JP2018017007A - Integration equipment and equipment unit equipped with the same - Google Patents

Integration equipment and equipment unit equipped with the same Download PDF

Info

Publication number
JP2018017007A
JP2018017007A JP2016147660A JP2016147660A JP2018017007A JP 2018017007 A JP2018017007 A JP 2018017007A JP 2016147660 A JP2016147660 A JP 2016147660A JP 2016147660 A JP2016147660 A JP 2016147660A JP 2018017007 A JP2018017007 A JP 2018017007A
Authority
JP
Japan
Prior art keywords
unit
water supply
facility
equipment
pipe
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
JP2016147660A
Other languages
Japanese (ja)
Inventor
康裕 白井
Yasuhiro Shirai
康裕 白井
修司 深尾
Shuji Fukao
修司 深尾
広一 浜田
Koichi Hamada
広一 浜田
陽一郎 冨岡
Yoichiro Tomioka
陽一郎 冨岡
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Lixil Corp
Original Assignee
Lixil Corp
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Lixil Corp filed Critical Lixil Corp
Priority to JP2016147660A priority Critical patent/JP2018017007A/en
Priority to PCT/JP2017/013538 priority patent/WO2018020740A1/en
Publication of JP2018017007A publication Critical patent/JP2018017007A/en
Pending legal-status Critical Current

Links

Images

Abstract

PROBLEM TO BE SOLVED: To provide a method of installing integration equipment efficiently by reducing scrambles between construction work for the installation of water section facility or the like and equipment work for the installation of water supply/drainage pipes, electric wires or the like.SOLUTION: An integration unit 1 is equipped with a standing unit 3 installed on a floor finished surface and a ceiling unit extending in the lateral direction. In the standing unit 3, a first drainage pump connected to a bathtub 8 and a first drainage pipe as well as a second drainage pump connected to a toilet bowl 10 and a second drainage pipe were installed. To the side face of the standing unit 3, the bathtub 8, the toilet bowl 10, a kitchen body 30, a wash stand 33 or the like were radially connected as water section facilities M. Connection recessed parts provided to the water section facilities including the bathtub 8 are fitted to connection recessed parts provided on the side face of the standing unit 3, by which the standing unit and the bathtub were electrically connected. A distribution panel is housed in the standing unit 3, and electric wires in the distribution panel are connected to electric wires connected to connectors of the bathtub 8, the toilet bowl 10 or the like through an interface.SELECTED DRAWING: Figure 3

Description

本発明は、例えば建物の居住空間等に設置され、配管等を収納して配置された集約設備及び設備ユニットに関する。   The present invention relates to an aggregation facility and a facility unit that are installed, for example, in a living space of a building and housed by piping and the like.

従来、居住空間において浴室、トイレ室、キッチン、洗面所等の水回り設備はそれぞれ独立させる間取りが一般的であり、これら水回り設備の建築工事と給水管や排水管等の配管敷設工事等の各種の設備工事が個別に必要であり、煩雑であった。即ち、水回り設備を施工するに当たっては建築工事と設備工事の取り合いが多いために、これらの事前打合せに多くの時間がかかっていた。さらに、施工現場においても建築工事と設備工事が錯綜することが多く、また、水回り設備の中でも浴室とトイレ室とでは施工時期が異なることが多いため施工に手間がかかっていた。これに対し、これらの水回り設備を集約して設置する間取りの設備ユニットも提案されている。   Conventionally, it has been common to arrange floor plans such as bathrooms, toilets, kitchens, and washrooms in living spaces that are independent of each other, such as building construction of these plumbing equipment and pipe laying work such as water supply and drain pipes. Various types of equipment construction was required individually and was complicated. That is, when constructing a water supply facility, it takes a lot of time for these prior meetings because there is a lot of interaction between construction work and facility work. In addition, there are many cases where construction work and facility work are complicated at the construction site, and the construction time is often different between the bathroom and the toilet room among watering facilities. On the other hand, a floor plan equipment unit that collects and installs these water facilities has also been proposed.

例えば、特許文献1に記載された衛生設備ユニットでは、躯体壁に水平フレームと垂直フレームを連結させて設置し、間仕切りパネルで仕切った複数のフレームユニットの各空間内に浴室やトイレ室、キッチン等の水回り設備を設置している。更に各フレームユニットに配管フレームを設置して水回り設備の給排水を行っている。これらの給排水管等は床仕上面の下側に延ばして外部設備に接続している。   For example, in the sanitary equipment unit described in Patent Document 1, a horizontal frame and a vertical frame are connected to a frame wall and installed in each space of a plurality of frame units partitioned by a partition panel. The water supply equipment is installed. In addition, piping frames are installed in each frame unit to supply and drain water facilities. These water supply and drainage pipes extend below the floor finish and are connected to external equipment.

特許第5715426号公報Japanese Patent No. 5715426

しかしながら、上述した特許文献1に記載の衛生設備ユニットでは、キッチン、洗面台、浴室等の各種の水回り設備をフレームに設置するユニット構造について開示されているが、これら水回り設備の給水管及び配水管や電気配線等については垂直フレーム、連結フレーム、配管フレーム内に収納させて水回り空間を形成するとしか開示されていなかった。   However, in the sanitary equipment unit described in Patent Document 1 described above, a unit structure in which various watering equipment such as a kitchen, a wash basin, and a bathroom are installed in a frame is disclosed. It has only been disclosed that water distribution pipes, electrical wiring, and the like are housed in vertical frames, connection frames, and piping frames to form water-circulating spaces.

また、給水管や排水管や電気配線等も個々に敷設しなければならず、給水管や排水管や電気配線等の敷設やメンテナンス等に制約があった。しかも、フレームや水回り設備等の建築工事と給排水管事や電気配線等の設備工事との取り合いが大きく、さらなる施工の効率化が望まれていた。   In addition, water supply pipes, drainage pipes, electrical wirings, and the like have to be individually laid, and there are restrictions on the installation and maintenance of the water supply pipes, drainage pipes, electrical wirings, and the like. In addition, there is a great deal of interaction between construction work such as frames and water facilities and equipment work such as water supply and drainage pipes and electrical wiring, and further efficiency in construction has been desired.

本発明は、このような課題に鑑みてなされたものであって、フレームや水回り設備等の建築工事と給排水管または電気配線等の設備工事との取り合いを低減させて効率よく設置できるようにした集約設備及び設備ユニットを提供することを目的とする。   The present invention has been made in view of such problems, and can be installed efficiently by reducing the balance between construction work such as a frame and watering equipment and equipment work such as a water supply / drainage pipe or electric wiring. An object of the present invention is to provide integrated facilities and equipment units.

本発明による集約設備は、少なくとも給水管及び排水管を収容していると共に、給水管と排水管の少なくとも一方を接続させる水回り設備を固定可能な連結部を備えたことを特徴とする。
本発明によれば、集約設備に給水管や配水管を集約して収容できるため建築工事と設備工事の取り合いが小さく効率的に施工でき、しかも集約設備の側部に設けた連結部を介して水回り設備を連結できるため、集約設備に対して水回り設備の位置決めと固定に調整が不要であり、墨出し等が必要なく簡単で精度良く連結できる。
The aggregation facility according to the present invention is characterized in that it includes at least a water supply pipe and a drainage pipe, and has a connecting portion capable of fixing a water supply facility for connecting at least one of the water supply pipe and the drainage pipe.
According to the present invention, water supply pipes and water distribution pipes can be collected and accommodated in the aggregated facility, so that the construction work and the facility work can be carried out efficiently and through the connecting portion provided on the side of the aggregated facility. Since the water supply equipment can be connected, there is no need to adjust the positioning and fixing of the water supply equipment with respect to the aggregated equipment.

本発明による集約設備は、少なくとも給水管及び排水管を収容していると共に、外部から延びる幹線に接続された分電盤を収容していることを特徴とする。
本発明は、屋外の配電盤から幹線を介して屋内に設置する分電盤を起立ユニットに設置したため、分電盤とこれに接続された電気配線等を主たる電気系統として集約設備内に集約して配設でき、建築工事と設備工事の取り合いを低減し、工場等で予め分電盤を組み込むことが可能で電気設備の施工が簡単になる。
The aggregation facility according to the present invention is characterized in that it houses at least a water supply pipe and a drain pipe and a distribution board connected to a main line extending from the outside.
In the present invention, since the distribution board installed indoors via the trunk line from the outdoor switchboard is installed in the standing unit, the distribution board and the electrical wiring connected to the distribution board are integrated into the central facility as the main electrical system. It can be installed, reducing the relationship between building work and facility work, and can install a distribution board in advance in a factory or the like, thus simplifying the installation of electrical equipment.

また、分電盤から延びる電気配線と側部に設置可能な水回り設備に接続される電気配線とがインターフェースを介して接続されていることが好ましい。
集約設備内で、分電盤から延びる電気配線と水回り設備から集約設備内に延びる電気配線とをインターフェースで接続できるため、電気配線の敷設に電気工事士等の専門技術者がいなくても簡単に取り付けできる。
Moreover, it is preferable that the electrical wiring extended from a distribution board and the electrical wiring connected to the water supply equipment which can be installed in a side part are connected via the interface.
In the centralized facility, the electrical wiring extending from the distribution board and the electrical wiring extending from the water supply facility into the centralized facility can be connected via an interface, so it is easy to lay the electrical wiring without the need for specialists such as an electrician. Can be attached to.

また、集約設備内に電気配線と換気ダクトが更に収容されていることが好ましい。
集約設備には電気配線と換気ダクトも収納されているため、集約設備内で各設備を一層集約できて外観をより単純化できる。
Moreover, it is preferable that electrical wiring and a ventilation duct are further accommodated in the aggregation facility.
Since the electrical facilities and ventilation ducts are also stored in the centralized facility, it is possible to further consolidate the facilities within the centralized facility and further simplify the appearance.

また、排水管に接続された排水ポンプが設けられていてもよい。
集約設備内で排水管に排水ポンプを接続することで水回り設備から回収した排水を上方に送って排出できるため、床仕上面の下側に排水設備を設置する必要がなく、集約設備の施工が簡単で済む。
In addition, a drain pump connected to the drain pipe may be provided.
By connecting a drainage pump to the drainage pipe in the centralized facility, the wastewater collected from the watering system can be sent upward and discharged, so there is no need to install a drainage system below the floor surface and the construction of the centralized facility Is easy.

また、集約設備はパネルで仕切られており、パネルに水回り設備を連結する連結部が設けられていてもよい。
集約設備の壁面を形成するパネルに設けた連結部で水回り設備を取り付けできるので、水回り設備の位置決めが簡単であり位置の調整が不要である。
In addition, the aggregation facility may be partitioned by a panel, and a connecting portion that connects the water-use facility to the panel may be provided.
Since the water supply facility can be attached by a connecting portion provided on the panel forming the wall surface of the aggregation facility, positioning of the water supply facility is easy and adjustment of the position is unnecessary.

