work for each work.

上記の作業者割り当て方法によると、作業者の習熟度を自動で更新できるので、作業者を管理する管理者が手作業で習熟度を更新する場合に比べて管理者の負担を軽減できる。 According to the worker assignment method described above, since the proficiency levels of workers can be automatically updated, the burden on the manager can be reduced compared to when the manager who manages the workers updates the proficiency levels manually.

[本開示の実施形態の詳細]
以下に、本開示の実施形態について説明する。本開示はこれらの例示に限定されるものではなく、特許請求の範囲によって示され、特許請求の範囲と均等の意味および範囲内での全ての変更が含まれることが意図される。
[Details of the embodiment of the present disclosure]
Embodiments of the present disclosure will be described below. The present disclosure is not limited to these examples, but is indicated by the scope of the claims, and is intended to include all modifications within the meaning and scope of equivalents of the scope of the claims.

本開示の実施形態は、装置、方法、これらの装置または方法の機能を実現するためのコンピュータプログラム、そのコンピュータプログラムを記録した記録媒体等の種々の態様で実現できる。 Embodiments of the present disclosure can be realized in various forms such as devices, methods, computer programs for realizing the functions of these devices or methods, and recording media recording the computer programs.

<実施形態1>
実施形態1を図1ないし図14に基づいて説明する。以降の説明では同一の構成要素には一部を除いて図面の符号を省略している場合がある。
<Embodiment 1>
Embodiment 1 will be described with reference to FIGS. 1 to 14. FIG. In the following description, the reference numerals in the drawings may be omitted except for some of the same components.

(1)基板生産設備
図1を参照して、実施形態1に係る基板生産設備2について説明する。基板生産設備2は基板を生産する生産ラインLを2ライン(生産ラインL1及びL2)備えている。各生産ラインLはローダー11、スクリーン印刷機12、印刷検査機13、ディスペンサ14、3台の表面実装機M(生産ラインL1の場合はM11、M12、M13、生産ラインL2の場合はM21、M22、M23)、実装後外観検査機15、リフロー装置16、硬化後外観検査機17及びアンローダー18を備えており、これらが複数のコンベア19を介して直列に接続されている。
(1) Substrate Production Equipment A substrate production equipment 2 according to the first embodiment will be described with reference to FIG. The substrate production facility 2 includes two production lines L (production lines L1 and L2) for producing substrates. Each production line L includes a loader 11, a screen printer 12, a print inspection machine 13, a dispenser 14, and three surface mounters M (M11, M12, M13 for production line L1, M21, M22 for production line L2). , M23), a post-mounting visual inspection machine 15, a reflow device 16, a post-curing visual inspection machine 17, and an unloader 18, which are connected in series via a plurality of conveyors 19.

各生産ラインLにはそれぞれその生産ラインLの作業を担当する作業者(生産ラインL1は作業者A、生産ラインL2は作業者B)が一人割り当てられている。1つの生産ラインLに割り当てられる作業者の数は二人以上であってもよい。
各作業者はそれぞれ携帯電話やタブレットコンピュータなどの携帯端末30(所定の送信先の一例)を携帯している。携帯端末30はアクセスポイント32を介して通信ネットワーク33に無線接続されている。携帯端末30はGPS(Global Positioning System)などの衛星測位システムから送信された電波を受信して携帯端末30の位置(言い換えると作業者の位置)を検出する位置検出センサ(例えばGPSセンサ)を備えている。携帯端末30の位置を検出する方法はこれに限られず、他の方法で検出してもよい。
Each production line L is assigned with one worker (worker A for the production line L1, worker B for the production line L2) who is in charge of the work of the production line L. The number of workers assigned to one production line L may be two or more.
Each worker carries a portable terminal 30 (an example of a predetermined destination) such as a mobile phone or a tablet computer. A mobile terminal 30 is wirelessly connected to a communication network 33 via an access point 32 . The mobile terminal 30 includes a position detection sensor (for example, a GPS sensor) that receives radio waves transmitted from a satellite positioning system such as GPS (Global Positioning System) and detects the position of the mobile terminal 30 (in other words, the position of the worker). ing. The method of detecting the position of the mobile terminal 30 is not limited to this, and other methods may be used.

管理者端末31(所定の通知先の一例)は各作業者を管理する管理者の端末である。管理者端末31は所謂パーソナルコンピュータであってもよいし、携帯電話やタブレットコンピュータなどの携帯端末であってもよい。
作業者割り当て装置1(コンピュータの一例)は生産ラインLで発生した作業に作業者を割り当てる装置である。
生産ラインLを構成している各装置、携帯端末30、管理者端末31及び作業者割り当て装置1は通信ネットワーク33を介して通信可能に接続されている。
A manager terminal 31 (an example of a predetermined notification destination) is a terminal of a manager who manages each worker. The administrator terminal 31 may be a so-called personal computer, or may be a mobile terminal such as a mobile phone or a tablet computer.
A worker allocation device 1 (an example of a computer) is a device that allocates workers to work that occurs on a production line L. FIG.
Each device constituting the production line L, the mobile terminal 30 , the manager terminal 31 and the worker assignment device 1 are communicably connected via a communication network 33 .

(2)生産ラインで発生する作業
生産ラインLでは各種の作業が発生する。例えばスクリーン印刷機12の場合は基板に印刷する半田ペーストを補給する作業や、スクリーン印刷機12の何らかのエラーに対処する作業などが発生する。例えば半田ペーストの量が所定量まで減少すると半田ペーストの補給作業が発生したことがスクリーン印刷機12から作業者割り当て装置1に通知される。何らかのエラーが発生した場合もエラー対処の作業が発生したことが作業者割り当て装置1に通知される。
(2) Work that occurs in the production line In the production line L, various types of work occur. For example, in the case of the screen printer 12, there are tasks such as replenishing solder paste to be printed on the board and coping with any errors in the screen printer 12. FIG. For example, when the amount of solder paste decreases to a predetermined amount, the screen printer 12 notifies the operator assignment device 1 that a solder paste replenishment operation has occurred. Even when some error occurs, the worker assignment device 1 is notified that work for coping with the error has occurred.

ディスペンサ14の場合は接着剤を補給する作業や、ディスペンサ14の何らかのエラーに対処する作業などが発生する。表面実装機Mの場合は部品を保持している部品テープが巻き回されているリールを交換する作業や、表面実装機Mの何らかのエラーに対処する作業などが発生する。 In the case of the dispenser 14, the work of replenishing the adhesive, the work of coping with some error of the dispenser 14, and the like occur. In the case of the surface mounter M, the work of replacing the reel around which the component tape holding the component is wound, the work of coping with some error of the surface mounter M, and the like occur.

理解を容易にするため、以降の説明では表面実装機Mで発生する作業を例に説明する。表面実装機Mでは種々のエラーが発生するが、以降の説明では表面実装機Mが備える実装ヘッドに関するエラーを例に説明する。表面実装機Mは部品テープや部品トレイなどによって供給される部品を実装ヘッドによって吸着し、部品を吸着している実装ヘッドを基板上の搭載位置に移動させて基板に部品を搭載する。その場合に、部品の吸着に失敗するエラー(以下、吸着エラーという)、部品を吸着している実装ヘッドを移動させているときに部品が落下するエラー(以下、部品落下エラーという)、吸着した部品が基板に搭載されず、実装ヘッドが部品を吸着したままで部品テープや部品トレイの位置まで戻ってくるエラー(以下、部品持ち帰りエラーという)などが発生する。 In order to facilitate understanding, in the following description, the work that occurs in the surface mounter M will be taken as an example. Various errors occur in the surface mounter M. In the following description, an error related to the mounting head provided in the surface mounter M will be described as an example. A surface mounter M picks up a component supplied from a component tape, a component tray, or the like by a mounting head, moves the mounting head picking up the component to a mounting position on the board, and mounts the component on the board. In that case, there will be an error where component pickup fails (hereinafter referred to as a pickup error), an error where a component drops while the mounting head that is picking up the component is being moved (hereinafter called a component drop error), and an An error occurs in which the component is not mounted on the board and the mounting head picks up the component and returns to the position of the component tape or the component tray (hereinafter referred to as component return error).

(3)作業者割り当て装置の電気的構成
図2を参照して、作業者割り当て装置1の電気的構成について説明する。作業者割り当て装置1は所謂パーソナルコンピュータであり、制御部40、記憶部41、通信部42(取得部の一例)、表示部43、操作部44などを備えている。
制御部40はCPU40AやRAM40Bなどを備えている。記憶部41はハードディスクなどの不揮発性の記憶媒体を備える記憶装置である。記憶部41には生産ラインLで発生した作業に作業者を割り当てる作業者割り当てプログラムなどの各種のプログラムや後述する各種のデータが記憶されている。制御部40は記憶部41に記憶されているプログラムを実行することによって作業者割り当て装置1の各部を制御する。通信部42は作業者割り当て装置1が携帯端末30などの他の装置と通信するための通信回路である。制御部40は通信部42を介して各携帯端末30から位置情報を受信(取得の一例)する。表示部43は液晶ディプレイなどの表示装置である。操作部44はキーボード、マウス、タッチパネルなどの入力装置である。
(3) Electrical Configuration of Worker Assignment Device The electrical configuration of the worker assignment device 1 will be described with reference to FIG. The worker assignment device 1 is a so-called personal computer, and includes a control section 40, a storage section 41, a communication section 42 (an example of an acquisition section), a display section 43, an operation section 44, and the like.
The control unit 40 includes a CPU 40A, a RAM 40B, and the like. The storage unit 41 is a storage device including a nonvolatile storage medium such as a hard disk. The storage unit 41 stores various programs such as a worker allocation program for allocating workers to work occurring on the production line L, and various data described later. The control unit 40 controls each unit of the worker assignment device 1 by executing programs stored in the storage unit 41 . The communication unit 42 is a communication circuit for the worker assignment device 1 to communicate with other devices such as the mobile terminal 30 . The control unit 40 receives (an example of acquisition) position information from each mobile terminal 30 via the communication unit 42 . The display unit 43 is a display device such as a liquid crystal display. The operation unit 44 is an input device such as a keyboard, mouse, and touch panel.

