JP7339545B2 - Product storage management method - Google Patents

Product storage management method Download PDF

Info

Publication number
JP7339545B2
JP7339545B2 JP2020056009A JP2020056009A JP7339545B2 JP 7339545 B2 JP7339545 B2 JP 7339545B2 JP 2020056009 A JP2020056009 A JP 2020056009A JP 2020056009 A JP2020056009 A JP 2020056009A JP 7339545 B2 JP7339545 B2 JP 7339545B2
Authority
JP
Japan
Prior art keywords
products
prediction
storage area
storage
processed
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
JP2020056009A
Other languages
Japanese (ja)
Other versions
JP2021157397A (en
Inventor
豊大 斎藤
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Nippon Steel Corp
Original Assignee
Nippon Steel Corp
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Nippon Steel Corp filed Critical Nippon Steel Corp
Priority to JP2020056009A priority Critical patent/JP7339545B2/en
Publication of JP2021157397A publication Critical patent/JP2021157397A/en
Application granted granted Critical
Publication of JP7339545B2 publication Critical patent/JP7339545B2/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Classifications

    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02PCLIMATE CHANGE MITIGATION TECHNOLOGIES IN THE PRODUCTION OR PROCESSING OF GOODS
    • Y02P80/00Climate change mitigation technologies for sector-wide applications
    • Y02P80/40Minimising material used in manufacturing processes
    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02PCLIMATE CHANGE MITIGATION TECHNOLOGIES IN THE PRODUCTION OR PROCESSING OF GOODS
    • Y02P90/00Enabling technologies with a potential contribution to greenhouse gas [GHG] emissions mitigation
    • Y02P90/02Total factory control, e.g. smart factories, flexible manufacturing systems [FMS] or integrated manufacturing systems [IMS]
    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02PCLIMATE CHANGE MITIGATION TECHNOLOGIES IN THE PRODUCTION OR PROCESSING OF GOODS
    • Y02P90/00Enabling technologies with a potential contribution to greenhouse gas [GHG] emissions mitigation
    • Y02P90/30Computing systems specially adapted for manufacturing

Landscapes

  • General Factory Administration (AREA)
  • Management, Administration, Business Operations System, And Electronic Commerce (AREA)

Description

本発明は、複数の上流工程で処理した製品を、製品置場を介して複数の下流工程でさらに処理する製造プロセスにおける、製品の置場管理方法に関する。 TECHNICAL FIELD The present invention relates to a product storage space management method in a manufacturing process in which a product processed in multiple upstream processes is further processed in multiple downstream processes via a product storage space.

製品を生産する製造プロセス、例えば鉄鋼製造プロセスでは、複数の処理ラインを有する上流工程で処理した製品を一旦製品置場に貯蔵した後に、複数の処理ラインを有する下流工程でさらに処理することが一般に行われている。例えば、複数の酸洗ラインで酸洗処理された製品は、それぞれ、酸洗ラインにて処理された製品を貯蔵する置場にそれぞれ貯蔵された後、下流工程である冷間圧延工程の置場に搬送され、生産順番を待って冷間圧延工程で冷間圧延される。なお、冷間圧延工程も複数の冷間圧延ラインを有しており、生産する製品の板厚や製品種類に応じて一の冷間圧延ラインが指定され、製品が処理されることが多い。 In a manufacturing process that produces products, for example, a steel manufacturing process, it is common practice to store products that have been processed in an upstream process that has multiple processing lines, temporarily store them in a product storage area, and then process them further in a downstream process that has multiple processing lines. It is For example, products that have been pickled in a plurality of pickling lines are each stored in storage areas for storing the products processed in the pickling lines, and then transported to storage areas for the cold rolling process, which is the downstream process. It is cold-rolled in the cold-rolling process after waiting for the production turn. The cold rolling process also has a plurality of cold rolling lines, and in many cases, one cold rolling line is designated according to the plate thickness and product type of the product to be produced, and the product is processed.

上記のような製造プロセスでは、生産性の観点から、上流工程及び下流工程の処理が滞りなく効率的に実施されることが求められている。生産効率は、上流工程及び下流工程の処理能力だけでなく、各工程に設けられる製品の置場の在庫状況や、工程間で製品を搬送する搬送装置の搬送能力等の影響も受ける。上流工程及び下流工程の効率的な生産を阻害するケースとして、例えば、上流工程の後面置場の最大貯蔵能力を超える製品貯蔵が要求されるような生産計画を実行すると、仕掛調整休止により処理を停止せざるを得ない事態が上流工程に発生する。また、例えば、下流工程の前面置場から下流工程で処理する製品が無くなるような生産計画を実行すると、材欠休止により処理を停止せざるを得ない事態が下流工程に発生する。 In the manufacturing process as described above, from the viewpoint of productivity, it is required that the upstream and downstream processes be performed smoothly and efficiently. Production efficiency is affected not only by the processing capacity of upstream and downstream processes, but also by the inventory status of product storage areas provided in each process, the transport capacity of transport devices that transport products between processes, and the like. As a case that hinders efficient production of upstream and downstream processes, for example, if a production plan is executed that requires product storage exceeding the maximum storage capacity of the rear storage area of the upstream process, processing will be stopped due to in-process adjustment suspension. A situation occurs in the upstream process that has to be done. Further, for example, if a production plan is executed in which there are no products to be processed in the downstream process from the front storage area of the downstream process, a situation occurs in the downstream process in which the processing must be stopped due to material shortage.

このような仕掛調整休止や材欠休止等の休止は、生産計画を作成した段階では発生しないものとされているが、実生産は計画通りにならない場合がある。従来は、生産実績や生産実績予測を踏まえて生産計画を都度再作成することで休止を回避している。 Such suspension due to in-process adjustment, shortage of materials, etc. is assumed not to occur at the stage of creating a production plan, but there are cases where actual production does not go as planned. Conventionally, suspensions are avoided by recreating production plans each time based on actual production results and production forecasts.

例えば特許文献1には、予め定められた生産計画に従って材料供給源と複数の工程と少なくとも一つの置場との間で被運搬材を運搬し、複数の工程において被運搬材を処理して、被運搬材から製品を生産する、被運搬材の物流管理を支援する物流管理支援装置が開示されている。特許文献1に記載の技術では、工程や置場の間の物流量に着目し、実際の物流量の予測値が物流量の上限を超える場合に警報を発して生産計画見直しを促したり、生産計画と生産実績との実態が乖離した場合には、今後生じる物流量の計画物流量からの変動を予測し、予測した変動に基づいて生産計画を見直して、置場間等の物流の滞りに起因する休止の発生を低減させたりする。 For example, in Patent Document 1, a material to be transported is transported between a material supply source, a plurality of processes, and at least one storage site according to a predetermined production plan, and the material to be transported is processed in the multiple processes, Disclosed is a physical distribution management support device for supporting physical distribution management of materials to be transported, which produces products from materials to be transported. In the technology described in Patent Document 1, attention is paid to the amount of distribution between processes and storage areas, and if the predicted value of the actual amount of distribution exceeds the upper limit of the amount of distribution, an alarm is issued to prompt a review of the production plan, or the production plan If there is a discrepancy between the actual situation and the actual production results, predict the fluctuations in the distribution volume that will occur in the future from the planned distribution volume, review the production plan based on the predicted fluctuations, and review the production plan based on the predicted fluctuations. Reduce the occurrence of pauses.

また、例えば特許文献2には、複数の作業工程を介して製品を生産する生産ラインの少なくとも一つの作業工程に設けられ、自作業工程の生産スケジュール、後作業工程の生産スケジュール及び自作業工程で生産された部品の現在の在庫量を記憶し、自作業工程で将来生産される部品の生産スケジュールを模擬実行した結果から生産スケジュールの修正案を作成し、当該修正案を模擬実行した結果、将来自作業工程で生産される部品が在庫切れになるかを判断し、その修正案を採用するか否かを表示する、生産計画修正システムが開示されている。特許文献2に記載の技術では、生産計画における上工程及び下工程の処理量を基に下工程の仕掛量を予測し、下工程の仕掛量が0にならないように生産計画の見直しを行うことで、下工程の材欠休止の発生を低減させている。 Further, for example, in Patent Document 2, provided in at least one work process of a production line that produces a product through a plurality of work processes, Memorize the current stock quantity of produced parts, create a revised plan for the production schedule from the results of simulated execution of the production schedule of parts to be produced in the future in the own work process, and simulate the revised plan. A production plan modification system is disclosed that determines whether a part to be produced in an in-house work process will be out of stock, and displays whether or not to adopt the modification plan. In the technique described in Patent Document 2, the amount of work in progress in the downstream process is predicted based on the amount of work in the upstream and downstream processes in the production plan, and the production plan is reviewed so that the amount of work in process in the downstream process does not become zero. This reduces the occurrence of material shortage stoppages in downstream processes.

特開2019-020875号公報JP 2019-020875 A 特開平6-143106号公報JP-A-6-143106

しかし、上記特許文献1は、生産計画の手法を開示しておらず、生産計画が実態を踏まえていない内容である場合には、生産計画と生産実績との実態の乖離が極めて大きくなる。この場合、生産実績の実態が判明した時点で生産計画の見直しや物流の修正を実施しても修正タイミングが遅すぎるため、休止の発生の頻度を低減することはできない。 However, Patent Literature 1 does not disclose a production planning method, and if the production plan is not based on the actual situation, the discrepancy between the production plan and actual production results becomes extremely large. In this case, even if the production plan is reviewed and the distribution is revised when the actual production results are clarified, the revision timing is too late, so the frequency of stoppages cannot be reduced.

また、上記特許文献2では、材欠休止の頻度は低減できると考えられるものの、置場の最大在庫能力を想定した予測も、上工程の後面置場から下工程の前面置場への輸送を踏まえた予測も実施していない。このため、上記特許文献2に記載の技術では、仕掛調整休止の抑制ができず、輸送能力の不足等により発生し得る休止の抑制ができない。 In addition, in Patent Document 2, although it is considered that the frequency of material shortages can be reduced, the prediction assuming the maximum inventory capacity of the storage area is also a prediction based on transportation from the rear storage area in the upstream process to the front storage area in the lower process. has not been implemented. For this reason, the technique described in Patent Document 2 cannot suppress suspension of work-in-progress adjustment, and suspension that may occur due to shortage of transportation capacity or the like cannot be suppressed.

そこで、本発明は、上記問題に鑑みてなされたものであり、本発明の目的とするところは、製品の製造プロセスにおいて、仕掛調整休止や材欠休止の発生頻度を減少させ、効率的な生産を実現することが可能な、製品の置場管理方法を提供することにある。 Therefore, the present invention has been made in view of the above problems, and the object of the present invention is to reduce the frequency of suspension of work-in-progress adjustment and shortage of materials in the manufacturing process of products, thereby achieving efficient production. To provide a product storage management method capable of realizing

上記課題を解決するために、本発明のある観点によれば、製造プロセスにおいて、生産スケジュールにしたがって、第1の工程にて処理された製品を貯蔵する第1の置場から、第2の工程にて処理される製品を貯蔵する第2の置場へ搬送する際の製品の置場管理方法であって、第1の工程は、複数の第1処理ラインを有し、第1の置場は、第1処理ラインそれぞれに対応して設けられた複数の第1貯蔵エリアを有し、第2の工程は、複数の第2処理ラインを有し、第2の置場は、第2処理ラインそれぞれに対応して設けられた複数の第2貯蔵エリアからなり、予測開始時点から第1の予測終了時点までの第1の予測期間の生産スケジュールについて、第1の予測期間に設定された複数の予測時点それぞれにおいて、第1の工程にて処理される製品数、第2の工程にて処理される製品数、及び、第1の置場及び第2の置場に貯蔵されている合計製品数に基づき、第1の工程または第2の工程での休止の発生有無を予測する第1の予測ステップと、第1の予測ステップにて休止が発生しないと予測された生産スケジュールについて、第1の予測期間よりも短い、予測開始時点から第2の予測終了時点までの第2の予測期間に設定された複数の予測時点それぞれにおいて、第1処理ラインそれぞれについて、第1処理ラインにて処理される製品数、当該第1処理ラインに対応する第1貯蔵エリアから各第2貯蔵エリアへ搬送される製品数、及び、予測開始時点での当該第1貯蔵エリアの製品在庫数に基づき、第1処理ラインでの休止の発生有無を予測し、第2処理ラインそれぞれについて、第2処理ラインにて処理される製品数、各第1貯蔵エリアから当該第2処理ラインに対応する第2貯蔵エリアへ搬送される製品数、及び、予測開始時点での当該第2貯蔵エリアの製品在庫数に基づき、第2処理ラインでの休止の発生有無を予測する、第2の予測ステップと、第1の予測ステップまたは第2の予測ステップにて休止が発生すると予測された場合に、生産スケジュールを調整する調整ステップと、を含む、製品の置場管理方法が提供される。 In order to solve the above problems, according to one aspect of the present invention, in the manufacturing process, according to the production schedule, from the first storage place that stores the product processed in the first step to the second step A product storage site management method when transporting products to be processed in a second storage site to a second storage site, wherein the first step includes a plurality of first processing lines, and the first storage site includes a first A plurality of first storage areas provided corresponding to each of the processing lines, the second step having a plurality of second processing lines, and a second storage area corresponding to each of the second processing lines. For the production schedule of the first forecast period from the forecast start time to the first forecast end time, at each of the plurality of forecast time points set in the first forecast period , based on the number of products processed in the first process, the number of products processed in the second process, and the total number of products stored in the first storage area and the second storage area, the first Shorter than the first prediction period for the first prediction step of predicting whether or not a pause will occur in the process or the second process, and the production schedule predicted that no pause will occur in the first prediction step, For each of the first processing lines, the number of products processed in the first processing line at each of the plurality of prediction times set in the second prediction period from the prediction start time to the second prediction end time, Occurrence of suspension in the first processing line based on the number of products transported from the first storage area corresponding to the processing line to each second storage area and the product inventory quantity in the first storage area at the time of prediction start Predicting the presence or absence of each second processing line, the number of products processed in the second processing line, the number of products transported from each first storage area to the second storage area corresponding to the second processing line, and , a second prediction step for predicting the presence or absence of pauses in the second processing line based on the number of products in stock in the second storage area at the time of prediction start; and the first prediction step or the second prediction step and an adjusting step of adjusting the production schedule when it is predicted that a stoppage will occur in the production site.

