JP2018197474A - Joint structure of wall member and foundation - Google Patents

Joint structure of wall member and foundation Download PDF

Info

Publication number
JP2018197474A
JP2018197474A JP2017103134A JP2017103134A JP2018197474A JP 2018197474 A JP2018197474 A JP 2018197474A JP 2017103134 A JP2017103134 A JP 2017103134A JP 2017103134 A JP2017103134 A JP 2017103134A JP 2018197474 A JP2018197474 A JP 2018197474A
Authority
JP
Japan
Prior art keywords
foundation
wall member
column base
wall
base steel
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
JP2017103134A
Other languages
Japanese (ja)
Other versions
JP6583348B2 (en
Inventor
治 田畑
Osamu Tabata
治 田畑
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Sekisui House Ltd
Original Assignee
Sekisui House Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Sekisui House Ltd filed Critical Sekisui House Ltd
Priority to JP2017103134A priority Critical patent/JP6583348B2/en
Publication of JP2018197474A publication Critical patent/JP2018197474A/en
Priority to JP2019008074A priority patent/JP6892991B2/en
Application granted granted Critical
Publication of JP6583348B2 publication Critical patent/JP6583348B2/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Foundations (AREA)
  • Load-Bearing And Curtain Walls (AREA)
  • Joining Of Building Structures In Genera (AREA)

Abstract

To provide a joint structure of a wall member and a foundation which saves a labor required for fixing work of driving many screws into a steel panel for fixing a base to a wall member, which has no positional deviation of an anchor bolt for avoiding an interference with the screw, and in which splitting does not occur even when bending acts on a base in an earthquake.SOLUTION: A joint structure of a wall member and a foundation comprises: a column base steel plate 3 whose lower side portion 3a is buried in and fixed to a foundation 2 and whose upper side portion 3b is exposed from a top face 2a of the foundation 2; a wall member 4 including a slit 4c formed upward from an opening of a bottom face so as to store the upper side portion 3b of the column base steel plate 3 which is exposed from the top face 2a of the foundation; an attachment pin hole 3c formed in the upper side portion 3b of the column base steel plate 3; a wall pin hole 4d formed with penetrating the slit 4c of the wall member 4 in a perpendicular direction; and a fastener 5 penetrating the attachment pin hole 3c and the wall pin hole 4d and fastening the column base steel plate 3 to the wall member 4.SELECTED DRAWING: Figure 1

Description

この発明は、主として木造住宅におけるCLTパネルなどの壁部材と基礎の接合構造に関する。   The present invention mainly relates to a joint structure between a wall member such as a CLT panel and a foundation in a wooden house.

周知のように、CLT(Cross Laminated Timber)は、板の層を各層で互いに直交するように積層接着した厚型パネルであり、日本農林規格(JAS)として直交集成板の名称により制定されているものであり、壁材、床材、天井材等の建築材料としても使用されるが、CLT自体が柱、梁にもなっている。しかし、このCLTを使用したパネル構法の日本における歴史は浅いために、建物の構成部材との接合は未だ十分に開発されていないのが実情である。このCLTと基礎との接合方法については、在来の木軸造と同様に、図9、図10に示すように、アンカーボルト30で基礎31と締結された土台32の上に通気スペーサ33を介してCLTパネル34を設置し、基礎31とCLTパネル34を外付けの鋼製プレート35によって両側から挟み込んで多数のビス36で固定している構造のものが、刊行物には示されていないが、実際の工法として知られている。   As is well known, CLT (Cross Laminated Timber) is a thick panel in which the layers of the board are laminated and bonded so that each layer is orthogonal to each other, and is established by the name of the orthogonal laminated board as Japanese Agricultural Standard (JAS). Although it is also used as a building material such as a wall material, a floor material, and a ceiling material, CLT itself is also a pillar and a beam. However, since the history of panel construction using CLT has not been long in Japan, the actual situation is that joints with building components have not yet been fully developed. About the joining method of this CLT and a foundation, as shown in FIG. 9 and FIG. 10, the ventilation spacer 33 is installed on the base 32 fastened with the foundation 31 with the anchor bolt 30, similarly to the conventional wooden shaft structure. In the publication, the CLT panel 34 is installed, and the foundation 31 and the CLT panel 34 are sandwiched from both sides by an external steel plate 35 and fixed with a large number of screws 36. However, it is known as an actual construction method.

又、構造・断熱パネルを土台を用いることなく基礎に直接設置する構法としては、特許文献1の図2に示されるように、基礎に埋め込んだアンカー鉄筋に固定しているプレートを基礎の側面から基礎の上方へと突出させて壁パネルと釘で固定する構造のものが開示されている。又、特許文献2の図1に示されるように、基礎の上面に置かれた換気台輪の上に壁パネルを載せて、基礎に埋め込んでいるアンカーボルトの上端部を壁パネルの下端部内に突出させて螺子で螺合固定した構造のものが開示されている。   In addition, as shown in FIG. 2 of Patent Document 1, as a construction method in which the structure / heat insulation panel is directly installed on the foundation without using a base, the plate fixed to the anchor reinforcing bar embedded in the foundation is viewed from the side of the foundation. A structure is disclosed that protrudes above the foundation and is fixed with a wall panel and a nail. Moreover, as shown in FIG. 1 of Patent Document 2, a wall panel is placed on a ventilation pedestal placed on the upper surface of the foundation, and the upper end of the anchor bolt embedded in the foundation is placed in the lower end of the wall panel. A structure that protrudes and is fixed by screwing with a screw is disclosed.

特開平11−13149号公報Japanese Patent Laid-Open No. 11-13149 特開2009−97215号公報JP 2009-97215 A

しかしながら上記の未刊行物記載の従来技術によると、土台32の敷設と、この土台32とCLTパネル34を固定するための鋼製パネル35を多数のビス36を打つ固定作業に要する手間が多くかかるという問題点がある。更に、土台32を貫通しているアンカーボルト30とビス36の干渉を避けるために位置ずれをさせなければならないという問題点がある。又、地震時に土台32に曲げが作用し割裂が生じるという問題点がある。加えて、土台32の上にCLTパネル34を設置しているので、土台32を固定するための基礎31に埋めたアンカーボルト30と基礎31の主筋37が共に材の中央に配置させたいが干渉を避けるためにずらさざるを得なく、その結果として土台32に曲げが作用するという問題点がある。   However, according to the prior art described in the above-mentioned unpublished documents, it takes a lot of labor to install the base 32 and to fix the base 32 and the steel panel 35 for fixing the CLT panel 34 with a large number of screws 36. There is a problem. Furthermore, there is a problem in that the position must be shifted in order to avoid interference between the anchor bolt 30 passing through the base 32 and the screw 36. In addition, there is a problem in that bending is applied to the base 32 during the earthquake, resulting in splitting. In addition, since the CLT panel 34 is installed on the base 32, the anchor bolt 30 buried in the base 31 for fixing the base 32 and the main bar 37 of the base 31 are both arranged in the center of the material. As a result, there is a problem that the base 32 is bent.

