JP2014095282A - Large span concrete slab form and construction method using the same - Google Patents

Large span concrete slab form and construction method using the same Download PDF

Info

Publication number
JP2014095282A
JP2014095282A JP2013050234A JP2013050234A JP2014095282A JP 2014095282 A JP2014095282 A JP 2014095282A JP 2013050234 A JP2013050234 A JP 2013050234A JP 2013050234 A JP2013050234 A JP 2013050234A JP 2014095282 A JP2014095282 A JP 2014095282A
Authority
JP
Japan
Prior art keywords
concrete
floor slab
steel
span
formwork
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
JP2013050234A
Other languages
Japanese (ja)
Other versions
JP6283169B2 (en
Inventor
Daisuke Takeuchi
大輔 竹内
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Yokogawa Sumikin Bridge Co Ltd
Original Assignee
Yokogawa Sumikin Bridge Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Yokogawa Sumikin Bridge Co Ltd filed Critical Yokogawa Sumikin Bridge Co Ltd
Priority to JP2013050234A priority Critical patent/JP6283169B2/en
Publication of JP2014095282A publication Critical patent/JP2014095282A/en
Application granted granted Critical
Publication of JP6283169B2 publication Critical patent/JP6283169B2/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Abstract

PROBLEM TO BE SOLVED: To provide a large span concrete slab form and a construction method using the same capable of omitting a falsework and expediting construction work through a structure which does not cause a fire resistance issue.SOLUTION: A bottom form plate 11 with steel rib materials 12 preliminarily fixed thereto is installed between a road side wall 1a and a central wall 1b without using an extensive falsework. A plurality of lower reinforcing bars 3a extended in a direction orthogonal to a span direction are inserted into each slit 13 on the steel rib material 12 with a space between the reinforcing bars 3a arranged in accordance with bar arrangement design. Other lower reinforcing bars 3b extended in the span direction are arranged on the lower reinforcing bars 3a and fixed thereto with binding wires. After arranging upper reinforcing bars 4a and 4b, concrete 7 is placed and cured. Fire-resistance performance is satisfied not by the bottom form plate 11 alone but by a reinforced concrete slab.

Description

本発明は、例えば掘割道路その他、地下・半地下大空間上部にスラブ厚の大きい大スパンのコンクリート床版を構築する場合に使用可能な大スパンコンクリート床版型枠およびその型枠を用いた大スパン鉄筋コンクリート床版の施工方法に関するものである。   The present invention is, for example, a large-span concrete floor slab form that can be used when constructing a large-span concrete floor slab with a large slab thickness above a large underground space or semi-underground large space, and a large size using the form slab. The present invention relates to a method for constructing a span reinforced concrete slab.

掘割道路や地下・半地下大空間の上部に、例えば500〜1000mmといったスラブ厚の大きいコンクリート床版を構築する場合、コンクリートの打設荷重に耐え得る大がかりな支保工で型枠を支持するのが一般的である。   When building a concrete floor slab with a large slab thickness of 500 to 1000 mm, for example, on the upper part of a digging road or large underground / semi-underground space, the formwork should be supported by a large support that can withstand the concrete loading load. It is common.

しかし、構築される床版下に大がかりな支保工を設置するには長い工期を要し、設置作業も含め支保工のコストが膨大となる他、施工中は支保工を設置した床版下のスペースでの作業が大きく制限されることになる。   However, it takes a long period of time to install a large support work under the floor slab to be built, and the cost of the support work including installation work becomes enormous. Work in space is severely limited.

また、大スパン構造では内空も大きく、支保工の設置や解体のための足場も大がかりとなる。   In addition, the large-span structure has a large inside sky, and a scaffold for the installation and dismantling of support works becomes a major factor.

これに対し、例えば特許文献1、2等に記載された底鋼板を有する鋼コンクリート合成床版を用い、大スパンの床版を支保工なしで架設することが考えられる。   On the other hand, for example, using a steel concrete composite slab having a bottom steel plate described in Patent Documents 1 and 2 and the like, it is conceivable to construct a large-span floor slab without supporting work.

特許第3191569号公報Japanese Patent No. 3119169 特開2008−144459号公報JP 2008-144459 A

上述のように、合成床版は支保工の省略や急速施工が可能であるという利点がある。しかしながら、耐火性が問題となる構造物では、床版の下面に鋼板が露出する鋼コンクリート合成床版は、耐火性の面で使用が制限されることになる。   As described above, the composite floor slab has the advantage that support work can be omitted and rapid construction is possible. However, in a structure in which fire resistance is a problem, the use of a steel-concrete composite floor slab in which the steel plate is exposed on the lower surface of the floor slab is limited in terms of fire resistance.

本発明は、上述のような課題を図ったものであり、耐火性が問題とならない構造での支保工の省略や急速施工を可能とする大スパンコンクリート床版型枠および該床版型枠を用いた施工方法を提供することを目的としたものである。   The present invention is intended to solve the above-described problems, and a large-span concrete floor slab form and a floor slab form that enables rapid construction and omission of support work in a structure in which fire resistance is not a problem. The purpose is to provide the construction method used.

本発明の床版型枠は、柱あるいは壁などの支持構造体上に鉄筋コンクリート床版を打設するための大スパンコンクリート床版型枠であって、型枠底板と、この型枠底板上に並列し、コンクリート打設時の荷重に耐え得るだけの断面剛性を有する複数の鋼製リブ材とを備え、鋼製リブ材のウェブにコンクリート床版に配筋される鉄筋を載置可能なスリットが複数形成されていることを特徴とするものである。   The floor slab form of the present invention is a large-span concrete floor slab form for placing a reinforced concrete floor slab on a support structure such as a column or wall, and the form bottom plate and the form bottom plate A plurality of steel rib members that are parallel to each other and have a cross-sectional rigidity that can withstand the load during concrete placement, and can be used to place the reinforcing bars that are placed on the concrete floor slabs on the steel rib material web A plurality of are formed.

構築される床版は要求される断面合成および強度を備えた鉄筋コンクリート床版としてコンクリート強度や鉄筋の配筋設計がなされる。   The constructed floor slab is designed as a reinforced concrete floor slab with the required cross-sectional composition and strength, and the reinforcement of the reinforcing bar is designed.

型枠底板上に並列させて配置される鋼製リブ材は、コンクリート打設時の荷重に耐え得るだけの断面剛性を有すればよく、断面剛性の確保の面からは帯状鋼板あるいは形鋼が好ましい。   The steel rib material arranged in parallel on the formwork bottom plate only needs to have a cross-sectional rigidity that can withstand the load when placing concrete. preferable.

型枠底板の材質は特に限定されないが、鋼製リブ材を溶接あるいはボルト接合可能であるといった点では鋼板が好ましい。   The material of the mold bottom plate is not particularly limited, but a steel plate is preferable in that a steel rib material can be welded or bolted.

