JP2017031562A - Construction method of continuous underground wall - Google Patents

Construction method of continuous underground wall Download PDF

Info

Publication number
JP2017031562A
JP2017031562A JP2015149200A JP2015149200A JP2017031562A JP 2017031562 A JP2017031562 A JP 2017031562A JP 2015149200 A JP2015149200 A JP 2015149200A JP 2015149200 A JP2015149200 A JP 2015149200A JP 2017031562 A JP2017031562 A JP 2017031562A
Authority
JP
Japan
Prior art keywords
ground improvement
excavation
improvement body
ground
groove
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
JP2015149200A
Other languages
Japanese (ja)
Other versions
JP6378652B2 (en
Inventor
田中 誠
Makoto Tanaka
田中  誠
雅俊 熊谷
Masatoshi Kumagai
雅俊 熊谷
博久 早川
Hirohisa Hayakawa
博久 早川
勝利 藤崎
Katsutoshi Fujisaki
勝利 藤崎
伊藤 弘之
Hiroyuki Ito
伊藤  弘之
淳 島村
Jun Shimamura
淳 島村
田中 誠治
Seiji Tanaka
誠治 田中
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Kajima Corp
Chemical Grouting Co Ltd
Original Assignee
Kajima Corp
Chemical Grouting Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Kajima Corp, Chemical Grouting Co Ltd filed Critical Kajima Corp
Priority to JP2015149200A priority Critical patent/JP6378652B2/en
Publication of JP2017031562A publication Critical patent/JP2017031562A/en
Application granted granted Critical
Publication of JP6378652B2 publication Critical patent/JP6378652B2/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Consolidation Of Soil By Introduction Of Solidifying Substances Into Soil (AREA)
  • Bulkheads Adapted To Foundation Construction (AREA)

Abstract

PROBLEM TO BE SOLVED: To provide a construction method for a continuous underground wall for readily constructing a continuous underground wall while preventing collapse of a groove wall during the construction work at a low altitude below a head.SOLUTION: In a construction method for a continuous underground wall, a scheduled excavation area S1 for an excavation groove G of a preceding element EA and an intermediate area S2 comprise a unit area. The construction method for a continuous underground wall includes a construction step in which ground improvement bodies 1 (1A, 1B) having the unit area inside are constructed for each of the unit areas. The following processes are performed in the construction step for each of the unit areas: forming a borehole GH in a ground; inserting a rod 12 into the borehole GH, the rod having a cylindrical tip rod 121, a nozzle 122, and an extension rod 123; spraying a liquid J from the nozzle 122 outward in a radial direction, the liquid containing a solidification material and water; and at the same time, rotating and lifting the rod 12 for constructing the ground improvement bodies 1 (1A, 1B) having a diameter greater than the borehole GH and strength greater than the ground.SELECTED DRAWING: Figure 1

Description

本発明は、地中連続壁構築方法に関する。   The present invention relates to an underground continuous wall construction method.

地中内に鉄筋コンクリート製等の地中連続壁を構築する地中連続壁構築方法としては、地中連続壁を先行エレメントと後行エレメントに分け、まず、地中に間隔をおいて先行エレメントを順次形成した後、この先行エレメントに後行エレメントを継ぎ足して前記地中連続壁を構築する方法が一般的に知られている。
この種の地中連続壁構築方法では、特許文献1に開示されているように、地中に間隔をおいて掘削機により掘削される掘削溝内に鉄筋籠を投入すると共にコンクリートを打設して、先行エレメントを形成した後、先行エレメント間の地盤等を掘削機により掘削して得られる掘削溝内に鉄筋籠を投入すると共にコンクリートを打設して、後行エレメントを形成することで、前記地中連続壁を構築している。
この一般的な地中連続壁構築方法を、例えば細粒分含有率が低い(例えば粒径0.075mm未満の土粒子の含有率が約35%以下)土層等を含む地盤において地中連続壁を施工する方法として採用すると、掘削機による地盤の掘削中や鉄筋籠の建て込み中等に、前記掘削溝の溝壁の一部が崩壊するおそれがある。そして、溝壁が崩壊すると、掘削機や鉄筋籠が崩壊した土砂内に埋没等して、掘削が不能になったり、コンクリートの打設が困難になったりするおそれがある。また、溝壁が崩壊すると、予定した地中連続壁の出来形が確保できず、さらに、崩壊した土砂が掘削溝の底部に堆積等して、地中連続壁に要求される支持力が得られないおそれもある。このため、溝壁崩壊リスクの高い土層を含む地盤等において、溝壁を保護しつつ地中連続壁を構築可能な地中連続壁構築方法が求められている。
As an underground continuous wall construction method for building underground continuous walls made of reinforced concrete, etc., the underground continuous wall is divided into a leading element and a trailing element. It is generally known to construct the underground continuous wall by sequentially forming and then adding a succeeding element to the preceding element.
In this type of underground continuous wall construction method, as disclosed in Patent Document 1, reinforcing rods are poured into the excavation groove excavated by the excavator at an interval in the ground and concrete is placed. Then, after forming the preceding element, by inserting a reinforcing bar into the excavation groove obtained by excavating the ground etc. between the preceding elements with an excavator, and placing concrete to form the trailing element, The underground continuous wall is constructed.
This general underground continuous wall construction method is, for example, continuous underground in a ground including a soil layer or the like having a low fine particle content (for example, the content of soil particles having a particle size of less than 0.075 mm is about 35% or less). If it is adopted as a method for constructing a wall, a part of the groove wall of the excavation groove may collapse during excavation of the ground by the excavator or erection of a reinforcing bar. When the groove wall collapses, the excavator and the reinforcing bar are buried in the collapsed earth and sand, making it impossible to excavate or making it difficult to place concrete. In addition, if the groove wall collapses, the planned shape of the underground continuous wall cannot be secured, and the collapsed earth and sand accumulate on the bottom of the excavation groove to obtain the required bearing capacity for the underground continuous wall. There is also a risk that it will not be possible. For this reason, there is a need for an underground continuous wall construction method capable of constructing an underground continuous wall while protecting the groove wall in a ground including a soil layer having a high risk of groove wall collapse.

ここで、地中連続壁の構築の際に溝壁の保護を必要とする場合、例えば、地中連続壁の構築に先立って、この地中連続壁の構築予定領域を挟むように2列のソイルモルタル柱列をSMW工法により構築することが一般的に行われている。詳しくは、大径のオーガスクリューを備えたベースマシンにより、地盤を掘削すると共に原位置の土砂とモルタル等とを原位置で混合及び撹拌して、2列のソイルモルタル柱列を形成し、この2列のソイルモルタル柱列により、地中連続壁の構築用の掘削溝の溝壁を保護することで、地中連続壁構築中における溝壁崩壊の発生を抑制している。   Here, when it is necessary to protect the groove wall during the construction of the underground continuous wall, for example, prior to the construction of the underground continuous wall, two rows are arranged so as to sandwich the construction planned area of the underground continuous wall. It is common practice to construct a soil mortar column by the SMW method. Specifically, a base machine equipped with a large-diameter auger screw excavates the ground and mixes and stirs the original soil and mortar at the original position to form two rows of soil mortar columns. By protecting the groove wall of the excavation groove for the construction of the underground continuous wall with the two rows of soil mortar columns, the occurrence of the groove wall collapse during the underground continuous wall construction is suppressed.

特開平5−132927号公報JP-A-5-132927

ところで、ソイルモルタル柱列により溝壁を保護して地中連続壁を構築する地中連続壁構築方法では、掘削及び混練用の比較的に大径且つ大重量のオーガスクリューを有する大型のベースマシンが必要である。また、この大型のベースマシンの地中連続壁構築予定箇所への据え付け時や搬出時等に、大型クレーンを必要とする。
しかしながら、地中連続壁の構築予定箇所の上空に何らかの構造物が存在する施工現場では、上記のような大型のベースマシンや大型クレーンを用いることができない場合もあり、工夫が求められている。
By the way, in the underground continuous wall construction method for constructing the underground continuous wall by protecting the groove wall by the soil mortar column, the large base machine having a relatively large diameter and heavy auger screw for excavation and kneading. is necessary. In addition, a large crane is required when installing or carrying out this large base machine at a place where the underground continuous wall construction is planned.
However, there is a case where a large base machine or a large crane as described above cannot be used at a construction site where some structure exists above the planned construction site of the underground continuous wall, and a device is required.

本発明は、このような実状に鑑み、地中連続壁の構築予定箇所の上空に何らかの構造物が存在し、クレーン作業が制約を受ける領域にて、地中連続壁の構築中における溝壁の崩壊を防止しつつ地中連続壁を容易に構築可能な地中連続壁構築方法を提供することを目的とする。   In the present invention, in view of such a situation, there is some structure above the planned construction site of the underground continuous wall, and in the region where the crane work is restricted, the groove wall during construction of the underground continuous wall An object of the present invention is to provide an underground continuous wall construction method capable of easily constructing an underground continuous wall while preventing collapse.

上記課題に対して、本発明の一側面に係る地中連続壁構築方法では、地中に間隔をおいて掘削される先行エレメント用の各掘削溝内に先行エレメントを形成した後、互いに隣り合う前記先行エレメントの端部を掘削すると共に該先行エレメント間の中間領域を掘削して得られる後行エレメント用の各掘削溝内に後行エレメントを形成して地中連続壁を構築する地中連続壁構築方法であって、一つの前記先行エレメント用の前記掘削溝の掘削予定領域と、一つの前記中間領域とを、それぞれ単位領域とし、前記先行エレメント用の前記掘削溝の掘削に先立って、前記単位領域が内部に位置する地盤改良体を、前記単位領域毎にそれぞれ造成する造成工程を含み、前記単位領域毎の前記造成工程では、前記地中に鉛直方向に延伸するボーリング孔を形成し、円筒状の先端ロッドと、当該先端ロッドの先端部側に設けられるノズルと、前記先端ロッドの基端部側に順次継ぎ足される延長ロッドと、を有するロッドを前記ボーリング孔に挿入し、固化材と水を含む液体を前記ノズルから半径方向外方に向けて噴射しつつ、前記ロッドを回転させると共に、前記ロッドを引き上げて、前記ボーリング孔より大径であり且つ前記地盤より強度の高い前記地盤改良体を造成する構成とする。   For the above problem, in the underground continuous wall construction method according to one aspect of the present invention, the preceding elements are formed in the excavation grooves for the preceding elements excavated in the ground at intervals, and then adjacent to each other. Underground continuation in which a continuous element is formed by forming a trailing element in each excavation groove for a trailing element obtained by excavating the end of the preceding element and excavating an intermediate region between the preceding elements. A wall construction method, wherein a drilling planned area of the excavation groove for one of the preceding elements and an intermediate area of each are set as unit areas, and prior to excavation of the excavation groove for the preceding element, A boring hole extending in the vertical direction into the ground in the forming step for each unit region, including a forming step for forming the ground improvement body in which the unit region is located for each unit region; Forming and inserting a rod having a cylindrical tip rod, a nozzle provided on the tip end side of the tip rod, and an extension rod sequentially added to the base end side of the tip rod into the boring hole, The rod is rotated while ejecting a liquid containing solidification material and water radially outward from the nozzle, and the rod is pulled up to be larger in diameter than the boring hole and higher in strength than the ground. The ground improvement body is constructed.

前記一側面による地中連続壁構築方法によれば、一つの先行エレメント用の掘削溝の掘削予定領域と、互いに隣り合う先行エレメント間の一つの中間領域とを、それぞれ単位領域とし、先行エレメント用の掘削溝の掘削に先立って、この単位領域が内部に位置する地盤改良体を、単位領域毎にそれぞれ造成している。そして、この単位領域毎の造成工程では、先端部側にノズルが設けられた先端ロッドの基端部側に延長ロッドを順次継ぎ足してなるロッドをボーリング孔内に挿入し、このボーリング孔内で前記ノズルから固化材と水を含む液体を半径方向外方に向けて噴射させつつ、ロッドを回転及び引き上げることで、地盤より強度の高い前記地盤改良体を造成している。
これにより、先行エレメント用の各掘削溝は、既に造成されている地盤改良体内を掘削することにより形成でき、後行エレメント用の各掘削溝は、既に造成されている地盤改良体と、既に形成されている互いに隣り合う先行エレメントの端部とを掘削することにより形成することができる。したがって、例えば、各地盤改良体強度を、その地盤改良体や先行エレメントを掘削する掘削装置の能力や工法等に応じて周囲の地盤よりも適宜高めに設定するだけで、各掘削溝の溝壁の安定化を図ることができるため、地中連続壁構築中における溝壁の崩壊を防止することができる。
そして、地中連続壁の構築予定箇所の上空に何らかの構造物が存在し、クレーン作業が制約を受ける領域であっても、単に小型の削孔機により前記ロッドを挿入可能な小径のボーリング孔を掘削し、そのボーリング孔に前記ロッドを延長しながら挿入し、そのロッドの先端のノズルから固化材と水を含む液体を噴射させつつロッドを回転及び引き上げるだけで、地中連続壁の構築予定箇所に周囲の地盤よりも適宜強度を高めた地盤改良体を予め構築(造成)することができる。なお、ロッド挿入用の小径の前記ボーリング孔や前記掘削溝を形成するための機械及び工法は、それぞれ、各掘削溝の掘削予定領域の地面からその上空に存在する構造物までの高さに応じて、適宜の機械及び工法を採用すればよい。
According to the underground continuous wall construction method according to the one aspect, a planned excavation area of an excavation groove for one preceding element and an intermediate area between adjacent preceding elements are set as unit areas, respectively. Prior to excavation of the excavation groove, a ground improvement body in which this unit region is located is formed for each unit region. Then, in the creation process for each unit region, a rod formed by sequentially adding extension rods to the proximal end portion side of the distal end rod provided with the nozzle on the distal end portion side is inserted into the boring hole, The ground improvement body having higher strength than the ground is created by rotating and pulling up the rod while ejecting a liquid containing solidified material and water from the nozzle outward in the radial direction.
As a result, each excavation groove for the preceding element can be formed by excavating the ground improvement body already formed, and each excavation groove for the succeeding element is already formed with the already established ground improvement body. Can be formed by excavating the ends of the adjacent preceding elements. Therefore, for example, the strength of each ground improvement body is set appropriately higher than the surrounding ground according to the ability and construction method of the excavation equipment for excavating the ground improvement body and the preceding element, and the groove wall of each excavation groove Therefore, it is possible to prevent the groove wall from collapsing during construction of the underground continuous wall.
And even if there is some structure above the planned construction site of the underground continuous wall and the area where the crane work is restricted, a small-diameter boring hole that can be inserted with a rod with a small drilling machine is provided. Drilling and inserting the rod into the borehole while extending the rod, and rotating and pulling up the rod while spraying a liquid containing solidification material and water from the nozzle at the tip of the rod In addition, it is possible to build (create) a ground improvement body having a strength appropriately higher than that of the surrounding ground. It should be noted that the machine and method for forming the small-diameter boring hole for inserting the rod and the excavation groove depend on the height from the ground in the planned excavation area of each excavation groove to the structure existing above it. Thus, an appropriate machine and construction method may be employed.

このようにして、地中連続壁の構築予定箇所の上空に何らかの構造物が存在し、クレーン作業が制約を受ける領域にて、地中連続壁の構築中における溝壁の崩壊を防止しつつ地中連続壁を容易に構築可能な地中連続壁構築方法を提供することができる。   In this way, in the area where there is some structure above the planned construction site of the underground continuous wall and the crane work is restricted, the ground wall is prevented from collapsing during the construction of the underground continuous wall. An underground continuous wall construction method capable of easily constructing an intermediate continuous wall can be provided.

本実施形態における地中連続壁構築方法により構築した地中連続壁Eの断面図である。It is sectional drawing of the underground continuous wall E constructed | assembled by the underground continuous wall construction method in this embodiment. 上記地中連続壁Eの上面図である。It is a top view of the underground continuous wall E. 上記実施形態における地盤改良体造成装置の概略構成を示す図であり、地中連続壁の構築予定箇所の地盤の断面図でもある。It is a figure which shows schematic structure of the ground improvement body formation apparatus in the said embodiment, and is also sectional drawing of the ground of the construction planned location of an underground continuous wall. 上記実施形態における掘削装置の概略構成を示す図である。It is a figure which shows schematic structure of the excavation apparatus in the said embodiment. 上記実施形態における地中連続壁構築方法の一例を説明するための概念図であり、地盤改良体の造成途中の状態を示した平面図である。It is a conceptual diagram for demonstrating an example of the underground continuous wall construction method in the said embodiment, and is the top view which showed the state in the middle of construction of a ground improvement body. 上記地盤改良体の造成が完了した状態を示した平面図である。It is the top view which showed the state which creation of the said ground improvement body was completed. 上記地盤改良体の造成工程の一例を説明するための概念図であり、ボーリング孔形成工程を示す図である。It is a conceptual diagram for demonstrating an example of the creation process of the said ground improvement body, and is a figure which shows a boring hole formation process. 先行エレメント用の各地盤改良体(第1地盤改良体)の造成を説明するための図である。It is a figure for demonstrating creation of the various ground improvement body (1st ground improvement body) for preceding elements. 上記第1地盤改良体の造成途中の状態を示す図である。It is a figure which shows the state in the middle of the creation of the said 1st ground improvement body. 上記第1地盤改良体の造成が完了した状態を示す図である。It is a figure which shows the state which creation of the said 1st ground improvement body was completed. 後行エレメント用の各地盤改良体(第2地盤改良体)の造成が完了し、造成工程が完了した状態を示す図である。It is a figure which shows the state which completed the creation of each ground improvement body (2nd ground improvement body) for succeeding elements, and the creation process was completed. 先行エレメント用の掘削溝の掘削途中の状態を示した図である。It is the figure which showed the state in the middle of excavation of the excavation groove for leading elements. 先行エレメント用の掘削溝の掘削が完了した状態を示した拡大平面図である。It is the enlarged plan view which showed the state which excavation of the excavation groove for the preceding elements was completed. 鉄筋籠建て込み工程を説明するための図である。It is a figure for demonstrating a reinforcing bar construction process. コンクリート打設工程を説明するための図であり、先行エレメントの形成が完了した状態を示す図でもある。It is a figure for demonstrating a concrete placement process, and is also a figure which shows the state which the formation of the preceding element was completed. 先行エレメントの形成が完了した状態を示す拡大平面図である。It is an enlarged plan view showing the state where the formation of the preceding element is completed. 後行エレメント用の掘削溝の掘削中の状態を示した図である。It is the figure which showed the state under excavation of the excavation groove for a succeeding element. 後行エレメント用の掘削溝の掘削が完了した状態を示した拡大平面図である。It is the enlarged plan view which showed the state which excavation of the excavation groove for succeeding elements was completed. 前記地盤改良体掘削工程の後の地盤改良体1の薄肉部厚さ及び造成径の設定手順を説明するためのフロー図である。It is a flowchart for demonstrating the setting procedure of the thin part thickness of the ground improvement body 1 and the formation diameter after the said ground improvement body excavation process. 地盤改良体の一軸圧縮強さと薄肉部厚さとの関係を示す図である。It is a figure which shows the relationship between the uniaxial compressive strength of a ground improvement body, and a thin part thickness. 地盤改良体の断面形状の変形例を示す図である。It is a figure which shows the modification of the cross-sectional shape of a ground improvement body. 地盤改良体の断面形状の別の変形例を示す図である。It is a figure which shows another modification of the cross-sectional shape of a ground improvement body.

