JP2018109281A - Tunnel inner structure, and construction method for the same - Google Patents

Tunnel inner structure, and construction method for the same Download PDF

Info

Publication number
JP2018109281A
JP2018109281A JP2016256782A JP2016256782A JP2018109281A JP 2018109281 A JP2018109281 A JP 2018109281A JP 2016256782 A JP2016256782 A JP 2016256782A JP 2016256782 A JP2016256782 A JP 2016256782A JP 2018109281 A JP2018109281 A JP 2018109281A
Authority
JP
Japan
Prior art keywords
tunnel
culverts
side wall
cross
pair
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
JP2016256782A
Other languages
Japanese (ja)
Other versions
JP6767864B2 (en
Inventor
中谷 郁夫
Ikuo Nakatani
郁夫 中谷
哲憲 谷口
Tetsunori Taniguchi
哲憲 谷口
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Geostr Corp
Original Assignee
Geostr Corp
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Geostr Corp filed Critical Geostr Corp
Priority to JP2016256782A priority Critical patent/JP6767864B2/en
Publication of JP2018109281A publication Critical patent/JP2018109281A/en
Application granted granted Critical
Publication of JP6767864B2 publication Critical patent/JP6767864B2/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Lining And Supports For Tunnels (AREA)

Abstract

PROBLEM TO BE SOLVED: To provide a tunnel inner structure and a construction method therefor that simplify construction work.SOLUTION: A tunnel inner structure according to one embodiment of the present invention includes a plurality of culverts installed in a tunnel, having a bottom part and a pair of side wall parts provided on both sides of the bottom part. Each of the two adjacent side wall parts is formed to have a cross-sectional thickness in a transverse direction of the tunnel thinner than a required performance thickness, and to have the cross-sectional thickness in the transverse direction of the tunnel thicker than the required performance thickness when the two adjacent side wall parts are coupled to each other.SELECTED DRAWING: Figure 1

Description

本発明は、トンネル内に形成される床面を支持するためのトンネル内構造およびトンネル内構造の築造方法に関する。   The present invention relates to an in-tunnel structure for supporting a floor surface formed in a tunnel and a method for constructing the in-tunnel structure.

シールドトンネルは、シールドマシンで掘削されたトンネル開口部を掘削に従ってセグメントで覆って構築される。シールドトンネルが構築された後、トンネル内の底部に床面が形成される。特許文献1には、トンネル内に型枠を設置して側壁及びインバートを構築するトンネル内部の構築方法が記載されている。
特許文献2には、トンネルの底部に底板となるインバートブロックを設置し、その上に一対の側板と天板をそれぞれピン結合して組み立てられるボックスカルバートによるトンネル内の床面構造が記載されている。
A shield tunnel is constructed by covering a tunnel opening excavated by a shield machine with a segment according to excavation. After the shield tunnel is constructed, a floor is formed at the bottom of the tunnel. Patent Document 1 describes a method for constructing a tunnel, in which a formwork is installed in the tunnel to construct a side wall and an invert.
Patent Document 2 describes a floor surface structure in a tunnel by a box culvert that is assembled by installing an invert block serving as a bottom plate at the bottom of the tunnel and pin-connecting a pair of side plates and a top plate to each other. .

特開2006−152746号公報JP 2006-152746 A 特開2009−150165号公報JP 2009-150165 A

特許文献1に記載された床面構造は、現場打ちのコンクリートで側壁及びインバートを構築するため、工期が延びる可能性がある。また、特許文献2に記載された床面構造は、分割された底板、一対の側板、天板をそれぞれ結合してボックスカルバートを構築するため、施工の手間が増加して工期が延びる可能性がある。   Since the floor structure described in Patent Document 1 is constructed with side wall and invert made of concrete cast on the spot, the work period may be extended. In addition, the floor structure described in Patent Document 2 is constructed by combining a divided bottom plate, a pair of side plates, and a top plate to construct a box culvert. is there.

本発明は、施工を簡略化することができるトンネル内構造およびトンネル内構造の築造方法を提供することを目的とする。   An object of this invention is to provide the construction method of the structure in a tunnel which can simplify construction, and the structure in a tunnel.

本発明の一態様に係るトンネル内構造は、トンネル内に設置される、底部と前記底部の両側に設けられた一対の側壁部とを有する複数のカルバートを備え、互いに隣接する二つの前記側壁部のそれぞれは、トンネル断面方向の断面厚さが要求性能厚さより薄く形成され、前記複数のカルバートを前記トンネル断面の水平方向に連続して配置し、互いに隣接する二つの前記側壁部同士を連結した際に連結された断面厚さが前記要求性能厚さ以上となるよう形成されている。   An in-tunnel structure according to an aspect of the present invention includes a plurality of culverts having a bottom portion and a pair of side wall portions provided on both sides of the bottom portion, which are installed in the tunnel, and the two side wall portions adjacent to each other. In each of the above, the cross-sectional thickness in the tunnel cross-sectional direction is formed thinner than the required performance thickness, the plurality of culverts are continuously arranged in the horizontal direction of the tunnel cross-section, and the two adjacent side wall portions are connected to each other The cross-sectional thickness connected at this time is formed to be equal to or greater than the required performance thickness.

本発明は、このような構成により、個々のカルバートを軽量化することができ、コストを低減すると共に施工性を向上することができる。   With this configuration, the present invention can reduce the weight of individual culverts, reduce costs, and improve workability.

トンネル内構造は、前記複数のカルバートが所定の間隔で離間して配置されており、前記複数のカルバートの間に生じた空間を埋める充填材によって形成された連結部を更に備えていてもよい。   The in-tunnel structure may further include a connecting portion formed by a filler that fills a space generated between the plurality of culverts, with the plurality of culverts being spaced apart at a predetermined interval.

