JP2018105091A - Method of constructing artificial ground on subbasement type road - Google Patents

Method of constructing artificial ground on subbasement type road Download PDF

Info

Publication number
JP2018105091A
JP2018105091A JP2016255735A JP2016255735A JP2018105091A JP 2018105091 A JP2018105091 A JP 2018105091A JP 2016255735 A JP2016255735 A JP 2016255735A JP 2016255735 A JP2016255735 A JP 2016255735A JP 2018105091 A JP2018105091 A JP 2018105091A
Authority
JP
Japan
Prior art keywords
girder
spc
road
steel
steel material
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
JP2016255735A
Other languages
Japanese (ja)
Other versions
JP6166454B1 (en
Inventor
亮平 黒沢
Ryohei Kurosawa
亮平 黒沢
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Kurosawa Construction Co Ltd
Original Assignee
Kurosawa Construction Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Kurosawa Construction Co Ltd filed Critical Kurosawa Construction Co Ltd
Priority to JP2016255735A priority Critical patent/JP6166454B1/en
Application granted granted Critical
Publication of JP6166454B1 publication Critical patent/JP6166454B1/en
Publication of JP2018105091A publication Critical patent/JP2018105091A/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Bridges Or Land Bridges (AREA)

Abstract

PROBLEM TO BE SOLVED: To construct an artificial ground on a subbasement type road at low cost without completely cutting off traffic in service.SOLUTION: A span length of a SPC girder 3 which is designed as a simple girder with a distance L of earth retaining walls 2a, 2b on both the sides of a subbasement type road as the span length and in which a steel frame material is disposed on the compressed side is shorter than l/2; a connecting steel frame 32 projecting from the end surface and a sheath 34 passing a connecting PC steel material therethrough are provided at the tip end of the SPC girder 3. The SPC girder 3 is stretched from the earth retaining walls 2a, 2b to a temporary pad 15 provided at the center of the road. The connecting steel frames 32 are connected to each other; concrete is pored and cured in the connecting part; the connecting PC steel material is inserted into the sheath 34 to introduce prestress to make them integrally connected. The temporary pad 15 is removed, so that the simple girder is formed between the earth retaining walls 2a, 2b. A number of the SPC girders 3 are constructed on the road to construct an artificial ground 10 on the subbasement type road.SELECTED DRAWING: Figure 2

Description

本発明は、半地下型道路の上部に交通を全面的に通行止めにすることなく人工地盤を構築する方法及びそれに使用する圧縮側に鉄骨鋼材を配設したプレキャストコンクリート桁に関する。   The present invention relates to a method for constructing an artificial ground without completely blocking traffic on an upper part of a semi-underground road and a precast concrete girder provided with a steel material on the compression side used for the method.

大都市の自動車交通を担う高速道路は用地難の関係から既存の道路上に高架道路を構築するか、堀の水を抜いて半地下型道路を構築することで都市交通の近代化を図ってきた。
しかし、半地下型道路の土留擁壁が長年月を経過して老朽化が進み、コンクリートの剥離や鉄筋の腐食が顕著となってきている。また、建設当時の設計基準は震度7の直下型地震を想定しておらず、地震の襲来でライフラインである高速道路が損傷を受ける可能性が大であり、損傷を受けた場合の物流に対する影響は多大なものとなり、経済や市民生活に大打撃を与えることは必至であることから早急に擁壁を改修することが喫緊の課題である。
Expressways that carry automobile traffic in large cities have been trying to modernize urban traffic by constructing elevated roads on existing roads due to site difficulties, or by constructing semi-underground roads by removing the moat water It was.
However, the retaining wall of the semi-underground road has deteriorated over the years, and the peeling of concrete and the corrosion of reinforcing bars have become remarkable. In addition, the design standards at the time of construction do not assume a direct earthquake with a seismic intensity of 7, and there is a high possibility that the expressway that is the lifeline will be damaged by the earthquake. The impact will be enormous, and it is inevitable that the economy and civic life will be severely affected.

都市における半地下型道路の逆T型の土留擁壁の老朽化と設計強度が低い時代のものであることから改修が必要となってきている。この改修工事に合わせて道路の幅員の拡幅及び道路の上空を有効利用するために道路の上に人工地盤を構築することが検討されている。
半地下型道路の上への人工地盤の構築にあたっては、道路両側の擁壁の間に桁を掛け渡すことが必要であるが、都市交通の停滞や停止は経済活動への影響が多大であり、改修工事などにおいても全面通行止めは許されるものでなく、少なくとも上下一車線の確保が必要である。また、工事中に落橋などの事故を起こすと人命にかかわることがあり、このようなことはあってはならないので安全確実に施工できる工法でなければならない。
更に、自動車の運転者の視界を妨げることなく安全に運転することができるように、道路上空の使用高さが制限されるので道路を横断する桁の高さをできるだけ低くすることが要求される。
Renovation is necessary because the reverse T-type retaining wall of semi-underground roads in the city is old and the design strength is low. In order to effectively widen the width of the road and to use the sky above the road in accordance with this renovation work, it is considered to construct an artificial ground on the road.
In constructing artificial ground on a semi-underground road, it is necessary to bridge girders between retaining walls on both sides of the road, but the stagnation and stoppage of urban traffic has a great impact on economic activities. In renovation work, etc., no full closure is permitted, and it is necessary to secure at least one upper and lower lane. Also, if an accident such as a fallen bridge occurs during construction, it can be fatal, and this should not be the case, so it must be a construction method that allows safe and reliable construction.
Furthermore, since the usage height over the road is limited so that it can be safely driven without obstructing the visibility of the driver of the car, it is required to make the height of the girder crossing the road as low as possible. .

人工地盤構築のために桁を掛け渡す対象である既存の半地下型道路の擁壁間の距離である支間長(スパン)は、対向4車線で40〜50m程度のものであり、この程度のスパンに対しては、本願発明者が開発した特許文献1、2に開示されているプレキャストコンクリートの桁断面の圧縮側に鉄骨鋼材を圧縮鋼材として配設して大きなプレストレスの導入を可能にして桁高を低くすると共に桁の自重を軽量化して下部構造への負担を軽減することができる構造の桁(以下、SPC桁という)がコスト及び短期間で施工することができることから適切であると考えられる。   The span length (span), which is the distance between retaining walls of existing semi-underground roads that are used to construct girders for the construction of artificial ground, is about 40-50m in the opposite four lanes. For the span, a steel frame steel material is arranged as a compression steel material on the compression side of the cross section of the precast concrete disclosed in Patent Documents 1 and 2 developed by the inventors of the present application, so that a large prestress can be introduced. A girder with a structure that can lower the girder height and reduce the weight of the girder by reducing the weight of the girder (hereinafter referred to as an SPC girder) is suitable because it can be constructed in a short period of time. Conceivable.

特許第3703760号公報Japanese Patent No. 3703760 特許第5706566号公報Japanese Patent No. 5706656

半地下型道路の上に道路交通を完全に止めることなく人工地盤を構築するには、片側一車線の交通を確保してその他を通行止めにして作業帯Wを確保して施工するのが安全工事を遂行するためには最も合理的と考えられる。従って、擁壁の間の中間部に支保工やサポートなどの仮受台を設け、擁壁から仮受台まで片側ずつPC桁を架設し、中央部の仮受台において桁同士を連結して一体化することが必要となる。
しかしながら、擁壁間を支間長(スパン)とする単純桁として設計された特許文献1、2に示された鉄骨鋼材を圧縮鋼材として配置したプレキャストコンクリート桁(SPC桁)を二分割して半分ずつ両擁壁から仮受台の間に架設し、桁の中央部で連結して一体化した後、仮受台を取り外して擁壁の間の全支間に掛け渡された単純桁とすることになるが、応力が最大となる桁の中央断面で切断して連結部を設けることは、最も多く与えてある中央断面のプレストレスが喪失されることになるので土留擁壁間を支間長(スパン)とした単純桁の設計断面では負荷に耐えることができなくなり、従って断面を大きくしなければならず、桁高を低くすると共に桁の自重を軽量化して下部構造への負担を軽減するというSPC桁の長所を十分活用することができないものとなる。
In order to build an artificial ground on a semi-underground road without completely stopping the road traffic, it is a safety work to secure the work zone W by securing one-lane traffic on one side and blocking other traffic It is considered the most reasonable to carry out. Therefore, a temporary support base such as a support or support is provided in the middle part between the retaining walls, and PC girders are installed one side at a time from the retaining wall to the temporary support base. It is necessary to integrate them.
However, a precast concrete girder (SPC girder) in which steel frame steel materials shown in Patent Documents 1 and 2 designed as simple girders with a retaining wall length (span) as a compressed steel material is divided into two halves. After laying between the retaining walls between the retaining walls and connecting and integrating them at the center of the girder, the temporary retaining base is removed to form a simple girder spanned between all the retaining walls. However, cutting the central section of the beam where the stress is maximum and cutting the connection section will lose the prestress of the central section that is most often applied. The design cross-section of the simple girder that can not withstand the load, and therefore the cross-section must be enlarged, and the SPC that lowers the girder height and lightens the girder's own weight to reduce the burden on the lower structure. Take full advantage of girder strength The ones that can not be bet.