上記のように土台32の上にCLTパネル34を設置する問題点を解消させるためには、前記した特許文献1又は特許文献2に記載の基礎上に直接に壁部材を載置する技術を用いればよいかもしれないが、しかし、特許文献1に記載の発明は、基礎に埋め込んだアンカー鉄筋に固定しているプレートを基礎の側面から基礎の上方へと突出させて壁パネルと釘で固定する構造であるので、支持力が弱く、地震や横方向からの力の作用には耐えにくいという問題点がある。又、特許文献2に記載の発明は、基礎の上面に置かれた換気台輪の上に壁パネルを載せて、基礎に埋め込んでいるアンカーボルトの上端部を壁パネルの下端部内に突出させて螺子で螺合固定した構造であるので、基礎と壁パネルとの連結がアンカーボルトだけのものとなり、連結強度が弱いという問題点がある。   In order to solve the problem of installing the CLT panel 34 on the base 32 as described above, a technique of placing a wall member directly on the foundation described in Patent Document 1 or Patent Document 2 described above is used. However, in the invention described in Patent Document 1, the plate fixed to the anchor reinforcing bar embedded in the foundation is protruded from the side of the foundation to the upper side of the foundation and fixed with the wall panel and the nail. Due to the structure, there is a problem that the supporting force is weak and it is difficult to withstand the action of an earthquake or a lateral force. In the invention described in Patent Document 2, a wall panel is placed on a ventilation pedestal placed on the upper surface of a foundation, and the upper end of an anchor bolt embedded in the foundation is projected into the lower end of the wall panel. Since the structure is screwed and fixed with screws, the connection between the foundation and the wall panel is only anchor bolts, and there is a problem that the connection strength is weak.

この発明は上記問題点を解決すべくなされたものであって、その手段とするところは、
基礎に下方側部を埋設固定され上方側部を基礎の表面から露出した柱脚鋼板と、該柱脚鋼板の基礎表面より露出した上方側部を収納するために底面の開口部から上方に向かって形成したスリットを具備する壁部材と、前記柱脚鋼板の上方側部に形成した取付ピン孔及び前記壁部材の前記スリットを直角方向に貫通して形成した壁ピン孔と、前記取付ピン孔及び壁ピン孔を貫通して柱脚鋼板と壁部材を締結する締結具と、を具備することを特徴とする壁部材と基礎の接合構造としたことにある。
The present invention has been made to solve the above-mentioned problems, and its means is as follows:
The lower side is embedded in the foundation and fixed, and the upper side is exposed from the surface of the foundation, and the upper side exposed from the foundation surface of the column base is directed upward from the bottom opening. A wall member having a slit formed therein, a mounting pin hole formed in an upper side portion of the column base steel plate, a wall pin hole formed by penetrating the slit of the wall member in a right angle direction, and the mounting pin hole And a fastener that passes through the wall pin hole and fastens the column base steel plate and the wall member.

又、前記壁部材がCLTパネルであることにある。更に、前記柱脚鋼板及び壁部材のスリットが基礎の幅方向に複数対設けられていることにある。更に又、前記基礎の上面と壁部材の底面の間に通気スペーサを介在させたことにある。又、前記柱脚鋼材の下方に杭棒を固定したことにある。   Further, the wall member is a CLT panel. Furthermore, a plurality of pairs of the column base steel plates and the slits of the wall member are provided in the width direction of the foundation. Furthermore, a ventilation spacer is interposed between the upper surface of the foundation and the bottom surface of the wall member. Further, a pile rod is fixed below the column base steel material.

又、前記締結具がドリフトピンであることにある。前記締結具がボルト、ナットであることにある。前記壁部材が、柱と兼用した壁材であることにある。前記基礎の長手方向に柱脚鋼板と壁部材のスリットが複数対設置されていることにある。   Further, the fastener is a drift pin. The fastener is a bolt or a nut. The wall member is a wall material that also serves as a pillar. A plurality of pairs of column base steel plates and wall member slits are installed in the longitudinal direction of the foundation.

この発明の壁部材と基礎の接合構造によると、基礎に下端側部を埋設固定された柱脚鋼板の上端側部を壁部材の底面の開口部からスリットに収納して、柱脚鋼板の周囲は壁部材によって囲まれているので、柱脚鋼板の取付ピン孔及び壁部材の壁ピン孔に貫通して固定するドリフトピンやボルトなどの締結具は、地震時の上下方向の大きな振動による柱脚鋼板の壁部材からの抜けを防止すると共に直接に基礎に連結接合することから土台を必要としていないので地震時の土台の曲げによる割裂も生じない。更に、締結具は壁部材の片方の面の壁ピン孔から柱脚鋼板の取付ピン孔を通って他方の面の壁ピン孔に達するように貫通させるか或いは打ち込むだけでよいので、壁部材の両面から締結具を貫通させるか或いは打ち込みさせる必要がないので、設置する手間が少なくてよい。又、基礎と壁部材は、基礎の上面から突出している柱脚鋼板の上方側部を壁部材の底面に基礎の長手方向に開口している開口部からスリットに挿入しているので、基礎の側面から上方へ張り出した金具を釘で壁パネルの両側面を固定している従来技術の接合構造と較べて、支持力が強く、地震や横方向からの力の作用にも十分に耐え得る。又、基礎と壁パネルとの連結がアンカーボルトだけの従来技術と異なり、連結強度が強くなる。   According to the joining structure of the wall member and the foundation of the present invention, the upper end side portion of the column base steel plate in which the lower end side portion is embedded and fixed to the foundation is housed in the slit from the opening on the bottom surface of the wall member, Are surrounded by wall members, so that the fixing pins such as drift pins and bolts that pass through and fix to the mounting pin holes of the column base steel plates and the wall pin holes of the wall members are pillars caused by large vertical vibrations during an earthquake. Since the base plate is not required because it prevents the leg steel plate from coming off the wall member and is directly connected to the foundation, splitting due to bending of the base during an earthquake does not occur. Furthermore, the fastener only has to be penetrated or driven so as to reach the wall pin hole on the other surface from the wall pin hole on one surface of the wall member through the mounting pin hole of the column base steel plate. Since there is no need to penetrate or drive the fastener from both sides, it is possible to reduce the installation effort. In addition, since the foundation and the wall member are inserted into the slit from the opening portion opened in the longitudinal direction of the foundation on the bottom surface of the wall member, the upper side portion of the column base steel plate protruding from the top surface of the foundation is inserted. Compared to the joint structure of the prior art in which the metal panel protruding upward from the side is fixed with the nails on both sides of the wall panel, it has a strong support force and can sufficiently withstand the action of an earthquake or a lateral force. In addition, the connection strength between the foundation and the wall panel is increased, unlike the prior art in which only anchor bolts are used.

前記壁部材が、CLTパネルのように柱を兼ねる壁材である場合には、別途の柱や壁材を設ける必要がなくなり施工が簡単である。又、CLTパネルであるので、室内側面はそのまま室内に露出させても奇麗であるから内装材の経費を節約できる。更に、構造材としての作用をも有するので、柱の作用を兼用でき、建築物の構造を簡素化できる。   When the wall member is a wall material that also serves as a column like a CLT panel, it is not necessary to provide a separate column or wall material, and the construction is simple. Further, since it is a CLT panel, the interior side can be exposed to the room as it is, so that the cost of interior materials can be saved. Furthermore, since it also has a function as a structural material, it can also function as a pillar, and the structure of the building can be simplified.

前記柱脚鋼板及び柱脚鋼板のスリットが基礎の幅方向に複数設けられている場合には、その分だけ基礎と壁部材の接合強度が強くなる。又、柱脚鋼板の下方側部の基礎への埋設部分を、基礎の長手方向の中心部に設置される主筋の位置から外して干渉を避けることができるので、基礎への主筋の位置を変えることもないので強度を維持できる。   In the case where a plurality of slits of the column base steel plates and column base steel plates are provided in the width direction of the foundation, the joint strength between the foundation and the wall member increases accordingly. In addition, since the portion embedded in the foundation on the lower side of the column base steel plate can be removed from the position of the main bar installed at the center in the longitudinal direction of the foundation, interference can be avoided, so the position of the main bar to the base is changed. There is nothing, so the strength can be maintained.

