JP2014052154A - Water heater - Google Patents

Water heater Download PDF

Info

Publication number
JP2014052154A
JP2014052154A JP2012198198A JP2012198198A JP2014052154A JP 2014052154 A JP2014052154 A JP 2014052154A JP 2012198198 A JP2012198198 A JP 2012198198A JP 2012198198 A JP2012198198 A JP 2012198198A JP 2014052154 A JP2014052154 A JP 2014052154A
Authority
JP
Japan
Prior art keywords
hot water
water supply
boiling
boiling operation
time
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
JP2012198198A
Other languages
Japanese (ja)
Inventor
Kohei Ogawa
耕平 小川
Takeharu Ando
丈晴 安東
Yuji Horiuchi
雄次 堀内
Koji Senda
孝司 千田
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Daikin Industries Ltd
Original Assignee
Daikin Industries Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Daikin Industries Ltd filed Critical Daikin Industries Ltd
Priority to JP2012198198A priority Critical patent/JP2014052154A/en
Publication of JP2014052154A publication Critical patent/JP2014052154A/en
Pending legal-status Critical Current

Links

Landscapes

  • Heat-Pump Type And Storage Water Heaters (AREA)

Abstract

PROBLEM TO BE SOLVED: To reduce noise due to boiling-up operation in a night time zone.SOLUTION: A water heater 1 includes a plurality of hot water supply units 2 each of which performs a boiling-up operation in a night time zone. Each of the hot water supply units 2 includes a heat pump unit 4 and a hot water storage tank 10 for storing hot water heated by the heat pump unit 4. One of the hot water supply units 2 has an earlier timing of starting up the boiling-up operation and an earlier timing of finishing the boiling-up operation in the night time zone than the others of the hot water supply units 2.

Description

本発明は、貯湯タンクおよびヒートポンプユニットを有する給湯ユニットを複数備えた給湯装置に関する。   The present invention relates to a hot water supply apparatus including a plurality of hot water supply units each having a hot water storage tank and a heat pump unit.

給湯装置は、給湯端末に供給される温水を貯留する貯湯タンクと、貯湯タンクに貯留される温水を加熱するためのヒートポンプユニットとを有する(例えば特許文献1参照)。ヒートポンプユニットは、圧縮機や水熱交換器などを含む冷媒回路を有する。給湯装置は、貯湯タンクから取り出した低温水を、水熱交換器において冷媒との熱交換により加熱して、タンクに戻すようになっている。この沸上運転は、電気料金の安い夜間時間帯に自動的に行われる。   The hot water supply apparatus includes a hot water storage tank that stores hot water supplied to the hot water supply terminal, and a heat pump unit that heats the hot water stored in the hot water storage tank (see, for example, Patent Document 1). The heat pump unit has a refrigerant circuit including a compressor and a water heat exchanger. The hot water supply apparatus heats the low-temperature water taken out from the hot water storage tank by heat exchange with the refrigerant in the water heat exchanger and returns it to the tank. This boiling operation is automatically performed at night time when electricity charges are low.

また、業務用などの給湯装置として、貯湯タンクとヒートポンプユニット(熱源機)を有する給湯ユニットを複数台備えたものがある(例えば特許文献2参照)。   Moreover, as a hot water supply apparatus for business use, there is one provided with a plurality of hot water supply units each having a hot water storage tank and a heat pump unit (heat source unit) (see, for example, Patent Document 2).

特開2002−122362号公報JP 2002-122362 A 特開2005−134064号公報JP 2005-134064 A

しかしながら、複数の給湯ユニットを有する従来の給湯装置では、夜間時間帯に全ての給湯ユニットが同時に沸上運転を行うため、ヒートポンプユニットの運転音が大きくなる。そのため、給湯装置の設置場所が住宅に近い場合などは、騒音が問題となる。   However, in a conventional hot water supply apparatus having a plurality of hot water supply units, since all the hot water supply units simultaneously perform a boiling operation during the night time, the operation sound of the heat pump unit is increased. Therefore, noise is a problem when the location of the hot water supply device is close to a house.

そこで、本発明は、夜間時間帯における沸上運転による騒音を低減できる給湯装置を提供することを目的とする。   Then, an object of this invention is to provide the hot water supply apparatus which can reduce the noise by the boiling operation in a night time zone.

第1の発明に係る給湯装置は、夜間時間帯に沸上運転を行う複数の給湯ユニットを備え、前記給湯ユニットは、ヒートポンプユニットと、前記ヒートポンプユニットで加熱された温水を貯留する貯湯タンクとを備え、1つの前記給湯ユニットは、別の前記給湯ユニットよりも、夜間時間帯における沸上運転を開始するタイミングおよび終了するタイミングが早いことを特徴とする。   A hot water supply apparatus according to a first aspect of the present invention includes a plurality of hot water supply units that perform boiling operation during night time, and the hot water supply unit includes a heat pump unit and a hot water storage tank that stores hot water heated by the heat pump unit. The one hot water supply unit is characterized in that the start timing and the end timing of the boiling operation in the night time zone are earlier than another hot water supply unit.

この給湯装置では、複数の給湯ユニットのうち2つの給湯ユニットは、夜間時間帯において沸上運転を行う時間帯がずれるため、全ての給湯ユニットが夜間時間帯に同時に沸上運転を行う場合に比べて、夜間時間帯の沸上運転による騒音を低減できる。   In this hot water supply apparatus, two hot water supply units out of a plurality of hot water supply units have different boiling time periods during the nighttime period, and therefore, compared with a case where all the hot water supply units simultaneously perform the boiling operation during the nighttime period. Thus, noise caused by boiling operation during night hours can be reduced.

第2の発明に係る給湯装置は、第1の発明において、夜間時間帯において最初に沸上運転を開始する前記給湯ユニットが、夜間時間帯の開始時刻に沸上運転を開始することを特徴とする。   A hot water supply apparatus according to a second invention is characterized in that, in the first invention, the hot water supply unit that starts boiling operation first in a night time zone starts boiling operation at a start time of the night time zone. To do.

この給湯装置では、夜間時間帯における最初の沸上運転が、夜間時間帯の開始時刻に開始されるため、夜間時間帯の給湯量が多い場合に湯切れを防止できる。   In this hot water supply device, since the first boiling operation in the night time zone is started at the start time of the night time zone, it is possible to prevent hot water shortage when the amount of hot water supply in the night time zone is large.

