JP2020197783A - Formation method of process chart - Google Patents

Formation method of process chart Download PDF

Info

Publication number
JP2020197783A
JP2020197783A JP2019102113A JP2019102113A JP2020197783A JP 2020197783 A JP2020197783 A JP 2020197783A JP 2019102113 A JP2019102113 A JP 2019102113A JP 2019102113 A JP2019102113 A JP 2019102113A JP 2020197783 A JP2020197783 A JP 2020197783A
Authority
JP
Japan
Prior art keywords
process chart
server
craftsman
construction
registered
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
JP2019102113A
Other languages
Japanese (ja)
Other versions
JP6864196B2 (en
Inventor
知岳 大▲橋▼
Tomotake Ohashi
知岳 大▲橋▼
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Living Ohashi KK
Original Assignee
Living Ohashi KK
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Living Ohashi KK filed Critical Living Ohashi KK
Priority to JP2019102113A priority Critical patent/JP6864196B2/en
Publication of JP2020197783A publication Critical patent/JP2020197783A/en
Application granted granted Critical
Publication of JP6864196B2 publication Critical patent/JP6864196B2/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Management, Administration, Business Operations System, And Electronic Commerce (AREA)

Abstract

To provide a method for constructing a building capable of effectively utilizing surplus time of craftsmen and causing less economical risk for a building owner.SOLUTION: A formation method of a process chart includes: a step in which a server forms a first process chart containing a plurality of processes, craftsmen in charge of respective processes, and construction periods of respective processes, on the basis of construction contents data containing data of craftsmen, surplus time data, the plurality of processes, the sequence order of the plurality of processes, required days for each process among the plurality of processes, and materials used in each process among the plurality of processes which are registered in a storage part; and a step in which the server notifies terminal devices of respective craftsmen in charge of the first process chart.SELECTED DRAWING: Figure 5

Description

本発明は、職人の余剰時間を有効活用することができ且つ建物所有者にとって経済的リスクが少ない工事を行うことを可能にする建物の工程表の作成方法に関する。 The present invention relates to a method for creating a process chart of a building, which makes it possible to effectively utilize the surplus time of craftsmen and to carry out construction work with less economic risk for the building owner.

地域資源としての空き家がここ数年増え続けている。総務省統計局による平成30年(2018年)の調査「住宅・土地統計調査」のデータによれば、日本に存在する住宅の数を表す「総住宅数」は6242万戸であり、「空き家数」は846万戸である。すなわち、総住宅数に占める空き家の割合を示す「空き家率」は13.6%に達している(非特許文献1)。 Unoccupied houses as a local resource have been increasing in recent years. According to the data of the 2018 survey "Housing and Land Statistics Survey" by the Statistics Bureau of the Ministry of Internal Affairs and Communications, the "total number of houses", which represents the number of houses existing in Japan, is 62.42 million, and "vacant houses". The number is 8.46 million. That is, the "vacant house rate", which indicates the ratio of vacant houses to the total number of houses, has reached 13.6% (Non-Patent Document 1).

「平成30年住宅・土地統計調査 住宅数概数集計 結果の要約」インターネット<https://www.stat.go.jp/data/jyutaku/2018/pdf/g#youyaku.pdf>"2018 Housing and Land Statistics Survey Summary of Results of Approximate Number of Houses" Internet <https://www.stat.go.jp/data/jyutaku/2018/pdf/g#youyaku.pdf>

このような空き家は、地域資源として活用されないだけでなく、概して適切に管理されていないために、老朽化による雨漏り、倒壊、景観の悪化、放火による火災、雪の重みによる倒壊や落雪等により、建物所有者や近隣住民に被害をもたらす可能性がある。 Not only are such vacant houses not used as local resources, but they are generally not properly managed, resulting in rain leaks, collapses, landscape deterioration due to aging, fires due to arson, collapses due to the weight of snow, and snowfall. It can cause damage to building owners and neighbors.

建物に人が住まずに空き家のままの状態になってしまう理由としては、主に、建物の老朽化が進んでも、建物所有者である大家に、空き家の改修工事のための経済的負担がかかることが挙げられる。 The main reason why people do not live in a building and it remains vacant is that even if the building is aging, the landlord, who is the owner of the building, will have to bear the financial burden of repairing the vacant house. This can be mentioned.

従来、老朽化した建物の改修工事を行うためには、建物所有者は、改修工事に関する相談を工務店と行う必要があり、また、工事費用の融資に関する相談を金融機関と行う必要があった。 In the past, in order to carry out renovation work on an aging building, the building owner had to consult with the contractor about the renovation work, and also had to consult with the financial institution about financing the construction cost. ..

そして、建物の改修工事の完了後には、建物所有者は、回収した建物の買い主または借り主を募集しつつ、工事を依頼した工務店には改修工事費用を支払う必要があり、融資を受けた金融機関には融資を返済する必要があった。 Then, after the completion of the renovation work of the building, the building owner needs to pay the renovation work cost to the contractor who requested the construction while recruiting the buyer or borrower of the recovered building, and the finance received the loan. The institution had to repay the loan.

しかしながら、買い主または借り主が決まるかどうかは工事完了時点において不明確であり、買い主または借り主が決まらない場合、建物所有者には、工事費用の支払い及び融資の返済が大きな負担となっていた。 However, it is unclear whether the buyer or borrower will be decided at the time of completion of the construction, and if the buyer or borrower is not decided, the building owner will have to pay the construction cost and repay the loan.

一方で、工事を行う職人は、時期によって繁忙期と閑散期の差が大きいことや、悪天候によって工事計画が変更になる等の理由で、スケジュールがたてにくく、余剰時間を有効活用することが難しかった。また、職人の所得向上も望まれている。 On the other hand, it is difficult for craftsmen who perform construction work to make a schedule because there is a large difference between the busy season and the off-season depending on the season, and the construction plan changes due to bad weather, so it is possible to make effective use of surplus time. was difficult. It is also desired to improve the income of craftsmen.

そこで、職人の余剰時間を有効活用することができ且つ建物所有者にとって経済的リスクが少ない建物の工事を行うことを可能とする方法が求められている。 Therefore, there is a need for a method that can effectively utilize the surplus time of craftsmen and enable the construction of a building with less economic risk for the building owner.

建物の工事の工程表の作成方法であって、
サーバに登録された複数の職人が所有する材料のデータが、共有材料データとして、端末装置から前記サーバに送信され前記サーバの記憶部に登録されるステップと、
前記複数の職人それぞれの余剰時間データが、端末装置から前記サーバに送信され前記サーバの記憶部に登録されるステップと、
前記建物の所有者の依頼内容及び前記登録された共有材料データに基づいて、工事内容データが作成され前記サーバの記憶部に登録されるステップであって、前記工事内容データは、複数の工程、前記複数の工程の順番、前記複数の工程の各工程の所要日数、及び前記複数の工程のそれぞれで使用する材料を含む、ステップと、
前記サーバが、前記記憶部に登録された前記職人のデータ、前記余剰時間データ、及び前記工事内容データに基づいて、前記複数の工程、前記複数の工程それぞれを担当する職人、及び前記複数の工程それぞれの工期を含む第1工程表を作成するステップと、
前記サーバが、前記担当する職人の端末装置に、前記第1工程表を通知するステップと、
を含む、工程表の作成方法を対象とする。
It is a method of creating a process chart for building construction,
A step in which material data owned by a plurality of craftsmen registered in a server is transmitted from a terminal device to the server as shared material data and registered in a storage unit of the server.
A step in which the surplus time data of each of the plurality of craftsmen is transmitted from the terminal device to the server and registered in the storage unit of the server.
It is a step in which construction content data is created based on the request content of the building owner and the registered shared material data and registered in the storage unit of the server, and the construction content data is a plurality of processes. A step that includes the order of the plurality of steps, the number of days required for each step of the plurality of steps, and the material used in each of the plurality of steps.
Based on the data of the craftsman, the surplus time data, and the construction content data registered in the storage unit, the server is in charge of the plurality of processes, the craftsman in charge of each of the plurality of processes, and the plurality of processes. Steps to create the first process chart including each construction period,
A step in which the server notifies the terminal device of the craftsman in charge of the first process chart, and
Including, the method of creating a process chart is targeted.

本発明によれば、職人の余剰時間を有効活用することができ且つ建物所有者にとって経済的リスクが少ない工事を行うことが可能となる。 According to the present invention, it is possible to effectively utilize the surplus time of the craftsman and to carry out the construction work with less economic risk for the building owner.

図1は、浴室の改修工事を行うための第1工程表の一例である。FIG. 1 is an example of a first process chart for performing bathroom repair work. 図2は、本方法の好ましい方法における処理の動作の例を示すフローチャートである。FIG. 2 is a flowchart showing an example of processing operation in a preferred method of the present method. 図3は、本方法の好ましい方法における処理の動作の例を示すフローチャートである。FIG. 3 is a flowchart showing an example of the operation of the process in the preferred method of the present method. 図4は、本方法の好ましい方法における処理の動作の例を示すフローチャートである。FIG. 4 is a flowchart showing an example of the operation of the process in the preferred method of the present method. 図5に、本方法により作成された工程表の一例である。FIG. 5 shows an example of a process chart created by this method. 図6は、本方法の好ましい実施形態の一例である。FIG. 6 is an example of a preferred embodiment of the method. 図7は、本方法の好ましい実施形態の一例である。FIG. 7 is an example of a preferred embodiment of the method. 図8は、本方法の好ましい実施形態の一例である。FIG. 8 is an example of a preferred embodiment of the method. 図9は、本方法の好ましい実施形態の一例である。FIG. 9 is an example of a preferred embodiment of the method. 図10は、本方法の好ましい実施形態の一例である。FIG. 10 is an example of a preferred embodiment of the method. 図11に、本方法の好ましい実施形態の一例である。FIG. 11 shows an example of a preferred embodiment of the method. 図12は、従来の工程表の一例である。FIG. 12 is an example of a conventional process chart.

本発明は、建物の工事の工程表の作成方法であって、サーバに登録された複数の職人が所有する材料のデータが、共有材料データとして、端末装置から前記サーバに送信され前記サーバの記憶部に登録されるステップと、前記複数の職人それぞれの余剰時間データが、端末装置から前記サーバに送信され前記サーバの記憶部に登録されるステップと、前記建物の所有者の依頼内容及び前記登録された共有材料データに基づいて、工事内容データが作成され前記サーバの記憶部に登録されるステップであって、前記工事内容データは、複数の工程、前記複数の工程の順番、前記複数の工程の各工程の所要日数、及び前記複数の工程のそれぞれで使用する材料を含む、ステップと、前記サーバが、前記記憶部に登録された前記職人のデータ、前記余剰時間データ、及び前記工事内容データに基づいて、前記複数の工程、前記複数の工程それぞれを担当する職人、及び前記複数の工程それぞれの工期を含む第1工程表を作成するステップと、前記サーバが、前記担当する職人の端末装置に、前記第1工程表を通知するステップと、を含む、工程表の作成方法を対象とする。 The present invention is a method for creating a process chart for building construction, in which data of materials owned by a plurality of craftsmen registered in a server is transmitted from a terminal device to the server as shared material data and stored in the server. The step to be registered in the department, the step in which the surplus time data of each of the plurality of craftsmen is transmitted from the terminal device to the server and registered in the storage unit of the server, the request contents of the owner of the building, and the registration. It is a step in which construction content data is created based on the shared material data and registered in the storage unit of the server, and the construction content data is a plurality of processes, an order of the plurality of processes, and the plurality of processes. The steps, the data of the craftsman registered in the storage unit, the surplus time data, and the construction content data of the step, including the required number of days of each process, and the materials used in each of the plurality of processes. Based on the above, a step of creating a first process chart including the plurality of processes, a craftsman in charge of each of the plurality of processes, and a construction period of each of the plurality of processes, and a terminal device of the craftsman in charge of the server. The target is a method for creating a process chart, including a step of notifying the first process chart.

本方法によれば、職人は各職人の余剰時間で工事を行うことができるので、余剰時間を有効活用することができる。そのため、職人個々の余剰時間を無駄にすることなく工事の成果として積み立てていき、工事を担当した職人は、後々成功報酬として工事費用の支払いを受けることができ、所得向上につながる。 According to this method, the craftsman can carry out the construction with the surplus time of each craftsman, so that the surplus time can be effectively utilized. Therefore, the surplus time of each craftsman is not wasted and is accumulated as the result of the construction, and the craftsman in charge of the construction can later receive the payment of the construction cost as a success fee, which leads to an increase in income.

また、本方法によれば、建物所有者は、工事を行った建物の買い主または借り主が決まった後で、工事費用の支払いを行えばよいので、建物所有者にとって経済的リスクが従来よりも少ない。そのため、空き家の価値を上げることができる。 In addition, according to this method, the building owner only has to pay the construction cost after the buyer or borrower of the building to be constructed is decided, so that the economic risk for the building owner is less than before. .. Therefore, the value of the vacant house can be increased.

本方法においては、サーバに登録された複数の職人が所有する材料のデータが、共有材料データとして、端末装置からサーバに送信されサーバの記憶部に登録される。 In this method, material data owned by a plurality of craftsmen registered in the server is transmitted from the terminal device to the server as shared material data and registered in the storage unit of the server.

サーバは、サーバの記憶部に、複数の職人のデータ(以下、職人データともいう)を登録することができる。本願において、登録するとは、サーバの記憶部に記憶することである。あらかじめ、職人データがサーバに登録されていてもよく、または工事の依頼の都度、職人データがサーバに登録されてもよい。任意のタイミングで、サーバに登録される職人データの追加または削除が行われてもよい。サーバに登録される職人は、特定の信頼のおける職人であることができる。 The server can register data of a plurality of craftsmen (hereinafter, also referred to as craftsman data) in the storage unit of the server. In the present application, registration means storing in the storage unit of the server. The craftsman data may be registered in the server in advance, or the craftsman data may be registered in the server each time a construction request is made. The craftsman data registered in the server may be added or deleted at any time. The craftsman registered on the server can be a particular trusted craftsman.