前記基礎の上面と壁部材の底面の間に通気スペーサを介在させることによって、床下空間の空気の流通をよくすることができる。又、これにより壁部材の底面に空気流通のための開口を設ける必要がない。   By interposing a ventilation spacer between the upper surface of the foundation and the bottom surface of the wall member, air circulation in the underfloor space can be improved. Moreover, it is not necessary to provide an opening for air circulation on the bottom surface of the wall member.

前記柱脚鋼材の下方に杭棒を固定した場合には、この杭棒が基礎のコンクリートに埋設固定されるので、柱脚鋼板の下方側部の基礎への埋設固定部分が少なくなっても強度維持できる。   When a pile rod is fixed below the column base steel, the pile rod is embedded and fixed in the concrete of the foundation. Can be maintained.

前記締結具がドリフトピンである時には、壁部材の片方の面に開口している壁ピン孔からドリフトピンをハンマーで打ち込んで反対側の壁部材に届くようにするだけでよいので設置が簡単である。この場合の壁ピン孔はドリフトピンの直径とほぼ同じである。前記締結具がボルト、ナットである場合には、壁部材の片方の面に開口している壁ピン孔からボルトを反対側の壁部材の壁ピン孔から出るまで差し込んでナットで締付固定するだけでよいので作業は簡単である。又、壁部材を取り外す際には、ナットを緩めてボルトを引き抜くだけの作業であるので簡単である。   When the fastener is a drift pin, it is only necessary to hit the drift pin with a hammer from a wall pin hole opened on one side of the wall member so that it reaches the opposite wall member, so that installation is easy. is there. The wall pin hole in this case is approximately the same as the diameter of the drift pin. When the fastener is a bolt or nut, the bolt is inserted from the wall pin hole opened on one side of the wall member until it comes out of the wall pin hole of the opposite wall member, and is fastened and fixed with the nut. The work is simple because it is only necessary. Further, when removing the wall member, it is easy because it is an operation of simply loosening the nut and pulling out the bolt.

前記基礎の長手方向に柱脚鋼板と壁部材のスリットが複数対設置されている場合には、基礎と壁部材の接合固定構造がより強く且つ安定させることができる。   In the case where a plurality of pairs of column base steel plates and wall member slits are installed in the longitudinal direction of the foundation, the joining and fixing structure between the foundation and the wall member can be stronger and stabilized.

この発明の実施形態の壁部材と基礎の接合直前斜視図The perspective view just before joining of the wall member and foundation of embodiment of this invention 図1のA−A線断面図AA line sectional view of FIG. この発明の壁部材と基礎の接合した状態の斜視説明図The perspective explanatory view of the state where the wall member and the foundation of this invention are joined 図2のB−B線断面図BB sectional view of FIG. この発明の他の実施形態の壁部材と基礎の接合直前斜視図The perspective view just before joining of the wall member and foundation of other embodiment of this invention 図5のC−C線断面図CC sectional view of FIG. この発明の他の実施形態の壁部材と基礎の接合状態の斜視説明図The perspective explanatory view of the joined state of the wall member and the foundation of another embodiment of the present invention 図7のD−D線断面DD cross section of FIG. 従来例の壁部材と基礎の接合状態の斜視説明図Perspective explanatory view of the joining state of the wall member and the foundation of the conventional example 図9のE−E線断面図EE sectional view of FIG.

この発明の壁部材と基礎の接合構造の実施形態について、以下図1乃至8に基づいて説明する。まず、図1乃至4に基づいて第1実施形態の壁部材と基礎の接合構造1について説明する。壁部材と基礎の接合構造1は、基礎2に下方側部3aを埋設固定され上方側部3bを基礎2の上面2aから露出した柱脚鋼板3と、該柱脚鋼板3の基礎表面2aより露出した上方側部3bを収納するために底面4aの開口部4bから上方に向かって形成したスリット4cを具備する壁部材としてのCLTパネル4と、前記柱脚鋼板3の上方側部3bに形成した取付ピン孔3c及び前記CLTパネル4の前記スリット4cを直角方向に貫通して形成した壁ピン孔4dと、前記取付ピン孔3c及び壁ピン孔4dを貫通して締結する締結具5と、を具備している。   DESCRIPTION OF THE PREFERRED EMBODIMENTS Embodiments of a wall member / foundation joint structure according to the present invention will be described below with reference to FIGS. First, the wall member-foundation joint structure 1 according to the first embodiment will be described with reference to FIGS. The wall member / foundation joining structure 1 includes a column base steel plate 3 in which a lower side portion 3 a is embedded and fixed to a foundation 2 and an upper side portion 3 b is exposed from an upper surface 2 a of the foundation 2, and a foundation surface 2 a of the column base steel plate 3. Formed on the CLT panel 4 as a wall member having a slit 4c formed upward from the opening 4b of the bottom surface 4a to accommodate the exposed upper side 3b, and the upper side 3b of the column base steel plate 3. A wall pin hole 4d formed by penetrating the mounting pin hole 3c and the slit 4c of the CLT panel 4 in a right angle direction, and a fastener 5 for fastening through the mounting pin hole 3c and the wall pin hole 4d. It has.

前記基礎2は、中心部に主筋6と他の鉄筋が配設されて周囲をコンクリートで7で固めて所定形状に形成したものであって、上面2aは所定の幅を有している。この基礎2の長手方向の上面2aには所定間隔を開けて所定厚さを有する通気スペーサ8が載置されている。   The foundation 2 has a main bar 6 and other reinforcing bars arranged at the center, and the periphery is solidified with concrete 7 and formed into a predetermined shape, and the upper surface 2a has a predetermined width. A ventilation spacer 8 having a predetermined thickness is placed on the upper surface 2a of the base 2 in the longitudinal direction with a predetermined interval.

