JP2019028819A - Production management assist system and method - Google Patents
Production management assist system and method Download PDFInfo
- Publication number
- JP2019028819A JP2019028819A JP2017148925A JP2017148925A JP2019028819A JP 2019028819 A JP2019028819 A JP 2019028819A JP 2017148925 A JP2017148925 A JP 2017148925A JP 2017148925 A JP2017148925 A JP 2017148925A JP 2019028819 A JP2019028819 A JP 2019028819A
- Authority
- JP
- Japan
- Prior art keywords
- production
- intermediate product
- date
- arrival
- production plan
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
- 238000000034 method Methods 0.000 title claims abstract description 342
- 238000004519 manufacturing process Methods 0.000 title claims abstract description 167
- 238000012545 processing Methods 0.000 claims abstract description 48
- 238000003860 storage Methods 0.000 claims abstract description 47
- 230000001186 cumulative effect Effects 0.000 claims abstract description 13
- 238000007726 management method Methods 0.000 claims description 118
- 239000013067 intermediate product Substances 0.000 claims description 77
- 238000004364 calculation method Methods 0.000 claims description 29
- 239000000047 product Substances 0.000 claims description 26
- 238000012937 correction Methods 0.000 claims description 20
- 238000000605 extraction Methods 0.000 claims description 14
- 239000000284 extract Substances 0.000 claims description 8
- 230000007704 transition Effects 0.000 description 31
- 238000010586 diagram Methods 0.000 description 19
- 238000012384 transportation and delivery Methods 0.000 description 10
- XEEYBQQBJWHFJM-UHFFFAOYSA-N Iron Chemical compound [Fe] XEEYBQQBJWHFJM-UHFFFAOYSA-N 0.000 description 4
- 238000010276 construction Methods 0.000 description 4
- 230000007423 decrease Effects 0.000 description 4
- 230000003111 delayed effect Effects 0.000 description 4
- 230000000694 effects Effects 0.000 description 4
- 238000012790 confirmation Methods 0.000 description 3
- 230000006870 function Effects 0.000 description 3
- 238000007689 inspection Methods 0.000 description 3
- 229910000831 Steel Inorganic materials 0.000 description 2
- 230000003247 decreasing effect Effects 0.000 description 2
- 238000009826 distribution Methods 0.000 description 2
- 238000005516 engineering process Methods 0.000 description 2
- 238000007730 finishing process Methods 0.000 description 2
- 229910052742 iron Inorganic materials 0.000 description 2
- 239000004973 liquid crystal related substance Substances 0.000 description 2
- 239000000463 material Substances 0.000 description 2
- 239000004065 semiconductor Substances 0.000 description 2
- 239000010959 steel Substances 0.000 description 2
- 238000009825 accumulation Methods 0.000 description 1
- 239000012141 concentrate Substances 0.000 description 1
- 238000005520 cutting process Methods 0.000 description 1
- 230000006866 deterioration Effects 0.000 description 1
- 238000011161 development Methods 0.000 description 1
- 238000005401 electroluminescence Methods 0.000 description 1
- 230000003203 everyday effect Effects 0.000 description 1
- 238000010438 heat treatment Methods 0.000 description 1
- 238000003780 insertion Methods 0.000 description 1
- 230000037431 insertion Effects 0.000 description 1
- 238000012946 outsourcing Methods 0.000 description 1
- 238000010422 painting Methods 0.000 description 1
- 238000013439 planning Methods 0.000 description 1
- 238000012958 reprocessing Methods 0.000 description 1
- 238000005096 rolling process Methods 0.000 description 1
- 239000002436 steel type Substances 0.000 description 1
- 238000009827 uniform distribution Methods 0.000 description 1
Images
Classifications
-
- Y—GENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
- Y02—TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
- Y02P—CLIMATE CHANGE MITIGATION TECHNOLOGIES IN THE PRODUCTION OR PROCESSING OF GOODS
- Y02P90/00—Enabling technologies with a potential contribution to greenhouse gas [GHG] emissions mitigation
- Y02P90/02—Total factory control, e.g. smart factories, flexible manufacturing systems [FMS] or integrated manufacturing systems [IMS]
-
- Y—GENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
- Y02—TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
- Y02P—CLIMATE CHANGE MITIGATION TECHNOLOGIES IN THE PRODUCTION OR PROCESSING OF GOODS
- Y02P90/00—Enabling technologies with a potential contribution to greenhouse gas [GHG] emissions mitigation
- Y02P90/30—Computing systems specially adapted for manufacturing
Landscapes
- General Factory Administration (AREA)
- Management, Administration, Business Operations System, And Electronic Commerce (AREA)
Abstract
Description
本発明は、製品を生産する工場における生産管理を支援する生産管理支援装置および方法に関する。 The present invention relates to a production management support apparatus and method for supporting production management in a factory that produces products.
製品を製造する工場では、製品の製造に必要な時間である製造工期を精度良く予測することが求められている(非特許文献1参照)。非特許文献1では、過去の実績データを活用して、製造における様々なばらつきの可能性を推定し、その推定結果を製造工期の予測に活用することで、ばらつきに伴う納期遅れの発生リスクを最小にしている。
In factories that manufacture products, it is required to accurately predict the manufacturing period, which is the time required to manufacture the products (see Non-Patent Document 1). In
上記非特許文献1に記載の技術は、ばらつきの影響による納期遅れを減らしつつ、遅れリスクを重視するあまり、過剰な余裕を持った計画を立案することを防止するような、生産計画を立案する段階において製造工期を予測するものである。したがって、上記非特許文献1に記載の技術では、製品の生産が開始された後の段階で、生産過程で生じたばらつき等の変動に対して、生産計画を修正する必要性の有無を判断する等の生産管理を支援することについては十分に検討されていない。
The technology described in Non-Patent
本発明は、上記問題を解決するもので、製品の生産開始後における生産管理を支援する生産管理支援装置および方法を提供することを目的とする。 The present invention solves the above-described problems, and an object of the present invention is to provide a production management support apparatus and method for supporting production management after starting production of a product.
本発明の第1態様は、
予め定められた生産計画に従って、複数の中間製品がそれぞれ計画順に通過する複数の工程において前記複数の中間製品をそれぞれ処理して、前記複数の中間製品から対応する複数の受注製品を生産する工場における生産管理を支援する生産管理支援装置であって、
前記生産計画と、前記複数の工程から予め選択された管理対象工程とを記憶する生産計画記憶部と、
前記複数の中間製品の前記複数の工程に対する仕掛状況を含む前記複数の受注製品の生産の進捗情報を記憶する進捗情報記憶部と、
前記管理対象工程を基準日以降に通過する前記中間製品を含む中間製品群を前記生産計画記憶部から抽出する中間製品群抽出部と、
前記中間製品群に含まれる前記中間製品が前記管理対象工程より前に通過する先行工程を含む先行工程群を前記生産計画記憶部から抽出する先行工程群抽出部と、
前記中間製品群に含まれる前記中間製品の、前記先行工程群に含まれる前記先行工程に対する仕掛状況を、前記基準日以前の分は前記進捗情報記憶部から抽出し、前記基準日以降の分は前記生産計画記憶部から抽出する仕掛状況抽出部と、
前記仕掛状況に基づき、前記中間製品群に含まれる前記中間製品が前記管理対象工程に到着する到着日と、前記到着日に前記管理対象工程に到着する前記中間製品の量である到着量と、を算出する到着情報計算部と、
前記基準日の直近における前記管理対象工程の処理量の実績値を前記進捗情報記憶部から取得し、前記到着量から前記実績値を減算した差の所定期間における移動平均値を累積した累積値をバランス指標として算出するバランス指標計算部と、
前記バランス指標に基づき、前記基準日以降の前記生産計画を修正することが必要であるか否かを判断する計画修正判断部と、
を備えるものである。
The first aspect of the present invention is:
In a factory for processing a plurality of intermediate products in a plurality of processes in which a plurality of intermediate products pass in the order of the plan according to a predetermined production plan, and producing a plurality of order-receiving products corresponding to the plurality of intermediate products. A production management support device for supporting production management,
A production plan storage unit for storing the production plan, and a management target process preselected from the plurality of processes;
A progress information storage unit for storing progress information of production of the plurality of ordered products including in-process status for the plurality of steps of the plurality of intermediate products;
An intermediate product group extraction unit that extracts an intermediate product group including the intermediate product that passes through the management target process after a reference date from the production plan storage unit;
A preceding process group extracting unit that extracts a preceding process group including a preceding process through which the intermediate product included in the intermediate product group passes before the process to be managed from the production plan storage unit;
The in-process status of the intermediate product included in the intermediate product group with respect to the preceding process included in the preceding process group is extracted from the progress information storage unit before the reference date, and the part after the reference date is extracted. An in-process status extracting unit that extracts from the production plan storage unit;
Based on the in-process status, an arrival date when the intermediate product included in the intermediate product group arrives at the management target process, and an arrival amount that is an amount of the intermediate product that arrives at the management target process on the arrival date; An arrival information calculation unit for calculating
A cumulative value obtained by accumulating a moving average value in a predetermined period of the difference obtained by subtracting the actual value from the arrival amount, obtaining the actual value of the processing amount of the management target process most recently on the reference date. A balance index calculation unit for calculating as a balance index;
A plan correction determination unit for determining whether it is necessary to correct the production plan after the reference date based on the balance index;
Is provided.
