JP2022094798A - Excavation method - Google Patents

Excavation method Download PDF

Info

Publication number
JP2022094798A
JP2022094798A JP2020207885A JP2020207885A JP2022094798A JP 2022094798 A JP2022094798 A JP 2022094798A JP 2020207885 A JP2020207885 A JP 2020207885A JP 2020207885 A JP2020207885 A JP 2020207885A JP 2022094798 A JP2022094798 A JP 2022094798A
Authority
JP
Japan
Prior art keywords
temporary
existing
excavation
column
replacement
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
JP2020207885A
Other languages
Japanese (ja)
Inventor
豊 上枝
Yutaka Ueda
明俊 濱田
Akitoshi Hamada
和範 若松
Kazunori Wakamatsu
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Takenaka Komuten Co Ltd
Original Assignee
Takenaka Komuten Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Takenaka Komuten Co Ltd filed Critical Takenaka Komuten Co Ltd
Priority to JP2020207885A priority Critical patent/JP2022094798A/en
Publication of JP2022094798A publication Critical patent/JP2022094798A/en
Pending legal-status Critical Current

Links

Images

Abstract

To provide an excavation method capable of carrying out excavation while appropriately supporting an existing column over a long time.SOLUTION: The excavation method executes: an installation step of installing a replacement structure 4 capable of freely supporting an existing column 1 from a ground part shifted from directly below the existing column 1; and an excavation step of executing excavation within an excavation target range 2A directly below the existing column 1 after the installation step. The replacement structure 4 has a plurality of temporary installed columns 6 fixed to a ground 2, and a replacement frame 9 for connecting the column heads of the temporary installed columns 6 to the existing column 1, and is configured to bear a long load and a short load transmitted from the existing column 1.SELECTED DRAWING: Figure 4

Description

本発明は、既存柱の直下の掘削対象範囲を掘削する掘削工法に関する。 The present invention relates to an excavation method for excavating an excavation target area directly under an existing pillar.

特許文献1には、既存柱(上部柱16a,16b)の直下の掘削対象範囲から外れた地盤から既存柱を支持自在なオイルジャッキ24を設置し、既存柱の直下の掘削対象範囲を掘削する掘削工法が示されている。 In Patent Document 1, an oil jack 24 capable of supporting an existing pillar from the ground outside the excavation target range directly under the existing pillar (upper pillar 16a, 16b) is installed, and the excavation target range directly under the existing pillar is excavated. The excavation method is shown.

特開2007-009658号公報Japanese Unexamined Patent Publication No. 2007-909658

しかし、このようにオイルジャッキ24が既存柱を支持する構成では、地震等によって生じた短期荷重をオイルジャッキ24が負担できないので、既存柱を掘削期間に亘って適切に支持できない虞がある。 However, in such a configuration in which the oil jack 24 supports the existing pillar, the oil jack 24 cannot bear the short-term load generated by an earthquake or the like, so that the existing pillar may not be properly supported over the excavation period.

この実情に鑑み、本発明の主たる課題は、既存柱を長期に亘って適切に支持しながら掘削できる掘削工法を提供する点にある。 In view of this situation, a main object of the present invention is to provide an excavation method capable of excavating while appropriately supporting an existing column for a long period of time.

本発明の第1特徴構成は、既存柱の直下から外れた地盤部分から前記既存柱を支持自在な受け替え構造体を設置する設置工程と、前記設置工程の後に前記既存柱の直下の掘削対象範囲を掘削する掘削工程とを実行し、前記受け替え構造体は、地盤に固定される複数の仮設柱と、当該仮設柱の柱頭部と前記既存柱とを接続する受け替えフレームとを有して、前記既存柱から伝達される長期荷重及び短期荷重を負担自在に構成されている点にある。 The first characteristic configuration of the present invention includes an installation step of installing a replacement structure capable of supporting the existing pillar from a ground portion deviating from the ground portion directly under the existing pillar, and an excavation target directly under the existing pillar after the installation step. Performing an excavation step of excavating an area, the replacement structure has a plurality of temporary columns fixed to the ground and a replacement frame connecting the stigma of the temporary columns and the existing columns. Therefore, the long-term load and the short-term load transmitted from the existing pillar can be freely borne.

本構成によれば、複数の仮設柱を地盤に固定すると共に仮設柱の柱頭部と既存柱とを受け替えフレームによって接続して受け替え構造体を構成するため、既存柱を支持する受け替え構造体の強度を高くし易い。そのため、受け替え構造体を、既存柱の長期荷重だけでなく既存梁の短期荷重も負担自在に構成し易く、このように受け替え構造体を既存柱の短期荷重を負担自在に構成することで受け替え構造体によって長期に亘って既存柱を適切に支持できる。 According to this configuration, a plurality of temporary columns are fixed to the ground, and the stigma of the temporary columns and the existing columns are connected by a replacement frame to form a replacement structure, so that the replacement structure supports the existing columns. It is easy to increase the strength of the body. Therefore, it is easy to construct the replacement structure not only the long-term load of the existing column but also the short-term load of the existing beam freely. The replacement structure can properly support existing columns for a long period of time.

