JP2003331120A - System and method for security value calculation of project and system and method for security value calculation of existent project object - Google Patents

System and method for security value calculation of project and system and method for security value calculation of existent project object

Info

Publication number
JP2003331120A
JP2003331120A JP2002135514A JP2002135514A JP2003331120A JP 2003331120 A JP2003331120 A JP 2003331120A JP 2002135514 A JP2002135514 A JP 2002135514A JP 2002135514 A JP2002135514 A JP 2002135514A JP 2003331120 A JP2003331120 A JP 2003331120A
Authority
JP
Japan
Prior art keywords
project
construction
contract
value
value calculation
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Withdrawn
Application number
JP2002135514A
Other languages
Japanese (ja)
Inventor
Sukeyuki Kogami
祐之 小上
Fusayoshi Moriguchi
房好 森口
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
MESSIAH INCUBATION KK
Original Assignee
MESSIAH INCUBATION KK
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by MESSIAH INCUBATION KK filed Critical MESSIAH INCUBATION KK
Priority to JP2002135514A priority Critical patent/JP2003331120A/en
Publication of JP2003331120A publication Critical patent/JP2003331120A/en
Withdrawn legal-status Critical Current

Links

Landscapes

  • Management, Administration, Business Operations System, And Electronic Commerce (AREA)
  • Financial Or Insurance-Related Operations Such As Payment And Settlement (AREA)

Abstract

<P>PROBLEM TO BE SOLVED: To provide a system and a method for security value calculation of a project which are suitably used to accurately calculate the economical value of a work in the middle of a construction allow a 3rd person to buy the work in the middle of the construction, and finish the work by using an additional loan from a financial institution. <P>SOLUTION: An in-process project security value calculation part 88 calculates the value at an implemented process stage regarding a project object from the finish value of the project object and contract amount information on an implemented process regarding the project object. A project finish value calculation part 85 receives design information from a design book management table 81 and also receives contract total amount information from a project implementation history table 83. A project construction completion value calculation part 86 receives progress states by completed processes from a project progress management table 82 and receives contract amount information of implemented processes from the project implementation history table 83. <P>COPYRIGHT: (C)2004,JPO

Description

【発明の詳細な説明】Detailed Description of the Invention

【0001】[0001]

【発明の属する技術分野】本発明は、例えばマンション
建設、戸建て住宅建設のように工期が数箇月から数年程
度の長期にわたると共に、施工業者が分業体制により施
工するような状況で、金融機関が建設途中の住宅の担保
価値を算定するような用途に用いて好適なプロジェクト
の施工途中での担保価値算定システム及び方法に関す
る。また、本発明はマンションや戸建て住宅のような数
十年乃至数百年の寿命を有するプロジェクト対象物であ
って、プロジェクト対象物の寿命が施主に引渡後の維持
補修に依存して大きく変動するような用途に用いて好適
な既設プロジェクト対象物の担保価値算定システム及び
方法に関する。
BACKGROUND OF THE INVENTION 1. Field of the Invention The present invention relates to a financial institution where the construction period is several months to several years, such as condominium construction and detached house construction, and the contractor is carrying out a division of labor system. The present invention relates to a collateral value calculation system and method during construction of a project suitable for use in calculating the collateral value of a house under construction. Further, the present invention is a project object having a life of several tens to several hundred years such as an apartment or a detached house, and the life of the project object varies greatly depending on maintenance and repair after delivery to the owner. The present invention relates to a system and method for calculating the collateral value of an existing project object suitable for such purposes.

【0002】[0002]

【従来の技術】不動産の債権化という時代の要請から、
建設途中の住宅のような工作物に対しても担保価値を算
定して、債権として流動化させたいという需要が金融市
場に存在する。特に、工作物の工事途中に請負業者が請
負工事を続行することが困難になった場合に、工事途中
の工作物をそのまま放置しておいたのでは、工作物の利
用をすることができず、社会経済上の損失も大きい。他
方、建設途中の住宅に関して現行民法は、不動産工事の
先取特権(民法第325条、327条、338条)を規
定していると共に、住宅工事と報酬との間に同時履行の
関係を充足させる為に、民事留置権(民法第297条)
や商事留置権(商法第521条)を認めている。そこ
で、金融市場参加者は、現行民法の枠内で建設途中の住
宅のような工作物の担保価値を算定する必要がある。
[Prior Art] From the demand of the era of real estate debt,
There is a demand in the financial market to calculate the collateral value of works such as houses under construction and liquidate them as bonds. In particular, if it is difficult for the contractor to continue the contract work during the construction of the work, if the work under construction is left as it is, the work cannot be used. The socio-economic loss is also large. On the other hand, regarding the housing under construction, the current Civil Code stipulates the lien for real estate construction (Civil Code Article 325, Article 327, Article 338) and fulfills the simultaneous fulfillment relationship between housing construction and remuneration. For civil detention (Civil Code Article 297)
And the Commercial Retention Right (Article 521 of the Commercial Code). Therefore, financial market participants need to calculate the collateral value of structures such as houses under construction within the framework of the current civil law.

【0003】また、依頼主が工事代金を支払うことが困
難になった場合にも、工作物の工事を途中で停止させざ
るを得なくなる。この場合、工事途中の工作物を第三者
が買受けたり、或いは金融機関からの追加融資により、
工事途中の工作物を完成させることができれば、社会経
済上の便益も大きい。
Also, when it becomes difficult for the client to pay the construction fee, the construction of the workpiece must be stopped on the way. In this case, a third party may purchase the work in progress or additional financing from a financial institution
If the work in progress can be completed, the social and economic benefits will be great.

【0004】[0004]

【発明が解決しようとする課題】しかし、工事途中の工
作物の経済的な価値を算出することは、完成された工作
物の場合に比較して、格段に難しいという課題があっ
た。即ち、工事途中の工作物を引継ぐ請負業者にとっ
て、工事途中の工作物を完成させる為に必要な費用と期
間の算定が困難であるという経済的な理由がある。ま
た、法的な理由として、請負契約の代表例である建築工
事において、建築対象物は民法第86条により不動産と
される。そして、不動産について「物権の設定及び移転
は当事者の意思表示のみに因りて其効力を生ず」るが
(民法第176条)、「不動産に関する物権の得喪及び
変更は登記法の定める所に従い登記をなすにあらざれ
ば、之を以て第三者に対抗することを得ず」(民法第1
77条)と規定されている。そこで、工事途中の工作物
は登記費用の観点から仮登記されることも稀であるた
め、事実上取引の対象となっていない。
However, there has been a problem that it is much more difficult to calculate the economic value of a workpiece in the process of construction, as compared with the case of a completed workpiece. That is, there is an economic reason that it is difficult for a contractor who takes over a work in progress to calculate the cost and period required to complete the work in progress. In addition, as a legal reason, in the construction work that is a typical example of a contract contract, the building object is a real estate under Article 86 of the Civil Code. And regarding real estate, "the establishment and transfer of property rights are not effective only due to the intention of the parties" (Article 176 of the Civil Code) If you look at it, you will not be able to compete against a third party without fail "(Civil Code No. 1
Article 77). Therefore, since the work in progress is rarely registered temporarily from the viewpoint of registration cost, it is not actually subject to transactions.

【0005】他方、中古住宅の場合は登記を経ているた
め取引の対象物として流通している。しかし、建物の建
築原価が経済的な価値として反映されにくく、また金融
機関における担保価値設定においても時価現有率表で定
められる建築後の年数を用いるのが一般的である。そこ
で、メンテナンスが行き届いていても、時価現有率表に
準拠した画一的な価値判断しかなされず、転売価格に適
正に反映されることは稀であった。例えば、競売市場に
おいて建築物の価値には、現実の施工コストを考慮する
ことはまれで、標準的な施工単価に対象物の面積を乗じ
て再建設コストを算出し、次に再建設コストから耐用年
数に対する建築後の経過年数から定まる償却額を算出し
て、一律の価値算定を行っている。
On the other hand, second-hand houses have been registered and are therefore distributed as objects of transactions. However, the building cost of a building is less likely to be reflected as an economic value, and it is common to use the number of years after construction, which is determined by the current market price ratio table, when setting the collateral value at financial institutions. Therefore, even if the maintenance is well done, only standardized value judgment based on the current market price ratio table is made, and it is rare that the resale price is properly reflected. For example, in the auction market, the actual construction cost is rarely considered in the value of a building, and the standard construction unit price is multiplied by the area of the object to calculate the reconstruction cost, and then the reconstruction cost is calculated. A uniform value is calculated by calculating the depreciation amount that is determined from the number of years after construction for the useful life.

【0006】本発明は上記の課題を解決するもので、第
1の目的は、工事途中の工作物の経済的な価値を正確に
算出でき、しかして工事途中の工作物を第三者が買受け
たり、金融機関による追加融資を用いて工作物を完成さ
せる用途に用いて好適なプロジェクトの担保価値算定シ
ステム及び方法を提供することを目的とする。また本発
明の第2の目的は、工作物の引渡し後も再建設価格の変
動やメンテナンスの状態を担保価値に適切に反映させる
ことのできる既設プロジェクトの担保価値算定システム
及び方法を提供することも目的とする。
The present invention solves the above problems. A first object of the present invention is to accurately calculate the economic value of a workpiece under construction, so that a third party can purchase the workpiece under construction. Another object of the present invention is to provide a collateral value calculation system and method suitable for a project that is used for the purpose of completing a work by using an additional loan from a financial institution. A second object of the present invention is also to provide a collateral value calculation system and method for an existing project that can appropriately reflect the fluctuation of the rebuilding price and the state of maintenance in the collateral value even after the delivery of the workpiece. To aim.

【0007】[0007]

【課題を解決するための手段】第1の目的を達成する本
発明のプロジェクトの担保価値算定システムは、図1に
示すように、プロジェクト対象物の完成状態情報と請負
契約総金額情報を用いて、前記プロジェクト対象物の完
成価値を算出するプロジェクト完成価値算出部85と、
プロジェクト進捗管理テーブル82から前記プロジェク
ト対象物における、請負業者により実施済みの工程毎の
進捗状況を受取ると共に、プロジェクト履行履歴テーブ
ル83から前記プロジェクト対象物に係る実施済み工程
の請負契約金額情報を受取るプロジェクト工事済価値算
出部86と、プロジェクト完成価値算出部85にて算出
された前記プロジェクト対象物の完成価値と、前記プロ
ジェクト工事済価値算出部86にて算出された前記プロ
ジェクト対象物に係る実施済み工程の請負契約金額情報
から、前記プロジェクト対象物に係る実施済み工程段階
での価値を算出するプロジェクト担保価値算定部88と
を備えている。
As shown in FIG. 1, a project collateral value calculation system of the present invention that achieves the first object uses completion status information of a project object and total contract amount information. A project completion value calculation unit 85 for calculating the completion value of the project object,
A project that receives from the project progress management table 82 the progress status of each process that has been executed by the contractor in the project object, and also receives contract contract amount information of the executed process related to the project object from the project fulfillment history table 83. Completed value of the project object calculated by the completed value calculating unit 86 and the project completed value calculating unit 85, and the completed process of the project object calculated by the project completed value calculating unit 86 And a project collateral value calculation unit 88 for calculating the value of the project object at the completed process stage from the contract contract amount information.

【0008】ここで、プロジェクト対象物の完成状態情
報には、実施済みの工程毎の状態を積算した積み上げ評
価部分、プロジェクト対象物が全体として旨く構築され
ているかの評価部分、使用者や施主にとっての使い勝手
の良さなどを総合的に評価した部分の少なくとも何れか
一つを含むとよい。また、プロジェクト対象物の請負契
約総金額情報には、完成した状態におけるプロジェクト
対象物の再調達原価としての建設費が含まれる。プロジ
ェクト対象物における土地部分の担保評価は、不動産鑑
定理論に従って適宜に定められる。
Here, in the completion status information of the project object, the accumulated evaluation part in which the states of the completed processes are integrated, the evaluation part of whether the project object as a whole is successfully constructed, the user or the owner. It is preferable to include at least one of the portions that are evaluated comprehensively for the ease of use and the like. Further, the total contract amount information of the project object includes the construction cost as the replacement cost of the project object in the completed state. The collateral evaluation of the land portion of the project object is appropriately determined according to the real estate appraisal theory.

【0009】このように構成された装置において、プロ
ジェクト完成価値算出部85は、プロジェクト対象物の
完成価値を算出するもので、主にプロジェクト対象物の
建設費に相当する請負契約総金額情報を用いる。さら
に、プロジェクト対象物の完成状態情報を用いて、例え
ばプロジェクト対象物に欠陥が存在している場合にプロ
ジェクト対象物の完成価値を減価したり、或いは隣接地
が都市計画等によって社会基盤が整備される場合には、
効用が増す分増価させる。プロジェクト工事済価値算出
部86は、既に実施済みの工程に対する建設費に相当す
る価値を算出する。プロジェクト担保価値算定部88
は、プロジェクト対象物の完工に対する実施済みの工程
の割合を考慮することで、建設途中のプロジェクト対象
物の担保価値を算出する。好ましくは、プロジェクト対
象物の完工に対する実施済みの工程は、追加実施工程の
実施見込みと比較すると、債務不履行に陥る可能性が低
いので、掛け目率として第1の乗率を用いるとよい。
In the apparatus configured as described above, the project completion value calculator 85 calculates the completion value of the project object, and mainly uses the total contract amount information corresponding to the construction cost of the project object. . Furthermore, by using the completion status information of the project object, for example, when the project object has a defect, the completion value of the project object is depreciated, or the adjacent land is improved in social infrastructure by city planning or the like. If
Increase the value as the utility increases. The project construction completed value calculation unit 86 calculates a value corresponding to the construction cost for the already executed process. Project collateral value calculation unit 88
Calculates the collateral value of the project object under construction by considering the ratio of completed processes to the completion of the project object. It is preferable to use the first multiplying factor as the multiplication factor because it is less likely that the process that has already been executed for the completion of the project object will be in default as compared with the prospect of performing the additional process.

【0010】好ましくは、本発明のプロジェクトの担保
価値算定システムにおけるプロジェクト完成価値算出部
85は、設計図書管理テーブル81からプロジェクト対
象物の完成状態情報を受取ると共に、プロジェクト履行
履歴テーブル83から前記プロジェクト対象物に係る請
負契約総金額情報を受取る構成とすると、プロジェクト
対象物の完成価値や建設予定費が円滑に取得できる。
Preferably, the project completion value calculation unit 85 in the project collateral value calculation system of the present invention receives the completion status information of the project object from the design book management table 81 and the project execution history table 83 from the project object. If it is configured to receive the total amount of contract contract amount related to the object, the completed value of the project object and the planned construction cost can be acquired smoothly.

【0011】第1の目的を達成する本発明のプロジェク
トの担保価値算定システムは、図1に示すように、プロ
ジェクト対象物の完成状態情報と請負契約総金額情報を
用いて、前記プロジェクト対象物の完成価値を算出する
プロジェクト完成価値算出部85と、プロジェクト進捗
管理テーブルから前記プロジェクト対象物を完成状態と
するのに必要な追加実施工程を受取ると共に、前記プロ
ジェクト履行履歴テーブル83から前記プロジェクト対
象物に係る追加実施工程の請負契約金額情報を受取るプ
ロジェクト追加工事価値算出部87と、前記プロジェク
ト完成価値算出部85にて算出された前記プロジェクト
対象物の完成価値と、前記プロジェクト追加工事価値算
出部87にて算出された前記プロジェクト対象物を完成
状態とするのに必要な追加実施工程の実施見込み金額か
ら、前記プロジェクト対象物に係る実施済み工程段階で
の価値を算出するプロジェクト担保価値算定部88とを
備えている。
As shown in FIG. 1, the project collateral value calculation system of the present invention which achieves the first object uses the completion status information of the project object and the total contract amount information of the project object as shown in FIG. The project completion value calculation unit 85 for calculating the completion value, and the additional execution process required to bring the project object to the completed state from the project progress management table are received, and the project execution history table 83 is used to convert the project object to the project object. The project additional construction value calculation unit 87 that receives the contract contract amount information of the additional implementation process, the completion value of the project object calculated by the project completion value calculation unit 85, and the project additional construction value calculation unit 87. It is necessary to complete the project object calculated by From practice estimated amount Do additional implementation process, and a project collateral valuation unit 88 for calculating a value of at Performed process steps according to the project object.

【0012】このように構成された装置において、プロ
ジェクト追加工事価値算出部87は、建設途中のプロジ
ェクト対象物を完成状態とするのに必要な追加実施工程
を用いて、追加実施工程に対応する請負契約金額を算出
する。プロジェクト担保価値算定部88は、プロジェク
ト対象物の完工に必要とされる追加実施工程の割合を考
慮することで、建設途中のプロジェクト対象物の担保価
値を算出する。好ましくは、プロジェクト対象物の完工
に対する追加実施工程は、実施済みの工程と比較する
と、債務不履行に陥る可能性が若干存在する為、実施見
積り金額に対する掛け目率として第1の乗率よりも低め
の第2の乗率を用いるとよい。
In the apparatus configured as described above, the project additional construction value calculation unit 87 uses the additional implementation process necessary to bring the project object under construction to a completed state, and performs the contract corresponding to the additional implementation process. Calculate the contract amount. The project collateral value calculation unit 88 calculates the collateral value of the project object under construction by considering the ratio of the additional execution process required for completion of the project object. Preferably, the additional implementation process for the completion of the project object has a possibility of falling into default when compared with the already implemented process, so the multiplication factor for the estimated implementation amount is lower than the first multiplication factor. The second multiplication factor may be used.

【0013】第1の目的を達成する本発明のプロジェク
トの担保価値算定システムは、図1に示すように、プロ
ジェクト進捗管理テーブル82からプロジェクト対象物
における、請負業者により実施済みの工程毎の進捗状況
を受取ると共に、プロジェクト履行履歴テーブル83か
ら前記プロジェクト対象物に係る実施済み工程の請負契
約金額情報を受取るプロジェクト工事済価値算出部86
と、前記プロジェクト進捗管理テーブル82から前記プ
ロジェクト対象物を完成状態とするのに必要な追加実施
工程を受取ると共に、前記プロジェクト履行履歴テーブ
ル83から前記プロジェクト対象物に係る追加実施工程
の請負契約金額情報を受取るプロジェクト追加工事価値
算出部87と、前記プロジェクト工事済価値算出部86
にて算出された前記プロジェクト対象物に係る実施済み
工程の請負契約金額情報と、前記プロジェクト追加工事
価値算出部にて算出された前記プロジェクト対象物を完
成状態とするのに必要な追加実施工程の実施見込み金額
から、前記プロジェクト対象物に係る実施済み工程段階
での価値を算出するプロジェクト担保価値算定部88と
を備えている。
As shown in FIG. 1, the project collateral value calculation system of the present invention which achieves the first object is, as shown in FIG. 1, the progress status of each process in the project object which has been executed by the contractor from the project progress management table 82. Project construction history table 83, and also receives the contracted contract amount information of the completed process related to the project object from the project fulfillment history table 83
And the additional execution process required to complete the project object from the project progress management table 82, and the contract contract amount information of the additional execution process related to the project object from the project fulfillment history table 83. Project additional construction value calculation unit 87 and the project construction completed value calculation unit 86
The contracted contract amount information of the completed process related to the project object calculated in step S1 and the additional execution process necessary to complete the project object calculated in the project additional construction value calculation unit. A project collateral value calculation unit 88 for calculating the value of the project object at the completed process step from the estimated execution amount.

【0014】このように構成された装置において、プロ
ジェクト担保価値算定部88は、プロジェクト対象物の
完工に対する実施済みの工程の実施金額と、完工に必要
とされる追加実施工程の実施金額を考慮することで、建
設途中のプロジェクト対象物の担保価値を算出する。好
ましくは、プロジェクト対象物の完工に対する実施済み
の工程は実施金額に対する掛け目率として第1の乗率を
用い、プロジェクト対象物の完工に対する追加実施工程
は実施見積り金額に対する掛け目率として第1の乗率よ
りも低めの第2の乗率を用いるとよい。
In the apparatus configured as described above, the project collateral value calculation unit 88 considers the implementation amount of the completed process for the completion of the project object and the implementation amount of the additional execution process required for completion. By doing so, the collateral value of the project object under construction is calculated. Preferably, the completed process for the completion of the project object uses the first multiplication factor as the multiplication factor with respect to the execution amount, and the additional execution process for the completion of the project object has the first multiplication factor as the multiplication factor with respect to the estimated implementation amount. It is better to use a lower second multiplying factor.

【0015】好ましくは、プロジェクト対象物は請負型
の工事、加工、開発又は役務とすると良い。請負型の工
事には、建設工事、プラント工事、土木工事、港湾工事
等が含まれる。請負型の加工には、製品の加工、組立加
工、部品の成形加工などが含まれる。請負型の開発に
は、特定目的の研究開発契約、プロジェクト契約が含ま
れる。請負型の役務には、ソフトウェア開発、データ入
力役務等がある。
[0015] Preferably, the project object is a contract type construction, processing, development or service. Contract-type work includes construction work, plant work, civil works, port work, and the like. Contract-type processing includes product processing, assembly processing, component forming processing, and the like. Contract-type development includes special purpose R & D contracts and project contracts. Contract-type services include software development and data entry services.

【0016】好ましくは、図1に示すように、プロジェ
クト担保価値算定部88にて算出された前記プロジェク
ト対象物に係る実施済み工程段階での価値に対して、前
記プロジェクト対象物に関する完成状態での売買市場デ
ータ、もしくは前記プロジェクト対象物の引渡し後の維
持管理記録(維持管理記録データベース84)を参酌し
て、当該価値の修正を行う価値調整部89を備えてもよ
い。
Preferably, as shown in FIG. 1, the value of the project object calculated by the project collateral value calculation unit 88 at the completed process step relating to the project object in the completed state of the project object is A value adjusting unit 89 that corrects the value may be provided by taking into consideration the trading market data or the maintenance record (maintenance record database 84) after the delivery of the project object.