登録される職人としては、工事に必要な職人であれば特に制限されないが、設計、基礎、足場、給水、排水、電気(電気設備、照明)、大工、木工、内装、外装、塗装、外壁、屋根、雨樋、瓦、住宅設備(住設)、建具、家具、畳、ふすま、障子等を扱う職人が挙げられる。 The registered craftsmen are not particularly limited as long as they are necessary for construction, but design, foundation, scaffolding, water supply, drainage, electricity (electrical equipment, lighting), carpenter, woodworking, interior, exterior, painting, exterior wall, Craftsmen who handle roofs, gutters, tiles, housing equipment (housing equipment), fittings, furniture, tatami mats, bran, shoji screens, etc. can be mentioned.

工種毎に1人ずつの職人が登録されてもよいが、好ましくは、工種毎に少なくとも2人以上、より好ましくは3人以上の職人が登録される。工種毎に複数人の職人を登録することにより、並行して複数の現場の工事を進めることが可能となる。また、工種毎に複数人の職人が登録されることにより、ある職人の都合がつかない場合に、他の職人が代わりに工事を進めることが可能となる。登録する職人の数の上限は特に制限されないが、例えば工種毎に10人、20人、または30人であることができる。 One craftsman may be registered for each work type, but preferably at least two or more, more preferably three or more craftsmen are registered for each work type. By registering multiple craftsmen for each type of work, it is possible to proceed with construction at multiple sites in parallel. In addition, by registering a plurality of craftsmen for each type of work, it is possible for another craftsman to proceed with the construction instead when one craftsman is not convenient. The upper limit of the number of craftsmen to be registered is not particularly limited, but can be, for example, 10, 20, or 30 for each type of work.

登録される職人データとしては、好ましくは、各職人の氏名、居住地の住所、作業場の住所、工種、報酬、及び電話番号、電子メールアドレス等の連絡先が含まれ、これらの職人データが、サーバの記憶部に登録される。報酬は、所定の期間あたりの職人に支払う報酬であり、好ましくは1日あたりの職人に支払う報酬である。 The craftsman data to be registered preferably includes the name of each craftsman, the address of the place of residence, the address of the workplace, the type of work, the reward, and the contact information such as the telephone number and the e-mail address. Registered in the storage of the server. The remuneration is a remuneration paid to a craftsman for a predetermined period, preferably a remuneration paid to a craftsman per day.

サーバが共有材料データとしてサーバの記憶部に登録する材料は、登録された各職人が所有する材料のうち使用する具体的予定がない材料であり、いわゆる在庫であり、以下、余剰材料ともいう。 The material that the server registers in the storage unit of the server as shared material data is a material that is not specifically planned to be used among the materials owned by each registered craftsman, is so-called inventory, and is also referred to as surplus material below.

登録される材料の種類としては、各職人が所有するもので工事に用いられるものであれば特に制限されないが、例えば、玄関、キッチン、浴室、石膏ボード、漆喰、珪藻土、クロス、材木、材木等の半端材等が含まれる。 The type of material to be registered is not particularly limited as long as it is owned by each craftsman and used for construction, but for example, entrance, kitchen, bathroom, gypsum board, plaster, diatomaceous earth, cloth, timber, timber, etc. Includes half-finished materials.

登録される材料データとしては、特に制限されないが、好ましくは、材料の種類、数、保管場所、外観写真、図面、証明書、型番、及び価格が含まれ、より好ましくは、材料の数、保管場所、外観写真、型番、及び価格が含まれる。これらが、共有材料データとしてサーバの記憶部に登録される。 The material data to be registered is not particularly limited, but preferably includes the type, number, storage location, appearance photograph, drawing, certificate, model number, and price of the material, and more preferably the number of materials and storage. Includes location, exterior photo, model number, and price. These are registered in the storage unit of the server as shared material data.

好ましくは、共有材料データには、工事に使用する材料の所定のセットが含まれる。材料の所定のセットには、好ましくは、駆体材料のセットとして、コンクリート類、砥石等の石材または材木、合板等の木材、内装材のセットとして、漆喰、ビニールクロス等、外装材のセットとして、タイル、サイディング等、及び住設機器のセットとして、キッチン、トイレ、浴室等が含まれる。共有材料データにおいて、工事に使用する材料が、職人の目利きに基づくパッケージ化されたセットプランとしてあらかじめ登録されていることで、建物所有者から工事依頼を受けたときに、登録されたパッケージ化されたセットプランに基づいて、短時間且つ低コストで、工事内容データが作成され得る。 Preferably, the shared material data includes a predetermined set of materials used in the construction. In a predetermined set of materials, preferably, as a set of body materials, as a set of stones or timbers such as concretes and grindstones, wood such as plywood, as a set of interior materials, as a set of exterior materials such as plaster and vinyl cloth. , Tiles, siding, etc., and as a set of housing equipment, kitchen, toilet, bathroom, etc. are included. In the shared material data, the materials used for construction are pre-registered as a packaged set plan based on the connoisseurs of the craftsmen, so that when a construction request is received from the building owner, the registered packaging will be provided. Construction content data can be created in a short time and at low cost based on the set plan.

材料の外観写真及び型番のうち、少なくとも一方が、共有材料データとして含まれていることが好ましい。材料の型番を共有材料データとして登録することにより、材料の種類等の特定、管理、及び選択が容易に行われ得る。材料の外観写真は、スマートフォンやデジタルカメラ等で撮影したものであることができる。スマートフォンで材料の外観写真を撮影し、そのままスマートフォンからサーバに写真データを送信しサーバに登録することができる。共有材料データとして登録された外観写真に基づいて、型番、図面、承認図等を入手することもできる。 It is preferable that at least one of the appearance photograph and the model number of the material is included as the shared material data. By registering the model number of the material as shared material data, the type of material and the like can be easily specified, managed, and selected. The external photograph of the material can be taken with a smartphone, a digital camera, or the like. You can take a photo of the appearance of the material with your smartphone, send the photo data from your smartphone to the server as it is, and register it on the server. It is also possible to obtain model numbers, drawings, approval drawings, etc. based on the external photographs registered as shared material data.

職人が所有する材料のデータは、端末装置からサーバに送信されることで、任意のタイミングで、サーバの記憶部に登録され得る。職人が所有する材料のデータが端末装置からサーバに送信してサーバの記憶部に登録されるタイミングは、好ましくは、余剰材料が発生する都度、余剰材料が発生する都度〜24時間以内毎、余剰材料が発生する都度〜1週間以内毎、余剰材料が発生する都度〜1か月以内毎、または余剰材料が発生する都度〜1年以内毎等の所定の期間内であり、より好ましくは、余剰材料が発生する都度〜24時間以内毎または余剰材料が発生する都度〜1週間以内毎である。サーバの記憶部に登録される共有材料として使用できる材料のデータが、余剰材料が発生する都度更新、毎日更新、または1週間単位で更新されることにより、共有材料データを最新に保つことができ、工程表がより効率よく作成され得る。 The data of the material owned by the craftsman can be registered in the storage unit of the server at an arbitrary timing by being transmitted from the terminal device to the server. The timing at which the data of the material owned by the craftsman is transmitted from the terminal device to the server and registered in the storage unit of the server is preferably the time when the surplus material is generated, every time the surplus material is generated, and every 24 hours or less. It is within a predetermined period such as every time a material is generated to within one week, every time a surplus material is generated to every one month, or every time a surplus material is generated to every one year, and more preferably, a surplus. Every time a material is generated to within 24 hours or every time a surplus material is generated to within a week. The shared material data can be kept up-to-date by updating the data of the material that can be used as the shared material registered in the storage part of the server every time surplus material is generated, daily update, or weekly update. , The process chart can be created more efficiently.

端末装置としては、インターネットに接続されてデータの送受信が可能であれば特に限定されないが、パソコンまたは情報通信端末装置が挙げられ、好ましくはスマートフォンが用いられる。サーバは、インターネットに接続されてデータの送受信が可能な通信部、記憶部、及び処理部を備えている。 The terminal device is not particularly limited as long as it is connected to the Internet and can transmit and receive data, but examples thereof include a personal computer or an information communication terminal device, and a smartphone is preferably used. The server includes a communication unit, a storage unit, and a processing unit that are connected to the Internet and capable of transmitting and receiving data.

記憶部には、複数の職人のデータ、複数の職人が所有する材料のデータ(共有材料データ)、下記に説明する複数の職人それぞれの余剰時間データ、工事内容データ、及び所望により工事費用データが、それぞれ登録され得る。 In the storage unit, data of multiple craftsmen, data of materials owned by multiple craftsmen (shared material data), surplus time data of each of the multiple craftsmen explained below, construction content data, and construction cost data if desired are stored. , Each can be registered.

処理部は、一個または複数個のプロセッサ及びその周辺回路を有する。処理部は、サーバの全体的な動作を統括的に制御するものであり、例えば、CPU(Central Processing Unit)である。処理部は、複数の職人のデータ、複数の職人が所有する材料のデータ(共有材料データ)、複数の職人それぞれの余剰時間データ、工事内容データ、及び所望により工事費用データの、送受信及び記憶部への記憶(登録)、並びに記憶部に登録されている上記データに基づき、後で説明する工程表の作成、修正、及び通知が実行されるように、通信部及び記憶部の動作を制御することができる。処理部は、記憶部に記憶されているプログラム(ドライバプログラム、オペレーティングシステムプログラム、アプリケーションプログラム等)に基づいて処理を実行する。また、処理部は、複数のプログラム(アプリケーションプログラム等)を並列に実行できる。 The processing unit has one or more processors and peripheral circuits thereof. The processing unit comprehensively controls the overall operation of the server, and is, for example, a CPU (Central Processing Unit). The processing unit is a transmission / reception and storage unit for data of multiple craftsmen, data of materials owned by multiple craftsmen (shared material data), surplus time data of each of multiple craftsmen, construction content data, and, if desired, construction cost data. Based on the storage (registration) in the storage unit and the above data registered in the storage unit, the operations of the communication unit and the storage unit are controlled so that the creation, modification, and notification of the process chart described later are executed. be able to. The processing unit executes processing based on a program (driver program, operating system program, application program, etc.) stored in the storage unit. In addition, the processing unit can execute a plurality of programs (application programs, etc.) in parallel.

本方法においては、複数の職人それぞれの余剰時間データが、端末装置からサーバに送信されサーバの記憶部に登録される。 In this method, the surplus time data of each of the plurality of craftsmen is transmitted from the terminal device to the server and registered in the storage unit of the server.

サーバは、余剰時間(空き時間)データを、職人毎の余剰時間データとしてサーバの記憶部に登録することができる。これにより、各職人の余剰時間を有効活用することができる。 The server can register the surplus time (free time) data in the storage unit of the server as the surplus time data for each craftsman. As a result, the surplus time of each craftsman can be effectively utilized.

余剰時間データには、上記職人データと関連付けて、各職人の余剰時間が登録される。余剰時間データの登録方法は、好ましくは、端末装置からインターネットを介して、サーバ上に作成された職人データに関連付けられたカレンダーに余剰時間の日時が入力され、これにより余剰時間データが登録され得る。 In the surplus time data, the surplus time of each craftsman is registered in association with the above craftsman data. The surplus time data is preferably registered by inputting the date and time of the surplus time into the calendar associated with the craftsman data created on the server from the terminal device via the Internet, whereby the surplus time data can be registered. ..

職人毎の余剰時間データは、端末装置からサーバに送信されることで、任意のタイミングで、サーバがサーバの記憶部に登録することができる。職人毎の余剰時間データが端末装置からサーバに送信されサーバの記憶部に登録されるタイミングは、好ましくは、余剰時間が変更される都度、余剰時間が変更される都度〜24時間以内毎、余剰時間が変更される都度〜3日以内毎、余剰時間が変更される都度〜1週間以内毎、または余剰時間が変更される都度〜1ヶ月以内毎等の所定の期間内であり、より好ましくは、余剰時間が変更される都度〜24時間以内毎または余剰時間が変更する都度〜3日以内毎である。余剰時間データを余剰時間が変更する都度更新、毎日更新、または1週間単位で更新することにより、余剰時間データを最新に保つことができ、工程表がより効率よく作成され得る。 The surplus time data for each craftsman is transmitted from the terminal device to the server, so that the server can register it in the storage unit of the server at an arbitrary timing. The timing at which the surplus time data for each craftsman is transmitted from the terminal device to the server and registered in the storage unit of the server is preferably every time the surplus time is changed, every time the surplus time is changed to within 24 hours, and the surplus. It is within a predetermined period such as every time the time is changed to within 3 days, every time the surplus time is changed to within 1 week, or every time the surplus time is changed to within 1 month, and more preferably. , Every time the surplus time is changed to within 24 hours or every time the surplus time is changed to within 3 days. By updating the surplus time data every time the surplus time is changed, daily update, or weekly update, the surplus time data can be kept up-to-date, and the process chart can be created more efficiently.

職人の余剰期間は、長期間における余剰時間だけでなく、短期間における余剰時間でもよい。余剰時間は、悪天候により工事を行えなくなった場合や、工期変更により工事できなくなってしまった場合等、急遽生じた余剰期間でもよい。余剰時間は、例えば、当日〜7日先までの短期間における余剰時間でもよく、または8日先以降の余剰時間でもよい。 The surplus period of the craftsman may be not only the surplus time in a long period but also the surplus time in a short period. The surplus time may be a surplus period that occurs in a hurry, such as when construction cannot be performed due to bad weather or when construction cannot be performed due to a change in construction period. The surplus time may be, for example, the surplus time in a short period from the current day to 7 days ahead, or the surplus time after 8 days ahead.