前記柱脚鋼板3は、四角形状の縦長な金属薄板からなり、下方側部3aが前記基礎2のコンクリート7に埋設され、上方側部3bが基礎3の上面2aから突出している。そして、下方側部3aにはコンクリート7を導入して硬化後の係合を良くするためと打設されるコンクリートの流動性をよくするための貫通穴3dが複数個形成され、上方側部3bには柱脚鋼板3をCLTパネル4に締結するための取付ピン孔3cが複数個上下左右方向に散らばって形成されている。このような柱脚鋼板3は基礎2の幅方向の中央部に2枚所定間隔を開けて平行に並べて上方側部3bを同じ高さ分だけ突出させて、且つ、必要な場合には基礎2の長手方向に所定間隔を開けて同じように柱脚鋼板3が設置されている。この設置は、内部に主筋6等の鉄筋が組まれたコンクリートメタル型枠へコンクリートを打設する前に図外のメタルアンカー定規の取付ガイドに柱脚鋼板3を取り付けしておき、コンクリート硬化後にメタルアンカー定規及びメタル型枠を取り外すことで行い得る。下方側部3aの基礎2への埋込み長さや上方側部3bの基礎3の上面2aからの突出長さは、建物の種類や構造によって適宜決定される。この実施形態では、基礎2の幅方向に2つの柱脚鋼材3を埋設した例について説明したが、次の第2実施形態で説明するように1つであっても、又、幅広の基礎2の場合には3つ以上であってもよい。更に又、設置される複数の柱脚鋼板3の大きさ、形状、埋込み長さ、突出長さ、設置間隔等は、全て均一であるとは限定されるものではなく、建物の構造、偏荷重が掛かりやすい箇所とそうでない箇所等々の諸要因によって適宜変えることができる。更に又、柱脚鋼板3を形成する金属薄板の金属の種類、外形状、金属薄板の厚さ、貫通孔3dや取付ピン孔3eの数と大きさ等も建物の構造によって適宜選択変更されることは勿論である。   The column base steel plate 3 is made of a rectangular vertically long metal thin plate, the lower side portion 3 a is embedded in the concrete 7 of the foundation 2, and the upper side portion 3 b protrudes from the upper surface 2 a of the foundation 3. The lower side portion 3a is formed with a plurality of through-holes 3d for introducing the concrete 7 to improve the engagement after hardening and for improving the fluidity of the placed concrete. The upper side portion 3b A plurality of mounting pin holes 3c for fastening the column base steel plate 3 to the CLT panel 4 are formed scattered in the vertical and horizontal directions. Two such column base steel plates 3 are arranged in parallel at a predetermined interval in the center in the width direction of the foundation 2 so that the upper side portion 3b protrudes by the same height, and if necessary, the foundation 2 Column base steel plates 3 are installed in the same manner with a predetermined interval in the longitudinal direction. This installation is done by attaching the column base steel plate 3 to the mounting guide of the metal anchor ruler (not shown) before placing the concrete on the concrete metal formwork in which the reinforcing bars such as the main reinforcement 6 are built, and after hardening the concrete This can be done by removing the metal anchor ruler and the metal formwork. The embedding length of the lower side portion 3a into the foundation 2 and the protruding length of the upper side portion 3b from the upper surface 2a of the foundation 3 are appropriately determined depending on the type and structure of the building. In this embodiment, the example in which the two column base steel members 3 are embedded in the width direction of the foundation 2 has been described. However, even if there is only one as described in the second embodiment, the wide foundation 2 is also wide. In the case of 3, it may be three or more. Furthermore, the size, shape, embedding length, protruding length, installation interval, etc. of the plurality of column base steel plates 3 to be installed are not limited to being uniform, but the structure of the building, the unbalanced load It can be appropriately changed depending on various factors such as a place where it is likely to be applied and a place where it is not. Furthermore, the metal type, outer shape, thickness of the metal thin plate, the number and size of the through holes 3d and the mounting pin holes 3e, and the like of the metal thin plate forming the column base steel plate 3 are appropriately selected and changed according to the structure of the building. Of course.

壁部材としての前記CLTパネル4は、前記したように、板の層を各層で互いに直交するように積層接着した厚型パネルであって、例えばその縦横方向の長さは3000mmと2000mmで形成された長方形をなしている柱と壁材とを兼ね備えた構造部材でもある。このCLTパネル4は、前記基礎2の上面2aに通気スペーサ8を介在させて載置され、床下空間の空気と大気が連通するように隙間を設けている。CLTパネル4の底面4aには、基礎2の上面2aから突出している柱脚鋼材3の上方側部3bを収納するスリット4cへの開口部4bが開口されている。この実施形態においては、基礎2の幅方向に2つの柱脚鋼材3が突出しているので、これに対応して2つのそれぞれのスリット4cの溝が形成されているがそのスリット4cの幅は柱脚鋼材3の厚さと略同幅でその内周形状は柱脚鋼材3の上方側部3bの外形状と略同じ形状としている。   As described above, the CLT panel 4 as a wall member is a thick panel in which the layers of a plate are laminated and bonded so that each layer is orthogonal to each other. For example, the length in the vertical and horizontal directions is 3000 mm and 2000 mm. It is also a structural member having both a rectangular pillar and a wall material. The CLT panel 4 is placed on the upper surface 2a of the foundation 2 with a ventilation spacer 8 interposed, and a gap is provided so that the air in the underfloor space communicates with the atmosphere. On the bottom surface 4 a of the CLT panel 4, an opening 4 b is opened to a slit 4 c that houses the upper side portion 3 b of the column base steel material 3 protruding from the top surface 2 a of the foundation 2. In this embodiment, since the two column base steel members 3 protrude in the width direction of the foundation 2, the grooves of the two slits 4 c are formed correspondingly, but the width of the slit 4 c is the column. The inner circumferential shape of the leg steel material 3 is substantially the same as the thickness of the leg steel material 3 and is substantially the same as the outer shape of the upper side portion 3 b of the column base steel material 3.

CLTパネル4を基礎2の上面2aに載置する際には、図1に示すように、吊り上げたCLTパネル4を基礎2の上方から開口部4bが柱脚鋼材3の真上に位置するようにしてから、矢印イのように下方へ徐々に下してスリット4cの内部に柱脚鋼材3を収納させる。1枚のCLTパネル4の底面4aにはその横方向の両端にそれぞれ幅方向に2つのスリット4cが並行して設けられているので合計4つのスリット4cが存在するが、これらスリット4cの内部に柱脚鋼材3が全て収納されるように開口部4bの位置合わせをしてから降下させて嵌め込み収納する。なお、CLTパネル4の下端部の外周面と底面4aのコーナーには樹脂テープ9を貼着して、雨水を吸い込まないように保護している。   When placing the CLT panel 4 on the upper surface 2a of the foundation 2, as shown in FIG. 1, the opening 4b of the lifted CLT panel 4 is positioned above the column base steel 3 from above the foundation 2. Then, the column base steel material 3 is accommodated in the slit 4c by gradually lowering as shown by the arrow a. The bottom surface 4a of one CLT panel 4 is provided with two slits 4c in parallel in the width direction at both ends in the lateral direction, so there are a total of four slits 4c. After the position of the opening 4b is adjusted so that all the column base steel 3 is stored, it is lowered and stored. In addition, the resin tape 9 is stuck on the outer peripheral surface of the lower end portion of the CLT panel 4 and the corner of the bottom surface 4a to protect it from inhaling rainwater.