本発明は、このような構成により、連結部によって隣接するカルバート同士を一体化することができる。   According to the present invention, the culverts adjacent to each other can be integrated by the connecting portion.

トンネル内構造は、前記連結部が互いに隣接する二つの前記側壁部の対向面から露出した複数の継手を介して隣接する二つの前記カルバートを連結するよう構成されていてもよい。   The in-tunnel structure may be configured to connect two adjacent culverts via a plurality of joints exposed from opposing surfaces of the two side wall portions adjacent to each other.

本発明は、このような構成により、隣接する二つの前記カルバートを一体化することができる。   According to the present invention, the two adjacent culverts can be integrated by such a configuration.

トンネル内構造は、前記カルバートがボックスカルバートであってもよい。   In the tunnel structure, the culvert may be a box culvert.

本発明は、このような構成により、施工性及び運搬性を向上することができる。   This invention can improve workability and transportability by such a structure.

トンネル内構造は、前記ボックスカルバートが上下に分割されて形成されていてもよい。   The in-tunnel structure may be formed by dividing the box culvert vertically.

本発明は、このような構成により、施工性及び運搬性を向上することができる。   This invention can improve workability and transportability by such a structure.

トンネル内構造は、前記カルバートがU型カルバートであってもよい。   In the tunnel structure, the culvert may be a U-shaped culvert.

本発明は、このような構成により、施工性及び運搬性を向上することができる。   This invention can improve workability and transportability by such a structure.

トンネル内構造は、前記U型カルバートの上部にRC床板が設置されていてもよい。   In the tunnel structure, an RC floor board may be installed on the U-shaped culvert.

本発明は、このような構成により、施工性及び運搬性を向上することができる。   This invention can improve workability and transportability by such a structure.

トンネル内構造は、前記複数のカルバートが前記トンネル断面方向に連続して配置され、前記複数のカルバートの両側は、流動化処理土によって一対の端部構造が形成されていてもよい。   In the tunnel structure, the plurality of culverts may be continuously arranged in the tunnel cross-sectional direction, and a pair of end structures may be formed by fluidized soil on both sides of the plurality of culverts.

本発明は、このような構成により、施工性及び運搬性を向上することができる。   This invention can improve workability and transportability by such a structure.

トンネル内構造は、前記複数のカルバートが前記トンネル断面方向に連続して配置され、前記複数のカルバートの両側は、端部ブロックが配置されていてもよい。   In the tunnel structure, the plurality of culverts may be continuously arranged in the tunnel cross-sectional direction, and end blocks may be arranged on both sides of the plurality of culverts.

本発明は、このような構成により、施工性及び運搬性を向上することができる。   This invention can improve workability and transportability by such a structure.

本発明の一態様にかかるトンネル内構造の築造方法は、底部と前記底部の両側に設けられた一対の側壁部とを有する複数のカルバートをトンネル内に設置するトンネル内構造の築造方法であって、互いに隣接する二つの前記側壁部のそれぞれは、トンネル断面の水平方向の断面厚さが要求性能厚さより薄く形成されており、前記複数のカルバートを前記トンネル断面の水平方向に連続して配置し、互いに隣接する二つの前記側壁部同士を連結し、連結された断面厚さが前記要求性能厚さ以上となるよう形成する。   A method for constructing a tunnel internal structure according to one aspect of the present invention is a method for constructing a tunnel internal structure in which a plurality of culverts having a bottom and a pair of side walls provided on both sides of the bottom are installed in the tunnel. Each of the two side wall portions adjacent to each other is formed such that the horizontal section thickness of the tunnel section is thinner than the required performance thickness, and the plurality of culverts are continuously arranged in the horizontal direction of the tunnel section. The two side wall portions adjacent to each other are connected to each other, and the connected cross-sectional thickness is equal to or greater than the required performance thickness.

本発明は、このような構成により、個々のカルバートを軽量化することができ、コストを低減すると共に施工性及び運搬性を向上することができる。   With this configuration, the present invention can reduce the weight of individual culverts, reduce costs, and improve workability and transportability.

本発明に係るトンネル内構造およびトンネル内構造の築造方法によると、施工を簡略化することができる。   According to the tunnel internal structure and the tunnel internal construction method according to the present invention, the construction can be simplified.

第1実施形態に係るトンネル内構造を示す斜視図である。It is a perspective view which shows the structure in a tunnel which concerns on 1st Embodiment. 隣接するボックスカルバートを連結する方法を示す図である。It is a figure which shows the method of connecting the adjacent box culvert. 隣接するボックスカルバートを連結する他の方法を示す図である。It is a figure which shows the other method of connecting adjacent box culverts. トンネル内構造を築造する方法を示すフローチャートである。It is a flowchart which shows the method of building the structure in a tunnel. シールドトンネルを示す断面斜視図である。It is a section perspective view showing a shield tunnel. シールドトンネルに一対のボックスカルバートを設置した状態を示す斜視図である。It is a perspective view which shows the state which installed a pair of box culvert in the shield tunnel. 一対のボックスカルバートを連結した状態を示す斜視図である。It is a perspective view which shows the state which connected a pair of box culvert. 一対のボックスカルバートの両側に端部構造を設ける状態を示す斜視図である。It is a perspective view which shows the state which provides an edge part structure on both sides of a pair of box culvert. 第2実施形態に係るトンネル内構造を示す斜視図である。It is a perspective view which shows the structure in a tunnel which concerns on 2nd Embodiment. 第3実施形態に係るトンネル内構造を示す斜視図である。It is a perspective view which shows the structure in a tunnel which concerns on 3rd Embodiment.

