JP2017182766A - Cost price distribution calculation processor, cost price distribution calculation processing method, and cost price distribution calculation processing program - Google Patents

Cost price distribution calculation processor, cost price distribution calculation processing method, and cost price distribution calculation processing program Download PDF

Info

Publication number
JP2017182766A
JP2017182766A JP2016188497A JP2016188497A JP2017182766A JP 2017182766 A JP2017182766 A JP 2017182766A JP 2016188497 A JP2016188497 A JP 2016188497A JP 2016188497 A JP2016188497 A JP 2016188497A JP 2017182766 A JP2017182766 A JP 2017182766A
Authority
JP
Japan
Prior art keywords
allocation
meter
amount
calculation
data
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
JP2016188497A
Other languages
Japanese (ja)
Other versions
JP6872337B2 (en
Inventor
法晴 卯月
Noriharu Uzuki
法晴 卯月
康平 都澤
Kohei Miyakozawa
康平 都澤
大輔 境
Daisuke Sakai
大輔 境
邦明 芹澤
Kuniaki Serizawa
邦明 芹澤
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Obic Co Ltd
Original Assignee
Obic Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Obic Co Ltd filed Critical Obic Co Ltd
Publication of JP2017182766A publication Critical patent/JP2017182766A/en
Application granted granted Critical
Publication of JP6872337B2 publication Critical patent/JP6872337B2/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Management, Administration, Business Operations System, And Electronic Commerce (AREA)
  • Financial Or Insurance-Related Operations Such As Payment And Settlement (AREA)

Abstract

PROBLEM TO BE SOLVED: To provide a cost price distribution calculation processor in which a cost price distribution calculation is performed based on a complex calculation method different according to a building and a journal entry can be created based on the result of the distribution calculation thereof.SOLUTION: A cost price distribution calculation processor 100 includes a controller 102. The controller 102 comprises: a metering meter data file 106a which stores metering meter data with respect to water supply, electricity, heat supply, or gas used in a building, and amount data with respect to the water supply, the electricity, the heat supply, or the gas used in the building; a distribution procedure master 106c which stores a distribution procedure associating an operation method calculating used amount of the water supply, the electricity, the heat supply, or the gas based on the metering meter data with a distribution basis of the used amount; and a calculation unit 102a which calculates distribution amount based on the metering meter data, the amount data and the distribution method.SELECTED DRAWING: Figure 1

Description

本発明は、原価配賦計算処理装置、原価配賦計算処理方法、および、原価配賦計算処理プログラムに関する。   The present invention relates to a cost allocation calculation processing device, a cost allocation calculation processing method, and a cost allocation calculation processing program.

特許文献1には、家主からの請求書に基づいて、データの入力が行われると、データ入力端末は、各転借人別に転借料や電気料等を按分して計算し、支払データや請求データをネットワークサーバへ送信する。ネットワークサーバでは、支払データや請求データを支払先別、請求先別に振り分け、集計し、さらに社内経理システムによって処理される支払伝票や請求伝票のフォーマットに対応させて編集処理する。例えば月末になると、ネットワークサーバから編集された支払データや請求データが伝票処理端末を介して社内経理システムへ転送され、蓄積されると共に伝票が起票され、支払伝票データや請求伝票データが伝票処理端末を介してプリンタへ送信され、支払伝票や請求伝票が出力される支払請求業務支援システムが開示されている。   In Patent Document 1, when data is input based on an invoice from the landlord, the data input terminal apportions and calculates the subcontracting fee, the electric fee, etc. for each lessee, and the payment data and billing data. To the network server. The network server sorts and aggregates payment data and billing data by payee and billing destination, and further edits the data according to the format of the payment slip and billing slip processed by the internal accounting system. For example, at the end of the month, payment data and billing data edited from the network server are transferred to the in-house accounting system via the slip processing terminal, stored and drafted, and payment slip data and billing slip data are slip processed. A payment request business support system is disclosed in which a payment slip and a billing slip are output to a printer via a terminal.

特開2002−83228号公報JP 2002-83228 A

しかしながら、上記特許文献1では、検針メーター毎の使用量の演算、面積按分・固定比率・使用量按分などの配賦基準、多段階配賦などで発生する配賦手順に基づいて、ビル毎に異なる複雑な計算方法による原価の配賦計算を行ったり、その計算結果から仕訳を作成したりすることができないという課題があった。   However, in Patent Document 1 described above, each building is calculated on the basis of calculation of usage for each meter-reading meter, allocation criteria such as area apportionment, fixed ratio, apportionment apportionment, etc. There has been a problem that it is impossible to perform cost allocation calculation by different complicated calculation methods and to create journals from the calculation results.

本発明は、上記問題点に鑑みてなされたものであって、ビル毎に異なる複雑な計算方法により原価の配賦計算を行うと共に、その配賦計算結果から仕訳を作成することが可能な原価配賦計算処理装置、原価配賦計算処理方法、および、原価配賦計算処理プログラムを提供することを目的とする。   The present invention has been made in view of the above problems, and performs cost allocation calculation by a complicated calculation method different for each building, and can generate a journal from the allocation calculation result. An object is to provide an allocation calculation processing device, a cost allocation calculation processing method, and a cost allocation calculation processing program.

上述した課題を解決し、目的を達成するために、本発明に係る原価配賦計算処理装置は、制御部を備えた原価配賦計算処理装置であって、前記制御部は、ビルで使用した水道、電気、熱供給、または、ガスに関する検針メーターデータと、当該ビルで使用した水道、電気、熱供給、または、ガスに関する金額データとを記憶する検針メーターデータ記憶手段と、検針メーターデータから水道、電気、熱供給、または、ガスの使用量を演算する演算方法と、前記使用量に対する配賦基準と、を紐付けた配賦手順を記憶する配賦手順記憶手段と、前記検針メーターデータ、前記金額データおよび前記配賦手順に基づいて、配賦金額を算出する算出手段と、を備えたことを特徴とする。   In order to solve the above-described problems and achieve the object, a cost allocation calculation processing device according to the present invention is a cost allocation calculation processing device including a control unit, and the control unit is used in a building. Meter reading data storage means for storing meter reading meter data relating to water supply, electricity, heat supply or gas, and amount data relating to water supply, electricity, heat supply or gas used in the building, and tap water from meter reading meter data An allocation procedure storage means for storing an allocation procedure in which a calculation method for calculating the usage amount of electricity, heat supply, or gas, and an allocation standard for the usage amount, and the meter-reading meter data, And calculating means for calculating an allocation amount based on the amount data and the allocation procedure.

また、本発明に係る原価配賦計算処理装置は、前記制御部は、配賦金額に基づいて、仕訳を作成する仕訳作成手段を更に備えたこと、を特徴とする。   The cost allocation calculation processing apparatus according to the present invention is characterized in that the control unit further includes journal creation means for creating a journal based on the allocated amount.

また、本発明に係る原価配賦計算処理装置は、前記配賦基準は、面積按分、固定比率、もしくは、水道、電気、熱供給またはガスの使用量按分であること、を特徴とする。   The cost allocation calculation processing apparatus according to the present invention is characterized in that the allocation standard is an area apportionment, a fixed ratio, or an apportionment of water, electricity, heat supply or gas usage.

また、本発明に係る原価配賦計算処理装置は、前記使用量は、前記ビルのテナントの使用量であること、を特徴とする。   The cost allocation calculation processing apparatus according to the present invention is characterized in that the usage amount is a usage amount of a tenant of the building.

また、本発明に係る原価配賦計算処理方法は、制御部を備えた原価配賦計算処理装置に実行させるための原価配賦計算処理方法であって、前記制御部で実行される、ビルで使用した水道、電気、熱供給、または、ガスに関する検針メーターデータと、当該ビルで使用した水道、電気、熱供給、または、ガスに関する金額データとを記憶する検針メーターデータ記憶ステップと、検針メーターデータから水道、電気、熱供給、または、ガスの使用量を演算する演算方法と、前記使用量に対する配賦基準と、を紐付けた配賦手順を記憶する配賦手順記憶ステップと、前記検針メーターデータ、前記金額データおよび前記配賦手順に基づいて、配賦金額を算出する算出ステップと、を含むことを特徴とする。   Further, a cost allocation calculation processing method according to the present invention is a cost allocation calculation processing method for causing a cost allocation calculation processing apparatus having a control unit to execute, and is executed by the control unit. Meter-meter data storage step for storing meter-meter data related to used water, electricity, heat supply, or gas, and amount-of-money data related to water, electricity, heat supply, or gas used in the building, meter-reading meter data An allocation procedure storage step for storing an allocation procedure in which a calculation method for calculating the usage amount of water, electricity, heat supply, or gas from the distribution amount and an allocation standard for the usage amount is stored; and the meter-reading meter And a calculation step of calculating an allocation amount based on the data, the amount data, and the allocation procedure.