本発明の第2態様は、
予め定められた生産計画に従って、複数の中間製品がそれぞれ計画順に通過する複数の工程において前記複数の中間製品をそれぞれ処理して、前記複数の中間製品から対応する複数の受注製品を生産する工場における生産管理を支援する生産管理支援方法であって、
複数の工程から予め選択された管理対象工程を基準日以降に通過する前記中間製品を含む中間製品群を、前記生産計画を記憶する生産計画記憶部から抽出する中間製品群抽出ステップと、
前記中間製品群に含まれる前記中間製品が前記管理対象工程より前に通過する先行工程を含む先行工程群を前記生産計画記憶部から抽出する先行工程群抽出ステップと、
前記中間製品群に含まれる前記中間製品の、前記先行工程群に含まれる前記先行工程に対する仕掛状況を、前記基準日以前の分は進捗情報を記憶する進捗情報記憶部から抽出し、前記基準日以降の分は前記生産計画記憶部から抽出する仕掛状況抽出ステップと、
前記仕掛状況に基づき、前記中間製品群に含まれる前記中間製品が前記管理対象工程に到着する到着日と、前記到着日に前記管理対象工程に到着する前記中間製品の量である到着量と、を算出する到着情報計算ステップと、
前記基準日の直近における前記管理対象工程の処理量の実績値を前記進捗情報記憶部から取得し、前記到着量から前記実績値を減算した差の所定期間における移動平均値を累積した累積値をバランス指標として算出するバランス指標計算ステップと、
前記バランス指標に基づき、前記基準日以降の前記生産計画を修正することが必要であるか否かを判断する計画修正判断ステップと、
を備えるものである。
The second aspect of the present invention is:
In a factory for processing a plurality of intermediate products in a plurality of processes in which a plurality of intermediate products pass in the order of the plan according to a predetermined production plan, and producing a plurality of order-receiving products corresponding to the plurality of intermediate products. A production management support method for supporting production management,
An intermediate product group extracting step for extracting an intermediate product group including the intermediate product that passes through a management target process selected in advance from a plurality of processes from a reference date, from a production plan storage unit that stores the production plan;
A preceding process group extracting step for extracting from the production plan storage unit a preceding process group including a preceding process through which the intermediate product included in the intermediate product group passes before the process to be managed;
The in-process status of the intermediate product included in the intermediate product group with respect to the preceding process included in the preceding process group is extracted from a progress information storage unit that stores progress information before the reference date, and the reference date Subsequent minutes are extracted from the production plan storage unit in-process status extraction step;
Based on the in-process status, an arrival date when the intermediate product included in the intermediate product group arrives at the management target process, and an arrival amount that is an amount of the intermediate product that arrives at the management target process on the arrival date; An arrival information calculation step for calculating
A cumulative value obtained by accumulating a moving average value in a predetermined period of the difference obtained by subtracting the actual value from the arrival amount, obtaining the actual value of the processing amount of the management target process most recently on the reference date. A balance index calculation step to calculate as a balance index;
A plan correction determination step for determining whether it is necessary to correct the production plan after the reference date based on the balance index;
Is provided.
第1態様又は第2態様では、基準日の直近における管理対象工程の処理量の実績値が取得され、到着日に管理対象工程に到着する中間製品の到着量から実績値を減算した差の所定期間における移動平均値を累積した累積値がバランス指標として算出される。バランス指標に基づき、基準日以降の生産計画を修正することが必要であるか否かが判断される。したがって、第1態様又は第2態様によれば、受注製品の生産開始後に、生産計画を修正することが必要であるか否かを判断することが可能になる。 In the first aspect or the second aspect, the actual value of the processing amount of the management target process most recently acquired is obtained, and a predetermined difference of the actual value is subtracted from the arrival amount of the intermediate product that arrives at the management target process on the arrival date. A cumulative value obtained by accumulating the moving average values in the period is calculated as a balance index. Based on the balance index, it is determined whether it is necessary to correct the production plan after the reference date. Therefore, according to the first aspect or the second aspect, it is possible to determine whether or not the production plan needs to be corrected after the production of the ordered product is started.
上記第1態様において、例えば、前記計画修正判断部は、前記バランス指標が予め定められた負の値である閾値未満のときに、前記生産計画を修正することが必要であると判断してもよい。 In the first aspect, for example, the plan correction determining unit may determine that the production plan needs to be corrected when the balance index is less than a predetermined negative value threshold. Good.
この態様では、バランス指標が予め定められた負の値である閾値未満のときに、生産計画を修正することが必要であると判断される。したがって、この態様によれば、バランス指標と閾値を比較するだけで、容易に、生産計画を修正することが必要であるか否かを判断することが可能になる。 In this aspect, it is determined that the production plan needs to be corrected when the balance index is less than a predetermined negative value threshold. Therefore, according to this aspect, it is possible to easily determine whether or not the production plan needs to be corrected only by comparing the balance index with the threshold value.
上記第1態様において、例えば、前記生産計画を修正することが必要であると前記計画修正判断部により判断されると警報を発令する警報発令部、をさらに備えてもよい。 In the first aspect, for example, an alarm issuing unit may be further provided that issues an alarm when the plan correction determining unit determines that the production plan needs to be corrected.
この態様では、生産計画を修正することが必要であると判断されると、警報が発令される。したがって、この態様によれば、生産計画を修正することが必要であることをユーザに報知することができる。 In this aspect, when it is determined that the production plan needs to be corrected, an alarm is issued. Therefore, according to this aspect, it is possible to notify the user that it is necessary to correct the production plan.
本発明によれば、バランス指標に基づき、基準日以降の生産計画を修正することが必要であるか否かが判断されるため、受注製品の生産開始後に、生産計画を修正することが必要であるか否かを判断することが可能になる。 According to the present invention, since it is determined whether or not it is necessary to correct the production plan after the reference date based on the balance index, it is necessary to correct the production plan after starting production of the ordered product. It is possible to determine whether or not there is.
(本発明の基礎となった知見)
まず、本発明の基礎となった知見が説明される。製品の製造を開始する前の生産計画を立案する段階では、通常、各工程における負荷の平準化、材料又は中間製品を運搬する物流の整流化等が図られている。しかし、製品の生産が実際に開始されると、様々な要因で製品生産の進捗が遅れて、生産計画に対するずれが発生する。
(Knowledge that became the basis of the present invention)
First, the knowledge that forms the basis of the present invention will be described. In the stage of creating a production plan before starting the manufacture of products, the leveling of loads in each process and the rectification of physical distribution for transporting materials or intermediate products are usually achieved. However, when production of a product is actually started, the progress of product production is delayed due to various factors, and a deviation from the production plan occurs.
上記非特許文献1に記載のように、例えば厚板の製造プロセスは、他の鉄鋼品種と異なり、圧延以降の精整工程の工程数が多いことが特徴である。また、厚板の場合、精整工程の数が多いだけではなく、切断、熱処理、塗装などの、製造仕様に基づいて予め定められた標準工程以外に、各工程での出来栄え(品質)によって通過の有無が決定される、手入れ、矯正、再処理などの標準外工程も考慮して、生産を管理する必要がある。精整工程の負荷を平準化させ、1つの工程に負荷を集中させないように生産を管理することが重要であるが、標準外工程の内容又は量によっては、後続の工程に、生産能力を超える負荷が一時的に集中し、製品の納期遅れが発生することもあり得る。
As described in
製品の納期を遵守するためには、生産計画と生産の進捗度合いとの乖離を許容範囲に抑えることが必要となる。生産量を減少させ、或いは生産能力を増強すると、確かに、生産計画と生産の進捗度合いとの乖離を許容範囲に抑えることが容易に行えるが、事業競争力の観点からは好ましくない。製品の生産は、可能な限り短い納期で、大量に、かつ最小のコストで行うことが重要である。このため、生産計画と生産の進捗度合いとの乖離が許容範囲より大きくなったときの対策は、比較的厳しい条件になるのが通常である。 In order to comply with the delivery date of the product, it is necessary to keep the deviation between the production plan and the progress of production within an allowable range. If the production volume is reduced or the production capacity is increased, it is certainly easy to keep the deviation between the production plan and the progress of production within an allowable range, but this is not preferable from the viewpoint of business competitiveness. It is important that the production of products be carried out in large quantities and at the lowest cost with the shortest possible delivery time. For this reason, it is normal that the countermeasures when the difference between the production plan and the progress of production becomes larger than the allowable range are relatively severe.