もしくは、型枠底板に、プレキャストコンクリート板(以下、PCa版)を用いてもよい。ここでいうPCa版とは、例えば鉄筋コンクリート板、鉄骨鉄筋コンクリート板、プレストレストコンクリート板、超高強度繊維補強コンクリート板などである。型枠底板にPCa版を用いる場合は、あらかじめ鋼製リブ材をPCa版内部に備えておけばよい(図5(a)参照)。   Or you may use a precast concrete board (henceforth PCa version) for a formwork baseplate. Here, the PCa plate is, for example, a reinforced concrete plate, a steel reinforced concrete plate, a prestressed concrete plate, an ultrahigh strength fiber reinforced concrete plate, or the like. When the PCa plate is used for the formwork bottom plate, a steel rib material may be provided in the PCa plate in advance (see FIG. 5 (a)).

この場合、PCa版を捨て型枠として利用することができ、PCa版の厚みを耐荷被覆(耐荷性能を確保するために必要なかぶりの一部)とすることもできる。   In this case, the PCa plate can be used as a discarded formwork, and the thickness of the PCa plate can be used as a load-resistant coating (a part of the fog necessary for ensuring load-bearing performance).

また、型枠底板に鉄骨鉄筋コンクリート板を用いる場合は、図6のように補強鋼材と下側リブ材に複数の孔を設けて、鉄筋をその孔に貫通させるように設置する。補強鋼材と下側リブ材に設けた孔がずれ止めとして作用するため、型枠底板のコンクリートと鋼材との一体化を図ることができる。   Moreover, when using a steel-frame reinforced concrete board for a formwork bottom plate, as shown in FIG. 6, a plurality of holes are provided in the reinforcing steel material and the lower rib material, and the reinforcing bars are installed so as to penetrate the holes. Since the holes provided in the reinforcing steel material and the lower rib material act as stoppers, it is possible to integrate the concrete and the steel material of the mold bottom plate.

本体にコンクリートを打設する時には、下側リブ材を型枠底板から引抜くような方向に荷重が作用することになるが、補強鋼材と下側リブ材を貫通する鉄筋を設けていることによって、この引抜き荷重に対して効率的に抵抗することができる。   When placing concrete in the main body, the load acts in the direction of pulling out the lower rib material from the formwork bottom plate, but by providing a reinforcing steel material and a reinforcing bar that penetrates the lower rib material. Thus, it is possible to efficiently resist the pulling load.

鋼製リブ材によって、コンクリート打設時の荷重に耐え得る断面剛性を確保するという観点からは、鋼製リブ材を床版側でなく、型枠底板の下側に設けることも考えられるが、その場合には内空断面を侵すため、利用空間が少なくなるという欠点や、鋼製リブ材を取り外してこの欠点を克服しようとしたとしても、その取外しが高所作業となり困難であるといった問題がある。   From the viewpoint of securing the cross-sectional rigidity that can withstand the load during concrete placement by the steel rib material, it is also conceivable to provide the steel rib material under the formwork bottom plate, not the floor slab side, In that case, the inner space cross section is affected, so there is a problem that the use space is reduced, and even if it is attempted to overcome this defect by removing the steel rib material, the removal is difficult due to the work at a high place. is there.

そこで、本発明では、鋼製リブ材をあえて埋め殺しとし、コンクリート打設時の荷重に耐えるための型枠の補剛の機能に加え、鉄筋コンクリート床版中に配筋される鉄筋、主として下端筋を支持するスペーサーの機能を持たせることとし、そのため鉄筋コンクリート床版下面からの必要なかぶり厚に相当する位置にスリットを設けている。   Therefore, in the present invention, the steel rib material is dared to be buried, in addition to the function of stiffening the formwork to withstand the load at the time of placing concrete, the reinforcing bars arranged in the reinforced concrete floor slab, mainly the bottom reinforcement Therefore, a slit is provided at a position corresponding to the required cover thickness from the lower surface of the reinforced concrete floor slab.

このように、本発明の床版型枠は、鋼製リブ材も含め、脱型せずそのまま捨型枠として使用することができるが、耐火性は期待していないため、必要なかぶり厚を確保して鉄筋が配筋され、鉄筋コンクリート床版として要求される耐火性能を満たすように設計することになる。   As described above, the floor slab form of the present invention, including the steel rib material, can be used as it is without removing the mold, but it is not expected to have fire resistance. It will be designed to meet the fire resistance required for reinforced concrete floor slabs by securing the reinforcing bars.

この場合、鉄筋は複数のスリット間に架設される形で配筋されるため、スリットの幅、特に水平方向に余裕がないと配筋作業が困難となるため、鋼製リブ材の長手方向に長い長溝状のスリット形状とするのが好ましい。長溝状のスリット形状であれば、鉄筋を斜めの状態から差し込んだり、複数本の鉄筋をまとめて差し込み、その後に適切な間隔になるよう水平移動させるといったことが可能となる。   In this case, since the reinforcing bars are laid between the slits, it will be difficult to place the slits, especially in the horizontal direction. It is preferable to have a long slot-like slit shape. If it is a long groove-like slit shape, it is possible to insert the reinforcing bars from an oblique state, or to insert a plurality of reinforcing bars together and then move them horizontally so as to obtain an appropriate interval.

このようにして、コンクリート床版の支持スパン直角方向に配筋される鉄筋を1本または複数本ずつ配置し、コンクリートを打設することで、鉄筋コンクリート床版を構築していくことができる。   Thus, a reinforced concrete slab can be constructed by arranging one or more reinforcing bars arranged in the direction perpendicular to the support span of the concrete slab and placing concrete.

鋼製リブ材は、下側リブ材と、該下側リブ材に対して連結部材を介して着脱可能な上側リブ材とに2分して構成することもできる。   The steel rib material can be divided into two parts: a lower rib material and an upper rib material that can be attached to and detached from the lower rib material via a connecting member.

その場合、下側リブ材は、下側リブ材を型枠底板上に並列配置した状態で、コンクリート打設前に作用する荷重を支持できるだけの断面剛性が確保できるようにする。すなわちその状態ではコンクリートの打設時の荷重を支えるには不十分であっても、作業者が型枠底板上で配筋作業を行う等、コンクリート打設前に作用する荷重を支持できるようにする。   In this case, the lower rib member can secure a cross-sectional rigidity sufficient to support the load acting before placing the concrete in a state where the lower rib member is arranged in parallel on the mold bottom plate. In other words, even if it is not enough to support the load when placing concrete in that state, the worker can support the load acting before placing the concrete, such as performing reinforcement work on the formwork bottom plate. To do.

その後、下側リブ材の上端部にコンクリート床版に配筋される鉄筋を載置し、下側リブ材に対し、連結部材を介して上側リブ材を接続することで、コンクリートの打設時の荷重に耐え得るだけの断面剛性となるようにする。   After that, the reinforcing ribs placed on the concrete floor slab are placed on the upper end of the lower rib member, and the upper rib member is connected to the lower rib member via a connecting member. The cross-sectional rigidity should be sufficient to withstand this load.