本発明は、以上の課題をクリアしつつ、低コストで半地下型道路の上に人工地盤を構築できるようにするものであり、供用中の道路交通を完全に遮断することなく、少なくとも上下一車線の対面交通を許容しながら幅員40〜50m程度の半地下型道路上に桁を掛け渡して人工地盤を構築するにあたり、幅員を支間長(スパン)とする単純桁として設計されたSPC桁の桁高を増大させることなくそのままの桁高で分割施工することを可能とするものである。   The present invention makes it possible to construct an artificial ground on a semi-underground road at a low cost while clearing the above-described problems, and at least one up and down without completely blocking the road traffic in service. SPC girder designed as a simple girder with span as the span length (span) when constructing artificial ground by spanning a girder on a semi-underground road with a width of around 40-50m while allowing lane facing traffic This makes it possible to divide and work with the same girder height without increasing the girder height.

両脇に擁壁を有する半地下型道路の上に人工地盤を構築する方法であって、圧縮側に鉄骨鋼材を配設したプレキャストコンクリートPC桁(SPC桁)を擁壁間の距離(L)を支間長とする単純桁として断面を設計し、この断面であって桁長が支間長の半分(L/2)未満のSPC桁であって、先端部に先端面から突出する連結用鉄骨と連結PC鋼材用シースが設けてあり、少なくとも上下各一車線の通行帯を確保してその他を通行止めとして作業帯を確保し、SPC桁を一方の土留擁壁から道路の中央に設置した仮受台の間に掛け渡し、通行止めの車線を切り替えて作業帯を変更して他方の土留擁壁からもSPC桁を仮受台に掛け渡して対向配置し、SPC桁の先端部から突出した連結用鉄骨同士を連結すると共に、前記連結PC鋼材挿入用シースに連結PC鋼材を挿入配設し、対向配置したSPC桁の間にコンクリートを打設して硬化させ、連結PC鋼材を緊張定着してプレストレスを付与して連結用鉄骨と連結PC鋼材を含む複合構造連結部を形成することによってSPC桁を連結一体化して支間長をLとする擁壁間のSPC単純桁を形成した後に、仮受台を撤去することを特徴とする半地下型道路の上に人工地盤を構築する方法である。
また、前記複合連結部を形成してSPC桁を連結一体化して支間長がLである擁壁間のSPC桁を形成した後、SPC桁の両端部をPC鋼材による緊張力で土留擁壁に剛結し、その後に前記仮受台を撤去する半地下型道路上に人工地盤を構築する方法である。
This is a method of constructing artificial ground on a semi-underground road with retaining walls on both sides. Precast concrete PC girders (SPC girders) with steel frames on the compression side are distances between retaining walls (L) The cross section is designed as a simple girder having a span length as a span girder, and this section is an SPC girder having a girder length less than half the span length (L / 2), and a connecting steel frame projecting from the front end surface to the front end portion; Temporary cradle with a sheath for connecting PC steel, securing at least one lane in the upper and lower lanes, securing a work zone as the other traffic stop, and installing the SPC girder from one retaining wall to the center of the road Bridge between the doors, change the working lane by switching the traffic lane, change the work zone, and place the SPC girder from the other retaining wall to the temporary receiving stand so as to face each other, and the connecting steel frame protruding from the tip of the SPC girder For connecting together and for connecting PC steel materials Connected PC steel material is inserted and disposed in the base, and concrete is placed between the SPC girders facing each other and hardened, and the connected PC steel material is tension-fixed and prestressed to provide the connection steel frame and the connected PC steel material. A semi-underground type characterized in that after the SPC simple girder between the retaining walls with the span length L is formed by forming the composite structure connecting portion including the SPC girder, the temporary support is removed. It is a method of constructing artificial ground on the road.
In addition, after forming the composite connecting portion and connecting and integrating the SPC girders to form the SPC girders between the retaining walls whose span length is L, both ends of the SPC girders are made into the retaining wall with tension by the PC steel material. This is a method of constructing an artificial ground on a semi-underground road that is rigidly connected and then removes the temporary cradle.

本発明の効果を以下に列挙する。
(1)単純桁として設計した支間長に適用するPC桁を二分割して、支間中央部に仮受台を設けて半分ずつ桁を架設して連結一体化することによって、少なくとも片側一車線の交通を確保することができ、安全に施工できることから、通行止めによる物流を停滞させないので経済に打撃を与えることがない。
(2)単純桁として支間長(スパン)に適用するPC桁を二分割して、桁の中央部に鉄骨連結とPC鋼材連結とからなる複合構造連結部を形成して一体化にすることによって、施工中に支間中央部のみに仮受台(支保工やサポート)を設けるだけで済み、単純桁として設計されたSPC桁は、桁高を低く抑えることができ、桁の自重が軽量であるので下部構造への負担を軽減することができ、経済的に人工地盤を構築することができる。
(3)複合構造連結部に貫通する連結PC鋼材が支間長の約1/3まで配置されることによって、予め分割部材に配置されたPC鋼材(プレテンション方式PC鋼材及びポストテンション方式PC鋼材)と充分な長さでラップされている状態になり、桁の中央断面にプレストレスがスムーズに伝達されて付与されているので、中央の複合構造連結部が強固な構造体となり、巨大地震にも耐えることができ、桁が道路面に落下して通行中の自動車を破壊して損害を与えたり、道路を閉塞したりして地震の被害の復旧活動を阻害することなく交通路として使用することが可能である。
(4)中央の複合構造連結部において、桁高を高くするふかしを設けることによって断面を拡大し、連結部に大きな連結用鉄骨部材の配置や連結PC鋼材を多く配置できるようにしたので連結部と共に桁全体の構造耐力が大幅に増加され、人工地盤の上に種々の建造物の構築に対応可能となり、都市の多様性が図れることになる。
(5)桁の両端を擁壁にPC鋼材で剛結することによってSPC桁は荷重による全曲げモーメントの一部を桁端が負担することになり、中央断面が負担する曲げモーメントを軽減させることができるので中央の連結鋼材としての鉄骨若しくはPC鋼材を減らすことができ、桁高を増大させることなく連結鋼材や連結用PC鋼材を配置するスペースを確保することができる。
(6)従来、PC単純桁橋の支間長(スパン)は、30〜40mが限界とされ、桁高スパン比は1/17.5が限界とされていたが、本願発明者が開発した(桁中央に連結部を設けない)SPC桁によって、支間長(スパン)を50〜70mまで拡大可能とし、桁高スパン比の限界を1/30に引き上げた(特許文献2:特許第5706566号公報の段落0003及び段落0012、0013参照)。
本発明は、桁中央に複合構造連結部を設けて分割した部材を連結一体化することによってSPC桁の特徴(利点)を保ちながら、支間長(スパン)を40〜50mの単純桁橋に適用すると共に、桁高スパン比を1/22〜1/30程度で桁高を低いものとすることを半地下型道路の上部に施工することを可能にした。
The effects of the present invention are listed below.
(1) By dividing the PC girder applied to the span length designed as a simple girder into two parts, providing a temporary cradle in the middle part of the span and linking the girder in half and connecting and integrating at least one side lane Since traffic can be secured and construction can be performed safely, the logistics due to closed roads will not be stagnated, so there will be no impact on the economy.
(2) By dividing the PC girder applied to the span length (span) as a simple girder in two and forming a composite structure coupling part consisting of steel frame coupling and PC steel material coupling at the center part of the girder and integrating them During construction, it is only necessary to provide a temporary stand (support work or support) at the center of the span. The SPC girder designed as a simple girder can keep the girder height low and the weight of the girder is lightweight. Therefore, the burden on the lower structure can be reduced, and the artificial ground can be constructed economically.
(3) PC steel material (pre-tension type PC steel material and post-tension type PC steel material) that is arranged in advance in the split member by connecting PC steel material penetrating through the composite structure connection part to about 1/3 of the span length Since the pre-stress is smoothly transmitted to the central section of the girder and applied to it, the central composite structure connection part becomes a strong structure, and even in the event of a huge earthquake Can be used as a roadway without damaging the damaged car by dropping the girder on the road surface and damaging it, or blocking the road and obstructing earthquake damage recovery activities Is possible.
(4) In the central composite structure connection part, the cross-section is enlarged by providing a puff that increases the girder height, so that it is possible to arrange a large number of connecting steel members and many connected PC steel materials in the connection part. At the same time, the structural strength of the whole girder will be greatly increased, and it will be possible to construct various buildings on the artificial ground, thereby achieving urban diversity.
(5) By connecting both ends of the girder to the retaining wall with PC steel, the SPC girder will bear a part of the total bending moment due to the load, and the bending end will be reduced by the central section. Therefore, it is possible to reduce the steel frame or PC steel material as the central connecting steel material, and to secure a space for arranging the connecting steel material or the connecting PC steel material without increasing the beam height.
(6) Conventionally, the span length (span) of PC simple girder bridges was limited to 30-40m, and the girder height span ratio was limited to 1 / 17.5. The span length (span) can be expanded to 50-70 m by using an SPC girder (no connection part is provided at the center of the girder), and the limit of the girder height span ratio is increased to 1/30 (Patent Document 2: Japanese Patent No. 5706656) Paragraph 0003 and paragraphs 0012 and 0013).
The present invention is applied to a simple girder bridge having a span length (span) of 40 to 50 m while maintaining the characteristics (advantages) of the SPC girder by connecting and integrating the divided members by providing a composite structure coupling portion in the center of the girder. At the same time, it was made possible to construct the upper part of the semi-underground road with a girder height span ratio of about 1/22 to 1/30 and a lower girder height.