生産計画が立案される際に、負荷を調整する対象となるような重要な工程が管理対象工程として選択される。通常、管理対象工程における仕掛量が一定範囲で推移するように生産計画が立案される。また、進捗状況が管理される際には、管理対象工程における仕掛量が管理される。これは、負荷の調整が適切で生産が順調であれば、管理対象工程における仕掛量は、一定の「ゆらぎ」の範囲内に収まるという知見に基づいている。 When a production plan is drawn up, an important process that is a target for adjusting the load is selected as a process to be managed. Usually, a production plan is drafted so that the amount of work in progress in the process to be managed changes within a certain range. Further, when the progress status is managed, the in-process amount in the management target process is managed. This is based on the knowledge that if the load adjustment is appropriate and the production is smooth, the in-process amount in the process to be managed falls within a certain range of “fluctuation”.
これに対して、管理対象工程における仕掛量が一定範囲から逸脱するような場合には、生産が追い付かず、中間製品の長期滞留、製品出荷の納期遅れが発生する。この影響を低減するためには、緊急出荷、一部製造の外部委託、要員追加等の様々な追加コストが発生する。 On the other hand, when the amount of work in progress in the process to be managed deviates from a certain range, production cannot catch up, causing a long stay of intermediate products and a delay in delivery of product shipment. In order to reduce this effect, various additional costs such as emergency shipping, outsourcing of partial production, and addition of personnel are generated.
そのような状況は、いわば工程間での変動の共鳴現象であり、問題が顕在化した段階で対処するのは困難である場合もある。そのため、管理対象工程における仕掛量の変動が小さい間に悪化の兆候を把握し、仕掛量の一定範囲からの乖離を許容範囲内に抑えることが生産管理上の課題になる。 Such a situation is, so to speak, a resonance phenomenon of fluctuation between processes, and it may be difficult to deal with when the problem becomes apparent. For this reason, it is a problem in production control to grasp signs of deterioration while the fluctuation of the in-process quantity in the process to be managed is small and to keep the deviation of the in-process quantity from a certain range within an allowable range.
上記非特許文献1には、生産計画を立案する段階で、製造工期を適切に予測する方法が開示されている。これに対して、本発明者は、生産計画が立案され、製品の生産が開始された後の過程で、ばらつき等の様々な変動が大きくなる前に、円滑な生産を継続するためには生産計画の修正が必要か否かを判断して、生産管理を支援する技術を想到した。
(実施の形態)
以下、本発明の一実施の形態が、図面を参照しながら説明される。なお、各図面において、同じ構成要素については同じ符号が用いられる。
(Embodiment)
Hereinafter, an embodiment of the present invention will be described with reference to the drawings. In each drawing, the same numerals are used about the same component.
(構成)
図1は、本実施形態における生産管理支援装置の構成例を概略的に示すブロック図である。図2は、本実施形態における生産管理支援装置が用いられる工場の生産ラインの要部を概略的に示すブロック図である。本実施形態における生産管理支援装置は、予め定められた生産計画に従って、複数の中間製品がそれぞれ計画順に通過する複数の工程において複数の中間製品をそれぞれ処理して、複数の中間製品から対応する複数の受注製品を生産する工場における生産管理を支援する。
(Constitution)
FIG. 1 is a block diagram schematically showing a configuration example of a production management support apparatus in the present embodiment. FIG. 2 is a block diagram schematically showing a main part of a production line of a factory in which the production management support apparatus according to this embodiment is used. The production management support device according to the present embodiment processes a plurality of intermediate products in a plurality of processes in which a plurality of intermediate products pass in the order of the plan according to a predetermined production plan, and a plurality of corresponding products from the plurality of intermediate products. Supporting production management in factories that produce orders.
図2に示されるように、本実施形態における生産管理支援装置により生産管理が支援される工場の生産ライン200は、管理対象工程220と、管理対象工程220より前の先行工程群210とを備える。先行工程群210は、第1工程211、第2工程212、第3工程213、第4工程214を含む。
As shown in FIG. 2, the
第1工程211、第2工程212、第3工程213、第4工程214は、それぞれ、単一の設備を有して、中間製品に対して単一の処理を行う工程であってもよい。代替的に、第1工程211、第2工程212、第3工程213、第4工程214は、それぞれ、複数の設備を有して、中間製品に対して複数の処理を順に行う複数の工程を含んでもよい。管理対象工程220は、上述のように、生産計画が立案される際に予め選択された、負荷を調整する対象となるような重要な工程である。
The
本実施形態では、第1工程211、第2工程212、第4工程214は、上述の標準工程であってもよい。第3工程213は、第2工程212で処理された中間製品に対する品質検査の結果に応じて実行されるか否かが決まる、上述の標準外工程であってもよい。例えば、第2工程212で処理された中間製品のうち、品質検査の結果が不合格の中間製品は、第3工程213に運搬されて処理され、その後に第4工程214に運搬されてもよく、一方、品質検査の結果が合格の中間製品は、第3工程213を省略して第4工程214に運搬されてもよい。例えば、第3工程213は、受注製品によっては、標準工程であってもよく、標準外工程であってもよく、生産計画では通過しない工程であってもよい。
In the present embodiment, the
図1に示されるように、本実施形態における生産管理支援装置100は、表示部110、入力部120、メモリ130、記憶部140、及び中央演算処理装置(CPU)150を備える。生産管理支援装置100は、例えばパーソナルコンピュータで構成される。
As shown in FIG. 1, the production
表示部110は、例えば液晶ディスプレイパネルを含む。表示部110は、CPU150により制御されて、後述のように、警報のメッセージ等を表示する。なお、表示部110は、液晶ディスプレイパネルに限られない。表示部110は、有機EL(electroluminescence)パネルなどの他のパネルを含んでもよい。
The
入力部120は、例えばマウス又はキーボードを含む。入力部120は、ユーザにより操作されると、その操作内容を示す操作信号をCPU150に出力する。なお、表示部110がタッチパネル式ディスプレイの場合には、マウス又はキーボードに代えて、タッチパネル式ディスプレイが入力部120を兼用してもよい。
The
メモリ130は、例えば半導体メモリ等により構成される。メモリ130は、例えばリードオンリーメモリ(ROM)、ランダムアクセスメモリ(RAM)、電気的に消去書き換え可能なROM(EEPROM)などを含む。メモリ130のROMは、CPU150を動作させる本実施形態の制御プログラムを記憶する。
The
CPU150は、メモリ130に記憶された本実施形態の制御プログラムに従って動作することによって、中間製品群抽出部151、先行工程群抽出部152、仕掛状況抽出部153、到着情報計算部154、バランス指標計算部155、計画修正判断部156、警報発令部157の機能を有する。CPU150の各部の具体的な機能は、後述される。なお、生産管理支援装置100は、CPU150に代えて、同一機能を果たす他のハードウェアを備えてもよい。
The
記憶部140は、例えばハードディスク又は半導体メモリ等により構成される。記憶部140は、生産計画記憶部141、進捗情報記憶部142を含む。各記憶部141,142は、互いに別の媒体で構成されてもよい。代替的に、各記憶部141,142は、記憶領域が分けられた一つの媒体で構成されてもよい。以下、生産計画記憶部141、進捗情報記憶部142に記憶される内容が説明される。
The
日付Tにおいて、生産ライン200の工程に投入される明細の集合は、例えば、
O(T)={O_j(T),j=1,2,・・・,n} (1)
で表される。式(1)から分かるように、本実施形態では、生産ライン200にn個の明細が工程に投入される。本明細書では、工程に投入される中間製品は、「明細」と称される。式(1)において、各々の明細O_j(T)には、受注製品に対応する製造仕様、数量又は重量、納期が決められている。なお、日付Tは、時分単位ならば「時刻T」と称される。式(1)は、生産計画記憶部141に記憶されている。
On date T, a set of details to be input to the process of the
O (T) = {O_j (T), j = 1, 2,..., N} (1)
It is represented by As can be seen from equation (1), in the present embodiment, n details are input to the
製造仕様は、規格、寸法、材料特性などの受注製品としての性能条件に加え、通過すべき工程及びその順序などの製造手順を含む。工程は、標準工程及び標準外工程を含み、更に、「出荷用倉庫への入庫」を含む。納期は、例えば「出荷用倉庫への入庫」の期限として設定される。 The production specifications include production procedures such as processes to be passed and their order in addition to performance conditions as ordered products such as standards, dimensions, and material characteristics. The process includes a standard process and a non-standard process, and further includes “entry into a shipping warehouse”. The delivery date is set, for example, as a deadline of “entry into the shipping warehouse”.
まず、管理対象工程220における生産の進捗状況を把握する手法が説明される。生産ライン200の全ての工程を含む工程集合Pは、例えば、
P={P_j,j=1,2,・・・} (2)
で表される。管理対象工程220は、工程集合Pの要素であるので、管理対象工程220を符号Pxで表すと、
Px∈P (3)
と表される。
First, a method of grasping the production progress status in the
P = {P_j, j = 1, 2,...} (2)
It is represented by Since the
Px∈P (3)
It is expressed.
