JP2011053962A - Method and system for changing production plan - Google Patents

Method and system for changing production plan Download PDF

Info

Publication number
JP2011053962A
JP2011053962A JP2009202911A JP2009202911A JP2011053962A JP 2011053962 A JP2011053962 A JP 2011053962A JP 2009202911 A JP2009202911 A JP 2009202911A JP 2009202911 A JP2009202911 A JP 2009202911A JP 2011053962 A JP2011053962 A JP 2011053962A
Authority
JP
Japan
Prior art keywords
delay
data
schedule
plan
construction
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
JP2009202911A
Other languages
Japanese (ja)
Inventor
Yukio Kurai
幸雄 倉井
Hidetoshi Kon
秀俊 昆
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Mitsubishi Electric Corp
Original Assignee
Mitsubishi Electric Corp
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Mitsubishi Electric Corp filed Critical Mitsubishi Electric Corp
Priority to JP2009202911A priority Critical patent/JP2011053962A/en
Publication of JP2011053962A publication Critical patent/JP2011053962A/en
Pending legal-status Critical Current

Links

Images

Classifications

    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02PCLIMATE CHANGE MITIGATION TECHNOLOGIES IN THE PRODUCTION OR PROCESSING OF GOODS
    • Y02P90/00Enabling technologies with a potential contribution to greenhouse gas [GHG] emissions mitigation
    • Y02P90/02Total factory control, e.g. smart factories, flexible manufacturing systems [FMS] or integrated manufacturing systems [IMS]
    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02PCLIMATE CHANGE MITIGATION TECHNOLOGIES IN THE PRODUCTION OR PROCESSING OF GOODS
    • Y02P90/00Enabling technologies with a potential contribution to greenhouse gas [GHG] emissions mitigation
    • Y02P90/30Computing systems specially adapted for manufacturing

Landscapes

  • Management, Administration, Business Operations System, And Electronic Commerce (AREA)
  • General Factory Administration (AREA)

Abstract

<P>PROBLEM TO BE SOLVED: To obtain a production plan change method that allows changing of a plan when a delay occurs in a production plan. <P>SOLUTION: Data regarding a manufacturing plan is obtained from a production plan backbone system as a target of production plan change processing, it is determined whether a delay occurs in manufacturing work or delivery of a purchase to be used in the work based on the obtained data, a delay reason for work or delivery where the delay occurs and a changed schedule of the manufacturing plan are collected, delay days for each manufacturing plan is determined based on the collected changed schedule, it is determined whether the delay days can be covered by margin days which are spare days set for each item, which is a management unit, and, when it is determined that the delay days can be covered by the margin days, replanning data where a schedule of the manufacturing plan is changed by appropriating the margin days to the delay days, is created. <P>COPYRIGHT: (C)2011,JPO&INPIT

Description

本発明は、生産計画の遅れを考慮した生産計画変更システムに関する。   The present invention relates to a production plan change system that takes into account delays in production planning.

従来、生産管理システムにおいて生産計画を策定するにあたっては、製品情報に基づき生産計画(初期計画)を自動で作成することが一般的である。また、策定した生産計画を管理するために、様々な技術が存在している。たとえば、下記特許文献1では、特定工程を実行する拠点における、予定納期に対する遅延を低減させるための技術が開示されている。また、下記特許文献2では、生産に遅延が発生した場合にその旨を迅速に通知することで、関係者によるタイムリーな対応を可能とするための技術が開示されている。また、下記特許文献3では、顧客からの受注状況に応じて生産を行う複数の生産工場における製品の品質,コスト,納期を一括して管理する技術が開示されている。   Conventionally, in producing a production plan in a production management system, it is common to automatically create a production plan (initial plan) based on product information. In addition, various technologies exist for managing the produced production plan. For example, Patent Document 1 below discloses a technique for reducing a delay with respect to a scheduled delivery date at a base that executes a specific process. Further, Patent Document 2 below discloses a technique for enabling timely response by concerned parties by promptly notifying when a delay occurs in production. Further, Patent Document 3 below discloses a technique for collectively managing product quality, cost, and delivery date in a plurality of production factories that perform production in accordance with orders received from customers.

特開2006−40039号公報Japanese Patent Laid-Open No. 2006-40039 特開2003−330519号公報JP 2003-330519 A 特開2004−246799号公報JP 2004-246799 A

しかしながら、上記従来の技術では、初期計画後に遅れが発生した場合の生産計画の変更については言及されていない。このため、生産計画の変更は、担当部門の判断および裁量に依存したマニュアル処理により行われる。変更にあたっては、製品を構成する細目および素品の親子関係(作業の順番),組織別・設備別の能力、といった点についても考慮が必要であるため、この方法によれば、担当者に多大な負荷がかかる、という問題があった。また、計画変更を実施せずに、作業自体の管理を担当部門の管理者に任せて運用で対応させる場合には、他部門への引渡しの納期に遅れが発生することとなる、という問題があった。   However, the above-described conventional technology does not mention a change in the production plan when a delay occurs after the initial plan. Therefore, the production plan is changed by manual processing depending on the judgment and discretion of the department in charge. When making changes, it is necessary to consider the details of the products and the parent-child relationship of products (order of work), organizational and facility-specific capabilities. There was a problem that a heavy load was applied. In addition, if the management of the work itself is entrusted to the manager of the department in charge without implementing the plan change, there will be a delay in delivery time for delivery to other departments. there were.

本発明は、上記に鑑みてなされたものであって、生産計画に遅れが発生した場合に計画を変更可能とする生産計画変更方法および生産計画変更システムを得ることを目的とする。   This invention is made in view of the above, Comprising: It aims at obtaining the production plan change method and production plan change system which can change a plan when a delay arises in a production plan.

上述した課題を解決し、目的を達成するために、本発明は、工事ごとの製造計画を管理する生産計画基幹システムと接続し、製造計画の変更を行う生産計画変更システム、における生産計画変更方法であって、生産計画変更処理の対象として、前記生産計画基幹システムから製造計画に関するデータを取得するデータ取得ステップと、前記データ取得ステップにて取得したデータに基づいて、製造の作業または作業に用いる購買品の納入に遅れが発生しているかどうかを判定する遅れ判定ステップと、遅れが発生している作業または納入についての遅れ理由、および製造計画の変更日程を収集する遅れ情報収集ステップと、前記遅れ情報収集ステップにて収集した変更日程に基づいて、製造計画ごとの遅れ日数を判断する遅れ日数決定ステップと、管理単位である細目に対して設定される予備日である余裕日数により、前記遅れ日数をまかなえるかどうかを判断し、まかなえると判断した場合は、当該余裕日数を当該遅れ日数に充当することで製造計画の日程を変更した再計画データを作成する余裕日数調整ステップと、を含むことを特徴とする。   In order to solve the above-described problems and achieve the object, the present invention is connected to a production plan backbone system that manages a production plan for each construction, and a production plan change system in a production plan change system that changes a production plan. And, as a target of the production plan change process, a data acquisition step for acquiring data relating to a manufacturing plan from the production plan basic system, and a manufacturing operation or work based on the data acquired in the data acquisition step A delay determination step for determining whether or not there is a delay in delivery of the purchased product, a delay information collection step for collecting a reason for the delay in the operation or delivery in which the delay has occurred, and a schedule for changing the production plan, Based on the change schedule collected in the delay information collection step, the delay days determination step for determining the delay days for each production plan. And if it is determined that the delayed days can be covered by the spare days that are spare days set for the sub-items that are the management unit, and if it is determined that the delayed days are covered, the spare days are applied to the delayed days. And a margin days adjustment step of creating rescheduling data in which the schedule of the production plan is changed.

本発明によれば、担当者への負荷を低減可能となり、迅速かつ正確な計画変更が可能となるという効果を奏する。   According to the present invention, it is possible to reduce the load on the person in charge, and there is an effect that it is possible to change the plan quickly and accurately.

図1は、本発明にかかる生産計画変更システムを含む生産管理システムの、本実施の形態の構成例を示す図である。FIG. 1 is a diagram showing a configuration example of the present embodiment of a production management system including a production plan change system according to the present invention. 図2は、生産管理基幹システムの内部構成例を示すブロック図である。FIG. 2 is a block diagram showing an example of the internal configuration of the production management backbone system. 図3−1は、工事DBの構成例を示す図である。FIG. 3A is a diagram illustrating a configuration example of a construction DB. 図3−2は、製造計画DBの構成例を示す図である。FIG. 3B is a diagram of a configuration example of the manufacturing plan DB. 図3−3は、買券DBの構成例を示す図である。FIG. 3-3 is a diagram illustrating a configuration example of the voucher DB. 図3−4は、工事実績DBの構成例を示す図である。FIG. 3-4 is a diagram illustrating a configuration example of the construction performance DB. 図4は、生産計画変更システムの構成例を示す図である。FIG. 4 is a diagram illustrating a configuration example of a production plan change system. 図5−1は、製造計画遅れDBの構成例を示す図である。FIG. 5A is a diagram illustrating a configuration example of a manufacturing plan delay DB. 図5−2は、買券遅れDBの構成例を示す図である。FIG. 5-2 is a diagram illustrating a configuration example of a ticket delay DB. 図5−3は、遅れ理由DBの構成例を示す図である。FIG. 5C is a diagram of a configuration example of the delay reason DB. 図5−4は、見直し頻度DBの構成例を示す図である。FIG. 5-4 is a diagram illustrating a configuration example of the review frequency DB. 図5−5は、遅れ要因DBの構成例を示す図である。FIG. 5-5 is a diagram illustrating a configuration example of the delay factor DB. 図6は、生産計画変更処理を説明するためのフローチャートである。FIG. 6 is a flowchart for explaining the production plan change process. 図7は、遅れ対応再計画処理を説明するためのフローチャートである。FIG. 7 is a flowchart for explaining the delay re-planning process. 図8は、最適化処理の概要を説明するための図である。FIG. 8 is a diagram for explaining an outline of the optimization process. 図9は、工事別遅れ状況を画面表示した場合の例を示す図である。FIG. 9 is a diagram illustrating an example when the delay status by construction is displayed on the screen.

以下に、本発明にかかる生産計画変更システムの実施の形態を図面に基づいて詳細に説明する。なお、この実施の形態によりこの発明が限定されるものではない。   Hereinafter, an embodiment of a production plan changing system according to the present invention will be described in detail with reference to the drawings. Note that the present invention is not limited to the embodiments.

実施の形態.
図1は、本発明にかかる生産計画変更システムを含む生産管理システムの、本実施の形態の構成例を示す図である。図1の生産管理システムは、一例として、生産管理基幹システム1と、生産計画変更システム2と、これらのシステムにアクセスするための端末3と、LAN(Local Area Network)などのネットワーク4とを備える。生産管理基幹システム1は、既存の基幹系システムであって、製品の生産管理を実施する。生産計画変更システム2は、生産管理基幹システム1にて管理する生産計画の変更を実施する。
Embodiment.
FIG. 1 is a diagram showing a configuration example of the present embodiment of a production management system including a production plan change system according to the present invention. The production management system in FIG. 1 includes, as an example, a production management backbone system 1, a production plan change system 2, a terminal 3 for accessing these systems, and a network 4 such as a LAN (Local Area Network). . The production management backbone system 1 is an existing backbone system, and performs production management of products. The production plan change system 2 changes the production plan managed by the production management backbone system 1.

図2は、生産管理基幹システム1の内部構成例を示すブロック図である。図2の生産管理基幹システム1は、一例として、工事DB11と、製造計画DB12と、買券DB13と、工事実績DB14と、通信I/F部15と、DB処理部16とを備える。工事DB11は、工事単位の情報を管理するためのデータベースである。製造計画DB12は、各工事における製造日程計画を管理するためのデータベースである。買券DB13は、工事に用いる購入品の納品日程を管理するためのデータベースである。工事実績DB14は、製造日程計画の実績を管理するためのデータベースである。なお、本実施の形態における工事とは、製品を生産することである。また、工事DB11,製造計画DB12,買券DB13,工事実績DB14が保持するデータを、それぞれ、工事データ,製造計画データ,買券データ,工事実績データと呼ぶ。   FIG. 2 is a block diagram illustrating an internal configuration example of the production management backbone system 1. The production management backbone system 1 in FIG. 2 includes, as an example, a construction DB 11, a manufacturing plan DB 12, a voucher DB 13, a construction performance DB 14, a communication I / F unit 15, and a DB processing unit 16. The construction DB 11 is a database for managing construction unit information. The production plan DB 12 is a database for managing a production schedule plan for each construction. The voucher DB 13 is a database for managing the delivery schedule of purchased items used for construction. The construction result DB 14 is a database for managing the results of the production schedule. Note that the construction in the present embodiment refers to producing a product. The data held in the construction DB 11, the production plan DB 12, the purchase ticket DB 13, and the construction result DB 14 are referred to as construction data, production plan data, purchase ticket data, and construction result data, respectively.

図3−1は、工事DB11の構成例を示す図である。図3−1の例では、工事DB11は、「工事番号」,「工事件名」,「注文元」,「機種」,「工事命令日」,「工事完了日」,「契約納期」,「工事規模」,「設計書種類」,「図面数」,「細目数」,「素品数」,「作業工程数」,「遅れポイント」,「遅れ日数」,「計画変更ポイント」、といった項目を備える。すなわち、当該工事DB11では、工事の基本情報と、工事の日程を管理するために必要な各種情報とを管理する。当該工事DB11のキー項目は「工事番号」である。   FIG. 3A is a diagram illustrating a configuration example of the construction DB 11. In the example of FIG. 3A, the construction DB 11 includes “construction number”, “construction subject”, “order source”, “model”, “construction order date”, “construction completion date”, “contract delivery date”, “construction”. Items such as “Scale”, “Design document type”, “Number of drawings”, “Number of sub-items”, “Number of original products”, “Number of work processes”, “Delay point”, “Delay days”, “Plan change point” are provided. . That is, the construction DB 11 manages basic information of construction and various information necessary for managing the construction schedule. The key item of the construction DB 11 is “construction number”.