SPC桁の(1)平面図、(2)正面図、(3)左右両端面図と中間部の断面図。(1) Plan view, (2) Front view, (3) Left and right end views and a cross-sectional view of an intermediate portion of an SPC girder. 本発明の施工工程図。The construction process figure of this invention. 複合構造連結部の形成過程の拡大説明図。Explanatory explanatory drawing of the formation process of a composite structure connection part. 連結部の上縁を拡大して桁高を拡大したSPC桁の(1)平面図、(2)正面図、(3)左右両端面図と中間部の断面図。(1) Plan view, (2) Front view, (3) Left and right end views and a cross-sectional view of the middle part of an SPC girder in which the upper edge of the connecting part is enlarged to enlarge the girder height. 連結部の上縁を拡大して桁高を拡大したSPC桁による施工工程図。The construction process figure by the SPC girder which expanded the girder height by enlarging the upper edge of a connection part. 連結部の上縁を拡大して桁高を拡大したSPC桁による複合構造連結部の形成過程の拡大説明図。The expansion explanatory drawing of the formation process of the composite structure connection part by the SPC girder which expanded the upper edge of the connection part and expanded the girder height. 連結部の下縁を拡大して桁高を拡大したSPC桁による施工工程図。The construction process figure by the SPC girder which expanded the lower edge of the connection part and expanded girder height. 連結部の下縁を拡大して桁高を拡大したSPC桁による複合構造連結部の形成過程の拡大説明図。The expansion explanatory drawing of the formation process of the composite structure connection part by the SPC girder which expanded the lower edge of the connection part and expanded the digit height. 連結部における連結PC鋼材を延長させてSPC桁の上縁に定着する施工工程図。The construction process figure which extends the connection PC steel material in a connection part, and fixes it to the upper edge of a SPC girder. 連結部における連結PC鋼材を延長させてSPC桁の上縁に定着する複合構造連結部の形成過程の拡大説明図。The expansion explanatory drawing of the formation process of the composite structure connection part which extends the connection PC steel material in a connection part, and fixes to the upper edge of a SPC girder. 連結部における連結PC鋼材を延長させてSPC桁の下縁に定着する施工工程図。The construction process figure which extends the connection PC steel material in a connection part, and fixes it to the lower edge of a SPC girder. 連結部における連結PC鋼材を延長させてSPC桁の下縁に定着する複合構造連結部の形成過程の拡大説明図。The expansion explanatory drawing of the formation process of the composite structure connection part which extends the connection PC steel material in a connection part, and fixes to the lower edge of a SPC girder. 擁壁側の桁端支点部における緊張鋼材を延長させてSPC桁に定着する施工工程図。The construction process figure which extends the tension steel material in the girder edge fulcrum part on the retaining wall side, and fixes it to a SPC girder. 連結部の桁の端部の下縁を延長したSPC桁による複合構造連結部の形成過程の拡大説明図。The expansion explanatory drawing of the formation process of the composite structure connection part by the SPC girder which extended the lower edge of the edge part of the connection part girder. 桁の支持点となる土留擁壁に緊張鋼材を配設しておき、桁と土留擁壁を剛結する構造の説明図。Explanatory drawing of the structure which arrange | positions tension steel materials in the retaining wall used as a supporting point of a girder, and connects a girder and the retaining wall rigidly. 桁の曲げモーメント分布図。Figure of bending moment distribution of girder. 道路上に作業帯を確保する方法説明図。Explanatory drawing of how to secure a work zone on the road. 半地下型道路の上に構築した人工地盤の道路に沿った断面図。Sectional drawing along the road of the artificial ground built on the semi-underground type road.

本発明を図面に基づいて詳しく以下に説明する。
本発明においては、人工地盤を構築する場所が半地下型道路の上であるという特殊性から、道路上に完成した人工地盤が運転者には覆い被さってトンネルのように見えて圧迫感を与えるので人工地盤となる桁の高さを可能な限り低くする必要がある。
SPC桁(圧縮側に鋼材を配設したプレストレストプレキャストコンクリート桁)は、桁断面の圧縮側に鉄骨鋼材を配置することによって見掛け上のコンクリート断面積を増大させて導入プレストレス量を増やすことができるものであり、桁の高さを通常のプレストレストコンクリート桁より低くすることができる特徴を有している。
The present invention will be described in detail below with reference to the drawings.
In the present invention, because the place where the artificial ground is constructed is on a semi-underground road, the artificial ground completed on the road covers the driver and looks like a tunnel, giving a feeling of pressure. Therefore, it is necessary to make the height of the girder used as artificial ground as low as possible.
SPC girders (prestressed precast concrete girders with steel on the compression side) can increase the pre-stress amount by increasing the apparent concrete cross-sectional area by placing steel on the compression side of the girders cross section. It has the characteristic that the height of a girder can be made lower than a normal prestressed concrete girder.