(4)記憶部に記憶されている各種のデータ
記憶部41に記憶されている各種のデータには習熟度テーブル、作業時間テーブル、標準/許容作業時間テーブル、生産ラインLを構成している各装置の位置を表す位置情報などが含まれる。以下、表1から表3を参照して、習熟度テーブル、作業時間テーブル、及び、標準/許容作業時間テーブルについて説明する。

Figure 2023019402000002
(4) Various data stored in the storage section Various data stored in the storage section 41 include a proficiency level table, a work time table, a standard/permissible work time table, and each Location information representing the location of the device and the like are included. The proficiency level table, work time table, and standard/permissible work time table will be described below with reference to Tables 1 to 3.
Figure 2023019402000002

表1は習熟度テーブルの一例である。習熟度テーブルには各作業者について作業毎にその作業者の習熟度が対応付けられている。習熟度は0から3の4段階で評価される。0が最も習熟度が低く、3が最も習熟度が高い。各作業の作業時間は作業者の習熟度が高いほど短くなる。

Figure 2023019402000003
Table 1 is an example of a proficiency level table. In the proficiency level table, the proficiency level of each worker is associated with each task. Proficiency is evaluated on a scale of 0 to 3. 0 is the lowest proficiency and 3 is the highest proficiency. The working time of each work becomes shorter as the worker's proficiency level increases.
Figure 2023019402000003

表2は作業時間テーブルの一例である。作業時間テーブルには作業者毎且つ作業毎にその作業の実際の作業時間が記録される。作業時間は1回の作業毎に記録される。具体的には例えば、作業者は作業を開始するときに携帯端末30を操作して作業者割り当て装置1に作業の開始を通知し、作業が終了すると携帯端末30を操作して作業の終了を通知する。作業者割り当て装置1は作業の開始が通知されたときから作業の終了が通知されたときまでの時間を作業時間として作業時間テーブルに記録する。

Figure 2023019402000004
Table 2 is an example of a work time table. The work time table records the actual work time of each work for each worker and for each work. Work hours are recorded for each work. Specifically, for example, the worker operates the mobile terminal 30 to notify the worker assignment apparatus 1 of the start of work when starting work, and operates the mobile terminal 30 to end the work when the work is finished. Notice. The worker assignment device 1 records the time from when the start of work is notified to when the end of work is notified as work time in the work time table.
Figure 2023019402000004

表3は標準/許容作業時間テーブルの一例である。標準/許容作業時間テーブルには各作業について標準作業時間と許容作業時間とが対応付けられている。標準作業時間はその作業の作業回数に対する標準的な作業時間である。標準作業時間は作業回数が多いほど短くなる。許容作業時間は各作業の作業時間として許容される時間である。作業時間が許容作業時間を超過した場合は、直ちに基板生産設備2が停止しないとしても、そのままでは基板生産設備2が停止する可能性がある。 Table 3 is an example of a standard/permissible work time table. The standard/allowable work time table associates the standard work time and the allowable work time for each work. The standard work time is the standard work time for the work count of the work. The standard working time becomes shorter as the number of operations increases. The allowable work time is the time allowed as work time for each work. If the work time exceeds the allowable work time, even if the board production equipment 2 does not immediately stop, the board production equipment 2 may stop as it is.

(5)作業者割り当て装置によって実行される処理
作業者割り当て装置1によって実行される以下の処理について説明する。
・作業計画の作成及び送信処理
・教育必要性通知処理
・作業遅延通知処理
・習熟度更新処理
(5) Processing Executed by Worker Assignment Device The following processing executed by the worker assignment device 1 will be described.
・Work plan creation and transmission processing ・Training necessity notification processing ・Work delay notification processing ・Proficiency level update processing

(5-1)作業計画の作成及び送信処理
作業者割り当て装置1は、基板生産設備2で1以上の作業が発生すると、各作業者の位置と、発生した作業についての各作業者の習熟度とに基づいて、各作業に割り当てる作業者と各作業の作業順序とを表す作業計画を作成し、作成した作業計画を各作業者の携帯端末30(所定の送信先の一例)に送信する。
(5-1) Work Plan Creation and Transmission Processing When one or more tasks occur in the board production equipment 2, the worker assignment device 1 determines the position of each worker and the proficiency level of each worker for the task that has occurred. Based on the above, a work plan representing the workers to be assigned to each work and the work order of each work is created, and the created work plan is transmitted to each worker's mobile terminal 30 (an example of a predetermined destination).

具体的には、作業者割り当て装置1は、作業者が作業位置まで移動する移動時間を短くする観点の作業計画と、各作業の作業時間を短くする観点の作業計画とを作成し、作成した作業計画のうち発生した全ての作業が最も早く終了する作業計画を送信する。移動時間を短くする観点の作業計画及び作業時間を短くする観点の作業計画は、作業に割り当てられている作業者が異なる複数の作業計画の一例である。以下、具体的に説明する。 Specifically, the worker assignment device 1 creates a work plan from the viewpoint of shortening the movement time for the worker to move to the work position, and a work plan from the viewpoint of shortening the work time of each work. Send the work plan that completes all the work that occurred the earliest among the work plans. The work plan from the viewpoint of shortening the travel time and the work plan from the viewpoint of shortening the work time are examples of a plurality of work plans in which different workers are assigned to the work. A specific description will be given below.

(5-1-1)作業計画の作成の仕方の設定
図3を参照して、作業計画の作成の仕方の設定について説明する。作業者割り当て装置1は、作業計画の作成の仕方の設定を受け付ける設定画面を表示部43に表示する。作業者を管理する管理者は表示された設定画面で作業計画の作成の仕方を設定する。
(5-1-1) Setting of How to Create a Work Plan Setting of how to create a work plan will be described with reference to FIG. The worker assignment device 1 displays on the display unit 43 a setting screen for accepting settings for how to create a work plan. The administrator who manages the workers sets the method of creating the work plan on the displayed setting screen.

作業計画の作成の仕方の設定には、生産ラインについての設定(第1の受付工程及び第2の受付工程の一例)、習熟度についての設定(第3の受付工程及び第4の受付工程の一例)、及び、作業細分化についての設定(第5の受付工程の一例)の3つの設定項目がある。
生産ラインについての設定では「全てのライン」、「担当ラインのみ」、「指定ライン優先(割り込みあり)」及び「指定ライン優先(割り込みなし)」のいずれか1つが選択される。「指定ライン優先(割り込みあり)」及び「指定ライン優先(割り込みなし)」が選択された場合は優先する生産ラインLの指定も行われる。以降の説明では指定された生産ラインLのことを指定ラインという。
For the setting of how to create a work plan, the setting for the production line (an example of the first reception process and the second reception process), the setting for the proficiency level (the third reception process and the fourth reception process) There are three setting items: one example), and a setting for work subdivision (an example of the fifth reception process).
In the setting of the production line, any one of "all lines", "only lines in charge", "designated line priority (with interruption)" and "designation line priority (without interruption)" is selected. When "prioritize designated line (with interruption)" and "prioritize designated line (without interruption)" are selected, the preferential production line L is also designated. In the following description, the specified production line L will be referred to as the specified line.

「全てのライン」は、各作業者にその作業者が担当する生産ラインL以外の生産ラインLで発生した作業も割り当てる設定である。
「担当するラインのみ」は、各作業者にその作業者が担当する生産ラインLで発生した作業のみを割り当てる設定である。
"All Lines" is a setting that allocates to each worker also the work that occurred on production lines L other than the production line L that the worker is in charge of.
"Only the line in charge" is a setting that assigns to each worker only the work that occurred in the production line L that the worker is in charge of.

「指定ライン優先(割り込みあり)」及び「指定ライン優先(割り込みなし)」は、各作業者が作業計画に従って作業しているときに指定ラインで新たに作業が発生した場合に、その新たに発生した作業を、指定ライン以外の生産ラインL(以下、非指定ラインという)で発生した作業を行っている作業者に割り当てる設定である。作業者割り当て装置1は新たに発生した作業を割り当てた作業計画を作成し直して作業者に送信する。 "Designated line priority (with interruption)" and "Designated line priority (no interruption)" are when new work occurs on the designated line while each worker is working according to the work plan. This is the setting for assigning the work done by the worker who is doing the work that occurred on the production line L other than the designated line (hereinafter referred to as the non-designated line). The worker assignment device 1 recreates a work plan in which newly generated work is assigned and transmits it to the workers.

割り込みありは、指定ラインで新たに発生した作業を、非指定ラインで発生した作業を行っている作業者に、その作業者が現在行っている作業を中断して割り当てる設定である。この場合、非指定ラインで発生した作業を行っている作業者は現在行っている作業を中断し、指定ラインで新たに発生した作業を優先して行う。作業者は指定ラインで新たに発生した作業が終了した後、中断した作業を再開する。すなわち、割り込みありの場合は非指定ラインで発生した作業を行っている作業者が現在行っている作業よりも指定ラインで新たに発生した作業が優先される。 With interruption is a setting that interrupts the work that the worker is currently doing and assigns the work that has newly occurred on the designated line to the worker that is doing the work that has occurred on the non-designated line. In this case, the worker who is performing the work that occurred on the non-designated line interrupts the current work and gives priority to the work that newly occurred on the designated line. After completing the new work on the designated line, the worker resumes the interrupted work. That is, when there is an interrupt, the work newly generated on the designated line is prioritized over the work currently being performed by the worker who is performing the work generated on the non-designated line.

割り込みなしは、非指定ラインで発生した作業を行っている作業者が現在行っている作業の中断はしないが、非指定ラインで発生した作業を行っている作業者が現在行っている作業の次の作業の前に、指定ラインで発生した新たな作業を割り込ませる設定である。すなわち、割り込みなしの場合は指定ラインで新たに発生した作業が、非指定ラインで発生した作業を行っている作業者の次の作業よりも優先される。 No interruption does not interrupt the work currently being done by the worker who is doing the work that occurred on the non-designated line, but the work that the worker who is doing the work that occurred on the non-designated line is not interrupted. It is a setting that interrupts new work that occurred on the specified line before the work of . In other words, when there is no interruption, the work newly generated on the designated line is prioritized over the next work of the worker who is performing the work generated on the non-designated line.