また、給水管及び排水管は上下方向に延びる起立ユニットに収容されており、該起立ユニットの上部から給水管及び排水管を取り出して外部に延ばしてもよい。
給水管及び排水管を集約設備の起立ユニット内に収容し、その上端部から横方向に延ばして外部の配管に接続することで水回り設備の排水を天井側に向けて排水でき、集約設備の床仕上面下側に排水設備を設置することなく排水できる。
The water supply pipe and the drain pipe may be accommodated in an upright unit extending in the vertical direction, and the water supply pipe and the drain pipe may be taken out from the upper part of the upright unit and extended to the outside.
The water supply pipe and the drain pipe are accommodated in the standing unit of the aggregation facility, and the drainage of the plumbing facility can be drained toward the ceiling side by extending horizontally from the upper end of the unit and connecting to the external piping. Drainage can be done without installing a drainage facility below the floor finish.

また、起立ユニットの上部には給水管及び排水管を載置して横方向に延びる天井ユニットが連結されていてもよい。
起立ユニット内の上端部に延ばした給水管及び排水管を、天井ユニットに載置して横方向に延ばすことで、給水管や排水管を下側から目視できないので見栄えが良い。
Moreover, the ceiling unit which mounts a water supply pipe and a drain pipe and extends in the horizontal direction may be connected to the upper part of the standing unit.
The water supply pipe and the drainage pipe extended to the upper end part in the standing unit are placed on the ceiling unit and extended laterally, so that the water supply pipe and the drainage pipe cannot be seen from the lower side, so that the appearance is good.

また、集約設備は側部に水回り設備を放射状に設置可能としてもよい。
集約設備の側部に水回り設備を放射状に設置できることで省スペースで設置強度が高くなる。
In addition, the aggregation facility may be configured such that water facilities can be installed radially on the side.
The installation strength can be increased in a small space by installing water-circulating equipment radially on the side of the central equipment.

また、集約設備には照明器具が設置されていてもよい。
集約設備の内部に配設された電気配線を通して起立ユニット照明器具を設置できるので、構成がシンプルで省スペースであり見栄えがよい。
Moreover, the lighting equipment may be installed in the aggregation facility.
Since the standing unit luminaire can be installed through the electric wiring arranged inside the aggregation facility, the configuration is simple, space-saving and good-looking.

本発明による設備ユニットは、給水管及び排水管と電気配線を収容した集約設備を備えており、集約設備の側部には、給水管と排水管の少なくとも一方を接続させる水回り設備が設置され、該水回り設備には電気配線が電気的に接続されていることを特徴とする。
集約設備の側部に水回り設備を設置するに際し、水回り設備に連結する給水管や排水管と電気配線とを起立ユニット内に集約させて収容できるため、建築工事と設備工事の取り合いを減らすことができる。
The facility unit according to the present invention includes a water supply pipe and a drainage pipe, and an aggregation facility that accommodates electrical wiring, and a watering facility for connecting at least one of the water supply pipe and the drainage pipe is installed on the side of the aggregation facility. The water supply facility is characterized in that electrical wiring is electrically connected.
When installing the water supply equipment on the side of the centralized equipment, the water supply pipes and drainage pipes connected to the water supply equipment and the electrical wiring can be integrated and accommodated in the upright unit, reducing the amount of construction work and equipment work. be able to.

本発明による集約設備によれば、集約設備に給水管や配水管を集約して収容できるため設備工事と建築工事の取り合いが小さく効率的に施工できる。また、集約設備の側部に連結部を介して水回り設備を連結できるため、集約設備に対して水回り設備の位置決めと固定に調整が不要であり、簡単で精度良く連結できるため設備ユニットの品質が安定する。   According to the aggregation facility according to the present invention, since the water supply pipes and the water distribution pipes can be accommodated in the aggregation facility, the work between the facility work and the building work can be carried out efficiently. In addition, since the plumbing equipment can be connected to the side of the aggregated equipment via a connecting part, there is no need to adjust the positioning and fixing of the plumbing equipment with respect to the aggregated equipment. Quality is stable.

本発明による集約設備は、分電盤を集約設備に設置したため分電盤と電気配線等を集約できることになり、工場等で予め分電盤を組み込むことが可能になり施工が簡単である。しかも、配管や電気設備等の設備工事と躯体やフレーム等の建築工事との取り合いを低減させることができる。   Since the distribution equipment according to the present invention has the distribution board installed in the integration equipment, the distribution board and the electrical wiring can be integrated, so that the distribution board can be incorporated in advance in a factory or the like and the construction is simple. In addition, it is possible to reduce the balance between equipment work such as piping and electric equipment and building work such as a frame and a frame.

本発明による設備ユニットは、水回り設備に連結する給水管や排水管と電気配線とを集約設備内に集約させて収容できて、建築工事と設備工事の取り合いを減らすことができる。   The equipment unit according to the present invention can accommodate the water supply pipe and drain pipe connected to the water supply equipment and the electrical wiring in a centralized equipment, and can reduce the relationship between the construction work and the equipment work.

本発明の実施形態による設備ユニットを居室内の床仕上面に設置した状態を示す模式図である。It is a schematic diagram which shows the state which installed the equipment unit by embodiment of this invention in the floor finishing surface in a living room. 実施形態による設備ユニットの斜視図である。It is a perspective view of the equipment unit by an embodiment. 図2に示す設備ユニットにおいて起立ユニットの周囲に水回り設備を備えた平面図である。FIG. 3 is a plan view of the equipment unit shown in FIG. 2 including a watering equipment around a standing unit. 起立ユニットの両側にトイレと浴室を設置した構成を示す説明図である。It is explanatory drawing which shows the structure which installed the toilet and the bathroom in the both sides of the standing unit. 設備ユニットをトイレ側から見た側面図である。It is the side view which looked at the equipment unit from the toilet side. 起立ユニットと天井ユニットを備えた集約設備の内部構造を示す説明図である。It is explanatory drawing which shows the internal structure of the aggregation equipment provided with the standing unit and the ceiling unit. 起立ユニットと浴槽との連結構造を示す説明図である。It is explanatory drawing which shows the connection structure of a standing unit and a bathtub. 設備ユニットを浴室側から見た一部破断側面図である。It is the partially broken side view which looked at the equipment unit from the bathroom side. 天井ユニットと浴室の開閉扉を示す要部縦断面図である。It is a principal part longitudinal cross-sectional view which shows the ceiling unit and the door of a bathroom. 図9に示す開閉扉の吊り構造のA部拡大図である。It is the A section enlarged view of the hanging structure of the door shown in FIG. (a),(b)は天井ユニットの変形例を示す断面図である。(A), (b) is sectional drawing which shows the modification of a ceiling unit.

以下、本発明の実施形態による設備ユニットSを添付図面によって説明する。
図1は実施形態による設備ユニットSをマンション等の各種の建物内に設けた居室空間Kに設置した模式図である。図1において、建物内の住居の居室空間K内に水回り設備Mを備えた設備ユニットSが設置されている。設備ユニットSは給排水管等の各種配管やダクト、電気設備等を収容した集約設備1とその周囲に設けた1または複数の水回り設備Mとで構成されており、設備ユニットSは居住空間K内の任意の位置で床仕上面2上に設置できる。
図2乃至図5は実施形態による設備ユニットSを示すものである。図2に示す設備ユニットSに設けた集約設備1は、床仕上面2から起立する起立ユニット3とその上部に設けた天井ユニット4とで略L字形に形成されている。起立ユニット3は例えば浴槽8や便器10等の各種の水回り設備Mを支持する塔状構造体であり、水平断面が縦横方向にそれぞれ所定幅を有する中空の筒体で形成され、床仕上面2から自立して鉛直方向に延びている。
Hereinafter, an equipment unit S according to an embodiment of the present invention will be described with reference to the accompanying drawings.
FIG. 1 is a schematic diagram in which the equipment unit S according to the embodiment is installed in a living room space K provided in various buildings such as an apartment. In FIG. 1, the equipment unit S provided with the water supply equipment M is installed in the living room space K of the house in the building. The equipment unit S is composed of an aggregation equipment 1 that accommodates various pipes such as water supply and drainage pipes, ducts, electrical equipment and the like, and one or a plurality of water facilities M provided around the equipment, and the equipment unit S is a living space K. It can be installed on the floor finishing surface 2 at any position inside.
2 to 5 show the equipment unit S according to the embodiment. The aggregation equipment 1 provided in the equipment unit S shown in FIG. 2 is formed in a substantially L shape by a standing unit 3 standing from the floor finishing surface 2 and a ceiling unit 4 provided thereon. The standing unit 3 is a tower-like structure that supports various watering facilities M such as a bathtub 8 and a toilet 10, and is formed of a hollow cylinder having a horizontal cross section having a predetermined width in the vertical and horizontal directions. It is independent from 2 and extends in the vertical direction.

天井ユニット4は水平方向に配設されていて断面略U字状に形成されて上部が開放されており、起立ユニット3の上端部に連結されている。起立ユニット3と天井ユニット4のコーナー部において、各配管は例えばL字管を介して連結され、天井ユニット4上の他端は居住空間Kの壁面を通して設備用の縦管を収納するパイプシャフトに格納された給水管や排水管などにそれぞれ接続されている。或いは、天井ユニット4は壁面と非接触に支持されていてもよい。天井ユニット4は図示しない天井面をなす天井スラブの梁からわずかに隙間を開けて下側に設置されているが、天井面に当接して設置してもよい。なお、図1に示す集約設備1では天井ユニット4は含まれていない。   The ceiling unit 4 is disposed in the horizontal direction, has a substantially U-shaped cross section, has an open top, and is connected to the upper end of the standing unit 3. At the corners of the standing unit 3 and the ceiling unit 4, each pipe is connected via, for example, an L-shaped pipe, and the other end on the ceiling unit 4 is a pipe shaft that houses a vertical pipe for equipment through the wall surface of the living space K. Each is connected to a stored water supply pipe or drainage pipe. Alternatively, the ceiling unit 4 may be supported in a non-contact manner with the wall surface. The ceiling unit 4 is installed on the lower side with a slight gap from a beam of a ceiling slab forming a ceiling surface (not shown), but may be installed in contact with the ceiling surface. In the aggregation facility 1 shown in FIG. 1, the ceiling unit 4 is not included.

起立ユニット3や天井ユニット4は例えば略四角形筒枠や略U字枠等のフレームをパネルで覆った筒状や枠状にした構成でもよいし、或いはフレームを用いることなく高剛性パネルだけで四面や三面を形成したフレームレス構造でもよい。また、起立ユニット3や天井ユニット4は略四角形筒状や断面略U字枠状に限定されるものではなく、略円筒状でもよいし他の多角形筒状でもよく、その断面形状は任意に設定できる。
本実施形態における起立ユニット3は例えば角筒状とされ、各角部に設けた補強用のフレーム3aと壁面をなすパネル材3bとで構成されている(図3、図6参照)。また、天井ユニット4は起立ユニット3の上端側面に接続されている。
The standing unit 3 and the ceiling unit 4 may be configured to have a cylindrical shape or a frame shape in which a frame such as a substantially rectangular tube frame or a substantially U-shaped frame is covered with a panel, or only a high-rigidity panel without using a frame. Or a frameless structure with three sides formed. Further, the standing unit 3 and the ceiling unit 4 are not limited to a substantially rectangular tube shape or a substantially U-shaped cross-sectional shape, and may be a substantially cylindrical shape or other polygonal tube shape, and the cross-sectional shape is arbitrary. Can be set.
The standing unit 3 in the present embodiment has, for example, a rectangular tube shape, and includes a reinforcing frame 3a provided at each corner and a panel member 3b forming a wall surface (see FIGS. 3 and 6). The ceiling unit 4 is connected to the upper end side surface of the standing unit 3.