図1は、本発明の人工地盤の構築に使用するSPC桁の一例を示すものであり、半地下型道路の上に掛け渡す桁の半分を示すものであって、SPC桁を製作する工場から建設現場までの運搬を考慮して3つのユニット3U、3U、3Uに分割したものであり、(1)平面図、(2)正面図及び(3)左右両端面図と中間部の断面図である。ユニット同士の連結部となる端面3Mは、断面四角形としてあり、各ユニットをPC鋼材を用いてポストテンション方式で圧着連結して一体化したSPC桁3a、3bである。
なお、各ユニットは、PC鋼材を配置してプレテンション方式でプレストレスを付与してあり、プレテンション方式PC鋼材35がSPC桁の構造耐力の一部となり、その後に配置するポストテンション方式PC鋼材35aの量を減らすことができる。
このSPC桁は、図1(3)のb−b断面に示すようにI型断面であり、圧縮側のフランジに圧縮鋼材とする鉄骨鋼材31を配設してある。図示の例の鉄骨鋼材31はL形の鉄骨組立材を対向させて桁の長手方向に渡って配設してある。桁ユニット3Uの端部の土留擁壁に載置する基部(端支点拡幅部)3Eは直方体としてあり、この部分を土留擁壁2に載せて設置する。
先頭側の桁ユニット3Uの端部3Tは、もう一方の対向する土留擁壁から道路中央に向かって設置されるSPC桁と道路の中央部で連結されて一体化される連結部であり、桁ユニット3Uの基部3Eと同様に直方体としてあり、連結用鉄骨32としてH形鋼が桁ユニット3Uの端面から他方の桁との接続に必要な長さを突出させてあり、桁内部側には一定長さ埋設されて桁ユニット3Uに定着してある。
FIG. 1 shows an example of an SPC girder used for constructing an artificial ground according to the present invention, showing half of the girder over a semi-underground road, from a factory that manufactures the SPC girder. It is divided into three units 3U 1 , 3U 2 , 3U 3 in consideration of transportation to the construction site. (1) Plan view, (2) Front view, and (3) Left and right end views and middle part It is sectional drawing. The end surface 3M that is a connecting portion between the units has a quadrangular cross section, and is an SPC girder 3a, 3b in which each unit is integrally joined by pressure bonding using a PC steel material by a post tension method.
Each unit is pre-stressed with PC steel placed and pre-stressed, and the pre-tensioned PC steel 35 becomes a part of the structural strength of the SPC girder and is placed after that. The amount of 35a can be reduced.
This SPC girder has an I-shaped cross section as shown in the bb cross section of FIG. 1 (3), and a steel steel material 31 as a compressed steel material is disposed on the compression side flange. The steel steel material 31 in the illustrated example is arranged over the longitudinal direction of the girder with the L-shaped steel assembly material facing each other. A base (end fulcrum widening portion) 3E placed on the earth retaining wall at the end of the girder unit 3U 1 is a rectangular parallelepiped, and this part is placed on the earth retaining wall 2 for installation.
End of the leading side girder unit 3U 3 3T is a connecting portion that is integrally coupled from the other opposing earth retaining retaining wall at the center of the SPC digits and road installed toward the center of the road, Like the base 3E of the girder unit 3U 1 , it is a rectangular parallelepiped, and the H-shaped steel as the connecting steel frame 32 projects the length necessary for connection with the other girder from the end surface of the girder unit 3U 3 , are fixed on the spar unit 3U 1 is embedded a predetermined length in the.

図2に示すように、前記のユニット同士をポストテンション方式PC鋼材35a(図示せず)で圧着連結して一体化したSPC桁3aと3bを半地下型道路1の両側に設けてある土留擁壁2a、2bと道路の中央に設置した仮受台15に順次に架設し、仮受台15の上で連結一体化して土留擁壁の間にSPC単純桁として掛け渡して人工地盤10を構築するものである。
交通を全面的に遮断することなく人工地盤を構築することが必須であり、走行中の自動車に損傷を与えるなど、人命を損なうことは絶対に避けなければならず、一方の土留擁壁2aから対向する土留擁壁2bの間の道路中央部に支保工やサポートなどの仮受台15を設置し、上下車線の一方を通行止めにして作業帯Wを形成し、他方の車線を通行帯Tとして上下対向走行させることによって走行中の自動車を巻き込む工事に起因する事故が起きないようにしている。
As shown in FIG. 2, the SPC girders 3a and 3b, in which the above units are connected to each other by a post-tension type PC steel material 35a (not shown) and integrated, are provided on both sides of the semi-underground road 1. The artificial ground 10 is constructed by sequentially laying it on the walls 2a and 2b and the temporary support 15 installed in the center of the road, and connecting and integrating on the temporary support 15 as an SPC simple girder between the retaining walls. To do.
It is indispensable to construct an artificial ground without blocking traffic completely, and it is absolutely necessary to avoid damaging human lives, such as damaging a running car, from one retaining wall 2a. A temporary pedestal 15 such as a support or support is installed in the center of the road between the opposing retaining walls 2b, and a work zone W is formed by blocking one of the upper and lower lanes. By causing the vehicle to run vertically opposite, accidents caused by construction involving a running car are prevented.

図2は人工地盤構築過程の全体説明図であり、図3はSPC桁3a、3bの連結部の拡大図であり、図2と図3の工程を示す番号は同じ手順の状態を示しており、両図に基づいて構築過程を説明する。
図2(1)に示すように、土留擁壁2aと2bを桁3の支点とし、擁壁間の距離(L)を支間長とする単純桁とした断面で設計されたSPC桁を略半分の長さ(L/2)にしたSPC桁3aを運搬可能な長さで3つのユニットに分割し、ポストテンション方式PC鋼材35a(図示せず)で圧着連結して一体化し、一方の土留擁壁2aと中間の仮受台15に適宜の工法、例えば架設桁による送り出し工法によって架設する。
ここで、図2(2)に示すように、それまで自動車を走行させる通行帯Tとしていた車線を通行止めにし、作業帯Wとしていた車線を開放して通行帯Tに切り替える。反対側の土留擁壁2bから中間の仮受台15に向かってSPC桁3bを送り出して仮受台15にSPC桁3bの先頭部を載せて支持し、両土留擁壁2a、2bから送り出してSPC桁3a、3bの先頭部から突出している連結用鉄骨32、32を突き合わせ状態とする。
図2(3)に示すように、連結用鉄骨32に添接板を設置してSPC桁3aと桁3bを連結して一体化し、連結部の周囲を型枠で囲ってコンクリートまたは無収縮モルタル33を打設し、固結後にSPC桁3a、3bの先頭部に設けた連結PC鋼材用シース34にPC鋼材を挿入して緊張定着することによって複合構造連結部36を形成し、二つのSPC桁3a、3bを強固に連結一体化する。
図2(4)に示すように中央の仮受台15を撤去すると、土留擁壁2a、2bの間に支間長(L)に適用するように設計された単純桁の桁高のSPC桁3が掛け渡された状態となる。桁3の上に床版4を形成することによって人工地盤10が完成するので、人工地盤の付属構造物、例えば地覆、高欄などを構築する。
また、図示は省略するが、SPC桁3aと3bの先端部から予め鉄筋を突出させておき、連結部に鉄筋を配置して突出した鉄筋を繋ぐこととし、鉄骨、PC鋼材及び鉄筋による複合構造連結部36とすることもできる。
FIG. 2 is an overall explanatory diagram of the artificial ground construction process, FIG. 3 is an enlarged view of the connecting portion of the SPC girders 3a and 3b, and the numbers indicating the steps in FIGS. 2 and 3 indicate the state of the same procedure. The construction process will be described with reference to both figures.
As shown in FIG. 2 (1), the SPC girder designed with a simple girder having the retaining wall 2a and 2b as the fulcrum of the girder 3 and the distance (L) between the retaining walls as the span length is substantially half. The SPC girder 3a having a length of L / 2 is divided into three units with a length that can be transported and integrated by crimping and connecting with a post-tension type PC steel material 35a (not shown). It is installed on the wall 2a and the intermediate cradle 15 by an appropriate construction method, for example, a delivery method using a construction girder.
Here, as shown in FIG. 2 (2), the lane that has been the traffic zone T until which the vehicle is traveling is blocked, the lane that has been the work zone W is opened, and the traffic zone T is switched to. The SPC girder 3b is sent out from the opposite retaining wall 2b toward the intermediate temporary receiving table 15, and the leading portion of the SPC beam 3b is placed on and supported by the temporary receiving table 15, and sent out from both the retaining walls 2a and 2b. The connecting steel frames 32 and 32 projecting from the leading portions of the SPC girders 3a and 3b are brought into a butted state.
As shown in FIG. 2 (3), a connecting plate is installed on the connecting steel frame 32, the SPC girder 3a and the girder 3b are connected and integrated, and the periphery of the connecting portion is surrounded by a formwork to form concrete or non-shrink mortar. 33, and after consolidation, a PC structure is inserted into a connection PC steel sheath 34 provided at the top of the SPC girders 3a and 3b to fix the tension, thereby forming a composite structure connection section 36. The beams 3a and 3b are firmly connected and integrated.
When the central cradle 15 is removed as shown in FIG. 2 (4), the SPC girder 3 with a simple girder height designed to be applied to the span length (L) between the retaining walls 2a, 2b. Will be in a state of being overlaid. Since the artificial ground 10 is completed by forming the floor slab 4 on the girders 3, an auxiliary structure of the artificial ground, for example, a ground cover, a railing, etc. is constructed.
Although not shown in the figure, a reinforcing bar is projected from the tip of the SPC girders 3a and 3b in advance, the reinforcing bar is arranged at the connecting part, and the protruding reinforcing bar is connected, and a composite structure including a steel frame, PC steel, and reinforcing bar The connecting portion 36 can also be used.

