JP2014211051A - Underground structure, and method for reconstructing building structure having underground skeleton - Google Patents

Underground structure, and method for reconstructing building structure having underground skeleton Download PDF

Info

Publication number
JP2014211051A
JP2014211051A JP2013088248A JP2013088248A JP2014211051A JP 2014211051 A JP2014211051 A JP 2014211051A JP 2013088248 A JP2013088248 A JP 2013088248A JP 2013088248 A JP2013088248 A JP 2013088248A JP 2014211051 A JP2014211051 A JP 2014211051A
Authority
JP
Japan
Prior art keywords
existing
underground
strut
new
rebuilding
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
JP2013088248A
Other languages
Japanese (ja)
Other versions
JP6229294B2 (en
Inventor
奥田 和弘
Kazuhiro Okuda
和弘 奥田
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Obayashi Corp
Original Assignee
Obayashi Corp
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Obayashi Corp filed Critical Obayashi Corp
Priority to JP2013088248A priority Critical patent/JP6229294B2/en
Publication of JP2014211051A publication Critical patent/JP2014211051A/en
Application granted granted Critical
Publication of JP6229294B2 publication Critical patent/JP6229294B2/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D29/00Independent underground or underwater structures; Retaining walls
    • E02D29/04Making large underground spaces, e.g. for underground plants, e.g. stations of underground railways; Construction or layout thereof
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D31/00Protective arrangements for foundations or foundation structures; Ground foundation measures for protecting the soil or the subsoil water, e.g. preventing or counteracting oil pollution
    • E02D31/10Protective arrangements for foundations or foundation structures; Ground foundation measures for protecting the soil or the subsoil water, e.g. preventing or counteracting oil pollution against soil pressure or hydraulic pressure
    • E02D31/12Protective arrangements for foundations or foundation structures; Ground foundation measures for protecting the soil or the subsoil water, e.g. preventing or counteracting oil pollution against soil pressure or hydraulic pressure against upward hydraulic pressure

Abstract

PROBLEM TO BE SOLVED: To suppress the occurrence of bottom base floating and bottom base swelling of an existing underground skeleton and to reduce construction cost when a building structure having an underground skeleton is reconstructed.SOLUTION: An underground structure 10 during reconstruction of a building structure having an underground skeleton includes: an existing bottom base 22 and existing walls 24 remaining in an underground without being demolished; existing pillars 26 remaining in an underground without being demolished except a part of an upper side; newly constructed piles 32 installed downward from an existing bottom base 22; newly constructed inverted pillars 34 with bottom edges thereof buried in the newly constructed piles 32, respectively; and temporary angle braces 40 connecting the existing pillars 26 and the newly constructed inverted pillars 34 respectively to each other so that force can be transmitted therebetween.

Description

本発明は、地下躯体を有する建造物の建替時の地下構造、及び地下躯体を有する建造物の建替え方法に関する。   The present invention relates to an underground structure at the time of rebuilding a building having an underground frame, and a method for rebuilding a building having an underground frame.

地下躯体を有する建造物を建替える方法として、既存の地下躯体の壁や底盤を残置して新設の地下躯体を構築する方法が知られている(例えば、特許文献1参照)。特許文献1に記載の方法では、既設の地下躯体の下方に位置する被圧帯水層からの水圧で既存の底盤が浮き上がったり盤ぶくれ現象が生じたりすることを抑える目的で、既存の底盤から下方に杭を打設してその上部にメガトラスの柱を取り付け、メガトラスの梁と既存の底盤との間に突っ張り部材としての逆打ち支柱を設置し、この状態で、既存の柱や梁を解体して新設の地下躯体を構築する。これにより、底盤に作用する水圧に対して、地下躯体の重量と杭の引抜き抵抗力とによってバランスがとられ、既存の底盤の浮き上がりや盤ぶくれ現象の発生が抑えられる。   As a method of rebuilding a building having an underground structure, a method of constructing a new underground structure by leaving the walls and bottom of an existing underground structure is known (for example, see Patent Document 1). In the method described in Patent Document 1, the existing bottom plate is used for the purpose of suppressing the existing bottom plate from being lifted or caused by the water pressure from the pressurized aquifer located below the existing underground structure. A pile of pillars is laid from the bottom and a mega truss pillar is attached to the top of the pile. A counter strut as a strut member is installed between the mega truss beam and the existing bottom plate. Dismantle and build a new underground structure. This balances against the water pressure acting on the bottom plate by the weight of the underground frame and the pull-out resistance of the piles, and suppresses the occurrence of the existing bottom plate lift and overburden phenomenon.