日付Tに生産ライン200の工程に投入された明細のうち、管理対象工程220を通過する明細の集合Ox(T)は、本実施形態では、全体集合である明細O(T)の一部、つまり真部分集合である。したがって、
Ox(T)⊂O(T) (4)
で表される。明細の集合Ox(T)は、生産計画記憶部141に記憶されている。
Among the details input to the process of the
Ox (T) ⊂O (T) (4)
It is represented by The set of details Ox (T) is stored in the production
明細の集合Ox(T)に含まれる各々の明細が、管理対象工程220より前に通過する工程の集合Ppreは、工程集合Pの真部分集合であるので、
Ppre⊂P (5)
と表される。管理対象工程220より前に通過する工程の集合Ppreは、先行工程群210に対応する。先行工程群210及び管理対象工程220を含む生産ライン200は、生産計画記憶部141に記憶されている。
Since the set Ppre of the process in which each specification included in the set Ox (T) of the specifications passes before the
Ppre⊂P (5)
It is expressed. A set Ppre of processes that pass before the
任意の日付tに生産ライン200の工程に投入され、管理対象工程220を通過する明細の集合Ox(t)は、過去の実績と生産計画とで確定している。ここで、日付tは、例えば、
t∈(Cr−α,・・・,Cr−1,Cr,Cr+1,・・・,Cr+β) (6)
と表される。式(6)において、Crは、現在の日付である。工程への投入日がCr以前の集合Ox(t)は、過去に投入済みであるので、進捗情報記憶部142に記憶されている、過去の実績を表す進捗情報により確定している。工程への投入日がCr以降(Crを含む)の集合Ox(t)は、生産計画記憶部141に記憶されている生産計画によって確定している。
A set of details Ox (t) that is input to the process of the
t∈ (Cr−α,..., Cr-1, Cr, Cr + 1,..., Cr + β) (6)
It is expressed. In equation (6), Cr is the current date. Since the set Ox (t) whose input date to the process is Cr or earlier has been input in the past, the set Ox (t) is determined based on the progress information representing the past results stored in the progress
任意の日付tに生産ライン200の工程に投入され、管理対象工程220を通過する明細の集合Ox(t)に含まれる各明細Ox_j(t)が通過する各工程のうち、管理対象工程220より前の先行工程の集合Ppre(Ox_j(t))は、工程集合Pの真部分集合であるので、
Ppre(Ox_j(t))⊂P (7)
と表される。なお、先行工程の集合Ppre(Ox_j(t))は、先行工程の集合Ppreの真部分集合でもあるので、式(5)から、
Ppre(Ox_j(t))⊂Ppre⊂P (8)
とも表される。
From each process through which each specification Ox_j (t) included in the set of specifications Ox (t) that is input to the process of the
Ppre (Ox_j (t)) ⊂P (7)
It is expressed. The preceding process set Ppre (Ox_j (t)) is also a true subset of the preceding process set Ppre.
Ppre (Ox_j (t)) ⊂Ppre⊂P (8)
It is also expressed.
上述の先行工程の集合Ppre(Ox_j(t))は、現在の日付Crにおいて、既に通過した工程の集合Ppre通過済(Ox_j(t))と、今後通過する予定の工程の集合Ppre通過予定(Ox_j(t))とに分割することができる。 The set Ppre (Ox_j (t)) of the preceding process described above has passed the set Ppre that has already passed (Ox_j (t)) and the set Ppre that is scheduled to pass in the future on the current date Cr. Ox_j (t)).
なお、集合Ppre通過済(Ox_j(t))は、標準外工程を含むが、集合Ppre通過予定(Ox_j(t))は、未だ処理が実行されていないため、標準外工程を含まない。しかしながら、実際には、相当の確率で標準外工程を含む場合もあるので、その分を予め含めてもよい。具体的には、例えば、ある工程Pzが標準外工程として追加される確率が、過去の実績に従えばρである場合を考える。この場合、乱数を発生させて、発生した乱数値がρ以下であれば、当該工程Pzを集合Ppre通過予定(Ox_j(t))に加えるという方法を用いてもよい。 The set Ppre passed (Ox_j (t)) includes a non-standard process, but the set Ppre scheduled pass (Ox_j (t)) does not include a non-standard process because the process has not yet been executed. However, in practice, non-standard processes may be included with a considerable probability, so that part may be included in advance. Specifically, for example, a case is considered where the probability that a certain process Pz is added as a non-standard process is ρ according to past results. In this case, a method of generating a random number and adding the process Pz to the set Ppre passing schedule (Ox_j (t)) if the generated random value is equal to or less than ρ may be used.
また、t≧Crであれば、今後投入される明細であるので、集合Ppre通過済(Ox_j(t))は、空集合であり、先行工程の集合Ppre(Ox_j(t))は、集合Ppre通過予定(Ox_j(t))のみを含むこととなる。 Further, if t ≧ Cr, the details will be introduced in the future, and the set Ppre passed (Ox_j (t)) is an empty set, and the preceding process set Ppre (Ox_j (t)) is set to the set Ppre. Only the scheduled passage (Ox_j (t)) is included.
このように、管理対象工程220を通過する明細の集合Ox(t)と、集合Ox(t)に含まれる各明細Ox_j(t)とに対して、通過済みの工程群と、通過予定の工程群とを求めることができる。そして、通過予定の工程の集合Ppre通過予定(Ox_j(t))に対し、明細が一定の処理時間で通過するという前提で、明細が仕掛として管理対象工程220に到着するタイミング(到着日)と到着量とを算出することができる。
In this way, for a set of details Ox (t) that passes through the
例えば、明細Ox_j(t)の、現在の日付Crにおける管理対象工程220より前に通過予定の工程の集合を{P1,P2,P3}とし、重量をw_jとし、工程P1,P2,P3の処理日数をそれぞれTt1,Tt2,Tt3とする。この場合、管理対象工程220には、日付(Cr+Tt1+Tt2+Tt3)に、重量w_jの仕掛が到着すると考えられる。
For example, the set of processes scheduled to pass before the
但し、一般に、処理日数Tt1,Tt2,Tt3は、工程P1,P2,P3における仕掛量、明細の処理順等に依存するため、ばらつきが発生する。また、管理対象工程220に到着するまでの日数(Tt1+Tt2+Tt3)もばらつく。この日数(Tt1+Tt2+Tt3)は、過去の実績の処理日数の平均値として取り扱ってもよい。或いは、この日数(Tt1+Tt2+Tt3)は、複数の日数に分散して到着するとして取り扱ってもよい。ここでは、例えば「5日」など、一定の数値が割り当てられているとして、説明が進められる。
However, in general, the processing days Tt1, Tt2, and Tt3 depend on the in-process amount in the processes P1, P2, and P3, the processing order of the details, and the like, and thus variations occur. Further, the number of days (Tt1 + Tt2 + Tt3) until arrival at the
次に、管理対象工程220における将来仕掛推移の予測について説明される。日付tにおいて通過予定の工程の集合が空集合でない明細の集合TOx(t)は、日付tでの「有効明細集合」と称される。このとき、有効明細集合TOx(t)の要素である有効明細Oは、
O∈TOx(t) (9)
と表される、有効明細集合TOx(t)の要素である有効明細Oは、ある通過日数τの後に、管理対象工程220に到着して仕掛となる。
Next, prediction of future in-process transition in the
O∈TOx (t) (9)
The effective item O that is an element of the effective item set TOx (t), which is expressed as follows, arrives at the
なお、管理対象工程220における将来仕掛推移を検討する場合、将来に投入される予定の明細で、先行工程群を通過済みの明細の集合は、空集合になる。逆に、既に管理対象工程220に到着済みの明細で、先行工程群を通過予定の明細の集合は空集合であり、有効明細集合には含まれない。通過日数τの算出手順は後述される。ここでは、通過日数τは既知として、仕掛推移の計算手順が説明される。
Note that when considering the future in-process transition in the
過去の日付t=Cr−αに投入された明細Oの、現在の日付t=Crにおける通過予定の工程の集合は、
{P_j,j=1,2,・・・} (10)
で表されるとする。明細が工程P_jを通過するのに要する通過日数(つまり処理日数)をτjとする。この時、明細Oが管理対象工程220に到着するまでの日数はΣτjとなる。したがって、管理対象工程220への到着日は、
Cr+Στj (11)
となる。なお、通過予定の工程の集合P_jの通過日数τjについても、その算出手順は後述されるが、ここでは既知とする。以下、仕掛推移の計算例が説明される。
A set of processes scheduled to pass on the current date t = Cr of the detail O input on the past date t = Cr−α is
{P_j, j = 1,2, ...} (10)
It is assumed that Let τj be the number of days required for the specification to pass through the process P_j (that is, the number of processing days). At this time, the number of days until the statement O arrives at the
Cr + Στj (11)
It becomes. Note that the calculation procedure for the passage days τj of the set P_j of processes scheduled to pass will be described later, but is assumed to be known here. Hereinafter, a calculation example of the in-process transition will be described.