第3の発明に係る給湯装置は、第1または第2の発明において、夜間時間帯において最後に沸上運転を開始する前記給湯ユニットが、夜間時間帯の終了時刻に沸上運転を終了できるように前記貯湯タンクの残湯量に基いて決定された開始時刻に沸上運転を開始することを特徴とする。   A hot water supply apparatus according to a third aspect of the present invention is the hot water supply apparatus according to the first or second aspect, wherein the hot water supply unit that starts the boiling operation last in the night time zone can end the boiling operation at the end time of the night time zone. The boiling operation is started at the start time determined based on the remaining hot water amount in the hot water storage tank.

この給湯装置では、夜間時間帯において最後に開始された沸上運転が、夜間時間帯の終了時刻頃に終了するため、夜間時間帯の途中で全ての給湯ユニットの沸上運転が終了する場合に比べて、夜間時間帯の貯湯タンク内の温水の放熱を低減できる。   In this hot water supply apparatus, since the boiling operation last started in the night time zone ends around the end time of the night time zone, the boiling operation of all the hot water supply units ends in the middle of the night time zone. In comparison, it is possible to reduce the heat dissipation of hot water in the hot water storage tank at night time.

第4の発明に係る給湯装置は、第1〜第3の発明のいずれかにおいて、1つの前記給湯ユニットの沸上運転が終了した時に、別の前記給湯ユニットが沸上運転を開始することを特徴とする。   A hot water supply apparatus according to a fourth aspect of the present invention is that in any one of the first to third aspects, when the boiling operation of one of the hot water supply units is completed, another hot water supply unit starts the boiling operation. Features.

この給湯装置では、複数の給湯ユニットのうち2つの給湯ユニットは、沸上運転を行う時間帯が重複しないため、騒音をより確実に低減できる。   In this hot water supply apparatus, two hot water supply units among a plurality of hot water supply units do not overlap in the time zone during which the boiling operation is performed, and therefore noise can be reduced more reliably.

以上の説明に述べたように、本発明によれば、以下の効果が得られる。   As described above, according to the present invention, the following effects can be obtained.

第1の発明では、複数の給湯ユニットのうち2つの給湯ユニットは、夜間時間帯において沸上運転を行う時間帯がずれるため、全ての給湯ユニットが夜間時間帯に同時に沸上運転を行う場合に比べて、夜間時間帯の沸上運転による騒音を低減できる。   In the first invention, two hot water supply units out of the plurality of hot water supply units have different boiling time periods during the night time period, and therefore when all the hot water supply units simultaneously perform the boiling operation during the night time period. In comparison, noise caused by boiling operation during night time can be reduced.

第2の発明では、夜間時間帯における最初の沸上運転が、夜間時間帯の開始時刻に開始されるため、夜間時間帯の給湯量が多い場合に湯切れを防止できる。   In the second invention, since the first boiling operation in the night time zone is started at the start time of the night time zone, it is possible to prevent hot water shortage when the amount of hot water supply in the night time zone is large.

第3の発明では、夜間時間帯において最後に開始された沸上運転が、夜間時間帯の終了時刻頃に終了するため、夜間時間帯の途中で全ての給湯ユニットの沸上運転が終了する場合に比べて、夜間時間帯の貯湯タンク内の温水の放熱を低減できる。   In the third aspect of the invention, the boiling operation last started in the night time zone ends at the end time of the night time zone, so that the boiling operation of all the hot water supply units ends in the middle of the night time zone. Compared with, it is possible to reduce the heat dissipation of hot water in the hot water storage tank at night time.

第4の発明では、複数の給湯ユニットのうち2つの給湯ユニットは、沸上運転を行う時間帯が重複しないため、騒音をより確実に低減できる。   In 4th invention, since the hot water supply unit among the several hot water supply units does not overlap the time zone which performs boiling operation, it can reduce noise more reliably.

本発明の第1実施形態に係る給湯装置の構成を示す図である。It is a figure which shows the structure of the hot water supply apparatus which concerns on 1st Embodiment of this invention. 給湯装置が備える給湯ユニットの配管系統図である。It is a piping system diagram of the hot water supply unit with which the hot water supply device is provided. 第1実施形態において、夜間時間帯における沸上運転の開始時刻を決定する手順を示すフローチャートである。In 1st Embodiment, it is a flowchart which shows the procedure which determines the start time of the boiling operation in a night time zone. 第1実施形態において、沸上所要時間の合計値が夜間時間帯の時間以下の場合の沸上運転の具体例を示すグラフである。In 1st Embodiment, it is a graph which shows the specific example of boiling operation in case the total value of boiling required time is below the time of a night time zone. 第1実施形態において、沸上所要時間の合計値が夜間時間帯の時間を超える場合の沸上運転の一例を示すグラフである。In 1st Embodiment, it is a graph which shows an example of the boiling operation in case the total value of boiling required time exceeds the time of a night time zone. 第1実施形態において、沸上所要時間の合計値が夜間時間帯の時間を超える場合の沸上運転の一例を示すグラフである。In 1st Embodiment, it is a graph which shows an example of the boiling operation in case the total value of boiling required time exceeds the time of a night time zone. 第2実施形態において、沸上所要時間の合計値が夜間時間帯の時間を超える場合の沸上運転の一例を示すグラフである。In 2nd Embodiment, it is a graph which shows an example of the boiling operation in case the total value of boiling required time exceeds the time of a night time zone. 第3実施形態において、沸上所要時間の合計値が夜間時間帯の時間を超える場合の沸上運転の一例を示すグラフである。In 3rd Embodiment, it is a graph which shows an example of boiling operation when the total value of boiling required time exceeds the time of a night time zone.

<第1実施形態>
以下、本発明の第1の実施形態に係る給湯装置について説明する。
図1に示すように、本実施形態の給湯装置1は、給湯端末に温水を供給するための装置であって、4つの給湯ユニット2(2A〜2D)と、給湯端末と4つの給湯ユニット2とを接続する給湯配管5と、給水源と4つの給湯ユニット2とを接続する給水配管6とを備える。図1および図2に示すように、各給湯ユニット2は、貯湯タンク10を有する貯湯ユニット3と、この貯湯ユニット3に接続された2つのヒートポンプユニット4とを有する。ヒートポンプユニット4は、貯湯タンク10に貯留される温水を加熱するためのものである。
<First Embodiment>
Hereinafter, the hot water supply apparatus according to the first embodiment of the present invention will be described.
As shown in FIG. 1, a hot water supply device 1 of the present embodiment is a device for supplying hot water to a hot water supply terminal, and includes four hot water supply units 2 (2A to 2D), a hot water supply terminal, and four hot water supply units 2. And a hot water supply pipe 6 for connecting a water supply source and the four hot water supply units 2 to each other. As shown in FIGS. 1 and 2, each hot water supply unit 2 has a hot water storage unit 3 having a hot water storage tank 10 and two heat pump units 4 connected to the hot water storage unit 3. The heat pump unit 4 is for heating the hot water stored in the hot water storage tank 10.

