JP2005299177A - Building and construction method thereof - Google Patents

Building and construction method thereof Download PDF

Info

Publication number
JP2005299177A
JP2005299177A JP2004115636A JP2004115636A JP2005299177A JP 2005299177 A JP2005299177 A JP 2005299177A JP 2004115636 A JP2004115636 A JP 2004115636A JP 2004115636 A JP2004115636 A JP 2004115636A JP 2005299177 A JP2005299177 A JP 2005299177A
Authority
JP
Japan
Prior art keywords
foundation
packing
base
building
foundation packing
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
JP2004115636A
Other languages
Japanese (ja)
Other versions
JP4364045B2 (en
Inventor
Tetsuya Niki
哲也 仁木
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Joto Techno Co Ltd
Original Assignee
Joto Techno Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Joto Techno Co Ltd filed Critical Joto Techno Co Ltd
Priority to JP2004115636A priority Critical patent/JP4364045B2/en
Publication of JP2005299177A publication Critical patent/JP2005299177A/en
Application granted granted Critical
Publication of JP4364045B2 publication Critical patent/JP4364045B2/en
Anticipated expiration legal-status Critical
Expired - Fee Related legal-status Critical Current

Links

Images

Landscapes

  • Foundations (AREA)
  • Joining Of Building Structures In Genera (AREA)

Abstract

<P>PROBLEM TO BE SOLVED: To provide a construction method of a building capable of facilitating the exact alignment of a sill based on a marking line with the exact alignment of a tabular body of an external facing plate or as a part of the external facing plate. <P>SOLUTION: The construction method of a building comprises a process describing the marking line 13 for the alignment of the sill 30 on the upper surface 11 of the foundation, a process mounting a foundation packing 20 forming a plurality of grooves 25 passing through in the vertical direction in the outside 22 of a long side of a rectangular tabular base body 21 having a predetermined thickness on the upper surface 11 of the foundation so that the marking line can be viewed from above through the grooves, a process mounting the sill 30 on the upper surface of the foundation packing 20 so that the outside of the sill 30 can located upward of the marking line and a process mounting the external facing plate or the tabular body 50 as a part of the external facing plate on the upper surface of the foundation packing 20 in an outside space side from the outside of the sill 30. <P>COPYRIGHT: (C)2006,JPO&NCIPI

Description

この発明は、基礎パッキンを基礎と土台との間に設ける建造物の施工方法と、当該建造物とに関する。特に、基礎パッキンを布基礎と木製土台との間に設ける建造物の施工方法と、当該建造物とに関する。 The present invention relates to a construction method for a building in which a foundation packing is provided between a foundation and a foundation, and the building. In particular, the present invention relates to a construction method for a building in which a foundation packing is provided between a cloth foundation and a wooden base, and the building.

木造住宅等の建造物を建築する手法としては、例えば、建物を建てるべき部位の外殻部や内殻部にコンクリート製の基礎を作った後、基礎の上面に土台の位置合わせ用の墨出し線を描き、墨出し線を基準として基礎の上に木材の土台を固定し、木製土台の上に柱を立て、柱の上に梁を載せるという手法がある。このような手法は、伝統的な日本建築の手法であり、木造住宅の建築において広く採用されている。 As a method of building a structure such as a wooden house, for example, a concrete foundation is made on the outer shell or inner shell of the part where the building is to be built, and then the ink is placed on the upper surface of the foundation for positioning the foundation. There is a method of drawing a line, fixing a timber base on the foundation based on the ink line, setting a pillar on the wooden base, and placing a beam on the pillar. Such a technique is a traditional Japanese architecture technique and is widely used in the construction of wooden houses.

コンクリート基礎(布基礎)は、セメント、砂、水を混合して流動状にして予め組み立てた金属製又は木製の型枠に流し込み、数日放置して固化させることにより作られる。この型枠は金属製又は木製の板を複数組み合わせて現場にて設置されるものであるので、その設置時の各板の位置合わせ状態を一直線上に並ぶように設置することは困難であることから、固化したコンクリート基礎の側縁にうねりが生じてしまうのが一般的である。そこで、コンクリート基礎の上面に墨出し線を描くことにより、この墨出し線を基準としてコンクリート基礎に対して木製土台が正確な位置に配置するようにしている。なお、コンクリート基礎の上面に描かれる墨出し線としては、例えば、木製土台の中心線で位置合わせを行うための心墨や、心墨から所定寸法だけ離して平行に描かれる逃げ墨等が用いられる。 Concrete foundations (cloth foundations) are made by mixing cement, sand, and water, pouring them into a fluidized metal or wooden formwork, and allowing them to stand for several days to solidify. Since this formwork is installed in the field by combining a plurality of metal or wooden plates, it is difficult to install so that the alignment state of each plate at the time of installation is aligned. Therefore, it is common that waviness is generated at the side edge of the solidified concrete foundation. Therefore, by drawing a summing line on the upper surface of the concrete foundation, the wooden base is arranged at an accurate position with respect to the concrete foundation based on the marking line. In addition, as the inking line drawn on the top surface of the concrete foundation, for example, a heart ink for alignment with the center line of the wooden base, a relief ink drawn in parallel with a predetermined dimension away from the heart ink, etc. are used. It is done.

このように墨出し線を描いて木製土台を載置する手法によれば、コンクリート基礎の側縁にうねりが生じていても、うねりのある側縁を基準として木製土台を配置するのではなく、正確な直線を呈する墨出し線を基準として、コンクリート基礎の上面に木製土台を精度よく載置することができるが、その一方で、水分を大量に含み、且つ、長期的に水分を排出するコンクリート自体の特性によって、コンクリート基礎が直接接触する木製土台との接触部位で、木製土台がコンクリート基礎の水分を吸って湿り乾燥しにくくなり、湿って乾燥を阻害すると経時的に木製土台の腐朽を招来するという問題があった。
また、コンクリート基礎と木製土台との間には隙間がないので、両者の間から換気するということができないのであるが、木造住宅においては、床下の換気を行う必要があるため、一般的に、コンクリート基礎の適当な部位に、例えば、縦200mm×横400mm程度の換気穴を形成するということが行われていた。しかし、コンクリート基礎には木造住宅の荷重等に耐え得るだけの充分な強度が必要であるため、このような大きな換気穴を多数形成することは困難であり、形成可能な換気穴の数には制限があった。そのため、床下空間の換気穴から遠い隅部には湿気が滞留し易いという問題があった。
According to the technique of drawing the ink line and placing the wooden base in this way, even if waviness occurs on the side edge of the concrete foundation, instead of placing the wooden base on the basis of the wavy side edge, A concrete foundation that can accurately place a wooden base on the upper surface of a concrete foundation, based on the ink marking line showing an accurate straight line, while containing a large amount of moisture and discharging moisture in the long term. Due to its own characteristics, the wooden foundation absorbs the moisture of the concrete foundation at the site of contact with the wooden foundation where the concrete foundation comes into direct contact, making it difficult to wet and drying. If the wet foundation inhibits drying, the wooden foundation will decay over time. There was a problem to do.
Also, since there is no gap between the concrete foundation and the wooden base, it is not possible to ventilate between the two, but in wooden houses it is necessary to ventilate under the floor, For example, a ventilation hole having a length of about 200 mm and a width of about 400 mm has been formed in an appropriate portion of a concrete foundation. However, concrete foundations need to be strong enough to withstand the load of a wooden house, so it is difficult to form many such large ventilation holes. There were restrictions. For this reason, there is a problem that moisture tends to stay in a corner portion far from the ventilation hole in the underfloor space.

このような理由により、従来の木造住宅の床下は、換気を充分に行うことができず湿気がこもり易く、木製土台は、床下の湿気とコンクリート基礎の水分とを吸収して常に湿った状態にあった。そのため、長年の間に土台が腐朽してしまうという問題があった。また、床下においてシロアリの繁殖に好適な湿気と温度とが保たれてしまい、シロアリによって土台が喰い荒らされるという問題もあった。また、換気が悪いとシロアリの他に腐朽菌が土台や柱に繁殖し、土台や柱を腐朽させるという問題もあった。さらに、コンクリート基礎に換気穴を形成すると、木造住宅の荷重等によって、換気穴の隅部からコンクリート基礎に亀裂が入ってしまうという問題もあった。 For this reason, under floors of conventional wooden houses cannot be adequately ventilated and moisture is easily trapped, and the wooden base absorbs moisture under the floor and moisture of the concrete foundation so that it is always moist. there were. For this reason, there has been a problem that the foundation will decay over the years. In addition, moisture and temperature suitable for termite breeding are kept under the floor, and there is also a problem that the base is devoured by termites. In addition, when there is poor ventilation, there is a problem that in addition to termites, decaying fungi propagate on the foundations and pillars, causing the foundations and pillars to decay. Furthermore, when the ventilation hole is formed in the concrete foundation, there is a problem that the concrete foundation is cracked from the corner of the ventilation hole due to the load of the wooden house.

このような問題を解決するために創案されたものが基礎パッキンである。基礎パッキンは、基礎と土台との間に設けられるものであり、長い実績を保ち現在も数多く木造住宅の建設に用いられている。なお、本出願人の先願である特許文献1〜3に、基礎パッキンの形状や材質が詳しく述べられている。 The basic packing has been created to solve such problems. Foundation packing is provided between the foundation and the foundation, and has a long track record and is still used for the construction of wooden houses. In addition, the shape and material of the basic packing are described in detail in Patent Documents 1 to 3, which are the prior applications of the present applicant.

従来の基礎パッキンの一例について、図面を用いて説明する。
図5は、従来の基礎パッキンの一例を模式的に示す斜視図である。
基礎パッキン100は、前後辺にそれぞれ3つの窪み101を有し、長手方向端辺には突起102と窪み103とを有する。突起102と窪み103とは、雌雄嵌合可能な形状となっている。基礎パッキン100の土台と接触する面には、通気のために長手方向に伸びた溝104が形成されている。また、基礎パッキン100には、上下方向に貫通した穴105が形成されている。穴105は、コンクリート基礎から上方へ突出したアンカーボルトを挿通するためのものである。また、基礎パッキン100は、長さLが200mm、幅Wが100mm、高さHが20mm程度の大きさを有している。
An example of a conventional basic packing will be described with reference to the drawings.
FIG. 5 is a perspective view schematically showing an example of a conventional basic packing.
The base packing 100 has three recesses 101 on the front and rear sides, and has a protrusion 102 and a recess 103 on the end in the longitudinal direction. The protrusion 102 and the recess 103 have a shape that allows male and female fitting. A groove 104 extending in the longitudinal direction for ventilation is formed on the surface of the base packing 100 that contacts the base. Further, the base packing 100 is formed with a hole 105 penetrating in the vertical direction. The hole 105 is for inserting an anchor bolt protruding upward from the concrete foundation. The base packing 100 has a length L of 200 mm, a width W of 100 mm, and a height H of about 20 mm.