以下、図面を参照しつつ、本発明の実施形態に係るトンネル内構造1について説明する。   Hereinafter, a tunnel internal structure 1 according to an embodiment of the present invention will be described with reference to the drawings.

[第1実施形態]
図1に示されるように、トンネル内構造1は、シールドトンネル10内に構築される構造物である。トンネル内構造1は、シールドトンネル10の底部に設置される一対のボックスカルバート20と、一対のボックスカルバート20の両側に設置される一対の端部構造40とによって構成される。
[First Embodiment]
As shown in FIG. 1, the in-tunnel structure 1 is a structure constructed in a shield tunnel 10. The in-tunnel structure 1 includes a pair of box culverts 20 installed at the bottom of the shield tunnel 10 and a pair of end structures 40 installed on both sides of the pair of box culverts 20.

ボックスカルバート20は、例えばプレキャストで形成されているコンクリート製のブロックである。プレキャストとは、工場で予め製造されることをいう。プレキャストで形成されたコンクリート部材を組み立てることにより、現場でコンクリートを打設する工法より工期を短縮することができる。ボックスカルバート20は、例えば鉄筋コンクリート構造で形成されている。ボックスカルバート20は、一体で形成されていてもよいし、分割して形成されていてもよい。   The box culvert 20 is a concrete block formed by precast, for example. Precast refers to being manufactured in advance at a factory. By assembling the concrete members formed by precast, the construction period can be shortened compared to the method of placing concrete on site. The box culvert 20 is formed of, for example, a reinforced concrete structure. The box culvert 20 may be integrally formed or may be divided.

ボックスカルバート20は、シールドトンネル10の底部に設置される底板21と、底板21の両側に設けられた一対の側壁部22,23と、側壁部22,23に支持された天板24とを有する。底板21は、方形の板状体である。底板21は、シールドトンネル10の内壁11の形状に合わせて下方に湾曲している。底板21の底面21aは、シールドトンネル10の底部に設置された際に、シールドトンネル10の内壁11の形状に合致するように形成されている。   The box culvert 20 has a bottom plate 21 installed at the bottom of the shield tunnel 10, a pair of side walls 22, 23 provided on both sides of the bottom plate 21, and a top plate 24 supported by the side walls 22, 23. . The bottom plate 21 is a square plate-like body. The bottom plate 21 is curved downward in accordance with the shape of the inner wall 11 of the shield tunnel 10. The bottom surface 21 a of the bottom plate 21 is formed so as to match the shape of the inner wall 11 of the shield tunnel 10 when installed on the bottom of the shield tunnel 10.

底板21のトンネル軸Lに直交する方向の両側にある一端21b及び他端21cからは、上方に起立して一対の側壁部22,23が設けられている。側壁部22,23は方形の板状体である。ボックスカルバート20が分割型の場合、側壁部22,23の上方に向かう途中には水平方向に沿って分割部22a,23aが設けられていてもよい。側壁部22の断面厚さt1は、側壁部23の断面厚さt2より薄く形成されている。側壁部23の断面厚さt2は、設計強度で要求される所定の厚さ(以下、要求性能厚さと呼ぶ)を満たすよう形成されている。一方、側壁部22の断面厚さt1は、要求性能厚さより薄く形成されている。   From one end 21b and the other end 21c on both sides of the bottom plate 21 in the direction orthogonal to the tunnel axis L, a pair of side wall portions 22 and 23 are provided standing upward. The side walls 22 and 23 are rectangular plate-like bodies. When the box culvert 20 is a split type, the split portions 22a and 23a may be provided along the horizontal direction in the middle of the upper side of the side wall portions 22 and 23. The cross-sectional thickness t1 of the side wall part 22 is formed thinner than the cross-sectional thickness t2 of the side wall part 23. The cross-sectional thickness t2 of the side wall portion 23 is formed to satisfy a predetermined thickness required for design strength (hereinafter referred to as required performance thickness). On the other hand, the cross-sectional thickness t1 of the side wall part 22 is formed thinner than the required performance thickness.

側壁部22の詳細な構成は後述する。側壁部22,23は、天板24を水平に支持している。天板24は、方形の板状体である。ボックスカルバート20には、このような構成により、シールドトンネル10のトンネル軸L方向に沿って台形断面の開口部Pが形成されている。一対のボックスカルバート20は、トンネル断面の水平方向に沿って対称に配置されている。一対のボックスカルバート20の間には、一対のボックスカルバート20を一体化するための連結部30が形成されている。連結部30は、対向する2つの側壁部22を連結する。連結部30は、例えばコンクリートやモルタルで形成される。連結部30の詳細な構成は後述する。   The detailed configuration of the side wall portion 22 will be described later. The side walls 22 and 23 support the top plate 24 horizontally. The top plate 24 is a rectangular plate-like body. The box culvert 20 has an opening P having a trapezoidal cross section along the tunnel axis L direction of the shield tunnel 10 with such a configuration. The pair of box culverts 20 are arranged symmetrically along the horizontal direction of the tunnel cross section. A connecting portion 30 for integrating the pair of box culverts 20 is formed between the pair of box culverts 20. The connecting part 30 connects the two side wall parts 22 facing each other. The connecting portion 30 is made of, for example, concrete or mortar. The detailed configuration of the connecting portion 30 will be described later.

一対のボックスカルバート20が連結されると、一対の開口部Pが形成される。トンネル内構造1をシールドトンネル10内に順次構築して連続させると、連続した開口部Pが形成される。連続した開口部Pは、例えば災害時の避難通路として用いられる。開口部Pは、避難通路の他、例えば換気口、通信や電力ケーブル等を敷設するための共同溝として用いられてもよい。開口部Pは、用途に合わせて断面積が決定される。そのため一対のボックスカルバート20は必ずしも対称の形状とは限らない。   When the pair of box culverts 20 are connected, a pair of openings P is formed. When the in-tunnel structure 1 is sequentially constructed in the shield tunnel 10 and continued, a continuous opening P is formed. The continuous opening P is used as an evacuation passage at the time of a disaster, for example. The opening P may be used as a common groove for laying a ventilation port, communication, power cable, etc., in addition to the escape passage. The cross-sectional area of the opening P is determined according to the application. For this reason, the pair of box culverts 20 is not necessarily symmetrical.