第1の予測ステップでは、第1の予測終了時点での、第1の工程にて処理される製品数から第2の工程にて処理される製品数を減じた値と、第1の置場及び第2の置場に貯蔵されている合計製品数とに基づき、第1の置場及び第2の置場の製品の過不足を算出し、第1の工程または第2の工程での休止の発生有無を予測してもよい。 In the first prediction step, the value obtained by subtracting the number of products processed in the second process from the number of products processed in the first process at the end of the first prediction, the first storage place and Based on the total number of products stored in the second storage area, the excess or deficiency of the products in the first storage area and the second storage area is calculated, and whether or not there is a pause in the first process or the second process You can predict.

第2の予測ステップでは、第1処理ラインそれぞれについて、処理される製品数から、当該第1処理ラインに対応する第1貯蔵エリアから各第2貯蔵エリアへ搬送される製品数を減じた値と、予測開始時点での当該第1貯蔵エリアの製品在庫数とに基づき、第1貯蔵エリアに貯蔵される製品の過不足を算出して、第1処理ラインでの休止の発生有無を予測し、第2処理ラインそれぞれについて、処理される製品数から、各第1貯蔵エリアから当該第2処理ラインに対応する第2貯蔵エリアへ搬送される製品数を減じた値と、予測開始時点での当該第2貯蔵エリアの製品在庫数とに基づき、第2貯蔵エリアに貯蔵される製品の過不足を算出して、第1処理ラインでの休止の発生有無を予測してもよい。 In a second prediction step, for each first processing line, the number of products to be processed minus the number of products to be conveyed from the first storage area corresponding to the first processing line to each second storage area; , based on the number of products in stock in the first storage area at the time of prediction start, calculate the excess or deficiency of the products stored in the first storage area, predict whether the first processing line will be suspended, For each second processing line, the number of products to be processed minus the number of products conveyed from each first storage area to the second storage area corresponding to the second processing line, and the value at the time of prediction start Based on the number of products in stock in the second storage area, the excess or deficiency of the products stored in the second storage area may be calculated to predict whether or not the first processing line will be suspended.

第1の予測ステップにて休止が発生すると予測された場合、調整ステップにて、生産スケジュールのうち、各工程の各処理ラインの製品単位の処理開始時間及び処理終了時間を表すスケジュール情報を変更し、その後、第1の予測ステップを再度実行してもよい。 When it is predicted that a pause will occur in the first prediction step, in the adjustment step, schedule information representing the processing start time and processing end time for each product in each processing line of each process is changed in the production schedule. , then the first prediction step may be performed again.

第2の予測ステップにて休止が発生すると予測された場合、調整ステップにて、第1の置場から第2の置場への製品の搬送能力を表す搬送能力情報を変更し、その後、第2の予測ステップを再度実行してもよい。 When it is predicted that a pause will occur in the second prediction step, in the adjustment step, the conveying capacity information representing the conveying capacity of the product from the first storage place to the second storage place is changed, and then the second The prediction step may be performed again.

また、製品の置場管理方法は、第1の予測ステップまたは第2の予測ステップにて休止が発生すると予測された場合に、予測結果をユーザに通知する通知ステップを含んでもよい。 Further, the product storage space management method may include a notification step of notifying the user of the prediction result when it is predicted that a pause will occur in the first prediction step or the second prediction step.

以上説明したように本発明によれば、製品の製造プロセスにおいて、仕掛調整休止や材欠休止の発生頻度を減少させ、効率的な生産を実現することができる。 As described above, according to the present invention, in the manufacturing process of a product, it is possible to reduce the occurrence frequency of in-process adjustment stoppages and material shortage stoppages, thereby realizing efficient production.

製造プロセスにおいて、上流工程から下流工程への製品の移動を説明する説明図である。FIG. 4 is an explanatory diagram illustrating the movement of a product from an upstream process to a downstream process in a manufacturing process; 本発明の一実施形態に係る置場管理装置を備える管理システムの一構成例を示す機能ブロック図である。1 is a functional block diagram showing one configuration example of a management system including a storage space management device according to one embodiment of the present invention; FIG. 第1の予測期間の生産スケジュールの一例を示す説明図である。FIG. 4 is an explanatory diagram showing an example of a production schedule for a first prediction period; FIG. 置場a、bの各貯蔵エリアa1~an、b1~bmの最大在庫数及び実績在庫数を含む在庫管理情報の一例を示す説明図である。FIG. 4 is an explanatory diagram showing an example of inventory management information including the maximum inventory quantity and the actual inventory quantity of storage areas a1 to an and b1 to bm of storage areas a and b; 搬送能力情報の一例を示す説明図である。FIG. 5 is an explanatory diagram showing an example of transport capability information; 同実施形態に係る製品の置場管理方法を示すフローチャートである。5 is a flow chart showing a product storage space management method according to the same embodiment. 第1の判定ステップにて仕掛調整休止が発生すると判定されたときの製品の在庫状況を示す説明図である。FIG. 10 is an explanatory diagram showing the inventory status of products when it is determined in the first determination step that the in-process adjustment suspension will occur; 第1の判定ステップにて欠材休止が発生すると判定されたときの製品の在庫状況を示す説明図である。FIG. 10 is an explanatory diagram showing the inventory status of products when it is determined in the first determination step that a shortage of products will be suspended; 生産スケジュールの調整の一例を示す説明図である。FIG. 4 is an explanatory diagram showing an example of adjusting a production schedule; 第2の予測期間の生産スケジュールの一例を示す説明図である。FIG. 10 is an explanatory diagram showing an example of a production schedule for a second prediction period; FIG. 置場aの各後面置場a1~anの製品の在庫状況の一例を示す説明図である。FIG. 3 is an explanatory diagram showing an example of the inventory status of products in rear storage areas a1 to an of the storage area a. 置場bの各前面置場b1~bmの製品の在庫状況の一例を示す説明図である。FIG. 4 is an explanatory diagram showing an example of the inventory status of products in front storage areas b1 to bm of the storage area b; 第2の判定ステップにて休止が発生すると判定されたときの製品の在庫状況を示す説明図である。FIG. 10 is an explanatory diagram showing the inventory status of products when it is determined in the second determination step that a pause will occur; 搬送能力情報の調整の一例を示す説明図である。FIG. 9 is an explanatory diagram showing an example of adjustment of conveying capability information; 製造プロセスの一例として、酸洗工程、冷延工程、焼鈍工程、めっき工程、梱包工程からなる鉄鋼製造プロセスを示す説明図である。BRIEF DESCRIPTION OF THE DRAWINGS It is explanatory drawing which shows the steel manufacturing process which consists of a pickling process, a cold-rolling process, an annealing process, a plating process, and a packing process as an example of a manufacturing process.

以下に添付図面を参照しながら、本発明の好適な実施の形態について詳細に説明する。なお、本明細書及び図面において、実質的に同一の機能構成を有する構成要素については、同一の符号を付することにより重複説明を省略する。 Preferred embodiments of the present invention will be described in detail below with reference to the accompanying drawings. In the present specification and drawings, constituent elements having substantially the same functional configuration are denoted by the same reference numerals, thereby omitting redundant description.

[1.プロセス概要]
まず、図1に基づいて、本発明の一実施形態に係る製品の製造プロセスの一例を説明する。図1は、製造プロセスにおいて、上流工程Aから下流工程Bへの製品の移動を説明する説明図である。
[1. Process overview]
First, based on FIG. 1, an example of a manufacturing process for a product according to one embodiment of the present invention will be described. FIG. 1 is an explanatory diagram illustrating movement of a product from an upstream process A to a downstream process B in a manufacturing process.

図1に示す製造プロセスでは、複数の上流処理ラインA1~Anを有する上流工程Aにて処理された製品を、トラック等の搬送装置10により、複数の下流処理ラインB1~Bmを有する下流工程Bへ搬送し、処理する。上流処理ラインA1~Anの出側には、後面置場a(単に「置場a」とも示す。)として、各上流処理ラインA1~Anにて処理された製品を貯蔵する後面貯蔵エリアa1~anが設けられている。同様に、下流処理ラインB1~Bmの入側には、前面置場b(単に「置場b」とも示す。)として、各下流処理ラインB1~Bmにて処理される製品を貯蔵する前面貯蔵エリアb1~bmが設けられている。なお、n、mは、2以上の自然数である。 In the manufacturing process shown in FIG. 1, products processed in an upstream process A having a plurality of upstream processing lines A1 to An are transferred to a downstream process B having a plurality of downstream processing lines B1 to Bm by a conveying device 10 such as a truck. transported to and processed. On the delivery side of the upstream processing lines A1 to An, there are rear storage areas a1 to an for storing the products processed by the respective upstream processing lines A1 to An as rear storage areas a (simply referred to as "storage areas a"). is provided. Similarly, on the inlet side of the downstream processing lines B1 to Bm, a front storage area b (also simply referred to as “storage location b”) is provided as a front storage area b1 for storing products to be processed in each of the downstream processing lines B1 to Bm. ~ bm are provided. Note that n and m are natural numbers of 2 or more.

例えば、製造プロセスが鉄鋼製造プロセスであり、上流工程Aを酸洗工程、下流工程Bを冷間圧延工程とする。この場合、酸洗工程の複数の酸洗ラインにて酸洗処理されたコイルCは、各酸洗ラインの出側に設けられた後面貯蔵エリアにそれぞれ貯蔵された後、搬送装置によって後面置場の後面貯蔵エリアから前面置場の前面貯蔵エリアへ搬送される。そして、前面貯蔵エリアに貯蔵されたコイルCは、各前面貯蔵エリアに対応した冷間圧延ラインにて冷間圧延される。 For example, the manufacturing process is a steelmaking process, the upstream process A is a pickling process, and the downstream process B is a cold rolling process. In this case, the coils C pickled in a plurality of pickling lines of the pickling process are stored in rear storage areas provided on the delivery side of each pickling line, and then transported to the rear storage area by the conveying device. It is transported from the rear storage area to the front storage area of the front storage area. Then, the coils C stored in the front storage areas are cold rolled in the cold rolling lines corresponding to the front storage areas.

このような製造プロセスにおいて、上流工程及び下流工程の処理が滞りなく効率的に実施されるためには、上流工程及び下流工程の処理能力に加え、各工程に設けられる製品の置場の在庫状況や、工程間で製品を搬送する搬送装置の搬送能力等を考慮した生産計画が必要である。一方で、上記をすべて詳細に考慮すると、生産計画の調整に時間を要することとなる。そこで、本実施形態に係る製品の置場管理方法により、上流工程及び下流工程の処理能力に加え、製品の置場の在庫状況及び搬送装置の搬送能力等を考慮して、効率的な処理を実現する生産計画を、調整負荷の増加も抑制しつつ立案する。以下、本実施形態に係る製品の置場管理方法について詳細に説明する。 In such a manufacturing process, in order for the processing of the upstream and downstream processes to be carried out smoothly and efficiently, in addition to the processing capacity of the upstream and downstream processes, the inventory status of the product storage areas provided in each process , production planning that takes into account the transport capacity of transport equipment that transports products between processes. On the other hand, if all the above are considered in detail, it will take time to adjust the production plan. Therefore, with the product storage space management method according to the present embodiment, in addition to the processing capacity of the upstream process and the downstream process, the inventory status of the product storage space, the transport capacity of the transport device, etc. are considered, and efficient processing is realized. Produce a production plan while suppressing an increase in adjustment load. The product storage management method according to the present embodiment will be described in detail below.

[2.製品の置場管理方法]
[2-1.システム構成]
まず、図2に基づいて、本実施形態に係る製品の置場管理方法を実行する置場管理装置120を備える管理システム100の構成について説明する。図2は、本実施形態に係る置場管理装置120を備える管理システム100の一構成例を示す機能ブロック図である。
[2. Product storage management method]
[2-1. System configuration]
First, based on FIG. 2, the configuration of a management system 100 including a storage space management device 120 that executes the product storage space management method according to the present embodiment will be described. FIG. 2 is a functional block diagram showing a configuration example of the management system 100 including the storage space management device 120 according to this embodiment.