本発明の第2特徴構成は、前記仮設柱は、平面視で前記掘削対象範囲から外れた地盤に固定される点にある。 The second characteristic configuration of the present invention is that the temporary pillar is fixed to the ground outside the excavation target range in a plan view.

本構成によれば、仮設柱を平面視で掘削対象範囲から外れた地盤に固定することで、既存柱の下方側に大きな空間を形成し易くなるため、掘削対象範囲の掘削作業が行い易くなる。 According to this configuration, by fixing the temporary column to the ground outside the excavation target range in a plan view, it becomes easy to form a large space on the lower side of the existing column, so that excavation work in the excavation target range becomes easy. ..

本発明の第3特徴構成は、前記受け替えフレームは、前記複数の仮設柱の柱頭部どうしを接続する水平姿勢の第1鉄骨フレーム部を有する点にある。 The third characteristic configuration of the present invention is that the replacement frame has a first steel frame portion in a horizontal posture for connecting the capital heads of the plurality of temporary columns.

本構成によれば、受け替えフレームに第1鉄骨フレームを備えることで、複数の仮設柱どうしを強固に接続することができ、受け替えフレームの強度を高めることができる。 According to this configuration, by providing the first steel frame in the replacement frame, a plurality of temporary columns can be firmly connected to each other, and the strength of the replacement frame can be increased.

本発明の第4特徴構成は、前記受け替えフレームは、前記仮設柱の柱頭部と前記既存柱の柱脚部を接続する水平姿勢の第2鉄骨フレーム部を有する点にある。 The fourth characteristic configuration of the present invention is that the replacement frame has a second steel frame portion in a horizontal posture that connects the stigma of the temporary column and the column base of the existing column.

本構成によれば、受け替えフレームに第2鉄骨フレームを備えることで、仮設柱と既存柱とを強固に接続することができ、受け替えフレームの強度を高めることができる。 According to this configuration, by providing the replacement frame with the second steel frame, the temporary column and the existing column can be firmly connected, and the strength of the replacement frame can be increased.

本発明の第5特徴構成は、前記受け替えフレームは、前記仮設柱の柱頭部と前記既存柱の柱脚部の上方側とを斜めに接続する斜め姿勢の第3鉄骨フレーム部を有する点にある。 The fifth characteristic configuration of the present invention is that the replacement frame has a third steel frame portion in an oblique posture that diagonally connects the stigma of the temporary column and the upper side of the column base portion of the existing column. be.

本特徴によれば、受け替えフレームに第3鉄骨フレームを備えることで、既存柱が柱脚部に対して傾倒することを防止し易くなり、受け替えフレームの強度を高めることができる。 According to this feature, by providing the replacement frame with the third steel frame, it becomes easy to prevent the existing columns from tilting with respect to the column base portion, and the strength of the replacement frame can be increased.

支柱と地盤とを示す側面図Side view showing the columns and the ground 第1実施形態の受け替え構造体の斜視図Perspective view of the replacement structure of the first embodiment 第1実施形態の受け替え構造体を設置した状態を示す側面図A side view showing a state in which the replacement structure of the first embodiment is installed. 第1実施形態の掘削対象範囲を掘削した状態を示す側面図Side view showing the state of excavating the excavation target range of the first embodiment 第1実施形態の掘削対象範囲を補強した状態を示す側面図A side view showing a state in which the excavation target range of the first embodiment is reinforced. 第1実施形態の受け替え構造体を撤去した状態を示す側面図A side view showing a state in which the replacement structure of the first embodiment is removed. 第2実施形態の受け替え構造体を設置した状態を示す側面図A side view showing a state in which the replacement structure of the second embodiment is installed. 第2実施形態の掘削対象範囲を掘削した状態を示す側面図Side view showing the state of excavating the excavation target range of the second embodiment 第2実施形態の掘削対象範囲を補強した状態を示す側面図A side view showing a state in which the excavation target range of the second embodiment is reinforced. 第2実施形態の受け替え構造体を撤去した状態を示す側面図A side view showing a state in which the replacement structure of the second embodiment is removed.

〔第1実施形態〕
本発明に係る第1実施形態の掘削工法の実施形態を図面に基づいて説明する。
本実施形態の掘削工法は、図1に示すように既存柱1が立設されている地盤2を掘削し、図6に示すように基礎構造体3を補強する場合に用いる掘削工法である。既存柱1は、建築物の一部を構成するものであり、地盤2に埋設された基礎構造体3上に立設されている。既存柱1は、鉄骨、詳しくはH型鋼によって構成されている。基礎構造体3は、鉄筋コンクリートによって構成されている。
[First Embodiment]
An embodiment of the excavation method of the first embodiment according to the present invention will be described with reference to the drawings.
The excavation method of the present embodiment is an excavation method used when excavating the ground 2 on which the existing pillar 1 is erected as shown in FIG. 1 and reinforcing the foundation structure 3 as shown in FIG. The existing pillar 1 constitutes a part of the building and is erected on the foundation structure 3 buried in the ground 2. The existing column 1 is composed of a steel frame, specifically H-shaped steel. The foundation structure 3 is made of reinforced concrete.

