JP2008105825A - Raw material transport ship allocation planning system and raw material ship allocation planning method - Google Patents

Raw material transport ship allocation planning system and raw material ship allocation planning method Download PDF

Info

Publication number
JP2008105825A
JP2008105825A JP2006291971A JP2006291971A JP2008105825A JP 2008105825 A JP2008105825 A JP 2008105825A JP 2006291971 A JP2006291971 A JP 2006291971A JP 2006291971 A JP2006291971 A JP 2006291971A JP 2008105825 A JP2008105825 A JP 2008105825A
Authority
JP
Japan
Prior art keywords
raw material
factory
ship
plan
allocation plan
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
JP2006291971A
Other languages
Japanese (ja)
Other versions
JP5011954B2 (en
JP2008105825A5 (en
Inventor
Minoru Nagai
実 永井
Yasuto Nagakura
康人 長倉
Hiroo Okada
寛生 岡田
Mikisuke Sasanuma
幹右 笹沼
Yuki Endo
雄輝 遠藤
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
JFE Steel Corp
Original Assignee
JFE Steel Corp
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by JFE Steel Corp filed Critical JFE Steel Corp
Priority to JP2006291971A priority Critical patent/JP5011954B2/en
Publication of JP2008105825A publication Critical patent/JP2008105825A/en
Publication of JP2008105825A5 publication Critical patent/JP2008105825A5/ja
Application granted granted Critical
Publication of JP5011954B2 publication Critical patent/JP5011954B2/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Management, Administration, Business Operations System, And Electronic Commerce (AREA)

Abstract

<P>PROBLEM TO BE SOLVED: To provide a raw material transport ship allocation planning system and a raw material ship allocation planning method, capable of producing an efficient berth unloading plan and stably supplying raw material. <P>SOLUTION: The raw material transport ship allocation planning system plans a ship allocation plan of steel raw material transport ship in the steel industry having a plurality of manufacturing plants. The raw material transport ship allocation planning system comprises a ship allocation plan planning device 110 planning a long period row material transport ship allocation plan, a ship allocation plan planning device 120 planning a short period row material transport ship allocation plan, and a factory-based cargo-handling adjusting device 210 adjusting a factory-based raw material transport ship allocation plan in each factory. The factory-based cargo-handling adjusting device 210 corrects the factory-based raw material transport ship allocation plan according to the short period raw material transport ship allocation plan. The ship allocation plan adjusting device 120 corrects the short period raw material transport ship allocation plan according to the corrected factory-based raw material transport ship allocation plan. By repeating those processing, the short period raw material ship allocation plan is planed. <P>COPYRIGHT: (C)2008,JPO&INPIT

Description

本発明は、鉄鋼石、石炭等の鉄鋼原料の海外からの輸送における輸送船の配船計画を作成する配船計画立案機能、及び輸送対象の積地である山元の作業進捗や船舶動静等の輸送作業進捗状況に変動が発生した場合の入船調整機能を有する原料輸送配船計画システム及び原料配船立案方法に関する。   The present invention relates to a ship allocation plan planning function for creating a ship allocation plan for transporting steel raw materials such as steel stone and coal from overseas, and the work progress of the mountain that is the loading target and the movement of the ship. TECHNICAL FIELD The present invention relates to a raw material transportation allocation plan system and a raw material allocation planning method having a ship entry adjustment function when a change occurs in the progress of transportation work.

従来から開発されている計画問題用の計算機システムには、計画立案のための制約条件や立案結果に関する評価基準を定式化し、数理計画的に解決する方式(数理計画方式)や、計画立案のための制約条件や立案担当者のノウハウをプログラムとして記述する方式(エキスパートシステム方式)等がある。   Conventionally developed computer systems for planning problems formulate constraints for planning and evaluation criteria for planning results, and solve them mathematically (mathematical programming), or for planning There are methods (expert system method) that describe the constraint conditions and know-how of the person in charge of planning as a program.

このエキスパートシステム方式は、制約条件や立案手順を変更し易い形で保持することを目指すものである(例えば特許文献1参照)。このような原料バースの最適制御装置は、原料船の入船予定、荷揚げ設備の修理予定、ヤード計画、荷揚げ能率等のデータを含む知識オブジェクトと、熟練オペレータの操業知識を含む知識ベース等を備えることにより、滞船費用が最小になるような原料船の接岸バース、荷揚げ作業時間等を決定し、荷役作業計画を自動化することを目指しており、原料輸送における荷揚げ作業の効率化を図るものである。
また、年間の輸送計画を実現するのに適した輸送船を決定するための適船選択知識ベース、輸送船の積載率向上を実現する積み合わせ決定知識ベース等を用いて配船計画装置により輸送タイミングを決定し、長期の原料輸送配船計画を立案すると共に、原料船動静の変動等に対応し、入船調整装置により日々の操作を行い、柔軟に計画の変更を行う技術もある(例えば特許文献2参照)。
特開平4−205204号公報 特開平8―272402号公報
This expert system method aims to hold constraint conditions and planning procedures in a form that can be easily changed (see, for example, Patent Document 1). Such an optimal control system for raw material berths includes a knowledge object including data such as a schedule for entering a raw material ship, a schedule for repairing a landing facility, a yard plan, and an unloading efficiency, and a knowledge base including operation knowledge of a skilled operator. Aims to automate the loading and unloading work plan by determining the berth berth and unloading work time of the raw material ship that minimizes the cost of berthing, and to improve the efficiency of unloading work in raw material transportation. .
In addition, using a ship allocation planning device using a suitable ship selection knowledge base for deciding a transport ship suitable for realizing an annual transport plan, a loading decision knowledge base for improving the loading ratio of a transport ship, etc. There is also a technology that decides the timing, formulates a long-term raw material transportation allocation plan, responds to fluctuations in the movement of the raw material ship, etc., performs daily operations with the ship entry adjustment device, and changes the plan flexibly (for example, patents) Reference 2).
JP-A-4-205204 JP-A-8-272402

しかしながら、原料船の入船計画を前提として荷揚げ作業計画を立案する必要があるため、実際に効率的な荷揚げ計画を実現するには、信頼性の高い入船計画が必須となる。
海外からの原料輸送計画においては、山元の積荷役作業の進捗状況や、天候等による船舶動静の変動の影響を受けたり、生産計画の変更により必要輸送対象の変化によって、当初の計画案に修正・変更が必要になったり、実際の作業状況と実績が乖離して使用不可能になることも多いという問題がある。即ち、一旦輸送計画を立案しても、外乱要因によって入船計画が変動し、その影響を受けて荷揚げ作業計画の変更を余儀無くされたり、計画自体に意味がなくなるような事態も少なくない。
However, since it is necessary to formulate an unloading work plan on the premise of an entry plan for a raw material ship, a highly reliable ship entry plan is indispensable to actually realize an efficient unloading plan.
In the raw material transportation plan from overseas, the original plan was revised due to changes in the necessary transportation targets due to changes in the shipping plan due to the progress of loading and unloading work in Yamamoto, fluctuations in vessel movement due to weather, etc.・ There are problems that it is often necessary to make changes, or that the actual work situation and actual results diverge and become unusable. In other words, once a transportation plan is made, there are not a few situations in which the ship entry plan fluctuates due to disturbance factors and the unloading work plan is forced to change due to the influence, or the plan itself becomes meaningless.

従来は、このような変動への対応として、配船担当者が積荷情報や船舶動静を随時確認し、その結果を基に、工場のヤード管理者と協議し、積み銘柄・量の変更や他船の振替え等の決定を行っていた。結局、工場の原料在庫、使用計画、輸送船の動静を別個に把握し、不都合の発生に応じて場当たり的な対応に終止していたのが実状である。
また、その結果原料在庫推移の長期的な見通しが立たず、原料の需給に対する安定した供給がし難いという問題もあった。
また、複数の工場がある製鉄会社においては、工場毎に制約条件が異なる場合がそれぞれ異なっており、また、至近の状況は工場でなければわからず、計画立案・調整といった2段階の処理では、各工場個別の制約条件を組み込んで処理することができなかったので、精度のよい計画を立案することはなかなか難しい。
Conventionally, in response to such fluctuations, the person in charge of dispatching has confirmed loading information and vessel movements as needed, and based on the results, consulted with the factory yard manager to change the loading brand and quantity, and so on. The decision was made to change ships. In the end, it was the actual situation that the raw material inventory of the factory, the usage plan, and the movement of the transport ship were grasped separately, and the response was stopped ad hoc according to the occurrence of inconvenience.
As a result, the long-term outlook for raw material inventory has not been established, and there has been a problem that it is difficult to stably supply raw materials for supply and demand.
Also, in steel companies that have multiple factories, there are different cases where the constraint conditions differ from factory to factory, and the closest situation must be the factory. In the two-stage process such as planning and adjustment, Since it was not possible to incorporate and process the constraint conditions of each factory, it is difficult to make a highly accurate plan.