また、前記CLTパネル4のスリット4cを形成した一方の外側面から他方の外側面に向かって壁ピン孔4dが前記柱脚鋼材3の取付ピン孔3cに対応した位置に形成されているので、柱脚鋼材3をスリット4cに収納した時には、取付ピン孔3cと壁ピン孔4dは一直線上にあって開通している。この一直線上に開通したピン孔4d、3cに締結具5であるドリフトピン又はボルトを矢印ロ方向に差し込んで締め付け固定することで、壁部材であるCLTパネル4の基礎2への接合構造1が構築される。ドリフトピンを用いる場合には、壁ピン孔4dの開口からドリフトピンの挿入時にハンマーで強く叩打することによって振動や捩じれ方向の力が作用しても抜け出ないように強固に固定できる。また、ドリフトピンを叩くだけでよいので固定がし易い。更に、ドリフトピンの先端をCLTパネル4の他方側面から突出しないように途中で止めることによって室内側のCLTパネル4の側面をきれいな状態としておくことが出来る。締結具5がボルト・ナットの場合にも同様に一直線上に開通したピン孔4d、3cにCLTパネル4の一方の外側面から矢印ロ方向にボルトを差し込んで他方の外側面に突出したボルトの先端のねじにナットを締め付けることで固定できる。この場合には、他方の外側面が室内側である時にはナットが露出することになるが、締結が確実に行われていることが目視出来る。また、解体する場合にはナットを緩めるだけでよいので作業が簡単である。   Further, since the wall pin hole 4d is formed at a position corresponding to the mounting pin hole 3c of the column base steel material 3 from the one outer surface where the slit 4c of the CLT panel 4 is formed toward the other outer surface, When the column base steel material 3 is stored in the slit 4c, the mounting pin hole 3c and the wall pin hole 4d are in a straight line and open. A drift pin or bolt as a fastener 5 is inserted into the pin holes 4d and 3c opened in a straight line in the direction indicated by an arrow B, and fixed, whereby the joining structure 1 to the foundation 2 of the CLT panel 4 as a wall member is obtained. Built. When the drift pin is used, it can be firmly fixed so that it does not come out even if a force in the direction of vibration or twist is applied by striking it with a hammer when inserting the drift pin from the opening of the wall pin hole 4d. Moreover, it is easy to fix because it is only necessary to hit the drift pin. Furthermore, by stopping the tip of the drift pin halfway so as not to protrude from the other side surface of the CLT panel 4, the side surface of the indoor CLT panel 4 can be kept clean. Similarly, when the fastener 5 is a bolt / nut, a bolt is inserted into the pin holes 4d, 3c opened in a straight line from one outer surface of the CLT panel 4 in the direction indicated by an arrow B and protruded from the other outer surface. It can be fixed by tightening a nut on the tip screw. In this case, the nut is exposed when the other outer surface is on the indoor side, but it can be visually confirmed that the fastening is securely performed. Further, when disassembling, the work is simple because it is only necessary to loosen the nut.

この発明の第2実施形態の壁部材と基礎の接合構造20について、図5乃至図8に基づいて説明する。前記第1実施形態の壁部材と基礎の接合構造1と異なるところは、柱脚鋼材3の数を1つにしたことと、これに伴いCLTパネル4のスリット4cの数も1つにしたこと、柱脚鋼材3の下方側部3aに貫通孔3dを設けることに代えて杭棒10を固定してこれによって基礎2のコンクレート7に柱脚鋼材3を確固に埋設したことである。これら以外は第1実施形態の壁部材と基礎の接合構造1と同じであるので、その説明を省略する。   A wall member-foundation joint structure 20 according to a second embodiment of the present invention will be described with reference to FIGS. The difference between the wall member and the foundation joint structure 1 of the first embodiment is that the number of column base steel members 3 is one and the number of slits 4c of the CLT panel 4 is also one accordingly. Instead of providing the through-hole 3d in the lower side portion 3a of the column base steel material 3, the pile rod 10 is fixed and thereby the column base steel material 3 is firmly embedded in the concrete 7 of the foundation 2. Other than these, the wall member and the basic joint structure 1 of the first embodiment are the same as those in the first embodiment, and the description thereof is omitted.

壁部材と基礎の接合構造20は、基礎2に下方側部3aを杭棒10と共に埋設固定され、上方側部3bを基礎2の上面2aから露出した柱脚鋼板3と、該柱脚鋼板3の基礎表面2aより露出した上方側部3bを収納するために底面4aの開口部4bから上方に向かって形成したスリット4cを具備するCLTパネル4と、前記柱脚鋼板3の上方側部3bに形成した取付ピン孔3c及び前記CLTパネル4の前記スリット4cを直角方向に貫通して形成した壁ピン孔4dと、前記取付ピン孔3c及び壁ピン孔4dを貫通して締結する締結具5と、を具備している。   The wall member / foundation joining structure 20 includes a column base steel plate 3 in which the lower side portion 3a is embedded and fixed to the foundation 2 together with the pile rod 10, and the upper side portion 3b is exposed from the upper surface 2a of the foundation 2, and the column base steel plate 3 CLT panel 4 having a slit 4c formed upward from opening 4b of bottom surface 4a to accommodate upper side 3b exposed from base surface 2a of the base, and upper side 3b of column base steel plate 3 A wall pin hole 4d formed by passing through the formed mounting pin hole 3c and the slit 4c of the CLT panel 4 in a right angle direction, and a fastener 5 for fastening through the mounting pin hole 3c and the wall pin hole 4d. Are provided.

前記柱脚鋼材3が前記第1実施形態の柱脚鋼材3と異なるところは、1つの柱脚鋼材3の下方側部3aの下端に杭棒10を溶接等によって固定して下方側部3aの一部と共に基礎2に埋設固定したことである。この杭棒10の周囲がコンクリート7によって固められることによって柱脚鋼材3が基礎2に固定される。そのために、第1実施形態の下方側部3aに形成されていた貫通孔3dは不要であるが、僅かに基礎2のコンクリート7に埋設されている下方側部3aに形成しておけばより確実に固定できる。この実施形態では杭棒10は2本であるが、1本或いは3本以上であっても良い。この1つの柱脚鋼材3に対応する1つのCLTパネル4のスリット4cは、CLTパネル4の底面4aの幅方向の中央の長手方向に開口された1つの開口部4bに通じており、吊上げられたCLTパネル4が上方から図5の矢印イ方向に降ろされて開口部4bが柱脚鋼材3の上方側部3bに嵌め込み収納される。これによって第1実施形態と同様に柱脚鋼材3の取付ピン穴3cと壁ピン穴4dが一直線上に並び締結具5が一方のCLTパネル4の側面から矢印ロ方向に挿入されて一体固定される。ドリフトピン或いはボルト・ナットによる連結固定は前述と同じであるので省略する。   The column base steel material 3 is different from the column base steel material 3 of the first embodiment in that the pile rod 10 is fixed to the lower end of the lower side portion 3a of one column base steel material 3 by welding or the like and the lower side portion 3a It is embedded and fixed in the foundation 2 together with a part. The column base steel material 3 is fixed to the foundation 2 by the periphery of the pile bar 10 being hardened by the concrete 7. Therefore, the through hole 3d formed in the lower side portion 3a of the first embodiment is unnecessary, but it is more reliable if it is formed in the lower side portion 3a embedded in the concrete 7 of the foundation 2 slightly. Can be fixed. In this embodiment, there are two pile rods 10, but one or three or more may be used. The slit 4c of one CLT panel 4 corresponding to this one column base steel material 3 leads to one opening 4b opened in the longitudinal direction of the center in the width direction of the bottom surface 4a of the CLT panel 4, and is lifted up. The CLT panel 4 is lowered from above in the direction of arrow A in FIG. 5, and the opening 4 b is fitted into and stored in the upper side portion 3 b of the column base steel material 3. As a result, as in the first embodiment, the mounting pin holes 3c and the wall pin holes 4d of the column base steel members 3 are arranged in a straight line, and the fastener 5 is inserted in the direction of the arrow B from the side surface of one CLT panel 4 and fixed integrally. The The connecting and fixing with the drift pins or bolts and nuts is the same as described above, and will be omitted.

前記杭棒10は、材質、長さ及び太さは建物の構造によって適宜選択して使用されるが、下端部に、図6〜8に良く現れているように、定着板10aを設けておくと引き抜きの力の作用に対して抗力を有し且つコンクリート7との接触面積も多くなるので強固に固定できる。基礎2の主筋6が基礎2の中心部に位置し、CLTパネル4が上面2aの中心に設置された場合には、コンクリート7の内部で重なり合うことを避けるために、配筋位置をずらせておくことが望ましい。   The pile rod 10 is used by appropriately selecting the material, length, and thickness depending on the structure of the building, but a fixing plate 10a is provided at the lower end as shown well in FIGS. Since it has a resistance against the action of the pulling force and increases the contact area with the concrete 7, it can be firmly fixed. When the main reinforcement 6 of the foundation 2 is located at the center of the foundation 2 and the CLT panel 4 is installed at the center of the upper surface 2a, the reinforcement arrangement positions are shifted in order to avoid overlapping in the concrete 7. It is desirable.