習熟度についての設定では「習熟度優先」、「教育優先」及び「余剰時間教育」のいずれか1つが選択される。
「習熟度優先」は、発生した作業に作業者を割り当てるとき、その作業の習熟度が相対的に高い作業者を優先して割り当てる設定である。
「教育優先」は、発生した作業に作業者を割り当てるとき、教育のために、他の作業者に比べてその作業の習熟度が低い作業者(言い換えると相対的に作業習熟度が低い作業者)を優先して割り当てる設定である。
「余剰時間教育」は、発生した全ての作業が終了する時間が目標時間より短い場合(すなわち目標時間までに余剰時間がある場合)に、目標時間を超えない範囲で、発生した作業に、他の作業者に比べてその作業の習熟度が低い作業者(言い換えると相対的に作業習熟度が低い作業者)を割り当てる設定である。言い換えると、「余剰時間教育」は余剰時間がある場合にだけ作業者を教育する設定である。
In setting the proficiency level, one of "proficiency level priority", "education priority", and "surplus time education" is selected.
"Proficiency Priority" is a setting in which, when assigning a worker to a task that has occurred, a worker with a relatively high level of proficiency in the task is preferentially assigned.
"Education priority" means that when assigning a worker to a task that has occurred, a worker with a lower proficiency in that task than other workers (in other words, a worker with a relatively low proficiency in ) are assigned with priority.
“Surplus time education” is a system where when the time to complete all the work that has occurred is shorter than the target time (i.e., when there is surplus time before the target time), This is a setting for allocating a worker whose proficiency level of the work is lower than that of the workers of (in other words, a worker whose work proficiency level is relatively low). In other words, "surplus time education" is a setting to educate workers only when there is surplus time.

作業細分化についての設定では「作業細分化する」及び「作業細分化しない」のいずれか1つが選択される。
「作業細分化する」は、発生した作業の数よりも作業者の数の方が多い場合(言い換えると作業者の数に余裕がある場合)に、1つの作業を細分化して複数の作業者で分担する設定である。「作業細分化しない」は作業を細分化しない設定である。「作業細分化しない」が選択されている場合は1つの作業に一人の作業者が割り当てられる。
Either one of "work subdivision" and "do not subdivide work" is selected in the setting of work subdivision.
"Subdivide work" is when the number of workers is greater than the number of tasks that have occurred (in other words, when the number of workers has room), one task is subdivided into multiple workers. It is a setting to share with. "Do not subdivide work" is a setting that does not subdivide work. If "do not subdivide work" is selected, one worker is assigned to one work.

(5-1-2)作業計画の作成例
以下、作業計画を作成する例について説明する。
(5-1-2) Example of creating a work plan An example of creating a work plan will be described below.

(作成例1)
作成例1は生産ラインLの設定として「全てのライン」、習熟度の設定として「習熟度優先」、作業細分化の設定として「作業細分化しない」が選択されている場合の例である。
図4に示すように、作成例1では生産ラインL1の表面実装機M11のリール交換、生産ラインL2の表面実装機M22の吸着エラー、生産ラインL2の表面実装機M23の吸着エラーがほぼ同時に発生している。
(Creation example 1)
Creation example 1 is an example in which "all lines" are selected as the setting for the production line L, "preferred skill level" is selected as the setting for the proficiency level, and "do not subdivide the work" is selected as the setting for the subdivision of work.
As shown in FIG. 4, in Example 1, the reel change of the surface mounter M11 on the production line L1, the adsorption error of the surface mounter M22 of the production line L2, and the adsorption error of the surface mounter M23 of the production line L2 occurred almost simultaneously. are doing.

移動時間を短くする観点の作業計画の作成について説明する。作業者の現在位置と作業位置との距離が近いほど移動時間が短くなることから、作業者割り当て装置1は、作業者の携帯端末30からその携帯端末30の位置(言い換えると作業者の位置)を表す位置情報を受信し、作業者の位置から近い位置で発生した作業を作業者に優先的に割り当てる。 I will explain how to create a work plan from the viewpoint of shortening the travel time. Since the closer the distance between the worker's current position and the work position is, the shorter the travel time is, the worker assignment device 1 determines the position of the mobile terminal 30 from the worker's mobile terminal 30 (in other words, the worker's position). position information representing the position of the worker, and preferentially assigns to the worker work that occurred at a position close to the worker's position.

具体的には、図4に示す例では生産ラインL1の作業者Aは生産ラインL1の表面実装機M11の近くにいるので、作業者割り当て装置1は作業者Aに表面実装機M11のリール交換を割り当てる。生産ラインL2の作業者Bは生産ラインL2の表面実装機M23の近くにいるので、作業者割り当て装置1は作業者Bに表面実装機M23の吸着エラーの対処を割り当てる。 Specifically, in the example shown in FIG. 4, the worker A on the production line L1 is near the surface mounter M11 on the production line L1. assign. Since the worker B on the production line L2 is near the surface mounter M23 on the production line L2, the worker assignment device 1 assigns the worker B to deal with the pickup error of the surface mounter M23.

図4に示す例では作業者Aに割り当てた作業(生産ラインL1の表面実装機M11のリール交換)の方が、作業者Bに割り当てた作業(生産ラインL2の表面実装機M23の吸着エラーの対処)よりも処理時間が短いものとする。ここで処理時間とは、移動時間と作業時間とを合計した時間のことをいう。この場合、作業者割り当て装置1は、先に作業が終了する作業者Aに、未だ作業者に割り当てられていない作業のうち作業者Aの位置(すなわち表面実装機M11の近傍の位置)に最も近い位置で発生した作業を割り当てる。ただし、図4に示す例では残りの作業が1つだけ(生産ラインL2の表面実装機M22の吸着エラーの対処だけ)であるので、作業者Aには移動時間によらず生産ラインL2の表面実装機M22の吸着エラーの対処が割り当てられる。 In the example shown in FIG. 4, the work assigned to worker A (exchange of reels of surface mounter M11 on production line L1) is the work assigned to worker B (suction error of surface mounter M23 on production line L2). countermeasure) is assumed to be shorter than the processing time. Here, the processing time is the total time of travel time and work time. In this case, the worker assignment device 1 assigns the worker A whose work has been completed first to the position of the worker A (that is, the position near the surface mounter M11) that is closest to the worker A among the tasks that have not yet been assigned to the worker. Assign work that occurs in close proximity. However, in the example shown in FIG. 4, there is only one remaining task (only the handling of the adsorption error of the surface mounter M22 on the production line L2). A countermeasure for the pick-up error of the mounter M22 is assigned.

図5に示す作業計画50は移動時間を短くする観点の作業計画を示している。図5に示すように、作業計画50では生産ラインL1の作業者Aに生産ラインL1の表面実装機M11のリール交換と、生産ラインL2の表面実装機M22の吸着エラーの対処とがこの順で割り当てられており、生産ラインL2の作業者Bに生産ラインL2の表面実装機M23の吸着エラーの対処が割り当てられている。
作業計画50において生産ラインL1の作業者Aに割り当てられている表面実装機M11のリール交換の移動時間は、1以上の作業が発生したときの作業者Aの位置から表面実装機M11までの移動時間である。作業者Aに割り当てられている表面実装機M22の吸着エラーの対処の移動時間は、表面実装機M11から表面実装機M22までの移動時間である。すなわち、各作業の移動時間は作業者がその作業の前に何処にいたかによって異なる。
A work plan 50 shown in FIG. 5 shows a work plan from the viewpoint of shortening the travel time. As shown in FIG. 5, in the work plan 50, the worker A on the production line L1 is instructed to replace the reel of the surface mounter M11 on the production line L1 and to deal with the adsorption error of the surface mounter M22 on the production line L2 in this order. Worker B on the production line L2 is assigned to deal with the pickup error of the surface mounter M23 on the production line L2.
The movement time for replacing the reel of the surface mounter M11 assigned to the worker A on the production line L1 in the work plan 50 is the movement from the position of the worker A to the surface mounter M11 when one or more tasks occur. It's time. The travel time for dealing with the pickup error of the surface mounter M22 assigned to worker A is the travel time from the surface mounter M11 to the surface mounter M22. That is, the travel time for each task varies depending on where the worker was prior to the task.

図4を参照して、作業時間を短くする観点の作業計画の作成について説明する。習熟度が高いほど作業時間が短くなることから、作業時間を短くする観点の作業計画では、作業者割り当て装置1は、各作業に、他の作業者に比べてその作業の習熟度が高い作業者(言い換えると相対的に習熟度が高い作業者)を優先的に割り当てる。具体的には、表1に示すように生産ラインL1の作業者Aは吸着エラーの対処の習熟度が相対的に高いので、作業者割り当て装置1は作業者Aに生産ラインL2の表面実装機M22の吸着エラーの対処を割り当てる。ここで、図4に示す例では吸着エラーの対処として生産ラインL2の表面実装機M22の吸着エラーの対処と生産ラインL2の表面実装機M23の吸着エラーの対処との2つが発生している。この場合、作業者割り当て装置1は移動時間を短くするために、これら2つの吸着エラーの対処のうち作業者Aの現在位置に近い位置で発生した吸着エラーの対処を割り当てる。一方、表1に示すように作業者Bはリール交換の習熟度が相対的に高いので、作業者割り当て装置1は作業者Bに生産ラインL1の表面実装機M11のリール交換を割り当てる。 Creation of a work plan from the viewpoint of shortening work time will be described with reference to FIG. Since the higher the proficiency level, the shorter the work time, in the work plan from the viewpoint of shortening the work time, the worker assignment device 1 assigns each work to a work whose proficiency level is higher than that of other workers. Workers (in other words, workers with relatively high proficiency) are preferentially assigned. Specifically, as shown in Table 1, since the worker A on the production line L1 has a relatively high degree of proficiency in dealing with the pickup error, the worker assignment device 1 assigns the worker A to the surface mounter on the production line L2. Allocate action for pick-up error of M22. Here, in the example shown in FIG. 4, as the handling of the adsorption error, there are two handlings of the adsorption error of the surface mounter M22 of the production line L2 and the handling of the adsorption error of the surface mounter M23 of the production line L2. In this case, the worker assignment device 1 allocates the handling of the adsorption error that occurred at a position close to the current position of the worker A among these two handling of the adsorption error in order to shorten the movement time. On the other hand, as shown in Table 1, since the worker B has a relatively high degree of proficiency in reel replacement, the worker assignment device 1 assigns the worker B to replace the reels of the surface mounter M11 on the production line L1.