【0017】第1の目的を達成する本発明のプロジェク
トの担保価値算定方法は、図2に示すように、プロジェ
クト対象物の完成状態情報と請負契約総金額情報を用い
て、前記プロジェクト対象物の完成価値を算出し(S1
01、S102)、プロジェクト進捗管理テーブル82
から前記プロジェクト対象物における、請負業者により
実施済みの工程毎の進捗状況を受取り(S103)、前
記プロジェクト履行履歴テーブル83から前記プロジェ
クト対象物に係る実施済み工程の請負契約金額情報を受
取り(S104)、前記プロジェクト対象物に係る完成
状態情報並びに請負契約総金額情報により算出された前
記プロジェクト対象物の完成価値と、前記プロジェクト
対象物に係る実施済み工程毎の進捗状況並びに請負契約
総金額情報から、前記プロジェクト対象物に係る実施済
み工程段階での価値を算出する(S105)それぞれの
工程をコンピュータを用いて実行させる。
As shown in FIG. 2, the method of calculating the collateral value of a project according to the present invention which achieves the first object, uses the completion status information of the project object and the total contract amount information of the project object, as shown in FIG. Calculate the completion value (S1
01, S102), project progress management table 82
From the project object, the progress status of each process executed by the contractor is received (S103), and the contracted contract amount information of the executed process related to the project object is received from the project fulfillment history table 83 (S104). , The completion value of the project object calculated by the completion status information and the contract contract total amount information related to the project object, and the progress status of each executed process related to the project object and the contract contract total amount information, The value of the project target object at the completed process step is calculated (S105), and each process is executed by using a computer.

【0018】第1の目的を達成する本発明のプロジェク
トの担保価値算定方法は、プロジェクト対象物の完成状
態情報と請負契約総金額情報を用いて、前記プロジェク
ト対象物の完成価値を算出し(S201、S202)、
プロジェクト進捗管理テーブル82から前記プロジェク
ト対象物を完成状態とするのに必要な追加実施工程を受
取り(S203)、前記プロジェクト履行履歴テーブル
83から前記プロジェクト対象物に係る追加実施工程の
請負契約金額情報を受取り(S204)、前記プロジェ
クト対象物に係る完成状態情報並びに請負契約総金額情
報により算出された前記プロジェクト対象物の完成価値
と、前記プロジェクト対象物を完成状態とするのに必要
な追加実施工程の実施見込み金額から、前記プロジェク
ト対象物に係る実施済み工程段階での価値を算出する
(S205)、それぞれの工程をコンピュータを用いて
実行させる。
In the project collateral value calculating method of the present invention which achieves the first object, the completion value of the project object is calculated by using the completion state information of the project object and the total contract amount information (S201). , S202),
The additional execution process required to complete the project object is received from the project progress management table 82 (S203), and the contract contract amount information of the additional execution process related to the project object is received from the project fulfillment history table 83. Receipt (S204), completion value of the project object calculated from the completion state information related to the project object and the total contract amount information, and an additional implementation process necessary to bring the project object to the completed state. The value of the project object at the completed process step is calculated from the estimated execution amount (S205), and each process is executed by using a computer.

【0019】第1の目的を達成する本発明のプロジェク
トの担保価値算定方法は、プロジェクト進捗管理テーブ
ル82から前記プロジェクト対象物における、請負業者
により実施済みの工程毎の進捗状況を受取り(S30
1)、前記プロジェクト履行履歴テーブル83から前記
プロジェクト対象物に係る実施済み工程の請負契約金額
情報を受取り(S302)、プロジェクト進捗管理テー
ブル82から前記プロジェクト対象物を完成状態とする
のに必要な追加実施工程を受取り(S303)、前記プ
ロジェクト履行履歴テーブル83から前記プロジェクト
対象物に係る追加実施工程の請負契約金額情報を受取り
(S304)、前記プロジェクト対象物に係る実施済み
工程毎の進捗状況並びに請負契約総金額情報と、前記プ
ロジェクト対象物を完成状態とするのに必要な追加実施
工程の実施見込み金額から、前記プロジェクト対象物に
係る実施済み工程段階での価値を算出する(S30
5)、それぞれの工程をコンピュータを用いて実行させ
る。
The method for calculating the collateral value of a project according to the present invention which achieves the first object is to receive, from the project progress management table 82, the progress status of each step in the project object which has been carried out by the contractor (S30).
1), receiving the contract contract amount information of the completed process related to the project object from the project fulfillment history table 83 (S302), and adding necessary to complete the project object from the project progress management table 82 Receive the implementation process (S303), receive contract amount information of the additional implementation process related to the project object from the project fulfillment history table 83 (S304), and progress status and contract for each completed process related to the project object The value of the project object at the completed process step is calculated from the contract total amount information and the estimated execution amount of the additional execution process required to complete the project object (S30).
5) Perform each step using a computer.

【0020】第2の目的を達成する本発明の既設プロジ
ェクトの担保価値算定システムは、図22に示すよう
に、既設プロジェクトを建設時と同一工法によって再建
設する場合の再調達価格を算定する再調達価格算定部9
1と、再調達価格算定部91で算出した再調達価格に前
記既設プロジェクトの耐用年数と経過年数を元に算出さ
れた現有価値率を乗じ、更に前記既設プロジェクトに対
する修繕により前記経過年数に対して延長された残存寿
命を考慮して、前記既設プロジェクトの現在有している
価値を算定する現有価値算定部94と、前記既設プロジ
ェクトの流通市場状態を参酌して、前記既設プロジェク
トに対する担保価値率を算定する担保価値算定部95と
を備えている。
As shown in FIG. 22, the collateral value calculation system for an existing project of the present invention which achieves the second object is a re-calculation price for re-constructing an existing project by the same construction method as at the time of construction. Procurement price calculator 9
1 and the replacement price calculated by the replacement price calculation unit 91, multiplied by the current value ratio calculated based on the useful life and the elapsed years of the existing project, and further with respect to the elapsed years by repairing the existing project. In consideration of the extended remaining life, the present value calculation unit 94 for calculating the present value of the existing project and the secondary market condition of the existing project are taken into consideration, and the collateral value rate for the existing project is calculated. And a collateral value calculation unit 95 for calculating.

【0021】このように構成された装置においては、再
調達価格算定部91によって既設プロジェクトを建設時
と同一工法によって再建設する場合の再調達価格を算定
している。この場合、再調達価格算定部91は、設計図
書管理テーブル81とプロジェクト進捗管理テーブル8
2を参照することによって、既設プロジェクトを建設時
と同一工法によって再建設する場合の所要資材と所要工
数の詳細を正確に把握できる。再調達価格算定部91
は、資材市況データ部92と施工積算データ部93を参
照して、担保価値算定時での資材と請負工数並びに請負
工数単価を積算することで、既設プロジェクトの再調達
価格における建設時と担保算定時の請負相場の影響を反
映させている。現有価値算定部94は既設プロジェクト
の現在有している価値を算定する際に、既設プロジェク
トに対する修繕により前記経過年数に対して延長された
残存寿命を考慮して現在価値を算定する。担保価値算定
部95は、前記既設プロジェクトの流通市場状態を参酌
して、前記既設プロジェクトに対する担保価値率を算定
して、流通市場における換金リスクを数値化している。
In the thus constructed apparatus, the replacement price calculation unit 91 calculates the replacement price when the existing project is reconstructed by the same construction method as at the time of construction. In this case, the replacement procurement price calculation unit 91 uses the design document management table 81 and the project progress management table 8
By referring to 2, it is possible to accurately grasp the details of the required materials and the required man-hours when the existing project is reconstructed by the same construction method as at the time of construction. Replacement price calculation unit 91
Refers to the material market data section 92 and the construction integration data section 93, and accumulates the materials and the contract man-hours and the unit cost of the contract man-hours at the time of calculating the collateral value to calculate the mortgage at the time of construction and the collateral at the replacement price of the existing project. It reflects the influence of the market price of the contract. When calculating the present value of the existing project, the present value calculating unit 94 calculates the present value in consideration of the remaining life extended with respect to the elapsed years due to the repair of the existing project. The collateral value calculation unit 95 calculates the collateral value rate for the existing project by taking the secondary market state of the existing project into consideration, and quantifies the cash risk in the secondary market.

【0022】第2の目的を達成する本発明の既設プロジ
ェクトの担保価値算定方法は、既設プロジェクトを建設
時と同一工法によって再建設する場合の再調達価格を算
定し、前記算出された再調達価格に前記既設プロジェク
トの耐用年数と経過年数を元に算出された現有価値率を
乗じ、更に前記既設プロジェクトに対する修繕により前
記経過年数に対して延長された残存寿命を考慮して、前
記既設プロジェクトの現在有している価値を算定し、前
記既設プロジェクトの流通市場状態を参酌して、前記既
設プロジェクトに対する担保価値率を算定する工程をコ
ンピュータを用いて実行させる。本発明の既設プロジェ
クトの担保価値算定方法では、再調達価格の算定、既設
プロジェクトの現在有している価値の算定、担保価値率
の算定に対してコンピュータを用いている。
The collateral value calculation method for an existing project of the present invention which achieves the second object is to calculate a replacement price when an existing project is reconstructed by the same construction method as at the time of construction, and calculate the replacement price calculated above. Is multiplied by the current value ratio calculated based on the service life and elapsed years of the existing project, and considering the remaining life extended to the elapsed years due to repairs to the existing project, the current The process of calculating the value possessed, taking into consideration the secondary market state of the existing project, and calculating the collateral value rate for the existing project is executed using a computer. In the method for calculating the collateral value of an existing project of the present invention, a computer is used for calculating the replacement price, calculating the value that the existing project currently has, and calculating the collateral value ratio.

【0023】[0023]

【発明の実施の形態】以下、本発明の実施の形態につい
て、図面を参照して説明する。なお、各図において互い
に同一或いは相当する部材には同一符号又は類似符号を
付し、重複した説明は省略する。
BEST MODE FOR CARRYING OUT THE INVENTION Embodiments of the present invention will be described below with reference to the drawings. In each figure, the same or corresponding members are designated by the same reference numerals or similar reference numerals, and duplicate description will be omitted.

【0024】図1は、本発明におけるプロジェクトの担
保価値算定システムの構成ブロック図である。図1にお
いて、本発明の担保価値算定システムが実装される担保
価値算定サーバー80は、設計図書管理テーブル81、
プロジェクト進捗管理テーブル82、プロジェクト履行
履歴テーブル83、維持管理記録データベース84、プ
ロジェクト完成価値算出部85、プロジェクト工事済価
値算出部86、プロジェクト追加工事価値算出部87、
プロジェクト担保価値算定部88並びに価値調整部89
で構成される。
FIG. 1 is a block diagram of a project collateral value calculation system according to the present invention. In FIG. 1, a collateral value calculation server 80 in which the collateral value calculation system of the present invention is implemented is a design book management table 81,
A project progress management table 82, a project implementation history table 83, a maintenance management record database 84, a project completion value calculation unit 85, a project construction completed value calculation unit 86, a project additional construction value calculation unit 87,
Project collateral value calculation unit 88 and value adjustment unit 89
Composed of.

【0025】なお、請負業者端末65は請負業者が用い
る端末装置であり、プロジェクト検査管理者端末31は
プロジェクト検査管理者が持つ端末であり、いずれも、
例えばブラウザ機能を有するパソコンや情報携帯端末、
インターネット接続機能を有する携帯電話機等が用いら
れる。また、設計図書サーバー90は、プロジェクト対
象物の設計図書が格納されたもので、設計図書の書誌的
事項を設計図書管理テーブル81に書込んで、プロジェ
クト対象物の設計図書にアクセスする為の管理テーブル
を設計図書管理テーブル81に作成している。
The contractor terminal 65 is a terminal device used by the contractor, and the project inspection manager terminal 31 is a terminal owned by the project inspection manager.
For example, a personal computer with a browser function or an information portable terminal,
A mobile phone or the like having an internet connection function is used. Further, the design book server 90 stores design books of project objects, and manages the bibliographical items of the design books by writing them in the design book management table 81 to access the design books of the project objects. The table is created in the design book management table 81.

【0026】本発明の第一の実施形態において、プロジ
ェクト完成価値算出部85は、設計図書管理テーブル8
1からプロジェクト対象物の完成状態情報を受取ると共
に、プロジェクト履行履歴テーブル83からプロジェク
ト対象物に係る請負契約総金額情報を受取る。また、プ
ロジェクト工事済価値算出部86は、プロジェクト進捗
管理テーブル82からプロジェクト対象物における、請
負業者(請負業者端末65)により実施済みの工程毎の
進捗状況を受取ると共に、プロジェクト履行履歴テーブ
ル83からプロジェクト対象物に係る実施済み工程の請
負契約金額情報を受取る。請負契約金額情報には、プロ
ジェクト対象物に係る実施済み工程の施工に必要とされ
る資材や設備品の調達価格と、施工に必要な労務費や機
材費、請負業者の粗利等が含まれる。
In the first embodiment of the present invention, the project completion value calculation unit 85 uses the design book management table 8
In addition to receiving the completion status information of the project object from 1, the contract contract total amount information related to the project object is received from the project fulfillment history table 83. Further, the project construction completed value calculation unit 86 receives from the project progress management table 82 the progress status of each process in the project object which has been carried out by the contractor (contractor terminal 65), and from the project implementation history table 83 Receive the contracted contract amount information of the executed process related to the object. The contract contract amount information includes the procurement price of the materials and equipment required for the construction of the completed process related to the project object, the labor cost and the equipment cost necessary for the construction, the gross profit of the contractor, etc. .

【0027】プロジェクト担保価値算定部88は、プロ
ジェクト完成価値算出部85にて算出されたプロジェク
ト対象物の完成価値と、プロジェクト工事済価値算出部
86にて算出されたプロジェクト対象物に係る実施済み
工程の請負契約金額情報から、プロジェクト対象物に係
る実施済み工程段階での価値を算出する。プロジェクト
対象物の完成価値は、例えば以下の基準〜で算出さ
れる。 プロジェクト対象物を完成状態とする為の実施コスト
(資材コスト、労務費、施工用設備の償却費や使用料、
施工状態を管理するための費用を含む)。 完成状態のプロジェクト対象物に類似する対象物が市
場において取引されている市場取引価格。 政府によって資産課税される場合の完成状態のプロジ
ェクト対象物に類似する対象物の課税標準額。 プロジェクト対象物に係る請負契約の締結時に対し
て、担保価値算出時の資材コスト、労務費などの実施コ
ストの変動分や、将来の担保権実行時に予想される実施
コストの変動分。 請負契約の締結時と担保価値算出時との時間差に基づ
く、利子率の影響。
The project collateral value calculation unit 88 calculates the completed value of the project object calculated by the project completed value calculation unit 85 and the completed process for the project object calculated by the project construction completed value calculation unit 86. Calculate the value of the project object at the completed process step from the contract contract amount information. The completion value of the project object is calculated, for example, by the following criteria. Implementation costs (material costs, labor costs, construction equipment depreciation costs, usage fees,
Includes costs for managing the construction status). The market transaction price at which an object similar to the completed project object is traded on the market. The standard amount of tax on an object that is similar to the completed project object when taxed by the government. Changes in implementation costs such as material costs and labor costs when calculating the collateral value, and changes in implementation costs expected when executing future security interests compared to when the contract contract for the project object is concluded. Effect of interest rate based on the time difference between the time a contract is signed and the time the collateral value is calculated.

【0028】プロジェクト担保価値算定部88のプロジ
ェクト対象物に係る実施済み工程にする担保価値の算定
は、プロジェクト対象物に係る実施済み工程の請負契約
金額に第1の乗率を乗じるとよい。第1の乗率は、既に
実施済み工程であるため、プロジェクト対象物を完成状
態とするのに必要な追加実施工程に対する担保価値の算
定に比較して、算定される担保価値が請負契約金額に近
いものとなるように定めることができる。第1の乗率
は、例えば0.6〜0.8程度に設定するとよい。
The project collateral value calculation unit 88 may calculate the collateral value for the executed process related to the project object by multiplying the contract contract amount of the executed process related to the project object by the first multiplication factor. The first multiplication factor is the already completed process, so the calculated collateral value is the contract amount compared to the calculation of the collateral value for the additional process that is necessary to complete the project object. Can be determined to be close. The first multiplication factor may be set to, for example, about 0.6 to 0.8.

【0029】本発明の第二の実施形態において、プロジ
ェクト完成価値算出部85は、設計図書管理テーブル8
1からプロジェクト対象物の完成状態情報を受取ると共
に、プロジェクト履行履歴テーブル83からプロジェク
ト対象物に係る請負契約総金額情報を受取る。また、プ
ロジェクト追加工事価値算出部87は、プロジェクト進
捗管理テーブル82からプロジェクト対象物を完成状態
とするのに必要な追加実施工程を受取ると共に、プロジ
ェクト履行履歴テーブル83からプロジェクト対象物に
係る追加実施工程の請負契約金額情報を受取る。
In the second embodiment of the present invention, the project completion value calculation unit 85 uses the design book management table 8
In addition to receiving the completion status information of the project object from 1, the contract contract total amount information related to the project object is received from the project fulfillment history table 83. In addition, the project additional construction value calculation unit 87 receives the additional execution process required to complete the project object from the project progress management table 82, and the additional execution process related to the project object from the project fulfillment history table 83. Receive contract contract amount information.

【0030】そして、プロジェクト担保価値算定部88
は、プロジェクト完成価値算出部85にて算出されたプ
ロジェクト対象物の完成価値と、プロジェクト追加工事
価値算出部87にて算出されたプロジェクト対象物を完
成状態とするのに必要な追加実施工程の実施見込み金額
から、プロジェクト対象物に係る実施済み工程段階での
価値を算出する。プロジェクト担保価値算定部88は、
プロジェクト対象物を完成状態とするのに必要な追加実
施工程の実施見込み金額に第2の乗率を乗じて実施済み
工程に対する担保価値を算定するとよい。第2の乗率
は、担保価値算定時と追加実施工程の実施見込み時期の
想定される経過時間に利子率を乗じて定める。また、追
加実施工程の実施が、突発的な要因によって実施不能状
態に陥る危険度と、遅延損害利率も考慮するとよい。第
2の乗率は、例えば0.4〜0.6程度に設定するとよ
い。
Then, the project collateral value calculation unit 88
Is the completion value of the project object calculated by the project completion value calculation unit 85 and the additional execution process necessary to bring the project object calculated by the project additional construction value calculation unit 87 to the completed state. From the estimated amount, calculate the value of the project object at the stage of the completed process. The project collateral value calculation unit 88
It is advisable to calculate the collateral value for the completed process by multiplying the estimated amount of additional process required to complete the project object by the second multiplier. The second multiplication factor is determined by multiplying the expected elapsed time between the calculation of the collateral value and the expected execution time of the additional execution process by the interest rate. In addition, it is good to consider the degree of risk that the implementation of the additional implementation process will be in an inoperable state due to a sudden factor, and the delayed loss interest rate. The second multiplication factor may be set to, for example, about 0.4 to 0.6.

【0031】本発明の第三の実施形態において、プロジ
ェクト工事済価値算出部86は、プロジェクト進捗管理
テーブル82からプロジェクト対象物における、請負業
者端末65により請負業者により実施済みの工程毎の進
捗状況を受取ると共に、プロジェクト履行履歴テーブル
83からプロジェクト対象物に係る実施済み工程の請負
契約金額情報を受取る。また、プロジェクト追加工事価
値算出部87は、プロジェクト進捗管理テーブル82か
らプロジェクト対象物を完成状態とするのに必要な追加
実施工程を受取ると共に、プロジェクト履行履歴テーブ
ル83からプロジェクト対象物に係る追加実施工程の請
負契約金額情報を受取る。そして、プロジェクト担保価
値算定部88は、プロジェクト工事済価値算出部86に
て算出されたプロジェクト対象物に係る実施済み工程の
請負契約金額情報と、プロジェクト追加工事価値算出部
87にて算出されたプロジェクト対象物を完成状態とす
るのに必要な追加実施工程の実施見込み金額から、プロ
ジェクト対象物に係る実施済み工程段階での価値を算出
する。
In the third embodiment of the present invention, the project completed value calculation unit 86 indicates the progress status of each process in the project target from the project progress management table 82 by the contractor terminal 65 by the contractor. At the same time, the contract contract amount information of the executed process relating to the project object is received from the project fulfillment history table 83. In addition, the project additional construction value calculation unit 87 receives the additional execution process required to complete the project object from the project progress management table 82, and the additional execution process related to the project object from the project fulfillment history table 83. Receive contract contract amount information. Then, the project collateral value calculation unit 88 calculates the contracted contract amount information of the executed process relating to the project object calculated by the project construction completed value calculation unit 86 and the project calculated by the project additional construction value calculation unit 87. The value of the project target at the stage of the completed process is calculated from the expected amount of the additional process required to complete the target.

【0032】なお、上記した実施形態に共通するものと
して、プロジェクト対象物が請負型の建設工事であり、
実施工程には、少なくとも基礎工事、屋根工事、内装下
地工事、完成検査のうち少なくとも一つを含む。また、
価値調整部89を備え、この価値調整部89は、プロジ
ェクト担保価値算定部88にて算出されたプロジェクト
対象物に係る実施済み工程段階での価値に対して、プロ
ジェクト対象物に関する完成状態での売買市場データ、
もしくは維持管理記録データベース84に記録されたプ
ロジェクト対象物の引渡し後の維持管理記録を参酌し
て、当該価値の修正を行う。
As common to the above-mentioned embodiments, the project object is a contract-type construction work,
The implementation process includes at least one of foundation work, roof work, interior groundwork, and completion inspection. Also,
The value adjusting unit 89 is provided, and the value adjusting unit 89 deals with the value of the project object calculated by the project collateral value calculating unit 88 in the completed process stage related to the project object in the completed state. Market data,
Alternatively, the value is corrected with reference to the maintenance record after the delivery of the project object recorded in the maintenance record database 84.

【0033】価値調整部89による価値調整は、プロジ
ェクト対象物の引渡し前は売買市場データ、引渡し後は
維持管理記録に依存する。前者は、取引事例との比較に
よるものであり、後者は周知の原価法、収益還元法に基
づく。後者は、具体的には、維持管理記録データベース
84に、プロジェクト対象物の維持管理記録として保管
される、例えば、図18〜図21に示されるマイホーム
点検・補修記録シートに記載された、設備、屋内外、建
具等、特定の点検項目毎ポイントを付し、経過年に従っ
て適当な係数を掛け合わせ、維持管理の度合いを数値表
現することにより実現される。マイホーム点検・補修記
録シートについては、後で詳細に説明する。
The value adjustment by the value adjusting unit 89 depends on the trading market data before the delivery of the project object and the maintenance record after the delivery. The former is based on comparison with transaction cases, and the latter is based on the well-known cost method and profit return method. The latter is, specifically, a facility stored in the maintenance record database 84 as a maintenance record of the project object, for example, the facility described in the home inspection / repair record sheet shown in FIGS. 18 to 21. It is realized by adding points for specific inspection items such as indoors and outdoors, fittings, etc., multiplying appropriate factors according to the elapsed years, and numerically expressing the degree of maintenance. My home inspection / repair record sheet will be explained in detail later.