以下に、本発明に係る地中連続壁構築方法の実施形態を添付図面に基づいて説明する。
本発明の一実施形態における地中連続壁構築方法は、地中連続壁構築予定領域に予め地盤改良体1を造成する造成工程と、地盤改良体1内を鉛直方向に掘削して掘削溝Gを形成する掘削工程と、掘削溝G内に鉄筋籠を建て込む鉄筋籠建て込み工程と、コンクリート打設工程とを含む。
図1は、本実施形態における地中連続壁構築方法により構築した地中連続壁Eの部分断面図を示し、図2は図1に示す地中連続壁Eの上面図(地上側から視た拡大平面図)を示す。図3は本実施形態における地中連続壁構築方法において用いる地盤改良体造成装置10の概略構成を示し、図4は本実施形態において用いる掘削装置20の概略構成を示す。なお、図1は、図2に示す地中連続壁Eの中心線Oを通る垂直断面図でもある。
Below, an embodiment of the underground continuous wall construction method concerning the present invention is described based on an accompanying drawing.
The underground continuous wall construction method according to an embodiment of the present invention includes a creation step of creating the ground improvement body 1 in advance in the underground continuous wall construction planned area, and excavating the inside of the ground improvement body 1 in the vertical direction to form the excavation groove G. The excavation process which forms reinforced concrete, the reinforcement bar construction process which builds a reinforcement bar in the excavation groove G, and the concrete placement process are included.
FIG. 1 shows a partial cross-sectional view of an underground continuous wall E constructed by the underground continuous wall construction method in the present embodiment, and FIG. 2 is a top view of the underground continuous wall E shown in FIG. 1 (viewed from the ground side). An enlarged plan view) is shown. FIG. 3 shows a schematic configuration of the ground improvement body generating apparatus 10 used in the underground continuous wall construction method in the present embodiment, and FIG. 4 shows a schematic configuration of the excavating apparatus 20 used in the present embodiment. 1 is also a vertical sectional view passing through the center line O of the underground continuous wall E shown in FIG.

本実施形態において、地中連続壁Eは、鉄筋コンクリート製の構造壁であり、壁厚tを有して地中内に立設し、水平一方向に適宜長さを有して延伸し、全体として横長矩形断面を有して構築される場合を一例にして挙げて説明する。この地中連続壁Eは、図1及び図2に示すように、その水平延伸方向に所定の間隔をおいて形成される先行エレメントEAと、互いに隣り合う先行エレメントEAの短辺側に順次継ぎ足される後行エレメントEBとからなり、先行エレメントEAと後行エレメントEBとが一列に交互に配列されて構成されている。先行エレメントEAと後行エレメントEBは、それぞれ矩形断面を有し、その短辺方向の長さが地中連続壁Eの壁厚tに相当し、長辺方向の面が地中連続壁Eの壁面になる。各図において、地中連続壁Eは、水平方向一端側の部分のみを図示するが、水平方向他端側まで、同じ構成で延伸している。   In this embodiment, the underground continuous wall E is a structural wall made of reinforced concrete, has a wall thickness t, is erected in the ground, and has an appropriate length in one horizontal direction, and is extended to the whole. As an example, the case of having a horizontally long rectangular cross section will be described. As shown in FIGS. 1 and 2, the underground continuous wall E is sequentially added to the preceding element EA formed at a predetermined interval in the horizontal extending direction and the shorter side of the preceding element EA adjacent to each other. The leading element EA and the trailing element EB are alternately arranged in a line. The leading element EA and the trailing element EB each have a rectangular cross section, the length in the short side direction corresponds to the wall thickness t of the underground continuous wall E, and the surface in the long side direction corresponds to the underground continuous wall E. It becomes a wall. In each figure, although the underground continuous wall E shows only the part of the horizontal direction one end side, it is extended | stretched by the same structure to the horizontal direction other end side.

また、本実施形態において、先行エレメントEAの出来上がり時(つまり、後行エレメントが継ぎ足される前)の長辺方向の長さであるエレメント幅Wは、後行エレメントEBの出来上がり時のエレメント幅Wと同じであるものとする。先行エレメントEAは、後行エレメントEBとの接続の際に、その端部の一部が掘削(切削)される。このため、継ぎ足された後の先行エレメントEAの幅は、図2に示すように、後行エレメントEBのエレメント幅Wより若干短くなっている。   In this embodiment, the element width W, which is the length in the long side direction when the preceding element EA is completed (that is, before the succeeding element is added), is the element width W when the succeeding element EB is completed. It shall be the same. The leading element EA is partly excavated (cut) at the time of connection with the trailing element EB. For this reason, the width of the preceding element EA after being added is slightly shorter than the element width W of the succeeding element EB, as shown in FIG.

本実施形態では、既存の鉄道高架橋の直下の低空頭且つ狭隘な施工場所、つまり、地中連続壁Eの構築予定領域の上空に、既設構造物として鉄道高架橋Bが存在する低空頭な場所である上、その構築予定領域の地上側周辺に、十分な作業スペースを確保することが困難な狭隘な場所で、地中に鉄筋コンクリート製の地中連続壁Eを構築する場合を一例として、以下説明する。
具体的には、地中連続壁Eの構築予定領域の鉄道高架橋Bは地面から約3〜4mの高さ位置に存在するものとする。なお、本実施形態では、既設構造物は鉄道高架橋Bであり、地中連続壁Eをこの鉄道高架橋Bの直下の低空頭且つ狭隘な場所に構築する場合で説明するが、これに限らず、地中連続壁Eの構築予定箇所の上空に何らかの構造物が存在し、クレーン作業が制約を受ける領域であれば、どのような施工場所でもよい。
また、本実施形態において、地中連続壁Eの構築予定領域を含む地盤は、地面側に位置する上層G1と、その上層G1の下方に位置する支持層G2とを含み、上層G1は細粒分含有率が低く(例えば、粒径0.075mm未満の土粒子の含有率が約35%以下)、支持層G2は適切な強度を有するものとする。また、本実施形態では、地中連続壁Eは、具体的には、その下端部が支持層G2に到達するように構築するものとする。
In this embodiment, a low-headed and narrow construction site directly under the existing railway viaduct, that is, a low-headed place where the railway viaduct B exists as an existing structure above the planned construction area of the underground continuous wall E. In addition, the following is an example of the construction of an underground continuous wall E made of reinforced concrete in a narrow place where it is difficult to secure sufficient work space around the ground side of the planned construction area. To do.
Specifically, it is assumed that the railway viaduct B in the planned construction area of the underground continuous wall E exists at a height of about 3 to 4 m from the ground. In the present embodiment, the existing structure is the railway viaduct B, and the underground continuous wall E will be described in a case where it is constructed at a low head and a narrow place directly below the railway viaduct B, but not limited to this. Any construction site may be used as long as some structure exists above the planned construction site of the underground continuous wall E and the crane work is restricted.
In the present embodiment, the ground including the planned construction area of the underground continuous wall E includes an upper layer G1 positioned on the ground side and a support layer G2 positioned below the upper layer G1, and the upper layer G1 is fine-grained. The fraction content is low (for example, the content of soil particles having a particle size of less than 0.075 mm is about 35% or less), and the support layer G2 has an appropriate strength. In the present embodiment, the underground continuous wall E is specifically constructed so that the lower end thereof reaches the support layer G2.

まず、本実施形態の地中連続壁構築方法において用いる地盤改良体造成装置10と掘削装置20の構成について、図3及び図4を参照して、以下に説明する。   First, the structure of the ground improvement body formation apparatus 10 and the excavation apparatus 20 used in the underground continuous wall construction method of this embodiment is demonstrated below with reference to FIG.3 and FIG.4.

前記地盤改良体造成装置10は、いわゆる高圧噴射撹拌工法により地盤に地盤改良体1(図2参照)を形成する装置である。地盤改良体造成装置10は、図3に示すように、その本体11とロッド12とを含んで構成される。   The ground improvement body creation device 10 is a device that forms the ground improvement body 1 (see FIG. 2) on the ground by a so-called high-pressure jet stirring method. The ground improvement body production | generation apparatus 10 is comprised including the main body 11 and the rod 12, as shown in FIG.

前記本体11は、噴射液を貯蔵する噴射液タンク(図示せず)と、噴射液を超高圧・大流量(例えば、圧力:20〜40MPa程度、吐出流量:0.1〜0.6m/分程度)で圧送可能な超高圧ポンプ(図示せず)と、エアーコンプレッサー(図示せず)とを備える。また、本体11の正面には、ロッド12を、その軸心を中心として回転させると共に、軸心に沿って引き上げ及び引き下げ可能に把持する把持部13が取付けられている。 The main body 11 includes an injection liquid tank (not shown) for storing the injection liquid, and an ultrahigh pressure and a large flow rate (for example, pressure: about 20 to 40 MPa, discharge flow rate: 0.1 to 0.6 m 3 / And an ultra-high pressure pump (not shown) capable of being pumped in about a minute) and an air compressor (not shown). A grip portion 13 is attached to the front surface of the main body 11 for rotating the rod 12 around its axis and gripping the rod 12 so as to be lifted and lowered along the axis.

噴射液は、適宜の固化材(例えばセメントなどの自硬性材料)と水とを含む液体としての固化材ミルクである。本実施形態では、噴射液は、固化材としてセメントを用いたセメントミルクであるものとして以下説明するが、固化材ミルクはこれに限らない。固化材ミルクは、地盤改良体1の一軸圧縮強さquが周囲地盤の強度より高い後述する所定の強度範囲内に収まるように配合されている。   The propellant is solidified milk as a liquid containing an appropriate solidifying material (for example, a self-hardening material such as cement) and water. In the present embodiment, the injection liquid will be described below as cement milk using cement as a solidifying material, but the solidifying material milk is not limited thereto. The solidified material milk is blended so that the uniaxial compressive strength qu of the ground improvement body 1 is within a predetermined strength range described later higher than the strength of the surrounding ground.

地盤改良体1の造成予定場所には、ピット(凹部)14が形成される。このピット14は、地面より所定深さ分だけ床掘りすることで形成される。
ここで、地盤改良体1は、地中連続壁Eの構築予定領域と重複する領域に、先行エレメントEA用の地盤改良体1としての第1地盤改良体1Aと後行エレメントEB用(つまり、後述する中間領域S2用)の地盤改良体1としての第2地盤改良体1Bとに分けて、複数形成される。各地盤改良体1は、隣り合う地盤改良体1と平面視で重なるように、適宜の断面形状を有して形成されている。
本実施形態おいては、各地盤改良体1(1A,1B)は、円形の断面形状を有して形成され、第1地盤改良体1Aの造成径(外径)をD3とし、第2地盤改良体1Bの造成径をD2とする。なお、地中連続壁Eの構築予定領域における地盤改良体1(1A,1B)の配置については後に詳述する。
A pit (concave portion) 14 is formed at the planned location of the ground improvement body 1. The pit 14 is formed by digging a floor by a predetermined depth from the ground.
Here, the ground improvement body 1 is used for the first ground improvement body 1A as the ground improvement body 1 for the preceding element EA and the succeeding element EB (that is, in a region overlapping the planned construction region of the underground continuous wall E (that is, It is divided into a second ground improvement body 1B as the ground improvement body 1 of the intermediate region S2 (to be described later), and a plurality of them are formed. The local board improvement body 1 is formed with an appropriate cross-sectional shape so as to overlap with the adjacent ground improvement body 1 in plan view.
In the present embodiment, each of the ground improvement bodies 1 (1A, 1B) is formed to have a circular cross-sectional shape, and the formation diameter (outer diameter) of the first ground improvement body 1A is D3, and the second ground The formation diameter of the improved body 1B is D2. In addition, arrangement | positioning of the ground improvement body 1 (1A, 1B) in the construction plan area | region of the underground continuous wall E is explained in full detail behind.

ピット14には、ロータリーボーリングマシン等の小型の削孔機(図示せず)によって、地中に鉛直方向に延伸する小径のボーリング孔であるガイドホールGHが形成される。ガイドホールGHは、例えば、上層G1と支持層G2との境界位置に達する深さまで形成される。このガイドホールGH内に、ロッド12が挿入される。ここで、ガイドホールGHの内径D1は、地盤改良体1の造成径、つまり地盤改良体1の外径(D2又はD3)よりも小さい。前記削孔機の削孔用ロッドは、適宜長さに分割されて、適宜継ぎ足して延長可能に構成されている。したがって、低空頭且つ狭隘な場所においても、クレーン等を使用せずに適宜深さのガイドホールGHを、容易に形成することができる。   A guide hole GH, which is a small-diameter boring hole extending vertically in the ground, is formed in the pit 14 by a small hole drill (not shown) such as a rotary boring machine. For example, the guide hole GH is formed to a depth that reaches the boundary position between the upper layer G1 and the support layer G2. The rod 12 is inserted into the guide hole GH. Here, the inner diameter D1 of the guide hole GH is smaller than the formation diameter of the ground improvement body 1, that is, the outer diameter (D2 or D3) of the ground improvement body 1. The drilling rod of the drilling machine is appropriately divided into lengths, and is configured to be extended as appropriate. Therefore, the guide hole GH having an appropriate depth can be easily formed without using a crane or the like even in a low-headed and narrow place.

地盤改良体1の造成時には、ロッド12とガイドホールGHとの間の隙間を通ってスライム状の混練土(スライム)が上昇し、ピット14に滞留する。このスライムは、ピット14に設置されるサンドポンプ15を介して、スライム貯留タンク16内に排泥される。   When the ground improvement body 1 is created, slime-like kneaded soil (slime) rises through the gap between the rod 12 and the guide hole GH and stays in the pit 14. This slime is discharged into the slime storage tank 16 via a sand pump 15 installed in the pit 14.

前記ロッド12は、円筒状の先端ロッド121と、この先端ロッド121の先端部側(下端部側)に設けられる噴射モニタ122と、先端ロッド121の基端部側(上端部側)に順次継ぎ足される適宜本数の延長ロッド123と、を有する。ロッド12の上端部側(つまり、延長ロッド123のうち最後に継ぎ足されるものの上端部側)が地面から突出して把持部13によって把持される。   The rod 12 is sequentially added to a cylindrical distal end rod 121, an injection monitor 122 provided on the distal end side (lower end side) of the distal end rod 121, and a proximal end side (upper end side) of the distal end rod 121. And an appropriate number of extension rods 123. The upper end portion side of the rod 12 (that is, the upper end portion side of the extension rod 123 to be added last) protrudes from the ground and is gripped by the grip portion 13.

先端ロッド121及び延長ロッド123は、例えば、外管と内管とからなる二重管によりそれぞれ構成される。なお、本実施形態では、先端ロッド121及び延長ロッド123は二重管構造である場合を一例に挙げて説明するが、これに限らず、三重管等の構造を適宜採用することができる。
本実施形態において、延長ロッド123のうち最後に継ぎ足されるものの上端部には、噴射液入口と圧縮空気入口を有するスイベル17が接続され、先端ロッド121の下端側には、カップリング(図示せず)を介して噴射モニタ122が接続されている。先端ロッド121と延長ロッド123との間、及び、各延長ロッド123,123間は適宜継手を介して接続される。
先端ロッド121及び延長ロッド123は、その内管がスイベル17の噴射液入口と連通して噴射液の流路となり、また、内管と外管との間の隙間がスイベル17の圧縮空気入口と連通して圧縮空気の流路となる。
The tip rod 121 and the extension rod 123 are each configured by, for example, a double tube including an outer tube and an inner tube. In the present embodiment, the case where the tip rod 121 and the extension rod 123 have a double tube structure will be described as an example. However, the present invention is not limited to this, and a structure such as a triple tube can be appropriately employed.
In the present embodiment, the swivel 17 having a jet liquid inlet and a compressed air inlet is connected to the upper end of the extension rod 123 to be added last, and a coupling (not shown) is connected to the lower end side of the tip rod 121. ) Is connected to the injection monitor 122. The distal end rod 121 and the extension rod 123 and the extension rods 123 and 123 are appropriately connected via a joint.
The tip rod 121 and the extension rod 123 have an inner pipe communicating with the jet liquid inlet of the swivel 17 to form a flow path for the jet liquid, and a gap between the inner pipe and the outer pipe is connected to the compressed air inlet of the swivel 17. It communicates and becomes a flow path of compressed air.