図4に示す例では生産ラインL1の作業者Aに割り当てた作業(生産ラインL2の表面実装機M22で発生した吸着エラーの対処)の方が、生産ラインL2の作業者Bに割り当てた作業(生産ラインL1の表面実装機M11のリール交換)よりも処理時間(=移動時間+作業時間)が短いものとする。この場合、作業者割り当て装置1は先に作業が終了する作業者Aに、未だ作業者に割り当てられていない作業のうち作業者Aの習熟度が高い作業を割り当てる。ただし、図4に示す例では残りの作業が1つだけ(生産ラインL2の表面実装機M23の吸着エラーの対処だけ)であるので、作業者割り当て装置1は作業者Aの習熟度によらず生産ラインL2の表面実装機M23の吸着エラーの対処を割り当てる。 In the example shown in FIG. 4, the work assigned to worker A on production line L1 (coping with a pickup error that occurred in surface mounter M22 on production line L2) is the work assigned to worker B on production line L2 ( It is assumed that the processing time (=moving time + working time) is shorter than the reel replacement of the surface mounter M11 on the production line L1. In this case, the worker assignment device 1 assigns to the worker A who finishes the work first, the work with the high proficiency level of the worker A among the tasks that have not yet been assigned to the worker. However, in the example shown in FIG. 4, since there is only one remaining work (only dealing with the adsorption error of the surface mounter M23 on the production line L2), the worker assignment device 1 does not depend on the skill level of the worker A. A countermeasure for the pickup error of the surface mounter M23 on the production line L2 is assigned.

図5に示す作業計画51は、作業時間を短くする観点で作成された作業計画を示している。作業計画51に示すように、生産ラインL1の作業者Aには生産ラインL2の表面実装機M22の吸着エラーの対処と、生産ラインL2の表面実装機M23の吸着エラーの対処とがこの順で割り当てられており、作業者Bには生産ラインL1の表面実装機M11のリール交換が割り当てられている。作業者Bは生産ラインL1の表面実装機M11までの距離が遠いことから、移動時間を短くする観点の作業計画に比べてリール交換の移動時間が長くなっている。 A work plan 51 shown in FIG. 5 is a work plan created from the viewpoint of shortening the work time. As shown in the work plan 51, the worker A on the production line L1 must deal with the pick-up error of the surface mounter M22 on the production line L2 and the pick-up error of the surface mounter M23 on the production line L2 in this order. The worker B is assigned to replace the reels of the surface mounter M11 on the production line L1. Since the worker B is far from the surface mounter M11 on the production line L1, the travel time for reel replacement is longer than in the work plan from the viewpoint of shortening the travel time.

図5から判るように、作成例1では移動時間を短くする観点の作業計画50よりも作業時間を短くする観点の作業計画51の方が、発生した全ての作業が早く終了する。このため、作業者割り当て装置1は作業時間を短くする観点の作業計画を作業者A及び作業者Bに送信する。
作成例1では作業時間を短くする観点の作業計画の方が移動時間を短くする観点の作業計画より早く終了するが、作業の発生の仕方によっては移動時間を短くする観点の作業計画の方が作業時間を短くする観点の作業計画より全ての作業が早く終了する場合もある。その場合は、作業者割り当て装置1は移動時間を短くする観点の作業計画を送信する。
As can be seen from FIG. 5, in creation example 1, the work plan 51 from the viewpoint of shortening the work time completes all the work earlier than the work plan 50 from the viewpoint of shortening the travel time. Therefore, the worker assignment device 1 transmits to workers A and B a work plan from the viewpoint of shortening the work time.
In creation example 1, the work plan with the viewpoint of shortening the work time ends earlier than the work plan with the viewpoint of shortening the travel time, but depending on how the work occurs, the work plan with the viewpoint of shortening the travel time is better. All the work may be completed earlier than the work plan from the viewpoint of shortening the work time. In that case, the worker assignment device 1 transmits a work plan from the viewpoint of shortening the travel time.

(作成例2)
作成例2は生産ラインの設定として「担当ラインのみ」、習熟度の設定として「習熟度優先」、作業細分化の設定として「作業細分化しない」が選択されている場合の例である。
(Creation example 2)
Creation example 2 is an example in which "only assigned line" is selected as the production line setting, "proficiency level priority" is selected as the proficiency level setting, and "no work subdivision" is selected as the work subdivision setting.

図6は発生した作業の一例である。図6に示す例では生産ラインL1でリール交換及び吸着エラーが発生しており、生産ラインL2でリール交換が発生している。この場合、作業者割り当て装置1は各作業者にその作業者が担当している生産ラインLの作業のみを割り当てる。
ここでは生産ラインL1の作業者Aを例に説明する。図7に示す作業計画52は作業者Aについて移動時間を短くする観点の作業計画である。移動時間を短くする観点の作業計画52の作成では、作業者割り当て装置1は最初に作業者Aの現在位置に近い作業である生産ラインL1の表面実装機M11のリール交換を割り当て、その後に表面実装機M12の吸着エラーの対処を割り当てる。図7に示す作業計画53は、作業者Aについて作業時間を短くする観点の作業計画である。作業時間を短くする観点の作業計画53の作成では、作業者割り当て装置1は最初に作業者Aに生産ラインL1の表面実装機M12の吸着エラーの対処を割り当て、その後に表面実装機M11のリール交換を割り当てる。
FIG. 6 is an example of the work that has occurred. In the example shown in FIG. 6, a reel exchange and a suction error occur on the production line L1, and a reel exchange occurs on the production line L2. In this case, the worker assignment device 1 assigns to each worker only the work of the production line L that the worker is in charge of.
Here, the worker A on the production line L1 will be described as an example. A work plan 52 shown in FIG. 7 is a work plan from the viewpoint of shortening the travel time of worker A. In FIG. In creating the work plan 52 from the viewpoint of shortening the travel time, the worker assignment device 1 first assigns the reel exchange of the surface mounter M11 of the production line L1, which is the work near the current position of the worker A, and then the surface mounter M11. Allocate the handling of the pick-up error of the mounter M12. A work plan 53 shown in FIG. 7 is a work plan from the viewpoint of shortening the work time for worker A. In FIG. In creating the work plan 53 from the viewpoint of shortening the work time, the worker assignment device 1 first assigns the worker A to deal with the pickup error of the surface mounter M12 of the production line L1, and then the reel of the surface mounter M11. Allocate exchanges.

作成例2の場合、作業時間を短くする観点の作業計画53では最初に作業者Aが表面実装機M12まで移動する移動時間が長くなることから、移動時間を短くする観点の作業計画52の方が、発生した全ての作業が早く終了する。このため、作業者割り当て装置1は移動時間を短くする観点の作業計画52を作業者Aに送信する。作業者Bについても同様である。 In the case of creation example 2, the work plan 53 from the viewpoint of shortening the work time takes a long time for worker A to first move to the surface mounter M12. However, all the work that occurs is finished early. Therefore, the worker assignment device 1 transmits to the worker A the work plan 52 from the viewpoint of shortening the travel time. The same applies to worker B.

(作成例3)
作成例3は生産ラインの設定として「指定ライン優先(割り込みあり)」、習熟度の設定として「習熟度優先」、作業細分化の設定として「作業細分化しない」が選択されている場合の例である。作成例3では指定ラインとして生産ラインL1が指定されたものとする。
(Creation example 3)
Creation example 3 is an example in which "specified line priority (with interruption)" is selected as the production line setting, "proficiency level priority" is selected as the proficiency level setting, and "do not subdivide work" is selected as the work subdivision setting. is. In creation example 3, it is assumed that the production line L1 is specified as the specified line.

図8Aに示すように、作業者Aは送信された作業計画55に従って生産ラインL1(指定ライン)の作業W1を行っており、作業者Bは送信された作業計画55に従って生産ラインL2(非指定ライン)の作業W2を行っているとする。
図8Aに示す例では、各作業者が作業計画55に従って作業を行っている途中の時点T1において生産ラインL1(指定ライン)で新たな作業W3が発生している。この場合、図8Bに示すように、作業者割り当て装置1は、生産ラインL1で発生した新たな作業W3を作業者B(すなわち非指定ラインの作業を行っている作業者)に割り当てた作業計画56を作成し直して作業者A及び作業者Bに送信する。具体的には、作業者割り当て装置1は、生産ラインL1で新たに発生した作業W3を、生産ラインL2の作業者Bが現在行っている作業W2を中断させて割り込ませる。
As shown in FIG. 8A, worker A is performing work W1 on production line L1 (designated line) according to the transmitted work plan 55, and worker B is performing work W1 on production line L2 (non-designated line) according to the transmitted work plan 55. line) is being performed.
In the example shown in FIG. 8A , a new work W3 occurs on the production line L1 (designated line) at time T1 while each worker is performing work according to the work plan 55 . In this case, as shown in FIG. 8B, the worker assignment device 1 assigns a new work W3 occurring on the production line L1 to the worker B (that is, the worker who is working on the non-designated line). 56 is recreated and sent to worker A and worker B. Specifically, the worker assignment device 1 interrupts the work W2 currently being performed by the worker B on the production line L2 to interrupt the work W3 that has newly occurred on the production line L1.

(作成例4)
作成例4は生産ラインの設定として「指定ライン優先(割り込みなし)」、習熟度の設定として「習熟度優先」、作業細分化の設定として「作業細分化しない」が選択されている場合の例である。作成例4も指定ラインとして生産ラインL1が指定されているものとする。
(Creation example 4)
Creation example 4 is an example in which "specified line priority (no interruption)" is selected as the production line setting, "proficiency level priority" is selected as the proficiency level setting, and "do not subdivide work" is selected as the work subdivision setting. is. It is also assumed that the production line L1 is specified as the specified line in creation example 4 as well.

図9Aに示す作業計画57では、時点T1において生産ラインL1で新たな作業W4が発生している。この場合、作業者割り当て装置1は、図9Bに示す作業計画58のように、生産ラインL1で発生した新たな作業W4を、生産ラインL2の作業者Bが現在行っている作業W2の次の作業W3の前に割り込ませる。 In the work plan 57 shown in FIG. 9A, a new work W4 occurs on the production line L1 at time T1. In this case, the worker assignment device 1 assigns the new work W4 generated on the production line L1 to the next work W2 currently performed by the worker B on the production line L2, as in the work plan 58 shown in FIG. 9B. Interrupt before work W3.

(作成例5)
作成例5は生産ラインの設定として「全てのライン」、習熟度の設定として「教育優先」、作業細分化の設定として「作業細分化しない」が選択されている場合の例である。
(Creation example 5)
Creation example 5 is an example in which "all lines" are selected as the production line setting, "education priority" is selected as the proficiency level setting, and "no work subdivision" is selected as the work subdivision setting.