また、本発明に係る原価配賦計算処理プログラムは、制御部を備えた原価配賦計算処理装置に実行させるための原価配賦計算処理プログラムであって、前記制御部において、ビルで使用した水道、電気、熱供給、または、ガスに関する検針メーターデータと、当該ビルで使用した水道、電気、熱供給、または、ガスに関する金額データとを記憶する検針メーターデータ記憶ステップと、検針メーターデータから水道、電気、熱供給、または、ガスの使用量を演算する演算方法と、前記使用量に対する配賦基準と、を紐付けた配賦手順を記憶する配賦手順記憶ステップと、前記検針メーターデータ、前記金額データおよび前記配賦手順に基づいて、配賦金額を算出する算出ステップと、を実行させることを特徴とする。   A cost allocation calculation processing program according to the present invention is a cost allocation calculation processing program for causing a cost allocation calculation processing device provided with a control unit to execute the water supply used in a building in the control unit. Meter meter data storage step for storing meter reading meter data relating to electricity, heat supply or gas and amount data relating to water, electricity, heat supply or gas used in the building, An allocation procedure storage step for storing an allocation procedure in which a calculation method for calculating the usage amount of electricity, heat supply, or gas, and an allocation reference for the usage amount, the meter-reading meter data, And a calculation step of calculating an allocation amount based on the amount data and the allocation procedure.

本発明によれば、ビル毎に異なる複雑な計算方法により原価の配賦計算を行うと共に、その配賦計算結果から仕訳を作成することが可能になるという効果を奏する。   According to the present invention, it is possible to perform cost allocation calculation by a complicated calculation method that is different for each building and to create a journal from the allocation calculation result.

図1は、原価配賦計算処理装置の構成の一例を示すブロック図である。FIG. 1 is a block diagram illustrating an example of a configuration of a cost allocation calculation processing apparatus. 図2は、原価配賦計算処理装置にて実行される処理の一例を示すフローチャートである。FIG. 2 is a flowchart illustrating an example of processing executed by the cost allocation calculation processing device. 図3は、原価配賦計算処理装置の原価配賦計算処理画面の一例を示す図である。FIG. 3 is a diagram illustrating an example of a cost allocation calculation processing screen of the cost allocation calculation processing device. 図4は、検針メーターデータファイルの一例を示す図である。FIG. 4 is a diagram showing an example of a meter-reading meter data file. 図5は、配賦パックマスタの一例を示す図である。FIG. 5 is a diagram illustrating an example of an allocation pack master. 図6は、配賦手順マスタの一例を示す図である。FIG. 6 is a diagram illustrating an example of an allocation procedure master. 図7は、演算マスタの一例を示す図である。FIG. 7 is a diagram illustrating an example of a calculation master. 図8は、配賦基準マスタの一例を示す図である。FIG. 8 is a diagram illustrating an example of an allocation reference master. 図9は、配賦経過の一例を示す図である。FIG. 9 is a diagram illustrating an example of allocation progress. 図10は、検針メーターデータファイルの一例を示す図である。FIG. 10 is a diagram showing an example of a meter reading meter data file. 図11は、配賦パックマスタの一例を示す図である。FIG. 11 is a diagram illustrating an example of an allocation pack master. 図12は、配賦手順マスタの一例を示す図である。FIG. 12 is a diagram illustrating an example of an allocation procedure master. 図13は、演算マスタの一例を示す図である。FIG. 13 is a diagram illustrating an example of a calculation master. 図14は、配賦基準マスタの一例を示す図である。FIG. 14 is a diagram illustrating an example of an allocation reference master. 図15は、配賦経過の一例を示す図である。FIG. 15 is a diagram illustrating an example of allocation progress.

本発明の実施形態を図面に基づいて詳細に説明する。なお、本発明は本実施形態により限定されるものではない。   Embodiments of the present invention will be described in detail with reference to the drawings. In addition, this invention is not limited by this embodiment.

[1.概要]
これまでは、ビル毎に配賦基準も異なり、且つ大規模ビルになるほどメーター(検針メーター)管理、配賦の仕組みも複雑であったため、個社対応で作り込み部分が多く発生することから、システム化することが困難だった。
[1. Overview]
Until now, the allocation standards differ for each building, and the larger the building, the more complicated the meter (metering meter) management and allocation mechanism. It was difficult to systematize.

本実施形態に係る原価配賦計算処理装置100は、検針メーター毎の使用量の演算、面積按分、固定比率および使用量按分などの配賦基準、多段階配賦などで発生する配賦手順をそれぞれマスタ化し、ビル毎に設定したそれらのマスタを配賦パックとして一元管理することで、ビル毎に異なる複雑な計算方法による水道光熱費等の原価の配賦計算が可能となり、その計算結果からの仕訳作成も行うことが可能となった。つまり、本実施形態に係る原価配賦計算処理装置100は、ビル毎に設定した水道光熱費等の原価について、予め設定した配賦パターンマスタの情報を元に配賦する仕組みであって、配賦基準、多段階配賦、あるいは、配賦手順の設定が可能である。また、請求処理についてもコアロジックが流用可能である。   The cost allocation calculation processing apparatus 100 according to the present embodiment performs an allocation procedure generated by calculation of usage amount for each meter-reading meter, allocation criteria such as area apportionment, fixed ratio, apportionment apportionment, and multi-stage allocation. By making each master a master and centrally managing those masters set for each building as a distribution pack, it becomes possible to calculate the cost allocation of utilities such as water and utility bills by a complicated calculation method that differs for each building. It is also possible to create journal entries. In other words, the cost allocation calculation processing apparatus 100 according to the present embodiment is a mechanism that allocates costs such as utility costs set for each building based on information of a preset allocation pattern master. Allocation criteria, multi-level allocation, or allocation procedure can be set. The core logic can also be used for billing.

[2.構成]
本実施形態に係る原価配賦計算処理装置100の構成の一例について、図1を参照して説明する。図1は、原価配賦計算処理装置100の構成の一例を示すブロック図である。
[2. Constitution]
An example of the configuration of the cost allocation calculation processing apparatus 100 according to the present embodiment will be described with reference to FIG. FIG. 1 is a block diagram illustrating an example of the configuration of the cost allocation calculation processing apparatus 100.

原価配賦計算処理装置100は、市販のデスクトップ型パーソナルコンピュータである。なお、原価配賦計算処理装置100は、デスクトップ型パーソナルコンピュータのような据置型情報処理装置に限らず、市販されているノート型パーソナルコンピュータ、PDA(Personal Digital Assistants)、スマートフォン、タブレット型パーソナルコンピュータなどの携帯型情報処理装置であってもよい。   The cost allocation calculation processing apparatus 100 is a commercially available desktop personal computer. The cost allocation calculation processing apparatus 100 is not limited to a stationary information processing apparatus such as a desktop personal computer, but is a commercially available notebook personal computer, PDA (Personal Digital Assistants), smartphone, tablet personal computer, or the like. It may be a portable information processing apparatus.

原価配賦計算処理装置100は、制御部102と通信インターフェース部104と記憶部106と入出力インターフェース部108と、を備えている。原価配賦計算処理装置100が備えている各部は、任意の通信路を介して通信可能に接続されている。   The cost allocation calculation processing apparatus 100 includes a control unit 102, a communication interface unit 104, a storage unit 106, and an input / output interface unit 108. Each unit included in the cost allocation calculation processing apparatus 100 is connected to be communicable via an arbitrary communication path.

通信インターフェース部104は、ルータ等の通信装置及び専用線等の有線又は無線の通信回線を介して、原価配賦計算処理装置100をネットワーク300に通信可能に接続する。通信インターフェース部104は、他の装置と通信回線を介してデータを通信する機能を有する。ここで、ネットワーク300は、原価配賦計算処理装置100とサーバ200とを相互に通信可能に接続する機能を有し、例えばインターネットやLAN(Local Area Network)等である。   The communication interface unit 104 communicatively connects the cost allocation calculation processing device 100 to the network 300 via a communication device such as a router and a wired or wireless communication line such as a dedicated line. The communication interface unit 104 has a function of communicating data with other devices via a communication line. Here, the network 300 has a function of connecting the cost allocation calculation processing apparatus 100 and the server 200 so that they can communicate with each other, and is, for example, the Internet or a LAN (Local Area Network).