この場合、床版に配筋される鉄筋は、下側リブ材の上端部に載せればよいため、上述したスリットに鉄筋を差し込む場合に比べ、さらに配筋作業が容易となる。   In this case, the reinforcing bars to be arranged on the floor slab may be placed on the upper end portion of the lower rib member, so that the reinforcing work is further facilitated as compared with the case where the reinforcing bars are inserted into the slits described above.

連結部材の形態や接続方法は特に限定されないが、スプライスプレートと高力ボルトを使用すれば、下側リブ材と上側リブ材を接続した状態での剛性確保が比較的容易である。   The form and connection method of the connecting member are not particularly limited, but if a splice plate and a high-strength bolt are used, it is relatively easy to ensure rigidity in a state where the lower rib member and the upper rib member are connected.

このようにして、上側リブ材を未連結の状態で架設し、下側リブ材の上にコンクリート床版の支持スパン直角方向に配筋される複数の鉄筋を載置し、連結部材を用いて下側リブ材に上側リブ材を連結した後、コンクリートを打設することで、鉄筋コンクリート床版を構築していくことができる。   In this way, the upper rib member is installed in an unconnected state, and a plurality of reinforcing bars arranged in the direction perpendicular to the support span of the concrete floor slab are placed on the lower rib member, and the connecting member is used. After connecting the upper rib material to the lower rib material, the concrete reinforced concrete slab can be constructed by placing concrete.

底鋼板が構造部材としての床版の一部を構成する合成床版の場合、耐火性の問題があるのに対し、本発明では必要なかぶり厚を確保した鉄筋によって補強された鉄筋コンクリート床版構造であるため、耐火性の問題をクリアすることができる。   In the case of a composite floor slab in which the bottom steel plate constitutes a part of the floor slab as a structural member, there is a problem of fire resistance, whereas in the present invention, a reinforced concrete floor slab structure reinforced by a reinforcing bar that secures the necessary cover thickness Therefore, the problem of fire resistance can be cleared.

コンクリート打設圧を、型枠底板上に並列させた複数の鋼製リブ材の断面剛性で受けることで、大がかりな支保工を要することなく、大スパンの施工が可能であり、特に急速施工が求められる条件において有用である。また、支保工等によって内空断面が侵されないことで、内空断面での作業を並行させることができる。   By receiving the concrete casting pressure with the cross-sectional rigidity of multiple steel rib members arranged in parallel on the formwork bottom plate, large span construction is possible without requiring extensive support work, especially rapid construction. Useful under the required conditions. In addition, since the inner cross section is not eroded by the support work or the like, the work on the inner cross section can be performed in parallel.

コンクリート床版に配筋される鉄筋を鋼製リブ材に形成したスリットで受けるようにしたことで、配筋作業も容易である。   Reinforcing work is easy because the reinforcing bars placed on the concrete slab are received by the slits formed in the steel rib material.

鋼製リブ材を下側リブ材と上側リブ材に2分し、上側リブ材を連結部材で着脱可能とした場合には、配筋作業がさらに容易である。   If the steel rib material is divided into a lower rib material and an upper rib material, and the upper rib material is made detachable by a connecting member, the bar arrangement work is further facilitated.

型枠底板をPCa版とした場合には、型枠底板を捨型枠兼耐荷被覆(耐荷性能を確保するために必要なかぶりの一部)として利用することができる。   When the formwork bottom plate is a PCa plate, the formwork bottom plate can be used as a discarded frame and load-resistant coating (a part of the fog necessary for ensuring load-proof performance).

また、型枠底板のPCa版を鉄骨鉄筋コンクリート板とし、補強鋼材および下側リブに複数の孔を設け、両者の孔を貫通する鉄筋を設置する場合、補強鋼材と下側リブに設けた孔がずれ止めとして作用し、コンクリートと鋼材とを一体化させることができる。   In addition, when the PCa plate of the mold bottom plate is a steel reinforced concrete plate and a plurality of holes are provided in the reinforcing steel material and the lower rib, and a reinforcing bar penetrating both holes is installed, the holes provided in the reinforcing steel material and the lower rib are Acts as a detent and can integrate concrete and steel.

本体コンクリート打設時は、下側リブを型枠底板から引抜くように荷重が作用するが、補強鋼材と下側リブの両者を貫通する鉄筋を配置することで、この引抜き荷重に対して効率的に抵抗することができる。   When placing concrete in the main body, the load acts so as to pull out the lower rib from the bottom plate of the formwork, but by placing reinforcing bars that penetrate both the reinforcing steel and the lower rib, it is efficient against this pull-out load. Can resist.

本発明の一実施形態を示したもので、(a)は平面図、(b)は(a)のA−A線断面図、(c)は(a)のB−B線断面図である。BRIEF DESCRIPTION OF THE DRAWINGS FIG. 1 shows an embodiment of the present invention, where (a) is a plan view, (b) is a sectional view taken along line AA in (a), and (c) is a sectional view taken along line BB in (a). . (a)は図1(b)の一部を拡大して示した図、(b)は図1(c)の拡大図である。(a) is the figure which expanded and showed a part of FIG.1 (b), (b) is the enlarged view of FIG.1 (c). 本発明の他の実施形態を示した鉛直断面図である。It is the vertical sectional view which showed other embodiment of this invention. (a)〜(d)は、図3の実施形態における施工手順を示す拡大断面図である。(a)-(d) is an expanded sectional view which shows the construction procedure in embodiment of FIG. 本発明における型枠底板にPCa版を用いた場合の一実施形態であり、パネルを敷設した時を示した概略斜視図である。It is one Embodiment at the time of using PCa plate for the formwork baseplate in this invention, and is the schematic perspective view which showed the time of laying the panel. 図5の実施形態の次の手順を示したものであり、床版の下側に配筋した時を示した概略斜視図である。FIG. 6 is a schematic perspective view showing the next procedure of the embodiment of FIG. 5 and showing the time when the bars are arranged below the floor slab. 図6の実施形態の次の手順を示したものであり、上側リブ材を接合した時を示した概略斜視図である。FIG. 7 is a schematic perspective view showing the next procedure of the embodiment of FIG. 6 and showing the time when the upper rib member is joined. 本発明において、型枠底板に鉄骨鉄筋コンクリート板を用いた場合の一実施形態を示したものであり、(a)(b)は断面図、(c)は補強鋼材、鉄筋、下側リブ材を示した概略斜視図である。In the present invention, an embodiment in which a steel frame reinforced concrete plate is used as a mold bottom plate is shown. (A) and (b) are cross-sectional views, and (c) is a reinforcing steel material, a reinforcing bar, and a lower rib material. It is the shown schematic perspective view.