特許第3761307号公報Japanese Patent No. 3761307

特許文献1に記載の方法では、逆打ち支柱が既存の柱の間に設置されるため、逆打ち支柱の荷重が、既存の底盤のスラブ等の低強度の箇所に作用する。そのため、既存の底盤に対して大掛かりな補強をする必要があり、施工コストが増加する。   In the method described in Patent Document 1, since the striking struts are installed between the existing pillars, the load of the striking struts acts on a low-strength portion such as a slab of the existing bottom panel. For this reason, it is necessary to reinforce the existing bottom plate, which increases the construction cost.

本発明は、上記事情に鑑みてなされたものであり、地下躯体を有する建造物を建替える際に、既存の地下躯体の底盤の浮き上がりや盤ぶくれ減少の発生を抑えると共に、施工コストを低減することを課題にするものである。   The present invention has been made in view of the above circumstances, and when reconstructing a building having an underground skeleton, it suppresses the occurrence of floating of the bottom of the existing underground skeleton and the reduction of board bulge and reduces the construction cost. It is a task to do.

上記課題を解決するために、本発明に係る地下構造は、地下躯体を有する建造物の建替時の地下構造であって、解体されずに地下に残置された既存の底盤及び地中壁と、上側の一部を除いて解体されずに地下に残置された既存の柱と、前記既存の底盤から下方に打設された新設の杭と、前記新設の杭に下端が埋設された新設の逆打ち支柱と、前記既存の柱と前記新設の逆打ち支柱とを力の伝達ができるように連結する力伝達部材とを備えることを特徴とする。   In order to solve the above problems, an underground structure according to the present invention is an underground structure at the time of rebuilding a building having an underground skeleton, and an existing bottom plate and an underground wall left underground without being dismantled. , Existing pillars left in the basement without being dismantled except for a part on the upper side, a new pile driven downward from the existing bottom plate, and a new pile whose lower end is buried in the new pile It is provided with a reverse strut, and a force transmission member that connects the existing pillar and the newly installed reverse strut so as to be able to transmit force.

前記地下構造において、前記力伝達部材は、前記既存の柱の上端と前記新設の逆打ち支柱との間に仮設された仮設方づえであってもよい。   In the underground structure, the force transmission member may be a temporary arrangement temporarily provided between an upper end of the existing column and the newly installed strut strut.

また、本発明に係る建替え方法は、地下躯体を有する建造物を、既存の底盤及び地中壁を地下に残置して建替える方法であって、既存の柱を上側の一部を除いて解体せずに地下に残置し、新設の杭を前記既存の底盤から下方に打設し、新設の逆打ち支柱をその下端が前記新設の杭に埋設されるように建入れ、前記既存の柱と前記新設の逆打ち支柱とを力伝達部材で力の伝達ができるように連結することを特徴とする。   Further, the rebuilding method according to the present invention is a method of rebuilding a building having an underground frame by leaving the existing bottom plate and underground wall in the basement, and excluding a part of the upper side of the existing column. Leave the basement in the basement without dismantling, place the new pile downward from the existing bottom plate, and install the new counter-strut strut so that its lower end is buried in the new pile. And the newly-provided striking strut are connected so that force can be transmitted by a force transmitting member.

前記建替え方法において、前記力伝達部材としての仮設方づえを、前記既存の柱の上端と前記新設の逆打ち支柱との間に仮設してもよい。   In the rebuilding method, a temporary arrangement as the force transmission member may be temporarily provided between an upper end of the existing column and the newly installed striking strut.

また、前記建替え方法において、少なくとも前記地下躯体の解体開始から前記力伝達部材で前記既存の柱と前記新設の逆打ち支柱とを連結するまでの間、前記地下躯体の内側に、地下水の揚圧力に抵抗する重量物を入れてもよい。   Further, in the rebuilding method, at least during the period from the start of dismantling of the underground structure to the connection of the existing pillar and the newly installed striking strut with the force transmission member, the underground water is pumped inside the underground structure. A heavy object that resists pressure may be added.

本発明によれば、地下躯体を有する建造物を建替える際に、既存の地下躯体の底盤の浮き上がりや盤ぶくれ減少の発生を抑えると共に、施工コストを低減することができる。   ADVANTAGE OF THE INVENTION According to this invention, when rebuilding the building which has an underground skeleton, while raising the bottom of the existing underground skeleton and generation | occurrence | production of board bulge reduction can be suppressed, construction cost can be reduced.

一実施形態に係る地下構造の概略構成を示す立断面図である。It is an elevation sectional view showing a schematic structure of an underground structure according to an embodiment. 地下部分を有するビルの建替えの手順を示す立断面図である。It is an elevation sectional view showing the procedure of rebuilding a building having an underground part. 地下部分を有するビルの建替えの手順を示す立断面図である。It is an elevation sectional view showing the procedure of rebuilding a building having an underground part. 地下部分を有するビルの建替えの手順を示す立断面図である。It is an elevation sectional view showing the procedure of rebuilding a building having an underground part. 地下部分を有するビルの建替えの手順を示す立断面図である。It is an elevation sectional view showing the procedure of rebuilding a building having an underground part. 地下部分を有するビルの建替えの手順を示す立断面図である。It is an elevation sectional view showing the procedure of rebuilding a building having an underground part. 地下部分を有するビルの建替えの手順を示す立断面図である。It is an elevation sectional view showing the procedure of rebuilding a building having an underground part. 地下部分を有するビルの建替えの手順を示す立断面図である。It is an elevation sectional view showing the procedure of rebuilding a building having an underground part. 地下部分を有するビルの建替えの手順を示す立断面図である。It is an elevation sectional view showing the procedure of rebuilding a building having an underground part.