掘削工法では、図3に示すように、既存柱1の直下から外れた地盤部分2Bから既存柱1を支持自在な受け替え構造体4を設置する設置工程と、図4に示すように、設置工程の後に既存柱1の直下の掘削対象範囲2Aを掘削する掘削工程とを実行する。そして、掘削工法によって掘削した後、図5に示すように、掘削対象範囲2Aに新たな基礎構造体(基礎スラブ)18を構築する補強工程と、図6に示すように、補強工程の後に設置工程で設置した受け替え構造体4を撤去する撤去工程と、を実行する。 In the excavation method, as shown in FIG. 3, the installation process of installing the replacement structure 4 capable of supporting the existing pillar 1 from the ground portion 2B deviating from directly under the existing pillar 1 and the installation as shown in FIG. After the process, an excavation step of excavating the excavation target range 2A directly under the existing pillar 1 is executed. Then, after excavating by the excavation method, as shown in FIG. 5, a reinforcement step of constructing a new foundation structure (foundation slab) 18 in the excavation target range 2A and installation after the reinforcement step as shown in FIG. The removal process of removing the replacement structure 4 installed in the process is executed.

次に、掘削工法で用いる受け替え構造体4や、掘削工法及びその後に実行する工程について説明するが、図1において左右方向となる方向を第1方向Xと称し、図1において奥行き方向となる方向を第2方向Yと称し、第1方向X及び第2方向Yと直交する方向を上下方向Zと称して説明する。 Next, the replacement structure 4 used in the excavation method, the excavation method, and the process to be executed thereafter will be described. In FIG. 1, the direction in the left-right direction is referred to as the first direction X, and in FIG. 1, it is the depth direction. The direction will be referred to as a second direction Y, and the direction orthogonal to the first direction X and the second direction Y will be referred to as a vertical direction Z.

図2に示すように、受け替え構造体4は、地盤2に固定される複数の仮設柱6と、当該仮設柱6の柱頭部6Aと既存柱1とを接続する受け替えフレーム9とを有して、既存柱1から伝達される長期荷重及び短期荷重を負担自在に構成されている。本実施形態では、受け替え構造体4は、仮設柱6を4本有すると共に、受け替えフレーム9によって4本の仮設柱6と第2方向Yに並ぶ2本の既存柱1とを接続しており、第2方向Yに並ぶ2本の既存柱1から伝達される長期荷重及び短期荷重を負担自在に構成されている。尚、受け替え構造体4は、既存の基礎構造体3と同等又はそれ以上の荷重を負担自在に構成されている。 As shown in FIG. 2, the replacement structure 4 has a plurality of temporary columns 6 fixed to the ground 2, and a replacement frame 9 for connecting the stigma 6A of the temporary columns 6 and the existing columns 1. Therefore, the long-term load and the short-term load transmitted from the existing pillar 1 can be freely borne. In the present embodiment, the replacement structure 4 has four temporary pillars 6, and the replacement frame 9 connects the four temporary pillars 6 and the two existing pillars 1 arranged in the second direction Y. The long-term load and the short-term load transmitted from the two existing pillars 1 arranged in the second direction Y can be freely borne. The replacement structure 4 is configured to freely bear a load equal to or greater than that of the existing basic structure 3.

仮設柱6は、2本の既存柱1に対して第1方向Xの一方側にある2本の第1仮設柱7と、2本の既存柱1に対して第1方向Xの他方側にある2本の第2仮設柱8とがあり、2本の第1仮設柱7及び2本の第2仮設柱8の夫々は、2本の既存柱1と同じ間隔で受け替え構造体4に備えられている。 The temporary pillars 6 have two first temporary pillars 7 on one side of the first direction X with respect to the two existing pillars 1 and two existing pillars 1 on the other side of the first direction X with respect to the two existing pillars 1. There are two second temporary pillars 8, and the two first temporary pillars 7 and the two second temporary pillars 8 are replaced in the replacement structure 4 at the same intervals as the two existing pillars 1. It is prepared.