また、各給湯ユニット2には、冷媒回路8と沸上回路7が2つずつ設けられている。冷媒回路は、ヒートポンプユニット4に設けられ、沸上回路7は、貯湯ユニット3とヒートポンプユニット4にわたって設けられている。   Each hot water supply unit 2 is provided with two refrigerant circuits 8 and two boiling circuits 7. The refrigerant circuit is provided in the heat pump unit 4, and the boiling circuit 7 is provided across the hot water storage unit 3 and the heat pump unit 4.

冷媒回路8は、圧縮機21と、水熱交換器22と、電動膨張弁23と、空気熱交換器24と、これらを順に接続する冷媒配管とを有し、例えばCOなどの冷媒が循環する。また、冷媒回路8は、水熱交換器22から出る高温高圧の冷媒と、空気熱交換器24から出る冷温低圧の冷媒との間で熱交換を行うためのガス熱交換器25を有する。また、空気熱交換器24の近傍には、空気熱交換器24の能力を調整するためのファン26が配置されている。 The refrigerant circuit 8 includes a compressor 21, a water heat exchanger 22, an electric expansion valve 23, an air heat exchanger 24, and a refrigerant pipe that connects them in order, for example, a refrigerant such as CO 2 circulates. To do. The refrigerant circuit 8 also includes a gas heat exchanger 25 for exchanging heat between the high-temperature and high-pressure refrigerant coming out of the water heat exchanger 22 and the cold and low-pressure refrigerant coming out of the air heat exchanger 24. A fan 26 for adjusting the capacity of the air heat exchanger 24 is disposed in the vicinity of the air heat exchanger 24.

圧縮機21で圧縮された冷媒は、水熱交換器22において温水との熱交換により冷却された後、ガス熱交換器25でさらに冷却される。その後、冷媒は電動膨張弁23において減圧された後、空気熱交換器24において外気との熱交換により加熱されて、圧縮機21に戻る。   The refrigerant compressed by the compressor 21 is cooled by heat exchange with hot water in the water heat exchanger 22 and then further cooled by the gas heat exchanger 25. Thereafter, the refrigerant is depressurized by the electric expansion valve 23, heated by the heat exchange with the outside air in the air heat exchanger 24, and returned to the compressor 21.

沸上回路7は、貯湯タンク10と、ポンプ31と、水熱交換器22と、三方弁32とが順に接続された回路である。貯湯タンク10、ポンプ31、及び三方弁32は、貯湯ユニット3に設けられ、水熱交換器22はヒートポンプユニット4に設けられている。   The boiling circuit 7 is a circuit in which the hot water storage tank 10, the pump 31, the water heat exchanger 22, and the three-way valve 32 are connected in order. The hot water storage tank 10, the pump 31, and the three-way valve 32 are provided in the hot water storage unit 3, and the water heat exchanger 22 is provided in the heat pump unit 4.

貯湯タンク10の上部には、給湯出口11と、上戻し口12が設けられており、貯湯タンク10の下部には、給水口13と、取出口14と、下戻し口15が設けられている。上戻し口12、取出口14、下戻し口15は、沸上回路7に接続されている。上戻し口12、取出口14、下戻し口15は、2つの沸上回路7で共有している。   A hot water supply outlet 11 and an upper return port 12 are provided in the upper part of the hot water storage tank 10, and a water supply port 13, an outlet 14, and a lower return port 15 are provided in the lower part of the hot water storage tank 10. . The upper return port 12, the outlet 14, and the lower return port 15 are connected to the boiling circuit 7. The upper return port 12, the outlet 14, and the lower return port 15 are shared by the two boiling circuits 7.

また、貯湯タンク10の外面には、貯湯タンク10内の温水の温度を検知する複数のタンクサーミスタ16が、上下方向に並んで取り付けられている。タンクサーミスタ16で検知された温度によって、貯湯タンク10内に高温の温水がどれだけ残っているかを検知できる(残湯量検知)。   A plurality of tank thermistors 16 for detecting the temperature of the hot water in the hot water storage tank 10 are attached to the outer surface of the hot water storage tank 10 side by side in the vertical direction. It is possible to detect how much hot water remains in the hot water storage tank 10 based on the temperature detected by the tank thermistor 16 (detection of remaining hot water).

三方弁32は、水熱交換器22の出口側を上戻し口12と下戻し口15のいずれかに連通するように切り換えるものであって、水熱交換器22で加熱された温水の温度(出湯温度)に応じて切り換えられる。出湯温度が低い場合(例えば沸上運転の開始直後)には、三方弁32は、水熱交換器22が下戻し口15に連通するように切り換えられ、出湯温度が目標出湯温度に近付くと、三方弁32は、水熱交換器22が上戻し口12に連通するように切り換えられる。   The three-way valve 32 switches the outlet side of the water heat exchanger 22 so as to communicate with either the upper return port 12 or the lower return port 15, and the temperature of the hot water heated by the water heat exchanger 22 ( It can be switched according to the temperature When the tapping temperature is low (for example, immediately after the start of the boiling operation), the three-way valve 32 is switched so that the water heat exchanger 22 communicates with the lower return port 15, and when the tapping temperature approaches the target tapping temperature, The three-way valve 32 is switched so that the water heat exchanger 22 communicates with the upper return port 12.

沸上運転時には、冷媒回路8の圧縮機21とファン26が駆動すると共に、沸上回路7のポンプ31が駆動して、貯湯タンク10の取出口14から温水が取り出されて、水熱交換器22に供給される。温水は水熱交換器22において加熱された後、上戻し口12または下戻し口15から貯湯タンク10内に戻される。   During the boiling operation, the compressor 21 and the fan 26 of the refrigerant circuit 8 are driven, and the pump 31 of the boiling circuit 7 is driven, and hot water is taken out from the outlet 14 of the hot water storage tank 10, and the water heat exchanger 22 is supplied. The hot water is heated in the water heat exchanger 22 and then returned to the hot water storage tank 10 from the upper return port 12 or the lower return port 15.