【0034】図2は、本発明におけるプロジェクトの価
値算定システムでの価値算定の手続きを説明するために
引用したフローチャートである。以下、図2に示すフロ
ーチャートを参照しながら本発明におけるプロジェクト
の価値算定システムの動作について詳細に説明する。
FIG. 2 is a flowchart quoted for explaining the procedure of value calculation in the project value calculation system according to the present invention. Hereinafter, the operation of the project value calculation system according to the present invention will be described in detail with reference to the flowchart shown in FIG.

【0035】第一の実施形態から説明する。担保価値算
定サーバー80は、まず、プロジェクト完成価値算出部
85で、設計図書管理テーブル81からプロジェクト対
象物の完成状態情報を受取り(S101)、また、プロ
ジェクト履行履歴テーブル83からプロジェクト対象物
に係る請負契約総金額情報を受取る(S102)。次
に、プロジェクト工事済価値算出部86で、プロジェク
ト進捗管理テーブル82からプロジェクト対象物におけ
る、請負業者により実施済みの工程毎の進捗状況を受取
り(S103)、また、プロジェクト履行履歴テーブル
83から前記プロジェクト対象物に係る実施済み工程の
請負契約金額情報を受取る(S104)。そして、プロ
ジェクト担保価値算定部88にて、プロジェクト対象物
に係る完成状態情報並びに請負契約総金額情報により算
出されたプロジェクト対象物の完成価値と、プロジェク
ト対象物に係る実施済み工程毎の進捗状況並びに請負契
約総金額情報から、プロジェクト対象物に係る実施済み
工程段階での価値を算出する(S105)。
The first embodiment will be described. In the collateral value calculation server 80, first, the project completion value calculation unit 85 receives the completion status information of the project object from the design book management table 81 (S101), and also the contract related to the project object from the project fulfillment history table 83. The contract total amount information is received (S102). Next, in the project construction completed value calculation unit 86, the progress status of each process in the project object, which has been executed by the contractor, is received from the project progress management table 82 (S103), and the project fulfillment history table 83 is used to retrieve the project. The contract contract amount information of the executed process relating to the object is received (S104). Then, the project collateral value calculation unit 88 calculates the completion value of the project object calculated based on the completion status information and the total contract amount information regarding the project object, and the progress status of each executed process related to the project object and The value of the project object at the completed process step is calculated from the total contract amount information (S105).

【0036】なお、価値調整部89は、上記のようにプ
ロジェクト担保価値算定部88にて算出されたプロジェ
クト対象物に係る実施済み工程段階での価値に対して、
プロジェクト対象物に関する完成状態での売買市場デー
タを参酌して、当該価値の修正を行う。なお、価値調整
部89は、プロジェクト対象物が施工途中で長期間報知
されていた等の特段の事情があるときは、維持管理記録
データベース84に記録されたプロジェクト対象物の引
渡し後の維持管理履歴を参酌して、当該価値の修正を行
う。
The value adjusting unit 89 calculates the value of the project object calculated by the project collateral value calculating unit 88 as described above at the completed process stage.
The value will be corrected by taking into consideration the market data of the completed trading market for the project object. In addition, the value adjusting unit 89 may record the maintenance history of the project subject after the delivery of the project subject recorded in the maintenance record database 84 when there are special circumstances such as that the project subject has been notified for a long time during the construction. In consideration of, correct the value.

【0037】次に、第二の実施形態について説明する。
担保価値算定サーバー80は、まず、プロジェクト完成
価値算出部85で、設計図書管理テーブル81からプロ
ジェクト対象物の完成状態情報を受取り(S201)、
また、プロジェクト履行履歴テーブル83からプロジェ
クト対象物に係る請負契約総金額情報を受取る(S20
2)。次に、プロジェクト追加工事価値算出部87で、
プロジェクト進捗管理テーブル82からプロジェクト対
象物を完成状態とするのに必要な追加実施工程を受取り
(S203)、また、プロジェクト履行履歴テーブル8
3からプロジェクト対象物に係る追加実施工程の請負契
約金額情報を受取る(S204)。
Next, a second embodiment will be described.
In the collateral value calculation server 80, first, the project completion value calculation unit 85 receives the completion status information of the project object from the design book management table 81 (S201),
Further, the contract contract total amount information related to the project object is received from the project fulfillment history table 83 (S20).
2). Next, in the project additional construction value calculation unit 87,
An additional execution process required to complete the project object is received from the project progress management table 82 (S203), and the project implementation history table 8
The contract contract amount information of the additional execution process relating to the project object is received from S3 (S204).

【0038】そして、プロジェクト担保価値算定部88
にて、プロジェクト対象物に係る完成状態情報並びに請
負契約総金額情報により算出されたプロジェクト対象物
の完成価値と、プロジェクト対象物を完成状態とするの
に必要な追加実施工程の実施見込み金額から、プロジェ
クト対象物に係る実施済み工程段階での価値を算出する
(S205)。
Then, the project collateral value calculation unit 88
At, from the completion value of the project object calculated from the completion status information related to the project object and the total contract amount information, and the estimated implementation amount of the additional implementation process necessary to bring the project object to the completed state, The value of the project object at the completed process step is calculated (S205).

【0039】続いて、第三の実施形態について説明す
る。担保価値算定サーバー80は、まず、プロジェクト
工事済価値算出部86で、プロジェクト進捗管理テーブ
ル82からプロジェクト対象物における、請負業者によ
り実施済みの工程毎の進捗状況を受取り(S301)、
また、プロジェクト履行履歴テーブル83からプロジェ
クト対象物に係る実施済み工程の請負契約金額情報を受
取る(S302)。次に、プロジェクト追加工事価値算
出部87で、プロジェクト進捗管理テーブル82からプ
ロジェクト対象物を完成状態とするのに必要な追加実施
工程を受取り(S303)、また、プロジェクト履行履
歴テーブル83からプロジェクト対象物に係る追加実施
工程の請負契約金額情報を受取る(S304)。
Next, the third embodiment will be described. In the collateral value calculation server 80, first, the project construction completed value calculation unit 86 receives, from the project progress management table 82, the progress status of each step of the project object which has been executed by the contractor (S301),
Further, the contract contract amount information of the executed process relating to the project object is received from the project fulfillment history table 83 (S302). Next, the project additional construction value calculation unit 87 receives an additional execution process required to bring the project object into a completed state from the project progress management table 82 (S303), and also receives the project object from the project fulfillment history table 83. The contract contract amount information of the additional execution process related to is received (S304).

【0040】そして、プロジェクト担保価値算定部88
がプロジェクト対象物に係る実施済み工程毎の進捗状況
並びに請負契約総金額情報と、プロジェクト対象物を完
成状態とするのに必要な追加実施工程の実施見込み金額
から、プロジェクト対象物に係る実施済み工程段階での
価値を算出する(S305)。
Then, the project collateral value calculation unit 88
Indicates the progress status of each completed process related to the project object and the total amount of contract contracts, and the estimated amount of additional execution steps required to complete the project object, the executed process related to the project object. The value at the stage is calculated (S305).

【0041】図3は、本発明のプロジェクトの担保価値
算定システムと連携するのに好ましい、プロジェクト完
成保証システムの構成ブロック図である。プロジェクト
の担保価値算定システムは、プロジェクト完成保証シス
テムで用いるデータベースと共用化することで、システ
ムの運用が容易に行われる。すなわち、設計図書管理テ
ーブル81には、設計監理者8が建設業者に対して引き
渡す詳細設計図面を格納する(図8参照)とよい。プ
ロジェクト進捗管理テーブル82には、プロジェクト検
査管理サーバー30における請負業者2により実施され
るプロジェクト対象物における工程毎の工程検査合格の
記録や、プロジェクト進捗管理部23に記録データとし
て管理されるプロジェクト対象物における工程毎の工程
検査合格の記録を用いるとよい。
FIG. 3 is a block diagram showing the construction of a project completion guarantee system which is preferable to cooperate with the project collateral value calculation system of the present invention. The collateral value calculation system for the project can be easily operated by sharing it with the database used in the project completion guarantee system. That is, it is advisable to store the detailed design drawing handed over by the design supervisor 8 to the construction company in the design book management table 81 (see FIG. 8). In the project progress management table 82, a record of the process inspection pass for each process in the project object implemented by the contractor 2 in the project inspection management server 30 and the project object managed as record data in the project progress management unit 23. It is advisable to use a record of process inspection pass for each process in.

【0042】プロジェクト履行履歴テーブル83には、
支払い代金算定部25の定めるプロジェクト支払額を請
負業者2に対して支払うように、出金管理部22によっ
て行われた預託金サーバー10に対する支払い指示を記
録するとよく、またプロジェクト代金決済サーバー20
から預託金サーバー10に指示された工事代金、資材代
金の請負業者、部材メーカ、下請業者に対する支払い指
示でもよい。
In the project fulfillment history table 83,
The payment instruction issued by the withdrawal management unit 22 to the deposit server 10 may be recorded so that the project payment amount determined by the payment amount calculation unit 25 is paid to the contractor 2, and the project price settlement server 20.
It may be a payment instruction to the deposit money server 10 for the construction fee, the material fee contractor, the component maker, and the subcontractor.

【0043】以下、図3を参照しながらプロジェクト完
成保証システムの構成について簡単に説明する。プロジ
ェクト完成保証システムは、プロジェクト代金の預託状
態を管理する預託金サーバー10、プロジェクト代金決
済サーバー20、完成保証管理サーバー40を備えてい
る。担保価値算定サーバー80は、プロジェクト完成保
証システムと連携して情報の共有を図っている。預託金
サーバー10には、プロジェクト代金の預託状態の管理
を容易にする為に、プロジェクト完成保証システムの対
象となるプロジェクト毎に専用口座12が設けられてい
る。
The configuration of the project completion assurance system will be briefly described below with reference to FIG. The project completion guarantee system includes a deposit server 10 that manages the deposit state of project costs, a project payment server 20, and a completion guarantee management server 40. The collateral value calculation server 80 cooperates with the project completion guarantee system to share information. The deposit server 10 is provided with a dedicated account 12 for each project subject to the project completion guarantee system in order to facilitate management of the deposit state of the project price.

【0044】プロジェクト代金決済サーバー20は、預
託金管理部21、出金管理部22、プロジェクト進捗管
理部23、プロジェクト支払い代金テーブル24、支払
い代金算定部25を備えている。預託金管理部21は、
プロジェクト代金の預託状態を管理する預託金サーバー
10から、プロジェクト代金の預託状態を受取る。プロ
ジェクト進捗管理部23は、プロジェクト検査管理サー
バー30から通知される、請負業者2により実施される
プロジェクト対象物における工程毎の工程検査合格が記
録される。プロジェクト支払い代金テーブル24は、プ
ロジェクト対象物における工程毎のプロジェクト支払額
を記録してある。この工程毎の請負代金支払額は、予め
依頼主1と請負業者2との間で合意されるもので、例え
ば標準的な工程毎のプロジェクト支払い規則や、預託金
の預託額並びに預託時期に関する規則に従って定められ
ている(図9参照)。
The project price settlement server 20 includes a deposit management unit 21, a withdrawal management unit 22, a project progress management unit 23, a project payment price table 24, and a payment price calculation unit 25. The deposit management unit 21
The deposit status of the project price is received from the deposit server 10 that manages the deposit status of the project price. The project progress management unit 23 records the process inspection pass for each process in the project object carried out by the contractor 2, which is notified from the project inspection management server 30. The project payment price table 24 records the project payment amount for each process in the project object. The contract payment amount for each process is agreed in advance between the client 1 and the contractor 2. For example, the standard project payment rule for each process, the deposit amount of deposits, and the rule regarding deposit timing. (See FIG. 9).

【0045】支払い代金算定部25は、プロジェクト支
払い代金テーブル24を参照して、プロジェクト進捗管
理部23に記録される工程検査合格に該当する工程に相
当するプロジェクト支払額を定める。出金管理部22
は、預託されたプロジェクト代金から、支払い代金算定
部25の定めるプロジェクト支払額を請負業者2に対し
て支払うように、預託金サーバー10に対して支払い指
示を行う。
The payment price calculation unit 25 refers to the project payment price table 24 to determine the project payment amount corresponding to the process corresponding to the process inspection pass recorded in the project progress management unit 23. Withdrawal Management Department 22
Instructs the deposit server 10 to pay the project payment amount determined by the payment price calculation unit 25 to the contractor 2 from the deposited project price.

【0046】完成保証管理サーバー40は、プロジェク
ト代金の預託されたプロジェクト対象物に関わる完成保
証契約を管理するもので、請負業務引継部42と引継請
負業者テーブル44を有している。引継請負業者テーブ
ル44は、プロジェクト対象物の業務遂行能力を備える
引継請負業者3を登録してある。請負業務引継部42
は、完成保証管理サーバー40に完成保証契約の登録さ
れたプロジェクト対象物について、請負業者2による業
務続行が困難となったとき、引継請負業者テーブル44
に登録された引継請負業者の中からプロジェクト対象物
の業務を引継ぐ引継請負業者3を選定すると共に、プロ
ジェクト進捗管理部23に登録された工程検査合格を用
いて引継により実施される工程を抽出する。請負業務引
継部42のプロジェクト代金支払い先の指定は、出金管
理部22による預託金サーバー10に対する支払い指示
において、工程検査合格に該当する工程を実施した引継
請負業者3としている。
The completion guarantee management server 40 manages the completion guarantee contract relating to the project object for which the project price is entrusted, and has a contract work transfer section 42 and a transfer contractor table 44. The takeover contractor table 44 is registered with the takeover contractor 3 having the business performance of the project object. Contracting Business Transfer Department 42
When the contractor 2 finds it difficult to continue the work for the project object for which the completion guarantee contract is registered in the completion guarantee management server 40, the takeover contractor table 44
The takeover contractor 3 that takes over the work of the project object is selected from among the takeover contractors registered in 1., and the process executed by the takeover is extracted using the process inspection pass registered in the project progress management unit 23. . The project payment destination of the contract work transfer unit 42 is designated as the transfer contractor 3 who has executed the process corresponding to the process inspection pass in the payment instruction to the deposit server 10 by the withdrawal management unit 22.

【0047】このように構成されたプロジェクト完成保
証システムでは、プロジェクト代金決済システムに用い
られるプロジェクト進捗管理部23を用いて、請負業者
2による実施状態を管理している。完成保証管理サーバ
ー40にて、プロジェクト代金の預託されたプロジェク
ト対象物に関わる完成保証契約を管理している場合に、
請負業者2による業務続行が困難となったとき、請負業
務引継部42により引継請負業者テーブル44に登録さ
れた引継請負業者の中からプロジェクト対象物の業務を
引継ぐ引継請負業者3を選定する。出金管理部22は、
預託されたプロジェクト代金から、支払い代金算定部2
5の定めるプロジェクト支払額を、工程検査合格に該当
する工程を実施した請負業者2又は/及び引継請負業者
3に支払うように、預託金サーバー10に対して支払い
指示を行う。このようにして、業務遂行途中に請負業者
2による業務続行が困難となっても、プロジェクト進捗
管理部23と請負業務引継部42により、プロジェクト
対象物の実施を引継請負業者3により円満に引継ぐこと
ができる。
In the project completion guarantee system thus configured, the project progress management section 23 used in the project price settlement system is used to manage the implementation state by the contractor 2. When the completion guarantee management server 40 manages the completion guarantee contract related to the project object for which the project price is entrusted,
When it becomes difficult for the contractor 2 to continue the work, the contracting work takeover unit 42 selects the takeover contractor 3 that takes over the work of the project object from among the takeover contractors registered in the takeover contractor table 44. Withdrawal management unit 22,
From the deposited project price to the payment price calculation unit 2
A payment instruction is issued to the deposit server 10 so that the project payment amount defined by 5 is paid to the contractor 2 or / and the takeover contractor 3 who executed the process corresponding to the process inspection pass. In this way, even if it becomes difficult for the contractor 2 to continue the work in the middle of performing the work, the project progress management unit 23 and the contract work transfer unit 42 allow the transfer contractor 3 to take over the implementation of the project object. You can

【0048】次に、図4を参照しながらプロジェクト完
成保証システムの動作について簡単に説明する。図4
は、プロジェクト完成保証システムでの代金決済の手続
きを説明するフローチャートである。まず、プロジェク
ト代金決済サーバー20は、プロジェクト代金(工事請
負代金)の預託状態を管理する預託金サーバー10か
ら、プロジェクト代金の入金状態を受取る(S110
2)。次に、プロジェクト代金決済サーバー20が、プ
ロジェクト検査管理サーバー30から通知されるプロジ
ェクト対象物における工程毎の工程検査合格を受取る
(S1202〜S1210)。すると、プロジェクト代
金決済サーバー20は、プロジェクト対象物における工
程毎のプロジェクト支払額を記録するプロジェクト支払
い代金テーブル24を参照して、工程検査合格に該当す
る工程に相当するプロジェクト支払額(工事代金)を定
め、プロジェクト支払額を、預託されたプロジェクト代
金から、工程検査合格に該当する工程を実施した請負業
者2に支払うように、預託金サーバー10に対して支払
い指示を行う(S1104〜S1112)。
Next, the operation of the project completion assurance system will be briefly described with reference to FIG. Figure 4
Is a flow chart for explaining a procedure for payment settlement in the project completion guarantee system. First, the project price settlement server 20 receives the deposit state of the project price from the deposit server 10 that manages the deposit state of the project price (construction contract price) (S110).
2). Next, the project price settlement server 20 receives the process inspection pass for each process of the project object notified from the project inspection management server 30 (S1202 to S1210). Then, the project price payment server 20 refers to the project payment price table 24 that records the project payment amount for each process in the project object, and refers to the project payment amount (construction price) corresponding to the process that passes the process inspection. Then, the deposit payment server 10 is instructed to pay the project payment amount from the deposited project price to the contractor 2 who has carried out the process corresponding to the process inspection pass (S1104 to S1112).

【0049】次に、完成保証管理サーバー40は、プロ
ジェクト代金の預託されたプロジェクト対象物に関わる
完成保証契約を管理する(S1300)。即ち、完成保
証契約に関わるプロジェクト対象物について、請負業者
2による業務続行(施工続行)が困難となったとき(S
1302)、完成保証管理サーバー40は、プロジェク
ト対象物の業務遂行能力(施工能力)を備える引継請負
業者を登録してある引継請負業者テーブル44に登録さ
れた引継請負業者から、プロジェクト対象物の業務(施
工)を引継ぐ引継請負業者3を選定すると共に、工程毎
の工程検査合格を用いて引継により実施(施工)される
工程を抽出する(S1304)。そして、完成保証管理
サーバー40は、預託金サーバー10に対する支払い指
示において、工程検査合格に該当する工程を実施(施
工)した引継請負業者3を支払先とする(S130
6)。
Next, the completion guarantee management server 40 manages the completion guarantee contract related to the project object for which the project price has been deposited (S1300). That is, when it becomes difficult for the contractor 2 to continue the work (continuation of construction) for the project object related to the completion guarantee contract (S
1302), the completion guarantee management server 40 receives the work of the project object from the takeover contractor registered in the takeover contractor table 44 in which the takeover contractor having the work performance (construction ability) of the project object is registered. A takeover contractor 3 that takes over (construction) is selected, and a process to be carried out (construction) is extracted by using the process inspection pass for each process (S1304). Then, the completion guarantee management server 40 sets the takeover contractor 3 who has executed (constructed) the process corresponding to the process inspection pass in the payment instruction to the deposit server 10 as the payee (S130).
6).

【0050】これらの施工状態の進行に応じて、担保価
値算定サーバー80は、完成保証契約に関わるプロジェ
クト対象物の工事請負代金情報を受取る(S140
2)。次に、プロジェクト検査管理サーバー30がプロ
ジェクト代金決済サーバー20に対して通知するプロジ
ェクト対象物における工程毎の工程検査合格に随伴し
て、プロジェクト検査管理サーバー30が担保価値算定
サーバー80に対してもプロジェクト対象物における工
程毎の工程検査合格を通知する(S1404、S140
8、S1412、S1416、S1420)。また、実
際の資金の流れも、工程検査合格に該当する工程を実施
した請負業者2に対して、預託金サーバー10からの支
払い完了情報を、担保価値算定サーバー80に対しても
通知する(S1406、S1410、S1414、S1
418、S1420、S1422)。このようにして、
担保価値算定サーバー80には、完成保証契約に関わる
プロジェクト対象物の工事進行状況と、資金の決済情報
が収集される。
In accordance with the progress of these construction states, the collateral value calculation server 80 receives construction contract price information of the project object related to the completion guarantee contract (S140).
2). Next, the project inspection management server 30 notifies the project price settlement server 20 that the project inspection management server 30 sends a project to the collateral value calculation server 80 in accordance with the passing of the process inspection for each process in the project object. Notification of process inspection pass for each process on the object (S1404, S140)
8, S1412, S1416, S1420). Also, regarding the actual flow of funds, the payment completion information from the deposit server 10 is also notified to the collateral value calculation server 80 to the contractor 2 who has executed the process corresponding to the process inspection pass (S1406). , S1410, S1414, S1
418, S1420, S1422). In this way
The collateral value calculation server 80 collects the construction progress status of the project object related to the completion guarantee contract and the settlement information of the funds.

【0051】図5は、本発明の一実施の形態を示す構成
ブロック図である。なお、図5において前記図3と同一
作用をするものには同一符号を付して、説明を省略す
る。図において、依頼主端末63は、依頼主1が用いる
端末装置である。請負業者端末65は、請負業者2が用
いる端末装置である。引継請負業者端末67は、引継請
負業者3が用いる端末装置である。プロジェクト代金決
済管理者端末26は、プロジェクト代金決済サーバー2
0の管理者が用いる端末装置である。プロジェクト検査
管理者端末31は、プロジェクト検査管理サーバー30
の管理者が用いる端末装置である。完成保証管理者端末
46は、完成保証管理サーバー40の管理者が用いる端
末装置である。金融機関端末61は、金融機関60が用
いる端末装置である。
FIG. 5 is a block diagram showing the configuration of an embodiment of the present invention. In FIG. 5, components having the same functions as those in FIG. 3 are designated by the same reference numerals and the description thereof will be omitted. In the figure, a client terminal 63 is a terminal device used by the client 1. The contractor terminal 65 is a terminal device used by the contractor 2. The takeover contractor terminal 67 is a terminal device used by the takeover contractor 3. The project payment settlement manager terminal 26 is the project payment server 2
0 is a terminal device used by the administrator. The project inspection manager terminal 31 is the project inspection management server 30.
Is a terminal device used by the administrator. The completion guarantee administrator terminal 46 is a terminal device used by the administrator of the completion guarantee management server 40. The financial institution terminal 61 is a terminal device used by the financial institution 60.