図3は、現在の日付Crを0として、過去に投入された明細及び現在から将来に投入が計画されている明細の進捗状況を表す明細情報を概略的に示す図である。図3に示されるように、明細情報300は、明細欄301、投入日欄302、現在工程欄303、将来工程欄304、通過日数欄305、到着日欄306、重量欄307を含む。到着情報計算部154は、生産計画記憶部141に記憶されている生産計画と、進捗情報記憶部142に記憶されている進捗情報とから、明細情報300を生成する。
FIG. 3 is a diagram schematically showing detailed information indicating the progress of the details input in the past and the details planned to be input in the future from the present, with the current date Cr as 0. FIG. As shown in FIG. 3, the
明細欄301は、明細を示す。投入日欄302は、明細の投入日を示す。現在工程欄303は、対応する明細が現在仕掛っている工程を示す。将来工程欄304は、対応する明細が将来仕掛る予定の工程を示す。通過日数欄305は、現在から管理対象工程220に到着するまでの日数を示す。到着日欄306は、対応する明細が管理対象工程220に到着するのが何日後であるかを示す。重量欄307は、対応する明細の重量を示す。
The
明細欄301と投入日欄302とから分かるように、図3には、過去の2日間に投入された明細O1〜O5と、本日(Cr)と将来の2日間とに投入が計画されている明細Q1〜Q4とが示されている。現在工程欄303と将来工程欄304とから分かるように、図3の例では、管理対象工程220までに通過する工程(先行工程群)は、工程P1,P2の2つの工程とされている。すなわち、図3の例では図2の構成が簡略化されている。
As can be seen from the
図3に示されるように、現在、明細O2、O3、O5は、工程P1に仕掛かっており、明細O1、O4は、工程P2に仕掛かっている。図3の例では、明細O4は、明細O2、O3よリ後で投入されたにも拘らず、明細O2、O3を追い越しており、先に管理対象工程220に到着する。
As shown in FIG. 3, the details O2, O3, and O5 are currently in process P1, and the details O1 and O4 are in process P2. In the example of FIG. 3, although the detail O4 has been input after the details O2 and O3, it has overtaken the details O2 and O3 and arrives at the
図3の例では、工程P1の処理日数(通過日数)は、3日とされ、工程P2の処理日数は、2日とされている。したがって、通過日数欄305に示されているように、工程P1に仕掛かっている明細O2,O3,O5の管理対象工程220までの通過日数は5日となり、工程P2に仕掛かっている明細O1,O4の通過日数は、2日となる。
In the example of FIG. 3, the number of processing days (passing days) in the process P1 is 3 days, and the processing days in the process P2 is 2 days. Therefore, as shown in the
図3では、現在の日付(Cr=0)を基準にしているので、過去に投入された明細O1〜O5の到着日については、通過日数欄305に記載の、現在工程及び将来工程を合わせた通過日数後が到着日になる。すなわち、投入日ではなくて現在の日付(Cr=0)に、現在通過中及び将来通過予定を合わせた通過日数を加えたものが到着日になる。一方、将来投入が計画されている明細Q1〜Q4の到着日については、投入日に直ぐに工程P1の仕掛りになったとみなして、投入日から通過日数後が到着日となる。
In FIG. 3, since the current date (Cr = 0) is used as a reference, the current process and the future process described in the
図4は、到着情報計算部154によって生成された到着情報400を概略的に示す図である。到着情報計算部154は、明細情報300(図3)から、到着情報400を生成する。図4の到着情報400は、明細情報300に示される各明細O1〜O5,Q1〜Q4の重量を到着日毎及び投入日毎に集計した情報を表す。
FIG. 4 is a diagram schematically showing the
図4に示されるように、到着情報400は、投入日欄401、到着日欄402、及び合計欄403,404を含む。投入日欄401は、明細が工程に投入された日付を表す。投入日欄401の「過去分」は、現在の日付(Cr=0)より過去に投入された明細O1〜O5を表し、「0」は、現在の日付(Cr=0)に投入された明細Q1を表し、「1」は、1日後に投入されることが計画されている明細Q2,Q3を表し、「2」は、2日後に投入されることが計画されている明細Q4を表す。
As shown in FIG. 4, the
到着日欄402は、明細が管理対象工程220に到着する日付を表す。到着日欄402の「2」は、現在の日付(Cr=0)から2日後に到着するように計画されている明細O1,O4を表し、「5」は、現在の日付(Cr=0)から5日後に到着するように計画されている明細O2,O3,O5,Q1を表し、「6」は、現在の日付(Cr=0)から6日後に到着するように計画されている明細Q2,Q3を表し、「7」は、現在の日付(Cr=0)から7日後に到着するように計画されている明細Q4を表す。
The
合計欄403は、到着日欄402に示される到着日毎の明細の合計重量を表し、合計欄404は、投入日欄401に示される投入日毎の明細の合計重量を表す。
The
図4に示されるように、投入日が「−2」から「2」までの5日間において投入された明細の合計重量は150[トン]である。このため、負荷の平準化を図る観点では、毎日30[トン]前後の明細が管理対象工程220に到着することが望ましい。しかし、図4の例では、到着日「5」において、その2倍以上である70[トン]の明細が到着しており、管理対象工程220に負荷が一時的に集中している。
As shown in FIG. 4, the total weight of the specifications input in 5 days from “−2” to “2” is 150 [tons]. For this reason, from the viewpoint of leveling the load, it is desirable that details about 30 [tons] arrive at the
上述のように、30[トン/日]前後の明細が管理対象工程220に到着することが、望ましいが、この場合には、通常、管理対象工程220の処理量は、30[トン/日]に設定される。その場合、図4に示されるように、到着日が「5」から「7」の3日間に、4日分の明細が管理対象工程220に到着することになる。したがって、管理対象工程220において、1日分の処理遅れが見込まれる。
As described above, it is desirable that the details around 30 [ton / day] arrive at the
以上のように、処理遅れなどの変動が許容範囲内に抑えられるように、変動を監視して対策を早めに講じることが必要になる。図3、図4の例では、上述のように、到着日「5」に過剰な量の明細が管理対象工程220に到着している。これによる影響を減らすためには、図4から分かるように、例えば、投入日「0」、「1」、「2」における投入量を減らすという方法がある。但し、この対策によって、明細が長期にわたって滞留して納期遅れが生じることを抑制できる可能性はあるものの、製品の生産量が減少し、生産能力が最大限に活用できないことになる。また、明細が滞留するのは止むを得ないとした上で、納期に対する余裕の短い明細を優先的に処理するという対策も考えられる。
As described above, it is necessary to monitor the variation and take measures early so that the variation such as processing delay is suppressed within the allowable range. In the example of FIGS. 3 and 4, as described above, an excessive amount of details arrives at the
図5は、管理対象工程220における仕掛量の推移の一例を概略的に示す図である。図6は、各日において管理対象工程220に10日以上滞留していた重量の推移を概略的に示す図である。図7は、第1工程211における仕掛量の推移の一例を概略的に示す図である。図8は、第2工程212における仕掛量の推移の一例を概略的に示す図である。図9は、第3工程213における仕掛量の推移の一例を概略的に示す図である。図10は、第4工程214における仕掛量の推移の一例を概略的に示す図である。図5〜図10の例は、121日間の推移を示している。図5〜図10を用いて、各工程における仕掛量の推移の具体例が説明される。
FIG. 5 is a diagram schematically illustrating an example of the transition of the in-process amount in the
図5に示されるように、管理対象工程220における仕掛量は、50日頃に重量W11を超えており、25日頃及び100日頃に、重量W12(=0.8×W11)を超えている。全期間の平均値は、約Waであり、標準偏差σは、約Wa/2であって、重量W11,W12を超えている期間は、平均値より1.5σ〜2σ上方に乖離している。
As shown in FIG. 5, the in-process amount in the
図6に示されるように、10日間以上の長期にわたって滞留している明細の重量は、50日頃に急増している。図5、図6を合わせると、仕掛量が平均値より上方に2σ乖離すると、納期遅れのリスクが高くなることが分かる。 As shown in FIG. 6, the weight of the specification staying for a long period of 10 days or more increases rapidly around 50 days. When FIG. 5 and FIG. 6 are combined, it can be seen that if the amount of work in progress is 2σ above the average value, the risk of delivery delay increases.