図3−1にて各項目に対して付した説明の通り、「工事番号」は、工事を一意に管理するための番号である。「工事件名」は、工事の名称である。「注文元」は、その工事を注文した顧客である。「機種」は、生産対象とする製品の機種である。「工事命令日」は、工事(生産)の開始日である。「工事完了日」は、工事(生産)の完了期限日である。「契約納期」は、上記「注文元」と契約した納期である。「工事規模」は、受注金額である。「設計書種類」は、生産対象とする製品について作成された設計書の数量である。「図面数」は、生産対象とする製品の図面の数である。「細目数」は、生産の管理単位である細目の数である。「素品数」は、生産対象とする製品にて、上記「細目」に属する部品の数である。「作業工程数」は、生産対象とする製品を製造するための全工程数である。「遅れポイント」は、遅れが発生した場合の遅延度数であって、一例として、ここでは、“設計/加工/組立/試験/出荷”といった工程単位で値を保持する。「遅れ日数」は、製造計画にて発生した遅れの日数であって、たとえば、上記の工程単位で値を保持する。「計画変更ポイント」は、製造計画を変更した件数であって、たとえば、上記の工程単位で値を保持する。   As described for each item in FIG. 3A, the “construction number” is a number for uniquely managing the construction. “Construction subject” is the name of the construction. “Order source” is the customer who ordered the construction. “Model” is the model of the product to be produced. “Construction order date” is the start date of construction (production). “Construction completion date” is the deadline date for completion of construction (production). The “contract delivery date” is a delivery date contracted with the “order source”. “Construction scale” is the order amount. “Design document type” is the quantity of design documents created for a product to be produced. “Number of drawings” is the number of drawings of the product to be produced. “Number of details” is the number of details which is a management unit of production. The “number of elementary products” is the number of parts belonging to the “details” in the product to be produced. The “number of work processes” is the total number of processes for manufacturing a product to be produced. The “delay point” is a delay frequency when a delay occurs, and as an example, here, a value is held in process units such as “design / processing / assembly / test / shipment”. “Delay days” is the number of days of delay that occurred in the production plan, and holds a value for each process unit, for example. The “plan change point” is the number of cases where the production plan is changed, and holds a value for each process unit, for example.

図3−2は、製造計画DB12の構成例を示す図である。図3−2の例では、製造計画DB12は、「工事番号」,「細目コード」,「素品コード」,「作業工程コード」,「部門コード」,「作業着手日(初期計画)」,「作業完了日(初期計画)」,「作業着手日(最新計画)」,「作業完了日(最新計画)」,「親細目コード」,「細目余裕日数」、といった項目を備える。すなわち、当該製造計画DB12では、各工事に属する細目単位で作業日程を管理する。当該製造計画DB12のキー項目は、「工事番号」,「細目コード」,「素品コード」,「作業工程コード」である。   FIG. 3B is a diagram illustrating a configuration example of the manufacturing plan DB 12. In the example of FIG. 3B, the production plan DB 12 includes “construction number”, “detail code”, “element code”, “work process code”, “department code”, “work start date (initial plan)”, Items such as “work completion date (initial plan)”, “work start date (current plan)”, “work completion date (current plan)”, “parent detail code”, and “detail margin days” are provided. That is, in the manufacturing plan DB 12, the work schedule is managed in units of details belonging to each construction. The key items of the production plan DB 12 are “construction number”, “detail code”, “element code”, and “work process code”.

図3−2にて各項目に対して付した説明の通り、「工事番号」は、工事を一意に管理するための番号である。「細目コード」は、細目のコードである。「素品コード」は、上記細目に属する部品のコードである。「作業工程コード」は、各素品に対して実施する作業工程のコードである。「部門コード」は、上記作業工程を実施する部門のコードである。「作業着手日(初期計画)」は、初期計画時、すなわち工事が発令された時点での、各作業工程への着手予定日である。「作業完了日(初期計画)」は、工事が発令された時点での、各作業工程の完了予定日である。「作業着手日(最新計画)」は、計画変更後の作業工程の着手予定日である。「作業完了日(最新計画)」は、計画変更後の作業工程の完了予定日である。「親細目コード」は、上記細目コードで示す細目からみて親となる細目の細目コードである。「細目余裕日数」は、細目単位の製造日程(着手日〜完了日)に対する予備日数である。   As described for each item in FIG. 3-2, the “construction number” is a number for uniquely managing the construction. “Fine code” is a fine code. The “element code” is a code of a part belonging to the details. The “work process code” is a code of a work process to be performed for each elementary product. The “department code” is a code of a department that performs the work process. The “work start date (initial plan)” is a scheduled start date for each work process at the time of initial planning, that is, when construction is issued. The “work completion date (initial plan)” is a scheduled completion date of each work process at the time the work is issued. “Work start date (latest plan)” is a scheduled start date of the work process after the plan change. The “work completion date (current plan)” is the scheduled completion date of the work process after the plan change. The “parent-detail code” is a fine-detail code that is a parent when viewed from the details indicated by the detail code. The “detail margin days” is the number of spare days for the production schedule (start date to completion date) in detail units.

なお、本実施の形態における製造計画では、細目単位に製造計画を策定する。細目は、階層構造を有し、管理のうえで下位の細目となる子細目と、上位の細目となる親細目が存在する。親細目は、複数の子細目を紐付けて管理する。親細目および子細目は、それぞれ、独自の細目余裕日数を保持する。また、本実施の形態における製造日程計画は、工事間で平行して策定されるとする。   In the production plan in the present embodiment, a production plan is formulated for each detailed unit. The sub-items have a hierarchical structure, and there are child sub-items that are subordinate subordinates and parent sub-items that are upper subordinates in terms of management. The parent item is managed by linking a plurality of child items. Each of the parent details and the child details has its own item margin days. In addition, it is assumed that the production schedule in the present embodiment is formulated in parallel between works.

図3−3は、買券DB13の構成例を示す図である。図3−3の例では、買券DB13は、「購買コード」,「工事番号」,「細目コード」,「素品コード」,「注文納期」,「回答納期」,「入着日」,「購入先」、といった項目を備える。「購買コード」は、購入品の注文番号である。「工事番号」は、上記購入品を使用する先の工事の番号である。「細目コード」は、上記購入品を使用する細目のコードである。「素品コード」は、上記細目のなかで、上記購入品を使用する部品のコードである。「注文納期」は、初期計画時の購入品の納入予定日である。「回答納期」は、注文納期を購入先に提示した結果、当該購入先から回答された納入予定日である。「入着日」は、購入先から当該購入品が実際に納品された日である。「購入先」は、上記購入品の購入先である。   FIG. 3-3 is a diagram illustrating a configuration example of the voucher DB 13. In the example of FIG. 3C, the voucher DB 13 includes “purchase code”, “construction number”, “detail code”, “element code”, “order delivery date”, “answer delivery date”, “arrival date”, “Purchase” is provided. “Purchase code” is the order number of the purchased item. “Construction number” is the number of the construction that uses the purchased product. The “detail code” is a detail code that uses the purchased product. The “element code” is a code of a part that uses the purchased item among the details. “Order delivery date” is the scheduled delivery date of the purchased product at the time of initial planning. “Reply delivery date” is a scheduled delivery date that is returned from the purchaser as a result of presenting the order delivery date to the purchaser. The “arrival date” is the date when the purchased item is actually delivered from the purchaser. “Purchase” is the purchaser of the purchased item.

図3−4は、工事実績DB14の構成例を示す図である。図3−4の例では、工事実績DB14は、「工事番号」,「細目コード」,「素品コード」,「部門コード」,「作業着手日(実績)」,「作業完了日(実績)」、といった項目を備える。図3−4にて各項目に対して付した説明の通り、「工事番号」は、工事を一意に管理するための番号である。「工事番号」,「細目コード」,「素品コード」,「部門コード」は、上述の製造計画DB12の項目と同様である。「作業着手日(実績)」は、実際に各作業工程が着手された実績日である。「作業完了日(実績)」は、実際に各作業工程が完了された実績日である。当該工事実績DB14のキー項目は、「工事番号」,「細目コード」,「素品コード」である。   FIG. 3-4 is a diagram illustrating a configuration example of the construction performance DB 14. In the example of FIG. 3-4, the construction result DB 14 stores “construction number”, “detail code”, “element code”, “department code”, “work start date (actual)”, and “work completion date (actual)”. And the like. As described for each item in FIG. 3-4, the “construction number” is a number for uniquely managing the construction. The “construction number”, “detail code”, “element code”, and “department code” are the same as the items in the manufacturing plan DB 12 described above. “Work start date (actual result)” is the actual date when each work process was actually started. “Work completion date (actual)” is the actual date when each work process was actually completed. The key items of the construction result DB 14 are “construction number”, “detail code”, and “element code”.

図4は、生産計画変更システム2の構成例を示す図である。図4の生産計画変更システム2は、一例として、制御部20と、記憶部30と、通信I/F部50とを備える。制御部20は、データ取得部21と、遅れ判定部22と、遅れ情報処理部23と、再計画部24と、再計画確認部25と、再計画確定部26と、メール機能部27とを備える。また、記憶部30は、工事DB31と、製造計画DB32と、買券DB33と、工事実績DB34と、製造計画遅れDB35と、買券遅れDB36と、遅れ理由DB37と、見直し頻度DB38と、遅れ要因DB39と、再計画DB40とを備える。   FIG. 4 is a diagram illustrating a configuration example of the production plan change system 2. The production plan change system 2 of FIG. 4 includes a control unit 20, a storage unit 30, and a communication I / F unit 50 as an example. The control unit 20 includes a data acquisition unit 21, a delay determination unit 22, a delay information processing unit 23, a replanning unit 24, a replanning confirmation unit 25, a replanning confirmation unit 26, and a mail function unit 27. Prepare. In addition, the storage unit 30 includes a construction DB 31, a production plan DB 32, a purchase ticket DB 33, a construction performance DB 34, a production plan delay DB 35, a ticket delay DB 36, a delay reason DB 37, a review frequency DB 38, and a delay factor. DB39 and replan DB40 are provided.

データ取得部21は、生産計画変更処理の対象として、生産管理基幹システム1(工事DB11,製造計画DB12,買券DB13,工事実績DB14)からデータを取得する。遅れ判定部22は、データ取得部21が取得したデータに基づいて、工事に遅れが発生しているかどうかを判定する。遅れ情報処理部23は、遅れが発生している工事について、メール機能部27を用いて、関係者から情報を収集する。再計画部24は、関係者から収集した情報に基づいて、遅れが発生している工事に対して再計画処理を実行し、再計画データを作成する。再計画確認部25は、メール機能部27を用いて再計画データを関連部門に通知し、承認を得る。再計画確定部26は、再計画データが認証された場合に、メール機能部27を用いて再計画に関するデータを送信し、また、その内容を蓄積するための各種処理を行う。メール機能部27は、電子メールの送信および受信を行うための機能を有する。なお、ここでは、関係者への通知のため電子メールを用いるが、他の手段であってもよい。   The data acquisition unit 21 acquires data from the production management backbone system 1 (construction DB 11, production plan DB 12, purchase ticket DB 13, construction result DB 14) as an object of the production plan change process. The delay determination unit 22 determines whether there is a delay in the construction based on the data acquired by the data acquisition unit 21. The delayed information processing unit 23 uses the mail function unit 27 to collect information from related parties regarding the construction in which the delay has occurred. The re-planning unit 24 executes re-planning processing for the construction in which the delay has occurred based on the information collected from the parties concerned, and creates re-planning data. The replan confirmation unit 25 notifies the related department of the replan data using the mail function unit 27 and obtains approval. When the re-planning data is authenticated, the re-planning determination unit 26 transmits data related to the re-planning using the mail function unit 27 and performs various processes for accumulating the contents. The mail function unit 27 has a function for sending and receiving electronic mail. Here, e-mail is used for notification to the parties concerned, but other means may be used.

工事DB31は、工事DB11の工事データを保持するためのデータベースである。製造計画DB32は、製造計画DB12の製造計画データを保持するためのデータベースである。買券DB33は、買券DB13の買券データを保持するためのデータベースである。工事実績DB34は、工事実績DB14の工事実績データを保持するためのデータベースである。製造計画遅れDB35は、製造計画に遅れが発生している製造計画データに対する遅れの情報を登録するためのデータベースである。買券遅れDB36は、納入に遅れが発生している購入品に対する遅れの情報を登録するためのデータベースである。遅れ理由DB37は、マスタであって、遅れ理由に応じた遅れ度数(重み付け)を管理するためのデータベースである。見直し頻度DB38は、計画変更が発生した頻度を蓄積するためのデータベースである。遅れ要因DB39は、遅れ要因の解析に役立てるために、遅れ理由などを蓄積するためのデータベースである。再計画DB40は、再計画処理による仮の再計画データを保持するためのデータベースである。   The construction DB 31 is a database for holding construction data of the construction DB 11. The production plan DB 32 is a database for holding the production plan data of the production plan DB 12. The voucher DB 33 is a database for holding the voucher data of the voucher DB 13. The construction performance DB 34 is a database for holding construction performance data of the construction performance DB 14. The manufacturing plan delay DB 35 is a database for registering delay information for manufacturing plan data in which a delay has occurred in the manufacturing plan. The ticket delay DB 36 is a database for registering delay information for purchased items that have been delayed in delivery. The delay reason DB 37 is a database for managing the delay frequency (weighting) corresponding to the reason for delay. The review frequency DB 38 is a database for accumulating the frequency at which a plan change has occurred. The delay factor DB 39 is a database for accumulating reasons for delay and the like in order to be useful for analysis of delay factors. The replan DB 40 is a database for holding temporary replan data by replan processing.