本実施形態に係る管理システム100は、製造プロセスにおいて、第1の工程にて処理された製品を貯蔵する第1の置場から、第2の工程にて処理される製品を貯蔵する第2の置場へ搬送する工程で、第1の置場及び第2の置場の製品の在庫状況を管理するシステムである。具体的には、管理システム100は、第1の工程及び第2の工程で製品を処理するにあたり、生産計画に基づき予め生成された生産スケジュールを実施した場合に、製品の過不足が生じて生産性が低下する可能性の有無を判定し、生産性が低下する場合には生産スケジュールを再調整し、生産効率の低下を抑制する。以下では、図1に示した製造プロセスにおける製品の在庫状況を管理する場合について説明する。図1において、上流工程Aは第1の工程、下流工程Bは第2の工程、後面置場aは第1の置場、前面置場bは第2の置場、コイルCは製品に対応する。また、上流工程Aの複数の上流処理ラインA1~Anは第1処理ライン、下流工程Bの複数の下流処理ラインB1~Bmは第2処理ライン、前面貯蔵エリアa1~anは第1貯蔵エリア、後面貯蔵エリアb1~bmは第2貯蔵エリアに対応する。 In the manufacturing process, the management system 100 according to the present embodiment moves from a first storage area for storing products processed in a first process to a second storage area for storing products processed in a second process. It is a system for managing the inventory status of the products in the first and second storage areas in the process of transporting them to. Specifically, when the management system 100 executes the production schedule generated in advance based on the production plan in processing the products in the first process and the second process, the excess or deficiency of the products occurs and the production is interrupted. If there is a possibility that productivity will decline, the production schedule will be readjusted to suppress the decline in production efficiency. A case of managing the product inventory status in the manufacturing process shown in FIG. 1 will be described below. In FIG. 1, the upstream process A corresponds to the first process, the downstream process B to the second process, the rear storage space a to the first storage space, the front storage space b to the second storage space, and the coil C to the product. Further, the plurality of upstream processing lines A1 to An of the upstream process A are the first processing lines, the plurality of downstream processing lines B1 to Bm of the downstream process B are the second processing lines, the front storage areas a1 to an are the first storage areas, The rear storage areas b1-bm correspond to the second storage areas.

管理システム100は、図2に示すように、入力装置110と、置場管理装置120と、出力装置130と、生産スケジュール記憶部140とを有して構成される。 The management system 100 includes an input device 110, a storage site management device 120, an output device 130, and a production schedule storage section 140, as shown in FIG.

入力装置110は、ユーザが情報を入力するための装置であって、例えばマウス、キーボード、タッチパネル、ボタン、スイッチ及びレバー等の、ユーザが情報を入力するために操作する装置である。入力装置110から入力された情報は、置場管理装置120へ出力される。例えば、ユーザは、入力装置110を用いて、生産計画に基づき予め生成された生産スケジュールについて、置場a、bにおける製品の在庫状況を予測する期間を入力する。入力装置110は、入力された情報を置場管理装置120へ出力する。 The input device 110 is a device for a user to input information, such as a mouse, a keyboard, a touch panel, a button, a switch, and a lever, and is operated by the user to input information. Information input from the input device 110 is output to the storage site management device 120 . For example, the user uses the input device 110 to input a period for predicting the inventory status of products at the storage sites a and b with respect to the production schedule generated in advance based on the production plan. The input device 110 outputs the input information to the storage site management device 120 .

置場管理装置120は、生産計画に基づき予め生成された生産スケジュールを実施した場合に、製品の過不足が生じて生産性が低下する可能性の有無を判定し、判定結果に基づいて生産スケジュールを調整する。置場管理装置120は、第1の判定部121と、第2の判定部123と、調整処理部125とを有する。 The storage space management device 120 determines whether or not there is a possibility that an excess or deficiency of products will occur and productivity will decrease when a production schedule generated in advance based on the production plan is executed, and based on the determination result, the production schedule will be adjusted. adjust. The storage space management device 120 has a first determination section 121 , a second determination section 123 and an adjustment processing section 125 .

第1の判定部121は、後述の生産スケジュール記憶部140に記録されている第1の予測期間の生産スケジュールに基づき、製品の移動状況及び貯蔵状況を大局的に予測する。第1の判定部121は、第1の予測期間に設定された複数の予測時点それぞれにおいて、上流工程A(第1の工程)にて処理される製品数、下流工程B(第2の工程)にて処理される製品数、及び、後面置場a(第1の置場)及び前面置場b(第2の置場)に貯蔵されている合計製品数に基づき、置場a、bにおける製品の過不足を判定する。第1の予測期間は、予測開始時点から第1の予測終了時点までの期間であり、例えば2~3週間程度に設定される。 The first determination unit 121 broadly predicts the product movement and storage conditions based on the production schedule for the first prediction period recorded in the production schedule storage unit 140, which will be described later. The first determination unit 121 determines the number of products processed in the upstream process A (first process), the number of products processed in the downstream process B (second process), and the Based on the number of products processed in and the total number of products stored in the rear storage area a (first storage area) and the front storage area b (second storage area), excess or deficiency of products in storage areas a and b judge. The first prediction period is a period from the start of prediction to the end of the first prediction, and is set, for example, to about two to three weeks.

上流工程A及び下流工程Bは複数の処理ラインをそれぞれ有しており、置場a、bも複数の処理ラインにそれぞれ対応した複数の貯蔵エリアを有する。このため、置場a、bにおける製品の過不足を正しく判定するには、処理ライン単位、貯蔵エリア単位で詳細に予測することが望ましい。しかし、第1の予測期間すべてにおいて詳細に予測すると、計算負荷が高くなる。そこで、第1の判定部121は、複数の処理ライン、複数の貯蔵エリアをそれぞれ1つのまとまりとみなした工程単位、置場単位で製品の在庫状況を予測する。なお、第1の判定部121での予測処理についての詳細は後述する。 The upstream process A and the downstream process B each have a plurality of processing lines, and the storage sites a and b also have a plurality of storage areas respectively corresponding to the plurality of processing lines. For this reason, it is desirable to make detailed predictions for each processing line and each storage area in order to correctly determine the excess or deficiency of products in the storage areas a and b. However, a detailed prediction over the entire first prediction period results in a high computational load. Therefore, the first determination unit 121 predicts the inventory status of products in units of processes and in units of storage areas, each of which considers a plurality of processing lines and a plurality of storage areas as one unit. Details of the prediction processing in the first determination unit 121 will be described later.

第1の判定部121は、置場a、bにおいて製品の過不足が発生すると判断した場合には、出力装置130に対し、製品の過不足の発生をユーザに通知するよう指示する。また、第1の判定部121は、調整処理部125に生産スケジュールの調整を指示する。そして、第1の判定部121は、調整後の生産スケジュールに基づき、製品の在庫状況を再度予測する。置場a、bにおいて製品の過不足は発生しないと判断した場合には、第1の判定部121は、この時点での生産スケジュールを設定候補とし、第2の判定部123に対して予測開始指示を行う。 When the first determination unit 121 determines that there is an excess or deficiency of products in the storage areas a and b, the first determination unit 121 instructs the output device 130 to notify the user of the occurrence of the excess or deficiency of the products. Also, the first determination unit 121 instructs the adjustment processing unit 125 to adjust the production schedule. Then, the first determination unit 121 predicts the product inventory status again based on the adjusted production schedule. If it is determined that there will be no excess or shortage of products in the storage areas a and b, the first determination unit 121 sets the current production schedule as a setting candidate, and instructs the second determination unit 123 to start prediction. I do.

第2の判定部123は、第1の判定部121にて調整された生産スケジュールに基づいて、第2の予測期間における各貯蔵エリアでの製品の過不足を判定する。第2の予測期間は、予測開始時点から第2の予測終了時点までの期間であり、第1の予測期間よりも短く設定される。第2の予測期間を長く設定しすぎると生産スケジュールの調整負荷が増加する一方、短く設定しすぎると予測精度が低下する。このため、第2の予測期間は、過去の実績に基づき設定されたり、シミュレーションにより適切な期間を求めて設定されたりする。第2の予測期間は、例えば2、3日程度に設定される。 Based on the production schedule adjusted by the first determination unit 121, the second determination unit 123 determines excess or deficiency of products in each storage area during the second prediction period. The second prediction period is a period from the prediction start point to the second prediction end point, and is set shorter than the first prediction period. If the second prediction period is set too long, the production schedule adjustment load will increase, while if it is set too short, the prediction accuracy will decrease. Therefore, the second prediction period is set based on past results, or is set by obtaining an appropriate period through simulation. The second prediction period is set, for example, to about two or three days.

具体的には、第2の判定部123は、上流工程Aの上流処理ラインA1~Anそれぞれについて、上流処理ラインAa~Anにて処理される製品数、当該上流処理ラインA1~Anに対応する後面貯蔵エリアa1~anから各前面貯蔵エリアb1~bmへ搬送される製品数、及び、予測開始時点での当該後面貯蔵エリアa1~anの製品在庫数に基づき、第1貯蔵エリアa1~anに貯蔵される製品の過不足を判定する。また、第2の判定部123は、下流工程Bの下流処理ラインB1~Bmそれぞれについて、下流処理ラインB1~Bmにて処理される製品数、各後面貯蔵エリアa1~anから当該下流処理ラインB1~Bmに対応する前面貯蔵エリアb1~bmへ搬送される製品数、及び、予測開始時点での当該前面貯蔵エリアb1~bmの製品在庫数に基づき、前面貯蔵エリアb1~bmに貯蔵される製品の過不足を判定する。なお、第2の判定部123での予測処理についての詳細は後述する。 Specifically, the second determination unit 123 determines, for each of the upstream processing lines A1 to An of the upstream process A, the number of products processed in the upstream processing lines Aa to An, and the number of products corresponding to the upstream processing lines A1 to An. Based on the number of products transported from the rear storage areas a1 to an to each of the front storage areas b1 to bm, and the number of products in stock in the rear storage areas a1 to an at the time of prediction start, to the first storage areas a1 to an Determining excess or deficiency of stored products. In addition, the second determination unit 123 determines the number of products to be processed in the downstream processing lines B1 to Bm for each of the downstream processing lines B1 to Bm of the downstream process B, Products to be stored in the front storage areas b1 to bm based on the number of products transported to the front storage areas b1 to bm corresponding to ~Bm and the number of products in stock in the front storage areas b1 to bm at the time of prediction start Judging the excess or deficiency of Details of the prediction processing in the second determination unit 123 will be described later.

このように、第2の判定部123では、第1の予測期間より短い期間について、貯蔵エリア単位で詳細に製品の過不足を判定する。第2の判定部123は、いずれかの貯蔵エリアa1~an、b1~bmにおいて製品の過不足が発生すると判断した場合には、出力装置130に対し、製品の過不足の発生をユーザに通知するよう指示する。また、第2の判定部123は、調整処理部125に生産スケジュールの調整を指示する。そして、第2の判定部123は、調整後の生産スケジュールに基づき、製品の在庫状況を再度予測する。一方、すべての貯蔵エリアa1~an、b1~bmで製品の過不足は発生しないと判定した場合には、第2の判定部123は、この時点での生産スケジュールにて生産を実施することを決定する。 In this way, the second determination unit 123 determines in detail the product excess/deficiency for each storage area for a period shorter than the first prediction period. When the second determination unit 123 determines that an excess or deficiency of products occurs in any of the storage areas a1 to an or b1 to bm, the output device 130 notifies the user of the occurrence of the excess or deficiency of the products. instruct to do so. The second determination unit 123 also instructs the adjustment processing unit 125 to adjust the production schedule. Then, the second determination unit 123 predicts the product inventory status again based on the adjusted production schedule. On the other hand, when it is determined that there is no excess or shortage of products in all of the storage areas a1 to an and b1 to bm, the second determination unit 123 decides to carry out production according to the production schedule at this time. decide.

調整処理部125は、置場に製品の過不足が発生すると予測された場合に、製品の過不足が生じなくなるように生産スケジュールを調整する。置場に製品の過不足が発生するケースとして、例えば、上流工程の後面置場の最大貯蔵能力を超える製品が後面置場に貯蔵される場合や、下流工程の前面置場から下流工程で処理する製品が無くなる場合等がある。調整処理部125は、それぞれのケースに応じて、製品の処理時期を変更したり、処理対象の製品の品種を変更したり、製品の搬送能力を変更したりすることにより、生産スケジュールを調整する。調整処理部125による生産スケジュール調整についての詳細は後述する。調整処理部125は、第1の判定部121及び第2の判定部123の指示を受けて生産スケジュールを調整し、調整後の生産スケジュールを第1の判定部121及び第2の判定部123に出力する。 The adjustment processing unit 125 adjusts the production schedule so that the excess or deficiency of products will not occur when it is predicted that there will be an excess or deficiency of products in the storage area. Cases in which excess or deficiency of products occurs in the storage area include, for example, cases in which products exceeding the maximum storage capacity of the rear storage area in the upstream process are stored in the rear storage area, or there are no products to be processed in the downstream process from the front storage area in the downstream process. There are cases, etc. The adjustment processing unit 125 adjusts the production schedule by changing the processing time of the product, changing the type of product to be processed, and changing the carrying capacity of the product according to each case. . The details of the production schedule adjustment by the adjustment processing unit 125 will be described later. The adjustment processing unit 125 adjusts the production schedule in response to instructions from the first determination unit 121 and the second determination unit 123, and transmits the adjusted production schedule to the first determination unit 121 and the second determination unit 123. Output.

出力装置130は、置場管理装置120の第1の判定部121及び第2の判定部123の判定結果を受けて、置場における製品の過不足の発生をユーザに通知する。出力装置130は、例えば、CRTディスプレイ装置、液晶ディスプレイ装置、プラズマディスプレイ装置、ELディスプレイ装置等の情報をユーザに視覚的に通知する表示装置であってもよく、プリンターや移動通信端末等であってもよい。あるいは、出力装置130は、スピーカー等のように、情報を音声として出力する音声出力装置であってもよい。 The output device 130 receives the determination results of the first determination unit 121 and the second determination unit 123 of the storage space management device 120 and notifies the user of the occurrence of excess or deficiency of products in the storage space. The output device 130 may be, for example, a CRT display device, a liquid crystal display device, a plasma display device, an EL display device, or a display device that visually notifies the user of information, or may be a printer, a mobile communication terminal, or the like. good too. Alternatively, the output device 130 may be an audio output device that outputs information as audio, such as a speaker.