図7に示されるように、第1工程211における仕掛量は、1日〜10日に多く、その後は次第に減少している。全期間の平均値は、約Wa1であり、標準偏差σは、約Wa1/2であって、重量W1を超えている期間を含む1日〜10日では、仕掛量が、大きく積みあがっている。
As shown in FIG. 7, the amount of work in progress in the
図8に示されるように、第2工程212における仕掛量は、90日〜100日で増大している。全期間の平均値は、約Wa2であり、標準偏差σは、約Wa2/2であって、仕掛量がW2を超えている90日〜100日頃の期間では、仕掛量が、平均値より上方に2σ以上振れている。
As shown in FIG. 8, the amount of work in progress in the
図9に示されるように、第3工程213における仕掛量は、20日〜40日で増大している。全期間の平均値は、約Wa3であり、標準偏差σは、Wa3より少し大きい値であって、仕掛量がW3を超えている期間では、仕掛量が、平均値より上方に2σ以上振れている。
As shown in FIG. 9, the amount of work in progress in the
図10に示されるように、第4工程214における仕掛量は、第1工程211〜第3工程213の仕掛量の増加が重ね合わさった形状になっている。全期間の平均値は、約Wa4であり、標準偏差σは、約Wa4/3であって、仕掛量が平均値より上方に2σ以上振れている期間は、50日頃及び110日頃である。図5〜図10から、先行工程の遅れが、後続工程に影響を及ぼしていることが分かる。
As shown in FIG. 10, the in-process amount in the
図1に戻って、バランス指標計算部155は、管理対象工程220における仕掛量と生産性(具体的には処理量)とのバランス度合を表すバランス指標を算出する。バランス指標計算部155は、管理対象工程220における、隣接する日付間の仕掛量の差分である仕掛量差分を以下の式(12)を用いて算出し、隣接する日付間の処理量の差分である処理量差分を以下の式(13)を用いて算出し、それらの差分の差異量を以下の式(14)を用いて算出する。
Returning to FIG. 1, the balance
仕掛量差分=日付Nにおける仕掛量−日付(N−1)における仕掛量 (12)
処理量差分=日付Nにおける処理量−日付(N−1)における処理量 (13)
差分差異量=仕掛量差分−処理量差分 (14)
処理量が一定であれば、処理量差分は0になるが、実際には生産性の変動により処理量が変化するため、その処理量差分を考える。これによって、生産性の変動も考慮することができる。
Work in progress difference = work in progress on date N−work in progress on date (N−1) (12)
Processing amount difference = processing amount on date N−processing amount on date (N−1) (13)
Difference difference amount = In-process difference-Processing amount difference (14)
If the processing amount is constant, the processing amount difference becomes 0. However, since the processing amount actually changes due to a change in productivity, the processing amount difference is considered. As a result, fluctuations in productivity can be taken into consideration.
バランス指標計算部155は、更に、差分差異量のM日移動平均を算出する。バランス指標計算部155は、式(15)に示されるように、このM日移動平均を累積した累積値をバランス指標として算出する。
The balance
バランス指標=Σ(差分差異量のM日移動平均) (15)
仕掛量及び処理量が大きく変動せずに、生産が安定している場合には、バランス指標は概ね0に保たれる。
Balance index = Σ (M-day moving average of difference difference) (15)
When the in-process amount and the processing amount do not fluctuate greatly and the production is stable, the balance index is generally kept at zero.
図11は、管理対象工程220における各日の処理量の推移を概略的に示す図である。図12は、差分差異量の5日移動平均の累積値を概略的に示す図である。図11、図12は、図5〜図10と同様に、121日間の推移を示す。
FIG. 11 is a diagram schematically showing the transition of the processing amount of each day in the
バランス指標計算部155は、図5に示される管理対象工程220における仕掛量のデータと、図11に示される管理対象工程220における処理量のデータとを用いて、上記式(12)〜(14)を用いて、仕掛量差分、処理量差分、差分差異量を算出する。バランス指標計算部155は、算出した差分差異量から、5日移動平均を算出し、更に、5日移動平均の累積値を算出する。
The balance
図12に示されるように、累積値は、50日近辺で大きなピークを持つ。これによって、この50日近辺の時期に仕掛量が大きく増え、仕掛量と処理量とのバランスが崩れていることが分かる。 As shown in FIG. 12, the cumulative value has a large peak around 50 days. As a result, it can be seen that the amount of work in progress greatly increases in the period around 50 days, and the balance between the amount of work in progress and the amount of processing is lost.
上述のように、5日移動平均の累積値(つまりバランス指標)は、概ね0になる筈であり、負の値になった後は正の値になる。例えば、図12において、10日〜30日に負の値になった分が、40日以降に正の値として現れる。累積値が負の値になるのは、先行工程(本実施形態では第4工程214)の進捗が遅れて、管理対象工程220に到着する明細が減少している状況を表す。その後、管理対象工程220に明細が集中して到着してくると、バランス指標は正の値に振れる。
As described above, the cumulative value (that is, the balance index) of the 5-day moving average should be approximately 0 and becomes a positive value after becoming a negative value. For example, in FIG. 12, a negative value on the 10th to 30th appears as a positive value after the 40th. The cumulative value becomes a negative value because the progress of the preceding process (the
図11に示されるように、40日〜50日の期間では、管理対象工程220における処理量が減少しており、この処理量の減少がバランス指標の増加の一因になっている。その後、50日〜55日頃に処理量が増加しており、これに伴ってバランス指標は50日過ぎから減少し始めている。また、図12に示されるように、バランス指標は、80日〜90日に負の値になった分、100日以降は正に振れて、仕掛量が増大していることを表す。しかし、図11に示されるように、処理量は減少しておらず、バランス指標の振れ幅も小さくなっている。
As shown in FIG. 11, in the period of 40 days to 50 days, the processing amount in the
このように、管理対象工程220に到着する明細の仕掛量と管理対象工程220における処理量とのバランスを考慮したバランス指標が、「0近辺」から大きく外れないように生産管理することが必要である。また、バランス指標が負方向に乖離すると、将来、正方向に乖離すると予測することができる。
As described above, it is necessary to manage production so that the balance index considering the balance between the in-process amount of the specification arriving at the
図1に戻って、計画修正判断部156は、負の値である閾値を予め設定しておき、バランス指標が閾値未満であるか否かを判断する。負の値である閾値は、本実施形態の制御プログラムの一部として、メモリ130の例えばROMに記憶されている。計画修正判断部156は、バランス指標が閾値未満であれば、その旨を警報発令部157に通知する。警報発令部157は、バランス指標が閾値未満であることが通知されると、警報を発令する。これによって、ユーザは、進捗状況を確認したり、生産計画を見直したりするなどの対策を講じることが可能になる。
Returning to FIG. 1, the plan
到着情報計算部154は、標準工期に基づき、管理対象工程220への明細の到着日及び到着量を算出する。各工程211〜214には、標準的な通過期間(例えば通過日数)である標準工期が設定されている。この標準工期は、過去の実績に基づいて設定される期間であり、その期間内に処理を完了すべきという管理値でもある。例えば「標準工期3日」は、工程での滞留日数が平均で3日以内に処理を完了すべきということを意味する。但し、標準工期が例えば3日に設定されていても、至急に処理すべき明細は、1日で処理を完了する場合もある。また、優先度の低い明細は、3日を超える長い期間にわたって滞留する場合もある。通過期間は、工程における処理順に影響される。
The arrival
例えば、標準工期がK[日]である場合、概算として、明細の重量Wのうち処理すべき分量が、標準工期であるK[日]が平均値となるように、K[日]の周辺に分散して配置される。本実施形態では、均等配分として、標準工期K[日]を中心として、1[日]〜2K[日]の各日にW/2Kを配置する。図3、図4の例では、工程P1、P2の通過日数を各々3日、2日としたが、これは、標準工期Kが各々3日、2日であることを意味する。 For example, when the standard work schedule is K [days], as a rough estimate, the amount to be processed of the weight W of the specification is around K [days] so that the standard work schedule K [days] is an average value. Are distributed and arranged. In the present embodiment, as an equal distribution, W / 2K is arranged on each day of 1 [day] to 2K [day] with the standard work schedule K [day] as the center. In the example of FIGS. 3 and 4, the passage days of the processes P1 and P2 are 3 days and 2 days, respectively, which means that the standard work schedule K is 3 days and 2 days, respectively.
なお、明細の重量Wの分散配置は、均等配分に限られない。代替的に、例えばK[日]の周囲で、(K−1)[日]は0.1×W、K[日]は0.6×W、(K+1)[日]は0.2×W、(K+2)[日]は0.1×Wのように、不均等に配分してもよい。さらに代替的に、K[日]に1.0×Wと、全処理量を集中させてもよい。この場合が最も簡単である。 The distributed arrangement of the weight W in the specification is not limited to the uniform distribution. Alternatively, for example, around K [day], (K-1) [day] is 0.1 × W, K [day] is 0.6 × W, and (K + 1) [day] is 0.2 ×. W and (K + 2) [days] may be distributed unevenly, such as 0.1 × W. Further alternatively, the total processing amount may be concentrated at 1.0 [W] in K [days]. This is the simplest case.