図10は発生した作業の一例である。図10に示す例では生産ラインL1の表面実装機M11でリール交換、表面実装機M12で吸着エラーが発生し、生産ラインL2の表面実装機M23でリール交換が発生している。
図11に示す作業計画59は教育優先の作業計画を示している。前述した表1に示すように、生産ラインL1の作業者Aは吸着エラーの対処に比べてリール交換の習熟度が低い。このため、作業者割り当て装置1は作業者Aの吸着エラーの対処の習熟度を向上させるために、作業者Aに表面実装機M11のリール交換と表面実装機M23のリール交換とを割り当てる。より具体的には、作業者割り当て装置1は、移動時間を短縮するために、生産ラインL1の作業者Aの現在位置に近い作業である表面実装機M11のリール交換を先に割り当て、その後に表面実装機M23のリール交換を割り当てる。一方、表1に示すように生産ラインL2の作業者Bはリール交換に比べて吸着エラーの対処の習熟度が低いため、作業者割り当て装置1は作業者Bに表面実装機M12の吸着エラーの対処を割り当てる。
FIG. 10 is an example of the work that has occurred. In the example shown in FIG. 10, the surface mounter M11 on the production line L1 has a reel exchange, the surface mounter M12 has a suction error, and the surface mounter M23 on the production line L2 has a reel exchange.
A work plan 59 shown in FIG. 11 indicates a work plan giving priority to education. As shown in Table 1 described above, the worker A on the production line L1 has a lower proficiency in reel replacement than in dealing with suction errors. For this reason, the worker assignment device 1 assigns the worker A to replace the reels of the surface mounter M11 and the surface mounter M23 in order to improve the worker A's proficiency in dealing with the pick-up error. More specifically, in order to shorten the travel time, the worker assignment device 1 first assigns the reel replacement of the surface mounter M11, which is a task near the current position of the worker A on the production line L1, and then Allocate reel replacement for the surface mounter M23. On the other hand, as shown in Table 1, since the worker B of the production line L2 has a lower proficiency in dealing with pickup errors than reel replacement, the worker assignment device 1 instructs the worker B to deal with the pickup error of the surface mounter M12. Assign an action.

(作成例6)
作成例6は生産ラインの設定として「全てのライン」、習熟度の設定として「余剰時間教育」、作業細分化の設定として「作業細分化しない」が選択されている場合の例である。
例えば生産ラインL1の表面実装機M11でリール交換、表面実装機M13で吸着エラーが発生し、生産ラインL2の表面実装機M21で吸着エラー、表面実装機M23でリール交換が発生したとする。この場合に、発生した全ての作業が早く終了する作業計画として図12Aに示す作業計画60が選択されたものとする。
(Creation example 6)
Creation example 6 is an example in which "all lines" are selected as the production line setting, "surplus time education" is selected as the proficiency level setting, and "no work subdivision" is selected as the work subdivision setting.
For example, assume that the surface mounter M11 on the production line L1 has a reel change, the surface mounter M13 has a suction error, the surface mounter M21 on the production line L2 has a suction error, and the surface mounter M23 has a reel change. In this case, it is assumed that the work plan 60 shown in FIG. 12A is selected as the work plan in which all the generated works are finished early.

図12Aにおいて目標時間は、全ての作業が終了する目標時間である。目標時間は作業者割り当て装置1によって設定される。例えばリール交換が発生しても表面実装機Mは直ちには停止しないが、リールが交換されないといずれ停止する。作業者割り当て装置1は、リールが交換されないことによって表面実装機Mが停止する時間よりも前に目標時間を設定する。あるいは、吸着エラーが発生した場合は表面実装機Mが直ちに停止する。その場合に、復旧までの目標とする時間が設定されている場合は、作業者割り当て装置1はその時間を目標時間とする。目標時間の設定はこれらに限られるものではなく、適宜に設定できる。 The target time in FIG. 12A is the target time when all the work is completed. A target time is set by the worker assignment device 1 . For example, the surface mounter M does not immediately stop when reel replacement occurs, but it will eventually stop if the reel is not replaced. The worker assignment device 1 sets the target time before the time when the surface mounter M stops due to the reel not being replaced. Alternatively, when an adsorption error occurs, the surface mounter M immediately stops. In this case, if a target time until recovery is set, the worker assignment device 1 sets that time as the target time. The setting of the target time is not limited to these, and can be set as appropriate.

図12Aに示す作業計画60では、全ての作業が終了する時間が目標時間より短い。すなわち目標時間までに余剰時間がある。このため、図12Bに示す作業計画61のように、作業者割り当て装置1は、余剰時間を超えない範囲で、教育のために各作業者にその作業者の習熟度が低い作業を割り当てる。具体的には、生産ラインL1の作業者Aはリール交換の習熟度が低いことから、作業者割り当て装置1は作業者Aに割り当てたいずれかの吸着エラーの対処に替えてリール交換(図12Bに示す例では表面実装機M11のリール交換)を割り当てる。一方、生産ラインL2の作業者Bは吸着エラーの対処の習熟度が低いことから、作業者割り当て装置1は作業者Bに割り当てたいずれかのリール交換に替えて吸着エラーの対処(図12Bに示す例では表面実装機M21の吸着エラーの対処)を割り当てる。 In the work plan 60 shown in FIG. 12A, the time for completing all the work is shorter than the target time. That is, there is surplus time before the target time. For this reason, as in the work plan 61 shown in FIG. 12B, the worker assignment device 1 assigns each worker a job with a low proficiency level for education within a range not exceeding the surplus time. Specifically, since the worker A on the production line L1 has a low proficiency in reel replacement, the worker assignment device 1 replaces the reel (Fig. 12B In the example shown in FIG. 2, the reel exchange of the surface mounter M11) is assigned. On the other hand, since the worker B on the production line L2 has a low proficiency in dealing with the pickup error, the worker assignment device 1 replaces one of the reels assigned to the worker B to deal with the pickup error (see FIG. 12B). In the example shown, the countermeasure for the pickup error of the surface mounter M21) is assigned.

図12Bに示す例では、作業者の割り当てを変更した後の作業計画61においても全ての作業が終了する時間が目標時間より短い。作業者割り当て装置1は目標時間を超えるまで割り当ての変更を繰り返し、目標時間を超える直前の作業計画を送信する。送信する作業計画は必ずしも目標時間を超える直前の作業計画でなくてもよい。例えば変更する作業は各作業者についてそれぞれ1つだけであってもよい。 In the example shown in FIG. 12B, the time to complete all the work is shorter than the target time even in the work plan 61 after changing the worker assignment. The worker assignment device 1 repeats assignment changes until the target time is exceeded, and transmits the work plan immediately before the target time is exceeded. The work plan to be transmitted does not necessarily have to be the work plan immediately before the target time is exceeded. For example, each worker may change only one work.

(作成例7)
作成例7は生産ラインの設定として「全てのライン」、習熟度の設定として「習熟度優先」、作業細分化の設定として「作業細分化する」が選択されている場合の例である。
(Creation example 7)
Creation example 7 is an example in which "all lines" are selected as the production line setting, "proficiency level priority" is selected as the proficiency level setting, and "work subdivision" is selected as the work subdivision setting.

図13Aは発生した作業の一例である。図13Aに示す例では生産ラインL1の表面実装機M11でリール交換が発生し、生産ラインL2では作業は発生していない。
図13Aに示すように、リール交換は新しいリールを用意する作業、現在使用中のリールを表面実装機M11から外す作業、新しいリールを表面実装機M11に装着する作業に細分化できる。これらの作業のうち新しいリールを用意する作業と、現在使用中のリールを表面実装機Mから外す作業とは、異なる作業者が並行して行うことができる。このため、作業者割り当て装置1は、「作業細分化する」が選択されている場合は、作業者の人数に余裕があれば作業を細分化し、細分化した作業にそれぞれ作業者を割り当てる。細分化した複数の作業について、どの作業にどの作業者を割り当てるかは適宜に決定できる。
FIG. 13A is an example of the work that has occurred. In the example shown in FIG. 13A, reel replacement occurs in the surface mounter M11 on the production line L1, and work does not occur on the production line L2.
As shown in FIG. 13A, the reel replacement can be subdivided into the work of preparing a new reel, the work of removing the reel currently in use from the surface mounter M11, and the work of mounting the new reel on the surface mounter M11. Of these operations, the operation of preparing a new reel and the operation of removing the reel currently in use from the surface mounter M can be performed by different operators in parallel. Therefore, when "subdivide work" is selected, the worker assignment device 1 subdivides the work if there is a margin in the number of workers, and assigns workers to each subdivided work. For a plurality of subdivided tasks, it is possible to appropriately determine which worker is assigned to which task.

図13Bに示す作業計画62は作業を細分化した作業計画の一例である。図13Bに示す例では生産ラインL1の作業者Aに新しいリールを用意する作業が割り当てられており、生産ラインL2の作業者Bに現在使用中のリールを表面実装機Mから外す作業と、新しいリールを表面実装機Mに装着する作業とが割り当てられている。細分化した作業にそれぞれ作業者を割り当てることにより、作業が終了する時間を短縮できる。 A work plan 62 shown in FIG. 13B is an example of a work plan in which work is subdivided. In the example shown in FIG. 13B, the work of preparing a new reel is assigned to the worker A of the production line L1, and the work of removing the reel currently in use from the surface mounter M and the work of preparing a new reel are assigned to the worker B of the production line L2. A task of mounting the reel on the surface mounter M is assigned. By assigning a worker to each subdivided work, the time required to complete the work can be shortened.

(5-1-3)作業計画の作成及び送信のフロー
図14を参照して、作業計画の作成及び送信のフローについて説明する。本処理は基板生産設備2で1つ以上の作業が発生すると開始される。ここでは生産ラインの設定として「指定ライン優先(割り込みあり)」又は「指定ライン優先(割り込みなし)」が選択された場合を例に説明する。
(5-1-3) Flow of Creation and Transmission of Work Plan A flow of creation and transmission of a work plan will be described with reference to FIG. This process is started when one or more operations occur in the board production equipment 2 . Here, an example will be described in which "specified line priority (with interruption)" or "designated line priority (without interruption)" is selected as the setting of the production line.