上述の通り、工事DB31,製造計画DB32,買券DB33,工事実績DB34は、工事DB11,製造計画DB12,買券DB13または工事実績DB14のデータのコピー(工事データ,製造計画データ,買券データ,工事実績データ)をそれぞれ保持する。また、製造計画遅れDB35,買券遅れDB36,遅れ理由DB37,見直し頻度DB38,遅れ要因DB39,再計画DB40が保持するデータを、それぞれ、製造計画遅れデータ,買券遅れデータ,遅れ理由データ,見直し頻度データ,遅れ要因データ,再計画データと呼ぶ。   As described above, the construction DB 31, the production plan DB 32, the purchase ticket DB 33, and the construction performance DB 34 are copies of the construction DB 11, the production plan DB 12, the purchase ticket DB 13, or the construction performance DB 14 (construction data, production plan data, purchase ticket data, Holds construction results data). Further, the data held in the manufacturing plan delay DB 35, the purchase ticket delay DB 36, the delay reason DB 37, the review frequency DB 38, the delay factor DB 39, and the replan DB 40 are respectively updated in the manufacture plan delay data, the ticket delay data, the delay reason data, and the review. It is called frequency data, delay factor data, and replan data.

工事DB31,製造計画DB32,買券DB33,工事実績DB34は、それぞれ、工事DB11,製造計画DB12,買券DB13,工事実績DB14と同じ構成である。   The construction DB 31, the production plan DB 32, the purchase ticket DB 33, and the construction performance DB 34 have the same configurations as the construction DB 11, the production plan DB 12, the purchase ticket DB 13, and the construction performance DB 14, respectively.

図5−1は、製造計画遅れDB35の構成例を示す図である。図5−1の例では、製造計画遅れDB35は、「工事番号」,「細目コード」,「素品コード」,「作業工程コード」,「部門コード」,「作業着手日(初期計画)」,「作業完了日(初期計画)」,「遅れ理由」,「着手可能日(最新計画)」,「完了可能日(最新計画)」、といった項目を備える。「工事番号」は、製造日程計画に遅れが発生した工事の番号である。「細目コード」は、上記工事において製造日程計画に遅れが発生した細目のコードである。「素品コード」は、上記工事において製造日程計画に遅れが発生した素品のコードである。「作業工程コード」は、上記工事において製造日程計画に遅れが発生した作業工程のコードである。「部門コード」は、上記作業工程を実施する部門のコードである。「作業着手日(初期計画)」は、工事が発令された時点での、各作業工程への着手予定日である。「作業完了日(初期計画)」は、工事が発令された時点での、各作業工程の完了予定日である。「着手可能日(最新計画)」は、計画変更後の作業工程の着手可能日である。「完了可能日(最新計画)」は、計画変更後の作業工程の完了可能日である。当該製造計画遅れDB35のキー項目は、「工事番号」,「細目コード」,「素品コード」,「作業工程コード」である。また、再計画DB40は、製造計画遅れDB35と同じ構成を有する。   FIG. 5A is a diagram illustrating a configuration example of the manufacturing plan delay DB 35. In the example of FIG. 5A, the production plan delay DB 35 includes “construction number”, “detail code”, “component code”, “work process code”, “department code”, “work start date (initial plan)”. , “Work completion date (initial plan)”, “reason for delay”, “startable date (current plan)”, “completion date (current plan)”. “Construction number” is the number of the construction in which the production schedule was delayed. The “detail code” is a detail code in which the production schedule is delayed in the above construction. The “element code” is an element code for which a delay has occurred in the manufacturing schedule plan in the above construction. The “work process code” is a code of a work process in which a delay has occurred in the production schedule plan in the above construction. The “department code” is a code of a department that performs the work process. The “work start date (initial plan)” is a scheduled start date for each work process at the time the work is issued. The “work completion date (initial plan)” is a scheduled completion date of each work process at the time the work is issued. “Available date (current plan)” is a date when the work process can be initiated after the plan is changed. “Completion date (current plan)” is a completion date of the work process after the plan change. The key items of the production plan delay DB 35 are “construction number”, “detail code”, “element code”, and “work process code”. Further, the replanning DB 40 has the same configuration as the manufacturing plan delay DB 35.

図5−2は、買券遅れDB36の構成例を示す図である。図5−2の例では、買券遅れDB36は、「購買コード」,「工事番号」,「細目コード」,「素品コード」,「部門コード」,「注文納期」,「回答納期」,「遅れ理由」,「回答納期(最新計画)」、といった項目を備える。「購買コード」は、納入に遅れが発生した購入品の注文番号である。「工事番号」は、上記購入品を使用する先の工事の番号である。「細目コード」は、上記購入品を使用する細目のコードである。「素品コード」は、上記細目のなかで、上記購入品を使用する部品のコードである。「部門コード」は、注文部門のコードである。「注文納期」は、初期計画時の購入品の納入予定日である。「回答納期」は、注文納期を購入先に提示した結果、当該購入先から回答された納入予定日である。「遅れ理由」は、購入品の納入が遅れる理由である。「回答納期(最新計画)」は、購入先からの最新の回答納期である。   FIG. 5-2 is a diagram illustrating a configuration example of the ticket delay DB 36. In the example of FIG. 5B, the ticket delay DB 36 includes “purchase code”, “construction number”, “detail code”, “element code”, “department code”, “order delivery date”, “answer delivery date”, Items such as “reason for delay” and “response delivery date (latest plan)” are provided. “Purchase code” is the order number of the purchased item that has been delayed in delivery. “Construction number” is the number of the construction that uses the purchased product. The “detail code” is a detail code that uses the purchased product. The “element code” is a code of a part that uses the purchased item among the details. “Department code” is a code of the order department. “Order delivery date” is the scheduled delivery date of the purchased product at the time of initial planning. “Reply delivery date” is a scheduled delivery date that is returned from the purchaser as a result of presenting the order delivery date to the purchaser. The “reason for delay” is the reason for delay in delivery of purchased products. The “response delivery date (latest plan)” is the latest response delivery date from the purchaser.

図5−3は、遅れ理由DB37の構成例を示す図である。図5−3の例では、遅れ理由DB37は、「作業工程コード」,「遅れ理由コード」,「遅れ理由名」,「遅れポイント」、といった項目を備える。当該データベースでは、作業遅れの理由を管理する。「作業工程コード」は、作業工程のコードである。「遅れ理由コード」は、遅れが発生した理由を示すコードである。「遅れ理由名」は、遅れ理由を分類した名称である。たとえば、“設計ミスによる作業遅延”,“設備の不備による作業遅延”,“購入品の発注ミス”といったように分類する。「遅れポイント」は、「作業工程コード」と「遅れ理由コード」の組み合わせに対応する遅れの度合いである。当該遅れ理由DB37のキー項目は、「作業工程コード」および「遅れ理由コード」である。   FIG. 5C is a diagram illustrating a configuration example of the delay reason DB 37. In the example of FIG. 5C, the delay reason DB 37 includes items such as “work process code”, “delay reason code”, “delay reason name”, and “delay point”. In this database, the reason for work delay is managed. The “work process code” is a work process code. The “delay reason code” is a code indicating the reason for the delay. The “reason for delay” is a name that classifies the reason for delay. For example, it is classified as “work delay due to design error”, “work delay due to inadequate equipment”, or “ordering mistake of purchased product”. The “delay point” is a degree of delay corresponding to a combination of “work process code” and “delay reason code”. The key items of the delay reason DB 37 are “work process code” and “delay reason code”.

図5−4は、見直し頻度DB38の構成例を示す図である。図5−4の例では、見直し頻度DB38は、「作業工程コード」,「部門コード」,「見直し頻度」、といった項目を備える。「作業工程コード」は、作業工程のコードである。「部門コード」は、上記作業工程を実施する部門のコードである。「見直し頻度」は、「作業工程コード」および「部門コード」の組み合わせに対して計画変更がなされた頻度である。頻度とは、たとえば、月ごとに計画変更の回数を蓄積した値であるが、他の定義でもよい。   FIG. 5-4 is a diagram illustrating a configuration example of the review frequency DB 38. In the example of FIG. 5-4, the review frequency DB 38 includes items such as “work process code”, “department code”, and “review frequency”. The “work process code” is a work process code. The “department code” is a code of a department that performs the work process. The “review frequency” is a frequency at which a plan change is made for a combination of “work process code” and “department code”. The frequency is, for example, a value obtained by accumulating the number of plan changes every month, but may be another definition.

図5−5は、遅れ要因DB39の構成例を示す図である。図5−5の例では、遅れ要因DB39は、「レコードID」,「日付」,「作業工程コード」,「遅れ理由名」,「部門コード」,「備考」といった項目を備える。「レコードID」は、各レコードの識別子である。「日付」は、遅れ理由を入力したときのシステム日付である。「作業工程コード」,「遅れ理由名」は、遅れ理由DB37の各項目と同じである。「部門コード」は、上記作業工程を実施する部門のコードである。「備考」は、遅れ状況を補足するための情報である。   FIG. 5-5 is a diagram illustrating a configuration example of the delay factor DB 39. In the example of FIG. 5-5, the delay factor DB 39 includes items such as “record ID”, “date”, “work process code”, “delay reason name”, “department code”, and “remarks”. “Record ID” is an identifier of each record. “Date” is the system date when the reason for delay is input. The “work process code” and “delay reason name” are the same as the items in the delay reason DB 37. The “department code” is a code of a department that performs the work process. “Remarks” is information for supplementing the delay situation.

つづいて、以上のように構成された生産計画変更システムの動作について説明する。図6は、生産計画変更処理を説明するためのフローチャートである。当該生産計画変更処理は、たとえば、日次で起動される。   Next, the operation of the production plan change system configured as described above will be described. FIG. 6 is a flowchart for explaining the production plan change process. The production plan change process is started daily, for example.

制御部20のデータ取得部21は、通信I/F部50を介して、生産管理基幹システム1に対し、データの収集を要求する。生産管理基幹システム1のDB処理部16は、通信I/F部50を介して当該要求を受信すると、工事DB11,製造計画DB12,買券DB13,工事実績DB14から全てのデータを読み出し、通信I/F部50を介して生産計画変更システム2へ送信する。生産計画変更システム2の通信I/F部50は、当該データを受信すると制御部20へ出力し、制御部20のデータ取得部21は、受信したデータを、それぞれ、工事DB31,製造計画DB32,買券DB33または工事実績DB34に登録する(ステップS1)。そして、遅れ判定部22に対し、データの収集を行った旨を通知する。   The data acquisition unit 21 of the control unit 20 requests the production management backbone system 1 to collect data via the communication I / F unit 50. When the DB processing unit 16 of the production management backbone system 1 receives the request via the communication I / F unit 50, the DB processing unit 16 reads all data from the construction DB 11, the manufacturing plan DB 12, the voucher DB 13, and the construction performance DB 14, and transmits the communication I. The data is transmitted to the production plan change system 2 via the / F unit 50. When the communication I / F unit 50 of the production plan changing system 2 receives the data, the communication I / F unit 50 outputs the data to the control unit 20, and the data acquisition unit 21 of the control unit 20 converts the received data into the construction DB 31, the production plan DB 32, Registration is made in the voucher DB 33 or the construction result DB 34 (step S1). Then, the delay determination unit 22 is notified that the data has been collected.

制御部20の遅れ判定部22は、工事DB31,製造計画DB32,買券DB33,工事実績DB34からデータを読み出し、当該データに基づいて、工事に遅れが発生しているかどうかを判定する(ステップS2)。工事の遅れは、作業の遅れまたは納入の遅れにより発生する。具体的には、作業の遅れを判定するために、以下の処理を行う。遅れ判定部22は、製造計画データと工事実績データとを、「工事番号」,「細目コード」,「素品コード」,「作業工程コード」が一致するもの同士で比較する。まず、工事実績データの「作業着手日(実績)」が、製造計画データの最新の作業着手日(すなわち、「作業着手日(最新計画)」の値,または当該値がセットされてなければ「作業着手日(初期計画)」の値)以前であるかどうかをチェックする。「作業着手日(実績)」が、製造計画データの最新の作業着手日以前である場合には、作業遅れによる着手日の遅延は発生していないと判断する。一方、「作業着手日(実績)」が、製造計画データの最新の作業着手日より後である場合には、作業遅れによる着手日の遅延が発生していると判断する。また、工事実績データの「作業完了日(実績)」が、製造計画データの最新の作業完了日(すなわち、「作業完了日(最新計画)」の値,または当該値がセットされてなければ「作業完了日(初期計画)」の値)以前であるかどうかをチェックする。「作業完了日(実績)」が、製造計画データの最新の作業完了日以前である場合には、作業遅れによる完了日の遅延は発生していないと判断する。一方、「作業完了日(実績)」が、製造計画データの最新の作業完了日より後である場合には、作業遅れによる完了日の遅延が発生していると判断する。   The delay determination unit 22 of the control unit 20 reads data from the construction DB 31, the production plan DB 32, the purchase ticket DB 33, and the construction performance DB 34, and determines whether or not there is a delay in the construction based on the data (step S2). ). Construction delays occur due to work delays or delivery delays. Specifically, the following processing is performed to determine work delay. The delay determination unit 22 compares the production plan data and the construction result data with those having the same “construction number”, “detail code”, “component code”, and “work process code”. First, the “work start date (actual)” in the construction result data is the latest work start date (that is, “work start date (current plan)” in the production plan data, or if the value is not set, “ Check whether it is before the value of “work start date (initial plan)”. If the “work start date (actual)” is before the latest work start date in the production plan data, it is determined that the start date is not delayed due to work delay. On the other hand, if the “work start date (actual)” is after the latest work start date of the production plan data, it is determined that the start date is delayed due to work delay. In addition, the “work completion date (actual)” of the construction performance data is the latest work completion date (that is, “work completion date (current plan)”) of the manufacturing plan data, or if the value is not set, “ Check whether it is before the value of “work completion date (initial plan)”. If the “work completion date (actual)” is before the latest work completion date in the production plan data, it is determined that the completion date is not delayed due to work delay. On the other hand, when the “work completion date (actual result)” is after the latest work completion date of the production plan data, it is determined that the completion date is delayed due to the work delay.