掘削対象範囲2Aは、地盤2における既存柱1の直下の範囲を含む範囲であり、掘削工程において掘削する範囲である。また、掘削対象範囲2Aは、補強工程において補強する範囲となる。
仮設柱6は、平面視で掘削対象範囲2Aから外れた地盤2に固定される。本実施形態では、第1仮設柱7は、掘削対象範囲2Aに対して第1方向Xの一方側の地盤2に固定され、第2仮設柱8は、掘削対象範囲2Aに対して第1方向Xの他方側の地盤2に固定される。このように、仮設柱6は、地盤2における掘削対象範囲2Aから第1方向Xに外れた地盤部分2Bに固定される。
The excavation target range 2A is a range including a range directly under the existing pillar 1 in the ground 2 and is a range to be excavated in the excavation process. Further, the excavation target range 2A is a range to be reinforced in the reinforcement process.
The temporary pillar 6 is fixed to the ground 2 outside the excavation target range 2A in a plan view. In the present embodiment, the first temporary pillar 7 is fixed to the ground 2 on one side of the first direction X with respect to the excavation target range 2A, and the second temporary pillar 8 is in the first direction with respect to the excavation target range 2A. It is fixed to the ground 2 on the other side of X. In this way, the temporary pillar 6 is fixed to the ground portion 2B deviating from the excavation target range 2A in the ground 2 in the first direction X.

<受け替えフレーム>
図2に示すように、受け替えフレーム9は、複数の仮設柱6の柱頭部6Aどうしを接続する水平姿勢の第1鉄骨フレーム部11を有する。詳しくは、受け替えフレーム9は、2本の第1仮設柱7の柱頭部6Aどうしを接続する1本の第1鉄骨フレーム部11と、2本の第2仮設柱8の柱頭部6Aどうしを接続する1本の第1鉄骨フレーム部11との、計2本の第1鉄骨フレーム部11を有している。
<Replacement frame>
As shown in FIG. 2, the replacement frame 9 has a first steel frame portion 11 in a horizontal posture that connects the stigmas 6A of the plurality of temporary columns 6. Specifically, the replacement frame 9 connects one first steel frame portion 11 connecting the stigmas 6A of the two first temporary columns 7 and the stigmas 6A of the two second temporary columns 8 to each other. It has a total of two first steel frame portions 11 including one first steel frame portion 11 to be connected.

また、受け替えフレーム9は、仮設柱6の柱頭部6Aと既存柱1の柱脚部1Bを接続する水平姿勢の第2鉄骨フレーム部12を有する。詳しくは、受け替えフレーム9は、第1仮設柱7の柱頭部6Aと既存柱1の柱脚部1Bとを接続する2本の第2鉄骨フレーム部12と、第2仮設柱8の柱頭部6Aと既存柱1の柱脚部1Bとを接続する2本の第2鉄骨フレーム部12との、計4本の第2鉄骨フレーム部12を有している。 Further, the replacement frame 9 has a second steel frame portion 12 in a horizontal posture that connects the stigma 6A of the temporary column 6 and the column base portion 1B of the existing column 1. Specifically, the replacement frame 9 includes two second steel frame portions 12 connecting the stigma 6A of the first temporary column 7 and the stigma 1B of the existing column 1, and the stigma of the second temporary column 8. It has a total of four second steel frame portions 12 including two second steel frame portions 12 connecting 6A and the stigma 1B of the existing column 1.

また、受け替えフレーム9は、仮設柱6の柱頭部6Aと既存柱1の柱脚部1Bの上方側とを斜めに接続する斜め姿勢の第3鉄骨フレーム部13を有する。詳しくは、受け替えフレーム9は、第1仮設柱7の柱頭部6Aと既存柱1の柱脚部1Bの上方側とを接続する2本の第3鉄骨フレーム部13と、第2仮設柱8の柱頭部6Aと既存柱1の柱脚部1Bの上方側とを接続する2本の第3鉄骨フレーム部13との、計4本の第3鉄骨フレーム部13を有している。 Further, the replacement frame 9 has a third steel frame portion 13 in an oblique posture that diagonally connects the stigma 6A of the temporary column 6 and the upper side of the column base portion 1B of the existing column 1. Specifically, the replacement frame 9 includes two third steel frame portions 13 connecting the stigma 6A of the first temporary column 7 and the upper side of the column base 1B of the existing column 1, and the second temporary column 8. It has a total of four third steel frame portions 13 including two third steel frame portions 13 connecting the column head 6A of the column 1 and the upper side of the column base portion 1B of the existing column 1.

また、受け替えフレーム9は、第1鉄骨フレーム部11と第2鉄骨フレーム部12とで囲まれる構面を補強する第4鉄骨フレーム部14を有する。詳しくは、受け替えフレーム9は、2本の第1仮設柱7の柱脚部6Bと2本の第1鉄骨フレーム部11とを接続する平面視でX字状に形成された第4鉄骨フレーム部14と、2本の第2仮設柱8の柱脚部6Bと2本の第1鉄骨フレーム部11とを接続する平面視でX字状に形成された第4鉄骨フレーム部14との、計2組の第4鉄骨フレーム部14を有している。 Further, the replacement frame 9 has a fourth steel frame portion 14 that reinforces the structure surrounded by the first steel frame portion 11 and the second steel frame portion 12. Specifically, the replacement frame 9 is a fourth steel frame frame formed in an X shape in a plan view connecting the column base portions 6B of the two first temporary columns 7 and the two first steel frame portions 11. A fourth steel frame portion 14 formed in an X shape in a plan view connecting the portion 14, the column base portion 6B of the two second temporary columns 8 and the two first steel frame portions 11. It has a total of two sets of fourth steel frame portions 14.