以下、本発明の具体的な実施形態を添付図面に基づいて説明する。   Hereinafter, specific embodiments of the present invention will be described with reference to the accompanying drawings.

図1および図2は本発明の一実施形態として、掘割道路の上部を横断する支間(側壁と中央壁間)約7m、床版厚50cmの大スパンの鉄筋コンクリート床版を構築するための床版型枠を示したものである。   FIG. 1 and FIG. 2 show a floor slab for constructing a large span reinforced concrete floor slab having a span of about 7 m (between the side wall and the central wall) and a floor slab thickness of 50 cm as an embodiment of the present invention. The formwork is shown.

図1(a)は平面図、図1(b)はそのA−A線断面図、図1(c)はB−B線断面図、図2(a)は図1(b)の一部を拡大して示した図、図2(b)は図1(c)の拡大図である。   1 (a) is a plan view, FIG. 1 (b) is a cross-sectional view taken along the line AA, FIG. 1 (c) is a cross-sectional view taken along the line BB, and FIG. 2 (a) is a part of FIG. FIG. 2 (b) is an enlarged view of FIG. 1 (c).

主要な型枠構成要素は、型枠底板11と、その型枠底板11上に並列配置した鋼製リブ材12であり、支持構造体としての道路側壁1a、中央壁1b間に大がかりな支保工を用いることなく架け渡した状態で、後述する配筋作業を行い、コンクリート7を打設養生することで、支持構造体1a、1bの上部に大スパンの鉄筋コンクリート床版2が構築される。なお、反対側の道路側壁は図示を省略しているが、ほぼ対称な構造となる。   The main formwork components are a formwork bottom plate 11 and a steel rib member 12 arranged in parallel on the formwork bottom plate 11, and a large support work between the road side wall 1a and the central wall 1b as a support structure. In the state where it is bridged without using the reinforced concrete floor slab 2, a large-span reinforced concrete slab 2 is constructed on the upper portions of the support structures 1 a and 1 b by performing the reinforcement work described later and placing and curing the concrete 7. In addition, although the illustration of the road sidewall on the opposite side is omitted, the structure is almost symmetrical.

本実施形態において、型枠底板11は幅50cmの長尺の帯状鋼板を接続プレート11aで幅方向に複数枚接続し、その上面に鋼製リブ材12として、高さ25cmの長尺の帯状鋼板を長手方向を一致させて、鉛直に取り付けることで、コンクリートの打設圧に耐える断面剛性を確保している。型枠底板11と鋼製リブ材12はボルト接合したり、あるいは予め溶接しておくなどして一体化する。   In the present embodiment, the mold bottom plate 11 is formed by connecting a plurality of long strip steel plates having a width of 50 cm in the width direction with a connection plate 11a, and a long strip steel plate having a height of 25 cm as a steel rib member 12 on the upper surface thereof. By matching the longitudinal direction with the vertical mounting, the cross-sectional rigidity to withstand the concrete pouring pressure is secured. The formwork bottom plate 11 and the steel rib member 12 are integrated by bolting or welding in advance.

本実施形態では、既に構築されている道路側壁1aおよび中央壁1bの上面に型枠受け材14を設置して、型枠受け材14で型枠底板11の両端から突出する鋼製リブ材12の余長部分を支持するようにしている。また、型枠底板11の両端部にはハンチ部底板15が連結材16を介して取り付けられ、ハンチ部の底型枠となっている。   In the present embodiment, the formwork receiving material 14 is installed on the upper surfaces of the road side wall 1a and the central wall 1b that have already been constructed, and the steel rib material 12 protruding from both ends of the formwork bottom plate 11 by the formwork receiving material 14. The extra length part is supported. In addition, a haunch portion bottom plate 15 is attached to both ends of the mold bottom plate 11 via a connecting member 16 to form a bottom mold frame of the haunch portion.

鋼製リブ材12には、長手方向に間隔をおいて複数のスリット13が形成されている。スリット13はその下端が構築される床版の下端筋3a、3bのかぶり厚に相当する高さになるように形成されており、架設スパン方向と直交する方向の下端筋3aを挿入することで、下端筋3aに対するスペーサーとして機能する。スリット13を長溝状のスリット形状とすれば、下端筋3aを挿入して仮置きする作業が容易である。   A plurality of slits 13 are formed in the steel rib member 12 at intervals in the longitudinal direction. The slit 13 is formed so that the lower end thereof has a height corresponding to the cover thickness of the lower end stripes 3a and 3b of the floor slab to be constructed. By inserting the lower end stripe 3a in the direction orthogonal to the span direction of installation, It functions as a spacer for the lower end muscle 3a. If the slit 13 is formed in the shape of a long groove, the work of inserting and temporarily placing the lower end stripe 3a is easy.

型枠底板11は脱型の必要はなく、鋼製リブ材12とともに捨て型枠となるが、耐火性に関しては強度に算入せず、構築される床版は鉄筋コンクリート床版として設計する。   The mold bottom plate 11 does not need to be removed from the mold, and becomes a discarded mold frame together with the steel rib member 12, but the fire resistance is not included in the strength, and the constructed floor slab is designed as a reinforced concrete floor slab.

一般的な施工手順としては、所定幅に分割され、あらかじめ鋼製リブ材12を取り付けた型枠底板11を、道路側壁1a、中央壁1b間に架設しながら、大がかりな支保工を用いることなく架け渡した状態で、接続プレート11aと高力ボルト等で幅方向に接続して行く。   As a general construction procedure, a formwork bottom plate 11 divided into a predetermined width and pre-attached with a steel rib member 12 is installed between the road side wall 1a and the central wall 1b without using a large support work. In the spanned state, the connecting plate 11a is connected in the width direction with a high strength bolt or the like.

道路側壁1aおよび中央壁1bへの架設は、前述のように型枠受け材14で鋼製リブ材12の余長部分を支持する形で行い、ハンチ部底板15をハンチ位置にセットする。また、コンクリート打設範囲について必要な側型枠等(図示せず)をセットする。   The construction on the road side wall 1a and the central wall 1b is performed in such a manner that the extra length portion of the steel rib member 12 is supported by the mold receiving member 14 as described above, and the haunch bottom plate 15 is set at the haunch position. Moreover, a necessary side mold or the like (not shown) is set for the concrete placement range.

次に、鋼製リブ材12の長溝状のスリット13に、スパン直交方向(鋼製リブ材12の長手方向と直角な方向)の下端筋3aを複数本ずつ挿入し、配筋設計に応じて間隔を整え、下端筋3aの上にさらにスパン方向の下端筋3bを載せ、結束線などで固定する。続いて、スペーサー(図示せず)を利用して上端筋4a、4bの配筋作業を行う。   Next, a plurality of lower end bars 3a in the span orthogonal direction (a direction perpendicular to the longitudinal direction of the steel rib member 12) are inserted into the long groove-like slits 13 of the steel rib member 12, and according to the bar arrangement design. The interval is adjusted, and the lower end stripe 3b in the span direction is further placed on the lower end stripe 3a, and fixed with a binding wire or the like. Subsequently, the upper end bars 4a and 4b are arranged using a spacer (not shown).

