JP2022033346A - Slab replacement method - Google Patents
Slab replacement method Download PDFInfo
- Publication number
- JP2022033346A JP2022033346A JP2022001494A JP2022001494A JP2022033346A JP 2022033346 A JP2022033346 A JP 2022033346A JP 2022001494 A JP2022001494 A JP 2022001494A JP 2022001494 A JP2022001494 A JP 2022001494A JP 2022033346 A JP2022033346 A JP 2022033346A
- Authority
- JP
- Japan
- Prior art keywords
- floor slab
- new
- deck
- existing
- bridge girder
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Granted
Links
Images
Landscapes
- Bridges Or Land Bridges (AREA)
Abstract
Description
本発明は、橋梁などの構造物を構成する床版の架け替え(既設床版の撤去とこれに替わる新設床版の設置)を行う方法に関する。 The present invention relates to a method for replacing a floor slab constituting a structure such as a bridge (removal of an existing floor slab and installation of a new floor slab in place of the existing floor slab).
橋梁は、例えば、複数の橋脚と、各々が複数の橋脚の上に跨がって橋軸方向に延びる複数の橋桁(H形鋼)と、複数の橋桁の上に跨がって配設される床版と、を含んで構成される。床版は、例えば鉄筋コンクリート製である。かかる床版については、長年の使用によるコンクリートの劣化や内部の鉄筋の腐食などの理由で、架け替え(既設床版の撤去と新設床版の設置)が求められる場合がある。 The bridge is arranged, for example, over a plurality of piers, a plurality of bridge girders (H-shaped steel) each straddling a plurality of piers and extending in the direction of the bridge axis, and a plurality of bridge girders. It is composed of a floor slab and a floor slab. The deck is made of, for example, reinforced concrete. For such decks, replacement (removal of existing decks and installation of new decks) may be required due to deterioration of concrete due to long-term use and corrosion of internal reinforcing bars.
床版の架け替えに用いられる装置としては、例えば特許文献1に記載の床版架設機が知られている。これは、橋軸方向前後の門型フレームを連結してなる無軌条・自走式の門型構造体と、門型構造体の天井部の下面側に前後方向及び横方向に移動可能に設けられる吊上装置(例えばチェーンブロック)と、を備えている。ここにおいて、新設床版はプレキャストコンクリート製である。
As a device used for replacing the deck, for example, the deck erection machine described in
このような架設機を用いた新設床版の架設作業は、
(1)架設機の後部での新設床版の取込み、すなわち、架設機の後部に位置させた吊上装置による、新設床版の長辺を橋軸方向に向けた状態での、新設床版の吊上げ
(2)吊上装置の前側への移動による、新設床版の架設位置までの移送
(3)新設床版の長辺を橋軸直角方向に向けるように、新設床版の向きの変更(90°回転)
(4)そして、所定位置への設置
という工程で行われる。
また、既設の床版の撤去作業は、入れ替わりで、ほぼ逆の工程で行われる。
The work of erection of a new floor slab using such an erection machine is
(1) Taking in the new deck at the rear of the erection machine, that is, the new deck with the long side of the new deck facing the bridge axis direction by the lifting device located at the rear of the erection machine. (2) Transfer of the new deck to the erection position by moving it to the front side of the lifting device (3) Changing the orientation of the new deck so that the long side of the new deck faces in the direction perpendicular to the bridge axis. (Rotation 90 °)
(4) Then, it is performed in the process of installing in a predetermined position.
In addition, the work of removing the existing floor slab is replaced and performed in almost the reverse process.
しかしながら、前述の架設機を用いる床版架け替え方法では、ある施工場所で既設床版の撤去から新設床版の設置までを行った後に前述の架設機が橋軸方向に移動して、次の施工場所で既設床版の撤去から新設床版の設置までを行う。ゆえに、ある施工場所での床版の架け替え作業が完了するまでは次の施工場所で床版の架け替え作業を開始することができず、その結果、橋梁の全長にわたって床版の架け替えを行うのに時間がかかるという問題点があった。 However, in the floor slab replacement method using the above-mentioned erection machine, the above-mentioned erection machine moves in the direction of the bridge axis after the existing floor slab is removed and the new floor slab is installed at a certain construction site, and the following From the removal of the existing floor slab to the installation of the new floor slab at the construction site. Therefore, until the floor slab replacement work at one construction site is completed, the floor slab replacement work cannot be started at the next construction site, and as a result, the floor slab replacement work is performed over the entire length of the bridge. There was a problem that it took time to do.
本発明は、このような実状に鑑み、橋梁などの構造物において、効率的な床版の架け替えを行うことができる、床版架け替え方法を提供することを目的とする。 In view of such an actual situation, it is an object of the present invention to provide a floor slab replacement method capable of efficiently replacing a deck in a structure such as a bridge.
そのため本発明に係る床版架け替え方法の第1~第8態様は、橋桁を有する構造物において、橋桁上に配設される床版を既設床版から新設床版に架け替える方法である。本発明に係る床版架け替え方法の第1~第8態様は、構造物の軸方向に複数の施工領域に区分けすることにより、複数の施工領域を設定することを含み、既設床版撤去工程、新設床版配置準備工程、及び新設床版配置工程を有し、既設床版撤去工程は、既設床版の床版片を撤去することを含み、新設床版配置準備工程は、床版片が撤去された橋桁上に新設床版を配置するための準備作業をすることを含み、新設床版配置工程は、前記準備作業がなされた橋桁上に新設床版を配置することを含む。本発明に係る床版架け替え方法の第1~第8態様では、軸方向に沿う床版架け替え施工進行方向において、前記進行方向前側から後側に向かって順に、既設床版撤去工程を実施する第1施工領域と、第1施工領域にて既設床版撤去工程が実施されている場合に新設床版配置準備工程を実施する第2施工領域と、第2施工領域にて新設床版配置準備工程が実施されている場合に新設床版配置工程を実施する第3施工領域と、が並ぶ。本発明に係る床版架け替え方法の第1~第8態様では、橋桁上の既設の床版上には、既設床版撤去工程で用いられる第1クレーン装置が位置し、橋桁上に新設された床版上には、新設床版配置工程で用いられる第2クレーン装置が位置する。
本発明に係る床版架け替え方法の第1態様では、第1クレーン装置は、軸方向に延びる一対の下部フレームと、一対の下部フレームに下端が連結された門型フレームと、門型フレームの上部に設けられた上部フレームと、上部フレームに対して軸方向に移動可能な吊上装置と、を含む。
本発明に係る床版架け替え方法の第2態様では、第1クレーン装置は、軸方向に延びる一対の下部フレームと、一対の下部フレームに下端が連結された門型フレームと、吊上装置と、を含み、一対の下部フレームには、転動可能な車輪が設けられている。
本発明に係る床版架け替え方法の第3態様では、第1クレーン装置は、軸方向に延びる一対の下部フレームと、一対の下部フレームに下端が連結された門型フレームと、吊上装置と、を含み、床版片を運搬する運搬車両が、門型フレーム内、及び、一対の下部フレーム間に配置され得る。
本発明に係る床版架け替え方法の第4態様では、第2クレーン装置は、軸方向に延びる一対の下部フレームと、一対の下部フレームに下端が連結された門型フレームと、門型フレームの上部に設けられた上部フレームと、上部フレームに対して軸方向に移動可能な吊上装置と、を含む。
本発明に係る床版架け替え方法の第5態様では、第2クレーン装置は、軸方向に延びる一対の下部フレームと、一対の下部フレームに下端が連結された門型フレームと、吊上装置と、を含み、一対の下部フレームには、転動可能な車輪が設けられている。
本発明に係る床版架け替え方法の第6態様では、第2クレーン装置は、軸方向に延びる一対の下部フレームと、一対の下部フレームに下端が連結された門型フレームと、吊上装置と、を含み、新設床版を搬送する搬送台車が、門型フレーム内、及び、一対の下部フレーム間を走行可能である。
本発明に係る床版架け替え方法の第7態様では、第2施工領域の軸方向の長さが、床版片の軸方向の長さよりも長い。
本発明に係る床版架け替え方法の第8態様では、第2施工領域の軸方向の長さが、新設床版の軸方向の長さよりも長い。
Therefore, the first to eighth aspects of the floor slab replacement method according to the present invention are methods for replacing the floor slab arranged on the bridge girder from the existing floor slab to the new floor slab in the structure having the bridge girder. The first to eighth aspects of the floor slab replacement method according to the present invention include setting a plurality of construction areas by dividing them into a plurality of construction areas in the axial direction of the structure, and include an existing deck slab removal step. , A new deck placement preparation process, and a new deck placement process, the existing deck removal process includes removing the deck piece of the existing deck, and the new deck placement preparation step is a deck piece. The new deck placement step includes placing the new deck on the bridge girder on which the preparatory work has been performed. In the first to eighth aspects of the floor slab replacement method according to the present invention, the existing floor slab removal step is carried out in order from the front side to the rear side in the traveling direction in the floor slab replacement construction progress direction along the axial direction. First construction area to be carried out, second construction area to carry out the new deck placement preparation process when the existing deck removal process is carried out in the first construction area, and new deck placement in the second construction area. There is a third construction area where the new floor slab placement process is carried out when the preparatory process is carried out. In the first to eighth aspects of the deck replacement method according to the present invention, the first crane device used in the existing deck removal step is located on the existing deck on the bridge girder, and is newly installed on the bridge girder. The second crane device used in the new deck placement process is located on the deck.
In the first aspect of the floor slab replacement method according to the present invention, the first crane device includes a pair of lower frames extending in the axial direction, a portal frame having a lower end connected to the pair of lower frames, and a portal frame. It includes an upper frame provided on the upper part and a lifting device that can move axially with respect to the upper frame.
In the second aspect of the floor slab replacement method according to the present invention, the first crane device includes a pair of lower frames extending in the axial direction, a portal frame having a lower end connected to the pair of lower frames, and a lifting device. , And the pair of lower frames are provided with rollable wheels.
In the third aspect of the floor slab replacement method according to the present invention, the first crane device includes a pair of lower frames extending in the axial direction, a portal frame having a lower end connected to the pair of lower frames, and a lifting device. , And transport vehicles carrying deck pieces may be placed within the portal frame and between a pair of lower frames.
In the fourth aspect of the floor slab replacement method according to the present invention, the second crane device includes a pair of lower frames extending in the axial direction, a portal frame having a lower end connected to the pair of lower frames, and a portal frame. It includes an upper frame provided on the upper part and a lifting device that can move axially with respect to the upper frame.
In the fifth aspect of the floor slab replacement method according to the present invention, the second crane device includes a pair of lower frames extending in the axial direction, a portal frame having a lower end connected to the pair of lower frames, and a lifting device. , And the pair of lower frames are provided with rollable wheels.
In the sixth aspect of the floor slab replacement method according to the present invention, the second crane device includes a pair of lower frames extending in the axial direction, a portal frame having a lower end connected to the pair of lower frames, and a lifting device. , And a transport crane for transporting the new deck can travel within the portal frame and between the pair of lower frames.
In the seventh aspect of the floor slab replacement method according to the present invention, the axial length of the second construction area is longer than the axial length of the floor slab piece.
In the eighth aspect of the floor slab replacement method according to the present invention, the axial length of the second construction area is longer than the axial length of the new floor slab.
本発明によれば、床版架け替え施工の進捗状況が異なる複数の施工領域にて、並行して(すなわち同時に)施工を進めることができるので、床版の架け替えを効率良く(換言すれば短期間で)行うことができる。 According to the present invention, it is possible to proceed with the construction in parallel (that is, at the same time) in a plurality of construction areas where the progress of the floor slab replacement construction is different, so that the floor slab replacement can be efficiently (in other words, in other words). Can be done in a short period of time).
以下、本発明の実施の形態について、図面を参照して説明する。尚、全図中、同一又は相当部分には同一符号を付すこととする。 Hereinafter, embodiments of the present invention will be described with reference to the drawings. In all the drawings, the same or corresponding parts are designated by the same reference numerals.