記憶部106には、各種のデータベース、テーブル、及びファイルなどが格納される。記憶部106には、OS(Operating System)と協働してCPU(Central Processing Unit)に命令を与えて各種処理を行うためのコンピュータプログラムが記録される。記憶部106として、例えば、RAM(Random Access Memory)・ROM(Read Only Memory)等のメモリ装置、ハードディスクのような固定ディスク装置、フレキシブルディスク、及び光ディスク等を用いることができる。記憶部106は、検針メーターデータファイル106aと、配賦パックマスタ106bと、配賦手順マスタ106cと、演算マスタ106dと、配賦基準マスタ106eと、配賦金額テーブル106fと、仕訳データテーブル106gとを備えている。   The storage unit 106 stores various databases, tables, files, and the like. The storage unit 106 stores a computer program for giving various instructions to a CPU (Central Processing Unit) in cooperation with an OS (Operating System). As the storage unit 106, for example, a memory device such as a RAM (Random Access Memory) and a ROM (Read Only Memory), a fixed disk device such as a hard disk, a flexible disk, and an optical disk can be used. The storage unit 106 includes a meter-reading meter data file 106a, an allocation pack master 106b, an allocation procedure master 106c, a calculation master 106d, an allocation reference master 106e, an allocation amount table 106f, and a journal data table 106g. It has.

検針メーターデータファイル106aは、ビルで使用した水道、電気、熱供給、または、ガスに関する検針メーターデータ(検針値データ)と、当該ビルで使用した水道、電気、熱供給、または、ガスに関する金額データ(光熱水費支払登録データ)とを記憶するファイルである。   The meter-reading meter data file 106a includes meter-reading meter data (meter-reading value data) related to water, electricity, heat supply, or gas used in a building, and monetary data related to water, electricity, heat supply, or gas used in the building. It is a file for storing (thermal energy bill payment registration data).

なお、検針値データは、例えば、検針区分(例えば、電気、水道、熱供給、ガス、など)、検針物件コード(検針物件CD)、検針を開始した月(検針該当月開始)、検針を終了した月(検針該当月終了)、メーター(検針メーター)コード(CD)およびメーターの使用量を含むものであってもよい。また、光熱水費支払登録データは、検針区分、支払先、検針物件CD、検針該当月開始、検針該当月終了、管理項目(例えば、電気代、水道代、熱供給代、ガス代、など)、使用量、金額、消費税、税込金額を含むものである。また、検針値データは、電力(電気)、水道、熱供給、ガスなどの区分ごとに用意されていてもよい。   The meter reading value data includes, for example, meter reading classification (for example, electricity, water supply, heat supply, gas, etc.), meter reading property code (meter reading property CD), month when meter reading is started (start of meter reading applicable month), and meter reading is completed. Month (end of meter reading applicable month), meter (meter reading meter) code (CD) and meter usage amount may be included. Also, the utility bill payment registration data includes meter reading category, payment destination, meter reading property CD, meter reading start month, meter reading end month, management items (for example, electricity bill, water bill, heat supply bill, gas bill, etc.) , Including usage, amount, consumption tax, tax included. Moreover, the meter reading value data may be prepared for each category such as electric power (electricity), water supply, heat supply, and gas.

配賦パックマスタ106bは、配賦の処理手順の設定を管理するマスタである。   The allocation pack master 106b is a master that manages the setting of allocation processing procedures.

なお、配賦パックマスタ106bは、例えば、配賦パックコード(配賦パックCD)、配賦パック名、配賦手順コード(配賦手順CD)、処理順などのデータを管理してもよい。   The allocation pack master 106b may manage data such as an allocation pack code (distribution pack CD), an allocation pack name, an allocation procedure code (allocation procedure CD), and a processing order.

配賦手順マスタ106cは、検針メーターデータから水道、電気、熱供給、または、ガスの使用量を演算する演算方法と、当該使用量に対する配賦基準と、を紐付けた配賦手順の設定を管理するマスタである。   The allocation procedure master 106c sets the allocation procedure that links the calculation method for calculating the usage amount of water, electricity, heat supply, or gas from the meter-reading meter data and the allocation standard for the usage amount. It is a master to manage.

なお、配賦手順マスタ106cは、例えば、配賦手順CD、配賦手順名、手順ID、配賦手順区分、原価の発生元(配賦元)であって使用量の演算対象となるグループを示す配賦元演算グループコード(配賦元演算グループCD)、配賦元検針物件を識別するためのデータ、配賦元検針区分、配賦元科目、配賦元部門および配賦基準コード(配賦基準CD)などを管理してもよい。   The allocation procedure master 106c includes, for example, an allocation procedure CD, an allocation procedure name, a procedure ID, an allocation procedure classification, a cost generation source (allocation source), and a group for which usage is calculated. Allocation source calculation group code (distribution source calculation group CD), data for identifying allocation source meter reading property, allocation source meter classification, allocation source item, allocation source department and allocation standard code (allocation) Qualification criteria CD) may be managed.

演算マスタ106dは、配賦基準値となる値(例えば、メーター(検針メーター)同士の使用量)の演算方法の設定(加減の設定、演算に必要な要素、など)を管理するマスタである。   The calculation master 106d is a master that manages setting of calculation methods (addition / subtraction settings, elements necessary for calculation, etc.) of values (for example, amounts used between meters (meter-reading meters)) serving as allocation reference values.

なお、演算マスタ106dは、例えば、演算グループCD、演算グループ名、メーターCDおよび演算データ(メーター同士の使用量の演算における加減等の定義を示すデータ)などを管理してもよい。   Note that the calculation master 106d may manage, for example, the calculation group CD, the calculation group name, the meter CD, and calculation data (data indicating the definition of addition / subtraction in the calculation of the usage amount between meters).

配賦基準マスタ106eは、各配賦対象(原価を配賦する対象であって、例えば、科目、部門、など)へ原価を配賦する際の、配賦係数(配賦基準)の設定を管理するマスタである。   The allocation standard master 106e sets the allocation coefficient (allocation standard) when allocating the cost to each allocation target (the target to allocate the cost, for example, item, department, etc.). It is a master to manage.

なお、配賦基準マスタ106eは、例えば、配賦基準CD、配賦基準名、配賦先科目、配賦先部門、配賦先メーター、配賦基準区分、配賦係数および端数調整区分などのデータを管理してもよい。また、端数調整区分は変数を格納するものであり、「1」が格納されている場合、演算結果の端数を切捨てることを意味し、「2」が格納されている場合、演算結果の端数を四捨五入することを意味し、「3」が格納されている場合、演算結果の端数を切上げることを意味し、「4」が格納されている場合、演算結果の端数を調整することを意味するように設定していてもよい。   The allocation standard master 106e includes, for example, an allocation standard CD, an allocation standard name, an allocation destination item, an allocation destination department, an allocation destination meter, an allocation standard category, an allocation coefficient, and a fraction adjustment category. Data may be managed. The fraction adjustment category stores variables. When “1” is stored, it means that the fraction of the operation result is rounded down. When “2” is stored, the fraction of the operation result is stored. Is rounded off. If "3" is stored, it means rounding up the operation result. If "4" is stored, it means adjusting the operation result. You may set as follows.

配賦金額テーブル106fは、配賦金額を管理するテーブルである。   The allocation amount table 106f is a table for managing the allocation amount.

仕訳データテーブル106gは、配賦金額に基づいて、作成された仕訳(仕訳データ)を管理するテーブルである。   The journal data table 106g is a table for managing a journal (journal data) created based on the allocated amount.

入出力インターフェース部108には、入力装置112及び出力装置114が接続されている。出力装置114には、モニタ(家庭用テレビを含む)の他、スピーカやプリンタを用いることができる。入力装置112には、キーボード、マウス、及びマイクの他、マウスと協働してポインティングデバイス機能を実現するモニタを用いることができる。なお、以下では、出力装置114をモニタ114とし、入力装置112をキーボード112またはマウス112として記載する場合がある。   An input device 112 and an output device 114 are connected to the input / output interface unit 108. As the output device 114, a speaker (including a home television), a speaker, and a printer can be used. As the input device 112, in addition to a keyboard, a mouse, and a microphone, a monitor that realizes a pointing device function in cooperation with the mouse can be used. In the following description, the output device 114 may be described as the monitor 114, and the input device 112 may be described as the keyboard 112 or the mouse 112.

制御部102は、原価配賦計算処理装置100を統括的に制御するCPU等である。制御部102は、OS等の制御プログラム・各種の処理手順等を規定したプログラム・所要データなどを格納するための内部メモリを有し、格納されているこれらのプログラムに基づいて、種々の情報処理を実行する。制御部102は、機能概念的に、算出部102aと、仕訳作成部102bと、配賦パックマスタメンテ102cと、配賦手順マスタメンテ102dと、演算マスタメンテ102eと、配賦基準マスタメンテ102fとを備えている。   The control unit 102 is a CPU or the like that comprehensively controls the cost allocation calculation processing apparatus 100. The control unit 102 has an internal memory for storing a control program such as an OS, a program defining various processing procedures, and necessary data, and various information processing based on these stored programs. Execute. In terms of functional concept, the control unit 102 includes a calculation unit 102a, a journal creation unit 102b, an allocation pack master maintenance 102c, an allocation procedure master maintenance 102d, a calculation master maintenance 102e, and an allocation reference master maintenance 102f. It has.