CLTパネル4は、CLTであることから自身が耐力性のある構造材にもなり得るので、この2つの実施形態においては、CLTパネル4は上方の荷重を支持する柱の役目と壁材の役目を兼用している。従って、基礎2の角部のCLTパネル4の直角接合や横方向に隣合う同士の平面接合については、それぞれの位置が合致するように柱脚鋼材3の基礎2への埋設固定位置が定められる。この発明の壁部材と基礎接合構造1、20は、CLTパネル4を基礎2の上面2aに土台を介在させることなく直接に載置固定するものであるからその分構造部材の節減や建設手数の省力化を図れると共に、土台の基礎への固定状態の不安定さによる建物の歪の発生を防止できる。尚、この発明の第1及び第2の実施形態においては、壁部材としてCLTパネルを使用した実施例について説明したが、集成材を枝状にした集成材や大断面柱等も使用できる。   Since the CLT panel 4 is a CLT, the CLT panel 4 itself can be a structural material having strength. In these two embodiments, the CLT panel 4 functions as a column that supports an upper load and a role as a wall material. Is also used. Therefore, the embedding fixing position of the column base steel material 3 to the foundation 2 is determined so that the respective positions coincide with each other for the right angle joining of the CLT panel 4 at the corner portion of the foundation 2 and the planar joining of the adjacent sides in the lateral direction. . Since the wall member and the foundation joint structures 1 and 20 according to the present invention are for directly mounting and fixing the CLT panel 4 on the upper surface 2a of the foundation 2 without interposing a base, the structural members can be saved and the construction work can be saved accordingly. In addition to saving labor, it is possible to prevent the building from being distorted due to instability of the fixed state of the foundation. In the first and second embodiments of the present invention, the example in which the CLT panel is used as the wall member has been described. However, it is also possible to use a laminated material in which the laminated material is branched, a large cross-sectional column, or the like.

この発明は、今後ますます有効利用されるであろう構造部材を兼ねた壁材としてのCLTパネルの基礎への接合構造であるから、多くの新築建物、とくに木造家屋や木造集合家屋に有効に活用されることが期待される。   Since the present invention is a joint structure to the foundation of the CLT panel as a wall material that also serves as a structural member that will be used more and more effectively in the future, it is effective for many new buildings, especially wooden houses and wooden collective houses. Expected to be utilized.

1、20 壁部材と基礎の接合構造
2 基礎
2a 上面
3 柱脚鋼材
3a 下方側部
3b 上方側部
3c 取付ピン孔
4 CLTパネル(壁部材)
4a 底面
4b 開口部
4c スリット
4d 壁ピン孔
5 締結具
6 主筋
7 コンクリート
8 通気スペーサ
9 樹脂テープ
10 杭棒
DESCRIPTION OF SYMBOLS 1,20 Joining structure 2 of wall member and foundation 2 Foundation 2a Upper surface 3 Column base steel material 3a Lower side part 3b Upper side part 3c Mounting pin hole 4 CLT panel (wall member)
4a Bottom 4b Opening 4c Slit 4d Wall pin hole 5 Fastener 6 Main reinforcement 7 Concrete 8 Venting spacer 9 Resin tape 10 Pile stick

この発明は上記問題点を解決すべくなされたものであって、その手段とするところは、中心部に鉄筋が配設されて周囲をコンクリートで固めて所定の幅を上面に有する基礎の前記コンクリートに複数の貫通穴を形成した下方側部埋設固定され上方側部が前記基礎の面から露出した金属薄板からなる柱脚鋼板と、該柱脚鋼板の基礎の上面より露出した上方側部を収納するために底面の開口部から上方に向かって形成したスリットを具備する壁部材と、前記柱脚鋼板の上方側部に形成した取付ピン孔及び前記壁部材の前記スリットを直角方向に貫通して形成した壁ピン孔と、前記取付ピン孔及び壁ピン孔を貫通して柱脚鋼板と壁部材を締結する締結具、を具備することを特徴とする壁部材と基礎の接合構造としたことにある。 The present invention has been made to solve the above-mentioned problems, and the means for this is the above-mentioned concrete of the foundation having a predetermined width on the upper surface, in which a reinforcing bar is arranged at the center, the periphery is solidified with concrete. lower side forming a plurality of through-holes are embedded and fixed in the column base steel sheet is upward side made of sheet metal which is exposed from the upper surface of the base, the upper exposed from the upper surface of the foundation of the columnar legs steel A wall member having a slit formed upward from the opening on the bottom surface to accommodate the side portion, a mounting pin hole formed in the upper side portion of the column base steel plate, and the slit of the wall member in a perpendicular direction A wall pin hole formed through the wall and a fastener for fastening the column base steel plate and the wall member through the mounting pin hole and the wall pin hole. It is in that.

又、前記壁部材がCLTパネルであることにある。更に、前記柱脚鋼板及び壁部材のスリットが基礎の幅方向に複数対設けられていることにある。更に又、前記基礎の上面と壁部材の底面の間に通気スペーサを介在させたことにある。又、前記柱脚鋼の下方に杭棒を固定したことにある。 Further, the wall member is a CLT panel. Furthermore, a plurality of pairs of the column base steel plates and the slits of the wall member are provided in the width direction of the foundation. Furthermore, a ventilation spacer is interposed between the upper surface of the foundation and the bottom surface of the wall member. Further, it lies in fixing the Kuibo below the column base steel plate.

前記柱脚鋼の下方に杭棒を固定した場合には、この杭棒が基礎のコンクリートに埋設固定されるので、柱脚鋼板の下方側部の基礎への埋設固定部分が少なくなっても強度維持できる。 When fixing the Kuibo below the column base steel plate, since the pile bars are embedded and fixed in the concrete of the foundation, even when fewer embedded and fixed portion of the basis for the lower side of column base steel sheet Strength can be maintained.

1、20 壁部材と基礎の接合構造
2 基礎
2a 上面
3 柱脚鋼
3a 下方側部
3b 上方側部
3c 取付ピン孔
4 CLTパネル(壁部材)
4a 底面
4b 開口部
4c スリット
4d 壁ピン孔
5 締結具
6 主筋
7 コンクリート
8 通気スペーサ
9 樹脂テープ
10 杭棒
1,20 wall member and joining structure of the basic second basic 2a top 3 column base steel plate 3a lower side 3b upper side 3c mounting pin holes 4 CLT panel (wall member)
4a Bottom 4b Opening 4c Slit 4d Wall pin hole 5 Fastener 6 Main reinforcement 7 Concrete 8 Venting spacer 9 Resin tape 10 Pile stick

Claims (9)