図1は、本発明に係る床版架け替え方法が適用され得る既設の橋梁の一例の側面図である。図2は、本発明の第1実施形態における床版架け替え方法の施工状態を示す側面図である。尚、本実施形態では、橋梁における床版架け替え施工の進行方向を前進方向として図1及び図2に示すように前後を規定して、以下説明する。ここで、床版架け替え施工進行方向は、橋梁の橋軸方向に沿う。また、本実施形態では、橋梁の橋軸直角方向を左右方向(横方向)として、以下説明する(図10A~図12参照)。 FIG. 1 is a side view of an example of an existing bridge to which the floor slab replacement method according to the present invention can be applied. FIG. 2 is a side view showing a construction state of the floor slab replacement method according to the first embodiment of the present invention. In this embodiment, the front and back are defined as shown in FIGS. 1 and 2 with the traveling direction of the floor slab replacement work on the bridge as the forward direction, and the following description will be made. Here, the direction of progress of the floor slab replacement work is along the bridge axis direction of the bridge. Further, in the present embodiment, the direction perpendicular to the bridge axis of the bridge is defined as the left-right direction (lateral direction), which will be described below (see FIGS. 10A to 12).
尚、本実施形態では、本発明の「構造物」(土木構造物)の一例として橋梁を挙げて説明するが、本発明の「構造物」は橋梁に限らない。また、前述の橋軸方向が、本発明の「構造物の軸方向」及び「橋梁の軸方向」に対応し得る。 In the present embodiment, a bridge will be described as an example of the "structure" (civil engineering structure) of the present invention, but the "structure" of the present invention is not limited to the bridge. Further, the above-mentioned bridge axial direction may correspond to the "axial direction of the structure" and the "axial direction of the bridge" of the present invention.
本発明の「構造物」の一例である橋梁1は、前後一対の橋台2a,2bと、橋台2a,2b間に間隔を空けて配設された複数の橋脚3と、各々が橋台2a,2b及び複数の橋脚3の上に跨がって橋軸方向に延びる複数の橋桁(H形鋼)4と、複数の橋桁4の上に跨がって配設されたコンクリート製の既設床版5と、を含んで構成される。尚、橋台2a,2b及び複数の橋脚3と複数の橋桁4との間には、図示しない支承が介装されている。ここで、本実施形態では、既設床版5が鉄筋コンクリート製である(RC床版である)として以下説明するが、この他、既設床版5は、プレストレストコンクリート製であってもよい(PC床版であってもよい)。また、橋桁4は、後述する図10A~図10Cに示すように、ウェブ4wと、上フランジ4fと、下フランジ(図示せず)とを有している。
The
本実施形態では、橋梁1の全長(橋長)Ltが300mであるとして以下説明するが、橋梁1の全長Ltは300mに限らない。また、本実施形態では、橋梁1の橋軸直角方向において既設床版5を分割しない、いわゆる全断面床版架け替え施工であるとして以下説明するが、施工形態はこれに限らず、例えば、橋梁1の橋軸直角方向において既設床版5を2つに分割する、いわゆる半断面床版架け替え施工であってもよい。
In the present embodiment, it will be described below assuming that the total length (bridge length) Lt of the
図1及び図2に加えて、図3及び図4を用いて、本実施形態における床版架け替え方法を説明する。図3は、本実施形態における床版架け替え方法のメインルーチンを示すフローチャートである。図4は、本実施形態における床版架け替え方法のサブルーチンを示すフローチャートである。 In addition to FIGS. 1 and 2, FIGS. 3 and 4 will be used to explain the floor slab replacement method in the present embodiment. FIG. 3 is a flowchart showing the main routine of the floor slab replacement method in the present embodiment. FIG. 4 is a flowchart showing a subroutine of the floor slab replacement method in the present embodiment.
橋梁1の床版架け替え施工(既設床版5の撤去と、これに替わる新設床版7の設置)は、全体的には、図3に示すメインルーチンに従う。
The floor slab replacement work of the bridge 1 (removal of the existing
まず、ステップS101では、橋梁1を橋軸方向に複数(本実施形態ではn個)の施工領域A1~Anに区分けすることにより、複数の施工領域A1~Anを設定する。尚、本実施形態では、施工領域A1~Anの各々の橋軸方向の長さが、それぞれ6mであるとして以下説明するが、施工領域A1~Anの各々の橋軸方向の長さは6mに限らない。例えば、橋梁1の全長Ltが300mであり、かつ、施工領域A1~Anの各々の橋軸方向の長さが、それぞれ6mである場合には、n=300/6=50となる。
First, in step S101, a plurality of construction areas A1 to An are set by dividing the bridge 1 into a plurality of construction areas A1 to An ( n in the present embodiment) in the bridge axis direction. In the present embodiment, the length of each of the construction areas A1 to An in the bridge axis direction will be described below as 6 m , but the length of each of the construction areas A1 to An in the bridge axis direction will be described below. The size is not limited to 6m. For example, when the total length Lt of the
次に、ステップS102では、施工領域A1~Anの各々にて、既設床版5の撤去と、これに替わる新設床版7の配置とを行う。本実施形態では、例えば図2に示すように、複数の施工領域Ak~Ak-6にて床版架け替え作業が並行して実施可能である。尚、本実施形態では、床版架け替え施工進行方向において、前側の施工領域(例えば施工領域Ak-4)と、この施工領域より後方の施工領域(例えば施工領域Ak-6)とにて、互いに異なる作業工程を並行して実施し得る。
Next, in step S102, the existing
施工領域A1~Anの全てで既設床版5の撤去と、これに替わる新設床版7の配置とが行われると(すなわち、橋梁1の全長Ltにわたって新設床版7の配置が完了すると)、ステップS103に進み、新設床版7と橋桁4とを固定して一体化すると共に、橋軸方向で隣り合う新設床版7同士を固定して一体化する。
このようにして、橋梁1の床版架け替え施工が行われる。
When the existing
In this way, the floor slab replacement work of the
前述のステップS102に関して、施工領域A1~Anの各々は、既設床版5の撤去から新設床版7の配置に至る複数段の作業工程を有する。この複数段の作業工程が図4に示されている。
図4に示すように、まず、ステップS1にて、前段(第1段)として、既設床版5の撤去作業を実施する。ここで、ステップS1が、本発明の「第1作業工程」に対応する。
With respect to the above-mentioned step S102 , each of the construction areas A1 to An has a plurality of work steps from the removal of the existing
As shown in FIG. 4, first, in step S1, the existing
次に、ステップS2にて、中段(第2段)として、既設床版5が撤去された施工領域に新設床版7を配置するための準備作業(新設床版7の配置準備作業)を実施する。ここで、ステップS2が、本発明の「第2作業工程」に対応する。
Next, in step S2, as the middle stage (second stage), preparatory work for arranging the
次に、ステップS3にて、後段(第3段)として、新設床版7の配置準備作業が実施された施工領域に新設床版7を配置する。ここで、ステップS3が、本発明の「第3作業工程」に対応する。
Next, in step S3, as the latter stage (third stage), the
ここで、ステップS1にて実施される既設床版5の撤去作業について、前述の図1~図4に加えて、図5及び図8A~図9Bを用いて説明する。
図5は、本実施形態における既設床版5の撤去方法を示すフローチャートである。図8A及び図8Bは、本実施形態における既設床版5の切断方法を示す図である。図9A及び図9Bは、本実施形態における既設床版5の縁切り方法を示す図である。
Here, the work of removing the existing
FIG. 5 is a flowchart showing a method of removing the existing
図5に示すように、まず、ステップS11では、既設床版5の切断作業を実施する。このステップS11では、図8A及び図8Bに示すように、既設床版5の後端から所定長さLa分前方の箇所に切断線5bを設定し、この切断線5bに沿って、コンクリートカッターやワイヤーソーなどのコンクリート切断装置を用いて既設床版5を切断して、床版片5aを形成する。本実施形態では、前述の所定長さLaが2mであるとしているが、前述の所定長さLaは2mに限らない。
As shown in FIG. 5, first, in step S11, the cutting work of the existing
次に、ステップS12にて、既設床版5の床版片5aの縁切り作業を実施する。このステップS12では、まず、図9Aに示すように、床版片5aの前方と後方とに、それぞれ、短縮状態の複数のジャッキ50a,50bを設置する。ここで、ジャッキ50a,50bは上下方向に伸縮自在であり、例えば油圧ジャッキである。
Next, in step S12, the edge cutting work of the
前側のジャッキ50aは、その下端部が既設床版5の上面に当接する。後側のジャッキ50bは、その下端部が橋桁4の上面4a(詳しくは、図10A~図10Cに示す橋桁4の上フランジ4fの上面4a)に当接する。
The lower end of the
また、図9Aに示すように、ジャッキ50a,50bの上に跨がるように、梁部材51が配置されている。梁部材51は、ジャッキ50a,50bの上端部に固定されている。梁部材51は、図示しないブラケットを有し、このブラケットと、床版片5aとを貫通するように、上下方向に延びるPC鋼棒52が配置されている。PC鋼棒52については、橋桁4をかわすように配置されている。PC鋼棒52の上端部及び下端部には、それぞれ、梁部材51(前述のブラケット)及び床版片5aとPC鋼棒52とを固定するための固定部材53a,53bが取り付けられている。
Further, as shown in FIG. 9A, the
次に、図9Bに示すように、ジャッキ50a,50bを伸長作動させることにより、梁部材51(前述のブラケット)及びPC鋼棒52を介して、床版片5aが引っ張り上げられる。このようにして、床版片5aが橋桁4から分離(縁切り)されると、ジャッキ50a,50bを短縮し、PC鋼棒52、梁部材51、及びジャッキ50a,50bを撤去する。
Next, as shown in FIG. 9B, by extending the
次に、図5のステップS13にて、橋桁4から縁切りされた床版片5aを、図2に示すクレーン装置20にて吊り上げ、床版片5aの長辺を橋軸方向に向けるように床版片5aの向きを変更して(すなわち90°回転させて)、この床版片5aを、クレーン装置20により、図示しない運搬車両の荷台に載せる。この運搬車両は、床版片5aを、施工領域A1~Anから床版架け替え施工進行方向前方に搬出し得る。尚、この運搬車両は、既設床版5上を走行可能である。
Next, in step S13 of FIG. 5, the
クレーン装置20は、前後方向に延びる左右一対の下部フレーム21と、左右一対の下部フレーム21に下端が連結された門型フレーム22と、門型フレーム22の上部に設けられた上部フレーム23と、上部フレーム23に対して前後左右に移動可能な吊上装置24と、を含んで構成されている。左右一対の下部フレーム21には、既設床版5上を転動可能な車輪が設けられている。門型フレーム22内、及び、左右一対の下部フレーム21間には、前述の運搬車両の荷台が配置され得る。
The
本実施形態では、1つの施工領域ごとに(すなわち施工領域A1~Anの各々で)、前述のステップS11~S13を3回実施することで、1つの施工領域の橋軸方向の長さ分である6m分の既設床版5の撤去作業を行う。
以上のようにして、図4のステップS1にて、既設床版5の撤去作業が実施される。
In the present embodiment, the length of one construction area in the bridge axis direction is obtained by performing the above-mentioned steps S11 to S13 three times for each construction area (that is, in each of the construction areas A1 to Ann). Remove the existing
As described above, the work of removing the existing
次に、図4のステップS2にて実施される新設床版7の配置準備作業について、前述の図1~図4に加えて、図6及び図10A~図10Cを用いて説明する。
図6は、本実施形態における新設床版7の配置準備方法を示すフローチャートである。図10A~図10Cは、本実施形態における新設床版7の配置準備方法を示す図である。ここで、図10A~図10Cは、後述する図11AのI-I断面に対応している。
Next, the arrangement preparation work of the
FIG. 6 is a flowchart showing a method of preparing the arrangement of the