本体11の噴射液タンク内の噴射液は、超高圧ポンプ、スイベル17の噴射液入口を介してロッド12の内管内に圧送される。また、本体11のエアーコンプレッサーからの圧縮空気は、スイベル17の圧縮空気入口を介してロッド12の外管と内管との間の流路に圧送される。   The spray liquid in the spray liquid tank of the main body 11 is pumped into the inner tube of the rod 12 through the ultrahigh pressure pump and the spray liquid inlet of the swivel 17. Further, the compressed air from the air compressor of the main body 11 is pumped to the flow path between the outer tube and the inner tube of the rod 12 via the compressed air inlet of the swivel 17.

噴射モニタ122は、ロッド12(先端ロッド121)の内管と連通する噴射液噴射ノズル(図示せず)と、前述の圧縮空気の流路と連通する圧縮空気噴射ノズル(図示せず)とを備える。すなわち、ロッド12の先端部側には、噴射液噴射ノズル及び圧縮空気噴射ノズルが設けられている。
噴射液噴射ノズルの先端は、噴射モニタ122の外周面の一部で径方向外向きに開口している。また、圧縮空気噴射ノズルの先端は、噴射液噴射ノズルの周囲で、径方向外向きに開口している。圧縮空気を噴射液噴射ノズルの周囲から噴射させることにより、噴射液を効率的に噴射させることができる。なお、本実施形態において、噴射モニタ122が本発明に係る「ノズル」に相当する。
The injection monitor 122 includes an injection liquid injection nozzle (not shown) that communicates with the inner tube of the rod 12 (tip rod 121) and a compressed air injection nozzle (not shown) that communicates with the aforementioned compressed air flow path. Prepare. That is, a jet liquid jet nozzle and a compressed air jet nozzle are provided on the tip end side of the rod 12.
The tip of the spray liquid spray nozzle opens outward in the radial direction at a part of the outer peripheral surface of the spray monitor 122. Moreover, the front-end | tip of a compressed air injection nozzle is opening the radial direction outward around the injection liquid injection nozzle. By injecting compressed air from around the injection liquid injection nozzle, the injection liquid can be efficiently injected. In the present embodiment, the injection monitor 122 corresponds to a “nozzle” according to the present invention.

地盤改良体造成装置10を作動させて地盤改良体1を造成するときには、まず、ガイドホールGHの下端部近傍に噴射モニタ122が位置するように、延長ロッド123を順次継ぎ足す。そして、この状態で、本体11の超高圧ポンプ及びエアーコンプレッサーを駆動させて、ロッド12内に、高圧の噴射液及び圧縮空気を圧送することで、噴射モニタ122の噴射液噴射ノズルから高圧の噴射液を、ガイドホールGHの半径方向外方に向けて連続的に噴射させると共に、噴射液噴射ノズルの周囲の圧縮空気噴射ノズルから圧縮空気を噴射させる。これにより、噴射液と圧縮空気とが混合したジェット流Jが形成される。また、ジェット流Jを噴射しつつ、ロッド12を把持部13により回転させる。このときに、ジェット流Jの圧力により、噴射モニタ122の周囲の地盤が切削されると共に、掘削土と噴射液とが撹拌混練されて地盤改良がなされる。これにより、固化材と水とを含むジェット流Jを噴射モニタ122から半径方向外方に向けて噴射可能に構成され、ガイドホールGHより大径であるソイルモルタル製の地盤改良体1の底部が形成される。   When the ground improvement body generating apparatus 10 is operated to create the ground improvement body 1, first, the extension rod 123 is sequentially added so that the injection monitor 122 is positioned near the lower end of the guide hole GH. In this state, the high pressure pump and the air compressor of the main body 11 are driven, and the high pressure injection liquid and the compressed air are pumped into the rod 12, whereby the high pressure injection is performed from the injection liquid injection nozzle of the injection monitor 122. The liquid is continuously jetted outward in the radial direction of the guide hole GH, and compressed air is jetted from the compressed air jet nozzles around the jet liquid jet nozzle. As a result, a jet flow J in which the jet liquid and the compressed air are mixed is formed. Further, the rod 12 is rotated by the grip portion 13 while jetting the jet stream J. At this time, the ground around the jet monitor 122 is cut by the pressure of the jet stream J, and the excavated soil and the jet liquid are stirred and kneaded to improve the ground. Accordingly, the bottom of the soil improvement body 1 made of soil mortar, which is configured to be able to inject the jet stream J including the solidified material and water outward from the injection monitor 122 in the radial direction, is larger than the guide hole GH. It is formed.

これに続けて、ジェット流Jを連続的に噴射させつつ、ロッド12を把持部13により回転駆動させながら所定の引き上げ速度で、図1に矢印で示す鉛直方向上方に引き上げる。このロッド12の引き上げは、ジェット流Jの噴射がピット14の近傍(例えば底面)に達するまで行われる。この引き上げの際、ロッド12はスイベル17と共に上昇する。したがって、例えば、スイベル17が鉄道高架橋Bに底面近傍の手前に位置するまでの間の適宜タイミングでジェット流Jの噴射を一旦停止させ、延長ロッド123のうちの地面から突出した適宜本数の延長ロッド123を取り外し、最上部の延長ロッド123の上端部をスイベル17に接続し直した後、ジェット流Jの噴射を再開すればよい。このようにして、ガイドホールGHより大径であり、且つ、上層G1と支持層G2との境界面に達する長さを有する円柱状の地盤改良体1が形成される(後述の図9参照)。   Subsequently, the jet stream J is continuously ejected, and the rod 12 is driven to rotate upward by the grip portion 13 and is pulled upward in the vertical direction indicated by an arrow in FIG. The rod 12 is pulled up until the jet stream J is injected near the pit 14 (for example, the bottom surface). During this lifting, the rod 12 rises with the swivel 17. Therefore, for example, the injection of the jet stream J is temporarily stopped at an appropriate timing until the swivel 17 is positioned in front of the bottom of the railway viaduct B, and an appropriate number of extension rods protruding from the ground among the extension rods 123. After removing 123 and reconnecting the upper end of the uppermost extension rod 123 to the swivel 17, the jet stream J may be restarted. In this way, a cylindrical ground improvement body 1 having a diameter larger than that of the guide hole GH and having a length reaching the boundary surface between the upper layer G1 and the support layer G2 is formed (see FIG. 9 described later). .

その後、地盤改良体1の一軸圧縮強さquは、徐々に増加し、地盤改良体1の材齢期間が長くなるにつれ強度増加速度は緩やかになり、所定の強度範囲内に略収まる。この一軸圧縮強さquの上記所定の強度範囲については後に詳述する。   Thereafter, the uniaxial compressive strength qu of the ground improvement body 1 gradually increases, and as the age period of the ground improvement body 1 becomes longer, the rate of strength increase becomes gradual and substantially falls within a predetermined strength range. The predetermined strength range of the uniaxial compressive strength qu will be described in detail later.

次に、前記掘削装置20について、図4を参照して説明する。
掘削装置20は、地盤改良体造成装置10により形成された地盤改良体1内を鉛直方向(図4に矢印で示す掘削方向)に掘削して掘削溝Gを形成するものである。
掘削装置20は、例えば、無限軌道を有して自走可能なベースマシン21と、ベースマシン21に支持されて直立する柱状のリーダ22と、リーダ22の頂部に前方に張り出すように水平に取り付けられる補助クレーン23と、掘削機24と、リーダ22に沿って昇降する昇降部25とを備えて構成されている。
Next, the excavator 20 will be described with reference to FIG.
The excavation device 20 excavates the ground improvement body 1 formed by the ground improvement body creation device 10 in the vertical direction (excavation direction indicated by an arrow in FIG. 4) to form the excavation groove G.
For example, the excavator 20 is horizontally arranged so as to project forward on the top of the leader 22, a base machine 21 having an endless track and capable of self-propelled, a column-shaped leader 22 supported by the base machine 21, and standing upright. An auxiliary crane 23 to be attached, an excavator 24, and an elevating unit 25 that elevates and descends along the leader 22 are configured.

前記ベースマシン21は、無限軌道を有して自走可能に構成されている。このベースマシン21には、補助クレーン23の揚重用のウインチ26が設けられている。ウインチ26より引き出されたワイヤロープ27は、補助クレーン23のガイドプーリーに架け渡されて、補助クレーン23の先端部の下方に位置する吊り具28に接続されている。補助クレーン23は、ウインチ26によりワイヤロープ27を巻き上げ又は送り出すことで、吊り具28を介して、掘削機24等の重量物を吊り上げ又は吊り下げることができる。   The base machine 21 has an endless track and is configured to be self-propelled. The base machine 21 is provided with a winch 26 for lifting the auxiliary crane 23. The wire rope 27 drawn out from the winch 26 is stretched over a guide pulley of the auxiliary crane 23 and connected to a lifting tool 28 located below the tip of the auxiliary crane 23. The auxiliary crane 23 can lift or suspend heavy objects such as the excavator 24 through the lifting tool 28 by winding or sending the wire rope 27 by the winch 26.

前記掘削機24は、水平方向に延伸する軸回りに回転して地盤等を掘削可能な複数(図では2個)のカッタードラム29を先端部に有し、横長矩形断面の溝孔(つまり、掘削溝G)を形成可能な、いわゆる水平多軸式連壁掘削機である。この掘削機24による掘削に並行して、図示を省略した処理プラントから水より大きい密度を有する適宜の安定液(例えばベントナイトを含む安定化用泥水)が、形成途中の掘削溝G内に供給される。なお、以下では、安定液は水より大きい密度を有する場合を一例として挙げて説明するが、これに限らず、後述するように安定液として水を使用してもよい場合もある。   The excavator 24 has a plurality of (two in the figure) cutter drums 29 that can rotate around an axis extending in the horizontal direction to excavate the ground or the like at the tip, and have a slot with a horizontally long rectangular cross section (that is, This is a so-called horizontal multi-axis continuous wall excavator capable of forming the excavation groove G). In parallel with excavation by the excavator 24, an appropriate stabilizing liquid (for example, stabilization mud containing bentonite) having a density larger than that of water is supplied from the treatment plant (not shown) into the excavation groove G that is being formed. The In the following description, the case where the stabilizing liquid has a density higher than that of water will be described as an example. However, the present invention is not limited thereto, and water may be used as the stabilizing liquid as described later.

前記昇降部25は、直列に連結された複数の円筒状の排泥用リバースロッド25aの一端側(上端側)を把持しつつ上昇又は下降可能に構成されている。このリバースロッド25aは、その下端部を掘削機24内のカッタードラム29近傍まで延設させて、適宜掘削機24に接続されている。つまり、リバースロッド25aは、一端側が昇降部25に把持され、他端側が掘削機24に接続されている。   The elevating part 25 is configured to be able to ascend or descend while gripping one end side (upper end side) of a plurality of cylindrical sludge reverse rods 25a connected in series. The reverse rod 25 a is connected to the excavator 24 as appropriate with its lower end extending to the vicinity of the cutter drum 29 in the excavator 24. That is, one end side of the reverse rod 25 a is held by the elevating unit 25 and the other end side is connected to the excavator 24.

掘削装置20を作動させて地盤改良体1を掘削するときには、例えば、掘削機24を作動させつつウインチ26によりワイヤロープ27を送り出すと共に、昇降部25を下降させて、地盤改良体1内を鉛直方向下方に向かって掘削する。なお、昇降部25が地面近傍まで下降した場合は、掘削機24を補助クレーン23により保持した(吊り上げた)状態で、昇降部25によるリバースロッド25aの把持を解除しつつ、昇降部25を上昇させる。そして、リバースロッド25aを適宜継ぎ足し、その継ぎ足されたリバースロッド25aを昇降部25により把持した後、再び、ウインチ26及び昇降部25により掘削機24を下降させることで、引き続き掘削を行う。
掘削装置20は、上記掘削に並行して、安定液を掘削溝G内に供給する。これと同時に、リバースロッド25aに接続された図示省略したサクションポンプが起動すると、安定液と地盤改良体1の掘削により発生した掘削土砂とが混合してできた泥水は、リバースロッド25aの下端開口部から吸引されて、掘削溝G外に排出される。排出された泥水は、上記処理プラント(図示省略)にて、適宜処理されて、安定液と残土に分離される。これにより、泥水から安定液を回収することができるようになっている。そして、回収された安定液は、再び掘削溝G内に供給され、以降、処理プラント(安定液タンク等)と掘削溝Gとの間で循環される。
When excavating the ground improvement body 1 by operating the excavator 20, for example, while operating the excavator 24, the wire rope 27 is sent out by the winch 26, and the elevating unit 25 is lowered to vertically move the ground improvement body 1. Drill in the downward direction. When the lifting unit 25 is lowered to the vicinity of the ground, the lifting unit 25 is lifted while the excavator 24 is held (lifted) by the auxiliary crane 23 while releasing the grip of the reverse rod 25a by the lifting unit 25. Let Then, after the reverse rod 25a is appropriately added and the reverse rod 25a thus added is gripped by the elevating unit 25, the excavator 24 is lowered again by the winch 26 and the elevating unit 25 to continue excavation.
The excavator 20 supplies the stabilizing liquid into the excavation groove G in parallel with the excavation. At the same time, when a suction pump (not shown) connected to the reverse rod 25a is started, the muddy water formed by mixing the stable liquid and the excavated soil generated by excavating the ground improvement body 1 is opened at the lower end of the reverse rod 25a. It is sucked from the section and discharged out of the excavation groove G. The discharged muddy water is appropriately processed at the processing plant (not shown) and separated into a stable liquid and residual soil. Thereby, it is possible to recover the stable liquid from the muddy water. Then, the recovered stable liquid is supplied again into the excavation groove G, and thereafter circulated between the processing plant (such as a stabilization liquid tank) and the excavation groove G.

このようにして、掘削装置20は、掘削溝Gの形成時に、掘削溝G内に安定液を供給し、地盤改良体1内で生じた掘削土砂を安定液と共に掘削溝G外に排出し、この排出された安定液を再び掘削溝G内に供給して循環させるように構成されている。つまり、掘削装置20は、いわゆるリバースサーキュレーション工法等により安定液を循環させている。   In this way, the excavator 20 supplies the stable liquid into the excavation groove G when the excavation groove G is formed, and discharges the excavated sediment generated in the ground improvement body 1 to the outside of the excavation groove G together with the stable liquid, The discharged stable liquid is supplied again into the excavation groove G and is circulated. That is, the excavator 20 circulates the stabilizing liquid by a so-called reverse circulation method or the like.

本実施形態においては、一回の鉛直方向の掘削により形成される掘削溝Gの短辺方向の内寸(溝厚さt1、後述する図13及び図18参照)は地中連続壁Eの壁厚tに相当し、一回の鉛直方向の掘削により形成される掘削溝Gの長辺方向の内寸(溝幅W1)は、先行エレメントEA及び後行エレメントEBの長辺方向の長さであるエレメント幅Wに相当する(つまり、t1=t、W1=W)。このように、本実施形態においては、掘削装置20は、一回の掘り下げ(1ガット)により各エレメントEA,EBの出来上がり時の断面形状と略等しい開口形状の掘削溝Gを形成可能に構成されている。
ここで、本実施形態において、掘削溝Gの溝幅W1(=エレメント幅W)は、ガイドホールGHの内径D1より大きく、且つ、第1地盤改良体1Aの造成径D3より小さい(つまり、D1<W1<D3)。
In the present embodiment, the inner dimension (groove thickness t1, see FIGS. 13 and 18 described later) of the excavation groove G formed by one vertical excavation is the wall of the underground continuous wall E. The inner dimension (groove width W1) in the long side direction of the excavation groove G formed by one excavation in the vertical direction, corresponding to the thickness t, is the length in the long side direction of the preceding element EA and the succeeding element EB. This corresponds to a certain element width W (that is, t1 = t, W1 = W). Thus, in this embodiment, the excavator 20 is configured to be able to form an excavation groove G having an opening shape that is substantially equal to the cross-sectional shape of each element EA, EB upon completion of one excavation (1 gut). ing.
Here, in this embodiment, the groove width W1 (= element width W) of the excavation groove G is larger than the inner diameter D1 of the guide hole GH and smaller than the formation diameter D3 of the first ground improvement body 1A (that is, D1). <W1 <D3).

