JP2017042715A - Construction method for waste disposal site - Google Patents

Construction method for waste disposal site Download PDF

Info

Publication number
JP2017042715A
JP2017042715A JP2015166930A JP2015166930A JP2017042715A JP 2017042715 A JP2017042715 A JP 2017042715A JP 2015166930 A JP2015166930 A JP 2015166930A JP 2015166930 A JP2015166930 A JP 2015166930A JP 2017042715 A JP2017042715 A JP 2017042715A
Authority
JP
Japan
Prior art keywords
water
region
ground
waste disposal
dam
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
JP2015166930A
Other languages
Japanese (ja)
Other versions
JP6764588B2 (en
Inventor
川口 正人
Masato Kawaguchi
正人 川口
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Shimizu Construction Co Ltd
Shimizu Corp
Original Assignee
Shimizu Construction Co Ltd
Shimizu Corp
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Shimizu Construction Co Ltd, Shimizu Corp filed Critical Shimizu Construction Co Ltd
Priority to JP2015166930A priority Critical patent/JP6764588B2/en
Publication of JP2017042715A publication Critical patent/JP2017042715A/en
Application granted granted Critical
Publication of JP6764588B2 publication Critical patent/JP6764588B2/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Consolidation Of Soil By Introduction Of Solidifying Substances Into Soil (AREA)
  • Processing Of Solid Wastes (AREA)

Abstract

PROBLEM TO BE SOLVED: To provide a construction method for a waste disposal site which enables an earlier start of the service of the waste disposal site.SOLUTION: A construction method for a waste disposal site, which is a construction method for a waste disposal site for constructing a waste disposal site in a predetermined region X, comprises a first ground improvement step of improving the ground of a partial region X1 of the predetermined region X, a first water-shielding step of providing a water-shielding part 3 in the surface of the ground G1 of the region X1, a first protective layer establishment step of providing a protective layer 6 in the surface of the water-shielding part 3 of the region X1, a first dam installation step of providing a dam 7 in the surface of the ground G1 of the boundary part Y1 of the region X1, a second ground improvement step of improving the ground of another region adjacent to the boundary part Y1 of the region X, a second water-shielding step of providing a water-shielding part 13 in the surface of the ground G2 of a region X2, a second protective layer establishment step of providing a protective layer 16 in the surface of the water-shielding part 13 of the region X2, a second dam installation step of providing the dam 17 in the boundary part Y2 different from the region X1 side in the region X2.SELECTED DRAWING: Figure 5

Description

本発明は、廃棄物処分場の構築方法に関するものである。   The present invention relates to a method for constructing a waste disposal site.

従来から、廃棄物処分場では、廃棄物から浸出する様々な有害物質が地盤に浸透して、地下水汚染や地盤汚染が生じることを防止するために、地盤の上に遮水シート等を設けて、その上に廃棄物を堆積している(下記特許文献1参照)。   Conventionally, in order to prevent various harmful substances leaching from the waste from penetrating into the ground and causing groundwater contamination and ground contamination, wastewater disposal sites have been provided with water shielding sheets on the ground. In addition, waste is deposited thereon (see Patent Document 1 below).

また、平地に廃棄物処分場を建設する場合には、地盤を掘削し、地盤の表面に遮水シートを敷設する。そして、廃棄物が遮水シートに直接接触して遮水シートに損傷等が生じないように、遮水シートの上に砂等の保護層を設け、その上に廃棄物を搬入している。一方、谷に廃棄物処分場を建設する場合には、法面を掘削した後に、平地の場合と同様に、遮水シートを敷設し、その上に保護層を設けている。   Also, when constructing a waste disposal site on flat ground, excavate the ground and lay a waterproof sheet on the surface of the ground. Then, a protective layer such as sand is provided on the water shielding sheet so that the waste does not directly contact the water shielding sheet and cause damage to the water shielding sheet, and the waste is carried thereon. On the other hand, when constructing a waste disposal site in the valley, after excavating the slope, a water shielding sheet is laid and a protective layer is provided thereon, as in the case of flat land.

地盤が軟弱な場合には、廃棄物の自重により地盤が不等沈下したり、遮水シートに局部的な引張応力が生じて遮水シートが破断したりする虞がある。そこで、地盤が軟弱な場合には、地盤改良して地盤を安定化させる必要がある。   When the ground is soft, the ground may sink unevenly due to the weight of the waste, or a local tensile stress may be generated in the waterproof sheet and the waterproof sheet may be broken. Therefore, when the ground is soft, it is necessary to improve the ground and stabilize the ground.

また、廃棄物から浸出した浸出水を集水する集水管を遮水シートの上に敷設し、下流側に設置された排水処理設備で水処理して、有害物質を取り除いて排水している。   In addition, a water collecting pipe that collects leachate leached from the waste is laid on a water shielding sheet, and water is treated with a wastewater treatment facility installed on the downstream side to remove harmful substances and drain the water.

特許第5666742号公報Japanese Patent No. 5666742

上記のように、廃棄物処分場を建設するために、地盤改良を行い、遮水シート、集水管及び保護層を設置するとともに排水処理施設を建設する等の工事を行う必要があり、工期が長期化していた。さらに、廃棄物処分場が大規模であると、工期がさらに長期化していた。このため、廃棄物をすみやかに処分することができないという問題点がある。   As mentioned above, in order to construct a waste disposal site, it is necessary to carry out construction work such as ground improvement, installation of water shielding sheets, water collection pipes and protective layers, and construction of wastewater treatment facilities. It was prolonged. Furthermore, if the waste disposal site was large, the construction period was even longer. For this reason, there is a problem that waste cannot be disposed of promptly.