本発明は、前記従来の問題点を解決するべくなされたものであり、効率的なバース荷揚げ計画の作成及び安定した原料供給を実現することのできる原料輸送配船計画システム及び原料配船立案方法を提供することを目的とする。   The present invention has been made to solve the above-mentioned conventional problems, and a raw material transport allocation plan system and a raw material allocation planning method capable of creating an efficient berth unloading plan and stable raw material supply. The purpose is to provide.

本発明に係る原料輸送配船計画システムは、複数の製造工場を有する鉄鋼業における鉄鋼原料輸送船の配船計画を立案する原料輸送配船計画システムであって、長期の原料輸送配船計画を立案する配船計画立案装置と、短期の原料輸送配船計画を作成する配船計画調整装置と、前記立案された長期及び短期の原料輸送配船計画がそれぞれ格納される第1の記憶手段と、各工場の工場別原料輸送配船計画を調整する工場別荷役調整装置と、各工場の調整された工場別原料輸送配船計画が格納される第2の記憶手段とを備える。
前記配船計画立案装置は、輸送船を割り当てるべき輸送銘柄を決定する輸送対象決定手段と、該決定された輸送銘柄を輸送船を割り当てる船舶決定手段と、該割り当てた輸送船の各工場における入船タイミングを決定する輸送タイミング決定手段とを備え、輸送船の各工場における入船タイミングを長期の原料輸送配船計画として前記第1の記憶手段に格納する。
前記配船計画調整装置は、前記長期の原料輸送配船計画を前記第1の記憶手段から読み込む入力手段と、前記長期の原料輸送配船計画に基づいて、工場毎の入船に関するタイミングを表示するとともに、修正入力を可能とする入船予定表示・入力手段と、前記長期の原料輸送配船計画に基づいて、船毎の航海に関するタイミングを表示するとともに、修正入力を可能とする航海予定表示・入力手段と、前記入船及び航海予定の修正入力に基づく在庫推移の予測を自動的に計算・表示する在庫推移計算・表示手段と、前記入船及び航海予定の修正入力に基づく早出・滞船料を自動的に計算・表示する早出・滞船料算出手段とを備え、修正された前記入船及び航海予定を前記短期の原料輸送配船計画として前記第1の記憶手段に格納する。
前記工場別荷役調整装置は、前記第1の記憶手段から前記短期の原料輸送配船計画のうち、各工場ごとの計画を読み込む入力手段と、該入力した各工場ごとの原料輸送配船計画に基づいて、各工場における入船に関するタイミングを表示するとともに、修正入力を可能とする入船予定表示・入力手段と、前記修正入力に基づく在庫推移の予測を自動的に計算・表示する在庫推移計算・表示手段と、前記修正入力に基づく早出・滞船料を自動的に計算・表示する早出・滞船料算出手段とを備え、各工場の調整された工場別原料輸送配船計画を前記第2の記憶手段に格納する。
The raw material transport allocation plan system according to the present invention is a raw material transport allocation plan system for drafting a distribution plan for a steel raw material transport ship in the steel industry having a plurality of manufacturing factories. A ship allocation plan planning device for planning, a ship allocation plan adjusting device for creating a short-term raw material transport allocation plan, and first storage means for storing the planned long-term and short-term raw material transport allocation plans, respectively. , A factory-specific cargo handling adjustment device that adjusts a factory-specific material transportation / shipment plan for each factory, and a second storage unit that stores the factory-specific material transportation / shipment plan adjusted for each factory.
The ship allocation planning device includes a transport object determining means for determining a transport brand to which a transport ship is to be assigned, a ship determining means for allocating the determined transport brand to a transport ship, and entry into each factory of the assigned transport ship. Transportation timing determining means for determining the timing, and the entry timing in each factory of the transport ship is stored in the first storage means as a long-term raw material transportation allocation plan.
The ship allocation plan adjusting device displays timing related to ship entry for each factory based on input means for reading the long-term material transport allocation plan from the first storage unit and the long-term material transport allocation plan. At the same time, the ship entry schedule display / input means that allows correction input and the timing related to the voyage for each ship are displayed based on the long-term raw material transportation allocation plan, and the voyage schedule display / input that allows correction input. Means, inventory transition calculation / display means for automatically calculating / displaying the forecast of inventory transition based on the correction input for the arrival and departure schedule, and early departure / stagnation fee based on the correction input for the arrival and departure schedule And the early entry and berthing fee calculation means for automatically calculating and displaying the information, and storing the modified entry and voyage schedule in the first storage means as the short-term raw material transportation allocation plan.
The factory-specific cargo handling adjustment device includes an input unit that reads a plan for each factory from the first storage unit in the short-term raw material transport allocation plan, and the input raw material transport allocation plan for each factory. Based on the ship entry timing at each factory, and the entry schedule display / input means that enables correction input, and inventory transition calculation / display that automatically calculates and displays the forecast of inventory transition based on the correction input And an early departure / arrival ship fee calculating means for automatically calculating / displaying an early departure / arrival ship fee based on the corrected input, and adjusting the factory-specific raw material transportation allocation plan by each factory Store in storage means.

また、本発明に係る原料輸送配船計画システムにおいて、前記配船計画調整装置は、前記工場別原料輸送配船計画を入力する入力手段を備え、前記第2の記憶手段に格納された前記工場別原料輸送配船計画を前記入力手段により取り込んで、前記工場別原料輸送配船計画に基づいて短期の原料輸送配船計画を調整する。
また、本発明に係る原料輸送配船計画システムにおいて、前記工場別荷役調整装置は、各工場毎の地域制約条件や設備制約条件に関するデータを入力する工場制約データ入力手段を備える。
Further, in the raw material transport allocation plan system according to the present invention, the shipping allocation adjustment device includes an input unit for inputting the factory-specific raw material transfer allocation plan, and the factory stored in the second storage unit A separate material transportation / shipping plan is fetched by the input means, and a short-term material transportation / shipping plan is adjusted based on the factory-specific material transportation / shipping plan.
Moreover, in the raw material transportation / ship allocation planning system according to the present invention, the factory-specific cargo handling adjustment device includes factory constraint data input means for inputting data on regional constraint conditions and facility constraint conditions for each factory.

また、本発明に係る原料配船立案方法は、上記の原料輸送配船計画システムを用いて原料輸送配船計画を立案する方法であって、
前記工場別荷役調整装置が、前記短期の原料輸送配船計画に基づいて、工場別原料輸送配船計画を修正するステップと、
前記配船計画調整装置が、前記修正された工場別原料輸送配船計画に基づいて、前記短期の原料輸送配船計画を修正するステップと
を繰り返して、原料配船計画を立案する。
Further, the raw material allocation plan method according to the present invention is a method for drafting a raw material transport allocation plan using the above-mentioned raw material transport allocation plan system,
A step of modifying the factory-specific material transport allocation plan based on the short-term material transport allocation plan,
The ship allocation plan adjusting device repeats the step of correcting the short-term material transport allocation plan based on the corrected factory-specific material transport allocation plan, and formulates a material allocation plan.

本発明においては、例えば本社(配船計画立案装置・配船計画調整装置)と工場(工場別荷役調整装置)との信号授受を共有化するためのシステムを構築し、本社で立案・調整した計画を各工場に送り、各工場で計画を各工場特有の制約条件で変更し、その計画を本社に送り、その工場で変更された情報に基づいて、再度計画を立案するようにしたので、最新の情報を電子データを用いて、双方で確認でき、業務効率が向上し、迅速となった。また、本社では把握しきれない、各工場特有の制約条件については、各工場で入力できる様にし、その各工場の情報を本社で統括し、さらに各工場にその情報を伝達する様にしたので、従来に比べて、細かい条件での配船計画が立案・修正できるようになっている。また、配船スケジュールに基づいて、工場の各銘柄について、在庫量や使用量を予測する機能を備えて、配船スケジュールを修正するようにしたので、修正する際の判断が容易になった。さらに、前記在庫量の予測に加えて、配船スケジュールに基づいて、滞留料や早出料を計算する機能を設け、滞留料や早出料からコストの最適なスケジュールを評価できるようになった。   In the present invention, for example, a system for sharing signals between the head office (ship allocation planning device / ship allocation planning adjustment device) and the factory (factory handling adjustment device) is constructed, and is planned and adjusted at the head office. Since the plan was sent to each factory, the plan was changed at each factory with the constraints specific to each factory, the plan was sent to the headquarters, and the plan was made again based on the information changed at that factory. The latest information can be confirmed on both sides using electronic data, which has improved operational efficiency and speed. In addition, the restriction conditions unique to each factory that cannot be grasped at the head office can be entered at each factory, the information of each factory is integrated at the head office, and the information is transmitted to each factory. Compared to the conventional system, it is now possible to make and modify a ship allocation plan under detailed conditions. In addition, based on the ship allocation schedule, a function for predicting the amount of inventory and usage for each brand in the factory is provided, and the ship allocation schedule is corrected, so that it is easy to make decisions when making corrections. Furthermore, in addition to the forecast of the inventory amount, a function for calculating a stay fee and an early delivery fee based on the ship allocation schedule is provided, so that an optimum schedule of costs can be evaluated from the stay fee and early delivery fee.