また、受け替えフレーム9は、仮設柱6と第1鉄骨フレーム部11とで囲まれる構面を補強する第5鉄骨フレーム部15を有する。詳しくは、受け替えフレーム9は、2本の第1仮設柱7の柱脚部6Bと第1鉄骨フレーム部11とを接続する2本の第5鉄骨フレーム部15と、2本の第2仮設柱8の柱脚部6Bと第1鉄骨フレーム部11とを接続する2本の第5鉄骨フレーム部15との、計4本の第5鉄骨フレーム部15を有している。 Further, the replacement frame 9 has a fifth steel frame portion 15 that reinforces the structure surrounded by the temporary pillar 6 and the first steel frame portion 11. Specifically, the replacement frame 9 includes two fifth steel frame portions 15 connecting the column bases 6B of the two first temporary columns 7 and the first steel frame portion 11, and two second temporary columns. It has a total of four fifth steel frame portions 15 including two fifth steel frame portions 15 connecting the column base portion 6B of the column 8 and the first steel frame portion 11.

<設置工程>
設置工程では、既存柱1を支持自在な受け替え構造体4を設置する工程である。設置工程では、図3に示すように、地盤2に第1仮設柱用基礎構造体16を構築してその第1仮設柱用基礎構造体16上に受け替え構造体4を設置する。つまり、まず、地盤2における掘削対象範囲2Aから第1方向Xに外れた地盤部分2Bであって掘削対象範囲2Aに隣接する部分を掘削して第1仮設柱用基礎構造体16を打設する。次に、受け替え構造体4の仮設柱6をアンカーボルト等の部材を用いて第1仮設柱用基礎構造体16に連結すると共に、受け替え構造体4の受け替えフレーム9を仮設柱6及び既存柱1に連結して、受け替え構造体4を設置する。
<Installation process>
The installation process is a process of installing a replacement structure 4 that can freely support the existing pillar 1. In the installation process, as shown in FIG. 3, a first temporary pillar foundation structure 16 is constructed on the ground 2, and a replacement structure 4 is installed on the first temporary pillar foundation structure 16. That is, first, the ground portion 2B deviating from the excavation target range 2A in the ground 2 in the first direction X and adjacent to the excavation target range 2A is excavated and the foundation structure 16 for the first temporary column is placed. .. Next, the temporary column 6 of the replacement structure 4 is connected to the foundation structure 16 for the first temporary column by using a member such as an anchor bolt, and the replacement frame 9 of the replacement structure 4 is connected to the temporary column 6 and the temporary column 6. The replacement structure 4 is installed by connecting to the existing pillar 1.

なお、例えば、図3において掘削対象範囲2Aの右側に示すように、受け替え構造体4の仮設柱6を立設する基礎とするために仮設柱6の近傍のみにコンクリートを打設して第1仮設柱用基礎構造体16を構築してもよく、図3において掘削対象範囲2Aの左側に示すように、既存柱1を有する建築物(図示せず)の基礎とするために仮設柱6の近傍を含む広範囲に亘ってコンクリートを打設して第1仮設柱用基礎構造体16としても機能する第1基礎構造体17を構築してもよい。 For example, as shown on the right side of the excavation target range 2A in FIG. 3, concrete is poured only in the vicinity of the temporary pillar 6 in order to use it as a foundation for erection of the temporary pillar 6 of the replacement structure 4. 1 The foundation structure 16 for temporary columns may be constructed, and as shown on the left side of the excavation target range 2A in FIG. 3, the temporary columns 6 are used as the foundation of a building (not shown) having the existing columns 1. The first foundation structure 17 which also functions as the foundation structure 16 for the first temporary column may be constructed by placing concrete over a wide range including the vicinity of the above.

<掘削工程>
掘削工程では、掘削対象範囲2Aを掘削する工程である。掘削工程では、図4に示すように、掘削対象範囲2Aを掘削して掘削対象範囲2Aの土砂や岩石を掘り取ると共に、掘削対象範囲2Aに打設されている基礎構造体3を除去する。このように、掘削対象範囲2Aを掘削することで、既存柱1から伝達される荷重が受け替え構造体4によって負担される状態となり、受け替え構造体4にて荷重を適切に負担しながら掘削することができる。
<Excavation process>
The excavation process is a process of excavating the excavation target range 2A. In the excavation process, as shown in FIG. 4, the excavation target range 2A is excavated to dig up the earth and sand and rocks in the excavation target range 2A, and the foundation structure 3 placed in the excavation target range 2A is removed. By excavating the excavation target range 2A in this way, the load transmitted from the existing pillar 1 is borne by the replacement structure 4, and the excavation is performed while appropriately bearing the load in the replacement structure 4. can do.