そこで、本発明は、上記事情に鑑みてなされたものであり、廃棄物処分場の供用を早期に開始することが可能な廃棄物処分場の構築方法を提供する。   Then, this invention is made | formed in view of the said situation, and provides the construction method of the waste disposal site which can start operation of a waste disposal site at an early stage.

上記目的を達成するために、本発明は以下の手段を採用している。
すなわち、本発明に係る廃棄物処分場の構築方法は、所定領域に廃棄物処分場を構築する廃棄物処分場の構築方法であって、前記所定領域のうち一部の領域を地盤改良する第一地盤改良工程と、前記一部の領域の地盤の表面に遮水部を設ける第一遮水工程と、前記一部の領域の前記遮水部の表面に保護層を設ける第一保護層造成工程と、前記一部の領域の境界部に堰堤を設ける第一堰堤設置工程と、前記所定領域のうち前記境界部に隣接する他の領域を地盤改良する第二地盤改良工程と、前記他の領域の地盤の表面に遮水部を設ける第二遮水工程と、前記他の領域の前記遮水部の表面に保護層を設ける第二保護層造成工程と、前記他の領域における前記一部の領域側とは異なる境界部に堰堤を設ける第二堰堤設置工程と、を備えることを特徴とする。
In order to achieve the above object, the present invention employs the following means.
That is, a construction method of a waste disposal site according to the present invention is a construction method of a waste disposal site that constructs a waste disposal site in a predetermined area, and is a method for improving the ground of a part of the predetermined area. One ground improvement step, a first water shielding step for providing a water shielding portion on the surface of the ground in the partial area, and a first protective layer formation for providing a protective layer on the surface of the water shielding portion in the partial region A first dam installation step of providing a dam at a boundary portion of the partial region, a second ground improvement step of improving the ground of another region adjacent to the boundary portion of the predetermined region, and the other A second water shielding step for providing a water shielding portion on the surface of the ground in the region, a second protective layer forming step for providing a protective layer on the surface of the water shielding portion in the other region, and the part in the other region. A second dam installation step of providing a dam at a boundary portion different from the region side of To.

このように構成された廃棄物処分場の構築方法では、廃棄物処分場が構築される所定領域のうち一部の領域において、地盤改良する第一地盤改良工程、地盤の表面に遮水部を設ける第一遮水工程、遮水部の表面に保護層を設ける第一保護層設置工程、及び境界部に堰堤を設ける第一堰堤設置工程を実施すれば、所定領域のうち一部の領域において廃棄物処分場の供用を先行して開始することができる。また、一部の領域において廃棄物処分場の供用を開始しつつ、他の領域において、地盤改良する第二地盤改良工程、地盤の表面に遮水部を設ける第二遮水工程、遮水部の表面に保護層を設ける第二保護層設置工程、及び一部の領域側とは異なる境界部に堰堤を設ける第二堰堤設置工程を実施すれば、他の領域においても、廃棄物処分場の供用を開始することができる。つまり、将来的に廃棄物処分場が設置される所定領域のうち一部の領域を他の領域よりも先行して廃棄物処分場の供用を開始することができるため、廃棄物処分場の供用を早期に開始することができる。   In the construction method of the waste disposal site constructed in this way, in some areas of the predetermined area where the waste disposal site is constructed, a first ground improvement process for improving the ground, and a water shielding portion on the surface of the ground. If you implement the first water-blocking step, the first protective layer-setting step that provides a protective layer on the surface of the water-blocking portion, and the first dam-setting step that provides a dam at the boundary, A waste disposal site can be started in advance. In addition, while starting operation of the waste disposal site in some areas, the second ground improvement process for improving the ground in other areas, the second water shielding process for providing a water shielding part on the surface of the ground, and the water shielding part If the second protective layer installation process for providing a protective layer on the surface of the material and the second dam installation process for providing a dam at the boundary part different from the part of the area side are implemented, The service can be started. In other words, since some of the predetermined areas where waste disposal sites will be installed in the future can be started in advance of other areas, the operation of waste disposal sites can be started. Can be started early.

また、本発明に係る廃棄物処分場の構築方法は、前記一部の領域に集水管を設置して水処理施設に接続する第一集水管設置工程と、前記他の領域に集水管を設置する第二集水管設置工程と、前記一部の領域の集水管と前記他の領域の集水管とを接続する集水管接続工程と、を備えることが好ましい。   In addition, the method for constructing a waste disposal site according to the present invention includes a first water collection pipe installation step in which a water collection pipe is installed in the partial area and connected to a water treatment facility, and a water collection pipe is installed in the other area. It is preferable to include a second water collecting pipe installing step, and a water collecting pipe connecting step for connecting the water collecting pipes in the partial area and the water collecting pipes in the other area.

このように構成された廃棄物処分場の構築方法では、第一集水管設置工程で一部の領域に集水管を設置して水処理施設に接続し、第二集水管設置工程で他の領域に集水管を設置し、集水管接続工程で一部の領域の集水管と他の領域の集水管とを接続するため、他の領域の集水管を流通する浸出水を、一部の領域の集水管に流通させて集水することができる。よって、他の領域の集水管を水処理施設側に直接接続する必要がないため、大規模な工事を伴わない。   In the construction method of the waste disposal site configured in this way, the water collecting pipe is installed in a part of the area in the first water collecting pipe installation process and connected to the water treatment facility, and the other area in the second water collecting pipe installation process. In order to connect the water collection pipes in some areas to the water collection pipes in other areas in the water collection pipe connection process, the leachate flowing through the water collection pipes in other areas is The water can be collected by circulating it through a water collection pipe. Therefore, since it is not necessary to directly connect the water collection pipes in other areas to the water treatment facility side, large-scale construction is not involved.