一の基礎パッキン100の突起102を、他の基礎パッキン100の窪み103に嵌合すると、2枚の基礎パッキン100を長手方向に結合することができる。また、一の基礎パッキン100の突起102を、他の基礎パッキン100の窪み101に嵌合すると、2枚の基礎パッキン100をT字型に組み合わせることができる。このように、長手方向又は前後方向に基礎パッキン100を繋ぎ合わせ、コンクリート基礎の面上に並べることができる。 When the protrusions 102 of one base packing 100 are fitted into the recesses 103 of the other base packing 100, the two base packings 100 can be joined in the longitudinal direction. Further, when the protrusions 102 of one foundation packing 100 are fitted into the recesses 101 of the other foundation packing 100, the two foundation packings 100 can be combined into a T-shape. In this way, the foundation packing 100 can be joined in the longitudinal direction or the front-rear direction and arranged on the surface of the concrete foundation.

このような基礎パッキンを、アンカーボルトが設けられた部分のコンクリート基礎の上面に載置する。コンクリート基礎の直角の隅部では、2枚の基礎パッキンをT字型又はL字型に組み合わせて載置する。コンクリート基礎の直線部では、基礎パッキンを1枚ずつ載置することもあるが、2枚の基礎パッキンを上述したように長手方向に結合して載置することもある。そして、基礎パッキンの上面に、アンカーボルトの通し穴を穿った土台用木材を載置し、アンカーボルトにナットを螺合させて緊締することにより、コンクリート基礎と基礎パッキンと木製土台とを固定することができる。勿論、単にコンクリート基礎の上面に基礎パッキンを載置するだけの部分もある。 Such a foundation packing is placed on the upper surface of the concrete foundation at the portion where the anchor bolt is provided. At the right corner of the concrete foundation, two foundation packings are placed in combination in a T-shape or L-shape. In the straight part of the concrete foundation, the foundation packing may be placed one by one, but the two foundation packings may be placed in the longitudinal direction as described above. Then, the base wood having the through holes for the anchor bolts is placed on the upper surface of the foundation packing, and the concrete foundation, the foundation packing, and the wooden base are fixed by screwing and tightening the nuts to the anchor bolts. be able to. Of course, there is also a part where the foundation packing is simply placed on the upper surface of the concrete foundation.

通常、コンクリート基礎の上面の全周域に基礎パッキンを載置するのではなく、一定の間隔を空けて載置し、基礎パッキンが載置されていない部分の隙間(高さ20mm程度)を換気穴として利用する。従って、基礎パッキンを用いることにより、コンクリート基礎に換気穴を形成する必要がなるため、基礎工事を省力化することができ、コンクリート基礎の強度を充分に保つことができる。また、木製土台の横滑りを防止して耐震性の高い構造とすることができる。また、水分を含むコンクリート基礎と木製土台との間に基礎パッキンが介装されるので木製土台に水分が浸潤しない。従って、木製土台の腐朽やシロアリの喰害を受け難く、木製土台の耐久性が向上して木造住宅の寿命が長くすることができる。 Usually, the foundation packing is not placed on the entire circumference of the upper surface of the concrete foundation, but is placed at a certain interval, and the gap (height of about 20 mm) in the part where the foundation packing is not placed is ventilated. Use as a hole. Therefore, since it is necessary to form a ventilation hole in the concrete foundation by using the foundation packing, the foundation work can be saved, and the strength of the concrete foundation can be sufficiently maintained. Moreover, it is possible to prevent the skid of the wooden base and make a structure having high earthquake resistance. In addition, since the foundation packing is interposed between the concrete foundation containing moisture and the wooden base, moisture does not infiltrate the wooden base. Therefore, the wooden base is less susceptible to decay and termite erosion, and the durability of the wooden base is improved and the life of the wooden house can be extended.

さらに、コンクリート基礎の上面に一定の間隔を空けて基礎パッキンを載置するため、コンクリート基礎の上面に描いた墨出し線の全てが基礎パッキンによって視認し得ない状態となることはない。従って、基礎パッキンを基礎の上面に載置しても、墨出し線を基準とした正確な木製土台の位置合わせを行うことができる。 Furthermore, since the foundation packing is placed on the upper surface of the concrete foundation with a certain interval, all of the inking lines drawn on the upper surface of the concrete foundation do not become invisible. Therefore, even if the foundation packing is placed on the upper surface of the foundation, it is possible to accurately align the wooden base with reference to the inking line.

このように基礎パッキンを用いる施工方法は基礎パッキン工法と称される。基礎パッキン工法によれば、建造物の換気性を向上させ、木製土台の腐朽やシロアリの喰害を防止することができ、建造物は堅牢となり耐震性を高めることができる。また、施工が簡便となり省略化を図ることができるという利点もある。 Thus, the construction method using a foundation packing is called a foundation packing construction method. According to the foundation packing method, the ventilation of the building can be improved, the wooden base can be prevented from decaying, and termite erosion can be prevented, and the building can be solid and can be improved in earthquake resistance. Further, there is an advantage that the construction is simple and can be omitted.

近年では、基礎パッキンについて種々の工夫がなされており、その一つとして、長尺の基礎パッキンが存在する。長尺の基礎パッキンは、図5に示した基礎パッキン100(以下、短尺の基礎パッキンともいう)に比べて、その長さが長く、例えば、長さLが900mm程度ある。長尺の基礎パッキンによれば、コンクリート基礎の上面の全周域を覆うように載置しても部品点数が増大してしまうということがない。 In recent years, various contrivances have been made for the basic packing, and one of them is a long basic packing. The long foundation packing has a longer length than the foundation packing 100 shown in FIG. 5 (hereinafter also referred to as a short foundation packing). For example, the length L is about 900 mm. According to the long foundation packing, the number of parts does not increase even if it is placed so as to cover the entire circumference of the upper surface of the concrete foundation.

また、コンクリート基礎の上面の全周域を覆うように長尺の基礎パッキンを載置する場合、コンクリート基礎の上面に一定の間隔を空けて短尺の基礎パッキンを載置する場合と比べて、基礎パッキンの位置合わせが不要となる。従って、施工がより簡便となり、さらなる省力化を図ることができる。
また、コンクリート基礎の上面に一定の間隔を空けて短尺の基礎パッキンを載置する場合、施工業者の技術力等によって、位置合わせの精度にばらつきが生じるおそれがあるが、コンクリート基礎の上面の全周域を覆うように長尺の基礎パッキンを載置する場合には、位置合わせの作業が不要となり、施工の質を均一化させることができる。
さらに、コンクリート基礎の上面の全周域を覆うように長尺の基礎パッキンを載置すると、木製土台の荷重が長尺の基礎パッキンの全域に均等に掛かることになるため、木製土台に撓み等が生じるおそれもない。
Also, when placing a long foundation packing so as to cover the entire circumference of the top surface of the concrete foundation, compared to placing a short foundation packing at a certain interval on the top surface of the concrete foundation, It is not necessary to align the packing. Therefore, the construction becomes simpler and further labor saving can be achieved.
In addition, when placing short foundation packings with a certain interval on the top surface of the concrete foundation, there is a risk that the accuracy of alignment may vary depending on the technical ability of the contractor. When a long foundation packing is placed so as to cover the peripheral area, alignment work is not required, and the construction quality can be made uniform.
Furthermore, if a long foundation packing is placed so as to cover the entire circumference of the top surface of the concrete foundation, the load on the wooden foundation will be applied evenly over the entire area of the long foundation packing, so the wooden foundation will bend. There is also no risk of occurrence.

このように、コンクリート基礎の上面の全周域を覆うように長尺の基礎パッキンを載置する施工方法には、多くの利点があり、近年では広く用いられるようになっている。
図6は、コンクリート基礎の上面の全周域を覆うように長尺の基礎パッキンを載置した様子を模式的に示す斜視図である。図中、200はコンクリート基礎、201及び202は部屋となる領域、203は玄関となる領域、302はアンカーボルトをそれぞれ示している。
As described above, the construction method in which the long foundation packing is placed so as to cover the entire circumference of the upper surface of the concrete foundation has many advantages, and has been widely used in recent years.
FIG. 6 is a perspective view schematically showing a state in which a long foundation packing is placed so as to cover the entire peripheral area of the upper surface of the concrete foundation. In the figure, 200 is a concrete foundation, 201 and 202 are rooms, 203 is an entrance area, and 302 is an anchor bolt.

図6に示すように、コンクリート基礎200の上面には、その全周域を覆うように長尺の基礎パッキン300、301が載置されている。玄関となる領域203を囲うコンクリート基礎200の上面には、通気用の貫通穴がその側面に形成されていない中実体の基礎パッキン(以下、遮蔽型の基礎パッキンともいう)300が載置されている。
部屋となる領域201、202を囲うコンクリート基礎200の上面には、通気用の貫通孔がその側面に形成されている基礎パッキン(以下、換気型の基礎パッキンともいう)301が載置されている。
As shown in FIG. 6, long foundation packings 300 and 301 are placed on the upper surface of the concrete foundation 200 so as to cover the entire circumference thereof. A solid foundation packing (hereinafter also referred to as a shield-type foundation packing) 300 having no through-holes for ventilation is placed on the upper surface of the concrete foundation 200 that surrounds the entrance region 203. Yes.
On the upper surface of the concrete foundation 200 that surrounds the areas 201 and 202 to be rooms, a foundation packing 301 (hereinafter also referred to as a ventilation-type foundation packing) 301 with a through-hole for ventilation formed on the side surface is placed. .

図6に示したように、コンクリート基礎の上面の全周域を覆うように長尺の基礎パッキンを載置する施工方法を用いる場合には、通常、遮蔽型の基礎パッキンと換気型の基礎パッキンとの両方を使用する。これは、以下のような理由による。すなわち、床下がなくて室内空間と外部空間とが土台を介して両側で接する箇所(例えば、玄関、勝手口、土間部等)においては、基礎パッキンから通気させる必要はなく、通気させると却って室内空間の気密性が悪化して冷暖房効率が低下してしまうから、遮蔽型の基礎パッキンを使用しているのである。一方、他の箇所においては、換気型の基礎パッキンを使用することにより、基礎パッキン自体に換気穴としての機能を持たせているのである。 As shown in FIG. 6, when using a construction method in which a long foundation packing is placed so as to cover the entire circumference of the upper surface of the concrete foundation, usually a shielded foundation packing and a ventilation foundation packing are used. And both. This is due to the following reasons. In other words, in places where there is no underfloor and the indoor space and the external space are in contact on both sides via the base (for example, the entrance, the doorway, the soil part, etc.), it is not necessary to ventilate from the basic packing. Since the airtightness of the space is deteriorated and the cooling and heating efficiency is lowered, the shield-type basic packing is used. On the other hand, in other places, the foundation packing itself has a function as a ventilation hole by using a ventilation type foundation packing.