以下、本発明の実施形態に係る原料輸送配船計画システムを、[全体システム]、[本社原料輸送配船システム]、[工場原料輸送配船システム]及び[工場別配船計画データの反映]に項を分けて図面を参照しながら詳細に説明する。
[全体システム]
図1は、本発明の原料輸送配船計画システムの全体構成を示す図である。本社で配船計画を立案・調整するための、本社原料輸送配船システム100と、工場で配船計画を調整するための工場原料輸送配船システム200とから構成される。
Hereinafter, the material transport ship allocation planning system according to the embodiment of the present invention is referred to as [Overall system], [Headquarters material transport ship allocation system], [Factory material transport ship allocation system] and [Reflecting factory-specific ship allocation plan data] This will be described in detail with reference to the drawings.
[Whole system]
FIG. 1 is a diagram showing an overall configuration of a raw material transportation / shipping planning system according to the present invention. The headquarters raw material transportation / shipping system 100 for planning / adjusting the ship allocation plan at the head office and the factory raw material transportation / shipping system 200 for adjusting the ship allocation plan at the factory are configured.

本社原料輸送配船システム100は、配船計画立案装置110、配船計画調整装置120、配船DB(データベース)130から構成されており、原料購買システム301、原料配分システム302、出帆管理システム303、工場原料管理システム304から配船計画を立案する際に必要なデータを入力できる様に、例えば、LAN、WANなどネットワーク回線や専用回線などで接続されている。なお、配船計画立案装置110及び配船計画調整装置120はコンピュータシステムによってそれぞれ構成されているものとする。   The headquarters material transportation / shipping system 100 includes a ship assignment planning device 110, a ship assignment plan adjusting device 120, and a ship assignment DB (database) 130. A material purchase system 301, a material distribution system 302, a sailing management system 303 are provided. For example, LAN and WAN are connected via a network line or a dedicated line so that necessary data can be input from the factory raw material management system 304 when making a ship allocation plan. It is assumed that the ship allocation plan planning device 110 and the ship allocation plan adjustment device 120 are each configured by a computer system.

配船計画立案装置110は、半年、3ヶ月、または1年に一回といったタイミングで、長期の配船計画を立案するための装置である。これは、半年、3ヶ月、または1年に1回策定される、販売計画や製造計画などに対応して立案されるものであり、その計画されたデータは、配船DB130に記憶される。この長期の配船計画に対して、配船計画調整装置120は、週単位や日単位での短期の計画を立案するための装置である。そして、長期の配船計画を配船DB130から読み出して、長期計画立案時から現時点までの実績を入力し、その最新の状況に基づいて、短期の配船計画を立案し、その期間について長期の配船計画を修正する。そして、一週間、数週間先までの最新の計画を作成し、配船DB130に最新の配船計画を記憶する。   The ship allocation planning apparatus 110 is an apparatus for preparing a long-term ship allocation plan at a timing such as once every six months, three months, or once a year. This is formulated in response to a sales plan, a production plan, or the like, which is formulated once every six months, three months, or one year, and the planned data is stored in the dispatching DB 130. In response to this long-term ship allocation plan, the ship allocation plan adjustment device 120 is a device for drafting a short-term plan in units of weeks or days. Then, the long-term ship allocation plan is read from the ship allocation DB 130, the results from the time of the long-term plan formulation to the present time are input, the short-term ship allocation plan is formulated based on the latest situation, Revise the ship allocation plan. Then, the latest plan for one week or several weeks ahead is created, and the latest dispatching plan is stored in the dispatching DB 130.

工場原料輸送配船システム200は、複数の製造工場の各工場にそれぞれ配置されるものであり、これはコンピュータシステムによって構成されている。工場原料輸送配船システム200は、本社原料輸送配船システム100の配船DB130から本社で立案した計画データを入力したり、工場原料輸送配船システム200のデータを本社原料輸送配船システム100に出力したりできるように、例えば、LAN、WANなどネットワーク回線や専用回線などで接続されている。この工場原料輸送配船システム200は、工場別荷役調整装置210と工場別配船DB220から構成されている。工場別荷役調整装置210では、本社原料輸送配船システム100の配船DB130から、自工場のデータのみを入力し、本社で立案した配船計画を確認できる様に表示させるとともに、各工場の最新の制約状況(満潮時刻、バース稼動状況、工場の修理日、官公庁の稼働日など)に合わせて、調整を行う。そして、調整された計画は、工場別配船DB(データベース)220に記憶される。この工場別配船DB220のデータは、本社に送信、または本社から読み出して、他の工場のデータと統合して、本社で再調整され、全社の配船計画として、修正される。各工場で調整された計画を統合した結果、不具合が有った場合には、本社での調整、工場での調整が、不具合がなくなるまで、繰り返される。
なお、本社原料輸送配船システム100及び工場原料輸送配船システム200は、分離された別のシステムとして記載しているが、例えば、本社に全てのシステムを置き、工場には端末のみを設置するようにしてもよいし、他の形態であっても実現できることは言うまでも無い。
The factory raw material transport / shipping system 200 is arranged in each factory of a plurality of manufacturing factories, and is constituted by a computer system. The factory raw material transportation / shipping system 200 inputs plan data prepared by the headquarters from the ship assignment DB 130 of the headquarters raw material transportation / shipping system 100, or the factory raw material transportation / shipping system 200 data is input to the headquarters raw material transportation / shipping system 100. For example, it is connected via a network line such as a LAN or WAN, or a dedicated line so that it can be output. The factory raw material transportation / shipping system 200 includes a factory-specific cargo handling adjustment device 210 and a factory-specific ship allocation DB 220. The factory-specific loading / unloading adjustment device 210 inputs only the data of its own factory from the dispatching DB 130 of the headquarters material transportation and dispatching system 100 and displays it so that the dispatching plan planned by the headquarters can be confirmed. Adjustments will be made in accordance with the conditions of restrictions (high tide time, berth operation status, factory repair date, government office operation date, etc.). Then, the adjusted plan is stored in the factory-specific ship allocation DB (database) 220. The data in the factory-based ship allocation DB 220 is transmitted to the head office or read from the head office, integrated with the data of other factories, readjusted at the head office, and corrected as a company-wide ship allocation plan. If there is a problem as a result of integrating the plans adjusted at each factory, the adjustment at the head office and the adjustment at the factory are repeated until the problem disappears.
In addition, although the headquarters material transportation / shipping system 100 and the factory material transportation / shipping system 200 are described as separate systems, for example, all systems are placed in the headquarters and only terminals are installed in the factory. Needless to say, it can be realized even in other forms.

[本社原料輸送配船システム100]
次に、本社原料輸送配船システム100の詳細の構成について、図2を用いて説明する。配船計画立案装置110は、データ入出力部111、輸送対象決定部112、船舶選択部113、輸送スケジュール決定部114及び輸送タイミング決定部115から構成される。データ入出力部111は、図1に示された原料購買システム301、原料配分システム302、工場原料管理システム304から長期の配船計画を立案するために必要な情報を入力する機能を有するとともに、立案した配船計画を配船DB130に出力し、記憶させる機能を有する。輸送対象決定部112は輸送スケジュールを決定する原料の銘柄を決定する処理を行い、船舶選択部は輸送対象決定部できまった当該輸送対象について、輸送適船を割り当てる処理をおこなう。輸送スケジュール決定部114は、その決定された輸送船に関して、当該輸送対象銘柄の他の積み合わせ銘柄を、決定する処理を行う。輸送タイミング決定部115は、所定の配船基準に従って輸送タイミングを決定する。そのようにして作成された計画を、船舶航海予定データ及び船舶積み銘柄・量データを含む配船計画データをデータ入出力部111を介して、配船DB130に書き込む。
[Headquarters material transportation and shipping system 100]
Next, a detailed configuration of the headquarters material transportation / shipment system 100 will be described with reference to FIG. The ship allocation planning apparatus 110 includes a data input / output unit 111, a transport target determining unit 112, a ship selecting unit 113, a transport schedule determining unit 114, and a transport timing determining unit 115. The data input / output unit 111 has a function of inputting information necessary for creating a long-term ship allocation plan from the raw material purchasing system 301, the raw material distribution system 302, and the factory raw material management system 304 shown in FIG. It has a function of outputting the planned ship allocation plan to the ship allocation DB 130 and storing it. The transport object determining unit 112 performs a process of determining the brand of the raw material for determining the transport schedule, and the ship selecting unit performs a process of assigning a suitable transport ship to the transport object that has been created by the transport object determining unit. The transport schedule determination unit 114 performs a process of determining other combined brands for the transport target brand with respect to the determined transport ship. The transport timing determination unit 115 determines the transport timing according to a predetermined ship allocation standard. The plan created in this manner is written in the ship assignment DB 130 via the data input / output unit 111, with the ship assignment plan data including the ship voyage schedule data and ship loading brand / quantity data.