また、納入の遅れに基づく工事の遅れを判定するために、以下の処理を行う。まず、遅れ判定部22は、買券データの「注文納期」、「回答納期」、「入着日」を比較する。「回答納期」のみデータがあり、「入着日」にデータがない場合、「回答納期」が「注文納期」以前であるかどうかをチェックする。一方、「回答納期」および「入着日」にいずれもデータがある場合、「入着日」が「回答納期」以前であるかどうかをチェックする。これらの結果、「回答納期」が「注文納期」より後であった場合、または「入着日」が「回答納期」より後であった場合には、納入に遅れが発生していると判定する。   In addition, the following processing is performed to determine the construction delay based on the delivery delay. First, the delay determination unit 22 compares “order delivery date”, “answer delivery date”, and “arrival date” of the voucher data. When there is data only for “response delivery date” and no data for “arrival date”, it is checked whether “response delivery date” is before “order delivery date”. On the other hand, if there is data in both “answer delivery date” and “arrival date”, it is checked whether “arrival date” is before “answer delivery date”. As a result, if the “response delivery date” is later than the “order delivery date”, or if the “arrival date” is later than the “response delivery date”, it is determined that there is a delay in delivery. To do.

以上のように遅れが発生していると判断した場合、遅れ判定部22は、遅れが発生している工事についての製造計画データを、製造計画遅れDB35に登録する。また、納入遅れが発生していると判断した買券データを買券遅れDB36に登録する。そして、当該製造計画データまたは当該買券データと、作業遅れまたは納入遅れを指定して、遅れ情報処理部23に遅れが発生している旨を通知する。   When it is determined that a delay has occurred as described above, the delay determination unit 22 registers the manufacturing plan data for the construction in which the delay has occurred in the manufacturing plan delay DB 35. Further, the voucher data determined to have a delivery delay is registered in the voucher delay DB 36. Then, the manufacturing plan data or the voucher data and work delay or delivery delay are designated, and the delay information processing unit 23 is notified that a delay has occurred.

遅れ情報処理部23は、当該製造計画データまたは当該買券データと、作業遅れまたは納入遅れが発生しているメッセージとをメール機能部27に出力するとともに、担当者へ電子メールを送信するよう指示する。   The delay information processing unit 23 outputs the manufacturing plan data or the voucher data and a message indicating that work delay or delivery delay has occurred to the mail function unit 27 and instructs the person in charge to send an e-mail. To do.

制御部20のメール機能部27は、上記データを受け取ると、たとえば、いずれのデータの場合にも「部門コード」を参照し、当該部門コードに該当するメールアドレスを、自身が保持するアドレス帳から取得する。そして、受け取ったデータ1件ずつについて、当該データの内容を含め、当該メールアドレスを宛先とし、通信I/F部50を介して、遅れ状況を収集するためのメールである遅れ理由収集メールを送信する(ステップS3)。   When receiving the data, the mail function unit 27 of the control unit 20 refers to the “department code” in any data, for example, and obtains the mail address corresponding to the department code from the address book held by itself. get. Then, for each received data, a delay reason collection mail that is a mail for collecting a delay situation is transmitted via the communication I / F unit 50 with the mail address as a destination including the contents of the data. (Step S3).

図1の端末3などにおいて遅れ理由収集メールを受信した各部門の担当者(関係者)は、電子メールの内容により、作業遅れまたは納入遅れが発生していると認識する。担当者は、作業遅れが発生している場合には、現場の状況などにより計画が変更になるかどうかを判断し、変更になる場合には変更後の日程をまとめる。また、納入遅れが発生している場合には、その事情などをまとめる。そして、担当者は、たとえば、これらの報告内容を上記電子メールに追加して、生産計画の管理者などに転送する。図1の端末3などにおいて、転送された遅れ理由収集メールを受信した管理者(関係者)は、当該メールに含まれるメッセージにより、作業遅れまたは納入遅れが発生していると認識する。管理者は、必要に応じて担当者や購入先に問合せを行い、また、生産管理基幹システム1における工事DB11,製造計画DB12,買券DB13,工事実績DB14や、生産計画変更システム2における遅れ要因DB39を参照する。そして、管理者は、遅れに対する対策を考え、遅れの理由によって予想される必要日数を勘案して計画の変更を判断する。そして、作業遅れまたは納入遅れにより変更される製造計画データの計画変更日程(作業着手日および/または作業完了日)を決定する。ここで、遅れにより製造計画を変更する対象となる製造計画データを、製造計画遅れ発生データという。また、納入遅れが発生した買券データを買券遅れ発生データという。納入遅れの場合には、さらに、購入先より最新回答納期を得る。なお、納入遅れの場合でも、既に購入品が入着している場合(入着日が確定している場合)には、最新の回答納期は必要ない。なお、ここでは担当者と管理者が作業を分担するが、たとえば管理者が全ての作業を行ってもよい。   The person in charge (related person) of each department who has received the delay reason collection mail at the terminal 3 or the like in FIG. 1 recognizes that work delay or delivery delay has occurred according to the content of the email. When the work delay occurs, the person in charge determines whether or not the plan is changed depending on the situation at the site, and if so, summarizes the schedule after the change. If there is a delivery delay, summarize the circumstances. Then, for example, the person in charge adds these report contents to the e-mail and transfers them to the manager of the production plan. In the terminal 3 of FIG. 1 and the like, the administrator (related person) who has received the forwarded delay reason collection mail recognizes that work delay or delivery delay has occurred due to the message included in the mail. The manager makes an inquiry to the person in charge or the purchaser as necessary, and the delay factor in the construction DB 11, manufacturing plan DB 12, voucher DB 13, construction result DB 14, and production plan change system 2 in the production management backbone system 1. Refer to DB39. Then, the manager considers countermeasures for the delay, and determines the plan change in consideration of the necessary number of days expected for the reason of the delay. Then, the schedule change schedule (work start date and / or work completion date) of the production plan data changed due to work delay or delivery delay is determined. Here, the production plan data for which the production plan is changed due to the delay is referred to as production plan delay occurrence data. The voucher data for which delivery delay has occurred is referred to as voucher delay occurrence data. In the case of delivery delay, the latest answer delivery date is obtained from the supplier. Even if delivery is delayed, the latest response delivery date is not necessary if the purchased item has already arrived (if the arrival date has been confirmed). Here, the person in charge and the administrator share the work. However, for example, the administrator may perform all the work.

管理者は、上記遅れ理由収集メールに対する応答である遅れ理由回答メールに、所定のコード体系による遅れ理由コード,および製造計画遅れ発生データに対応付けた計画変更日程、必要があれば買券遅れ発生データに対応付けた最新回答納期を入力し、さらに、遅れ要因を把握するために有用となる「備考」を入力して、生産計画変更システム2に返信する。遅れ理由回答メールは、予め決められたフォーマットとする。たとえば、作業遅れの場合は、作業完了日のみが変更となる。作業着手日および作業完了日のうち一方のみが変更になる場合に、ここでは、変更されない方には元々の日程を計画変更日程に入力する。なお、変更されない方を空欄とする仕様でもよい。したがって、遅れ理由回答メールには、上記でセットされた遅れ理由コードと、製造計画遅れ発生データに対応付けた計画変更日程、必要があれば買券遅れ発生データに対応付けた最新回答納期が含まれる。   The administrator must add a delay reason code based on a predetermined code system and a schedule change schedule associated with the production plan delay occurrence data to the delay reason response mail, which is a response to the above delay reason collection mail. The latest answer delivery date associated with the data is input, and “remarks” useful for grasping the cause of the delay are input and returned to the production plan change system 2. The delay reason reply mail has a predetermined format. For example, in the case of work delay, only the work completion date is changed. When only one of the work start date and the work completion date is changed, the original schedule is input to the plan change schedule for those who are not changed. In addition, the specification which makes the direction which is not changed blank. Therefore, the delay reason response email includes the delay reason code set above, the schedule change schedule associated with the production plan delay occurrence data, and if necessary, the latest response delivery date associated with the ticket delay occurrence data. It is.

生産計画変更システム2における制御部20のメール機能部27は、遅れ理由回答メールを受信すると(ステップS4)、遅れ情報処理部23に出力する。遅れ情報処理部23は、遅れ理由回答メールを受け取ると、最新回答納期が含まれる場合は、対応付けられた買券データの項目[「購買コード」,「工事番号」,「細目コード」,「素品コード」,「部門コード」,「注文納期」,「回答納期」]をセットし、遅れ理由回答メールに含まれる遅れ理由コードを「遅れ理由コード」にセットし、遅れ理由回答メールに含まれる最新回答納期を「回答納期(最新計画)」にセットしたデータを、買券遅れDB36に登録する。   When the mail function unit 27 of the control unit 20 in the production plan change system 2 receives the delay reason reply mail (step S4), the mail function unit 27 outputs it to the delay information processing unit 23. When the delay information processing unit 23 receives the delay reason reply mail, if the latest reply delivery date is included, the items [“purchase code”, “construction number”, “detail code”, “ Set "Fundament code", "Department code", "Order delivery date", "Response delivery date"], set the delay reason code included in the delay reason response email to "Delay reason code", and include it in the delay reason response email Data in which the latest answer delivery date is set to “answer delivery date (latest plan)” is registered in the ticket delay DB 36.

また、遅れ情報処理部23は、当該遅れ理由回答メールに基づいて、工事ごとの遅れの度合いを示す遅れポイント、および工事ごとの遅れ日数を算出する(ステップS5)。なお、図3−1の例では、遅れポイント,遅れ日数,計画変更ポイントは、それぞれ、作業工程ごと((1)設計/(2)加工/(3)組立/(4)試験/(5)出荷)に分けて集計される。   The delay information processing unit 23 calculates a delay point indicating the degree of delay for each construction and the number of days for each construction based on the delay reason reply mail (step S5). In the example of FIG. 3-1, the delay point, the number of days of delay, and the plan change point are respectively for each work process ((1) design / (2) processing / (3) assembly / (4) test / (5). (Shipment) and aggregated.

遅れポイントについて説明する。具体的には、遅れ情報処理部23は、遅れ理由回答メールに含まれる製造計画遅れ発生データの「作業工程コード」と、回答された「遅れ理由コード」を取得し、これらをキーに、遅れ理由DB37の「遅れポイント」を読み出す。そして、当該製造計画遅れ発生データの「工事番号」をキーに、工事DB31から該当する工事データを読み出す。そして、当該工事データにおいて、上記作業工程コードに該当する工程の「遅れポイント」に、上記で読み出した遅れポイントを加算する。   The delay point will be described. Specifically, the delay information processing unit 23 acquires the “work process code” of the production plan delay occurrence data included in the delay reason reply mail and the answered “delay reason code”, and uses these as keys to delay. The “delay point” in the reason DB 37 is read. Then, the corresponding construction data is read from the construction DB 31 using the “construction number” of the production plan delay occurrence data as a key. Then, in the construction data, the delay point read out above is added to the “delay point” of the process corresponding to the work process code.

また、遅れ情報処理部23は、遅れ理由回答メールに含まれる「遅れ理由コード」および「備考」と、製造計画遅れ発生データの「作業工程コード」および「部門コード」をセットしたデータを、遅れ要因DB39に登録する。この際、「レコードID」および「日付」(システム日付)は、遅れ要因DB39にて自動で付与される。   In addition, the delay information processing unit 23 delays the data in which the “delay reason code” and “remarks” included in the delay reason reply mail and the “work process code” and “department code” of the production plan delay occurrence data are set. Register in the factor DB 39. At this time, “record ID” and “date” (system date) are automatically given by the delay factor DB 39.

遅れ日数について説明する。遅れ情報処理部23は、回答された製造計画遅れ発生データとキー項目が同一のデータを、製造計画DB32から読み出す。当該製造計画DB32の製造計画データでは、「作業完了日(最新計画)」に値がセットされていれば「作業完了日(最新計画)」が、セットされていなければ「作業完了日(初期計画)」が最新の作業完了日である。遅れ情報処理部23は、最新の作業完了日と、遅れ理由回答メールにて指定された計画変更日程のうちの作業完了日とを比較し、その差分である遅れ日数を得る。なお、作業完了日に変更がなければ、遅れ日数はゼロである。   The delay days will be described. The delay information processing unit 23 reads from the manufacturing plan DB 32 data that has the same key item as the answered manufacturing plan delay occurrence data. In the production plan data of the production plan DB 32, “work completion date (latest plan)” is set if a value is set in “work completion date (latest plan)”, and “work completion date (initial plan) is not set. ) ”Is the latest work completion date. The late information processing unit 23 compares the latest work completion date with the work completion date in the schedule change schedule designated by the delay reason reply mail, and obtains the number of late days as the difference. If there is no change in the work completion date, the number of days delayed is zero.

遅れ情報処理部23は、当該製造計画遅れ発生データの「工事番号」をキーに、工事DB31から該当する工事データを読み出す。そして、当該工事データにおいて、当該製造計画遅れ発生データの作業工程コードに該当する工程の「遅れ日数」に、上記で算出した遅れ日数を加算する。   The delay information processing unit 23 reads the corresponding construction data from the construction DB 31 using the “construction number” of the production plan delay occurrence data as a key. Then, in the construction data, the delay days calculated as described above are added to the “delay days” of the process corresponding to the work process code of the production plan delay occurrence data.