また、貯湯ユニット3は、貯湯タンク10の給湯出口11と給湯配管5とを接続する給湯配管33と、貯湯タンク10の給水口13と給水配管6とを接続する給水配管34とを有する。   The hot water storage unit 3 includes a hot water supply pipe 33 that connects the hot water supply outlet 11 of the hot water storage tank 10 and the hot water supply pipe 5, and a water supply pipe 34 that connects the water supply port 13 of the hot water storage tank 10 and the water supply pipe 6.

給湯端末への給湯を行う場合、貯湯タンク10の給湯出口11から温水が出湯されると同時に、給水源からの水が給水口13から貯湯タンク10内に供給される。そのため、貯湯タンク10内の温水がすべて加熱されて高温となっている場合を除けば、貯湯タンク10内の温水の温度は、上部が高温、下部が低温となっている。4つの貯湯タンク10から給湯端末までの給湯配管の長さが異なることなどが理由で、1回の給湯時に4つの貯湯タンク10からそれぞれ出湯される流量は異なる。そのため、4つの貯湯タンク10の残湯量は異なっている場合がある。   When hot water is supplied to the hot water supply terminal, hot water is discharged from the hot water supply outlet 11 of the hot water storage tank 10, and at the same time, water from the water supply source is supplied into the hot water storage tank 10 from the water supply port 13. Therefore, except for the case where all the hot water in the hot water storage tank 10 is heated to a high temperature, the temperature of the hot water in the hot water storage tank 10 is high at the top and low at the bottom. The flow rates discharged from the four hot water storage tanks 10 at the time of one hot water supply differ because the lengths of the hot water supply pipes from the four hot water storage tanks 10 to the hot water supply terminals are different. Therefore, the remaining hot water amounts of the four hot water storage tanks 10 may be different.

次に、給湯装置1の制御部(図示省略)について説明する。制御部は4つの給湯ユニット2の沸上運転を制御する。制御部は、電気料金が安価な夜間時間帯(例えば22時から7時)に、4つの給湯ユニット2が沸上運転を行うように制御する。この場合の沸上運転を、夜間自動沸上運転と称する。また、制御部は、時間帯に関わらず、貯湯タンク10の残湯量が所定量未満となった場合には、その貯湯タンク10を有する給湯ユニット2が沸上運転を行うように制御する。この場合の沸上運転を、湯切れ沸上運転と称する。   Next, the control part (illustration omitted) of the hot water supply apparatus 1 is demonstrated. The control unit controls the boiling operation of the four hot water supply units 2. The control unit controls the four hot water supply units 2 to perform a boiling operation during a night time zone (for example, from 22:00 to 7:00) where the electricity rate is inexpensive. The boiling operation in this case is referred to as nighttime automatic boiling operation. Moreover, a control part controls so that the hot water supply unit 2 which has the hot water storage tank 10 performs boiling operation, when the remaining hot water amount of the hot water storage tank 10 becomes less than predetermined amount irrespective of a time slot | zone. The boiling operation in this case is referred to as a hot water boiling operation.

1つの給湯ユニット2に関して、時刻または残湯量による沸上運転開始条件が成立すると、制御部は、この給湯ユニット2が有する2つのヒートポンプユニット4の圧縮機21、ファン26を駆動するとともに、この給湯ユニット2が有する貯湯ユニット3の2つのポンプ31を駆動して、沸上運転を開始する。沸上運転時、制御部は、水熱交換器22で加熱された温水の温度に基いて三方弁32を制御する。また、制御部は、貯湯タンク10内の温水の温度が目標沸上温度に達したときに、沸上運転を終了する。   When the boiling operation start condition based on the time or the amount of remaining hot water is satisfied for one hot water supply unit 2, the control unit drives the compressors 21 and the fans 26 of the two heat pump units 4 included in the hot water supply unit 2, and the hot water supply. The two pumps 31 of the hot water storage unit 3 included in the unit 2 are driven to start the boiling operation. During the boiling operation, the control unit controls the three-way valve 32 based on the temperature of the hot water heated by the water heat exchanger 22. Further, the controller ends the boiling operation when the temperature of the hot water in the hot water storage tank 10 reaches the target boiling temperature.

以下、制御部による4つの給湯ユニット2の夜間自動沸上運転の開始時刻(以下、沸上開始時刻という)の決定方法について、図3に示すフローチャートを用いて説明する。   Hereinafter, a method of determining the start time (hereinafter referred to as boiling start time) of the nighttime automatic boiling operation of the four hot water supply units 2 by the control unit will be described with reference to the flowchart shown in FIG.

制御部は、夜間時間帯の前に、沸上開始時刻を決定する。制御部は、まず、4つの貯湯タンク10のそれぞれの残湯量から、4つの給湯ユニット2のそれぞれの沸上所要時間を算出する(ステップS1)。   The control unit determines the boiling start time before the night time zone. First, the control unit calculates the required boiling time of each of the four hot water supply units 2 from the amount of remaining hot water in each of the four hot water storage tanks 10 (step S1).

4つの沸上所要時間の合計時間が、夜間時間帯の時間(以下、夜間時間という)以下の場合には(ステップS2、NO)、制御部は、算出された沸上所要時間に基いて、4つの給湯ユニット2の沸上運転の時間が重複しないように、4つの給湯ユニット2の沸上開始時刻を決定する(ステップS3)。より具体的には、4つの給湯ユニット2の沸上運転の時間を、夜間時間帯の開始時刻側に詰める(前詰め)か、もしくは、夜間時間帯の終了時刻側に詰める(後詰め)ようにして、沸上開始時刻を決定する。前詰めおよび後詰めのいずれを用いるかは、予め決定されていてもよく、リモコンの操作によって選択できるようになっていてもよい。   When the total time of the four boiling required times is equal to or less than the time of the night time zone (hereinafter referred to as night time) (step S2, NO), the control unit, based on the calculated boiling required time, The boiling start times of the four hot water supply units 2 are determined so that the boiling operation times of the four hot water supply units 2 do not overlap (step S3). More specifically, the boiling operation time of the four hot water supply units 2 is packed on the start time side of the night time zone (prepared) or on the end time side of the night time zone (post-packed). Thus, the boiling start time is determined. Whether to use front-packing or back-packing may be determined in advance, or may be selected by operating a remote controller.