基礎に下方側部を埋設固定され上方側部を基礎の表面から露出した柱脚鋼板と、該柱脚鋼板の基礎表面より露出した上方側部を収納するために底面の開口部から上方に向かって形成したスリットを具備する壁部材と、前記柱脚鋼板の上方側部に形成した取付ピン孔及び前記壁部材の前記スリットを直角方向に貫通して形成した壁ピン孔と、前記取付ピン孔及び壁ピン孔を貫通して柱脚鋼板と壁部材を締結する締結具と、を具備することを特徴とする壁部材と基礎の接合構造。   The lower side is embedded in the foundation and fixed, and the upper side is exposed from the surface of the foundation, and the upper side exposed from the foundation surface of the column base is directed upward from the bottom opening. A wall member having a slit formed therein, a mounting pin hole formed in an upper side portion of the column base steel plate, a wall pin hole formed by penetrating the slit of the wall member in a right angle direction, and the mounting pin hole And a fastener for penetrating the column base steel plate and the wall member through the wall pin hole, and a joining structure of the wall member and the foundation. 前記壁部材がCLTパネルであることを特徴とする請求項1に記載の壁部材と基礎の接合構造   The wall member-foundation joint structure according to claim 1, wherein the wall member is a CLT panel. 前記柱脚鋼板及び壁部材のスリットが基礎の幅方向に複数対設けられていることを特徴とする請求項1又は請求項2に記載の壁部材と基礎の接合構造。   3. The wall member-foundation joint structure according to claim 1 or 2, wherein a plurality of pairs of the column base steel plates and the wall member slits are provided in the width direction of the foundation. 前記基礎の上面と壁部材の底面の間に通気スペーサを介在させたことを特徴とする請求項1乃至3のいずれか一項に記載の壁部材と基礎の接合構造。   The wall member / foundation joining structure according to any one of claims 1 to 3, wherein a ventilation spacer is interposed between the upper surface of the foundation and the bottom surface of the wall member. 前記柱脚鋼材の下方に杭棒を固定したことを特徴とする請求項1乃至4のいずれか一項に記載の壁部材と基礎の接合構造。   5. The wall member-foundation joint structure according to claim 1, wherein a pile bar is fixed below the column base steel material. 前記締結具がドリフトピンであることを特徴とする請求項1乃至5のいずれか一項に記載の壁部材と基礎の接合構造。   The wall member-foundation joint structure according to any one of claims 1 to 5, wherein the fastener is a drift pin. 前記締結具がボルト、ナットであることを特徴とする請求項1乃至5のいずれか一項に記載の壁部材と基礎の接合構造。   The said fastener is a volt | bolt and a nut, The joining structure of the wall member and foundation as described in any one of Claim 1 thru | or 5 characterized by the above-mentioned. 前記壁部材が、柱と兼用した壁材であることを特徴とする請求項1乃至7のいずれか一項に記載の壁部材と基礎の接合構造。   The wall member-foundation joint structure according to any one of claims 1 to 7, wherein the wall member is a wall material also used as a pillar. 前記基礎の長手方向に柱脚鋼板と壁部材のスリットが複数対設置されていることを特徴とする請求項1乃至8のいずれか一項に記載の壁部材と基礎の接合構造。
The wall member-foundation joint structure according to any one of claims 1 to 8, wherein a plurality of pairs of column base steel plates and wall member slits are installed in the longitudinal direction of the foundation.
JP2017103134A 2017-05-24 2017-05-24 Wall member and foundation joint structure Active JP6583348B2 (en)

Priority Applications (2)

Application Number Priority Date Filing Date Title
JP2017103134A JP6583348B2 (en) 2017-05-24 2017-05-24 Wall member and foundation joint structure
JP2019008074A JP6892991B2 (en) 2017-05-24 2019-01-21 Joint structure of wall member and foundation

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP2017103134A JP6583348B2 (en) 2017-05-24 2017-05-24 Wall member and foundation joint structure

Related Child Applications (1)

Application Number Title Priority Date Filing Date
JP2019008074A Division JP6892991B2 (en) 2017-05-24 2019-01-21 Joint structure of wall member and foundation

Publications (2)

Publication Number Publication Date
JP2018197474A true JP2018197474A (en) 2018-12-13
JP6583348B2 JP6583348B2 (en) 2019-10-02

Family

ID=64663689

Family Applications (1)

Application Number Title Priority Date Filing Date
JP2017103134A Active JP6583348B2 (en) 2017-05-24 2017-05-24 Wall member and foundation joint structure

Country Status (1)

Country Link
JP (1) JP6583348B2 (en)

Cited By (10)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109853840A (en) * 2019-02-18 2019-06-07 北京工业大学 A kind of assembled sandwich out-hung panel system
CN110439141A (en) * 2019-07-26 2019-11-12 广州大学 It is a kind of for fabricated shear wall can tolerance steel section jointing structure
WO2020209150A1 (en) * 2019-04-08 2020-10-15 積水ハウス株式会社 Clt structure
CN112459260A (en) * 2020-10-28 2021-03-09 上海建工二建集团有限公司 Steel structure connecting device of prefabricated vertical component construction node
JP2021059902A (en) * 2019-10-07 2021-04-15 大豊建設株式会社 Wall structure, and construction method of wall structure
JP2021059901A (en) * 2019-10-07 2021-04-15 大豊建設株式会社 Wall structure, and construction method of wall structure
CN113513107A (en) * 2020-08-20 2021-10-19 中国建筑标准设计研究院有限公司 Assembled integral mortise-tenon joint multi-cavity steel plate combined shear wall and manufacturing method thereof
CN114482341A (en) * 2022-02-23 2022-05-13 中青建安建设集团有限公司 Connection structure of assembly type structure wallboard
CN114658113A (en) * 2022-04-25 2022-06-24 中交一公局集团有限公司 Wind-resistant anchor bolt device convenient to maintain and used for assembly type wood structure building
CN116950225A (en) * 2023-08-25 2023-10-27 中国电建集团华东勘测设计研究院有限公司 Connecting piece and prefabricated building component

Citations (14)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS50159132A (en) * 1974-06-12 1975-12-23
JPH04108921A (en) * 1990-08-29 1992-04-09 Tategu Sogo Shosha Futaba:Kk Mat foundation panel
JPH07247629A (en) * 1994-03-03 1995-09-26 Nippon Steel Corp Anchor structure using perforated steel plate
JPH08311993A (en) * 1995-05-17 1996-11-26 Sekisui House Ltd Connection structure and connection metal member of column base in wooden framework
JPH09195401A (en) * 1996-01-19 1997-07-29 Sumitomo Forestry Co Ltd Under floor ventilating construction and ventilation parting edge material
JPH111962A (en) * 1997-06-11 1999-01-06 Sekisui House Ltd Connector for column and sill for wooden framework
JP2000129952A (en) * 1998-10-23 2000-05-09 Ohbayashi Corp Earthquake resistant wall, and execution method thereof
JP2001234584A (en) * 2000-02-23 2001-08-31 Itochu Kenzai Corp Jointed construction of wall column and floor beam using veneer laminated member
JP2002309591A (en) * 2001-04-13 2002-10-23 Nippon Steel Corp Structure for joining pile head to steel footing beam
JP2004143911A (en) * 2002-02-27 2004-05-20 Yui Sekkei:Kk Wall structural body using timber and its construction method
JP2005299177A (en) * 2004-04-09 2005-10-27 Joto Techno Co Ltd Building and construction method thereof
JP2015200177A (en) * 2015-07-02 2015-11-12 住友林業株式会社 Formation method of building foundation and temporary support metal fitting
JP2016180281A (en) * 2015-03-25 2016-10-13 株式会社益田建設 House exterior wall construction method
JP2017053187A (en) * 2015-09-11 2017-03-16 積水ハウス株式会社 Residential structure