算出部102aは、検針値データ、光熱水費支払登録データおよび配賦手順に基づいて、配賦金額を算出する。   The calculation unit 102a calculates the allocation amount based on the meter reading value data, the utility water payment registration data, and the allocation procedure.

仕訳作成部102bは、配賦金額に基づいて、仕訳を作成する。   The journal creation unit 102b creates a journal based on the allocated amount.

配賦パックマスタメンテ102cは、配賦の処理手順を管理する。   The allocation pack master maintenance 102c manages the allocation processing procedure.

配賦手順マスタメンテ102dは、配賦元と、配賦基準とを紐付けた配賦手順を管理する。なお、配賦手順マスタメンテ102dは、例えば、メーター(検針メーター)個別の使用量を配賦元にするか、使用量を演算する際に対象となる演算グループ(演算GP)を配賦元にするか、科目を配賦元にするか、を設定可能にしてもよい。   The allocation procedure master maintenance 102d manages an allocation procedure in which an allocation source and an allocation standard are linked. The allocation procedure master maintenance 102d uses, for example, the meter (meter reading meter) individual usage amount as the allocation source, or sets the target calculation group (calculation GP) when calculating the usage amount as the allocation source. It may be possible to set whether the subject is an allocation source.

演算マスタメンテ102eは、配賦基準値となる値の演算方法を管理する。   The calculation master maintenance 102e manages a calculation method of a value serving as an allocation reference value.

配賦基準マスタメンテ102fは、各配賦対象へ原価を配賦する際の配賦係数を管理する。なお、配賦基準マスタメンテ102fは、配賦係数を、面積按分、固定配賦および使用量基準配賦(使用量按分)の3つのパターンで設定可能としてもよい。   The allocation reference master maintenance 102f manages an allocation coefficient when distributing the cost to each allocation target. The allocation standard master maintenance 102f may be able to set the allocation coefficient in three patterns of area apportionment, fixed apportionment, and use amount reference apportionment (use apportionment apportionment).

[3.処理の具体例]
本実施形態の具体例について、図2から図15を参照して説明する。図2は、原価配賦計算処理装置100にて実行される処理の一例を示すフローチャートである。
[3. Specific example of processing]
A specific example of this embodiment will be described with reference to FIGS. FIG. 2 is a flowchart illustrating an example of processing executed by the cost allocation calculation processing device 100.

図2に示すように、まず、算出部102aは、検針メーターデータファイル106aに記憶されている、ビルで使用した水道、電気、熱供給、または、ガスに関する検針メーターデータ(検針値データ)、配賦パックマスタ106bに記憶されている、当該ビルで使用した水道、電気、熱供給、または、ガスに関する金額データ(光熱水費支払登録データ)、並びに、配賦手順マスタ106cに記憶されている、検針メーターデータから水道、電気、熱供給、または、ガスの使用量を演算する演算方法と、当該使用量に対する配賦基準と、を紐付けた配賦手順に基づいて、配賦金額を算出し、配賦金額テーブル106fに格納する(ステップS1)。   As shown in FIG. 2, first, the calculation unit 102a stores meter reading meter data (meter reading value data) relating to water, electricity, heat supply, or gas used in the building, which is stored in the meter reading meter data file 106a. Amount data (water / water bill payment registration data) related to water, electricity, heat supply, or gas used in the building, stored in the distribution pack master 106b, and stored in the distribution procedure master 106c, The allocation amount is calculated based on the allocation procedure that links the usage method of water, electricity, heat supply, or gas from meter reading meter data and the allocation standard for the usage. And stored in the allocation amount table 106f (step S1).

次に、図2に示すように、仕訳作成部102bは、配賦金額に基づいて、仕訳(仕訳データ)を作成して、仕訳データテーブル106gに格納し(ステップS2)、処理を終了する。   Next, as shown in FIG. 2, the journal creation unit 102b creates a journal (journal data) based on the allocated amount, stores it in the journal data table 106g (step S2), and ends the process.

なお、仕訳作成部102bは、ステップS1にて算出した配賦金額に基づいて、例えば、配賦元から各配賦対象へ配賦金額を振り替える振替仕訳に関する仕訳データを作成してもよい。   The journal creation unit 102b may create journal data related to transfer journals that transfer the allocation amount from the allocation source to each allocation target, for example, based on the allocation amount calculated in step S1.

また、本実施形態において、原価配賦計算処理を行う場合、オペレータは、出力装置114に表示される原価配賦計算処理画面Mの各項目(領域)に抽出条件(検針メーターデータファイル106aから抽出するデータの条件、配賦パックマスタ106bの指定条件など)を入力し、F10:実行ボタンを押下することで、原価配賦計算処理が実行されてもよい。   Further, in the present embodiment, when performing the cost allocation calculation process, the operator extracts an extraction condition (extracted from the meter-reading meter data file 106a) in each item (area) of the cost allocation calculation processing screen M displayed on the output device 114. The cost allocation calculation process may be executed by inputting the data conditions to be executed, the designation conditions of the allocation pack master 106b, etc.) and pressing the F10: execute button.

ここで、図3を参照して、原価配賦計算処理画面Mの構成例を説明する。図3は、原価配賦計算処理装置100の原価配賦計算処理画面Mの一例を示す図である。   Here, a configuration example of the cost allocation calculation processing screen M will be described with reference to FIG. FIG. 3 is a diagram illustrating an example of the cost allocation calculation processing screen M of the cost allocation calculation processing device 100.

図3に示すように、原価配賦計算処理画面Mは、大別して、該当月Fromを指定するための領域M1と、該当月Toを指定するための領域M2と、配賦パックを指定するための領域M3と、エラーファイル(CSVファイル)の出力先を指定するための領域M4とで構成されている。   As shown in FIG. 3, the cost allocation calculation processing screen M is roughly divided into an area M1 for designating the corresponding month From, an area M2 for designating the corresponding month To, and an allocation pack. Area M3 and an area M4 for designating the output destination of the error file (CSV file).

なお、原価配賦計算処理画面Mに入力された抽出条件について、エラーチェックが行われてもよい。エラーチェックは、例えば、(1)マスタ未登録チェック、(2)仕訳計上済みチェックなどであってもよい。   Note that an error check may be performed on the extraction condition input in the cost allocation calculation processing screen M. The error check may be, for example, (1) a master unregistered check, (2) a journal entry checked check, or the like.

ここで、上記(1)マスタ未登録チェックは、例えば、配賦パックマスタ106b、配賦手順マスタ106c、演算グループマスタ(演算マスタ106d)および配賦基準マスタ106eにて各マスタメンテの設定が未登録である場合、エラーとしてもよい。また、配賦パックマスタ106bをチェックする場合、配賦パックマスタメンテ102cによる設定が登録されているか確認し、登録されていない場合、エラー内容「配賦パックマスタが未登録です。」をオペレータに通知してもよい。また、配賦手順マスタ106cをチェックする場合、配賦パックマスタ106bに設定されている配賦手順マスタ106cが登録されているか確認し、登録されていない場合、エラー内容「配賦手順マスタが未登録です。」をオペレータに通知してもよい。また、演算マスタ106dをチェックする場合、配賦手順マスタ106cに設定されている演算マスタ106dが登録されているか確認し、登録されていない場合、エラー内容「演算マスタが未登録です。」をオペレータに通知してもよい。また、配賦基準マスタ106eをチェックする場合、配賦手順マスタ106cに設定されている配賦基準マスタ106eが登録されているか確認し、登録されていない場合、エラー内容「配賦基準マスタが未登録です。」をオペレータに通知してもよい。   Here, (1) master unregistration check is, for example, that each master maintenance is not set in the distribution pack master 106b, the allocation procedure master 106c, the calculation group master (calculation master 106d), and the allocation reference master 106e. If it is registration, an error may occur. In addition, when checking the distribution pack master 106b, it is confirmed whether the setting by the distribution pack master maintenance 102c is registered. If the setting is not registered, the error content “Distribution pack master is not registered” is sent to the operator. You may be notified. Also, when checking the allocation procedure master 106c, it is confirmed whether the allocation procedure master 106c set in the allocation pack master 106b is registered. "Registration" may be notified to the operator. In addition, when checking the calculation master 106d, it is confirmed whether the calculation master 106d set in the allocation procedure master 106c is registered. If the calculation master 106d is not registered, an error message “Calculation master is not registered” is displayed. May be notified. In addition, when checking the allocation standard master 106e, it is confirmed whether the allocation standard master 106e set in the allocation procedure master 106c is registered. "Registration" may be notified to the operator.

また、上記(2)仕訳計上済みチェックは、例えば、振替仕訳(仕訳データ)が作成済みの場合に再度原価配賦計算処理を実行した場合をエラーとし、エラー内容「振替仕訳計上済みデータがあります。」をオペレータに通知してもよい。   In addition, in the above (2) Check journal entry check, for example, if transfer journals (journal data) have been created, an error will occur if the cost allocation calculation process is executed again. May be notified to the operator.