そして、遅れ情報処理部23は、当該製造計画遅れ発生データに対して、上記で算出した遅れ日数を対応付け、再計画部24に出力する。   Then, the delayed information processing unit 23 associates the calculated number of days of delay with the production plan delay occurrence data and outputs it to the replanning unit 24.

再計画部24は、製造計画遅れ発生データを受けとると、遅れ対応再計画処理を行う(ステップS6)。図7は、遅れ対応再計画処理を説明するためのフローチャートである。再計画部24は、当該製造計画遅れ発生データの「細目余裕日数」と、当該製造計画遅れ発生データに対応付けられた遅れ日数とを比較する(ステップS21)。   When receiving the production plan delay occurrence data, the replanning unit 24 performs a delay replanning process (step S6). FIG. 7 is a flowchart for explaining the delay re-planning process. The re-planning unit 24 compares the “detail margin days” of the production plan delay occurrence data with the delay days associated with the production plan delay occurrence data (step S21).

細目余裕日数が遅れ日数以上である場合には(ステップS21:Yes)、該当する細目内で遅れをカバーできるため、再計画部24は、同一細目内の素品の製造日程を変更する(ステップS22)。具体的には、まず、上記製造計画遅れ発生データの「工事番号」,「細目コード」,「素品コード」と値が同じ製造計画データであって、当該製造計画遅れ発生データの「作業工程コード」よりも、工程が後になる作業工程コードを保持する製造計画データを、製造計画DB32から読み出す。   When the detailed margin days are equal to or greater than the delay days (step S21: Yes), since the delay can be covered within the corresponding detail, the re-planning unit 24 changes the production schedule of the element within the same detail (step S22). Specifically, first, manufacturing plan data having the same values as the “construction number”, “detailed code”, and “element code” of the above-mentioned manufacturing plan delay occurrence data, The manufacturing plan data holding the work process code that follows the process is read from the manufacturing plan DB 32 rather than the “code”.

つづいて、日程を遅れ日数の分だけ後ろへずらす。再計画部24は、読み出した製造計画データにて、「作業完了日(初期計画)」のみが入力されている場合は、「作業完了日(初期計画)」に遅れ日数を足して、「作業完了日(最新計画)」とする。一方、既に「作業完了日(最新計画)」が入力されている場合は、その値に遅れ日数を足して、新たな「作業完了日(最新計画)」とする。また、変更計画日にて指定される作業着手日を「作業着手日(最新計画)」とする。変更計画日にて作業着手日に変更がない場合には、元の「作業着手日(初期計画)」または「作業着手日(最新計画)」のままとする。また、細目余裕日数から遅れ日数(ずらした日数)を減算した値を、新たな細目余裕日数とする。   Next, shift the schedule back by the number of days delayed. When only the “work completion date (initial plan)” is input in the read production plan data, the re-planning unit 24 adds the number of days delayed to the “work completion date (initial plan)” Completed date (current plan) ". On the other hand, if the “work completion date (latest plan)” has already been input, the new work completion date (latest plan) is obtained by adding the number of days late. Further, the work start date designated by the change plan date is defined as “work start date (current plan)”. When there is no change in the work start date on the change plan date, the original “work start date (initial plan)” or “work start date (current plan)” is left as it is. Also, a value obtained by subtracting the number of days delayed (number of days shifted) from the number of days of fine margin is set as a new number of days of fine margin.

そして、再計画部24は、製造計画DB32から読み出したデータ項目のうち「工事番号」,「細目コード」,「素品コード」,「作業工程コード」,「部門コード」,「作業着手日(初期計画)」,「作業完了日(初期計画)」をセットし、また、遅れ理由回答メールに含まれる遅れ理由,上記で得た「作業着手日(最新計画)」,「作業完了日(最新計画)」,「細目余裕日数」をセットした再計画データを作成し、当該再計画データを再計画DB40に登録する。   Then, the re-planning unit 24 selects “construction number”, “detail code”, “product code”, “work process code”, “department code”, “work start date (from the data items read from the production plan DB 32). "Initial plan)", "Work completion date (initial plan)", and the reason for delay included in the reply email for reason for delay, "Work start date (current plan)", "Work completion date (latest plan) obtained above" Plan) ”and“ detail margin days ”are created, and the replan data is registered in the replan DB 40.

一方、細目余裕日数が遅れ日数未満である場合には(ステップS21:No)、該当する細目内で遅れをカバーできないので、再計画部24は、製造計画遅れ発生データの親細目までを含めた「細目余裕日数」と、遅れ日数とを比較する(ステップS23)。具体的には、再計画部24は、製造計画DB32から、「工事番号」および「細目コード」が製造計画遅れ発生データの「工事番号」および「親細目コード」と合致する製造計画データ(親細目製造計画データ)を読み出す。再計画部24は、製造計画遅れ発生データの「細目余裕日数」と、この親細目製造計画データの「細目余裕日数」とを加算した値を、遅れ日数と比較する。   On the other hand, when the detailed margin days are less than the delay days (step S21: No), since the delay cannot be covered within the corresponding details, the re-planning unit 24 includes the parent details of the production plan delay occurrence data. The “detail margin days” are compared with the delay days (step S23). Specifically, the re-planning unit 24 reads from the production plan DB 32 the production plan data (parent code) whose “construction number” and “detail code” match the “construction number” and “parent detail code” of the production plan delay occurrence data. Read out detailed manufacturing plan data). The replanning unit 24 compares the value obtained by adding the “fine margin days” of the production plan delay occurrence data and the “fine margin days” of the parent detailed production plan data with the delay days.

その結果、上記加算した値、すなわち、親細目までを含めた細目余裕日数が、遅れ日数以上である場合には(ステップS23:Yes)、遅れが発生した細目(子細目)およびその親細目のなかで遅れをカバーできるため、再計画部24は、親細目内の素品、および遅れが発生した子細目内の素品の製造日程を変更する(ステップS24)。まず、子細目から日程をずらす。再計画部24は、子細目の製造計画遅れ発生データの「工事番号」,「細目コード」,「素品コード」と値が同じ製造計画データであって、当該製造計画遅れ発生データの「作業工程コード」よりも、工程が後になる作業工程コードを保持する製造計画データを、製造計画DB32から読み出す。そして、たとえば、上述したステップS21の処理と同様、「作業着手日(最新計画)」および「作業完了日(最新計画)」を設定し、また、ここでは、新たな細目余裕日数をゼロとする。   As a result, when the added value, that is, the extra days including the sub-items is equal to or greater than the number of days of delay (step S23: Yes), the sub-item (child sub-item) in which the delay has occurred and the sub-item of the sub-item In particular, since the delay can be covered, the re-planning unit 24 changes the production schedule of the element within the parent item and the element within the child item where the delay has occurred (step S24). First, shift the schedule from the child details. The re-planning unit 24 is the production plan data having the same values as the “construction number”, “detail code”, and “product code” of the production plan delay occurrence data of the sub-items, The manufacturing plan data holding the work process code that follows the process is read from the manufacturing plan DB 32 rather than the “process code”. Then, for example, the “work start date (latest plan)” and “work completion date (latest plan)” are set in the same manner as in the process of step S21 described above, and the new fine margin days are set to zero here. .

つぎに、再計画部24は、親細目の日程をずらす。再計画部24は、たとえば、遅れ日数から、子細目でまかなった遅れ日数(子細目の細目余裕日数)を減算して残存遅れ日数とする。そして、親細目製造計画データにて、残存遅れ日数分だけ、「作業着手日(最新計画)」および「作業完了日(最新計画)」をずらして設定し、また、親細目の「細目余裕日数」から当該残存遅れ日数を減算した値を、新たな細目余裕日数とする。   Next, the re-planning unit 24 shifts the schedule of the parent details. For example, the re-planning unit 24 subtracts the number of days delayed by the child details (number of days of child details) from the number of days delayed to obtain the remaining days of delay. Then, in the parent detailed manufacturing plan data, the "work start date (current plan)" and "work completion date (current plan)" are set differently by the number of days that are left behind. The value obtained by subtracting the number of days of remaining lag from "" is set as the new fine margin days.

製造計画遅れ発生データに該当する製造計画データ、および親細目製造計画データのいずれについても、「工事番号」,「細目コード」,「素品コード」,「作業工程コード」,「部門コード」,「作業着手日(初期計画)」,「作業完了日(初期計画)」をセットし、また、遅れ理由回答メールに含まれる遅れ理由,上記で得た「作業着手日(最新計画)」,「作業完了日(最新計画)」,「細目余裕日数」をセットした再計画データを作成し、当該再計画データを再計画DB40に登録する。   For each of the production plan data corresponding to the production plan delay occurrence data and the parent detailed production plan data, “construction number”, “detail code”, “element code”, “work process code”, “department code”, Set “work start date (initial plan)” and “work completion date (initial plan)”, and the reason for delay included in the reply email for reason for delay, “work start date (current plan)”, “ Re-plan data in which the “work completion date (current plan)” and “detail margin days” are set is created, and the re-plan data is registered in the re-plan DB 40.

なお、親細目までの範囲で製造計画データを変更する際には、たとえば、子細目に細目余裕日数を残し、その日数分、親細目の日程をさらに後ろへずらす仕様とするなど、自由に設計してよい。   In addition, when changing the production plan data within the range up to the sub-items, for example, it is possible to design freely, such as leaving specifications for the sub-items to be shifted further backwards by leaving the number of days in the sub-items. You can do it.

一方、親細目までを含めた細目余裕日数が、遅れ日数未満である場合には(ステップS23:No)、遅れが発生した細目(子細目)およびその親細目のなかで遅れをカバーできないので、再計画部24は、つぎに、製造計画遅れ発生データと親細目が同一である他の子細目(他細目)までを含めた「細目余裕日数」と、遅れ日数とを比較する(ステップS25)。具体的には、再計画部24は、製造計画DB32から、「工事番号」および「親細目コード」が親細目製造計画データの「工事番号」および「細目コード」と合致する製造計画データ(他細目製造計画データ)を読み出す。再計画部24は、製造計画遅れ発生データの「細目余裕日数」と、この他細目製造計画データの「細目余裕日数」とを加算した値を、遅れ日数と比較する。当該加算した値が遅れ日数より小さい場合には、さらに、親細目製造計画データの「細目余裕日数」を加算して、遅れ日数と比較する。   On the other hand, when the detailed margin days including the sub-details are less than the delay days (step S23: No), the delay cannot be covered in the details (child sub-items) where the delay occurred and the parent details. Next, the re-planning unit 24 compares the “days of fine items” including other child details (other details) having the same parent details as the production plan delay occurrence data with the days of delay (step S25). . Specifically, the re-planning unit 24 produces from the production plan DB 32 the production plan data (others) in which “construction number” and “parent detail code” match the “construction number” and “detail code” of the parent detail production plan data. Read out detailed manufacturing plan data). The re-planning unit 24 compares the value obtained by adding the “fine margin days” of the production plan delay occurrence data and the “fine margin days” of the other fine production plan data with the delay days. When the added value is smaller than the number of days late, the “detail margin days” of the parent detailed manufacturing plan data are further added and compared with the days late.

これにより、他細目までを含めた細目余裕日数が、遅れ日数以上である場合には(ステップS25:Yes)、遅れが発生した細目(子細目)および他細目、さらにはその親細目のなかで遅れをカバーできるため、再計画部24は、他細目および親細目内の素品と、遅れが発生した細目内の素品の、製造日程を変更する(ステップS26)。再計画部24は、たとえば、遅れが発生した子細目,他細目,親細目、の順に、細目余裕日数を遅れ日数に充当する。そして、上述同様に処理を行い、再計画データを作成して再計画DB40に登録する。   As a result, when the number of days of detail including other details is equal to or greater than the number of days of delay (step S25: Yes), the details (child details) and other details that have been delayed, and the parent details Since the delay can be covered, the re-planning unit 24 changes the production schedules of the other sub-item and the parent sub-item and the sub-item in which the delay has occurred (step S26). For example, the re-planning unit 24 allocates the extra margin days to the delayed days in the order of child details, other details, and parent details in which the delay has occurred. Then, processing is performed in the same manner as described above to create replan data and register it in the replan DB 40.

一方、他細目までを含めた細目余裕日数が、遅れ日数未満である場合には(ステップS25:No)、他細目までのなかで遅れをカバーできないので、再計画部24は、遅れ度数の低い他の工事案件について計画変更を実施することを決定し、この製造計画遅れ発生データに関する処理を終了する(ステップS27)。なお、当該製造計画遅れ発生データについては、別途マニュアルで処理を行う。   On the other hand, when the fine margin days including up to other details are less than the number of delay days (step S25: No), since the delay cannot be covered within the other details, the re-planning unit 24 has a low delay frequency. It is decided to change the plan for another construction project, and the process related to the production plan delay occurrence data is terminated (step S27). The production plan delay occurrence data is processed manually separately.