図13は、各工程の通過重量を表す明細情報1300を概略的に示す図である。図13に示されるように、明細情報1300は、工程欄1301、通過日欄1302、明細欄1303、合計欄1304,1305を備える。工程欄1301は、図13の例では、図3と同様に、工程P1,P2を含む。通過日欄1302は、明細の配分された重量が各工程を通過する通過日を表す。明細欄1303は、図3の例と同様に、明細O1〜O5,Q1〜Q4を含む。合計欄1304は、各工程における通過日毎の通過重量を表す。合計欄1305は、明細毎の重量を表す。合計欄1305の数値は、図3の重量欄307の数値と同じである。
FIG. 13 is a diagram schematically showing
明細情報1300は、図3の例において、明細の重量が均等に配分された場合の工程P1,P2の通過重量を通過日毎に表す。例えば明細O2では、工程P1の標準工期K=3であり、2K=6であるので、重量20[トン]が工程P1の1日〜6日に均等配分されている。そして、その均等配分された各々は、工程P2の標準工期K=2であり、2K=4であるので、さらに工程P2の4日間に均等配分されている。例えば工程P1の1日の3.3[トン]は、工程P2の2日〜5日の4日間に均等配分される。例えば工程P1の2日の3.3[トン]は、工程P2の3日〜6日の4日間に均等配分される。その他も同様に配分され、通過日毎に集計されている。
The
図13において、工程P1に対応する合計欄1304に記載された合計重量は、工程P2への到着量を表す。また、工程P2に対応する合計欄1304に記載された合計重量は、管理対象工程220への到着量を表す。
In FIG. 13, the total weight described in the
図14は、管理対象工程220への到着日毎の到着量を概略的に示す図である。図14の推移1401は、図13に示される工程P2の通過日を管理対象工程220への到着日として到着日毎の到着量を表す。図14の推移1402は、図4の到着日における到着量を表し、到着日を均等配分せずに標準工期K[日]に集中させた場合に相当する。
FIG. 14 is a diagram schematically showing an arrival amount for each arrival date to the
図14に示されるように、推移1401では、推移1402に比べて、仕掛量の変動幅が平滑化されている。しかし、推移1401,1402のいずれの場合でも、4日〜5日後に遅延分の負荷が集中する傾向を読み取ることができる。
As shown in FIG. 14, in the
このように、管理対象工程220への到着日及び到着量を算出することにより、工程P2の通過日「4」に集中している重量26[トン]を低減するために、将来に投入が計画されている明細Q2〜Q4の投入時期を遅らせる等の対策を検討することができる。また、明細Q2〜Q4の投入時期を遅らせた状態で、同様に到着日及び到着量を算出することにより、明細の集中が低減されたことの効果を確認することができる。
Thus, in order to reduce the weight 26 [tons] concentrated on the passage date “4” of the
図15は、図14に比べて管理対象工程220の生産性が低下した場合の到着量を概略的に示す図である。例えば、3日〜6日にかけて、管理対象工程220の生産性が低下して処理量が10[トン/日]減少した場合、図15に示されるように、推移1501,1502は、図14の3日〜6日の到着量(仕掛量)に10[トン/日]が上乗せされた形となる。これによって、負荷の集中度合いが更に強調されることになる。
FIG. 15 is a diagram schematically showing an arrival amount when the productivity of the
図16は、図15の場合のバランス指標の推移を概略的に示す図である。図16の推移1601,1602では、それぞれ、図15の推移1501,1502に対して、初期値をゼロとすれば、傾向としては、同じ傾向を示している。
FIG. 16 is a diagram schematically showing the transition of the balance index in the case of FIG. The
例えば、計画修正判断部156は、バランス指標が20以上を、負荷が集中しており生産調整が必要な管理水準であるとしてもよい。計画修正判断部156は、図16の推移1601の例では、日付「3」において、負荷を下げるような計画の修正が必要であると判断してもよい。警報発令部157は、計画の修正が必要であることを表すメッセージを表示部110に表示してもよい。ユーザは、例えば、バランス指標が管理水準である20未満になるように、将来投入分の明細の投入時期を遅らせるように、生産計画を修正してもよい。
For example, the plan
(動作)
図17は、図1の生産管理支援装置の動作を概略的に示すフローチャートである。図17の動作は、例えば入力部120を用いてユーザによって指示されると実行される。ユーザは、例えば1日に1回、図17の動作実行を指示してもよい。
(Operation)
FIG. 17 is a flowchart schematically showing the operation of the production management support apparatus of FIG. The operation in FIG. 17 is executed when instructed by the user using the
ステップS1700において、中間製品群抽出部151は、生産計画記憶部141に記憶されている管理対象工程を取得する。ステップS1705において、中間製品群抽出部151は、生産計画記憶部141に記憶されている生産計画から、基準日(例えば現在の日付)以降に管理対象工程を通過する中間製品からなる中間製品群を抽出して、抽出した中間製品群をメモリ130の例えばRAMに保存する。
In step S <b> 1700, the intermediate product
ステップS1710において、先行工程群抽出部152は、生産計画記憶部141に記憶されている生産計画から、中間製品群が管理対象工程より前に通過する先行工程群を抽出して、抽出した先行工程群をメモリ130の例えばRAMに保存する。
In step S <b> 1710, the preceding process
ステップS1715において、仕掛状況抽出部153は、生産計画記憶部141に記憶されている生産計画と、進捗情報記憶部142に記憶されている進捗情報とから、基準日における、先行工程群に対する中間製品群の仕掛状況を抽出して、明細情報1300(図13)を生成する。仕掛状況抽出部153は、生成した明細情報1300をメモリ130の例えばRAMに保存する。
In step S1715, the in-process
ステップS1720において、到着情報計算部154は、明細情報1300から、先行工程群210に仕掛っている中間製品群が管理対象工程220に到着する到着日及び到着量を算出して、算出した到着日及び到着量をメモリ130の例えばRAMに保存する。ステップS1725において、バランス指標計算部155は、基準日の直近における管理対象工程220の処理量(例えば現在の日付から過去1週間の平均値)を取得する。バランス指標計算部155は、取得した処理量と、到着日及び到着量とを用いて、バランス指標を算出する。バランス指標計算部155は、算出したバランス指標をメモリ130の例えばRAMに保存する。
In step S1720, the arrival
ステップS1730において、計画修正判断部156は、バランス指標が負の値である閾値未満であるか否かを判断する。バランス指標が閾値以上であれば(ステップS1730でNO)、図17の処理は終了する。バランス指標が閾値未満であれば(ステップS1730でYES)、処理はステップS1735に進む。
In step S1730, the plan
ステップS1735において、計画修正判断部156は、進捗状況の確認が必要であることを警報発令部157に通知する。ステップS1740において、この通知を受けて、警報発令部157は、進捗状況の確認が必要であることを報知する警報を発令する。警報発令部157は、進捗状況の確認が必要であることを表すメッセージを表示部110に表示してもよい。その後、図17の処理は終了する。
In step S1735, the plan
(効果)
以上説明されたように、本実施形態では、算出したバランス指標が負の値である閾値未満であれば、警報を発令するようにしている。上述のように、バランス指標が負の値に大きく振れている場合には、先行工程群において生産の遅延が発生しており、将来的に、負荷が管理対象工程に集中する可能性が高い。したがって、本実施形態によれば、算出したバランス指標が負の値である閾値未満であれば、警報を発令することにより、進捗状況を確認するなどの対策を講じることが可能になる。
(effect)
As described above, in the present embodiment, if the calculated balance index is less than a negative threshold value, an alarm is issued. As described above, when the balance index largely fluctuates to a negative value, production delay occurs in the preceding process group, and it is highly possible that the load will concentrate on the process to be managed in the future. Therefore, according to the present embodiment, if the calculated balance index is less than a negative threshold value, it is possible to take measures such as confirming the progress by issuing an alarm.
(変形された実施形態)
上記実施形態では、図17のステップS1730において、計画修正判断部156は、バランス指標が負の値である閾値未満であるか否かを判断しているが、これに限られない。図17のステップS1730において、計画修正判断部156は、バランス指標が正の値である閾値を超えるか否かを判断してもよい。図17のステップS1735において、計画修正判断部156は、生産計画の修正が必要であることを警報発令部157に通知してもよい。図17のステップS1740において、警報発令部157は、通知を受けて、生産計画の修正が必要であることを表すメッセージを表示部110に表示してもよい。
(Modified embodiment)
In the above embodiment, the plan
上述のように、バランス指標が正の値に大きく振れている場合には、管理対象工程220に負荷が集中していることを表す。そこで、この変形された実施形態によれば、ユーザは、生産計画を修正するなどの対策を講じることが可能になる。
As described above, when the balance index greatly fluctuates to a positive value, it indicates that the load is concentrated on the
110 表示部
141 生産計画記憶部
142 進捗情報記憶部
151 中間製品群抽出部
152 先行工程群抽出部
153 仕掛状況抽出部
154 到着情報計算部
155 バランス指標計算部
156 計画修正判断部
157 警報発令部
DESCRIPTION OF
Claims (4)
前記生産計画と、前記複数の工程から予め選択された管理対象工程とを記憶する生産計画記憶部と、
前記複数の中間製品の前記複数の工程に対する仕掛状況を含む前記複数の受注製品の生産の進捗情報を記憶する進捗情報記憶部と、
前記管理対象工程を基準日以降に通過する前記中間製品を含む中間製品群を前記生産計画記憶部から抽出する中間製品群抽出部と、
前記中間製品群に含まれる前記中間製品が前記管理対象工程より前に通過する先行工程を含む先行工程群を前記生産計画記憶部から抽出する先行工程群抽出部と、
前記中間製品群に含まれる前記中間製品の、前記先行工程群に含まれる前記先行工程に対する仕掛状況を、前記基準日以前の分は前記進捗情報記憶部から抽出し、前記基準日以降の分は前記生産計画記憶部から抽出する仕掛状況抽出部と、
前記仕掛状況に基づき、前記中間製品群に含まれる前記中間製品が前記管理対象工程に到着する到着日と、前記到着日に前記管理対象工程に到着する前記中間製品の量である到着量と、を算出する到着情報計算部と、
前記基準日の直近における前記管理対象工程の処理量の実績値を前記進捗情報記憶部から取得し、前記到着量から前記実績値を減算した差の所定期間における移動平均値を累積した累積値をバランス指標として算出するバランス指標計算部と、
前記バランス指標に基づき、前記基準日以降の前記生産計画を修正することが必要であるか否かを判断する計画修正判断部と、
を備える生産管理支援装置。 In a factory for processing a plurality of intermediate products in a plurality of processes in which a plurality of intermediate products pass in the order of the plan according to a predetermined production plan, and producing a plurality of order-receiving products corresponding to the plurality of intermediate products. A production management support device for supporting production management,
A production plan storage unit for storing the production plan, and a management target process preselected from the plurality of processes;
A progress information storage unit for storing progress information of production of the plurality of ordered products including in-process status for the plurality of steps of the plurality of intermediate products;
An intermediate product group extraction unit that extracts an intermediate product group including the intermediate product that passes through the management target process after a reference date from the production plan storage unit;
A preceding process group extracting unit that extracts a preceding process group including a preceding process through which the intermediate product included in the intermediate product group passes before the process to be managed from the production plan storage unit;
The in-process status of the intermediate product included in the intermediate product group with respect to the preceding process included in the preceding process group is extracted from the progress information storage unit before the reference date, and the part after the reference date is extracted. An in-process status extracting unit that extracts from the production plan storage unit;
Based on the in-process status, an arrival date when the intermediate product included in the intermediate product group arrives at the management target process, and an arrival amount that is an amount of the intermediate product that arrives at the management target process on the arrival date; An arrival information calculation unit for calculating
A cumulative value obtained by accumulating a moving average value in a predetermined period of the difference obtained by subtracting the actual value from the arrival amount, obtaining the actual value of the processing amount of the management target process most recently on the reference date. A balance index calculation unit for calculating as a balance index;
A plan correction determination unit for determining whether it is necessary to correct the production plan after the reference date based on the balance index;
A production management support device comprising:
請求項1に記載の生産管理支援装置。 The plan correction determination unit determines that the production plan needs to be corrected when the balance index is less than a predetermined negative value threshold.