以下、本発明の一実施形態を、図面を参照しながら説明する。図1は、一実施形態に係る地下構造10の概略構成を示す立断面図である。本実施形態に係る地下構造10は、地下部分を有するビルの建替え時の地下部分の構造である。この図に示すように、地下構造10は帯水層1に位置するため、地下構造10には揚圧力Pが作用する。また、地下構造10の下方には粘土層2を介して被圧帯水層3が存在するため、地下構造10の下方の地盤には被圧水の水圧が作用している。   Hereinafter, an embodiment of the present invention will be described with reference to the drawings. FIG. 1 is an elevational sectional view showing a schematic configuration of an underground structure 10 according to an embodiment. The underground structure 10 according to the present embodiment is a structure of an underground part at the time of rebuilding a building having an underground part. As shown in this figure, since the underground structure 10 is located in the aquifer 1, the lifting pressure P acts on the underground structure 10. In addition, since the pressurized aquifer 3 exists below the underground structure 10 via the clay layer 2, the water pressure of the pressurized water acts on the ground below the underground structure 10.

地下構造10は、解体されずに残置された既存躯体20と、既存躯体20の内側に構築された新設躯体30とを備えている。既存躯体20は、既存底盤22と、既存壁24と、既存柱26とを備えている。また、新設躯体30は、逆打ち支柱34と、新設梁36と、新設スラブ37とを備えている。逆打ち支柱34は、新設の杭32に支持されている。   The underground structure 10 includes an existing case 20 that is left without being dismantled, and a new case 30 that is built inside the existing case 20. The existing frame 20 includes an existing bottom plate 22, an existing wall 24, and an existing column 26. In addition, the new housing 30 includes a reverse strut 34, a new beam 36, and a new slab 37. The counter strut 34 is supported by a newly installed pile 32.

既存底盤22は、基礎スラブ22Aと、基礎スラブ22A上に縦横に構築された基礎梁22Bと、基礎梁22B上に構築されたスラブ22Cとを備えている。また、既存壁24は、地下構造10を構築する地下空間の全周を囲った地中壁であり、周囲の地盤の土圧を受けている。既存柱26は、グランドレベルGLから所定長さだけ解体されてその下側は残置されている。ここで、既存柱26は、縦横の基礎梁22Bが交差した部分(仕口部)に接合されており、当該部分に既存柱26から荷重が作用している。   The existing bottom plate 22 includes a foundation slab 22A, a foundation beam 22B constructed vertically and horizontally on the foundation slab 22A, and a slab 22C constructed on the foundation beam 22B. The existing wall 24 is an underground wall that surrounds the entire circumference of the underground space that constructs the underground structure 10 and receives the earth pressure of the surrounding ground. The existing pillar 26 is disassembled by a predetermined length from the ground level GL, and the lower side is left behind. Here, the existing column 26 is joined to a portion (a joint portion) where the vertical and horizontal foundation beams 22B intersect, and a load is applied to the portion from the existing column 26.

杭32は、鉄筋コンクリート造の多段拡径杭であり、基礎底盤22のスラブ22C及び基礎スラブ22Aを貫通して被圧帯水層3まで打設されている。この杭32の被圧帯水層3に位置する部分に拡底部32A及び複数段の拡径部32Bが設けられており、これらにより杭32の引抜き抵抗力Rが増大されている。また、逆打ち支柱34は、杭32に下端が埋設されて地上まで延びる鉄骨の柱であり、杭32に逆打ち支柱34から荷重が作用している。また、新設梁36は、逆打ち支柱34間に架設された鉄骨の梁である。   The pile 32 is a reinforced concrete multi-stage enlarged pile, and is pierced to the pressurized aquifer 3 through the slab 22C and the foundation slab 22A of the foundation bottom board 22. An expanded bottom portion 32A and a plurality of stages of expanded diameter portions 32B are provided in a portion of the pile 32 located in the pressured aquifer 3, and the pulling resistance force R of the pile 32 is increased thereby. The striking strut 34 is a steel column having a lower end embedded in the pile 32 and extending to the ground, and a load acts on the pile 32 from the striking strut 34. The new beam 36 is a steel beam erected between the counter struts 34.