(処理具体例1)
ここで、例えば、大阪サンプルビルを対象とした場合のステップS1(図2参照)における算出部102aの処理具体例について、図4から図9を参照して説明する。図4は、検針メーターデータファイル106aの一例を示す図である。図5は、配賦パックマスタ106bの一例を示す図である。図6は、配賦手順マスタ106cの一例を示す図である。図7は、演算マスタ106dの一例を示す図である。図8は、配賦基準マスタ106eの一例を示す図である。図9は、配賦経過の一例を示す図である。
(Processing Example 1)
Here, for example, a specific processing example of the calculation unit 102a in step S1 (see FIG. 2) when the Osaka sample building is targeted will be described with reference to FIGS. FIG. 4 is a diagram illustrating an example of the meter-reading meter data file 106a. FIG. 5 is a diagram illustrating an example of the distribution pack master 106b. FIG. 6 is a diagram illustrating an example of the allocation procedure master 106c. FIG. 7 is a diagram illustrating an example of the calculation master 106d. FIG. 8 is a diagram illustrating an example of the allocation reference master 106e. FIG. 9 is a diagram illustrating an example of allocation progress.

なお、本説明では、検針メーターデータファイル106aには、図4に示すように、電力(電気)に関する検針メーターデータ(検針値データ)と、水道に関する検針メーターデータ(検針値データ)と、光熱水費支払登録データとが格納されていることを前提とする。   In this description, as shown in FIG. 4, the meter-reading meter data file 106a includes meter-reading meter data (meter-reading value data) related to electric power (electricity), meter-reading meter data (meter-reading value data) related to water supply, and photothermal water. It is assumed that the expense payment registration data is stored.

また、本説明では、あらかじめ配賦パックマスタメンテ102cによる管理(マスタメンテ)が行われ、配賦の処理手順が、図5に示す配賦パックマスタ106bにて管理されているものとする。   Further, in this description, it is assumed that management (master maintenance) by the allocation pack master maintenance 102c is performed in advance, and the allocation processing procedure is managed by the allocation pack master 106b shown in FIG.

なお、本説明では、配賦パックマスタ106bに、エネルギー会社へ支払う金額(原価)を各科目または各部門に配賦するために必要な使用量を計算するステップ(配賦ステップ(I))と、配賦ステップ(I)で求めた使用量または固定値を配賦係数(配賦基準)として、各科目または各部門へ原価を配賦するステップ(配賦ステップ(II))が設定されているものとする。   In addition, in this description, the step (allocation step (I)) of calculating the usage amount required to allocate the amount (cost) paid to the energy company to each item or each department in the allocation pack master 106b; The step (allocation step (II)) that allocates the cost to each item or department is set with the usage amount or fixed value obtained in allocation step (I) as the allocation coefficient (allocation standard) It shall be.

また、本説明では、あらかじめ配賦手順マスタメンテ102dによる管理が行われ、配賦元と配賦基準の紐付けの設定が、図6に示す配賦手順マスタ106cにて管理されているものとする。   In this description, management by the allocation procedure master maintenance 102d is performed in advance, and the setting of the association between the allocation source and the allocation standard is managed by the allocation procedure master 106c shown in FIG. To do.

なお、配賦手順マスタメンテ102dは、メーター個別の使用量を配賦元にするか、演算GP(演算グループ)を配賦元にするか、または、科目を配賦元にするかを設定可能にしてもよい。   In addition, the allocation procedure master maintenance 102d can set whether the usage amount of each meter is the allocation source, the calculation GP (calculation group) is the allocation source, or the item is the allocation source. It may be.

また、本説明では、あらかじめ演算マスタメンテ102eによる管理が行われ、メーター同士の使用量の加減の設定が、図7に示す演算マスタ106dにて管理されているものとする。   Further, in this description, it is assumed that management by the operation master maintenance 102e is performed in advance, and the setting for adjusting the amount of use between the meters is managed by the operation master 106d shown in FIG.

また、本説明では、あらかじめ配賦基準マスタメンテ102fによる管理が行われ、各科目または各部門へ配賦する際の配賦係数(配賦基準)の設定が、図8に示す配賦基準マスタ106eにて管理されているものとする。   Further, in this description, management by the allocation standard master maintenance 102f is performed in advance, and the allocation coefficient (allocation standard) setting for allocation to each item or each department is the allocation standard master shown in FIG. It is assumed that it is managed at 106e.

以上、図4から図8に基づく配賦経過の一例を、図9を用いて説明する。まず、エネルギー会社へ支払う金額を各科目または各部門に配賦するために必要な使用量を計算する配賦ステップ(I)において、算出部102aは、(1)から(4)の値を用いて計算を行い、各科目または各部門に配賦するために必要な使用量((5)の値)を算出する。   An example of the allocation process based on FIGS. 4 to 8 will be described with reference to FIG. First, in the allocation step (I) for calculating the usage amount required to allocate the amount paid to the energy company to each subject or each department, the calculation unit 102a uses the values (1) to (4). To calculate the amount of use (value of (5)) necessary for allocation to each subject or department.

そして、配賦ステップ(I)で求めた使用量((5)の値)、または固定値を配賦係数として、算出部102aは、各科目または各部門へ原価を配賦する配賦ステップ(II)において、(5)から(7)までの値を用いて計算を行い、各科目または各部門への原価の配賦金額((8)の値)を算出する。   Then, the calculation unit 102a allocates the cost to each item or each department using the usage amount (value of (5)) obtained in the allocation step (I) or a fixed value as an allocation coefficient ( In II), the calculation is performed using the values from (5) to (7) to calculate the cost allocation amount (value of (8)) to each item or department.

そして、算出部102aは、算出した配賦金額を配賦金額テーブル106fに格納する。   Then, the calculation unit 102a stores the calculated allocation amount in the allocation amount table 106f.

以上で、(処理具体例1)の説明を終了する。   This is the end of the description of (Processing Example 1).

(処理具体例2)
更に、例えば、東京サンプルビルを対象とした場合のステップS1(図2参照)における算出部102aの処理具体例について、図10から図15を参照して説明する。図10は、検針メーターデータファイル106aの一例を示す図である。図11は、配賦パックマスタ106bの一例を示す図である。図12は、配賦手順マスタ106cの一例を示す図である。図13は、演算マスタ106dの一例を示す図である。図14は、配賦基準マスタ106eの一例を示す図である。図15は、配賦経過の一例を示す図である。
(Processing Example 2)
Further, for example, a specific processing example of the calculation unit 102a in step S1 (see FIG. 2) when the Tokyo sample building is targeted will be described with reference to FIGS. FIG. 10 is a diagram illustrating an example of the meter-reading meter data file 106a. FIG. 11 is a diagram illustrating an example of the allocation pack master 106b. FIG. 12 is a diagram illustrating an example of the allocation procedure master 106c. FIG. 13 is a diagram illustrating an example of the operation master 106d. FIG. 14 is a diagram illustrating an example of the allocation reference master 106e. FIG. 15 is a diagram illustrating an example of allocation progress.

なお、本説明では、検針メーターデータファイル106aには、図10に示すように、電力に関する検針値データと、水道に関する検針値データと、光熱水費支払登録データと、が格納されていることを前提とする。   In the present description, as shown in FIG. 10, the meter-reading meter data file 106a stores meter-reading value data related to power, meter-reading value data related to water supply, and utility bill payment registration data. It is assumed.

また、本説明では、あらかじめ配賦パックマスタメンテ102cによる管理が行われ、配賦の処理手順の設定が、図11に示す配賦パックマスタ106bにて管理されているものとする。   Further, in this description, it is assumed that management by the allocation pack master maintenance 102c is performed in advance, and setting of the allocation processing procedure is managed by the allocation pack master 106b shown in FIG.

なお、本説明では、配賦パックマスタ106bに、エネルギー会社へ支払う金額を各科目または各部門に配賦するために必要な使用量を計算するステップ(配賦ステップ(I))と、配賦ステップ(I)で求めた使用量、または固定値を配賦係数として、各科目または各部門へ原価を配賦するステップ(配賦ステップ(II))と、配賦ステップ(II)で求めた各科目または各部門の振替金額をさらに別の科目または部門へ配賦(2段階配賦)するステップ(配賦ステップ(III))と、が設定されているものとする。   In this description, the allocation pack master 106b calculates the amount used to allocate the amount to be paid to the energy company to each item or department (allocation step (I)), Using the amount used in step (I) or a fixed value as an allocation coefficient, the cost was allocated to each item or department (allocation step (II)) and the allocation step (II) It is assumed that a step (allocation step (III)) for allocating the transfer amount of each item or department to another item or department (allocation step (III)) is set.