次に、地中連続壁Eの構築予定領域における地盤改良体1の配置について、図5及び図6を参照して詳述する。図5は地盤改良体1の造成途中(第1地盤改良体1Aの造成後)の状態を示した平面図であり、図6は地盤改良体1の造成が完了した状態(第2地盤改良体1Bの造成後の状態)を示した平面図である。
本実施形態において、地盤改良体1は、先行エレメントEA用の第1地盤改良体1Aと、後行エレメントEB用の第2地盤改良体1Bとの2種類に分けて造成されている。
ここで、先行エレメントEAは、地中に一定の間隔をおいて掘削される先行エレメントEA用の掘削溝G(後述する図13参照)内に形成される。一方、後行エレメントEBは、先行エレメントEAが形成された後、互いに隣り合う先行エレメントEAの短辺側端部を掘削すると共に互いに隣り合う先行エレメントEA間の中間領域S2(後述する図15及び図16参照)を掘削して得られる後行エレメントEB用の各掘削溝G(後述する図18参照)内に形成される。この一つの先行エレメントEA用の掘削溝Gの掘削予定領域S1と、一つの中間領域S2とを、それぞれ、地盤改良体1の造成の単位領域とする。
Next, arrangement | positioning of the ground improvement body 1 in the construction plan area | region of the underground continuous wall E is explained in full detail with reference to FIG.5 and FIG.6. FIG. 5 is a plan view showing a state during the formation of the ground improvement body 1 (after the formation of the first ground improvement body 1A), and FIG. 6 is a state where the formation of the ground improvement body 1 is completed (second ground improvement body). It is the top view which showed the state after the creation of 1B.
In this embodiment, the ground improvement body 1 is divided into two types of a first ground improvement body 1A for the preceding element EA and a second ground improvement body 1B for the following element EB.
Here, the preceding element EA is formed in the excavation groove G (see FIG. 13 described later) for the preceding element EA excavated at a certain interval in the ground. On the other hand, after the leading element EA is formed, the trailing element EB excavates the short side end portion of the preceding element EA adjacent to each other and the intermediate region S2 between the adjacent preceding elements EA (FIG. 15 and FIG. It is formed in each excavation groove G (see FIG. 18 described later) for the succeeding element EB obtained by excavating (see FIG. 16). The planned excavation area S1 of the excavation groove G for one preceding element EA and one intermediate area S2 are set as unit areas for the formation of the ground improvement body 1, respectively.

先行エレメントEA用の第1地盤改良体1Aは、図5に示すように、その内部に、一つの先行エレメントEA用の掘削溝Gの掘削予定領域(つまり単位領域)S1が位置するように配置されている。
一方、後行エレメントEB用の第2地盤改良体1Bは、図6に示すように、その内部に、互いに隣り合う先行エレメントEA用の掘削予定領域S1間の領域が位置するように配置されている。先行エレメントEAの出来上がり後の状態で言い換えると、第2地盤改良体1Bは、その内部に、互いに隣り合う先行エレメントEA間の一つの中間領域(つまり単位領域)S2が位置するように配置されている。
このように、地盤改良体(1A,1B)1は、先行エレメントEA用の掘削溝Gの掘削に先立って、単位領域(S1又はS2)が内部に位置するように、単位領域毎にそれぞれ配置され、互いに隣接する地盤改良体1はその一部を重複させて造成されている。つまり、第1地盤改良体1Aと第2地盤改良体1Bとは互いに一部重複させて造成されている。また、この地盤改良体1の重複部分における地中連続壁Eの壁厚方向の重複長さは壁厚tより大きくなるように設定されている。
As shown in FIG. 5, the first ground improvement body 1A for the preceding element EA is disposed so that a planned excavation area (that is, a unit area) S1 of the excavation groove G for the preceding element EA is located therein. Has been.
On the other hand, as shown in FIG. 6, the second ground improvement body 1B for the trailing element EB is arranged so that the area between the adjacent excavation scheduled areas S1 for the preceding element EA is located inside the second ground improvement body 1B. Yes. In other words, in the state after the preceding element EA is completed, the second ground improvement body 1B is arranged so that one intermediate area (that is, unit area) S2 between the adjacent preceding elements EA is located inside. Yes.
Thus, the ground improvement body (1A, 1B) 1 is arranged for each unit area so that the unit area (S1 or S2) is located inside prior to excavation of the excavation groove G for the preceding element EA. The ground improvement bodies 1 adjacent to each other are formed by overlapping a part thereof. That is, the first ground improvement body 1A and the second ground improvement body 1B are formed so as to partially overlap each other. The overlapping length in the wall thickness direction of the underground continuous wall E in the overlapping portion of the ground improvement body 1 is set to be larger than the wall thickness t.

また、本実施形態においては、第2地盤改良体1Bの造成径D2は、第1地盤改良体1Aの造成径D3より小さくなるように設定されている。つまり、中間領域S2に対応して造成される地盤改良体1(1B)の水平断面積は、先行エレメントEA用の掘削溝Gの掘削予定領域S1に対応して造成される地盤改良体1(1A)の水平断面積より小さくなるように設定されている。   In the present embodiment, the creation diameter D2 of the second ground improvement body 1B is set to be smaller than the creation diameter D3 of the first ground improvement body 1A. That is, the horizontal cross-sectional area of the ground improvement body 1 (1B) formed corresponding to the intermediate area S2 is the ground improvement body 1 (corresponding to the planned excavation area S1 of the excavation groove G for the preceding element EA). It is set to be smaller than the horizontal sectional area of 1A).

次に、本発明に係る地中連続壁構築方法の一実施形態を、図1、図2、図7〜図18を参照して、一般的なボーリング装置(図示省略)と、上記地盤改良体造成装置10と、掘削装置20を用いた場合について詳述する。
なお、以下の説明では、説明の便宜上、先行エレメントEA用の複数の第1地盤改良体1Aを先に造成した後、後行エレメントEB用の第2地盤改良体1Bを造成するものとし、その後、まず、先行エレメントEAを全て形成し、最後に、後行エレメントEBを全て形成して地中連続壁Eを構築する場合を一例として説明する。また、掘削溝Gの溝幅W1、掘削溝Gの溝厚さt1、第1地盤改良体1Aの造成径D3、第2地盤改良体1Bの造成径D2は、それぞれ適宜に決定され、地盤改良体1(1A,1B)の一軸圧縮強さquは、地盤改良体1の形成が完了してから地盤改良体1に掘削溝Gを形成可能となるまでの期間に応じて設定する所定の材齢日(例えば材齢42日目)において、周囲地盤の強度より高い所定の強度範囲内に収まるように設定されているものとして説明する。
Next, referring to FIG. 1, FIG. 2, FIG. 7 to FIG. 18, an embodiment of the underground continuous wall construction method according to the present invention will be described with reference to a general boring device (not shown) and the above ground improvement body. The case where the creation device 10 and the excavation device 20 are used will be described in detail.
In the following description, for convenience of explanation, it is assumed that after the first ground improvement body 1A for the leading element EA is first formed, the second ground improvement body 1B for the trailing element EB is formed, and thereafter First, an example will be described in which the preceding element EA is all formed, and finally the trailing element EB is formed to construct the underground continuous wall E. Further, the groove width W1 of the excavation groove G, the thickness t1 of the excavation groove G, the formation diameter D3 of the first ground improvement body 1A, and the formation diameter D2 of the second ground improvement body 1B are determined as appropriate, and the ground improvement The uniaxial compressive strength qu of the body 1 (1A, 1B) is a predetermined material that is set according to the period from when the formation of the ground improvement body 1 is completed until the excavation groove G can be formed in the ground improvement body 1 Description will be made on the assumption that an age day (for example, material age 42) is set to fall within a predetermined strength range higher than the strength of the surrounding ground.

本実施形態において、地中連続壁構築方法は、高圧噴射撹拌工法を用いた地盤改良体1の造成工程と、水平多軸式の掘削機24を用いた掘削工程と、鉄筋籠建て込み工程と、コンクリート打設工程とを含む。図7〜図11は造成工程を示し、図12及び図13は先行エレメントEA用の掘削溝Gの掘削工程を示し、図14は鉄筋籠建て込み工程を示し、図15及び図16はコンクリート打設工程を示し、図17及び図18は後行エレメントEB用の掘削溝Gの掘削工程を示す。   In the present embodiment, the underground continuous wall construction method includes a process for creating the ground improvement body 1 using a high-pressure jet agitation method, a drilling process using a horizontal multi-axis excavator 24, and a reinforcing bar building process. And a concrete placing process. 7 to 11 show the creation process, FIGS. 12 and 13 show the excavation process of the excavation groove G for the leading element EA, FIG. 14 shows the reinforcing bar erection process, and FIG. 15 and FIG. FIG. 17 and FIG. 18 show the excavation process of the excavation groove G for the trailing element EB.

造成工程では、初めに第1地盤改良体1Aの造成を行う。この造成では、まず、図7に示すように、第1地盤改良体1Aの形成予定場所(先行エレメントEA用の掘削予定領域S1)において、地面より所定深さ分だけ床掘りして、凹状のピット14を形成する。そして、前記ボーリング装置としての小型の削孔機(図示せず)によって、掘削予定領域S1の鉛直方向に延びる中心軸X1に、軸心が略一致するように、地中に鉛直方向に延伸するロッド12ガイド用のガイドホールGHを上層G1と支持層G2との境界位置に達する深さまで形成する。前記削孔機は小型であり、且つ、削孔用ロッドが適宜長さに分割されているため、低空頭且つ狭隘な施工場所であっても、例えば、手押し台車等により容易に搬入、据え付け及び搬出することができる上、所望の深さまでガイドホールGHを削孔することができる。   In the creation step, first, the first ground improvement body 1A is created. In this creation, as shown in FIG. 7, first, in a planned formation place of the first ground improvement body 1A (excavation planned area S1 for the preceding element EA), a floor is dug by a predetermined depth from the ground, and a concave shape is formed. A pit 14 is formed. Then, by a small drilling machine (not shown) as the boring device, it extends in the vertical direction into the ground so that the axial center substantially coincides with the central axis X1 extending in the vertical direction of the planned excavation area S1. A guide hole GH for guiding the rod 12 is formed to a depth reaching the boundary position between the upper layer G1 and the support layer G2. Since the drilling machine is small and the drilling rod is appropriately divided into lengths, it can be easily carried in, installed, and installed by a handcart, etc. even in a low-headed and narrow construction site. In addition to being able to carry out, the guide hole GH can be drilled to a desired depth.

次に、ガイドホールGHの削孔完了後、図8に示すように、地盤改良体造成装置10を、把持部13の軸心がガイドホールGHの軸心(X1)と略一致するように配置する。この地盤改良体造成装置10は、ガイドホールGHの削孔機と同様に、比較的に小型であるため、手押し台車等により所定位置に配置される。その後、ロッド12をガイドホールGH内に挿入し、ガイドホールGHの下端部近傍に噴射モニタ122が位置するまで延長ロッド123を順次継ぎ足す。そして、この状態で、噴射モニタ122からその半径方向外方に向けて、固化材と水とを含む噴射液と圧縮空気とを混合させたジェット流Jを噴射しつつ、ロッド12を回転駆動させながら所定の引き上げ速度(例えば10min/m)で引き上げる。ここで、例えば、噴射液の吐出圧力は約38MPaに設定され、吐出流量は約190L/minに設定されている。このロッド12の引き上げは、ジェット流Jの噴射がピット14の近傍(例えば底面)に達するまで行われる。この引き上げの際、最上部等の延長ロッド123が順次取り外されて、スイベル17が鉄道高架橋Bの底面に干渉しないようにする。これにより、図9に示すように、ガイドホールGHより大径の造成径D3を有し、且つ、上層G1と支持層G2との境界面に達する長さを有する円柱状の第1地盤改良体1Aを造成する。その後、隣接する先行エレメントEA用の掘削予定領域S1において、図7及び図8と同じ手順で次の第1地盤改良体1Aを造成する。これを順次繰り返して、図10に示すように、第1地盤改良体1Aの造成を完了させる。これにより、各第1地盤改良体1Aの内部に、先行エレメントEA用の掘削溝Gの掘削予定領域S1が位置する。   Next, after completion of the drilling of the guide hole GH, as shown in FIG. 8, the ground improvement body generating device 10 is arranged so that the axis of the gripping portion 13 substantially coincides with the axis (X1) of the guide hole GH. To do. Since the ground improvement body generating apparatus 10 is relatively small like the drilling machine for the guide hole GH, it is disposed at a predetermined position by a hand cart or the like. Thereafter, the rod 12 is inserted into the guide hole GH, and the extension rod 123 is sequentially added until the injection monitor 122 is positioned near the lower end of the guide hole GH. In this state, the rod 12 is driven to rotate while injecting a jet stream J, which is a mixture of a solidified material, water-containing injection liquid, and compressed air, from the injection monitor 122 outward in the radial direction. While pulling up at a predetermined pulling speed (for example, 10 min / m). Here, for example, the discharge pressure of the spray liquid is set to about 38 MPa, and the discharge flow rate is set to about 190 L / min. The rod 12 is pulled up until the jet stream J is injected near the pit 14 (for example, the bottom surface). At the time of this lifting, the extension rod 123 such as the uppermost portion is sequentially removed so that the swivel 17 does not interfere with the bottom surface of the railway viaduct B. As a result, as shown in FIG. 9, a cylindrical first ground improvement body having a construction diameter D3 larger than the guide hole GH and a length reaching the boundary surface between the upper layer G1 and the support layer G2. Create 1A. Thereafter, in the planned excavation area S1 for the adjacent preceding element EA, the next first ground improvement body 1A is created in the same procedure as in FIGS. This is sequentially repeated to complete the creation of the first ground improvement body 1A as shown in FIG. Accordingly, the planned excavation area S1 of the excavation groove G for the preceding element EA is located inside each first ground improvement body 1A.

次に、第2地盤改良体1Bの造成を第1地盤改良体1Aの造成と同様にして順次行う。この造成においては、各ガイドホールGHは、その軸心を中間領域S2の鉛直方向に延びる中心軸X2(言い換えると、互いに隣り合う中心軸X1の中央を通る軸)に略一致させて形成される。これにより、各第2地盤改良体1Bの内部に、中間領域S2が位置し、図11に示すように、第1地盤改良体1Aと第2地盤改良体1Bとが一体的に造成された地盤改良体群が形成される。その後、地盤改良体造成装置10は搬出され、造成工程が完了する。このように、本実施形態において、地盤改良体1(1A,1B)は、地中連続壁Eの構築方向に沿って一列に配列されている。   Next, the formation of the second ground improvement body 1B is sequentially performed in the same manner as the formation of the first ground improvement body 1A. In this construction, each guide hole GH is formed so that its axis is substantially coincident with a central axis X2 extending in the vertical direction of the intermediate region S2 (in other words, an axis passing through the center of adjacent central axes X1). . As a result, the intermediate region S2 is located inside each second ground improvement body 1B, and as shown in FIG. 11, the first ground improvement body 1A and the second ground improvement body 1B are integrally formed. Improved body groups are formed. Then, the ground improvement body production | generation apparatus 10 is carried out and a creation process is completed. Thus, in this embodiment, the ground improvement bodies 1 (1A, 1B) are arranged in a line along the construction direction of the underground continuous wall E.

この地盤改良体1の一軸圧縮強さquは、例えば、材齢28日目において約570kN/m2となり、材齢42日目において約790kN/m2となり、その後、強度増加速度は緩やかになり、周囲地盤より高い所定の強度範囲(例えば、約500から約1000kN/m2)内に略収まる。この所定の強度範囲の下限値は、地盤改良体1の周囲地盤の強度より高く設定され、所定の強度範囲の上限値は、掘削溝Gを形成する掘削装置20の掘削力に応じて設定される。なお、後述するように、所定の材齢日における地盤改良体1の一軸圧縮強さquが前記所定の強度範囲内に収まるように、噴射液(固化材ミルク)が配合されている。
本実施形態では、このように、先行エレメントEA用の掘削溝Gの掘削に先立って、単位領域(S1,S2)が内部に位置する地盤改良体1(1A,1B)を、単位領域(S1,S2)毎にそれぞれ造成する造成工程を含み、単位領域毎の造成工程では、ロッド12をガイドホールGHに挿入し、セメントミルクを噴射モニタ122から半径方向外方に向けて噴射しつつ、ロッド12を回転させると共に、ロッド12を引き上げて、ガイドホールGHより大径であり且つ地盤より強度の高い地盤改良体1(1A,1B)を造成する。
The uniaxial compressive strength qu of soil improvement body 1, for example, about 570kN / m 2 next to the age of 28 days, about 790kN / m 2 next to the age of 42 days, then, the strength increase rate becomes gentle , Approximately within a predetermined strength range higher than the surrounding ground (for example, about 500 to about 1000 kN / m 2 ). The lower limit value of the predetermined strength range is set higher than the strength of the surrounding ground of the ground improvement body 1, and the upper limit value of the predetermined strength range is set according to the excavation force of the excavator 20 that forms the excavation groove G. The In addition, as will be described later, the jet liquid (solidified milk) is blended so that the uniaxial compressive strength qu of the ground improvement body 1 on a predetermined material age falls within the predetermined strength range.
In the present embodiment, prior to excavation of the excavation groove G for the preceding element EA, the ground improvement body 1 (1A, 1B) in which the unit area (S1, S2) is located is replaced with the unit area (S1). , S2), and in each of the unit regions, the rod 12 is inserted into the guide hole GH and the cement milk is sprayed radially outward from the spray monitor 122 while the rod is inserted. 12 is rotated, and the rod 12 is pulled up to create the ground improvement body 1 (1A, 1B) having a diameter larger than that of the guide hole GH and higher in strength than the ground.