また、既存柱26の上端と、逆打ち支柱34と新設梁36との仕口部との間には、架設方づえ40が設置されている。この仮設方づえ40は、各既存柱26毎に複数ずつ設けられた鉄骨部材であり、各仮設方づえ40は、既存柱26の上端と、逆打ち支柱34と新設梁36との仕口部との間に両者間で力を伝達できるように設けられている。本実施形態では、既存柱26の上端に新設梁36がモルタルで結合され、当該新設梁36と仮設方づえ40の一端、仮設方づえ40の他端と上記仕口部は、ボルト等で結合されている。   In addition, an erection method 40 is installed between the upper end of the existing column 26 and the joint portion between the counter-strike column 34 and the new beam 36. The temporary arrangement 40 is a steel member provided for each of the existing columns 26, and each temporary arrangement 40 has a joint between the upper end of the existing column 26, the back strut 34 and the new beam 36. It is provided so that force can be transmitted between the two. In the present embodiment, a new beam 36 is connected to the upper end of the existing column 26 with mortar, and the new beam 36 and one end of the temporary setting 40, and the other end of the temporary setting 40 and the above-mentioned joint portion are connected with a bolt or the like. Has been.

以上のような構成の地下構造10では、解体されることにより軽量化された既存躯体20の重量が揚圧力Pより小さいことによって、既存底盤22、既存柱26及び仮設方づえ40を介して逆打ち支柱34に引抜力Qが作用する。それに対して、杭32には地盤から引抜き抵抗力Rが生じる。この引抜き抵抗力Rと引抜力Qとのバランスが取れるように、杭32の径、打設深さや拡底部32A及び多段の拡径部32Bの寸法等が設定されている。   In the underground structure 10 having the above-described configuration, the weight of the existing frame 20 that has been reduced in weight by being disassembled is smaller than the lifting pressure P, so that it is reversed via the existing bottom plate 22, the existing column 26, and the temporary arrangement 40. A pulling force Q acts on the strut 34. On the other hand, the pulling resistance force R is generated in the pile 32 from the ground. The diameter of the pile 32, the placement depth, the dimensions of the expanded bottom portion 32A and the multistage expanded portion 32B, and the like are set so that the drawing resistance force R and the drawing force Q can be balanced.

図2〜図9は、地下部分を有するビル100の建替えの手順を示す立断面図である。図2に示すように、既存建造物としてのビル100の地下部分には、上記既存躯体20の既存底盤22、既存壁24、及び既存柱26に加えて既存梁27及び既存スラブ28が存在する。   2 to 9 are elevational sectional views showing a procedure for rebuilding the building 100 having an underground portion. As shown in FIG. 2, an existing beam 27 and an existing slab 28 exist in addition to the existing bottom plate 22, existing wall 24, and existing column 26 of the existing frame 20 in the underground portion of the building 100 as an existing building. .

まず、図3に示すように、既存スラブ28(図2参照)を解体する。また、既存躯体20の内側を土砂で埋める。そして、既存底盤22に杭32を貫通させるための孔をあける。ここで、既存底盤22の基礎スラブ22A、基礎梁22B、スラブ22Cで囲まれた空間には鉄筋が配筋され、コンクリートが充填されており、開口周辺の補強が行われている。図4に示すように、杭32を打設して逆打ち支柱34を建入れする。杭32を打設する工程では、下部に拡底部32A及び複数段の拡径部32Bを構築する。また、逆打ち支柱34を建入れする工程では、逆打ち支柱34の下端をコンクリートが硬化前の杭32の頭部に挿入する。   First, as shown in FIG. 3, the existing slab 28 (see FIG. 2) is disassembled. The inside of the existing housing 20 is filled with earth and sand. And the hole for making the pile 32 penetrate the existing bottom board 22 is made. Here, reinforcing bars are arranged in the space surrounded by the foundation slab 22A, the foundation beam 22B, and the slab 22C of the existing bottom board 22, and the surroundings of the opening are reinforced. As shown in FIG. 4, the pile 32 is driven and the back strut 34 is erected. In the step of placing the pile 32, a bottom expanded portion 32A and a plurality of stages of expanded diameter portions 32B are constructed in the lower portion. Moreover, in the process of erection the back strut 34, the lower end of the back strut 34 is inserted into the head of the pile 32 before the concrete is hardened.

次に、図5及び図6に示すように、既存躯体20を地上側から解体すると共に、逆打ち工法により新設躯体30を地上側から構築する。この工程では、既存躯体20の内側を各階の既存梁27が表出するまで掘り起こし、表出した既存梁27を既存柱26から切断し、既存柱26の表出した部分を切断する。ここで、既存壁24は解体せずに残置して山留め壁とする。そして、解体が終了した階に新設梁36を架設し、新設スラブ37を構築する。このような解体作業と、逆打ち工法による新設躯体30の構築作業とを所定階まで繰り返す。   Next, as shown in FIGS. 5 and 6, the existing housing 20 is disassembled from the ground side, and the new housing 30 is constructed from the ground side by a reverse driving method. In this step, the inside of the existing frame 20 is dug up until the existing beam 27 on each floor is exposed, the existing beam 27 that is exposed is cut from the existing column 26, and the exposed portion of the existing column 26 is cut. Here, the existing wall 24 is left without being dismantled to form a retaining wall. Then, a new beam 36 is installed on the floor where the dismantling is completed, and a new slab 37 is constructed. Such dismantling work and the construction work of the new housing 30 by the reverse driving method are repeated up to a predetermined floor.