【0052】担保価値算定サーバー80、預託金サーバ
ー10、プロジェクト代金決済サーバー20、プロジェ
クト検査管理サーバー30並びに完成保証管理サーバー
40には、例えばミニコン、オフコン、サーバーのよう
な高速情報処理能力のあるコンピュータが用いられる。
預託金サーバー10は、プロジェクト代金に引当てるた
めの預託金を管理する情報処理装置で、預託金管理機関
が運営している。専用口座12は、プロジェクト対象物
毎にプロジェクト代金の預託や支払いをするために預託
金サーバー10に設けられる。預託金サーバー10やプ
ロジェクト代金決済サーバー20は、専用口座12の残
高により請負業者2に支払われるプロジェクト代金の預
託状態を知ることができる。
The collateral value calculation server 80, the deposit server 10, the project price settlement server 20, the project inspection management server 30, and the completion guarantee management server 40 are, for example, computers with high-speed information processing capability such as minicomputers, office computers, and servers. Is used.
The deposit server 10 is an information processing device that manages deposits to be allocated to project costs, and is operated by a deposit management institution. The dedicated account 12 is provided in the deposit server 10 in order to deposit and pay the project price for each project object. The deposit server 10 and the project payment server 20 can know the deposit status of the project price paid to the contractor 2 from the balance of the dedicated account 12.

【0053】プロジェクト代金決済サーバー20は、プ
ロジェクト検査管理サーバー30から送られるプロジェ
クト対象物の請負業務の進行状況に応じて、預託金サー
バー10の管理している預託金をプロジェクト代金とし
て請負業者2に支払う状態を管理する情報処理装置で、
プロジェクト代金決済管理機関が運営している。
The project payment server 20 sends the deposit managed by the deposit server 10 to the contractor 2 as the project price according to the progress of the contract work of the project object sent from the project inspection management server 30. An information processing device that manages the payment status,
Operated by the project payment management organization.

【0054】プロジェクト検査管理サーバー30は、プ
ロジェクトの進行状態を管理する検査情報を取扱う情報
処理装置である。プロジェクトが建築請負工事の場合に
は、法的義務としての監理建築士による品質管理検査報
告書の合否情報を用いて、建築目的物の業務進行状態を
監理するとよい。ここで、品質管理検査報告書とは、例
えば住宅の品質確保の促進等に関する法律(以下「品確
法」という)第5条に規定する住宅性能評価書、住宅金
融金庫法代18条の2に規定する住宅の安全性と居住性
に関する基準に該当する耐久性を確認する書類をいう。
監理建築士とは、建築士である工事監理者をいう(建築
基準法第5条の4、建築士法第2条第6項)。プロジェ
クトが請負契約に基づく場合には、依頼主1による任意
の契約条件に検査の内容を含ませておくと良い。完成保
証管理サーバー40は、依頼主1が請負契約の完成保証
特約を締結した場合に、その請負契約の完成保証に必要
な情報を管理する情報処理装置である。
The project inspection management server 30 is an information processing device that handles inspection information for managing the progress of a project. When the project is construction contract work, it is advisable to supervise the work progress of the construction object by using the pass / fail information of the quality control inspection report by the supervising architect as a legal obligation. Here, the quality control inspection report refers to, for example, the housing performance evaluation report stipulated in Article 5 of the Act on Promotion of Ensuring the Quality of Houses (hereinafter referred to as the "Quality Assurance Act"), the Housing Finance Bank Act Article 18-2. A document that confirms the durability corresponding to the standard for safety and habitability of a specified house.
A supervising architect means a construction supervisor who is an architect (Building Standard Act, Article 5-4, Architect Act, Article 2, Paragraph 6). When the project is based on a contract contract, it is advisable to include the contents of the inspection in an arbitrary contract condition by the client 1. The completion guarantee management server 40 is an information processing device that manages the information necessary for the completion guarantee of the contract contract when the client 1 concludes the contract guarantee completion contract.

【0055】プロジェクト対象物の完成保証特約を締結
すると、完成保証特約を締結した請負契約に関して、プ
ロジェクト検査管理サーバー30によりプロジェクトの
進行状態が適切に把握される。そして、プロジェクト対
象物の請負業務を担当している請負業者2による業務続
行が困難な状況に移行したときは、請負業務引継部42
により引継請負業者3を選定して、引継請負業者3によ
る業務を続行してプロジェクト対象物を完成させる。こ
の際に、引継請負業者3の業務代金は、預託金サーバー
10の管理している預託金から支払われるため、依頼主
に不測の損害を生ずるおそれがない。
When the completion guarantee contract for the project object is concluded, the project inspection management server 30 appropriately grasps the progress of the project regarding the contract contract for which the completion guarantee contract is concluded. When the contractor 2 who is in charge of the contract work of the project object has a difficulty in continuing the work, the contract work transfer unit 42.
Then, the takeover contractor 3 is selected, and the work by the takeover contractor 3 is continued to complete the project object. At this time, since the business fee of the takeover contractor 3 is paid from the deposit managed by the deposit server 10, there is no possibility of causing unexpected damage to the client.

【0056】通信網7は、預託金サーバー10、プロジ
ェクト代金決済サーバー20、プロジェクト検査管理サ
ーバー30並びに完成保証管理サーバー40と、依頼主
端末63、請負業者端末65、引継請負業者端末67、
プロジェクト代金決済管理者端末26、プロジェクト検
査管理者端末31、完成保証管理者端末46並びに金融
機関端末61を相互に接続するもので、例えばLAN(L
ocal Area Network)、WAN(Wide Area Network)が用
いられる。通信網7には光ファイバ通信回線、銅線を用
いた有線回線、移動体通信用の無線回線などがある。イ
ンターネットは、通信網7をインフラとして使用するも
ので、通信プロトコルとしてHTTP(Hyper Text Tran
sfer Protocol)やWAP(Wireless Application Protoc
ol)を用い、通信情報がHTML(Hyper Text Markup La
nguage)、XML(eXtensible Markup Language)、WM
L(Wireless Markup Language)のような言語で記載され
たウェブページ情報を伝送する。
The communication network 7 includes a deposit server 10, a project payment server 20, a project inspection management server 30, a completion guarantee management server 40, a client terminal 63, a contractor terminal 65, a takeover contractor terminal 67,
The project price settlement manager terminal 26, the project inspection manager terminal 31, the completion guarantee manager terminal 46, and the financial institution terminal 61 are mutually connected. For example, LAN (L
Local Area Network) and WAN (Wide Area Network) are used. The communication network 7 includes an optical fiber communication line, a wire line using a copper wire, a wireless line for mobile communication, and the like. The Internet uses the communication network 7 as an infrastructure, and HTTP (Hyper Text Tran
sfer Protocol) and WAP (Wireless Application Protoc)
ol) and the communication information is HTML (Hyper Text Markup La
nguage), XML (eXtensible Markup Language), WM
Web page information written in a language such as L (Wireless Markup Language) is transmitted.

【0057】図6は請負業者端末や引継請負業者端末に
表示される画面の一例を示す図で、ここではプロジェク
ト対象物が建築物で、請負契約が建築請負工事の場合に
おける概要を示してある。請負業者端末65の画面に
は、契約管理番号、プロジェクト名、建築主、建築地、
建築請負業者、構造、工期、建物面積、建築面積、延床
面積、施工面積、工事請負代金、工事請負代金支払いの
各欄が設けられている。構造には、木造住宅の場合には
木造軸組工法住宅、2x4工法住宅、プレハブ住宅など
があり、耐火建築物の場合には鉄骨、鉄筋コンクリー
ト、軽量鉄骨、プレキャストコンクリート等の別があ
る。
FIG. 6 is a diagram showing an example of a screen displayed on the contractor terminal or the takeover contractor terminal. Here, an outline is shown in the case where the project object is a building and the contract contract is a construction contract work. . On the screen of the contractor terminal 65, the contract management number, project name, builder, building site,
There are columns for building contractor, structure, construction period, building area, building area, total floor area, construction area, construction contract price, and construction contract payment. The structure includes a wooden framed construction house, a 2x4 construction house, a prefabricated house in the case of a wooden house, and steel frame, reinforced concrete, lightweight steel frame, precast concrete, etc. in the case of a fireproof building.

【0058】図7は請負業者端末や引継請負業者端末に
表示される画面の一例を示す図で、建築請負工事の細目
として仮設工事を示してある。請負業者端末65の画面
には、仮設工事の詳細として、造り方、足場工事、仮設
水道、仮設電気、仮設トイレ、レッカー等の各欄が設け
られている。仮設工事の各欄に対して、仕様、数量、単
価、金額を記入する項目が設けられている。
FIG. 7 is a diagram showing an example of a screen displayed on the contractor terminal or the takeover contractor terminal, and shows temporary work as a detail of the construction contract work. On the screen of the contractor terminal 65, as details of the temporary construction, columns such as how to build, scaffold construction, temporary water supply, temporary electricity, temporary toilet, and wrecker are provided. Items for specifications, quantity, unit price, and amount are provided for each column of temporary construction.

【0059】図8は本発明のプロジェクト代金決済シス
テムとプロジェクト完成保証システムを用いた建築請負
工事の手続きの流れを説明する図である。ここでは、図
において、設計監理者8は、依頼主1としての建築主7
1の意図する建築目的物の設計図面を作成するもので、
併せて請負業者2としての建設業者72に対して建築目
的物の詳細設計図面を引き渡す。なお、建築目的物はプ
ロジェクト対象物に相当し、引継請負業者3は引継建設
業者73に相当している。完成保証機構5は、設計監理
者8、完成保証管理サーバー40並びにプロジェクト代
金決済サーバー20を有機的に統合して、プロジェクト
対象物の完成を依頼主に対して保証する機関で、例えば
法人により設置された情報処理機関を有している。
FIG. 8 is a diagram for explaining the flow of the procedure for the construction contracting work using the project payment system and the project completion guarantee system of the present invention. Here, in the figure, the design supervisor 8 is the architect 7 as the client 1.
To create a design drawing of the intended building objective of 1.
At the same time, the detailed design drawing of the building object is handed over to the contractor 72 as the contractor 2. The construction object corresponds to the project object, and the takeover contractor 3 corresponds to the takeover construction company 73. The completion guarantee mechanism 5 is an organization that organically integrates the design supervisor 8, the completion guarantee management server 40, and the project price settlement server 20 to guarantee the completion of the project object to the client, and is set up by, for example, a corporation. It has a registered information processing organization.

【0060】金融機関60は、建築目的物の建築資金を
供与するもので、銀行のような一般的な融資機能を有す
る金融機関の他、投資組合、投資会社が含まれる。金融
機関の貸付けには、建築主71に対して融資を実行する
建設資金ローン、請負業者2としての建設業者72に対
して融資を実行するコンストラクションローンがある。
投資組合や投資会社のプロジェクトファイナンスや投資
は、プロジェクトの完成および完成後の利回り並びに残
存価値により投資資金を回収するもので、建築主71や
請負業者2としての建設業者72に対してプロジェクト
資金の投資を行う。損保会社62は、損害保険会社であ
って、建築目的物の施工に付随して発生する偶然の事故
に対するリスクヘッジを負担する。
The financial institution 60 provides a construction fund for a construction object, and includes a financial institution having a general lending function such as a bank, an investment union, and an investment company. The lending by the financial institution includes a construction financing loan for lending to the building owner 71 and a construction loan for lending to the construction company 72 as the contractor 2.
Project finance and investment of investment unions and investment companies collect investment funds by the completion of the project, the yield after completion, and the residual value, and the project funds are provided to the building owner 71 and the contractor 72 as the contractor 2. Make an investment. The non-life insurance company 62 is a non-life insurance company, and bears risk hedging against accidental accidents that accompany the construction of the building object.

【0061】部材メーカ64は、建築目的物の施工に用
いられる内装材、外装材、建材等を建設業者72に供給
する。下請業者66は、建設業者72の指示に従い、建
築目的物の施工を行うもので、仮設工事、基礎工事、屋
根工事、外壁工事、内装工事、建具工事、板金工事、左
官工事、タイル工事、塗装工事、電気工事、給排水道工
事、ガス配管工事、設備機器工事、美装工事、外溝工事
等の各工事の専門業者が該当する。部材メーカ64と下
請業者66は、プロジェクト代金決済サーバー20との
関係では、請負業者2として扱われる。
The member maker 64 supplies the construction company 72 with interior materials, exterior materials, building materials and the like used for construction of the construction object. The subcontractor 66 carries out the construction of the construction object according to the instructions of the construction company 72. Temporary construction, foundation construction, roof construction, outer wall construction, interior construction, joinery construction, sheet metal construction, plastering construction, tile construction, painting. Applicable to specialists in each work such as construction, electrical work, water supply and drainage work, gas piping work, equipment and equipment work, beauty work, and outer trench work. The member maker 64 and the subcontractor 66 are treated as the contractor 2 in relation to the project price settlement server 20.

【0062】次に、図8を用いて建築請負工事の手続き
の流れを説明する。最初に建築主71と設計監理者8の
間で、建築目的物の詳細打合せが行われる(ステップ
)。建築目的物の詳細が建築主71と設計監理者8の
間で合意に達すると、設計監理者8は建設業者72に対
して詳細設計図面を引き渡す(ステップ)。これに対
して、建設業者72から設計監理者8に対して、見積明
細が提供される(ステップ)。
Next, the procedure of the construction contracting work will be described with reference to FIG. First, the building owner 71 and the design supervisor 8 hold a detailed meeting on the building object (step). When the details of the building object are agreed between the building owner 71 and the design supervisor 8, the design supervisor 8 hands over the detailed design drawing to the builder 72 (step). On the other hand, the construction contractor 72 provides the design supervisor with the quotation details (step).

【0063】次に、完成保証機構5は、プロジェクト代
金決済システムを用いるために、建設業者72から建築
目的物の所有権を譲受ける(ステップA)。なお、建
築目的物の所有権を譲受ける物権的構成に代えて、建築
目的物の工事請負代金の受取りに関して債権譲渡を受け
る債権的構成としてもよい。また、完成保証機構5は、
建築主71が建築目的物の工事請負契約を途中で解除し
ようとする場合に、既に建築目的物の工事が進行した工
程に対応する工事請負代金に対しては、プロジェクト代
金から優先して弁済を受ける特約を締結する(ステップ
B)。なお、工事途中での工事請負契約解除に対し
て、優先弁済の特約を締結するのに代えて、建築主71
から建築目的物の先取特権の譲渡を受ける構成としても
よい。さらに、完成保証機構5は、プロジェクト代金決
済システムを用いて部材メーカ64や下請業者66に支
払保証を行い(ステップC)、建築主71に対しては
完成保証書を渡す(ステップD)。なお、建築主71
若しくは金融機関60の合意があれば、部材メーカ64
や下請業者66と同様にして、建設業者72に直接支払
い保証や支払いを行ってもよい。
Next, the completion guarantee mechanism 5 receives the ownership of the construction object from the builder 72 in order to use the project price settlement system (step A). Note that, instead of the physical property structure in which the ownership of the building object is transferred, a receivable structure in which a claim is transferred with respect to the receipt of the construction contract price of the building object may be adopted. In addition, the completion assurance mechanism 5
When the builder 71 tries to cancel the construction contract contract for the construction object on the way, for the construction contract price corresponding to the process in which the construction of the construction object has already proceeded, priority is given to the payment from the project price. Conclude the special contract to receive (step B). In addition, instead of concluding a preferential repayment contract for the cancellation of the construction contract contract during construction, the builder 71
It may be configured to receive the transfer of the lien of the building object from the company. Further, the completion guarantee mechanism 5 guarantees the payment to the member maker 64 and the subcontractor 66 by using the project price settlement system (step C), and passes the completion guarantee to the builder 71 (step D). The architect 71
Or, if there is an agreement from the financial institution 60, the component manufacturer 64
Similarly to the subcontractor 66 or the subcontractor 66, the construction contractor 72 may be directly provided with a payment guarantee or payment.

【0064】金融機関60は、建築目的物の工事請負代
金をプロジェクト資金の投融資として建築主71に供与
したり(ステップA)、或いはプロジェクト資金の投
融資として請負業者2に投融資される状態で預託される
(ステップB)。預託されたプロジェクト資金の投融
資は、プロジェクト代金決済サーバー20にて管理され
る。また、プロジェクト完成保証システムが不測の災害
によって影響を受けないように、損保会社62との間で
建築目的物の施工に関する保険契約を締結する(ステッ
プC)。保険契約によって、建設業者72は工事損害
保険、労働災害、PL(製造物責任法)、火災等に対す
るリスクヘッジを行うことができる(ステップD)。
The financial institution 60 provides the construction contractor for the construction object to the building owner 71 as an investment and loan of the project fund (step A), or makes a loan to the contractor 2 as an investment and loan of the project fund. (Step B). Investment and loan of the deposited project funds are managed by the project price settlement server 20. Further, in order to prevent the project completion guarantee system from being affected by an unforeseen disaster, an insurance contract regarding the construction of the construction object is concluded with the non-life insurance company 62 (step C). The insurance contract allows the construction company 72 to carry out risk hedging against construction damage insurance, occupational accidents, PL (Product Liability Law), fire, etc. (step D).

【0065】建築主71は、建築目的物の工事請負代金
を預託して、プロジェクト代金決済サーバー20に支払
い権限を委譲する(ステップ)。現実の預託金の管理
は預託金サーバー10により行われる。建設業者72は
建設現場において、建築目的物の施工を行う(ステップ
)。そして、建設業者72は、必要に応じて品確法の
予定する程度の水準で、建築目的物の施工状態を自主検
査する(ステップ)。そして、建設業者72は自主検
査の結果を完成保証機構5に報告する(ステップ)。
この報告は、建築目的物に対して予め定められた工程が
完了する度に、遅滞なく工程毎に行う。
The builder 71 deposits the construction contract price of the construction object and transfers the payment authority to the project price settlement server 20 (step). The actual deposit management is performed by the deposit server 10. The construction company 72 executes the construction of the construction object at the construction site (step). Then, the construction company 72 voluntarily inspects the construction state of the construction object at a level as scheduled by the Product Assurance Act, if necessary (step). Then, the construction company 72 reports the result of the self-inspection to the completion assurance mechanism 5 (step).
This report is made for each process without delay each time a predetermined process is completed for the building object.

【0066】建築目的物の施工状態が進行して、設計監
理者8による施工状態検査が必要な工程の施工が完了す
ると、遅滞なく設計監理者8が建設現場に出向いて、建
築目的物の施工状態を検査する(ステップ10)。そし
て、設計監理者8は建築目的物の施工状態検査結果を、
検査対象となる工程毎にプロジェクト検査管理機構9に
知らせる(ステップ11)。
When the construction state of the building object progresses and the construction of the process requiring the construction state inspection by the design supervisor 8 is completed, the design supervisor 8 goes to the construction site without delay and constructs the construction object. Inspect the condition (step 10). Then, the design supervisor 8
The project inspection management mechanism 9 is notified for each process to be inspected (step 11).

【0067】プロジェクト検査管理機構9では、プロジ
ェクト検査管理サーバー30に設計監理者8による建築
目的物の施工状態検査結果を記録する。さらに、プロジ
ェクト検査管理機構9の建築監理者による施工状態検査
が必要な工程の施工が完了すると、遅滞なく建築監理者
によって、建築目的物の施工状態検査が行われる(ステ
ップ12)。もし該当する工程の検査結果が合格であれ
ば、プロジェクト検査管理機構9(プロジェクト検査管
理サーバー30)からプロジェクト代金決済サーバー2
0に対して、支払い指示がなされる(ステップ13)。
In the project inspection management mechanism 9, the project inspection management server 30 records the construction state inspection result of the building objective by the design supervisor 8. Further, when the construction supervision of the project inspection management organization 9 completes the construction of the process requiring the construction state inspection, the construction supervision person conducts the construction state inspection of the construction object without delay (step 12). If the inspection result of the corresponding process is passed, the project inspection management mechanism 9 (project inspection management server 30) to the project payment server 2
A payment instruction is issued to 0 (step 13).

【0068】次に、図4を参照して、図9(B)の請負
工事代金支払い規定に準拠する場合を例に、プロジェク
ト代金決済システムを説明する。プロジェクト代金決済
サーバー20は、建築目的物の工事請負代金の預託状態
を管理する預託金サーバー10から、建築目的物の工事
請負代金の預託状態を受取る(S1102)。次に、プ
ロジェクト検査管理サーバー30から基礎工事完了検査
合格を通知されると(S1202)、プロジェクト代金
決済サーバー20は基礎工事代金を請負業者2、資材を
供給した部材メーカ64、現実の施工をした下請業者6
6に支払うように、預託金サーバー10に指示する(S
1104)。
Next, with reference to FIG. 4, the project price settlement system will be described by taking the case of complying with the contract construction price payment regulation of FIG. 9B as an example. The project price settlement server 20 receives the deposit state of the construction contract price of the building object from the deposit server 10 that manages the deposit state of the construction contract price of the building object (S1102). Then, when the project inspection management server 30 notifies that the foundation construction completion inspection has passed (S1202), the project price settlement server 20 did the contractor 2 for the foundation construction price, the member manufacturer 64 who supplied the material, and the actual construction. Subcontractor 6
Direct deposit server 10 to pay 6 (S
1104).

【0069】プロジェクト検査管理サーバー30から屋
根工事完了検査合格を通知されると(S1204)、プ
ロジェクト代金決済サーバー20は屋根工事代金を請負
業者2、資材を供給した部材メーカ64、現実の施工を
した下請業者66に支払うように、預託金サーバー10
に指示する(S1106)。プロジェクト検査管理サー
バー30から内装下地工事完了検査合格を通知されると
(S1206)、プロジェクト代金決済サーバー20は
内装下地工事代金を請負業者2、資材を供給した部材メ
ーカ64、現実の施工をした下請業者66に支払うよう
に、預託金サーバー10に指示する(S1108)。
When the project inspection management server 30 notifies that the roof construction completion inspection has been passed (S1204), the project price settlement server 20 performs the roof construction fee on the contractor 2, the member manufacturer 64 who has supplied the material, and the actual construction. Deposit server 10 to pay subcontractor 66
(S1106). When the project inspection management server 30 notifies the completion of the interior groundwork completion inspection (S1206), the project price settlement server 20 contracts the interior groundwork price to the contractor 2, the material manufacturer 64 who supplied the material, and the subcontractor who actually performed the construction. The deposit server 10 is instructed to pay to the trader 66 (S1108).