一対のボックスカルバート20の両端には、一対の端部構造40が設けられている。例えば、端部構造40の上面41の高さは、ボックスカルバート20の天板24の高さと同一に形成される。端部構造40は、例えば流動化処理土によって形成される。端部構造40を流動化処理土で形成する際、側壁部23が型枠の一部となる。トンネル内構造1をシールドトンネル10内に順次築造していくと、既に形成された端部構造40も型枠となるため、端部構造40の型枠はトンネル断面方向の一部に設けるだけでよい。そのため、トンネル内構造1は、築造時に型枠の一部を省略することができ施工性が向上する。   A pair of end structures 40 are provided at both ends of the pair of box culverts 20. For example, the height of the upper surface 41 of the end structure 40 is formed to be the same as the height of the top plate 24 of the box culvert 20. The end structure 40 is formed by fluidized soil, for example. When the end structure 40 is formed of fluidized soil, the side wall portion 23 becomes a part of the mold. When the tunnel inner structure 1 is sequentially built in the shield tunnel 10, the end structure 40 that has already been formed becomes a mold, so the mold of the end structure 40 is only provided in a part of the tunnel cross-sectional direction. Good. Therefore, the tunnel inner structure 1 can omit a part of the formwork at the time of construction, and the workability is improved.

端部構造40は、ボックスカルバート20が水平方向に変位した際、ボックスカルバート20に対して変位と反対方向の反力を与える。このとき、端部構造40が弾性変形してボックスカルバート20の変位によって生じる運動エネルギーを吸収し、端部構造40は、ボックスカルバート20の変位に対するダンパーとなる。従って、端部構造40は、ボックスカルバート20に生じる振動を端部構造40が無い場合に比して早期に収束させる。   The end structure 40 gives a reaction force in the direction opposite to the displacement to the box culvert 20 when the box culvert 20 is displaced in the horizontal direction. At this time, the end structure 40 is elastically deformed to absorb the kinetic energy generated by the displacement of the box culvert 20, and the end structure 40 becomes a damper against the displacement of the box culvert 20. Therefore, the end structure 40 converges the vibration generated in the box culvert 20 earlier than in the case where the end structure 40 is not provided.

一対の端部構造40を設置した後、天板24と端部構造40との上方には、例えば土層50が敷かれて路面が形成される。天板24の上方には、土層の他、例えば床板を載置してその上に路面を形成してもよい。また、端部構造40は、流動化処理土で形成されるものの他、例えばコンクリートで形成されたブロックであってもよい。端部構造40がブロックの場合、施工性が向上する。   After the pair of end structure 40 is installed, for example, a soil layer 50 is laid on the top plate 24 and the end structure 40 to form a road surface. In addition to the soil layer, for example, a floor plate may be placed on the top plate 24 to form a road surface thereon. Further, the end structure 40 may be a block formed of concrete, for example, in addition to the one formed of fluidized soil. When the end structure 40 is a block, workability is improved.

次に、対向する2つの側壁部22を連結する連結部30の詳細について説明する。   Next, the detail of the connection part 30 which connects two opposing side wall parts 22 is demonstrated.

図2に示されるように、一対のボックスカルバート20が所定の間隔で離間して配置される。この状態で隙間Qが生じる。隙間Qにおいて一対のボックスカルバート20の天板24の一端24a側からは、天板24の内部に配筋された複数の主鉄筋Rの端部R1が露出している。複数の端部R1が対向して配置された際に、互い違いに配置されるように、主鉄筋Rが天板24内部に配筋されている。端部R1は、主鉄筋Rが折り曲げられてトンネル軸L方向から見てループ状に形成されている。これにより、端部R1は、ループ継手となる。   As shown in FIG. 2, a pair of box culverts 20 are arranged at a predetermined interval. In this state, a gap Q is generated. From the one end 24a side of the top plate 24 of the pair of box culverts 20 in the gap Q, end portions R1 of the plurality of main reinforcing bars R arranged inside the top plate 24 are exposed. The main reinforcing bars R are arranged inside the top plate 24 so as to be alternately arranged when the plurality of end portions R1 are arranged to face each other. The end R1 is formed in a loop shape when the main reinforcing bar R is bent and viewed from the tunnel axis L direction. Thereby, the end R1 becomes a loop joint.

互いに対抗する一対の側壁部22の対向面22bからは、例えば無数のジベル鉄筋T等の継手が露出している。互いに対抗する無数のジベル鉄筋Tは、互いに干渉しないように互い違いに配置される。   For example, innumerable joints such as a dowel rebar T are exposed from the opposing surfaces 22b of the pair of side wall portions 22 facing each other. The innumerable dowel rebars T that oppose each other are arranged alternately so as not to interfere with each other.

図3に示されるように、ジベル鉄筋Tの代わりに、帯状の鋼板に鋼板の軸線に沿って複数の孔が設けられた鋼板ジベルGを用いてもよい。一対の端部構造40を設置した後、例えば隙間Qにコンクリートやモルタル等の充填材を充填する。充填材が固結すると、連結部30が形成される。一対のボックスカルバート20は、連結部30によって側壁部22の対向面22bから露出した複数の継手を介して一体化される。   As shown in FIG. 3, a steel plate gibel G in which a plurality of holes are provided in a strip-shaped steel plate along the axis of the steel plate may be used instead of the gibber reinforcing bar T. After installing the pair of end structures 40, for example, the gap Q is filled with a filler such as concrete or mortar. When the filler is consolidated, a connecting portion 30 is formed. The pair of box culverts 20 are integrated through a plurality of joints exposed from the facing surface 22 b of the side wall portion 22 by the connecting portion 30.