つぎに、再計画部24は、製造計画を最適とするための最適化処理を行う。まず、再計画部24は、製造計画DB32から製造計画データを全て読み出し、再計画DB40から再計画データを全て読み出す。再計画部24は、製造計画データに対し、キー項目が合致する再計画データを対応付ける。そして、製造計画データをベースにして、キー項目に対する「作業着手日(初期計画)」,「作業着手日(最新計画)」,「作業完了日(初期計画)」,「作業完了日(最新計画)」に基づいて、最新の日程である最新着手日および最新完了日を抽出する。その際、再計画データが対応づけられる場合には、同様に、再計画データによる最新の日程である最新着手日および最新完了日を抽出し、製造計画データの最新の着手日および完了日と置き換えて、最適化対象データとする。そして、当該最適化対象データを「部門コード」ごとに時系列で並べ、部門単位作業スケジュールを作成する。具体的には、最新着手日の早い順に、最新着手日および最新完了日をセットし、「細目余裕日数」を付加して1工程分の作業スケジュールとする。これを、それぞれの最適化対象データについて行う。ここでは、作業スケジュールを、工事番号単位に作成することとする。   Next, the re-planning unit 24 performs an optimization process for optimizing the manufacturing plan. First, the replanning unit 24 reads all the production plan data from the production plan DB 32 and reads all the replan data from the replan DB 40. The replanning unit 24 associates the replanning data with the matching key items with the production plan data. Then, based on the production plan data, “work start date (initial plan)”, “work start date (current plan)”, “work completion date (initial plan)”, “work completion date (current plan) for key items. ) ”, The latest start date and the latest completion date, which are the latest schedule, are extracted. At that time, if the replan data is associated, similarly, the latest start date and the latest completion date, which are the latest schedule based on the replan data, are extracted and replaced with the latest start date and completion date of the production plan data. Therefore, the data is to be optimized. Then, the optimization target data is arranged in time series for each “department code” to create a department unit work schedule. Specifically, the latest start date and the latest completion date are set in the order of the latest start date, and the “detail margin days” are added to form a work schedule for one process. This is performed for each optimization target data. Here, a work schedule is created for each construction number.

また、再計画部24は、工事DB31から、「工事番号」と、作業工程ごとの「遅れポイント」とを読み出し、工事番号ごとに遅れポイントを加算する。そして、遅れポイントが高い順に工事番号を並べ、優先順位をつける。   Further, the re-planning unit 24 reads the “construction number” and the “delay point” for each work process from the construction DB 31, and adds the delay point for each construction number. Then, the construction numbers are arranged in descending order of the delay points, and priorities are assigned.

そして、再計画部24は、部門コードごとに、工事番号単位の作業スケジュールにおいて、製造日程を変更する処理を行う。まず、再計画部24は、工事番号単位の部門単位作業スケジュールにて、空き日があるかどうかをチェックすることにより、他作業が実施可能であるかどうかを判断する(ステップS28)。たとえば、1日でも空いていたら、他作業が実施可能であると判断することとしてもよいし、所定の日数を設定してもよい。いずれの部門コードについても、他作業が実施可能でないと判断した場合(ステップS28:No)、最適化を行わずに、図7の遅れ対応再計画処理を終了する。一方、他作業が実施可能であると判断した場合(ステップS28:Yes)、以下の処理を行う。   Then, the re-planning unit 24 performs a process of changing the production schedule in the work schedule in units of construction numbers for each department code. First, the re-planning unit 24 determines whether or not other work can be performed by checking whether or not there is a free day in the department unit work schedule for each work number (step S28). For example, it may be determined that other work can be performed if one day is available, or a predetermined number of days may be set. If it is determined that no other work can be performed for any department code (step S28: No), the delay re-planning process in FIG. 7 is terminated without performing optimization. On the other hand, when it is determined that other work can be performed (step S28: Yes), the following processing is performed.

図8は、最適化処理の概要を説明するための図である。既に述べたように、工事は平行して行われるため、図8では、一例として、ある部門コードに対して、工事#A,工事#B,工事#C,工事#Dの作業スケジュールが存在する場合を示す。ここで、工事#Aについて、8/1〜8/30までの作業スケジュールが策定され、遅れにより、8/1〜8/5が空きとなったとする。空きとなった日程を空き日程という。たとえば、工事#Bは、8/1以降の作業スケジュールとして、図8に示すように、製造計画#B01,製造計画#B02,製造計画#B03を有し、遅れポイントが“10”であったとする。また、工事#Cは、8/1以降の作業スケジュールとして、製造計画#C01,製造計画#C02,製造計画#C03を有し、遅れポイントが“20”であったとする。また、工事#Dは、8/1以降の作業スケジュールとして、製造計画#D01,製造計画#D02,製造計画#D03を有し、遅れポイントが“15”であったとする。また、工事#Aの遅れポイントが“15”であったとする。   FIG. 8 is a diagram for explaining an outline of the optimization process. As already described, since the construction is performed in parallel, in FIG. 8, as an example, there is a work schedule of construction #A, construction #B, construction #C, construction #D for a certain department code. Show the case. Here, it is assumed that a work schedule from 8/1 to 8/30 is formulated for the construction #A, and 8/1 to 8/5 are vacant due to a delay. An empty schedule is called an empty schedule. For example, construction #B has a production plan # B01, a production plan # B02, and a production plan # B03 as shown in FIG. 8 as work schedules after 8/1, and the delay point is “10”. To do. Further, it is assumed that the construction #C has a production plan # C01, a production plan # C02, and a production plan # C03 as work schedules after 8/1, and the delay point is “20”. Also, it is assumed that the construction #D has a production plan # D01, a production plan # D02, and a production plan # D03 as work schedules after 8/1, and the delay point is “15”. Further, it is assumed that the delay point of construction #A is “15”.

再計画部24は、工事#Aについて8/1〜8/5(5日間)が空き日程であるので、他の工事の前倒しを実施する。ここで、工事#A〜工事#Dのなかで、遅れポイントが最も高い工事は工事#Cであるので、工事#Cの作業スケジュールを前倒すことで、製造日程を変更する(ステップS29)。空き日程の開始日である8/1以降に最も早く開始する作業は製造計画#C01であるため、再計画部24は、製造計画#C01の日程を前倒しする。ここで、図8では、製造計画#C01は、8/1〜8/5の日程(5日間)であるため、前倒した場合、空き日程内に収まる(図8の(1))。   Since the replanning unit 24 has 8/1 to 8/5 (5 days) of work #A as an empty schedule, it implements other work ahead of schedule. Here, among the works #A to #D, the work with the highest delay point is the work #C. Therefore, the production schedule is changed by moving the work schedule of the work #C forward (step S29). Since the work that starts earliest after 8/1, which is the start date of the vacant schedule, is the production plan # C01, the replanning unit 24 advances the schedule for the production plan # C01. Here, in FIG. 8, since the production plan # C01 is a schedule of 8/1 to 8/5 (5 days), if it is moved forward, it falls within the vacant schedule ((1) of FIG. 8).

製造計画#C01を前倒しにすると、製造計画#C02の前段に空き日程が発生する。したがって、再計画部24は、製造計画#C02を、製造計画#C01の後段に前倒す(図8の(2))。ここで、製造計画#C02の日程は、8/10〜8/20(11日間)であるため、製造計画#C01の日程(5日間)に収まらない。したがって、再計画部24は、代わりに、遅れポイントが最も低い工事を後ろ倒す。ここで、工事#A〜工事#Dのなかで、遅れポイントが最も低い工事は工事#Bであるので、再計画部24は、工事#Bの作業スケジュールを後ろ倒すことで、製造日程を変更する(ステップS30)。製造計画#B01の日程は、8/5に開始し、8/5〜8/12(8日間)であるため、製造計画#B01の日程が、前倒し後の製造計画#C02の日程と新たに重複する。したがって、再計画部24は、重複する日数分、製造計画#B01の日程を後ろ倒す(図8の(3))。なお、ここでは、遅れポイントが低い製造計画#B01の日程が、前倒し後の製造計画#C02の日程と重複する場合を示すが、一般には、日程が重複する製造計画のなかで、最も遅れポイントが低い工事に属する製造計画を後ろ倒す。   If the production plan # C01 is moved forward, an empty schedule is generated before the production plan # C02. Therefore, the replanning unit 24 moves the production plan # C02 forward to the subsequent stage of the production plan # C01 ((2) in FIG. 8). Here, since the schedule of manufacturing plan # C02 is 8/10 to 8/20 (11 days), it does not fall within the schedule of manufacturing plan # C01 (5 days). Therefore, the replanning unit 24 instead puts back the construction with the lowest delay point. Here, among the construction #A to the construction #D, the construction with the lowest delay point is the construction #B. Therefore, the re-planning unit 24 changes the production schedule by putting back the work schedule of the construction #B. (Step S30). Since the schedule of the production plan # B01 starts on 8/5 and is 8/5 to 8/12 (8 days), the schedule of the production plan # B01 is newly added to the schedule of the production plan # C02 after the advance. Duplicate. Therefore, the re-planning unit 24 pushes back the schedule of the production plan # B01 by the number of overlapping days ((3) in FIG. 8). In this example, the schedule of the production plan # B01 with a low delay point overlaps with the schedule of the production plan # C02 after the advance, but in general, the most delayed point among the production plans with overlapping schedules. The manufacturing plan belonging to the low construction is pushed back.

製造計画#B01を後ろ倒すと、製造計画#B04の日程と重複することとなる。したがって、再計画部24は、同工事に属する製造計画のなかで、重複した日数分、以後の製造計画を後ろ倒す。図8の例では、重複した日数分、製造計画#B02を後ろ倒し(図8の(4))、さらに、同日数分、製造計画#B03を後ろ倒す(図8の(5))。当該工事(工事#B)のなかで、空き日程が発生していた場合、後ろ倒しの過程で当該空き日程を消化する。   If manufacturing plan # B01 is pushed back, it will overlap with the schedule of manufacturing plan # B04. Therefore, the re-planning unit 24 puts back the subsequent production plans by the number of overlapping days in the production plans belonging to the construction. In the example of FIG. 8, the production plan # B02 is postponed by the number of overlapping days ((4) of FIG. 8), and the production plan # B03 is postponed by the same number of days ((5) of FIG. 8). If a vacant schedule has occurred in the construction (construction #B), the vacant schedule is digested in the process of carrying back.

再計画部24は、以上の処理を、全ての空き日程について繰り返し実行する。そして、作業が完了すると、製造計画データ(または再計画データ)のキー項目を用いて、最適化した着手日および完了日を、それぞれ、「着手可能日(最新計画)」または「完了可能日(最新計画)」としてセットし、再計画DB40を更新する。以上により図7の処理を終了する。上記の場合、ある工事の前倒しに対応させるために、他の工事を後ろ倒すので、工事単位の製造計画の整合性を維持することができる。   The re-planning unit 24 repeatedly executes the above processing for all vacant dates. Then, when the work is completed, the optimized start date and completion date are respectively set to “startable date (current plan)” or “completed date ( The latest plan) ”is set, and the replan DB 40 is updated. Thus, the process of FIG. 7 ends. In the above case, in order to cope with the advancement of a certain construction, the other construction is postponed, so that the consistency of the manufacturing plan for each construction can be maintained.

図6の処理に戻り、再計画部24は、再計画が完了した旨を再計画確認部25に通知する。再計画確認部25は、これを受けると、再計画DB40から全ての再計画データを読み出す。そして、再計画確認部25は、メール機能部27に対して、再計画データの承認を求める承認要求メールを、関係者に送信するよう指示する。メール機能部27は、たとえば、再計画データの承認を求めるメッセージと、再計画データとを含めたメールを、各部門の担当者や全体の管理者といった関係者に送信する(ステップS7)。再計画確認部25は、承認に必要である所定の関係者から、通信I/F部50およびメール機能部27を介して、承認要求メールに対する応答である承認応答メールを受信する。当該承認応答メールにより、承認する旨が回答された場合は、再計画確認部25は、再計画が承認されたことを再計画確定部26に通知する。   Returning to the processing of FIG. 6, the replanning unit 24 notifies the replanning confirmation unit 25 that the replanning is completed. Upon receiving this, the replan confirmation unit 25 reads all replan data from the replan DB 40. Then, the re-planning confirmation unit 25 instructs the mail function unit 27 to send an approval request mail for requesting approval of the re-planning data to related parties. The mail function unit 27 transmits, for example, a message requesting approval of the re-planning data and a mail including the re-planning data to related parties such as the person in charge of each department and the overall manager (step S7). The re-planning confirmation unit 25 receives an approval response mail that is a response to the approval request mail via the communication I / F unit 50 and the mail function unit 27 from a predetermined party required for approval. When the approval response email indicates that the approval is accepted, the replan confirmation unit 25 notifies the replan determination unit 26 that the replan has been approved.

これを受けた再計画確定部26は、再計画データが示す再計画が確定したと判断する(ステップS8)。また、再計画確定部26は、たとえば、再計画DB40の再計画データを全て読み出し、当該再計画データに基づいて、変更後の製造日程データとして、たとえば、工事ごとの工程表などを作成する。そして、再計画確定部26は、変更後の製造日程データを添えて、新たな製造日程データを配信するようメール機能部27に通知する。メール機能部27は、必要な関係者(たとえば、全ての管理者および作業者など)に対し、受け取った製造日程データをメール配信する(ステップS9)。また、再計画確定部26は、メール機能部27に対し、承認応答メールを送信してきた関係者などに、再計画が承認された旨を通知するメールを送信するよう制御する(ステップS10)。   Upon receiving this, the replan determination unit 26 determines that the replan indicated by the replan data has been determined (step S8). For example, the replan determination unit 26 reads all the replan data in the replan DB 40 and creates, for example, a process chart for each construction as the production schedule data after the change based on the replan data. Then, the re-planning determination unit 26 notifies the mail function unit 27 to distribute the new production schedule data with the production schedule data after the change. The mail function unit 27 distributes the received production schedule data to necessary parties (for example, all managers and workers) by mail (step S9). In addition, the replan determination unit 26 controls the mail function unit 27 to transmit a mail notifying that the replan has been approved to the parties who have transmitted the approval response mail (step S10).