図4(a)は、前詰めで沸上開始時刻を決定する場合の具体例である。図4(a)では、夜間時間の開始時刻を、給湯ユニット2Aの沸上開始時刻としている。また、給湯ユニット2Aの沸上開始時刻に給湯ユニット2Aの沸上所要時間を足した時刻を、給湯ユニット2Bの沸上開始時刻としている。給湯ユニット2C、2Dの沸上開始時刻の説明は、給湯ユニット2Bと同様であるため省略する。   Fig.4 (a) is a specific example in the case of determining the boiling start time by the last preparation. In Fig.4 (a), the start time of night time is made into the boiling start time of the hot water supply unit 2A. Also, the time obtained by adding the required boiling time of the hot water supply unit 2A to the boiling start time of the hot water supply unit 2A is set as the boiling start time of the hot water supply unit 2B. The description of the boiling start time of the hot water supply units 2C and 2D is the same as that of the hot water supply unit 2B, and will be omitted.

図4(b)は、後詰めで沸上開始時刻を決定する場合の具体例である。図4(b)では、夜間時間帯の終了時刻から給湯ユニット2Aの沸上所要時間を引いた時刻を、給湯ユニット2Aの沸上開始時刻としている。また、給湯ユニット2Aの沸上開始時刻から給湯ユニット2Bの沸上所要時間を引いた時刻を、給湯ユニット2Bの沸上開始時刻としている。給湯ユニット2C、2Dの沸上開始時刻の説明は、給湯ユニット2Bと同様であるため省略する。   FIG.4 (b) is a specific example in the case of determining the boiling start time by backpacking. In FIG. 4B, the time obtained by subtracting the required boiling time of the hot water supply unit 2A from the end time of the night time zone is set as the boiling start time of the hot water supply unit 2A. The time obtained by subtracting the required boiling time of the hot water supply unit 2B from the boiling start time of the hot water supply unit 2A is set as the boiling start time of the hot water supply unit 2B. The description of the boiling start time of the hot water supply units 2C and 2D is the same as that of the hot water supply unit 2B, and will be omitted.

図4(a)および図4(b)中の沸上所要時間は、夜間時間帯の前の残湯量に基いて算出されたものであるため、夜間時間帯に給湯があった場合には、図中の沸上所要時間よりも実際の沸上所要時間が長くなる。そのため、1つの給湯ユニット2の沸上運転が終了する前に、次の沸上運転が開始する場合がある。また、後詰めの場合には、夜間時間帯の終了時刻の後で、最後の沸上運転が終了する場合がある。   Since the boiling time in FIG. 4 (a) and FIG. 4 (b) is calculated based on the amount of remaining hot water before the night time zone, when hot water is supplied during the night time zone, The actual boiling time is longer than the boiling time in the figure. Therefore, the next boiling operation may start before the boiling operation of one hot water supply unit 2 ends. In addition, in the case of back-packing, the last boiling operation may end after the end time of the night time zone.

制御部は、4つの沸上所要時間の合計時間が、夜間時間を超える場合には(ステップS2、YES)、グループごとの沸上所要時間の合計時間が夜間時間以下となるように、4つの給湯ユニット2を複数のグループに分ける(ステップS4)。   When the total time of the four boiling required times exceeds the night time (step S2, YES), the control unit sets the four boiling required times for each group to be equal to or less than the night time. The hot water supply units 2 are divided into a plurality of groups (step S4).

例えば図5に示すように、給湯ユニット2A〜2Dの沸上所要時間が、5時間、4時間、3時間、3時間の場合には、給湯ユニット2A、2Cをグループ1とし、給湯ユニット2B、2Dをグループ2とする。
また例えば図6に示すように、給湯ユニット2A〜2Dの沸上所要時間が、6時間、5時間、3.5時間、3.5時間の場合には、給湯ユニット2Aをグループ1とし、給湯ユニット2B、2Cをグループ2とし、給湯ユニット2Dをグループ3とする。
For example, as shown in FIG. 5, when the required boiling time of the hot water supply units 2A to 2D is 5 hours, 4 hours, 3 hours, and 3 hours, the hot water supply units 2A and 2C are group 1 and the hot water supply units 2B, 2B, Let 2D be Group 2.
For example, as shown in FIG. 6, when the required boiling time of the hot water supply units 2A to 2D is 6 hours, 5 hours, 3.5 hours, and 3.5 hours, the hot water supply unit 2A is group 1 and Units 2B and 2C are group 2 and hot water supply unit 2D is group 3.

制御部は、奇数番号のグループの給湯ユニット2の沸上運転が上述の前詰めで並ぶように、奇数番号のグループの給湯ユニット2の沸上開始時刻を決定するとともに、偶数番号のグループの給湯ユニット2の沸上運転が上述の後詰めで並ぶように、偶数番号のグループの給湯ユニット2の沸上開始時刻を決定する(ステップS5)(図5および図6参照)。   The control unit determines the boiling start time of the hot water supply units 2 in the odd-numbered groups and sets the hot water supply in the even-numbered groups so that the boiling operations of the hot water supply units 2 in the odd-numbered groups are arranged in the above-mentioned order. The boiling start times of the hot water supply units 2 in the even-numbered groups are determined so that the boiling operations of the units 2 are arranged in the last order (step S5) (see FIGS. 5 and 6).

本実施形態の給湯装置1では、前詰めおよび後詰めの一方または両方によって、4つの給湯ユニット2の夜間自動沸上運転の開始時刻を決定する。そのため、複数の給湯ユニット2のうち少なくとも2つの給湯ユニット2は、夜間時間帯において沸上運転を行う時間帯がずれる。したがって、全ての給湯ユニット2が夜間時間帯に同時に沸上運転を行う場合に比べて、夜間時間帯の沸上運転による騒音を低減できる。   In the hot water supply apparatus 1 of the present embodiment, the start time of the nighttime automatic boiling operation of the four hot water supply units 2 is determined by one or both of the pre-packing and the post-packing. Therefore, at least two hot water supply units 2 among the plurality of hot water supply units 2 are out of time during which the boiling operation is performed during the night time. Therefore, compared with the case where all the hot water supply units 2 perform the boiling operation at the same time during the night time, noise due to the boiling operation during the night time can be reduced.