図6に示すように、まず、ステップS21では、既設床版5(床版片5a)が撤去されて外部に露出している橋桁4の上面4a(詳しくは、図10Aに示す橋桁4の上フランジ4fの上面4a)のケレン作業を実施する。ここで、ケレン作業は、橋桁4の上面4aに残留しているコンクリート片などを除去することを含み得る。
As shown in FIG. 6, first, in step S21, the existing floor slab 5 (
次に、ステップS22では、ケレン作業が実施された橋桁4の上フランジ4fの左右両側部に、例えばゴム製のフランジシール60を設置する(図10B参照)。フランジシール60は、橋軸方向に延びる板状である。このフランジシール60は、前述のステップS103にて新設床版7と橋桁4とを固定して一体化する際に新設床版7と橋桁4との間の空間9(図11B参照)内に打設されるモルタルが空間9外に漏れ出ることを防ぐためのものである。
Next, in step S22, for example, rubber flange seals 60 are installed on the left and right sides of the
次に、ステップS23では、新設床版7の配置高さを調整するための複数の高さ調整材70を、橋桁4の上フランジ4fの上面4aに設置する(図10C参照)。高さ調整材70は、上下方向に伸縮自在であることが好ましい。高さ調整材70は、例えば、上下方向に伸縮自在な手動式のジャッキであり得る。又は、高さ調整材70は、それ自体の高さが決定された後に変形不可能な剛性を有する部材(スペーサー)により構成されてもよい。複数の高さ調整材70は、橋軸方向に互いに間隔を空けて、橋軸方向に並んでいる。
Next, in step S23, a plurality of
尚、高さ調整材70については、前述のステップS3及び後述のステップS31にて新設床版7が橋桁4上に配置されたときに、計画された新設床版7の配置高さとなるように、新設床版7の橋桁4上への配置に先立って、高さ調整材70自体の高さ調整が行われ得る。高さ調整材70自体の高さ調整は、ステップS23にて橋桁4の上フランジ4fの上面4aに設置する前に行ってもよく、また、橋桁4の上フランジ4fの上面4aに設置した後に行ってもよい。
Regarding the
本実施形態では、フランジシール60の設置後に高さ調整材70の設置を行っているが、この他、フランジシール60の設置に先立って高さ調整材70の設置を行ってもよい。すなわち、ステップS22とステップS23とを入れ替えてもよい。
以上のようにして、図4のステップS2にて、新設床版7の配置準備作業が実施される。
In the present embodiment, the
As described above, in step S2 of FIG. 4, the arrangement preparation work of the
次に、図4のステップS3にて実施される新設床版7の配置作業について、前述の図1~図4に加えて、図7、図11A、図11B及び図12を用いて説明する。
図7は、本実施形態における新設床版7の配置方法を示すフローチャートである。図11A及び図11Bは、本実施形態における新設床版7の配置方法を示す図である。ここで、図11Bは、図11AのI-I断面に対応している。図12は、スタッドジベル80の設置方法を示す図である。
Next, the arrangement work of the
FIG. 7 is a flowchart showing a method of arranging the
図7に示すように、まず、ステップS31では、橋桁4の上フランジ4fの上面4aに設置された複数の高さ調整材70に、新設床版7を載置する(図11A及び図11B参照)。これにより、橋桁4の上フランジ4fの上面4aと、新設床版7の下面7bと、フランジシール60とによって囲まれた空間9が形成される。
As shown in FIG. 7, first, in step S31, the
新設床版7は、プレキャストコンクリート製である(すなわち、PCa床版である)。新設床版7は、橋軸方向を短辺とし、橋軸直角方向を長辺とする、略矩形状である。本実施形態では、新設床版7の橋軸方向の長さが2mであるが、新設床版7の橋軸方向の長さは2mに限らない。
新設床版7には、橋桁4の上フランジ4fの上面4aに相対するように、複数の貫通孔7aが形成されている。
The
The
ステップS31における新設床版7の配置作業(載置作業)には、図2に示すクレーン装置30が用いられる。クレーン装置30は、前後方向に延びる左右一対の下部フレーム31と、左右一対の下部フレーム31に下端が連結された門型フレーム32と、門型フレーム32の上部に設けられた上部フレーム33と、上部フレーム33に対して前後左右に移動可能な吊上装置34と、を含んで構成されている。左右一対の下部フレーム31には、橋桁4上に載置された新設床版7上を転動可能な車輪が設けられている。門型フレーム32内、及び、左右一対の下部フレーム31間を、搬送台車40が走行可能である。
The
クレーン装置30によって吊り上げられる予定の新設床版7は、搬送台車40によって、橋台2b(図1参照)に隣接する地面上からクレーン装置30まで搬送される。尚、橋桁4上に載置されて隣り合う新設床版7同士の間の隙間を上から覆うように鉄板などの板状部材を敷くことで、搬送台車40の走行安定性を向上させてもよい。搬送台車40は、自走式であってもよい。搬送台車40は、ゴム製のタイヤが使用された車輪を含んで構成されることが好ましい。
The
橋台2bに隣接する地面上では、クレーン装置30まで搬送台車40によって搬送される予定の新設床版7が、図示しない運搬車両から、この運搬車両より重量が軽い搬送台車40に荷卸しされる。この荷卸し作業には、前述のクレーン装置20,30と同様の構成のクレーン装置を用いてもよい。
従って、本実施形態では、新設床版7を、床版架け替え施工進行方向後方から施工領域A1~Anに搬入する。
On the ground adjacent to the
Therefore, in the present embodiment, the newly installed
尚、本実施形態では、搬送台車40上からクレーン装置30によって新設床版7を吊り上げた後に、クレーン装置30によって新設床版7の長辺を橋軸直角方向に向けるように新設床版7の向きを変更する(すなわち90°回転させる)。
In the present embodiment, after the
本実施形態では、1つの施工領域ごとに(すなわち施工領域A1~Anの各々で)、前述のステップS31を3回実施することで、1つの施工領域の橋軸方向の長さ分である6m分(つまり3枚)の新設床版7の配置作業を行う。
In the present embodiment, by performing the above-mentioned step S31 three times for each construction area (that is, in each of the construction areas A1 to Ann), the length of one construction area in the bridge axis direction can be obtained. Arrangement work of a certain 6m (that is, 3 sheets) of
次に、図7のステップS32では、図12に示すように、複数のスタッドジベル80を、新設床版7の貫通孔7a内に位置するように、橋桁4の上フランジ4fの上面4aに溶接固定する。尚、ステップS32のスタッドジベル80の設置作業の途中で搬送台車40が通過する場合には、搬送台車40の通過時にスタッドジベル80の設置作業を中断する。
以上のようにして、図4のステップS3にて、新設床版7の配置作業が実施される。
Next, in step S32 of FIG. 7, as shown in FIG. 12, a plurality of stud gibber 80s are welded to the
As described above, the arrangement work of the
図2に示す、ある時刻での施工状態では、施工領域Ak+1にクレーン装置20が位置する。施工領域Ak+1の後方に位置する施工領域Akでは、前述のステップS1(ステップS11~S13)に示した作業が実施されている。施工領域Akの後方に位置する施工領域Ak-1では、前述のステップS21に示した作業が実施されている。施工領域Ak-1の後方に位置する施工領域Ak-2では、前述のステップS22に示した作業が実施されている。施工領域Ak-2の後方に位置する施工領域Ak-3では、前述のステップS23に示した作業が実施されている。施工領域Ak-3の後方に位置する施工領域Ak-4では、前述のステップS31に示した作業が実施されている。施工領域Ak-4の後方に位置する施工領域Ak-5にはクレーン装置30が位置する。施工領域Ak-5の後方に位置する施工領域Ak-6では、前述のステップS32に示した作業が実施されている。尚、図2に示す符号「α」は、前述のステップS1~S3(ステップS11~S32)の途中で作業を休止していることを示す。
In the construction state at a certain time shown in FIG. 2, the
本実施形態では、ステップS1の作業が行われている施工領域(例えば、図2に示す施工領域Ak)からステップS32の作業が行われている施工領域(例えば、図2に示す施工領域Ak-6)までを覆うように、仮設テント10が設けられている。それゆえ、ステップS21でのケレン作業や、ステップS32での溶接作業が、仮設テント10内で実施される。尚、仮設テント10によって覆われる施工領域は、図2に示したものに限らない。
In the present embodiment, the construction area where the work of step S1 is performed (for example, the construction area Ak shown in FIG. 2) to the construction area where the work of step S32 is performed (for example, the construction area A shown in FIG. 2). A
このようにして、本実施形態では、床版架け替え施工進行方向において、前側の施工領域と、この施工領域より後方の施工領域とにて、互いに異なる作業工程を並行して(すなわち同時に)実施可能である。
また、本実施形態では、床版架け替え施工進行方向において、前側の施工領域から後側の施工領域に向かうほど(例えば、図2に示す施工領域Akから施工領域Ak-6に向かうほど)、後段の作業工程となるように(すなわちステップS32に近づくように)、複数段の作業工程(ステップS1~S32)を並行して(すなわち同時に)実施可能である。
In this way, in the present embodiment, different work processes are performed in parallel (that is, at the same time) in the construction area on the front side and the construction area behind this construction area in the floor slab replacement construction progress direction. It is possible.
Further, in the present embodiment, in the floor slab replacement construction progress direction, the more from the front side construction area to the rear side construction area (for example, from the construction area Ak shown in FIG. 2 to the construction area Ak-6 ). ), It is possible to carry out a plurality of work steps (steps S1 to S32) in parallel (that is, at the same time) so as to be a work step in a subsequent stage (that is, to approach step S32).
本実施形態では、図2に示すように、床版架け替え施工進行方向において、クレーン装置30の前方にクレーン装置20が位置している。
In the present embodiment, as shown in FIG. 2, the
本実施形態では、床版架け替え施工が進むのに追従して、仮設テント10及びクレーン装置20,30が前進する。ゆえに、複数段の作業工程(ステップS1~S32)を並行して(すなわち同時に)実施可能な床版架け替えシステムも前進する。ここで、この床版架け替えシステムは仮設テント10及びクレーン装置20,30を含む。
In the present embodiment, the
図13は、本実施形態における時刻t=t1~t10と施工領域A1~A9の各々の作業工程との関係を示す図である。図14は、本実施形態における時刻t=t1~t15と施工領域A1~A8の各々の作業工程との関係を示す図である。 FIG. 13 is a diagram showing the relationship between the times t = t1 to t10 and the respective work processes of the construction areas A1 to A9 in the present embodiment. FIG. 14 is a diagram showing the relationship between the times t = t1 to t15 and the respective work processes of the construction areas A1 to A8 in the present embodiment.
尚、図13及び図14に示す符号「α」は、前述の図2と同様に、前述のステップS1~S3(ステップS11~S32)の途中で作業を休止していることを示す。 The reference numeral “α” shown in FIGS. 13 and 14 indicates that the work is suspended in the middle of the above-mentioned steps S1 to S3 (steps S11 to S32) as in the above-mentioned FIG.
また、前述の時刻t1~t2間の時間,時刻t2~t3間の時間,・・・,時刻t13~t14間の時間,時刻t14~t15間の時間は、それぞれ、同じ時間(本実施形態では1.2時間とするが、これに限らない)である。また、1つの施工領域(すなわち施工領域A1~Anの各々)について、ステップS1,S21,S22,S23,S31,S32の作業工程時間が同じである。この作業工程時間の設定に際して、ステップS1,S21,S22,S23,S31,S32のうち、どの作業工程がクリティカルパスになっているかが考慮され得る。 Further, the time between the times t1 and t2, the time between the times t2 and t3, ..., the time between the times t13 and t14, and the time between the times t14 and t15 are the same time (in the present embodiment). 1.2 hours, but not limited to this). Further, the work process time of steps S1, S21, S22, S23, S31, and S32 is the same for one construction area (that is, each of the construction areas A1 to Ann). When setting the work process time, it is possible to consider which of the steps S1, S21, S22, S23, S31, and S32 is the critical path.