一方、配船計画調整装置120は、データ入出力部121、入船予定表示・変更部122、船舶航海予定表示・変更部123、在庫推移予測計算部124、在庫推移表示部125及び早出・滞船料算出部126から構成され、配船計画立案装置110で作成された長期の配船計画を、週単位や日単位での計画に修正する。データ入出力部121では、配船DB130から長期の計画を入力するとともに、日々の操業における工場在庫計画、使用計画、山元の荷役状況のズレ、原料船動静の変動に対応するために、工場銘柄別原料使用計画データ、工場銘柄別原料使用実績データ、工場銘柄別原料在庫実績データ、原料船動静最新データ、積地荷役進捗最新データを読み込む。また、修正された計画データを配船DBに出力し、記憶する。   On the other hand, the ship allocation plan adjustment device 120 includes a data input / output unit 121, a ship arrival schedule display / change unit 122, a ship voyage schedule display / change unit 123, an inventory transition prediction calculation unit 124, an inventory transition display unit 125, and an early departure / stagnation ship. The long-term ship allocation plan that is configured by the fee calculation unit 126 and created by the ship allocation plan planning apparatus 110 is corrected to a weekly or daily plan. In the data input / output unit 121, a long-term plan is input from the ship assignment DB 130, and in order to cope with fluctuations in factory inventory plans, usage plans, loading / unloading status of Yamamoto, and movements of raw material ships in daily operations. Loads raw material usage plan data, raw material usage data by factory brand, raw material inventory data by factory brand, raw material ship movement latest data, and loading / unloading progress latest data. Further, the corrected plan data is output to the dispatching DB and stored.

入船予定表示・変更部122は、データ入出力部121を介して入力されたデータにもとづいて、各工場の各バースへの入船予定を、バース単位に、表示する処理を行う。また、表示された入船予定を変更する機能も有し、必要に合わせて予定の修正が可能となっている。船舶航海予定予定表示・変更部123は、データ入出力部を介して入力されたデータにもとづいて、各船舶の航海予定を、船舶単位に、その航海予定を表示する。また、表示された航海予定を変更する機能も有し、必要に合わせて予定の修正が可能となっている。在庫推移予測計算部124は、データ入出力部を介して入力されたデータにもとづいて、各原料銘柄の種別(塊鉱石・粉鉱石などの鉄鉱石の鉱種、強粘炭・非微粘炭などの原料炭の炭種)ごとに、現状の在庫実績量と、今後の受入予定量と、製造使用予定量とを比較して、今後の在庫の推移を計算する。在庫推移表示部125は、その計算された在庫推移の結果を、画面に表示する。早出・滞船料算出部126は、配船スケジュールに基づいて、各船の早出料(despatch money)や予定期間を超えた場合の滞船料(demurrage)を計算する。この算出において早出料、滞船料の算出に必要な単位時間あたりの料金は、予め船毎や会社毎に設定されて、演算部にパラメータとして記憶されており、増減滞在時間を乗じることによって求めることができる。   Based on the data input via the data input / output unit 121, the entry schedule display / change unit 122 performs a process of displaying the entry schedule to each berth of each factory in units of berths. It also has a function to change the displayed entry schedule, and the schedule can be modified as necessary. The ship voyage schedule display / change unit 123 displays the voyage schedule of each ship for each ship based on the data input via the data input / output unit. It also has a function to change the displayed sailing schedule, and the schedule can be modified as necessary. Based on the data input via the data input / output unit, the inventory transition prediction calculation unit 124 determines the type of each raw material brand (mineral type of iron ore such as lump ore or fine ore, strong or non-thin cohesive coal For each type of coking coal, etc.), compare the current actual inventory amount, the future acceptance amount, and the planned production and usage amount to calculate the future inventory change. The inventory transition display unit 125 displays the calculated inventory transition result on the screen. The early departure / departure fee calculation unit 126 calculates an early departure fee (despatch money) for each ship and a demurrage when the scheduled period is exceeded, based on the ship allocation schedule. In this calculation, the fee per unit time required for calculating the early departure fee and the berthing fee is set in advance for each ship or company and is stored as a parameter in the calculation unit, and is obtained by multiplying the increase / decrease stay time. be able to.

入船予定、船舶航海予定、在庫推移、早出・滞船料に基づいて、配船計画調整を行う担当者(操作者)は、入船予定変更、航海予定変更を行って、コストなど最適な結果が得られる計画になるまで、作業を繰り返す。このように、工場への入船予定の変動や需給の不好況等の問題が生じれば、配船DB130にアクセスしながら、船毎の積み銘柄・量の変更、他工場揚げ予定の積荷の振替え、他船への積込み変更、航海途中の他積地への寄港の追加等の指定を行うことができる。   The person in charge (operator) who adjusts the ship allocation plan based on the schedule for entering the ship, the schedule for ship voyage, inventory transitions, early departure and berthing charges, changes the schedule for entering the ship, changes the schedule for voyage, and provides optimal results such as costs. Repeat until you get a plan. In this way, if problems such as fluctuations in the schedule of entering the factory and unfavorable supply and demand conditions occur, changing the loading brand / amount for each ship, transferring the cargo scheduled to be lifted by other factories, while accessing the dispatching DB 130 It is possible to specify loading changes to other ships, addition of port calls to other loading points during the voyage, etc.

また、配船計画調整装置120には、積地毎の輸送船舶の入港予定情報、船舶毎の航海予定情報、原料使用計画と入港予定に基づく工場銘柄別の原料在庫推移を随時表示可能とし、日々の操業において、需給担当者がそれを監視し、適正在庫範囲内に推移が収まらない場合は、入船調整を実施することもできる。例えば、ある銘柄の在庫切れが近い場合は、他工場向けの輸送船の振替えや寄港順変更、山元の荷役状況により停泊時間が長い場合は、積込み銘柄や量の変更を指定する。   In addition, the ship allocation plan adjustment device 120 can display the port entry schedule information of the transport ship for each loading point, the ship schedule information for each ship, the raw material inventory change by factory brand based on the raw material use plan and the port entry schedule, In day-to-day operations, supply and demand personnel can monitor it, and if the transition does not fall within the appropriate inventory range, it is also possible to adjust ship entry. For example, if a certain brand is almost out of stock, transfer of a shipping ship for another factory, change in port order, or if the berth is long due to the cargo handling situation at Yamamoto, change the loading brand or quantity.

次に、この本社原料輸送配船システム100の処理過程を、配船計画立案装置110について図4を用いて説明する。
データ入出力部111においては、原料購買システムから図7に示すような年間原料購入計画データや、図8に示すような原料船年間稼働計画データを、原料配分システム302から図9に示すような工場銘柄別原料使用計画データ、工場原料管理システム304から図10に示すような工場銘柄別原料在庫予定データを入力する(Step101)。
Next, the processing process of the headquarters material transportation / shipping system 100 will be described with reference to FIG.
In the data input / output unit 111, annual raw material purchase plan data as shown in FIG. 7 from the raw material purchase system and raw material ship annual operation plan data as shown in FIG. 8 are sent from the raw material distribution system 302 as shown in FIG. Raw material use plan data by factory brand and raw material stock schedule data by factory brand as shown in FIG. 10 are input from the factory raw material management system 304 (Step 101).

次に、輸送対象決定部112においては、輸送スケジュールを決定する原料の銘柄を選択し、決定する処理を行う。また、この時、計画立案する期間内(例えば、6ヶ月、3ヶ月、1年など)の各年月旬や週毎に、各工場ごと、各銘柄ごとに、その量を設定する(Step102)。これは、図17のような画面に表形式で各工場・各銘柄に対する各年月ごとの、予定量を入力するための入力画面を用いて入力する。そして、この入力された値に基づいて。操業上一定量以上の在庫を必要とする必須銘柄、在庫余裕の少ない銘柄が先に選ばれる等、輸送の重要度、緊急度の高い銘柄から順に選定していく。   Next, in the transportation object determination unit 112, a brand of a material for which a transportation schedule is determined is selected and a process of determining is performed. At this time, the amount is set for each factory and each brand every month or week within the planning period (for example, 6 months, 3 months, 1 year, etc.) (Step 102). . This is entered on a screen as shown in FIG. 17 by using an input screen for inputting a scheduled amount for each factory and each brand in a table format. And based on this input value. Select from the brands with the highest importance and importance of transportation, such as the essential brands that require a certain amount of inventory for operation and the brands with a small stock margin.