ここで、既存躯体20の内側の土砂は、揚圧力Pに対してバランスを取るためのウエイトであり、解体作業を進める上記所定階、即ち既存躯体20の内側の土砂を掘り起こす深さは、解体途中の既存躯体20の重量と揚圧力Pとの差を考慮して設定する。   Here, the earth and sand inside the existing chassis 20 is a weight for balancing against the lifting pressure P, and the above-mentioned predetermined floor where the dismantling work is performed, that is, the depth at which the sand inside the existing chassis 20 is dug is It sets in consideration of the difference between the weight of the existing housing 20 on the way and the lifting pressure P.

次に、図7に示すように、各既存柱26毎に複数の仮設方づえ40を設置する。この工程では、新設梁36を既存柱26の上端にモルタルで結合し、当該新設梁26に各仮設方づえ40の一端を、各仮設方づえ40の他端を逆打ち支柱34と新設梁36との仕口部にボルト等で接続する。これにより、逆打ち支柱34に作用する引抜力Qと杭32に地盤から作用する引抜き抵抗力Rとのバランスが取れ、既存躯体20の揚圧力Pによる浮き上がりや、被圧水の水圧による地盤の盤ぶくれ現象が抑えられる。   Next, as shown in FIG. 7, a plurality of temporary arrangements 40 are installed for each existing pillar 26. In this step, the new beam 36 is connected to the upper end of the existing column 26 with mortar, and one end of each temporary setting 40 is connected to the new beam 26, and the other end of each temporary setting 40 is inverted to the strut 34 and the new beam 36. Connect to the joint with bolts. As a result, the pulling force Q acting on the back strut 34 and the pulling resistance force R acting on the pile 32 from the ground can be balanced, and the existing frame 20 can be lifted by the lifting pressure P or the ground pressure by the water pressure of the pressurized water. The blistering phenomenon is suppressed.

そこで、図8に示すように、上記所定階から最下階までの既存躯体20の解体作業と新設躯体30の構築作業とを実施する。この工程では、新設底盤38を構築して該新設底盤38と杭32の頭部と接合する。これにより、既存底盤22を介して新設躯体30に作用する揚圧力Pと、それに抵抗する新設躯体30等の重量及び杭32に地盤から作用する引抜き抵抗力Rとのバランスが取れ、新設躯体30の揚圧力Pによる浮き上がりや、被圧水の水圧による地盤の盤ぶくれ現象が抑えられる。そのため、図9に示すように、仮設方づえ40の撤去と既存柱26の解体とが可能になる。   Therefore, as shown in FIG. 8, the dismantling work of the existing housing 20 and the construction work of the new housing 30 are performed from the predetermined floor to the lowest floor. In this step, the new bottom board 38 is constructed and joined to the new bottom board 38 and the head of the pile 32. As a result, the balance between the lifting pressure P acting on the new frame 30 via the existing bottom plate 22 and the weight of the new frame 30 and the like resisting it and the pulling resistance R acting on the pile 32 from the ground can be achieved. Therefore, it is possible to suppress the floating due to the lifting pressure P and the ground bulging phenomenon due to the water pressure of the pressurized water. Therefore, as shown in FIG. 9, it is possible to remove the temporary arrangement 40 and dismantle the existing pillar 26.

以上説明したように、本実施形態に係る建替え方法では、既存柱26を上側の一部を除いて解体せずに地下に残置し、新設の杭32を既存底盤22から下方に打設し、新設の逆打ち支柱34をその下端が新設の杭32に埋設されるように建入れ、既存柱26と新設の逆打ち支柱34とを仮設方づえ40で力の伝達ができるように連結する。これによって、既存躯体20に作用する揚圧力Pと、それに抵抗する既存躯体20の重量及び杭32に地盤から作用する引抜き抵抗力Rとのバランスを取ることができる。従って、既存躯体20の揚圧力Pによる浮き上がりや、被圧水の水圧による地盤の盤ぶくれ現象を抑えた状態で、最下階まで既存躯体20の解体作業と新設躯体30の構築作業とを実施できる。   As described above, in the rebuilding method according to the present embodiment, the existing pillar 26 is left in the basement without being dismantled except for a part on the upper side, and the new pile 32 is driven downward from the existing bottom board 22. The newly installed counter strut 34 is erected so that the lower end is embedded in the new pile 32, and the existing pillar 26 and the new counter strut 34 are connected so that force can be transmitted by the temporary arrangement 40. . This makes it possible to balance the lifting pressure P acting on the existing housing 20 with the weight of the existing housing 20 resisting it and the pulling resistance R acting on the pile 32 from the ground. Therefore, the dismantling work of the existing housing 20 and the construction work of the new housing 30 are performed up to the lowest floor in a state where the lifting of the existing housing 20 due to the lifting pressure P and the ground bulging phenomenon due to the water pressure of the pressurized water are suppressed. Can be implemented.