図13及び図14に示すように、本実施形態では、時刻t1~t13の間で、施工領域A1~A6での床版架け替え(既設床版5の撤去と、これに替わる新設床版7の配置)が完了する。
As shown in FIGS. 13 and 14 , in the present embodiment, the floor slab is replaced in the construction areas A1 to A6 between the times t1 to t13 (removal of the existing
この点、図15は、従来の床版架け替え方法の一例における時刻t1~t13と施工領域A1,A2の各々の作業工程との関係を示している。図15は、施工領域A1で既設床版5の撤去と、これに替わる新設床版7の配置を行った後に、施工領域A2で既設床版5の撤去と、これに替わる新設床版7の配置を行うと、時刻t1~t13の作業時間がかかることを示している。
In this regard, FIG. 15 shows the relationship between the times t1 to t13 and the respective work processes of the construction areas A1 and A2 in an example of the conventional floor slab replacement method. In FIG. 15, after the existing
従って、図13~図15の図示から明らかなように、本実施形態の床版架け替え方法を用いると、従来の床版架け替え方法に比べてはるかに迅速に床版架け替え施工を進めることができる。 Therefore, as is clear from the illustrations of FIGS. 13 to 15, when the floor slab replacement method of the present embodiment is used, the floor slab replacement work can proceed much more quickly than the conventional floor slab replacement method. Can be done.
前述の図3のステップS103では、橋桁4上に配置された新設床版7の貫通孔7aから空間9内(図11B参照)にモルタルを注入・打設することで、このモルタルとスタッドジベル80(図12参照)とにより、新設床版7と橋桁4とが固定されて一体化される。また、前述の図3のステップS103では、橋軸方向で隣り合う新設床版7同士の間の間詰部(図示せず)にて鉄筋コンクリート工が実施されることで、これら新設床版7同士が固定されて一体化される。
In step S103 of FIG. 3 described above, the mortar and the
本実施形態によれば、床版架け替え方法は、構造物(橋梁1)を構造物(橋梁1)の軸方向に複数の施工領域A1~Anに区分けすることにより、複数の施工領域A1~Anを設定することを含む。施工領域A1~Anは、各々が、既設床版5の撤去から新設床版7の配置に至る複数段の作業工程(ステップS1~S3(S11~S32))を有する。構造物(橋梁1)の軸方向(橋軸方向)に沿う床版架け替え施工進行方向において、床版架け替え施工進行方向前側の施工領域と、この施工領域より床版架け替え施工進行方向後方の施工領域とにて、互いに異なる作業工程を並行して実施する(図2、図13及び図14参照)。これにより、床版架け替え施工の進捗状況が異なる複数の施工領域にて、並行して(すなわち同時に)施工を進めることができるので、既設床版5から新設床版7への架け替えを効率良く(換言すれば短期間で)行うことができる(図13~図15参照)。
According to the present embodiment, the floor slab replacement method divides the structure (bridge 1 ) into a plurality of construction areas A1 to Ann in the axial direction of the structure (bridge 1), thereby forming a plurality of construction areas. Includes setting A 1 to An. Each of the construction areas A1 to An has a plurality of work steps (steps S1 to S3 (S11 to S32)) from the removal of the existing
また本実施形態によれば、床版架け替え施工進行方向前側の施工領域から床版架け替え施工進行方向後側の施工領域に向かうほど後段の作業工程となるように(例えば、図2に示すように、施工領域Akから施工領域Ak-6に向かうほど、ステップS32に近づくように)、複数段の作業工程を並行して実施する(図2、図13及び図14参照)。これにより、床版架け替え施工進行方向に沿って、各作業工程を継続しつつ前進させることができるので、各作業工程の休止時間(作業待ち時間)の発生を抑制でき、ひいては、床版架け替え施工を効率良く行うことができる。 Further, according to the present embodiment, the work process is performed in the later stage from the construction area on the front side in the floor slab replacement construction progress direction to the construction area on the rear side in the floor slab replacement construction progress direction (for example, shown in FIG. 2). As described above, the work process of a plurality of stages is carried out in parallel (see FIGS. 2, 13 and 14) so as to approach step S32 from the construction area Ak to the construction area Ak-6 . As a result, each work process can be advanced while continuing along the direction of the floor slab replacement work, so that the occurrence of pause time (work waiting time) in each work process can be suppressed, and eventually the floor slab can be hung. Replacement work can be performed efficiently.
また本実施形態によれば、撤去された既設床版5(床版片5a)を施工領域A1~Anから床版架け替え施工進行方向前方に搬出し、新設床版7を施工領域A1~Anに床版架け替え施工進行方向後方から搬入する。これにより、既設床版5(床版片5a)の搬出作業と新設床版7の搬入作業とが錯綜することを抑制することができる。
Further, according to the present embodiment, the removed existing floor slab 5 (
また本実施形態によれば、各施工領域A1~Anがそれぞれ有する複数段の作業工程は、施工領域の既設床版5の撤去作業を実施する第1作業工程(ステップS1)と、既設床版5が撤去された施工領域に新設床版7を配置するための準備作業を実施する第2作業工程(ステップS2)と、この準備作業が実施された施工領域に新設床版7を配置する第3作業工程(ステップS3)と、を含む。ゆえに、新設床版7の配置に先立って新設床版7の配置のための様々な準備を行うことで、新設床版7の配置を円滑に行うことができる。
Further, according to the present embodiment, the multi-stage work steps of each of the construction areas A1 to Ann are the first work step (step S1) for removing the existing
また本実施形態によれば、第2作業工程(ステップS2)は、第3作業工程(ステップS3)にて施工領域に配置される新設床版7の配置高さを調整するための高さ調整材70を橋梁1の橋桁4の上面4aに設けること(ステップS23)を含む。これにより、ステップS31(ステップS3)にて、新設床版7を、計画の配置高さで容易に施工領域に配置することができる。
Further, according to the present embodiment, the second work step (step S2) is a height adjustment for adjusting the placement height of the
また本実施形態によれば、第2作業工程(ステップS2)は、橋梁1の橋桁4の上面4aに対してケレン作業を実施すること(ステップS21)を含む。このケレン作業は、仮設テント10内で実施される。それゆえ、仮設テント10が雨除けとして機能し得るので、雨天でもケレン作業を実施することができる。また、ケレン作業で発生する粉じんが仮設テント10内に留まり得るので、当該粉じんの外部への飛散を抑制することができる。
Further, according to the present embodiment, the second work step (step S2) includes performing a cleaning work on the
また本実施形態によれば、施工領域A1~Anの各々が有する複数段の作業工程のうち、溶接作業を含む作業工程(例えばステップS32)では、仮設テント10内で溶接作業が実施される。それゆえ、仮設テント10が雨除けとして機能し得るので、雨天でも溶接作業を実施することができる。
Further, according to the present embodiment, in the work process including the welding work (for example, step S32) among the multi-stage work steps of each of the construction areas A1 to Ann, the welding work is carried out in the
また本実施形態によれば、新設床版7がプレキャストコンクリート製である。ゆえに、床版架け替えの施工現場での新設床版7の設置作業を簡素化することができる。
Further, according to the present embodiment, the
また本実施形態によれば、橋梁1の全長にわたって新設床版7の配置が完了した後に、新設床版7と橋梁1の橋桁4とを固定して一体化すると共に、橋梁1の軸方向(橋軸方向)で隣り合う新設床版7同士を固定して一体化する(ステップS103)。これにより、新設床版7と橋桁4との一体化と、隣り合う新設床版7同士の一体化とを、橋梁1の全長にわたってまとめて行うことができるので、これらの一体化作業を短期間で効率良く行うことができる。
Further, according to the present embodiment, after the arrangement of the
尚、本実施形態では、橋梁1の全長にわたって新設床版7の配置が完了した後に、新設床版7と橋桁4とを固定して一体化すると共に、橋軸方向で隣り合う新設床版7同士を固定して一体化するが、この他、橋梁1の全長よりも短く、かつ、複数の施工領域を含む所定区間にわたって新設床版7の配置が完了した後に、この所定区間にてまとめて、新設床版7と橋桁4とを固定して一体化すると共に、橋軸方向で隣り合う新設床版7同士を固定して一体化してもよい。
In the present embodiment, after the arrangement of the
図16A及び図16Bは、本発明の第2実施形態における時刻t1~t19と施工領域A1~A20の各々の作業工程との関係を示す図である。
前述の第1実施形態と異なる点について説明する。
16A and 16B are diagrams showing the relationship between the times t1 to t19 and the respective working steps of the construction areas A1 to A20 in the second embodiment of the present invention.
The differences from the first embodiment described above will be described.
本実施形態では、前述の第1実施形態に比べて、施工領域A1~Anの各々の橋軸方向の長さを短縮している。本実施形態では、施工領域A1~Anの各々の橋軸方向の長さを、それぞれ2mとしているが、施工領域A1~Anの各々の橋軸方向の長さは2mに限らない。例えば、橋梁1の全長Ltが300mであり、かつ、施工領域A1~Anの各々の橋軸方向の長さが、それぞれ2mである場合には、n=300/2=150となる。
In the present embodiment, the lengths of the construction areas A1 to An in the bridge axis direction are shortened as compared with the first embodiment described above. In the present embodiment, the length of each of the construction areas A 1 to An in the bridge axis direction is 2 m, but the length of each of the construction areas A 1 to An in the bridge axis direction is not limited to 2 m. .. For example, when the total length Lt of the
また、本実施形態では、前述の時刻t1~t2間の時間,時刻t2~t3間の時間,・・・,時刻t17~t18間の時間,時刻t18~t19間の時間は、それぞれ、同じ時間(本実施形態では0.4時間とするが、これに限らない)である。 Further, in the present embodiment, the time between the times t1 and t2, the time between the times t2 and t3, ..., the time between the times t17 and t18, and the time between the times t18 and t19 are the same time, respectively. (In this embodiment, it is set to 0.4 hours, but the present invention is not limited to this).
本実施形態では、1つの施工領域(すなわち施工領域A1~Anの各々)について、ステップS1の作業工程時間が0.4時間であり、ステップS21の作業工程時間が0.8時間(0.4時間×2)であり、ステップS22,S23の作業工程時間が、それぞれ、1.2時間(0.4時間×3)であり、ステップS31の作業工程時間が0.4時間であり、ステップS32の作業工程時間が0.4時間である。 In the present embodiment, the work process time of step S1 is 0.4 hours and the work process time of step S21 is 0.8 hours (0) for one construction area (that is, each of the construction areas A1 to Ann). .4 hours x 2), the work process time of steps S22 and S23 is 1.2 hours (0.4 hours x 3), respectively, and the work process time of step S31 is 0.4 hours. The work process time in step S32 is 0.4 hours.
本実施形態では、図16A及び図16Bに示すように、各作業工程の特性に応じて、各作業工程の時間配分の最適化と、各作業工程の作業範囲の最適化とを実現することができる。例えば、図16Aの時刻t6~t7,t9~t10、及び、図16Bの時刻t12~t13,t15~t16,t18~t19において、ステップS21のケレン作業を休止することにより、仮設テント10内で粉じんが慢性的に発生することを抑制することができる。
In the present embodiment, as shown in FIGS. 16A and 16B, it is possible to realize optimization of the time allocation of each work process and optimization of the work range of each work process according to the characteristics of each work process. can. For example, at times t6 to t7, t9 to t10 in FIG. 16A and times t12 to t13, t15 to t16, and t18 to t19 in FIG. 16B, dust is dusted in the
図17は、本発明の第3実施形態における新設床版7の配置方法を示すフローチャートである。
前述の第1実施形態と異なる点について説明する。
FIG. 17 is a flowchart showing a method of arranging the
The differences from the first embodiment described above will be described.