Patent Citations (14)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS50159132A (en) * 1974-06-12 1975-12-23
JPH04108921A (en) * 1990-08-29 1992-04-09 Tategu Sogo Shosha Futaba:Kk Mat foundation panel
JPH07247629A (en) * 1994-03-03 1995-09-26 Nippon Steel Corp Anchor structure using perforated steel plate
JPH08311993A (en) * 1995-05-17 1996-11-26 Sekisui House Ltd Connection structure and connection metal member of column base in wooden framework
JPH09195401A (en) * 1996-01-19 1997-07-29 Sumitomo Forestry Co Ltd Under floor ventilating construction and ventilation parting edge material
JPH111962A (en) * 1997-06-11 1999-01-06 Sekisui House Ltd Connector for column and sill for wooden framework
JP2000129952A (en) * 1998-10-23 2000-05-09 Ohbayashi Corp Earthquake resistant wall, and execution method thereof
JP2001234584A (en) * 2000-02-23 2001-08-31 Itochu Kenzai Corp Jointed construction of wall column and floor beam using veneer laminated member
JP2002309591A (en) * 2001-04-13 2002-10-23 Nippon Steel Corp Structure for joining pile head to steel footing beam
JP2004143911A (en) * 2002-02-27 2004-05-20 Yui Sekkei:Kk Wall structural body using timber and its construction method
JP2005299177A (en) * 2004-04-09 2005-10-27 Joto Techno Co Ltd Building and construction method thereof
JP2016180281A (en) * 2015-03-25 2016-10-13 株式会社益田建設 House exterior wall construction method
JP2015200177A (en) * 2015-07-02 2015-11-12 住友林業株式会社 Formation method of building foundation and temporary support metal fitting
JP2017053187A (en) * 2015-09-11 2017-03-16 積水ハウス株式会社 Residential structure

Cited By (19)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109853840A (en) * 2019-02-18 2019-06-07 北京工业大学 A kind of assembled sandwich out-hung panel system
GB2596740A (en) * 2019-04-08 2022-01-05 Sekisui House Kk CLT structure
WO2020209150A1 (en) * 2019-04-08 2020-10-15 積水ハウス株式会社 Clt structure
JP2020172743A (en) * 2019-04-08 2020-10-22 積水ハウス株式会社 CLT structure
JP7243400B2 (en) 2019-04-08 2023-03-22 積水ハウス株式会社 CLT structure
GB2596740B (en) * 2019-04-08 2023-02-08 Sekisui House Kk CLT structure
US11708679B2 (en) 2019-04-08 2023-07-25 Sekisui House, Ltd. CLT structure
CN110439141A (en) * 2019-07-26 2019-11-12 广州大学 It is a kind of for fabricated shear wall can tolerance steel section jointing structure
JP2021059901A (en) * 2019-10-07 2021-04-15 大豊建設株式会社 Wall structure, and construction method of wall structure
JP6994012B2 (en) 2019-10-07 2022-01-14 大豊建設株式会社 Wall structure and how to build the wall structure
JP7030754B2 (en) 2019-10-07 2022-03-07 大豊建設株式会社 Wall structure and how to build the wall structure
JP2021059902A (en) * 2019-10-07 2021-04-15 大豊建設株式会社 Wall structure, and construction method of wall structure
CN113513107A (en) * 2020-08-20 2021-10-19 中国建筑标准设计研究院有限公司 Assembled integral mortise-tenon joint multi-cavity steel plate combined shear wall and manufacturing method thereof
CN112459260A (en) * 2020-10-28 2021-03-09 上海建工二建集团有限公司 Steel structure connecting device of prefabricated vertical component construction node
CN114482341A (en) * 2022-02-23 2022-05-13 中青建安建设集团有限公司 Connection structure of assembly type structure wallboard
CN114482341B (en) * 2022-02-23 2024-01-19 中青建安建设集团有限公司 Connection structure of assembled building wallboard
CN114658113A (en) * 2022-04-25 2022-06-24 中交一公局集团有限公司 Wind-resistant anchor bolt device convenient to maintain and used for assembly type wood structure building
CN114658113B (en) * 2022-04-25 2023-09-22 中交一公局集团有限公司 Wind-resistant anchor bolt device of assembled wood structure building convenient to maintain
CN116950225A (en) * 2023-08-25 2023-10-27 中国电建集团华东勘测设计研究院有限公司 Connecting piece and prefabricated building component

Also Published As

Publication number Publication date
JP6583348B2 (en) 2019-10-02

Similar Documents

Publication Publication Date Title
JP6583348B2 (en) Wall member and foundation joint structure
JPH07217226A (en) Reinforcing method for reinforced concrete floor slab
JP4895284B2 (en) Reinforcement structure of existing steel structural members
KR100763886B1 (en) An Apparatus for Fixing Curtain Wall
KR20070027432A (en) A fastener for fixing a reinforcing bar assembly, a mold panel, and a ceiling panel by fixing pin
JP2016169565A (en) In-plane shear bearing force structure, and roof structure, wall structure and floor structure having in-plane shear bearing force structure
JP6892991B2 (en) Joint structure of wall member and foundation
JP7339865B2 (en) How to install wall panels
KR101363795B1 (en) Joint construction of modular unit structure and foundation concrete
JP2020122268A (en) Structure with vibration control device
JP6860354B2 (en) Building structure
JP5142575B2 (en) Seismic reinforcement method for wooden buildings and wooden buildings
WO2022254533A1 (en) Anchor support tool and form set for foundation
JP6731467B2 (en) Building structure
JP5095424B2 (en) Wall panel mounting structure and mounting method
JP4871363B2 (en) Column / beam joint structure and unit building reconstruction method
JP5658455B2 (en) Unit building
JP3967824B2 (en) Building floor sound insulation
AU2010257353A1 (en) Building foundation structure, foundation construction method, and anchor bolt installation jig
JP5102111B2 (en) Wall panel mounting equipment in wooden buildings
JP4207214B2 (en) Construction methods for interior and exterior base materials and concrete structures
JPS6340579Y2 (en)
JP2005351068A (en) Structure for reinforcing reentrant part of existing wooden building
JP2015161061A (en) Ligneous frame structure
JP4778329B2 (en) Column fixing jig

Legal Events

Date Code Title Description
A621 Written request for application examination

Free format text: JAPANESE INTERMEDIATE CODE: A621

Effective date: 20170720

A131 Notification of reasons for refusal

Free format text: JAPANESE INTERMEDIATE CODE: A131

Effective date: 20180710

A601 Written request for extension of time

Free format text: JAPANESE INTERMEDIATE CODE: A601

Effective date: 20180720

A521 Request for written amendment filed

Free format text: JAPANESE INTERMEDIATE CODE: A523

Effective date: 20180905

A131 Notification of reasons for refusal

Free format text: JAPANESE INTERMEDIATE CODE: A131

Effective date: 20181120

A521 Request for written amendment filed

Free format text: JAPANESE INTERMEDIATE CODE: A523

Effective date: 20190121

A131 Notification of reasons for refusal

Free format text: JAPANESE INTERMEDIATE CODE: A131

Effective date: 20190702

A521 Request for written amendment filed

Free format text: JAPANESE INTERMEDIATE CODE: A523

Effective date: 20190716

TRDD Decision of grant or rejection written
A01 Written decision to grant a patent or to grant a registration (utility model)

Free format text: JAPANESE INTERMEDIATE CODE: A01

Effective date: 20190806

A61 First payment of annual fees (during grant procedure)

Free format text: JAPANESE INTERMEDIATE CODE: A61

Effective date: 20190819

R150 Certificate of patent or registration of utility model

Ref document number: 6583348

Country of ref document: JP

Free format text: JAPANESE INTERMEDIATE CODE: R150

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250