The production management support apparatus according to claim 1.
請求項1又は2に記載の生産管理支援装置。 An alarm issuing unit that issues an alarm when it is determined by the plan correction determining unit that the production plan needs to be corrected,
The production management support apparatus according to claim 1 or 2.
複数の工程から予め選択された管理対象工程を基準日以降に通過する前記中間製品を含む中間製品群を、前記生産計画を記憶する生産計画記憶部から抽出する中間製品群抽出ステップと、
前記中間製品群に含まれる前記中間製品が前記管理対象工程より前に通過する先行工程を含む先行工程群を前記生産計画記憶部から抽出する先行工程群抽出ステップと、
前記中間製品群に含まれる前記中間製品の、前記先行工程群に含まれる前記先行工程に対する仕掛状況を、前記基準日以前の分は進捗情報を記憶する進捗情報記憶部から抽出し、前記基準日以降の分は前記生産計画記憶部から抽出する仕掛状況抽出ステップと、
前記仕掛状況に基づき、前記中間製品群に含まれる前記中間製品が前記管理対象工程に到着する到着日と、前記到着日に前記管理対象工程に到着する前記中間製品の量である到着量と、を算出する到着情報計算ステップと、
前記基準日の直近における前記管理対象工程の処理量の実績値を前記進捗情報記憶部から取得し、前記到着量から前記実績値を減算した差の所定期間における移動平均値を累積した累積値をバランス指標として算出するバランス指標計算ステップと、
前記バランス指標に基づき、前記基準日以降の前記生産計画を修正することが必要であるか否かを判断する計画修正判断ステップと、
を備える生産管理支援方法。 In a factory for processing a plurality of intermediate products in a plurality of processes in which a plurality of intermediate products pass in the order of the plan according to a predetermined production plan, and producing a plurality of order-receiving products corresponding to the plurality of intermediate products. A production management support method for supporting production management,
An intermediate product group extracting step for extracting an intermediate product group including the intermediate product that passes through a management target process selected in advance from a plurality of processes from a reference date, from a production plan storage unit that stores the production plan;
A preceding process group extracting step for extracting from the production plan storage unit a preceding process group including a preceding process through which the intermediate product included in the intermediate product group passes before the process to be managed;
The in-process status of the intermediate product included in the intermediate product group with respect to the preceding process included in the preceding process group is extracted from a progress information storage unit that stores progress information before the reference date, and the reference date Subsequent minutes are extracted from the production plan storage unit in-process status extraction step;
Based on the in-process status, an arrival date when the intermediate product included in the intermediate product group arrives at the management target process, and an arrival amount that is an amount of the intermediate product that arrives at the management target process on the arrival date; An arrival information calculation step for calculating
A cumulative value obtained by accumulating a moving average value in a predetermined period of the difference obtained by subtracting the actual value from the arrival amount, obtaining the actual value of the processing amount of the management target process most recently on the reference date. A balance index calculation step to calculate as a balance index;
A plan correction determination step for determining whether it is necessary to correct the production plan after the reference date based on the balance index;
A production management support method comprising:
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP2017148925A JP2019028819A (en) | 2017-08-01 | 2017-08-01 | Production management assist system and method |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP2017148925A JP2019028819A (en) | 2017-08-01 | 2017-08-01 | Production management assist system and method |
Publications (1)
Publication Number | Publication Date |
---|---|
JP2019028819A true JP2019028819A (en) | 2019-02-21 |
Family
ID=65476379
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
JP2017148925A Pending JP2019028819A (en) | 2017-08-01 | 2017-08-01 | Production management assist system and method |
Country Status (1)
Country | Link |
---|---|
JP (1) | JP2019028819A (en) |
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
WO2024090395A1 (en) * | 2022-10-25 | 2024-05-02 | 京セラ株式会社 | Production management device, production management method, production management program, and recording medium |
Citations (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JPH01183348A (en) * | 1988-01-13 | 1989-07-21 | Nec Corp | Production system controller |
JPH11282923A (en) * | 1998-03-31 | 1999-10-15 | Mitsubishi Electric Corp | Circulation type production process schedule planning method |
-
2017
- 2017-08-01 JP JP2017148925A patent/JP2019028819A/en active Pending
Patent Citations (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JPH01183348A (en) * | 1988-01-13 | 1989-07-21 | Nec Corp | Production system controller |
JPH11282923A (en) * | 1998-03-31 | 1999-10-15 | Mitsubishi Electric Corp | Circulation type production process schedule planning method |
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
WO2024090395A1 (en) * | 2022-10-25 | 2024-05-02 | 京セラ株式会社 | Production management device, production management method, production management program, and recording medium |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
JP5012660B2 (en) | Product quality prediction and control method | |
Fithri et al. | Analysis of inventory control by using economic order quantity model–A case study in PT semen padang | |
JP6740860B2 (en) | Safety stock determination device, method and program | |
CN110633820B (en) | Warehouse address recommendation method and device and computer readable storage medium | |
CN111352403A (en) | Process design method for rolling plates | |
JP5309882B2 (en) | Schedule creation system, schedule creation method, and schedule creation program | |
JP2019028819A (en) | Production management assist system and method | |
JP2018012559A (en) | Yard management apparatus, yard management method, and program | |
CN116384718B (en) | Intelligent decision-based supplier joint scheduling method, system and equipment | |
JP6849550B2 (en) | Logistics management support equipment and methods | |
JP2017117049A (en) | Method and device for physical distribution management | |
JP5803318B2 (en) | Operation rule creation method and production logistics plan creation method | |
JP7192382B2 (en) | YARD MANAGEMENT DEVICE, YARD MANAGEMENT METHOD, AND PROGRAM | |
JP2011227605A (en) | Schedule preparation method, schedule preparation program, and schedule preparation device | |
JP2010198340A (en) | Inventory management device and inventory management method | |
JP6613743B2 (en) | Safety stock determination device, method and program | |
JP6086102B2 (en) | Production planning method and program for steel products | |
JP2021111132A (en) | Plan creation support device, prediction model construction device, method and program | |
JP6695298B2 (en) | Order control device | |
JP2014149766A (en) | Production planning method, production planning program, and production planning device | |
JP2009104399A (en) | Manufacturing support system for product, manufacturing system for product, manufacturing support method for product and manufacturing method for product | |
US7039483B1 (en) | Manufacturing management system and method | |
JP6519014B2 (en) | Safety stock determination device, method and program | |
JP5803693B2 (en) | Production logistics schedule creation system and production logistics schedule creation method | |
JP7339545B2 (en) | Product storage management method |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
A621 | Written request for application examination |
Free format text: JAPANESE INTERMEDIATE CODE: A621 Effective date: 20190930 |
|
A977 | Report on retrieval |
Free format text: JAPANESE INTERMEDIATE CODE: A971007 Effective date: 20200923 |
|
A131 | Notification of reasons for refusal |
Free format text: JAPANESE INTERMEDIATE CODE: A131 Effective date: 20201013 |
|
A02 | Decision of refusal |
Free format text: JAPANESE INTERMEDIATE CODE: A02 Effective date: 20201117 |