次に、地盤改良体1の掘削工程では、例えば、先行エレメントEA用の掘削溝Gを全て形成する。
詳しくは、掘削装置20を、その掘削機24の軸心が第1地盤改良体1Aの延伸方向の中心軸(つまりX1)と略一致するように配置する。その後、第1地盤改良体1Aの上端部近傍にカッタードラム29を位置させて掘削可能な状態となる。第1地盤改良体1Aの造成が完了してから、掘削装置20を配置して第1地盤改良体1Aに掘削溝Gを形成可能となるまでの期間として、例えば約1か月から1か月半ほど要するため、掘削開始時の第1地盤改良体1Aの一軸圧縮強さquは、前記所定の強度範囲に収まっている。この状態で、掘削機24をウインチ26や昇降部25により下降させる。これにより、第1地盤改良体1Aの軸心に溝中心が合された掘削溝Gが形成され始める。そして、図12に示すように、掘削機24は、そのカッタードラム29が支持層G2を貫入するまで下降する。その結果、第1地盤改良体1Aの造成径D3より小さい溝幅W1及び地中連続壁Eの壁厚tと略一致する溝厚さt1を有し、その溝中心を第1地盤改良体1Aの延伸方向の中心軸(X1)と合わせて形成され、且つ、支持層G2に達する掘削溝Gが形成される。この掘削溝Gを構成する長辺方向及び短辺方向の4つの溝壁は、いずれも第1地盤改良体1Aの掘削面からなる。その後、隣接する掘削予定領域S1において掘削溝Gの掘削を順次繰り返して、図13に示すように、先行エレメントEA用の掘削溝Gの形成を完了させる。
ここで、掘削溝Gが中心軸(X1)に沿って形成された第1地盤改良体1Aは、中空改良体となり、適宜箇所にその壁厚が最小となる薄肉部を有する。なお、薄肉部厚さ(以下において薄肉部厚さという)T(T3)及び造成径D(D3)の設定手順と、薄肉部厚さTと第1地盤改良体1Aの一軸圧縮強さquとの関係については、後に詳述する。
Next, in the excavation process of the ground improvement body 1, for example, all the excavation grooves G for the leading element EA are formed.
Specifically, the excavator 20 is arranged so that the axis of the excavator 24 substantially coincides with the central axis (that is, X1) in the extending direction of the first ground improvement body 1A. Thereafter, the cutter drum 29 is positioned in the vicinity of the upper end portion of the first ground improvement body 1A so that excavation is possible. The period from the completion of the creation of the first ground improvement body 1A to the time when the excavation device 20 is arranged and the excavation groove G can be formed in the first ground improvement body 1A is, for example, about 1 month to 1 month. Since it takes about half, the uniaxial compressive strength qu of the first ground improvement body 1A at the start of excavation is within the predetermined strength range. In this state, the excavator 24 is lowered by the winch 26 or the lifting unit 25. Thereby, the excavation groove G in which the groove center is aligned with the axial center of the first ground improvement body 1A starts to be formed. Then, as shown in FIG. 12, the excavator 24 descends until the cutter drum 29 penetrates the support layer G2. As a result, it has a groove width W1 smaller than the formation diameter D3 of the first ground improvement body 1A and a groove thickness t1 that substantially matches the wall thickness t of the underground continuous wall E, and the center of the groove is the first ground improvement body 1A. The excavation groove G that is formed together with the central axis (X1) in the extending direction of the steel and reaches the support layer G2 is formed. Each of the four groove walls in the long side direction and the short side direction constituting the excavation groove G is formed by the excavation surface of the first ground improvement body 1A. Thereafter, the excavation of the excavation groove G is sequentially repeated in the adjacent excavation planned area S1 to complete the formation of the excavation groove G for the preceding element EA as shown in FIG.
Here, the 1st ground improvement body 1A in which the excavation groove G was formed along the central axis (X1) turns into a hollow improvement body, and has a thin part in which the wall thickness becomes the minimum in an appropriate place. In addition, the thin part thickness (hereinafter referred to as the thin part thickness) T (T3) and the creation diameter D (D3) setting procedure, the thin part thickness T and the uniaxial compressive strength qu of the first ground improvement body 1A The relationship will be described in detail later.

上記掘削に並行して、安定液を掘削溝G内に供給する。これと同時に、サクションポンプ(図示省略)を起動させ、掘削溝G内の掘削土砂と安定液からなる泥水を、排泥用のリバースロッド25aの先端開口部から吸引して上昇させ、処理プラントのスクリーニング部(図示省略)に導いて、掘削溝G外に排出する。また、スクリーン部により、泥水から掘削土砂を適宜取り除き、安定液を回収する。そして、回収した安定液を再び掘削溝G内に供給し、安定液タンクと掘削溝Gとの間で循環させる。これにより、掘削溝Gの溝壁の安定化を図りつつ、掘削溝Gを適宜深さまで掘削する。   In parallel with the excavation, a stable liquid is supplied into the excavation groove G. At the same time, a suction pump (not shown) is activated, and the muddy water composed of the excavated earth and sand and the stabilizing liquid in the excavation groove G is sucked and raised from the tip opening of the reverse rod 25a for discharging mud. It guides to a screening part (illustration omitted), and discharges outside the excavation groove G. Moreover, a screen part removes excavation earth and sand from muddy water suitably, and collects a stable liquid. Then, the recovered stable liquid is supplied again into the excavation groove G and is circulated between the stable liquid tank and the excavation groove G. Thus, the excavation groove G is excavated to an appropriate depth while stabilizing the groove wall of the excavation groove G.

次に、先行エレメントEA用の鉄筋籠建て込み工程では、図14に示すように、各掘削溝G内に、予め分割して形成された概略矩形状の鉄筋籠30を、地上側で順次継ぎ足して建て込む。この建て込みは、最下部の鉄筋籠30が掘削溝Gの底部に到達するまで行う。この鉄筋籠建て込み時に、掘削溝G内には、上記掘削工程で用いた安定液をそのまま満たしておくものとする。   Next, in the reinforcing bar erection process for the leading element EA, as shown in FIG. 14, approximately rectangular reinforcing bar ridges 30 formed in advance in each excavation groove G are sequentially added on the ground side. Build. This erection is performed until the lowermost reinforcing bar 30 reaches the bottom of the excavation groove G. It is assumed that the excavation groove G is filled with the stabilizing liquid used in the excavation process as it is when the reinforcing bar is installed.

鉄筋建て込み後、コンクリート打設工程では、例えば、掘削溝G内に安定液が満たされた状態で、各掘削溝G内にトレミ管をその下端部が掘削溝Gの底部に位置するように挿入する。そして、このトレミ管の下端部開口からコンクリートを掘削溝G内に打設すると共に、安定液を適宜排出して、図15及び図16に示すように、各掘削溝G内にコンクリートを打設する。これにより、先行エレメントEA用の各掘削溝G内に先行エレメントEAがそれぞれ形成される。   After the reinforcement is built, in the concrete placing process, for example, the excavation groove G is filled with the stabilizing liquid, and the tremi pipe is placed in each excavation groove G so that its lower end is located at the bottom of the excavation groove G. insert. Then, concrete is poured into the excavation groove G from the lower end opening of the tremi pipe, and the stabilizing liquid is appropriately discharged, and the concrete is cast into each excavation groove G as shown in FIGS. To do. Thereby, the preceding element EA is formed in each excavation groove G for the preceding element EA.

次に、後行エレメントEBの形成を、図17及び図18に示すように、例えば、先行エレメントEAの形成と同様にして順次行う。
詳しくは、掘削装置20を、その掘削機24の軸心が第2地盤改良体1Bの延伸方向の中心軸(つまりX2)と略一致するように配置して、掘削機24を下降させる。これにより、第2地盤改良体1Bの軸心に溝中心が合された掘削溝Gが形成され始める。この掘削において、掘削機24は、互いに隣り合う先行エレメントEAの短辺側端部を掘削(切削)すると共にこの互いに隣り合う先行エレメントEA間の中間領域S2を掘削して、後行エレメント用の掘削溝Gを得る。これにより、第2地盤改良体1Bの造成径D2より大きい溝幅W1及び地中連続壁Eの壁厚tと略一致する溝厚さt1を有し、その溝中心を第2地盤改良体1Bの延伸方向の中心軸(X2)と合わせて形成され、且つ、支持層G2に達する掘削溝Gが形成される。この掘削溝Gを構成する溝壁のうち短辺方向の2つの溝壁は、それぞれ先行エレメントEAの短辺側端部の掘削(切削)面からなる。また、この掘削溝Gを構成する溝壁のうち長辺方向の2つの溝壁は、その両端部分については第1地盤改良体1Aの掘削面からなり、それ以外の部分部については第2地盤改良体1Bの掘削面からなる。その後、隣接する中間領域S2を含む掘削予定領域において掘削溝Gの掘削を順次繰り返して、図17及び図18に示すように、後行エレメントEB用の掘削溝Gの形成を完了させる。なお、鉄筋籠30の幅は先行エレメントEAのエレメント幅Wより適宜小さく設定され、短辺側端部の切削時に、鉄筋籠30を切削することがないように構成されている。
ここで、掘削溝Gが中心軸(X2)に沿って形成された第2地盤改良体1Bは、適宜箇所にその壁厚が最小となる薄肉部を有する。なお、薄肉部厚さT(T2)及び造成径D(D2)の設定手順と、薄肉部厚さTと第2地盤改良体1Bの一軸圧縮強さquとの関係については、後に詳述する。
Next, as shown in FIGS. 17 and 18, the subsequent element EB is sequentially formed in the same manner as the formation of the preceding element EA, for example.
In detail, the excavator 20 is disposed so that the axis of the excavator 24 is substantially coincident with the central axis (that is, X2) in the extending direction of the second ground improvement body 1B, and the excavator 24 is lowered. Thereby, the excavation groove G in which the groove center is aligned with the axial center of the second ground improvement body 1B starts to be formed. In this excavation, the excavator 24 excavates (cuts) the short-side end portions of the adjacent preceding elements EA and excavates an intermediate region S2 between the adjacent preceding elements EA, so as to The excavation groove G is obtained. Thereby, it has the groove width W1 larger than the formation diameter D2 of the second ground improvement body 1B and the groove thickness t1 substantially coincident with the wall thickness t of the underground continuous wall E, and the groove center is defined as the second ground improvement body 1B. An excavation groove G that is formed in alignment with the central axis (X2) in the extending direction and reaches the support layer G2 is formed. Of the groove walls constituting the excavation groove G, the two groove walls in the short side direction are respectively formed by excavation (cutting) surfaces at the short side end of the preceding element EA. Of the groove walls constituting the excavation groove G, the two groove walls in the long side direction consist of the excavation surface of the first ground improvement body 1A at both ends, and the second ground for the other portions. It consists of the excavation surface of the improved body 1B. Thereafter, the excavation of the excavation groove G is sequentially repeated in the planned excavation area including the adjacent intermediate area S2, and the formation of the excavation groove G for the trailing element EB is completed as shown in FIGS. In addition, the width | variety of the reinforcing bar 30 is set suitably smaller than the element width W of the preceding element EA, and it is comprised so that the reinforcing bar 30 may not be cut at the time of cutting of a short side edge part.
Here, the 2nd ground improvement body 1B in which the excavation groove G was formed along the central axis (X2) has a thin part where the wall thickness becomes the minimum in an appropriate place. In addition, the setting procedure of the thin part thickness T (T2) and the formed diameter D (D2) and the relationship between the thin part thickness T and the uniaxial compressive strength qu of the second ground improvement body 1B will be described in detail later. .

次に、先行エレメントEAと同様に、後行エレメントEB用の各掘削溝G内に、鉄筋籠30を継ぎ足して建て込むと共に、トレミ管を用いてコンクリートを打設することで、図1及び図2に示すように、先行エレメントEAと後行エレメントEBとが一列に交互に配列され、壁厚tを有する地中連続壁Eの構築が完了する。   Next, as with the preceding element EA, in each excavation groove G for the succeeding element EB, a reinforcing bar 30 is added and built, and concrete is placed using a tremi pipe, and FIG. 1 and FIG. As shown in FIG. 2, the leading element EA and the trailing element EB are alternately arranged in a line, and the construction of the underground continuous wall E having the wall thickness t is completed.

ところで、掘削装置20による削孔性を考慮すると、地盤改良体1の強度は低強度に抑制されている方が、施工効率(削孔効率)が高い。そこで、本実施形態においては、噴射液の配合を工夫して、低強度の地盤改良体1の施工を実現した。本実施形態においては、周囲地盤よりも高く設定しつつ掘削装置20による掘削溝Gの施工効率を考慮して、地盤改良体1の一軸圧縮強さquは、所定の材齢日(例えば材齢42日目)において、所定の強度範囲内(例えば、約500kN/m2から約1000kN/m2の範囲内)に収まるように設定されている。所定の材齢日は、地盤改良体1の形成が完了してから地盤改良体1に掘削孔BHを削孔可能となるまでの期間に応じて設定される。なお、上記一軸圧縮強さについての約500kN/m2から約1000kN/m2の範囲(所定の強度範囲)は、掘削装置20の掘削力と地盤の強度とに応じて定める地盤改良体1の後述する許容強度範囲R1に相当する。 By the way, considering the drilling performance by the excavator 20, the construction efficiency (drilling efficiency) is higher when the strength of the ground improvement body 1 is suppressed to a low strength. Therefore, in the present embodiment, the construction of the low strength ground improvement body 1 is realized by devising the composition of the spray liquid. In the present embodiment, in consideration of the construction efficiency of the excavation groove G by the excavator 20 while setting it higher than the surrounding ground, the uniaxial compressive strength qu of the ground improvement body 1 is a predetermined age (for example, material age). in day 42), within a predetermined intensity range (for example, it sets to fit about 500 kN / m 2 in the range of about 1000 kN / m 2). The predetermined material age is set according to a period from when the formation of the ground improvement body 1 is completed to when the excavation hole BH can be drilled in the ground improvement body 1. In addition, the range (predetermined strength range) of about 500 kN / m 2 to about 1000 kN / m 2 with respect to the uniaxial compressive strength is the ground improvement body 1 determined according to the excavating force of the excavator 20 and the strength of the ground. This corresponds to an allowable strength range R1 described later.

次に、薄肉部厚さT(T1,T2)と造成径D(D3,D2)の設定手順と、薄肉部厚さT(T1,T2)と地盤改良体1の一軸圧縮強さquとの関係について説明する。
図19は薄肉部厚さT及び造成径Dの設定手順を説明するためのフロー図であり、図20は一軸圧縮強さquと薄肉部厚さTとの関係を示す図である。
Next, the setting procedure of the thin part thickness T (T1, T2) and the formed diameter D (D3, D2), the thin part thickness T (T1, T2) and the uniaxial compressive strength qu of the ground improvement body 1 The relationship will be described.
FIG. 19 is a flowchart for explaining a procedure for setting the thin portion thickness T and the forming diameter D, and FIG. 20 is a view showing the relationship between the uniaxial compressive strength qu and the thin portion thickness T.

薄肉部厚さT及び造成径Dの設定手順は、大きく分類するとSTEP1とSTEP2の2つの手順からなる。STEP1では、所定の条件を満たす薄肉部厚さTの範囲を設定し、STEP2では、最終的な薄肉部厚さT及び造成径Dを設定して溝壁防護を目的とした地盤改良体1の施工仕様を決定する。以下に、各STEPについて詳述する。   The setting procedure of the thin part thickness T and the forming diameter D is roughly divided into two procedures, STEP1 and STEP2. In STEP 1, the range of the thin part thickness T satisfying the predetermined condition is set, and in STEP 2, the final thin part thickness T and the formation diameter D are set, and the ground improvement body 1 for the purpose of protecting the groove wall is set. Determine construction specifications. Below, each STEP is explained in full detail.

STEP1では、図19に示すように、STEP11において、必要とするエレメント(EA,EB)のエレメント幅W及び壁厚tに応じて掘削溝Gの溝幅W1及び溝厚さt1を決定する。次に、STEP12において、掘削形状の寸法をW1,t1とし、地盤改良体1の一軸圧縮強さquの値を変化させた場合について、掘削溝Gの溝壁の崩壊についての必要安全率Fsを満足する薄肉部厚さTを、例えば、三次元円筒すべり法を用いて算出する。これにより、図20に示すように、必要安全率Fsを満足する薄肉部厚さTと地盤改良体1の一軸圧縮強さquとの関係線Lin1が得られる。本実施形態では、必要安全率Fsは1.5に設定した。なお、計算手法は、三次元円筒すべり法に限らず、例えば、プロトジャコノフ法、有限要素法等の適宜の手法を用いることができる。   In STEP1, as shown in FIG. 19, in STEP11, the groove width W1 and the groove thickness t1 of the excavation groove G are determined according to the element width W and wall thickness t of the required elements (EA, EB). Next, in STEP 12, when the dimensions of the excavation shape are W1, t1, and the value of the uniaxial compressive strength qu of the ground improvement body 1 is changed, the necessary safety factor Fs for the collapse of the groove wall of the excavation groove G is set. The satisfactory thin part thickness T is calculated using, for example, a three-dimensional cylindrical sliding method. As a result, as shown in FIG. 20, a relational line Lin1 between the thin portion thickness T satisfying the necessary safety factor Fs and the uniaxial compressive strength qu of the ground improvement body 1 is obtained. In the present embodiment, the necessary safety factor Fs is set to 1.5. Note that the calculation method is not limited to the three-dimensional cylindrical sliding method, and for example, an appropriate method such as a proto-jakonov method or a finite element method can be used.