次に、船舶選択部113においては、使用可能な船舶候補に対して、輸送対象決定部できまった当該輸送対象を、その候補の船舶に対して、割り当てる処理をおこなう(Step103)。該当銘柄の産地の港への入港に適していること、現在位置が近いこと、傭船料が低いこと等を選定の基準にしたり、例えば「当該航路の割当て回数累計が年間稼動計画の回数以内である船を選択する」、「在庫切り日・調整日数≧入船日である船を選択する」といった船舶選択知識ベースを用いて、自動的に決定してもよいし、全て自動的に決定できないときは、画面に使用可能な船舶のリストと、輸送対象のリストを表示して、どの船舶に、どの輸送対象を割り当てるかを選択していく入力画面を用いて入力してもよい。また、操作者が、手動入力で全てのデータを入力してもよい。そして、輸送船舶を選定できたか判定し、該当銘柄の輸送に適する輸送船舶を選定できない場合は、その銘柄の輸送を諦め、ステップ101の輸送対象銘柄選定処理に戻り、他の銘柄の選定を行う(Step104)。必要な輸送対象に対して完了するまで繰り返す。輸送船舶を選定できた場合には、輸送ロット編成処理で、該当銘柄に同産地や輸送経路上の産地からの銘柄の積み合わせを加えて、輸送単位を編成する(Step105)。積み合わせをする銘柄は、輸送対象銘柄選定処理と同様の基準と、輸送経路の適合性によって選べばよい。   Next, in the ship selection part 113, the process which allocates the said transport target made by the transport target determination part with respect to the useable ship candidate with respect to the ship of the candidate is performed (Step103). Based on selection criteria such as being suitable for entry to the port of production of the relevant brand, close current position, low chartering fees, etc. When a ship selection knowledge base such as “Select a ship” or “Select a ship with a stock cut-out date / adjustment days ≧ ship entry date” may be automatically determined or when all cannot be determined automatically May be input using an input screen in which a list of ships that can be used and a list of transportation objects are displayed on the screen, and which transportation object is assigned to which ship. Further, the operator may input all data by manual input. Then, it is determined whether or not a transport ship has been selected. If a transport ship suitable for transporting the corresponding brand cannot be selected, the transport of that brand is abandoned, and the process returns to the target brand selection process in step 101 to select another brand. (Step 104). Repeat until required transport object is complete. If a transport ship can be selected, a transport unit is organized by adding the brands from the same production area or production area on the transportation route to the corresponding brand in the transportation lot organization process (Step 105). The brands to be stacked may be selected according to the same criteria as the transport brand selection process and the suitability of the transport route.

輸送スケジュール決定部114においては、積み、揚げの各経由地への輸送船舶入港日時を予測し、船舶入港スケジュール、荷役作業スケジュールを決定する(Step106)。荷役作業スケジュール決定は、経由する積地、揚地の全てについて行う。例えば、「最大積み合わせ銘柄数を守る」「積み合わせ銘柄は同一航路内から選択する」「同工場内の銘柄ごと配分率に応じて各積載量を決定する」等の輸送スケジュール決定知識ベースを用いて、自動的にスケジュールを決定してもよいし、操作者が手動で入力してもよい。
最後に、必要量を計画したか否か判定し、これらの処理を全揚地(工場)において輸送が必要な銘柄全てについて行うか、必要量を達成するまで繰り返す(Step107)。
The transport schedule determination unit 114 predicts the date and time of arrival of a transport ship to each transit point for loading and unloading, and determines a ship port entry schedule and a cargo handling work schedule (Step 106). The cargo handling work schedule is determined for all loading and unloading sites. For example, a transportation schedule determination knowledge base such as “Protect the maximum number of products to be combined”, “Select the products to be combined from the same route”, “Determine each load amount according to the distribution rate for each product in the factory”, etc. The schedule may be automatically determined or manually input by the operator.
Finally, it is determined whether the necessary amount is planned, and these processes are performed for all brands that need to be transported in all landing sites (factories), or are repeated until the necessary amount is achieved (Step 107).

このようにして作成された計画を、船舶航海予定データ及び船舶積み銘柄・量データを含む配船計画データをデータ入出力部111を介して、配船DB130に書き込む。この配船DB130に書き込む配船データは、図15に示すようなデータであり、各船コードに対して、「積み港コード」、「積み年月日」、「銘柄コード」、「積み重量」の組合せ、と「揚げ港コード」、「揚げ年月日」、「銘柄コード」、「揚げ重量」の組合せが、年月日順に並ぶような形態である。ここで、「揚げ港コード」は実質工場種別を示すコードであるが、後述する工場毎にデータ分類を容易にするために「工場コード」を配給計画データに加えても良い。   The plan created in this manner is written into the ship assignment DB 130 via the data input / output unit 111, with the ship assignment plan data including the ship voyage schedule data and ship loading brand / quantity data. The ship allocation data to be written in the ship allocation DB 130 is data as shown in FIG. 15. For each ship code, “loading port code”, “loading date”, “brand code”, “loading weight” And the combination of “Fried Port Code”, “Fried Date”, “Brand Code”, and “Fried Weight” are arranged in order of date. Here, the “ship port code” is a code indicating the actual factory type, but the “factory code” may be added to the distribution plan data in order to facilitate data classification for each factory described later.

このように決定された長期の配船計画データを、本社において、日々の操業に合わせて短期の配船計画に調整するための、配船計画調整装置120の処理過程を、図5を用いて説明する。
データ入出力部121によって、原料配分システム302から図9に示すような工場銘柄別原料使用計画データ、工場原料管理システム304から図11に示すような工場銘柄別原料使用実績データ、図12に示すような工場銘柄別原料在庫実績データ、出帆管理システム303から図14に示すような原料船動静最新情報、図13に示すような積地荷役進捗最新情報等の必要データを入力する(Step201)。ここで、工場銘柄別原料使用計画情報は、長期計画を立案した際とは異なり日々の運用において、逐次更新されている最新のものである。
The processing process of the ship allocation plan adjusting device 120 for adjusting the long-term ship allocation plan data determined in this way to a short-term ship allocation plan in accordance with daily operations at the head office is shown in FIG. explain.
By the data input / output unit 121, the raw material use plan data by factory brand as shown in FIG. 9 from the raw material distribution system 302, the raw material use result data by factory brand as shown in FIG. 11 from the factory raw material management system 304, shown in FIG. Necessary data such as factory stock-specific raw material inventory result data, sailing management system 303 as shown in FIG. 14 as raw material ship movement and static information, as shown in FIG. 13 and loading / unloading progress latest information as shown in FIG. 13 are input (Step 201). Here, the raw material use plan information for each factory brand is the latest information that is sequentially updated in daily operations, unlike when a long-term plan is drawn up.

次に、入船予定表示・変更部122を用いて、最新の配船計画に基づいて、図18に示すように、各工場の各バース毎に入船予定を表示する(Step202)。同様に、船舶航海予定表示・変更部123を用いて、船舶ごとの航海予定を表示(Step203)を行う。さらに、在庫推移予測計算部124において在庫を計算し、在庫推移表示部125に図19に示すように画面にグラフ表示させる(Step204)。そして、早出・滞船料算出部126において、配船スケジュールに基づいて、各船の早出料(despatch money)や予定期間を超えた場合の滞船料(demurrage)を計算する。この算出において早出料、滞船料の算出に必要な単位時間あたりの料金は、予め船毎や会社毎に設定されて、演算部にパラメータとして記憶されており、増減滞在時間を乗じることによって求めればよい(Step205)。   Next, using the arrival schedule display / change unit 122, the arrival schedule is displayed for each berth of each factory as shown in FIG. 18 based on the latest allocation plan (Step 202). Similarly, the voyage schedule for each ship is displayed using the ship voyage schedule display / change unit 123 (Step 203). Further, the inventory transition prediction calculation unit 124 calculates the inventory, and causes the inventory transition display unit 125 to display a graph on the screen as shown in FIG. 19 (Step 204). Then, the early departure / delayed vessel fee calculation unit 126 calculates an early departure fee (despatch money) for each vessel and a demurrage when the scheduled period is exceeded based on the ship allocation schedule. In this calculation, the fee per unit time required for calculating the early departure fee and the berthing fee is set in advance for each ship or company and stored as a parameter in the calculation unit, and is obtained by multiplying the increase / decrease stay time. (Step 205).

そして、これらの表示された情報に基づいて、計画と実績とのズレが大きいか否か判断をする(Step206)。この計画と実績とのずれは、在庫量の許容範囲を予め設定しておき、その範囲内に予測値が入っているか否かを自動的に判断するようにしてもよいし、操作者が画面で、時間変化の傾向などから判断するようにしてもよい。その結果、ズレが大きい場合には入船予定を変更(Step208)、航海予定を変更(Step209)し、Step202に戻り、前述の処理を繰り返す。そして、計画と実績とのズレがなくなったら、更新後の計画データを配船DBに出力、記憶する(Step207)。このような変更指定を行い、その結果に基づく在庫推移をシミュレートしながら、本社原料輸送配船システム100では、入船調整を行うことができる。   And based on these displayed information, it is judged whether the gap with a plan and a track record is large (Step206). The deviation between the plan and the actual result may be determined by setting an allowable range of the stock quantity in advance and automatically determining whether or not the predicted value is within the range. Thus, the determination may be made based on the tendency of time change. As a result, if the deviation is large, the entry schedule is changed (Step 208), the navigation schedule is changed (Step 209), the process returns to Step 202, and the above-described processing is repeated. Then, when there is no difference between the plan and the actual result, the updated plan data is output and stored in the ship assignment DB (Step 207). The headquarters material transportation / shipping system 100 can perform ship entry adjustment while performing such a change designation and simulating the inventory transition based on the result.