実開昭54−181721号公報Japanese Utility Model Publication No. 54-181721 実開昭54−181708号公報Japanese Utility Model Publication No. 54-181708 特公昭55−40734号公報Japanese Patent Publication No. 55-40734

しかしながら、上述したように、コンクリート基礎の上面の全周域を覆うように長尺の基礎パッキンを略隙間なく載置する施工方法を用いる場合には、以下のような問題が生じることがあった。 However, as described above, the following problems may occur when using a construction method in which a long foundation packing is placed almost without any gap so as to cover the entire circumference of the upper surface of the concrete foundation. .

図7(a)〜(c)は、従来の建造物の施工方法の一例を模式的に示す斜視図である。
まず、幅120mmのコンクリート基礎410の上面411に、墨出し線(逃げ墨)413を描く(図7(a)参照)。墨出し線413は、コンクリート基礎10の壁面412から3mm程度離間している。
7A to 7C are perspective views schematically illustrating an example of a conventional construction method for a building.
First, inking line (running ink) 413 is drawn on the upper surface 411 of the concrete foundation 410 having a width of 120 mm (see FIG. 7A). The inking line 413 is separated from the wall surface 412 of the concrete foundation 10 by about 3 mm.

次に、基礎パッキン420をコンクリート基礎410の上面411に載置する。基礎パッキン420は、アンカーボルト(図示せず)を挿通させるためのボルト挿通孔424が複数形成された基体421からなり、長さ910mm、幅120mm、高さ20mmである。この基礎パッキン420を幅120mmのコンクリート基礎410の上面411に載置すると、基礎パッキン420によって墨出し線413が覆われ、墨出し線413を視認することができなくなってしまう(図7(b)参照)。 Next, the foundation packing 420 is placed on the upper surface 411 of the concrete foundation 410. The base packing 420 includes a base body 421 in which a plurality of bolt insertion holes 424 for inserting anchor bolts (not shown) are formed, and has a length of 910 mm, a width of 120 mm, and a height of 20 mm. When the foundation packing 420 is placed on the upper surface 411 of the concrete foundation 410 having a width of 120 mm, the ink marking line 413 is covered by the foundation packing 420, and the ink marking line 413 cannot be visually recognized (FIG. 7B). reference).

その後、基礎パッキン420上に木製土台430を載置し、アンカーボルト(図示せず)によってコンクリート基礎410と木製土台430とを固定する。そして、コンクリート基礎410の壁面412及び基礎パッキン420の側面422に、モルタル440を塗布して硬化させ、モルタル440の上側に位置するように、外装板の一部となる板状体(例えば、合板等)450を木製土台430に取り付ける(図7(c)参照)。 Thereafter, the wooden base 430 is placed on the foundation packing 420, and the concrete foundation 410 and the wooden base 430 are fixed by anchor bolts (not shown). Then, a mortar 440 is applied to the wall surface 412 of the concrete foundation 410 and the side surface 422 of the foundation packing 420 and cured, and a plate-like body (for example, plywood) that becomes a part of the exterior plate so as to be positioned above the mortar 440. Etc.) 450 is attached to the wooden base 430 (see FIG. 7C).

このように、図7に示した施工方法では、コンクリート基礎410の上面411の全周域を覆うように基礎パッキン420を載置するため、基礎パッキン420によって墨出し線413が覆われ、木製土台430を載置する際には、墨出し線413を視認することができない。従って、墨出し線413を基準とした木製土台430の正確な位置合わせを行うことが困難であり、スムーズな施工を行うことができないという問題があった。 In this way, in the construction method shown in FIG. 7, the foundation packing 420 is placed so as to cover the entire circumference of the upper surface 411 of the concrete foundation 410. When placing 430, the inking line 413 cannot be visually recognized. Therefore, there is a problem that it is difficult to accurately position the wooden base 430 with reference to the ink marking line 413, and smooth construction cannot be performed.

このような問題は、幅の狭い基礎パッキンをコンクリート基礎410の上面411に所定間隔を隔てて複数配置すれば、当該基礎パッキン間から墨出し線を覗くことができることから、解消し得るとも考えられるが、幅の狭い基礎パッキンを使用した場合には、以下のような別の問題が生じることがあった。 It is considered that such a problem can be solved by arranging a plurality of narrow foundation packings on the upper surface 411 of the concrete foundation 410 with a predetermined interval, since the ink drawing line can be seen from between the foundation packings. However, when a narrow base packing is used, another problem as described below may occur.

図8(a)〜(b)は、従来の建造物の施工方法の他の一例を模式的に示す斜視図である。
まず、幅120mmのコンクリート基礎410の上面411に、図7(a)と同様に墨出し線413を描いた後、図7に示した基礎パッキン420より幅が狭い基礎パッキン520を、コンクリート基礎410の上面411に載置する(図8(a)参照)。基礎パッキン520は、基体521の幅が102mmである以外、図7に示した基礎パッキン420と同形状を有する。基礎パッキン520は基体521の幅が狭いので、幅120mmのコンクリート基礎410の上面に載置する際に、基礎パッキン420によって墨出し線413が覆われないようにすることが可能である。
8A to 8B are perspective views schematically showing another example of a conventional construction method for a building.
First, after drawing the ink marking line 413 on the upper surface 411 of the concrete foundation 410 having a width of 120 mm, the foundation packing 520 having a narrower width than the foundation packing 420 shown in FIG. (See FIG. 8A). The foundation packing 520 has the same shape as the foundation packing 420 shown in FIG. 7 except that the width of the base 521 is 102 mm. Since the foundation packing 520 has a narrow base 521, the foundation packing 420 can prevent the marking line 413 from being covered when the base packing 520 is placed on the upper surface of the concrete foundation 410 having a width of 120 mm.

その後、基礎パッキン520上に木製土台430を載置し、アンカーボルト(図示せず)によってコンクリート基礎410と木製土台430とを固定する。そして、コンクリート基礎410の壁面412及び基礎パッキン520の側面522に、モルタル440を塗布して硬化させ、モルタル440の上側に位置するように板状体450を木製土台430に取り付ける(図8(b)参照)。 Thereafter, the wooden base 430 is placed on the foundation packing 520, and the concrete foundation 410 and the wooden base 430 are fixed by anchor bolts (not shown). And the mortar 440 is apply | coated and hardened to the wall surface 412 of the concrete foundation 410, and the side surface 522 of the foundation packing 520, and the plate-shaped object 450 is attached to the wooden base 430 so that it may be located above the mortar 440 (FIG.8 (b). )reference).

図8に示した施工方法では、基礎パッキン520を載置しても墨出し線413を視認可能な状態が維持されるため、墨出し線413を基準とした木製土台430の正確な位置合わせを行うことができる。
しかしながら、幅の狭い基礎パッキン520を使用する工法の場合には、基礎パッキン520がその上方に載置される木製土台430から受ける家屋の荷重に耐え得るように、コンクリート基礎410の上面411に所定間隔を隔てて所定位置に基礎パッキン520を載置する必要がある。このような幅の狭い基礎パッキン520の載置位置や間隔等の注意事項は、この幅の狭い基礎パッキン520を提供する施工者に対して、施工方法のマニュアル等を配布したり、研修を行ってその施工方法を熟知してもらうように促しているが、施工者の熟練度が影響するといった問題は否めないものであった。
そこで、基礎パッキンを上述したようにコンクリート基礎410の上面411の全周に載置することで、施工者の熟練度によらず安全性を確保し得ることが提案されているが、これにより、新たに墨出し線が視認することができなくなるという問題が発生するのである。
In the construction method shown in FIG. 8, since the state where the inking line 413 can be visually recognized is maintained even when the foundation packing 520 is placed, accurate alignment of the wooden base 430 with respect to the inking line 413 is performed. It can be carried out.
However, in the case of the construction method using the narrow foundation packing 520, the upper surface 411 of the concrete foundation 410 is predetermined on the upper surface 411 of the concrete foundation 410 so that the foundation packing 520 can withstand the load of the house received from the wooden base 430 placed thereon. It is necessary to place the base packing 520 at a predetermined position with a gap. As for the precautions such as the mounting position and interval of the narrow foundation packing 520, manuals of construction methods and the like are distributed to the installers who provide the narrow foundation packing 520, and training is conducted. Although it encourages them to become familiar with the construction method, the problem of the influence of the skill level of the installer is undeniable.
Therefore, it has been proposed that the safety packing can be secured regardless of the skill level of the installer by placing the foundation packing on the entire circumference of the upper surface 411 of the concrete foundation 410 as described above. There is a problem that a new ink line cannot be visually recognized.

また、モルタル440の上面441を精度よく平坦とするのは困難であり、上面441には多少の凹凸が生じてしまうため、板状体450を取り付ける際にモルタル440の上面441を基準とした板状体450の位置合わせを行った場合、位置合わせを正確に行うことが困難であり、スムーズな施工を行うことができないという問題があった。 Further, it is difficult to accurately flatten the upper surface 441 of the mortar 440, and some unevenness is generated on the upper surface 441. Therefore, a plate based on the upper surface 441 of the mortar 440 is attached when the plate-like body 450 is attached. When the alignment of the state body 450 is performed, there is a problem that it is difficult to perform alignment accurately and smooth construction cannot be performed.

本発明は、上述した課題に鑑みてなされたものであり、その目的は、墨出し線を基準とした土台の正確な位置合わせを容易に行うことができる基礎パッキンを用いた建造物の施工方法及び建造物を提供することにある。また、本発明の目的は、外装板又は外装板の一部となる板状体の正確な位置合わせを容易に行うことができる基礎パッキンを用いた建造物の施工方法及び建造物を提供することにある。 The present invention has been made in view of the above-described problems, and the object thereof is a method for constructing a building using a base packing that can easily perform accurate positioning of a base with reference to the ink marking line. And to provide buildings. Moreover, the objective of this invention is providing the construction method and building of a building using the foundation packing which can perform the exact position alignment of the exterior board or the plate-shaped body used as a part of an exterior board easily. It is in.