また、本実施形態では、夜間時間帯に給湯がなかった場合には、1つの給湯ユニット2の沸上運転が終了した時に、別の給湯ユニット2が沸上運転を開始するため、この2つの給湯ユニット2は、沸上運転を行う時間帯が重複しない。そのため、騒音をより確実に低減できる。   In the present embodiment, when there is no hot water supply during the night time period, when the boiling operation of one hot water supply unit 2 is completed, another hot water supply unit 2 starts the boiling operation. The hot water supply unit 2 does not overlap the time zone during which the boiling operation is performed. Therefore, noise can be reduced more reliably.

また、前詰めで沸上開始時刻を決定した場合、夜間時間帯における最初の沸上運転が、夜間時間帯の開始時刻に開始されるため、夜間時間帯の給湯量が多い場合に湯切れを防止できる。   In addition, when the boiling start time is determined by the last preparation, the first boiling operation in the night time zone is started at the start time in the night time zone, so the hot water runs out when there is a large amount of hot water supply in the night time zone. Can be prevented.

また、後詰めで沸上開始時刻を決定した場合、夜間時間帯において最後に開始された沸上運転が、夜間時間帯の終了時刻頃に終了するため、夜間時間帯の途中で全ての給湯ユニットの沸上運転が終了する場合に比べて、夜間時間帯の貯湯タンク10内の温水の放熱を低減できる。   In addition, when the boiling start time is determined by backpacking, the boiling operation that was started last in the night time zone ends at the end time of the night time zone, so all hot water supply units are in the middle of the night time zone. Compared with the case where the boiling operation is completed, it is possible to reduce the heat radiation of the hot water in the hot water storage tank 10 during the night time.

<第2実施形態>
次に、本発明の第2実施形態に係る給湯装置について説明する。但し、上記第1実施形態と同様の構成を有するものについては、同じ符号を用いて適宜その説明を省略する。
本実施形態の給湯装置は、制御部による4つの給湯ユニットの夜間自動沸上運転の開始時刻の決定方法が、上記第1実施形態と異なる。その他の構成は、上記第1実施形態と同じである。
Second Embodiment
Next, a hot water supply apparatus according to a second embodiment of the present invention will be described. However, about the thing which has the structure similar to the said 1st Embodiment, the description is abbreviate | omitted suitably using the same code | symbol.
The hot water supply apparatus of this embodiment differs from the first embodiment in the method for determining the start time of nighttime automatic boiling operation of four hot water supply units by the control unit. Other configurations are the same as those in the first embodiment.

制御部は、夜間自動沸上運転の開始時刻の決定する際、まず、第1実施形態と同様に、4つの貯湯タンク10の残湯量に基いて、4つの給湯ユニット2の沸上所要時間を算出する。   When determining the start time of the nighttime automatic boiling operation, the control unit first determines the boiling time of the four hot water supply units 2 based on the remaining hot water amount of the four hot water storage tanks 10 as in the first embodiment. calculate.

4つの沸上所要時間の合計時間が夜間時間以下の場合には、制御部は、第1実施形態と同様に、4つの給湯ユニット2の沸上運転時間が前詰めまたは後詰めとなるように、4つの給湯ユニット2の沸上開始時刻を決定する。   When the total time of the four boiling required times is equal to or less than the night time, the controller is configured so that the boiling operation times of the four hot water supply units 2 are pre-packed or post-packed as in the first embodiment. The boiling start times of the four hot water supply units 2 are determined.

4つの沸上所要時間の合計時間が夜間時間を超える場合には、制御部は、4つの給湯ユニット2の沸上運転の時間を、前詰めで並べてから後詰めで並べて、それでも夜間時間帯に全ての沸上運転時間が収まらない場合には、残りの沸上運転時間を前詰めで並べることで、4つの給湯ユニット2の沸上開始時刻を決定する。具体例を図7に示す。図7では、前詰めと後詰めだけで、4つの給湯ユニット2の沸上運転の時間が夜間時間帯に収まっている。夜間時間帯に給湯があった場合には、実際に沸上運転を終了するタイミングは、図7より遅くなる場合がある。   When the total time of the four boiling times exceeds the night time, the control unit arranges the boiling operation times of the four hot water supply units 2 from the front end to the rear end and still in the night time zone. When all the boiling operation times do not fit, the boiling start times of the four hot water supply units 2 are determined by arranging the remaining boiling operation times in front-alignment. A specific example is shown in FIG. In FIG. 7, the boiling operation time of the four hot water supply units 2 is within the night time zone only by the front packing and the back packing. When there is hot water supply during the night time, the timing of actually ending the boiling operation may be later than that in FIG.

本実施形態の給湯装置では、第1実施形態と同様に、全ての給湯ユニット2が夜間時間帯に同時に沸上運転を行う場合に比べて、夜間時間帯の沸上運転による騒音を低減できる。   In the hot water supply apparatus of the present embodiment, as in the first embodiment, it is possible to reduce noise due to the boiling operation during the night time period, as compared to the case where all the hot water supply units 2 perform the boiling operation simultaneously during the night time period.

<第3実施形態>
次に、本発明の第3実施形態に係る給湯装置について説明する。但し、上記第1実施形態と同様の構成を有するものについては、同じ符号を用いて適宜その説明を省略する。
本実施形態の給湯装置は、制御部による4つの給湯ユニットの夜間自動沸上運転の開始時刻の決定方法が、上記第1実施形態と異なる。その他の構成は、上記第1実施形態と同じである。
<Third Embodiment>
Next, a hot water supply apparatus according to a third embodiment of the present invention will be described. However, about the thing which has the structure similar to the said 1st Embodiment, the description is abbreviate | omitted suitably using the same code | symbol.
The hot water supply apparatus of this embodiment differs from the first embodiment in the method for determining the start time of nighttime automatic boiling operation of four hot water supply units by the control unit. Other configurations are the same as those in the first embodiment.

制御部は、夜間自動沸上運転の開始時刻の決定する際、まず、第1実施形態と同様に、4つの貯湯タンク10の残湯量に基いて、4つの給湯ユニット2の沸上所要時間を算出する。   When determining the start time of the nighttime automatic boiling operation, the control unit first determines the boiling time of the four hot water supply units 2 based on the remaining hot water amount of the four hot water storage tanks 10 as in the first embodiment. calculate.