余剰時間の単位は、月、日、時、分等の任意であることができ、好ましくは、午前または午後等の半日等の一日未満の単位、1日以上〜1週間未満の単位、1週間以上1ヶ月未満の単位、または1ヶ月以上1年以下の単位であり、より好ましくは1日以上〜1週間未満の単位または1週間以上1ヶ月未満の単位である。 The unit of surplus time can be arbitrary such as month, day, hour, minute, etc., preferably a unit of less than one day such as half a day such as morning or afternoon, a unit of one day or more and less than one week, 1 It is a unit of a week or more and less than one month, or a unit of one month or more and one year or less, and more preferably a unit of one day or more and less than one week or a unit of one week or more and less than one month.

本方法においては、建物の所有者の依頼内容及び登録された共有材料データに基づいて、工事内容データが作成されサーバの記憶部に登録される。工事内容データには、複数の工程、前記複数の工程の順番、前記複数の工程の各工程の所要日数、及び前記複数の工程のそれぞれで使用する材料が含まれる。 In this method, construction content data is created and registered in the storage unit of the server based on the request content of the building owner and the registered shared material data. The construction content data includes a plurality of steps, the order of the plurality of steps, the number of days required for each step of the plurality of steps, and the materials used in each of the plurality of steps.

サーバは、建物の所有者の依頼に基づく工事内容をサーバの記憶部に登録することができる。建物の所有者の依頼には、例えば、改修工事、建て替え工事、取り壊し工事、新築工事等が含まれる。サーバに登録された建物の所有者の依頼に基づく工事内容に応じて、サーバの処理部は、必要な工程、工程の順番、及び各工程の所要日数を含む工事内容データを作成し、記憶部に登録することができる。サーバの処理部はまた、前記登録した工事内容データに基づき、サーバの記憶部に登録された共有材料データから、各工程で使用する材料を選択し、組み合わせることができる。これにより、複数の職人が所有する材料ストックを活用することができ、工事の際に、新たに仕入れる材料を少なくすることができ、好ましくはゼロにすることができる。材料ストックを活用することにより、材料を新規発注するよりも、安価に工事を行うことができ、且つ職人の材料ストックを有効活用することもできる。使用する材料を所有する職人と工事を担当する職人は、別でもよいが好ましくは同じであり、工程表を作成する際に、担当する職人を選択する条件の1つとしてもよい。 The server can register the construction contents based on the request of the building owner in the storage unit of the server. Requests from building owners include, for example, renovation work, rebuilding work, demolition work, new construction work, and the like. According to the construction content based on the request of the building owner registered in the server, the processing unit of the server creates the construction content data including the required process, the order of the processes, and the required number of days for each process, and stores it. You can register with. The processing unit of the server can also select and combine the materials used in each process from the shared material data registered in the storage unit of the server based on the registered construction content data. As a result, it is possible to utilize the material stock owned by a plurality of craftsmen, reduce the amount of newly purchased materials during construction, and preferably reduce the number to zero. By utilizing the material stock, the construction can be carried out at a lower cost than when a new material is ordered, and the material stock of the craftsman can be effectively utilized. The craftsman who owns the materials to be used and the craftsman who is in charge of the construction may be different, but preferably the same, and may be one of the conditions for selecting the craftsman in charge when creating the process chart.

工事内容データには、好ましくは、予定工事期間、完成後の建物のCADによる3Dパースデータ、売却する場合の想定売却価格及び賃貸にだす場合の見込み賃料のうち少なくとも一方のデータ、及び工事費用データが含まれる。工事費用データは、好ましくは、サーバの記憶部に登録された工程の種類の単価、工程数、各工程の所要日数、及び複数の工程のそれぞれで使用する材料費に基づいて、サーバの処理部により算出される。サーバは、工事費用データに基づいて、工事費用を建物所有者に通知することができる。サーバの処理部は、登録された共有材料データ内の材料だけで足りるか否かを判定し、判定結果を、各工程を担当する職人に通知することができる。各工程を担当する職人は、通知に基づいて、足りない材料の新規発注を行うことができる。 The construction content data preferably includes data on the planned construction period, 3D perspective data by CAD of the completed building, estimated selling price when selling, and estimated rent when renting, and construction cost data. Is included. The construction cost data is preferably based on the unit price of the type of process registered in the storage unit of the server, the number of processes, the number of days required for each process, and the material cost used in each of the plurality of processes. Is calculated by. The server can notify the building owner of the construction cost based on the construction cost data. The processing unit of the server can determine whether or not only the material in the registered shared material data is sufficient, and notify the craftsman in charge of each process of the determination result. The craftsman in charge of each process can place a new order for the missing material based on the notification.

本方法においては、建物所有者は、買い主または借り主が決まる前は工事費用を支払う必要がなく、買い主または借り主が決まってから工事費用を支払えばよいので、建物所有者にとって経済的制約が従来よりも少なく、売買契約または賃貸借契約につながりやすい魅力ある建物になる工事内容に決定することが従来よりも容易になる。 In this method, the building owner does not have to pay the construction cost before the buyer or the borrower is decided, and only has to pay the construction cost after the buyer or the borrower is decided, so that the building owner has a conventional economic constraint. It will be easier than before to decide on the construction content that will make the building attractive, which can easily lead to sales contracts or lease contracts.

本方法においては、好ましくは、使用する材料がパッケージ化されたセットプランがサーバの記憶部にあらかじめ登録されており、登録されたパッケージ化されたセットプランに基づいて、工事内容データが作成される。職人の目利きに基づくパッケージ化されたセットプランの材料を用いて工事を行うことができるので、工事完成後の建物は売買契約または賃貸借契約につながりやすい魅力ある物件となり得る。これにより、工事内容及び工事費用についての打ち合わせの省略または簡略化を行うことができる。登録された工事内容データは、建物所有者の希望に基づいて修正されてもよい。 In this method, preferably, a set plan in which the materials to be used are packaged is registered in advance in the storage unit of the server, and construction content data is created based on the registered packaged set plan. .. Since the construction can be carried out using the materials of the packaged set plan based on the connoisseur of the craftsman, the building after the construction is completed can be an attractive property that can easily lead to a sales contract or a lease contract. This makes it possible to omit or simplify meetings regarding construction details and construction costs. The registered construction content data may be modified based on the wishes of the building owner.

工事内容データに含まれる複数の工程及び複数の工程の順番は、本方法で作成する工程表の対象となる工事内容に基づいて、決定され得る。複数の工程及び複数の工程の順番は、従来行われている工事と同様であることができる。複数の工程としては、例えば、電気、水道(給排水設備)、大工、内装、外装、住設等が挙げられる。 The order of the plurality of processes and the plurality of processes included in the construction content data can be determined based on the construction content that is the target of the process chart created by this method. The order of the plurality of steps and the plurality of steps can be the same as that of the conventional construction. Examples of the plurality of processes include electricity, water supply (water supply / drainage equipment), carpentry, interior, exterior, housing, and the like.

好ましくは、対象となる工事内容に応じた順番を含む工程パターンが、サーバの記憶部にあらかじめ登録されており、対象となる工事内容がサーバに登録されると、サーバが、登録された対象となる工事内容に基づいて、サーバの記憶部に登録された工程パターンを、複数の工程及び複数の工程の順番として取得する。 Preferably, a process pattern including an order according to the target construction content is registered in advance in the storage unit of the server, and when the target construction content is registered in the server, the server becomes the registered target. The process pattern registered in the storage unit of the server is acquired as the order of a plurality of processes and a plurality of processes based on the construction contents.

複数の工程の各工程の所要日数は、本方法で作成する工程表の対象となる工事内容に基づいて、決定され得る。本方法においては、各工程の所要日数は、従来行われている工事における工程の所要日数よりも長く設定され得る。 The required number of days for each process of the plurality of processes can be determined based on the construction content to be the target of the process chart created by this method. In this method, the required number of days for each process can be set longer than the required number of days for the process in the conventional construction.

本方法においては、職人の余剰時間を利用して工程表が作成されるため、従来の工期よりも長い工期となり、例えば3倍〜5倍の工期となる。そのため、例えば、従来は1日〜1週間程度で行っていた工程が、3日〜3週間程度で計画され得る。本方法で作成した工程表の工期は、従来の工期よりも長くなるが、工事完成後に建物の買い主または借り主が決まるまで、建物所有者には工事費用の請求は行われないため、建物所有者の経済的リスクは小さい。本願において、工期とは、工程の工事が行われる期間を意味し、週単位、日単位、時単位等の所望の単位で定めることができる。 In this method, since the process chart is created by using the surplus time of the craftsman, the construction period is longer than the conventional construction period, for example, the construction period is 3 to 5 times. Therefore, for example, a process that was conventionally performed in about 1 day to 1 week can be planned in about 3 days to 3 weeks. The construction period of the schedule created by this method will be longer than the conventional construction period, but the building owner will not be charged the construction cost until the buyer or borrower of the building is decided after the construction is completed. The economic risk of is small. In the present application, the construction period means a period during which the construction of the process is performed, and can be determined in a desired unit such as a weekly unit, a daily unit, or an hourly unit.

好ましくは、各工程の所要日数がサーバの記憶部にあらかじめ登録されており、対象となる工事内容がサーバに登録されると、サーバが、登録された対象となる工事内容に基づいて、複数の工程及び複数の工程の順番とともに、各工程の所要日数を取得する。 Preferably, the required number of days for each process is registered in advance in the storage unit of the server, and when the target construction content is registered in the server, the server may perform a plurality of registrations based on the registered target construction content. Acquire the required number of days for each process as well as the order of the process and a plurality of processes.

工事内容データにおいては、複数の工程は、複数の工程のそれぞれで使用する材料と関連付けられる。例えば、キッチンは水道工程及び住設工程で使用されるので、キッチンと水道工程及び住設工程とが関連付けてサーバの記憶部に登録される。 In the construction content data, the plurality of processes are associated with the materials used in each of the plurality of processes. For example, since the kitchen is used in the water supply process and the housing process, the kitchen and the water supply process and the housing process are associated and registered in the storage unit of the server.

本方法においては、サーバが、記憶部に登録された職人のデータ、余剰時間データ、及び工事内容データに基づいて、複数の工程、複数の工程それぞれを担当する職人、及び複数の工程それぞれの工期を含む第1工程表を作成する。サーバは、第1工程表の作成の際に、サーバの処理部により工事費用を算出して工事費用データとして記憶部に登録してもよい。工事費用は、好ましくは、サーバの記憶部に登録された工程の種類、工程数、各工程の所要日数、複数の工程のそれぞれで使用する材料、及び各工程を担当する職人の報酬単価に基づいて、サーバの処理部により算出される。工事内容データに工事費用データが含まれる場合は、サーバは、第1工程表の作成の際に、前記工事費用データを修正してもよい。 In this method, the server has a plurality of processes, a craftsman in charge of each of the plurality of processes, and a construction period of each of the plurality of processes based on the data of the craftsman registered in the storage unit, the surplus time data, and the construction content data. Create a first process chart including. When creating the first process chart, the server may calculate the construction cost by the processing unit of the server and register it in the storage unit as the construction cost data. The construction cost is preferably based on the type of process registered in the storage unit of the server, the number of processes, the number of days required for each process, the materials used in each of the plurality of processes, and the remuneration unit price of the craftsman in charge of each process. It is calculated by the processing unit of the server. When the construction content data includes the construction cost data, the server may modify the construction cost data when creating the first process chart.

サーバは、記憶部に登録された職人のデータ、余剰時間データ、及び工事内容データから、記憶部に登録された複数の工程の各工程を担当する職人を選択する。 The server selects a craftsman in charge of each process of a plurality of processes registered in the storage unit from the data of the craftsman registered in the storage unit, the surplus time data, and the construction content data.

サーバは、好ましくは、工程の順番にしたがって、各工程を担当する職人を選択する。工程の順番にしたがって、工程毎に、登録された余剰時間データに基づいて、工期終了日が最も早くなる職人を選択することができる。一つの工程を担当可能な職人が2人以上いる場合でどの職人でも工期が同じ場合は、好ましくは、工事現場に居住地または作業場がより近い職人を選択する。 The server preferably selects a craftsman in charge of each process according to the order of the processes. According to the order of the processes, the craftsman who has the earliest end date of the construction period can be selected for each process based on the registered surplus time data. If there are two or more craftsmen who can take charge of one process and all the craftsmen have the same construction period, it is preferable to select a craftsman whose place of residence or work place is closer to the construction site.

サーバが、第1工程表を作成する際、各工程の工期は、工事内容データに含まれる工程の所要日数と、登録された余剰時間データとに基づいて、決定され得る。各工程の工期は、余剰時間データに基づき、工事内容データに含まれる工程の所要日数以上で設定される。例えば、工事内容データに含まれる工程の所要日数が3日の場合に、3日連続の余剰時間データが登録されている場合は、3日続けて工事を行うことができるので、当該工程の工期は3日に設定され得る。例えば、工事内容データに含まれる工程の所要日数が3日の場合に、1日ずつの不連続の余剰時間データが登録されている場合は、3日連続して工事を行うことはできないので、当該工程の工期は3日よりも長く設定され得る。 When the server creates the first process chart, the construction period of each process can be determined based on the required number of days of the process included in the construction content data and the registered surplus time data. The construction period of each process is set based on the surplus time data and the required number of days or more of the process included in the construction content data. For example, if the required number of days of the process included in the construction content data is 3 days and the surplus time data for 3 consecutive days is registered, the construction can be performed continuously for 3 days, so that the construction period of the process is Can be set to 3 days. For example, if the number of days required for the process included in the construction content data is 3 days and the discontinuous surplus time data for each day is registered, the construction cannot be performed continuously for 3 days. The construction period of the process can be set longer than 3 days.