天井面と天井ユニット4との間に適宜の隙間を設置した方が、天井が高く見えるため好ましい。天井面は突出する梁や施工誤差等の関係で水平でない場合があり、天井ユニット4を天井面から離すことで水平に設置することができる。しかも、天井面と天井ユニット4との間に隙間を設けると後述するように天井ユニット4に配設した各種配管や換気ダクト21等のメンテナンスを行いやすい。
また、床仕上面2から天井ユニット4までの距離は適宜設定できるが、一例をいえば、2118mm〜1720mmの範囲、或いは2118mm〜1830mmの範囲に設定できる。
It is preferable to install an appropriate gap between the ceiling surface and the ceiling unit 4 because the ceiling looks high. The ceiling surface may not be horizontal due to protruding beams, construction errors, and the like, and can be installed horizontally by separating the ceiling unit 4 from the ceiling surface. In addition, when a gap is provided between the ceiling surface and the ceiling unit 4, maintenance of various pipes and ventilation ducts 21 provided in the ceiling unit 4 is facilitated as will be described later.
Moreover, although the distance from the floor finish 2 to the ceiling unit 4 can be set as appropriate, for example, it can be set in the range of 2118 mm to 1720 mm, or in the range of 2118 mm to 1830 mm.

集約設備1における起立ユニット3及び天井ユニット4の投影面内の空間には起立ユニット3に例えば浴槽8が設置されている。浴槽8は起立ユニット3に対して床仕上面2上に固定されていてもよいし、図示しない回動軸を介して起立ユニット3に沿った起立位置と床仕上面2上に設置した倒伏位置との間で回動可能に連結されていてもよい。図1は浴槽8を収納した起立状態を示している。浴槽8の上方には天井ユニット4が設置されており、これが浴槽8の天井になる。   In the space in the projection plane of the standing unit 3 and the ceiling unit 4 in the aggregation facility 1, for example, a bathtub 8 is installed in the standing unit 3. The bathtub 8 may be fixed on the floor finishing surface 2 with respect to the standing unit 3, and the standing position along the standing unit 3 and the lying position installed on the floor finishing surface 2 via a rotation shaft (not shown). And may be connected so as to be rotatable. FIG. 1 shows a standing state in which the bathtub 8 is housed. A ceiling unit 4 is installed above the bathtub 8, and this becomes the ceiling of the bathtub 8.

起立ユニット3と浴槽8の連結構造が図7に示されている。図7において、起立ユニット3のパネル材3bには連結凹部9が形成され、浴槽8の短片側の側部には連結凹部9に嵌合する連結凸部13が形成されている。連結凹部9と連結凸部13とで連結部を構成する。起立ユニット3の連結凹部9に浴槽8の連結凸部13を嵌合させることで浴槽8を高精度に位置決めして連結固定できる。しかも、連結凹部9と連結凸部13は嵌合状態で図示しない爪部やねじ締め等によって浴槽8が離脱しないよう起立ユニット3に固定してもよい。なお、起立ユニット3に連結凸部13を設け、浴槽8に連結凹部9を設けてもよい。
また、連結凹部9と連結凸部13にはそれぞれ通電用のコネクタt1、t2が配設され、連結凹部9と連結凸部13の嵌合状態でコネクタt1とt2が電気的に接合されて通電状態になる。
The connection structure of the standing unit 3 and the bathtub 8 is shown in FIG. In FIG. 7, the connection recess 9 is formed in the panel material 3 b of the standing unit 3, and the connection protrusion 13 that fits into the connection recess 9 is formed on the side of the short piece side of the bathtub 8. The connecting concave portion 9 and the connecting convex portion 13 constitute a connecting portion. By fitting the connecting convex portion 13 of the bathtub 8 into the connecting concave portion 9 of the standing unit 3, the bathtub 8 can be positioned and fixed with high accuracy. In addition, the connecting concave portion 9 and the connecting convex portion 13 may be fixed to the standing unit 3 so that the bathtub 8 is not detached by a claw portion or a screw tightening (not shown) in a fitted state. In addition, the connection convex part 13 may be provided in the standing unit 3, and the connection concave part 9 may be provided in the bathtub 8.
Further, the connection recesses 9 and the connection projections 13 are respectively provided with current-carrying connectors t1 and t2, and the connectors t1 and t2 are electrically connected to each other when the connection recesses 9 and the connection projections 13 are fitted. It becomes a state.

また、図3乃至図5に示すように、起立ユニット3の浴槽8と反対側の側面には水洗便器等の便器10が固定されている。図4に示す例では便器10は床仕上面2より上側に浮いて起立ユニット3の側面に固定されているが、床仕上面2上に設置固定されていてもよい。また、便器10は例えば図示しない回動軸回りに起立及び倒伏可能に支持され、起立ユニット3にその一部が収納可能であってもよい。浴槽8と便器10は集約設備1に設置された水回り設備Mである。   As shown in FIGS. 3 to 5, a toilet 10 such as a flush toilet is fixed to the side surface of the standing unit 3 opposite to the bathtub 8. In the example shown in FIG. 4, the toilet bowl 10 floats above the floor finishing surface 2 and is fixed to the side surface of the standing unit 3, but may be installed and fixed on the floor finishing surface 2. In addition, the toilet 10 may be supported so as to be able to stand and fall around a rotation shaft (not shown), and a part of the toilet 10 may be housed in the standing unit 3. The bathtub 8 and the toilet bowl 10 are water facilities M installed in the aggregation facility 1.

また、図3において、起立ユニット3の両側面には例えばパネル状の側壁12a、12bが略平行に配列されている。側壁12a、12bは所定厚みを有する壁体で、フレーム材とパネル材とで構成された構造部材である。この側壁12a、12bによって、起立ユニット3を補強しており、延在方向の一方の端部では浴槽8の起立ユニット3側の一部を囲っている。
側壁12a、12bの他方の端部は起立ユニット3の浴槽8と反対側に延びて便器10の両側部を仕切る空間を形成し、この空間はトイレ室16を形成する。トイレ室16の先端開口にトイレ扉11が開閉可能に取り付けられている。なお、トイレ扉11は設置しなくてもよい。
In FIG. 3, for example, panel-shaped side walls 12 a and 12 b are arranged substantially in parallel on both side surfaces of the standing unit 3. The side walls 12a and 12b are wall bodies having a predetermined thickness, and are structural members composed of a frame material and a panel material. The side wall 12a, 12b reinforces the standing unit 3, and at one end in the extending direction, a part of the bathtub 8 on the side of the standing unit 3 is surrounded.
The other ends of the side walls 12 a and 12 b extend to the opposite side of the tub 8 of the standing unit 3 to form a space that partitions both sides of the toilet 10, and this space forms a toilet room 16. A toilet door 11 is attached to the opening of the front end of the toilet room 16 so that it can be opened and closed. The toilet door 11 may not be installed.

起立ユニット3の一方の側面に連結された一方の側壁12aの外側において、その下部には流し台やガス台等を有する下部キャビネット29を備えたキッチン本体30がキッチンとして設置されている。図5に示すように、キッチン本体30の上方には側壁12aの上部に上部キャビネット31が取り付けられている。また、起立ユニット3の他方の側面に連結された他方の側壁12bの外側において、その下部に洗面ボウル等を有する洗面台33が取り付けられている。キッチン本体30や洗面台33も水回り設備Mである。
なお、これらの水回り設備Mは、起立ユニット3との関係で浴槽8と同様にそれぞれ連結凹部9と連結凸部13からなる連結部を有するものとする。
On the outside of one side wall 12a connected to one side surface of the upright unit 3, a kitchen body 30 having a lower cabinet 29 having a sink, a gas stand, and the like is installed as a kitchen at the lower part thereof. As shown in FIG. 5, an upper cabinet 31 is attached to the upper part of the side wall 12 a above the kitchen body 30. Further, on the outside of the other side wall 12 b connected to the other side surface of the standing unit 3, a wash basin 33 having a wash bowl or the like is attached to the lower part thereof. The kitchen body 30 and the wash basin 33 are also water facilities M.
In addition, these watering facilities M shall have the connection part which consists of the connection recessed part 9 and the connection convex part 13 similarly to the bathtub 8, in relation to the standing unit 3, respectively.

また、図4及び図6に示す集約設備1において、浴槽8内の排水は排水管を介して略角筒状の起立ユニット3内に設置した第一排水ポンプ(圧送ポンプ)P1に供給され、第一排水管17を介して起立ユニット3及び天井ユニット4を通して外部に排出される。また、第一排水ポンプ(圧送ポンプ)P1には、キッチン本体30や洗面台33の排水管も接続されている。
第一排水ポンプ(圧送ポンプ)P1は排水や排水中のごみ等の物体をインペラ(羽根車)で砕く等して第一排水管17を通して上方に圧送する。この第一排水管17は起立ユニット3内を上方に延びて略90度方向を変えて断面略U字状の天井ユニット4上を横方向に延びて外部に突出している。
4 and 6, the drainage in the bathtub 8 is supplied to a first drainage pump (pressure pump) P1 installed in an upright unit 3 having a substantially rectangular tube shape through a drainage pipe. It is discharged outside through the standing unit 3 and the ceiling unit 4 through the first drain pipe 17. Further, the drainage pipes of the kitchen body 30 and the wash basin 33 are also connected to the first drainage pump (pressure feed pump) P1.
The first drainage pump (pressure feed pump) P1 pulverizes an object such as drainage or waste in the drainage with an impeller (impeller) and pumps it upward through the first drainage pipe 17. The first drain pipe 17 extends upward in the upright unit 3 and changes its direction by approximately 90 degrees to extend laterally on the ceiling unit 4 having a substantially U-shaped cross section and protrudes to the outside.

また、便器10内の汚物や汚水を含む排水は排水管を介して起立ユニット3内の第二排水ポンプ(圧送ポンプ)P2に排出され、第二排水管18を介して外部に排出される。第二排水ポンプP2は、排水中の汚物等をインペラ(羽根車)で砕く等して第二排水管18の上方に圧送する。この第二排水管18は第一排水管17と同様に、起立ユニット3内を上方に延びて略90度方向を変えて天井ユニット4上を横方向に延びて外部に突出している。
なお、第一排水ポンプP1および第二排水ポンプP2には小型のタンクが設けられており、各ポンプP1,P2は例えばタンクに貯留した排水の水位によってON/OFF制御されるように構成されている。
Further, the waste water including the filth and waste water in the toilet 10 is discharged to the second drain pump (pressure pump) P2 in the standing unit 3 through the drain pipe, and is discharged to the outside through the second drain pipe 18. The second drainage pump P <b> 2 pumps filth and the like in the drainage above the second drainage pipe 18 by crushing it with an impeller (impeller). Similar to the first drain pipe 17, the second drain pipe 18 extends upward in the upright unit 3, changes direction by approximately 90 degrees, extends in the lateral direction on the ceiling unit 4, and protrudes to the outside.
The first drainage pump P1 and the second drainage pump P2 are provided with small tanks, and each pump P1, P2 is configured to be ON / OFF controlled according to the level of drainage stored in the tank, for example. Yes.