図4は、人工地盤構築に使用するSPC桁の他の例であり、桁の連結部端部の上縁を上方向に拡大して拡大部(ふかし)3Hを設けたものであり、この拡大部3Hに連結PC鋼材34aを挿通するシース34Sが設置してある。両方のSPC桁3a、3bの拡大部(ふかし)3Hに設けたシース34Sに連結PC鋼材34aを挿通して緊張定着することによってSPC桁3a、3bを強固に連結する複合構造連結部36を形成したものである。
拡大部3Hを設けたことによって桁断面が拡大され、複合構造連結部36に比較的大きな断面の鉄骨部材を配置することができ、また、連結用のPC鋼材を多く配置できるようになり、桁全体の構造耐力を増大することができるので完成した人工地盤上に大荷重の建造物が構築可能となるので人工地盤の用途が拡大される。
図5及び図6は、図4に示した端部に拡大部3Hを設けたSPC桁を用いた場合の梁を掛け渡す工程と複合連結構造36の施工過程を図2、図3と同様に示すものであり、いずれの工程も図2、図3と同じであり、接続端部に拡大部(ふかし)3Hが設けてあることが異なる点である。
図7及び図8に示す例は、桁端部の拡大部(ふかし)3HをSPC桁の下縁に形成したものであり、図5、図6の例とは上下を逆にしたものである。
FIG. 4 shows another example of an SPC girder used for construction of artificial ground, in which the upper edge of the end of the connecting part of the girder is enlarged upward to provide an enlarged part 3F. A sheath 34 </ b> S for inserting the connected PC steel material 34 a is installed in the portion 3 </ b> H. A composite structure connecting portion 36 that firmly connects the SPC girders 3a and 3b is formed by inserting the connecting PC steel material 34a into the sheath 34S provided in the enlarged portions (flicks) 3H of both SPC girders 3a and 3b and fixing the tension. It is a thing.
By providing the enlarged portion 3H, the cross section of the girder is enlarged, and a steel member having a relatively large cross section can be arranged in the composite structure coupling portion 36, and more PC steel materials for coupling can be arranged. Since the overall structural strength can be increased, it is possible to construct a heavy-load building on the completed artificial ground, so that the use of the artificial ground is expanded.
5 and FIG. 6 show the process of passing the beam and the construction process of the composite connection structure 36 in the case of using the SPC girder having the enlarged portion 3H provided at the end shown in FIG. These steps are the same as those shown in FIGS. 2 and 3, except that an enlarged portion 3H is provided at the connection end.
In the example shown in FIG. 7 and FIG. 8, an enlarged portion (splash) 3H at the end of the girder is formed at the lower edge of the SPC girder, and is upside down from the example of FIGS. .

図9及び図10に示す例は、連結PC鋼材34としてPCケーブルを複合構造連結部36から桁の支点方向に比較的長い距離を延長させたものであり、図示の例はSPC桁連結部の次のユニットの桁の上縁に突出させた延長定着部5に緊張定着したものである。
この場合、桁中央部の連結部における連結PC鋼材の緊張定着作業には、道路中央部の車線を通行止めにして作業帯Wを設け、左右の土留擁壁2a、2b側の車線を通行帯Tとして通行帯Tの上では作業をしないようにする。作業帯Wと通行帯Tの切り替えの平面図を図17に示す。
なお、延長定着部5は、図11及び図12に示すようにSPC桁3の下縁側に突出させたものであっても構わない。
In the example shown in FIG. 9 and FIG. 10, a PC cable is extended as a connecting PC steel material 34 by a relatively long distance from the composite structure connecting portion 36 in the direction of the fulcrum of the girder. The tension is fixed to the extension fixing portion 5 that protrudes from the upper edge of the next unit girder.
In this case, for the tension fixing work of the connected PC steel material at the connecting part in the center part of the girder, the work zone W is provided by blocking the lane in the center part of the road, and the lane in the lane on the left and right retaining wall 2a, 2b side Do not work on the lane T. A plan view of switching between the work zone W and the traffic zone T is shown in FIG.
The extension fixing unit 5 may be protruded to the lower edge side of the SPC beam 3 as shown in FIGS. 11 and 12.

また、図13に示すように延長定着部5を桁の上縁または下縁から突出させることなくユニットの接続部の端面に延長定着部5を設けて連結PC鋼材を定着してもよい。
以上の図示例、特に図9〜図13に示した複合構造連結部36に配設される連結PC鋼材34(2次PC鋼材)は、分割部材であるユニットに予め配置されている1次PC鋼材(プレテンション方式PC鋼材35とポストテンション方式PC鋼材35a)と十分な長さのラップ部分を有するものであるので桁の中央断面において十分なプレストレスが付与されることになり、中央断面に生じる大きな曲げ応力を2次PC鋼材と1次PC鋼材とで共同負担して桁両端の支点に伝達することになる。
また、本発明においては、片側一車線の通行帯Tを確保してその他の車線を通行止めにして作業帯Wを確保して施工するという原則を守る必要があるが、1次PC鋼材と2次PC鋼材のラップ長を長くすると、現場作業である2次PC鋼材の両端定着部5の作業が作業帯Wを越えて通行帯Tに入りこむので好ましくない。そして、連結完成後の桁が基本的に単純桁の構造であることを考慮すると、図16(2)のモーメント図に示すように、桁の中央区間において、支間長の約1/3までの区間では曲げモーメントは大きなものであるが、その区間の外側ではモーメントは約半分近くまで減少して小さな値となるので、2次PC鋼材を支間長(L)の約1/3の区間に配置することによって必要な強度を得ることができ、工事期間も短縮することが可能であるので合理的なものであることからラップ区間を支間長(L)の1/3までとするのが好ましい。
Further, as shown in FIG. 13, the extended fixing portion 5 may be provided on the end surface of the connecting portion of the unit without causing the extended fixing portion 5 to protrude from the upper edge or the lower edge of the girders, and the connected PC steel material may be fixed.
The connected PC steel 34 (secondary PC steel) disposed in the above-described illustrated example, in particular, the composite structure connecting portion 36 illustrated in FIGS. 9 to 13 is the primary PC previously disposed in the unit that is a divided member. Since the steel material (pre-tension type PC steel material 35 and post-tension type PC steel material 35a) and a sufficiently long lap portion are provided, sufficient prestress is applied to the central cross section of the girder. The resulting large bending stress is jointly borne by the secondary PC steel material and the primary PC steel material and transmitted to the fulcrum at both ends of the girder.
Further, in the present invention, it is necessary to observe the principle of securing the work zone W by securing the lane T of one lane and blocking the other lanes, but the primary PC steel and the secondary If the wrap length of the PC steel material is increased, the work of the both-end fixing part 5 of the secondary PC steel material, which is a field work, enters the traffic zone T beyond the work zone W, which is not preferable. Then, considering that the girders after completion of the connection are basically simple girders, as shown in the moment diagram of FIG. 16 (2), in the central section of the girders, up to about 1/3 of the span length. The bending moment is large in the section, but outside the section, the moment decreases to almost half and becomes a small value, so the secondary PC steel is placed in the section of about 1/3 of the span length (L). By doing so, the necessary strength can be obtained and the construction period can be shortened, so that it is reasonable, and therefore, the lap section is preferably set to 1/3 of the span length (L).