第1工程表を作成する際、工程間の日時の間隔は、前の工程の工事の終盤から後の工程の工事が開始されてもよく、または前の工程の工事の完了直後に後の工程の工事が開始する、すなわち、各工程の間はなくてもよいが、好ましくは1日以上、より好ましくは2日以上の間を設ける。各工程の間の上限は特に限定されるものではないが、例えば7日以内としてもよい。各工程間が、土曜日、祝日、及び祭日のうち少なくとも一つとしてもよい。 When creating the first process chart, the date and time interval between processes may be such that the work of the subsequent process may be started from the end of the work of the previous process, or the work of the later process may be started immediately after the completion of the work of the previous process. Construction starts, that is, it does not have to be between each step, but preferably one day or more, more preferably two days or more. The upper limit between each step is not particularly limited, but may be, for example, 7 days or less. Each step may be at least one of Saturdays, public holidays, and public holidays.

本方法で作成する工程表においては、職人の余剰時間を有効活用するために工期を従来よりも長く設定するため、前の工程が完了してから後の工程が開始するように工程間の間隔に余裕を持たせることができる。これにより、工事の進捗が遅延した場合でも、工程表を見直さないですむ場合があり、また、前の工程の工事の進捗に後の工程の工事が影響されにくくなり各工程を担当する職人の作業効率をより向上することができる。 In the process chart created by this method, the construction period is set longer than before in order to effectively utilize the surplus time of the craftsman, so the interval between processes is started so that the subsequent process starts after the previous process is completed. Can be given a margin. As a result, even if the progress of the construction is delayed, it may not be necessary to review the schedule, and the progress of the construction of the previous process is less likely to be affected by the construction of the subsequent process, so that the craftsman in charge of each process Work efficiency can be further improved.

本方法で作成する工程表は、好ましくは、横軸に年月日並びに縦軸に各工程及び各工程を担当する職人が表示された形式である。縦軸及び横軸の表示が逆でもよい。工程表が前記好ましい形式であることにより、職人は担当する工程の予定工期を容易に把握することができる。 The process chart created by this method is preferably in a format in which the date is displayed on the horizontal axis and each process and the craftsman in charge of each process are displayed on the vertical axis. The display on the vertical axis and the horizontal axis may be reversed. Since the process chart has the preferred format, the craftsman can easily grasp the planned construction period of the process in charge.

図1に、浴室の改修工事を行うための第1工程表の一例を示す。図1の第1工程表では、浴室の解体からユニットバスを設置するまでの工程が示されており、電気及び給水の前工程、大工の中工程、木工、住設、及び内装の後工程、電気及び給水の最終工程、並びに全期間にわたる外回りの工程に分けて、第1週〜第5週の工程が示されている。 FIG. 1 shows an example of a first process chart for performing bathroom repair work. The first process chart in FIG. 1 shows the process from dismantling the bathroom to installing the unit bath, including the pre-process of electricity and water supply, the middle process of carpentry, the post-process of woodworking, housing, and interior decoration. The process of the first week to the fifth week is shown by dividing into the final process of electricity and water supply and the outer process over the entire period.

電気及び給水は工事に必要なので前工程に入り、ユニットバスを使えるようにするために最終工程にも入る。電気及び給水の前工程が完了すると、大工の中工程の工事が開始され、中工程の工事が完了すると、木工、住設、及び内装の後工程の工事が開示される。外回りは、他の工程と並行して進めることができるため、全期間にわたる工程となっている。 Since electricity and water supply are necessary for construction, we will enter the previous process and also enter the final process so that the unit bath can be used. When the pre-process of electricity and water supply is completed, the construction of the middle process of the carpenter is started, and when the construction of the middle process is completed, the construction of the post-process of woodworking, housing, and interior is disclosed. Since the outer circumference can be carried out in parallel with other processes, it is a process over the entire period.

本方法においては、サーバが、担当する職人の端末装置に、第1工程表を通知する。 In this method, the server notifies the terminal device of the craftsman in charge of the first process chart.

第1工程表の通知方法は、特に限定されないが、好ましくは電子メールで通知される。電子メールには第1工程表が添付されてもよく、または電子メールで第1工程表がサーバで閲覧可能にアップロードされたことを通知してもよい。 The notification method of the first process chart is not particularly limited, but is preferably notified by e-mail. The first process chart may be attached to the e-mail, or the first process chart may be notified by e-mail that the first process chart has been uploaded so as to be viewable on the server.

各工程を担当する職人は、通知された第1工程表に基づいて、建物の工事を行うことができる。 The craftsman in charge of each process can carry out the construction of the building based on the notified first process chart.

好ましくは、工程表の担当する工程の工事が完了次第、完了報告が端末装置からサーバに送信され、その工程の工事が完了したことがサーバの工程表に反映される。各職人は、端末装置で完了報告が反映された工程表を確認して、予定通りに工事に入れることを判断することができる。より好ましくは、その工程の工事が完了したことが工程表に反映されたことが、サーバから少なくとも次の工程の職人の端末装置に通知される。サーバから少なくとも次の工程の職人の端末装置に前記通知が送信されることにより、次の工程の職人が確実に担当する工程の工事を開始することができる。 Preferably, as soon as the construction of the process in charge of the process chart is completed, the completion report is transmitted from the terminal device to the server, and the completion of the construction of the process is reflected in the process chart of the server. Each craftsman can check the process chart in which the completion report is reflected on the terminal device and decide to start the construction as scheduled. More preferably, the server notifies at least the terminal device of the craftsman of the next process that the completion of the construction of the process is reflected in the process chart. By transmitting the notification from the server to at least the terminal device of the craftsman in the next process, the construction of the process in which the craftsman in the next process is surely in charge can be started.

好ましくは、工程の工事の進捗状況が端末装置からサーバに送信され、送信された進捗状況は工程表とリンクして各職人が閲覧可能にアップロードされる。各職人は、現場に行って進捗状況を確認する必要がなく、端末装置で進捗状況を確認することができ、予定通りに工事に入れるかどうかを容易に把握することができる。 Preferably, the progress of the construction of the process is transmitted from the terminal device to the server, and the transmitted progress is linked to the process chart and uploaded so that each craftsman can view it. Each craftsman does not have to go to the site to check the progress status, and can check the progress status with the terminal device, and can easily grasp whether or not the construction can be started as scheduled.

進捗状況には、好ましくはテキストデータ及び写真データが含まれ、より好ましくは写真データが含まれる。 The progress status preferably includes text data and photographic data, and more preferably photographic data.

テキストデータによれば、進捗状況を具体的に説明することが可能である。写真データによれば、工事現場を撮影するだけで、進捗状況報告を容易に行うことができ、サーバにアップロードされた写真をみて、その後の工程を担当する職人は進捗状況の確認を目視で容易に行うことができる。 According to the text data, it is possible to explain the progress concretely. According to the photo data, it is possible to easily report the progress status just by taking a picture of the construction site, and the craftsman in charge of the subsequent process can easily check the progress status visually by looking at the photo uploaded to the server. Can be done.

進捗状況がサーバに送信されるタイミングは、工程の工事が完了する前であり、好ましくは工程の工事完了予定日の半日前〜7日前、より好ましくは1日前〜3日前である。進捗状況をサーバに送信する頻度は、好ましくは3日に1回、より好ましくは2日に1回、さらに好ましくは毎日である。これにより、次の工程を担当する職人は、予定通りに担当する工程の工事を開始することができるかどうかを、より容易に把握することができる。 The timing at which the progress status is transmitted to the server is before the construction of the process is completed, preferably half a day to seven days before the scheduled completion date of the process, and more preferably one to three days before the scheduled completion date of the process. The frequency of sending the progress to the server is preferably once every three days, more preferably once every two days, and even more preferably every day. As a result, the craftsman in charge of the next process can more easily grasp whether or not the construction of the process in charge can be started as scheduled.

本方法においては、好ましくは、第1工程表に基づく工事が完成した建物の売買契約または賃貸借契約の後に、建物の所有者の端末装置に、工事費用の請求の通知が行われ、及び担当する職人の端末装置に、工事の報酬の支払いの通知が行われる。 In this method, preferably, after the sales contract or lease contract of the building for which the construction based on the first schedule has been completed, the terminal device of the owner of the building is notified of the claim for the construction cost and is in charge of it. The craftsman's terminal device is notified of the payment of the construction fee.

本方法においては、好ましくは、建物の売買契約または賃貸借契約がなされたことがサーバに登録されると、サーバが、サーバの記憶部に登録された工事費用データに基づく工事費用の請求を、建物の所有者の端末装置に通知することができる。 In this method, preferably, when a building sales contract or a lease contract is registered in the server, the server charges the construction cost based on the construction cost data registered in the storage unit of the server. Can notify the owner's terminal device.

本方法においては、好ましくは、建物の所有者からの工事費用が支払われたことがサーバに登録されると、サーバが、担当する職人の端末装置に、工事の報酬の支払いを通知することができる。 In this method, preferably, when the construction cost paid by the building owner is registered in the server, the server notifies the terminal device of the craftsman in charge of the payment of the construction fee. it can.

本方法によれば、工事が完成した建物の売買契約または賃貸借契約がなされた後、工事費用が建物の所有者に請求され得る。また、本方法によれば、建物の所有者から工事費用が支払われた後、担当する職人に工事の報酬の支払いを行うことができる。 According to this method, the construction cost can be charged to the owner of the building after the sales contract or the lease contract of the completed building is made. Further, according to this method, after the construction cost is paid by the owner of the building, the construction fee can be paid to the craftsman in charge.

建物の売買契約がなされた場合は、建物所有者は、売却代金から、請求された工事費用を支払うことができる。建物の賃貸借契約がなされた場合は、建物所有者は、金融機関から融資を受けて、請求された工事費用を支払うことができる。その際、建物所有者は、金融機関に対して、工事が完成した建物に抵当権をつけさせることができるので、建物所有者は融資を受けやすく、経済的リスクが少ない。 If a sales contract is made for the building, the building owner can pay the invoiced construction cost from the sale price. If a building lease agreement is made, the building owner can obtain a loan from a financial institution and pay the invoiced construction cost. At that time, the building owner can make the financial institution mortgage the completed building, so that the building owner can easily obtain a loan and has less economic risk.

本方法で作成する工程表の対象となる工事は、特に制限されないが、改修工事、建て替え工事、取り壊し工事、新築工事等が含まれる。本方法で作成する工程表の対象となる工事は、好ましくは、空き家の改修工事であり、例えば、倉庫を住居用建物に改修する工事が挙げられる。 The work subject to the process chart created by this method is not particularly limited, but includes repair work, rebuilding work, demolition work, new construction work, and the like. The work subject to the process chart created by this method is preferably the work of repairing an unoccupied house, and examples thereof include the work of repairing a warehouse into a residential building.

好ましくは、前記第1工程表を通知するステップは、前記サーバが、前記第1工程表の通知を受けた職人の全員から、前記第1工程表を承諾することを受信すると、前記第1工程表を確定し、前記確定された第1工程表を前記担当する職人の端末装置に通知することを含む。 Preferably, the step of notifying the first process chart is the first step when the server receives the acceptance of the first process chart from all the craftsmen who have received the notification of the first process chart. This includes finalizing the table and notifying the terminal device of the craftsman in charge of the finalized first process chart.

各工程を担当する職人は、前記確定された第1工程表に基づいて建物の工事を行うことができる。第1工程表の通知を受けた職人の全員からの承諾に基づく第1工程表の確定通知を確認してから工事が行われるようにすることによって、各工程を担当する職人は、各工程の工事をより安心して行うことができる。 The craftsman in charge of each process can carry out the construction of the building based on the finalized first process chart. By confirming the confirmation notice of the first process chart based on the consent of all the craftsmen who received the notification of the first process chart, the craftsmen in charge of each process can perform the construction work. The construction can be done with more peace of mind.

本方法は、好ましくは、
(A)前記サーバが前記担当する職人の端末装置に第n工程表を通知した後に前記第n工程表の工程のうち少なくとも一つの工程の進捗が前記第n工程表の計画に対して遅延または早まる場合に、前記進捗が遅延または早まる工程の修正工期データが、前記端末装置から前記サーバに送信され前記サーバの記憶部に登録されること、
(B)前記サーバが、前記登録された修正工期データ及び前記余剰時間データに基づいて、前記進捗が遅延または早まる工程よりも後の工程の工期データを修正するか否かを判断すること、
(C)前記サーバが、前記判断、前記登録された修正工期データ、及び前記余剰時間データに基づいて、前記第n工程表の工程のうち少なくとも一つの工程の修正工期を含む第n+1工程表を作成すること、並びに
(D)前記サーバが、前記工期が修正された工程を担当する職人の端末装置に、前記第n+1工程表を通知すること、
を含む。nは1以上の自然数である。
This method preferably
(A) After the server notifies the terminal device of the craftsman in charge of the nth process chart, the progress of at least one process of the nth process chart is delayed or delayed with respect to the plan of the nth process chart. In the case of accelerating, the correction work period data of the process of delaying or accelerating the progress is transmitted from the terminal device to the server and registered in the storage unit of the server.
(B) The server determines whether or not to correct the construction period data of the process after the process whose progress is delayed or accelerated based on the registered correction construction period data and the surplus time data.
(C) Based on the judgment, the registered correction work period data, and the surplus time data, the server performs an n + 1 process chart including a correction work period of at least one process in the nth process table. To create, and (D) the server notifies the terminal device of the craftsman in charge of the process whose construction period has been modified, the n + 1 process chart.
including. n is a natural number of 1 or more.