この状態で、コンクリートの打設を行い、養生を行うことで床版が完成する。型枠底板11はそのまま捨て型枠として残すが、側型枠等は脱型する場合と、捨て型枠として残す場合といずれでもよい。   In this state, concrete is placed and cured to complete the floor slab. The formwork bottom plate 11 is left as it is as a discarded formwork, but the side formwork or the like may be either removed from the mold or left as a formwork.

床版の幅によっては、以上の作業を複数回繰り返すことになる。   Depending on the width of the slab, the above operation is repeated several times.

図3および図4は本発明の他の実施形態を示したもので、対象や施工条件は図1および図2の実施形態と同様である。   3 and 4 show another embodiment of the present invention, and the objects and construction conditions are the same as those of the embodiment of FIGS.

図3は鉛直断面図、図4(a)〜(d)は図3に対応する施工手順を示したもので、それぞれ左側の図がスパン直交方向からみた拡大断面図、右側の図がそれと直交する方向の拡大断面図である。   3 is a vertical cross-sectional view, and FIGS. 4A to 4D show the construction procedure corresponding to FIG. 3, with the left-hand side view being an enlarged cross-sectional view seen from the span orthogonal direction and the right-side view being perpendicular thereto. It is an expanded sectional view of the direction to do.

本実施形態は、鋼製リブ材を、下側リブ材22aと上側リブ材22bに分けて構成し、これらを複数枚の連結プレート23を介して高ボルトなどで接合するようにしたものである。   In the present embodiment, the steel rib material is divided into a lower rib material 22a and an upper rib material 22b, and these are joined by a high bolt or the like via a plurality of connecting plates 23. .

連結プレート23は、あらかじめ下側リブ材22aまたは上側リブ材22bに取り付けておくことで、現場作業が容易となる。その場合、あらかじめ取り付けておく側はボルト接合でなく、溶接でもよい。   By attaching the connecting plate 23 to the lower rib member 22a or the upper rib member 22b in advance, field work is facilitated. In that case, the side to be attached in advance may be welded instead of bolted.

下側リブ材22aは、型枠底板11上に並列配置した状態で、作業者が型枠底板11上で配筋作業を行う等、コンクリート打設前に作用する荷重を支持するのに十分な断面剛性が確保できるようにする。   The lower rib member 22a is sufficient to support a load acting before placing concrete, such as an operator performing reinforcement work on the mold bottom plate 11 in a state of being arranged in parallel on the mold bottom plate 11. Ensure that cross-sectional rigidity is ensured.

その後、下側リブ材22aの上端部にコンクリート床版2に配筋される下端筋3a、3bを載置し、下側リブ材22aに対し、連結部材23を介して上側リブ材22bを接続することで、コンクリート7の打設時の荷重に耐え得る断面剛性を確保する。   Thereafter, lower end bars 3a and 3b arranged on the concrete floor slab 2 are placed on the upper end portion of the lower rib member 22a, and the upper rib member 22b is connected to the lower rib member 22a via the connecting member 23. By doing so, the cross-sectional rigidity which can endure the load at the time of placement of the concrete 7 is ensured.

この場合、床版に配筋される下端筋3a、3bは、下側リブ材22aの上端部に載せるだけでよいため、図1、図2の実施形態のように、スリット13に下端筋3aを差し込む場合に比べ、配筋作業が容易である。他の構成は、図1、図2の実施形態と同様である。   In this case, since the lower end bars 3a and 3b arranged on the floor slab need only be placed on the upper end portion of the lower rib member 22a, the lower end bars 3a are provided in the slit 13 as in the embodiment of FIGS. Compared to the case of inserting the bar, the bar arrangement work is easier. Other configurations are the same as those of the embodiment of FIGS.

一般的な施工手順としては、所定幅に分割され、あらかじめ下側リブ材22aを取り付けた型枠底板11を、道路側壁1a、中央壁1b間に架設しながら、大がかりな支保工を用いることなく架け渡した状態で、接続プレート11aと高力ボルト等で幅方向に接続して行く(図4(a)参照)。   As a general construction procedure, the frame bottom plate 11 divided into a predetermined width and previously attached with the lower rib member 22a is installed between the road side wall 1a and the central wall 1b without using a large support work. In the spanned state, the connecting plate 11a is connected in the width direction with a high-strength bolt or the like (see FIG. 4 (a)).

道路側壁1aおよび中央壁1bへの架設は、型枠受け材14で下側リブ材22aの余長部分を支持する形で行い、ハンチ部底板15をハンチ位置にセットする(図3参照)。   Construction on the road side wall 1a and the central wall 1b is performed by supporting the extra length of the lower rib member 22a with the mold receiving member 14, and the haunch bottom plate 15 is set at the haunch position (see FIG. 3).

次に、下側リブ材22aの上端部に、スパン直交方向の下端筋3aを載置して行き、配筋設計に応じて間隔を整え、下端筋3aの上にさらにスパン方向の下端筋3bを載せ、結束線などで固定する(図4(b)参照)。   Next, the lower end reinforcement 3a in the span orthogonal direction is placed on the upper end portion of the lower rib member 22a, the interval is adjusted according to the arrangement of the reinforcement, and the lower end reinforcement 3b in the span direction is further placed on the lower end reinforcement 3a. And fix it with a binding wire (see Fig. 4 (b)).

下端筋3a、3bの配筋作業を行った後、連結プレート23を介して下側リブ材22aの上方に上側リブ材22bを高力ボルト接合等により連結する(図4(c)参照)。   After performing the bar arrangement work of the lower end bars 3a and 3b, the upper rib member 22b is connected to the upper side of the lower rib member 22a through the connecting plate 23 by high-strength bolt bonding or the like (see FIG. 4C).

続いて、スペーサー(図示せず)を利用して上端筋4a、4bの配筋作業を行い、コンクリート7を打設し、養生を行うことで床版が完成する(図4(d)参照)。   Subsequently, the upper end bars 4a and 4b are laid using a spacer (not shown), the concrete 7 is placed and cured, and the floor slab is completed (see FIG. 4 (d)). .

その他の作業は、図1、図2の実施形態と同様である。   Other operations are the same as those in the embodiment of FIGS.

図5〜図8は、本発明の他の実施形態を示したもので、対象や施工条件は図1および図2の実施形態と同様である。   5 to 8 show other embodiments of the present invention, and the objects and construction conditions are the same as those of the embodiments of FIGS. 1 and 2.