また、本説明では、あらかじめ配賦手順マスタメンテ102dによる管理が行われ、配賦元と配賦基準の紐付けの設定が、配賦手順マスタ106cにて管理されているものとする。   Further, in this description, it is assumed that management by the allocation procedure master maintenance 102d is performed in advance, and that the allocation procedure master 106c manages the allocation of the allocation source and the allocation standard.

なお、本説明では、2段階配賦(配賦ステップ(III))を行うため、図6の例と異なり、配賦ステップ(III)に係る配賦手順(配賦手順名「2次配賦」のレコードに格納されているデータ(図12参照))の設定まで行っている。   In this description, since two-stage allocation (allocation step (III)) is performed, unlike the example of FIG. 6, the allocation procedure (allocation procedure name “secondary allocation” related to allocation step (III) is used. ”(Data stored in the record (see FIG. 12)) is set.

また、本説明では、あらかじめ演算マスタメンテ102eによる管理が行われ、メーター同士の使用量の加減の設定が、図13に示す演算マスタ106dにて管理されているものとする。   Further, in this description, it is assumed that management by the operation master maintenance 102e is performed in advance, and the setting for adjusting the amount of use between the meters is managed by the operation master 106d shown in FIG.

また、本説明では、あらかじめ配賦基準マスタメンテ102fによる管理が行われ、各科目または各部門へ配賦する際の配賦係数の設定が、図14に示す配賦基準マスタ106eにて管理されているものとする。   Further, in this description, management by the allocation standard master maintenance 102f is performed in advance, and the allocation coefficient setting for allocation to each item or each department is managed by the allocation standard master 106e shown in FIG. It shall be.

なお、本説明では、2段階配賦を行うため、図7の例と異なり、配賦ステップ(III)に係る配賦係数(配賦基準CD「301」および「302」のレコードに格納されているデータ(図14参照))の設定まで行っている。   In this description, since the two-stage allocation is performed, unlike the example of FIG. 7, the allocation coefficient (allocation standard CD “301” and “302”) is stored in the allocation step (III). Data (see FIG. 14)) is set.

以上、図10から図14に基づく配賦経過の一例を、図15を用いて説明する。まず、エネルギー会社へ支払う金額を各科目または各部門に配賦するために必要な使用量を計算する配賦ステップ(I)において、算出部102aは、(1)および(2)の値を用いて計算を行い、各科目または各部門に配賦するために必要な使用量((3)の値)を算出する。   As described above, an example of the allocation process based on FIGS. 10 to 14 will be described with reference to FIG. First, in the allocation step (I) for calculating the usage amount required to allocate the amount to be paid to the energy company to each subject or each department, the calculation unit 102a uses the values of (1) and (2). To calculate the amount of usage (value of (3)) necessary for allocation to each subject or department.

そして、配賦ステップ(I)で求めた使用量((3)の値)、または固定値を配賦係数として、算出部102aは、各科目または各部門へ原価を配賦する配賦ステップ(II)において、(3)から(5)までの値を用いて計算を行い、各科目または各部門への原価の配賦金額((6)の値)を算出する。   Then, the calculation unit 102a allocates the cost to each item or each department using the usage amount (value of (3)) obtained in the allocation step (I) or a fixed value as an allocation coefficient ( In II), the calculation is performed using the values from (3) to (5) to calculate the cost allocation amount (value of (6)) to each item or department.

そして、配賦ステップ(II)で求めた各科目または各部門の振替金額(配賦金額)をさらに別の科目または部門へ配賦する配賦ステップ(III)において、算出部102aは、(7)から(9)までの値(図15参照)を用いて計算を行い、さらに別の科目または部門へ配賦する2段階配賦に係る配賦金額((10)の値)を算出する。   Then, in the allocation step (III) in which the transfer amount (allocation amount) of each item or each department obtained in the allocation step (II) is allocated to another item or department, the calculation unit 102a (7 ) To (9) are used for calculation (see FIG. 15), and an allocation amount (value of (10)) relating to the two-stage allocation to be allocated to another item or department is calculated.

そして、算出部102aは、算出した配賦金額を配賦金額テーブル106fに格納する。   Then, the calculation unit 102a stores the calculated allocation amount in the allocation amount table 106f.

以上で、(処理具体例2)の説明を終了する。   This is the end of the description of (Processing Example 2).

なお、原価配賦計算処理を実行した後は、振替表とPL表(損益計算書)で確認してもよい。また、原価配賦計算処理を一度実行した後に、再度実行した場合は、再計算を行ってもよい。また、振替仕訳(仕訳データ)が作成済みの場合に再度原価配賦計算処理を実行した場合は、エラーとしてもよい。   In addition, after performing the cost allocation calculation process, you may confirm with a transfer table and PL table (income statement). Further, when the cost allocation calculation process is executed once and then executed again, recalculation may be performed. Further, when the transfer journal (journal data) has been created and the cost allocation calculation process is executed again, an error may be generated.

このように、本実施形態に係る原価配賦計算処理装置100によれば、ビル毎に異なる複雑な計算方法による原価の配賦計算が可能となり、計算結果からの仕訳作成も行うことが可能となった。   As described above, according to the cost allocation calculation processing apparatus 100 according to the present embodiment, it is possible to perform cost allocation calculation by a complicated calculation method different for each building, and it is also possible to create a journal entry from the calculation result. became.

なお、上記実施形態では、水道光熱費の原価の配賦計算の例で説明したが、必ずしもこれに限定されず、自社の労務費や人件費等の共通費における原価の配賦計算などにも応用が可能である。また、本発明は、ビルなどのオーナーがテナント毎の原価を正確に把握できるようにすることを目的としているが、複数テナントに限るものではなく、1テナントであっても運用が可能であり、例えば部門配賦として用いることができる。   In the above embodiment, the example of the allocation calculation of the cost of water and utility costs has been described. However, the present invention is not necessarily limited to this, and the allocation calculation of the cost in common costs such as labor costs and labor costs of the company is also not necessary. Application is possible. In addition, the present invention aims to enable an owner such as a building to accurately grasp the cost for each tenant, but is not limited to a plurality of tenants, and can be operated even with one tenant, For example, it can be used as a division allocation.

[4.他の実施形態]
本発明は、上述した実施形態以外にも、特許請求の範囲に記載した技術的思想の範囲内において種々の異なる実施形態にて実施されてよいものである。
[4. Other Embodiments]
In addition to the above-described embodiments, the present invention may be implemented in various different embodiments within the scope of the technical idea described in the claims.

例えば、実施形態において説明した各処理のうち、自動的に行われるものとして説明した処理の全部または一部を手動的に行うこともでき、あるいは、手動的に行われるものとして説明した処理の全部または一部を公知の方法で自動的に行うこともできる。   For example, among the processes described in the embodiments, all or part of the processes described as being automatically performed can be performed manually, or all of the processes described as being performed manually are all performed. Alternatively, a part can be automatically performed by a known method.

また、本明細書中や図面中で示した処理手順、制御手順、具体的名称、各処理の登録データや検索条件等のパラメータを含む情報、画面例、データベース構成については、特記する場合を除いて任意に変更することができる。   In addition, the processing procedures, control procedures, specific names, information including parameters such as registration data and search conditions for each processing, screen examples, and database configurations shown in the present specification and drawings, unless otherwise specified. Can be changed arbitrarily.

また、原価配賦計算処理装置100に関して、図示の各構成要素は機能概念的なものであり、必ずしも物理的に図示の如く構成されていることを要しない。   Moreover, regarding the cost allocation calculation processing apparatus 100, each illustrated component is functionally conceptual and does not necessarily need to be physically configured as illustrated.

例えば、原価配賦計算処理装置100が備える処理機能、特に制御部102にて行われる各処理機能については、その全部または任意の一部を、CPUおよび当該CPUにて解釈実行されるプログラムにて実現してもよく、また、ワイヤードロジックによるハードウェアとして実現してもよい。尚、プログラムは、本実施形態で説明した処理を情報処理装置に実行させるためのプログラム化された命令を含む一時的でないコンピュータ読み取り可能な記録媒体に記録されており、必要に応じて原価配賦計算処理装置100に機械的に読み取られる。すなわち、ROMまたはHDD(Hard Disk Drive)などの記憶部106などには、OSと協働してCPUに命令を与え、各種処理を行うためのコンピュータプログラムが記録されている。このコンピュータプログラムは、RAMにロードされることによって実行され、CPUと協働して制御部102を構成する。   For example, regarding the processing functions provided in the cost allocation calculation processing apparatus 100, in particular, each processing function performed by the control unit 102, the CPU or a program that is interpreted and executed by the CPU is used for all or any part thereof. You may implement | achieve and may implement | achieve as hardware by a wired logic. The program is recorded on a non-transitory computer-readable recording medium including programmed instructions for causing the information processing apparatus to execute the processing described in this embodiment, and cost allocation is performed as necessary. It is mechanically read by the calculation processing device 100. That is, in the storage unit 106 such as a ROM or an HDD (Hard Disk Drive), a computer program for giving instructions to the CPU in cooperation with the OS and performing various processes is recorded. This computer program is executed by being loaded into the RAM, and constitutes the control unit 102 in cooperation with the CPU.