サーバが担当する職人の端末装置に第n工程表を通知した後に、悪天候、体調不良等の理由で工程表の工程のうち少なくとも一つの工程の進捗が第n工程表の計画に対して遅延する場合、または予定よりも工事が早く進み工程表の工程のうち少なくとも一つの工程の進捗が第n工程表の計画に対して早まる場合、進捗が遅延または早まる工程の修正工期データが、端末装置からサーバに送信されサーバの記憶部に登録され得る。 After notifying the terminal device of the craftsman in charge of the server of the nth process chart, the progress of at least one process of the process chart is delayed with respect to the plan of the nth process chart due to bad weather, poor physical condition, etc. In the case, or when the construction progresses earlier than planned and the progress of at least one of the processes in the schedule is faster than the plan in the nth schedule, the correction work period data of the process whose progress is delayed or accelerated is obtained from the terminal device. It can be sent to the server and registered in the storage of the server.

図2は、上記好ましい方法における処理の動作の例を示すフローチャートである。 FIG. 2 is a flowchart showing an example of processing operation in the above preferred method.

サーバは、進捗が遅延または早まる工程の修正工期データを登録することができる(S301)。 The server can register the correction construction period data of the process whose progress is delayed or accelerated (S301).

サーバは、登録された修正工期データと余剰時間データとに基づいて、進捗が遅延または早まる工程よりも後の工程の工期データを修正するか否かを判断することができる(S302)。 Based on the registered correction work period data and the surplus time data, the server can determine whether or not to correct the work period data of the process after the process whose progress is delayed or accelerated (S302).

第n+1工程表において、進捗が遅延または早まる工程よりも後の工程の工期データを修正するか否かのサーバの判断は、第n工程表及び第n+1工程表でそれぞれ設定した工程間の日時の間隔に基づいて行うことができる。 In the n + 1 process chart, the server determines whether to correct the construction period data of the process after the process whose progress is delayed or accelerated, by the date and time between the processes set in the nth process table and the n + 1 process table, respectively. It can be done based on the interval.

進捗が遅延する場合に、サーバが、第n+1工程表の各工程間の設定日時に基づき、第n工程表で設けた工程間の間隔で遅延を吸収できないと判断する場合は、進捗が遅延する工程よりも後の工程の工期データを、余剰時間データに基づいて修正することができる。例えば、第n工程表で設定した工程間の間隔が3日であり、且つ第n+1工程表で設定した工程間の間隔を2日とした場合であって、進捗の遅延が1日超の場合は、余剰時間データに基づいて、遅延する工程よりも後の工程の工期データを修正することができる。 When the progress is delayed, if the server determines that the delay cannot be absorbed at the interval between the processes provided in the nth process chart based on the set date and time between each process in the n + 1 process table, the progress is delayed. The construction period data of the process after the process can be corrected based on the surplus time data. For example, when the interval between processes set in the nth process chart is 3 days and the interval between processes set in the n + 1 process table is 2 days, and the delay in progress is more than 1 day. Can correct the construction period data of the process after the delayed process based on the surplus time data.

進捗が遅延する場合に、サーバが、第n+1工程表の各工程間の設定日時に基づき、第n工程表で設けた工程間の間隔で遅延を吸収できると判断する場合は、第n+1工程表において、進捗が遅延する工程よりも後の工程の工期データを修正しなくてもよい。例えば、第n工程表で設定した工程間の間隔が2日であり、且つ第n+1工程表で設定した工程間の間隔を0日とした場合であって、進捗の遅延が2日以内の場合は、遅延する工程よりも後の工程の工期データを修正しなくてもよい。 When the progress is delayed, if the server determines that the delay can be absorbed at the intervals between the processes provided in the nth process chart based on the set date and time between each process in the n + 1 process table, the n + 1 process table In, it is not necessary to revise the construction period data of the process after the process whose progress is delayed. For example, when the interval between processes set in the nth process chart is 2 days and the interval between processes set in the n + 1 process table is 0 days, and the progress delay is within 2 days. Does not have to correct the construction period data of the process after the delayed process.

進捗が早まる場合は、進捗が早まる工程よりも後の工程の工期データを修正しなくてもよい。 When the progress is accelerated, it is not necessary to revise the construction period data of the process after the process in which the progress is accelerated.

進捗が早まる場合であって、第n+1工程表の工程間の間隔を所定の範囲内に設定する場合は、サーバが、工程間の間隔が所定の範囲内になるように、進捗が早まる工程よりも後の工程の工期データを、余剰時間データに基づいて修正することができる。サーバは、余剰時間データに基づいて、工程間の間隔を所定の範囲内にできる限り近づけることができる。 When the progress is accelerated and the interval between processes in the n + 1 process chart is set within a predetermined range, the server performs the process faster than the process so that the interval between processes is within the predetermined range. The construction period data of the subsequent process can be corrected based on the surplus time data. Based on the surplus time data, the server can bring the intervals between processes as close as possible within a predetermined range.

第n+1工程表を作成する際、各工程の間は第n工程表と同じでもよく、変えてもよい。各工程の間隔はなくてもよいが、好ましくは1日以上、より好ましくは2日以上の間を設ける。これにより、工事の進捗がさらに遅延または早まる場合でも、工程表を見直さないですむ場合がある。 When creating the n + 1 process chart, the process may be the same as or changed between the steps. The interval between each step may not be necessary, but it is preferably provided for one day or more, more preferably for two days or more. As a result, even if the progress of the construction is further delayed or accelerated, it may not be necessary to review the schedule.

サーバは、前記判断、前記登録された修正工期データ、及び前記余剰時間データに基づいて、第n工程表の工程のうち少なくとも一つの工程の修正工期を含む第n+1工程表を作成することができる(S303、S305)。 Based on the judgment, the registered correction work period data, and the surplus time data, the server can create an n + 1 process chart including a correction work period of at least one process in the nth process table. (S303, S305).

サーバは、進捗が遅延または早まる工程よりも後の工程の工期データを修正しないと判断した場合は、前記登録された修正工期データ及び前記余剰時間データに基づいて、進捗が遅延または早まる工程のみの修正工期を含む第n+1工程表を作成することができる(S305)。 If the server determines that it does not modify the construction period data of the process after the process whose progress is delayed or accelerated, only the process whose progress is delayed or accelerated based on the registered correction period data and the surplus time data. The n + 1 process chart including the correction work period can be created (S305).

サーバは、進捗が遅延または早まる工程よりも後の工程の工期データを修正すると判断した場合は、前記登録された修正工期データ及び前記余剰時間データに基づいて、進捗が遅延または早まる工程とそれよりも後の工程のうち少なくとも一つの工程との修正工期を含む第n+1工程表を作成することができる(S303)。 When the server determines to correct the construction period data of the process after the process whose progress is delayed or accelerated, the process whose progress is delayed or accelerated based on the registered correction period data and the surplus time data and the process which progresses thereafter. It is possible to create an n + 1 process chart including a correction work period with at least one of the subsequent processes (S303).

サーバは、修正工期を含む第n+1工程表を作成する際に、各工程を担当する職人の記憶部に登録済みの余剰時間データが不十分であり第n+1工程表を作成できないと判断する場合、第n工程表の工程を担当する職人の端末装置に余剰時間データの修正を要求する通知を行うことができる。修正余剰時間データが端末装置から送信されサーバの記憶部に登録されると、サーバは、登録された修正余剰時間データに基づいて、第n+1工程表を作成することができる。 When the server creates the n + 1 process chart including the correction work period, if it determines that the surplus time data registered in the memory of the craftsman in charge of each process is insufficient and the n + 1 process chart cannot be created. It is possible to notify the terminal device of the craftsman in charge of the process of the nth process chart to request the correction of the surplus time data. When the modified surplus time data is transmitted from the terminal device and registered in the storage unit of the server, the server can create the n + 1th process chart based on the registered modified surplus time data.

サーバはまた、修正工期を含む第n+1工程表を作成する際に、各工程を担当する職人の記憶部に登録済みの余剰時間データが不十分であり第n+1工程表を作成できないと判断する場合、第n工程表の当該工程を担当する職人以外のサーバに登録された別の職人に、余剰時間データの送信及び登録を要求する通知を行うことができる。別の職人の登録された修正余剰時間データに基づいて、第n+1工程表を作成することができる。この場合、サーバは、担当する職人を変更することを、第n工程表の当該工程を担当していた職人及び第n+1工程表の当該工程を担当する職人の端末装置に、通知することができる。 When the server also determines that the surplus time data registered in the memory of the craftsman in charge of each process is insufficient when creating the n + 1 process chart including the correction work period, the n + 1 process chart cannot be created. , It is possible to notify another craftsman registered in the server other than the craftsman in charge of the process in the nth process chart to transmit the surplus time data and request registration. The n + 1 process chart can be created based on the corrected surplus time data registered by another craftsman. In this case, the server can notify the terminal device of the craftsman who was in charge of the process in the nth process chart and the craftsman in charge of the process in the n + 1 process chart to change the craftsman in charge. ..

サーバは、工期が修正された工程を担当する職人の端末装置に、第n+1工程表を通知することができる(S304)。これにより、職人は、担当する工程の工事を行うことができる。 The server can notify the terminal device of the craftsman in charge of the process whose construction period has been modified to the n + 1 process chart (S304). As a result, the craftsman can carry out the construction of the process in charge.

nの上限は特に限定されないが、例えば10、20、または30であることができる。 The upper limit of n is not particularly limited, but may be 10, 20, or 30, for example.

前記(A)〜(D)を1回以上繰り返してもよい。すなわち、前記(A)〜(D)を2回以上行ってもよい。 The above (A) to (D) may be repeated once or more. That is, the above (A) to (D) may be performed twice or more.

職人は、悪天候等の外部要因で担当する工程の工事を行うことができずに余剰時間が新たに生じることがあり得る。例えば、悪天候等の外部要因で進捗が遅延する工程を担当する職人には、新たな余剰時間が発生し得る。このような外部要因で担当する工程の工事ができずに新たな余剰時間が発生した場合、その工程の修正工期データとともに発生した修正余剰時間データがサーバの記憶部に登録され得る。 The craftsman may not be able to carry out the construction of the process he is in charge of due to external factors such as bad weather, and extra time may be newly generated. For example, a new surplus time may occur for a craftsman who is in charge of a process whose progress is delayed due to external factors such as bad weather. When a new surplus time is generated because the work of the process in charge cannot be performed due to such an external factor, the correction surplus time data generated together with the correction work period data of the process can be registered in the storage unit of the server.

好ましくは、サーバは、記憶部に登録された職人の修正余剰時間データに基づいて、その職人の工種に適合し且つ停止している他の現場の工程の工事があるか否かを判断し、当該工事があると判断した場合は、前記職人の端末装置に前記他の現場の工事の工程表を通知する。通知された他の現場の工程表に基づいて、職人は前記他の現場の工事を行うことができる。 Preferably, the server determines, based on the craftsman's modified surplus time data registered in the storage unit, whether there is work in another field process that is suitable for the craftsman's work type and is stopped. If it is determined that there is such work, the terminal device of the craftsman is notified of the work schedule of the work at the other site. Based on the notified schedule of other sites, the craftsman can perform the construction of the other sites.

サーバからの前記他の現場の工事の工程表の通知に対し、端末装置からサーバに承諾または拒否の返答が送信され得る。サーバは、前記他の現場の工事の工程表を承諾することを受信すると、前記他の現場の工程表が確定されたことを前記他の現場の工程表の工程を担当する職人に通知することができる。 In response to the notification of the construction schedule of the other site from the server, the terminal device may send a response of acceptance or refusal to the server. When the server receives the acceptance of the construction schedule of the other site, the server notifies the craftsman in charge of the process of the schedule of the other site that the schedule of the construction of the other site has been finalized. Can be done.

本方法で作成する工程表の対象となる工事は、同時期に1つでもよいが、好ましくは同時期に複数である。すなわち、本方法で作成する工程表は、並行して行われる複数の工事に適用することができる。並行して行われる複数の工事を行うことにより、悪天候等によりある現場の工事を進めることができない場合に、他の現場の工事を行うことができるので、職人の余剰時間を有効活用することができる。 The number of works subject to the process chart created by this method may be one at the same time, but preferably a plurality at the same time. That is, the process chart created by this method can be applied to a plurality of works performed in parallel. By performing multiple works performed in parallel, if the work at one site cannot proceed due to bad weather, etc., the work at another site can be performed, so the surplus time of the craftsman can be effectively utilized. it can.

本方法は、好ましくは、
(a)前記サーバが前記担当する職人の端末装置に前記第n工程表を通知した後に、前記第n工程表に含まれる職人のうち少なくとも一人の前記記憶部に登録された余剰時間データが変更され登録された場合に、前記サーバが、前記変更された余剰時間データを含む前記記憶部に登録された余剰時間データに基づいて、前記余剰時間データが変更された職人が担当する工程及びそれよりも後の工程のうち少なくとも一つの工程の工期を修正する必要があるかどうかを判断すること、
(b)前記サーバが、前記余剰時間データが変更された職人が担当する工程及びそれよりも後の工程のうち少なくとも一つの工程の工期を修正する必要があると判断した場合に、前記変更された余剰時間データを含む前記記憶部に登録された余剰時間データに基づいて、前記少なくとも一つの工程の修正工期を含む第n+1工程表、前記少なくとも一つの工程を担当する職人が変更された第n+1工程表、またはそれらの組み合わせを作成すること、並びに
(c)前記サーバが、前記工期が修正された工程を担当する職人、前記担当が変更され第n+1工程表の工程を担当することになった職人、またはそれらの組み合わせの端末装置に、前記第n+1工程表を通知すること、
を含む。nは1以上の自然数である。
This method preferably
(A) After the server notifies the terminal device of the craftsman in charge of the nth process chart, the surplus time data registered in the storage unit of at least one of the craftsmen included in the nth process chart is changed. When the surplus time data is registered, the server is in charge of the process in which the craftsman whose surplus time data is changed based on the surplus time data registered in the storage unit including the changed surplus time data, and more. To determine if it is necessary to modify the construction period of at least one of the subsequent processes,
(B) When the server determines that it is necessary to correct the construction period of at least one of the process in charge of the process in which the surplus time data is changed and the process after that, the change is made. Based on the surplus time data registered in the storage unit including the surplus time data, the n + 1 process chart including the correction work period of the at least one process, and the n + 1 in which the craftsman in charge of the at least one process is changed. Creating a process chart or a combination thereof, and (c) the server will be in charge of the process of the n + 1 process chart with the craftsman in charge of the process whose construction period has been modified and the person in charge changed. Notifying the craftsman or the terminal device of the combination thereof of the n + 1 process chart,
including. n is a natural number of 1 or more.