生産スケジュール記憶部140は、生産計画に基づき生成された生産スケジュールを記憶する。生産スケジュールは、当初、生産計画に基づき予め設定されており、生産スケジュール記憶部140に記録される。その後、所定のタイミングで置場管理装置120による生産スケジュールの見直しが行われ、調整処理部125により再調整された生産スケジュールが、第2の判定部123によりすべての貯蔵エリアa1~an、b1~bmで製品の過不足は発生しないと判定されると、生産スケジュール記憶部140の生産スケジュールは調整後の生産スケジュールに更新される。また、生産スケジュール記憶部140は、上流工程Aから下流工程Bへ製品を搬送する搬送能力情報も記憶してもよい。 The production schedule storage unit 140 stores a production schedule generated based on the production plan. The production schedule is initially preset based on the production plan and recorded in the production schedule storage unit 140 . Thereafter, the production schedule is reviewed by the storage area management device 120 at a predetermined timing, and the production schedule readjusted by the adjustment processing unit 125 is determined by the second determination unit 123 for all the storage areas a1 to an and b1 to bm. , the production schedule in the production schedule storage unit 140 is updated to the adjusted production schedule. In addition, the production schedule storage unit 140 may also store information on the transport capability for transporting products from the upstream process A to the downstream process B. FIG.

以上、本実施形態に係る管理システム100の一構成例について説明した。 A configuration example of the management system 100 according to the present embodiment has been described above.

なお、管理システム100の置場管理装置120は、例えばCPU(Central Processing Unit)やDSP(Digital Signal Processor)等の各種のプロセッサによって構成され、置場管理装置120の機能は、当該プロセッサが所定のプログラムにしたがって動作されることにより実現され得る。なお、置場管理装置120は、上述のように各種のプロセッサであってもよいし、プロセッサとメモリ等の記憶装置とが一体的に構成されたいわゆるマイコンであってもよい。あるいは、置場管理装置120は、PC(Personal Computer)やサーバ等の各種の情報処理装置であってもよい。 The storage management device 120 of the management system 100 is composed of various processors such as a CPU (Central Processing Unit) and a DSP (Digital Signal Processor). Therefore, it can be realized by being operated. The storage space management device 120 may be various processors as described above, or may be a so-called microcomputer in which a processor and a storage device such as a memory are integrated. Alternatively, the storage space management device 120 may be various information processing devices such as a PC (Personal Computer) and a server.

また、生産スケジュール記憶部140は、RAM(Random Access Memory)等のメモリであってもよく、データ格納用のストレージ装置であってもよい。RAM等のメモリは、例えば置場管理装置120に内蔵されてもよい。ストレージ装置は、例えば、HDD(Hard Disk Drive)等の磁気記憶デバイス、半導体記憶デバイス、光記憶デバイスまたは光磁気記憶デバイス等により構成可能である。 Moreover, the production schedule storage unit 140 may be a memory such as a RAM (Random Access Memory) or a storage device for storing data. A memory such as a RAM may be built in the storage site management device 120, for example. The storage device can be composed of, for example, a magnetic storage device such as a HDD (Hard Disk Drive), a semiconductor storage device, an optical storage device, a magneto-optical storage device, or the like.

[2-2.置場管理処理]
次に、図3~図14に基づいて、本実施形態に係る製品の置場管理方法を説明する。図3は、第1の予測期間の生産スケジュールの一例を示す説明図である。図4は、置場a、bの各貯蔵エリアa1~an、b1~bmの最大在庫数及び実績在庫数を含む在庫管理情報の一例を示す説明図である。図5は、搬送能力情報の一例を示す説明図である。図6は、本実施形態に係る製品の置場管理方法を示すフローチャートである。図7は、第1の判定ステップにて仕掛調整休止が発生すると判定されたときの製品の在庫状況を示す説明図である。図8は、第1の判定ステップにて欠材休止が発生すると判定されたときの製品の在庫状況を示す説明図である。図9は、生産スケジュールの調整の一例を示す説明図である。図10は、第2の予測期間の生産スケジュールの一例を示す説明図である。図11は、置場aの各後面置場a1~anの製品の在庫状況の一例を示す説明図である。図12は、置場bの各前面置場b1~bmの製品の在庫状況の一例を示す説明図である。図13は、第2の判定ステップにて休止が発生すると判定されたときの製品の在庫状況を示す説明図である。図14は、搬送能力情報の調整の一例を示す説明図である。
[2-2. Storage management processing]
Next, a product storage management method according to the present embodiment will be described with reference to FIGS. 3 to 14. FIG. FIG. 3 is an explanatory diagram showing an example of a production schedule for the first prediction period. FIG. 4 is an explanatory diagram showing an example of inventory management information including the maximum inventory quantity and the actual inventory quantity of each of the storage areas a1 to an and b1 to bm of the storage areas a and b. FIG. 5 is an explanatory diagram showing an example of transport capability information. FIG. 6 is a flow chart showing the product storage management method according to the present embodiment. FIG. 7 is an explanatory diagram showing the inventory status of products when it is determined in the first determination step that the in-process adjustment suspension will occur. FIG. 8 is an explanatory diagram showing the inventory status of products when it is determined in the first determination step that there will be a shortage of products. FIG. 9 is an explanatory diagram showing an example of production schedule adjustment. FIG. 10 is an explanatory diagram showing an example of the production schedule for the second prediction period. FIG. 11 is an explanatory diagram showing an example of the inventory status of products in the rear storage areas a1 to an of the storage area a. FIG. 12 is an explanatory diagram showing an example of the inventory status of products in the front storage areas b1 to bm of the storage area b. FIG. 13 is an explanatory diagram showing the inventory status of products when it is determined in the second determination step that a pause will occur. FIG. 14 is an explanatory diagram showing an example of adjustment of conveying capability information.

本実施形態に係る製品の置場管理方法では、置場a、bの在庫数予測と各貯蔵エリアの在庫数予測との2段階で在庫予測し、ある程度先の生産スケジュールの調整を踏まえて、直近の物流状況を考慮した生産スケジュールの調整を行う。これにより、従来と比べて仕掛調整休止や材欠休止の発生頻度を減少させる。 In the product storage management method according to the present embodiment, the inventory is predicted in two steps, that is, the inventory quantity prediction for the storage locations a and b and the inventory quantity prediction for each storage area. Adjust the production schedule considering the logistics situation. As a result, the frequency of stoppages for work-in-progress adjustment and material shortages can be reduced compared to the conventional method.

まず、本実施形態に係る製品の置場管理方法を実行するにあたり、生産スケジュール記憶部140には、生産スケジュールが記憶されている。生産スケジュールは、顧客からの受注に基づき計画され、各工程の各処理ラインについて製品単位の処理開始時間及び処理終了時間を示したスケジュール情報と各置場の各貯蔵エリアの最大在庫数及び実績在庫数を示した在庫管理情報とを含んでいる。 First, a production schedule is stored in the production schedule storage unit 140 in executing the product storage space management method according to the present embodiment. The production schedule is planned based on the order received from the customer, and schedule information indicating the processing start time and processing end time for each product unit for each processing line of each process, and the maximum inventory quantity and actual inventory quantity in each storage area of each storage area. and inventory control information indicating

スケジュール情報は、例えば図3に示すように、上流工程Aの各上流処理ラインA1~Anそれぞれの、処理するコイルの製造番号とその処理開始時間及び処理終了時間を含んでいる。下流工程Bも同様に、下流工程Bの各下流処理ラインB1~Bmそれぞれの、処理するコイルの製造番号とその処理開始時間及び処理終了時間を含んでいる。図3では、スケジュール情報を時系列に並べて表している。図3を見ると、スケジュール情報から、例えば上流処理ラインA1で処理するコイル1001は、下流処理ラインB2で処理し、上流処理ラインA1で処理するコイル1002は、下流処理ラインB1で処理する、といったように、上流工程Aから下流工程Bへの移動先を特定できる。 For example, as shown in FIG. 3, the schedule information includes the serial numbers of the coils to be processed and their processing start and end times for each of the upstream processing lines A1 to An of the upstream process A. As shown in FIG. Similarly, the downstream process B includes the manufacturing number of the coil to be processed and the process start time and process end time of each of the downstream process lines B1 to Bm of the downstream process B. FIG. In FIG. 3, the schedule information is arranged in chronological order. Looking at FIG. 3, from the schedule information, for example, the coil 1001 processed in the upstream processing line A1 is processed in the downstream processing line B2, and the coil 1002 processed in the upstream processing line A1 is processed in the downstream processing line B1. Thus, the destination of movement from the upstream process A to the downstream process B can be specified.

また、在庫管理情報は、例えば図4に示すように、置場a、bの各貯蔵エリアai、bjの最大在庫数及び実績在庫数を含む。最大在庫数は、貯蔵可能な最大の製品数を表す。実績在庫数は、ある時点において貯蔵されている製品数を表す。以下、各置場a、b及び各貯蔵エリアai、bjの最大在庫数及び実績在庫数を以下のように表す。なお、i、jは自然数であり、i=1~n、j=1~mとする。 The inventory management information includes, for example, the maximum inventory quantity and the actual inventory quantity of each of the storage areas ai and bj of the storage sites a and b, as shown in FIG. Maximum stock quantity represents the maximum number of products that can be stocked. The actual inventory count represents the number of products in stock at a certain point in time. Hereinafter, the maximum inventory quantity and the actual inventory quantity of each storage area a, b and each storage area ai, bj are expressed as follows. Note that i and j are natural numbers, i=1 to n and j=1 to m.

Nai:貯蔵エリアaiの最大在庫数
Nbj:貯蔵エリアbjの最大在庫数
N0ai:貯蔵エリアaiの予測開始時点(T0)での実績在庫数
N0bj:貯蔵エリアbjの予測開始時点(T0)での実績在庫数
ΣNai:置場aの最大在庫数
ΣNbj:置場bの最大在庫数
ΣN0ai:置場aの予測開始時点(T0)での実績在庫数
ΣN0bj:置場bの予測開始時点(T0)での実績在庫数
Nab:置場a、bの合計最大在庫数(=ΣNai+ΣNbj)
N0ab:置場a、bの予測開始時点(T0)での合計実績在庫数
(=ΣN0ai+ΣN0bj)
Nai: Maximum inventory quantity in storage area ai Nbj: Maximum inventory quantity in storage area bj N0ai: Actual inventory quantity at the forecast start time (T0) for storage area ai N0bj: Actual performance at the forecast start time (T0) for storage area bj Inventory quantity ΣNai: Maximum inventory quantity of storage location a ΣNbj: Maximum inventory quantity of storage location b ΣN0ai: Actual inventory quantity of storage location a at the forecast start time (T0) ΣN0bj: Actual inventory quantity of storage location b at the forecast start time (T0) Nab: total maximum number of stocks of storage areas a and b (= ΣNai + ΣNbj)
N0ab: Total actual inventory quantity at the forecast start point (T0) of storage sites a and b
(= ΣN0ai + ΣN0bj)

例えば、図4に示す例では、貯蔵エリアa1のコイルの最大在庫数Na1は100個、予測開始時点(T0)での実績在庫数N0a1は80個である。貯蔵エリアb1のコイルの最大在庫数Nb1は70個、予測開始時点(T0)での実績在庫数N0b1は50個である。置場aの最大在庫数ΣNaiは800個、予測開始時点(T0)での実績在庫数は700個である。置場bの最大在庫数ΣNbiは700個、予測開始時点(T0)での実績在庫数は650個である。そして、置場a、bの合計最大在庫数Nabは1500個、予測開始時点(T0)での合計実績在庫数N0abは1350個である。 For example, in the example shown in FIG. 4, the maximum inventory quantity Na1 of coils in the storage area a1 is 100, and the actual inventory quantity N0a1 at the prediction start time (T0) is 80 pieces. The maximum inventory quantity Nb1 of coils in the storage area b1 is 70, and the actual inventory quantity N0b1 at the prediction start point (T0) is 50 coils. The maximum inventory quantity ΣNai of the place a is 800, and the actual inventory quantity at the prediction start point (T0) is 700 pieces. The maximum inventory quantity ΣNbi of the place b is 700, and the actual inventory quantity at the prediction start point (T0) is 650 pieces. The total maximum inventory quantity Nab of the locations a and b is 1,500, and the total actual inventory quantity N0ab at the prediction start time (T0) is 1,350.

さらに、生産スケジュール記憶部140は、上流工程Aから下流工程Bへ製品を搬送する搬送能力情報を生産スケジュールとして記憶している。搬送能力情報は、例えば図5に示すように、後面貯蔵エリアaiから前面貯蔵エリアbjへの1時間当たりの標準運搬量Kaibj(個/h)により表すことができる。例えば、図5に示す例では、後面貯蔵エリアa1から前面貯蔵エリアb1への標準運搬量Ka1b1は2個/hであり、後面貯蔵エリアa2から前面貯蔵エリアb2への標準運搬量Ka2b2は3個/hである。搬送能力情報は、搬送装置10の搬送能力や上流工程A及び下流工程Bの処理能力等を考慮して、予め設定されている。なお、搬送能力情報は、後述するように、生産スケジュールの見直しが必要な場合に変更することも可能である。 Furthermore, the production schedule storage unit 140 stores information on the transfer capability for transferring products from the upstream process A to the downstream process B as a production schedule. For example, as shown in FIG. 5, the transport capacity information can be represented by the standard transport amount Kaibj (pieces/h) per hour from the rear storage area ai to the front storage area bj. For example, in the example shown in FIG. 5, the standard transportation amount Ka1b1 from the rear storage area a1 to the front storage area b1 is 2 pieces/h, and the standard transportation amount Ka2b2 from the rear storage area a2 to the front storage area b2 is 3 pieces. /h. The carrying capacity information is set in advance in consideration of the carrying capacity of the carrier device 10, the processing capacity of the upstream process A and the downstream process B, and the like. As will be described later, the transport capacity information can be changed when the production schedule needs to be reviewed.