また、再計画確定部26は、製造計画DB32の製造計画データと、再計画DB40の再計画データとを比較し、工事番号単位に、計画変更ポイントを算出する。ここで、図3−1の工事DB31では、計画変更ポイントは、計画変更した作業件数、すなわち素品の工程ごとの遅れ件数である。したがって、再計画確定部26は、製造計画遅れDB35に存在する製造計画遅れデータを、「工事番号」および「作業工程コード」をキーにカウントし、計画変更ポイントを集計する(ステップS11)。そして、「工事番号」に計画変更ポイントを対応させ、工事DB31にて、「工事番号」の「計画変更ポイント」に対し、集計した計画変更ポイントを加算する(ステップS11)。   Further, the replan determination unit 26 compares the production plan data in the production plan DB 32 with the replan data in the replan DB 40 and calculates a plan change point for each work number. Here, in the construction DB 31 in FIG. 3A, the plan change point is the number of work changed in plan, that is, the number of delays for each process of the original product. Therefore, the replan determination unit 26 counts the production plan delay data existing in the production plan delay DB 35 using the “construction number” and “work process code” as keys, and totals the plan change points (step S11). Then, the plan change points are made to correspond to the “construction number”, and the total plan change points are added to the “plan change point” of the “construction number” in the construction DB 31 (step S11).

また、再計画確定部26は、工事に対する各種評価処理を行う(ステップS12)。たとえば、再計画確定部26は、製造計画遅れDB35の製造計画遅れデータを参照し、「作業工程コード」および「部門コード」をキーに、データ件数をカウントする。そして、見直し頻度DB38の「作業工程コード」および「部門コード」に対する「見直し頻度」に、カウントした値を加算する。   In addition, the re-planning determination unit 26 performs various evaluation processes for the construction (step S12). For example, the replan determination unit 26 refers to the manufacturing plan delay data in the manufacturing plan delay DB 35 and counts the number of data using “work process code” and “department code” as keys. Then, the counted value is added to “review frequency” for “work process code” and “department code” in the review frequency DB 38.

また、再計画確定部26は、工事別遅れ状況を、たとえば、管理者端末(図示せず)や、生産計画変更システム2内に設けられた管理用画面(図示せず)などに出力し、表示させる。図9は、工事別遅れ状況を画面表示した場合の例を示す図である。図9では、工事に関する基礎データとして、「工事番号」,「(工事)件名」,「設計書数」,「細目数」,「素品数」といった情報が表示され、また、作業工程別に、「全体」,「遅れポイント」,「遅れ日数」,「計画変更ポイント」が表示される。「全体」とは、工事内に対して管理される各工程の数である。「遅れポイント」は、工事DB11の「遅れポイント」であって、各工程で遅れが発生した件数である。「遅れ日数」は、同様に、各工程で遅れが発生した日数である。「計画変更ポイント」は、同様に、各工程で計画変更した件数である。このような帳票を出力することで、管理者などは、工事別遅れ状況をリアルタイムに把握できる。   In addition, the replan determination unit 26 outputs the construction-specific delay status to, for example, an administrator terminal (not shown), a management screen (not shown) provided in the production plan change system 2, and the like. Display. FIG. 9 is a diagram illustrating an example when the delay status by construction is displayed on the screen. In FIG. 9, information such as “construction number”, “(construction) subject”, “number of design documents”, “number of sub-items”, and “number of elementary products” is displayed as basic data regarding the construction. "Overall", "Delayed point", "Delayed days", and "Plan change point" are displayed. “Overall” is the number of processes managed for the construction. The “delay point” is a “delay point” in the construction DB 11 and is the number of cases where a delay has occurred in each process. Similarly, “delayed days” is the number of days in which a delay has occurred in each process. Similarly, the “plan change point” is the number of cases where the plan has been changed in each process. By outputting such a form, an administrator or the like can grasp the delay status by construction in real time.

以上により、図6の生産計画変更処理が終了する。再計画確定部26は、工事DB31の「遅れポイント」,「遅れ日数」,「計画変更ポイント」を、生産管理基幹システム1の工事DB11に対し、通信I/F部50,生産管理基幹システム1の通信I/F部15およびDB処理部16を介してインタフェースし、反映させる。また、再計画確定部26は、再計画DB40の「着手可能日(最新計画)」および「完了可能日(最新計画)」を、「作業着手日(最新計画)」および「作業完了日(最新計画)」として、上述同様に、生産管理基幹システム1の製造計画DB12に対してインタフェースし、反映させる。   Thus, the production plan change process in FIG. 6 ends. The re-planning determination unit 26 transmits the “delay point”, “delay days”, and “plan change point” of the construction DB 31 to the construction DB 11 of the production management backbone system 1, the communication I / F unit 50, the production management backbone system 1. The communication I / F unit 15 and the DB processing unit 16 are interfaced and reflected. In addition, the replan determination unit 26 sets the “work start date (latest plan)” and “completion possible date (latest plan)”, “work start date (latest plan)” and “work completion date (latest plan) in the replan DB 40 In the same manner as described above, it is interfaced with the manufacturing plan DB 12 of the production management backbone system 1 and reflected.

なお、図6の生産計画変更処理は、たとえば、日次により起動されるとしたが、遅れ理由回答メールの受信以降の処理(図6:ステップS4以降)は、随時処理となる。したがって、次回の起動タイミングまでに図6の生産計画変更処理が完了しない場合には、たとえば、当該処理を終了する。生産計画変更処理が完了しない場合とは、遅れ情報処理部が、全ての遅れ理由回答メールを受信しないことや、再計画確認部25が、再計画への全ての承認を受信しないことにより、後続の処理が完了しない場合である。この場合、次回起動タイミングの生産管理基幹システム1のデータを用いて、改めて処理を行うこととなる。処理を終了するにあたり、遅れ理由DB37,見直し頻度DB38,遅れ要因DB39、以外のデータベースが保持するデータを削除する。   Note that the production plan change process in FIG. 6 is started on a daily basis, for example, but the process after the reception of the delay reason reply mail (FIG. 6: after step S4) is a process at any time. Therefore, if the production plan change process of FIG. 6 is not completed by the next start timing, for example, the process is terminated. The case where the production plan change process is not completed means that the delayed information processing unit does not receive all reply emails for reason for delay, and the replan confirmation unit 25 does not receive all approvals for the replan. This is a case where the process of is not completed. In this case, processing is performed again using the data of the production management backbone system 1 at the next activation timing. At the end of the process, data held in a database other than the delay reason DB 37, the review frequency DB 38, and the delay factor DB 39 are deleted.

以上説明したように、本実施の形態の生産計画変更システムでは、生産計画に遅れが発生しているかどうかを判定し、その旨を関係者に通知することで遅れ理由および変更後の日程を収集する構成とした。その際、工事単位で遅れ状況を管理することとした。また、回答される変更後の日程に基づいて、製造計画の遅れを細目単位で調整する構成とした。さらに、調整により空き日程が発生したことを検出した場合には、遅れ度合いを加味して、工事間で生産計画を変更し、生産計画を最適化する構成とした。   As explained above, the production plan change system according to the present embodiment collects the reason for the delay and the schedule after the change by determining whether or not there is a delay in the production plan and notifying relevant parties to that effect. It was set as the structure to do. At that time, it was decided to manage the delay situation by construction unit. In addition, the delay in the production plan is adjusted in detail units based on the updated schedule that is answered. Furthermore, when it is detected that an empty schedule has occurred due to the adjustment, the production plan is changed between constructions in consideration of the degree of delay, and the production plan is optimized.

これにより、生産計画に遅れが発生したことを自動的に判定でき、遅れが発生した場合に、自動で計画を変更可能となり、従来マニュアルによる計画変更を行う場合と比較して、担当者への負荷を低減可能となり、迅速かつ正確な計画変更が可能となる。また、遅れを自動判定して遅れ度合いを算出することで、工事評価に役立てることができ、より効率のよい管理が可能となる。   As a result, it is possible to automatically determine that a delay has occurred in the production plan, and in the event of a delay, the plan can be automatically changed. The load can be reduced, and the plan can be changed quickly and accurately. Further, by automatically determining the delay and calculating the degree of delay, it can be used for construction evaluation, and more efficient management becomes possible.

なお、上記実施の形態では、図3−2の製造計画DBの構成にて説明したとおり、製造の管理単位である細目にて複数の素品を管理し、製造計画を細目単位で管理する場合を説明したが、他の方法で製造計画を管理する場合でもよい。たとえば、製造計画を素品単位で管理し、製造計画データでは、作業の親子関係のみに基づき親素品を管理してもよい。また、ここでは、親細目が複数の子細目を管理する階層構造をとる場合を説明したが、他の階層構造であってもよい。すなわち、製造計画データで、生産部品をどのような階層で管理する場合にも、上記同様に処理を実施できる。   In the above embodiment, as described in the configuration of the manufacturing plan DB in FIG. 3-2, a plurality of products are managed in detail, which is a management unit of manufacturing, and a manufacturing plan is managed in detail units. However, the manufacturing plan may be managed by another method. For example, the manufacturing plan may be managed in units of elementary products, and in the production plan data, the parent products may be managed based only on the parent-child relationship of work. Also, here, a case has been described in which the parent item has a hierarchical structure in which a plurality of child items are managed, but another hierarchical structure may be employed. In other words, the process can be performed in the same manner as described above even when the production parts are managed in any hierarchy using the production plan data.

以上のように、本発明にかかる生産計画変更システムは、生産計画を行う場合に有用であり、特に、既存の生産計画基幹システムと連携するシステムに適している。   As described above, the production plan change system according to the present invention is useful when performing a production plan, and is particularly suitable for a system that cooperates with an existing production plan backbone system.

1 生産管理基幹システム
2 生産計画変更システム
3 端末
4 ネットワーク
11 工事DB
12 製造計画DB
13 買券DB
14 工事実績DB
15 通信I/F部
16 DB処理部
20 制御部
21 データ取得部
22 遅れ判定部
23 遅れ情報処理部
24 再計画部
25 再計画確認部
26 再計画確定部
27 メール機能部
30 記憶部
31 工事DB
32 製造計画DB
33 買券DB
34 工事実績DB
35 製造計画遅れDB
36 買券遅れDB
37 遅れ理由DB
38 見直し頻度DB
39 遅れ要因DB
40 再計画DB
50 通信I/F部
1 Production management backbone system 2 Production plan change system 3 Terminal 4 Network 11 Construction DB
12 Production plan DB
13 Purchase DB
14 construction results DB
DESCRIPTION OF SYMBOLS 15 Communication I / F part 16 DB processing part 20 Control part 21 Data acquisition part 22 Delay judgment part 23 Delay information processing part 24 Replanning part 25 Replanning confirmation part 26 Replanning confirmation part 27 Mail function part 30 Storage part 31 Construction DB
32 Manufacturing plan DB
33 voucher DB
34 construction results DB
35 Production plan delay DB
36 Ticket delay DB
37 Reason DB
38 Review frequency DB
39 Delay factor DB
40 Replan DB
50 Communication I / F part

Claims (14)