また、このコンピュータプログラムは、原価配賦計算処理装置100に対して任意のネットワークを介して接続されたアプリケーションプログラムサーバに記憶されていてもよく、必要に応じてその全部または一部をダウンロードすることも可能である。   The computer program may be stored in an application program server connected to the cost allocation calculation processing apparatus 100 via an arbitrary network, and the computer program may be downloaded in whole or in part as necessary. Is also possible.

また、本実施形態で説明した処理を実行するためのプログラムを、一時的でないコンピュータ読み取り可能な記録媒体に格納してもよく、また、プログラム製品として構成することもできる。ここで、この「記録媒体」とは、メモリーカード、USB(Universal Serial Bus)メモリ、SD(Secure Digital)カード、フレキシブルディスク、光磁気ディスク、ROM、EPROM(Erasable Programmable Read Only Memory)、EEPROM(登録商標)(Electrically Erasable and Programmable Read Only Memory)、CD−ROM(Compact Disk Read Only Memory)、MO(Magneto−Optical disk)、DVD(Digital Versatile Disk)、および、Blu−ray(登録商標) Disc等の任意の「可搬用の物理媒体」を含むものとする。   In addition, a program for executing the processing described in this embodiment may be stored in a non-temporary computer-readable recording medium, or may be configured as a program product. Here, the “recording medium” refers to a memory card, USB (Universal Serial Bus) memory, SD (Secure Digital) card, flexible disk, magneto-optical disk, ROM, EPROM (Erasable Programmable Read Only Memory), EEPROM (registration). Trademark) (Electrically Erasable and Programmable Read Only Memory), CD-ROM (Compact Disk Read Only Memory), MO (Magneto-Optical disk), DVD (Digital Digital, Trademark) Any “portable physical media It is intended to include.

また、「プログラム」とは、任意の言語または記述方法にて記述されたデータ処理方法であり、ソースコードまたはバイナリコード等の形式を問わない。なお、「プログラム」は必ずしも単一的に構成されるものに限られず、複数のモジュールやライブラリとして分散構成されるものや、OSに代表される別個のプログラムと協働してその機能を達成するものをも含む。なお、実施形態に示した各装置において記録媒体を読み取るための具体的な構成および読み取り手順ならびに読み取り後のインストール手順等については、周知の構成や手順を用いることができる。   The “program” is a data processing method described in an arbitrary language or description method, and may be in any form such as source code or binary code. Note that the “program” is not necessarily limited to a single configuration, and functions are achieved in cooperation with a separate configuration such as a plurality of modules and libraries or a separate program represented by the OS. Including things. In addition, a well-known structure and procedure can be used about the specific structure and reading procedure for reading a recording medium in each apparatus shown to embodiment, the installation procedure after reading, etc.

記憶部106に格納される各種のデータベース等は、RAM、ROM等のメモリ装置、ハードディスク等の固定ディスク装置、フレキシブルディスク、及び、光ディスク等のストレージ手段であり、各種処理やウェブサイト提供に用いる各種のプログラム、テーブル、データベース、及び、ウェブページ用ファイル等を格納する。   Various databases and the like stored in the storage unit 106 are storage means such as a memory device such as a RAM and a ROM, a fixed disk device such as a hard disk, a flexible disk, and an optical disk. Programs, tables, databases, web page files, and the like.

また、原価配賦計算処理装置100は、既知のパーソナルコンピュータまたはワークステーション等の情報処理装置として構成してもよく、また、任意の周辺装置が接続された当該情報処理装置として構成してもよい。また、原価配賦計算処理装置100は、当該装置に本実施形態で説明した処理を実現させるソフトウェア(プログラムまたはデータ等を含む)を実装することにより実現してもよい。   The cost allocation calculation processing apparatus 100 may be configured as an information processing apparatus such as a known personal computer or workstation, or may be configured as the information processing apparatus to which an arbitrary peripheral device is connected. . Further, the cost allocation calculation processing device 100 may be realized by installing software (including a program or data) that realizes the processing described in the present embodiment in the device.

更に、装置の分散・統合の具体的形態は図示するものに限られず、その全部または一部を、各種の付加等に応じてまたは機能負荷に応じて、任意の単位で機能的または物理的に分散・統合して構成することができる。すなわち、上述した実施形態を任意に組み合わせて実施してもよく、実施形態を選択的に実施してもよい。   Furthermore, the specific form of distribution / integration of the devices is not limited to that shown in the figure, and all or a part of them may be functionally or physically in arbitrary units according to various additions or according to functional loads. It can be configured to be distributed and integrated. That is, the above-described embodiments may be arbitrarily combined and may be selectively implemented.

本発明は、特に、不動産賃貸業や区分所有建物管理組合などにおける水道光熱費、あるいは会社の労務費や人件費等の共通費の配賦計算などにおいて有用である。   The present invention is particularly useful in the calculation of allocation of common expenses such as utility expenses in the real estate leasing business and the division-owned building management association, or labor costs and labor costs of the company.

100 原価配賦計算処理装置
102 制御部
102a 算出部
102b 仕訳作成部
102c 配賦パックマスタメンテ
102d 配賦手順マスタメンテ
102e 演算マスタメンテ
102f 配賦基準マスタメンテ
104 通信インターフェース部
106 記憶部
106a 検針メーターデータファイル
106b 配賦パックマスタ
106c 配賦手順マスタ
106d 演算マスタ
106e 配賦基準マスタ
106f 配賦金額テーブル
106g 仕訳データテーブル
108 入出力インターフェース部
112 入力装置
114 出力装置
200 サーバ
300 ネットワーク
DESCRIPTION OF SYMBOLS 100 Cost allocation calculation processing apparatus 102 Control part 102a Calculation part 102b Journal creation part 102c Allocation pack master maintenance 102d Allocation procedure master maintenance 102e Calculation master maintenance 102f Allocation standard master maintenance 104 Communication interface part 106 Storage part 106a Meter reading meter data File 106b Allocation pack master 106c Allocation procedure master 106d Calculation master 106e Allocation reference master 106f Allocation amount table 106g Journal data table 108 Input / output interface unit 112 Input device 114 Output device 200 Server 300 Network

Claims (6)