連結部30が形成されると、連結部30と一対の側壁部22で形成された隔壁の厚さは、要求性能厚さより薄く形成されていた一方の側壁部22の断面厚さt1と、他方の側壁部22の断面厚さt1と連結部30の厚さとを加えて要求性能厚さ以上に形成される。   When the connecting portion 30 is formed, the thickness of the partition wall formed by the connecting portion 30 and the pair of side wall portions 22 is equal to the cross-sectional thickness t1 of the one side wall portion 22 formed thinner than the required performance thickness, and the other By adding the cross-sectional thickness t1 of the side wall portion 22 and the thickness of the connecting portion 30 to the required performance thickness.

次に、トンネル内構造1の築造方法について説明する。   Next, the construction method of the tunnel inner structure 1 will be described.

図4は、トンネル内構造1を築造する処理を示すフローチャートである。図5に示されるように、セグメント12が組まれてシールドトンネル10が築造される。図6に示されるように、シールドトンネル10内の底部に一対のボックスカルバート20を所定の間隔で離間して設置する(S10)。ボックスカルバート20は、例えば地上からシールドマシンの発進立坑に搬入される。その後、ボックスカルバート20は、シールドトンネル10の入り口から内部を通って設置点まで運搬され、例えばクレーンで設置される。   FIG. 4 is a flowchart showing a process for building the tunnel internal structure 1. As shown in FIG. 5, the segments 12 are assembled to build the shield tunnel 10. As shown in FIG. 6, a pair of box culverts 20 are installed at a predetermined interval at the bottom of the shield tunnel 10 (S10). The box culvert 20 is carried into the start shaft of a shield machine from the ground, for example. Thereafter, the box culvert 20 is transported from the entrance of the shield tunnel 10 through the inside to the installation point, and is installed by a crane, for example.

図7に示されるように、一対のボックスカルバート20の間に生じた隙間Qを充填材で充填し、連結部30を形成する(S11)。連結部30が固結すると、一対のボックスカルバート20同士が一体化される。図8に示されるように、一対のボックスカルバート20の両側に一対の端部構造40を設置する(S12)。端部構造40は、例えば流動化処理土で形成される。その後、一対のボックスカルバート20と一対の端部構造40の上面に路面(不図示)を形成する(S13)。   As shown in FIG. 7, the gap Q generated between the pair of box culverts 20 is filled with a filler to form the connecting portion 30 (S11). When the connecting portion 30 is consolidated, the pair of box culverts 20 are integrated. As shown in FIG. 8, a pair of end structures 40 are installed on both sides of the pair of box culverts 20 (S12). The end structure 40 is formed of fluidized soil, for example. Thereafter, road surfaces (not shown) are formed on the upper surfaces of the pair of box culverts 20 and the pair of end structure 40 (S13).

上記の工程を繰り返し行って、トンネル内構造1をシールドトンネル10のトンネル軸Lに沿って順次築造することにより、シールドトンネル10内に路面が形成される。シールドトンネル10内に連続して築造されたトンネル内構造1は、土層50の下に構築されるため、トンネル軸L方向に隣接したトンネル構造1の各ブロック同士は、必ずしも継手、ボルト及びPC鋼材等の連結部材によって連結されていなくてもよいが、連結されていてもよい。   The road surface is formed in the shield tunnel 10 by repeatedly constructing the in-tunnel structure 1 along the tunnel axis L of the shield tunnel 10 by repeating the above steps. Since the in-tunnel structure 1 continuously built in the shield tunnel 10 is constructed under the soil layer 50, each block of the tunnel structure 1 adjacent in the tunnel axis L direction is not necessarily connected with a joint, a bolt, and a PC. Although it may not be connected by connecting members, such as steel materials, it may be connected.

上述したようにトンネル内構造1によると、各ボックスカルバート20の一部を薄肉化したり軽量化したりして運搬性を向上し、コストを低減し、施工性を向上することができる。トンネル内構造1によると、一対のボックスカルバート20の設置後に連結部30を形成することにより、各ボックスカルバート20の一部を薄肉化等しても設計上必要な強度を確保することができ、安全性を向上させることができる。   As described above, according to the in-tunnel structure 1, a part of each box culvert 20 can be made thinner or lighter to improve transportability, reduce costs, and improve workability. According to the tunnel internal structure 1, by forming the connecting portion 30 after the pair of box culverts 20 are installed, the strength necessary for design can be ensured even if a part of each box culvert 20 is thinned, Safety can be improved.

[第2実施形態]
第1実施形態では、ボックスカルバート20でトンネル内構造1を築造していた。第2実施形態では、U字断面を有するU型カルバート20Uで築造された変形例を示す。以下の説明では、第1実施形態と同一の構成については同一の符号を用い、同様の説明については省略する。
[Second Embodiment]
In the first embodiment, the in-tunnel structure 1 is constructed by the box culvert 20. 2nd Embodiment shows the modification built with the U-shaped culvert 20U which has a U-shaped cross section. In the following description, the same reference numerals are used for the same configurations as those in the first embodiment, and the same descriptions are omitted.