(S100:第1の予測ステップ)
本実施形態に係る製品の置場管理方法は、図6に示すように、置場管理装置120の第1の判定部121により、第1の予測期間において、置場単位で、製品の在庫数を予測し、製品の過不足による休止の発生有無が予測される(S100)。第1の予測ステップでは、現時点での製造状況から、現在の生産スケジュールに基づき製品の製造を続けた場合に、休止が発生する可能性を大局的に予測する。すなわち、第1の予測ステップでは、予測開始時点から第1の予測終了時点までの第1の予測期間に設定された複数の予測時点それぞれにおいて、上流工程Aにて処理される製品数、下流工程Bにて処理される製品数、及び、置場a、bに貯蔵されている合計製品数に基づき、置場a、bにおける製品の過不足を算出し、休止が発生する可能性を予測する。
(S100: first prediction step)
In the product storage management method according to the present embodiment, as shown in FIG. 6, the first determination unit 121 of the storage management device 120 predicts the number of products in stock for each storage location in the first prediction period. , the presence or absence of suspension due to excess or shortage of products is predicted (S100). In the first prediction step, from the current manufacturing situation, a global prediction is made of the possibility of suspension if the product continues to be manufactured based on the current production schedule. That is, in the first prediction step, at each of a plurality of prediction points set in the first prediction period from the start of prediction to the end of the first prediction, the number of products processed in the upstream process A, Based on the number of products processed in B and the total number of products stored in storage locations a and b, the excess or deficiency of products in storage locations a and b is calculated, and the possibility of suspension occurring is predicted.

第1の予測ステップを具体的に説明すると、まず、第1の判定部121は、図3に示すように、第1の予測期間T1をp個に分割し、複数の予測時点T1_u(u=1~p、pは2以上の自然数。T1_p=T1)を設定する。ここで、予測開始時T0及び第1の予測期間T1は、予め設定されていてもよく、ユーザが入力装置110を用いて指定してもよい。図3では、予測開始時T0は現時点からk日後の午前0時に設定され、第1の予測期間T1は15日に設定されている。また、第1の予測期間T1を分割する間隔は、適宜設定可能であり、例えば図3では1時間に設定されている。つまり、図3に示す例では、第1の予測期間T1を360分割している。 Specifically describing the first prediction step, first, as shown in FIG. 1 to p, where p is a natural number equal to or greater than 2. Set T1_p=T1). Here, the prediction start time T0 and the first prediction period T1 may be set in advance, or may be designated by the user using the input device 110 . In FIG. 3, the prediction start time T0 is set to midnight k days after the current time, and the first prediction period T1 is set to 15 days. Also, the interval at which the first prediction period T1 is divided can be set as appropriate, and is set to one hour in FIG. 3, for example. That is, in the example shown in FIG. 3, the first prediction period T1 is divided into 360.

第1の判定部121は、予測開始時T0から各予測時点T1_uに到達した時点での、上流工程A全体で処理される製品数から下流工程B全体で処理される製品数を減じた値(以下、「処理差分数」ともいう。)を算出する。また、第1の判定部121は、置場a、bの予測開始時点(T0)での合計実績在庫数N0abを算出する。そして、第1の判定部121は、処理差分数と合計実績在庫数N0abとの和を、合計在庫数として、各予測時点T1_uについて算出する。合計在庫数は、休止発生の可能性の有無を判定するために用いられる。 The first determination unit 121 calculates a value ( Hereinafter, it is also referred to as “the number of processing differences”.) is calculated. In addition, the first determination unit 121 calculates the total actual inventory quantity N0ab at the prediction start point (T0) of the storage sites a and b. Then, the first determination unit 121 calculates the sum of the processing difference number and the total actual inventory quantity N0ab as the total inventory quantity for each prediction time point T1_u. The total number of inventory is used to determine whether there is a possibility of suspension.

各予測時点T1_uにおける合計在庫数が、置場a、bの合計最大在庫数Nabを超過する場合は、製品を置場a、bに貯蔵できず、仕掛調整休止が発生する可能性がある。例えば、図7に示すケースでは、予測時点T1_180に到達した時点で、上流工程A全体で処理される製品数は15000個、下流工程B全体で処理される製品数は14700個と見積もられ、処理差分数は300個となる。合計実績在庫数N0abは1350個であることから、このときの合計在庫数は1650個となり、合計最大在庫数Nab1500個を超えている。このような場合には、仕掛調整休止が発生する可能性があると判定される。 If the total inventory quantity at each prediction time T1_u exceeds the total maximum inventory quantity Nab of the storage sites a and b, there is a possibility that the product cannot be stored in the storage sites a and b, resulting in work-in-progress adjustment suspension. For example, in the case shown in FIG. 7, the number of products processed in the entire upstream process A is estimated to be 15000, and the number of products processed in the entire downstream process B is estimated to be 14700 when the prediction time T1_180 is reached. The number of processed differences is 300. Since the total actual stock quantity N0ab is 1350 pieces, the total stock quantity at this time is 1650 pieces, which exceeds the total maximum stock quantity Nab of 1500 pieces. In such a case, it is determined that there is a possibility that work-in-progress adjustment suspension will occur.

また、各予測時点T1_uにおける処理差分数が0以下となる場合は、製品が不足し、材欠休止が発生する可能性がある。例えば、図8に示すケースでは、予測時点T1_80に到達した時点で、上流工程A全体で処理される製品数は600個、下流工程B全体で処理される製品数は970個と見積もられ、処理差分数は-20個となる。このような場合には、下流工程Bでの処理能力に対して前面置場bの製品の在庫数が不足しており、材欠休止が発生する可能性があると判定される。 Further, when the number of processing differences at each predicted time T1_u is 0 or less, there is a possibility that products will be in short supply and material shortage will occur. For example, in the case shown in FIG. 8, the number of products processed in the entire upstream process A is estimated to be 600 and the number of products processed in the entire downstream process B is estimated to be 970 when the prediction time T1_80 is reached. The number of processed differences is -20. In such a case, it is determined that the number of products in the front storage space b is insufficient for the processing capacity of the downstream process B, and there is a possibility that a material shortage will occur.

このように、第1の判定部121は、予測開始時点から第1の予測終了時点までの第1の予測期間に設定された複数の予測時点それぞれにおいて、上流工程Aにて処理される製品数、下流工程Bにて処理される製品数、及び、置場a、bに貯蔵されている合計製品数に基づき、置場a、bにおける製品の過不足を算出し、休止が発生する可能性を予測する。 In this way, the first determination unit 121 determines the number of products processed in the upstream process A at each of the plurality of prediction points set in the first prediction period from the prediction start point to the first prediction end point. , the number of products processed in downstream process B, and the total number of products stored in storage sites a and b, calculate the excess or deficiency of products in storage sites a and b, and predict the possibility of suspension. do.

(S110:通知ステップ)
ステップS100の第1の予測ステップにより、休止が発生する可能性があると判定されると、第1の判定部121は、出力装置130に対して、休止が発生する可能性があることを通知する指示を行う。出力装置130は、当該指示を受けて、仕掛調整休止や材欠休止等の休止が発生する可能性があることをユーザに通知する(S110)。例えば出力装置130がディスプレイであれば、ディスプレイに通知内容を表示したり、ディスプレイの表示色を警告を表す色にしたりする。また、例えば出力装置130がスピーカーであれば、通知内容あるいはそれを表す音を出力する。このようにして、ユーザに対してこのまま操業を続けた場合に休止が発生する可能性があることが通知される。
(S110: notification step)
When the first prediction step of step S100 determines that a pause may occur, the first determination unit 121 notifies the output device 130 of the possibility of a pause. give instructions to In response to the instruction, the output device 130 notifies the user that there is a possibility that a suspension such as a suspension for work-in-progress adjustment or a shortage of materials will occur (S110). For example, if the output device 130 is a display, the content of notification is displayed on the display, or the display color of the display is changed to a warning color. Also, for example, if the output device 130 is a speaker, it outputs notification content or a sound representing it. In this way, the user is notified that a pause may occur if the operation is continued as it is.

(S120:第1の調整ステップ)
ステップS100の第1の予測ステップにより、休止が発生する可能性があると判定されると、調整処理部125により、生産スケジュールの見直しが行われる(S120)。例えば、調整処理部125は、第1の予測ステップの結果に基づいて、製品の生産時期を変更する等、工程A、Bで処理する製品数を増減して、休止が回避されるように生産スケジュールのスケジュール情報を調整する。
(S120: first adjustment step)
When it is determined in the first prediction step of step S100 that there is a possibility of suspension, the adjustment processing unit 125 reviews the production schedule (S120). For example, based on the results of the first prediction step, the adjustment processing unit 125 increases or decreases the number of products processed in processes A and B, such as by changing the product production period, so as to avoid interruptions in production. Adjust schedule information for schedules.

例えば、調整前のスケジュール情報が図3であり、図7に示した仕掛調整休止が発生する可能性があるケースを考える。このとき、調整処理部125は、例えば図9に示すように、予測時点T1_180に到達した時点での上流工程A全体で処理される製品数を減らし、下流工程B全体で処理される製品数を増やすように、予測開始時T0から予測時点T1_180までのスケジュール情報を調整する。これにより、合計在庫数が合計最大在庫数Nab以下となるようにして、仕掛調整休止の発生を回避する。 For example, consider a case where the schedule information before adjustment is shown in FIG. 3 and there is a possibility that the work-in-progress adjustment suspension shown in FIG. 7 will occur. At this time, as shown in FIG. 9, for example, the adjustment processing unit 125 reduces the number of products processed in the entire upstream process A at the time when the prediction time T1_180 is reached, and reduces the number of products processed in the entire downstream process B. The schedule information from the prediction start time T0 to the prediction time T1_180 is adjusted so as to increase. As a result, the total number of inventories is made equal to or less than the total maximum number of inventories Nab, thereby avoiding the occurrence of work-in-progress adjustment suspension.

工程A、Bにて処理される製品数の増減は、スケジュール情報を変更することにより可能である。例えば、図9下側に示すように、予測時点T1_180に到達した時点での上流工程A全体で処理される製品数を減らすために、例えば、予測開始時T0から予測時点T1_180までに処理予定であった製品が、より後で処理されるように変更される。図9の例では、上流処理ラインA1のコイル1003及び上流処理ラインA1のコイル2511の処理時期が変更されている。また、予測時点T1_180に到達した時点での下流工程B全体で処理される製品数を増やすために、例えば、予測開始時T0から予測時点T1_180までに処理予定であった製品が、より単位時間当たりの製品処理数が多い品種に変更される。例えば、当初、下流処理ラインB1で処理予定のコイル0003が、図9では、コイル0003よりも単位時間当たりの製品処理数が多いコイル0515、0516に変更されている。 The number of products processed in processes A and B can be increased or decreased by changing the schedule information. For example, as shown in the lower part of FIG. The product that was there is changed to be processed later. In the example of FIG. 9, the processing timings of the coil 1003 of the upstream processing line A1 and the coil 2511 of the upstream processing line A1 are changed. In addition, in order to increase the number of products to be processed in the entire downstream process B at the time when the prediction time T1_180 is reached, for example, the number of products scheduled to be processed from the prediction start time T0 to the prediction time T1_180 is increased per unit time. is changed to a product type with a large number of products processed. For example, the coil 0003, which was originally scheduled to be processed in the downstream processing line B1, is changed to coils 0515 and 0516 that can process more products per unit time than the coil 0003 in FIG.

このように、休止が回避されるように調整処理部125によりスケジュール情報が調整されると、第1の判定部121は、調整後のスケジュール情報に基づき、再度ステップS100の処理を実行する。そして、ステップS100の第1の予測ステップにより、休止が発生する可能性はないと判定されると、ステップS130の処理が実行される。 In this way, when the schedule information is adjusted by the adjustment processing unit 125 so as to avoid a pause, the first determination unit 121 executes the process of step S100 again based on the adjusted schedule information. Then, when it is determined in the first prediction step of step S100 that there is no possibility of a pause, the process of step S130 is executed.

(S130:第2の予測ステップ)
次いで、置場管理装置120の第2の判定部123により、第2の予測期間において、貯蔵エリア単位で、製品の在庫数を予測し、製品の過不足による休止の発生有無が予測される(S130)。第2の予測ステップでは、現時点での製造状況から、現在の生産スケジュールに基づき製品の製造を続けた場合に、休止が発生する可能性を、搬送装置10による製品の搬送能力も考慮して詳細に予測する。このとき、生産スケジュールは、第1の予測ステップにて休止が発生する可能性はないと判定されたときのものを用いる。
(S130: second prediction step)
Next, the second determination unit 123 of the storage space management device 120 predicts the number of products in stock for each storage area in the second prediction period, and predicts whether there will be a pause due to excess or deficiency of products (S130). ). In the second prediction step, based on the current manufacturing situation, the possibility of suspension occurring when product manufacturing is continued based on the current production schedule is detailed in consideration of the product transport capacity of the transport device 10. predict to At this time, the production schedule used when it is determined in the first prediction step that there is no possibility of a pause occurring is used.