第n工程表が通知された後に、工程を担当する職人の余剰時間が変わることがあり得る。第n工程表が通知される前または工程表が作成される前に、工程を担当する職人の余剰時間は変わっていたが、変更された余剰時間データがサーバの記憶部に登録されていないこともあり得る。 After the nth process chart is notified, the surplus time of the craftsman in charge of the process may change. The surplus time of the craftsman in charge of the process has changed before the nth process chart is notified or before the process chart is created, but the changed surplus time data is not registered in the storage unit of the server. There can also be.

このように、第n工程表が通知された後に第n工程表に含まれる工程を担当する職人の余剰時間が変わる場合、または第n工程表が通知される前に余剰時間が変わっていたが、変更された余剰時間データがサーバに登録される前に第n工程表が通知された場合に、変更された余剰時間データがサーバに送信されサーバの記憶部に登録されると、サーバは、変更された余剰時間データを含む記憶部に登録された余剰時間データに基づいて、第n工程表の工程の工期を修正する必要があるかどうかを判断することができる。 In this way, when the surplus time of the craftsman in charge of the process included in the nth process chart changes after the nth process chart is notified, or when the surplus time changes before the nth process chart is notified. If the nth process chart is notified before the changed surplus time data is registered in the server, and the changed surplus time data is transmitted to the server and registered in the storage part of the server, the server Based on the surplus time data registered in the storage unit including the changed surplus time data, it can be determined whether or not it is necessary to modify the construction period of the process in the nth process chart.

図3は、上記好ましい方法における処理の動作の例を示すフローチャートである。 FIG. 3 is a flowchart showing an example of processing operation in the above preferred method.

サーバは、記憶部に登録された余剰時間データを変更し登録することができる(S501)。 The server can change and register the surplus time data registered in the storage unit (S501).

サーバは、変更された余剰時間データを含む記憶部に登録された余剰時間データに基づいて、第n工程表の工程の工期を修正する必要があるかどうかを判断することができる(S502)。 The server can determine whether or not it is necessary to modify the construction period of the process in the nth process chart based on the surplus time data registered in the storage unit including the changed surplus time data (S502).

サーバは、余剰時間データの変更が工程の工期に影響すると判断した場合は、影響される工程の工期を修正して第n+1工程表を作成するか、または影響される工程を担当する職人を変更して第n+1工程表を作成するか、またはそれらの組み合わせの第n+1工程表を作成することができる(S503)。 If the server determines that the change in surplus time data affects the construction period of the process, it corrects the construction period of the affected process to create the n + 1 process chart, or changes the craftsman in charge of the affected process. The n + 1 process chart can be created, or the n + 1 process chart of a combination thereof can be created (S503).

サーバは、第n工程表において、工程の工期に割り当てられていた余剰時間データが変更され、工期に割り当てる余剰時間が不足すると判断した場合、登録された余剰時間に基づいて、工期を延長した第n+1工程表を作成することができる。 When the server determines in the nth process chart that the surplus time data assigned to the construction period of the process is changed and the surplus time allocated to the construction period is insufficient, the server extends the construction period based on the registered surplus time. An n + 1 process chart can be created.

サーバはまた、第n工程表において、工程の工期に割り当てられていた余剰時間データが変更され、工期に割り当てる余剰時間が不足すると判断した場合、第n工程表の当該工程を担当する職人以外のサーバに登録された別の職人の余剰時間データを割り当てることができるか否かを判断し、割り当て可能と判断した場合は、当該工程を担当する職人を変更して、第n+1工程表を作成することができる。この場合、サーバは、担当する職人を変更することを、第n工程表の当該工程を担当していた職人及び第n+1工程表の当該工程を担当する職人の端末装置に、通知することができる。 If the server determines that the surplus time data assigned to the construction period of the process is changed in the nth process chart and the surplus time allocated to the construction period is insufficient, the server other than the craftsman in charge of the process in the nth process chart. Judge whether the surplus time data of another craftsman registered in the server can be assigned, and if it is judged that it can be assigned, change the craftsman in charge of the process and create the n + 1 process chart. be able to. In this case, the server can notify the terminal device of the craftsman who was in charge of the process in the nth process chart and the craftsman in charge of the process in the n + 1 process chart to change the craftsman in charge. ..

サーバは、余剰時間データの変更が工期に影響しなくても、設定した工程間の間隔に影響すると判断した場合は、第n工程表の工程の工期を修正することができる。 If the server determines that the change in the surplus time data does not affect the construction period but affects the interval between the set processes, the server can modify the construction period of the process in the nth process chart.

サーバは、好ましくは、第n工程表で設定した工程間の日時の間隔を変更する必要性の有無で、第n工程表の工程の工期を修正する必要があるかどうかを判断する。すなわち、当初作成した第n工程表で設定した工程間の日時の間隔を変更する必要がない場合は、余剰時間データが変更された職人が担当する工程よりも後の工程の工期を修正しない。当初作成した第n工程表で設定した工程間の日時の間隔を変更する必要がある場合は、当初作成した第n工程表で設定した工程間の日時を維持するように、余剰時間データが変更された職人が担当する工程よりも後の工程の工期を修正する。 The server preferably determines whether or not it is necessary to modify the construction period of the process of the nth process chart depending on whether or not it is necessary to change the date and time interval between the processes set in the nth process chart. That is, when it is not necessary to change the date and time interval between the processes set in the nth process chart initially created, the construction period of the process after the process in charge of the craftsman whose surplus time data has been changed is not modified. If it is necessary to change the date and time interval between the processes set in the originally created nth process chart, the surplus time data is changed so as to maintain the date and time between the processes set in the originally created nth process table. Correct the construction period of the process after the process that the craftsman is in charge of.

別法では、好ましくは、第n工程表で設定した工程間の日時の間隔の範囲内で吸収可能かどうかで判断する。すなわち、当初作成した第n工程表で設定した工程間の日時が例えば2日の場合に、余剰時間データが変更された職人が担当する工程の工期の延長が2日以内の場合は、余剰時間データが変更された職人が担当する工程よりも後の工程の工期を修正せず、余剰時間データが変更された職人が担当する工程の工期の延長が2日超の場合は、余剰時間データが変更された職人が担当する工程よりも後の工程の工期を修正することができる。 In another method, it is preferably determined whether or not absorption is possible within the range of the date and time interval between the processes set in the nth process chart. That is, if the date and time between the processes set in the nth process chart initially created is, for example, 2 days, and the extension of the process period of the process in charge of the craftsman whose surplus time data has been changed is within 2 days, the surplus time If the construction period of the process after the process in charge of the craftsman whose data has been changed is not modified and the extension of the construction period of the process in charge of the process in charge of the craftsman whose data has been changed is more than 2 days, the surplus time data will be displayed. It is possible to modify the construction period of the process after the process in charge of the changed craftsman.

第n工程表で設定した工程間の日時の間隔と、第n+1工程表で設定する工程間の日時の間隔は、異なるように設定してもよい。各工程間の間隔は、それぞれ異なってもよい。 The date and time interval between the processes set in the nth process chart and the date and time interval between the processes set in the n + 1 process table may be set differently. The intervals between the steps may be different.

サーバは、工期が修正された工程を担当する職人、担当が変更され第n+1工程表の工程を担当することになった職人、またはそれらの組み合わせの端末装置に、第n+1工程表を通知することができる(S504)。これにより、職人は、担当する工程の工事を行うことができる。 The server notifies the craftsman in charge of the process whose construction period has been modified, the craftsman whose charge has been changed to be in charge of the process in the n + 1 process chart, or a combination of these terminal devices in the n + 1 process chart. Can be done (S504). As a result, the craftsman can carry out the construction of the process in charge.

nの上限は特に限定されないが、例えば10、20、または30であることができる。 The upper limit of n is not particularly limited, but may be 10, 20, or 30, for example.

前記(a)〜(c)を1回以上繰り返してもよい。すなわち、前記(a)〜(c)を2回以上行ってもよい。 The above (a) to (c) may be repeated once or more. That is, the above (a) to (c) may be performed twice or more.

好ましくは、本方法は、前記サーバが、前記第n+1工程表の工程のうち少なくとも一つの工程の工期が前記第n工程表の前記少なくとも一つの工程の工期と比べて所定の期間を超えて遅れると判断する場合であって、前記登録された複数の職人のデータ及び前記登録された余剰時間データに基づいて、前記工期が遅れる工程を担当する職人を別の職人に変更すると前記第n+1工程表の前記少なくとも一つの工程の工期を所定の期間早められると判断する場合に、前記担当する職人を前記別の職人に変更して前記第n+1工程表を作成すること、並びに
前記サーバが、前記別の職人の端末装置に、前記第n+1工程表を通知すること、
を含む。
Preferably, in this method, the server delays the construction period of at least one step of the steps in the n + 1 schedule by more than a predetermined period as compared with the construction period of at least one step in the nth schedule. If the craftsman in charge of the process whose construction period is delayed is changed to another craftsman based on the data of the plurality of registered craftsmen and the registered surplus time data, the n + 1 process chart When it is determined that the construction period of at least one process of the above can be advanced by a predetermined period, the craftsman in charge is changed to the other craftsman to create the n + 1 process chart, and the server is the same. Notifying the terminal device of the craftsman of the n + 1 process chart,
including.

図4は、上記好ましい方法における処理の動作の例を示すフローチャートである。 FIG. 4 is a flowchart showing an example of processing operation in the above preferred method.

サーバは、第n+1工程表の工程のうち少なくとも一つの工程の工期が第n工程表の前記少なくとも一つの工程の工期と比べて所定の期間を超えて遅れるか否かを判断することができる。(S701)。 The server can determine whether or not the construction period of at least one of the steps in the n + 1 schedule is delayed by more than a predetermined period as compared with the construction period of at least one step in the nth schedule. (S701).

サーバは、上記所定の期間を超えて遅れると判断した場合に、登録された複数の職人のデータ及び登録された余剰時間データに基づいて、工期が遅れる工程を担当する職人を別の職人に変更すると第n+1工程表の前記少なくとも一つの工程の工期を所定の期間早められるか否かを判断することができる(S702)。 When the server determines that the delay exceeds the above-mentioned predetermined period, the server changes the craftsman in charge of the process for which the construction period is delayed to another craftsman based on the registered data of multiple craftsmen and the registered surplus time data. Then, it can be determined whether or not the construction period of at least one process in the n + 1 process chart can be advanced by a predetermined period (S702).

サーバは、上記所定の期間を超えて遅れるが、上記職人を変更することにより第n+1工程表の前記少なくとも一つの工程の工期を所定の期間早められると判断した場合、担当する職人を別の職人に変更して第n+1工程表を作成することができる(S703)。 The server is delayed beyond the predetermined period, but if it is determined that the construction period of at least one process in the n + 1 process chart can be advanced by a predetermined period by changing the craftsman, the craftsman in charge is changed to another craftsman. The n + 1 process chart can be created by changing to (S703).

サーバは、担当する職人を別の職人に変更して第n+1工程表を作成すると、前記別の職人の端末装置に、第n+1工程表を通知することができる(S704)。 When the server changes the craftsman in charge to another craftsman and creates the n + 1th process chart, the server can notify the terminal device of the other craftsman of the n + 1 process chart (S704).

上記所定の期間とは、特に限定されるものではないが、例えば3日以上、1週間以上、2週間以上、または1ヶ月以上である。工期の遅れに関する所定の期間と、工期を早めることに関する所定の期間とは、同じでもよく異なってもよい。 The predetermined period is not particularly limited, but is, for example, 3 days or more, 1 week or more, 2 weeks or more, or 1 month or more. The predetermined period for delaying the construction period and the predetermined period for advancing the construction period may be the same or different.

サーバは、別の職人の端末装置に第n+1工程表を通知する際、第n工程表の工期が遅れる工程を担当する職人の端末装置にも、第n+1工程表または担当が変わったことを通知してもよい。 When the server notifies the terminal device of another craftsman of the n + 1 process chart, it also notifies the terminal device of the craftsman who is in charge of the process whose construction period of the nth process chart is delayed, that the n + 1 process table or the person in charge has changed. You may.

好ましくは、本方法において、前記第n+1工程表を通知することが、前記サーバが、前記第n+1工程表の通知を受けた職人の全員から、前記第n+1工程表を承諾することを受信すると、前記第n+1工程表を確定し、前記確定された第n+1工程表を、前記承諾した職人の端末装置に通知することを含む。 Preferably, in the present method, notifying the n + 1 process chart means that the server receives acceptance of the n + 1 process chart from all the craftsmen who have received the notification of the n + 1 process chart. This includes finalizing the n + 1 process chart and notifying the terminal device of the approved craftsman of the finalized n + 1 process chart.

第n+1工程表の通知を受けた職人が承諾したことを確認して、担当する職人に第n+1工程表が確定したことを通知してから工事を行うことによって、各工程を担当する職人は、各工程の工事をより安心して行うことができる。 By confirming that the craftsman who received the notification of the n + 1 process chart has consented and notifying the craftsman in charge that the n + 1 process chart has been finalized, the craftsman in charge of each process can perform the construction. The construction of each process can be performed with greater peace of mind.