本発明に係る廃棄物処分場の構築方法によれば、廃棄物処分場の供用を早期に開始することができる。   According to the construction method of the waste disposal site according to the present invention, the operation of the waste disposal site can be started at an early stage.

本発明の一実施形態に係る廃棄物処分場の土地の構成を示す模式的な平面図である。It is a typical top view which shows the structure of the land of the waste disposal site which concerns on one Embodiment of this invention. 本発明の一実施形態に係る廃棄物処分場の構築方法の第一地盤改良工程を説明するための図である。It is a figure for demonstrating the 1st ground improvement process of the construction method of the waste disposal site which concerns on one Embodiment of this invention. 本発明の一実施形態に係る廃棄物処分場の構築方法の第一遮水工程を説明するための図である。It is a figure for demonstrating the 1st water shielding process of the construction method of the waste disposal site which concerns on one Embodiment of this invention. 本発明の一実施形態に係る廃棄物処分場の構築方法の第一集水管設置工程、集水管接続工程、第一保護層造成工程及び第一堰堤設置工程を説明するための図である。It is a figure for demonstrating the 1st water collection pipe installation process of the construction method of the waste disposal site which concerns on one Embodiment of this invention, a water collection pipe connection process, a 1st protective layer creation process, and a 1st dam installation process. 本発明の一実施形態に係る廃棄物処分場の構築方法の第二遮水工程、第二集水管設置工程、第二保護層造成工程及び第二堰堤設置工程を説明するための図である。It is a figure for demonstrating the 2nd water-blocking process of the construction method of the waste disposal site which concerns on one Embodiment of this invention, the 2nd water collecting pipe installation process, the 2nd protective layer creation process, and the 2nd dam installation process. 本発明の一実施形態の変形例に係る廃棄物処分場の構築方法の第一地盤改良工程を説明するための図である。It is a figure for demonstrating the 1st ground improvement process of the construction method of the waste disposal site which concerns on the modification of one Embodiment of this invention. 本発明の一実施形態の変形例に係る廃棄物処分場の構築方法の第一遮水工程を説明するための図である。It is a figure for demonstrating the 1st water shielding process of the construction method of the waste disposal site which concerns on the modification of one Embodiment of this invention. 本発明の一実施形態の変形例に係る廃棄物処分場の構築方法の第一集水管設置工程、第一保護層造成工程及び第一堰堤設置工程を説明するための図である。It is a figure for demonstrating the 1st water collection pipe installation process, the 1st protective layer creation process, and the 1st dam installation process of the construction method of the waste disposal site which concerns on the modification of one Embodiment of this invention. 本発明の一実施形態の変形例に係る廃棄物処分場の構築方法の第二遮水工程、第二集水管設置工程、第二保護層造成工程及び第二堰堤設置工程を説明するための図である。The figure for demonstrating the 2nd water-blocking process of the construction method of the waste disposal site which concerns on the modification of one Embodiment of this invention, the 2nd water collecting pipe installation process, the 2nd protective layer creation process, and the 2nd dam installation process It is.

本発明の一実施形態に係る廃棄物処分場の構築方法について、図1から図5を用いて説明する。
図1は、本発明の一実施形態に係る廃棄物処分場の土地の構成を示す模式的な平面図である。
図1に示すように、本実施形態では、二点鎖線で示す谷底A1が形成された土地(所定領域)Xに、廃棄物処分場を建設するものである。谷の斜面A2に沿って、谷を囲むように切り回し放水路Pを先行して施工する。切り回し放水路Pは、土地X内に上流側の流入河川Qの水が入らないようにするためのものである。
A construction method for a waste disposal site according to an embodiment of the present invention will be described with reference to FIGS.
FIG. 1 is a schematic plan view showing a configuration of land in a waste disposal site according to an embodiment of the present invention.
As shown in FIG. 1, in this embodiment, a waste disposal site is constructed on land (predetermined area) X on which a valley bottom A1 indicated by a two-dot chain line is formed. Along the slope A2 of the valley, the water discharge path P is cut in advance so as to surround the valley. The cut-off water discharge channel P is for preventing the water of the upstream inflowing river Q from entering the land X.

図2は、第一地盤改良工程を説明するための図である。
まず、図2に示すように、土地Xのうち下流側の一部の領域X1において、地盤G1を安定化させる第一地盤改良工程を行う。
FIG. 2 is a diagram for explaining the first ground improvement process.
First, as shown in FIG. 2, a first ground improvement process for stabilizing the ground G <b> 1 is performed in a partial area X <b> 1 on the downstream side of the land X.

次に、第一遮水工程を行う。
図3は、第一遮水工程を説明するための図である。
図3に示すように、領域X1の下流側に堰堤1及び水処理施設2を設置し、堰堤1から地盤改良した領域X1の地盤G1の表面にわたって、遮水シート(遮水部)3を敷設する。遮水シート3は、例えば熱可塑性エラストマー等の樹脂素材からなる防水性を有するシートを採用することができる。また、堰堤1の下流側には、水処理施設2を設置し、堰堤1と水処理施設2との間に水抜き管4を設置しておく。水処理施設2は、廃棄物から浸出した浸出水が後述する集水管5等により導入され、浄化して有害物質等を取り除いた後、所定の水域に放流する。
Next, a first water shielding step is performed.
FIG. 3 is a diagram for explaining the first water shielding step.
As shown in FIG. 3, the dam 1 and the water treatment facility 2 are installed on the downstream side of the region X1, and the water shielding sheet (water shielding portion) 3 is laid over the surface of the ground G1 in the region X1 improved from the dam 1 to the ground. To do. As the water shielding sheet 3, for example, a waterproof sheet made of a resin material such as a thermoplastic elastomer can be adopted. In addition, a water treatment facility 2 is installed on the downstream side of the dam 1, and a drain pipe 4 is installed between the dam 1 and the water treatment facility 2. In the water treatment facility 2, the leachate leached from the waste is introduced through a water collecting pipe 5 and the like which will be described later, and after purifying and removing harmful substances, it is discharged into a predetermined water area.