ここで、既存柱26を介して既存底盤22から逆打ち支柱34に荷重が伝達されるように構成したことによって、既存柱26と既存底盤22との接合部には大きな耐力が要求されるが、当該部分は、縦横の基礎梁22Bと既存柱26とが交差した仕口部であり、元々大きな荷重に耐えるように構築されている。従って、既存底盤22の補強を不要もしくは減らすことができ、施工コストを低減できる。   Here, since a load is transmitted from the existing bottom plate 22 to the counter strut 34 through the existing column 26, a large proof stress is required at the joint between the existing column 26 and the existing bottom plate 22. The part is a joint portion where the vertical and horizontal foundation beams 22B intersect with the existing columns 26, and is originally constructed to withstand a large load. Therefore, the reinforcement of the existing bottom board 22 can be omitted or reduced, and the construction cost can be reduced.

また、既存躯体20の浮き上がりや盤ぶくれ現象の抑制を目的として、既存躯体20に揚圧力Pが作用しないように、既存躯体20の下方の地盤を遮水壁で囲むという方法が知られている。この方法では、薬液注入工法等により遮水壁を構築するため、施工コストが高くなる。それに対して、本実施形態に係る方法では、解体する既存柱26、本設の杭32、逆打ち支柱34や仮設方づえ40によって、既存躯体20の浮き上がりや盤ぶくれ現象を抑制することができるため、遮水壁を構築する方法に比して施工コストを低減できる。特に、仮設材は仮設方づえ40のみであり、その他は、解体する既存柱26、本設の杭32、逆打ち支柱34であるため、施工コストの低減の効果は大きい。   Further, for the purpose of suppressing the lifting of the existing chassis 20 and the board bulging phenomenon, a method of surrounding the ground below the existing chassis 20 with a water shielding wall is known so that the lifting pressure P does not act on the existing chassis 20. Yes. In this method, since the impermeable wall is constructed by a chemical solution injection method or the like, the construction cost increases. On the other hand, in the method according to the present embodiment, the existing column 26 to be dismantled, the main pile 32, the counter strut 34, and the temporary arrangement 40 can suppress the lifting of the existing frame 20 and the phenomenon of board bulge. Therefore, the construction cost can be reduced as compared with the method of constructing the water shielding wall. In particular, the temporary material is only the temporary arrangement 40, and the other is the existing pillar 26 to be disassembled, the main pile 32, and the counter strut 34, and thus the effect of reducing the construction cost is great.

また、本実施形態に係る建替え方法では、少なくとも既存躯体20の解体開始から仮設方づえ40で既存柱26と逆打ち支柱34とを連結するまでの間、既存躯体20の内側に、地下水の揚圧力Pに抵抗する重量物たる土砂を入れる。これによって、既存躯体20の解体開始から仮設方づえ40で既存柱26と逆打ち支柱34とを連結するまでの間、揚水力Pによる既存躯体20の浮き上がりや盤ぶくれ現象の発生を抑制できる。   Further, in the rebuilding method according to the present embodiment, at least the groundwater is placed inside the existing housing 20 from the start of the dismantling of the existing housing 20 until the existing pillar 26 and the counter strut 34 are connected with the temporary arrangement 40. Put heavy earth and sand that resists lifting pressure P. Thereby, from the start of the dismantling of the existing housing 20 to the connection of the existing pillar 26 and the counter strut 34 with the temporary arrangement 40, it is possible to suppress the occurrence of the lifting of the existing housing 20 due to the pumping force P and the occurrence of the blistering phenomenon. .

なお、上述の実施形態は、本発明の理解を容易にするためのものであり、本発明を限定するものではない。本発明はその趣旨を逸脱することなく、変更、改良され得ると共に本発明にはその等価物が含まれることは勿論である。例えば、上述の実施形態では、仮設方づえ40を用いたが、既存柱26と逆打ち支柱34との間で荷重を伝達できるものであれば、ブレース等の他の部材、構造を用いることができる。   In addition, the above-mentioned embodiment is for making an understanding of this invention easy, and does not limit this invention. It goes without saying that the present invention can be changed and improved without departing from the gist thereof, and that the present invention includes equivalents thereof. For example, in the above-described embodiment, the temporary arrangement 40 is used. However, other members and structures such as braces may be used as long as the load can be transmitted between the existing pillar 26 and the counter strut 34. it can.