図9に示されるように、トンネル内構造2は、一対のU型カルバート20Uと、連結部30と、一対の端部構造40とを有する。U型カルバート20Uは、ボックスカルバート20の天板24を取り除いた構造を有する。U型カルバート20Uでトンネル内構造2を築造した後、一対のU型カルバート20Uと、連結部30と、一対の端部構造40との上部に、例えば鉄筋コンクリートで形成されたRC床板Eを載置する。RC床板Eの上面に路面が形成される。U型カルバート20Uを用いると、運搬時に互い違いに配置することにより積載効率が向上する。   As shown in FIG. 9, the in-tunnel structure 2 includes a pair of U-shaped culverts 20 </ b> U, a connecting portion 30, and a pair of end structure 40. The U-shaped culvert 20U has a structure in which the top plate 24 of the box culvert 20 is removed. After constructing the tunnel inner structure 2 with the U-shaped culvert 20U, an RC floor plate E made of reinforced concrete, for example, is placed on top of the pair of U-shaped culverts 20U, the connecting portion 30, and the pair of end structure 40 To do. A road surface is formed on the upper surface of the RC floor plate E. When the U-shaped culvert 20U is used, the loading efficiency is improved by staggering them during transportation.

トンネル内構造2によると、ボックスカルバート20より軽量なU型カルバート20Uを用いることにより、運搬性及び積載性を向上することができ、コストを低減し、施工性を向上することができる。   According to the tunnel inner structure 2, by using the U-shaped culvert 20U that is lighter than the box culvert 20, it is possible to improve transportability and loadability, reduce costs, and improve workability.

[第3実施形態]
第1実施形態では、トンネル内構造1は、一対のボックスカルバート20で築造した。第3実施形態では、3連のボックスカルバートを用いる変形例を示す。
[Third Embodiment]
In the first embodiment, the in-tunnel structure 1 is constructed by a pair of box culverts 20. In the third embodiment, a modification using a triple box culvert is shown.

図10に示されるように、トンネル内構造3は、3連のボックスカルバート20A,20B,20Cを有する。トンネル内構造3には、3連のボックスカルバート20A,20B,20Cにより、3連の空間PA,PB,PCが形成される。図示するように、ボックスカルバート20B,20Cは対称に形成されているが、必ずしも対称で形成されていなくてもよい。   As shown in FIG. 10, the in-tunnel structure 3 includes three box culverts 20A, 20B, and 20C. In the in-tunnel structure 3, triple spaces PA, PB, and PC are formed by triple box culverts 20A, 20B, and 20C. As illustrated, the box culverts 20B and 20C are formed symmetrically, but are not necessarily formed symmetrically.

トンネル内構造3によると、複数のボックスカルバート20A,20B,20Cを用いることにより、複数の空間PA,PB,PCを形成することができ、使用目的にあわせて空間を形成することができる。   According to the tunnel internal structure 3, a plurality of spaces PA, PB, PC can be formed by using a plurality of box culverts 20A, 20B, 20C, and a space can be formed according to the purpose of use.

本発明のいくつかの実施形態を説明したが、これらの実施形態は、例として提示したものであり、発明の範囲を限定することは意図していない。これら実施形態は、その他の様々な形態で実施されることが可能であり、発明の要旨を逸脱しない範囲で、種々の省略、置き換え、変更を行うことができる。これら実施形態やその変形は、発明の範囲や要旨に含まれると同様に、特許請求の範囲に記載された発明とその均等の範囲に含まれるものである。例えば、上記実施形態は左右対称に例示したが、トンネル内構造1〜3の片側をそれぞれ組み合わせて非対称の構造を築造してもよい。また、トンネル内構造は、上述した技術的思想に基づいて、4連以上の複数のカルバートを用いて築造されてもよい。   Although several embodiments of the present invention have been described, these embodiments are presented by way of example and are not intended to limit the scope of the invention. These embodiments can be implemented in various other forms, and various omissions, replacements, and changes can be made without departing from the spirit of the invention. These embodiments and their modifications are included in the scope and gist of the invention, and are also included in the invention described in the claims and the equivalents thereof. For example, although the said embodiment illustrated left-right symmetrically, you may build an asymmetrical structure combining each one side of the tunnel inner structures 1-3. Further, the tunnel internal structure may be constructed using a plurality of culverts of four or more based on the above technical idea.

1,2,3…トンネル内構造、10…シールドトンネル、11…内壁、12…セグメント、20,20A,20B,20C…ボックスカルバート、20U…U型カルバート、21…底板、21a…底面、21b…一端、21c…他端、22…側壁部、22a…分割部、22b…対向面、23…側壁部、23a…分割部、24…天板、24a…一端、30…連結部、40…端部構造、41…上面、50…土層、E…床板、G…鋼板ジベル、L…トンネル軸、P…開口部、PA…空間、PB…空間、PC…空間、Q…隙間、R…主鉄筋、R1…端部、T…ジベル鉄筋 1, 2, 3 ... Tunnel internal structure, 10 ... Shield tunnel, 11 ... Inner wall, 12 ... Segment, 20, 20A, 20B, 20C ... Box culvert, 20U ... U-shaped culvert, 21 ... Bottom plate, 21a ... Bottom, 21b ... One end, 21c ... The other end, 22 ... Side wall part, 22a ... Dividing part, 22b ... Opposite surface, 23 ... Side wall part, 23a ... Dividing part, 24 ... Top plate, 24a ... One end, 30 ... Connecting part, 40 ... End part Structure: 41 ... Upper surface, 50 ... Soil layer, E ... Floor plate, G ... Steel plate diver, L ... Tunnel shaft, P ... Opening, PA ... Space, PB ... Space, PC ... Space, Q ... Gap, R ... Main rebar , R1 ... end, T ... Giber rebar

Claims (10)