上述した課題を解決するために、本発明は、以下のようなものを提供する。
(1)基礎と土台との間に基礎パッキンを設ける建造物の施工方法であって、
上記基礎の上面に、上記土台の位置合わせのための墨出し線を描く工程と、
所定の厚さを有する矩形板状の基体の長辺外側面に上下方向に貫通した複数の溝が形成された基礎パッキンを、上記溝を介して上方から上記墨出し線を視認し得るように、上記基礎の上面に載置する工程と、
上記土台の外側面が上記墨出し線の上方に位置するように、上記土台を上記基礎パッキンの上面に載置する工程と、
上記土台の外側面より外部空間側における上記基礎パッキンの上面に、外装板又は当該外装板の一部となる板状体を載置する工程と
を含むことを特徴とする建造物の施工方法。
In order to solve the above-described problems, the present invention provides the following.
(1) A construction method for a building in which a foundation packing is provided between a foundation and a foundation,
On the top surface of the foundation, drawing a summing line for positioning the foundation;
A basic packing in which a plurality of grooves penetrating in the vertical direction are formed on the outer side of the long side of a rectangular plate-like substrate having a predetermined thickness so that the marking line can be visually recognized from above through the grooves. Placing on the upper surface of the foundation;
Placing the foundation on the upper surface of the foundation packing so that the outer surface of the foundation is located above the inking line;
Placing the exterior plate or a plate-like body that is a part of the exterior plate on the upper surface of the foundation packing on the outer space side from the outer side surface of the foundation.

(1)の発明によれば、基礎の上面を覆うように基礎パッキンを載置しても、溝を介して上方から墨出し線を視認することができるため、複数の基礎パッキンを基準線としての墨出し線に沿って精度良く設置することが可能となる。このように精度良く複数の基礎パッキンを上記基準線に沿って設置することによって、平面視矩形板状の基礎パッキンの長辺外側面が複数の基礎パッキン間で略一直線上に並ぶことになる。そして、複数の基礎パッキンの長辺外側面が略一直線上に並んで第2の基準線として機能するので、この第2の基準線としての長辺外側面群に沿って土台の外側面を位置決めし、土台を基礎パッキンの上面に設置することによって、間接的に上記墨出し線を基準とした土台の位置合わせを行うことができ、スムーズな施工を行うことができる。 According to the invention of (1), even if the foundation packing is placed so as to cover the upper surface of the foundation, the inking line can be visually recognized from above through the groove, so that a plurality of foundation packings are used as reference lines. It is possible to install it with high accuracy along the ink marking line. As described above, by installing the plurality of foundation packings along the reference line with high accuracy, the long side outer surface of the rectangular packing in the plan view rectangular plate shape is arranged in a substantially straight line between the plurality of foundation packings. And since the long side outer side surfaces of a plurality of foundation packings are aligned in a straight line and function as a second reference line, the outer side surface of the base is positioned along the long side outer side surface group as the second reference line. In addition, by installing the base on the upper surface of the foundation packing, the base can be indirectly aligned with respect to the ink marking line, and smooth construction can be performed.

基礎パッキンは金型成形等によって製造されるため、基礎パッキンの長辺外側面には、うねりが生じることがなく、その平坦さが充分に確保される。従って、基礎パッキンの長辺外側面群に沿って土台の外側面を位置決めすることにより、土台の位置合わせを正確に行うことができる。 Since the basic packing is manufactured by molding or the like, the long side outer surface of the basic packing is not swelled, and its flatness is sufficiently secured. Therefore, positioning of the foundation can be performed accurately by positioning the outer surface of the foundation along the long side outer surface group of the foundation packing.

また、基礎パッキンの長辺外側面に形成された溝を介して上方より墨出し線を視認し得るから、例えば、基礎上面の中央寄りに墨出し線を描いて、溝の底面が墨出し線の上方に位置するように基礎パッキンを基礎の上面に載置することができる。このように、(1)の発明によれば、基礎上面の中央寄りに墨出し線を描いても、墨出し線が視認し得る状態を確保することができるから、基礎の側縁にうねりが生じている場合であっても、基礎上面に確実に墨出し線を描くことができる利点もある。 In addition, since the inking line can be visually recognized from above through the groove formed on the outer side of the long side of the foundation packing, for example, the inking line is drawn near the center of the upper surface of the foundation, and the bottom surface of the groove is the inking line. The foundation packing can be placed on the upper surface of the foundation so as to be located above the foundation. As described above, according to the invention of (1), even if the inking line is drawn near the center of the upper surface of the foundation, it is possible to secure a state where the inking line can be visually recognized. Even if it occurs, there is also an advantage that the inking line can be surely drawn on the upper surface of the foundation.

また、モルタルを塗布する際、基礎パッキンの長辺外側面に形成された複数の溝にモルタルが入り込んで硬化するため、モルタルと基礎パッキンとの密着性が向上し、モルタルの剥離を防止することができるとともに、基礎パッキンの滑りや横ズレ等を防止することができる。さらに、幅の狭い基礎パッキンを用いなくても、墨出し線を視認可能な状態とすることができるため、幅の広い基礎パッキンを用いて基礎パッキンと基礎又は土台との接触面積を充分に確保することができる。従って、基礎パッキン又は土台の滑りや横ズレを防止することができ、振動や衝撃等によって基礎パッキンが変形してしまうことを防止することができる。 In addition, when applying mortar, since the mortar enters and cures into the grooves formed on the outer side of the long side of the foundation packing, the adhesion between the mortar and the foundation packing is improved, and the mortar is prevented from peeling off. In addition, the foundation packing can be prevented from slipping or laterally shifting. In addition, the marking line can be made visible without using a narrow foundation packing, so a sufficient contact area between the foundation packing and the foundation or foundation can be secured using a wide foundation packing. can do. Therefore, it is possible to prevent the foundation packing or the base from slipping or laterally shifting, and it is possible to prevent the foundation packing from being deformed by vibration or impact.

さらに、本発明は、以下のようなものを提供する。
(2)基礎と土台との間に基礎パッキンを設ける建造物の施工方法であって、
所定の厚さを有する矩形板状の基体の長辺外側面に上下方向に貫通した複数の溝が形成された基礎パッキンを、当該基礎パッキンの一方の長辺外側面が上記基礎の外壁面より外部空間側に位置するように、上記基礎の上面に載置することを特徴とする建造物の施工方法。
Furthermore, the present invention provides the following.
(2) A construction method for a building in which a foundation packing is provided between the foundation and the foundation,
A base packing in which a plurality of grooves penetrating in the vertical direction is formed on the long side outer surface of a rectangular plate-like substrate having a predetermined thickness, and one long side outer surface of the base packing is from the outer wall surface of the base. A construction method for a building, which is placed on the upper surface of the foundation so as to be located on the outer space side.

(2)の発明によれば、基礎パッキンの一方の長辺外側面が、上記基礎の外側面より外部空間側に位置するため、基礎パッキンの上面に土台を載置しても、基礎パッキンの上面の全てが土台によって覆われることがなく、当該基礎パッキンの外部空間側に突出した部分(以下、突出部分ともいう)の上面には土台が及ばない。従って、突出部分の上面(基礎パッキンの上面)を基準として、外装板又は外装板の一部となる板状体の位置合わせを容易に行うことが可能となり、スムーズな施工を行うことが可能となる。
また、モルタルを塗布する際、基礎パッキンの長辺外側面に形成された複数の溝にモルタルが入り込んで硬化するため、モルタルと基礎パッキンとの密着性が向上し、モルタルの剥離を防止することができるとともに、基礎パッキンの滑りや横ズレ等を防止することができる。
According to the invention of (2), since one long side outer surface of the foundation packing is located on the outer space side from the outer surface of the foundation, even if the base is placed on the upper surface of the foundation packing, The entire upper surface is not covered with the base, and the base does not reach the upper surface of the portion protruding to the external space side of the foundation packing (hereinafter also referred to as a protruding portion). Therefore, it is possible to easily align the exterior plate or the plate-like body that is a part of the exterior plate with reference to the upper surface of the protruding portion (the upper surface of the base packing), and it is possible to perform smooth construction. Become.
In addition, when applying mortar, since the mortar enters and cures into the grooves formed on the outer side of the long side of the foundation packing, the adhesion between the mortar and the foundation packing is improved, and the mortar is prevented from peeling off. In addition, the foundation packing can be prevented from slipping or laterally shifting.

また、(2)の発明においては、基礎パッキンの一方の長辺外側面に形成された溝の底面と基礎の壁面とが略同一平面上に位置するように、基礎パッキンを基礎の上面に載置し、溝の底面を基準とした土台の位置合わせを行うことができる。このようにした場合、墨出し線を描く工程を省略し、基礎の壁面を基準とした土台の位置合わせを行うことができる。 In the invention of (2), the foundation packing is mounted on the upper surface of the foundation so that the bottom surface of the groove formed on the outer surface of one long side of the foundation packing and the wall surface of the foundation are located on substantially the same plane. The base can be aligned with respect to the bottom surface of the groove. In this case, the step of drawing the inking line can be omitted, and the base can be aligned based on the wall surface of the foundation.

また、(2)の発明においては、基礎の上面に墨出し線(逃げ墨)を描いた後、基礎パッキンの一方の長辺外側面に形成された溝の底面が墨出し線上に位置するように、基礎パッキンを基礎の上面に載置し、溝の底面を基準とした土台の位置合わせを行うことができる。このようにした場合、基礎にうねりが生じていても、墨出し線を基準とした基礎パッキンの位置合わせと土台の位置合わせとを行うことができる。 In addition, in the invention of (2), after drawing the inking line (escape) on the upper surface of the foundation, the bottom surface of the groove formed on the outer surface of one long side of the foundation packing is positioned on the inking line. In addition, the foundation packing can be placed on the upper surface of the foundation, and the base can be aligned with respect to the bottom surface of the groove. In this case, even if the foundation is wavy, it is possible to perform the alignment of the foundation packing and the alignment of the base with reference to the inking line.

さらに、本発明は、以下のようなものを提供する。
(3)墨出し線が上面に描かれた基礎と、
所定の厚さを有する矩形板状の基体の長辺外側面に上下方向に貫通した複数の溝が形成され、かつ、上記溝を介して上方から上記墨出し線を視認し得るように上記基礎の上面に載置された基礎パッキンと、
その外側面が上記墨出し線の上方に位置するように上記基礎パッキンの上面に載置された土台と、
上記土台の外側面より外部空間側における上記基礎パッキンの上面に載置され、かつ、外装板又は当該外装板の一部となる板状体と
を備えたことを特徴とする建造物。
Furthermore, the present invention provides the following.
(3) The basics where the ink line is drawn on the upper surface,
A plurality of grooves penetrating in the vertical direction are formed on the outer side of the long side of the rectangular plate-like substrate having a predetermined thickness, and the inking line is visible from above through the grooves. A foundation packing placed on the upper surface of
A base placed on the upper surface of the foundation packing so that its outer surface is located above the inking line;
A building comprising: an exterior plate or a plate-like body that is a part of the exterior plate and is placed on the upper surface of the foundation packing on the outer space side from the outer surface of the foundation.