次に、第一集水管設置工程を行う。
図4は、第一集水管設置工程、第一保護層造成工程及び第一堰堤設置工程を説明するための図である。
図4に示すように、領域X1の谷底A1に沿って有孔管からなる集水管5を設置し、水処理施設2に接続された水抜き管4と接続する。
Next, a 1st water collection pipe installation process is performed.
Drawing 4 is a figure for explaining the 1st water collecting pipe installation process, the 1st protection layer creation process, and the 1st dam installation process.
As shown in FIG. 4, a water collecting pipe 5 made of a perforated pipe is installed along the valley bottom A <b> 1 of the region X <b> 1 and connected to the water drain pipe 4 connected to the water treatment facility 2.

次に、第一保護層造成工程を行う。
領域X1において、遮水シート3の上に保護層6を設け、保護層6内に集水管5を埋設する。保護層6として、不織布等の保護マットや砂等を採用することができる。
Next, a first protective layer creation step is performed.
In the region X <b> 1, the protective layer 6 is provided on the water shielding sheet 3, and the water collecting pipe 5 is embedded in the protective layer 6. As the protective layer 6, a protective mat such as a nonwoven fabric or sand can be employed.

次に、第一堰堤設置工程を行う。
領域X1の上流側の境界部Y1に仮堰堤(堰堤)7を設置し、仮堰堤7の少なくとも下流側の側面7Aに仮堰堤用シート8を敷設する。仮堰堤用シート8は、廃棄物から浸み出した有害物質が隣接する上流側の領域X2に浸出するのを防止するものである。この際に、集水管5を仮堰堤7に貫通させ、上流側の端部5Xを封鎖しておく。
なお、領域X1に保護層6を設ける作業を下流側から行いつつ、領域X1の上流側に仮堰堤7を設置するように、第一保護層造成工程と第一堰堤設置工程とを同時進行で行ってもよい。
これにより、領域X1では、廃棄物(図5参照)W1の搬入が可能となる。
Next, the first dam installation process is performed.
A temporary dam (weir) 7 is installed at the boundary Y1 on the upstream side of the region X1, and a temporary dam sheet 8 is laid on at least the side surface 7A on the downstream side of the temporary dam 7. The temporary dam sheet 8 prevents toxic substances leached from the waste from leaching into the adjacent upstream region X2. At this time, the water collecting pipe 5 is passed through the temporary dam 7 and the upstream end 5X is sealed.
In addition, while performing the operation | work which provides the protective layer 6 in the area | region X1 from the downstream, the 1st protective layer formation process and the 1st dam installation process are progressing simultaneously so that the temporary dam 7 may be installed in the upstream of the area | region X1. You may go.
Thereby, in the area | region X1, waste (refer FIG. 5) W1 can be carried in.

次に、領域X1の境界部Y1の上流側の領域X2において、領域X1と同様の作業を行う。
まず、領域X2において、地盤G2を改良する第二地盤改良工程を行う。
Next, the same operation as that of the region X1 is performed in the region X2 upstream of the boundary portion Y1 of the region X1.
First, in the area X2, a second ground improvement process for improving the ground G2 is performed.

図5は、第二遮水工程、第二集水管設置工程、集水管接続工程、第二保護層造成工程及び第二堰堤設置工程を説明するための図である。
次に第二遮水工程を行う。
図5に示すように、遮水シート13を領域X2の地盤G2の表面に設置し、下流側の端部を領域X1に設置された遮水シート3と溶着等により接続する。
FIG. 5 is a diagram for explaining the second water shielding step, the second water collecting pipe installation step, the water collecting pipe connection step, the second protective layer creation step, and the second dam installation step.
Next, a second water shielding step is performed.
As shown in FIG. 5, the water shielding sheet 13 is installed on the surface of the ground G2 in the region X2, and the downstream end is connected to the water shielding sheet 3 installed in the region X1 by welding or the like.

次に、領域X2の谷底A1に沿って集水管15を設置する第二集水管設置工程を行う。その後、下流側の端部を仮堰堤7に貫通させた集水管5と集水管15とを接続する集水管接続工程を行う。   Next, the 2nd water collecting pipe installation process which installs the water collecting pipe 15 along the valley bottom A1 of the area | region X2 is performed. Then, the water collection pipe connection process which connects the water collection pipe 5 and the water collection pipe 15 which let the edge part of the downstream side penetrate the temporary dam 7 is performed.

次に、領域X2において、遮水シート13の上に保護層16を設け、保護層16内に集水管15を埋設する第二保護層造成工程を行う。   Next, in the region X <b> 2, a protective layer 16 is provided on the water-impervious sheet 13, and a second protective layer creation step is performed in which the water collecting pipe 15 is embedded in the protective layer 16.