次に、STEP13において、掘削装置20の掘削力と地盤の強度とに基づいて、地盤改良体1の許容強度範囲R1を設定する。ここでは、許容強度範囲R1の下限値R1minを周囲地盤の強度より高い値である約500kN/m2とし、許容強度範囲R1の上限値R1maxを掘削装置20の掘削性を考慮して約1000kN/m2とする。この許容強度範囲R1は本実施形態における掘削装置20による削孔可能強度の一例であり、採用する掘削装置の掘削力等に応じて適宜定めることができる。
また、例えば、掘削溝G及び地盤改良体1の鉛直方向の傾きや、掘削溝の寸法精度や、地盤改良体1の造成径精度等の掘削溝G及び地盤改良体1の施工精度に基づいて、施工可能な最小の壁厚である最小壁厚Tminを設定する。ここでは最小壁厚Tmin=50mmとする。
そして、STEP14において、上記地盤改良体1の許容強度範囲R1と必要安全率Fsとに基づいて、安全壁厚範囲R2を設定する。具体的には、図20に示す地盤改良体1の薄肉部厚さTと一軸圧縮強さquとの関係線Lin1において、許容強度範囲R1の下限値R1minと上限値R1maxにそれぞれ対応する薄肉部厚さTの下限値と上限値を求める。図22では、安全壁厚範囲R2の下限値R2minは120mmとなり、安全壁厚範囲R2の上限値R2maxは200mmとなる。この安全壁厚範囲R2内(つまり、R2max≧T≧R2min)で薄肉部厚さTを設定することにより、必要安全率Fsを満足させることができる。ここで、図20から分かるように、一軸圧縮強さquが小さい場合、薄肉部厚さTを大きくすると必要安全率Fsを満足させることができ、一軸圧縮強さquが大きい場合、薄肉部厚さTは小さくても必要安全率を満足させることができる。
このようにして、薄肉部厚さTは、掘削装置20の掘削力と地盤の強度とに応じて定める地盤改良体1の許容強度範囲R1と、掘削溝Gの溝壁崩壊についての必要安全率Fsとに基づいて定める安全壁厚範囲R2内で定める。
Next, in STEP 13, the allowable strength range R1 of the ground improvement body 1 is set based on the excavation force of the excavator 20 and the strength of the ground. Here, the lower limit value R1min of the allowable strength range R1 is set to about 500 kN / m 2 that is higher than the strength of the surrounding ground, and the upper limit value R1max of the allowable strength range R1 is set to about 1000 kN / and m 2. This allowable strength range R1 is an example of drilling strength by the excavator 20 in the present embodiment, and can be determined as appropriate according to the excavation force of the excavator to be employed.
Further, for example, based on the vertical inclination of the excavation groove G and the ground improvement body 1, the dimensional accuracy of the excavation groove, the construction accuracy of the excavation groove G and the ground improvement body 1 such as the formation accuracy of the ground improvement body 1, and the like. The minimum wall thickness Tmin, which is the minimum wall thickness that can be constructed, is set. Here, the minimum wall thickness Tmin = 50 mm.
In STEP 14, a safe wall thickness range R2 is set based on the allowable strength range R1 of the ground improvement body 1 and the necessary safety factor Fs. Specifically, in the relationship line Lin1 between the thin portion thickness T and the uniaxial compressive strength qu of the ground improvement body 1 shown in FIG. 20, the thin portion corresponding to the lower limit value R1min and the upper limit value R1max of the allowable strength range R1, respectively. A lower limit value and an upper limit value of the thickness T are obtained. In FIG. 22, the lower limit value R2min of the safety wall thickness range R2 is 120 mm, and the upper limit value R2max of the safety wall thickness range R2 is 200 mm. The required safety factor Fs can be satisfied by setting the thin portion thickness T within the safety wall thickness range R2 (that is, R2max ≧ T ≧ R2min). Here, as can be seen from FIG. 20, when the uniaxial compressive strength qu is small, the required safety factor Fs can be satisfied by increasing the thin portion thickness T. When the uniaxial compressive strength qu is large, the thin portion thickness Even if the length T is small, the necessary safety factor can be satisfied.
In this way, the thickness T of the thin wall portion is determined by the allowable strength range R1 of the ground improvement body 1 determined according to the excavation force of the excavator 20 and the strength of the ground, and the necessary safety factor for the groove wall collapse of the excavation groove G. It is determined within the safety wall thickness range R2 determined based on Fs.

また、薄肉部厚さTは、具体的には、前記安全壁厚範囲R2のうちの、掘削溝G及び地盤改良体1の施工精度に応じて定める前記最小壁厚Tmin以上の範囲で設定する必要がある。このため、STEP15において、最小壁厚Tminが安全壁厚範囲R2の上限値R2max以下であるか否かを判定する。R2max≧Tmin(STEP15:YES)の場合、STEP16において、安全壁厚範囲R2のうちの最小壁厚Tmin以上の範囲である施工壁厚範囲R3を設定する。薄肉部厚さTは、この施工壁厚範囲R3内(つまり、R2max≧T≧Tmin)で定めることが可能となり、次のSTEP2に進む。本実施形態では、安全壁厚範囲R2の下限値R2min(=120mm)は最小壁厚Tmin(=50mm)より大きいため、施工壁厚範囲R3は安全壁厚範囲R2と一致する。
なお、安全壁厚範囲R2の上限値R2maxが最小壁厚Tminより小さい(STEP15:NO)場合は、最小壁厚Tminが少なくとも安全壁厚範囲R2の上限値R2max以下になるように、例えば、地盤改良体造成装置10のロッド12や掘削装置20の掘削機24の位置決めをより厳密に管理する等して最小壁厚Tminを下げ、施工精度を向上させればよい(STEP15’)。
Moreover, the thin part thickness T is specifically set within the minimum wall thickness Tmin determined according to the construction accuracy of the excavation groove G and the ground improvement body 1 in the safety wall thickness range R2. There is a need. For this reason, in STEP 15, it is determined whether or not the minimum wall thickness Tmin is equal to or less than the upper limit value R2max of the safe wall thickness range R2. In the case of R2max ≧ Tmin (STEP 15: YES), in STEP 16, a construction wall thickness range R3 that is a range equal to or larger than the minimum wall thickness Tmin in the safety wall thickness range R2 is set. The thin part thickness T can be determined within the construction wall thickness range R3 (that is, R2max ≧ T ≧ Tmin), and the process proceeds to the next STEP2. In this embodiment, since the lower limit value R2min (= 120 mm) of the safety wall thickness range R2 is larger than the minimum wall thickness Tmin (= 50 mm), the construction wall thickness range R3 coincides with the safety wall thickness range R2.
When the upper limit value R2max of the safe wall thickness range R2 is smaller than the minimum wall thickness Tmin (STEP 15: NO), for example, the ground is set so that the minimum wall thickness Tmin is at least equal to or lower than the upper limit value R2max of the safe wall thickness range R2. The construction accuracy may be improved by lowering the minimum wall thickness Tmin by, for example, more strictly managing the positioning of the rod 12 of the improved body building apparatus 10 and the excavator 24 of the excavator 20 (STEP 15 ′).

STEP2では、まず、STEP21において、施工壁厚範囲R3内で適切な薄肉部厚さTを決定する。次に、STEP22において、第1地盤改良体1Aについては、掘削溝Gを構成する長辺方向及び短辺方向(全方向)の4つの溝壁において、上記決定した薄肉部厚さTを確保可能な地盤改良体1の造成径D(D3)を決定する。一方、第2地盤改良体1Bについては、掘削溝Gを構成する長辺方向の2つの溝壁において、上記決定した薄肉部厚さTを確保可能な地盤改良体1の造成径D(D2)を決定する。
詳しくは、本実施形態において、薄肉部厚さTは、施工壁厚範囲(=安全壁厚範囲R2)R3内、つまり、120mm〜200mmの範囲内で定めた。第1地盤改良体1Aの造成径D3は、第2地盤改良体1Bの造成径D2より小さくなるように設定した。
ここで、造成径D(D2,D3)が大きくなるほど地盤改良体1の施工費が高くなるが、施工現場における総合的な施工精度等を考慮すると、造成径Dを大きくした方が余裕を持って施工することができる。
このようにして、最終的な薄肉部厚さT(T3,T2)及び造成径D(D3,D2)の値を設定して、溝壁防護を目的とした地盤改良体1の施工仕様を決定する。
In STEP2, first, in STEP21, an appropriate thin part thickness T is determined within the construction wall thickness range R3. Next, in STEP 22, for the first ground improvement body 1A, the above-determined thin portion thickness T can be secured in the four groove walls in the long side direction and the short side direction (all directions) constituting the excavation groove G. A formation diameter D (D3) of the ground improvement body 1 is determined. On the other hand, with respect to the second ground improvement body 1B, the formation diameter D (D2) of the ground improvement body 1 that can secure the determined thin wall thickness T in the two groove walls in the long side direction constituting the excavation groove G. To decide.
Specifically, in the present embodiment, the thin portion thickness T is determined within the construction wall thickness range (= safe wall thickness range R2) R3, that is, within a range of 120 mm to 200 mm. The creation diameter D3 of the first ground improvement body 1A was set to be smaller than the creation diameter D2 of the second ground improvement body 1B.
Here, the construction cost of the ground improvement body 1 increases as the creation diameter D (D2, D3) increases. However, considering the overall construction accuracy at the construction site, the creation diameter D has a margin. Can be installed.
In this way, the final thin wall thickness T (T3, T2) and the creation diameter D (D3, D2) are set, and the construction specifications of the ground improvement body 1 for the purpose of protecting the groove wall are determined. To do.

かかる本実施形態による地中連続壁構築方法によれば、一つの先行エレメントEA用の掘削溝Gの掘削予定領域S1と、互いに隣り合う先行エレメントEA間の一つの中間領域S2とを、それぞれ単位領域とし、先行エレメントEA用の掘削溝Gの掘削に先立って、この単位領域が内部に位置する地盤改良体1(1A,1B)を、単位領域毎にそれぞれ造成している。そして、この単位領域毎の造成工程では、先端部側に噴射モニタ122が設けられた先端ロッド121の基端部側に延長ロッド123を順次継ぎ足してなるロッド12をガイドホールGH内に挿入し、このガイドホールGH内で噴射モニタ122から固化材ミルクを含むジェット流Jを半径方向外方に向けて噴射させつつ、ロッド12を回転及び引き上げることで、地盤より強度の高い地盤改良体1を造成している。
これにより、先行エレメントEA用の各掘削溝Gは、既に造成されている地盤改良体1A内を掘削することにより形成でき、後行エレメントEB用の各掘削溝Gは、既に造成されている地盤改良体1A,1Bと、既に形成されている互いに隣り合う先行エレメントEAの短辺側端部とを掘削することにより形成することができる。したがって、例えば、各地盤改良体強度を、その地盤改良体1や先行エレメントEAを掘削する掘削装置20の能力や工法等に応じて周囲の地盤よりも適宜高めに設定するだけで、各掘削溝Gの溝壁の安定化を図ることができるため、地中連続壁構築中における溝壁の崩壊を防止することができる。
そして、地中連続壁Eの構築予定箇所の上空に何らかの構造物が存在し、クレーン作業が制約を受ける領域であっても、単に小型の削孔機により地盤改良体造成装置10のロッド12を挿入可能な小径のガイドホールGHを掘削し、そのガイドホールGHにロッド12を順次挿入してジェット流Jを噴射させつつロッドを回転及び引き上げるだけで、地中連続壁Eの構築予定箇所に周囲の地盤よりも適宜強度を高めた地盤改良体1を予め構築(造成)することができる。なお、ガイドホールGHや掘削溝Gを形成するための機械及び工法は、それぞれ、各掘削溝Gの掘削予定領域の地面からその上空に存在する構造物までの高さに応じて、本実施形態のように、適宜の機械及び工法を採用すればよい。
According to the underground continuous wall construction method according to this embodiment, the planned excavation area S1 of the excavation groove G for one preceding element EA and one intermediate area S2 between the adjacent preceding elements EA are unitized. Prior to excavation of the excavation groove G for the preceding element EA, the ground improvement body 1 (1A, 1B) in which the unit area is located is formed for each unit area. Then, in the creation process for each unit region, the rod 12 formed by sequentially adding the extension rod 123 to the proximal end side of the distal end rod 121 provided with the injection monitor 122 on the distal end side is inserted into the guide hole GH, The ground improvement body 1 having higher strength than the ground is created by rotating and pulling up the rod 12 while jetting the jet stream J containing the solidified milk from the jet monitor 122 in the guide hole GH radially outward. doing.
Accordingly, each excavation groove G for the leading element EA can be formed by excavating the ground improvement body 1A that has already been created, and each excavation groove G for the subsequent element EB has been already created. It can be formed by excavating the improved bodies 1A and 1B and the short-side ends of the adjacent preceding elements EA that are already formed. Therefore, for example, each excavation groove is simply set to a strength higher than that of the surrounding ground according to the capability and construction method of the excavator 20 for excavating the ground improvement body 1 and the leading element EA. Since stabilization of the groove wall of G can be aimed at, collapse of the groove wall during construction of the underground continuous wall can be prevented.
And even if there is some structure above the planned construction site of the underground continuous wall E and the crane operation is restricted, the rod 12 of the ground improvement body building device 10 is simply attached by a small drilling machine. A small diameter guide hole GH that can be inserted is excavated, the rod 12 is sequentially inserted into the guide hole GH, and the jet stream J is sprayed to rotate and pull up the rod. It is possible to construct (create) a ground improvement body 1 having a strength appropriately higher than that of the ground. The machine and the method for forming the guide hole GH and the excavation groove G are different from each other according to the height from the ground in the planned excavation area of each excavation groove G to the structure existing above it. Thus, an appropriate machine and construction method may be employed.

このようにして、地中連続壁の構築予定箇所の上空に何らかの構造物が存在し、クレーン作業が制約を受ける領域にて、地中連続壁の構築中における溝壁の崩壊を防止しつつ地中連続壁を容易に構築可能な地中連続壁構築方法を提供することができる。   In this way, in the area where there is some structure above the planned construction site of the underground continuous wall and the crane work is restricted, the ground wall is prevented from collapsing during the construction of the underground continuous wall. An underground continuous wall construction method capable of easily constructing an intermediate continuous wall can be provided.

また、本実施形態では、掘削溝Gの形成時及び鉄筋籠建て込み時に、掘削溝G内に安定液を供給する構成とした。これにより、掘削溝Gの溝壁のより確実な安定化を図った状態で、掘削溝Gを適宜深さまで掘削可能であると共に鉄筋籠を建て込むことができる。
なお、例えば、地盤に掘削溝を直接削孔しつつ、安定液を供給して溝壁の崩壊を抑制する工法が一般的に知られている。しかし、この工法であっても、地盤の地下水位が比較的高い場合や、掘削装置による掘削溝内への安定液の供給量と吸引量のアンバランスが一時的に生じた場合等においては、溝壁が崩壊する可能性が高い。一方、本実施形態においては、掘削溝Gを形成する工程に先立って地盤改良体1を造成しているため、掘削溝Gの溝壁の崩壊リスクを完全に排除することができる。
Moreover, in this embodiment, it was set as the structure which supplies a stable liquid in the excavation groove G at the time of formation of the excavation groove G, and at the time of reinforcement reinforcement construction. Thus, the excavation groove G can be excavated to an appropriate depth and a reinforcing bar can be built in a state in which the groove wall of the excavation groove G is more reliably stabilized.
In addition, for example, a method is generally known in which, while directly excavating an excavation groove in the ground, a stabilizing liquid is supplied to suppress the collapse of the groove wall. However, even with this construction method, when the groundwater level of the ground is relatively high, or when there is a temporary imbalance between the amount of stable liquid supplied to the excavation groove and the suction amount by the excavator, There is a high possibility that the groove wall will collapse. On the other hand, in this embodiment, since the ground improvement body 1 is created prior to the step of forming the excavation groove G, the risk of collapse of the groove wall of the excavation groove G can be completely eliminated.

また、先行エレメントEA用の掘削溝Gの掘削予定領域S1をカバーする地盤改良体1を造成することにより、後行エレメントEB用の掘削溝Gの掘削予定領域の水平方向両端部も同時に造成することができる。このため、本実施形態では、中間領域S2に対応して造成される地盤改良体(第2地盤改良体1B)1の水平断面積は、先行エレメントEA用の掘削溝Gの掘削予定領域S1に対応して造成される地盤改良体(第1地盤改良体1A)1の水平断面積より小さくなるように設定されている。つまり、本実施形態では、D2はD3より小さくなるように設定されている。これにより、地盤改良体1の造成範囲を狭めることができ、地盤改良体1の造成コストを低くすることができる。   In addition, by creating the ground improvement body 1 that covers the planned excavation area S1 of the excavation groove G for the preceding element EA, both horizontal end portions of the planned excavation area of the excavation groove G for the subsequent element EB are also formed at the same time. be able to. For this reason, in the present embodiment, the horizontal cross-sectional area of the ground improvement body (second ground improvement body 1B) 1 created corresponding to the intermediate area S2 is set in the planned excavation area S1 of the excavation groove G for the preceding element EA. It is set to be smaller than the horizontal cross-sectional area of the corresponding ground improvement body (first ground improvement body 1A) 1 created. That is, in this embodiment, D2 is set to be smaller than D3. Thereby, the creation range of the ground improvement body 1 can be narrowed, and the creation cost of the ground improvement body 1 can be lowered.

また、本実施形態では、地盤改良体1は、単に、地中連続壁Eの構築方向に沿って一列に配列される構成である。したがって、地中連続壁Eの構築予定領域を挟むように、2列のソイルモルタル柱列をSMW工法により構築する一般的な工法と比較して、地盤改良体の造成に要する工期を短縮することができる。また、上記一般的な工法においては、掘削機による掘削溝の掘削性を考慮して、ソイルモルタル柱列は地中連続壁Eの出来形ラインに隣接して又は出来形ラインから若干のクリアランスを設けて配置され、いずれの場合においても、溝掘削後、出来形ラインと地盤改良体の外周との間に土砂が残存し、この残存土砂を後工程において除去する作業を必要としていたところ、本実施形態による地中連続壁構築方法では、上記除去作業が不要となる。   Moreover, in this embodiment, the ground improvement body 1 is a structure which is simply arranged in a line along the construction direction of the underground continuous wall E. Therefore, compared with the general construction method that constructs two rows of soil mortar columns by the SMW method so as to sandwich the planned construction area of the underground continuous wall E, the construction period required to create the ground improvement body is shortened. Can do. In addition, in the above general construction method, considering the excavation ability of the excavation groove by the excavator, the soil mortar column is adjacent to the completed line of the underground continuous wall E or has a slight clearance from the completed line. In any case, after excavation of the trench, earth and sand remained between the completed line and the outer periphery of the ground improvement body, and it was necessary to remove this residual earth and sand in a subsequent process. In the underground continuous wall construction method according to the embodiment, the above removal work is not necessary.