(3)の発明によれば、土台と基礎との間に基礎パッキンが設けられているにも拘わらず、墨出し線を基準とした土台の位置合わせが行われているため、土台が精度よく設けられた建造物を提供することができる。さらに、基礎パッキンの長辺外側面に形成された溝にモルタルが入り込んで硬化するため、モルタルと基礎パッキンとの密着性に優れ、モルタルの剥離、基礎パッキンの滑りや横ズレが生じるおそれがない。 According to the invention of (3), although the foundation packing is provided between the foundation and the foundation, the foundation is aligned with respect to the inking line, so the foundation is accurate. Provided buildings can be provided. Furthermore, since the mortar enters the groove formed on the outer side of the long side of the base packing and hardens, it has excellent adhesion between the mortar and the base packing, and there is no risk of peeling of the mortar, slipping or lateral displacement of the base packing. .

さらに、本発明は、以下のようなものを提供する。
(4)基礎と土台との間に基礎パッキンが設けられた建造物であって、
所定の厚さを有する矩形板状の基体の長辺外側面に上下方向に貫通した複数の溝が形成された基礎パッキンが、当該基礎パッキンの一方の長辺外側面が上記基礎の外壁面より外部空間側に位置するように、上記基礎の上面に載置されていることを特徴とする建造物。
Furthermore, the present invention provides the following.
(4) A building with a foundation packing between the foundation and the foundation,
A foundation packing in which a plurality of grooves penetrating in the vertical direction is formed on the long side outer surface of a rectangular plate-shaped substrate having a predetermined thickness, and one long side outer surface of the foundation packing is from the outer wall surface of the foundation. A building characterized by being placed on the upper surface of the foundation so as to be located on the external space side.

(4)の発明によれば、外装板又は外装板の一部となる板状体の位置合わせが突出部分の上面を基準として行われているため、外装板又は外装板の一部となる板状体が精度よく取り付けられた建造物を提供することができる。また、基礎パッキンの長辺外側面に形成された複数の溝にモルタルが入り込んで硬化するため、モルタルと基礎パッキンとの密着性に優れ、モルタルの剥離を防止することができる。 According to the invention of (4), since the alignment of the exterior plate or the plate-like body that becomes a part of the exterior plate is performed with reference to the upper surface of the protruding portion, the exterior plate or the plate that becomes a part of the exterior plate It is possible to provide a building to which the state body is attached with high accuracy. In addition, since the mortar enters and cures into the plurality of grooves formed on the outer side of the long side of the basic packing, the adhesiveness between the mortar and the basic packing is excellent, and the mortar can be prevented from peeling off.

本発明によれば、墨出し線を基準とした土台の正確な位置合わせを容易に行うことができるとともに、外装板又は外装板の一部となる板状体の正確な位置合わせを容易に行うことができ、さらに、基礎パッキン又は土台の滑りや横ズレと、振動や衝撃等による基礎パッキンの変形とを防止することができる。 According to the present invention, it is possible to easily perform accurate positioning of the base with reference to the inking line, and to easily perform accurate positioning of the exterior plate or a plate-like body that is a part of the exterior plate. Furthermore, it is possible to prevent the foundation packing or the base from slipping or laterally shifting, and deformation of the foundation packing due to vibration or impact.

本発明に係る建造物の施工方法について図面に基づいて説明する。なお、以下においては、理解を容易とするために、本発明の一実施形態として各部分又は要素の寸法を示すこととするが、本発明は、勿論、これらの寸法によって限定されるものではない。 A construction method for a building according to the present invention will be described with reference to the drawings. In the following, for ease of understanding, the dimensions of each part or element will be shown as an embodiment of the present invention. However, the present invention is not, of course, limited by these dimensions. .

[第1実施形態]
図1(a)〜(c)は、第1実施形態に係る建造物の施工方法の一例を模式的に示す部分拡大斜視図である。図2は、図1(b)に示した基礎パッキン及び基礎を上方から見た様子を模式的に示す平面図である。
[First Embodiment]
Drawing 1 (a)-(c) is a partial expansion perspective view showing typically an example of the construction method of the building concerning a 1st embodiment. FIG. 2 is a plan view schematically showing the foundation packing and the foundation shown in FIG. 1B as viewed from above.

(i)建造物(図示せず)を建てるべき部分の内殻部及び外殻部に、幅W150mmのコンクリート基礎10(図2参照)を作る。具体的には、まず、木製の型枠(図示せず)を組み立て、次に、セメント、砂、水を混合して流動状にして型枠に流し込み、数日放置して固化させてコンクリート基礎10を作る。このようにした場合、木製の型枠が水分を含んで変形してしまい、コンクリート基礎10にうねりが生じることがある。 (I) A concrete foundation 10 (see FIG. 2) having a width W f of 150 mm is formed on the inner shell portion and the outer shell portion where a building (not shown) is to be built. Specifically, first a wooden formwork (not shown) is assembled, then cement, sand and water are mixed and fluidized, poured into a formwork, left to solidify for a few days, and then a concrete foundation Make 10. In this case, the wooden formwork may be deformed including moisture, and the concrete foundation 10 may be swelled.

次に、コンクリート基礎10の上面11に、墨出し線(逃げ墨)13を描く(図1(a)参照)。墨出し線13は、木製土台30の外側面で木製土台30の位置合わせを行うためのものであり、コンクリート基礎10にうねりがあっても木製土台30を正確に載置し得るようにするためのものである。墨出し線13と壁面12との距離Gは6mm程度である(図2参照)。 Next, the ink drawing line (running ink) 13 is drawn on the upper surface 11 of the concrete foundation 10 (see FIG. 1A). The inking line 13 is for aligning the wooden base 30 on the outer surface of the wooden base 30, so that the wooden base 30 can be accurately placed even when the concrete foundation 10 is wavy. belongs to. The distance G between the inking line 13 and the wall surface 12 is about 6 mm (see FIG. 2).

(ii)上述したように、コンクリート基礎10の上面に墨出し線13を描いた後、上面11上に基礎パッキン20を載置する(図1(b)、図2参照)。
ここで、基礎パッキン20について説明する。基礎パッキン20は、矩形板状の基体21からなり、基体の幅Wは120mmである。図示しないが、基体21の長さは910mmであり、高さは20mmである。また、基体21の長辺外側面22には、上下方向に貫通した複数の溝25(深さD:6mm)が形成されている(図2参照)。
図中、23は、溝25の底面であり、24は、コンクリート基礎10に垂設されたアンカーボルト(図示せず)を挿通するためのボルト挿通孔である。
(Ii) As described above, after drawing the inking line 13 on the upper surface of the concrete foundation 10, the foundation packing 20 is placed on the upper surface 11 (see FIGS. 1B and 2).
Here, the basic packing 20 will be described. The base packing 20 is composed of a rectangular plate-like base body 21 and the base body width Wp is 120 mm. Although not shown, the base 21 has a length of 910 mm and a height of 20 mm. Further, a plurality of grooves 25 (depth D: 6 mm) penetrating in the vertical direction are formed on the long side outer surface 22 of the base body 21 (see FIG. 2).
In the figure, 23 is a bottom surface of the groove 25, and 24 is a bolt insertion hole for inserting an anchor bolt (not shown) suspended from the concrete foundation 10.

(ii)の工程においては、基礎パッキン20を、溝25を介して上方から墨出し線21を視認し得るように、コンクリート基礎10の上面11に載置する(図1(b)、図2参照)。このとき、図1(b)、図2に示すように、溝25の底面23が墨出し線21の上方に位置するように基礎パッキン20を載置するようにすれば、基礎パッキン20の位置合わせが容易となり、施工をよりスムーズにすることができる。 In the step (ii), the foundation packing 20 is placed on the upper surface 11 of the concrete foundation 10 so that the inking line 21 can be visually recognized from above via the groove 25 (FIGS. 1B and 2). reference). At this time, as shown in FIGS. 1B and 2, if the base packing 20 is placed so that the bottom surface 23 of the groove 25 is positioned above the marking line 21, the position of the base packing 20 is set. Matching becomes easy and construction can be made smoother.

また、第1実施形態においては、図1(b)、図2に示すように、基礎パッキン20の長辺外側面22と、コンクリート基礎10の側面12とが略同一平面上に位置するようにコンクリート基礎10の上面11に基礎パッキン20を載置している。このような工法は、一般的に外面(そとづら)施工と称されるものである。なお、コンクリート基礎10の上面11に基礎パッキン20を載置する工法としては、外面施工の他に、例えば、コンクリート基礎10の中心線と基礎パッキンの中心線とを合わせる芯々施工等がある。 Moreover, in 1st Embodiment, as shown in FIG.1 (b) and FIG. 2, the long side outer side surface 22 of the foundation packing 20 and the side surface 12 of the concrete foundation 10 are located on substantially the same plane. A foundation packing 20 is placed on the upper surface 11 of the concrete foundation 10. Such a construction method is generally referred to as outer surface construction. In addition, as a construction method for placing the foundation packing 20 on the upper surface 11 of the concrete foundation 10, there is, for example, a core construction in which the center line of the concrete foundation 10 and the center line of the foundation packing are aligned.

(iii)次に、基礎パッキン20上に木製土台30を載置する。このとき、基礎パッキン20の長辺外側面22を基準として木製土台30の外側面を位置決めして木製土台30を載置することができるので、間接的に墨出し線13を基準とした木製土台30の位置合わせを行うことができ、スムーズな施工を行うことができる。その後、アンカーボルト(図示せず)によって、コンクリート基礎10と木製土台30とを固定する。 (Iii) Next, the wooden base 30 is placed on the foundation packing 20. At this time, since the outer surface of the wooden base 30 can be positioned with the long side outer surface 22 of the foundation packing 20 as a reference and the wooden base 30 can be placed, the wooden base is indirectly based on the ink marking line 13. 30 alignment can be performed and smooth construction can be performed. Thereafter, the concrete foundation 10 and the wooden base 30 are fixed by anchor bolts (not shown).