[工場原料輸送配船システム200]
次に、図3を用いて、工場毎に置かれる工場原料輸送配船システム200を説明する。
工場原料輸送配船システム200は、工場別荷役調整装置210と工場別配船DB(データベース)220とから構成される。工場別荷役調整装置210は、データ入出力部211、入船予定表示・変更部212、在庫推移予測計算部213、在庫推移表示部214及び早出・滞船料算出部215から構成され、本社原料輸送配船システム100で作成された日々の配船計画を、各工場独自の制約条件(満潮時刻、バース稼動状況、工場の修理日、官公庁の稼働日など)に基づいて、さらに確度の高い計画に修正する。また、工場別配船DB220は、各工場毎で修正された配船計画データを記憶するデータベースである。
[Factory raw material transport and distribution system 200]
Next, a factory raw material transport / shipment system 200 placed for each factory will be described with reference to FIG.
The factory raw material transportation / shipping system 200 includes a factory-specific cargo handling adjustment device 210 and a factory-specific ship allocation DB (database) 220. The factory-specific cargo handling adjustment device 210 includes a data input / output unit 211, a ship arrival schedule display / change unit 212, an inventory transition prediction calculation unit 213, an inventory transition display unit 214, and an early departure / stagnation fee calculation unit 215. The daily ship assignment plan created by the ship assignment system 100 will be a more accurate plan based on each factory's unique constraints (high tide time, berth operation status, factory repair date, government office operation date, etc.) Correct it. Further, the factory-based ship allocation DB 220 is a database that stores ship allocation plan data corrected for each factory.

データ入出力部211は、本社システムの配船DB130で修正された自分の工場に関する、日々の配船計画を入力するとともに、工場内の操業状況や各工場の港別の制約条件の情報データを読み込む。また、修正された計画データを工場別配船DB220に出力し、記憶する。入船予定表示・変更部212は、データ入出力部211を介して入力されたデータにもとづいて、自工場の各バースへの入船予定を、バース単位に、表示する処理を行う。また、表示された入船予定を変更する機能も有し、必要に合わせて予定の修正が可能となっている。在庫推移予測計算部213は、データ入出力部211を介して入力されたデータにもとづいて、各原料銘柄ごとに、現状の在庫実績量と、今後の受入予定量と、製造使用予定量とを比較して、今後の在庫の推移を計算する。在庫推移表示部214は、その計算された在庫推移の結果を、画面に表示する。早出・滞船料算出部215は、配船スケジュールに基づいて、各船の早出料(despatch money)や予定期間を超えた場合の滞船料(demurrage)を計算する。この算出において早出料、滞船料の算出に必要な単位時間あたりの料金は、予め船毎や会社毎に設定されて、演算部にパラメータとして記憶されており、増減滞在時間を乗じることによって求めることができる。   The data input / output unit 211 inputs a daily ship allocation plan related to its own factory corrected in the ship allocation DB 130 of the head office system, and also provides information on the operation status in the factory and the constraint conditions for each factory port. Read. Further, the corrected plan data is output to the factory-based ship allocation DB 220 and stored. The entry schedule display / change unit 212 performs a process of displaying the entry schedule to each berth of the own factory in units of berths based on the data input via the data input / output unit 211. It also has a function to change the displayed entry schedule, and the schedule can be modified as necessary. Based on the data input via the data input / output unit 211, the inventory transition prediction calculation unit 213 calculates the current actual inventory amount, the future acceptance amount, and the scheduled production / use amount for each raw material brand. Compare and calculate future inventory trends. The inventory transition display unit 214 displays the calculated inventory transition result on the screen. The early departure / shipment fee calculation unit 215 calculates a departure fee (despatch money) for each ship and a demurrage when the scheduled period is exceeded based on the ship allocation schedule. In this calculation, the fee per unit time required for calculating the early departure fee and the berthing fee is set in advance for each ship or company and is stored as a parameter in the calculation unit, and is obtained by multiplying the increase / decrease stay time. be able to.

配船計画調整を行う担当者(操作者)は、入船予定、在庫推移、早出・滞船料に基づいて、入船予定変更、航海予定変更を行い、コストなど最適な結果が得られる計画になるまで、作業を繰り返す。このように、各工場特有の制約条件を考慮することが可能となり、確度の高い計画が立案できる。   The person in charge (operator) who adjusts the ship allocation plan changes the ship arrival schedule and the voyage schedule based on the arrival schedule, inventory transitions, early departure and berthing charges, and plans to obtain optimal results such as costs. Repeat the process until In this way, it becomes possible to consider the constraint conditions unique to each factory, and a highly accurate plan can be made.

次に、工場別荷役調整装置210の処理を図6を用いて説明する。
データ入出力部211によって、工場原料管理システム304から図11に示すような工場銘柄別原料使用実績データ、図12に示すような工場銘柄別原料在庫実績データなどの必要データを入力する(Step301)。
次に、入船予定表示・変更部212を用いて、本社システムから入力した、最新の配船計画に基づいて、自工場の各バース毎に入船予定を表示する(Step302)。自工場のデータを抽出するには、図15の配船計画データの揚げ港コードあるいは工場コードをキーとして、抽出すればよい。
次に、在庫推移予測計算部213において在庫を計算し、在庫推移表示部214の画面にグラフ表示させる(Step303)。そして、早出・滞船料算出部215において、配船スケジュールに基づいて、各船の早出料(despatch money)や予定期間を超えた場合の滞船料(demurrage)を計算する。この算出において早出料、滞船料の算出に必要な単位時間あたりの料金は、予め船毎や会社毎に設定されて、演算部にパラメータとして記憶されており、増減滞在時間を乗じることによって求めればよい(Step304)。
Next, processing of the factory-specific cargo handling adjustment device 210 will be described with reference to FIG.
The data input / output unit 211 inputs necessary data such as factory brand-specific raw material usage record data as shown in FIG. 11 and factory brand-specific raw material inventory record data as shown in FIG. 11 from the factory raw material management system 304 (Step 301). .
Next, using the arrival schedule display / change unit 212, the arrival schedule is displayed for each berth of the own factory based on the latest allocation plan inputted from the head office system (Step 302). In order to extract the data of the own factory, it is only necessary to extract it using the landing port code or the factory code of the ship allocation plan data of FIG. 15 as a key.
Next, the inventory transition prediction calculation unit 213 calculates the inventory and displays the graph on the screen of the inventory transition display unit 214 (Step 303). Then, the early departure / delayed vessel fee calculation unit 215 calculates an early departure fee (despatch money) for each vessel and a demurrage for exceeding the scheduled period based on the dispatch schedule. In this calculation, the fee per unit time required for calculating the early departure fee and the berthing fee is set in advance for each ship or company and stored as a parameter in the calculation unit, and is obtained by multiplying the increase / decrease stay time. (Step 304).

そして、これらの表示された情報に基づいて、計画と実績とのズレが大きいか否か判断をする(Step305)。この計画と実績とのずれは、在庫量の許容範囲を予め設定しておき、その範囲内に予測値が入っているか否かを自動的に判断するようにしてもよいし、操作者が画面で、時間変化の傾向などから判断するようにしてもよい。その結果、ズレが大きい場合には入船予定を変更(Step307)、Step302に戻り、前述の処理を繰り返す。そして、計画と実績とのズレがなくなったら、更新後の計画データを工場別配船DB220に出力、記憶する(Step306)。このような変更指定を行い、その結果に基づく在庫推移や早出・滞船料をシミュレートしながら、工場毎に、入船調整を行うことができる。   And based on these displayed information, it is judged whether the gap with a plan and a track record is large (Step305). The deviation between the plan and the actual result may be determined by setting an allowable range of the stock quantity in advance and automatically determining whether or not the predicted value is within the range. Thus, the determination may be made based on the tendency of time change. As a result, if the deviation is large, the entry schedule is changed (Step 307), the process returns to Step 302, and the above-described processing is repeated. Then, when there is no difference between the plan and the actual result, the updated plan data is output and stored in the factory-specific ship allocation DB 220 (Step 306). It is possible to perform ship entry adjustment for each factory while performing such change designation and simulating inventory transitions and early departure / shipment charges based on the results.

[工場別配船計画データの反映]
上述の処理をまとめると図16のようになる。本社の配船計画立案装置110で、長期の計画を立案した(Step401)のち、日々の配船計画を本社の配船計画調整装置120で調整する(Step402)。その配船データを各工場で読み込んで、工場での入船状況に合わせて、工場別荷役調整装置210により配船計画を修正して工場別配船DB220に記憶する(Step403)。そして、各工場毎に修正された計画データは、工場別配船DB220から、配船計画調整装置120によって読み込まれ(Step404)、各工場のデータを統合したのち、本社原料輸送配船システム100の配船DB130に書き込み、データ更新する。そして、Step201〜208の処理を行い、全社的な配船計画データとして、不具合がないかを検証する(Step402)。この処理を繰り返して、最適な計画を立案する。
[Reflection of ship allocation plan data by factory]
The above processing is summarized as shown in FIG. After preparing a long-term plan with the ship allocation plan planning apparatus 110 at the head office (Step 401), the daily ship allocation plan is adjusted with the ship allocation plan adjustment apparatus 120 at the head office (Step 402). The ship allocation data is read in each factory, and the ship allocation plan is corrected by the factory loading / unloading adjustment device 210 according to the ship entry situation in the factory, and stored in the factory allocation DB 220 (Step 403). Then, the plan data corrected for each factory is read by the ship allocation plan adjustment device 120 from the factory-specific ship allocation DB 220 (Step 404), and after integrating the data of each factory, Write to the ship assignment DB 130 and update the data. And the process of Step 201-208 is performed and it is verified whether there is a malfunction as company-wide ship allocation plan data (Step 402). This process is repeated to create an optimal plan.