図5〜図7は、本発明の型枠底板11にPCa版と鋼製リブ材12を組み合わせたハイブリッド型枠を使用した場合の概略斜視図であり、施工手順を示している。鋼製リブ材は、図3、図4と同様で、下側リブ材22aと上側リブ材22bに分けて構成し、これらを複数枚の連結プレート23を介して高ボルトなどで接合するようにしたものである。   FIGS. 5-7 is a schematic perspective view at the time of using the hybrid formwork which combined the PCa plate and the steel rib material 12 with the formwork baseplate 11 of this invention, and has shown the construction procedure. The steel rib material is the same as in FIGS. 3 and 4, and is divided into a lower rib material 22 a and an upper rib material 22 b, and these are joined by a high bolt or the like via a plurality of connecting plates 23. It is a thing.

まず、ステップ1として、図5にパネル敷設時を示した。型枠底板11にはあらかじめ工場などで下側リブ材22aを設けたPCa版を使用する。   First, as step 1, FIG. For the mold bottom plate 11, a PCa plate provided with a lower rib member 22a in advance at a factory or the like is used.

下側リブ材22aは、型枠底板11上に並列配置した状態で、作業者が型枠底板11上で配筋作業を行う等、コンクリート打設前に作用する荷重を支持するのに十分な断面剛性が確保できるようにする。   The lower rib member 22a is sufficient to support a load acting before placing concrete, such as an operator performing reinforcement work on the mold bottom plate 11 in a state of being arranged in parallel on the mold bottom plate 11. Ensure that cross-sectional rigidity is ensured.

連結プレート23は、あらかじめ下側リブ材22aに取り付けておくことで、現場作業が容易となる。その場合、あらかじめ取り付けておく側はボルト接合でなく、溶接でもよい。   By attaching the connecting plate 23 to the lower rib member 22a in advance, field work is facilitated. In that case, the side to be attached in advance may be welded instead of bolted.

次に、ステップ2として、図6に床版下側の配筋を示した。下側リブ材22aの上端部にコンクリート床版2に配筋される下端筋3a、3bを載置し、下側リブ材22aをスペーサとして利用している。   Next, as Step 2, FIG. 6 shows the bar arrangement below the floor slab. Lower end bars 3a and 3b arranged on the concrete floor slab 2 are placed on the upper end portion of the lower rib member 22a, and the lower rib member 22a is used as a spacer.

ステップ3として、図7に上側リブ材22bの接合を示した。下側リブ材22aに対し、連結部材23を介して上側リブ材22bを接続し、コンクリート7の打設時の荷重に耐え得る断面剛性を確保する。   As Step 3, FIG. 7 shows joining of the upper rib member 22b. The upper rib member 22b is connected to the lower rib member 22a via the connecting member 23 to ensure a cross-sectional rigidity that can withstand the load when the concrete 7 is placed.

この場合、床版に配筋される下端筋3a、3bは、下側リブ材22aの上端部に載せるだけでよいため、図1、図2の実施形態のように、スリット13に下端筋3aを差し込む場合に比べ、配筋作業が容易である。   In this case, since the lower end bars 3a and 3b arranged on the floor slab need only be placed on the upper end portion of the lower rib member 22a, the lower end bars 3a are provided in the slit 13 as in the embodiment of FIGS. Compared to the case of inserting the bar, the bar arrangement work is easier.

また、PCa版を捨て型枠として利用することができ、PCa版の厚みを耐荷被覆(耐荷性能を確保するために必要なかぶりの一部)とすることもできる。   Further, the PCa plate can be used as a discarded formwork, and the thickness of the PCa plate can be used as a load-resistant coating (a part of the fog necessary for ensuring load-bearing performance).

他の構成やその他の作業は、図1〜4の実施形態と同様である。   Other configurations and other operations are the same as those in the embodiment of FIGS.

図8は、本発明の型枠底板11のPCa版に補強鋼材として溝形鋼を設けた鉄骨鉄筋コンクリート板を使用した場合を示したもので、図8(a)、(b)は断面図、図8(c)は斜視図である。   FIG. 8 shows a case where a steel reinforced concrete plate provided with channel steel as a reinforcing steel material is used for the PCa plate of the mold bottom plate 11 of the present invention, and FIGS. 8 (a) and 8 (b) are sectional views, FIG. 8C is a perspective view.

図8(a)〜(c)に示したように、溝形鋼31と下側リブ材22aにそれぞれ複数の孔を設け、溝形鋼31と下側リブ材22aの孔を貫通させるように鉄筋を設け、PCa版を構成する。   As shown in FIGS. 8A to 8C, a plurality of holes are provided in each of the groove steel 31 and the lower rib member 22a, and the holes of the groove steel 31 and the lower rib member 22a are passed through. Reinforcing bars are provided to form a PCa plate.

溝形鋼31と下側リブ材22に設けた孔がずれ止めとして作用し、型枠底板のコンクリートと鋼材との一体化を図ることができる。   The hole provided in the channel steel 31 and the lower rib member 22 acts as a stopper, so that the concrete of the formwork bottom plate and the steel material can be integrated.

下側リブ材22aに連結プレート23を高ボルトなどで接合する以降の作業や他の構成は図1〜7の実施形態と同様である。   Operations after the joining plate 23 is joined to the lower rib member 22a with a high bolt or the like and other configurations are the same as those in the embodiment of FIGS.

型枠底板11に鉄骨鉄筋コンクリート板を用いる場合、本体にコンクリートを打設する時には、下側リブ材22aを型枠底板11から引抜くような方向に荷重が作用することになる。しかし、補強鋼材31と下側リブ材22aを貫通する鉄筋を設けていることによって、この引抜き荷重に対して効率的に抵抗することができる。   When a steel frame reinforced concrete plate is used for the mold bottom plate 11, when concrete is placed on the main body, a load acts in such a direction that the lower rib member 22 a is pulled out from the mold bottom plate 11. However, by providing a reinforcing bar that penetrates the reinforcing steel member 31 and the lower rib member 22a, it is possible to efficiently resist this pulling load.

溝型鋼31が、図8(a)では外向き、図8(b)では内向きで設置した例を示しているが、どちらも有効的である。   Although the example in which the grooved steel 31 is installed outward in FIG. 8 (a) and inward in FIG. 8 (b) is shown, both are effective.

ここでは補強鋼材として溝形鋼を用いた例を示しているが、H形鋼その他補強鋼材に複数の孔を設けることができ、強度面で問題のないものであればよく、特に限定されない。   Here, an example in which channel steel is used as the reinforcing steel material is shown, but a plurality of holes can be provided in the H-shaped steel and other reinforcing steel materials, and any material may be used as long as it has no problem in strength, and is not particularly limited.