<補強工程>
補強工程では、掘削対象範囲2Aにコンクリートを打設して建築物の基礎として機能する新たな基礎構造体(以下、第2基礎構造体と称する)18を構築する工程である。補強工程では、図5に示すように、掘削工程において掘削されている掘削対象範囲2Aにコンクリートを打設して第2基礎構造体18を構築し、既存柱1をアンカーボルト等の部材を用いて第2基礎構造体18に連結する。そして、第2基礎構造体18は、第1基礎構造体17と隣接する掘削対象範囲2Aに構築されるため、建築物の基礎として機能する第2基礎構造体18と第1基礎構造体17とが一体化される。
<Reinforcement process>
The reinforcement step is a step of placing concrete in the excavation target range 2A to construct a new foundation structure (hereinafter referred to as a second foundation structure) 18 that functions as a foundation of a building. In the reinforcement process, as shown in FIG. 5, concrete is placed in the excavation target range 2A excavated in the excavation process to construct the second foundation structure 18, and the existing column 1 is used with members such as anchor bolts. It is connected to the second foundation structure 18. Since the second foundation structure 18 is constructed in the excavation target range 2A adjacent to the first foundation structure 17, the second foundation structure 18 and the first foundation structure 17 function as the foundation of the building. Is integrated.

<撤去工程>
撤去工程では、受け替え構造体4を撤去する工程である。撤去工程では、図6に示すように、受け替えフレーム9を既存柱1及び仮設柱6から外すと共に仮設柱6を第1仮設柱用基礎構造体16から外して受け替え構造体4を撤去する。このように、受け替え構造体4を撤去することで、既存柱1から伝達される荷重が第2基礎構造体18によって負担される状態となる。
<Removal process>
The removal step is a step of removing the replacement structure 4. In the removal step, as shown in FIG. 6, the replacement frame 9 is removed from the existing pillar 1 and the temporary pillar 6, and the temporary pillar 6 is removed from the foundation structure 16 for the first temporary pillar, and the replacement structure 4 is removed. .. By removing the replacement structure 4 in this way, the load transmitted from the existing pillar 1 is borne by the second foundation structure 18.

〔第2実施形態〕
第2実施形態では、受け替え構造体4の構成や、地盤2における受け替え構造体4を支持する箇所が、第1実施形態と異なる。第2実施形態では、第1実施形態と異なる点を主に説明し、同じ構成については説明を省略する場合がある。
[Second Embodiment]
In the second embodiment, the configuration of the replacement structure 4 and the location of supporting the replacement structure 4 in the ground 2 are different from those in the first embodiment. In the second embodiment, the differences from the first embodiment will be mainly described, and the description of the same configuration may be omitted.

掘削対象範囲2Aは、地盤2における既存柱1の直下の範囲を含む範囲であり、掘削工程において掘削する範囲である。また、掘削対象範囲2Aは、補強工程において既存の基礎構造体3を補強する範囲となる。本実施形態では、第1仮設柱7及び第2仮設柱8は、平面視で掘削対象範囲2Aに囲まれた第2仮設柱用基礎構造体21に固定される。 The excavation target range 2A is a range including a range directly under the existing pillar 1 in the ground 2 and is a range to be excavated in the excavation process. Further, the excavation target range 2A is a range for reinforcing the existing foundation structure 3 in the reinforcement step. In the present embodiment, the first temporary column 7 and the second temporary column 8 are fixed to the foundation structure 21 for the second temporary column surrounded by the excavation target range 2A in a plan view.

<受け替えフレーム>
図7に示すように、受け替えフレーム9は、第2方向Yに並ぶ仮設柱6の柱頭部6Aどうしを接続する水平姿勢の第6鉄骨フレーム部(図示せず)と、第6鉄骨フレームの中間部と既存柱1の柱脚部1Bとを接続する水平姿勢の第7鉄骨フレーム部20とを有する。
<Replacement frame>
As shown in FIG. 7, the replacement frame 9 includes a sixth steel frame portion (not shown) in a horizontal posture connecting the stigmas 6A of the temporary columns 6 arranged in the second direction Y, and the sixth steel frame. It has a seventh steel frame portion 20 in a horizontal posture that connects the intermediate portion and the stigma portion 1B of the existing column 1.

<設置工程>
設置工程では、図7に示すように、地盤2における既存柱1の直下から外れた部分を掘削対象範囲2Aの下端よりも下方側まで掘削し、その掘削した穴に第2仮設柱用基礎構造体21を構築するためのコンクリートを打設した後に仮設柱6を挿入して仮設柱6を地盤2に固定する。図7に示す例では、第2仮設柱用基礎構造体21は、掘削対象範囲2Aの下端より下方側に構築されている。そして、受け替えフレーム9を仮設柱6及び既存柱1に連結して、受け替え構造体4を設置する。
<Installation process>
In the installation process, as shown in FIG. 7, a portion of the ground 2 deviating from directly below the existing column 1 is excavated to the lower side of the lower end of the excavation target range 2A, and the excavated hole is used for the foundation structure for the second temporary column. After placing concrete for constructing the body 21, a temporary pillar 6 is inserted to fix the temporary pillar 6 to the ground 2. In the example shown in FIG. 7, the foundation structure 21 for the second temporary column is constructed below the lower end of the excavation target range 2A. Then, the replacement frame 9 is connected to the temporary pillar 6 and the existing pillar 1 to install the replacement structure 4.