次に、コンクリート基礎10の壁面12と、基礎パッキン20の長辺外側面22とにモルタル40を塗布して硬化させる。このとき、基礎パッキン20の長辺外側面22に形成された複数の溝25にモルタル40が入り込んで硬化するため、モルタル40と基礎パッキン20との密着性が向上し、モルタル40の剥離を防止することができる。
(iv)次に、モルタル40の上側に位置するように、外装板の一部となる板状体(例えば、合板等)50を木製土台30に取り付ける(図1(c)参照)。
Next, the mortar 40 is applied to the wall surface 12 of the concrete foundation 10 and the long side outer surface 22 of the foundation packing 20 and cured. At this time, since the mortar 40 enters and cures into the plurality of grooves 25 formed on the long side outer surface 22 of the base packing 20, the adhesion between the mortar 40 and the base packing 20 is improved, and the mortar 40 is prevented from peeling off. can do.
(Iv) Next, a plate-like body (for example, plywood) 50 that is a part of the exterior plate is attached to the wooden base 30 so as to be positioned above the mortar 40 (see FIG. 1C).

図1及び図2を用いて説明したように、第1実施形態に係る建造物の施工方法によれば、コンクリート基礎10の上面11を覆うように基礎パッキン20を載置しても、溝25を介して墨出し線13を視認することができるため、複数の基礎パッキン20を基準線としての墨出し線13に精度良く設置することが可能となる。このように精度良く複数の基礎パッキン20を上記基準線に沿って設置することによって、平面視矩形板状の基礎パッキン20の長辺外側面22が複数の基礎パッキン20間で略一直線上に並ぶことになる。そして、複数の基礎パッキン20の長辺外側面22が略一直線上に並んで第2の基準線として機能するので、この第2の基準線としての長辺外側面22群に沿って木製土台30の外側面を位置決めし、木製土台30を基礎パッキン20の上面26に設置することによって、間接的に墨出し線13を基準とした木製土台30の位置合わせを行うことができ、スムーズな施工を行うことができる。 As described with reference to FIGS. 1 and 2, according to the building construction method according to the first embodiment, even if the foundation packing 20 is placed so as to cover the upper surface 11 of the concrete foundation 10, the groove 25. Since the inking line 13 can be visually recognized through this, a plurality of basic packings 20 can be accurately installed on the inking line 13 as a reference line. By installing the plurality of foundation packings 20 along the reference line with high accuracy in this way, the long side outer surface 22 of the rectangular base packing 20 in a plan view is arranged in a substantially straight line between the plurality of foundation packings 20. It will be. And since the long side outer side surface 22 of the some foundation packing 20 is located in a line on a substantially straight line, and functions as a 2nd reference line, the wooden base 30 along the long side outer side surface 22 group as this 2nd reference line. By positioning the outer surface of the base plate 30 and installing the wooden base 30 on the upper surface 26 of the foundation packing 20, it is possible to indirectly align the wooden base 30 with the ink marking line 13 as a reference, thereby achieving smooth construction. It can be carried out.

また、モルタル40を塗布する際、基礎パッキン20の長辺外側面22に形成された複数の溝25にモルタル40が入り込んで硬化するため、モルタル40と基礎パッキン20との密着性が向上し、モルタル40の剥離を防止することができるとともに、基礎パッキン20の滑りや横ズレ等を防止することができる。 Further, when the mortar 40 is applied, since the mortar 40 enters and cures into the plurality of grooves 25 formed on the long side outer surface 22 of the foundation packing 20, the adhesion between the mortar 40 and the foundation packing 20 is improved. While peeling of the mortar 40 can be prevented, the foundation packing 20 can be prevented from slipping or laterally shifting.

また、図2に示したように、幅W120mmの基礎パッキンを、幅W120mmのコンクリート基礎10の上面11に載置しても、コンクリート基礎10の上面に描いた墨出し線(逃げ墨)13を視認可能な状態とすることができる。このように第1実施形態に係る建造物の施工方法によれば、幅の広い基礎パッキンを使用することができ、基礎パッキン20とコンクリート基礎10又は木製土台30との接触面積を充分に確保することができる。従って、基礎パッキン20又は木製土台30の滑りや横ズレを防止することができ、振動や衝撃等によって基礎パッキン20が変形してしまうことを防止することができる。 In addition, as shown in FIG. 2, even if a foundation packing having a width W p of 120 mm is placed on the upper surface 11 of the concrete foundation 10 having a width W f of 120 mm, the inking line drawn on the upper surface of the concrete foundation 10 (escape) Ink) 13 can be made visible. Thus, according to the construction method of the building which concerns on 1st Embodiment, a wide foundation packing can be used and the contact area of the foundation packing 20 and the concrete foundation 10 or the wooden base 30 is fully ensured. be able to. Accordingly, it is possible to prevent the foundation packing 20 or the wooden base 30 from slipping or laterally shifting, and to prevent the foundation packing 20 from being deformed by vibration or impact.

また、第1実施形態に係る建造物の施工方法により施工された建造物は、木製土台30とコンクリート基礎10との間に基礎パッキン20が設けられているにも拘わらず、墨出し線13を基準とした木製土台30の位置合わせが行われているため、木製土台30が精度よく設けられる。さらに、基礎パッキン20の長辺外側面22に形成された溝25にモルタル40が入り込んで硬化するため、モルタル40と基礎パッキン20との密着性に優れ、モルタル40の剥離、基礎パッキン20の滑りや横ズレが生じるおそれがない。 Moreover, the building constructed by the construction method according to the first embodiment has the ink marking line 13 in spite of the fact that the foundation packing 20 is provided between the wooden base 30 and the concrete foundation 10. Since the alignment of the wooden base 30 as a reference is performed, the wooden base 30 is provided with high accuracy. Further, since the mortar 40 enters and hardens into the groove 25 formed on the long side outer surface 22 of the foundation packing 20, the adhesion between the mortar 40 and the foundation packing 20 is excellent, and the mortar 40 is peeled off and the foundation packing 20 slips. And there is no risk of lateral displacement.

[第2実施形態]
図3(a)〜(c)は、第2実施形態に係る建造物の施工方法を模式的に示す部分拡大斜視図である。図4は、図3(b)に示した基礎パッキン及び基礎を上方から見た様子を模式的に示す平面図である。なお、図3及び図4においては、上述した図1及び図2に示した構成要素と対応する構成要素には同一の符号を付した。
[Second Embodiment]
Drawing 3 (a)-(c) is a partial expansion perspective view showing typically the construction method of the building concerning a 2nd embodiment. FIG. 4 is a plan view schematically showing the foundation packing and the foundation shown in FIG. 3 and 4, the same reference numerals are given to the components corresponding to the components shown in FIGS. 1 and 2 described above.

(i)建造物(図示せず)を建てるべき部分の内殻部及び外殻部に、幅W120mmのコンクリート基礎10を作る(図3(a)、図4参照)。 (I) A concrete foundation 10 having a width W f of 120 mm is formed on the inner shell and the outer shell of a portion where a building (not shown) is to be built (see FIGS. 3A and 4).

(ii)次に、コンクリート基礎10の上面11に墨出し線を描かず、コンクリート基礎10の上面11に基礎パッキン20を載置する(図3(b)、図4参照)。基礎パッキン20については既に説明済であるので、ここでの説明は省略する。この(ii)の工程においては、基礎パッキン20の長辺外側面22に形成された溝25の底面23と、コンクリート基礎10の壁面12とが略同一平面上に位置するように、コンクリート基礎10の上面11に基礎パッキン20を載置する。このとき、長辺外側面22とコンクリート基礎10の壁面12との距離は、溝25の深さD(6mm)と同じになる。 (Ii) Next, the foundation packing 20 is placed on the upper surface 11 of the concrete foundation 10 without drawing the marking line on the upper surface 11 of the concrete foundation 10 (see FIGS. 3B and 4). Since the basic packing 20 has already been described, description thereof is omitted here. In the step (ii), the concrete foundation 10 is arranged such that the bottom surface 23 of the groove 25 formed on the long side outer surface 22 of the foundation packing 20 and the wall surface 12 of the concrete foundation 10 are located on substantially the same plane. The base packing 20 is placed on the upper surface 11 of the substrate. At this time, the distance between the long side outer surface 22 and the wall surface 12 of the concrete foundation 10 is the same as the depth D (6 mm) of the groove 25.

(iii)次に、基礎パッキン20上に木製土台30を載置する。このとき、溝25の底面23とコンクリート基礎10の壁面12とが略同一平面上に位置しているので、溝25の底面23を基準として木製土台30の位置合わせを行うことにより、墨出し線を描くことなく、コンクリート基礎10の壁面12を基準とした木製土台30の位置合わせを行うことができる。その後、アンカーボルト(図示せず)によって、コンクリート基礎10と木製土台30とを固定する。 (Iii) Next, the wooden base 30 is placed on the foundation packing 20. At this time, since the bottom surface 23 of the groove 25 and the wall surface 12 of the concrete foundation 10 are located on substantially the same plane, by aligning the wooden base 30 with the bottom surface 23 of the groove 25 as a reference, the ink marking line is obtained. The wooden base 30 can be aligned with respect to the wall surface 12 of the concrete foundation 10 without drawing. Thereafter, the concrete foundation 10 and the wooden base 30 are fixed by anchor bolts (not shown).

次に、コンクリート基礎10の壁面12と、基礎パッキン20の長辺外側面22とにモルタル40を塗布して硬化させる。このとき、基礎パッキン20の長辺外側面22に形成さり複数の溝25にモルタル40が入り込んで硬化するため、モルタル40と基礎パッキン20との密着性が向上し、モルタル40の剥離を防止することができる。また、モルタル40を塗布する際には、基礎パッキン20の上面26を基準として溝25から上方に食み出したモルタル40を溝25内に押し込むことにより、突出部分の平坦さを容易に確保することができるため、外装板の一部となる板状体50の位置合わせを正確に行うことができる。 Next, the mortar 40 is applied to the wall surface 12 of the concrete foundation 10 and the long side outer surface 22 of the foundation packing 20 and cured. At this time, since the mortar 40 is formed in the outer side surface 22 of the long side of the foundation packing 20 and is cured by entering into the plurality of grooves 25, adhesion between the mortar 40 and the foundation packing 20 is improved, and peeling of the mortar 40 is prevented. be able to. Further, when the mortar 40 is applied, the flatness of the protruding portion is easily ensured by pushing the mortar 40 that protrudes upward from the groove 25 with respect to the upper surface 26 of the base packing 20 into the groove 25. Therefore, it is possible to accurately align the plate-like body 50 that is a part of the exterior plate.