また、本実施形態では、掘削溝Gの形成後の地盤改良体1の薄肉部厚さTを、許容強度範囲R1と、必要安全率Fsとに基づいて定める安全壁厚範囲R2内で定めている。これにより、溝壁の崩壊をより確実に防止することができる。
さらに、本実施形態では、薄肉部厚さTは、安全壁厚範囲R2のうちの、掘削溝G及び地盤改良体1の施工精度に応じて定める最小壁厚Tmin以上の範囲である施工壁厚範囲R3内で定められている。これにより、施工精度を考慮して、薄肉部厚さTを設定することができる。
In the present embodiment, the thickness T of the ground improvement body 1 after the formation of the excavation groove G is determined within the safety wall thickness range R2 determined based on the allowable strength range R1 and the necessary safety factor Fs. Yes. Thereby, collapse of a groove wall can be prevented more reliably.
Furthermore, in this embodiment, the thin wall thickness T is a construction wall thickness that is within a minimum wall thickness Tmin determined in accordance with the construction accuracy of the excavation groove G and ground improvement body 1 in the safety wall thickness range R2. It is determined within the range R3. Thereby, the thin part thickness T can be set in consideration of construction accuracy.

また、本実施形態では、地盤改良体1の一軸圧縮強さquは、地盤改良体1の造成が完了してから地盤改良体1に掘削溝Gを形成可能となるまでの期間に応じて設定する所定の材齢日において、所定の強度範囲内に収まるように設定されている。これにより、地盤改良体1に掘削溝Gを形成する際に、その一軸圧縮強さquを、確実に意図する強度範囲内に設定することができる。   Moreover, in this embodiment, the uniaxial compressive strength qu of the ground improvement body 1 is set according to the period until it becomes possible to form the excavation groove G in the ground improvement body 1 after the creation of the ground improvement body 1 is completed. It is set so as to be within a predetermined strength range on a predetermined material age day. Thereby, when forming the excavation groove G in the ground improvement body 1, the uniaxial compressive strength qu can be reliably set within the intended strength range.

また、本実施形態では、所定の強度範囲の下限値は、地盤改良体1の周囲地盤の強度より高く設定され、所定の強度範囲の上限値は、掘削溝Gを形成する掘削装置20の掘削力に応じて設定されている。これにより、地盤改良体1の所定の材齢日における一軸圧縮強さquを、周囲地盤よりも高く設定しつつ掘削装置20による掘削溝Gの施工効率を考慮して、確実に低強度に設定することができるため、溝壁崩壊の防止と掘削溝Gの施工効率の向上を効率的に両立させることができる。なお、本実施形態においては、所定の強度範囲は、その下限値(許容強度範囲R1の下限値R1mim)を約500kN/m2とし、上限値(許容強度範囲R1の上限値R1max)を1000kN/m2とした場合を一例に挙げて説明したが、これに限らず、掘削装置20の掘削力及び周囲地盤の強度に応じて適宜定めることができる。 Further, in the present embodiment, the lower limit value of the predetermined strength range is set higher than the strength of the surrounding ground of the ground improvement body 1, and the upper limit value of the predetermined strength range is the excavation of the excavator 20 that forms the excavation groove G. It is set according to the force. Thereby, the uniaxial compressive strength qu on the predetermined age of the ground improvement body 1 is set higher than the surrounding ground, and the construction efficiency of the excavation groove G by the excavator 20 is set to ensure a low strength. Therefore, prevention of groove wall collapse and improvement in construction efficiency of the excavation groove G can be achieved at the same time. In the present embodiment, the predetermined intensity range has a lower limit value (lower limit value R1mim of allowable intensity range R1) of about 500 kN / m 2 and an upper limit value (upper limit value R1max of allowable intensity range R1) of 1000 kN / Although the case of the m 2 and described by way of example, not limited to this and can be suitably determined according to the intensity of the drilling force and surrounding soil of the excavation device 20.

なお、本実施形態において、各地盤改良体1(1A,1B)は、出来上がり時において、それぞれ円形の断面形状を有して形成される場合で説明したが、地盤改良体1の形状はこれに限らず適宜形状を採用することができる。
例えば、図21に示すように、各地盤改良体1(1A,1B)は、それぞれ半円の断面形状を有していてもよい。この場合、例えば、第1地盤改良体1Aの鉛直方向に延びる側面と第2地盤改良体1Bの鉛直方向に延びる側面とが一列に揃うように、各地盤改良体1(1A,1B)を配置するとよい。また、図示を省略するが、円形や半円に限らず、扇形であってもよいし、扇形中心で反転させて2つの扇形が一体となったリボン形であってもよいし、矩形状であってもよい。矩形状の場合は、例えば、単位領域毎の造成において、ガイドホールGHを複数個所に設けて造成すればよい。また、各地盤改良体1(1A,1B)は、複数の小地盤改良体を互いに一部重ねて一体的に形成されてなるものでもよい。
In the present embodiment, the local ground improvement body 1 (1A, 1B) has been described as being formed with a circular cross-sectional shape at the time of completion. The shape can be appropriately adopted without limitation.
For example, as shown in FIG. 21, each board improvement body 1 (1A, 1B) may have a semicircular cross-sectional shape. In this case, for example, each ground improvement body 1 (1A, 1B) is arranged so that the side surface extending in the vertical direction of the first ground improvement body 1A and the side surface extending in the vertical direction of the second ground improvement body 1B are aligned. Good. Although not shown in the drawings, the shape is not limited to a circle or a semicircle, and may be a fan shape, a ribbon shape that is inverted at the center of a fan shape and integrated with two fan shapes, or a rectangular shape. There may be. In the case of a rectangular shape, for example, in the creation for each unit region, the guide holes GH may be provided at a plurality of locations. Moreover, each board improvement body 1 (1A, 1B) may be formed integrally by partially overlapping a plurality of small ground improvement bodies.

また、本実施形態において、第2地盤改良体1Bの水平断面積は、第1地盤改良体1Aの水平断面積より小さくなるように設定されものとしたが、これに限らず、第1地盤改良体1Aの水平断面と略一致させてもよいし、大きくなるように設定してもよい。
また、第1地盤改良体1Aと第2地盤改良体1Bとは互いに相似形であるものとしたが、これに限らず、互いに異なる種類の断面形状(円形、半円、扇形、リボン形、矩形、団子状等)を採用してもよい。例えば、図22に示すように、第1地盤改良体1Aとしては、複数の円が一部重なり合って一体となった団子状の断面形状を採用し、第2地盤改良体1Bとしては、円形の断面形状を採用してもよい。
また、各第1地盤改良体1Aにおいても異なる種類の形状及び大きさの改良体を採用してもよいし、各第2地盤改良体1Bにおいても同様である。
また、本実施形態において、第1地盤改良体1A及び第2地盤改良体1Bはそれぞれ一定の間隔(ピッチ)で配置されるものとしたが、これに限らず、不等間隔で配置してもよい。
In the present embodiment, the horizontal cross-sectional area of the second ground improvement body 1B is set to be smaller than the horizontal cross-sectional area of the first ground improvement body 1A. The horizontal section of the body 1A may be substantially coincident, or may be set to be large.
In addition, the first ground improvement body 1A and the second ground improvement body 1B are similar to each other, but are not limited to this, and different types of cross-sectional shapes (circular, semicircular, fan-shaped, ribbon-shaped, rectangular) , Dumplings, etc.) may be employed. For example, as shown in FIG. 22, as the first ground improvement body 1A, a dumpling-like cross-sectional shape in which a plurality of circles are partially overlapped and integrated is adopted, and as the second ground improvement body 1B, a circular shape is adopted. A cross-sectional shape may be adopted.
Further, different types of shapes and sizes of the first ground improvement bodies 1A may be adopted, and the same applies to the second ground improvement bodies 1B.
Moreover, in this embodiment, although the 1st ground improvement body 1A and the 2nd ground improvement body 1B shall be each arrange | positioned by the fixed space | interval (pitch), it is not restricted to this, You may arrange | position at unequal intervals. Good.

また、本実施形態において、各地盤改良体1は、それぞれ地表面から支持層G2まで延設されるものとして説明したが、これに限らない。例えば、配管等の埋設物が地中連続壁Eの構築予定領域を横断するように既に埋設されている場合等には、その埋設部分に位置する適宜本数の地盤改良体1については、埋設物の下端近傍から支持層G2まで延設すればよい。この場合、造成工程におけるロッド12の引き上げは、ジェット流Jの噴射がピット埋設物の下端近傍に達するまで行えばよい。   Moreover, in this embodiment, although the local board improvement body 1 demonstrated each extending from the ground surface to the support layer G2, it is not restricted to this. For example, when buried objects such as pipes have already been buried so as to cross the planned construction area of the underground continuous wall E, for the appropriate number of ground improvement bodies 1 located in the buried part, What is necessary is just to extend from the lower end vicinity to the support layer G2. In this case, the rod 12 may be pulled up in the creation process until the jet stream J is injected near the lower end of the pit buried object.

また、本実施形態においては、説明の便宜上、第1地盤改良体1Aを全て造成した後、第2地盤改良体1Bを造成するものとして説明したが、地盤改良体1の造成作業の単位はこれに限らない。例えば、地中連続壁Eの水平方向長さが長い場合等には、適宜小区分に分けて、その小区間毎に、第1地盤改良体1A、第2地盤改良体1Bを造成するとよい。   Further, in the present embodiment, for convenience of explanation, the first ground improvement body 1A is created, and then the second ground improvement body 1B is created. However, the ground improvement body 1 is constructed in units of this. Not limited to. For example, when the horizontal direction length of the underground continuous wall E is long, the first ground improvement body 1A and the second ground improvement body 1B may be created for each of the small sections as appropriate.

また、本実施形態においては、説明の便宜上、造成工程の完了後、先行エレメントEAを全て形成した後に、後行エレメントEBの形成を開始するものとして説明したが、これに限らない。上記造成と同様に、小区間毎に、先行エレメントEAと後行エレメントEBの形成を適宜行うとよい。   Further, in the present embodiment, for the sake of convenience of explanation, it has been described that the formation of the succeeding element EB is started after all the leading elements EA are formed after the creation process is completed, but the present invention is not limited thereto. Similar to the above construction, the leading element EA and the trailing element EB may be appropriately formed for each small section.

また、本実施形態においては、説明の便宜上、全先行エレメントEA用の掘削工程の完了後、鉄筋籠建て込み工程に進み、その後、コンクリート打設工程に進むものとして説明したが、先行エレメントEAの形成の作業単位はこれに限らない。例えば、一つの先行エレメントEA毎に掘削、鉄筋籠建て込み、コンクリート打設を完了させてから、次の先行エレメントEAの施工を実施したり、適宜小区分に分けて、その小区分毎に施工したりするとよい。また、後行エレメントEBについても同様である。   Further, in the present embodiment, for the sake of convenience of explanation, it has been described that after completion of the excavation process for all the preceding elements EA, the process proceeds to the reinforcing bar construction process, and then proceeds to the concrete placing process. The unit of work for formation is not limited to this. For example, after excavation, rebar construction, and concrete placement are completed for each preceding element EA, construction of the next leading element EA is carried out or divided into small sections as appropriate, and construction is performed for each small section. It is good to do. The same applies to the succeeding element EB.

また、本実施形態では、先行エレメントEA及び後行エレメントEBは、掘削溝G内に、予め分割して形成された鉄筋籠30を順次継ぎ足して建て込むと共にコンクリートを打設して形成されてなる鉄筋コンクリート製のエレメントである場合を一例として説明したが、これに限らない。例えば、打設する材料については、コンクリートに限らず、セメント系材料であればよく、例えば、ソイルモルタル等を打設してもよい。また、各エレメント(EA,EB)は、鉄筋とセメント系材料からなるものに限らず、例えば、各掘削溝G内に、予め分割して形成されたコンクリート製部材又は鋼製部材を順次継ぎ足して建て込み、その後、各掘削溝Gの溝壁と建て込まれたコンクリート製部材又は鋼製部材との間に、コンクリート、モルタル、セメントペースト及びソイルモルタル等のセメント系材料を充填して形成されるものであってもよい。この場合、セメント系材料には、各種混和材などを使用してブリージングを抑制させた材料を使用するとよい。   Further, in the present embodiment, the leading element EA and the trailing element EB are formed by sequentially adding and building the reinforcing bar rods 30 formed in advance in the excavation groove G and placing concrete. Although the case where it was an element made from reinforced concrete was demonstrated as an example, it is not restricted to this. For example, the material to be placed is not limited to concrete but may be a cement-based material. For example, soil mortar may be placed. In addition, each element (EA, EB) is not limited to one made of a reinforcing bar and a cement-based material. For example, in each excavation groove G, concrete members or steel members formed in advance are sequentially added. After erection, it is formed by filling cement-based materials such as concrete, mortar, cement paste and soil mortar between the groove wall of each excavation groove G and the erected concrete member or steel member. It may be a thing. In this case, as the cement-based material, it is preferable to use a material in which breathing is suppressed by using various admixtures.

また、本実施形態では、掘削溝Gの形成後、その掘削溝G内に、水より大きい密度を有する適宜の安定液(例えばベントナイトを含む安定化用泥水)をそのまま満たしておくものとしたが、これに限らない。地中連続壁Eの構築予定領域の地下水の水位が低い場合等において、例えば、掘削溝G内に単に清水を充填させるだけで、掘削溝内の清水の水頭と地下水の水頭との間に十分な水頭差を確保することができる場合がある。これにより、鉄筋籠建て込み工程及びコンクリート等のセメント系材料の打設工程において、鉄筋表面に、安定化用泥水の微粒子を付着させることなく、各エレメントEA,EBを構築することができる。   Further, in the present embodiment, after the excavation groove G is formed, the excavation groove G is filled with an appropriate stabilizing liquid having a density larger than water (for example, stabilization mud containing bentonite) as it is. Not limited to this. In the case where the groundwater level in the construction planned area of the underground continuous wall E is low, for example, simply filling the excavation groove G with fresh water is sufficient between the freshwater head in the excavation groove and the groundwater head. In some cases, it is possible to ensure a sufficient head differential. Thereby, each element EA, EB can be constructed without attaching fine particles of stabilizing mud on the surface of the reinforcing bar in the reinforcing bar building process and the placing process of cement-based material such as concrete.

また、地盤改良体1は周囲の地盤よりも高い強度に設定されているため、地中連続壁Eの構築予定領域の地下水の水位が低い場合等においては、掘削溝Gの形成中及びそれ以降の工程において、掘削溝G内に安定液を使用しなくても、溝壁の崩壊リスクを完全に排除することができる場合もある。したがって、本実施形態においては、掘削溝Gの形成時に、掘削溝G内に安定液を供給する構成としたが、地中連続壁Eの構築予定領域の地下水の水位等の地盤状況によっては、これに限らず、安定液を用いなくてもよい場合もある。この場合、掘削溝Gを形成する工法は、低空頭下且つ狭隘な施工場所で施工可能な適宜の工法を採用すればよい。   In addition, since the ground improvement body 1 is set to have a higher strength than the surrounding ground, when the groundwater level in the construction planned area of the underground continuous wall E is low, the excavation groove G is being formed and thereafter. In this process, there is a case where the risk of collapse of the groove wall can be completely eliminated without using a stabilizing liquid in the excavation groove G. Therefore, in the present embodiment, when the excavation groove G is formed, a stable liquid is supplied into the excavation groove G. However, depending on the ground conditions such as the groundwater level in the construction planned area of the underground continuous wall E, However, the present invention is not limited to this, and there may be a case where a stabilizer is not required. In this case, the construction method for forming the excavation groove G may be an appropriate construction method that can be constructed at a low construction site and in a narrow construction site.

また、本実施形態では、先行エレメントEA用の掘削溝Gの大きさと後行エレメントEB用の掘削溝Gの大きさは同じであるものとして説明したが、これに限らず、異ならせてもよい。また、本実施形態では、各エレメント(EA,EB)用の掘削溝Gは、一回の鉛直方向の掘削(1ガット)により形成するものとしたが、これに限らず、複数回の鉛直方向の掘削により形成してもよい。例えば、前述の図22に示した変形例においては、一つの先行エレメントEA用の掘削溝Gは、例えば、3ガットにより形成されている。   In the present embodiment, the size of the excavation groove G for the preceding element EA and the size of the excavation groove G for the subsequent element EB are described as being the same. However, the present invention is not limited to this, and may be different. . In the present embodiment, the excavation groove G for each element (EA, EB) is formed by one excavation (one gut) in the vertical direction. You may form by excavating. For example, in the modified example shown in FIG. 22, the excavation groove G for one preceding element EA is formed by, for example, 3 guts.