次に、第二堰堤設置工程を行う。
領域X2の上流側の境界部Y2に仮堰堤17を設置し、仮堰堤17の少なくとも下流側の側面17Aに仮堰堤用シート18を敷設する。集水管15を仮堰堤17に貫通させ、上流側の端部15Xを封鎖しておく。
これにより、領域X2では、廃棄物(不図示)の搬入が可能となる。次に、領域X2の上流側で、同様に作業を繰り返すことにより、下流側の領域から順次廃棄物処分場の供用を開始することができる。
Next, the second dam installation process is performed.
The temporary dam 17 is installed at the boundary Y2 on the upstream side of the region X2, and the temporary dam sheet 18 is laid on at least the side surface 17A on the downstream side of the temporary dam 17. The water collecting pipe 15 is passed through the temporary dam 17, and the upstream end 15X is sealed.
Thereby, in the area | region X2, a waste (not shown) can be carried in. Next, by repeating the same operation on the upstream side of the region X2, the operation of the waste disposal site can be started sequentially from the downstream region.

このように構成された廃棄物処分場の構築方法では、廃棄物処分場が構築される土地Xのうち一部の領域X1において、地盤G1を改良する第一地盤改良工程、地盤G1の表面に遮水シート3を設ける第一遮水工程、遮水シート3の表面に保護層6を設ける第一保護層設置工程、及び境界部Y1に仮堰堤7を設ける第一堰堤設置工程を実施すれば、領域X1において廃棄物処分場の供用を先行して開始することができる。また、領域X1において廃棄物処分場の供用を開始しつつ、他の領域X2において、地盤G2を改良する第二地盤改良工程、地盤G2の表面に遮水シート13を設ける第二遮水工程、遮水シート13の表面に保護層16を設ける第二保護層設置工程、及び領域X1側とは異なる境界部Y2に仮堰堤17を設ける第二堰堤設置工程を実施すれば、領域X2において、廃棄物処分場の供用を開始することができる。つまり、将来的に廃棄物処分場が設置されるXのうち領域X1を領域X2よりも先行させて廃棄物処分場の供用を開始することができるため、廃棄物処分場の供用を早期に開始することができる。   In the construction method of the waste disposal site configured as described above, in the region X1 of the land X where the waste disposal site is constructed, the first ground improvement step for improving the ground G1, the surface of the ground G1 If the first water shielding step of providing the water shielding sheet 3, the first protective layer installation step of providing the protective layer 6 on the surface of the water shielding sheet 3, and the first dam installation step of providing the temporary dam 7 at the boundary Y <b> 1 are performed. In the area X1, the operation of the waste disposal site can be started in advance. In addition, while starting operation of the waste disposal site in the area X1, in the other area X2, a second ground improvement process for improving the ground G2, a second water shielding process for providing the water shielding sheet 13 on the surface of the ground G2, If the second protective layer installation step in which the protective layer 16 is provided on the surface of the water-impervious sheet 13 and the second dam installation step in which the temporary dam 17 is provided in the boundary portion Y2 different from the region X1 side are performed, the disposal in the region X2 The disposal site can be started. In other words, because it is possible to start the operation of the waste disposal site by putting the region X1 ahead of the region X2 in the X where the waste disposal site will be installed in the future, the operation of the waste disposal site is started early. can do.

また、第一集水管設置工程で領域X1に集水管5を設置して水処理施設2側に接続し、第二集水管設置工程で領域X2に集水管15を設置し、集水管接続工程で集水管5と集水管15とを接続するため、領域X2の集水管15を流通する浸出水を、領域X1の集水管5に流通させて集水することができる。よって、他の領域X2の集水管15を水処理施設2側に直接接続する必要がないため、大規模な工事を伴わない。   Moreover, the water collecting pipe 5 is installed in the area X1 in the first water collecting pipe installation process and connected to the water treatment facility 2 side, the water collecting pipe 15 is installed in the area X2 in the second water collecting pipe installation process, and the water collecting pipe connection process. Since the water collecting pipe 5 and the water collecting pipe 15 are connected, the leachate flowing through the water collecting pipe 15 in the region X2 can be circulated through the water collecting pipe 5 in the region X1 to collect water. Therefore, since it is not necessary to directly connect the water collecting pipe 15 of the other region X2 to the water treatment facility 2 side, large-scale construction is not involved.

また、廃棄物処分場を一部の領域ずつ供用していくが、施工の初期の段階で土地Xの最下流側に水処理施設2を設置して、各領域の廃棄物から浸出した浸出水を水処理施設2に導入することで、複数の水処理施設2を設置する必要がない。   In addition, the waste disposal site will be used in some areas, but at the initial stage of construction, the water treatment facility 2 is installed on the most downstream side of the land X, and the leachate leached from the waste in each area It is not necessary to install a plurality of water treatment facilities 2 by introducing to the water treatment facility 2.

次に、上記に示す実施形態の変形例として、上流側から順次廃棄物処分場の供用を開始する方法について、主に図6から図8を用いて説明する。
なお、以下の変形例において、前述した実施形態で用いた部材と同一の部材には同一の符号を付して、その説明を省略する。
Next, as a modification of the above-described embodiment, a method for sequentially starting in-use of the waste disposal site from the upstream side will be described mainly with reference to FIGS.
In the following modified examples, the same members as those used in the above-described embodiment are denoted by the same reference numerals, and the description thereof is omitted.

図6は、第一地盤改良工程を説明するための図である。
まず、図1に示すように、上記に示す実施形態と同様に、土地Xにおいて切り回し放水路Pを施工した後、図6に示すように、上流側の領域X11で地盤G11を安定化させるために第一地盤改良工程を行う。
FIG. 6 is a diagram for explaining the first ground improvement process.
First, as shown in FIG. 1, similarly to the embodiment shown above, after cutting and turning the drainage channel P in the land X, as shown in FIG. 6, the ground G <b> 11 is stabilized in the upstream region X <b> 11. Therefore, the first ground improvement process is performed.