S101では、作業者割り当て装置1は各作業者の携帯端末30からその携帯端末30の位置(言い換えるとその携帯端末30を携帯している作業者の位置)を表す位置情報を受信する。
S102では、作業者割り当て装置1は、S101で受信した位置情報によって表される各作業者の位置と、各作業についての各作業者の習熟度とに基づいて、移動時間を短くする観点の作業計画と、作業時間を短くする観点の作業計画とを作成する(作成工程及び作成処理の一例)。
In S101, the worker assignment device 1 receives position information representing the position of the mobile terminal 30 (in other words, the position of the worker carrying the mobile terminal 30) from the mobile terminal 30 of each worker.
In S102, the worker assignment device 1 selects work from the viewpoint of shortening the travel time based on the position of each worker represented by the position information received in S101 and the proficiency level of each worker for each work. Create a plan and a work plan from the viewpoint of shortening the work time (an example of the creation process and creation process).

S103では、作業者割り当て装置1はS102で作成した作業計画のうち発生した全ての作業が最も早く終了する作業計画を作業者の携帯端末30(所定の送信先の一例)に送信する(送信工程及び送信処理の一例)。
S104では、作業者割り当て装置1はS103で送信した作業計画の作業が全て終了したか否かを判断し、終了していない場合はS105に進み、終了している場合は処理を終了する。
In S103, the worker assignment device 1 transmits to the mobile terminal 30 of the worker (an example of a predetermined transmission destination) the work plan that completes all the work that occurred the earliest among the work plans created in S102 (transmitting step and an example of transmission processing).
In S104, the worker assignment apparatus 1 determines whether or not all the work of the work plan transmitted in S103 has been completed.

S105では、作業者割り当て装置1は指定ラインで新たな作業が発生しているか否かを判断する。作業者割り当て装置1は、新たな作業が発生していない場合はS104に戻り、発生している場合はS101に戻って処理を繰り返す。S101に戻った場合は非指定ラインの作業者の作業に当該新たな作業を割り込ませた作業計画が作成し直されて作業者に送信される。 In S105, the worker assignment device 1 determines whether or not new work is occurring on the designated line. The worker assignment device 1 returns to S104 if no new work has occurred, and returns to S101 if new work has occurred, and repeats the process. When the process returns to S101, a work plan in which the new work is interrupted by the work of the worker on the non-designated line is recreated and sent to the worker.

(5-2)教育必要性通知処理
作業者割り当て装置1は、各作業者について、作業時間テーブルを参照して作業毎に作業回数を集計するとともに、各作業の平均の作業時間を計算する。作業者割り当て装置1は、標準/許容作業時間テーブルを参照して、作業回数に対して平均の作業時間が標準作業時間より長いか否かを判断する。作業者割り当て装置1は、各作業者について平均の作業時間が標準作業時間より長い作業がある場合はその作業についてその作業者の教育が必要であることを管理者端末31(所定の通知先の一例)に通知する(第1の通知工程の一例)。作業者割り当て装置1は作業者の教育が必要であることを管理者の電子メールアドレスに宛てて電子メールで送信してもよい。
(5-2) Training Necessity Notification Processing For each worker, the worker assignment device 1 looks up the work time table to tally the number of times of work for each work and calculates the average work time for each work. The worker assignment device 1 refers to the standard/allowable work time table and determines whether or not the average work time is longer than the standard work time for the number of times of work. The worker assignment device 1 notifies the administrator terminal 31 (predetermined notification destination (an example) (an example of the first notification step). The worker assignment device 1 may send an e-mail to the manager's e-mail address indicating that worker education is required.

(5-3)作業遅延通知処理
表2に示す標準/許容作業時間テーブルを参照して、作業遅延通知処理について説明する。作業時間が許容作業時間を超過した場合、直ちに基板生産設備2が停止しないとしても、そのままでは基板生産設備2が停止する可能性がある。作業者割り当て装置1は、携帯端末30から作業の開始が通知されると作業時間のカウントを開始し、カウントした時間が許容作業時間を超過した場合は、許容作業時間を超過したことを管理者端末31に通知する(第2の通知工程の一例)。作業者割り当て装置1は許容作業時間を超過したことを管理者の電子メールアドレスに宛てて電子メールで送信してもよい。
(5-3) Work Delay Notification Processing With reference to the standard/allowable work time table shown in Table 2, work delay notification processing will be described. When the work time exceeds the allowable work time, even if the board production equipment 2 does not stop immediately, the board production equipment 2 may stop as it is. When the mobile terminal 30 notifies the worker assignment device 1 of the start of work, it starts counting the work time. The terminal 31 is notified (an example of the second notification step). The worker assignment device 1 may send an e-mail to the e-mail address of the manager that the allowable work time has been exceeded.

(5-4)習熟度更新処理
作業者割り当て装置1は、作業時間テーブルを参照して、各作業者について作業毎にその作業の累積作業時間を集計し、累積作業時間に応じて習熟度テーブルの習熟度を更新する。例えば、作業者割り当て装置1は、累積作業時間が0~10時間の場合は習熟度として0、10~20時間の場合は習熟度として1、20~30時間の場合は習熟度として2などのように更新する(更新工程の一例)。
(5-4) Proficiency level update process The worker assignment device 1 refers to the work time table, aggregates the cumulative work time of each work for each worker, and updates the proficiency level table according to the cumulative work time. update proficiency in For example, the worker assignment device 1 assigns a proficiency level of 0 when the cumulative work time is 0 to 10 hours, a proficiency level of 1 when the cumulative work time is 10 to 20 hours, and a proficiency level of 2 when the cumulative work time is 20 to 30 hours. (an example of an update process).

ここでは累積作業時間に基づいて習熟度を更新する場合を例に説明したが、累積作業回数に基づいて習熟度を更新してもよい。例えば累積作業回数が0~10回の場合は習熟度として0、10~20回の場合は習熟度として1、20~30回の場合は習熟度として2などのように更新してもよい。 Although the case where the proficiency level is updated based on the cumulative work time has been described as an example, the proficiency level may be updated based on the cumulative number of times of work. For example, the proficiency level may be updated to 0 when the cumulative number of operations is 0 to 10, to 1 when the cumulative number of operations is 10 to 20, and to 2 when the cumulative number of operations is 20 to 30.

(6)実施形態の効果
実施形態1に係る作業者割り当て方法によると、各作業者の位置と発生した作業についての各作業者の習熟度とに基づいて、各作業に割り当てる作業者と各作業の作業順序とを表す作業計画を作成する。このため実施形態1に係る作業者割り当て方法によると、作業者(あるいは管理者)の判断によって対応する場合に比べ、基板生産設備2で発生した全ての作業が短時間で終了するように作業者を割り当てることができる。
(6) Effect of Embodiment According to the worker assignment method according to the first embodiment, based on the position of each worker and the proficiency level of each worker with respect to the work that has occurred, the worker assigned to each work and each work Create a work plan that represents the work order and For this reason, according to the worker assignment method according to the first embodiment, compared to the case where the worker (or manager) decides to deal with the situation, the workers are arranged so that all the work occurring in the board production equipment 2 can be completed in a short time. can be assigned.

上記の作業者割り当て方法によると、作業に割り当てられている作業者が異なる複数の作業計画を作成し、作成した複数の作業計画のうち発生した全ての作業が最も早く終了する作業計画を所定の送信先に送信するので、発生した全ての作業が短時間で終了する可能性が高くなる。 According to the worker assignment method described above, a plurality of work plans with different workers assigned to the work are created, and the work plan that completes all the work that occurred the earliest among the created work plans is specified as a predetermined work plan. Since it will be sent to the destination, it is more likely that all the work that has occurred will be completed in a short time.

上記の作業者割り当て方法によると、移動時間を短くする観点の作業計画と作業時間を短くする観点の作業計画とを作成し、作成した作業計画のうち全ての作業が最も早く終了する作業計画を送信する。このため、移動時間だけを考慮して作業計画を作成する場合や、作業時間だけを考慮して作業計画を作成する場合に比べ、発生した全ての作業が短時間で終了する可能性が高くなる。 According to the above worker assignment method, a work plan from the viewpoint of shortening the travel time and a work plan from the viewpoint of shortening the work time are created, and among the created work plans, the work plan that completes all the work fastest is selected. Send. Therefore, compared to creating a work plan that considers only travel time or only work time, it is more likely that all the work that has occurred will be completed in a short time. .

上記の作業者割り当て方法によると、各作業者に担当の生産ラインLの作業だけを割り当てるか、又は、担当する生産ラインL以外の作業も割り当てるかの設定を受け付ける受付工程を含むので、担当する生産ラインLで発生した作業だけを割り当てるか、又は、担当する生産ラインL以外の作業も割り当てるかのどちらかに固定されている場合に比べ、作業を割り当てる自由度が向上する。 According to the worker assignment method described above, since it includes a reception process for accepting settings as to whether to assign each worker only the work of the production line L in charge, or to assign work other than the production line L in charge to each worker, The degree of freedom in assigning work is improved compared to the case where only the work that occurred on the production line L is assigned or the work other than the production line L in charge is also assigned.

上記の作業者割り当て方法によると、指定ラインで新たな作業が発生した場合に、非指定ラインで作業を行っている作業者に当該新たな作業を割り当てるので、指定ラインで発生した作業を短時間で終了できる。 According to the worker assignment method described above, when new work occurs on a designated line, the new work is assigned to a worker who is working on a non-designated line. can be terminated with

上記の作業者割り当て方法によると、「指定ライン優先(割り込みあり)」の場合は非指定ラインで発生した作業を行っている作業者の現在の作業を中断させて新たな作業を割り込ませるので、指定ラインで発生した作業を短時間で終了できる。 According to the above worker allocation method, in the case of "designated line priority (with interruption)", the current work of the worker who is doing the work that occurred on the non-designated line is interrupted and new work is interrupted. The work that occurred on the designated line can be completed in a short time.

上記の作業者割り当て方法によると、「指定ライン優先(割り込みなし)」の場合は非指定ラインで発生した作業を行っている作業者の現在の作業の後、当該作業者の次の作業の前に新たな作業を割り込ませるので、指定ラインで発生した作業を短時間で終了できる。 According to the above worker allocation method, in the case of "designated line priority (no interruption)", after the current work of the worker who is doing the work that occurred on the non-designated line, before the next work of the worker can be interrupted by the new work, the work that occurred on the designated line can be completed in a short time.