起立ユニット3及び天井ユニット4内には、浴槽8やキッチン本体30等に給湯を行う給湯管19と、浴槽8や便器10、更にはキッチン本体30や洗面台33の水道の蛇口等に給水を行う給水管20とが収容されている。
起立ユニット3及び天井ユニット4内には、浴室15やキッチン本体30を換気するための換気ダクト21が収容されている。トイレ室16内では、便器10の下側付近に開口22aを有していて臭気を吸引し排気する排気ダクト22も設置されている。これら換気ダクト21や排気ダクト22も起立ユニット3及び天井ユニット4を通って外部に延びている。なお、換気ダクト21に設けられる換気ファンや排気ダクト22に設けられる排気ファンは適宜の位置に設置されていればよく、例えば、起立ユニット3内に設置されていれもよいし、天井ユニット4内や外部に設置されていてもよい。
In the standing unit 3 and the ceiling unit 4, water is supplied to the hot water supply pipe 19 for supplying hot water to the bathtub 8 and the kitchen body 30, the bathtub 8 and the toilet bowl 10, and the water faucet of the kitchen body 30 and the washstand 33. The water supply pipe 20 to be performed is accommodated.
A ventilation duct 21 for ventilating the bathroom 15 and the kitchen body 30 is housed in the standing unit 3 and the ceiling unit 4. In the toilet room 16, an exhaust duct 22 that has an opening 22a near the lower side of the toilet 10 and sucks and exhausts odors is also installed. The ventilation duct 21 and the exhaust duct 22 also extend to the outside through the standing unit 3 and the ceiling unit 4. In addition, the ventilation fan provided in the ventilation duct 21 and the exhaust fan provided in the exhaust duct 22 should just be installed in an appropriate position, for example, may be installed in the standing unit 3, or in the ceiling unit 4 Or may be installed outside.

また、キッチン本体30の上部には上部キャビネット31の一部に代えて空調機23が側壁12aに設置されていてもよい。空調機23の送風は、例えば冷気は空調機23の吹き出し口から直接室内に送風してもよい。一方、温風は起立ユニット3内に上下方向に配設した図示しない空調ダクトを通して床仕上面近傍または足元から排気するように構成してもよい。
集約設備1内には、浴槽8や便器10、キッチン本体30や洗面台33等に給電したり信号送受信したりするための電気配線(配線)24も束ねて設置されているが、これら電気配線24は配線配管25内に通線していてもよいし、或いは配線配管25を用いずに、束ねてまたは個別に配設していてもよい。また、これらの配管以外に空調用の配管(冷媒配管)、ガス管等を含んでいてもよい。
In addition, an air conditioner 23 may be installed on the side wall 12 a instead of a part of the upper cabinet 31 at the upper part of the kitchen body 30. For example, cold air may be blown directly into the room from the air outlet of the air conditioner 23. On the other hand, the warm air may be configured to be exhausted from the vicinity of the floor finish surface or from the foot through an air conditioning duct (not shown) disposed in the upright direction in the standing unit 3.
In the aggregation facility 1, electric wiring (wiring) 24 for supplying power to the bathtub 8, the toilet bowl 10, the kitchen body 30, the wash basin 33, etc. and transmitting / receiving signals is also bundled and installed. 24 may be connected to the wiring pipe 25, or may be bundled or individually arranged without using the wiring pipe 25. In addition to these pipes, air-conditioning pipes (refrigerant pipes), gas pipes, and the like may be included.

なお、各配管や換気ダクト21、排気ダクト22等の断面形状は任意であり、天井ユニット4の高さを圧縮するために楕円形や長方形等の扁平な断面形状の配管やダクト等を採用してもよい。また、図6や図8において、本実施形態では、天井ユニット4を断面略U字状に形成して上部を天井側に開放したため、各配管や換気ダクト21や排気ダクト22や電気配線等を取り出し易くメンテナンスや交換等が容易になる。なお、天井ユニット4の上面に開閉可能な蓋を設置すれば、埃やごみ等の付着を防いで各部材のメンテナンスや交換等を容易に行える。   In addition, the cross-sectional shape of each piping, the ventilation duct 21, the exhaust duct 22, etc. is arbitrary, and in order to compress the height of the ceiling unit 4, piping, a duct, etc. of flat cross-sectional shapes, such as an ellipse and a rectangle, are employ | adopted. May be. 6 and 8, in this embodiment, since the ceiling unit 4 is formed in a substantially U-shaped cross section and the upper part is opened to the ceiling side, each pipe, ventilation duct 21, exhaust duct 22, electrical wiring, etc. Easy to take out and easy to maintain and replace. If a lid that can be opened and closed is installed on the upper surface of the ceiling unit 4, it is possible to easily maintain and replace each member while preventing adhesion of dust and dirt.

次に、浴室15の扉開閉構造について図3及び図4、図8乃至図10によって説明する。
図3及び図4、図8及び図9において、天井ユニット4の下面の幅方向両端部には例えば2対のガラス扉からなる開閉扉35が吊り下げ機構36によってスライド可能に吊り下げられている。図3及び図4、図8において、2対の開閉扉35は起立ユニット3側の側壁12a、12bの内側と浴槽8の外側(居住空間Kの壁面側)端部との間でそれぞれスライド可能に配設されている。なお、浴槽8の外側端部に目隠し用の間仕切り等を設けてもよい。
Next, the door opening and closing structure of the bathroom 15 will be described with reference to FIGS. 3, 4, and 8 to 10.
3, 4, 8, and 9, an opening / closing door 35 formed of, for example, two pairs of glass doors is slidably suspended by a suspension mechanism 36 at both ends in the width direction of the lower surface of the ceiling unit 4. . 3, 4, and 8, the two pairs of opening / closing doors 35 can slide between the inside of the side walls 12 a and 12 b on the standing unit 3 side and the outside of the bathtub 8 (the wall surface side of the living space K). It is arranged. In addition, you may provide the partition for blindfolds etc. in the outer side edge part of the bathtub 8. FIG.

開閉扉35が、浴室15の両側を仕切る側壁12a、12bと浴槽8の外側端部との間の空間をスライドすることで浴室15の開放空間Oを開閉できる。例えば、一対の開閉扉35を浴槽8の外側端部にスライドさせることで、開放空間Oの開口を通して入浴者が浴槽8に出入り可能となる。
図9において、吊り下げ機構36は、平面視略長方形の浴槽8を仕切る一対の長辺側部8aに対向する天井ユニット4の下面両側にそれぞれ設置されている。開閉扉35の外側には側壁12a、12b上にタイルパネル34が貼り付けられている。
The open / close door 35 can open and close the open space O of the bathroom 15 by sliding the space between the side walls 12 a and 12 b partitioning both sides of the bathroom 15 and the outer end of the bathtub 8. For example, the bather can enter and exit the bathtub 8 through the opening of the open space O by sliding the pair of opening / closing doors 35 to the outer end of the bathtub 8.
In FIG. 9, the suspension mechanisms 36 are respectively installed on both sides of the lower surface of the ceiling unit 4 facing the pair of long side portions 8 a that partition the bathtub 8 that is substantially rectangular in plan view. A tile panel 34 is attached to the outside of the open / close door 35 on the side walls 12a, 12b.

次に、図9及び図10によって、開閉扉35の吊り下げ機構36について詳述する。
図9及び図10において、天井ユニット4の下面の幅方向両端部に設けた一対のレール受け部40が天井ユニット4の長手方向に延びており、この一対のレール受け部40には浴室15の両側に沿ってスライド可能な開閉扉35の各複数対の車輪44が設置されている。浴槽8の外側端部と側壁12a、12bの間の浴室15の開放空間Oを各一対の開閉扉35で開閉可能とされている(図4参照)。
図10に示す吊り下げ機構36の拡大図において、天井ユニット4の幅方向両端下面には上部枠体37の下面にねじ止めされた下部枠体38が設置されている。下部枠体38内の上部には中央開口40bを挟んで両側に一対のレール部40aが形成されたレール受け部40が長手方向に沿って延びている。
Next, the suspension mechanism 36 of the open / close door 35 will be described in detail with reference to FIGS. 9 and 10.
9 and 10, a pair of rail receiving portions 40 provided at both ends in the width direction of the lower surface of the ceiling unit 4 extend in the longitudinal direction of the ceiling unit 4, and the pair of rail receiving portions 40 includes the bathroom 15. A plurality of pairs of wheels 44 of the open / close door 35 slidable along both sides are provided. The open space O of the bathroom 15 between the outer end of the bathtub 8 and the side walls 12a, 12b can be opened and closed by each pair of opening / closing doors 35 (see FIG. 4).
In the enlarged view of the suspension mechanism 36 shown in FIG. 10, a lower frame body 38 screwed to the lower surface of the upper frame body 37 is installed on the lower surface of both ends in the width direction of the ceiling unit 4. A rail receiving portion 40 having a pair of rail portions 40a formed on both sides of the central opening 40b is extended along the longitudinal direction at an upper portion in the lower frame 38.

一方、開閉扉35の上端部を両面側から挟んで支持する一対の支持部42の上部に支持軸43が突出形成されている。この支持軸43は中央開口40bを通してレール受け部40から下方の支持部42に延びており、支持軸43の上部両側にはレール部40aに載置されて摺動可能な一対の車輪44が支持されている。
一対の支持部42で挟持されて吊り下げられた開閉扉35は下方に垂下されており、図9に示すように、その下端部は浴槽8の長辺側部8aの天端に設けた受け溝46内に納められている。そのため、開閉扉35を天井ユニット4のレール受け部40に沿ってスライド移動させると、浴槽8の受け溝46にガイドされて摺動して開閉作動する。
On the other hand, a support shaft 43 projects from the upper part of a pair of support portions 42 that support the upper end portion of the open / close door 35 from both sides. The support shaft 43 extends from the rail receiving portion 40 to the lower support portion 42 through the central opening 40b, and a pair of slidable wheels 44 mounted on the rail portion 40a are supported on both sides of the upper portion of the support shaft 43. Has been.
The open / close door 35 sandwiched and suspended by the pair of support portions 42 hangs downward, and its lower end is a receiver provided at the top end of the long side portion 8a of the bathtub 8 as shown in FIG. It is stored in the groove 46. Therefore, when the open / close door 35 is slid along the rail receiving portion 40 of the ceiling unit 4, the open / close door 35 is guided and slid by the receiving groove 46 of the bathtub 8 to open and close.

なお、浴槽8の両側の長辺側部8aに設けた受け溝46は浴槽8の外側端部から起立ユニット3側に向けてわずかに下方傾斜しており、受け溝46内に落ち込んだ湯や水は起立ユニット3側に流れて浴槽8内に落下するように形成されている。また、受け溝46に流れ込んだ湯や水は、起立ユニット3側に流れて浴槽8の上面と起立ユニット3との隙間からその下方に設けた排水パンに誘導して起立ユニット3内の排水管に接続して排水するようにしてもよい。なお、受け溝46は、浴槽8の上縁面に形成される溝としたが、これに限られることなく、断面コ字状のレールを設けてもよい。
また、レール受け部40の起立ユニット3から離間した外側端部には開閉扉35が外れることを阻止するための図示しないストッパーが設けられている。
In addition, the receiving groove 46 provided in the long side part 8a on both sides of the bathtub 8 is slightly inclined downward from the outer end of the bathtub 8 toward the upright unit 3 side. Water is formed so as to flow to the standing unit 3 side and fall into the bathtub 8. Moreover, the hot water or water that has flowed into the receiving groove 46 flows to the standing unit 3 side and is guided to the drain pan provided below the upper surface of the bathtub 8 and the standing unit 3 to the drain pipe in the standing unit 3. You may make it drain by connecting to. The receiving groove 46 is a groove formed on the upper edge surface of the bathtub 8, but is not limited thereto, and a rail having a U-shaped cross section may be provided.
Further, a stopper (not shown) for preventing the opening / closing door 35 from coming off is provided at an outer end portion of the rail receiving portion 40 that is separated from the standing unit 3.