トンネル内に設置される、底部と前記底部の両側に設けられた一対の側壁部とを有する複数のカルバートを備え、
互いに隣接する二つの前記側壁部のそれぞれは、トンネル断面方向の断面厚さが要求性能厚さより薄く形成され、前記複数のカルバートを前記トンネル断面の水平方向に連続して配置し、互いに隣接する二つの前記側壁部同士を連結した際に連結された断面厚さが前記要求性能厚さ以上となるよう形成されている、
トンネル内構造。
A plurality of culverts having a bottom portion and a pair of side wall portions provided on both sides of the bottom portion, installed in a tunnel;
Each of the two side wall portions adjacent to each other is formed such that a cross-sectional thickness in the tunnel cross-sectional direction is thinner than a required performance thickness, and the plurality of culverts are continuously arranged in the horizontal direction of the tunnel cross-section, The cross-sectional thickness connected when the two side wall portions are connected to each other is formed to be equal to or greater than the required performance thickness.
Tunnel structure.
前記複数のカルバートは、所定の間隔で離間して配置されており、
前記複数のカルバートの間に生じた空間を埋める充填材によって形成された連結部を更に備える、
請求項1に記載のトンネル内構造。
The plurality of culverts are spaced apart at a predetermined interval,
Further comprising a connecting portion formed by a filler filling a space generated between the plurality of culverts,
The tunnel internal structure according to claim 1.
前記連結部は、互いに隣接する二つの前記側壁部の対向面から露出した複数の継手を介して隣接する二つの前記カルバートを連結する、
請求項2に記載のトンネル内構造。
The connecting portion connects the two adjacent culverts through a plurality of joints exposed from opposing surfaces of the two adjacent side wall portions,
The in-tunnel structure according to claim 2.
前記カルバートは、ボックスカルバートである、
請求項1から3のいずれか1項に記載のトンネル内構造。
The culvert is a box culvert,
The in-tunnel structure according to any one of claims 1 to 3.
前記ボックスカルバートは、上下に分割されて形成されている、
請求項4に記載のトンネル内構造。
The box culvert is divided into upper and lower parts,
The in-tunnel structure according to claim 4.
前記カルバートはU型カルバートである、
請求項1から3のいずれか1項に記載のトンネル内構造。
The culvert is a U-shaped culvert,
The in-tunnel structure according to any one of claims 1 to 3.
前記U型カルバートの上部にRC床板が設置される、
請求項6に記載のトンネル内構造。
An RC floor board is installed on top of the U-shaped culvert.
The in-tunnel structure according to claim 6.
前記複数のカルバートは前記トンネル断面方向に連続して配置され、前記複数のカルバートの両側は、流動化処理土によって一対の端部構造が形成される、
請求項1〜7のいずれか1項に記載のトンネル内構造。
The plurality of culverts are continuously arranged in the tunnel cross-sectional direction, and a pair of end structures are formed by fluidized soil on both sides of the plurality of culverts.
The tunnel internal structure according to any one of claims 1 to 7.
前記複数のカルバートは前記トンネル断面方向に連続して配置され、前記複数のカルバートの両側は、端部ブロックが配置される、
請求項1〜7のいずれか1項に記載のトンネル内構造。
The plurality of culverts are arranged continuously in the tunnel cross-sectional direction, and end blocks are arranged on both sides of the plurality of culverts.
The tunnel internal structure according to any one of claims 1 to 7.
底部と前記底部の両側に設けられた一対の側壁部とを有する複数のカルバートをトンネル内に設置するトンネル内構造の築造方法であって、
互いに隣接する二つの前記側壁部のそれぞれは、トンネル断面の水平方向の断面厚さが要求性能厚さより薄く形成されており、
前記複数のカルバートを前記トンネル断面の水平方向に連続して配置し、
互いに隣接する二つの前記側壁部同士を連結し、連結された断面厚さが前記要求性能厚さ以上となるよう形成する、
トンネル内構造の築造方法。
A method for constructing a tunnel internal structure in which a plurality of culverts having a bottom part and a pair of side wall parts provided on both sides of the bottom part are installed in the tunnel,
Each of the two side wall portions adjacent to each other is formed such that the horizontal section thickness of the tunnel section is thinner than the required performance thickness.
The plurality of culverts are continuously arranged in the horizontal direction of the tunnel cross section,
Two adjacent side wall portions are connected to each other, and the connected cross-sectional thickness is equal to or greater than the required performance thickness.
How to build the tunnel structure.
JP2016256782A 2016-12-28 2016-12-28 How to build the structure inside the tunnel and the structure inside the tunnel Active JP6767864B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP2016256782A JP6767864B2 (en) 2016-12-28 2016-12-28 How to build the structure inside the tunnel and the structure inside the tunnel

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP2016256782A JP6767864B2 (en) 2016-12-28 2016-12-28 How to build the structure inside the tunnel and the structure inside the tunnel

Publications (2)

Publication Number Publication Date
JP2018109281A true JP2018109281A (en) 2018-07-12
JP6767864B2 JP6767864B2 (en) 2020-10-14

Family

ID=62844994

Family Applications (1)

Application Number Title Priority Date Filing Date
JP2016256782A Active JP6767864B2 (en) 2016-12-28 2016-12-28 How to build the structure inside the tunnel and the structure inside the tunnel

Country Status (1)

Country Link
JP (1) JP6767864B2 (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN112096425A (en) * 2020-11-20 2020-12-18 北京城建道桥建设集团有限公司 Transverse passage supporting system for position of ingate and construction method thereof
CN112324467A (en) * 2020-12-08 2021-02-05 中铁第四勘察设计院集团有限公司 Model of shield tunnel cast-in-place internal structure and test manufacturing method thereof