<掘削工程>
掘削工程では、図8に示すように、掘削対象範囲2Aを掘削して掘削対象範囲2Aの土砂や岩石を掘り取ると共に、掘削対象範囲2Aにある基礎構造体3を除去し、既存柱1を受け替え構造体4のみで支持するようにする。
また、本実施形態では、掘削工程において、図8において掘削対象範囲2Aの左側に示すように、既存柱1を有する建築物の基礎として広範囲に亘ってコンクリートを打設するために、掘削対象範囲2Aに隣接する部分も掘削している。
<Excavation process>
In the excavation process, as shown in FIG. 8, the excavation target range 2A is excavated to excavate the earth and sand and rocks in the excavation target range 2A, and the foundation structure 3 in the excavation target range 2A is removed to remove the existing pillar 1. It is supported only by the replacement structure 4.
Further, in the present embodiment, in the excavation process, as shown on the left side of the excavation target range 2A in FIG. 8, the excavation target range is to be cast over a wide range as the foundation of the building having the existing pillar 1. The part adjacent to 2A is also excavated.

<補強工程>
補強工程では、図9に示すように、掘削対象範囲2Aにコンクリートを打設して第2基礎構造体18を構築し、既存柱1をアンカーボルト等の部材を用いて第2基礎構造体18に連結する。また、補強工程では、掘削工程において掘削した穴における第2仮設柱用基礎構造体21を打設していない部分にもコンクリートを打設する。
<Reinforcement process>
In the reinforcement step, as shown in FIG. 9, concrete is poured into the excavation target range 2A to construct the second foundation structure 18, and the existing pillar 1 is used as a member such as an anchor bolt to construct the second foundation structure 18. Connect to. Further, in the reinforcing process, concrete is also placed in the portion of the hole excavated in the excavation process where the foundation structure 21 for the second temporary column is not placed.

<撤去工程>
撤去工程では、図10に示すように、受け替えフレーム9を既存柱1や仮設柱6から取り外すと共に仮設柱6における掘削対象範囲2Aから上方に突出している部分を切断して、仮設柱6の一部を第2基礎構造体18内や第2仮設柱用基礎構造体21内に残した状態で受け替えフレーム9を撤去する。このように、受け替え構造体4を撤去することで、既存柱1から伝達される荷重が第2基礎構造体18によって負担される状態となる。
<Removal process>
In the removal step, as shown in FIG. 10, the replacement frame 9 is removed from the existing pillar 1 and the temporary pillar 6, and the portion of the temporary pillar 6 protruding upward from the excavation target range 2A is cut to form the temporary pillar 6. The replacement frame 9 is removed with a part left in the second foundation structure 18 and the foundation structure 21 for the second temporary column. By removing the replacement structure 4 in this way, the load transmitted from the existing pillar 1 is borne by the second foundation structure 18.

〔別実施形態〕
本発明の他の実施形態について説明する。尚、以下に説明する各実施形態の構成は、それぞれ単独で適用することに限らず、他の実施形態の構成と組み合わせて適用することも可能である。
[Another Embodiment]
Other embodiments of the present invention will be described. It should be noted that the configurations of the respective embodiments described below are not limited to being applied independently, but can also be applied in combination with the configurations of other embodiments.

(1)上記第1実施形態では、受け替えフレーム9に、第1鉄骨フレーム部11と第2鉄骨フレーム部12と第3鉄骨フレーム部13とを備える構成を例として説明した。しかし、このような構成に限定されない。例えば、受け替えフレーム9に、第1鉄骨フレーム部11と第2鉄骨フレーム部12と第3鉄骨フレーム部13とのうちの一部又は全部を備えなくてもよい。 (1) In the first embodiment, the configuration in which the replacement frame 9 is provided with the first steel frame portion 11, the second steel frame portion 12, and the third steel frame portion 13 has been described as an example. However, it is not limited to such a configuration. For example, the replacement frame 9 may not include a part or all of the first steel frame portion 11, the second steel frame portion 12, and the third steel frame portion 13.