本実施形態では、ステップS103の替わりとして、ステップS32の後に、ステップS33が追加されている。すなわち、本実施形態では、1つの施工領域ごとに(すなわち施工領域A1~Anの各々で)、ステップS32のスタッドジベル80の設置作業を行い、これに続けて、ステップS33にて、新設床版7と橋桁4とを固定して一体化すると共に、橋軸方向で隣り合う新設床版7同士を固定して一体化する。これら一体化作業については、前述の第1実施形態と同様であるので、その説明を省略する。
In the present embodiment, instead of step S103, step S33 is added after step S32. That is, in the present embodiment, the
尚、前述の第2実施形態において、本実施形態と同様に、ステップS103の替わりとして、ステップS32の後に、ステップS33を追加してもよいことは言うまでもない。 Needless to say, in the above-mentioned second embodiment, as in the present embodiment, step S33 may be added after step S32 instead of step S103.
図18は、本発明の第4実施形態における新設床版7の配置準備方法を示すフローチャートである。
前述の第1実施形態と異なる点について説明する。
FIG. 18 is a flowchart showing a method of preparing for placement of the
The differences from the first embodiment described above will be described.
本実施形態では、前述のステップS21にて橋桁4の上フランジ4fの上面4aのケレン作業を実施した後に、ステップS24に進み、橋桁4の上フランジ4fの上面4aの形状の測量を実施する。この測量が完了した後に、ステップS22に進み、橋桁4の上フランジ4fの左右両側部に、フランジシール60を設置する。すなわち、本実施形態では、ステップS21とステップS22との間にステップS24が追加されている。
In the present embodiment, after performing the cleaning work on the
尚、前述の第2及び第3実施形態において、本実施形態と同様に、ステップS21とステップS22との間にステップS24を追加してもよいことは言うまでもない。 Needless to say, in the second and third embodiments described above, step S24 may be added between step S21 and step S22 as in the present embodiment.
図19は、本発明の第5実施形態における新設床版7の配置方法を示すフローチャートである。
前述の第1実施形態と異なる点について説明する。
FIG. 19 is a flowchart showing a method of arranging the
The differences from the first embodiment described above will be described.
本実施形態では、前述のステップS31にて、橋桁4の上フランジ4fの上面4aに設置された複数の高さ調整材70に、新設床版7を載置した後に、ステップS34に進み、新設床版7の高さ調整を実施する。この高さ調整が完了した後に、ステップS32に進み、複数のスタッドジベル80を、新設床版7の貫通孔7a内に位置するように、橋桁4の上フランジ4fの上面4aに溶接固定する。すなわち、本実施形態では、ステップS31とステップS32との間にステップS34が追加されている。
In the present embodiment, after the
尚、前述の第2~第4実施形態において、本実施形態と同様に、ステップS31とステップS32との間にステップS34を追加してもよいことは言うまでもない。 Needless to say, in the above-mentioned second to fourth embodiments, step S34 may be added between step S31 and step S32 as in the present embodiment.
図20は、本発明の第6実施形態における新設床版7の配置準備方法を示すフローチャートである。
前述の第1実施形態と異なる点について説明する。
FIG. 20 is a flowchart showing a method of preparing for placement of the
The differences from the first embodiment described above will be described.
本実施形態では、新設床版7に複数のインサートが埋め込まれている。各インサートは、新設床版7を上下に貫通する雌ねじ部を有する。この雌ねじ部には、上側に頭部を有するボルトの雄ねじ部が螺合している。このボルトの雄ねじ部の下端部は、新設床版7の下面7bから下方に突出しており、橋桁4の上フランジ4fの上面4aに当接可能である。このボルトの雄ねじ部の、雌ねじ部に対するねじ込み度合いを変化させることで、ボルトの雄ねじ部の下端部が新設床版7の下面7bから下方に突出する突出量が変化し得る。ゆえに、これらインサート及びボルト(以下、「インサート・ボルト」と称する)が、新設床版7の配置高さを調整するための高さ調整材として機能し得る。
In this embodiment, a plurality of inserts are embedded in the
本実施形態では、新設床版7の配置高さを調整するための高さ調整材(例えば、前述のインサート・ボルト)が、前述のステップS31に先立って、新設床版7に複数設けられている。ゆえに、前述の高さ調整材70が不要となるので、本実施形態では、図20に示すように、前述のステップS23が省略され得る。
In the present embodiment, a plurality of height adjusting materials (for example, the above-mentioned insert bolt) for adjusting the arrangement height of the
尚、前述の第2~第5実施形態において、本実施形態と同様に、新設床版7の配置高さを調整するための高さ調整材(例えば、前述のインサート・ボルト)を、前述のステップS31に先立って新設床版7に複数設ければ、前述の高さ調整材70が不要となるので、ステップS23を省略することができることは言うまでもない。特に、前述の第5実施形態において、本実施形態と同様に、新設床版7の配置高さを調整するための高さ調整材(例えば、前述のインサート・ボルト)を、前述のステップS31に先立って新設床版7に複数設けて、ステップS23を省略した場合には、ステップS34における新設床版7の高さ調整において、これら高さ調整材(例えば、前述のインサート・ボルト)が用いられ得る。
In the above-mentioned second to fifth embodiments, as in the present embodiment, the height adjusting material (for example, the above-mentioned insert bolt) for adjusting the arrangement height of the
前述の第1実施形態では、複数の作業工程(ステップS1,S21~S23,S31,S32)の各々に対応するように、作業員及び装置を含む作業チームを個別に編成し(すなわち分業化し)、これら作業チームが作業工程の順序(ステップS1,S21~S23,S31,S32)に従って橋軸方向に1列に並んでいる(つまり、これら作業チームからなる、床版架け替えのための生産ラインのようなものが形成されている)。そして、これら作業チームが並行して、各々の作業の実施と前方への移動とを繰り返すことで、床版架け替え施工が進む。ゆえに、これら作業チームによる、前方への移動を伴う流れ作業によって、床版架け替え施工が進む。この点は、第1実施形態のみならず、第2~第6実施形態においても同様である。ここにおいて、各作業チームによる作業、及び、作業チーム同士の連携などに関して、AI(人工知能)技術などを含むICT(情報通信技術)などを活用することにより、床版架け替え施工の一部又は全部のオートメーション化を実現することができ、ひいては、大幅な生産性向上を図ることができる。従って、本発明に係る床版架け替え方法は、ICTなどの活用によるi-Construction(登録商標)化の推進をもって、インフラ維持管理更新における生産性向上を図ると共に、魅力ある職場環境の創生により若年層の建設業への入職者の増加に貢献するための基盤技術の1つとなり得るものであり、産業上の利用可能性は大である。 In the above-mentioned first embodiment, a work team including a worker and an apparatus is individually organized (that is, division of labor) so as to correspond to each of a plurality of work processes (steps S1, S21 to S23, S31, S32). , These work teams are lined up in a row in the direction of the bridge axis according to the order of work processes (steps S1, S21 to S23, S31, S32) (that is, a production line consisting of these work teams for deck replacement). Something like is formed). Then, these work teams repeat the execution of each work and the movement to the front in parallel, so that the floor slab replacement work proceeds. Therefore, the floor slab replacement work will proceed by the assembly line work accompanied by the forward movement by these work teams. This point is the same not only in the first embodiment but also in the second to sixth embodiments. Here, regarding the work by each work team and the cooperation between the work teams, by utilizing ICT (Information and Communication Technology) including AI (artificial intelligence) technology, a part of the floor slab replacement work or All automation can be achieved, which in turn can significantly improve productivity. Therefore, the floor slab replacement method according to the present invention aims to improve productivity in infrastructure maintenance and renewal by promoting i-Construction (registered trademark) by utilizing ICT, etc., and by creating an attractive work environment. It can be one of the basic technologies to contribute to the increase of the number of young people entering the construction industry, and its industrial applicability is great.
前述の第1~第6実施形態において、例えば、施工領域A1~Anのいずれかにおいて作業が遅れ気味である場合には、作業が遅れ気味である施工領域の作業員の人員を増やすなど、施工の進捗状況に応じて、前述の作業チームの編成(構成)を変化できるようにしてもよい(すなわち、作業チームの編成(構成)に柔軟性を持たせてもよい)。 In the above-mentioned first to sixth embodiments, for example, when the work is delayed in any of the construction areas A1 to Ann, the number of workers in the construction area where the work is likely to be delayed is increased. , The above-mentioned organization (configuration) of the work team may be changed according to the progress of construction (that is, the organization (configuration) of the work team may be made flexible).
前述の第1~第6実施形態では、既設床版5の撤去作業(前述のステップS1)が実施される施工領域の橋軸方向の長さが一定(第1及び第3~第6実施形態では6m、第2実施形態では2m)のまま、床版架け替え施工が進行する例を示したが、この他、既設床版5の撤去作業(前述のステップS1)が実施される施工領域の橋軸方向の長さが、時刻に応じて変化してもよい。すなわち、既設床版5の撤去作業(前述のステップS1)が実施される施工領域の橋軸方向の長さに柔軟性を持たせてもよい。既設床版5の撤去作業(前述のステップS1)が実施される施工領域の橋軸方向の長さが時刻に応じて変化する場合には、それに追従するように、後続の作業が適宜調整され得る。 In the above-mentioned first to sixth embodiments, the length of the construction area in which the removal work of the existing floor slab 5 (step S1 described above) is carried out is constant in the bridge axis direction (first and third to sixth embodiments). In the case of 6 m, 2 m in the second embodiment), an example in which the floor slab replacement work proceeds is shown. The length in the direction of the bridge axis may change depending on the time. That is, the length of the construction area in which the removal work of the existing floor slab 5 (step S1 described above) is carried out in the bridge axis direction may be made flexible. If the length of the construction area in which the removal work of the existing floor slab 5 (step S1 described above) is carried out changes depending on the time, the subsequent work is appropriately adjusted to follow it. obtain.
前述の第1~第6実施形態では、施工領域A1~Anの各々の橋軸方向の長さが一定(第1及び第3~第6実施形態では6m、第2実施形態では2m)であるが、この他、施工領域A1~Anの各々の橋軸方向の長さが相互に異なっていてもよい。 In the above-mentioned first to sixth embodiments, the lengths of the construction areas A1 to An in the bridge axis direction are constant (6 m in the first and third to sixth embodiments, 2 m in the second embodiment). However, in addition to this, the lengths of the construction areas A1 to An in the bridge axis direction may be different from each other.
前述の第1実施形態では、施工領域A1~Anの各々において、前述のステップS31とステップS32との間に作業休止期間(図2に符号「α」に対応する期間)を設けているが、この作業休止期間は、前述のステップS31とステップS32との間に限らない。これに加えて、又は、これに替えて、前述のステップS1とステップS21との間、ステップS21とステップS22との間、ステップS22とステップS23との間、及び、ステップS23とステップS31との間、のうちの少なくとも1つに、任意に、作業休止期間を設けてもよい。この点は、第1実施形態に限らず、第2~第6実施形態においても同様である。ここにおいて、作業休止期間は、各作業の作業時間の調整代として機能し得る。 In the above-mentioned first embodiment, a work rest period (a period corresponding to the reference numeral “α” in FIG. 2) is provided between the above-mentioned steps S31 and S32 in each of the construction areas A1 to Ann. However, this work suspension period is not limited to between step S31 and step S32 described above. In addition to or instead of this, between step S1 and step S21, between step S21 and step S22, between step S22 and step S23, and between step S23 and step S31. At least one of the intervals may optionally be provided with a work suspension period. This point is the same not only in the first embodiment but also in the second to sixth embodiments. Here, the work suspension period can function as an adjustment allowance for the work time of each work.
前述の第1~第6実施形態では、施工領域A1~Anの各々の作業工程の順序が同じであるが、この他、施工領域A1~Anのうちの一部の作業工程の順序が、前述の第1~第6実施形態にて説明した作業工程の順序と異なっていてもよい。 In the above-mentioned first to sixth embodiments, the order of the work steps of the construction areas A1 to An is the same, but in addition to this, some of the work steps of the construction areas A1 to Ann are The order may be different from the order of the work steps described in the first to sixth embodiments described above.