図14に示す例は、連結部となるSPC桁の端部の下縁を延長した下縁延長部3Jを形成したものである。この下縁延長部3J同士を突き合わせ、下縁延長部3J間に目地を設けて目地材を充填するだけでよく、連結部のベッド型枠は不要となり、現場の手間や時間を省くことができる。   In the example shown in FIG. 14, a lower edge extension 3 </ b> J is formed by extending the lower edge of the end portion of the SPC girder serving as a connecting portion. It is only necessary to abut the lower edge extension portions 3J and provide joints between the lower edge extension portions 3J to fill the joint material. A bed form frame at the connecting portion is not necessary, and labor and time at the site can be saved. .

さらに、図15は、桁の支持部である土留擁壁2に桁の端部をPC鋼棒の緊張力Pによって土留擁壁2に定着して剛結したものである。
土留擁壁2に予めPC鋼棒39を配設しておきその先端部は土留擁壁内に定着しておく。桁3の架設後にカプラー39cで延長PC鋼棒39eを接続して桁3の天端まで延長させ、桁3の中央部の複合構造連結部36が完成して分割された桁が一体化されて単純桁として完成した後に、SPC桁3と土留擁壁2の間には目地モルタル39mを充填して硬化させた後に、PC鋼棒39を桁端部の上面に緊張定着して桁端部を土留擁壁2に剛結する。
なお、図示は省略するが、剛結方法はこれに限ることなく、例えば、土留擁壁2と桁3の端部との間に水平方向にPC鋼棒39eを貫通して、同様に緊張定着して剛結することとしてもよい。
Further, FIG. 15 shows a structure in which the end of the spar is fixed to the retaining wall 2 by a tension P of the PC steel rod and rigidly connected to the retaining wall 2 which is a supporting part of the spar.
A PC steel rod 39 is disposed in advance on the retaining wall 2 and its tip is fixed in the retaining wall. After the installation of the girder 3, the extension PC steel bar 39e is connected by the coupler 39c and extended to the top end of the girder 3, the composite structure connecting part 36 at the center of the girder 3 is completed, and the divided girder is integrated. After being completed as a simple girder, the joint mortar 39m was filled between the SPC girder 3 and the retaining wall 2 and hardened, and then the PC steel bar 39 was tension-fixed on the upper surface of the girder end to fix the end of the girder. Rigidly attached to the retaining wall 2.
In addition, although illustration is abbreviate | omitted, the rigid fastening method is not restricted to this, For example, the PC steel rod 39e is penetrated horizontally between the earth retaining wall 2 and the end part of the girder 3, and the tension is fixed similarly. Then, it may be rigidly connected.

図16(1)にSPC桁を仮受台に載置したときのモーメント図を示す。連結前の分割されたSPC桁3a、3bは、土留擁壁2と仮受台15で両端部を支持された支間長がL/2とする単純桁であるので、支持点におけるモーメントはゼロであり、支間長がL/2とする各桁の中央部で最大のモーメントなる。これが、桁の中央部の連結部において連結一体化されて複合構造連結部が完成すると、この桁は端部が両土留擁壁2a、2bで支持された支間長がLとなる単純桁となっていることから、モーメント分布は、図16(2)のようになる。
更に、図15に示すように桁端部が土留擁壁2に緊張鋼材39によって緊張力Pで緊張定着されると、桁端部には負のモーメントが作用することから図16(3)のモーメント図に示すように、支間長がLとなるSPC桁に作用する荷重による曲げモーメントの一部が桁端に負担されることになり、桁中央部の複合連結部36に作用する曲げ応力が軽減されることになり、桁高を低くすることができる。
FIG. 16A shows a moment diagram when the SPC girder is placed on the temporary cradle. Since the divided SPC girders 3a and 3b before the connection are simple girders with the span length supported at both ends by the retaining wall 2 and the temporary support 15 and L / 2, the moment at the support point is zero. There is a maximum moment at the center of each girder where the span length is L / 2. When this is connected and integrated at the connecting portion at the center of the girder to complete the composite structure connecting portion, this girder becomes a simple girder whose end is supported by both retaining wall retaining walls 2a and 2b and the span length is L. Therefore, the moment distribution is as shown in FIG.
Further, as shown in FIG. 15, when the end of the spar is tension-fixed to the retaining wall 2 by the tension steel material 39 by the tension steel P, a negative moment acts on the end of the spar, so that FIG. As shown in the moment diagram, a part of the bending moment due to the load acting on the SPC girder whose span length is L is borne at the end of the girder, and the bending stress acting on the composite connecting portion 36 at the center of the girder is It will be reduced, and the digit height can be lowered.

道路を全面的に通行止めにすることなくSPC桁を道路上に掛け渡すための作業帯Wを確保する手法の一例を以下に示す。ここに示す例は、上下各2車線の道路を例にしたものである。
図17(1)に示すように、上下線のいずれかの二車線を上下通行に利用して通行帯Tを確保し、反対側の二車線の道路の略半分以上を通行止めにして作業帯Wを確保するものであり、土留擁壁2からSPC桁を中央線付近に設置した仮受台に掛け渡す際に適したものである。
図17(2)に示す例は、上下線の路側帯側をそれぞれ交通に供する通行帯Tとし、中央線側を通行止めにすることによって中央線を中心にした作業帯Wを確保するものであり、両側の土留擁壁からSPC桁を掛け渡して複合構造連結部36を形成する作業時に適した作業帯Wが形成される。
An example of a method for securing a work zone W for passing the SPC girder over the road without completely blocking the road is shown below. The example shown here is an example of a road with two lanes above and below.
As shown in FIG. 17 (1), the traffic zone T is secured by using one of the two lanes of the upper and lower lines for up and down traffic, and approximately half or more of the roads on the opposite two lanes are closed. This is suitable when the SPC girder is passed from the retaining wall 2 to a temporary cradle installed near the center line.
In the example shown in FIG. 17 (2), the roadside belt side of the upper and lower lines is used as a traffic belt T for traffic, and the work belt W around the central line is secured by blocking the traffic on the central line side. The work band W suitable for the work of forming the composite structure connecting portion 36 by spanning the SPC girders from the retaining walls on both sides is formed.

図18(1)は、架設した桁3の道路長手方向の断面を示すものであり、桁3が一定間隔あけて並列させて土留擁壁2の間に架設してあり、桁3、3の間にプレキャストコンクリート製床版41が掛け渡してあり、更に、左右両側端の桁3には地覆45がSPC桁3と一体に成型されたものであり、人工地盤の両端部の道路に面する部分の部材は可能な限りプレキャスト製とすることによって、現場作業を省略できるようにしたものであり、現場で組立てるだけで道路に面する構造体を迅速に形成できるようにし、その後の作業、例えば、トップコンクリート42を打設して合成床版を形成し、その上に仕上げや舗装工事と共に高欄の取り付け工事等を道路通行規制を解除して形成された人工地盤の構造体の上に行うことができ、工期の短縮を図ることができる。
図18(2)は土留擁壁2の位置の断面図であり、図18(3)は桁3の上縁を拡大して拡大部(ふかし)3Hとした部分の横断面図であり、図18(4)は、並列させた桁3同士の間にプレキャスト製の横桁3Pを設け、それらを貫通する緊張鋼材37によって道路に面する構造体を迅速に形成できるようにしたものであり、横桁3Pの完成後は道路通行規制を解除して形成された人工地盤10の構造体の上で種々の作業を行うことができるようにしたものである。
FIG. 18 (1) shows a cross section of the installed girder 3 in the longitudinal direction of the road. The girder 3 is installed between the retaining walls 2 in parallel with a predetermined interval. A precast concrete floor slab 41 is stretched between them, and the ground cover 45 is formed integrally with the SPC girder 3 on the left and right side girders 3, and faces the roads on both ends of the artificial ground. The parts of the parts to be made are made of precast as much as possible, so that the field work can be omitted, the structure facing the road can be quickly formed just by assembling at the field, the subsequent work, For example, a concrete floor slab is formed by placing the top concrete 42, and then finishing and paving work, as well as railing installation work, etc. are performed on the artificial ground structure formed by releasing road traffic restrictions. Can shorten the work period It is possible to achieve.
18 (2) is a cross-sectional view of the position of the retaining wall 2, and FIG. 18 (3) is a cross-sectional view of a portion where the upper edge of the girder 3 is enlarged to form an enlarged portion (flick) 3H. 18 (4) is provided with precast cross beams 3P between the parallel beams 3 so that a structure facing the road can be quickly formed by the tension steel material 37 penetrating them. After the cross beam 3P is completed, various operations can be performed on the structure of the artificial ground 10 formed by releasing the road traffic regulation.