【0070】プロジェクト検査管理サーバー30から工
事完了検査合格を通知されると(S1208)、プロジ
ェクト代金決済サーバー20は工事完了代金を請負業者
2に支払うように、預託金サーバー10に指示する(S
1110)。最後に、プロジェクト検査管理サーバー3
0から経過観察検査合格を通知されると(S120
8)、プロジェクト代金決済サーバー20は保留金を一
括して請負業者2、資材を供給した部材メーカ64、現
実の施工をした下請業者66に支払うように、預託金サ
ーバー10に指示する(S1112)。
When the project inspection management server 30 notifies the construction completion inspection pass (S1208), the project payment server 20 instructs the deposit server 10 to pay the construction completion payment to the contractor 2 (S).
1110). Finally, the project inspection management server 3
When the follow-up inspection pass is notified from 0 (S120
8), the project price settlement server 20 instructs the deposit server 10 to collectively pay the reserved amount to the contractor 2, the material manufacturer 64 that has supplied the material, and the subcontractor 66 that has actually performed the construction (S1112). .

【0071】次に、プロジェクト代金決済システムに加
えて、プロジェクト完成保証システムの特約を建築主7
1が締結した場合について説明する。プロジェクト完成
保証システムの特約を用いて、建築目的物の施工に対す
る完成保証契約を締結し、引継建設業者73の選定を予
め予約しておくことで、建築主71には以下の効果があ
る。 完成保証契約により請負工事契約の履行が保証される
ので、建築目的物の完成及び品質並びに仕様が保証さ
れ、建築主71は安心して建設業者に建築目的物の施工
を依頼できる。 建設業者72に請負工事の施工が困難な状況が発生し
ても、引継建設業者73による請負工事契約の履行が保
証されるので、建築目的物が確実に完成する。
Next, in addition to the project price settlement system, the contractor of the project completion guarantee system is provided with a contract.
The case where 1 is concluded will be described. By concluding a completion guarantee contract for the construction of the construction object using the special contract of the project completion guarantee system and pre-selecting the succeeding construction company 73, the builder 71 has the following effects. Since the completion guarantee contract guarantees the performance of the contract work contract, the completion, quality and specifications of the building object are guaranteed, and the builder 71 can request the builder to construct the building object with peace of mind. Even if the contractor 72 encounters a situation in which it is difficult to carry out the contract work, the successor contractor 73 guarantees the fulfillment of the contract work contract, so that the construction object is surely completed.

【0072】引継建設業者73の選定基準は、建設現場
の所在地と引継建設業者73の所在地が同じ地域内にあ
るか、引継建設業者73の業務遂行能力に比較して建築
目的物の施工規模が適切であるか、引継建設業者73の
施工単価は市場価格に比較して適切であるか等を総合的
に判断して行うものである。
The selection criterion for the takeover construction company 73 is that the location of the construction site and the location of the takeover construction company 73 are in the same area, or that the construction scale of the construction object is compared with the work performance of the takeover construction company 73. Whether or not it is appropriate, whether the construction unit price of the takeover construction company 73 is appropriate in comparison with the market price, etc. is comprehensively judged.

【0073】図8において、破線部分がプロジェクト完
成保証システムの手続きの流れを説明するものである。
完成保証管理サーバー40において、引継請負業者テー
ブル44に登録された引継請負業者3としての引継建設
業者73の中から、建築目的物の施工を引継ぐ能力のあ
る引継建設業者73を選定しておく(イ)。そして、完
成保証契約に関わる建築目的物について、請負業者2と
しての建設業者72による業務続行が困難となったと
き、完成保証管理サーバー40にて抽出された引継建設
業者73に対して、建築主71による残工事の発注が行
われる(ロ)。引継建設業者73は、建設現場において
建築目的物の施工における残工事を施工する(ハ)。す
ると、完成保証管理サーバー40はプロジェクト代金決
済サーバー20による預託金サーバー10に対する支払
い指示において、残工事に対する工程検査合格を条件と
して、残工事の実施代金を引継建設業者73、資材を供
給した部材メーカ64、現実の施工をした下請業者66
に支払う(ニ)。
In FIG. 8, the broken line portion illustrates the procedure flow of the project completion assurance system.
In the completion guarantee management server 40, the takeover contractor 73 having the ability to take over the construction of the building object is selected from among the takeover contractors 73 as the takeover contractor 3 registered in the takeover contractor table 44 ( I). When it becomes difficult for the contractor 72 as the contractor 2 to continue the operation of the construction object related to the completion guarantee contract, the successor 73, extracted by the completion guarantee management server 40, is requested to the builder. The remaining work is ordered by 71 (b). The takeover construction company 73 carries out the remaining work in the construction of the construction object at the construction site (C). Then, the completion guarantee management server 40, in the payment instruction to the deposit server 10 by the project price settlement server 20, on condition that the process inspection pass for the remaining work is passed, the execution price of the remaining work is taken over by the contractor 73 and the member manufacturer who supplied the material. 64, subcontractor 66 who did the actual construction
Pay to (d).

【0074】図8において、二点鎖線部分がプロジェク
ト完成保証システムとプロジェクトの担保価値算定シス
テムの連携における手続きの流れを説明するものであ
る。担保価値算定サーバー80には、設計監理者8が建
設業者に対して引き渡す詳細設計図面が保存されると共
に、詳細設計図面の書誌的事項が設計図書管理テーブル
81に保存される(ホ)。また、担保価値算定サーバー
80は、プロジェクト検査管理機構9や建設業者72に
より実施されるプロジェクト対象物における工程毎の工
程検査合格の記録をプロジェクト進捗管理テーブル82
に保存する(ヘ)。さらに、担保価値算定サーバー80
は、プロジェクト代金決済サーバー20から預託金サー
バー10に指示された工事代金、資材代金の請負業者、
部材メーカ、下請業者に対する支払い指示をプロジェク
ト履行履歴テーブル83に保存する(ト)。
In FIG. 8, the chain double-dashed line portion illustrates the procedure flow in the cooperation between the project completion guarantee system and the project collateral value calculation system. The collateral value calculation server 80 stores the detailed design drawing handed over by the design supervisor 8 to the builder, and the bibliographic items of the detailed design drawing are stored in the design book management table 81 (e). In addition, the collateral value calculation server 80 records a record of the process inspection pass for each process in the project object carried out by the project inspection management mechanism 9 and the construction company 72 in the project progress management table 82.
Save to (F). Furthermore, the collateral value calculation server 80
Is a contractor for the construction price and the material price instructed by the project price settlement server 20 to the deposit server 10.
The payment instruction to the component manufacturer and the subcontractor is stored in the project fulfillment history table 83 (g).

【0075】次に、図4の設例を用いて、プロジェクト
完成保証システムを説明する。当初の請負業者2は、建
築目的物について、基礎工事完了検査合格と屋根工事完
了検査合格を受けられる段階まで施工し、その後施工続
行が困難となった(S1302)。すると、完成保証管
理サーバー40により引継請負業者3が選定される(S
1304)。引継請負業者3は、建築目的物について、
内装下地工事完了検査合格と完成検査合格判定を受けら
れる段階まで施工して、建築目的物を建築主71に引渡
せる状態まで施工した。そこで、完成保証管理サーバー
40、プロジェクト代金決済サーバー20並びに預託金
サーバー10による連携が成立して、引継請負業者3、
資材を供給した部材メーカ64、現実の施工をした下請
業者66に対して、内装下地工事代金と工事完了代金が
支払われる。
Next, the project completion guarantee system will be described using the example of FIG. The initial contractor 2 constructed the construction object up to the stage where the foundation construction completion inspection passed and the roof construction completion inspection passed, and then it became difficult to continue the construction (S1302). Then, the completion guarantee management server 40 selects the takeover contractor 3 (S
1304). The takeover contractor 3 is
The construction was carried out until the completion of the interior groundwork completion inspection and the completion inspection pass judgment, and the construction object was delivered to the building owner 71. Therefore, the completion guarantee management server 40, the project price settlement server 20, and the deposit server 10 are linked to each other, and the takeover contractor 3,
The interior foundation work price and the construction completion price are paid to the member manufacturer 64 that has supplied the material and the subcontractor 66 that has actually performed the construction.

【0076】図9は本発明のプロジェクト代金決済シス
テムにおける代金預託規定と代金支払い規定の一例を示
す図で、(A)は請負工事代金預託規定、(B)は請負
工事代金支払い規定を示している。代金預託規定は、事
前調査費として建築目的物一戸当たりの一定額(例えば
20万円)、契約締結時、工事着手時、屋根完了時、内
装下地完了時、完成検査合格時にそれぞれ請負工事代金
の1/5を建築主71が預託すればよい。
FIG. 9 is a diagram showing an example of the deposit deposit regulation and the deposit payment regulation in the project payment settlement system of the present invention. There is. The price deposit rules are a fixed amount per building object (for example, 200,000 yen) as a preliminary inspection fee, contract contract, contract start, construction start, roof completion, interior groundwork completion, completion inspection pass The builder 71 should deposit 1/5.

【0077】代金支払い規定は、基礎工事完了検査合
格、屋根工事完了検査合格、内装下地工事完了検査合
格、工事完了検査合格に対して、基礎工事、屋根工事、
内装下地工事、工事完了の各工程の工事代金に対して9
0%を建設業者72、資材を供給した部材メーカ64、
現実の施工をした下請業者66に支払う。そして、建築
目的物を建築主71に引渡し後、一定期間経過後に経過
観察検査を行い、経過観察検査に合格すれば各工程の工
事代金の留保金を支払う。経過観察検査は、例えば3箇
月経過後に行うアフターメンテナンス点検をいう。留保
金は、基礎工事、屋根工事、内装下地工事、工事完了の
各工事代金の10%程度である。
The payment rules are as follows: basic construction completion inspection passed, roof construction completion inspection passed, interior groundwork completion inspection passed, construction completion inspection passed, foundation construction, roof construction,
9 for the work price of each process of interior groundwork and construction completion
0% is the construction company 72, 64 is the material manufacturer that supplied the materials,
Pay the subcontractor 66 who did the actual construction. Then, after passing the building object to the building owner 71, a follow-up inspection is performed after a certain period of time, and if the follow-up inspection is passed, a reservation for the construction fee of each process is paid. The follow-up inspection is, for example, an after-maintenance inspection performed after 3 months. Retainage is about 10% of the basic construction, roof construction, interior groundwork, and construction completion.

【0078】図10は建築目的物の工程と、プロジェク
ト検査管理サーバーで取扱う工程検査の一例を示す図
で、木造軸組工法住宅3階建ての場合を示してある。木
造軸組工法住宅では、施工工程として、仮設工事10
1、基礎工事102、躯体工事103、屋根工事10
4、外壁工事105、内装下地工事106、内装工事1
07、竣工108が存在している。基礎工事102に
は、鉄筋組立加工、定着、ピッチ、開口補強、基礎立上
り幅等があり、コンクリート打設、アンカーチェックも
含まれる。躯体工事103には、床下設備配線、配管、
一階床組、防腐防蟻処理、小屋根が含まれる。屋根工事
104には、防湿シート、水切鉄板、屋根仕上材等が含
まれる。外壁工事105には、内外部金物確認、サイデ
ィング、サッシ廻り防水テープ等が含まれる。内装下地
工事106には、内部隠蔽部設備配線・配管等、内部合
板、PB貼付等、各種設備機器の設置等が含まれる。内
装工事107には、内装仕上げ、設備機器取付、設備配
管仕上げ等が含まれる。
FIG. 10 is a diagram showing an example of the process of the construction object and the process inspection handled by the project inspection management server, showing the case of a three-story wooden frame construction method house. For a wooden frame construction method, temporary construction work 10
1, foundation work 102, skeleton work 103, roof work 10
4, exterior wall work 105, interior groundwork 106, interior work 1
07, completion 108 exists. The foundation work 102 includes rebar assembly processing, anchorage, pitch, opening reinforcement, foundation rise width, and the like, including concrete placement and anchor check. The frame work 103 includes underfloor equipment wiring, piping,
Includes 1st floor flooring, antiseptic treatment, and small roof. The roof construction 104 includes a moisture-proof sheet, a draining iron plate, a roof finishing material, and the like. The outer wall work 105 includes confirmation of internal and external hardware, siding, waterproof tape around the sash, and the like. The interior ground work 106 includes installation of various equipment and devices such as internal concealment unit equipment wiring and piping, internal plywood, PB sticking, and the like. The interior work 107 includes interior finish, equipment installation, equipment piping finish, and the like.

【0079】プロジェクト検査管理機構9は、建築目的
物の各工程に対して検査を行い、検査結果をプロジェク
ト検査管理サーバー30に格納する。検査には監理検
査、品質管理検査、設備監理検査の3態様がある。プロ
ジェクト検査管理サーバー30からプロジェクト代金決
済サーバー20に対して、支払い指示がなされる条件と
しての建築目的物の施工状態検査には、監理検査、品質
管理検査、設備監理検査の何れか一種類でもよく、また
住宅金融公庫の定める検査規則に従ってもよく、要する
に建築目的物の施工状態検査として利用適格を有するも
のであれば良い。
The project inspection management mechanism 9 inspects each process of the building object and stores the inspection result in the project inspection management server 30. There are three types of inspection: supervision inspection, quality control inspection, and equipment supervision inspection. The construction inspection of the construction object as a condition for the payment instruction from the project inspection management server 30 to the project payment server 20 may be any one of supervision inspection, quality control inspection, and equipment supervision inspection. Moreover, it may be in accordance with the inspection rules stipulated by the Housing Finance Corporation, in short, as long as it is eligible for use as an inspection of the construction condition of the building object.

【0080】ここで、監理検査とは、設計監理者による
責任において、建築目的物の工事を設計図書と照合し、
その工事が設計図書のとおり実施されているか確認する
ことを言う(建築基準法第5条の4)。木造軸組工法住
宅3階建ての場合には、第1回監理検査201は遣方完
了時に行われ、第2回監理検査202は基礎配筋完了時
に行われ、第3回監理検査203は棟上げ・火打ち・筋
交等において行われ、第4回監理検査204は屋根工事
完了時に行われ、第5回監理検査205は内装下地完了
時に行われ、第6回監理検査206は建物竣工検査とし
て行われる。
Here, the supervision inspection is the responsibility of the design supervision person to check the construction of the construction object with the design document,
It is to confirm that the work is being carried out according to the design documents (Building Standard Act Article 5-4). In the case of a three-story wooden frame construction method, the first supervision inspection 201 is performed when the usage is completed, the second supervision inspection 202 is performed when the basic bar arrangement is completed, and the third supervision inspection 203 is raised.・ Fourth inspection 204 is performed at the completion of roof construction, fifth inspection 205 is performed at the completion of interior groundwork, and sixth inspection 206 is performed as a building completion inspection. Be seen.

【0081】品質管理検査とは、建築目的物の工事を設
計図書と照合し、その工事が設計図書のとおり実施され
ているか詳細に確認することを言う(品確法第5条)。
木造軸組工法住宅3階建ての場合には、第1回品質管理
検査221は基礎配筋完了時に行われ、第2回品質管理
検査222は一階床組完了時に行われ、第3回品質管理
検査223は小屋根完了時に行われ、第4回品質管理検
査224は屋根工事完了時に行われ、第5回品質管理検
査225は内装下地完了時に行われ、第6回品質管理検
査226は建物竣工検査として行われる。
Quality control inspection refers to checking the construction work of a building object with a design document and confirming in detail whether the construction work is performed according to the design document (Article 5 of the Product Assurance Law).
In the case of a three-story wooden frame construction method, the first quality control inspection 221 is performed when the basic bar arrangement is completed, the second quality control inspection 222 is performed when the first floor is completed, and the third quality inspection is performed. The control inspection 223 is performed when the small roof is completed, the fourth quality control inspection 224 is performed when the roof construction is completed, the fifth quality control inspection 225 is performed when the interior groundwork is completed, and the sixth quality control inspection 226 is the building. It is performed as a completion inspection.

【0082】設備監理検査とは、建築目的物の設備を設
計図書と照合し、その設備が設計図書のとおり実施され
ているか確認することを言う。木造軸組工法住宅3階建
ての場合には、第1回設備監理検査241は一階床組完
了時に行われ、第2回設備監理検査242は建物竣工検
査として行われる。
The equipment supervision inspection means checking the equipment of the construction object with the design document and confirming whether the equipment is carried out according to the design document. In the case of a three-story wooden frame construction method, the first equipment supervision inspection 241 is performed when the first floor floor construction is completed, and the second equipment supervision inspection 242 is performed as a building completion inspection.

【0083】次に、プロジェクト進捗管理テーブル82
での記録に用いて好適な、プロジェクト対象物としての
建築目的物の品質管理検査報告書について説明する。図
11は建築目的物の施工状態検査として用いられる品質
管理検査報告書の表紙部を示している。品質管理検査報
告書の表紙部には、建築目的物の品質管理検査を担当し
た監理建築士の氏名が表示され、工事概要欄と品質管理
検査の検査日欄が設けられている。工事概要欄には、工
事名、建設地住所、建築主氏名、建築主住所、工事請負
業者、工事監理者、現場担当係員、敷地面積、述べ床面
積、構造、階数、建築確認の表示、公的中間検査済証、
公的完了検査済証の各欄が設けられている。公的中間検
査済証と公的完了検査済証には、検査日時と許可番号の
表示がなされる。品質管理検査の検査日欄には、各回の
品質管理検査のために基礎工事完了日時と検査日、一階
床組完了日時と検査日、小屋根完了日時と検査日、屋根
工事完了日時と検査日、内装下地完了日時と検査日、建
物竣工日時と検査日を表記する。
Next, the project progress management table 82
The quality control inspection report of the building object as the project object, which is suitable for the recording in the above, will be described. FIG. 11 shows the cover portion of the quality control inspection report used as the construction state inspection of the building object. On the cover of the quality control inspection report, the name of the supervising architect in charge of the quality control inspection of the building object is displayed, and a construction summary column and an inspection date column of the quality control inspection are provided. In the construction summary column, the construction name, construction site address, architect name, builder address, construction contractor, construction supervisor, site staff, site area, statement floor area, structure, number of floors, building confirmation display, public Intermediate inspection certificate,
Each column of official completion inspection certificate is provided. On the official intermediate inspection certificate and official completion inspection certificate, the date and time of the inspection and the permit number are displayed. In the inspection date column of the quality control inspection, for each quality control inspection, the basic construction completion date and time, inspection date, first floor floor assembly completion date and inspection date, small roof completion date and inspection date, roof construction completion date and time and inspection The date, the date and time when the interior groundwork is completed and the inspection date, and the date and time when the building is completed and the inspection date are described.

【0084】図12は基礎工事完了時に行われる第1回
品質管理検査報告書を示す図である。第1回品質管理検
査報告書では、構造の安定に関する性能表示事項とし
て、地盤又は杭の許容支持力等及びその設定方法、基礎
の構造方法及び形式等、耐震等級、耐風等級、耐積雪等
級が設けられている。検査項目としての地盤に対して、
確認内容として地盤の種類と支持力、地盤調査による確
認、地盤改良及び杭の状況がある。なお各確認内容欄に
は、検査方法の選択欄、判定結果としての適と不適の選
択をする欄、指示事項欄が設けられている。検査項目と
しての地業に対して、確認内容として栗石の状況、捨て
コンクリートの状況、防湿フィルムの状態がある。検査
方法には、A:目視、B:計測、C:施工関連図書の確
認、D:写真の確認の何れかが選択される。
FIG. 12 is a view showing the first quality control inspection report which is carried out when the foundation work is completed. In the 1st quality control inspection report, the allowable bearing capacity of the ground or pile and its setting method, the construction method and type of foundation, seismic resistance class, wind resistance class, snow resistance class, etc. It is provided. For the ground as an inspection item,
The contents of confirmation include the type and bearing capacity of the ground, confirmation by ground survey, ground improvement and pile condition. In addition, each confirmation content column is provided with an inspection method selection column, a column for selecting whether the inspection result is appropriate or not, and an instruction item column. Regarding the groundwork as an inspection item, the details of the confirmation include the condition of cobblestone, the condition of abandoned concrete, and the condition of moisture-proof film. As the inspection method, any one of A: visual inspection, B: measurement, C: confirmation of construction-related books, and D: confirmation of photograph is selected.

【0085】基礎の構造方法及び形式等の性能表示事項
について、検査項目としての基礎2(形式)に対して、
確認内容として基礎の構造方法、基礎の形式がある。耐
震等級、耐風等級、耐積雪等級の性能表示事項につい
て、検査項目としての基礎1(寸法・配筋)に対して、
確認内容として基礎の配置、根入れの深さ、立上り部分
の高さと厚さ、基礎底盤の寸法、鉄筋(主筋・補強筋)
の径、位置、被覆の状況欄がある。さらに、開口部の補
強、被覆の状況、鉄筋・ミルシートの確認、アンカーボ
ルト・ホールダウンアンカーの品質、埋め込み長さ、位
置が確認内容として設けられている。基礎1(コンクリ
ート・型枠)に対して、確認内容として基礎コンクリー
トの配合表、型枠の状況がある。
Regarding the performance display items such as the structure method and the form of the foundation, with respect to the foundation 2 (form) as the inspection item,
The contents of confirmation include the structure method of the foundation and the format of the foundation. For performance indication items such as earthquake resistance class, wind resistance class, snow resistance class, with respect to basic 1 (dimensions and bar arrangement) as inspection items,
The contents of the confirmation include the placement of the foundation, the depth of the rooting, the height and thickness of the rising portion, the dimensions of the base of the foundation, and the reinforcing bars (main bars and reinforcing bars).
There are columns for diameter, position, and coating status. Furthermore, the contents of confirmation include reinforcement of the opening, the condition of coating, confirmation of reinforcing bars and mill sheets, quality of anchor bolts and hole down anchors, embedding length, and position. For Foundation 1 (concrete and formwork), the contents of confirmation include the mix of basic concrete and the condition of the formwork.