4つの沸上所要時間の合計時間が夜間時間以下の場合には、制御部は、第1実施形態と同様に、4つの給湯ユニット2の沸上運転時間が前詰めまたは後詰めとなるように、4つの給湯ユニット2の沸上開始時刻を決定する。   When the total time of the four boiling required times is equal to or less than the night time, the controller is configured so that the boiling operation times of the four hot water supply units 2 are pre-packed or post-packed as in the first embodiment. The boiling start times of the four hot water supply units 2 are determined.

4つの沸上所要時間の合計時間が夜間時間を超える場合には、制御部は、4つの沸上所要時間の合計時間と夜間時間との差を、給湯ユニット2の数から1引いた数(本実施形態では3)で割る。制御部は、4つの給湯ユニット2の沸上運転の時間を、算出された時間の分だけ重複させつつ、夜間時間帯の開始時刻から終了時刻にわたってずらして並べて、4つの給湯ユニット2の沸上開始時刻を決定する。つまり、1つの給湯ユニット2の沸上開始時刻に沸上所要時間を足した時刻(沸上終了予定時刻)から、算出された時間を引いた時刻を、別の給湯ユニット2の沸上開始時刻とする。具体例1を図8に示す。図8では、4つの沸上所要時間の合計値が12時間で、沸上運転の重複する時間が1時間となっている。夜間時間帯に給湯があった場合には、実際に沸上運転を終了するタイミングは、図8より遅くなる場合がある。   When the total time of the four boiling required times exceeds the night time, the control unit subtracts the difference between the total time of the four boiling required times and the night time by one from the number of the hot water supply units 2 ( In this embodiment, it is divided by 3). The control unit arranges the boiling-up times of the four hot water supply units 2 by shifting them from the start time to the end time of the night time zone while overlapping the calculated time by the calculated time. Determine the start time. That is, the time obtained by subtracting the calculated time from the time obtained by adding the required boiling time to the boiling start time of one hot water supply unit 2 (scheduled boiling end time) is the boiling start time of another hot water supply unit 2. And Specific example 1 is shown in FIG. In FIG. 8, the total value of the four boiling required times is 12 hours, and the overlapping time of the boiling operation is 1 hour. When there is hot water supply during the night time, the timing of actually ending the boiling operation may be later than that in FIG.

本実施形態の給湯装置では、第1実施形態と同様に、全ての給湯ユニット2が夜間時間帯に同時に沸上運転を行う場合に比べて、夜間時間帯の沸上運転による騒音を低減できる。   In the hot water supply apparatus of the present embodiment, as in the first embodiment, it is possible to reduce noise due to the boiling operation during the night time period, as compared to the case where all the hot water supply units 2 perform the boiling operation simultaneously during the night time period.

以上、本発明の実施の形態について説明したが、本発明の具体的な構成は、上記第1〜第3実施形態に限定されるものでないと考えられるべきである。本発明の範囲は、上記実施形態の説明だけではなく特許請求の範囲によって示され、さらに特許請求の範囲と均等の意味および範囲内でのすべての変更が含まれる。   As mentioned above, although embodiment of this invention was described, it should be thought that the specific structure of this invention is not limited to the said 1st-3rd embodiment. The scope of the present invention is shown not only by the description of the above-described embodiment but also by the scope of claims for patent, and further includes meanings equivalent to the scope of claims for patent and all modifications within the scope.

上記第1および第2実施形態では、後詰めで沸上開始時刻を決定する場合、夜間時間帯における最後の沸上開始時刻を、夜間時間帯の終了時刻から沸上所要時間を引いた時刻としているが、夜間時間帯に給湯があった場合でも夜間時間帯内に沸上運転を終了できるように、夜間時間帯の終了時刻よりも若干(例えば1時間)早い時刻から沸上所要時刻を引い時刻を、沸上開始時刻としてもよい。   In the first and second embodiments described above, when determining the boiling start time by backpacking, the last boiling start time in the night time zone is the time obtained by subtracting the boiling required time from the end time of the night time zone. However, even if there is hot water supply during the night time zone, the boiling time is subtracted from the time slightly earlier (for example, 1 hour) than the end time of the night time zone so that the boiling operation can be completed within the night time zone. The time may be the boiling start time.

4つの給湯ユニット2の夜間自動沸上運転の開始時刻の決定方法は、1つの給湯ユニット2が、別の給湯ユニット2よりも、沸上運転を開始するタイミングおよび終了するタイミングが早くなるような方法であれば、上記第1〜第3実施形態以外の方法であってもよい。上記第1〜第3実施形態では、夜間時間帯の前に、全ての給湯ユニット2の沸上開始時刻を決定しているが、夜間時間帯の残湯量に基いて、夜間時間帯の途中で、一部の給湯ユニット2の沸上開始時刻を決定してもよい。   The method for determining the start time of the nighttime automatic boiling operation of the four hot water supply units 2 is such that one hot water supply unit 2 starts and ends more quickly than another hot water supply unit 2. If it is a method, methods other than the said 1st-3rd embodiment may be sufficient. In the first to third embodiments, the boiling start times of all the hot water supply units 2 are determined before the night time zone, but based on the remaining hot water amount in the night time zone, The boiling start time of some hot water supply units 2 may be determined.

上記第1〜第3実施形態では、4つの給湯ユニット2の夜間自動沸上運転は、必ず時間をずらして行われるが、全ての給湯ユニット2の夜間自動沸上運転を同時に行うか、第1〜第3実施形態のようにずらして行うか、リモコンで選択できるようになっていてもよい。   In the first to third embodiments, the nighttime automatic boiling operation of the four hot water supply units 2 is always performed at different times, but the nighttime automatic boiling operation of all the hot water supply units 2 is performed simultaneously, It may be shifted as in the third embodiment or selected with a remote controller.

上記第1〜第3実施形態では、1つの給湯ユニット2が有するヒートポンプユニット4の数は、2つであるが、1つであっても、3つ以上であってもよい。また、複数の給湯ユニット2ごとに、ヒートポンプユニット4の数が異なっていてもよい。   In the said 1st-3rd embodiment, although the number of the heat pump units 4 which one hot water supply unit 2 has is two, it may be one or three or more. Further, the number of heat pump units 4 may be different for each of the plurality of hot water supply units 2.