次に、モルタル40の上側に位置するように、外装板の一部となる板状体50を木製土台30に取り付ける(図3参照)。このとき、基礎パッキン20の突出部分の上面26を基準として、外装板の一部となる板状体50の位置合わせを行うことができるため、外装板の一部となる板状体50の位置合わせが容易であり、スムーズな施工が可能となる。 Next, the plate-shaped body 50 which becomes a part of an exterior board is attached to the wooden base 30 so that it may be located above the mortar 40 (refer FIG. 3). At this time, since it is possible to align the plate-like body 50 that is a part of the exterior plate with reference to the upper surface 26 of the protruding portion of the base packing 20, the position of the plate-like body 50 that is a part of the exterior plate. Matching is easy and smooth construction is possible.

図3及び図4を用いて説明したように、第2実施形態に係る建造物の施工方法によれば、基礎パッキン20の一方の長辺外側面22が、コンクリート基礎10の壁面(外側面)12より外部空間側に位置するため、基礎パッキン20の上面26に木製土台30を載置しても、基礎パッキン20の上面26の全てが木製土台30によって覆われることがなく、基礎パッキン20の突出部分の上面26には木製土台30が及ばない(図3(c)参照)。従って、突出部分の上面26を基準として、外装板の一部となる板状体50の位置合わせを容易に行うことが可能となり、スムーズな施工を行うことが可能となる。
また、モルタル40を塗布する際、基礎パッキン20の長辺外側面22に形成された複数の溝25にモルタル40が入り込んで硬化するため、モルタル40と基礎パッキン20との密着性が向上し、モルタル40の剥離を防止することができるとともに、基礎パッキン20の滑りや横ズレ等を防止することができる。
As described with reference to FIGS. 3 and 4, according to the building construction method according to the second embodiment, one long side outer surface 22 of the foundation packing 20 is the wall surface (outer surface) of the concrete foundation 10. 12, since the wooden base 30 is placed on the upper surface 26 of the foundation packing 20, the entire upper surface 26 of the foundation packing 20 is not covered with the wooden foundation 30, and the foundation packing 20 The wooden base 30 does not reach the upper surface 26 of the protruding portion (see FIG. 3C). Therefore, it is possible to easily align the plate-like body 50 that becomes a part of the exterior plate with reference to the upper surface 26 of the protruding portion, and it is possible to perform smooth construction.
Further, when the mortar 40 is applied, since the mortar 40 enters and cures into the plurality of grooves 25 formed on the long side outer surface 22 of the foundation packing 20, the adhesion between the mortar 40 and the foundation packing 20 is improved. While peeling of the mortar 40 can be prevented, the foundation packing 20 can be prevented from slipping or laterally shifting.

また、第2実施形態に係る建造物の施工方法では、基礎パッキン20の一方の長辺外側面22に形成された溝25の底面23と、コンクリート基礎10の壁面12とが略同一平面上に位置するように、基礎パッキン20をコンクリート基礎10の上面11に載置し、溝25の底面23を基準とした木製土台30の位置合わせを行っている。このようにした場合、墨出し線を描く工程を省略し、コンクリート基礎10の壁面12を基準とした木製土台30の位置合わせを行うことができる。 Moreover, in the construction method of the building which concerns on 2nd Embodiment, the bottom face 23 of the groove | channel 25 formed in the one long side outer surface 22 of the foundation packing 20, and the wall surface 12 of the concrete foundation 10 are on substantially the same plane. The foundation packing 20 is placed on the upper surface 11 of the concrete foundation 10 so as to be positioned, and the wooden base 30 is aligned with respect to the bottom surface 23 of the groove 25. In this case, it is possible to omit the step of drawing the inking line and to align the wooden base 30 with the wall surface 12 of the concrete foundation 10 as a reference.

なお、第2実施形態に係る建造物の施工方法においては、コンクリート基礎10の上面11に墨出し線(逃げ墨)を描いた後、基礎パッキン20の一方の長辺外側面22に形成された溝25の底面23が墨出し線上に位置するように、基礎パッキン20をコンクリート基礎10の上面11に載置し、溝25の底面23を基準とした木製土台30の位置合わせを行うこととしてもよい。このようにした場合、コンクリート基礎10にうねりが生じていても、墨出し線を基準とした木製土台30の正確な位置合わせを行うことができる。 In addition, in the construction method of the building which concerns on 2nd Embodiment, after drawing inking line (escape) on the upper surface 11 of the concrete foundation 10, it formed in one long side outer side surface 22 of the foundation packing 20. The foundation packing 20 may be placed on the upper surface 11 of the concrete foundation 10 so that the bottom surface 23 of the groove 25 is positioned on the marking line, and the wooden base 30 may be aligned with respect to the bottom surface 23 of the groove 25. Good. In this case, even when the concrete foundation 10 is wavy, it is possible to accurately align the wooden base 30 with reference to the inking line.

以上、第1、第2実施形態に係る建造物の施工方法について説明したが、本発明の建造物の施工方法に用いる基礎パッキンとしては、所定の厚さを有する矩形板状の基体の長辺外側面に上下方向に貫通した複数の溝が形成された基礎パッキンであれば、特に限定されるものではない。ただし、本発明の建造物の施工方法においては、基礎の上面の全周域を覆うように基礎パッキンを載置しても、墨出し線を視認し得るようにすることができるから、長尺の基礎パッキンを好適に使用することができる。長尺の基礎パッキンを用いる場合には、部品点数を少なくすることができ、有利である。 As mentioned above, although the construction method of the building which concerns on 1st, 2nd embodiment was demonstrated, as a basic packing used for the construction method of the building of this invention, the long side of the rectangular-plate-shaped base | substrate which has predetermined | prescribed thickness It is not particularly limited as long as it is a basic packing in which a plurality of grooves penetrating in the vertical direction are formed on the outer surface. However, in the construction method of the building of the present invention, even if the foundation packing is placed so as to cover the entire peripheral area of the upper surface of the foundation, it is possible to visually recognize the inking line. The basic packing can be suitably used. When a long basic packing is used, the number of parts can be reduced, which is advantageous.

また、本発明の建造物の施工方法においては、基礎の側面と基礎パッキンの基体の長辺外側面とにモルタルを塗布して硬化させることにより、モルタルと基礎パッキンとの密着性を向上させてモルタルの剥離や基礎パッキンの滑り、横ズレを防止することができるから、遮蔽型の基礎パッキンを好適に使用することができる。 In the construction method of the building of the present invention, the adhesion between the mortar and the foundation packing is improved by applying and curing the mortar on the side of the foundation and the outer side of the long side of the foundation of the foundation packing. Since it is possible to prevent peeling of the mortar, slipping of the base packing, and lateral displacement, a shield-type base packing can be suitably used.

上述した第2実施形態に係る建造物の施工方法によれば、基礎パッキンの上面の一部を基準として、外装板又は外装板の一部となる板状体の位置合わせを行うことが可能となるが、本発明の建造物の施工方法においては、外装板又は外装板の一部となる板状体の位置合わせではなく、内装板又は内装板の一部となる板状体の位置合わせを行うこととしてもよい。 According to the construction method for a building according to the second embodiment described above, it is possible to perform alignment of the exterior plate or the plate-like body that is a portion of the exterior plate, based on a part of the upper surface of the foundation packing. However, in the construction method of the building of the present invention, not the alignment of the outer plate or the plate-like body that becomes a part of the outer plate, but the alignment of the inner plate or the plate-like body that becomes a part of the inner plate. It may be done.

(a)〜(c)は、第1実施形態に係る建造物の施工方法の一例を模式的に示す斜視図である。(A)-(c) is a perspective view which shows typically an example of the construction method of the building which concerns on 1st Embodiment. 図1(b)に示した基礎パッキン及び基礎を上方から見た様子を模式的に示す平面図である。It is a top view which shows typically a mode that the foundation packing shown in FIG.1 (b) and the foundation were seen from upper direction. (a)〜(c)は、第2実施形態に係る建造物の施工方法の一例を模式的に示す斜視図である。(A)-(c) is a perspective view which shows typically an example of the construction method of the building which concerns on 2nd Embodiment. 図3(b)に示した基礎パッキン及び基礎を上方から見た様子を模式的に示す平面図である。It is a top view which shows typically a mode that the foundation packing shown in FIG.3 (b) and the foundation were seen from upper direction. 従来の基礎パッキンの一例を模式的に示す斜視図である。It is a perspective view which shows typically an example of the conventional basic packing. コンクリート基礎の上面の全周域を覆うように長尺の基礎パッキンを載置した様子を模式的に示す斜視図である。It is a perspective view which shows typically a mode that the elongate foundation packing was mounted so that the perimeter area of the upper surface of a concrete foundation might be covered. (a)〜(c)は、従来の建造物の施工方法の一例を模式的に示す斜視図である。(A)-(c) is a perspective view which shows typically an example of the construction method of the conventional building. (a)〜(b)は、従来の建造物の施工方法の他の一例を模式的に示す斜視図である。(A)-(b) is a perspective view which shows typically another example of the construction method of the conventional building.

符号の説明Explanation of symbols

10 コンクリート基礎
11 上面
12 壁面
13 墨出し線
20 基礎パッキン
21 基体
22 長辺外側面
23 (溝の)底面
24 ボルト挿通孔
25 溝
26 上面
30 木製土台
40 モルタル
50 板状体
100 基礎パッキン
101、103 窪み
102 突起
104 溝
105 穴
200 コンクリート基礎
201、202 部屋となる領域
203 玄関となる領域
300 遮蔽型の基礎パッキン
301 換気型の基礎パッキン
302 アンカーボルト
410 コンクリート基礎
411 上面
412 壁面
413 墨出し線
420、520 基礎パッキン
421、521 基体
422、522 長辺外側面
424、524 ボルト挿通孔
430 木製土台
440 モルタル
450 板状体
DESCRIPTION OF SYMBOLS 10 Concrete foundation 11 Upper surface 12 Wall surface 13 Marking line 20 Foundation packing 21 Base body 22 Long side outer side surface 23 (Groove) bottom surface 24 Bolt insertion hole 25 Groove 26 Upper surface 30 Wooden base 40 Mortar 50 Plate-like body 100 Foundation packing 101, 103 Indentation 102 Protrusion 104 Groove 105 Hole 200 Concrete foundation 201, 202 Room 203 area Entrance area 300 Shielded foundation packing 301 Ventilation foundation packing 302 Anchor bolt 410 Concrete foundation 411 Upper surface 412 Wall surface 413 Inking line 420, 520 Foundation packing 421, 521 Base 422, 522 Long side outer surface 424, 524 Bolt insertion hole 430 Wooden base 440 Mortar 450 Plate

Claims (4)