【0086】図13は一階床組完了時に行われる第2回
品質管理検査報告書を示す図である。第2回品質管理検
査報告書では、構造の安定に関する性能表示事項として
耐震等級、耐風等級、耐積雪等級が設けられている。こ
の耐震等級、耐風等級、耐積雪等級の性能表示事項につ
いて、検査項目としての土台・枠組がある。土台・枠組
に対する確認内容として、土台の品質、寸法・形状、継
手、金物位置があり、さらにアンカーボルト・ホールダ
ウンアンカーの品質、埋め込み長さ、位置、締付け状
況、土台の水平レベルがある。
FIG. 13 is a diagram showing a second quality control inspection report performed at the completion of the first floor assembly. In the 2nd Quality Control Inspection Report, seismic resistance grade, wind resistance grade, and snow load resistance grade are provided as performance indication items related to structural stability. There are foundations and frameworks as inspection items for the performance indication items of the earthquake resistance class, wind resistance class, and snow resistance class. The contents to be checked for the base / framework include the quality of the base, dimensions / shapes, joints, and the position of the metal fittings, as well as the quality of anchor bolts / hole down anchors, embedded length, position, tightening status, and horizontal level of the base.

【0087】劣化の軽減に関する性能表示事項として、
地盤の防蟻、基礎高さ、床下換気、土台の防腐防蟻があ
る。地盤の防蟻に対する確認内容として、コンクリート
による場合にはコンクリートの打設範囲、土壌処理によ
る場合には土壌処理の材料、状態がある。基礎の高さに
対する確認内容として、地盤面から基礎天端までの高さ
がある。床下換気に対する確認内容として、コンクリー
トの打設範囲、厚さ、防湿フィルムの種類・厚さ、設置
状況、床下換気口の位置と大きさ、基礎パッキンの位置
と大きさ、断熱材の設置位置・種類・厚さ(基礎断熱工
法)がある。土台の防腐防蟻に対する確認内容として、
部材の樹種・寸法、薬剤処理の材料・状態、土台と外壁
の取合部(水切り等)がある。
As performance display items relating to reduction of deterioration,
There are anti-termites for ground, foundation height, underfloor ventilation, and anti-corrosion for foundations. As the contents to be confirmed for the ground's ant control, when concrete is used, the range of concrete placement, and when soil treatment is used, the material and condition of soil treatment. The confirmation contents for the height of the foundation include the height from the ground surface to the top of the foundation. Confirmation contents for underfloor ventilation include concrete placement range, thickness, moisture-proof film type / thickness, installation status, underfloor ventilation hole position and size, foundation packing position and size, and heat insulating material installation position. There are types and thicknesses (basic insulation method). As confirmation contents for the antiseptic and ant on the base,
There are tree species / dimensions of materials, materials / conditions of chemical treatment, and joints between base and outer wall (drainer etc.).

【0088】図14は小屋根完了時に行われる第3回品
質管理検査報告書を示す図である。第3回品質管理検査
報告書では、構造の安定に関する性能表示事項として、
耐震等級、耐風等級、耐積雪等級が設けられている。こ
の耐震等級、耐風等級、耐積雪等級について、検査項目
としての部材の品質、土台・柱等、耐力壁(筋交いの場
合と面材の場合)が設けられている。部材の品質に対す
る確認内容として、部材の品質が設けられている。土台
・柱等に対する確認内容として、柱の小径、土台の寸法
・形状、継手、金物位置があり、さらにアンカーボルト
・ホールダウンアンカーの品質、埋め込み長さ、位置、
締付け状況、土台の水平レベルがある。
FIG. 14 is a view showing a third quality control inspection report which is carried out when the small roof is completed. In the third quality control inspection report,
There are earthquake resistance class, wind resistance class, and snow resistance class. Regarding the seismic resistance class, wind resistance class, and snow cover class, the quality of members as inspection items, foundations, columns, etc., and bearing walls (for braces and face materials) are provided. The quality of the member is provided as the confirmation content for the quality of the member. The details to be confirmed for the foundation / pillars are the diameter of the pillar, the dimensions / shape of the foundation, the joint, and the position of the metal fittings.
There are tightening conditions and the horizontal level of the foundation.

【0089】耐力壁(筋交いの場合)に対する確認内容
として、1階耐力壁の位置・長さ、種類・断面、2階耐
力壁の位置・長さ、種類・断面、3階耐力壁の位置・長
さ、種類・断面がある。耐力壁(面材の場合)に対する
確認内容として、1階面材の耐力壁の位置・長さ、種類
・断面、面材垂直レベル、留付状況、釘の種類、間隔、
2階面材並びに3階面材の耐力壁の位置・長さ、種類・
断面、面材垂直レベル、留付状況、釘の種類、間隔があ
る。
As the contents to be confirmed for the load bearing wall (in the case of bracing), the position / length, type / cross section of the first load bearing wall, position / length, type / cross section of the second load bearing wall, position of the third load bearing wall, etc. There are length, type and cross section. As the confirmation contents for the bearing wall (in the case of face material), the position / length, type / section of the bearing wall of the 1st floor face material, vertical level of face material, fastening status, type of nail, spacing,
Position, length, type of bearing wall of 2nd floor and 3rd floor
Cross section, vertical level of face material, fastening condition, nail type, spacing.

【0090】第3回品質管理検査報告書における性能表
示事項として、耐震等級、耐風等級、耐積雪等級に加え
て、劣化対策等級、維持管理対策等級、省エネルギー対
策等級、ホルムアルデヒド対策等級がある(図示せ
ず)。耐震等級、耐風等級、耐積雪等級についての検査
項目として、さらに準耐力壁、床組等、屋根面、接合
部、横架材があり、各検査項目について確認内容が定め
られている。劣化対策等級についての検査項目として、
外壁の枠組等があり、さらに確認内容が定められてい
る。維持管理対策等級についての検査項目として、専用
配管と地中配管が設けられており、さらに各検査項目に
ついて確認内容が定められている。省エネルギー対策等
級についての検査項目として、躯体の断熱性能が設けら
れており、さらに確認内容が定められている。ホルムア
ルデヒド対策等級についての検査項目として、構造用パ
ネル等級が設けられており、さらに確認内容が定められ
ている。
As performance indication items in the third quality control inspection report, in addition to seismic resistance class, wind resistance class, snow resistance class, there are deterioration countermeasure class, maintenance management class, energy saving measure class, formaldehyde measure class (Fig. (Not shown). The inspection items for earthquake resistance, wind resistance, and snow resistance grades include quasi-bearing walls, flooring, etc., roof surfaces, joints, and horizontal members, and the items to be checked are defined for each inspection item. As an inspection item for the deterioration countermeasure grade,
There is a framework for the outer wall, etc., and the details of confirmation are specified. Dedicated pipes and underground pipes are provided as inspection items for maintenance management grades, and the contents to be confirmed for each inspection item are specified. As an inspection item for the energy conservation measure grade, the heat insulation performance of the body is provided and the details of the confirmation are specified. Structural panel grades are provided as inspection items for formaldehyde countermeasure grades, and the details of confirmation are specified.

【0091】図15は屋根工事完了時に行われる第4回
品質管理検査報告書を示す図である。第4回品質管理検
査報告書では、構造の安定に関する性能表示事項とし
て、耐震等級、耐風等級、耐積雪等級が設けられてい
る。この耐震等級、耐風等級、耐積雪等級について、検
査項目としての部材の品質、土台・柱等、耐力壁(筋交
いの場合と面材の場合)が設けられている。各検査項目
における確認内容は、第3回品質管理検査報告書と共通
している点が多い。
FIG. 15 is a diagram showing a fourth quality control inspection report which is carried out at the completion of roof construction. In the 4th Quality Control Inspection Report, seismic resistance class, wind resistance class, and snow resistance class are provided as performance indication items related to structural stability. Regarding the seismic resistance class, wind resistance class, and snow cover class, the quality of members as inspection items, foundations, columns, etc., and bearing walls (for braces and face materials) are provided. The details of each inspection item are similar to those of the 3rd quality control inspection report.

【0092】第4回品質管理検査報告書における性能表
示事項として、耐震等級、耐風等級、耐積雪等級に加え
て、劣化対策等級、省エネルギー対策等級、ホルムアル
デヒド対策等級、光・視環境等級がある(図示せず)。
耐震等級、耐風等級、耐積雪等級についての検査項目と
して、さらに準耐力壁、床組等、屋根面、接合部、横架
材があり、さらに各検査項目についての確認内容が定め
られている。劣化対策等級についての検査項目として、
外壁の枠組等があり、さらに確認内容が定められてい
る。省エネルギー対策等級についての検査項目として、
躯体の断熱性能が設けられており、さらに確認内容が定
められている。ホルムアルデヒド対策等級についての検
査項目として、構造用パネル等級が設けられており、さ
らに確認内容が定められている。光・視環境等級につい
ての検査項目として、単純開口及び方位別開口比があ
り、さらに確認内容が定められている。
As performance indication items in the 4th quality control inspection report, in addition to earthquake resistance class, wind resistance class, snow resistance class, deterioration prevention grade, energy saving measure grade, formaldehyde countermeasure grade, light / visual environment grade ( (Not shown).
As the inspection items for the earthquake resistance class, wind resistance class, and snow cover class, there are semi-bearing walls, floor sets, roof surfaces, joints, and horizontal members, and the details to be checked for each inspection item are specified. As an inspection item for the deterioration countermeasure grade,
There is a framework for the outer wall, etc., and the details of confirmation are specified. As inspection items for energy conservation measures grade,
Insulation performance of the body is provided and the details of confirmation are specified. Structural panel grades are provided as inspection items for formaldehyde countermeasure grades, and the details of confirmation are specified. The inspection items for light / visual environment grade include simple aperture and azimuth-specific aperture ratio, and the details of confirmation are defined.

【0093】図16は内装下地完了時に行われる第5回
品質管理検査報告書を示す図である。第5回品質管理検
査報告書では、構造の安定に関する性能表示事項とし
て、耐震等級、耐風等級、耐積雪等級が設けられてい
る。この耐震等級、耐風等級、耐積雪等級について、検
査項目としての耐力壁(筋交いの場合と面材の場合)、
準耐力壁が設けられている。耐力壁(筋交いの場合)に
対する確認内容として、1階耐力壁の位置・長さ、種類
・断面、2階耐力壁の位置・長さ、種類・断面、3階耐
力壁の位置・長さ、種類・断面があり、耐力壁(面材の
場合)に対する確認内容として、1階面材の耐力壁の位
置・長さ、種類・断面、面材垂直レベル、留付状況、釘
の種類、間隔、2階面材並びに3階面材の耐力壁の位置
・長さ、種類・断面、面材垂直レベル、留付状況、釘の
種類、間隔がある点は、第3回及び第4回品質管理検査
報告書と共通している。
FIG. 16 is a diagram showing a fifth quality control inspection report which is carried out when the interior groundwork is completed. In the 5th Quality Control Inspection Report, seismic resistance class, wind resistance class and snow resistance class are provided as performance indication items related to structural stability. With regard to this earthquake resistance class, wind resistance class, snow resistance class, load bearing walls as inspection items (for braces and face materials),
A semi-bearing wall is provided. As confirmation contents for the bearing wall (in the case of bracing), the position and length, type and cross section of the 1st floor bearing wall, the position and length of 2nd bearing wall, the type and cross section, the position and length of 3rd bearing wall, There are types and cross sections, and the confirmation contents for the load bearing wall (in the case of face material) are the position and length of the load bearing wall of the 1st floor face material, type and cross section, face material vertical level, fastening status, type of nails, spacing The positions and lengths, types and cross sections of bearing walls of the 2nd and 3rd floor panels, the vertical level of the panel, the fastening conditions, the types of nails, and the intervals are the 3rd and 4th quality. It is common with the management inspection report.

【0094】準耐力壁に対する確認内容は、1階、2階
並びに3階の準耐力壁の位置・長さ、1階、2階並びに
3階の垂れ壁・腰壁の位置・長さ、巾と両隣の状況があ
る。さらに、準耐力壁に対する確認内容として、面材の
種類、厚さ、高さ、釘の種類と留付状況がある。
The confirmation contents for the quasi-bearing walls are the positions / lengths of the quasi-bearing walls on the first, second and third floors, the positions / lengths and widths of the hanging walls / waist walls on the first, second and third floors. And there is a situation on both sides. Furthermore, the confirmation contents for the quasi-bearing wall include the type of face material, thickness, height, type of nails and fastening status.

【0095】第5回品質管理検査報告書における性能表
示事項として、耐震等級、耐風等級、耐積雪等級に加え
て、劣化対策等級、維持管理対策等級、省エネルギー対
策等級、ホルムアルデヒド対策等級、光・視環境等級、
音の透過損失等級、高齢者等配慮対策等級がある(図示
せず)。耐震等級、耐風等級、耐積雪等級についての検
査項目として、さらに床組等、屋根面、接合部、横架材
があり、さらに各検査項目についての確認内容が定めら
れている。劣化対策等級についての検査項目として、小
屋裏換気、浴室・脱衣室の防水があり、さらに確認内容
が定められている。維持管理対策等級についての検査項
目として、電気設備、給水配管、給湯配管、汚水排水配
管のような専用配管が設けられており、さらに各検査項
目についての確認内容が定められている。
As the performance indication items in the 5th quality control inspection report, in addition to earthquake resistance class, wind resistance class, snow resistance class, deterioration measure class, maintenance measure class, energy saving measure class, formaldehyde measure class, light / visual grade Environmental grade,
There are sound transmission loss grades and grades for consideration of elderly people (not shown). As the inspection items for the earthquake resistance class, wind resistance class, and snow cover class, there are floor sets, roof surfaces, joints, and horizontal members, and the confirmation contents for each inspection item are defined. As the inspection items for the deterioration prevention grade, there are attic ventilation, waterproofing of bathrooms and dressing rooms, and further confirmation items are stipulated. As inspection items for the maintenance management grade, dedicated pipes such as electrical equipment, water supply pipes, hot water supply pipes, and sewage drainage pipes are provided, and the confirmation contents for each inspection item are specified.

【0096】省エネルギー対策等級についての検査項目
として、躯体の断熱性能、躯体の気密性、開口部の断熱
性能等、開口部の日射遮蔽性能が設けられており、さら
に各検査項目についての確認内容が定められている。ホ
ルムアルデヒド対策等級についての検査項目として、構
造用パネル等級が設けられており、さらに確認内容が定
められている。光・視環境等級についての検査項目とし
て、単純開口及び方位別開口比があり、さらに確認内容
が定められている。音の透過損失等級についての検査項
目として、構造用パネル等級が設けられており、さらに
確認内容が定められている。高齢者等配慮対策等級につ
いての検査項目として、手すりがあり、さらに確認内容
が定められている。
As the inspection items for the energy saving measure grade, the heat insulation performance of the skeleton, the airtightness of the skeleton, the heat insulation performance of the opening, etc. are provided, and the solar radiation shielding performance of the opening is provided. It is set. Structural panel grades are provided as inspection items for formaldehyde countermeasure grades, and the details of confirmation are specified. The inspection items for light / visual environment grade include simple aperture and azimuth-specific aperture ratio, and the details of confirmation are defined. Structural panel grades are provided as inspection items for sound transmission loss grades, and further confirmation contents are specified. There is a handrail as an inspection item for the grade of consideration measures for the elderly, etc., and further confirmation contents are specified.

【0097】図17は建物竣工時に行われる第6回品質
管理検査報告書を示す図である。第6回品質管理検査報
告書では、火災時の安全に関する性能表示事項として、
感知警報装置設置等級、脱出対策、耐火等級がある。感
知警報装置設置等級に対する検査項目として、感知警報
装置が設けられている。感知警報装置に対する確認内容
として、感知部分の設置場所、種別、取付位置、感度
等、警報部分の性能がある。脱出対策に対する検査項目
として、脱出対策が設けられており、確認内容として避
難器具の設置、直通階段に直接通ずるバルコニーがあ
る。耐火等級に対する検査項目として、開口部の耐火性
能と外壁・軒裏の構造がある。開口部の耐火性能に対す
る確認内容として、対象となる範囲と開口部の耐火性能
がある。外壁・軒裏の構造に対する確認内容として、対
象となる範囲と外壁・軒裏の構造がある。
FIG. 17 is a diagram showing a sixth quality control inspection report conducted at the time of building completion. In the 6th quality control inspection report, as the performance indication items related to safety at the time of fire,
There are detection alarm installation grades, escape measures, and fire resistance grades. A detection and warning device is provided as an inspection item for the installation grade. The confirmation contents for the detection and alarm device include the performance of the alarm part such as the installation location, type, installation position and sensitivity of the sensing part. Evacuation measures are provided as inspection items for evacuation measures, and confirmation items include installation of evacuation equipment and balconies that directly lead to stairs. The inspection items for the fire resistance grade are the fire resistance of the opening and the structure of the outer wall and eaves. The items to be checked for the fire resistance of the opening are the target range and the fire resistance of the opening. The confirmation contents for the structure of the outer wall and the eaves include the target range and the structure of the outer wall and the eaves.

【0098】劣化の軽減に関する性能表示事項として、
劣化対策等級が設けられている。劣化対策等級に関する
検査項目として、浴室・脱衣室の防水があり、確認内容
として、浴室・脱衣室の防水が設けられている。維持管
理の配慮に関する性能表示事項として、維持対策等級が
設けられている。維持対策等級に対する検査項目とし
て、専用配水管の清掃措置と配管点検口が設けられてい
る。専用配水管の清掃措置に対する確認内容として、専
用配水管の掃除口、トラップの清掃措置が設けられてい
る。配管点検口に対する確認内容として、開口(点検
口)の位置、開口と配管の関係が設けられている。
As performance display items relating to reduction of deterioration,
A deterioration countermeasure grade is provided. The inspection items related to the deterioration countermeasure grade include waterproofing of the bathroom and dressing room, and the contents of confirmation include waterproofing of the bathroom and dressing room. A maintenance measure class is provided as a performance display item related to maintenance consideration. As inspection items for maintenance measures, dedicated water pipe cleaning measures and pipe inspection openings are provided. As the contents to be checked for the cleaning of the exclusive water pipe, the cleaning port of the exclusive water pipe and the cleaning of the trap are provided. As the contents to be checked for the pipe inspection port, the position of the opening (inspection port) and the relationship between the opening and the pipe are provided.

【0099】第6回品質管理検査報告書における性能表
示事項として、さらにホルムアルデヒド対策等級、全般
換気対策等級、局所換気設備、高齢者等配慮対策等級が
ある(図示せず)。ホルムアルデヒド対策等級について
の検査項目として、居室の内装材、パーティクルボー
ド、MDF等級、合板等級、構造用パネル等級、複合フ
ローリング等級、集成材等級、単板積層材等級があり、
さらに各検査項目についての確認内容が定められてい
る。全般換気対策等級についての検査項目として、全般
換気の措置が設けられており、さらに確認内容が定めら
れている。局所換気設備についての検査項目として、便
所、浴室、台所、脱衣所のような局所の換気方法が設け
られており、さらに確認内容が定められている。高齢者
等配慮対策等級についての検査項目として、部屋の配
置、段差、階段、手すり、通路・出入口の幅員、寝室・
浴室・便所の広さがあり、さらに各検査項目についての
確認内容が定められている。
Performance display items in the sixth quality control inspection report further include formaldehyde countermeasure grade, general ventilation countermeasure grade, local ventilation equipment, and elderly person consideration countermeasure grade (not shown). Inspection items for formaldehyde countermeasure grades include interior materials for living rooms, particle boards, MDF grades, plywood grades, structural panel grades, composite flooring grades, laminated wood grades, and veneer laminate grades.
Furthermore, the details of confirmation for each inspection item are defined. General ventilation measures are provided as inspection items for the general ventilation countermeasure class, and further confirmation contents are specified. Local ventilation methods such as toilets, bathrooms, kitchens, dressing rooms are provided as inspection items for local ventilation equipment, and the details of confirmation are specified. The inspection items for consideration measures grades for the elderly include room layout, steps, stairs, handrails, width of passages and doorways, bedrooms,
There is a large bathroom / toilet area, and the details of confirmation for each inspection item are specified.

【0100】このような第1回から第6回品質管理検査
報告書のうち、図9(A)の代金預託規定と図9(B)
の代金支払い規定と関連するものは、以下に示す回の品
質管理検査報告書における工程検査合格である。代金預
託規定において、屋根完了時は第4回品質管理検査報告
書、内装下地完了時は第5回品質管理検査報告書、完成
検査合格時は第6回品質管理検査報告書である。代金支
払い規定において、基礎工事完了検査合格は第1回品質
管理検査報告書、屋根工事完了検査合格は第4回品質管
理検査報告書、内装下地工事完了検査合格は第5回品質
管理検査報告書、工事完了検査合格は第6回品質管理検
査報告書に対応している。
Of the 1st to 6th quality control inspection reports, the deposit deposit rules of FIG. 9 (A) and FIG. 9 (B).
Related to the price payment regulation of the above is the process inspection pass in the quality control inspection report of the following times. In the price deposit rules, the 4th quality control inspection report is completed when the roof is completed, the 5th quality control inspection report is completed when the interior base is completed, and the 6th quality control inspection report is passed when the completion inspection is passed. In the payment regulation, the first quality control inspection report passes if the foundation construction completion inspection passes, the fourth quality control inspection report passes if the roof construction completion inspection passes, and the fifth quality control inspection report passes if the interior groundwork completion inspection passes Passing the construction completion inspection corresponds to the 6th quality control inspection report.

【0101】続いて、維持管理記録データベース84に
記録されるプロジェクト対象物の引渡し後の維持管理記
録について説明する。図18は建物の維持管理記録の一
例を示す図で、個人向け住宅であるマイホーム用の点検
・補修記録シートの引渡し後第1年経過時用を示してい
る。点検・補修記録シートには、管理用に記録日欄、補
修(点検)実施業者名称欄、業者住所欄、電話番号欄、
シート番号欄、記録者欄が設けられている。第1年経過
時には点検部位として設備を点検・補修の対象としてい
る。設備としては、給水管、水栓器具、配水管、トラッ
プ、台所シンク、洗面設備、便所、浴室、ガス管、給湯
器、換気設備、電気設備がある。
Next, the maintenance record after the delivery of the project object recorded in the maintenance record database 84 will be described. FIG. 18 is a diagram showing an example of a maintenance record of a building, and shows a record for the first year after the delivery of the inspection / repair record sheet for my home, which is a personal residence. The inspection / repair record sheet has a record date column, a repair (inspection) supplier name column, a vendor address column, a telephone number column, for management,
A sheet number column and a recorder column are provided. At the end of the first year, equipment is inspected and repaired as an inspection site. Facilities include water pipes, faucet devices, water pipes, traps, kitchen sinks, sink facilities, toilets, bathrooms, gas pipes, water heaters, ventilation facilities, and electrical facilities.