本発明の実施形態に係る原料輸送配船計画システムの全体構成図。1 is an overall configuration diagram of a raw material transport allocation planning system according to an embodiment of the present invention. 本社原料輸送配船システムの構成図。The block diagram of the headquarters material transportation dispatch system. 工場原料輸送配船システムの構成図。The block diagram of a factory raw material transport ship allocation system. 本社配船計画立案装置の処理を示すフローチャート。The flowchart which shows the process of a headquarters allocation plan planning apparatus. 本社原料配船計画調整装置の処理を示すフローチャート。The flowchart which shows the process of the headquarters raw material allocation plan adjustment apparatus. 工場別荷役調整装置の処理を示すフローチャート。The flowchart which shows the process of the cargo handling adjustment apparatus classified by factory. 年間原料購入計画データを示す図。The figure which shows annual raw material purchase plan data. 原料船年間稼働計画データを示す図。The figure which shows raw material ship annual operation plan data. 工場銘柄別原料使用計画データを示す図。The figure which shows the raw material use plan data according to factory brand. 工場銘柄別原料在庫予定データを示す図。The figure which shows the raw material stock schedule data according to a factory brand. 工場銘柄別原料使用実績データを示す図。The figure which shows the raw material use performance data according to factory brand. 工場銘柄別原料在庫実績データを示す図。The figure which shows the raw material inventory performance data according to factory brand. 原料船動静最新データを示す図。The figure which shows raw material ship movement latest data. 積み地荷役進捗最新データを示す図。The figure which shows the loading / unloading progress latest data. 配船計画データを示す図。The figure which shows ship allocation plan data. 原料輸送配船計画システムの全体の処理を示すフローチャート。The flowchart which shows the whole process of the raw material transport allocation plan system. 入船予定表示画面例を示す図。The figure which shows the example of a ship arrival schedule display screen. 入船予定表示画面例を示す図。The figure which shows the example of a ship arrival schedule display screen. 在庫推移表示画面例を示す図。The figure which shows the example of a stock transition display screen.

符号の説明Explanation of symbols

100 本社原料輸送配船システム、110 配船計画立案装置、111 データ入出力部、112 輸送対象決定部、113 船舶選択部、114 輸送スケジュール決定部、115 輸送タイミング決定部、120 配船計画調整装置、121 データ入出力部、122 入船予定表示・選変更部、123 船舶航海予定表示・変更部、124 在庫推移予測計算部、125 在庫推移表示部、126 早出・滞船料算出部、130 配船DB、200 工場原料輸送配船システム、210 工場別荷役調整装置、211 データ入出力部、212 入船予定表示・変更部、213 在庫推移予測計算部、214 在庫推移表示部、215 早出・滞船料算出部、220 工場別配船DB、301 原料購買システム、302 原料配分システム、303 出帆管理システム、304 工場原料管理システム。   DESCRIPTION OF SYMBOLS 100 Headquarters raw material transport ship allocation system, 110 Ship dispatch plan planning apparatus, 111 Data input / output part, 112 Transport object determination part, 113 Ship selection part, 114 Transport schedule determination part, 115 Transport timing determination part, 120 Ship dispatch plan adjustment apparatus , 121 Data input / output unit, 122 Entry schedule display / selection change unit, 123 Ship voyage schedule display / change unit, 124 Inventory transition prediction calculation unit, 125 Inventory transition display unit, 126 Early departure / arrival ship fee calculation unit, 130 DB, 200 factory raw material transportation and distribution system, 210 factory-specific cargo handling adjustment device, 211 data input / output unit, 212 entry schedule display / change unit, 213 inventory transition prediction calculation unit, 214 inventory transition display unit, 215 early departure / stagnation fee Calculation unit, 220 Ship allocation DB by factory, 301 Raw material purchasing system, 302 Raw material distribution system, 303 Launch management system 304 factory raw materials management systems.

Claims (4)

複数の製造工場を有する鉄鋼業における鉄鋼原料輸送船の配船計画を立案する原料輸送配船計画システムであって、
長期の原料輸送配船計画を立案する配船計画立案装置と、
短期の原料輸送配船計画を作成する配船計画調整装置と、
前記立案された長期及び短期の原料輸送配船計画がそれぞれ格納される第1の記憶手段と、
各工場の工場別原料輸送配船計画を調整する工場別荷役調整装置と、
各工場の調整された工場別原料輸送配船計画が格納される第2の記憶手段と
を備え、
前記配船計画立案装置は、
輸送船を割り当てるべき輸送銘柄を決定する輸送対象決定手段と、
該決定された輸送銘柄を輸送船を割り当てる船舶決定手段と、
該割り当てた輸送船の各工場における入船タイミングを決定する輸送タイミング決定手段とを備え、輸送船の各工場における入船タイミングを長期の原料輸送配船計画として前記第1の記憶手段に格納し、
前記配船計画調整装置は、
前記長期の原料輸送配船計画を前記第1の記憶手段から読込む入力手段と、
前記長期の原料輸送配船計画に基づいて、工場毎の入船に関するタイミングを表示するとともに、修正入力を可能とする入船予定表示・入力手段と、
前記長期の原料輸送配船計画に基づいて、船毎の航海に関するタイミングを表示するとともに、修正入力を可能とする航海予定表示・入力手段と、
前記入船及び航海予定の修正入力に基づく在庫推移の予測を自動的に計算・表示する在庫推移計算・表示手段と、
前記入船及び航海予定の修正入力に基づく早出・滞船料を自動的に計算・表示する早出・滞船料算出手段とを備え、修正された前記入船及び航海予定を前記短期の原料輸送配船計画として前記第1の記憶手段に格納し、
前記工場別荷役調整装置は、
前記第1の記憶手段から前記短期の原料輸送配船計画のうち、各工場ごとの計画を読込む入力手段と、
該入力した各工場ごとの原料輸送配船計画に基づいて、各工場における入船に関するタイミングを表示するとともに、修正入力を可能とする入船予定表示・入力手段と、
前記修正入力に基づく在庫推移の予測を自動的に計算・表示する在庫推移計算・表示手段と、
前記修正入力に基づく早出・滞船料を自動的に計算・表示する早出・滞船料算出手段とを備え、各工場の調整された工場別原料輸送配船計画を前記第2の記憶手段に格納する
ことを特徴とする原料輸送配船計画システム。
A material transportation ship allocation planning system for planning a ship allocation plan for steel material transportation ships in the steel industry having a plurality of manufacturing plants,
A ship allocation plan planning device for planning a long-term raw material transportation ship allocation plan;
A ship allocation plan adjustment device for creating a short-term raw material transport allocation plan;
A first storage means for storing the drafted long-term and short-term raw material transportation allocation plans;
A factory-specific cargo handling adjustment device that adjusts the factory-specific material transport allocation plan for each factory,
A second storage means for storing a factory-specific raw material transportation allocation plan for each factory;
The ship allocation planning device
A transport object determining means for determining a transport brand to which a transport ship should be assigned;
A ship determining means for allocating a transport ship to the determined transport brand;
Transportation timing determining means for determining the entry timing in each factory of the assigned transport ship, and storing the entry timing in each factory of the transport ship in the first storage means as a long-term raw material transportation allocation plan,
The ship allocation plan adjusting device is
Input means for reading the long-term raw material transportation allocation plan from the first storage means;
Based on the long-term raw material transport allocation plan, while displaying the timing related to entering the factory for each factory, the entry schedule display / input means that enables correction input,
Based on the long-term raw material transportation allocation plan, while displaying the timing related to the voyage for each ship, the voyage schedule display and input means that enables correction input,
Inventory transition calculation / display means for automatically calculating / displaying the forecast of inventory transition based on the correction input of the ship entry and voyage schedule,
Early departure / arrival fee calculation means for automatically calculating / displaying the early departure / arrival fee based on the corrected input of the arrival / voyage schedule, and the short-term raw material transportation of the corrected entry / voyage fee Store in the first storage means as a ship assignment plan,
The factory-specific cargo handling adjustment device is:
Among the short-term raw material transportation and shipping plan from the first storage means, input means for reading a plan for each factory;
Based on the input raw material transportation allocation plan for each factory, the ship entry timing display / input means for displaying the timing related to entry at each factory and enabling correction input,
Inventory transition calculation / display means for automatically calculating / displaying inventory transition prediction based on the correction input;
An early departure / arrival ship fee calculating means for automatically calculating / displaying an early departure / arrival ship fee based on the correction input, and the adjusted raw material transportation / shipment plan according to factory of each factory is stored in the second storage means Raw material transportation ship planning system characterized by storing.
前記配船計画調整装置は、前記工場別原料輸送配船計画を入力する入力手段を備え、前記第2の記憶手段に格納された前記工場別原料輸送配船計画を前記入力手段により取り込んで、前記工場別原料輸送配船計画に基づいて短期の原料輸送配船計画を調整することを特徴とする請求項1記載の原料輸送配船計画システム。   The ship allocation plan adjusting device includes an input unit for inputting the factory-specific raw material transport allocation plan, and takes in the factory-specific raw material transport allocation plan stored in the second storage unit by the input unit, 2. The raw material transportation / shipping plan according to claim 1, wherein a short-term raw material transportation / shipping plan is adjusted based on the factory-specific material transportation / shipping plan. 前記工場別荷役調整装置は、各工場毎の地域制約条件や設備制約条件に関するデータを入力する工場制約データ入力手段
を備えたことを特徴とする請求項1または2記載の原料輸送配船計画システム。
3. The material transportation ship allocation plan system according to claim 1, wherein the factory-specific cargo handling adjustment device includes factory constraint data input means for inputting data relating to regional constraint conditions and facility constraint conditions for each factory. .
請求項1〜3の何れかに記載の原料輸送配船計画システムを用いて原料輸送配船計画を立案する方法であって、
前記工場別荷役調整装置が、前記短期の原料輸送配船計画に基づいて、工場別原料輸送配船計画を修正するステップと、
前記配船計画調整装置が、前記修正された工場別原料輸送配船計画に基づいて、前記短期の原料輸送配船計画を修正するステップと
を繰り返し、短期の原料配船計画を立案することを特徴とする原料配船立案方法。
A method for drafting a raw material transport allocation plan using the raw material transport allocation plan system according to any one of claims 1 to 3,
A step of modifying the factory-specific material transport allocation plan based on the short-term material transport allocation plan,
The ship allocation plan adjustment device repeats the step of correcting the short-term raw material transport allocation plan based on the modified factory-specific raw material transport allocation plan, and formulates a short-term raw material allocation plan Characteristic raw material dispatch planning method.
JP2006291971A 2006-10-27 2006-10-27 Raw material transport allocation plan system and raw material transport allocation plan planning method Active JP5011954B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP2006291971A JP5011954B2 (en) 2006-10-27 2006-10-27 Raw material transport allocation plan system and raw material transport allocation plan planning method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP2006291971A JP5011954B2 (en) 2006-10-27 2006-10-27 Raw material transport allocation plan system and raw material transport allocation plan planning method