1 半地下型道路
10 人工地盤
15 仮受台
2、2a、2b 土留擁壁
3、3a、3b SPC桁
3E 基部
3H 拡大部(ふかし)
3U1〜3 桁ユニット
3M 桁ユニットの連結部
3J 下縁延長部
3P 横桁
31 鉄骨鋼材
32 連結用鉄骨
33 コンクリート、無収縮モルタル
34、34a 連結PC鋼材
34S 連結PC鋼材用シース
35 プレテンション方式PC鋼材
35a ポストテンション方式PC鋼材
36 複合構造連結部(連結部)
37 横方向緊張鋼材
39 桁端定着緊張鋼材
39c カプラー
39e 延長緊張鋼材
39m 目地モルタル
4 床版
45 地覆
5 延長定着部
G 地面
T 通行帯
W 作業帯
1 Semi-underground road 10 Artificial ground 15 Temporary cradle 2, 2a, 2b Earth retaining wall 3, 3a, 3b SPC girder 3E Base 3H Enlarged part (Fushikashi)
3U 1-3 Girder Unit 3M Girder Unit Connection 3J Lower Edge Extension 3P Cross Girder 31 Steel Frame 32 Connection Steel 33 Concrete, Non-shrink Mortar 34, 34a Connection PC Steel 34S Connection PC Steel Sheath 35 Pretension Method PC Steel 35a Post-tension PC steel 36 Composite structure connecting part (connecting part)
37 Lateral tension steel material 39 Girder end fixing tension steel material 39c Coupler 39e Extended tension steel material 39m Joint mortar
4 Floor slab 45 Ground cover 5 Extension fixing part G Ground T Traffic zone W Work zone

Claims (9)

両脇に擁壁を有する半地下型道路の上に人工地盤を構築する方法であって、圧縮側に鉄骨鋼材を配設したプレキャストコンクリートPC桁(SPC桁)を擁壁間の距離(L)を支間長とする単純桁として断面を設計し、この断面であって桁長が支間長の半分(L/2)未満のSPC桁であって、先端部に先端面から突出する連結用鉄骨と連結PC鋼材用シースが設けてあり、少なくとも上下各一車線の通行帯を確保してその他を通行止めとして作業帯を確保し、SPC桁を一方の土留擁壁から道路の中央に設置した仮受台の間に掛け渡し、通行止めの車線を切り替えて作業帯を変更して他方の土留擁壁からもSPC桁を仮受台に掛け渡して対向配置し、SPC桁の先端部から突出した連結用鉄骨同士を連結すると共に、前記連結PC鋼材挿入用シースに連結PC鋼材を挿入配設し、対向配置したSPC桁の間にコンクリートを打設して硬化させ、連結PC鋼材を緊張定着してプレストレスを付与して連結用鉄骨と連結PC鋼材を含む複合構造連結部を形成することによってSPC桁を連結一体化して支間長をLとする擁壁間のSPC単純桁を形成した後に、仮受台を撤去することを特徴とする半地下型道路の上に人工地盤を構築する方法。 This is a method of constructing artificial ground on a semi-underground road with retaining walls on both sides. Precast concrete PC girders (SPC girders) with steel frames on the compression side are distances between retaining walls (L) The cross section is designed as a simple girder having a span length as a span girder, and this section is an SPC girder having a girder length less than half the span length (L / 2), and a connecting steel frame projecting from the front end surface to the front end portion; Temporary cradle with a sheath for connecting PC steel, securing at least one lane in the upper and lower lanes, securing a work zone as the other traffic stop, and installing the SPC girder from one retaining wall to the center of the road Bridge between the doors, change the working lane by switching the traffic lane, change the work zone, and place the SPC girder from the other retaining wall to the temporary receiving stand so as to face each other, and the connecting steel frame protruding from the tip of the SPC girder For connecting together and for connecting PC steel materials Connected PC steel material is inserted and disposed in the base, and concrete is placed between the SPC girders facing each other and hardened, and the connected PC steel material is tension-fixed and prestressed to provide the connection steel frame and the connected PC steel material. A semi-underground type characterized in that after the SPC simple girder between the retaining walls with the span length L is formed by forming the composite structure connecting portion including the SPC girder, the temporary support is removed. How to build artificial ground on the road. 請求項1において、前記複合連結部を形成してSPC桁を一体化した後、SPC単純桁の両端部をPC鋼材による緊張力で擁壁に剛結し、その後に仮受台を撤去することを特徴とする半地下型道路の上に人工地盤を構築する方法。 In Claim 1, after forming the said composite connection part and integrating a SPC girder, the both ends of a SPC simple girder are rigidly connected to the retaining wall with the tension | tensile_strength by PC steel material, and removes a temporary support stand after that. A method of constructing artificial ground on a semi-underground road characterized by 請求項1または2において、少なくとも上下一車線の通行帯を確保して反対側の道路略半分以上を通行止めにして作業帯を確保し、前記SPC桁を掛け渡して複合構造連結部を形成することを特徴とする半地下型道路の上に人工地盤を構築する方法。 In Claim 1 or 2, securing a traffic zone of at least one upper and lower lane, securing a work zone by blocking over approximately half or more of the opposite road, and spanning the SPC girder to form a composite structure connecting portion A method of constructing artificial ground on a semi-underground road characterized by 請求項1または2において、片側対向二車線の交通を確保して反対側の道路略半分以上を通行止めにして作業帯を確保した状態で前記SPC桁を掛け渡し、その後、道路両側に片側一車線ずつの通行帯を確保し、道路の中央を通行止めにして作業帯を確保して複合構造連結部を形成することを特徴とする半地下型道路の上に人工地盤を構築する方法。 3. The vehicle according to claim 1 or 2, wherein the SPC girder is routed in a state in which traffic on one side opposite two lanes is secured and approximately half or more of the opposite road is closed and a work zone is secured, and then one side lane on both sides of the road. A method of constructing artificial ground on a semi-underground road characterized by securing each traffic zone and blocking the center of the road to secure a work zone to form a composite structure connection part. 両脇に擁壁を有する半地下型道路の上部に人工地盤を構築するための桁断面の圧縮側に鉄骨鋼材が配設されているSPC桁であって、桁断面が擁壁間を支間長(L)の単純桁として設計されたものであり、桁長さが支間長(L)の二分の一未満のものが複合構造連結部で連結されたものであり、複合構造連結部はSPC桁の先端から突出させてある連結用鉄骨で連結されており、連結用鉄骨はSPC桁の先端部に埋設されて先端部より突出させたものであり、連結部に渡って連結PC鋼材が配設されて緊張定着してあることを特徴とするSPC桁。 An SPC girder in which steel frame steel material is arranged on the compression side of the girder cross section for constructing artificial ground on the upper part of the semi-underground road with retaining walls on both sides, and the girder cross section is the span length between the retaining walls (L) is designed as a simple girder, and the girder length is less than one half of the span length (L), which is joined by a composite structure connecting part. The composite structure connecting part is an SPC girder. It is connected with a connecting steel frame that protrudes from the tip of the steel, and the connecting steel is embedded in the tip of the SPC girder and protrudes from the tip, and the connecting PC steel material is arranged across the connecting part. SPC girder characterized by being tensioned. 請求項5において、前記複合構造連結部に配設されている連結PC鋼材が支間長(L)の1/3以下の区間に配置されていることを特徴とするSPC桁。 6. The SPC girder according to claim 5, wherein the connected PC steel material disposed in the composite structure connecting portion is disposed in a section of 1/3 or less of the span length (L). 請求項5または6において、複合構造連結部において桁高を大きくした拡大部(ふかし)が設けてあることを特徴とするSPC桁。 The SPC girder according to claim 5 or 6, wherein an enlarged portion (fluff) having a larger girder height is provided in the composite structure connecting portion. 請求項5〜7のいずれかのSPC桁が半地下型道路の両脇の土留擁壁に架設されており、桁端部がPC鋼材によって擁壁に緊張定着されて擁壁に剛結されていることを特徴とするSPC桁。 The SPC girder according to any one of claims 5 to 7 is erected on the retaining wall on both sides of the semi-underground road, and the end of the girder is tension-fixed to the retaining wall by the PC steel material and rigidly connected to the retaining wall. SPC digit characterized by 請求項5〜8のいずれかにおいて、桁高スパン比が1/22〜1/30であることを特徴とするSPC桁。 9. The SPC girder according to claim 5, wherein the girder height span ratio is 1/22 to 1/30.
JP2016255735A 2016-12-28 2016-12-28 Construction method of artificial ground on semi-underground road Active JP6166454B1 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP2016255735A JP6166454B1 (en) 2016-12-28 2016-12-28 Construction method of artificial ground on semi-underground road