また、本実施形態では、地中連続壁Eは、水平一方向に、つまり、直線的に延伸するものとして説明したが、これに限らず、湾曲するように延伸してもよい。また、地中連続壁Eは、横長矩形断面を有するものに限らず、所定の壁厚を有した円弧状の断面等の適宜断面形状を適用できる。また、地中連続壁Eは、中空構造であってもよく、例えば、円筒状に形成されてなるものでもよい。   In the present embodiment, the underground continuous wall E has been described as extending in one horizontal direction, that is, linearly. However, the present invention is not limited to this, and the underground continuous wall E may be extended so as to be curved. In addition, the underground continuous wall E is not limited to having a horizontally long rectangular cross section, and an appropriate cross sectional shape such as an arc-shaped cross section having a predetermined wall thickness can be applied. Moreover, the underground continuous wall E may have a hollow structure, for example, may be formed in a cylindrical shape.

また、本実施形態では、掘削装置20は、いわゆる水平多軸式の掘削機24を用いた場合で説明したが、これに限らず、各掘削溝Gの掘削予定領域の地面から上空に存在する既設構造物までの高さに応じて、例えば、バケット式等の適宜の連壁用の掘削機を採用することができる。   Further, in the present embodiment, the excavator 20 has been described using a so-called horizontal multi-axis excavator 24, but the present invention is not limited to this, and the excavator 20 exists above the ground in the planned excavation area of each excavation groove G. Depending on the height to the existing structure, for example, an appropriate continuous wall excavator such as a bucket type can be employed.

また、地中連続壁Eの構築予定領域の上方に存在する既設構造物の一例として、鉄道高架橋Bを挙げたが、既設構造物は鉄道高架橋Bに限らず、どのようなものでもよい。そして、施工場所は、低空頭且つ狭隘な場所であるものとしたが、これに限らず、地中連続壁Eの構築予定領域の上方の既設構造物までの距離が十分にある場所や、既設構造物が上方に無い場合や、低空頭であるが十分なスペースを確保可能な場所でもよい。   Moreover, although the railway viaduct B was mentioned as an example of the existing structure which exists above the construction plan area | region of the underground continuous wall E, an existing structure is not restricted to the railway viaduct B, What kind of thing may be sufficient. The construction site is a low-headed and narrow place, but is not limited to this, a place where there is a sufficient distance to the existing structure above the planned construction area of the underground continuous wall E, It may be a place where there is no structure above or a place where a sufficient space can be secured even though the head is low.

以上、本発明の好ましい実施形態について説明したが、本発明は上記実施形態に制限されるものではなく、本発明の技術的思想に基づいて種々の変形及び変更が可能である。   As mentioned above, although preferable embodiment of this invention was described, this invention is not restrict | limited to the said embodiment, A various deformation | transformation and change are possible based on the technical idea of this invention.

1…地盤改良体(第1地盤改良体、第2地盤改良体)、10…地盤改良体造成装置、11…本体、12…ロッド、13…把持部、14…ピット、15…サンドポンプ、16…スライム貯留タンク、17…スイベル、20…掘削装置、21…ベースマシン、22…リーダ、23…補助クレーン、24…掘削機、25…昇降部、25a…リバースロッド、26…ウインチ、27…ワイヤロープ、28…吊り具、29…カッタードラム、121…先端ロッド、122…噴射モニタ(ノズル)、123…延長ロッド、261…先端掘削ロッド管、262…削孔ビット、263…延長掘削ロッド管、B…鉄道高架橋(既設構造物)、BH…掘削孔、D1…ガイドホールの内径、D2…第2地盤改良体の造成径、D3…第1地盤改良体の造成径、E…地中連続壁、EA…先行エレメント、EB…後行エレメント、G…掘削溝、G1…上層、G2…支持層、GH…ボーリング孔(ガイドホール)、J…ジェット流、R1…許容強度範囲、R2…安全壁厚範囲、R3…施工壁厚範囲、S1…掘削予定領域、S2…中間領域、t…壁厚、t1…溝厚さ、W…エレメント幅、W1…溝幅 DESCRIPTION OF SYMBOLS 1 ... Ground improvement body (1st ground improvement body, 2nd ground improvement body), 10 ... Ground improvement body formation apparatus, 11 ... Main body, 12 ... Rod, 13 ... Holding part, 14 ... Pit, 15 ... Sand pump, 16 ... slime storage tank, 17 ... swivel, 20 ... excavator, 21 ... base machine, 22 ... leader, 23 ... auxiliary crane, 24 ... excavator, 25 ... lifting part, 25a ... reverse rod, 26 ... winch, 27 ... wire Rope, 28 ... Suspension tool, 29 ... Cutter drum, 121 ... Tip rod, 122 ... Injection monitor (nozzle), 123 ... Extension rod, 261 ... Tip drilling rod tube, 262 ... Drilling bit, 263 ... Extension drilling rod tube, B ... Railway viaduct (existing structure), BH ... excavation hole, D1 ... inner diameter of guide hole, D2 ... creation diameter of second ground improvement body, D3 ... creation diameter of first ground improvement body, E ... underground connection Connecting wall, EA ... preceding element, EB ... trailing element, G ... excavation groove, G1 ... upper layer, G2 ... support layer, GH ... boring hole (guide hole), J ... jet flow, R1 ... allowable strength range, R2 ... Safety wall thickness range, R3 ... construction wall thickness range, S1 ... planned excavation area, S2 ... intermediate area, t ... wall thickness, t1 ... groove thickness, W ... element width, W1 ... groove width

Claims (6)

地中に間隔をおいて掘削される先行エレメント用の各掘削溝内に先行エレメントを形成した後、互いに隣り合う前記先行エレメントの端部を掘削すると共に該先行エレメント間の中間領域を掘削して得られる後行エレメント用の各掘削溝内に後行エレメントを形成して地中連続壁を構築する地中連続壁構築方法であって、
一つの前記先行エレメント用の前記掘削溝の掘削予定領域と、一つの前記中間領域とを、それぞれ単位領域とし、
前記先行エレメント用の前記掘削溝の掘削に先立って、前記単位領域が内部に位置する地盤改良体を、前記単位領域毎にそれぞれ造成する造成工程を含み、
前記単位領域毎の前記造成工程では、
前記地中に鉛直方向に延伸するボーリング孔を形成し、
円筒状の先端ロッドと、当該先端ロッドの先端部側に設けられるノズルと、前記先端ロッドの基端部側に順次継ぎ足される延長ロッドと、を有するロッドを前記ボーリング孔に挿入し、
固化材と水を含む液体を前記ノズルから半径方向外方に向けて噴射しつつ、前記ロッドを回転させると共に、前記ロッドを引き上げて、前記ボーリング孔より大径であり且つ前記地盤より強度の高い前記地盤改良体を造成する、地中連続壁構築方法。
After forming the preceding element in each excavation groove for the preceding element excavated at a distance in the ground, excavating the end of the preceding element adjacent to each other and excavating the intermediate region between the preceding elements An underground continuous wall construction method for constructing an underground continuous wall by forming a downstream element in each excavation groove for the subsequent element obtained,
A drilling planned area of the excavation groove for one of the preceding elements and one intermediate area are each set as a unit area,
Prior to excavation of the excavation groove for the preceding element, including a creation step of creating, for each unit region, a ground improvement body in which the unit region is located,
In the creation process for each unit region,
Forming a borehole extending vertically in the ground,
Inserting a rod having a cylindrical tip rod, a nozzle provided on the tip end side of the tip rod, and an extension rod sequentially added to the base end side of the tip rod into the boring hole,
The rod is rotated while ejecting a liquid containing solidification material and water radially outward from the nozzle, and the rod is pulled up to be larger in diameter than the boring hole and higher in strength than the ground. An underground continuous wall construction method for creating the ground improvement body.
前記地盤改良体は、前記地中連続壁の構築方向に沿って一列に配列される、請求項1に記載の地中連続壁構築方法。   The underground continuous wall construction method according to claim 1, wherein the ground improvement bodies are arranged in a line along a construction direction of the underground continuous wall. 前記中間領域用の前記地盤改良体と、前記先行エレメント用の前記地盤改良体とを、互いに一部重複させて造成する、請求項1又は2に記載の地中連続壁構築方法。   The underground continuous wall construction method according to claim 1 or 2, wherein the ground improvement body for the intermediate region and the ground improvement body for the preceding element are partially overlapped with each other. 前記各掘削溝内に、予め分割して形成された鉄筋籠を順次継ぎ足して建て込むと共にセメント系材料を打設して、前記先行エレメント又は前記後行エレメントを形成する、請求項1〜3のいずれか1つに記載の地中連続壁構築方法。   In each of the excavation grooves, rebar bars formed in advance are sequentially added and built, and a cement-based material is placed to form the leading element or the trailing element. The underground continuous wall construction method according to any one of the above. 前記各掘削溝内に、予め分割して形成されたコンクリート製部材又は鋼製部材を順次継ぎ足して建て込み、
前記各掘削溝の溝壁と前記建て込まれた前記コンクリート製部材又は鋼製部材との間に、セメント系材料を充填して、前記先行エレメント又は前記後行エレメントを形成する、請求項1〜4のいずれか1つに記載の地中連続壁構築方法。
In each of the excavation grooves, concrete members or steel members formed by dividing in advance are built in order,
The cemented material is filled between the groove wall of each excavation groove and the built-in concrete member or steel member to form the preceding element or the trailing element. 5. The underground continuous wall construction method according to any one of 4 above.
前記掘削溝の形成後の前記地盤改良体は、その壁厚が最小となる薄肉部を有し、
前記薄肉部の厚さは、前記掘削溝を形成する掘削装置の掘削力と地盤の強度とに応じて定める前記地盤改良体の許容強度範囲と、前記掘削溝の溝壁崩壊についての必要安全率とに基づいて定める安全壁厚範囲内で定められる、請求項1〜5のいずれか1つに記載の地中連続壁構築方法。
The ground improvement body after the formation of the excavation groove has a thin wall portion whose wall thickness is minimized,
The thickness of the thin wall portion is the allowable strength range of the ground improvement body determined according to the excavation force of the excavator that forms the excavation groove and the strength of the ground, and the necessary safety factor for the collapse of the groove wall of the excavation groove The underground continuous wall construction method according to any one of claims 1 to 5, wherein the underground continuous wall construction method is defined within a safety wall thickness range determined on the basis of.
JP2015149200A 2015-07-29 2015-07-29 Underground continuous wall construction method Active JP6378652B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP2015149200A JP6378652B2 (en) 2015-07-29 2015-07-29 Underground continuous wall construction method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP2015149200A JP6378652B2 (en) 2015-07-29 2015-07-29 Underground continuous wall construction method

Publications (2)

Publication Number Publication Date
JP2017031562A true JP2017031562A (en) 2017-02-09
JP6378652B2 JP6378652B2 (en) 2018-08-22

Family

ID=57985974

Family Applications (1)

Application Number Title Priority Date Filing Date
JP2015149200A Active JP6378652B2 (en) 2015-07-29 2015-07-29 Underground continuous wall construction method

Country Status (1)

Country Link
JP (1) JP6378652B2 (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2021067120A (en) * 2019-10-25 2021-04-30 鹿島建設株式会社 Construction method of underground continuous wall
CN114855818A (en) * 2022-05-23 2022-08-05 中铁二十局集团第一工程有限公司 High-pressure rotary spraying reinforcement method for double-row narrow-distance ground wall

Citations (13)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US4005582A (en) * 1975-08-12 1977-02-01 Icos Corporation Of America Method of constructing underground concrete walls and reinforcement cage therefor
JPS5854124A (en) * 1981-09-24 1983-03-31 Ohbayashigumi Ltd Constructing method for preliminary underground wall preceding excavation of ditch for continuous underground wall
JPS6085117A (en) * 1983-10-14 1985-05-14 Ohbayashigumi Ltd Method of improving ground prior to construction of underground continuous wall
JPH05118032A (en) * 1991-10-25 1993-05-14 Ohbayashi Corp Execution method of continuous underground wall
JPH05321511A (en) * 1992-05-21 1993-12-07 Nippon Steel Corp Construction method for underground vessel in weak ground
JPH06193046A (en) * 1993-10-01 1994-07-12 Yoshinobu Koiwa Pit construction method
JPH0931972A (en) * 1995-07-25 1997-02-04 Ohbayashi Corp Construction of underground continuous wall
JPH11280060A (en) * 1998-03-31 1999-10-12 Tone Geo Tech Co Ltd Work execution method for continuous underground wall
JP2004308129A (en) * 2003-04-02 2004-11-04 Toda Constr Co Ltd Construction method of diaphragm wall
JP2007016507A (en) * 2005-07-08 2007-01-25 Taisei Corp Ground improvement method and reinforcing method of existing structural foundation
JP2009102897A (en) * 2007-10-24 2009-05-14 Maeda Corp Method for estimating strength of soil improving body
JP2014136865A (en) * 2013-01-15 2014-07-28 Tokyo Electric Power Co Inc:The Earth-retaining wall and construction method thereof
JP2015094098A (en) * 2013-11-11 2015-05-18 藤井 俊彦 Construction method of ground improvement wall

Patent Citations (13)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US4005582A (en) * 1975-08-12 1977-02-01 Icos Corporation Of America Method of constructing underground concrete walls and reinforcement cage therefor
JPS5854124A (en) * 1981-09-24 1983-03-31 Ohbayashigumi Ltd Constructing method for preliminary underground wall preceding excavation of ditch for continuous underground wall
JPS6085117A (en) * 1983-10-14 1985-05-14 Ohbayashigumi Ltd Method of improving ground prior to construction of underground continuous wall
JPH05118032A (en) * 1991-10-25 1993-05-14 Ohbayashi Corp Execution method of continuous underground wall
JPH05321511A (en) * 1992-05-21 1993-12-07 Nippon Steel Corp Construction method for underground vessel in weak ground
JPH06193046A (en) * 1993-10-01 1994-07-12 Yoshinobu Koiwa Pit construction method
JPH0931972A (en) * 1995-07-25 1997-02-04 Ohbayashi Corp Construction of underground continuous wall
JPH11280060A (en) * 1998-03-31 1999-10-12 Tone Geo Tech Co Ltd Work execution method for continuous underground wall
JP2004308129A (en) * 2003-04-02 2004-11-04 Toda Constr Co Ltd Construction method of diaphragm wall
JP2007016507A (en) * 2005-07-08 2007-01-25 Taisei Corp Ground improvement method and reinforcing method of existing structural foundation
JP2009102897A (en) * 2007-10-24 2009-05-14 Maeda Corp Method for estimating strength of soil improving body
JP2014136865A (en) * 2013-01-15 2014-07-28 Tokyo Electric Power Co Inc:The Earth-retaining wall and construction method thereof
JP2015094098A (en) * 2013-11-11 2015-05-18 藤井 俊彦 Construction method of ground improvement wall

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2021067120A (en) * 2019-10-25 2021-04-30 鹿島建設株式会社 Construction method of underground continuous wall
JP7248558B2 (en) 2019-10-25 2023-03-29 鹿島建設株式会社 How to build a diaphragm wall
CN114855818A (en) * 2022-05-23 2022-08-05 中铁二十局集团第一工程有限公司 High-pressure rotary spraying reinforcement method for double-row narrow-distance ground wall
CN114855818B (en) * 2022-05-23 2023-09-12 中铁二十局集团第一工程有限公司 Double-row narrow-distance ground wall high-pressure rotary spraying reinforcement method

Also Published As

Publication number Publication date
JP6378652B2 (en) 2018-08-22

Similar Documents

Publication Publication Date Title
JP6343445B2 (en) Construction method of earth retaining wall
JP6517133B2 (en) Pile construction method
JP4520913B2 (en) Ground improvement method and existing structure foundation reinforcement method
JP6378652B2 (en) Underground continuous wall construction method
JP6576230B2 (en) Rotating cap, ready-made pile burying device, pile foundation construction method
JP4234120B2 (en) Facility method for underground wall
JP6753768B2 (en) How to remove slime on cast-in-place concrete piles
US9181673B2 (en) Tools and methods for constructing large diameter underground piles
JP5015558B2 (en) Fiber reinforced cement ground improvement method
JP5189946B2 (en) Pile hole drilling method
JP2017089319A (en) Vertical shaft construction method
JP4550792B2 (en) Construction method of underground wall
JP2005282063A (en) Composite field preparation pile, its construction method and device for preparing composite field preparation pile
JP6162356B1 (en) Method for excavating pile bottom sediment and stirring in hole and rotary table device used therefor
JP2014163213A (en) Removal method for existing pile
JP5284168B2 (en) Excavation member for earth retaining member construction and earth retaining member construction method
JP5253963B2 (en) Excavation method and pile construction method
JP4074198B2 (en) How to remove existing piles
JP2007285064A (en) Construction method of foundation pile
JP5506880B2 (en) Pile construction method
JPS59195925A (en) Construction of on-site concrete pile
JP4072686B2 (en) Multi-axis high-pressure jet agitating ground improvement device and method
JP3471742B2 (en) Continuous underground wall construction method
JP2016079745A (en) Drilling method and construction method for cast-in-place pile
JP6634251B2 (en) Pile foundation structure, ready-made pile burying device, method of constructing pile foundation structure using said ready-made pile burying device

Legal Events

Date Code Title Description
A621 Written request for application examination

Free format text: JAPANESE INTERMEDIATE CODE: A621

Effective date: 20171116

A977 Report on retrieval

Free format text: JAPANESE INTERMEDIATE CODE: A971007

Effective date: 20180709

TRDD Decision of grant or rejection written
A01 Written decision to grant a patent or to grant a registration (utility model)

Free format text: JAPANESE INTERMEDIATE CODE: A01

Effective date: 20180717

A61 First payment of annual fees (during grant procedure)

Free format text: JAPANESE INTERMEDIATE CODE: A61

Effective date: 20180727

R150 Certificate of patent or registration of utility model

Ref document number: 6378652

Country of ref document: JP

Free format text: JAPANESE INTERMEDIATE CODE: R150

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250