Citations (9)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS6221150U (en) * 1985-07-16 1987-02-07
JP2000291036A (en) * 1999-04-08 2000-10-17 Kumagai Gumi Co Ltd Precast shaft
JP2005002612A (en) * 2003-06-10 2005-01-06 Koken Sangyo Kk River crossing structure and its construction method
JP3127563U (en) * 2006-09-25 2006-12-07 興建産業株式会社 Multiple box culvert
JP2008075307A (en) * 2006-09-20 2008-04-03 Taisei Corp Method and equipment for conveying tunnel material
JP2012001899A (en) * 2010-06-14 2012-01-05 Ohbayashi Corp Construction method of tunnel ballast part and tunnel ballast part
JP2012046877A (en) * 2010-08-24 2012-03-08 Kajima Corp Construction apparatus and construction method of tunnel
JP2015028282A (en) * 2013-06-25 2015-02-12 鹿島建設株式会社 Floor slab for shield tunnel, floor slab construction method of shield tunnel and construction method of shield tunnel
CN104564101A (en) * 2015-01-14 2015-04-29 中交第二航务工程局有限公司 Single-tube double-layer tunnel simultaneous construction method

Patent Citations (9)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS6221150U (en) * 1985-07-16 1987-02-07
JP2000291036A (en) * 1999-04-08 2000-10-17 Kumagai Gumi Co Ltd Precast shaft
JP2005002612A (en) * 2003-06-10 2005-01-06 Koken Sangyo Kk River crossing structure and its construction method
JP2008075307A (en) * 2006-09-20 2008-04-03 Taisei Corp Method and equipment for conveying tunnel material
JP3127563U (en) * 2006-09-25 2006-12-07 興建産業株式会社 Multiple box culvert
JP2012001899A (en) * 2010-06-14 2012-01-05 Ohbayashi Corp Construction method of tunnel ballast part and tunnel ballast part
JP2012046877A (en) * 2010-08-24 2012-03-08 Kajima Corp Construction apparatus and construction method of tunnel
JP2015028282A (en) * 2013-06-25 2015-02-12 鹿島建設株式会社 Floor slab for shield tunnel, floor slab construction method of shield tunnel and construction method of shield tunnel
CN104564101A (en) * 2015-01-14 2015-04-29 中交第二航务工程局有限公司 Single-tube double-layer tunnel simultaneous construction method

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN112096425A (en) * 2020-11-20 2020-12-18 北京城建道桥建设集团有限公司 Transverse passage supporting system for position of ingate and construction method thereof
CN112324467A (en) * 2020-12-08 2021-02-05 中铁第四勘察设计院集团有限公司 Model of shield tunnel cast-in-place internal structure and test manufacturing method thereof

Also Published As

Publication number Publication date
JP6767864B2 (en) 2020-10-14

Similar Documents

Publication Publication Date Title
KR100938918B1 (en) Top-down construction method using steel frame by channel
KR101200927B1 (en) Cnnecting structure of precast body and pile and constructing method of the same
KR101161332B1 (en) Construction method of the underground tunnel
KR101851557B1 (en) Arch structure with reinforced arch rib segment and arch structure construction method therefor
US20130008125A1 (en) Construction method for new underground structure
KR20120087418A (en) Concrete Wall having Vertical Connection of Precast Concrete Wall Panel and Constructing Method
JP6767864B2 (en) How to build the structure inside the tunnel and the structure inside the tunnel
JP2018188851A (en) Steel concrete composite structure and construction method of steel concrete composite structure
KR101570938B1 (en) Method for constructing dam using steel pipe pile and precast concrete block
KR101679666B1 (en) Core structure dor modular building and constructio method therefor
KR101324231B1 (en) Soil cement wall structure and method for constructing thereof
RU80171U1 (en) COMBINED-MONOLITHIC PILED BASE
JP5750246B2 (en) Composite beam, building, and composite beam construction method
JP6228836B2 (en) Reverse winding method
KR20090043625A (en) Method for constructing underground slabs using asymmetric girder
JP2017040122A (en) Reinforced concrete column-beam joint precast member
KR20080103260A (en) Reinforcing bar assembly for separate concrete pours and strut system method utilizing the same
JP6766468B2 (en) Segment wall and tunnel lining
JP6445311B2 (en) Box culvert and its construction method
JP2014169551A (en) Block for foundation construction of structure
JP6827294B2 (en) Segment wall and tunnel lining
JP2018168561A (en) Underground structure and method of constructing underground structure
KR20220065461A (en) WIRE STRUCTURE FOR STAGGERED LAPPING IN SLURRY WALL, SLURRY WALL and CONSTRUCTION METHOD FOR THE SAME
KR101058982B1 (en) Middle beam for earth retaining wall using phc pile and construction method of the same
JP6684088B2 (en) Seismic retrofitting structure and method for existing buildings

Legal Events

Date Code Title Description
A521 Request for written amendment filed

Free format text: JAPANESE INTERMEDIATE CODE: A523

Effective date: 20170209

A621 Written request for application examination

Free format text: JAPANESE INTERMEDIATE CODE: A621

Effective date: 20190705

A977 Report on retrieval

Free format text: JAPANESE INTERMEDIATE CODE: A971007

Effective date: 20200630

TRDD Decision of grant or rejection written
A01 Written decision to grant a patent or to grant a registration (utility model)

Free format text: JAPANESE INTERMEDIATE CODE: A01

Effective date: 20200908

A61 First payment of annual fees (during grant procedure)

Free format text: JAPANESE INTERMEDIATE CODE: A61

Effective date: 20200918

R150 Certificate of patent or registration of utility model

Ref document number: 6767864

Country of ref document: JP

Free format text: JAPANESE INTERMEDIATE CODE: R150

S531 Written request for registration of change of domicile

Free format text: JAPANESE INTERMEDIATE CODE: R313531

R350 Written notification of registration of transfer

Free format text: JAPANESE INTERMEDIATE CODE: R350

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250