基礎と土台との間に基礎パッキンを設ける建造物の施工方法であって、
前記基礎の上面に、前記土台の位置合わせのための墨出し線を描く工程と、
所定の厚さを有する矩形板状の基体の長辺外側面に上下方向に貫通した複数の溝が形成された基礎パッキンを、前記溝を介して上方から前記墨出し線を視認し得るように、前記基礎の上面に載置する工程と、
前記土台の外側面が前記墨出し線の上方に位置するように、前記土台を前記基礎パッキンの上面に載置する工程と、
前記土台の外側面より外部空間側における前記基礎パッキンの上面に、外装板又は当該外装板の一部となる板状体を載置する工程と
を含むことを特徴とする建造物の施工方法。
A construction method for a building in which a foundation packing is provided between a foundation and a foundation,
Drawing an inking line for alignment of the foundation on the upper surface of the foundation;
A basic packing in which a plurality of grooves penetrating in the vertical direction is formed on the outer side of the long side of a rectangular plate-like substrate having a predetermined thickness so that the inking line can be visually recognized from above through the grooves. Placing on the upper surface of the foundation;
Placing the foundation on the upper surface of the foundation packing such that the outer surface of the foundation is positioned above the inking line;
Placing the exterior plate or a plate-like body that is a part of the exterior plate on the upper surface of the foundation packing on the outer space side from the outer side surface of the foundation.
基礎と土台との間に基礎パッキンを設ける建造物の施工方法であって、
所定の厚さを有する矩形板状の基体の長辺外側面に上下方向に貫通した複数の溝が形成された基礎パッキンを、当該基礎パッキンの一方の長辺外側面が前記基礎の外壁面より外部空間側に位置するように、前記基礎の上面に載置することを特徴とする建造物の施工方法。
A construction method for a building in which a foundation packing is provided between a foundation and a foundation,
A base packing in which a plurality of grooves penetrating in the vertical direction is formed on the long side outer surface of a rectangular plate-shaped substrate having a predetermined thickness, and one long side outer surface of the base packing is from the outer wall surface of the base. A construction method for a building, which is placed on the upper surface of the foundation so as to be located on the outer space side.
墨出し線が上面に描かれた基礎と、
所定の厚さを有する矩形板状の基体の長辺外側面に上下方向に貫通した複数の溝が形成され、かつ、前記溝を介して上方から前記墨出し線を視認し得るように前記基礎の上面に載置された基礎パッキンと、
その外側面が前記墨出し線の上方に位置するように前記基礎パッキンの上面に載置された土台と、
前記土台の外側面より外部空間側における前記基礎パッキンの上面に載置され、かつ、外装板又は当該外装板の一部となる板状体と
を備えたことを特徴とする建造物。
The basics with the ink line drawn on the top,
A plurality of grooves penetrating in the vertical direction are formed on the outer surface of the long side of the rectangular plate-shaped substrate having a predetermined thickness, and the inking line is visible from above through the grooves. A foundation packing placed on the upper surface of
A base placed on the upper surface of the foundation packing such that its outer surface is located above the inking line;
A building comprising: an exterior plate or a plate-like body that is a part of the exterior plate and is placed on the upper surface of the foundation packing on the outer space side from the outer surface of the base.
基礎と土台との間に基礎パッキンが設けられた建造物であって、
所定の厚さを有する矩形板状の基体の長辺外側面に上下方向に貫通した複数の溝が形成された基礎パッキンが、当該基礎パッキンの一方の長辺外側面が前記基礎の外壁面より外部空間側に位置するように、前記基礎の上面に載置されていることを特徴とする建造物。
A building with a foundation packing between the foundation and the foundation,
A foundation packing in which a plurality of grooves penetrating in the vertical direction is formed on the long side outer surface of a rectangular plate-like substrate having a predetermined thickness, and one long side outer surface of the foundation packing is from the outer wall surface of the foundation. A building characterized by being placed on the upper surface of the foundation so as to be located on the external space side.
JP2004115636A 2004-04-09 2004-04-09 Construction method of building and building Expired - Fee Related JP4364045B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP2004115636A JP4364045B2 (en) 2004-04-09 2004-04-09 Construction method of building and building

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP2004115636A JP4364045B2 (en) 2004-04-09 2004-04-09 Construction method of building and building

Publications (2)

Publication Number Publication Date
JP2005299177A true JP2005299177A (en) 2005-10-27
JP4364045B2 JP4364045B2 (en) 2009-11-11

Family

ID=35331061

Family Applications (1)

Application Number Title Priority Date Filing Date
JP2004115636A Expired - Fee Related JP4364045B2 (en) 2004-04-09 2004-04-09 Construction method of building and building

Country Status (1)

Country Link
JP (1) JP4364045B2 (en)

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2007126944A (en) * 2005-11-07 2007-05-24 Joto Techno Co Ltd Foundation packing
JP2008127756A (en) * 2006-11-16 2008-06-05 Mitsui Kagaku Sanshi Kk Long foundation packing
JP2018197474A (en) * 2017-05-24 2018-12-13 積水ハウス株式会社 Joint structure of wall member and foundation

Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS6013150A (en) * 1983-06-30 1985-01-23 塩野 輝之 Foundation waterproof mat
JPS6017808U (en) * 1983-07-15 1985-02-06 ミサワホ−ム株式会社 Synthetic resin base
JPS62160345A (en) * 1986-01-09 1987-07-16 桜井工業株式会社 Perforated ventialtion plate provided between foundation andbase
JPH0849307A (en) * 1994-08-05 1996-02-20 Misawa Homes Co Ltd Water drip structure of foundation
JP2002276042A (en) * 2001-03-19 2002-09-25 Joto Techno Co Ltd Foundation packing
JP2004084315A (en) * 2002-08-27 2004-03-18 Sumitomo Forestry Co Ltd Tool for inspecting anchor bolt for construction accuracy

Patent Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS6013150A (en) * 1983-06-30 1985-01-23 塩野 輝之 Foundation waterproof mat
JPS6017808U (en) * 1983-07-15 1985-02-06 ミサワホ−ム株式会社 Synthetic resin base
JPS62160345A (en) * 1986-01-09 1987-07-16 桜井工業株式会社 Perforated ventialtion plate provided between foundation andbase
JPH0849307A (en) * 1994-08-05 1996-02-20 Misawa Homes Co Ltd Water drip structure of foundation
JP2002276042A (en) * 2001-03-19 2002-09-25 Joto Techno Co Ltd Foundation packing
JP2004084315A (en) * 2002-08-27 2004-03-18 Sumitomo Forestry Co Ltd Tool for inspecting anchor bolt for construction accuracy

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2007126944A (en) * 2005-11-07 2007-05-24 Joto Techno Co Ltd Foundation packing
JP2008127756A (en) * 2006-11-16 2008-06-05 Mitsui Kagaku Sanshi Kk Long foundation packing
JP2018197474A (en) * 2017-05-24 2018-12-13 積水ハウス株式会社 Joint structure of wall member and foundation

Also Published As

Publication number Publication date
JP4364045B2 (en) 2009-11-11

Similar Documents

Publication Publication Date Title
JP4018740B2 (en) Formwork method for interior / exterior material foundation formwork panel and concrete structure
RU2440473C2 (en) Vertical construction joints
JP4092341B2 (en) Foundation packing and construction method
JP4364045B2 (en) Construction method of building and building
US20100095628A1 (en) Wall system
JP2010112090A (en) Connection member and connection method without requiring temporary member
JP4869681B2 (en) Foundation packing
US4548008A (en) Tile panel having convex and concave portions around substrate board, and method for production thereof
JP2002129662A (en) Sole plate, structure and method of installing sole plate, and method of mounting building main body
KR102477121B1 (en) Deck panel for Euroform
JP3997161B2 (en) Void structure on foundation
JPH08165727A (en) Construction panel body and joint method thereof
JP2020148077A (en) Concrete form and insulation decorative plate, building and concrete structural skeleton forming method
CN110725434A (en) PEC wall and major structure wet-type connected node
GB2106158A (en) Permanent formwork
JP4626943B2 (en) Foundation packing, mortar stopper and building construction method
CN219931609U (en) Hollowed-out stair template
CN211850123U (en) PEC wall and major structure wet-type connected node
JP2786412B2 (en) Exterior panel covering structure of concrete building and covering construction method
KR200415136Y1 (en) block Assembly for architecture
KR200415591Y1 (en) The euroform for slab
KR20070006540A (en) Concrete crack prevention device
JPH0547701B2 (en)
JPH065464Y2 (en) Outer wall board
JPS6337364Y2 (en)

Legal Events

Date Code Title Description
A621 Written request for application examination

Free format text: JAPANESE INTERMEDIATE CODE: A621

Effective date: 20070312

RD04 Notification of resignation of power of attorney

Free format text: JAPANESE INTERMEDIATE CODE: A7424

Effective date: 20070831

A977 Report on retrieval

Free format text: JAPANESE INTERMEDIATE CODE: A971007

Effective date: 20081210

A131 Notification of reasons for refusal

Free format text: JAPANESE INTERMEDIATE CODE: A131

Effective date: 20081216

A521 Request for written amendment filed

Free format text: JAPANESE INTERMEDIATE CODE: A523

Effective date: 20090213

RD02 Notification of acceptance of power of attorney

Free format text: JAPANESE INTERMEDIATE CODE: A7422

Effective date: 20090213

A131 Notification of reasons for refusal

Free format text: JAPANESE INTERMEDIATE CODE: A131

Effective date: 20090407

A521 Request for written amendment filed

Free format text: JAPANESE INTERMEDIATE CODE: A523

Effective date: 20090605

TRDD Decision of grant or rejection written
A01 Written decision to grant a patent or to grant a registration (utility model)

Free format text: JAPANESE INTERMEDIATE CODE: A01

Effective date: 20090818

A01 Written decision to grant a patent or to grant a registration (utility model)

Free format text: JAPANESE INTERMEDIATE CODE: A01

A61 First payment of annual fees (during grant procedure)

Free format text: JAPANESE INTERMEDIATE CODE: A61

Effective date: 20090818

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20120828

Year of fee payment: 3

R150 Certificate of patent or registration of utility model

Ref document number: 4364045

Country of ref document: JP

Free format text: JAPANESE INTERMEDIATE CODE: R150

Free format text: JAPANESE INTERMEDIATE CODE: R150

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20120828

Year of fee payment: 3

RD02 Notification of acceptance of power of attorney

Free format text: JAPANESE INTERMEDIATE CODE: R3D02

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20120828

Year of fee payment: 3

RD04 Notification of resignation of power of attorney

Free format text: JAPANESE INTERMEDIATE CODE: R3D04

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20120828

Year of fee payment: 3

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20150828

Year of fee payment: 6

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

LAPS Cancellation because of no payment of annual fees