Publications (3)

Publication Number Publication Date
JP2008105825A true JP2008105825A (en) 2008-05-08
JP2008105825A5 JP2008105825A5 (en) 2009-08-13
JP5011954B2 JP5011954B2 (en) 2012-08-29

Family

ID=39439507

Family Applications (1)

Application Number Title Priority Date Filing Date
JP2006291971A Active JP5011954B2 (en) 2006-10-27 2006-10-27 Raw material transport allocation plan system and raw material transport allocation plan planning method

Country Status (1)

Country Link
JP (1) JP5011954B2 (en)

Cited By (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
WO2010041432A1 (en) * 2008-10-06 2010-04-15 新日本製鐵株式会社 Ship allocation plan creation device, method, and program
WO2010058584A1 (en) * 2008-11-21 2010-05-27 新日本製鐵株式会社 System, method and program for making composition plan and allocation of ships
WO2017037826A1 (en) * 2015-08-31 2017-03-09 株式会社日立製作所 Transportation plan assistance device and transportation plan assistance system
JP2019197538A (en) * 2018-05-08 2019-11-14 Jfeスチール株式会社 Ship assignment plan creation method, operation method by the method, and ship assignment plan creation device
CN112686439A (en) * 2020-12-25 2021-04-20 广州智湾科技有限公司 Intelligent automatic container terminal energy-saving comprehensive scheduling method

Citations (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH11100127A (en) * 1997-09-29 1999-04-13 Nkk Corp Raw material handling control method
JP2005343630A (en) * 2004-06-03 2005-12-15 Chugoku Electric Power Co Inc:The Sea physical distribution management system and sea physical distribution management method

Patent Citations (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH11100127A (en) * 1997-09-29 1999-04-13 Nkk Corp Raw material handling control method
JP2005343630A (en) * 2004-06-03 2005-12-15 Chugoku Electric Power Co Inc:The Sea physical distribution management system and sea physical distribution management method

Cited By (10)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
WO2010041432A1 (en) * 2008-10-06 2010-04-15 新日本製鐵株式会社 Ship allocation plan creation device, method, and program
JP4669583B2 (en) * 2008-10-06 2011-04-13 新日本製鐵株式会社 Ship allocation plan creation device, method and program
JPWO2010041432A1 (en) * 2008-10-06 2012-03-08 新日本製鐵株式会社 Ship allocation plan creation device, method and program
WO2010058584A1 (en) * 2008-11-21 2010-05-27 新日本製鐵株式会社 System, method and program for making composition plan and allocation of ships
JP4669582B2 (en) * 2008-11-21 2011-04-13 新日本製鐵株式会社 Formulation and dispatch plan creation system, method and program
CN102137803A (en) * 2008-11-21 2011-07-27 新日本制铁株式会社 System, method and program for making composition plan and allocation of ships
JPWO2010058584A1 (en) * 2008-11-21 2012-04-19 新日本製鐵株式会社 Formulation and dispatch plan creation system, method and program
WO2017037826A1 (en) * 2015-08-31 2017-03-09 株式会社日立製作所 Transportation plan assistance device and transportation plan assistance system
JP2019197538A (en) * 2018-05-08 2019-11-14 Jfeスチール株式会社 Ship assignment plan creation method, operation method by the method, and ship assignment plan creation device
CN112686439A (en) * 2020-12-25 2021-04-20 广州智湾科技有限公司 Intelligent automatic container terminal energy-saving comprehensive scheduling method

Also Published As

Publication number Publication date
JP5011954B2 (en) 2012-08-29

Similar Documents

Publication Publication Date Title
Halvorsen-Weare et al. Routing and scheduling in a liquefied natural gas shipping problem with inventory and berth constraints
JP4669583B2 (en) Ship allocation plan creation device, method and program
KR101296933B1 (en) System, method and storage medium for storing program for making composition plan and allocation of ships
Epstein et al. A strategic empty container logistics optimization in a major shipping company
JP5011954B2 (en) Raw material transport allocation plan system and raw material transport allocation plan planning method
KR20100045499A (en) Transportation management system
Sun et al. The impact of liner shipping unreliability on the production–distribution scheduling of a decentralized manufacturing system
Siswanto et al. A Simulation study of sea transport based fertilizer product considering disruptive supply and congestion problems
JP6904373B2 (en) Ship allocation plan creation method, operation method by that method, and ship allocation plan creation device
Fink et al. Flexibility planning in global inbound logistics
JP5272534B2 (en) Ship operation plan creation method and apparatus
JP5569199B2 (en) Ship allocation plan creation device, method and program
Zhu et al. Optimisation of containerised air cargo forwarding plans considering a hub consolidation process with cargo loading
JPH08272402A (en) Inference device for raw material transportation plan assignment of ships
WO2023131989A1 (en) Cargo tracking system, cargo tracking method, and program
JP2017187854A (en) Ship assignment plan creation method, iron mill operation method, and ship assignment plan creation device
Dikos et al. Supply chain optimization and planning in Heracles General Cement Company
Zheng et al. A GRASP algorithm for trailer scheduling of crossdock operations in cold-chain logistics
EP4191491A1 (en) Ship allocation plan formulation method, and operation method and ship allocation plan formulation device that are based on said ship allocation plan formulation method
KR20150121414A (en) System for managing supply and demand of bituminous coal
JP6710090B2 (en) Shipment planning device and shipment planning method
Praharsi The application of Lean
Bingul et al. Cut-Off Optimization in Liner Shipping: A Case Study
Praharsi The application of Lean Six Sigma and supply chain
Smith Production Scheduling at Ardent Mills in Alton, IL

Legal Events

Date Code Title Description
A521 Request for written amendment filed

Free format text: JAPANESE INTERMEDIATE CODE: A523

Effective date: 20090626

A621 Written request for application examination

Free format text: JAPANESE INTERMEDIATE CODE: A621

Effective date: 20090626

A977 Report on retrieval

Free format text: JAPANESE INTERMEDIATE CODE: A971007

Effective date: 20111004

A131 Notification of reasons for refusal

Free format text: JAPANESE INTERMEDIATE CODE: A131

Effective date: 20120131

A521 Request for written amendment filed

Free format text: JAPANESE INTERMEDIATE CODE: A523

Effective date: 20120329

TRDD Decision of grant or rejection written
A01 Written decision to grant a patent or to grant a registration (utility model)

Free format text: JAPANESE INTERMEDIATE CODE: A01

Effective date: 20120508

A01 Written decision to grant a patent or to grant a registration (utility model)

Free format text: JAPANESE INTERMEDIATE CODE: A01

A61 First payment of annual fees (during grant procedure)

Free format text: JAPANESE INTERMEDIATE CODE: A61

Effective date: 20120521

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20150615

Year of fee payment: 3

R150 Certificate of patent or registration of utility model

Ref document number: 5011954

Country of ref document: JP

Free format text: JAPANESE INTERMEDIATE CODE: R150

Free format text: JAPANESE INTERMEDIATE CODE: R150

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250