また、集約設備1における各配管等を収納した天井ユニット4は必ずしも断面略U字状に形成されていなくてもよい。例えば、図11(a)に示すように断面略矩形状の筒型に形成されていてもよいし、或いは図11(b)に示すように平板状等の載置面に形成されていてもよい。いずれの場合でも、天井ユニット4は第一排水管17や第二排水管18や給湯管19や給水管20や換気ダクト21や排気ダクト22等を居室空間Kの床仕上面側から目視できないように配設できればよく、美観を損ねることがない。   Moreover, the ceiling unit 4 which accommodated each piping etc. in the aggregation equipment 1 does not necessarily need to be formed in cross-sectional substantially U shape. For example, it may be formed in a cylindrical shape having a substantially rectangular cross section as shown in FIG. 11 (a), or may be formed on a mounting surface such as a flat plate as shown in FIG. 11 (b). Good. In any case, the ceiling unit 4 cannot see the first drain pipe 17, the second drain pipe 18, the hot water pipe 19, the water pipe 20, the ventilation duct 21, the exhaust duct 22, etc. from the floor finish surface side of the living room space K. As long as it can be disposed in the, the aesthetic appearance is not impaired.

次に起立ユニット3内に設置した電気系統について説明する。
図6において、起立ユニット3内には屋外の配電盤から幹線45を介して接続された分電盤47が設置され、分電盤47はリミッターや漏電遮断器や安全ブレーカー等を備えている。複数の安全ブレーカー48から引き出された複数の電気配線24は各水回り設備Mの電気設備や照明器具等から延びる電気配線24とインターフェース49を介してそれぞれ接続されている。
例えば、一部の電気配線24はインターフェース49を介してパネル材3bの連結凹部9に設けたコネクタt1に通電され、浴槽8のコネクタt2に電気的に接続されている。他の電気配線24によって各排水ポンプP1,P2内の駆動モータ等に通電できる。また、起立ユニット3のパネル材3bに開閉可能な扉を設けて分電盤47を目視確認できるようにした。なお、天井ユニット4に設置された幹線45を収納する配線配管25と、起立ユニット3の分電盤47の下方に設置された電気配線24を収納する配線配管25とが分離して配設されていてもよい。
Next, the electric system installed in the standing unit 3 will be described.
In FIG. 6, a distribution board 47 connected from an outdoor switchboard via a trunk line 45 is installed in the standing unit 3, and the distribution board 47 includes a limiter, a leakage breaker, a safety breaker, and the like. The plurality of electrical wires 24 drawn out from the plurality of safety breakers 48 are respectively connected to the electrical wires 24 extending from the electrical facilities of each watering facility M, the lighting fixtures, and the like through an interface 49.
For example, a part of the electrical wiring 24 is energized to the connector t1 provided in the connection recess 9 of the panel material 3b via the interface 49, and is electrically connected to the connector t2 of the bathtub 8. The other electric wiring 24 can energize the drive motors in the drainage pumps P1 and P2. Further, a door that can be opened and closed is provided on the panel material 3b of the standing unit 3 so that the distribution board 47 can be visually confirmed. In addition, the wiring pipe 25 for storing the main line 45 installed in the ceiling unit 4 and the wiring pipe 25 for storing the electric wiring 24 installed below the distribution board 47 of the standing unit 3 are separately provided. It may be.

また、起立ユニット3の各側面には、浴槽8への給湯や温度調整等を行うためのコントロールパネルや便器10の操作パネル等が設置されていてもよい(図示せず)。起立ユニット3の各側面には、照明、給湯、空調等を制御するスイッチ、コンセント、コントローラー、リモコンや、玄関等の周辺環境の状態を把握し制御するカメラ等の撮影機器または赤外線センサ等の監視機器等を制御する受像機やリモコン等を設置してもよい。そして、集約設備1の内部に収納した複数の電気配線24等を通して上述したスイッチやリモコン等に電力を供給したり制御信号を入出力したりすることができる。   Moreover, the control panel for performing hot water supply to the bathtub 8, temperature adjustment, etc., the operation panel of the toilet bowl 10, etc. may be installed in each side surface of the standing unit 3 (not shown). On each side of the standing unit 3, there is a switch for controlling lighting, hot water supply, air conditioning, etc., an outlet, a controller, a remote controller, and a photographing device such as a camera that grasps and controls the state of the surrounding environment such as the entrance, or an infrared sensor or the like. You may install the receiver, remote control, etc. which control apparatus etc. Then, it is possible to supply power and input / output control signals to the above-described switches, remote controllers, and the like through a plurality of electrical wires 24 and the like housed in the aggregation facility 1.

また、図8に示すように、天井ユニット4等の上部にはLED等の照明器具51が設置され、天井に向けて光を照射し反射させることで居室全体を間接照明することができる。一方、キッチン本体30や洗面台33等の下部には、その足元や巾木部分に照明器具52が設置され、夜間の足元照明とすることができる。また、上部キャビネット31や洗面台33の上部棚53の下面には棚下照明として照明器具54が設置されている。これらの照明群により、夜間、照明をほのかに照らすことで家の中での移動時の安全性向上等にも貢献する。
また、上述した集約設備1の側面に照明器具等を設置してもよく、例えば起立ユニット3の側面のパネル材3b等に照明器具を設置したり埋め込んだりしてもよい。
Moreover, as shown in FIG. 8, lighting fixtures 51, such as LED, are installed in the upper part of ceiling unit 4 grade | etc., And the whole living room can be indirectly illuminated by irradiating and reflecting light toward a ceiling. On the other hand, in the lower part of the kitchen body 30 and the wash basin 33, etc., lighting fixtures 52 are installed at the feet and the baseboard portions, so that it is possible to illuminate the feet at night. Moreover, the lighting fixture 54 is installed in the lower surface of the upper shelf 53 of the upper cabinet 31 or the wash basin 33 as under-shelf illumination. These lighting groups contribute to improving safety when moving in the house by illuminating the light at night.
Moreover, you may install a lighting fixture etc. in the side surface of the aggregation equipment 1 mentioned above, for example, you may install a lighting fixture in the panel material 3b etc. of the side surface of the standing unit 3, or may be embedded.

更に、起立ユニット3のパネル材3bからなる側面やコーナー部の足元付近や腰高付近、そしてキッチン本体30や洗面台33の足元付近等にコンセント56を設置した。これらのコンセント56は水回り設備Mに用いるものではなく、生活家電等の電源として用いることができる。これによって、タコ足配線にならず、腰高に設置することで高齢者等が掃除機等の使用時に使い勝手がよくなる。
通常の建築設計では、建物の施工時にコンセント56を設置した後、またはある期間生活した後で異なる場所に設置したいと考えることがある。本実施形態では、集約設備1の設置に合わせて最初から使いやすい位置に複数設置されているのでコンセント56の使いやすい空間を確保できる。
Furthermore, outlets 56 were installed near the sides and corners of the side and corners of the standing unit 3, near the waist, and near the feet of the kitchen body 30 and the washstand 33. These outlets 56 are not used for the water supply facility M, but can be used as a power source for household appliances. As a result, the octopus foot wiring is not used, but the waist and the like are installed, so that the elderly and the like are easy to use when using a vacuum cleaner or the like.
In normal architectural design, it may be desired to install the outlet 56 at the time of construction of the building or install it in a different place after living for a certain period. In the present embodiment, since a plurality of units are installed at easy-to-use positions from the beginning in accordance with the installation of the aggregation facility 1, an easy-to-use space for the outlet 56 can be secured.

本実施形態においては、起立ユニット3内に設けた第一及び第二排水管17,18や給湯管19や給水管20等の各種の配管や電気配線24等は床仕上面に引き込むことなく、床仕上面2側から起立ユニット3を通して立ち上げて天井ユニット4を介して天井側に取り回すように集約した。そのため、集約設備1とその周囲の浴槽8や便器10やキッチン本体30や洗面台33等の水回り設備Mを床仕上面2上で適宜位置に選択的に且つ容易に設置できる。そして、天井ユニット4から例えば居住空間Kの壁面を通して外部に延ばす等することができて、設置の自由度が高い。   In the present embodiment, various pipes such as the first and second drain pipes 17, 18, the hot water supply pipe 19, the water supply pipe 20, and the electric wiring 24 provided in the standing unit 3 are not drawn into the floor finish surface. From the floor finishing surface 2 side, it started up through the standing unit 3 and was aggregated so as to be routed through the ceiling unit 4 to the ceiling side. Therefore, it is possible to selectively and easily install the water facilities M such as the aggregation facility 1 and the surrounding bathtub 8, the toilet 10, the kitchen body 30, and the wash basin 33 on the floor finishing surface 2. And it can extend outside from the ceiling unit 4 through the wall surface of the living space K, for example, and the freedom degree of installation is high.

本実施形態による設備ユニットSは上述した構成を備えており、次にその施工方法について説明する。
まず、建築工事で床仕上面2まで施工する。このとき、床仕上面2の下部(二重床内)には設備配管類は一切設置する必要がないため、建築工事との取り合いがない。続いて、居室空間K内の適宜の位置に集約設備1の起立ユニット3を床仕上面2上に設置する。居室空間K内での起立ユニット3の設置位置は中央でもよいし、コーナー部でもよいし、或いはいずれかの壁面に近接または当接する位置に設置してもよい。図1に示す例では居室空間Kの中央付近に設置した。起立ユニット3の内部には第一排水ポンプP1と第二排水ポンプP2が設置されており、第一排水ポンプP1に第一排水管17を接続して上方に延ばしている。同様に第二排水ポンプP2に第二排水管18を接続して上方に延ばしている。
The equipment unit S according to the present embodiment has the above-described configuration, and the construction method will be described next.
First, the floor construction surface 2 is constructed by construction work. At this time, since there is no need to install any equipment piping under the floor finishing surface 2 (in the double floor), there is no interaction with the construction work. Subsequently, the standing unit 3 of the aggregation facility 1 is installed on the floor finishing surface 2 at an appropriate position in the living room space K. The installation position of the standing unit 3 in the living room space K may be the center, the corner, or the position close to or in contact with any wall surface. In the example shown in FIG. 1, it is installed near the center of the living room space K. A first drain pump P1 and a second drain pump P2 are installed inside the standing unit 3, and a first drain pipe 17 is connected to the first drain pump P1 and extends upward. Similarly, the second drainage pipe 18 is connected to the second drainage pump P2 and extends upward.