前述の第1~第6実施形態において、既設床版5は、プレキャストコンクリート製であってもよい(PCa床版であってもよい)。既設床版5は、場所打ちコンクリート製であってもよい。既設床版5は、鋼床版や合成床版などであってもよい。
In the above-mentioned first to sixth embodiments, the existing
前述の第1~第6実施形態において、新設床版7は、ハーフプレキャストコンクリート製などの、床版の一部にプレキャストコンクリートが使用される床版であってもよい。新設床版7は、プレストレストコンクリート製であってもよい(PC床版であってもよい)。新設床版7は、鋼床版や合成床版などであってもよい。
In the above-mentioned first to sixth embodiments, the
前述の第1~第6実施形態では、本発明の「構造物」の一例として橋梁を挙げて説明したが、本発明の「構造物」は橋梁に限らない。例えば、本発明の「構造物」が、床版を有するトンネルであってもよい。 In the above-mentioned first to sixth embodiments, a bridge has been described as an example of the "structure" of the present invention, but the "structure" of the present invention is not limited to the bridge. For example, the "structure" of the present invention may be a tunnel having a deck.
図示の実施形態はあくまで本発明を例示するものであり、本発明は、説明した実施形態により直接的に示されるものに加え、特許請求の範囲内で当業者によりなされる各種の改良・変更を包含するものであることは言うまでもない。
尚、特願2017-202222号の出願当初の請求項は以下の通りであった。
[請求項1]
構造物における床版の架け替え方法であって、
前記構造物を前記構造物の軸方向に複数の施工領域に区分けすることにより、複数の施工領域を設定することを含み、
各施工領域は、それぞれ、既設床版の撤去から新設床版の配置に至る複数段の作業工程を有し、
前記構造物の軸方向に沿う床版架け替え施工進行方向において、前記進行方向前側の施工領域と、この施工領域より前記進行方向後方の施工領域とにて、互いに異なる作業工程を並行して実施する、床版架け替え方法。
[請求項2]
前記進行方向前側の施工領域から前記進行方向後側の施工領域に向かうほど後段の作業工程となるように、複数段の作業工程を並行して実施する、請求項1に記載の床版架け替え方法。
[請求項3]
撤去された既設床版を前記施工領域から前記進行方向前方に搬出し、
新設床版を前記施工領域に前記進行方向後方から搬入する、請求項1又は請求項2に記載の床版架け替え方法。
[請求項4]
各施工領域がそれぞれ有する複数段の作業工程は、
当該施工領域の既設床版の撤去作業を実施する第1作業工程と、
既設床版が撤去された当該施工領域に新設床版を配置するための準備作業を実施する第2作業工程と、
前記準備作業が実施された当該施工領域に新設床版を配置する第3作業工程と、
を含む、請求項1~請求項3のいずれか1つに記載の床版架け替え方法。
[請求項5]
前記構造物は橋梁であり、
前記第2作業工程は、前記第3作業工程にて当該施工領域に配置される新設床版の配置高さを調整するための高さ調整材を前記橋梁の橋桁の上面に設けることを含む、請求項4に記載の床版架け替え方法。
[請求項6]
前記構造物は橋梁であり、
前記第2作業工程は、前記橋梁の橋桁の上面に対してケレン作業を実施することを含む、請求項4又は請求項5に記載の床版架け替え方法。
[請求項7]
仮設テント内で前記ケレン作業が実施される、請求項6に記載の床版架け替え方法。
[請求項8]
各施工領域がそれぞれ有する複数段の作業工程のうち、溶接作業を含む作業工程では、仮設テント内で前記溶接作業が実施される、請求項1~請求項7のいずれか1つに記載の床版架け替え方法。
[請求項9]
前記構造物は橋梁であり、
前記橋梁の全長にわたって新設床版の配置が完了した後に、新設床版と前記橋梁の橋桁とを固定して一体化すると共に、前記橋梁の軸方向で隣り合う新設床版同士を固定して一体化する、請求項1~請求項8のいずれか1つに記載の床版架け替え方法。
[請求項10]
前記新設床版がプレキャストコンクリート製である、請求項1~請求項9のいずれか1つに記載の床版架け替え方法。
The illustrated embodiment is merely an example of the present invention, and the present invention includes various improvements and modifications made by those skilled in the art within the scope of the claims, in addition to those directly shown by the described embodiments. Needless to say, it is an inclusion.
The initial claims of Japanese Patent Application No. 2017-202222 were as follows.
[Claim 1]
It is a method of replacing the floor slab in a structure.
Including setting a plurality of construction areas by dividing the structure into a plurality of construction areas in the axial direction of the structure.
Each construction area has a multi-stage work process from the removal of the existing floor slab to the placement of the new floor slab.
In the floor slab replacement construction progress direction along the axial direction of the structure, different work processes are carried out in parallel in the construction area on the front side of the progress direction and the construction area behind the construction area in the progress direction. How to replace the floor slab.
[Claim 2]
The floor slab replacement according to
[Claim 3]
The removed existing floor slab is carried out from the construction area to the front in the traveling direction.
The floor slab replacement method according to
[Claim 4]
The multi-stage work process that each construction area has is
The first work process to remove the existing floor slab in the construction area and
The second work process to carry out the preparatory work for arranging the new floor slab in the construction area where the existing floor slab has been removed, and
The third work process of arranging the new floor slab in the construction area where the preparatory work was carried out, and
The floor slab replacement method according to any one of
[Claim 5]
The structure is a bridge
The second work step includes providing a height adjusting material for adjusting the placement height of the new deck placed in the construction area in the third work step on the upper surface of the bridge girder of the bridge. The floor slab replacement method according to
[Claim 6]
The structure is a bridge
The floor slab replacement method according to
[Claim 7]
The floor slab replacement method according to
[Claim 8]
The floor according to any one of
[Claim 9]
The structure is a bridge
After the placement of the new deck is completed over the entire length of the bridge, the new deck and the bridge girder of the bridge are fixed and integrated, and the new decks adjacent to each other in the axial direction of the bridge are fixed and integrated. The floor slab replacement method according to any one of
[Claim 10]
The method for replacing a floor slab according to any one of
1 橋梁
2a,2b 橋台
3 橋脚
4 橋桁
4a 上面
4f 上フランジ
4w ウェブ
5 既設床版
5a 床版片
5b 切断線
7 新設床版
7a 貫通孔
7b 下面
9 空間
10 仮設テント
20,30 クレーン装置
21,31 下部フレーム
22,32 門型フレーム
23,33 上部フレーム
24,34 吊上装置
40 搬送台車
50a,50b ジャッキ
51 梁部材
52 PC鋼棒
53a,53b 固定部材
60 フランジシール
70 高さ調整材
80 スタッドジベル
A1~Ak~An 施工領域
1
Claims (10)
前記構造物の軸方向に複数の施工領域に区分けすることにより、複数の施工領域を設定することを含み、
既設床版撤去工程、新設床版配置準備工程、及び新設床版配置工程を有し、
前記既設床版撤去工程は、既設床版の床版片を撤去することを含み、
前記新設床版配置準備工程は、前記床版片が撤去された前記橋桁上に新設床版を配置するための準備作業をすることを含み、
前記新設床版配置工程は、前記準備作業がなされた前記橋桁上に新設床版を配置することを含み、
前記軸方向に沿う床版架け替え施工進行方向において、前記進行方向前側から後側に向かって順に、前記既設床版撤去工程を実施する第1施工領域と、前記第1施工領域にて前記既設床版撤去工程が実施されている場合に前記新設床版配置準備工程を実施する第2施工領域と、前記第2施工領域にて前記新設床版配置準備工程が実施されている場合に前記新設床版配置工程を実施する第3施工領域と、が並び、
前記橋桁上の既設の床版上には、前記既設床版撤去工程で用いられる第1クレーン装置が位置し、
前記橋桁上に新設された床版上には、前記新設床版配置工程で用いられる第2クレーン装置が位置し、
前記第1クレーン装置は、前記軸方向に延びる一対の下部フレームと、一対の前記下部フレームに下端が連結された門型フレームと、前記門型フレームの上部に設けられた上部フレームと、前記上部フレームに対して前記軸方向に移動可能な吊上装置と、を含む、
床版架け替え方法。 In a structure having a bridge girder, it is a method of replacing an existing floor slab with a new floor slab arranged on the bridge girder.
Including setting a plurality of construction areas by dividing into a plurality of construction areas in the axial direction of the structure.
It has an existing floor slab removal process, a new floor slab placement preparation process, and a new floor slab placement process.
The step of removing the existing floor slab includes removing the floor slab piece of the existing floor slab.
The new deck placement preparation step includes preparatory work for placing the new deck on the bridge girder from which the deck piece has been removed.
The new floor slab placement step includes arranging the new floor slab on the bridge girder on which the preparatory work has been performed.
In the floor slab replacement construction progress direction along the axial direction, the existing floor slab removal step is carried out in order from the front side to the rear side in the travel direction, and the existing installation in the first construction area. The second construction area where the new deck placement preparation process is carried out when the deck removal process is carried out, and the new construction when the new deck placement preparation step is carried out in the second construction area. The third construction area where the floor slab placement process is carried out is lined up,
The first crane device used in the existing deck removal process is located on the existing deck on the bridge girder.
The second crane device used in the new deck placement process is located on the deck newly installed on the bridge girder.
The first crane device includes a pair of lower frames extending in the axial direction, a portal frame having a lower end connected to the pair of lower frames, an upper frame provided on the upper portion of the portal frame, and the upper portion. A hoisting device that is movable in the axial direction with respect to the frame, and the like.
How to replace the deck.
前記構造物の軸方向に複数の施工領域に区分けすることにより、複数の施工領域を設定することを含み、
既設床版撤去工程、新設床版配置準備工程、及び新設床版配置工程を有し、
前記既設床版撤去工程は、既設床版の床版片を撤去することを含み、
前記新設床版配置準備工程は、前記床版片が撤去された前記橋桁上に新設床版を配置するための準備作業をすることを含み、
前記新設床版配置工程は、前記準備作業がなされた前記橋桁上に新設床版を配置することを含み、
前記軸方向に沿う床版架け替え施工進行方向において、前記進行方向前側から後側に向かって順に、前記既設床版撤去工程を実施する第1施工領域と、前記第1施工領域にて前記既設床版撤去工程が実施されている場合に前記新設床版配置準備工程を実施する第2施工領域と、前記第2施工領域にて前記新設床版配置準備工程が実施されている場合に前記新設床版配置工程を実施する第3施工領域と、が並び、
前記橋桁上の既設の床版上には、前記既設床版撤去工程で用いられる第1クレーン装置が位置し、
前記橋桁上に新設された床版上には、前記新設床版配置工程で用いられる第2クレーン装置が位置し、
前記第1クレーン装置は、前記軸方向に延びる一対の下部フレームと、一対の前記下部フレームに下端が連結された門型フレームと、吊上装置と、を含み、
一対の前記下部フレームには、転動可能な車輪が設けられている、
床版架け替え方法。 In a structure having a bridge girder, it is a method of replacing an existing floor slab with a new floor slab arranged on the bridge girder.
Including setting a plurality of construction areas by dividing into a plurality of construction areas in the axial direction of the structure.
It has an existing floor slab removal process, a new floor slab placement preparation process, and a new floor slab placement process.
The step of removing the existing floor slab includes removing the floor slab piece of the existing floor slab.
The new deck placement preparation step includes preparatory work for placing the new deck on the bridge girder from which the deck piece has been removed.
The new floor slab placement step includes arranging the new floor slab on the bridge girder on which the preparatory work has been performed.