上記の作業者割り当て方法によると、「教育優先」が設定されている場合は、各作業に当該作業の習熟度が相対的に低い作業者を優先して割り当てる。このため作業者の習熟度を向上させることができる。 According to the worker assignment method described above, when "priority on education" is set, workers with relatively low proficiency in each task are preferentially assigned to each task. Therefore, it is possible to improve the proficiency of the operator.

上記の作業者割り当て方法によると、「余剰時間教育」が設定されている場合は、目標時間内に全ての作業が終了する範囲で作業者を教育できるので、生産性の低下を抑制しつつ作業者を教育できる。 According to the worker allocation method described above, when "surplus time training" is set, workers can be trained to the extent that all work is completed within the target time. can educate people.

上記の作業者割り当て方法によると、作業者の数が作業の数より多い場合は、1つの作業を細分化して複数の作業者を割り当てるので、作業が終了する時間を短縮できる。 According to the worker assignment method described above, when the number of workers is larger than the number of works, one work is subdivided and a plurality of workers are assigned, so that the time for completing the work can be shortened.

上記の作業者割り当て方法によると、作業者が作業を行った作業時間が当該作業の標準作業時間より長かった場合は、当該作業者について当該作業の教育が必要であることを管理者端末31に通知するので、管理者はどの作業者にどの作業の教育が必要であるかの判断が容易になる。 According to the worker assignment method described above, when the work time of a worker is longer than the standard work time of the work, the manager terminal 31 is notified that the worker needs training for the work. This notification makes it easy for the manager to determine which worker needs training for which task.

上記の作業者割り当て方法によると、作業の実際の作業時間が許容時間を超過した場合に、許容時間を超過したことを管理者端末31に通知するので、管理者は許容時間を超過した作業を手伝うよう他の作業者に指示することにより、作業の遅れを抑制できる。 According to the worker assignment method described above, when the actual work time exceeds the allowable time, the manager terminal 31 is notified that the allowable time has been exceeded. By instructing other workers to help, work delays can be suppressed.

上記の作業者割り当て方法によると、各作業者について、作業毎に当該作業の累積作業時間及び当該作業の累積作業回数の少なくとも一方に基づいて当該作業者の習熟度を自動で更新するので、作業を管理する管理者が手作業で習熟度を更新する場合に比べて管理者の負担を軽減できる。 According to the worker assignment method described above, for each worker, the proficiency level of the worker is automatically updated based on at least one of the cumulative work time of the work and the number of cumulative work of the work. The burden on the administrator can be reduced compared to when the administrator who manages manually updates the proficiency level.

<他の実施形態>
本明細書によって開示される技術は上記記述及び図面によって説明した実施形態に限定されるものではなく、例えば次のような実施形態も本明細書によって開示される技術的範囲に含まれる。
<Other embodiments>
The technology disclosed in this specification is not limited to the embodiments described in the above description and drawings, and the following embodiments are also included in the technical scope disclosed in this specification.

(1)上記実施形態1では移動時間を短くする観点の作業計画と作業時間を短くする観点の作業計画とを作成し、いずれか全ての作業が最も早く終了する作業計画を送信する場合を例に説明した。これに対し、作成する作業計画はいずれか一方だけでもよい。例えば、作業時間を短くする観点の作業計画だけを作成してもよい。その場合に、習熟度が同じ作業者が複数いる場合は、作業位置の近くにいる作業者を割り当ててもよい。あるいは、移動時間を短くする観点の作業計画だけを作成してもよい。その場合に、移動時間が同程度の作業者が複数いる場合は、習熟度が高い作業者を割り当ててもよい。 (1) In the first embodiment, a work plan for shortening the travel time and a work plan for shortening the work time are created, and the work plan that completes all the work fastest is transmitted. explained to On the other hand, only one of the work plans may be created. For example, only a work plan from the viewpoint of shortening work time may be created. In that case, if there are a plurality of workers with the same proficiency level, a worker near the work position may be assigned. Alternatively, only the work plan from the viewpoint of shortening the travel time may be created. In that case, if there are multiple workers with similar travel times, a worker with a high proficiency level may be assigned.

(2)上記実施形態1では基板生産設備2で発生する作業として表面実装機Mで発生する作業を例に説明したが、基板生産設備2で発生する作業は基板生産設備2で発生する任意の作業であってよい。 (2) In the above-described first embodiment, the work that occurs in the surface mounter M has been described as an example of the work that occurs in the board production equipment 2. It can be work.

(3)上記実施形態1では作業に割り当てられている作業者が異なる複数の作業計画を作成する例として移動時間を短くする観点の作業計画と作業時間を短くする観点の作業計画とを作成する場合を例に説明したが、複数の作業計画を作成する方法はこれに限られず、適宜に選択可能である。
例えば、作業者をランダムに作業に割り当てることによって複数の作業計画を作成し、そのうち発生した全ての作業が最も早く終了する作業計画を採用してもよい。
あるいは、移動時間を短くする観点の作業計画や作業時間を短くする観点の作業計画とは別に、ある特定の作業については移動時間を短くする観点で作業者を割り当て、別のある特定の作業については作業時間を短くする観点で作業者を割り当てた作業計画を作成し、それら複数の作業計画のうち発生した全ての作業が最も早く終了する作業計画を採用してもよい。
(3) In the first embodiment, as an example of creating a plurality of work plans with different workers assigned to the work, a work plan from the viewpoint of shortening the travel time and a work plan from the viewpoint of shortening the work time are created. Although the case has been described as an example, the method of creating a plurality of work plans is not limited to this, and can be selected as appropriate.
For example, a plurality of work plans may be created by randomly assigning workers to work, and the work plan that completes all the work that has occurred the earliest may be adopted.
Alternatively, separate from the work plan from the viewpoint of shortening the travel time and the work plan from the viewpoint of shortening the work time, for one specific work, workers are assigned from the viewpoint of shortening the travel time, and for another specific work In order to shorten the work time, a work plan may be created in which workers are assigned, and the work plan in which all the work that has occurred can be completed earliest among the plurality of work plans may be adopted.

1: 作業者割り当て装置(コンピュータの一例)
2: 基板生産設備
30: 携帯端末(所定の送信先の一例)
31: 管理者端末(所定の通知先の一例)
40: 制御部
41: 記憶部
42: 通信部(取得部の一例)
50: 作業計画
51: 作業計画
52: 作業計画
53: 作業計画
55: 作業計画
56: 作業計画
57: 作業計画
58: 作業計画
59: 作業計画
60: 作業計画
61: 作業計画
62: 作業計画
A: 作業者
B: 作業者
L(L1、L2): 生産ライン
1: Worker assignment device (an example of a computer)
2: Substrate production equipment 30: Mobile terminal (an example of a predetermined destination)
31: Administrator terminal (an example of a predetermined notification destination)
40: Control unit 41: Storage unit 42: Communication unit (an example of an acquisition unit)
50: work plan 51: work plan 52: work plan 53: work plan 55: work plan 56: work plan 57: work plan 58: work plan 59: work plan 60: work plan 61: work plan 62: work plan A: Worker B: Worker L (L1, L2): Production line

Claims (15)