更に、給湯管19や給水管20や換気ダクト21や排気ダクト22等も同様に収納され、また分電盤47と電気配線24も起立ユニット3内に収納されている。なお、起立ユニット3は工場においてフレーム3aを構築し、その内部に適宜配管・配線・ダクト類や分電盤47等を取り付けた状態で現場に搬入し、施工現場にて起立ユニット3のパネル材3bを取り付けるようにしてもよいし、パネル材3bまで工場で取り付けて搬入するようにしてもよい。   Further, the hot water supply pipe 19, the water supply pipe 20, the ventilation duct 21, the exhaust duct 22, and the like are similarly stored, and the distribution board 47 and the electric wiring 24 are also stored in the standing unit 3. The stand-up unit 3 is constructed at the factory with a frame 3a, and is transported to the site with appropriate piping, wiring, ducts, distribution boards 47, etc. installed therein, and panel members of the stand-up unit 3 at the construction site. 3b may be attached, or the panel material 3b may be attached and carried in the factory.

図2及び図3において、起立ユニット3は例えば略角筒状であり、その側面に予め設けた連結部の連結凹部9と浴槽8の連結凸部13によって浴槽8を連結固定し、同時にコネクタt1、t2同士も電気的に接続する。これによって、浴室15の起立ユニット3の側面に設置した操作パネル等が通電状態になり、給湯や追い焚き等の各種の操作を行える。便器10も同様に連結部で機械的及び電気的に連結固定する。浴槽8の排水管を第一排水ポンプP1に、便器10の排水管を第二排水ポンプP2にそれぞれ接続する。また、起立ユニット3の他の対向する側面に設けた連結部にキッチン本体30と洗面台33をそれぞれ同様に機械的及び電気的に連結し、その排水管を第一排水ポンプP1に接続する。
しかも、起立ユニット3と各水回り設備Mとを各連結凹部9と連結凸部13からなる連結部によって連結することで、各水回り設備Mを精度よく取り付けることができ、各水回り設備Mを取り付ける際の墨出し等が不要になる。
2 and 3, the standing unit 3 has, for example, a substantially rectangular tube shape, and the bathtub 8 is connected and fixed by the connecting concave portion 9 of the connecting portion provided in advance on the side surface and the connecting convex portion 13 of the bathtub 8, and at the same time, the connector t1. , T2 are also electrically connected. As a result, the operation panel or the like installed on the side surface of the standing unit 3 in the bathroom 15 is energized, and various operations such as hot water supply and chasing can be performed. Similarly, the toilet 10 is mechanically and electrically connected and fixed at the connecting portion. The drain pipe of the bathtub 8 is connected to the first drain pump P1, and the drain pipe of the toilet 10 is connected to the second drain pump P2. Moreover, the kitchen main body 30 and the washstand 33 are similarly mechanically and electrically connected to the connection part provided in the other opposing side surface of the standing unit 3, respectively, and the drainage pipe is connected to the 1st drainage pump P1.
In addition, by connecting the standing unit 3 and each water supply facility M by a connecting portion including each connection recess 9 and the connection convex portion 13, each water supply facility M can be accurately attached. There is no need for ink marking when attaching.

これらの水回り設備Mは起立ユニット3の略角筒状の各側面に放射状に設置して設備ユニットSを形成する。しかも、各配管等は起立ユニット3を介して天井側に延ばすことで、各水回り設備Mの建築工事と設備工事との錯綜や取り合いをなくすことができる。図1に示すように、設備ユニットSを例えば居室空間Kの中央付近に設置することで、その周囲を有効活用することができる。
具体的には、設備ユニットSの周囲をリビングや寝室として利用したり、動線としての通路(廊下)や脱衣スペース、化粧直しのスペースとしても利用したりできる。つまり、余計な間仕切り壁などを設けることなく、居室空間Kを最大限有効活用することができる。また、設備ユニットSを中心に居室空間Kを図示しない壁面パネルや家具等で仕切ることで、トイレ室16や浴室15や台所や居室や洗面所やその廊下等を区画形成してもよい。
These watering facilities M are installed radially on each side of the upright unit 3 in a substantially rectangular tube shape to form an equipment unit S. In addition, by extending the pipes and the like to the ceiling side through the standing unit 3, it is possible to eliminate the complications and interactions between the construction work and the facility work of each watering facility M. As shown in FIG. 1, by installing the equipment unit S near the center of the living room space K, for example, the surroundings can be used effectively.
Specifically, the surroundings of the equipment unit S can be used as a living room or a bedroom, and can also be used as a passage (corridor) as a flow line, a dressing space, or a retouching space. In other words, the living room space K can be utilized to the maximum extent without providing an extra partition wall. Further, the toilet room 16, the bathroom 15, the kitchen, the living room, the washroom, and the corridor thereof may be partitioned by partitioning the room space K around the equipment unit S with a wall panel or furniture (not shown).

また、起立ユニット3の上端部に天井ユニット4を連結し、天井側に延ばした配管やダクト等を天井ユニット4上に載置する等して横方向にガイドして外部に突出させ外部配管等に連結させる。或いは、予め起立ユニット3に天井ユニット4を連結した略L字型の集約設備1を居室空間K内の床仕上面2に設置しておいてもよい。また、天井側に延ばした配管やダクト等は、天井ユニット4を設けない場合(図1参照)でも、天井に沿って横方向に配設することで壁面等を介して外部に突出させてもよい。
このようにして、居室空間K内の適宜位置に設備ユニットSを設置できる。
なお、起立ユニット3や各水回り設備Mの下面に予め床仕上面2上での滑りをよくする潤滑性の高いボード材(スライダーボード)を固定して置いてもよい。これによって、設備ユニットSの起立ユニット3や水回り設備Mを居室空間K内に設置したり移動させたりする場合に、重量があっても床仕上面2を傷つけることなくスムーズに移動させることができる。設備ユニットSを床仕上面2に固定する場合には、ネジ等で取り外し可能に床仕上面2に固定すればよい。
In addition, the ceiling unit 4 is connected to the upper end of the standing unit 3, and a pipe or duct extending to the ceiling side is placed on the ceiling unit 4 to be guided in the lateral direction so as to protrude to the outside. Connect to. Alternatively, a substantially L-shaped aggregation facility 1 in which the standing unit 3 and the ceiling unit 4 are connected in advance may be installed on the floor finishing surface 2 in the living room space K. In addition, pipes and ducts extending to the ceiling side may be protruded to the outside through a wall surface or the like even when the ceiling unit 4 is not provided (see FIG. 1) or disposed laterally along the ceiling. Good.
In this way, the equipment unit S can be installed at an appropriate position in the living room space K.
In addition, a board material (slider board) with high lubricity that improves sliding on the floor finish surface 2 may be previously fixed to the lower surface of the standing unit 3 and each watering facility M. As a result, when the standing unit 3 of the equipment unit S or the water supply equipment M is installed or moved in the living room space K, it can be moved smoothly without damaging the floor surface 2 even if it is heavy. it can. When the equipment unit S is fixed to the floor finishing surface 2, it may be fixed to the floor finishing surface 2 so as to be removable with screws or the like.

本実施形態による設備ユニットSの使用方法の一例を説明すると次の通りである。
集約設備1に設置した浴槽8は、使用状態で図2乃至図4に示すように床仕上面2上に設置されている。この状態で、図示しないコントロールパネルまたは操作パネルを操作して集約設備1内の給湯管19を通して浴槽8内に給湯する。給湯終了後、開閉扉35を浴槽8の長辺側部8aに形成した受け溝46に沿ってスライドして開口することで入浴者が浴室15内に入って入浴できる。なお、受け溝46に湯水等が流入したとしても、受け溝46は起立ユニット3側に傾斜しているために、受け溝46を経由して浴槽8内に流し込むことができる。
入浴後は浴槽8内の湯を排出させ、第一排水ポンプP1によって第一排水管17を通して天井側に圧送して排水する。
An example of how to use the equipment unit S according to the present embodiment will be described as follows.
The bathtub 8 installed in the aggregation facility 1 is installed on the floor finishing surface 2 as shown in FIGS. In this state, hot water is supplied into the bathtub 8 through the hot water supply pipe 19 in the aggregation facility 1 by operating a control panel or an operation panel (not shown). After the hot water supply is finished, the bather can enter the bathroom 15 and take a bath by sliding the opening / closing door 35 along the receiving groove 46 formed in the long side portion 8a of the bathtub 8 and opening it. Even if hot water or the like flows into the receiving groove 46, the receiving groove 46 can be poured into the bathtub 8 via the receiving groove 46 because the receiving groove 46 is inclined toward the standing unit 3.
After bathing, the hot water in the bathtub 8 is drained, and is drained by being pumped to the ceiling side through the first drain pipe 17 by the first drain pump P1.

次に、便器10を使用する場合には、常時、便座を加温できると共に使用後に操作パネルの操作によって局部を洗浄できる。そして、給水管20からの給水を予め溜めた図示しないタンクからの給水で便器10内の汚水や汚物等を流し、汚水や汚物等は排水管を介して第二排水ポンプP2に設けたタンクに排水される。第二排水ポンプP2では汚物や汚水がインペラ等で砕かれた状態で第二排水管18第を通して天井側に圧送して排水される。キッチン本体30や洗面台33においても、同様に給湯管19や給水管20から湯や水が給水され、排水として第一排水ポンプP1に排出される。   Next, when the toilet bowl 10 is used, the toilet seat can be always heated and the local portion can be washed by operating the operation panel after use. Then, the sewage and filth in the toilet bowl 10 are made to flow by water supplied from a tank (not shown) in which the water supply from the water supply pipe 20 is stored in advance, and the sewage and filth etc. flow into a tank provided in the second drainage pump P2 through the drain pipe. Drained. In the second drainage pump P2, filth and sewage are crushed by an impeller and the like, and are pumped and drained through the second drainage pipe 18 to the ceiling side. Similarly, in the kitchen body 30 and the wash basin 33, hot water or water is supplied from the hot water supply pipe 19 or the water supply pipe 20 and discharged to the first drain pump P1 as waste water.

上述したように、本実施形態による集約設備1を備えた設備ユニットSによれば、天井側に延びる各種配管やダクト等を収納した起立ユニット3を床仕上面2に設置した後で各側面に浴槽8や便器10等の水回り設備Mを連結するようにしたから、起立ユニット3回りに配管等や電気系統を集約して設置できる。しかも、配管等は床仕上面2に引き込んで床下から取り回すことがないため、一層施工工事が容易になる。建築工事と設備工事と配線工事等が錯綜することがなく、取り合いを減らして効率よく施工でき、居住空間K内での建築全体の工事を軽減し省施工になる。
また、分電盤47を起立ユニット3内に取り付けて電気配線24を接続することで、内部の配線系統や周囲に設置した各水回り設備Mへの配線、設備ユニットSの周囲に設置した照明器具の配線やコンセント等の設置等も集約できる。しかも、電気系統の設置に際してインターフェース49やコンセントt1、t2等を接続することで専門の電気工事士等によらず簡単に配電工事ができる。
As described above, according to the equipment unit S provided with the aggregation equipment 1 according to the present embodiment, the upright unit 3 containing various pipes and ducts extending to the ceiling side is installed on the floor surface 2 and then installed on each side surface. Since the water supply facilities M such as the bathtub 8 and the toilet bowl 10 are connected, piping and the electric system can be integrated and installed around the standing unit 3. Moreover, since the piping and the like are not drawn into the floor finishing surface 2 and routed from under the floor, construction work is further facilitated. Construction work, facility work, wiring work, etc. are not complicated, and the work can be efficiently performed with less work, and the construction of the entire building in the living space K is reduced and the work is saved.
Moreover, the distribution board 47 is installed in the upright unit 3 and the electrical wiring 24 is connected, so that the wiring to the internal wiring system and surrounding water facilities M installed in the surroundings, and the lighting installed around the equipment unit S are provided. Installation of equipment wiring and outlets can also be consolidated. In addition, when the electric system is installed, the interface 49 and the outlets t1, t2 and the like are connected so that the power distribution work can be easily performed without depending on a professional electrician or the like.