In the floor slab replacement construction progress direction along the axial direction, the existing floor slab removal step is carried out in order from the front side to the rear side in the travel direction, and the existing installation in the first construction area. The second construction area where the new deck placement preparation process is carried out when the deck removal process is carried out, and the new construction when the new deck placement preparation step is carried out in the second construction area. The third construction area where the floor slab placement process is carried out is lined up,
The first crane device used in the existing deck removal process is located on the existing deck on the bridge girder.
The second crane device used in the new deck placement process is located on the deck newly installed on the bridge girder.
The first crane device includes a pair of lower frames extending in the axial direction, a gantry frame having a lower end connected to the pair of lower frames, and a lifting device.
The pair of lower frames are provided with rollable wheels.
How to replace the deck.
前記構造物の軸方向に複数の施工領域に区分けすることにより、複数の施工領域を設定することを含み、
既設床版撤去工程、新設床版配置準備工程、及び新設床版配置工程を有し、
前記既設床版撤去工程は、既設床版の床版片を撤去することを含み、
前記新設床版配置準備工程は、前記床版片が撤去された前記橋桁上に新設床版を配置するための準備作業をすることを含み、
前記新設床版配置工程は、前記準備作業がなされた前記橋桁上に新設床版を配置することを含み、
前記軸方向に沿う床版架け替え施工進行方向において、前記進行方向前側から後側に向かって順に、前記既設床版撤去工程を実施する第1施工領域と、前記第1施工領域にて前記既設床版撤去工程が実施されている場合に前記新設床版配置準備工程を実施する第2施工領域と、前記第2施工領域にて前記新設床版配置準備工程が実施されている場合に前記新設床版配置工程を実施する第3施工領域と、が並び、
前記橋桁上の既設の床版上には、前記既設床版撤去工程で用いられる第1クレーン装置が位置し、
前記橋桁上に新設された床版上には、前記新設床版配置工程で用いられる第2クレーン装置が位置し、
前記第1クレーン装置は、前記軸方向に延びる一対の下部フレームと、一対の前記下部フレームに下端が連結された門型フレームと、吊上装置と、を含み、
前記床版片を運搬する運搬車両が、前記門型フレーム内、及び、一対の前記下部フレーム間に配置され得る、
床版架け替え方法。 In a structure having a bridge girder, it is a method of replacing an existing floor slab with a new floor slab arranged on the bridge girder.
Including setting a plurality of construction areas by dividing into a plurality of construction areas in the axial direction of the structure.
It has an existing floor slab removal process, a new floor slab placement preparation process, and a new floor slab placement process.
The step of removing the existing floor slab includes removing the floor slab piece of the existing floor slab.
The new deck placement preparation step includes preparatory work for placing the new deck on the bridge girder from which the deck piece has been removed.
The new floor slab placement step includes arranging the new floor slab on the bridge girder on which the preparatory work has been performed.
In the floor slab replacement construction progress direction along the axial direction, the existing floor slab removal step is carried out in order from the front side to the rear side in the travel direction, and the existing installation in the first construction area. The second construction area where the new deck placement preparation process is carried out when the deck removal process is carried out, and the new construction when the new deck placement preparation step is carried out in the second construction area. The third construction area where the floor slab placement process is carried out is lined up,
The first crane device used in the existing deck removal process is located on the existing deck on the bridge girder.
The second crane device used in the new deck placement process is located on the deck newly installed on the bridge girder.
The first crane device includes a pair of lower frames extending in the axial direction, a gantry frame having a lower end connected to the pair of lower frames, and a lifting device.
A carrier vehicle carrying the deck pieces may be placed within the gantry frame and between the pair of lower frames.
How to replace the deck.
前記構造物の軸方向に複数の施工領域に区分けすることにより、複数の施工領域を設定することを含み、
既設床版撤去工程、新設床版配置準備工程、及び新設床版配置工程を有し、
前記既設床版撤去工程は、既設床版の床版片を撤去することを含み、
前記新設床版配置準備工程は、前記床版片が撤去された前記橋桁上に新設床版を配置するための準備作業をすることを含み、
前記新設床版配置工程は、前記準備作業がなされた前記橋桁上に新設床版を配置することを含み、
前記軸方向に沿う床版架け替え施工進行方向において、前記進行方向前側から後側に向かって順に、前記既設床版撤去工程を実施する第1施工領域と、前記第1施工領域にて前記既設床版撤去工程が実施されている場合に前記新設床版配置準備工程を実施する第2施工領域と、前記第2施工領域にて前記新設床版配置準備工程が実施されている場合に前記新設床版配置工程を実施する第3施工領域と、が並び、
前記橋桁上の既設の床版上には、前記既設床版撤去工程で用いられる第1クレーン装置が位置し、
前記橋桁上に新設された床版上には、前記新設床版配置工程で用いられる第2クレーン装置が位置し、
前記第2クレーン装置は、前記軸方向に延びる一対の下部フレームと、一対の前記下部フレームに下端が連結された門型フレームと、前記門型フレームの上部に設けられた上部フレームと、前記上部フレームに対して前記軸方向に移動可能な吊上装置と、を含む、
床版架け替え方法。 In a structure having a bridge girder, it is a method of replacing an existing floor slab with a new floor slab arranged on the bridge girder.
Including setting a plurality of construction areas by dividing into a plurality of construction areas in the axial direction of the structure.
It has an existing floor slab removal process, a new floor slab placement preparation process, and a new floor slab placement process.
The step of removing the existing floor slab includes removing the floor slab piece of the existing floor slab.
The new deck placement preparation step includes preparatory work for placing the new deck on the bridge girder from which the deck piece has been removed.
The new floor slab placement step includes arranging the new floor slab on the bridge girder on which the preparatory work has been performed.
In the floor slab replacement construction progress direction along the axial direction, the existing floor slab removal step is carried out in order from the front side to the rear side in the travel direction, and the existing installation in the first construction area. The second construction area where the new deck placement preparation process is carried out when the deck removal process is carried out, and the new construction when the new deck placement preparation step is carried out in the second construction area. The third construction area where the floor slab placement process is carried out is lined up,
The first crane device used in the existing deck removal process is located on the existing deck on the bridge girder.
The second crane device used in the new deck placement process is located on the deck newly installed on the bridge girder.
The second crane device includes a pair of lower frames extending in the axial direction, a portal frame having a lower end connected to the pair of lower frames, an upper frame provided on the upper portion of the portal frame, and the upper portion. A hoisting device that is movable in the axial direction with respect to the frame, and the like.
How to replace the deck.
前記構造物の軸方向に複数の施工領域に区分けすることにより、複数の施工領域を設定することを含み、
既設床版撤去工程、新設床版配置準備工程、及び新設床版配置工程を有し、
前記既設床版撤去工程は、既設床版の床版片を撤去することを含み、
前記新設床版配置準備工程は、前記床版片が撤去された前記橋桁上に新設床版を配置するための準備作業をすることを含み、
前記新設床版配置工程は、前記準備作業がなされた前記橋桁上に新設床版を配置することを含み、
前記軸方向に沿う床版架け替え施工進行方向において、前記進行方向前側から後側に向かって順に、前記既設床版撤去工程を実施する第1施工領域と、前記第1施工領域にて前記既設床版撤去工程が実施されている場合に前記新設床版配置準備工程を実施する第2施工領域と、前記第2施工領域にて前記新設床版配置準備工程が実施されている場合に前記新設床版配置工程を実施する第3施工領域と、が並び、
前記橋桁上の既設の床版上には、前記既設床版撤去工程で用いられる第1クレーン装置が位置し、
前記橋桁上に新設された床版上には、前記新設床版配置工程で用いられる第2クレーン装置が位置し、
前記第2クレーン装置は、前記軸方向に延びる一対の下部フレームと、一対の前記下部フレームに下端が連結された門型フレームと、吊上装置と、を含み、
一対の前記下部フレームには、転動可能な車輪が設けられている、
床版架け替え方法。 In a structure having a bridge girder, it is a method of replacing an existing floor slab with a new floor slab arranged on the bridge girder.
Including setting a plurality of construction areas by dividing into a plurality of construction areas in the axial direction of the structure.
It has an existing floor slab removal process, a new floor slab placement preparation process, and a new floor slab placement process.
The step of removing the existing floor slab includes removing the floor slab piece of the existing floor slab.
The new deck placement preparation step includes preparatory work for placing the new deck on the bridge girder from which the deck piece has been removed.
The new floor slab placement step includes arranging the new floor slab on the bridge girder on which the preparatory work has been performed.
In the floor slab replacement construction progress direction along the axial direction, the existing floor slab removal step is carried out in order from the front side to the rear side in the travel direction, and the existing installation in the first construction area. The second construction area where the new deck placement preparation process is carried out when the deck removal process is carried out, and the new construction when the new deck placement preparation step is carried out in the second construction area. The third construction area where the floor slab placement process is carried out is lined up,
The first crane device used in the existing deck removal process is located on the existing deck on the bridge girder.
The second crane device used in the new deck placement process is located on the deck newly installed on the bridge girder.
The second crane device includes a pair of lower frames extending in the axial direction, a gantry frame having a lower end connected to the pair of lower frames, and a lifting device.
The pair of lower frames are provided with rollable wheels.
How to replace the deck.
前記構造物の軸方向に複数の施工領域に区分けすることにより、複数の施工領域を設定することを含み、
既設床版撤去工程、新設床版配置準備工程、及び新設床版配置工程を有し、
前記既設床版撤去工程は、既設床版の床版片を撤去することを含み、
前記新設床版配置準備工程は、前記床版片が撤去された前記橋桁上に新設床版を配置するための準備作業をすることを含み、
前記新設床版配置工程は、前記準備作業がなされた前記橋桁上に新設床版を配置することを含み、
前記軸方向に沿う床版架け替え施工進行方向において、前記進行方向前側から後側に向かって順に、前記既設床版撤去工程を実施する第1施工領域と、前記第1施工領域にて前記既設床版撤去工程が実施されている場合に前記新設床版配置準備工程を実施する第2施工領域と、前記第2施工領域にて前記新設床版配置準備工程が実施されている場合に前記新設床版配置工程を実施する第3施工領域と、が並び、
前記橋桁上の既設の床版上には、前記既設床版撤去工程で用いられる第1クレーン装置が位置し、
前記橋桁上に新設された床版上には、前記新設床版配置工程で用いられる第2クレーン装置が位置し、
前記第2クレーン装置は、前記軸方向に延びる一対の下部フレームと、一対の前記下部フレームに下端が連結された門型フレームと、吊上装置と、を含み、
前記新設床版を搬送する搬送台車が、前記門型フレーム内、及び、一対の前記下部フレーム間を走行可能である、
床版架け替え方法。 In a structure having a bridge girder, it is a method of replacing an existing floor slab with a new floor slab arranged on the bridge girder.
Including setting a plurality of construction areas by dividing into a plurality of construction areas in the axial direction of the structure.
It has an existing floor slab removal process, a new floor slab placement preparation process, and a new floor slab placement process.
The step of removing the existing floor slab includes removing the floor slab piece of the existing floor slab.
The new deck placement preparation step includes preparatory work for placing the new deck on the bridge girder from which the deck piece has been removed.
The new floor slab placement step includes arranging the new floor slab on the bridge girder on which the preparatory work has been performed.
In the floor slab replacement construction progress direction along the axial direction, the existing floor slab removal step is carried out in order from the front side to the rear side in the travel direction, and the existing installation in the first construction area. The second construction area where the new deck placement preparation process is carried out when the deck removal process is carried out, and the new construction when the new deck placement preparation step is carried out in the second construction area. The third construction area where the floor slab placement process is carried out is lined up,
The first crane device used in the existing deck removal process is located on the existing deck on the bridge girder.
The second crane device used in the new deck placement process is located on the deck newly installed on the bridge girder.
The second crane device includes a pair of lower frames extending in the axial direction, a gantry frame having a lower end connected to the pair of lower frames, and a lifting device.
The transport carriage that transports the new deck can travel within the gantry frame and between the pair of lower frames.
How to replace the deck.