図7は、第一遮水工程を説明するための図である。
次に、第一遮水工程を行う。
図7に示すように、領域X11の上流側に堰堤11を設置し、堰堤11から地盤改良した領域X11の地盤G11の表面にわたって、遮水シート23を敷設する。また、土地Xの最も下流側に水処理施設2を設置しておく。
FIG. 7 is a diagram for explaining the first water shielding step.
Next, a first water shielding step is performed.
As shown in FIG. 7, the dam 11 is installed on the upstream side of the region X11, and the water-impervious sheet 23 is laid from the dam 11 over the surface of the ground G11 in the region X11 improved in the ground. In addition, the water treatment facility 2 is installed on the most downstream side of the land X.

図8は、第一集水管設置工程、第一保護層造成工程及び第一堰堤設置工程を説明するための図である。
次に、図8に示すように、領域X11の谷底A1に沿って集水管25を設置する第一集水管設置工程を行う。
FIG. 8 is a diagram for explaining the first water collecting pipe installation step, the first protective layer creation step, and the first dam installation step.
Next, as shown in FIG. 8, the 1st water collection pipe installation process which installs the water collection pipe 25 along the valley bottom A1 of the area | region X11 is performed.

次に、領域X11において、遮水シート23の上に保護層26を設け、保護層26内に集水管25を埋設する第一保護層造成工程を行う。   Next, in the region X <b> 11, a first protective layer forming step is performed in which the protective layer 26 is provided on the water shielding sheet 23 and the water collecting pipe 25 is embedded in the protective layer 26.

次に、第一堰堤設置工程を行う。
領域X11の下流側の境界部Y11に仮堰堤27を設置し、仮堰堤27の少なくとも上流側の側面27Aに仮堰堤用シート28を敷設する。この際に、仮堰堤27に集水管25に接続された揚水井戸(不図示。以下同じ。)を設置しておき、揚水井戸で汲み出した水を、土地Xの外周部に設置した配管(不図示。以下同じ。)を経由させて、水処理施設2に導入できるようにしておく。
なお、領域X11に保護層26を設ける作業を上流側から行いつつ、領域X11の下流側に仮堰堤27を設置するように、第一保護層造成工程と第一堰堤設置工程とを同時進行で行ってもよい。
これにより、領域X11では、廃棄物W21(図9参照)の搬入が可能となる。
Next, the first dam installation process is performed.
The temporary dam 27 is installed at the boundary Y11 on the downstream side of the region X11, and the temporary dam sheet 28 is laid on at least the upstream side surface 27A of the temporary dam 27. At this time, a pumping well (not shown; the same applies hereinafter) connected to the water collecting pipe 25 is installed in the temporary dam 27, and the water pumped from the pumping well is installed on the outer periphery of the land X (not shown). It is possible to introduce it into the water treatment facility 2 via the figure.
In addition, while performing the operation | work which provides the protective layer 26 in the area | region X11 from upstream, the 1st protective layer formation process and the 1st dam installation process are advanced simultaneously so that the temporary dam 27 may be installed in the downstream of the area | region X11. You may go.
Thereby, in the area | region X11, the waste W21 (refer FIG. 9) can be carried in.

次に、領域X11の境界部Y11の下流側の領域X12において、領域X11と同様の作業を行う。
まず、領域X12において、地盤G12を改良する第二地盤改良工程を行う。
Next, the same operation as that in the region X11 is performed in the region X12 on the downstream side of the boundary portion Y11 of the region X11.
First, in the region X12, a second ground improvement process for improving the ground G12 is performed.

次に第二遮水工程を行う。
図9は、第二遮水工程、第二集水管設置工程、第二保護層造成工程及び第二堰堤設置工程を説明するための図である。
図9に示すように、遮水シート33を領域X12の地盤G12の表面に設置し、上流側の端部を領域X11に設置された遮水シート23と溶着等により接続する。
Next, a second water shielding step is performed.
FIG. 9 is a diagram for explaining the second water shielding step, the second water collecting pipe installation step, the second protective layer creation step, and the second dam installation step.
As shown in FIG. 9, the water shielding sheet 33 is installed on the surface of the ground G12 in the region X12, and the upstream end is connected to the water shielding sheet 23 installed in the region X11 by welding or the like.

次に、領域X12の谷底A1に沿って集水管35を設置する第二集水管設置工程を行う。   Next, the 2nd water collection pipe installation process which installs the water collection pipe 35 along the valley bottom A1 of the area | region X12 is performed.

次に、領域X12において、遮水シート33の上に保護層36を設け、保護層36内に集水管35を埋設する第二保護層造成工程を行う。   Next, in the region X <b> 12, a protective layer 36 is provided on the water shielding sheet 33, and a second protective layer forming step is performed in which the water collecting pipe 35 is embedded in the protective layer 36.

次に、第二堰堤設置工程を行う。
領域X12の下流側の境界部Y12に仮堰堤37を設置し、仮堰堤37の少なくとも上流側の側面37Aに仮堰堤用シート38を敷設する。この際に、仮堰堤37に集水管35に接続された揚水井戸(不図示。以下同じ。)を設置しておき、揚水井戸で汲み出した水を、土地Xの外周部に設置された配管を経由させて、水処理施設2に導入できるようにしておく。
これにより、領域X12では、廃棄物(不図示)の搬入が可能となる。次に、領域X12の下流側で、同様に作業を繰り返すことにより、上流側の領域から順次廃棄物処分場の供用を開始することができる。
Next, the second dam installation process is performed.
A temporary dam 37 is installed at the boundary Y12 on the downstream side of the region X12, and a temporary dam sheet 38 is laid on at least the upstream side surface 37A of the temporary dam 37. At this time, a pumping well (not shown; the same applies hereinafter) connected to the water collecting pipe 35 is installed in the temporary dam 37, and the water pumped out from the pumping well is installed on the outer periphery of the land X. It is made to be able to be introduced into the water treatment facility 2 via the route.
Thereby, in area | region X12, a waste (not shown) can be carried in. Next, by repeating the same operation on the downstream side of the region X12, the operation of the waste disposal site can be started sequentially from the upstream region.