また、配管やダクトと電気系統等を収容した集約設備1と水回り設備Mを設備ユニットSとしてユニット化し集約して床仕上面2上の任意の位置に設置できるため、生活スタイルの多様化に対応できて住居構造の自由度が高い。しかも、起立ユニット3を中心として放射状に各種の水回り設備Mを設置できるため、水回り設備Mに隣接する居室スペースや廊下等の通路等を適宜選択できて多様な空間を選択でき、居住空間K全体に効率的な配置で装備できる。
起立ユニット3に各水回り設備Mを連結部で連結できるため、各水回り設備Mの位置調整や墨出し等が不要で位置ずれを抑制して施工精度が高い。
In addition, it is possible to diversify the lifestyle because the centralized facility 1 and the water supply facility M that accommodates pipes, ducts, electrical systems, etc. can be unitized as a unit S and installed at any position on the floor surface 2 It can be used and has a high degree of freedom in housing structure. Moreover, since various water facilities M can be installed radially around the standing unit 3, a living space adjacent to the water facilities M, a passage such as a corridor can be selected as appropriate, and various spaces can be selected. Equipped with efficient layout throughout K.
Since each water supply facility M can be connected to the standing unit 3 by a connecting portion, position adjustment of each water supply facility M, ink marking and the like are unnecessary, and displacement is suppressed and construction accuracy is high.

また、集約設備1は起立ユニット3が略角筒状であり、天井ユニット4を連結して略L字状に形成したため、従来のフレームユニット構造と比較して支持強度と剛性が高くねじれに強い。起立ユニット3の両側に構造部材(構造体)となる側壁12a、12bを設置して起立ユニット3の各側面にそれぞれ水回り設備Mを連結した構成であるため、一層高い支持強度を有する。
更に、集約設備1の起立ユニット3及び天井ユニット4は断面略筒状で大径の第一及び第二排水管17,18や給湯管19及び給水管20、そして換気ダクト21や排気ダクト22や分電盤47を含む電気系統等を集約して設置できる。そのため、設備の配設経路がまとまって単純化できて浴槽8や便器10等の各水回り設備Mへの接続とメンテナンスが容易である。また、天井ユニット4は断面略U字状であるため、各配管等のメンテナンスや交換等が容易である。
Further, since the upright unit 3 has a substantially rectangular tube shape and is formed in a substantially L shape by connecting the ceiling unit 4 in the aggregation facility 1, the support strength and rigidity are higher and the twisting resistance is stronger than the conventional frame unit structure. . Since the side walls 12a and 12b, which are structural members (structures), are installed on both sides of the standing unit 3 and the water facilities M are connected to the respective side surfaces of the standing unit 3, the support strength is further increased.
Further, the standing unit 3 and the ceiling unit 4 of the aggregation facility 1 are substantially cylindrical in cross section and have a large diameter first and second drain pipes 17 and 18, a hot water supply pipe 19 and a water supply pipe 20, a ventilation duct 21, an exhaust duct 22, The electrical system including the distribution board 47 can be integrated and installed. For this reason, the arrangement route of the facilities can be simplified and the connection and maintenance to each watering facility M such as the bathtub 8 and the toilet bowl 10 are easy. Moreover, since the ceiling unit 4 has a substantially U-shaped cross section, maintenance and replacement of each pipe and the like are easy.

なお、本発明による設備ユニットSは上述した実施形態に限定されるものではなく、本発明の趣旨を逸脱しない範囲で適宜の変更や置換等が可能である。以下に、本発明の変形例等について説明するが、上述した実施形態で説明した部品や部材等と同一または同様なものについては同一の符号を用いて説明を省略する。   Note that the equipment unit S according to the present invention is not limited to the above-described embodiment, and can be appropriately changed or replaced without departing from the spirit of the present invention. In the following, modifications and the like of the present invention will be described, but the same or similar parts and components as those described in the above-described embodiments will be described using the same reference numerals.

上述した実施形態において、設備ユニットSの集約設備1内に収納した各種配管を天井側に延ばすように構成したが、本発明では第一及び第二排水管17,18や給湯管19及び給水管20等の配管は床仕上面2の下側、例えば床仕上面2と床スラブの間の下部空間等に敷設してもよい。この場合には床仕上面2の下側で配管設置工事が必要になる。
なお、配管を床仕上面2に引き込んで床下から取り回す場合、第一及び第二排水管17,18において適切な排水勾配が確保できる場合には第一及び第二排水ポンプP1,P2を設置せず、排水を自然流下方式としてもよい。
また、上述した各配管やダクト等の少なくとも一部を集約設備1の起立ユニット3を通して天井側に誘導させ、残りの一部を床下側に誘導するように構成してもよい。
In the embodiment described above, the various pipes housed in the aggregation equipment 1 of the equipment unit S are configured to extend to the ceiling side. However, in the present invention, the first and second drain pipes 17 and 18, the hot water supply pipe 19 and the water supply pipe are used. The piping such as 20 may be laid on the lower side of the floor finishing surface 2, for example, in the lower space between the floor finishing surface 2 and the floor slab. In this case, piping installation work is required below the floor finishing surface 2.
When the pipe is drawn into the floor finishing surface 2 and routed from under the floor, the first and second drainage pumps P1 and P2 are installed when an appropriate drainage gradient can be secured in the first and second drainage pipes 17 and 18. Without draining, the drainage may be a natural flow method.
Further, at least a part of each of the above-described pipes and ducts may be guided to the ceiling side through the standing unit 3 of the aggregation facility 1 and the remaining part may be guided to the under floor side.

また、設備ユニットSにおいて、起立ユニット3の各側面に浴槽8、便器10、キッチン本体30、洗面台33を放射状に連結したが、配列は適宜選択できる。また、水回り設備Mは、必ずしも浴槽8、便器10、キッチン本体30、洗面台33の4種類全てを設置する必要はなく、任意の1種類以上を設置できればよい。
なお、水回り設備Mは上述した4種類のものに限定されるものではなく、適宜の設備を設置できる。例えば、浴槽8に加えて防水パンを設置してもよく、浴槽8の代わりに浴室ユニット、またはシャワーユニットを設置してもよい。さらには、便器10の代わりにトイレユニットを設置してもよい。全自動洗濯機等を設置してもよい。
また、水回り設備Mは、上述した浴槽8、便器10、キッチン本体30、洗面台33等の設備機器に代えて、浴槽8を有する浴室15、便器10を有するトイレ室16、キッチン本体30を備えた台所、洗面台33を備えた洗面所等の設備空間としてもよい。
Moreover, in the equipment unit S, although the bathtub 8, the toilet bowl 10, the kitchen main body 30, and the washstand 33 were connected to each side of the standing unit 3 radially, arrangement | sequence can be selected suitably. Moreover, it is not always necessary to install all four types of the water supply facility M, that is, the bathtub 8, the toilet 10, the kitchen body 30, and the wash basin 33, as long as any one or more types can be installed.
The water supply facility M is not limited to the four types described above, and appropriate facilities can be installed. For example, a waterproof pan may be installed in addition to the bathtub 8, and a bathroom unit or a shower unit may be installed instead of the bathtub 8. Furthermore, a toilet unit may be installed instead of the toilet bowl 10. A fully automatic washing machine or the like may be installed.
Moreover, instead of the above-described equipment such as the bathtub 8, the toilet 10, the kitchen body 30, and the wash basin 33, the watering facility M includes a bathroom 15 having the bathtub 8, a toilet room 16 having the toilet 10, and the kitchen body 30. It is good also as equipment spaces, such as a kitchen provided, and a washroom provided with the washstand 33.

また、集約設備1において、起立ユニット3に必ずしも天井ユニット4を連結する必要はなく、起立ユニット3だけを設置してもよい。この場合、各配管は起立ユニット3の上端から湾曲させて居住空間Kの壁面等の適宜方向に延ばせばよい。その際、各配管が大径で湾曲することで通水時等に暴れることを防ぐために略L字状のエルボー配管を配設してその両端部に分断した配管の各端部をそれぞれ連結してもよい。   In the aggregation facility 1, it is not always necessary to connect the ceiling unit 4 to the standing unit 3, and only the standing unit 3 may be installed. In this case, each pipe may be curved from the upper end of the standing unit 3 and extended in an appropriate direction such as a wall surface of the living space K. At that time, in order to prevent the pipes from being curved with large diameters and being exposed to water, etc., a substantially L-shaped elbow pipe is arranged, and each end of the pipe divided at both ends is connected. May be.

なお、起立ユニット3の上部から建物の居住空間Kの壁面方向に向かって、あるいは、角筒状の起立ユニット3の4つの側面に対して直交する各方向に配管やダクト等を支持するフレームや天井ユニット4等が設けられていてもよい。また、起立ユニット3から延びるフレームや天井ユニット4等にスライド扉もしくはカーテン等の空間を仕切る機構が取り付けられていてもよい。
フレームや天井ユニット4等に設置したスライド扉やカーテン等の仕切り部材は、未使用時には起立ユニット3の周囲や周辺、もしくは壁面側に収納されたり畳まれたりして設置してもよい。
A frame that supports pipes, ducts and the like from the upper part of the standing unit 3 toward the wall surface of the living space K of the building, or in each direction orthogonal to the four side surfaces of the rectangular tubular standing unit 3 A ceiling unit 4 or the like may be provided. Further, a mechanism for partitioning a space such as a sliding door or a curtain may be attached to the frame extending from the standing unit 3, the ceiling unit 4, or the like.
Partition members such as slide doors and curtains installed on the frame, the ceiling unit 4 and the like may be installed around the upright unit 3 or around the upright unit 3 or on the wall side when not in use.

本発明による設備ユニットSにおいて、居住空間Kを広く使う場合、浴槽8や便器10やトイレ本体30や洗面台33等の水回り設備Mが起立ユニット3に対して常設の仕切り壁等のような仕切り部材を設けずにオープンな空間に設定する場合がある。この場合、仕切り部材がないため他人の視線や臭気、湿気や水はね等が周囲に流れたり飛散したりするおそれがある。   In the equipment unit S according to the present invention, when the living space K is widely used, water facilities M such as the bathtub 8, the toilet 10, the toilet body 30, the wash basin 33, etc. There is a case where an open space is set without providing a partition member. In this case, since there is no partition member, there is a possibility that another person's line of sight, odor, moisture, water splash, etc. may flow or scatter around.