【0102】給水管、水栓器具の点検項目としては、水
漏れ、赤水、パッキングの異常、作動不良がある。配水
管、トラップの点検項目としては、水漏れ、つまり、悪
臭がある。台所シンク、洗面設備の点検項目としては、
水漏れ、割れ,腐食がある。便所の点検項目としては、
便器周りの水漏れや水洗タンク周りの水漏れがある。浴
室の点検項目としては、タイル等の割れ、ジョイント部
(ユニット)の割れや隙間がある。ガス管の点検項目と
しては、ガス漏れ、ゴム管の劣化がある。給湯器の点検
項目としては、水漏れ、ガス漏れ、器具の異常がある。
換気設備の点検項目としては、作動不良がある。電気設
備の点検項目としては、スイッチ作動不良、スイッチ破
損、コンセント破損がある。
Inspection items for the water supply pipe and the faucet device include water leak, red water, abnormal packing, and malfunction. Water leaks, that is, foul odors, are inspection items for water pipes and traps. Check items for kitchen sinks and washbasins include:
Water leaks, cracks, or corrosion. To check the toilet,
There is a leak around the toilet bowl or a flush tank. Check items in the bathroom include cracks in tiles, joints (units), and gaps. Gas pipe inspection items include gas leakage and rubber pipe deterioration. Check items for the water heater include water leaks, gas leaks, and equipment malfunctions.
There is a malfunction in the inspection item of ventilation equipment. Electrical equipment inspection items include defective switch operation, switch damage, and outlet damage.

【0103】図19は建物の維持管理記録の一例を示す
図で、マイホーム用の点検・補修記録シートの引渡し後
第3年経過時用を示している。図18に示す第1年経過
時用と比較して、点検部位として、屋外部分と建具が追
加されている。屋外部分としては、外壁、雨どい、軒
裏、バルコニーがある。建具としては玄関建具・窓、雨
戸・網戸、窓枠、戸袋等の木部、内部建具がある。
FIG. 19 is a diagram showing an example of the maintenance record of the building, showing the third year after the delivery of the inspection / repair record sheet for my home. Compared with the one for the passage of the first year shown in FIG. 18, an outdoor part and a fitting are added as inspection parts. Outdoor areas include outer walls, rain gutters, backsides and balconies. The fittings include entrance fittings / windows, shutters / screens, window frames, wooden parts such as door pockets, and internal fittings.

【0104】外壁の点検項目としては、腐朽、さび、割
れ、シーリングの破断がある。雨どいの点検項目として
は、詰まり、はずれ、ひびがある。軒裏の点検項目とし
ては、腐朽、雨漏り、はがれ、たわみがある。バルコニ
ーの点検項目としては、手すりぐらつき、腐朽、さび、
割れ、蟻害、床沈みがある。玄関建具・窓の点検項目と
しては、隙間や開閉不良がある。雨戸・網戸の点検項目
としては、さびや建付不良がある。窓枠、戸袋等の木部
の点検項目としては、さび、雨漏り、コーキング不良が
ある。内部建具の点検項目としては、隙間、開閉不良、
破損がある。
Items to be inspected on the outer wall include decay, rust, cracks, and breaking of the sealing. Inspection items for rain gutters include clogging, detachment and cracks. Items to be checked on the back of the eaves include decay, rain leak, peeling, and bending. Balconies should be checked for handrails, decay, rust,
There are cracks, ant damage, and floor sinking. There are gaps and poor opening and closing as inspection items for entrance doors and windows. There are rust and defective installation as inspection items for rain doors and screen doors. Inspection items for wooden parts such as window frames and door pockets include rust, rain leak, and caulking failure. Inspection items for internal fittings include gaps, poor opening and closing,
There is damage.

【0105】図20は建物の維持管理記録の一例を示す
図で、マイホーム用の点検・補修記録シートの引渡し後
第5年経過時用を示している。図19に示す第3年経過
時用と比較して、点検部位として、屋内と屋外部分のう
ち布基礎が追加されている。屋内の点検部位として土
台、床組があり、点検項目として腐朽、さび、蟻害、床
沈みがある。布基礎の点検項目として、割れ、蟻道、不
同沈下、換気不良がある。
FIG. 20 is a diagram showing an example of the maintenance record of the building, showing the record for the fifth year after the delivery of the inspection / repair record sheet for my home. Compared to the third year aging type shown in FIG. 19, a cloth foundation is added as an inspection site between the indoor and outdoor parts. The indoor inspection parts include the foundation and floor assembly, and the inspection items include decay, rust, ant damage, and floor sinking. Inspection items for the cloth foundation include cracks, ant roads, uneven settlement, and poor ventilation.

【0106】図21は建物の維持管理記録の一例を示す
図で、マイホーム用の点検・補修記録シートの引渡し後
第35年経過時用を示している。図20に示す第5年経
過時用と比較して、点検部位として、屋内のうち柱、は
り、壁(室内側)、天井、小屋組、階段が追加されてい
る。柱、はりの点検項目として腐朽、さび、蟻害、割れ
がある。壁(室内側)の点検項目として割れ、雨漏り、
目地破断、腐朽、さび、蟻害、さびがある。天井、小屋
組の点検項目として腐朽、さび、はがれ、たわみ、雨漏
り、蟻害、割れがある。階段の点検項目として沈み、腐
朽、さび、割れ、蟻害がある。なお、建物の維持管理記
録は定期に行うのがよく、例えば引渡し後第10年、1
5年、20年、25年、30年については、例えば図2
1に示す第35年経過時用を用いるとよい。
FIG. 21 is a view showing an example of the maintenance record of the building, showing the 35th year after the delivery of the inspection / repair record sheet for my home. Compared to the fifth year-old one shown in FIG. 20, as columns to be inspected, pillars, beams, walls (inside the room), ceilings, sheds, and stairs are added. Inspection items for pillars and beams include decay, rust, ant damage, and cracks. As a check item on the wall (inside the room), cracks, leaks,
There are joint breakage, decay, rust, ant damage, and rust. Items to be inspected on the ceiling and the roof cottage are decay, rust, peeling, flexure, rain leak, ant damage, and cracks. Inspection items for stairs include sinking, decay, rust, cracking, and ant damage. It should be noted that the maintenance record of the building should be recorded regularly, for example, 10th year after delivery,
For 5 years, 20 years, 25 years and 30 years, for example, see FIG.
It is preferable to use the one for the 35th year as shown in 1.

【0107】続いて、建築目的物が完成した後に用いて
好適な既設プロジェクト対象物の担保価値算定システム
について説明する。建築目的物が完成した後は、建物の
保存登記がなされているのが通例であるため、金融機関
による担保価値算定においても、例えば再調達原価とし
て住宅金融公庫の標準建築費に経年減価額を控除し、一
定の掛け目率(例えば使用形態が自用であれば60%、
賃貸用であれば40%)にて担保価値が算定される。
Next, a description will be given of a collateral value calculation system suitable for an existing project object that is used after the construction object is completed. After the construction object is completed, it is customary that the building is registered for preservation, so even when calculating the collateral value by a financial institution, for example, as a replacement cost, the annual depreciation is added to the standard building cost of the Housing Finance Corporation. After deducting, a certain multiplication factor (for example, 60% if the usage is for personal use,
The collateral value is calculated at 40% for rent.

【0108】しかしながら、建物を取り壊して住宅を新
築しようとする場合は別として、建物の維持管理が良好
であれば、当該建物の市場売却価格も適正なものとされ
なければ、住宅所有者は住宅を積極的に修繕しようとし
ない。第2の発明である既設プロジェクト対象物の担保
価値算定システム及び方法においては、プロジェクト対
象物の設計図書、施工状態、保守状態を正確に記録して
おくことで、再調達価格を正確に見積もると共に、現有
価値率も正確に算定することを可能としている。
However, apart from the case where a building is demolished and a new house is constructed, if the maintenance of the building is good and the market sale price of the building is not appropriate, the homeowner will Don't try to repair. In the system and method for calculating the collateral value of an existing project object, which is the second invention, by accurately recording the design document, construction status, and maintenance status of the project object, it is possible to accurately estimate the replacement price. It is also possible to accurately calculate the current value rate.

【0109】図22は、本発明の一実施の形態を示す既
設プロジェクトの担保価値算定システムの構成ブロック
図である。図において、再調達価格算定部91は、既設
プロジェクトの担保価値を算定する時点での再調達価格
を計算するもので、設計図書管理テーブル81、プロジ
ェクト進捗管理テーブル82、資材市況データ部92、
施工積算データ部93と接続されている。再調達価格算
定部91は、設計図書管理テーブル81とプロジェクト
進捗管理テーブル82を参照することによって、既設プ
ロジェクトを建設時と同一工法によって再建設する場合
の所要資材と所要工数の詳細を把握する。再調達価格算
定部91は、資材市況データ部92と施工積算データ部
93を参照して、担保価値算定時での資材と工数並びに
工数単価を積算することで、既設プロジェクトの再調達
価格を計算する。この場合、担保価値算定時と建設時と
で既設プロジェクトの資材価格や施工価格に変動が少な
い場合には、再調達価格算定部91では、さらにプロジ
ェクト履行履歴テーブル83に記録された債務履行状態
の情報が再調達価格算定に参酌される。
FIG. 22 is a configuration block diagram of a collateral value calculation system for an existing project, showing an embodiment of the present invention. In the figure, a replacement price calculation unit 91 calculates a replacement price at the time of calculating the collateral value of an existing project, and includes a design book management table 81, a project progress management table 82, a material market data unit 92,
It is connected to the construction integration data section 93. The repurchase price calculation unit 91 refers to the design document management table 81 and the project progress management table 82 to grasp the details of the required materials and the required man-hours when the existing project is reconstructed by the same construction method as at the time of construction. The re-procurement price calculation unit 91 calculates the re-procurement price of the existing project by referring to the material market condition data unit 92 and the construction integration data unit 93, and accumulating the materials, the man-hours, and the unit cost per man-hour when the collateral value is calculated. To do. In this case, when there is little change in the material price and construction price of the existing project at the time of calculating the collateral value and at the time of construction, the repurchase price calculation unit 91 further determines whether the debt fulfillment status recorded in the project fulfillment history table 83 The information is taken into account in the replacement price calculation.

【0110】現有価値算定部94は、既設プロジェクト
の現在有している価値を算定するもので、再調達価格算
定部91で算出した再調達価格に既設プロジェクトの耐
用年数と経過年数を元に算出された現有価値率を乗じ、
更に維持管理記録データベース84に記録された修繕状
態を考慮する。担保価値算定部95は、プロジェクト対
象物の流通市場データ96を参照して、換金に要する平
均的な期間、担保物件を仮に売却する場合の買受け人、
並びにプロジェクト対象物の売却人の状態を参酌して、
担保価値率を算定する。換金が容易な市場環境であれ
ば、現有価値算定部94で算定された現有価値額に近い
ものとなり、換金が困難な市場環境の場合は現有価値算
定部94で算定された現有価値額に対する掛け目率を低
くする。
The present valuable value calculation unit 94 calculates the present value of the existing project, and calculates the replacement price calculated by the replacement price calculation unit 91 based on the useful life and elapsed years of the existing project. Multiplied by the current value ratio
Furthermore, the repair status recorded in the maintenance record database 84 is considered. The collateral value calculation unit 95 refers to the secondary market data 96 of the project object, the average period required for cash conversion, the purchaser when the collateral property is temporarily sold,
Also, taking into account the status of the seller of the project object,
Calculate the collateral value rate. In a market environment where cash exchange is easy, the value is close to the current value price calculated by the current value calculation unit 94, and in a market environment where cash conversion is difficult, it is a multiplication factor for the current value calculated by the current value calculation unit 94. Lower the rate.

【0111】次に、このように構成された既設プロジェ
クトの担保価値算定システムの使用状態を説明する。図
23は既設プロジェクトが木造住宅の場合における、建
物に対する担保価値の算定の一例を示す図である。ここ
では、説明を簡単にするために、担保価値算定時と建設
時とで既設プロジェクトの資材価格や施工価格に変動が
なく、再調達価格算定部91では単に当初の建築価格を
もって再調達価格とする場合を説明する。また、現有価
値算定部94では木造住宅の耐用年数を30年とし、建
築価格を基準として毎年3%づつ定額で減価償却するも
のとし、30年経過後は減価償却をゼロとして建築価格
の10%を建物残存価値とみなす。また、点検・補修が
あったときは、補修工事代金については次回の補修工事
までに毎年定額で減価償却するものとする。なお、木造
住宅に対する修繕の効用は、木造住宅の建設後の経過年
数に対して延長された残存寿命が、補修工事代金と等し
いものとして現在価値を算定しているが、補修工事によ
る残存寿命延長効果が大きい場合には、補修工事代金に
一定の乗率を掛けて現在価値を算定してもよい。
Next, the usage state of the collateral value calculation system of the existing project thus constructed will be described. FIG. 23 is a diagram showing an example of calculation of the collateral value for a building when the existing project is a wooden house. Here, in order to simplify the explanation, there is no change in the material price and construction price of the existing project at the time of calculating the collateral value and at the time of construction, and the replacement price calculation unit 91 simply uses the initial construction price as the replacement price. A case will be described. In addition, the current valuable value calculation unit 94 sets the useful life of the wooden house to 30 years, and depreciates it by a fixed amount every 3% based on the building price. After 30 years, depreciation is set to zero and the building price is 10%. Is regarded as the residual value of the building. In addition, if there is an inspection or repair, the repair work price will be depreciated by a fixed amount every year before the next repair work. Regarding the utility of repairs on wooden houses, the present value is calculated as the remaining life extended with respect to the number of years elapsed after the construction of the wooden house is equal to the repair work price, but the remaining life extension by repair work is extended. When the effect is large, the present value may be calculated by multiplying the repair work price by a certain multiplication factor.

【0112】図23に示す説例では、既設プロジェクト
の当初の建築価格は、1500万円であり、毎年45万
円づつ定額で減価償却して、30年経過後の建物残存価
値は150万円となる。点検・補修は、前述のマイホー
ム用の点検・補修記録シートに従い、引渡後1年、3
年、5年後に行われるものとし、5年経過後は5年間隔
で建物が取り壊されるか、朽腐するまで継続されるもの
とする。木造住宅の場合、朽腐とは屋根が落ちて壁が崩
落するような状態をいい、適切な保守を行わない場合は
建築後40年程度、適切に保守を行えば建築後70年以
上経過すると朽腐に至る。
In the example shown in FIG. 23, the initial construction price of the existing project is 15 million yen, and the remaining value of the building after 30 years is 1.5 million yen after depreciation by 450,000 yen every year. Becomes For inspection and repair, in accordance with the above-mentioned inspection and repair record sheet for my home, 1 year after delivery, 3
It shall take place 5 years later, and after 5 years, it shall continue at 5 year intervals until the building is demolished or decays. In the case of a wooden house, decay means a state in which the roof falls and the walls collapse. About 40 years after construction if proper maintenance is not performed, and 70 years or more after construction if properly maintained. Leads to decay.

【0113】図23に示す説例では、1年点検では補修
工事が発生せず、3年点検で補修工事代金20万円が発
生し、5年点検で補修工事代金50万円が発生し、その
後10年点検以降の5年間隔の点検で毎回補修工事代金
150万円が発生している。このとき、補修後建物価値
が現有価値算定部94で算定される既設プロジェクトの
現有価値となる。また、5年間隔で行われる修繕の補修
工事代金は、建築価格の10%である150万円とし、
5年間で償却されるものとする。定期に修繕を行うこと
によって、木造住宅の建物残存価値を比較的高く維持す
ることができ、朽腐することを防止できる。
In the example shown in FIG. 23, the repair work does not occur in the one-year inspection, the repair work cost 200,000 yen occurs in the three-year inspection, and the repair work cost 500,000 yen occurs in the five-year inspection. After the 10-year inspection, 1.5 million yen was incurred for repair work every 5 years. At this time, the repaired building value becomes the current value of the existing project calculated by the current value calculation unit 94. In addition, the repair work price for repairs performed at intervals of 5 years is 1.5%, which is 10% of the building price,
It shall be amortized over 5 years. By carrying out regular repairs, the residual value of the wooden house can be kept relatively high, and it can be prevented from decaying.

【0114】なお、上記の実施の形態においては、既設
プロジェクトの担保価値算定システムとして再調達価格
を基礎に現有価値を算定すると共に補修工事代金も考慮
する場合を説明したが、本発明はこれに限定されるもの
ではなく、プロジェクト対象物のうち建物に関しては、
金融機関において各種の担保評価基準に対して補修工事
代金を考慮する場合に用いて好適である。たとえば、金
融機関において各種の担保評価基準として売却確定金
額、裁判所での競売手続きを基準とする最低売却金額、
不動産鑑定士による鑑定評価額、取引事例比較法、収益
還元法、原価法による産出額、固定資産税による評価が
存在するが、一般的に補修工事に応じて実質的な建物の
残存寿命が延びるので、残存寿命が延びた相当期間を現
有価値の算定に反映させるとよい。
In the above embodiment, the case where the present valuable value is calculated based on the replacement price as the collateral value calculation system for the existing project and the repair work price is also taken into consideration is explained. It is not limited, but regarding buildings among the project objects,
It is suitable for use in financial institutions when considering the repair work price against various collateral evaluation criteria. For example, at a financial institution, various collateral evaluation criteria are the fixed sale amount, the minimum sale amount based on the auction procedure in the court,
There are appraisal values by real estate appraisers, transaction case comparison method, profit reduction method, output value by cost method, and property tax assessment, but in general the remaining life of a building is extended depending on repair work. Therefore, it is advisable to reflect the considerable period of extended remaining life in the calculation of the current value.

【0115】[0115]

【発明の効果】本発明のプロジェクトの担保価値算定シ
ステムによれば、プロジェクト対象物の完成状態情報と
請負契約総金額情報を用いて、前記プロジェクト対象物
の完成価値を算出するプロジェクト完成価値算出部と、
プロジェクト進捗管理テーブルから前記プロジェクト対
象物における工程毎の進捗状況を受取ると共に、前記プ
ロジェクト履行履歴テーブルから前記プロジェクト対象
物に係る実施済み工程の請負契約金額情報を受取るプロ
ジェクト工事済価値算出部と、前記プロジェクト完成価
値算出部にて算出された前記プロジェクト対象物の完成
価値と、前記プロジェクト工事済価値算出部にて算出さ
れた前記プロジェクト対象物に係る実施済み工程の請負
契約金額情報から、前記プロジェクト対象物に係る実施
済み工程段階での価値を算出するプロジェクト担保価値
算定部とを備えているので、工事途中の工作物の経済的
な価値を正確に算出することができ、工事途中の工作物
を第三者が買受けたり、金融機関による追加融資が利用
しやすくなる。
According to the project collateral value calculation system of the present invention, the project completion value calculation unit for calculating the completion value of the project object by using the completion state information of the project object and the total contract amount information. When,
A project construction completed value calculation unit that receives the progress status of each process in the project object from the project progress management table, and also receives the contract contract amount information of the executed process related to the project object from the project fulfillment history table, From the completed value of the project object calculated by the project completed value calculation unit and the contracted contract amount information of the completed process related to the project object calculated by the project completed value calculation unit, the project object Since it has a project collateral value calculation unit that calculates the value at the completed process stage related to the object, it is possible to accurately calculate the economic value of the work in progress and It will be easier for third parties to buy and to use additional financing by financial institutions.

【0116】また、本発明の既設プロジェクトの担保価
値算定システムによれば、既設プロジェクトを建設時と
同一工法によって再建設する場合の再調達価格を算定す
る再調達価格算定部と、前記再調達価格算定部で算出し
た再調達価格に前記既設プロジェクトの耐用年数と経過
年数を元に算出された現有価値率を乗じ、更に前記既設
プロジェクトに対する修繕により前記経過年数に対して
延長された残存寿命を考慮して、前記既設プロジェクト
の現在有している価値を算定する現有価値算定部と、前
記既設プロジェクトの流通市場状態を参酌して、前記既
設プロジェクトに対する担保価値率を算定する担保価値
算定部とを備えている。そこで、プロジェクト対象物の
引渡し後に発生する建設コストの変動は再調達価格算定
部で担保価値に織り込み、プロジェクト対象物のメンテ
ナンスの状態を現有価値算定部で担保価値に織り込むこ
とで、適正な維持管理がなされているプロジェクト対象
物が市場において適正に評価されることができるように
なり、完成後から年月の経過したプロジェクト対象物の
担保価値算定が正確に行える。
Further, according to the collateral value calculation system for an existing project of the present invention, a replacement price calculation unit for calculating a replacement price when the existing project is reconstructed by the same construction method as the construction, and the replacement price. The replacement price calculated by the calculation unit is multiplied by the current value ratio calculated based on the useful life and elapsed years of the existing project, and the remaining life extended for the elapsed years due to repairs to the existing project is considered. Then, a current value calculation unit that calculates the value that the existing project currently has, and a collateral value calculation unit that calculates the collateral value ratio for the existing project by taking into consideration the secondary market state of the existing project. I have it. Therefore, fluctuations in construction costs that occur after the delivery of the project object is factored into the collateral value at the replacement price calculation section, and the maintenance status of the project object is factored into the collateral value at the current value calculation section to ensure proper maintenance management. It becomes possible to properly evaluate the project object that has been made in the market, and it is possible to accurately calculate the collateral value of the project object whose years have passed since its completion.

【図面の簡単な説明】[Brief description of drawings]

【図1】 本発明の一実施の形態を示すプロジェクトの
担保価値算定システムの構成ブロック図である。
FIG. 1 is a configuration block diagram of a project collateral value calculation system showing an embodiment of the present invention.

【図2】 プロジェクトの担保価値算定システムでの担
保価値算定の手続きを説明するフローチャートである。
FIG. 2 is a flowchart illustrating a procedure for calculating collateral value in a collateral value calculation system for a project.

【図3】 本発明の一実施の形態を示すプロジェクト完
成保証システムの構成ブロック図である。
FIG. 3 is a configuration block diagram of a project completion assurance system showing an embodiment of the present invention.

【図4】 プロジェクト完成保証システムでの代金決済
の手続きを説明するフローチャートである。
FIG. 4 is a flowchart illustrating a procedure for payment settlement in the project completion guarantee system.

【図5】 本発明の一実施の形態を示す構成ブロック図
である。
FIG. 5 is a configuration block diagram showing an embodiment of the present invention.

【図6】 請負業者端末や引継請負業者端末に表示され
る画面の一例を示す図である。
FIG. 6 is a diagram showing an example of a screen displayed on a contractor terminal or a takeover contractor terminal.