1 帯水層、2 粘土層、3 被圧帯水層、10 地下構造、20 既存躯体、22 既存底盤、22A 基礎スラブ、22B 基礎梁、22C スラブ、24 既存壁、26 既存柱、27 既存梁、28 既存スラブ、30 新設躯体、32 杭、32A 拡底部、32B 拡径部、34 逆打ち支柱、36 新設梁、37 新設スラブ、38 新設底盤、40 仮設方づえ、100 ビル 1 aquifer, 2 clay layer, 3 aquifer, 10 underground structure, 20 existing frame, 22 existing bottom, 22A foundation slab, 22B foundation beam, 22C slab, 24 existing wall, 26 existing column, 27 existing beam , 28 Existing slab, 30 New housing, 32 Pile, 32A Expanded bottom, 32B Expanded diameter, 34 Reverse strut, 36 New beam, 37 New slab, 38 New bottom, 40 Temporary arrangement, 100 Building

Claims (5)

地下躯体を有する建造物の建替時の地下構造であって、
解体されずに地下に残置された既存の底盤及び地中壁と、
上側の一部を除いて解体されずに地下に残置された既存の柱と、
前記既存の底盤から下方に打設された新設の杭と、
前記新設の杭に下端が埋設された新設の逆打ち支柱と、
前記既存の柱と前記新設の逆打ち支柱とを力の伝達ができるように連結する力伝達部材と
を備える地下構造。
An underground structure at the time of rebuilding a building having an underground frame,
The existing bottom and underground walls left underground without being dismantled;
Existing pillars left in the basement without being dismantled except for a part on the upper side,
A new pile driven downward from the existing bottom plate,
A new striking strut with a lower end embedded in the new pile;
An underground structure comprising: a force transmission member that couples the existing pillar and the newly installed counter-strut so that force can be transmitted.
前記力伝達部材は、前記既存の柱の上端と前記新設の逆打ち支柱との間に仮設された仮設方づえである請求項1に記載の地下構造。   2. The underground structure according to claim 1, wherein the force transmission member is a temporary arrangement temporarily installed between an upper end of the existing column and the newly-arranged striking strut. 3. 地下躯体を有する建造物を、既存の底盤及び地中壁を地下に残置して建替える方法であって、
既存の柱を上側の一部を除いて解体せずに地下に残置し、
新設の杭を前記既存の底盤から下方に打設し、
新設の逆打ち支柱をその下端が前記新設の杭に埋設されるように建入れ、
前記既存の柱と前記新設の逆打ち支柱とを力伝達部材で力の伝達ができるように連結する建替え方法。
A method of rebuilding a building having an underground structure by leaving the existing bottom and underground walls underground.
Leave the existing pillars in the basement without dismantling except for the upper part,
A new pile is driven downward from the existing bottom plate,
A newly installed strut is installed so that its lower end is buried in the new pile,
A rebuilding method in which the existing pillar and the newly installed striking strut are coupled so that force can be transmitted by a force transmission member.
前記力伝達部材としての仮設方づえを、前記既存の柱の上端と前記新設の逆打ち支柱との間に仮設する請求項3に記載の建替え方法。   The rebuilding method according to claim 3, wherein a temporary arrangement as the force transmission member is temporarily installed between an upper end of the existing column and the newly-turned strut. 少なくとも前記地下躯体の解体開始から前記力伝達部材で前記既存の柱と前記新設の逆打ち支柱とを連結するまでの間、前記地下躯体の内側に、地下水の揚圧力に抵抗する重量物を入れる請求項3又は請求項4に記載の建替え方法。   At least a heavy object that resists the groundwater uplift pressure is placed inside the underground frame from the start of dismantling of the underground frame to the connection between the existing column and the newly installed striking strut with the force transmission member. The rebuilding method according to claim 3 or claim 4.
JP2013088248A 2013-04-19 2013-04-19 Method of rebuilding a structure having an underground structure and underground structure Active JP6229294B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP2013088248A JP6229294B2 (en) 2013-04-19 2013-04-19 Method of rebuilding a structure having an underground structure and underground structure

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP2013088248A JP6229294B2 (en) 2013-04-19 2013-04-19 Method of rebuilding a structure having an underground structure and underground structure

Publications (2)

Publication Number Publication Date
JP2014211051A true JP2014211051A (en) 2014-11-13
JP6229294B2 JP6229294B2 (en) 2017-11-15

Family

ID=51930991

Family Applications (1)

Application Number Title Priority Date Filing Date
JP2013088248A Active JP6229294B2 (en) 2013-04-19 2013-04-19 Method of rebuilding a structure having an underground structure and underground structure

Country Status (1)

Country Link
JP (1) JP6229294B2 (en)