前記新設床版配置準備工程は、前記橋桁の上面に対するケレン作業、前記橋桁の上面に対する高さ調整材の設置作業、及び、前記橋桁の上面に対するシールの設置作業の少なくとも1つを含み、
前記新設床版配置工程は新設床版の載置作業を含む、
請求項1~請求項6のいずれか1つに記載の床版架け替え方法。 The existing floor slab removal step includes lifting work of the floor slab piece.
The new deck placement preparation step includes at least one of cleaning work on the upper surface of the bridge girder, installation work of a height adjusting material on the upper surface of the bridge girder, and installation work of a seal on the upper surface of the bridge girder.
The new floor slab placement process includes the installation work of the new floor slab.
The floor slab replacement method according to any one of claims 1 to 6.
前記構造物の軸方向に複数の施工領域に区分けすることにより、複数の施工領域を設定することを含み、
既設床版撤去工程、新設床版配置準備工程、及び新設床版配置工程を有し、
前記既設床版撤去工程は、既設床版の床版片を撤去することを含み、
前記新設床版配置準備工程は、前記床版片が撤去された前記橋桁上に新設床版を配置するための準備作業をすることを含み、
前記新設床版配置工程は、前記準備作業がなされた前記橋桁上に新設床版を配置することを含み、
前記軸方向に沿う床版架け替え施工進行方向において、前記進行方向前側から後側に向かって順に、前記既設床版撤去工程を実施する第1施工領域と、前記第1施工領域にて前記既設床版撤去工程が実施されている場合に前記新設床版配置準備工程を実施する第2施工領域と、前記第2施工領域にて前記新設床版配置準備工程が実施されている場合に前記新設床版配置工程を実施する第3施工領域と、が並び、
前記第2施工領域の前記軸方向の長さが、前記床版片の前記軸方向の長さよりも長く、
前記橋桁上の既設の床版上には、前記既設床版撤去工程で用いられる第1クレーン装置が位置し、
前記橋桁上に新設された床版上には、前記新設床版配置工程で用いられる第2クレーン装置が位置する、
床版架け替え方法。 In a structure having a bridge girder, it is a method of replacing an existing floor slab with a new floor slab arranged on the bridge girder.
Including setting a plurality of construction areas by dividing into a plurality of construction areas in the axial direction of the structure.
It has an existing floor slab removal process, a new floor slab placement preparation process, and a new floor slab placement process.
The step of removing the existing floor slab includes removing the floor slab piece of the existing floor slab.
The new deck placement preparation step includes preparatory work for placing the new deck on the bridge girder from which the deck piece has been removed.
The new floor slab placement step includes arranging the new floor slab on the bridge girder on which the preparatory work has been performed.
In the floor slab replacement construction progress direction along the axial direction, the existing floor slab removal step is carried out in order from the front side to the rear side in the travel direction, and the existing installation in the first construction area. The second construction area where the new deck placement preparation process is carried out when the deck removal process is carried out, and the new construction when the new deck placement preparation step is carried out in the second construction area. The third construction area where the floor slab placement process is carried out is lined up,
The axial length of the second construction area is longer than the axial length of the deck piece.
The first crane device used in the existing deck removal process is located on the existing deck on the bridge girder.
The second crane device used in the new deck placement process is located on the deck newly installed on the bridge girder.
How to replace the deck.
前記構造物の軸方向に複数の施工領域に区分けすることにより、複数の施工領域を設定することを含み、
既設床版撤去工程、新設床版配置準備工程、及び新設床版配置工程を有し、
前記既設床版撤去工程は、既設床版の床版片を撤去することを含み、
前記新設床版配置準備工程は、前記床版片が撤去された前記橋桁上に新設床版を配置するための準備作業をすることを含み、
前記新設床版配置工程は、前記準備作業がなされた前記橋桁上に新設床版を配置することを含み、
前記軸方向に沿う床版架け替え施工進行方向において、前記進行方向前側から後側に向かって順に、前記既設床版撤去工程を実施する第1施工領域と、前記第1施工領域にて前記既設床版撤去工程が実施されている場合に前記新設床版配置準備工程を実施する第2施工領域と、前記第2施工領域にて前記新設床版配置準備工程が実施されている場合に前記新設床版配置工程を実施する第3施工領域と、が並び、
前記第2施工領域の前記軸方向の長さが、前記新設床版の前記軸方向の長さよりも長く、
前記橋桁上の既設の床版上には、前記既設床版撤去工程で用いられる第1クレーン装置が位置し、
前記橋桁上に新設された床版上には、前記新設床版配置工程で用いられる第2クレーン装置が位置する、
床版架け替え方法。 In a structure having a bridge girder, it is a method of replacing an existing floor slab with a new floor slab arranged on the bridge girder.
Including setting a plurality of construction areas by dividing into a plurality of construction areas in the axial direction of the structure.
It has an existing floor slab removal process, a new floor slab placement preparation process, and a new floor slab placement process.
The step of removing the existing floor slab includes removing the floor slab piece of the existing floor slab.
The new deck placement preparation step includes preparatory work for placing the new deck on the bridge girder from which the deck piece has been removed.
The new floor slab placement step includes arranging the new floor slab on the bridge girder on which the preparatory work has been performed.
In the floor slab replacement construction progress direction along the axial direction, the existing floor slab removal step is carried out in order from the front side to the rear side in the travel direction, and the existing installation in the first construction area. The second construction area where the new deck placement preparation process is carried out when the deck removal process is carried out, and the new construction when the new deck placement preparation step is carried out in the second construction area. The third construction area where the floor slab placement process is carried out is lined up,
The axial length of the second construction area is longer than the axial length of the new deck.
The first crane device used in the existing deck removal process is located on the existing deck on the bridge girder.
The second crane device used in the new deck placement process is located on the deck newly installed on the bridge girder.
How to replace the floor slab.
前記新設床版配置準備工程は、前記橋桁の上面に対するケレン作業、前記橋桁の上面に対する高さ調整材の設置作業、及び、前記橋桁の上面に対するシールの設置作業の少なくとも1つを含み、
前記新設床版配置工程は新設床版の載置作業を含む、
請求項8又は請求項9に記載の床版架け替え方法。 The existing floor slab removal step includes lifting work of the floor slab piece.
The new deck placement preparation step includes at least one of cleaning work on the upper surface of the bridge girder, installation work of a height adjusting material on the upper surface of the bridge girder, and installation work of a seal on the upper surface of the bridge girder.
The new floor slab placement process includes the installation work of the new floor slab.
The floor slab replacement method according to claim 8 or 9.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP2022001494A JP7148746B2 (en) | 2017-10-18 | 2022-01-07 | Floor slab replacement method |
Applications Claiming Priority (2)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP2017202222A JP7442256B2 (en) | 2017-10-18 | 2017-10-18 | How to replace the floor slab |
JP2022001494A JP7148746B2 (en) | 2017-10-18 | 2022-01-07 | Floor slab replacement method |
Related Parent Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
JP2017202222A Division JP7442256B2 (en) | 2017-10-18 | 2017-10-18 | How to replace the floor slab |
Publications (2)
Publication Number | Publication Date |
---|---|
JP2022033346A true JP2022033346A (en) | 2022-02-28 |
JP7148746B2 JP7148746B2 (en) | 2022-10-05 |
Family
ID=87884639
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
JP2022001494A Active JP7148746B2 (en) | 2017-10-18 | 2022-01-07 | Floor slab replacement method |
Country Status (1)
Country | Link |
---|---|
JP (1) | JP7148746B2 (en) |
Citations (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JP2004300688A (en) * | 2003-03-28 | 2004-10-28 | Pc Bridge Co Ltd | Mobile pre-cast floor slab erection machine |
JP2015229818A (en) * | 2014-06-03 | 2015-12-21 | オリエンタル白石株式会社 | Composite structure of steel girder and precast floor slab, and construction method therefor |
-
2022
- 2022-01-07 JP JP2022001494A patent/JP7148746B2/en active Active
Patent Citations (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JP2004300688A (en) * | 2003-03-28 | 2004-10-28 | Pc Bridge Co Ltd | Mobile pre-cast floor slab erection machine |
JP2015229818A (en) * | 2014-06-03 | 2015-12-21 | オリエンタル白石株式会社 | Composite structure of steel girder and precast floor slab, and construction method therefor |
Non-Patent Citations (2)
Title |
---|
伊藤寛彦 保科和利 栗原悠: "鋼橋のPC床版架設の施工", 第19回土木施工管理技術論文集, JPN6022013518, 2 June 2015 (2015-06-02), JP, pages 13 - 16, ISSN: 0004749347 * |
本間修平: "計画工程を維持するために取り組んだ『床版取替』について", 第19回土木施工管理技術論文報告集, JPN6022013515, 2 June 2015 (2015-06-02), JP, pages 53 - 56, ISSN: 0004749346 * |
Also Published As
Publication number | Publication date |
---|---|
JP7148746B2 (en) | 2022-10-05 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
JP7442256B2 (en) | How to replace the floor slab | |
JP6081117B2 (en) | How to remove existing bridge and update existing bridge | |
KR101014779B1 (en) | Construction method by concrete lining in parallel with excavation, working platform for reinforcement and waterproofing work and lining form for pouring lining concrete | |
JP2013174075A (en) | Reconstruction technique for bridge girder | |
JP6793542B2 (en) | Floor slab erection method and floor slab erection equipment | |
JP2017218865A (en) | Precast floor slab erection machine, and transfer method for precast floor slab erection machine at replacement location of precast floor slab | |
JP3954869B2 (en) | Bridge girder replacement method | |
JP2006265884A (en) | Method of removing existing pier of viaduct | |
JP6529378B2 (en) | Invert construction method, tunnel construction method and Teruha crane for tunnel | |
JP2019120115A (en) | Method of constructing tunnel lining structure | |
JP5184248B2 (en) | Construction method of level crossing | |
JP2017193885A (en) | Reconstruction method of lining part in existing 2-traffic lane road tunnel | |
JP4559370B2 (en) | Girder erection method by erection gutter from the side of bridge | |
JP2022033346A (en) | Slab replacement method | |
JPH08170486A (en) | Tunnel excavated muck carry-out gantry | |
JP2023029610A (en) | Slab replacement method | |
JP2023101672A (en) | Floor slab replacement method | |
JP6974233B2 (en) | Floor slab replacement method and floor slab replacement device | |
JP6843001B2 (en) | Reinforcing bar cage built-in system | |
JP5613294B1 (en) | Bridge repair method | |
JP2000265777A (en) | Transferable stage for repairing tunnel and tunnel repair method using the same | |
JP6395056B2 (en) | How to make precast concrete slabs | |
JP2019019477A (en) | Floor slab replacement method and portal crane | |
JP5893703B2 (en) | Side groove reclaim structure | |
JP6626599B1 (en) | Floor slab cutting device |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
A621 | Written request for application examination |
Free format text: JAPANESE INTERMEDIATE CODE: A621 Effective date: 20220113 |
|
A871 | Explanation of circumstances concerning accelerated examination |
Free format text: JAPANESE INTERMEDIATE CODE: A871 Effective date: 20220113 |
|
A131 | Notification of reasons for refusal |
Free format text: JAPANESE INTERMEDIATE CODE: A131 Effective date: 20220412 |
|
A521 | Request for written amendment filed |
Free format text: JAPANESE INTERMEDIATE CODE: A523 Effective date: 20220609 |
|
TRDD | Decision of grant or rejection written | ||
A01 | Written decision to grant a patent or to grant a registration (utility model) |
Free format text: JAPANESE INTERMEDIATE CODE: A01 Effective date: 20220906 |
|
A61 | First payment of annual fees (during grant procedure) |
Free format text: JAPANESE INTERMEDIATE CODE: A61 Effective date: 20220922 |
|
R150 | Certificate of patent or registration of utility model |
Ref document number: 7148746 Country of ref document: JP Free format text: JAPANESE INTERMEDIATE CODE: R150 |