【図7】 請負業者端末や引継請負業者端末に表示され
る画面の一例を示す図である。
FIG. 7 is a diagram showing an example of a screen displayed on a contractor terminal or a takeover contractor terminal.

【図8】 本発明のプロジェクトの担保価値算定システ
ムとプロジェクト完成保証システムを用いた、建築請負
工事の手続きの流れを説明する図である。
FIG. 8 is a diagram illustrating a procedure of a building contracting work using the project collateral value calculation system and the project completion guarantee system of the present invention.

【図9】 本発明のプロジェクトの担保価値算定システ
ムにおける代金預託規定と代金支払い規定の一例を示す
図である。
FIG. 9 is a diagram showing an example of price deposit rules and price payment rules in the project collateral value calculation system of the present invention.

【図10】 建築目的物の工程と、プロジェクト検査管
理サーバーで取扱う工程検査の一例を示す図である。
FIG. 10 is a diagram showing an example of a process of a building object and a process inspection handled by a project inspection management server.

【図11】 建築目的物の施工状態検査として用いられ
る品質管理検査報告書の表紙部を示している。
FIG. 11 shows the cover of a quality control inspection report used as an inspection of the construction state of a building object.

【図12】 基礎工事完了時に行われる第1回品質管理
検査報告書の一例を示す図である。
FIG. 12 is a diagram showing an example of a first quality control inspection report performed at the completion of foundation work.

【図13】 一階床組完了時に行われる第2回品質管理
検査報告書の一例を示す図である。
FIG. 13 is a diagram showing an example of a second quality control inspection report which is performed when the first floor floor assembly is completed.

【図14】 小屋根完了時に行われる第3回品質管理検
査報告書の一例を示す図である。
FIG. 14 is a diagram showing an example of a third quality control inspection report performed at the completion of a small roof.

【図15】 屋根工事完了時に行われる第4回品質管理
検査報告書の一例を示す図である。
FIG. 15 is a diagram showing an example of a fourth quality control inspection report performed at the time of completion of roof construction.

【図16】 内装下地完了時に行われる第5回品質管理
検査報告書の一例を示す図である。
FIG. 16 is a diagram showing an example of a fifth quality control inspection report performed at the time of completion of the interior groundwork.

【図17】 建物竣工時に行われる第6回品質管理検査
報告書の一例を示す図である。
FIG. 17 is a diagram showing an example of a sixth quality control inspection report performed at the time of building completion.

【図18】 建物の維持管理記録(1年点検用)の一例
を示す図である。
FIG. 18 is a diagram showing an example of a building maintenance record (for one-year inspection).

【図19】 建物の維持管理記録(3年点検用)の一例
を示す図である。
FIG. 19 is a diagram showing an example of a building maintenance record (for 3-year inspection).

【図20】 建物の維持管理記録(5年点検用)の一例
を示す図である。
FIG. 20 is a diagram showing an example of a building maintenance record (for 5-year inspection).

【図21】 建物の維持管理記録(35年点検用)の一
例を示す図である。
FIG. 21 is a diagram showing an example of a building maintenance record (for 35-year inspection).

【図22】 本発明の一実施の形態を示す既設プロジェ
クトの担保価値算定システムの構成ブロック図である。
FIG. 22 is a configuration block diagram of a collateral value calculation system for an existing project showing an embodiment of the present invention.

【図23】 既設プロジェクトが木造住宅の場合におけ
る、建物に対する担保価値の算定の一例を示す図であ
る。
FIG. 23 is a diagram showing an example of calculation of a collateral value for a building when the existing project is a wooden house.

【符号の説明】[Explanation of symbols]

20 プロジェクト代金決済サーバー 30 プロジェクト検査管理サーバー 40 完成保証管理サーバー 80 担保価値算定システム 81 設計図書管理テーブル 82 プロジェクト進捗管理テーブル 83 プロジェクト履行履歴テーブル 84 維持管理記録データベース 85 プロジェクト完成価値算出部 86 プロジェクト工事済価値算出部 87 プロジェクト追加工事価値算出部 88 プロジェクト担保価値算定部 89 価値調整部 90 設計図書サーバー 91 再調達価格算定部 94 現有価値算定部 95 担保価値算定部 20 Project payment server 30 Project inspection management server 40 Completion Guarantee Management Server 80 Collateral value calculation system 81 Design book management table 82 Project progress management table 83 Project fulfillment history table 84 Maintenance record database 85 Project Completion Value Calculation Department 86 Project Construction Value Calculation Department 87 Project Additional Construction Value Calculation Department 88 Project Collateral Value Calculation Department 89 Value adjustment department 90 Design book server 91 Replacement Price Calculation Department 94 Current Valuable Value Calculation Department 95 Collateral Value Calculation Department

Claims (13)

【特許請求の範囲】[Claims] 【請求項1】 プロジェクト対象物の完成状態情報と請
負契約総金額情報を用いて、前記プロジェクト対象物の
完成価値を算出するプロジェクト完成価値算出部と;プ
ロジェクト進捗管理テーブルから前記プロジェクト対象
物における工程毎の進捗状況を受取ると共に、前記プロ
ジェクト履行履歴テーブルから前記プロジェクト対象物
に係る実施済み工程の請負契約金額情報を受取るプロジ
ェクト工事済価値算出部と;前記プロジェクト完成価値
算出部にて算出された前記プロジェクト対象物の完成価
値と、前記プロジェクト工事済価値算出部にて算出され
た前記プロジェクト対象物に係る実施済み工程の請負契
約金額情報から、前記プロジェクト対象物に係る実施済
み工程段階での価値を算出するプロジェクト担保価値算
定部と;を備えるプロジェクトの担保価値算定システ
ム。
1. A project completion value calculating unit for calculating a completion value of the project object by using completion status information of the project object and total contract amount information; and a step in the project object from a project progress management table. A project construction completed value calculation unit that receives the progress status of each project and also receives the contract contract amount information of the executed process related to the project object from the project fulfillment history table; From the completed value of the project object and the contracted contract amount information of the executed process related to the project object calculated by the project construction value calculation unit, the value at the executed process stage related to the project object is calculated. A project collateral value calculation unit for calculating; Project collateral value calculation system.
【請求項2】 前記プロジェクト担保価値算定部は、前
記プロジェクト対象物に係る実施済み工程に対して、前
記請負契約金額に第1の乗率を乗じて実施済み工程に対
する担保価値を算定する請求項1に記載のプロジェクト
の担保価値算定システム。
2. The project collateral value calculating unit calculates a collateral value for an executed process by multiplying the contract contract amount by a first multiplier for the executed process related to the project object. The project collateral value calculation system described in 1.
【請求項3】 プロジェクト対象物の完成状態情報と請
負契約総金額情報を用いて、前記プロジェクト対象物の
完成価値を算出するプロジェクト完成価値算出部と;プ
ロジェクト進捗管理テーブルから前記プロジェクト対象
物を完成状態とするのに必要な追加実施工程を受取ると
共に、前記プロジェクト履行履歴テーブルから前記プロ
ジェクト対象物に係る追加実施工程の請負契約金額情報
を受取るプロジェクト追加工事価値算出部と;前記プロ
ジェクト完成価値算出部にて算出された前記プロジェク
ト対象物の完成価値と、前記プロジェクト追加工事価値
算出部にて算出された前記プロジェクト対象物を完成状
態とするのに必要な追加実施工程の実施見込み金額か
ら、前記プロジェクト対象物に係る実施済み工程段階で
の価値を算出するプロジェクト担保価値算定部と;を備
えるプロジェクトの担保価値算定システム。
3. A project completion value calculation unit for calculating the completion value of the project object by using the completion status information of the project object and the total contract amount information; and the project object completion from the project progress management table. A project additional construction value calculation unit that receives an additional execution process required to bring it into a state, and also receives contract contract amount information of the additional execution process related to the project object from the project fulfillment history table; From the completed value of the project object calculated in step 1 above, and the estimated amount of additional execution steps required to bring the project object to the completed state calculated in the project additional construction value calculator, A professional who calculates the value of the target object at the implemented process stage. A project collateral value calculation system including a project collateral value calculation unit;
【請求項4】 前記プロジェクト担保価値算定部は、前
記プロジェクト対象物を完成状態とするのに必要な追加
実施工程の実施見込み金額に第2の乗率を乗じて実施済
み工程に対する担保価値を算定する請求項3に記載のプ
ロジェクトの担保価値算定システム。
4. The project collateral value calculation unit calculates a collateral value for an already-executed process by multiplying an estimated execution amount of the additional execution process required to complete the project object by a second multiplier. The project collateral value calculation system according to claim 3.
【請求項5】 前記プロジェクト完成価値算出部は、前
記請負契約総金額情報に加えて、さらに完成状態の前記
プロジェクト対象物に類似するプロジェクト対象物に関
して市場における売買情報を加味して前記プロジェクト
対象物の完成価値を算出する請求項1乃至請求項4の何
れか一つに記載のプロジェクトの担保価値算定システ
ム。
5. The project completion value calculation unit, in addition to the contract contract total amount information, further takes into account market trading information regarding a project object similar to the completed project object in the market. The project collateral value calculation system according to claim 1, wherein the completed value is calculated.
【請求項6】 プロジェクト進捗管理テーブルからプロ
ジェクト対象物における実施済みの工程毎の進捗状況を
受取ると共に、プロジェクト履行履歴テーブルから前記
プロジェクト対象物に係る実施済み工程の請負契約金額
情報を受取るプロジェクト工事済価値算出部と;前記プ
ロジェクト進捗管理テーブルから前記プロジェクト対象
物を完成状態とするのに必要な追加実施工程を受取ると
共に、前記プロジェクト履行履歴テーブルから前記プロ
ジェクト対象物に係る追加実施工程の請負契約金額情報
を受取るプロジェクト追加工事価値算出部と;前記プロ
ジェクト工事済価値算出部にて算出された前記プロジェ
クト対象物に係る実施済み工程の請負契約金額情報と、
前記プロジェクト追加工事価値算出部にて算出された前
記プロジェクト対象物を完成状態とするのに必要な追加
実施工程の実施見込み金額から、前記プロジェクト対象
物に係る実施済み工程段階での価値を算出するプロジェ
クト担保価値算定部と;を備えるプロジェクトの担保価
値算定システム。
6. A project construction completed, which receives a progress status of each completed process in the project object from the project progress management table and also receives contract contract amount information of the executed process related to the project object from the project fulfillment history table. A value calculation unit; receives an additional execution process required to bring the project object to a completed state from the project progress management table, and receives a contract contract amount of the additional execution process related to the project object from the project fulfillment history table. A project additional construction value calculation unit that receives information; and a contracted contract amount information of the completed process relating to the project object calculated by the project construction value calculation unit,
Calculate the value at the completed process step for the project object from the estimated amount of additional execution process required to complete the project object calculated by the project additional construction value calculation unit. A collateral value calculation system for a project, comprising: a project collateral value calculation unit;
【請求項7】 前記プロジェクト対象物が請負型の建設
工事であり;前記実施工程には、少なくとも基礎工事、
屋根工事、内装下地工事、完成検査のうち少なくとも一
つを含む請求項1乃至請求項6の何れか一つに記載のプ
ロジェクトの担保価値算定システム。
7. The project object is a contract-type construction work;
The collateral value calculation system for a project according to any one of claims 1 to 6, which includes at least one of roof construction, interior groundwork, and completion inspection.
【請求項8】 さらに、前記プロジェクト担保価値算定
部にて算出された前記プロジェクト対象物に係る実施済
み工程段階での価値に対して、前記プロジェクト対象物
に関する完成状態での売買市場データ、もしくは前記プ
ロジェクト対象物の引渡し後の維持管理記録を参酌し
て、当該価値の修正を行う価値調整手段を備える;請求
項1乃至請求項7の何れか一つに記載のプロジェクトの
担保価値算定システム。
8. Further, the value of the project object calculated at the project collateral value calculation unit at the stage of the completed process with respect to the value of the trading market data in the completed state of the project object, or The collateral value calculation system for a project according to any one of claims 1 to 7, further comprising a value adjusting means for correcting the value by taking into consideration the maintenance record after the delivery of the project object.
【請求項9】 プロジェクト対象物の完成状態情報と請
負契約総金額情報を用いて、前記プロジェクト対象物の
完成価値を算出し;プロジェクト進捗管理テーブルから
前記プロジェクト対象物における実施済みの工程毎の進
捗状況を受取り;前記プロジェクト履行履歴テーブルか
ら前記プロジェクト対象物に係る実施済み工程の請負契
約金額情報を受取り;前記プロジェクト対象物の完成価
値と、前記プロジェクト対象物に係る実施済み工程毎の
進捗状況並びに請負契約総金額情報から、前記プロジェ
クト対象物に係る実施済み工程段階での価値を算出す
る;工程をコンピュータを用いて実行させるプロジェク
トの担保価値算定方法。
9. The completion value of the project object is calculated using the completion status information of the project object and the total contract amount information; the progress of each completed process in the project object from the project progress management table. Receives the status; receives contract contract amount information of the completed process for the project object from the project fulfillment history table; complete value of the project object and the progress of each executed process for the project object, and A value at the completed process step for the project object is calculated from the contract contract total amount information; a collateral value calculation method for a project in which the process is executed using a computer.
【請求項10】 プロジェクト対象物の完成状態情報と
請負契約総金額情報を用いて、前記プロジェクト対象物
の完成価値を算出し;プロジェクト進捗管理テーブルか
ら前記プロジェクト対象物を完成状態とするのに必要な
追加実施工程を受取り;前記プロジェクト履行履歴テー
ブルから前記プロジェクト対象物に係る追加実施工程の
請負契約金額情報を受取り;前記プロジェクト対象物の
完成価値と、前記プロジェクト対象物を完成状態とする
のに必要な追加実施工程の実施見込み金額から、前記プ
ロジェクト対象物に係る実施済み工程段階での価値を算
出する;工程をコンピュータを用いて実行させるプロジ
ェクトの担保価値算定方法。
10. The completion value of the project object is calculated using the completion status information of the project object and the total contract amount information; necessary for setting the completion status of the project object from the project progress management table. To receive the contract execution amount information of the additional execution process relating to the project object from the project fulfillment history table; to complete value of the project object and to complete the project object. A value at the completed process step of the project object is calculated from the expected amount of the necessary additional execution process; a collateral value calculation method for the project in which the process is executed using a computer.
【請求項11】 プロジェクト進捗管理テーブルから前
記プロジェクト対象物における実施済みの工程毎の進捗
状況を受取り;前記プロジェクト履行履歴テーブルから
前記プロジェクト対象物に係る実施済み工程の請負契約
金額情報を受取り;プロジェクト進捗管理テーブルから
前記プロジェクト対象物を完成状態とするのに必要な追
加実施工程を受取り;前記プロジェクト履行履歴テーブ
ルから前記プロジェクト対象物に係る追加実施工程の請
負契約金額情報を受取り;前記プロジェクト対象物に係
る実施済み工程毎の進捗状況並びに請負契約総金額情報
と、前記プロジェクト対象物を完成状態とするのに必要
な追加実施工程の実施見込み金額から、前記プロジェク
ト対象物に係る実施済み工程段階での価値を算出する;
工程をコンピュータを用いて実行させるプロジェクトの
担保価値算定方法。
11. A progress status of each completed process in the project object is received from a project progress management table; contract contract amount information of an executed process related to the project object is received from the project fulfillment history table; Receives additional execution process required to complete the project object from the progress management table; receives contract contract amount information of the additional execution process related to the project object from the project fulfillment history table; the project object Based on the progress status of each performed process and the total amount of contracted contract and the estimated amount of the additional process required to complete the project object, Calculate the value of;
A collateral value calculation method for a project in which a process is executed using a computer.
【請求項12】 既設プロジェクトを建設時と同一工法
によって再建設する場合の再調達価格を算定する再調達
価格算定部と;前記再調達価格算定部で算出した再調達
価格に前記既設プロジェクトの耐用年数と経過年数を元
に算出された現有価値率を乗じ、更に前記既設プロジェ
クトに対する修繕により前記経過年数に対して延長され
た残存寿命を考慮して、前記既設プロジェクトの現在有
している価値を算定する現有価値算定部と;前記既設プ
ロジェクトの流通市場状態を参酌して、前記既設プロジ
ェクトに対する担保価値率を算定する担保価値算定部
と;を備える既設プロジェクトの担保価値算定システ
ム。
12. A replacement procurement price calculation unit for calculating a replacement procurement price when an existing project is reconstructed by the same construction method as at the time of construction; and a replacement procurement price calculated by the replacement procurement price calculation unit for the durability of the existing project. Multiply the current value ratio calculated based on the number of years and the number of years elapsed, and further consider the remaining life extended to the number of years elapsed due to repairs to the existing project, and calculate the value that the existing project currently has. A collateral value calculation system for an existing project, comprising: a current value calculation unit for calculating; and a collateral value calculation unit for calculating a collateral value rate for the existing project, taking into consideration the secondary market state of the existing project.
【請求項13】 既設プロジェクトを建設時と同一工法
によって再建設する場合の再調達価格を算定し;前記算
出された再調達価格に前記既設プロジェクトの耐用年数
と経過年数を元に算出された現有価値率を乗じ、更に前
記既設プロジェクトに対する修繕により前記経過年数に
対して延長された残存寿命を考慮して、前記既設プロジ
ェクトの現在有している価値を算定し;前記既設プロジ
ェクトの流通市場状態を参酌して、前記既設プロジェク
トに対する担保価値率を算定する;工程をコンピュータ
を用いて実行させる既設プロジェクトの担保価値算定方
法。
13. A replacement price when an existing project is rebuilt by the same construction method as that at the time of construction is calculated; the calculated replacement price is calculated based on the service life and elapsed years of the existing project. The value of the existing project is calculated by multiplying the value ratio and further considering the remaining life extended to the elapsed years by the repair of the existing project; Taking the above into consideration, the collateral value rate for the existing project is calculated; a collateral value calculation method for the existing project in which the process is executed using a computer.
JP2002135514A 2002-05-10 2002-05-10 System and method for security value calculation of project and system and method for security value calculation of existent project object Withdrawn JP2003331120A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP2002135514A JP2003331120A (en) 2002-05-10 2002-05-10 System and method for security value calculation of project and system and method for security value calculation of existent project object

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP2002135514A JP2003331120A (en) 2002-05-10 2002-05-10 System and method for security value calculation of project and system and method for security value calculation of existent project object

Publications (1)

Publication Number Publication Date
JP2003331120A true JP2003331120A (en) 2003-11-21

Family

ID=29697819

Family Applications (1)

Application Number Title Priority Date Filing Date
JP2002135514A Withdrawn JP2003331120A (en) 2002-05-10 2002-05-10 System and method for security value calculation of project and system and method for security value calculation of existent project object

Country Status (1)

Country Link
JP (1) JP2003331120A (en)

Cited By (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2007041776A (en) * 2005-08-02 2007-02-15 Shinginko Tokyo Ltd Construction cost credit trust method, senior beneficial interest value calculation device and computer program
KR100914659B1 (en) * 2007-05-29 2009-08-31 주식회사 신한은행 System and Method for Evaluating Project Finance and Program Recording Medium
JP2011048597A (en) * 2009-08-27 2011-03-10 Mas Tax Consulting Co Ltd Collateral value assessment device, collateral value assessment program, and financing system
CN102521698A (en) * 2011-12-14 2012-06-27 华北电力大学 Key process identifying and monitoring method for large building project quality
JP2019109699A (en) * 2017-12-18 2019-07-04 株式会社オービック Construction fee processing apparatus, construction fee processing method, and construction fee processing program

Cited By (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2007041776A (en) * 2005-08-02 2007-02-15 Shinginko Tokyo Ltd Construction cost credit trust method, senior beneficial interest value calculation device and computer program
KR100914659B1 (en) * 2007-05-29 2009-08-31 주식회사 신한은행 System and Method for Evaluating Project Finance and Program Recording Medium
JP2011048597A (en) * 2009-08-27 2011-03-10 Mas Tax Consulting Co Ltd Collateral value assessment device, collateral value assessment program, and financing system
CN102521698A (en) * 2011-12-14 2012-06-27 华北电力大学 Key process identifying and monitoring method for large building project quality
JP2019109699A (en) * 2017-12-18 2019-07-04 株式会社オービック Construction fee processing apparatus, construction fee processing method, and construction fee processing program
JP7042076B2 (en) 2017-12-18 2022-03-25 株式会社オービック Construction price processing equipment, construction price processing method, and construction price processing program

Similar Documents

Publication Publication Date Title
Charette et al. UNIFORMAT II elemental classification for building specifications, cost estimating, and cost analysis
Bajari et al. Auctions versus negotiations in procurement: an empirical analysis
JP2003331120A (en) System and method for security value calculation of project and system and method for security value calculation of existent project object
JP2003331016A (en) System and method for preserving evidence of project
JP2003141431A (en) Project completion guaranteeing system and method
Tolson Dictionary of construction terms
Heldmann Be Your Own House Contractor: Save 25% Without Lifting a Hammer
OE ASSESSMENT OF NEWLY CONSTRUCTED PROPERTY
EDWARDS et al. LSU HSC Connector
Cannon et al. Procedural guidelines for estimating residential and business structure value for use in flood damage estimations
MINUTES et al. A. CALL TO ORDER B. PLEDGE OF ALLEGIANCE C. PRAYER D. PROCLAMATION
Suhendi et al. The Percentage of Structural Costs in Houses Structured Type 30, 36, 45 and 70 with Houses with Simple Structures
GRADING et al. REPUBLIC OF KENYA
SAMBURU REPUBLIC OF KENYA
FRANK ADMINISTRATION & FINANCE DESIGN AND CONSTRUCTION SPECIFICATIONS FOR THE BRESSLER RESEARCH BUILDING-FAÇADE RESTORATION
SPECIAL INSPECTOR GENERAL FOR IRAQ RECONSTRUCTION ARLINGTON VA Baghdad Police College. Baghdad, Iraq
Kesik Economic Assessment of Basement Systems
Angell remodeling older minnesota homes
Officer Sample Only
Napier et al. Preparing technical requirements for third party contracting of army facilities
Mesra NOTICE INVITING OFFERS
Magar Practical approach to construction industry using best value and six sigma techniques
CITY Building, Fire, AND Related Codes
JP2001175716A (en) System for managing real estate information
PA DAHUK REHABILITATION CENTER DAHUK, IRAQ

Legal Events

Date Code Title Description
A300 Application deemed to be withdrawn because no request for examination was validly filed

Free format text: JAPANESE INTERMEDIATE CODE: A300

Effective date: 20050802