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2016199915A (en) * 2015-04-10 2016-12-01 株式会社竹中工務店 Foundation structure and foundation construction method
JP2017186820A (en) * 2016-04-07 2017-10-12 鹿島建設株式会社 Forming method of pile and pile
JP2022028077A (en) * 2018-01-24 2022-02-14 株式会社竹中工務店 Inverted construction method

Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH11141140A (en) * 1997-11-06 1999-05-25 Takenaka Komuten Co Ltd Rebuilding method of building
JP2001271499A (en) * 2000-03-24 2001-10-05 Kajima Corp Temporary bearing construction method for existing building by steel batter brace member
JP2001303599A (en) * 2000-04-19 2001-10-31 Shimizu Corp Building demolishing and constructing method and building
JP2009127251A (en) * 2007-11-21 2009-06-11 Takenaka Komuten Co Ltd Rebuilding method of building

Patent Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH11141140A (en) * 1997-11-06 1999-05-25 Takenaka Komuten Co Ltd Rebuilding method of building
JP2001271499A (en) * 2000-03-24 2001-10-05 Kajima Corp Temporary bearing construction method for existing building by steel batter brace member
JP2001303599A (en) * 2000-04-19 2001-10-31 Shimizu Corp Building demolishing and constructing method and building
JP2009127251A (en) * 2007-11-21 2009-06-11 Takenaka Komuten Co Ltd Rebuilding method of building

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2016199915A (en) * 2015-04-10 2016-12-01 株式会社竹中工務店 Foundation structure and foundation construction method
JP2017186820A (en) * 2016-04-07 2017-10-12 鹿島建設株式会社 Forming method of pile and pile
JP2022028077A (en) * 2018-01-24 2022-02-14 株式会社竹中工務店 Inverted construction method
JP7193065B2 (en) 2018-01-24 2022-12-20 株式会社竹中工務店 Reverse construction method

Also Published As

Publication number Publication date
JP6229294B2 (en) 2017-11-15

Similar Documents

Publication Publication Date Title
KR101014796B1 (en) Top-down underground construction method using prefabricated concrete column member as temporary bridge column
KR101205783B1 (en) The complex execution method which dismantling work of existing underground structure and constructs of new building simultaneously
CN203654294U (en) Foundation pit supporting structure used in reverse building method
KR100967497B1 (en) Method for constructing an underground structure
KR20090101985A (en) Self-supporting retaining wall of steel truss
CN203411993U (en) Simple and fast retaining wall
CN103526781A (en) Integrated-tray, shock-insulation and reinforcing structure for historic building foundation and construction method thereof
JP6229294B2 (en) Method of rebuilding a structure having an underground structure and underground structure
CN102220764B (en) Construction method of deep foundation pit bracing system
JP2015055106A (en) Underground structure, and method of reconstructing building structure with underground skeleton
KR101054696B1 (en) Top-down construction method for underground structure with slurry wall retained by slab diaphragm effect
JP2000352296A (en) Method o constructing passage just under underground structure
JP6209911B2 (en) Method of rebuilding a structure having an underground structure and underground structure
JP6768477B2 (en) How to build an underground structure
KR101310677B1 (en) Top down method using precast composite retaining wall and raker in slope
CN112832252B (en) Deep foundation pit supporting construction method with large height difference of two sides
KR100967496B1 (en) Device for constructing an underground structure
JP6461690B2 (en) Foundation structure and foundation construction method
KR102181416B1 (en) method of constructing earthquake-proof ALC house
JP6938198B2 (en) Construction method
RU2581853C1 (en) Method for construction of pile foundation
CN218933149U (en) SMW construction method pile structure
JP2006188862A (en) Construction method of structure, and foundation structure used for the same
JP2012136841A (en) Method for excavating ground under spread foundation of existing building, and base-isolating method for existing building
CN108442406B (en) Semi-reverse construction method foundation pit inner supporting structure and construction method thereof

Legal Events

Date Code Title Description
A621 Written request for application examination

Free format text: JAPANESE INTERMEDIATE CODE: A621

Effective date: 20160318

A977 Report on retrieval

Free format text: JAPANESE INTERMEDIATE CODE: A971007

Effective date: 20170313

A131 Notification of reasons for refusal

Free format text: JAPANESE INTERMEDIATE CODE: A131

Effective date: 20170321

A521 Request for written amendment filed

Free format text: JAPANESE INTERMEDIATE CODE: A523

Effective date: 20170509

TRDD Decision of grant or rejection written
A01 Written decision to grant a patent or to grant a registration (utility model)

Free format text: JAPANESE INTERMEDIATE CODE: A01

Effective date: 20170919

A61 First payment of annual fees (during grant procedure)

Free format text: JAPANESE INTERMEDIATE CODE: A61

Effective date: 20171002

R150 Certificate of patent or registration of utility model

Ref document number: 6229294

Country of ref document: JP

Free format text: JAPANESE INTERMEDIATE CODE: R150