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP2016255735A JP6166454B1 (en) 2016-12-28 2016-12-28 Construction method of artificial ground on semi-underground road

Publications (2)

Publication Number Publication Date
JP6166454B1 JP6166454B1 (en) 2017-07-19
JP2018105091A true JP2018105091A (en) 2018-07-05

Family

ID=59351406

Family Applications (1)

Application Number Title Priority Date Filing Date
JP2016255735A Active JP6166454B1 (en) 2016-12-28 2016-12-28 Construction method of artificial ground on semi-underground road

Country Status (1)

Country Link
JP (1) JP6166454B1 (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109826097A (en) * 2019-02-18 2019-05-31 腾达建设集团股份有限公司 A kind of interim prestressing force implementation method in the section of bridge subsection

Families Citing this family (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN114439267B (en) * 2022-02-16 2024-03-22 浙大城市学院 Transformation of oversized independent underground garage into road structure and construction method thereof
CN114790686B (en) * 2022-02-18 2023-08-22 樊永攀 Connecting device for bridge construction and bridge construction method

Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH07268808A (en) * 1994-04-01 1995-10-17 Nippon Doro Kodan Bridge precast floor slab and partial replacement method thereof
US6668412B1 (en) * 1997-05-29 2003-12-30 Board Of Regents Of University Of Nebraska Continuous prestressed concrete bridge deck subpanel system
JP3703760B2 (en) * 2001-12-20 2005-10-05 黒沢建設株式会社 Girder bridge
JP2009041272A (en) * 2007-08-09 2009-02-26 Ps Mitsubishi Construction Co Ltd Construction method for bridge
JP2009041271A (en) * 2007-08-09 2009-02-26 Ps Mitsubishi Construction Co Ltd Construction method for bridge
JP2010101094A (en) * 2008-10-24 2010-05-06 Asahi Engineering Kk Structure for rigidly connecting bridge pier and concrete girder together
JP5706566B1 (en) * 2014-07-16 2015-04-22 黒沢建設株式会社 SPC composite girder bridge design method and girder bridge

Patent Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH07268808A (en) * 1994-04-01 1995-10-17 Nippon Doro Kodan Bridge precast floor slab and partial replacement method thereof
US6668412B1 (en) * 1997-05-29 2003-12-30 Board Of Regents Of University Of Nebraska Continuous prestressed concrete bridge deck subpanel system
JP3703760B2 (en) * 2001-12-20 2005-10-05 黒沢建設株式会社 Girder bridge
JP2009041272A (en) * 2007-08-09 2009-02-26 Ps Mitsubishi Construction Co Ltd Construction method for bridge
JP2009041271A (en) * 2007-08-09 2009-02-26 Ps Mitsubishi Construction Co Ltd Construction method for bridge
JP2010101094A (en) * 2008-10-24 2010-05-06 Asahi Engineering Kk Structure for rigidly connecting bridge pier and concrete girder together
JP5706566B1 (en) * 2014-07-16 2015-04-22 黒沢建設株式会社 SPC composite girder bridge design method and girder bridge

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109826097A (en) * 2019-02-18 2019-05-31 腾达建设集团股份有限公司 A kind of interim prestressing force implementation method in the section of bridge subsection

Also Published As

Publication number Publication date
JP6166454B1 (en) 2017-07-19

Similar Documents

Publication Publication Date Title
JP6323776B2 (en) Replacement method of concrete floor slab for elevated road and replacement PC floor slab by the same method
KR102009134B1 (en) Construction Method of Long Span Girder Bridge
KR101394193B1 (en) Incremental launching apparatus for launching concrete slab for composite bridge using form of buried type
CN104929034A (en) Small modularized steel-concrete rapid-construction box girder bridge and construction method thereof
KR101007708B1 (en) Semi-hinge rahman bridge and method for constructing the same
KR101633431B1 (en) Expandable bridge sidewalk and it&#39;s construction method
CN103938546A (en) Simple-supported continuous construction method and structure thereof
JP2015151768A5 (en)
KR100522170B1 (en) Method of constructing simple and continuous composite bridges
CN108867310A (en) The short rib T beam bridge of pretensioning prestressed concrete and its construction method
JP6166454B1 (en) Construction method of artificial ground on semi-underground road
CN106223183A (en) Assembled concrete-filled rectangular steel tube combination truss bridge and construction method
KR102396444B1 (en) Composite structure of bridge deck and open box girder
KR101260863B1 (en) Rhamen bridge having prestressed concrete girder of arch-shaped and construction method thereof
KR20090098180A (en) Method for broadening width of existing bridge without temporary road
KR101242842B1 (en) Construction method for corrugated steel plate web-psc composite beam
KR101640921B1 (en) Precast Concrete Underground Box Structures for Underground Roads and Construction Method of Such Structures
CN103205930B (en) Structure for continuous transformation of existing simply supported hollow slab girder bridge and construction method of structure
KR101356724B1 (en) Retaining walls and construction method thereof
JP2020090785A (en) Widening structural body, widening structure, floor slab widening construction method, and floor slab renewal method
KR101735077B1 (en) Bridge deck using precast concrete panel
CN209854536U (en) Concrete large cantilever bridge pier structure
JP4477467B2 (en) Bridge structure and its replacement method
KR102630598B1 (en) Construction structure of bridge having corrugated steel plate structure and construction method of bridge using the same
KR20130090709A (en) Construction method for corrugated steel plate web-psc composite beam

Legal Events

Date Code Title Description
A131 Notification of reasons for refusal

Free format text: JAPANESE INTERMEDIATE CODE: A131

Effective date: 20170516

A521 Request for written amendment filed

Free format text: JAPANESE INTERMEDIATE CODE: A523

Effective date: 20170523

TRDD Decision of grant or rejection written
A01 Written decision to grant a patent or to grant a registration (utility model)

Free format text: JAPANESE INTERMEDIATE CODE: A01

Effective date: 20170620

A61 First payment of annual fees (during grant procedure)

Free format text: JAPANESE INTERMEDIATE CODE: A61

Effective date: 20170622

R150 Certificate of patent or registration of utility model

Ref document number: 6166454

Country of ref document: JP

Free format text: JAPANESE INTERMEDIATE CODE: R150