1a…側壁(支持構造体)、1b…中央壁(支持構造体)、2…大スパン鉄筋コンクリート床版、3a、3b…下端筋、4a、4b…上端筋、5…壁主筋、6…せん断補強筋、7…コンクリート、
11…底板、11a…接続プレート、12…リブ材、13…スリット、14…型枠受け材、15…ハンチ部底板、16…連結材、
22a…下側リブ材、22b…上側リブ材、23…連結プレート、
31…補強鋼材(溝形鋼)、32…鉄筋
DESCRIPTION OF SYMBOLS 1a ... Side wall (support structure), 1b ... Center wall (support structure), 2 ... Large span reinforced concrete floor slab, 3a, 3b ... Lower end reinforcement, 4a, 4b ... Upper end reinforcement, 5 ... Wall main reinforcement, 6 ... Shear reinforcement Muscle, 7 ... concrete,
DESCRIPTION OF SYMBOLS 11 ... Bottom plate, 11a ... Connection plate, 12 ... Rib material, 13 ... Slit, 14 ... Formwork receiving material, 15 ... Haunch part bottom plate, 16 ... Connection material,
22a ... lower rib material, 22b ... upper rib material, 23 ... connecting plate,
31 ... Reinforced steel (channel steel), 32 ... Rebar

Claims (6)

支持構造体上に鉄筋コンクリート床版を打設するための大スパンコンクリート床版型枠であって、型枠底板と、前記型枠底板上に並列し、コンクリート打設時の荷重に耐え得るだけの断面剛性を有する複数の鋼製リブ材とを備え、前記鋼製リブ材には前記コンクリート床版に配筋される鉄筋を載置可能なスリットが複数形成されていることを特徴とする大スパンコンクリート床版型枠。   A large-span concrete floor slab formwork for placing reinforced concrete floor slabs on a support structure, parallel to the formwork bottom plate and the formwork bottom plate, and capable of withstanding the load during concrete placement A plurality of steel rib members having a cross-sectional rigidity, wherein the steel rib members are formed with a plurality of slits on which reinforcing bars arranged on the concrete floor slab can be placed. Concrete floor slab formwork. 前記鋼製リブ材は帯状鋼板または形鋼であることを特徴とする請求項1記載の大スパンコンクリート床版型枠。   2. The large-span concrete floor slab form according to claim 1, wherein the steel rib member is a strip steel plate or a shape steel. 前記スリットは前記鋼製リブ材の長手方向に長い長溝状のスリットであることを特徴とする請求項1または2記載の大スパンコンクリート床版型枠。   The large-span concrete floor slab form according to claim 1 or 2, wherein the slit is a long groove-like slit long in the longitudinal direction of the steel rib material. 支持構造体上に鉄筋コンクリート床版を打設するための大スパンコンクリート床版型枠であって、型枠底板と、前記型枠底板上に並列し、コンクリート打設時の荷重に耐え得るだけの断面剛性を有する複数の鋼製リブ材とを備え、前記鋼製リブ材はコンクリート打設前に作用する荷重を支持可能な下側リブ材と、該下側リブ材に対して連結部材を介して着脱可能な上側リブ材に2分され、前記下側リブ材と上側リブ材とを連結した状態でコンクリート打設時の荷重を支持するようにしたものであり、前記下側リブ材の上端部に前記コンクリート床版に配筋される鉄筋を載置可能としたことを特徴とする大スパンコンクリート床版型枠。   A large-span concrete floor slab formwork for placing reinforced concrete floor slabs on a support structure, parallel to the formwork bottom plate and the formwork bottom plate, and capable of withstanding the load during concrete placement A plurality of steel rib members having a cross-sectional rigidity, wherein the steel rib members are capable of supporting a load acting before placing the concrete, and the lower rib members are connected via a connecting member. The upper rib member is divided into two parts, the upper rib member being detachable and supporting the load at the time of placing the concrete in a state where the lower rib member and the upper rib member are connected. A large-span concrete slab formwork characterized in that a reinforcing bar placed on the concrete slab can be placed on the part. 請求項1、2または3記載の大スパンコンクリート床版型枠を前記支持構造体による支持スパン間に架設し、前記各スリット内に前記コンクリート床版の支持スパン直角方向に配筋される鉄筋を1本または複数本ずつ配置し、コンクリートを打設することを特徴とする大スパンコンクリート床版型枠を用いた鉄筋コンクリート床版の施工方法。   A large-span concrete floor slab form according to claim 1, 2, or 3 is laid between support spans by the support structure, and reinforcing bars are arranged in each slit in a direction perpendicular to the support span of the concrete floor slab. A method for constructing a reinforced concrete slab using a large-span concrete slab formwork, wherein one or a plurality of slabs are placed and concrete is placed. 請求項4記載の大スパンコンクリート床版型枠を、前記上側リブ材を未連結の状態で前記支持構造体による支持スパン間に架設し、前記下側リブ材の上に前記コンクリート床版の支持スパン直角方向に配筋される複数の鉄筋を載置し、連結部材を用いて前記下側リブ材に前記上側リブ材を連結した後、コンクリートを打設することを特徴とする大スパンコンクリート床版型枠を用いた鉄筋コンクリート床版の施工方法。   5. A large-span concrete floor slab form according to claim 4, wherein the upper rib member is unconnected between support spans by the support structure, and the concrete floor slab is supported on the lower rib member. A large-span concrete floor characterized by placing a plurality of reinforcing bars arranged in a direction perpendicular to the span, connecting the upper rib material to the lower rib material using a connecting member, and then placing concrete. Construction method of reinforced concrete floor slab using plate formwork.
JP2013050234A 2012-10-09 2013-03-13 Large span concrete floor slab formwork and construction method using the floor slab formwork Active JP6283169B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP2013050234A JP6283169B2 (en) 2012-10-09 2013-03-13 Large span concrete floor slab formwork and construction method using the floor slab formwork

Applications Claiming Priority (3)

Application Number Priority Date Filing Date Title
JP2012224107 2012-10-09
JP2012224107 2012-10-09
JP2013050234A JP6283169B2 (en) 2012-10-09 2013-03-13 Large span concrete floor slab formwork and construction method using the floor slab formwork

Related Child Applications (1)

Application Number Title Priority Date Filing Date
JP2017240145A Division JP6553161B2 (en) 2012-10-09 2017-12-15 Large span concrete floor slab formwork and construction method using the floor slab formwork

Publications (2)

Publication Number Publication Date
JP2014095282A true JP2014095282A (en) 2014-05-22
JP6283169B2 JP6283169B2 (en) 2018-02-21

Family

ID=50938567

Family Applications (2)

Application Number Title Priority Date Filing Date
JP2013050234A Active JP6283169B2 (en) 2012-10-09 2013-03-13 Large span concrete floor slab formwork and construction method using the floor slab formwork
JP2017240145A Active JP6553161B2 (en) 2012-10-09 2017-12-15 Large span concrete floor slab formwork and construction method using the floor slab formwork

Family Applications After (1)

Application Number Title Priority Date Filing Date
JP2017240145A Active JP6553161B2 (en) 2012-10-09 2017-12-15 Large span concrete floor slab formwork and construction method using the floor slab formwork

Country Status (1)