上記第1〜第3実施形態では、給湯装置1が有する給湯ユニット2の数は、4つであるが、複数であれば、3つ以下であっても、5つ以上であってもよい。   In the said 1st-3rd embodiment, although the number of the hot water supply units 2 which the hot water supply apparatus 1 has is four, as long as it is plural, it may be three or less, or may be five or more.

本発明を利用すれば、夜間時間帯における沸上運転による騒音を低減できる。   If this invention is utilized, the noise by the boiling operation in a night time zone can be reduced.

1 給湯装置
2(2A〜2D) 給湯ユニット
3 貯湯ユニット
4 ヒートポンプユニット
7 沸上回路
8 冷媒回路
10 貯湯タンク
DESCRIPTION OF SYMBOLS 1 Hot water supply apparatus 2 (2A-2D) Hot water supply unit 3 Hot water storage unit 4 Heat pump unit 7 Boiling circuit 8 Refrigerant circuit 10 Hot water storage tank

Claims (4)

夜間時間帯に沸上運転を行う複数の給湯ユニットを備え、
前記給湯ユニットは、ヒートポンプユニットと、前記ヒートポンプユニットで加熱された温水を貯留する貯湯タンクとを備え、
1つの前記給湯ユニットは、別の前記給湯ユニットよりも、夜間時間帯における沸上運転を開始するタイミングおよび終了するタイミングが早いことを特徴とする給湯装置。
Equipped with multiple hot water supply units that perform boiling operation at night time,
The hot water supply unit includes a heat pump unit and a hot water storage tank for storing hot water heated by the heat pump unit,
One of the hot water supply units has a timing for starting and ending boiling-up operation in a night time zone earlier than another hot water supply unit.
夜間時間帯において最初に沸上運転を開始する前記給湯ユニットが、夜間時間帯の開始時刻に沸上運転を開始することを特徴とする請求項1に記載の給湯装置。   The hot water supply device according to claim 1, wherein the hot water supply unit that starts boiling operation first in a night time zone starts boiling operation at a start time of the night time zone. 夜間時間帯において最後に沸上運転を開始する前記給湯ユニットが、夜間時間帯の終了時刻に沸上運転を終了できるように前記貯湯タンクの残湯量に基づいて決定された開始時刻に沸上運転を開始することを特徴とする請求項1または2に記載の給湯装置。   Boiling operation at the start time determined based on the remaining amount of hot water in the hot water storage tank so that the hot water supply unit that starts boiling operation at the end of the night time period can finish the boiling operation at the end time of the night time period The hot water supply apparatus according to claim 1, wherein the hot water supply apparatus is started. 1つの前記給湯ユニットの沸上運転が終了した時に、別の前記給湯ユニットが沸上運転を開始することを特徴とする請求項1〜3のいずれかに記載の給湯装置。   The hot water supply apparatus according to any one of claims 1 to 3, wherein when the boiling operation of one of the hot water supply units is finished, another hot water supply unit starts the boiling operation.
JP2012198198A 2012-09-10 2012-09-10 Water heater Pending JP2014052154A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP2012198198A JP2014052154A (en) 2012-09-10 2012-09-10 Water heater

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP2012198198A JP2014052154A (en) 2012-09-10 2012-09-10 Water heater

Publications (1)

Publication Number Publication Date
JP2014052154A true JP2014052154A (en) 2014-03-20

Family

ID=50610777

Family Applications (1)

Application Number Title Priority Date Filing Date
JP2012198198A Pending JP2014052154A (en) 2012-09-10 2012-09-10 Water heater

Country Status (1)

Country Link
JP (1) JP2014052154A (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2017129312A (en) * 2016-01-20 2017-07-27 三菱電機株式会社 Hot water system
JP2018112337A (en) * 2017-01-10 2018-07-19 三菱電機株式会社 Water heater control system

Citations (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH06323627A (en) * 1993-05-12 1994-11-25 Sekisui Chem Co Ltd Hot water feeding system
JP2012097949A (en) * 2010-11-01 2012-05-24 Mitsubishi Electric Corp Water heater control system, water heater control device, water heater control method, and program

Patent Citations (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH06323627A (en) * 1993-05-12 1994-11-25 Sekisui Chem Co Ltd Hot water feeding system
JP2012097949A (en) * 2010-11-01 2012-05-24 Mitsubishi Electric Corp Water heater control system, water heater control device, water heater control method, and program

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2017129312A (en) * 2016-01-20 2017-07-27 三菱電機株式会社 Hot water system
JP2018112337A (en) * 2017-01-10 2018-07-19 三菱電機株式会社 Water heater control system

Similar Documents

Publication Publication Date Title
KR101222331B1 (en) Heat-pump hot water apparatus
AU2014399713B2 (en) Heating and hot water supply system
WO2014002133A1 (en) Heat-pump type hot water supply/heating system
JP6239333B2 (en) Hot water supply system and control method thereof
JP2010091181A (en) Storage water heater and heat pump water heater
KR101621168B1 (en) Hot water supply system
JP6183840B2 (en) Hot water supply system and control method thereof
JP5427015B2 (en) Hot water storage water heater
JP4818780B2 (en) Water heater
JP2007327728A (en) Heat pump hot-water supply system
JP2014052154A (en) Water heater
JP5329245B2 (en) Water heater
JP5192406B2 (en) Method for determining boiling target temperature of heat pump water heater
JP5734882B2 (en) Hot water storage water heater
JP2013250012A (en) Water heater
JP5584163B2 (en) Hot water storage water heater
JP3869749B2 (en) Hot water storage water heater
JP5580244B2 (en) Hot water storage water heater
JP6119499B2 (en) Hot water storage water heater
JP5468479B2 (en) Heat pump hot water storage system
JP2014092310A (en) Heat pump water heater
JP5498130B2 (en) Boiling set temperature determination method of heat pump hot water storage type hot water supply and heating system
JP5694905B2 (en) Heat pump type water heater
JP2009287872A (en) Heating system and heating hot water system
JP6536387B2 (en) Hot water supply system

Legal Events

Date Code Title Description
A621 Written request for application examination

Free format text: JAPANESE INTERMEDIATE CODE: A621

Effective date: 20140312

A977 Report on retrieval

Free format text: JAPANESE INTERMEDIATE CODE: A971007

Effective date: 20141119

A131 Notification of reasons for refusal

Free format text: JAPANESE INTERMEDIATE CODE: A131

Effective date: 20141209

A02 Decision of refusal

Free format text: JAPANESE INTERMEDIATE CODE: A02

Effective date: 20150407