なお、上述した実施の形態において示した各構成部材の諸形状や組み合わせ等は一例であって、本発明の主旨から逸脱しない範囲において設計要求等に基づき種々変更可能である。   The various shapes and combinations of the constituent members shown in the above-described embodiments are merely examples, and various modifications can be made based on design requirements and the like without departing from the gist of the present invention.

例えば、上記に示す実施形態及び変形例では、土地Xの下流側または上流側から廃棄物処分場の供用を開始する例を挙げて説明したが、本発明はこれに限られない。供用を開始する箇所は適宜選択可能であり、例えば土地Xの中流側から上流(下流)側に向かって供用を開始した後に、中流側から下流(上流)側に向かって供用を開始してもよい。   For example, in the embodiment and the modification described above, the example of starting the operation of the waste disposal site from the downstream side or the upstream side of the land X has been described, but the present invention is not limited thereto. The location where the service is started can be selected as appropriate. For example, after starting operation from the midstream side of the land X toward the upstream (downstream) side, the service can be started from the midstream side toward the downstream (upstream) side. Good.

1,11…堰堤
2…水処理施設
3,13,23,33…遮水シート
4…水抜き管
5,15,25,35…集水管
6,16,26,36…保護層
7,17,27,37…仮堰堤
A1…谷底
A2…斜面
G1,G2,G11,G12地盤
W1,W21…廃棄物
Y1,…境界部
X…土地(所定領域)
X1,X11…一部の領域
X2,X12…他の領域
DESCRIPTION OF SYMBOLS 1,11 ... Dam 2 ... Water treatment facilities 3, 13, 23, 33 ... Water shielding sheet 4 ... Drain pipes 5, 15, 25, 35 ... Catch pipes 6, 16, 26, 36 ... Protective layers 7, 17, 27, 37 ... Temporary dam A1 ... Valley bottom A2 ... Slope G1, G2, G11, G12 Ground W1, W21 ... Waste Y1, ... Boundary X ... Land (predetermined area)
X1, X11 ... some areas X2, X12 ... other areas

Claims (2)

所定領域に廃棄物処分場を構築する廃棄物処分場の構築方法であって、
前記所定領域のうち一部の領域を地盤改良する第一地盤改良工程と、
前記一部の領域の地盤の表面に遮水部を設ける第一遮水工程と、
前記一部の領域の前記遮水部の表面に保護層を設ける第一保護層造成工程と、
前記一部の領域の境界部に堰堤を設ける第一堰堤設置工程と、
前記所定領域のうち前記境界部に隣接する他の領域を地盤改良する第二地盤改良工程と、
前記他の領域の地盤の表面に遮水部を設ける第二遮水工程と、
前記他の領域の前記遮水部の表面に保護層を設ける第二保護層造成工程と、
前記他の領域における前記一部の領域側とは異なる境界部に堰堤を設ける第二堰堤設置工程と、を備えることを特徴とする廃棄物処分場の構築方法。
A waste disposal site construction method for constructing a waste disposal site in a predetermined area,
A first ground improvement step of improving the ground of a part of the predetermined area;
A first water shielding step of providing a water shielding portion on the surface of the ground in the partial area;
A first protective layer forming step of providing a protective layer on the surface of the water shielding portion in the partial area;
A first dam installation step of providing a dam at the boundary of the partial area;
A second ground improvement step of improving the ground of the other region adjacent to the boundary portion of the predetermined region;
A second water shielding step of providing a water shielding portion on the surface of the ground in the other region;
A second protective layer forming step of providing a protective layer on the surface of the water shielding portion in the other region;
And a second dam installation step of providing a dam at a boundary portion different from the partial region side in the other region.
前記一部の領域に集水管を設置して水処理施設に接続する第一集水管設置工程と、
前記他の領域に集水管を設置する第二集水管設置工程と、
前記一部の領域の集水管と前記他の領域の集水管とを接続する集水管接続工程と、を備えることを特徴とする廃棄物処分場の構築方法。
A first water collecting pipe installation step of installing a water collecting pipe in the partial area and connecting it to a water treatment facility;
A second water collecting pipe installation step of installing a water collecting pipe in the other area;
A method for constructing a waste disposal site, comprising: a water collecting pipe connecting step for connecting the water collecting pipes in the partial area and the water collecting pipes in the other area.
JP2015166930A 2015-08-26 2015-08-26 How to build a waste disposal site Active JP6764588B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP2015166930A JP6764588B2 (en) 2015-08-26 2015-08-26 How to build a waste disposal site

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP2015166930A JP6764588B2 (en) 2015-08-26 2015-08-26 How to build a waste disposal site

Publications (2)

Publication Number Publication Date
JP2017042715A true JP2017042715A (en) 2017-03-02
JP6764588B2 JP6764588B2 (en) 2020-10-07

Family

ID=58209140

Family Applications (1)

Application Number Title Priority Date Filing Date
JP2015166930A Active JP6764588B2 (en) 2015-08-26 2015-08-26 How to build a waste disposal site

Country Status (1)