第2の予測ステップでは、第2の予測期間に設定された複数の予測時点それぞれにおいて、上流処理ラインにて処理される製品数、当該上流処理ラインに対応する後面貯蔵エリアから各前面貯蔵エリアへ搬送される製品数、及び、予測開始時点での当該後面貯蔵エリアの製品在庫数に基づき、各後面貯蔵エリアにおける製品の過不足を算出し、休止が発生する可能性を予測する。また、第2の予測期間に設定された複数の予測時点それぞれにおいて、下流処理ラインにて処理される製品数、各後面貯蔵エリアから当該下流処理ラインに対応する前面貯蔵エリアへ搬送される製品数、及び、予測開始時点での当該前面貯蔵エリアの製品在庫数に基づき、各後面貯蔵エリアにおける製品の過不足を算出し、休止が発生する可能性を予測する。 In the second prediction step, at each of a plurality of prediction times set in the second prediction period, the number of products to be processed in the upstream processing line, the number of products from the rear storage area corresponding to the upstream processing line to each front storage area Based on the number of products to be transported and the number of products in stock in the rear storage area at the start of prediction, the excess or deficiency of products in each rear storage area is calculated to predict the possibility of suspension. Also, the number of products processed in the downstream processing line and the number of products transported from each rear storage area to the front storage area corresponding to the downstream processing line at each of the plurality of prediction points set in the second prediction period. , and based on the number of products in stock in the front storage area at the time of prediction start, the excess or deficiency of products in each rear storage area is calculated, and the possibility of suspension occurring is predicted.

第2の予測ステップを具体的に説明すると、まず、第2の判定部123は、図10に示すように、第2の予測期間T2をq個に分割し、複数の予測時点T2_v(v=1~q、qは2以上の自然数。T2_q=T2)を設定する。ここで、第2の予測期間T2は、予め設定されていてもよく、ユーザが入力装置110を用いて指定してもよい。図10では、第2の予測期間T2は4日に設定されている。また、第2の予測期間T2を分割する間隔は、適宜設定可能であり、例えば図10では1時間に設定されている。つまり、図10に示す例では、第2の予測期間T2を96分割している。なお、第2の予測期間T2の分割数qは、第1の予測期間T1の分割数pと同一であってもよく、異なってもよい。 Specifically describing the second prediction step, first, as shown in FIG. 1 to q, q is a natural number equal to or greater than 2. Set T2_q=T2). Here, the second prediction period T2 may be set in advance, or may be designated by the user using the input device 110 . In FIG. 10, the second prediction period T2 is set to 4 days. Also, the interval at which the second prediction period T2 is divided can be set as appropriate, and is set to one hour in FIG. 10, for example. That is, in the example shown in FIG. 10, the second prediction period T2 is divided into 96 parts. Note that the division number q of the second prediction period T2 may be the same as or different from the division number p of the first prediction period T1.

次いで、第2の判定部123は、後面貯蔵エリアaiに着目し、予測開始時T0から各予測時点T2_vに到達した時点での、上流処理ラインAiで処理される製品数から、後面貯蔵エリアaiから前面貯蔵エリアb1~bmへ搬送される製品数ΣKaibj×T2_v(j=1→m)を減じた値(以下、「残後面貯蔵数」ともいう。)を算出する。また、第2の判定部123は、予測開始時T0から各予測時点T2_vに到達した時点での残後面貯蔵数に、予測開始時点(T0)での実績在庫数N0aiを加えた後面貯蔵エリアaiの過不足評価値をそれぞれ算出する。そして、第2の判定部123は、各予測時点T2_vにおける過不足評価値と、各後面貯蔵エリアaiの最大在庫数Naiとを比較する。 Next, the second determination unit 123 focuses on the rear storage area ai, and determines the number of products processed in the upstream processing line Ai from the prediction start time T0 to each prediction time T2_v. is subtracted by the number of products ΣKaibj×T2_v (j=1→m) to be conveyed to the front storage areas b1 to bm (hereinafter also referred to as “remaining rear surface storage number”). In addition, the second determination unit 123 determines the rear storage area ai obtained by adding the actual inventory quantity N0ai at the prediction start time (T0) to the remaining rear storage quantity at each prediction time T2_v from the prediction start time T0. Calculate the excess/deficiency evaluation value of each. Then, the second determination unit 123 compares the excess/deficiency evaluation value at each prediction time T2_v with the maximum inventory quantity Nai of each rear storage area ai.

各予測時点T2_vにおける過不足評価値が各後面貯蔵エリアaiの最大在庫数Naiを超過している場合は、製品を後面貯蔵エリアaiに貯蔵できず、仕掛調整休止が発生する可能性がある。例えば、図11に示すケースでは、後面貯蔵エリアa1において、予測時点T2_50に到達した時点で、上流処理ラインA1で処理される製品数は90個、後面貯蔵エリアa1から前面貯蔵エリアb1~bmへ搬送される製品数(ΣKa1bj×T2_50)は50個と見積もられ、残後面貯蔵数は40個となる。このときの後面貯蔵エリアa1の過不足評価値は120個であり、後面貯蔵エリアa1の最大在庫数Na1の100個を超えている。このような場合には、仕掛調整休止が発生する可能性があると判定される。 If the excess/deficiency evaluation value at each prediction time T2_v exceeds the maximum stock quantity Nai of each rear storage area ai, there is a possibility that products cannot be stored in the rear storage area ai, resulting in work-in-progress adjustment suspension. For example, in the case shown in FIG. 11, when the prediction time T2_50 is reached in the rear storage area a1, the number of products processed in the upstream processing line A1 is 90, and the number of products to be processed from the rear storage area a1 to the front storage areas b1 to bm is 90. The number of products to be transported (ΣKa1bj×T2_50) is estimated to be 50, and the number of remaining rear surface storage is 40. At this time, the excess/deficiency evaluation value of the rear storage area a1 is 120, which exceeds the maximum stock quantity Na1 of 100 in the rear storage area a1. In such a case, it is determined that there is a possibility that work-in-progress adjustment suspension will occur.

また、各予測時点T2_vにおける過不足評価値が0以下となる場合は、製品が不足し、材欠休止が発生する可能性がある。例えば、図11に示すケースでは、後面貯蔵エリアanにおいて、予測時点T2_50に到達した時点で、上流処理ラインA1で処理される製品数は600個、後面貯蔵エリアanから前面貯蔵エリアb1~bmへ搬送される製品数(ΣKanbj×T2_50)は700個と見積もられ、残後面貯蔵数は-100個となる。このとき、後面貯蔵エリアanの最大在庫数Nanの50個であることから、後面貯蔵エリアanの過不足評価値は-50個となる。さらに、予測時点T2_96に到達した時点でも、後面貯蔵エリアanの過不足評価値は-50個であり、後面貯蔵エリアanの過不足評価値は-50個のままである。このような場合には、下流工程Bの各下流処理ラインの処理能力に対して、後面貯蔵エリアanの製品の在庫数が不足する結果、前面貯蔵エリアb1~bmへ必要な製品を搬送することができず、材欠休止が発生する可能性があると判定される。 Moreover, when the excess/deficiency evaluation value at each prediction time T2_v is 0 or less, there is a possibility that products will be in short supply and material shortage will occur. For example, in the case shown in FIG. 11, in the rear storage area an, when the prediction time T2_50 is reached, the number of products processed in the upstream processing line A1 is 600, and the number of products processed from the rear storage area an to the front storage areas b1 to bm is 600. The number of products to be transported (ΣKanbj×T2_50) is estimated to be 700, and the number of remaining rear surface storages is −100. At this time, since the maximum inventory number Nan of the rear storage area an is 50, the excess/deficiency evaluation value of the rear storage area an is -50. Furthermore, even when the predicted time T2_96 is reached, the excess/deficiency evaluation value of the rear storage area an is -50, and the excess/deficiency evaluation value of the rear storage area an remains -50. In such a case, the inventory of products in the rear storage area an is insufficient with respect to the processing capacity of each downstream processing line in the downstream process B, and as a result, the necessary products cannot be transported to the front storage areas b1 to bm. It is judged that there is a possibility that material shortage will occur.

さらに、第2の判定部123は、前面貯蔵エリアbjに着目し、予測開始時T0から各予測時点T2_vに到達した時点での、後面貯蔵エリアa1~anから前面貯蔵エリアbjへ搬送される製品数ΣKaibj×T2_v(i=1→n)から、下流処理ラインBjで処理される製品数を減じた値(以下、「残前面貯蔵数」ともいう。)を算出する。また、第2の判定部123は、予測開始時T0から各予測時点T2_vに到達した時点での残後面貯蔵数に、予測開始時点(T0)での実績在庫数N0bjを加えた後面貯蔵エリアbjの過不足評価値をそれぞれ算出する。そして、第2の判定部123は、各予測時点T2_vにおける過不足評価値と、各後面貯蔵エリアbjの最大在庫数Nbjとを比較する。 Furthermore, the second determination unit 123 focuses on the front storage area bj, and determines the number of products transported from the rear storage areas a1 to an to the front storage area bj at the time from the prediction start time T0 to each prediction time T2_v. A value obtained by subtracting the number of products processed in the downstream processing line Bj from the number ΣKaibj×T2_v (i=1→n) (hereinafter also referred to as “remaining front storage number”) is calculated. In addition, the second determination unit 123 determines the rear storage area bj obtained by adding the actual inventory quantity N0bj at the prediction start time (T0) to the remaining rear storage quantity at each prediction time T2_v from the prediction start time T0. Calculate the excess/deficiency evaluation value of each. Then, the second determination unit 123 compares the excess/deficiency evaluation value at each prediction time T2_v with the maximum stock quantity Nbj of each rear storage area bj.

各予測時点T2_vにおける過不足評価値が各前面貯蔵エリアbjの最大在庫数Nbjを超過している場合は、製品を前面貯蔵エリアbjに貯蔵できず、仕掛調整休止が発生する可能性がある。例えば、図12に示すケースでは、前面貯蔵エリアb2において、予測時点T2_50に到達した時点で、後面貯蔵エリアa1~anから前面貯蔵エリアb2へ搬送される製品数(ΣKaib2×T2_50)は1020個、下流処理ラインB2で処理される製品数は1000個と見積もられ、残前面貯蔵数は20個となる。このときの前面貯蔵エリアb2の過不足評価値は110個であり、前面貯蔵エリアb2の最大在庫数Nb2の100個を超えている。このような場合には、仕掛調整休止が発生する可能性があると判定される。 If the excess/deficiency evaluation value at each prediction time T2_v exceeds the maximum stock quantity Nbj of each front storage area bj, there is a possibility that products cannot be stored in the front storage area bj, resulting in work-in-progress adjustment suspension. For example, in the case shown in FIG. 12, the number of products (ΣKaib2×T2_50) transported from the rear storage areas a1 to an to the front storage area b2 at the predicted time T2_50 in the front storage area b2 is 1020. The number of products to be processed in the downstream processing line B2 is estimated at 1000, and the number of remaining front stocks is 20. At this time, the excess/deficiency evaluation value of the front storage area b2 is 110, which exceeds the maximum inventory quantity Nb2 of 100 in the front storage area b2. In such a case, it is determined that there is a possibility that work-in-progress adjustment suspension will occur.

また、各予測時点T2_vにおける過不足評価値が0以下となる場合は、製品が不足し、材欠休止が発生する可能性がある。例えば、図12に示すケースでは、前面貯蔵エリアb1において、予測時点T2_50に到達した時点で、後面貯蔵エリアa1~anから前面貯蔵エリアb1へ搬送される製品数(ΣKaib1×T2_50)は700個、下流処理ラインB1で処理される製品数は750個と見積もられ、残前面貯蔵数は-50個となる。このとき、予測開始時点(T0)での前面貯蔵エリアb1の実績在庫数N0b1の50個であることから、前面貯蔵エリアb1の過不足評価値は0個となる。このような場合には、下流工程Bの各下流処理ラインの処理能力に対して、後面貯蔵エリアa1~anから前面貯蔵エリアbjに搬送され貯蔵される製品が不足しており、材欠休止が発生する可能性があると判定される。 Moreover, when the excess/deficiency evaluation value at each prediction time T2_v is 0 or less, there is a possibility that products will be in short supply and material shortage will occur. For example, in the case shown in FIG. 12, the number of products (ΣKaib1×T2_50) transported from the rear storage areas a1 to an to the front storage area b1 at the predicted time T2_50 in the front storage area b1 is 700. The number of products processed in the downstream processing line B1 is estimated at 750, and the number of remaining front stocks is -50. At this time, since the actual stock quantity N0b1 of the front storage area b1 at the prediction start time (T0) is 50, the excess/deficiency evaluation value of the front storage area b1 is zero. In such a case, the number of products transported and stored from the rear storage areas a1 to an to the front storage area bj is insufficient with respect to the processing capacity of each downstream processing line in the downstream process B, resulting in material shortage suspension. determined to occur.

このように、第2の判定部123は、予測開始時点から第2の予測終了時点までの第2の予測期間に設定された複数の予測時点それぞれにおいて、搬送装置による搬送能力も考慮して、各貯蔵エリアai、bjにおける製品の過不足を算出し、休止が発生する可能性を予測する。 In this way, the second determination unit 123 considers the carrying capacity of the carrier at each of the plurality of prediction times set in the second prediction period from the prediction start time to the second prediction end time. The excess or deficiency of products in each storage area ai, bj is calculated, and the possibility of suspension occurring is predicted.