制御部を備えた原価配賦計算処理装置であって、
前記制御部は、
ビルで使用した水道、電気、熱供給、または、ガスに関する検針メーターデータと、当該ビルで使用した水道、電気、熱供給、または、ガスに関する金額データとを記憶する検針メーターデータ記憶手段と、
検針メーターデータから水道、電気、熱供給、または、ガスの使用量を演算する演算方法と、前記使用量に対する配賦基準と、を紐付けた配賦手順を記憶する配賦手順記憶手段と、
前記検針メーターデータ、前記金額データおよび前記配賦手順に基づいて、配賦金額を算出する算出手段と、
を備えたことを特徴とする原価配賦計算処理装置。
A cost allocation calculation processing device equipped with a control unit,
The controller is
Meter-meter data storage means for storing meter-meter data relating to water, electricity, heat supply or gas used in the building, and amount data relating to water, electricity, heat supply or gas used in the building;
An allocation procedure storage means for storing an allocation procedure in which a calculation method for calculating the usage amount of water, electricity, heat supply, or gas from meter-reading meter data and an allocation standard for the usage amount are stored;
Based on the meter-reading meter data, the amount data, and the allocation procedure, a calculation means for calculating an allocation amount;
A cost allocation calculation processing apparatus characterized by comprising:
前記制御部は、
配賦金額に基づいて、仕訳を作成する仕訳作成手段
を更に備えたこと、を特徴とする請求項1に記載の原価配賦計算処理装置。
The controller is
The cost allocation calculation processing apparatus according to claim 1, further comprising a journal creation unit that creates a journal based on the allocated amount.
前記配賦基準は、
面積按分、固定比率、もしくは、水道、電気、熱供給またはガスの使用量按分であること、
を特徴とする請求項1または2に記載の原価配賦計算処理装置。
The allocation criteria are:
Area apportionment, fixed ratio, or apportioning of water, electricity, heat supply or gas usage,
The cost allocation calculation processing apparatus according to claim 1 or 2, characterized in that:
前記使用量は、
前記ビルのテナントの使用量であること、を特徴とする請求項1から3のうちいずれか一つに記載の原価配賦計算処理装置。
The amount used is
The cost allocation calculation processing device according to any one of claims 1 to 3, wherein the usage amount is a usage amount of a tenant of the building.
制御部を備えた原価配賦計算処理装置に実行させるための原価配賦計算処理方法であって、
前記制御部で実行される、
ビルで使用した水道、電気、熱供給、または、ガスに関する検針メーターデータと、当該ビルで使用した水道、電気、熱供給、または、ガスに関する金額データとを記憶する検針メーターデータ記憶ステップと、
検針メーターデータから水道、電気、熱供給、または、ガスの使用量を演算する演算方法と、前記使用量に対する配賦基準と、を紐付けた配賦手順を記憶する配賦手順記憶ステップと、
前記検針メーターデータ、前記金額データおよび前記配賦手順に基づいて、配賦金額を算出する算出ステップと、
を含むことを特徴とする原価配賦計算処理方法。
A cost allocation calculation processing method for causing a cost allocation calculation processing device provided with a control unit to execute,
Executed by the control unit,
Meter-meter data storage step for storing meter-meter data related to water, electricity, heat supply, or gas used in the building, and amount data related to water, electricity, heat supply, or gas used in the building;
An allocation procedure storage step for storing an allocation procedure in which a calculation method for calculating the usage amount of water, electricity, heat supply, or gas from meter-reading meter data and an allocation standard for the usage amount are stored;
A calculation step of calculating an allocation amount based on the meter-reading meter data, the amount data, and the allocation procedure;
The cost allocation calculation processing method characterized by including.
制御部を備えた原価配賦計算処理装置に実行させるための原価配賦計算処理プログラムであって、
前記制御部において、
ビルで使用した水道、電気、熱供給、または、ガスに関する検針メーターデータと、当該ビルで使用した水道、電気、熱供給、または、ガスに関する金額データとを記憶する検針メーターデータ記憶ステップと、
検針メーターデータから水道、電気、熱供給、または、ガスの使用量を演算する演算方法と、前記使用量に対する配賦基準と、を紐付けた配賦手順を記憶する配賦手順記憶ステップと、
前記検針メーターデータ、前記金額データおよび前記配賦手順に基づいて、配賦金額を算出する算出ステップと、
を実行させるための原価配賦計算処理プログラム。
A cost allocation calculation processing program for causing a cost allocation calculation processing device having a control unit to execute,
In the control unit,
Meter-meter data storage step for storing meter-meter data related to water, electricity, heat supply, or gas used in the building, and amount data related to water, electricity, heat supply, or gas used in the building;
An allocation procedure storage step for storing an allocation procedure in which a calculation method for calculating the usage amount of water, electricity, heat supply, or gas from meter-reading meter data and an allocation standard for the usage amount are stored;
A calculation step of calculating an allocation amount based on the meter-reading meter data, the amount data, and the allocation procedure;
Cost allocation calculation processing program to execute.
JP2016188497A 2016-03-28 2016-09-27 Cost allocation calculation processing device, cost allocation calculation processing method, and cost allocation calculation processing program Active JP6872337B2 (en)

Applications Claiming Priority (2)

Application Number Priority Date Filing Date Title
JP2016064338 2016-03-28
JP2016064338 2016-03-28

Publications (2)

Publication Number Publication Date
JP2017182766A true JP2017182766A (en) 2017-10-05
JP6872337B2 JP6872337B2 (en) 2021-05-19

Family

ID=60007118

Family Applications (1)

Application Number Title Priority Date Filing Date
JP2016188497A Active JP6872337B2 (en) 2016-03-28 2016-09-27 Cost allocation calculation processing device, cost allocation calculation processing method, and cost allocation calculation processing program

Country Status (1)

Country Link
JP (1) JP6872337B2 (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2019174949A (en) * 2018-03-27 2019-10-10 株式会社オービック Common expenses management device, common expenses management method and common expenses management program
JP2021056673A (en) * 2019-09-27 2021-04-08 株式会社オービック Safety cooperation membership fee breakdown management device, safety cooperation membership fee breakdown management method, and safety cooperation membership fee breakdown management program

Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2000215263A (en) * 1998-11-17 2000-08-04 Fujitsu Ltd Accounting system/method processing transaction data, and storage medium storing program for the same
JP2006185318A (en) * 2004-12-28 2006-07-13 Hitachi Eng Co Ltd Energy information management device
JP2010218034A (en) * 2009-03-13 2010-09-30 Toshiba Corp Integrated management system and method
WO2015004759A1 (en) * 2013-07-09 2015-01-15 三菱重工業株式会社 Billing device for circulated water use system

Patent Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2000215263A (en) * 1998-11-17 2000-08-04 Fujitsu Ltd Accounting system/method processing transaction data, and storage medium storing program for the same
JP2006185318A (en) * 2004-12-28 2006-07-13 Hitachi Eng Co Ltd Energy information management device
JP2010218034A (en) * 2009-03-13 2010-09-30 Toshiba Corp Integrated management system and method
WO2015004759A1 (en) * 2013-07-09 2015-01-15 三菱重工業株式会社 Billing device for circulated water use system

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2019174949A (en) * 2018-03-27 2019-10-10 株式会社オービック Common expenses management device, common expenses management method and common expenses management program
JP7131936B2 (en) 2018-03-27 2022-09-06 株式会社オービック Common expense management device, common expense management method, and common expense management program
JP2021056673A (en) * 2019-09-27 2021-04-08 株式会社オービック Safety cooperation membership fee breakdown management device, safety cooperation membership fee breakdown management method, and safety cooperation membership fee breakdown management program
JP7360879B2 (en) 2019-09-27 2023-10-13 株式会社オービック Safety cooperation membership fee breakdown management device, safety cooperation membership fee breakdown management method, and safety cooperation membership fee breakdown management program

Also Published As

Publication number Publication date
JP6872337B2 (en) 2021-05-19

Similar Documents

Publication Publication Date Title
JP7046143B2 (en) Debt Management Device, Debt Management Method, and Debt Management Program
JP7121827B2 (en) Project accounting management device, project accounting management method, and project accounting management program
JP2017182765A (en) Counterbalance journal entry recording device, counterbalance journal entry recording method, and counterbalance journal entry recording program
JP2021177427A (en) Project management device, project management method, and project management program
JP6872337B2 (en) Cost allocation calculation processing device, cost allocation calculation processing method, and cost allocation calculation processing program
JP2019159963A (en) Management report creation device, management report creation method and management report creation program
JP2017168087A (en) Expense journalizing automatic generation device, expense journalizing automatic generation method, and expense journalizing automatic generation program
JP2022002145A (en) Classification data preparation device, classification data creation method and classification data creation program
JP2017174400A (en) Sales claim data expansion device, sales claim data expansion method, and sales claim data expansion program
JP2024015351A (en) Cost budget/actual management device, cost budget/actual management method, and cost budget/actual management program
JP7011470B2 (en) Work-in-process automatic transfer device, work-in-process automatic transfer method, and work-in-process automatic transfer program
JP7074458B2 (en) Workflow management device, workflow management method and workflow management program
JP2019160144A (en) Classification data preparation device, method for creating classification data, and classification data creation program
JP2019168980A (en) Progress rate calculation device, progress rate calculation method and progress rate calculation program
JP7011500B2 (en) Management report creation device, management report creation method and management report creation program
JP2016091384A (en) Information processor, program, and information processing method
JP2021157777A (en) Article journal generation device, article journal generation method, and article journal generation program
JP2017188081A (en) Payment request electronic approval device, payment request electronic approval method, and payment request electronic approval program
JP2016184395A (en) Decision request workflow ordering device, decision request workflow ordering method, and decision request workflow ordering program
JP2017182789A (en) Distribution simulation device, distribution simulation method, and distribution simulation program
JP2019159873A (en) Management report preparing device, management report preparing method and management report preparing program
JP2019016234A (en) Sales management device, sales management method, and sales management program
JP2020166614A (en) Deposit transfer device, deposit transfer method, and deposit transfer program
JP2019174949A (en) Common expenses management device, common expenses management method and common expenses management program
JP2024093374A (en) Invoice issuing device, invoice issuing method and invoice issuing program

Legal Events

Date Code Title Description
A621 Written request for application examination

Free format text: JAPANESE INTERMEDIATE CODE: A621

Effective date: 20190904

A977 Report on retrieval

Free format text: JAPANESE INTERMEDIATE CODE: A971007

Effective date: 20200722

A131 Notification of reasons for refusal

Free format text: JAPANESE INTERMEDIATE CODE: A131

Effective date: 20201201

A601 Written request for extension of time

Free format text: JAPANESE INTERMEDIATE CODE: A601

Effective date: 20201207

A521 Request for written amendment filed

Free format text: JAPANESE INTERMEDIATE CODE: A523

Effective date: 20210322

TRDD Decision of grant or rejection written
A01 Written decision to grant a patent or to grant a registration (utility model)

Free format text: JAPANESE INTERMEDIATE CODE: A01

Effective date: 20210406

A61 First payment of annual fees (during grant procedure)

Free format text: JAPANESE INTERMEDIATE CODE: A61

Effective date: 20210419

R150 Certificate of patent or registration of utility model

Ref document number: 6872337

Country of ref document: JP

Free format text: JAPANESE INTERMEDIATE CODE: R150

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250