1 既存柱
1B 柱脚部
2A 掘削対象範囲
4 受け替え構造体
6 仮設柱
6A 柱頭部
9 受け替えフレーム
11 第1鉄骨フレーム部
12 第2鉄骨フレーム部
13 第3鉄骨フレーム部
1 Existing column 1B Column base 2A Excavation target range 4 Replacement structure 6 Temporary column 6A Capital 9 Replacement frame 11 1st steel frame part 12 2nd steel frame part 13 3rd steel frame part

Claims (5)

既存柱の直下から外れた地盤部分から前記既存柱を支持自在な受け替え構造体を設置する設置工程と、前記設置工程の後に前記既存柱の直下の掘削対象範囲を掘削する掘削工程とを実行し、
前記受け替え構造体は、地盤に固定される複数の仮設柱と、当該仮設柱の柱頭部と前記既存柱とを接続する受け替えフレームとを有して、前記既存柱から伝達される長期荷重及び短期荷重を負担自在に構成されている掘削工法。
An installation process of installing a replacement structure that can support the existing pillar from the ground portion directly under the existing pillar, and an excavation process of excavating the excavation target area directly under the existing pillar after the installation process are executed. death,
The replacement structure has a plurality of temporary columns fixed to the ground and a replacement frame connecting the stigma of the temporary columns and the existing columns, and a long-term load transmitted from the existing columns. And an excavation method that is configured to freely bear short-term loads.
前記仮設柱は、平面視で前記掘削対象範囲から外れた地盤に固定される請求項1に記載の掘削工法。 The excavation method according to claim 1, wherein the temporary pillar is fixed to the ground outside the excavation target range in a plan view. 前記受け替えフレームは、前記複数の仮設柱の柱頭部どうしを接続する水平姿勢の第1鉄骨フレーム部を有する請求項1又は2に記載の掘削工法。 The excavation method according to claim 1 or 2, wherein the replacement frame has a first steel frame portion in a horizontal posture in which the stigmas of the plurality of temporary columns are connected to each other. 前記受け替えフレームは、前記仮設柱の柱頭部と前記既存柱の柱脚部を接続する水平姿勢の第2鉄骨フレーム部を有する請求項1から3の何れか一項に記載の掘削工法。 The excavation method according to any one of claims 1 to 3, wherein the replacement frame has a second steel frame portion in a horizontal posture connecting the stigma of the temporary column and the column base portion of the existing column. 前記受け替えフレームは、前記仮設柱の柱頭部と前記既存柱の柱脚部の上方側とを斜めに接続する斜め姿勢の第3鉄骨フレーム部を有する請求項1から4の何れか一項に記載の掘削工法。
According to any one of claims 1 to 4, the replacement frame has a third steel frame portion in an oblique posture that diagonally connects the stigma of the temporary column and the upper side of the column base portion of the existing column. The described excavation method.
JP2020207885A 2020-12-15 2020-12-15 Excavation method Pending JP2022094798A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP2020207885A JP2022094798A (en) 2020-12-15 2020-12-15 Excavation method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP2020207885A JP2022094798A (en) 2020-12-15 2020-12-15 Excavation method

Publications (1)

Publication Number Publication Date
JP2022094798A true JP2022094798A (en) 2022-06-27

Family

ID=82162463

Family Applications (1)

Application Number Title Priority Date Filing Date
JP2020207885A Pending JP2022094798A (en) 2020-12-15 2020-12-15 Excavation method

Country Status (1)

Country Link
JP (1) JP2022094798A (en)

Similar Documents

Publication Publication Date Title
JP2008013926A (en) Existing building foundation reinforcing method
JP4069509B2 (en) Construction method of reverse struts in the outer periphery of underground excavation space
JP5092705B2 (en) Support structure of structure, construction method of underground structure, replacement method of foundation load
KR102190622B1 (en) Multi-steel boxes for connecting structures and construction method using the same
JP3850785B2 (en) Caisson laying method using main foundation pile
JP2022094798A (en) Excavation method
KR101587062B1 (en) Steel composite underground earth retaining wall structure and it&#39;s construction method
KR102076969B1 (en) Top-down construction method for concrete building structure using steel pile underground wall and shear support plate
JP2016223084A (en) Construction method of underground structure by inverted construction method
JP6868881B2 (en) Foundation structure and its foundation construction method
KR101383817B1 (en) Top down method
JP2011246910A (en) Construction method of underground structure
KR102254227B1 (en) High-strength concrete pile structure with pc pile cap and construction method
JP2016089481A (en) Extension method for underground facility
JP7128094B2 (en) Construction method of foundation structure
CN114215106A (en) Multi-pile support column structure adopting upper steel structure full-reverse construction method and construction method
KR100650134B1 (en) Early remove support method
JP4466418B2 (en) Soil cement wall pile, soil cement structure
KR101707376B1 (en) Structure for constructing underground structure using composite beams and the construction method thereof
JP6083788B2 (en) Temporary support method for foundation
JPH11140892A (en) Method for excavating ground and method for constructing underground structure using the same
JP2017119953A (en) Building method using reverse out method
JP4466419B2 (en) Soil cement column wall
JP3228199U (en) Construction structure of earth retaining support
JP6529241B2 (en) Building foundation structure and construction method of building foundation structure

Legal Events

Date Code Title Description
A621 Written request for application examination

Free format text: JAPANESE INTERMEDIATE CODE: A621

Effective date: 20230921

A131 Notification of reasons for refusal

Free format text: JAPANESE INTERMEDIATE CODE: A131

Effective date: 20240327

A977 Report on retrieval

Free format text: JAPANESE INTERMEDIATE CODE: A971007

Effective date: 20240329