(S140:通知ステップ)
ステップS130の第2の予測ステップにより、休止が発生する可能性があると判定されると、第2の判定部123は、出力装置130に対して、休止が発生する可能性があることを通知する指示を行う。出力装置130は、当該指示を受けて、仕掛調整休止や材欠休止等の休止が発生する可能性があることをユーザに通知する(S140)。ステップS140の通知処理は、ステップS110の処理と同様に行えばよい。これにより、ユーザに対してこのまま操業を続けた場合に休止が発生する可能性があることが通知される。
(S140: notification step)
When the second prediction step of step S130 determines that a pause may occur, the second determination unit 123 notifies the output device 130 of the possibility of a pause. give instructions to In response to the instruction, the output device 130 notifies the user that there is a possibility that a suspension such as suspension for work in process adjustment or shortage of materials will occur (S140). The notification process of step S140 may be performed in the same manner as the process of step S110. This notifies the user that a pause may occur if the operation is continued as it is.

(S150:第2の調整ステップ)
ステップS130の第2の予測ステップにより、休止が発生する可能性があると判定されると、調整処理部125により、上流工程Aから下流工程Bへ製品を搬送する搬送能力情報の見直しが行われる(S150)。例えば、調整処理部125は、第2の予測ステップの結果に基づいて、上流工程Aから下流工程Bへの製品の搬送能力を変更する等して、搬送する製品数を増減し、休止が回避されるように生産スケジュールの搬送能力情報を調整する。
(S150: Second adjustment step)
When the second prediction step of step S130 determines that there is a possibility that a pause will occur, the adjustment processing unit 125 reviews the conveying capability information for conveying the product from the upstream process A to the downstream process B. (S150). For example, based on the result of the second prediction step, the adjustment processing unit 125 increases or decreases the number of products to be transported by, for example, changing the transport capability of products from the upstream process A to the downstream process B to avoid suspension. Adjust the capacity information in the production schedule so that

例えば、調整前の搬送能力情報が図5のように設定されているときに、図11に示したように、上流処理ラインA1で仕掛調整休止が発生する可能性があり、上流処理ラインAnで材欠休止が発生する可能性があるケースを考える。このとき、調整処理部125は、例えば図13に示すように、上流処理ラインA1については予測時点T2_50までの後面貯蔵エリアa1から前面貯蔵エリアb1~bmへ搬送される製品数を増やし、上流処理ラインAnについては予測時点T2_96までの後面貯蔵エリアanから前面貯蔵エリアb1~bmへ搬送される製品数を減らすように、搬送能力情報を変更する。これにより、上流処理ラインA1については合計在庫数が合計最大在庫数Na1以下となるようにして仕掛調整休止の発生を回避し、上流処理ラインAnについては合計在庫数が0より大きくなるようにして材欠休止の発生を回避する。 For example, when the pre-adjustment transport capacity information is set as shown in FIG. 5, as shown in FIG. Consider the case where outages may occur. At this time, as shown in FIG. 13, for example, for the upstream processing line A1, the adjustment processing unit 125 increases the number of products transported from the rear storage area a1 to the front storage areas b1 to bm until the predicted time T2_50, and For the line An, the conveying capacity information is changed so as to reduce the number of products conveyed from the rear storage area an to the front storage areas b1 to bm until the predicted time T2_96. As a result, the total inventory quantity of the upstream processing line A1 is set to be equal to or less than the total maximum inventory quantity Na1 to avoid the occurrence of work-in-progress adjustment suspension, and the total inventory quantity of the upstream processing line An is set to be greater than 0. Avoid material outages.

搬送能力情報の変更は、例えば、図14に示すように、生産スケジュール記憶部140に記録されている搬送能力情報の数値を変更することにより可能である。具体的には、置場aから置場bへ製品を搬送する搬送装置10の1台当たりの搬送量を増やしたり、搬送装置10の台数を増やしたりすることで、置場aから置場bへ搬送される製品数を増やすことができる。同様に、置場aから置場bへ製品を搬送する搬送装置10の1台当たりの搬送量を減らしたり、搬送装置10の台数を減らしたりすることで、置場aから置場bへ搬送される製品数を減らすことができる。 The transfer capability information can be changed, for example, by changing the numerical value of the transfer capability information recorded in the production schedule storage unit 140, as shown in FIG. Specifically, by increasing the transport amount per one transport device 10 that transports the product from the storage site a to the storage site b, or by increasing the number of the transport devices 10, the product is transported from the storage site a to the storage site b. You can increase the number of products. Similarly, by reducing the transport amount per transport device 10 that transports products from the storage site a to the storage site b, or by reducing the number of transport devices 10, the number of products transported from the storage site a to the storage site b can be reduced.

例えば図14の搬送能力情報では、上流処理ラインA1については、後面貯蔵エリアa1から前面貯蔵エリアb1~bmへ搬送される製品数を増やすために、搬送元を後面貯蔵エリアa1とする製品の搬送能力が大きくなるよう変更されている。また、上流処理ラインAnについては、後面貯蔵エリアa1から前面貯蔵エリアb1~bmへ搬送される製品数を減らすために、搬送元を後面貯蔵エリアanとする製品の搬送能力が小さくなるよう変更されている。このとき、置場aから置場bへ製品を搬送する搬送装置10の数が限られている場合には、使用可能な搬送装置10の配分を変更して、搬送能力が調整される。 For example, in the conveying capacity information of FIG. 14, regarding the upstream processing line A1, in order to increase the number of products conveyed from the rear storage area a1 to the front storage areas b1 to bm, it is possible to convey products from the rear storage area a1. It has been modified to be more powerful. Also, regarding the upstream processing line An, in order to reduce the number of products that are transported from the rear storage area a1 to the front storage areas b1 to bm, the transport capacity of the products whose transport source is the rear storage area an is changed to be small. ing. At this time, if the number of conveying devices 10 that convey products from place a to place b is limited, the distribution of usable conveying devices 10 is changed to adjust the conveying capacity.

このように、休止が回避されるように調整処理部125により搬送能力情報が変更されると、第2の判定部123は、変更後の搬送能力情報に基づき、第1の予測ステップにて調整された生産スケジュールのスケジュール情報について再度ステップS130の処理を実行する。そして、ステップS130の第2の予測ステップにより、休止が発生する可能性はないと判定されると、第2の判定部123は、現時点での生産スケジュールを確定し、図6に示す処理を終了する。 In this way, when the adjustment processing unit 125 changes the conveying capability information so as to avoid a pause, the second determination unit 123 adjusts in the first prediction step based on the changed conveying capability information. The process of step S130 is executed again for the schedule information of the produced production schedule. Then, when it is determined by the second prediction step of step S130 that there is no possibility of a pause occurring, the second determination unit 123 determines the current production schedule and terminates the processing shown in FIG. do.

以上、本実施形態に係る製品の置場管理方法について説明した。本実施形態によれば、置場a、bの在庫数予測と各貯蔵エリアの在庫数予測との2段階で在庫予測し、ある程度先の生産スケジュールの調整を踏まえて、直近の物流状況を考慮した生産スケジュールの調整を行う。これにより、従来と比べて仕掛調整休止や材欠休止の発生頻度を減少させることができる。 The product storage management method according to the present embodiment has been described above. According to the present embodiment, the inventory is predicted in two steps, that is, the inventory quantity prediction for the storage areas a and b and the inventory quantity prediction for each storage area, and the recent distribution situation is considered based on the adjustment of the production schedule to some extent ahead. Adjust the production schedule. As a result, it is possible to reduce the occurrence frequency of work-in-progress adjustment stoppages and material shortage stoppages compared to the conventional art.

製造プロセスにおいて、上述の本発明の一実施形態に係る製品の置場管理方法と従来の製品の置場管理方法を適用し置場の在庫数を管理したときの、休止の発生頻度及び生産スケジュールの調整負荷を比較した。ここでは、製造プロセスの一例として、図15に示すような、酸洗工程、冷延工程、焼鈍工程、めっき工程、梱包工程からなる鉄鋼製造プロセスについて検討した。各工程は、いずれも3つの処理ラインを有しているものとして、2週間分の生産計画を策定した。各処理ラインの前面置場にある製品は、生産計画に従い、対応する処理ラインで処理された後、後面置場へ貯蔵され、さらに生産計画に従い、後工程の処理ラインの前面置場へ運搬されるものとした。このとき、酸洗工程の各処理ラインでは、材欠休止及び仕掛調整休止は発生しないものとした。 In the manufacturing process, when the product storage space management method according to the embodiment of the present invention and the conventional product storage space management method are applied to manage the number of stocks in the storage space, the occurrence frequency of suspensions and the adjustment load of the production schedule compared. Here, as an example of the manufacturing process, a steel manufacturing process consisting of a pickling process, a cold rolling process, an annealing process, a plating process, and a packing process as shown in FIG. 15 was examined. Assuming that each process has three processing lines, a two-week production plan was formulated. The products in the front storage area of each processing line shall be stored in the rear storage area after being processed in the corresponding processing line according to the production plan, and further transported to the front storage area of the subsequent processing line according to the production plan. did. At this time, it was assumed that material shortage and in-process adjustment suspension would not occur in each processing line of the pickling process.

実施例では、上述の本実施形態に係る製品の置場管理方法を適用し、以下のように2段階の在庫予測を、1日1回実行した。
(第1の予測)予測期間:当日~2週間先
前工程の後面貯蔵エリアと後工程の前面貯蔵エリアとを集約した置場単位で、製品の在庫数を予測した。予測の結果、休止が発生する可能性があると予測された場合は、休止が発生する可能性がなくなるまで生産スケジュールのスケジュール情報を調整した。
(第2の予測)予測期間:当日~3日間先
貯蔵エリア単位で製品の在庫数を予測した。予測の結果、休止が発生する可能性があると予測された場合は、休止が発生する可能性がなくなるまで搬送能力情報を調整した。
In the example, the product storage space management method according to the present embodiment described above was applied, and the following two-stage inventory prediction was performed once a day.
(First prediction) Prediction period: From today to two weeks ahead The number of products in stock is predicted for each storage area that aggregates the rear storage area of the previous process and the front storage area of the subsequent process. As a result of the prediction, when it was predicted that there was a possibility of a pause, the schedule information of the production schedule was adjusted until the possibility of a pause disappeared.
(Second prediction) Prediction period: Today to 3 days ahead The number of products in stock was predicted for each storage area. As a result of the prediction, when it was predicted that there was a possibility that a pause would occur, the transport capacity information was adjusted until the possibility of a pause disappearing.

一方、比較例1として、上記特許文献1の手法により、予測期間を当日~3日間先までとして、1日1回の頻度で、置場単位で製品の在庫数を予測した。予測の結果、休止が発生する可能性があると予測された場合は、休止が発生する可能性がなくなるまで搬送能力情報を調整した。 On the other hand, as Comparative Example 1, by the method of Patent Document 1, the number of products in stock was predicted for each storage site once a day, with the prediction period set to the current day to three days ahead. As a result of the prediction, when it was predicted that there was a possibility that a pause would occur, the transport capacity information was adjusted until the possibility of a pause disappearing.

また、比較例2として、予測期間を当日~2週間先までとして、1日1回の頻度で、貯蔵エリア単位に在庫量を予測した。予測の結果、休止が発生する可能性があると予測された場合は、休止が発生する可能性がなくなるまで生産スケジュールのスケジュール情報及び搬送能力情報を調整した。 In addition, as a comparative example 2, the forecast period is from the current day to two weeks ahead, and the inventory amount is forecast for each storage area once a day. As a result of the prediction, when it was predicted that there was a possibility that a stoppage would occur, the schedule information and transport capacity information of the production schedule were adjusted until the possibility of a stoppage was eliminated.

実施例及び比較例1、2について、休止の発生頻度及び生産スケジュールの調整負荷を比較した結果を下記表1に示す。 Table 1 below shows the results of comparing the occurrence frequency of stoppages and the adjustment load of the production schedule for Example and Comparative Examples 1 and 2.

Figure 0007339545000001
Figure 0007339545000001

比較例1は、仕掛調整休止及び材欠休止ともに、実施例及び比較例に比べて発生回数が多かった。これは、生産計画と生産実績との実態の乖離が極めて大きくなった場合には、生産スケジュールを見直すタイミングが3日前であるのは遅すぎであり、休止発生の抑制効果が低下するためと考えられる。これに対し、実施例及び比較例2は、仕掛調整休止及び材欠休止ともに、休止回数が半減した。 In Comparative Example 1, the number of occurrences of both work-in-progress adjustment suspension and material shortage suspension was higher than in Examples and Comparative Examples. This is because when the discrepancy between the actual production plan and the actual production results becomes extremely large, it is too late to revise the production schedule three days in advance, and it is thought that the effect of suppressing the occurrence of stoppages will decrease. be done. On the other hand, in Example and Comparative Example 2, the number of pauses was halved for both in-process adjustment pauses and material shortage pauses.

実施例と比較例2とは休止回数は同等の結果であるが、生産スケジュールの調整に要する調整負荷は大きく異なり、実施例の調整負荷は、比較例2の40%程度であった。比較例2では、予測期間すべてにおいて貯蔵エリア単位で在庫予測を実施したため、休止の発生が予測される場合には生産スケジュールを貯蔵エリア単位で調整せねばならない。このため、比較例2では、生産スケジュールの調整負荷が実施例に比べて極めて大きくなったと考えられる。 Although the results of the Example and Comparative Example 2 are the same in terms of the number of stops, the adjustment load required to adjust the production schedule is significantly different. In Comparative Example 2, since the inventory forecast was performed for each storage area in the entire forecast period, the production schedule must be adjusted for each storage area when a stoppage is expected. For this reason, in Comparative Example 2, it is considered that the adjustment load of the production schedule became extremely large compared to the example.