Country Link
JP (1) JP6764588B2 (en)

Citations (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH08323316A (en) * 1995-06-05 1996-12-10 Kajima Corp System for preventing contamination of ground water of final waste disposition plant
JP2002143801A (en) * 2000-11-14 2002-05-21 Ohbayashi Corp Waste disposal site
JP2002159931A (en) * 2000-11-28 2002-06-04 Okumura Corp Execution method for landfill disposal site
JP2002361195A (en) * 2001-06-04 2002-12-17 Hanashima Masataka Landfilling treatment method for waste
JP2003285018A (en) * 2002-03-28 2003-10-07 Taisei Corp Waste landfilling method
JP2005087782A (en) * 2003-09-12 2005-04-07 Kumagai Gumi Co Ltd Draining method of zone scheduled to be waste treatment site
JP2007313432A (en) * 2006-05-25 2007-12-06 Nippon Kankyo Calcium Kenkyusho:Kk Equipment at embankment covering waste disposal site
JP2010504198A (en) * 2006-09-25 2010-02-12 クオン カン,ヨン Waste landfill construction method

Patent Citations (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH08323316A (en) * 1995-06-05 1996-12-10 Kajima Corp System for preventing contamination of ground water of final waste disposition plant
JP2002143801A (en) * 2000-11-14 2002-05-21 Ohbayashi Corp Waste disposal site
JP2002159931A (en) * 2000-11-28 2002-06-04 Okumura Corp Execution method for landfill disposal site
JP2002361195A (en) * 2001-06-04 2002-12-17 Hanashima Masataka Landfilling treatment method for waste
JP2003285018A (en) * 2002-03-28 2003-10-07 Taisei Corp Waste landfilling method
JP2005087782A (en) * 2003-09-12 2005-04-07 Kumagai Gumi Co Ltd Draining method of zone scheduled to be waste treatment site
JP2007313432A (en) * 2006-05-25 2007-12-06 Nippon Kankyo Calcium Kenkyusho:Kk Equipment at embankment covering waste disposal site
JP2010504198A (en) * 2006-09-25 2010-02-12 クオン カン,ヨン Waste landfill construction method

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
廃棄物と建設発生土の地盤工学的有効利用, JPN6020013036, 30 September 1998 (1998-09-30), pages 166 - 168, ISSN: 0004249219 *

Also Published As

Publication number Publication date
JP6764588B2 (en) 2020-10-07

Similar Documents

Publication Publication Date Title
KR101769594B1 (en) Draining member for embankment and method for installing the same
JP2006200141A (en) Method and structure for treatment of water inflow in tunnel
KR100896707B1 (en) The stucture for exclude leachate of waste reclaimed land
JP2009114784A (en) Rainwater storage device and its construction method
KR100607714B1 (en) The landfill having the drainage system against rain and the method for forming this landfill
JP2011058173A (en) Method for improving soft ground
JP2017042715A (en) Construction method for waste disposal site
JP4632586B2 (en) Purification method for contaminated soil
JP2016069793A (en) Ground improvement method and ground improvement system
JP4721569B2 (en) Contaminated soil diffusion prevention method
JP3507808B2 (en) Landfill device and method
JP2014223560A (en) Simple bottom slab structure of final disposal site
KR100348515B1 (en) Engineering methods to improve subsurface of soft ground
JP2015217351A (en) Groundwater purification system and groundwater purification method
JP3684981B2 (en) Contaminated soil purification method
KR102253356B1 (en) Waste leachate removal method in waste landfill
JP2019157511A (en) Purification mass
JP4256752B2 (en) Waste disposal method
JP3402202B2 (en) Collection and drainage structure of waste disposal site
JP2003340392A (en) Venting equipment of landfill site and construction method thereof
JPH08323318A (en) Water-shielding sheet laying structure in waste disposal plant
JP2023002004A (en) Drainage system and drainage method
JP2005087782A (en) Draining method of zone scheduled to be waste treatment site
JP2015077539A (en) Waterproof structure for periphery of final disposal site
JP2004351240A (en) Structure of landfill waste layer

Legal Events

Date Code Title Description
A621 Written request for application examination

Free format text: JAPANESE INTERMEDIATE CODE: A621

Effective date: 20180615

RD03 Notification of appointment of power of attorney

Free format text: JAPANESE INTERMEDIATE CODE: A7423

Effective date: 20181005

A977 Report on retrieval

Free format text: JAPANESE INTERMEDIATE CODE: A971007

Effective date: 20190725

A131 Notification of reasons for refusal

Free format text: JAPANESE INTERMEDIATE CODE: A131

Effective date: 20190813

A521 Request for written amendment filed

Free format text: JAPANESE INTERMEDIATE CODE: A523

Effective date: 20191004

A02 Decision of refusal

Free format text: JAPANESE INTERMEDIATE CODE: A02

Effective date: 20200407

A521 Request for written amendment filed

Free format text: JAPANESE INTERMEDIATE CODE: A523

Effective date: 20200629

A911 Transfer to examiner for re-examination before appeal (zenchi)

Free format text: JAPANESE INTERMEDIATE CODE: A911

Effective date: 20200714

TRDD Decision of grant or rejection written
A01 Written decision to grant a patent or to grant a registration (utility model)

Free format text: JAPANESE INTERMEDIATE CODE: A01

Effective date: 20200804

A61 First payment of annual fees (during grant procedure)

Free format text: JAPANESE INTERMEDIATE CODE: A61

Effective date: 20200901

R150 Certificate of patent or registration of utility model

Ref document number: 6764588

Country of ref document: JP

Free format text: JAPANESE INTERMEDIATE CODE: R150