基板を生産する基板生産設備で発生した作業に作業者を割り当てる作業者割り当て方法であって、
1以上の前記作業が発生した場合に、各前記作業者の位置と、発生した前記作業についての各前記作業者の習熟度とに基づいて、各前記作業に割り当てる前記作業者と各前記作業の作業順序とを表す作業計画を作成する作成工程を含む、作業者割り当て方法。
A worker assignment method for assigning a worker to a work that occurs in a board production facility that produces boards,
When one or more of the tasks occur, the worker assigned to each task and the assignment of each task based on the position of each worker and the proficiency level of each worker with respect to the task that has occurred A method of assigning workers, including the steps of creating a work plan representing a work sequence.
請求項1に記載の作業者割り当て方法であって、
前記作成工程において、前記作業に割り当てられている作業者が異なる複数の前記作業計画を作成し、
当該作業者割り当て方法は、
前記作成工程で作成した複数の前記作業計画のうち発生した全ての前記作業が最も早く終了する前記作業計画を所定の送信先に送信する送信工程を含む、作業者割り当て方法。
The worker assignment method of claim 1, comprising:
In the creation step, creating a plurality of work plans with different workers assigned to the work,
The worker assignment method is
A method of assigning workers, comprising a transmission step of transmitting to a predetermined transmission destination the work plan in which all the work that has occurred among the plurality of work plans created in the creation step is completed earliest.
請求項2に記載の作業者割り当て方法であって、
前記作成工程において、前記作業者が前記作業の作業位置まで移動する移動時間を短くする観点の前記作業計画と、各前記作業の作業時間を短くする観点の前記作業計画とを作成する、作業者割り当て方法。
A worker assignment method according to claim 2, wherein
In the creation step, the worker creates the work plan from the viewpoint of shortening the movement time for the worker to move to the work position of the work, and the work plan from the viewpoint of shortening the work time of each work. Allocation method.
請求項1から請求項3のいずれか一項に記載の作業者割り当て方法であって、
前記基板生産設備は前記基板を生産する生産ラインを複数有し、
各前記作業者は担当する前記生産ラインが割り当てられており、
当該作業者割り当て方法は、
各前記作業者に当該作業者が担当する前記生産ラインの前記作業だけを割り当てるか、又は、担当する前記生産ライン以外の前記作業も割り当てるかの設定を受け付ける第1の受付工程を含み、
前記作成工程において、担当する前記生産ラインの前記作業だけを割り当てる設定がされている場合は各前記作業者に当該作業者が担当する前記生産ラインの前記作業だけを割り当て、担当する前記生産ライン以外の前記作業も割り当てる設定がされている場合は担当する前記生産ライン以外の前記作業も割り当てる、作業者割り当て方法。
A worker assignment method according to any one of claims 1 to 3,
The board production facility has a plurality of production lines for producing the board,
Each worker is assigned a production line to be in charge,
The worker assignment method is
a first receiving step of receiving a setting as to whether each worker is assigned only the work on the production line that the worker is in charge of, or whether the work other than the production line that the worker is in charge of is also assigned;
In the creation process, if it is set to allocate only the work of the production line that the worker is in charge of, only the work of the production line that the worker is in charge of is assigned to each worker, and only the work of the production line that the worker is in charge of is assigned. A worker assignment method for assigning the above-mentioned work other than the above-mentioned production line to which the worker is in charge when the above-mentioned work is also assigned.
請求項1から請求項4のいずれか一項に記載の作業者割り当て方法であって、
前記基板生産設備は前記基板を生産する生産ラインを複数有し、
当該作業者割り当て方法は、
複数の前記生産ラインのうちいずれかの前記生産ラインの指定を受け付ける第2の受付工程を含み、
各前記作業者が前記作業計画に従って前記作業を行っているときに前記第2の受付工程で指定された前記生産ラインで新たな作業が発生した場合は、前記作成工程において、指定された前記生産ライン以外の前記作業を行っている前記作業者に当該新たな作業を割り当てた作業計画を作成し直す、作業者割り当て方法。
A worker assignment method according to any one of claims 1 to 4,
The board production facility has a plurality of production lines for producing the board,
The worker assignment method is
including a second receiving step of receiving designation of one of the plurality of production lines;
If new work occurs on the production line specified in the second reception process while each worker is performing the work according to the work plan, the production line specified in the creation process A method of assigning workers, wherein a work plan is recreated in which the new work is assigned to the workers who are doing the work outside the line.
請求項5に記載の作業者割り当て方法であって、
前記作成工程において、指定された前記生産ライン以外の前記作業を行っている前記作業者の現在の前記作業を中断させて前記新たな作業を割り込ませる、作業者割り当て方法。
A worker assignment method according to claim 5, wherein
A method of assigning workers, wherein in the creation process, the current work of the worker who is doing the work other than the designated production line is interrupted and the new work is interrupted.
請求項5に記載の作業者割り当て方法であって、
前記作成工程において、指定された前記生産ライン以外の前記作業を行っている前記作業者の現在の前記作業の後、当該作業者の次の前記作業の前に前記新たな作業を割り込ませる、作業者割り当て方法。
A worker assignment method according to claim 5, wherein
In the creation process, the new work is interrupted after the current work of the worker who is performing the work other than the designated production line and before the next work of the worker. method of assignment.
請求項1から請求項7のいずれか一項に記載の作業者割り当て方法であって、
発生した前記作業の習熟度が低い前記作業者に当該作業を優先して割り当てる教育優先を行うか否かの設定を受ける第3の受付工程を含み、
前記教育優先を行う設定がされている場合は、前記作成工程において、発生した前記作業に当該作業の習熟度が相対的に低い前記作業者を優先して割り当てる、作業者割り当て方法。
A worker assignment method according to any one of claims 1 to 7,
Including a third receiving step of receiving a setting as to whether or not to give priority to training for preferentially allocating the work to the worker who has a low proficiency level for the work,
A method of assigning a worker to a worker having a relatively low degree of proficiency in the work that has occurred in the creation process, when the training priority is set.
請求項1から請求項8のいずれか一項に記載の作業者割り当て方法であって、
余剰時間教育を行うか否かの設定を受け付ける第4の受付工程を含み、
前記余剰時間教育を行う設定がされている場合は、前記作成工程において、目標時間内に全ての前記作業が終了する範囲で、発生した前記作業に当該作業の習熟度が相対的に低い前記作業者を優先して割り当てる、作業者割り当て方法。
A worker assignment method according to any one of claims 1 to 8,
Including a fourth reception step for receiving a setting as to whether or not to perform extra time education,
When the surplus time education is set, in the creation process, the work with a relatively low proficiency level for the work that has occurred within the range that all the work is completed within the target time A worker assignment method that prioritizes and assigns workers.
請求項1から請求項9のいずれか一項に記載の作業者割り当て方法であって、
発生した前記作業を細分化して複数の前記作業者に割り当てる細分化を行うか否かの設定を受け付ける第5の受付工程を含み、
細分化を行う設定がされており、且つ、前記作業者の数が前記作業の数より多い場合は、前記作成工程において、1つの前記作業を細分化して複数の前記作業者を割り当てる、作業者割り当て方法。
A worker assignment method according to any one of claims 1 to 9,
including a fifth receiving step of receiving a setting as to whether or not to subdivide the generated work and allocate it to a plurality of workers;
When subdivision is set and the number of said workers is greater than the number of said works, in said creation step, one said work is subdivided and a plurality of said workers are assigned. Allocation method.
請求項1から請求項10のいずれか一項に記載の作業者割り当て方法であって、
前記作業者が前記作業を行った作業時間が当該作業の標準作業時間より長かった場合に、当該作業者について当該作業の教育が必要であることを所定の通知先に通知する第1の通知工程を含む、作業者割り当て方法。
A worker assignment method according to any one of claims 1 to 10,
A first notification step of notifying a predetermined notification destination that the worker needs to be educated for the work when the work time for the work performed by the worker is longer than the standard work time for the work. worker assignment method, including
請求項1から請求項11のいずれか一項に記載の作業者割り当て方法であって、
前記作業の実際の作業時間が許容作業時間を超過した場合に、前記許容作業時間を超過したことを所定の通知先に通知する第2の通知工程を含む、作業者割り当て方法。
A worker assignment method according to any one of claims 1 to 11,
A worker assignment method, comprising: a second notification step of notifying a predetermined notification destination of the fact that the allowable work time has been exceeded when the actual work time of the work exceeds the allowable work time.
請求項1から請求項12のいずれか一項に記載の作業者割り当て方法であって、
各前記作業者について、前記作業毎に当該作業の累積作業時間及び当該作業の累積作業回数の少なくとも一方に基づいて当該作業の習熟度を更新する更新工程を含む、作業者割り当て方法。
A worker assignment method according to any one of claims 1 to 12,
A method for allocating workers, comprising an update step of updating a proficiency level of each worker for each work based on at least one of a cumulative work time of the work and a cumulative work count of the work.
基板を生産する基板生産設備で発生した作業に作業者を割り当てる作業者割り当てプログラムであって、
1以上の前記作業が発生した場合に、各前記作業者の位置と、発生した前記作業についての各前記作業者の習熟度とに基づいて、各前記作業に割り当てる前記作業者と各前記作業の作業順序とを表す作業計画を作成する作成処理をコンピュータに実行させる、作業者割り当てプログラム。
A worker assignment program for assigning workers to work occurring in board production equipment for producing boards,
When one or more of the tasks occur, the worker assigned to each task and the assignment of each task based on the position of each worker and the proficiency level of each worker with respect to the task that has occurred A worker assignment program for causing a computer to execute a creation process for creating a work plan representing a work order.
基板を生産する基板生産設備で発生した作業に作業者を割り当てる作業者割り当て装置であって、
各前記作業についての各前記作業者の習熟度が記憶されている記憶部と、
各前記作業者の位置を表す位置情報を取得する取得部と、
制御部と、
を備え、
前記制御部は、1以上の前記作業が発生した場合に、前記取得部によって取得した各前記作業者の位置と、発生した前記作業についての各前記作業者の習熟度とに基づいて、各前記作業に割り当てる前記作業者と各前記作業の作業順序とを表す作業計画を作成する作成処理を実行する、作業者割り当て装置。
A worker assignment device for assigning workers to work occurring in board production equipment for producing boards,
a storage unit that stores the proficiency level of each worker for each work;
an acquisition unit that acquires position information representing the position of each worker;
a control unit;
with
When one or more of the tasks have occurred, the control unit performs each A worker assignment device that executes creation processing for creating a work plan representing the workers to be assigned to the work and the work order of each work.
JP2021124093A 2021-07-29 2021-07-29 Worker assignment method, worker assignment program, and worker assignment system Pending JP2023019402A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP2021124093A JP2023019402A (en) 2021-07-29 2021-07-29 Worker assignment method, worker assignment program, and worker assignment system

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP2021124093A JP2023019402A (en) 2021-07-29 2021-07-29 Worker assignment method, worker assignment program, and worker assignment system

Publications (1)

Publication Number Publication Date
JP2023019402A true JP2023019402A (en) 2023-02-09

Family

ID=85160595

Family Applications (1)

Application Number Title Priority Date Filing Date
JP2021124093A Pending JP2023019402A (en) 2021-07-29 2021-07-29 Worker assignment method, worker assignment program, and worker assignment system

Country Status (1)

Country Link
JP (1) JP2023019402A (en)

Similar Documents

Publication Publication Date Title
US11029670B2 (en) Management apparatus and management method
US7245978B2 (en) Managing apparatus for managing assisting work to assist substrate-related-work performing system, and managing program for managing assisting work to assist substrate-related-work performing system
JP7150525B2 (en) Work management device and work management method
JP4478108B2 (en) Maintenance work support system for component mounting system and component mounting system including the same
JP2009140380A (en) Scheduling device and operation management method and program
JP4796462B2 (en) Component assembly assignment method, component assembly assignment device, and mounter for mounting machine
JP2017208408A (en) Shipping management device, shipping management system, and program
JP6395708B2 (en) Management method and management apparatus for electronic component mounting system having a plurality of production lines
JP2023019402A (en) Worker assignment method, worker assignment program, and worker assignment system
JP2018092970A (en) Component mounting system, worker assigning system, and worker assigning method
JP6114921B2 (en) Component mounting system and component mounting method
JP5038970B2 (en) Mounting condition determining method, mounting condition determining apparatus, component mounting method, component mounter, and program
JP6748718B2 (en) Production planning system and production planning method
JPWO2020039545A1 (en) Mobile work management device, mobile work device, mounting system and management method
JP2015207686A (en) Method and apparatus for determining arrangement of component
JP4887328B2 (en) Mounting condition determination method
JP2009043947A (en) Mounting facility, mounting machine, mounting line, mounting work optimizing equipment, and mounting work optimizing method
JP2005216945A (en) Method and device for setting arrangement of feeder
JP2016115915A (en) Data management device and method
JPH1187996A (en) Method of setting arrangement of tool for work machine handing parts, and its device
JP2006171916A (en) Production planning method
WO2023012880A1 (en) Process management device
JP2024005625A (en) Splicing work assignment device, component mounting system, splicing work assignment method, and splicing work assignment program
JP6830185B2 (en) Component mounting system, worker allocation system, and worker allocation method
JP2024005780A (en) Management program for surface-mounted machine, management device, management method and component mounting system

Legal Events

Date Code Title Description
A621 Written request for application examination

Free format text: JAPANESE INTERMEDIATE CODE: A621

Effective date: 20231206