工事ごとの製造計画を管理する生産計画基幹システムと接続し、製造計画の変更を行う生産計画変更システム、における生産計画変更方法であって、
生産計画変更処理の対象として、前記生産計画基幹システムから製造計画に関するデータを取得するデータ取得ステップと、
前記データ取得ステップにて取得したデータに基づいて、製造の作業または作業に用いる購買品の納入に遅れが発生しているかどうかを判定する遅れ判定ステップと、
遅れが発生している作業または納入についての遅れ理由、および製造計画の変更日程を収集する遅れ情報収集ステップと、
前記遅れ情報収集ステップにて収集した変更日程に基づいて、製造計画ごとの遅れ日数を判断する遅れ日数決定ステップと、
管理単位である細目に対して設定される予備日である余裕日数により、前記遅れ日数をまかなえるかどうかを判断し、まかなえると判断した場合は、当該余裕日数を当該遅れ日数に充当することで製造計画の日程を変更した再計画データを作成する余裕日数調整ステップと、
を含むことを特徴とする生産計画変更方法。
A production plan change method in a production plan change system that connects to a production plan backbone system that manages a production plan for each construction and changes the production plan,
As a target of the production plan change process, a data acquisition step of acquiring data related to a manufacturing plan from the production plan basic system;
Based on the data acquired in the data acquisition step, a delay determination step of determining whether there is a delay in manufacturing work or delivery of purchases used in the work,
A delay information collection step that collects the reason for the delay in the work or delivery in which the delay is occurring, and the schedule for the change in the manufacturing plan
Based on the change schedule collected in the delay information collection step, a delay days determination step for determining the delay days for each production plan;
It is determined whether or not the delayed days can be covered by the spare days that are spare days set for the details that are the management unit, and if it is determined that they can be covered, the spare days are applied to the delayed days. An extra days adjustment step to create re-planning data with a modified schedule,
A production plan change method characterized by comprising:
さらに、
遅れが発生した件数である遅れポイントまたは遅れが発生した日数である遅れ日数のうち1つ以上を、工事単位の遅れ指標として算出する工事評価算出ステップと、
前記余裕日数調整ステップで作成された再計画データにおいて、遅れにより他作業が実施可能である空き日程があるかどうかを判断する第1の空き日程判断ステップと、
前記第1の空き日程判断ステップにて空き日程があると判断された場合は、前記空き日程に対し、当該空き日程以降に開始する製造計画であって、前記遅れ指標により遅れ度合いが高いことが示される工事に属する製造計画について、前倒しによる日程の変更を行う日程前倒しステップと、
前記日程前倒しステップの結果、後ろ倒しが必要となった場合に、前記遅れ指標により遅れ度合が低いことが示される工事に属する製造計画について、後ろ倒しによる日程の変更を行って新たな再計画データを作成する日程後ろ倒しステップと、
前記日程後ろ倒しステップにて作成される再計画データを対象に、他作業が実施可能である空き日程があるかどうかを判断する第2の空き日程判断ステップと、
を含み、
前記第2の空き日程判断ステップにて空き日程があると判断された場合は、前記日程前倒しステップ、前記日程後ろ倒しステップ、前記第2の空き日程判断ステップのそれぞれを繰り返す、
ことを特徴とする請求項1に記載の生産計画変更方法。
further,
A construction evaluation calculation step for calculating one or more of delay points that are the number of delays or days of delay that are the number of days in which delays have occurred, as a delay index for a construction unit;
In the re-planning data created in the margin days adjustment step, a first vacancy schedule determination step for determining whether there is a vacancy schedule that can be performed due to a delay,
If it is determined in the first vacancy schedule determination step that there is a vacancy schedule, the vacancy schedule is a manufacturing plan that starts after the vacancy schedule, and the degree of delay is high due to the delay index. For the production plan belonging to the indicated construction, schedule advance step to change schedule by advance,
As a result of the schedule advancement step, if it is necessary to postpone, new replanning data by changing the schedule due to postponement for the production plan belonging to the construction indicated by the delay indicator that the degree of delay is low To create a schedule step backwards,
A second free schedule determination step for determining whether there is a free schedule in which other work can be performed on the re-planning data created in the schedule postponement step;
Including
When it is determined that there is an empty schedule in the second empty schedule determination step, the schedule advance step, the schedule backward step, and the second empty schedule determination step are repeated.
The production plan changing method according to claim 1, wherein:
前記遅れ情報収集ステップにて収集した遅れ理由を保存する遅れ理由保存ステップ、
をさらに含むことを特徴とする請求項1または2に記載の生産計画変更方法。
A delay reason storing step for storing the delay reason collected in the delay information collecting step;
The production plan changing method according to claim 1, further comprising:
工事単位に、再計画処理によって計画変更した件数である計画変更ポイントを、遅れ指標の1つとして算出する変更ポイント算出ステップ、
をさらに含むことを特徴とする請求項1、2または3に記載の生産計画変更方法。
A change point calculation step for calculating, as one of the delay indicators, a plan change point, which is the number of cases where the plan has been changed by the re-planning process for each construction unit,
The production plan changing method according to claim 1, 2 or 3, further comprising:
再計画データに対する承認を得るためのメールを送信する制御を行う承認取得ステップと、
前記承認取得ステップにて再計画データが承認された場合に、工事ごとの製造計画の日程を示す日程データを作成し、当該日程データを配布する日程データ配布ステップと、
をさらに含むことを特徴とする請求項1〜4のいずれか1つに記載の生産計画変更方法。
An approval acquisition step for controlling to send an email for obtaining approval for the re-planning data;
When re-planning data is approved in the approval acquisition step, schedule data showing the schedule of the manufacturing plan for each construction, and schedule data distribution step for distributing the schedule data;
The production plan changing method according to any one of claims 1 to 4, further comprising:
工事ごとの遅れ状況を、1以上の遅れ指標を含めて出力する遅れ状況出力ステップ、
をさらに含むことを特徴とする請求項1〜5のいずれか1つに記載の生産計画変更方法。
Delay status output step for outputting the delay status for each construction including one or more delay indicators,
The production plan changing method according to claim 1, further comprising:
作成された再計画データに基づく変更後の製造計画の日程を、前記生産計画基幹システムに反映させるインタフェースステップ、
をさらに含むことを特徴とする請求項1〜6のいずれか1つに記載の生産計画変更方法。
An interface step for reflecting the schedule of the production plan after the change based on the created re-planning data in the production planning core system;
The production plan changing method according to any one of claims 1 to 6, further comprising:
工事ごとの製造計画を管理する生産計画基幹システムと接続し、製造計画の変更を行う生産計画変更システムであって、
工事データを保持するための工事記憶手段と、
製造計画データを保持するための製造計画記憶手段と、
工事に用いる購入品の納品日程である買券データを保持するための買券記憶手段と、
工事実績データを保持するための工事実績記憶手段と、
生産計画変更処理の対象として、前記生産計画基幹システムから製造計画に関するデータを取得し、前記工事記憶手段、前記製造計画記憶手段、前記買券記憶手段、前記工事実績記憶手段に保存するデータ取得手段と、
前記製造計画データ、前記買券データおよび前記工事実績データに基づいて、製造の作業または作業に用いる購買品の納入に遅れが発生しているかどうかを判定する遅れ判定手段と、
遅れが発生している作業または納入についての遅れ理由、および製造計画の変更日程を収集するための制御を行い、また、収集した変更日程に基づいて、前記製造計画データごとの遅れ日数を判断する遅れ情報処理手段と、
管理単位である細目に対して設定される予備日である余裕日数により、前記遅れ日数をまかなえるかどうかを判断し、まかなえると判断した場合は、当該余裕日数を当該遅れ日数に充当することで製造計画の日程を変更した再計画データを作成する再計画手段と、
前記再計画データを保持するための再計画記憶手段と、
を備えることを特徴とする生産計画変更システム。
A production plan change system that connects to a production plan core system that manages a production plan for each construction and changes the production plan.
Construction storage means for holding construction data;
Manufacturing plan storage means for holding manufacturing plan data;
Voucher storage means for holding voucher data which is the delivery schedule of purchased items used in the construction;
Construction results storage means for holding construction results data;
Data acquisition means for acquiring production plan data from the production plan backbone system as a target for production plan change processing and storing it in the construction storage means, the manufacturing plan storage means, the voucher storage means, and the construction result storage means When,
Based on the production plan data, the voucher data, and the construction performance data, a delay determination means for determining whether there is a delay in manufacturing work or delivery of purchases used in the work,
Performs control to collect the reason for the delay in the work or delivery in which the delay has occurred and the schedule for changing the production plan, and determines the number of days to be delayed for each of the production plan data based on the collected change schedule. Delayed information processing means;
It is determined whether or not the delayed days can be covered by the spare days that are spare days set for the details that are the management unit, and if it is determined that they can be covered, the spare days are applied to the delayed days. A re-planning means for creating re-planning data with a modified plan schedule;
Re-plan storage means for holding the re-plan data;
A production plan change system characterized by comprising:
さらに、
前記遅れ情報処理手段は、遅れが発生した件数である遅れポイントまたは遅れが発生した日数である遅れ日数のうち1つ以上を、工事単位の遅れ指標として算出して、前記工事記憶手段に反映させ、
前記再計画手段は、
自身が作成する再計画データにおいて、遅れにより他作業が実施可能である空き日程があるかどうかを判断し、空き日程があると判断した場合に、前記空き日程に対し、当該空き日程以降に開始する製造計画であって、前記遅れ指標により遅れ度合いが高いことが示される工事に属する製造計画データについて、前倒しによる日程の変更を行い、
前倒しの結果、後ろ倒しが必要となった場合に、前記遅れ指標により遅れ度合が低いことが示される工事に属する製造計画データについて、後ろ倒しによる日程の変更を行って新たな再計画データを作成する、
ことを特徴とする請求項8に記載の生産計画変更システム。
further,
The delay information processing means calculates one or more of a delay point, which is the number of cases where a delay has occurred, or a delay day, which is the number of days that a delay has occurred, as a delay indicator for a construction unit, and reflects it in the construction storage means. ,
The re-planning means includes
In the re-planning data that you create, determine if there is a vacant schedule that can be performed due to delay, and if it is determined that there is a vacant schedule, start after the vacant schedule for the vacant schedule For the manufacturing plan data belonging to the construction that is shown to be a high degree of delay by the delay index, the schedule is changed in advance,
As a result of the advance, if it is necessary to postpone, the production plan data belonging to the construction indicated by the delay index to indicate a low degree of delay will be updated to create new replanned data. To
The production plan change system according to claim 8, wherein:
さらに、
遅れ理由を蓄積するための遅れ要因記憶手段、
を備え、
前記遅れ情報収集手段は、収集した遅れ理由を前記遅れ要因記憶手段に保存する、
ことを特徴とする請求項8または9に記載の生産計画変更システム。
further,
Delay factor storage means for accumulating delay reasons,
With
The delay information collecting means stores the collected delay reasons in the delay factor storage means.
10. The production plan change system according to claim 8 or 9, wherein
さらに、
工事単位に、再計画処理によって計画変更した件数である計画変更ポイントを、遅れ指標の1つとして算出し、前記工事記憶手段に反映させる前記再計画確定手段、
を備えることを特徴とする請求項8、9または10に記載の生産計画変更システム。
further,
The re-plan decision means for calculating a plan change point, which is the number of cases changed by the re-planning process, as one of the delay indexes for the construction unit, and reflecting it in the construction storage means,
The production plan change system according to claim 8, wherein the production plan change system is provided.
再計画データに対する承認を得るための制御を行う再計画確認手段、
をさらに備え、
前記再計画確認手段が再計画データを承認した場合に、前記再計画記憶手段の再計画データが確定したと判断し、工事ごとの製造計画の日程を示す日程データを作成し、当該日程データを配布する制御を行う再計画確定手段、
をさらに備えることを特徴とする請求項8〜11のいずれか1つに記載の生産計画変更システム。
Replan confirmation means to control to obtain approval for replan data,
Further comprising
When the replan confirmation means approves the replan data, it is determined that the replan data in the replan storage means is confirmed, and schedule data indicating the schedule of the manufacturing plan for each construction is created, and the schedule data is Re-planning confirmation means for controlling distribution,
The production plan change system according to any one of claims 8 to 11, further comprising:
前記再計画確定手段は、さらに、前記工事記憶手段から工事ごとの遅れ指標を読み出し、1以上の遅れ指標を含めた帳票を出力する、
ことを特徴とする請求項8〜12のいずれか1つに記載の生産計画変更システム。
The re-planning confirmation means further reads out a delay index for each construction from the construction storage means and outputs a form including one or more delay indices.
The production plan change system according to any one of claims 8 to 12, wherein
前記再計画確定手段は、さらに、前記再計画記憶手段から再計画データを読み出し、当該再計画データを前記生産計画基幹システムに反映させるための制御を行う、
ことを特徴とする請求項8〜13のいずれか1つに記載の生産計画変更システム。
The replan determination unit further reads out the replan data from the replan storage unit, and performs control for reflecting the replan data in the production plan backbone system.
The production plan change system according to any one of claims 8 to 13, wherein the system changes.
JP2009202911A 2009-09-02 2009-09-02 Method and system for changing production plan Pending JP2011053962A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP2009202911A JP2011053962A (en) 2009-09-02 2009-09-02 Method and system for changing production plan

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP2009202911A JP2011053962A (en) 2009-09-02 2009-09-02 Method and system for changing production plan

Publications (1)

Publication Number Publication Date
JP2011053962A true JP2011053962A (en) 2011-03-17

Family

ID=43942889

Family Applications (1)

Application Number Title Priority Date Filing Date
JP2009202911A Pending JP2011053962A (en) 2009-09-02 2009-09-02 Method and system for changing production plan

Country Status (1)

Country Link
JP (1) JP2011053962A (en)

Cited By (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN111340383A (en) * 2020-03-09 2020-06-26 中国船舶工业综合技术经济研究院 Method and system for dynamically adjusting schedule plan of assembled component under random disturbance
CN111950864A (en) * 2020-07-22 2020-11-17 上海凯宝健康科技有限公司 Work order management system
JP2020197783A (en) * 2019-05-31 2020-12-10 有限会社リビングオオハシ Formation method of process chart
KR20210027901A (en) * 2019-09-03 2021-03-11 현대건설주식회사 Management system and method for constructing precast concrete
JP2021149185A (en) * 2020-03-16 2021-09-27 株式会社東芝 Periodic inspection information cooperation system and periodic inspection information cooperation method

Cited By (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2020197783A (en) * 2019-05-31 2020-12-10 有限会社リビングオオハシ Formation method of process chart
KR20210027901A (en) * 2019-09-03 2021-03-11 현대건설주식회사 Management system and method for constructing precast concrete
KR102353408B1 (en) * 2019-09-03 2022-01-19 현대건설(주) Management system and method for constructing precast concrete
CN111340383A (en) * 2020-03-09 2020-06-26 中国船舶工业综合技术经济研究院 Method and system for dynamically adjusting schedule plan of assembled component under random disturbance
CN111340383B (en) * 2020-03-09 2023-09-15 中国船舶工业综合技术经济研究院 Method and system for dynamically adjusting schedule plan of assembly component under random disturbance
JP2021149185A (en) * 2020-03-16 2021-09-27 株式会社東芝 Periodic inspection information cooperation system and periodic inspection information cooperation method
JP7346337B2 (en) 2020-03-16 2023-09-19 株式会社東芝 Periodic inspection information linkage system and periodic inspection information linkage method
CN111950864A (en) * 2020-07-22 2020-11-17 上海凯宝健康科技有限公司 Work order management system

Similar Documents

Publication Publication Date Title
US6947903B1 (en) Method and system for monitoring a supply-chain
US6889197B2 (en) Supply chain architecture
US7225040B2 (en) Method and system for reducing lead-time in the packaging industry
US20060212323A1 (en) Production management system
JP2000148785A (en) Commercial transaction management system
JP2011053962A (en) Method and system for changing production plan
JP2004021364A (en) Management intention decision support system
KR20030024538A (en) Production managing system
Luh et al. A Lagrangian relaxation based approach to schedule asset overhaul and repair services
JP5276607B2 (en) FORECAST MANAGEMENT SYSTEM, ITS CONTROL METHOD, AND ITS PROGRAM
JP2007041799A (en) Project management support system
JP2001344485A (en) System and method for electronic transaction and recording medium with recorded processing program thereof
WO2004023229A1 (en) Back order management system
WO2001052158A2 (en) Tupply chain architecture
JP5056962B2 (en) Sales production delivery system and sales production delivery method for steel strip products
US20150120355A1 (en) Mobile terminal management server and mobile terminal management program
JP2007004386A (en) Business management program and management device using the same
JP5199795B2 (en) Forecast management system and program
JP2019175232A (en) Production planning device, production planning method, and program
US20150073856A1 (en) Mobile terminal management server and mobile terminal management program
JP4279342B1 (en) Awareness program and system
JP2003345969A (en) Supporting system and method for business operation
JP5204683B2 (en) Forecast management device and program thereof
JP2005301396A (en) Integrated sales management cooperation system and method
JP2001325494A (en) System and method for procuring materials