第n+1工程表の通知を受けた職人が第n+1工程表を承諾できない場合は、承諾できないことが端末装置からサーバに送信され、且つ登録された余剰時間データが修正され得る。 If the craftsman who has received the notification of the n + 1 process chart cannot accept the n + 1 process chart, the terminal device transmits to the server that he / she cannot accept the n + 1 process chart, and the registered surplus time data can be corrected.

本方法においては、好ましくは、工程表をm個の工程に分けて、職人もm個のグループに分ける。これにより、m個の現場の工事を並行して行うことができる。mは1以上の自然数である。これにより、職人の余剰時間をより効率よく工事に活用することができる。mの上限は、登録する職人の数に応じて大きくすることができ、特に限定されるものではないが、例えば10、20、または30であることができる。例えば、工程表を前工程、中工程、及び後工程の3つの工程に分けて、職人を3つのグループに分けることにより、3つの現場の工事を並行して行うことができる。 In this method, preferably, the process chart is divided into m processes, and the craftsmen are also divided into m groups. As a result, m on-site construction can be carried out in parallel. m is a natural number of 1 or more. As a result, the surplus time of the craftsman can be utilized more efficiently for construction. The upper limit of m can be increased according to the number of craftsmen to be registered, and is not particularly limited, but can be, for example, 10, 20, or 30. For example, by dividing the process chart into three processes, a pre-process, an intermediate process, and a post-process, and dividing the craftsmen into three groups, the construction work at the three sites can be performed in parallel.

例えば、工程表を前工程、中工程、及び後工程の3つの工程に分ける場合、職人も、解体〜大工等の前工程グループ、ボード設置〜設備設置等の中工程グループ、及び内装等の後工程グループの3つのグループに分ける。その場合、前工程グループが、第1の現場の前工程の工事を完了した後、中工程グループが第1の現場の中工程の工事を開始し、前工程グループは第2の現場の前工程の工事を開始することができる。前工程グループが第2の現場の前工程の工事を完了し、中工程グループが第1の現場の中工程の工事を完了した後、後工程グループが第1の現場の後工程の工事を開始し、中工程グループは第2の現場の中工程の工事を開始し、前工程グループは第3の現場の前工程の工事を開始することができる。このようにして、職人の余剰時間をより効率よく工事に活用することができる。 For example, when the process chart is divided into three processes, a pre-process, an intermediate process, and a post-process, the craftsman also has a pre-process group such as dismantling-carpenter, an intermediate process group such as board installation-equipment installation, and after interior decoration. Divide into three groups of process groups. In that case, after the front-end process group completes the work of the front-end process of the first site, the middle-process group starts the work of the middle-process of the first site, and the front-end process group is the front-end process of the second site. Construction can be started. After the front-end process group completes the work of the front-end process at the second site and the middle-end process group completes the work of the middle-end process at the first site, the back-end process group starts the work of the back-end process at the first site. However, the middle process group can start the construction of the middle process at the second site, and the front process group can start the construction of the front process at the third site. In this way, the surplus time of the craftsman can be utilized more efficiently for construction.

本方法においては、好ましくは、工事対象の建物の事前の診断結果をサーバの記憶部に登録して、サーバが、建物の改修工事を行うか、解体して新築するか等を判断することができる。診断項目としては、建物の躯体が著しく傷んでいないかどうか、建物内のインフラ設備が古いために現行のインフラ設備と合わせることが難しいかどうか等の項目が挙げられる。サーバは、サーバの記憶部にあらかじめ登録された躯体強度、インフラ設備を満たすかどうか等の診断項目を満たすかどうかを判断して、工事の種類を決定することができる。 In this method, it is preferable that the preliminary diagnosis result of the building to be constructed is registered in the storage unit of the server, and the server determines whether the building is to be repaired or dismantled and newly constructed. it can. Diagnostic items include whether the building's skeleton is not significantly damaged and whether it is difficult to match it with the current infrastructure because the infrastructure inside the building is old. The server can determine the type of construction by determining whether or not the diagnostic items such as the skeleton strength registered in advance in the storage unit of the server and whether or not the infrastructure equipment is satisfied are satisfied.

(実施例1)
図5に、本方法の実施形態の一例を示す。図5は、本方法で作成した戸建て住宅の改修工事を行うための第1工程表の一例である。図5の第1工程表には、解体、電気設備工事、給排水設備工事、大工造作工事、内装工事、住設機器工事、及び家具建具工事、並びに最終工程として、電気設備工事、給排水設備工事、及び処分の各工程、それぞれの工程を担当する職人A、B、C、D、E、F、及びG、並びにそれぞれの工程の工期が示されている。
(Example 1)
FIG. 5 shows an example of an embodiment of this method. FIG. 5 is an example of the first process chart for carrying out the repair work of the detached house created by this method. In the first process chart of FIG. 5, dismantling, electrical equipment construction, water supply and drainage equipment construction, carpentry construction work, interior work, housing equipment construction, furniture fittings construction, and as the final process, electrical equipment construction, water supply and drainage equipment construction, And each process of disposal, craftsmen A, B, C, D, E, F, and G in charge of each process, and the construction period of each process are shown.

それぞれの工程の工期は、開始日及び終了日の日付と日付に関連付けて表示された網掛け部分で示されている。それぞれの工程の工期の前、後、または両方に予備日が設けられており、星印で示されている。 The construction period of each process is indicated by the date of the start date and the end date and the shaded portion displayed in association with the date. Preliminary days are provided before, after, or both of the construction periods for each process and are indicated by asterisks.

第1工程表は、記憶部に登録された職人のデータ、職人毎の余剰時間データ、並びに複数の工程、複数の工程の順番、複数の工程の各工程の所要日数、及び複数の工程のそれぞれで使用する材料を含む工事内容データに基づいて、サーバにより作成された。職人の余剰時間を工期に割り当てているので、従来の工事の4倍の工期で作成されている。 The first process chart includes the data of craftsmen registered in the storage unit, the surplus time data for each craftsman, and the plurality of processes, the order of multiple processes, the number of days required for each process of multiple processes, and each of the plurality of processes. Created by the server based on the construction content data including the materials used in. Since the surplus time of the craftsmen is allocated to the construction period, it is created in four times the construction period of the conventional construction.

(実施例2)
図6及び図7に、本方法の好ましい実施形態の一例を示す。図6は、図5の第1工程表における大工造作工事工程の工事の進捗が遅延したため、工期の終了日の日付欄のデータを2019年4月30日から2019年5月2日に変更し、サーバに登録したときの例である。
(Example 2)
6 and 7 show an example of a preferred embodiment of the method. In FIG. 6, the data in the date column of the end date of the construction period was changed from April 30, 2019 to May 2, 2019 because the progress of the carpentry construction work process in the first process chart of FIG. 5 was delayed. , This is an example when registered in the server.

図7は、図6の大工造作工事工程の終了日変更のサーバへの登録に伴い、サーバが、登録された修正工期データに基づいて、大工造作工事工程よりも後の工程の工期データを修正すると判断し、登録された修正工期データ及び職人毎の余剰時間データに基づいて、大工造作工事工程の工期を2日延長し、その後の工程の工期を2日ずらして作成した第2工程表である。追加された工程日には「1」が表示されている。第1工程表と第2工程表とでは、両方とも工程間の間隔を2日設けており、工期の変更とともに予備日も更新されている。 In FIG. 7, the server corrects the construction period data of the process after the carpentry construction process based on the registered correction construction period data in accordance with the registration of the end date change of the carpentry construction process of FIG. 6 to the server. Based on the registered correction construction period data and surplus time data for each craftsman, the construction period of the carpentry construction process was extended by 2 days, and the construction period of the subsequent process was shifted by 2 days in the second process chart. is there. "1" is displayed on the added process date. In both the first process chart and the second process chart, the interval between processes is set to 2 days, and the preliminary date is updated along with the change of the construction period.

(実施例3)
図8及び図9に、本方法の好ましい実施形態の一例を示す。図8は、図7の第2工程表の通知後に、第2工程表の職人Fの住設機器工事工程に工期に割り当てられていた記憶部に登録された余剰時間データのうち、2019年5月15日に半日設けられていた余剰時間が削除され記憶部に登録されたことにより、職人Fが担当する住設機器工事工程の工期の終了日の日付欄のデータが2019年5月15日から2019年5月17日に変更され、サーバに登録されたときの例である。
(Example 3)
8 and 9 show an example of a preferred embodiment of the method. FIG. 8 shows the surplus time data registered in the storage unit assigned to the construction period of the housing equipment construction process of the craftsman F in the second process chart after the notification of the second process chart in FIG. Since the surplus time set for half a day on the 15th of March was deleted and registered in the storage section, the data in the date column of the end date of the construction period of the housing equipment construction process in charge of craftsman F is May 15, 2019. This is an example when it was changed from May 17, 2019 and registered in the server.

図9は、図8の住設機器工事工程の工期終了日の変更がサーバへ登録されたことに伴い、サーバが、登録された修正工期データに基づいて、住設機器工事工程よりも後の工程の工期データを修正すると判断し、登録された修正工期データ及び職人毎の余剰時間データに基づいて、住設機器工事工程の工期を2日延長し、その後の工程の工期を2日ずらして作成した第3工程表である。追加された工程日には「2」が表示されている。第2工程表と第3工程表とでは、両方とも工程間の間隔を2日設けており、工期の変更とともに予備日も更新されている。 FIG. 9 shows that the server is after the housing equipment construction process based on the registered correction construction period data due to the change of the construction period end date of the housing equipment construction process of FIG. 8 being registered in the server. Judging that the construction period data of the process will be revised, based on the registered correction construction period data and surplus time data for each craftsman, the construction period of the housing equipment construction process will be extended by 2 days, and the construction period of the subsequent process will be shifted by 2 days. This is the created third process chart. "2" is displayed on the added process date. In both the second process chart and the third process chart, the interval between processes is set to two days, and the preliminary date is updated along with the change of the construction period.

(実施例4)
図10及び図11に、本方法の好ましい実施形態の一例を示す。図10は、図5の第1工程表における大工造作工事工程の工事の進捗が早まったため、工期の終了日の日付欄のデータを2019年4月30日から2019年4月25日に変更し、サーバに登録したときの例である。
(Example 4)
10 and 11 show an example of a preferred embodiment of the method. In FIG. 10, the data in the date column of the end date of the construction period was changed from April 30, 2019 to April 25, 2019 because the progress of the carpentry construction work process in the first process chart of FIG. 5 was accelerated. , This is an example when registered in the server.

図11は、図10の大工造作工事工程の終了日変更のサーバへの登録に伴い、サーバが、登録された修正工期データに基づいて、大工造作工事工程よりも後の工程の工期データを修正すると判断し、登録された修正工期データ及び職人毎の余剰時間データに基づいて、大工造作工事工程の工期を5日短縮し、その後の工程の工期を5日ずらして作成した第2工程表である。第1工程表と第2工程表とでは、両方とも工程間の間隔を2日設けており、工期の変更とともに予備日も更新されている。 In FIG. 11, with the registration of the end date change of the carpentry work process of FIG. 10 to the server, the server corrects the work period data of the process after the carpentry work process based on the registered correction work period data. Based on the registered correction construction period data and surplus time data for each craftsman, the construction period of the carpentry construction process was shortened by 5 days, and the construction period of the subsequent process was shifted by 5 days in the second process chart. is there. In both the first process chart and the second process chart, the interval between processes is set to 2 days, and the preliminary date is updated along with the change of the construction period.

(比較例1)
図12は、本方法を用いずに作成した従来の工程表である。工期は短いが、職人の余剰時間を活用せずに各工程の工期を設定している。
(Comparative Example 1)
FIG. 12 is a conventional process chart created without using this method. Although the construction period is short, the construction period for each process is set without utilizing the surplus time of the craftsmen.