以上、添付図面を参照しながら本発明の好適な実施形態について詳細に説明したが、本発明はかかる例に限定されない。本発明の属する技術の分野における通常の知識を有する者であれば、特許請求の範囲に記載された技術的思想の範疇内において、各種の変更例または修正例に想到し得ることは明らかであり、これらについても、当然に本発明の技術的範囲に属するものと了解される。 Although the preferred embodiments of the present invention have been described in detail above with reference to the accompanying drawings, the present invention is not limited to such examples. It is obvious that a person having ordinary knowledge in the technical field to which the present invention belongs can conceive of various modifications or modifications within the scope of the technical idea described in the claims. It is understood that these also naturally belong to the technical scope of the present invention.

10 搬送装置
100 管理システム
110 入力装置
120 置場管理装置
121 第1の判定部
123 第2の判定部
125 調整処理部
130 出力装置
140 生産スケジュール記憶部
REFERENCE SIGNS LIST 10 carrier device 100 management system 110 input device 120 storage site management device 121 first determination unit 123 second determination unit 125 adjustment processing unit 130 output device 140 production schedule storage unit

Claims (6)

製造プロセスにおいて、生産スケジュールにしたがって、第1の工程にて処理された製品を貯蔵する第1の置場から、第2の工程にて処理される製品を貯蔵する第2の置場へ搬送する際の製品の置場管理方法であって、
前記第1の工程は、複数の第1処理ラインを有し、
前記第1の置場は、前記第1処理ラインそれぞれに対応して設けられた複数の第1貯蔵エリアを有し、
前記第2の工程は、複数の第2処理ラインを有し、
前記第2の置場は、前記第2処理ラインそれぞれに対応して設けられた複数の第2貯蔵エリアからなり、
予測開始時点から第1の予測終了時点までの第1の予測期間の前記生産スケジュールについて、前記第1の予測期間に設定された複数の予測時点それぞれにおいて、前記第1の工程にて処理される製品数、前記第2の工程にて処理される製品数、及び、前記第1の置場及び前記第2の置場に貯蔵されている合計製品数に基づき、前記第1の工程または前記第2の工程での休止の発生有無を予測する第1の予測ステップと、
前記第1の予測ステップにて休止が発生しないと予測された生産スケジュールについて、前記第1の予測期間よりも短い、前記予測開始時点から第2の予測終了時点までの第2の予測期間に設定された複数の予測時点それぞれにおいて、
前記第1処理ラインそれぞれについて、前記第1処理ラインにて処理される製品数、当該第1処理ラインに対応する第1貯蔵エリアから前記各第2貯蔵エリアへ搬送される製品数、及び、前記予測開始時点での当該第1貯蔵エリアの製品在庫数に基づき、前記第1処理ラインでの休止の発生有無を予測し、
前記第2処理ラインそれぞれについて、前記第2処理ラインにて処理される製品数、前記各第1貯蔵エリアから当該第2処理ラインに対応する前記第2貯蔵エリアへ搬送される製品数、及び、前記予測開始時点での当該第2貯蔵エリアの製品在庫数に基づき、前記第2処理ラインでの休止の発生有無を予測する、第2の予測ステップと、
前記第1の予測ステップまたは前記第2の予測ステップにて休止が発生すると予測された場合に、生産スケジュールを調整する調整ステップと、
を含む、製品の置場管理方法。
In the manufacturing process, according to the production schedule, when transporting from the first storage location storing the products processed in the first step to the second storage location storing the products processed in the second step A product storage management method,
The first step has a plurality of first processing lines,
The first storage area has a plurality of first storage areas provided corresponding to each of the first processing lines,
The second step has a plurality of second processing lines,
The second storage area comprises a plurality of second storage areas provided corresponding to each of the second processing lines,
The production schedule for the first prediction period from the prediction start point to the first prediction end point is processed in the first step at each of a plurality of prediction points set in the first prediction period. Based on the number of products, the number of products processed in the second step, and the total number of products stored in the first storage location and the second storage location, the first step or the second a first prediction step of predicting the presence or absence of pauses in the process;
A second prediction period from the start of prediction to the end of the second prediction, which is shorter than the first prediction period, is set for the production schedule for which no suspension is predicted in the first prediction step. At each of the multiple prediction time points obtained,
For each of the first processing lines, the number of products processed in the first processing line, the number of products conveyed from the first storage area corresponding to the first processing line to the respective second storage areas, and Based on the number of products in stock in the first storage area at the start of prediction, predicting whether or not there will be a pause in the first processing line,
for each of said second processing lines, the number of products to be processed in said second processing line, the number of products to be conveyed from each of said first storage areas to said second storage area corresponding to said second processing line; and a second prediction step of predicting whether or not the second processing line will be suspended based on the number of products in stock in the second storage area at the start of the prediction;
an adjustment step of adjusting a production schedule when it is predicted that a pause will occur in the first prediction step or the second prediction step;
product storage management methods, including;
前記第1の予測ステップでは、前記第1の予測終了時点での、前記第1の工程にて処理される製品数から前記第2の工程にて処理される製品数を減じた値と、前記第1の置場及び前記第2の置場に貯蔵されている合計製品数とに基づき、前記第1の置場及び前記第2の置場の前記製品の過不足を算出し、前記第1の工程または前記第2の工程での休止の発生有無を予測する、請求項1に記載の製品の置場管理方法。 In the first prediction step, a value obtained by subtracting the number of products processed in the second process from the number of products processed in the first process at the end of the first prediction; Based on the total number of products stored in the first storage area and the second storage area, the excess or deficiency of the products in the first storage area and the second storage area is calculated, and the first step or the 2. The product storage management method according to claim 1, wherein the presence or absence of suspension in the second process is predicted. 前記第2の予測ステップでは、
前記第1処理ラインそれぞれについて、処理される製品数から、当該第1処理ラインに対応する第1貯蔵エリアから各前記第2貯蔵エリアへ搬送される製品数を減じた値と、前記予測開始時点での当該第1貯蔵エリアの製品在庫数とに基づき、前記第1貯蔵エリアに貯蔵される前記製品の過不足を算出して、前記第1処理ラインでの休止の発生有無を予測し、
前記第2処理ラインそれぞれについて、処理される製品数から、各前記第1貯蔵エリアから当該第2処理ラインに対応する前記第2貯蔵エリアへ搬送される製品数を減じた値と、前記予測開始時点での当該第2貯蔵エリアの製品在庫数とに基づき、前記第2貯蔵エリアに貯蔵される前記製品の過不足を算出して、前記第1処理ラインでの休止の発生有無を予測する、請求項1または2に記載の製品の置場管理方法。
In the second prediction step,
For each of the first processing lines, a value obtained by subtracting the number of products to be transported from the first storage area corresponding to the first processing line to each of the second storage areas from the number of products to be processed, and the predicted start time Calculating the excess or deficiency of the products stored in the first storage area based on the number of products in stock in the first storage area in and predicting whether or not there will be a pause in the first processing line,
for each of the second processing lines, a value obtained by subtracting the number of products to be transferred from each of the first storage areas to the second storage area corresponding to the second processing line from the number of products to be processed; calculating the excess or deficiency of the products stored in the second storage area based on the number of products in stock in the second storage area at the time, and predicting whether there will be a pause in the first processing line; The product storage management method according to claim 1 or 2.
前記第1の予測ステップにて休止が発生すると予測された場合、
前記調整ステップにて、前記生産スケジュールのうち、各工程の各処理ラインの製品単位の処理開始時間及び処理終了時間を表すスケジュール情報を変更し、
その後、前記第1の予測ステップを再度実行する、請求項1~3のいずれか1項に記載の製品の置場管理方法。
When it is predicted that a pause will occur in the first prediction step,
In the adjustment step, of the production schedule, schedule information representing the processing start time and processing end time for each product of each processing line of each process is changed,
4. The product storage site management method according to any one of claims 1 to 3, wherein said first prediction step is then executed again.
前記第2の予測ステップにて休止が発生すると予測された場合、
前記調整ステップにて、前記第1の置場から前記第2の置場への製品の搬送能力を表す搬送能力情報を変更し、
その後、前記第2の予測ステップを再度実行する、請求項1~4のいずれか1項に記載の製品の置場管理方法。
If it is predicted that a pause will occur in the second prediction step,
changing, in the adjusting step, conveying capacity information representing the conveying capacity of the product from the first storage site to the second storage site;
5. The product storage site management method according to any one of claims 1 to 4, wherein said second prediction step is then executed again.
前記第1の予測ステップまたは前記第2の予測ステップにて休止が発生すると予測された場合に、予測結果をユーザに通知する通知ステップを含む、請求項1~5のいずれか1項に記載の製品の置場管理方法。 6. The method according to any one of claims 1 to 5, comprising a notification step of notifying a user of a prediction result when it is predicted that a pause will occur in the first prediction step or the second prediction step. Product storage management method.
JP2020056009A 2020-03-26 2020-03-26 Product storage management method Active JP7339545B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP2020056009A JP7339545B2 (en) 2020-03-26 2020-03-26 Product storage management method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP2020056009A JP7339545B2 (en) 2020-03-26 2020-03-26 Product storage management method

Publications (2)

Publication Number Publication Date
JP2021157397A JP2021157397A (en) 2021-10-07
JP7339545B2 true JP7339545B2 (en) 2023-09-06

Family

ID=77919135

Family Applications (1)

Application Number Title Priority Date Filing Date
JP2020056009A Active JP7339545B2 (en) 2020-03-26 2020-03-26 Product storage management method

Country Status (1)

Country Link
JP (1) JP7339545B2 (en)

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2000090171A (en) 1998-09-10 2000-03-31 Toshiba Corp Stock management device and stock management system using same
JP2006309572A (en) 2005-04-28 2006-11-09 Nippon Steel Corp Production shipping plan preparation system and method for steel products
JP2019020875A (en) 2017-07-13 2019-02-07 株式会社神戸製鋼所 Logistics support device and method
JP2019207671A (en) 2018-05-28 2019-12-05 株式会社神戸製鋼所 Simulation device, simulation method, and simulation program
JP2020017117A (en) 2018-07-26 2020-01-30 株式会社神戸製鋼所 Simulation device, simulation method and simulation program

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2000090171A (en) 1998-09-10 2000-03-31 Toshiba Corp Stock management device and stock management system using same
JP2006309572A (en) 2005-04-28 2006-11-09 Nippon Steel Corp Production shipping plan preparation system and method for steel products
JP2019020875A (en) 2017-07-13 2019-02-07 株式会社神戸製鋼所 Logistics support device and method
JP2019207671A (en) 2018-05-28 2019-12-05 株式会社神戸製鋼所 Simulation device, simulation method, and simulation program
JP2020017117A (en) 2018-07-26 2020-01-30 株式会社神戸製鋼所 Simulation device, simulation method and simulation program

Also Published As

Publication number Publication date
JP2021157397A (en) 2021-10-07

Similar Documents

Publication Publication Date Title
US10872309B2 (en) System and method for root cause analysis and early warning of inventory problems
US6606527B2 (en) Methods and systems for planning operations in manufacturing plants
US6684117B2 (en) Methods and systems for scheduling work
Hendry et al. Customer enquiry management: part of a hierarchical system to control lead times in make-to-order companies
CN110097203A (en) Inventory's dispatching method, inventory's dispatching device and computer readable storage medium
US6243612B1 (en) Processing system having a scheduling system based on a composite ratio of process scheduling factors
Vandaele et al. Advanced resource planning
JP6493812B2 (en) Inventory management method, inventory management apparatus, and program
Aguirre et al. Medium-term optimization-based approach for the integration of production planning, scheduling and maintenance
CN111522316A (en) Optimal dynamic selection method for belt conveying process of stock yard
JP2021071950A (en) Shipping plan generating apparatus and shipping plan generating method
JP7339545B2 (en) Product storage management method
US20070130024A1 (en) Systems and methods for time-dependent protection of available quantities
US6920365B2 (en) System and method for pull-in order planning and control
CN114066351A (en) Intelligent accessory inventory management method based on accessory purchasing-warehousing cooperation
US20140379423A1 (en) Market Price based Raw Material Procurement
JP6849550B2 (en) Logistics management support equipment and methods
JP2008105825A (en) Raw material transport ship allocation planning system and raw material ship allocation planning method
WO2020031430A1 (en) Composition ratio correction device, composition ratio correction method, and composition ratio correction program
US7606724B2 (en) Demand dispatch system and method
JP2010198340A (en) Inventory management device and inventory management method
JP5114682B2 (en) Order assignment apparatus, method, computer program, and computer-readable storage medium
JP2001273021A (en) Supporting system for stock control and supporting device for stock control
JP7364894B2 (en) Transport destination determining device, predictive model building device, method and program
CN116384718B (en) Intelligent decision-based supplier joint scheduling method, system and equipment

Legal Events

Date Code Title Description
A621 Written request for application examination

Free format text: JAPANESE INTERMEDIATE CODE: A621

Effective date: 20221104

A977 Report on retrieval

Free format text: JAPANESE INTERMEDIATE CODE: A971007

Effective date: 20230621

TRDD Decision of grant or rejection written
A01 Written decision to grant a patent or to grant a registration (utility model)

Free format text: JAPANESE INTERMEDIATE CODE: A01

Effective date: 20230725

A61 First payment of annual fees (during grant procedure)

Free format text: JAPANESE INTERMEDIATE CODE: A61

Effective date: 20230807

R151 Written notification of patent or utility model registration

Ref document number: 7339545

Country of ref document: JP

Free format text: JAPANESE INTERMEDIATE CODE: R151