Country Link
JP (2) JP6283169B2 (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2016003530A (en) * 2014-06-19 2016-01-12 ジオスター株式会社 Buried form for floor slab
JP2017166229A (en) * 2016-03-16 2017-09-21 ジオスター株式会社 Box culvert

Families Citing this family (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
DE102019107427A1 (en) 2018-03-27 2019-10-02 Ngk Spark Plug Co., Ltd. Gas sensor element, heater, and gas sensor

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS564111Y2 (en) * 1976-10-19 1981-01-29
JPS5831322U (en) * 1981-08-25 1983-03-01 川崎製鉄株式会社 H-shaped steel for embedded girder
JPH08170311A (en) * 1994-12-16 1996-07-02 Nippon Steel Corp Floor slab with ct type steel
JPH10121419A (en) * 1996-10-23 1998-05-12 Fujisen Kyoryo Doboku Kk Assembly for floor panel
JP2000038798A (en) * 1998-07-22 2000-02-08 Ishikawajima Constr Materials Co Ltd Semi-precast floor slab

Family Cites Families (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP3579167B2 (en) * 1996-02-16 2004-10-20 株式会社横河ブリッジ Deck for road surface and its laying method
JP2000038796A (en) * 1998-07-23 2000-02-08 Nkk Corp Floorboard and its execution
US7197854B2 (en) * 2003-12-01 2007-04-03 D.S. Brown Co. Prestressed or post-tension composite structural system
JP4661709B2 (en) * 2006-07-10 2011-03-30 Jfeスチール株式会社 Plate structure, tunnel segment, floor slab and reinforced concrete pier using the same
JP2009215757A (en) * 2008-03-10 2009-09-24 Haltec:Kk Floor slab structure
JP6042622B2 (en) * 2012-03-09 2016-12-14 株式会社横河住金ブリッジ Floor slab structure using sandwich type composite slab panel
JP5628242B2 (en) * 2012-06-05 2014-11-19 国立大学法人 岡山大学 Steel formwork slab

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS564111Y2 (en) * 1976-10-19 1981-01-29
JPS5831322U (en) * 1981-08-25 1983-03-01 川崎製鉄株式会社 H-shaped steel for embedded girder
JPH08170311A (en) * 1994-12-16 1996-07-02 Nippon Steel Corp Floor slab with ct type steel
JPH10121419A (en) * 1996-10-23 1998-05-12 Fujisen Kyoryo Doboku Kk Assembly for floor panel
JP2000038798A (en) * 1998-07-22 2000-02-08 Ishikawajima Constr Materials Co Ltd Semi-precast floor slab

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2016003530A (en) * 2014-06-19 2016-01-12 ジオスター株式会社 Buried form for floor slab
JP2017166229A (en) * 2016-03-16 2017-09-21 ジオスター株式会社 Box culvert

Also Published As

Publication number Publication date
JP6283169B2 (en) 2018-02-21
JP6553161B2 (en) 2019-07-31
JP2018059397A (en) 2018-04-12

Similar Documents

Publication Publication Date Title
KR101556545B1 (en) Method for constructing using a double wall Precast Concrete
JP2011026786A (en) Structure for reinforcing building
KR101011070B1 (en) Connection method between steel plate concrete structure and different structure
KR101937680B1 (en) Prefabricated Precast Structure and Construction Method Thereof
JP6553161B2 (en) Large span concrete floor slab formwork and construction method using the floor slab formwork
KR101221970B1 (en) Construction Method for Basement Structure without Temporary Structure
JP6108595B2 (en) Ribbed precast concrete plate and method of placing concrete floor slab and beam using it
KR101617221B1 (en) Joint structure of remodeling modular unit for seismic retrofitting and joint method of using it
KR101011252B1 (en) Rigid-frame bridge frame for reinforcing negative moment part and rigid-frame bridge having it
KR20090068536A (en) Concrete-composite crossbeam and construction methods of slab structure using the same
JP2012077471A (en) Joint structure of precast members and concrete precast members
JP6983533B2 (en) Construction method of steel-concrete composite structure and steel-concrete composite structure
KR20120136071A (en) Composite beam with partially filled concrete
JP4028831B2 (en) Removable support beam
KR101672991B1 (en) Pre-assembled structure for reinforced concrete column
KR102269141B1 (en) Deck plate wall installation method using underground pavement
KR100608097B1 (en) Reinforce structure of iron frame pier for building
KR101954387B1 (en) Grid precast concrete structure and constructing method thereof
KR101357280B1 (en) Pc column for constructing multi story simultaneously and pc integrating method using this pc column
JP5750246B2 (en) Composite beam, building, and composite beam construction method
JP5870455B2 (en) Precast concrete wall and joint structure between column and beam
KR101545713B1 (en) Composite type cutoff wall of steel temporary facility and construction method of the same
JP2017223055A (en) Form-reinforcement integral structure and reinforced concrete, and form-reinforcement integral construction method
KR100664965B1 (en) Carbon-glass fiber composite concrete mold, its manufacturing method and construction method
KR101884453B1 (en) Pre-climbing core construction method for top-down construction

Legal Events

Date Code Title Description
A621 Written request for application examination

Free format text: JAPANESE INTERMEDIATE CODE: A621

Effective date: 20160308

A711 Notification of change in applicant

Free format text: JAPANESE INTERMEDIATE CODE: A711

Effective date: 20160308

A521 Request for written amendment filed

Free format text: JAPANESE INTERMEDIATE CODE: A821

Effective date: 20160308

A977 Report on retrieval

Free format text: JAPANESE INTERMEDIATE CODE: A971007

Effective date: 20170113

A131 Notification of reasons for refusal

Free format text: JAPANESE INTERMEDIATE CODE: A131

Effective date: 20170307

A521 Request for written amendment filed

Free format text: JAPANESE INTERMEDIATE CODE: A523

Effective date: 20170426

A02 Decision of refusal

Free format text: JAPANESE INTERMEDIATE CODE: A02

Effective date: 20170919

A521 Request for written amendment filed

Free format text: JAPANESE INTERMEDIATE CODE: A523

Effective date: 20171215

A911 Transfer to examiner for re-examination before appeal (zenchi)

Free format text: JAPANESE INTERMEDIATE CODE: A911

Effective date: 20171225

TRDD Decision of grant or rejection written
A01 Written decision to grant a patent or to grant a registration (utility model)

Free format text: JAPANESE INTERMEDIATE CODE: A01

Effective date: 20180116

A61 First payment of annual fees (during grant procedure)

Free format text: JAPANESE INTERMEDIATE CODE: A61

Effective date: 20180126

R150 Certificate of patent or registration of utility model

Ref document number: 6283169

Country of ref document: JP

Free format text: JAPANESE INTERMEDIATE CODE: R150

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

S531 Written request for registration of change of domicile

Free format text: JAPANESE INTERMEDIATE CODE: R313531

R350 Written notification of registration of transfer

Free format text: JAPANESE INTERMEDIATE CODE: R350

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250