Claims (8)

建物の工事の工程表の作成方法であって、
サーバに登録された複数の職人が所有する材料のデータが、共有材料データとして、端末装置から前記サーバに送信され前記サーバの記憶部に登録されるステップと、
前記複数の職人それぞれの余剰時間データが、端末装置から前記サーバに送信され前記サーバの記憶部に登録されるステップと、
前記建物の所有者の依頼内容及び前記登録された共有材料データに基づいて、工事内容データが作成され前記サーバの記憶部に登録されるステップであって、前記工事内容データは、複数の工程、前記複数の工程の順番、前記複数の工程の各工程の所要日数、及び前記複数の工程のそれぞれで使用する材料を含む、ステップと、
前記サーバが、前記記憶部に登録された前記職人のデータ、前記余剰時間データ、及び前記工事内容データに基づいて、前記複数の工程、前記複数の工程それぞれを担当する職人、及び前記複数の工程それぞれの工期を含む第1工程表を作成するステップと、
前記サーバが、前記担当する職人の端末装置に、前記第1工程表を通知するステップと、
を含む、工程表の作成方法。
It is a method of creating a process chart for building construction,
A step in which material data owned by a plurality of craftsmen registered in a server is transmitted from a terminal device to the server as shared material data and registered in a storage unit of the server.
A step in which the surplus time data of each of the plurality of craftsmen is transmitted from the terminal device to the server and registered in the storage unit of the server.
It is a step in which construction content data is created based on the request content of the building owner and the registered shared material data and registered in the storage unit of the server, and the construction content data is a plurality of processes. A step that includes the order of the plurality of steps, the number of days required for each step of the plurality of steps, and the material used in each of the plurality of steps.
Based on the data of the craftsman, the surplus time data, and the construction content data registered in the storage unit, the server is in charge of the plurality of processes, the craftsman in charge of each of the plurality of processes, and the plurality of processes. Steps to create the first process chart including each construction period,
A step in which the server notifies the terminal device of the craftsman in charge of the first process chart, and
How to create a process chart, including.
前記第1工程表を通知するステップが、前記サーバが、前記第1工程表の通知を受けた職人の全員から、前記第1工程表を承諾することを受信すると、前記第1工程表を確定し、前記確定された第1工程表を前記担当する職人の端末装置に通知することを含む、請求項1に記載の工程表の作成方法。 When the step of notifying the first process chart receives that the server accepts the first process chart from all the craftsmen who have received the notification of the first process chart, the first process chart is confirmed. The method for creating a process chart according to claim 1, further comprising notifying the terminal device of the craftsman in charge of the finalized first process chart. (A)前記サーバが前記担当する職人の端末装置に第n工程表を通知した後に前記第n工程表の工程のうち少なくとも一つの工程の進捗が前記第n工程表の計画に対して遅延または早まる場合に、前記進捗が遅延または早まる工程の修正工期データが、前記端末装置から前記サーバに送信され前記サーバの記憶部に登録されること、
(B)前記サーバが、前記登録された修正工期データに基づいて、前記進捗が遅延または早まる工程よりも後の工程の工期データを修正するか否かを判断すること、
(C)前記サーバが、前記判断、前記登録された修正工期データ、及び前記余剰時間データに基づいて、前記第n工程表の工程のうち少なくとも一つの工程の修正工期を含む第n+1工程表を作成すること、並びに
(D)前記サーバが、前記工期が修正された工程を担当する職人の端末装置に、前記第n+1工程表を通知すること、
nは1以上の自然数である、
請求項1または2に記載の工程表の作成方法。
(A) After the server notifies the terminal device of the craftsman in charge of the nth process chart, the progress of at least one process of the nth process chart is delayed or delayed with respect to the plan of the nth process chart. In the case of accelerating, the correction work period data of the process of delaying or accelerating the progress is transmitted from the terminal device to the server and registered in the storage unit of the server.
(B) The server determines whether or not to correct the construction period data of the process after the process whose progress is delayed or accelerated based on the registered correction construction period data.
(C) Based on the judgment, the registered correction work period data, and the surplus time data, the server performs an n + 1 process chart including a correction work period of at least one process in the nth process table. To create, and (D) the server notifies the terminal device of the craftsman in charge of the process whose construction period has been modified, the n + 1 process chart.
n is a natural number greater than or equal to 1.
The method for creating a process chart according to claim 1 or 2.
前記(A)〜(D)を1回以上繰り返すことを含む、請求項3に記載の工程表の作成方法。 The method for creating a process chart according to claim 3, which comprises repeating the above (A) to (D) one or more times. (a)前記サーバが前記担当する職人の端末装置に前記第n工程表を通知した後に、前記第n工程表に含まれる職人のうち少なくとも一人の前記記憶部に登録された余剰時間データが変更され登録された場合に、前記サーバが、前記変更された余剰時間データを含む前記記憶部に登録された余剰時間データに基づいて、前記余剰時間データが変更された職人が担当する工程及びそれよりも後の工程のうち少なくとも一つの工程の工期を修正する必要があるかどうかを判断すること、
(b)前記サーバが、前記余剰時間データが変更された職人が担当する工程及びそれよりも後の工程のうち少なくとも一つの工程の工期を修正する必要があると判断した場合に、前記変更された余剰時間データを含む前記記憶部に登録された余剰時間データに基づいて、前記少なくとも一つの工程の修正工期を含む第n+1工程表、前記少なくとも一つの工程を担当する職人が変更された第n+1工程表、またはそれらの組み合わせを作成すること、並びに
(c)前記サーバが、前記工期が修正された工程を担当する職人、前記担当が変更され第n+1工程表の工程を担当することになった職人、またはそれらの組み合わせの端末装置に、前記第n+1工程表を通知すること、
を含み、
nは1以上の自然数である、
請求項1〜4のいずれか一項に記載の工程表の作成方法。
(A) After the server notifies the terminal device of the craftsman in charge of the nth process chart, the surplus time data registered in the storage unit of at least one of the craftsmen included in the nth process chart is changed. When the surplus time data is registered, the server is in charge of the process in which the craftsman whose surplus time data is changed based on the surplus time data registered in the storage unit including the changed surplus time data, and more. To determine if it is necessary to modify the construction period of at least one of the subsequent processes,
(B) When the server determines that it is necessary to correct the construction period of at least one of the process in charge of the process in which the surplus time data is changed and the process after that, the change is made. Based on the surplus time data registered in the storage unit including the surplus time data, the n + 1 process chart including the correction work period of the at least one process, and the n + 1 in which the craftsman in charge of the at least one process is changed. Creating a process chart or a combination thereof, and (c) the server will be in charge of the process of the n + 1 process chart with the craftsman in charge of the process whose construction period has been modified and the person in charge changed. Notifying the craftsman or the terminal device of the combination thereof of the n + 1 process chart,
Including
n is a natural number greater than or equal to 1.
The method for creating a process chart according to any one of claims 1 to 4.
前記(a)〜(c)を1回以上繰り返すことを含む、請求項5に記載の工程表の作成方法。 The method for creating a process chart according to claim 5, which comprises repeating the above (a) to (c) one or more times. 前記サーバが、前記第n+1工程表の工程のうち少なくとも一つの工程の工期が前記第n工程表の前記少なくとも一つの工程の工期と比べて所定の期間を超えて遅れると判断する場合であって、前記登録された複数の職人のデータ及び前記登録された余剰時間データに基づいて、前記工期が遅れる工程を担当する職人を別の職人に変更すると前記第n+1工程表の前記少なくとも一つの工程の工期を所定の期間早められると判断する場合に、前記担当する職人を前記別の職人に変更して前記第n+1工程表を作成すること、並びに
前記サーバが、前記別の職人の端末装置に、前記第n+1工程表を通知すること、
を含む、請求項3〜6のいずれか一項に記載の工程表の作成方法。
The case where the server determines that the construction period of at least one of the steps in the n + 1 process chart is delayed by more than a predetermined period as compared with the construction period of at least one process in the nth process chart. When the craftsman in charge of the process whose construction period is delayed is changed to another craftsman based on the data of the plurality of registered craftsmen and the registered surplus time data, the at least one process of the n + 1 process chart When it is determined that the construction period can be advanced by a predetermined period, the craftsman in charge is changed to the other craftsman to create the n + 1 process chart, and the server is used for the terminal device of the other craftsman. Notifying the n + 1 process chart,
The method for creating a process chart according to any one of claims 3 to 6, which comprises.
前記第n+1工程表を通知することが、前記サーバが、前記第n+1工程表の通知を受けた職人の全員から、前記第n+1工程表を承諾することを受信すると、前記第n+1工程表を確定し、前記確定された第n+1工程表を、前記承諾した職人の端末装置に通知することを含む、
請求項3〜7のいずれか一項に記載の工程表の作成方法。
When the server receives the acceptance of the n + 1 process chart from all the craftsmen who have received the notification of the n + 1 process chart, the notification of the n + 1 process chart confirms the n + 1 process chart. Then, the finalized n + 1 process chart includes notifying the terminal device of the approved craftsman.
The method for creating a process chart according to any one of claims 3 to 7.
JP2019102113A 2019-05-31 2019-05-31 How to create a process chart Active JP6864196B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP2019102113A JP6864196B2 (en) 2019-05-31 2019-05-31 How to create a process chart

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP2019102113A JP6864196B2 (en) 2019-05-31 2019-05-31 How to create a process chart

Publications (2)

Publication Number Publication Date
JP2020197783A true JP2020197783A (en) 2020-12-10
JP6864196B2 JP6864196B2 (en) 2021-04-28

Family

ID=73648282

Family Applications (1)

Application Number Title Priority Date Filing Date
JP2019102113A Active JP6864196B2 (en) 2019-05-31 2019-05-31 How to create a process chart

Country Status (1)

Country Link
JP (1) JP6864196B2 (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN113793079A (en) * 2021-11-18 2021-12-14 捷宏润安工程顾问有限公司 Engineering cost project management system and method based on big data

Citations (9)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2002056049A (en) * 2000-08-08 2002-02-20 Maeda Corp System and method for matching worker and construction retail system using the sames
JP2003050839A (en) * 2001-06-01 2003-02-21 Ishin Co Ltd Process management system for construction
JP2005267488A (en) * 2004-03-22 2005-09-29 Asahi Kasei Homes Kk Process management system
US20060074608A1 (en) * 2004-10-01 2006-04-06 Freeman Clay System and method for designing building structures with associated estimates and schedules
JP2006146870A (en) * 2005-06-13 2006-06-08 Shoji Yuasa Integrated material management system
JP2009139996A (en) * 2007-12-03 2009-06-25 Riraito:Kk Construction management system
JP2011053962A (en) * 2009-09-02 2011-03-17 Mitsubishi Electric Corp Method and system for changing production plan
JP2017097598A (en) * 2015-11-24 2017-06-01 大成建設株式会社 System for collecting byproduct from construction site
JP2018197952A (en) * 2017-05-24 2018-12-13 大成建設株式会社 Construction surplus material wide area certification operation system

Patent Citations (9)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2002056049A (en) * 2000-08-08 2002-02-20 Maeda Corp System and method for matching worker and construction retail system using the sames
JP2003050839A (en) * 2001-06-01 2003-02-21 Ishin Co Ltd Process management system for construction
JP2005267488A (en) * 2004-03-22 2005-09-29 Asahi Kasei Homes Kk Process management system
US20060074608A1 (en) * 2004-10-01 2006-04-06 Freeman Clay System and method for designing building structures with associated estimates and schedules
JP2006146870A (en) * 2005-06-13 2006-06-08 Shoji Yuasa Integrated material management system
JP2009139996A (en) * 2007-12-03 2009-06-25 Riraito:Kk Construction management system
JP2011053962A (en) * 2009-09-02 2011-03-17 Mitsubishi Electric Corp Method and system for changing production plan
JP2017097598A (en) * 2015-11-24 2017-06-01 大成建設株式会社 System for collecting byproduct from construction site
JP2018197952A (en) * 2017-05-24 2018-12-13 大成建設株式会社 Construction surplus material wide area certification operation system

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN113793079A (en) * 2021-11-18 2021-12-14 捷宏润安工程顾问有限公司 Engineering cost project management system and method based on big data

Also Published As

Publication number Publication date
JP6864196B2 (en) 2021-04-28

Similar Documents

Publication Publication Date Title
US9152934B2 (en) Arrangements for administrating and managing a construction project
Lu et al. Demystifying construction project time–effort distribution curves: BIM and non-BIM comparison
WO2006073406A1 (en) System and method for automated management of custom home design and build projects
AU2016321238B2 (en) Systems and methods for processing orders for structural designs
US20150161695A1 (en) Systems and methods for normalizing and comparatively displaying disparate service offerings
CN104318342A (en) Distance-based work task recommendation and undertaking system and method
JP6864196B2 (en) How to create a process chart
Higham et al. Project finance for construction
Sinclair et al. Construction cost data workbook
Stein Disruptive development: modular manufacturing in multifamily housing
CA2836936A1 (en) Method and system for selecting labour resources
Rowley et al. Understanding how policy settings affect developer decisions
AU2020102657A4 (en) Systems and Methods for Building and Construction Management and Resource Sharing
WO2012145788A1 (en) Construction management methods
JP6407375B1 (en) Method and computer system for assessing building value
US20070203805A1 (en) Method for designing and constructing a residence for a customer
Page Medium-density housing supply and demand analysis
JP2003331120A (en) System and method for security value calculation of project and system and method for security value calculation of existent project object
Holm A Contractor's Guide to Planning, Scheduling, and Control
JP6442099B1 (en) Method and computer system for assessing building value
BEACH et al. APROXIMATE BILLS OF QUANTITIES
JP2024055878A (en) Wooden house construction support system, wooden house construction support device, and wooden house construction support method
Staley et al. Fort Mackinac restoration: cost-management project delivery
Jackson Renovating Your Home
De Gabriele Old house, new place: The lowdown on relocated homes

Legal Events

Date Code Title Description
RD03 Notification of appointment of power of attorney

Free format text: JAPANESE INTERMEDIATE CODE: A7423

Effective date: 20191226

A521 Request for written amendment filed

Free format text: JAPANESE INTERMEDIATE CODE: A821

Effective date: 20191226

A621 Written request for application examination

Free format text: JAPANESE INTERMEDIATE CODE: A621

Effective date: 20200121

A871 Explanation of circumstances concerning accelerated examination

Free format text: JAPANESE INTERMEDIATE CODE: A871

Effective date: 20200121

RD04 Notification of resignation of power of attorney

Free format text: JAPANESE INTERMEDIATE CODE: A7424

Effective date: 20200110

A975 Report on accelerated examination

Free format text: JAPANESE INTERMEDIATE CODE: A971005

Effective date: 20200206

A977 Report on retrieval

Free format text: JAPANESE INTERMEDIATE CODE: A971007

Effective date: 20200626

A131 Notification of reasons for refusal

Free format text: JAPANESE INTERMEDIATE CODE: A131

Effective date: 20200721

A601 Written request for extension of time

Free format text: JAPANESE INTERMEDIATE CODE: A601

Effective date: 20200918

A521 Request for written amendment filed

Free format text: JAPANESE INTERMEDIATE CODE: A523

Effective date: 20201112

A521 Request for written amendment filed

Free format text: JAPANESE INTERMEDIATE CODE: A523

Effective date: 20201118

TRDD Decision of grant or rejection written
A01 Written decision to grant a patent or to grant a registration (utility model)

Free format text: JAPANESE INTERMEDIATE CODE: A01

Effective date: 20210216

A61 First payment of annual fees (during grant procedure)

Free format text: JAPANESE INTERMEDIATE CODE: A61

Effective date: 20210304

R150 Certificate of patent or registration of utility model

Ref document number: 6864196

Country of ref document: JP

Free format text: JAPANESE INTERMEDIATE CODE: R150

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250