上述した問題点を考慮すると、使用時のみ用いる仕切り壁等の仕切り部材を設ける必要がある。
その為、起立ユニット3から延びるフレームもしくは天井ユニット4等にスライド扉やカーテン等を設置することで、設備ユニット3を設けた居住空間Kを通常はオープンな空間とし、各種の水回り設備Mの使用時にはスライド扉やカーテン等で仕切って浴室15やトイレ室16等をクローズに仕切ることができる。そのため、居住空間Kを広く、かつ水回りも快適に使用することができる。
しかも、居住空間K内のこれらのフレームや天井ユニット4にスライド扉やカーテン等のような仕切り部材を設けるだけで良い。また、これらの仕切り部材は、通常時は邪魔にならないように起立ユニット3の周囲、周辺、もしくは居住空間Kの壁面側に収納されていても良い。
Considering the above-described problems, it is necessary to provide a partition member such as a partition wall used only during use.
Therefore, by installing sliding doors, curtains, etc. on the frame extending from the standing unit 3 or the ceiling unit 4 etc., the living space K provided with the equipment unit 3 is usually an open space, and various watering equipment M When in use, the bathroom 15 or the toilet room 16 can be partitioned by a sliding door or curtain. Therefore, the living space K can be widened and the water can be used comfortably.
Moreover, it is only necessary to provide a partition member such as a sliding door or a curtain on the frame or the ceiling unit 4 in the living space K. In addition, these partition members may be housed around the standing unit 3 or around the standing unit 3 or on the wall surface side of the living space K so as not to disturb the normal state.

S 設備ユニット
1 集約設備
3 起立ユニット
4 天井ユニット
8 浴槽
10 便器
12a、12b 側壁
15 浴室
16 トイレ室
17 第一排水管
18 第二排水管
19 給湯管
20 給水管
21 換気ダクト
22 排気ダクト
24 電気配線
25 配線配管
30 キッチン本体
33 洗面台
35 開閉扉
47 分電盤
49 インターフェース
P1 第一排水ポンプ
P2 第二排水ポンプ
M 水回り設備
S equipment unit 1 aggregation equipment 3 standing unit 4 ceiling unit 8 bathtub 10 toilet 12a, 12b side wall 15 bathroom 16 toilet room 17 first drain pipe 18 second drain pipe 19 hot water pipe 20 water pipe 21 ventilation duct 22 exhaust duct 24 electric wiring 25 Wiring and piping 30 Kitchen body
33 Wash basin 35 Open / close door 47 Distribution board 49 Interface P1 First drain pump P2 Second drain pump M

Claims (11)

少なくとも給水管及び排水管を収容していると共に、前記給水管と排水管の少なくとも一方を接続させる水回り設備を固定可能な連結部を備えたことを特徴とする集約設備。   An aggregation facility characterized in that at least a water supply pipe and a drain pipe are accommodated, and a connecting portion capable of fixing a watering facility for connecting at least one of the water supply pipe and the drain pipe is provided. 少なくとも給水管及び排水管を収容していると共に、外部から延びる幹線に接続された分電盤を収容していることを特徴とする集約設備。   An aggregation facility characterized in that it contains at least a water supply pipe and a drain pipe and a distribution board connected to a main line extending from the outside. 前記分電盤から延びる電気配線と側部に設置可能な水回り設備に接続される電気配線とがインターフェースを介して接続されている請求項2に記載された集約設備。   The aggregation facility according to claim 2, wherein an electrical wiring extending from the distribution board and an electrical wiring connected to a water supply facility that can be installed on a side portion are connected via an interface. 電気配線と換気ダクトが更に収容されている請求項1または2に記載された集約設備。   The aggregation facility according to claim 1, further comprising an electrical wiring and a ventilation duct. 前記排水管に接続された排水ポンプが設けられている請求項1から4のいずれか1項に記載された集約設備。   The aggregation facility according to claim 1, wherein a drainage pump connected to the drainage pipe is provided. 前記集約設備はパネルで仕切られており、前記パネルに水回り設備を連結する連結部が設けられている請求項1から5のいずれか1項に記載された集約設備。   The aggregation facility according to any one of claims 1 to 5, wherein the aggregation facility is partitioned by a panel, and a connecting portion that connects a water supply facility to the panel is provided. 前記給水管及び排水管は上下方向に延びる起立ユニットに収容されており、該起立ユニットの上部から前記給水管及び排水管を取り出して外部に延ばした請求項1から6のいずれか1項に記載された集約設備。   The said water supply pipe and drainage pipe are accommodated in the standing unit extended in an up-down direction, The said water supply pipe and drainage pipe were taken out from the upper part of this standing unit, and were extended to the exterior. Aggregated equipment. 前記起立ユニットの上部には前記給水管及び排水管を載置して横方向に延びる天井ユニットが連結されている請求項7に記載された集約設備。   The aggregation facility according to claim 7, wherein a ceiling unit that extends in a horizontal direction by placing the water supply pipe and the drain pipe is connected to an upper portion of the standing unit. 前記集約設備は側部に水回り設備を放射状に設置可能とした請求項1から8のいずれか1項に記載された集約設備。   The aggregation facility according to any one of claims 1 to 8, wherein the aggregation facility is configured such that water-side facilities can be radially installed on a side portion. 前記集約設備には照明器具が設置されている請求項1から9のいずれか1項に記載された集約設備。   The aggregation facility according to claim 1, wherein a lighting fixture is installed in the aggregation facility. 給水管及び排水管と電気配線を収容した集約設備を備えており、
前記集約設備の側部には、前記給水管と排水管の少なくとも一方を接続させる水回り設備が設置され、該水回り設備には前記電気配線が電気的に接続されていることを特徴とする設備ユニット。
It is equipped with centralized facilities that contain water supply and drainage pipes and electrical wiring.
A watering facility for connecting at least one of the water supply pipe and the drainage pipe is installed on a side of the aggregation facility, and the electrical wiring is electrically connected to the watering facility. Equipment unit.
JP2016147660A 2016-07-27 2016-07-27 Integration equipment and equipment unit equipped with the same Pending JP2018017007A (en)

Priority Applications (2)

Application Number Priority Date Filing Date Title
JP2016147660A JP2018017007A (en) 2016-07-27 2016-07-27 Integration equipment and equipment unit equipped with the same
PCT/JP2017/013538 WO2018020740A1 (en) 2016-07-27 2017-03-31 Facility core structure and facility unit construction method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP2016147660A JP2018017007A (en) 2016-07-27 2016-07-27 Integration equipment and equipment unit equipped with the same

Publications (1)

Publication Number Publication Date
JP2018017007A true JP2018017007A (en) 2018-02-01

Family

ID=61081432

Family Applications (1)

Application Number Title Priority Date Filing Date
JP2016147660A Pending JP2018017007A (en) 2016-07-27 2016-07-27 Integration equipment and equipment unit equipped with the same

Country Status (1)

Country Link
JP (1) JP2018017007A (en)

Citations (9)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH01142143A (en) * 1987-11-27 1989-06-05 Takenaka Komuten Co Ltd Multifunctional framing in building
JPH08209786A (en) * 1995-02-06 1996-08-13 Inax Corp Connection structure of toilet bowl and discharge water pipe
JP2006045945A (en) * 2004-08-05 2006-02-16 Nishihara Engineering Co Ltd Air conditioning equipment and plumbing equipment in building
JP2006070539A (en) * 2004-09-01 2006-03-16 Mitsubishi Plastics Ind Ltd Piping decorative cover
JP2007056514A (en) * 2005-08-23 2007-03-08 Komatsu House Ltd Home care unit and construction method of care space
JP2010101138A (en) * 2008-10-27 2010-05-06 Panasonic Electric Works Co Ltd Power supply structure of water section equipment unit
JP2011111756A (en) * 2009-11-25 2011-06-09 Panasonic Electric Works Co Ltd Wall panel for bathroom
JP2015086596A (en) * 2013-10-31 2015-05-07 株式会社Lixil Sanitary facility unit and dwelling structure
JP2016118072A (en) * 2014-12-22 2016-06-30 株式会社大林組 Indoor structure unit and indoor structure

Patent Citations (9)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH01142143A (en) * 1987-11-27 1989-06-05 Takenaka Komuten Co Ltd Multifunctional framing in building
JPH08209786A (en) * 1995-02-06 1996-08-13 Inax Corp Connection structure of toilet bowl and discharge water pipe
JP2006045945A (en) * 2004-08-05 2006-02-16 Nishihara Engineering Co Ltd Air conditioning equipment and plumbing equipment in building
JP2006070539A (en) * 2004-09-01 2006-03-16 Mitsubishi Plastics Ind Ltd Piping decorative cover
JP2007056514A (en) * 2005-08-23 2007-03-08 Komatsu House Ltd Home care unit and construction method of care space
JP2010101138A (en) * 2008-10-27 2010-05-06 Panasonic Electric Works Co Ltd Power supply structure of water section equipment unit
JP2011111756A (en) * 2009-11-25 2011-06-09 Panasonic Electric Works Co Ltd Wall panel for bathroom
JP2015086596A (en) * 2013-10-31 2015-05-07 株式会社Lixil Sanitary facility unit and dwelling structure
JP2016118072A (en) * 2014-12-22 2016-06-30 株式会社大林組 Indoor structure unit and indoor structure

Similar Documents

Publication Publication Date Title
US4118854A (en) Powder room and bathroom system and method of assembling same
US3221454A (en) Pre-fabricated utility building assembly
WO2015064298A1 (en) Sanitary equipment unit and dwelling structure
US4574533A (en) Portable home
EP3759286B1 (en) Prefabricated sanitary modular kit
EP0731020A1 (en) Prefabricated cubicle for sanitary facilities, in particular in the cabins of ships, or the like
US20070283488A1 (en) Hygiene device
WO2018020740A1 (en) Facility core structure and facility unit construction method
JP6713870B2 (en) Bathtub equipment
JP2018017006A (en) Facility unit and dwelling structure
JP2018017007A (en) Integration equipment and equipment unit equipped with the same
JP2018017005A (en) Construction method of equipment unit
US2557470A (en) Unitary bathroom structure
JPS63132615A (en) Bathtub unit with low window
JP3182313B2 (en) Residential interior structure, interior wall structure and unit equipment room
JP6685846B2 (en) Self-supporting equipment unit
WO2020264231A1 (en) Bathroom module
JP2006045945A (en) Air conditioning equipment and plumbing equipment in building
JP2979831B2 (en) Unit bathroom drainage structure
JPH0433034Y2 (en)
JP2010203112A (en) Bathroom unit and method for installing the same
IT201800020662A1 (en) FURNITURE STRUCTURE
CN203320982U (en) Water-saving type double-layer house
JPS63304843A (en) Sanitary equipment room
Friederich et al. Planning the electrical installation

Legal Events

Date Code Title Description
A80 Written request to apply exceptions to lack of novelty of invention

Free format text: JAPANESE INTERMEDIATE CODE: A80

Effective date: 20160826

A621 Written request for application examination

Free format text: JAPANESE INTERMEDIATE CODE: A621

Effective date: 20190314

A131 Notification of reasons for refusal

Free format text: JAPANESE INTERMEDIATE CODE: A131

Effective date: 20200128

A521 Request for written amendment filed

Free format text: JAPANESE INTERMEDIATE CODE: A523

Effective date: 20200317

A131 Notification of reasons for refusal

Free format text: JAPANESE INTERMEDIATE CODE: A131

Effective date: 20200602

A521 Request for written amendment filed

Free format text: JAPANESE INTERMEDIATE CODE: A523

Effective date: 20200729

A02 Decision of refusal

Free format text: JAPANESE INTERMEDIATE CODE: A02

Effective date: 20200915