JP2014010683A - 負荷量予測装置および負荷量予測方法 - Google Patents
負荷量予測装置および負荷量予測方法 Download PDFInfo
- Publication number
- JP2014010683A JP2014010683A JP2012147518A JP2012147518A JP2014010683A JP 2014010683 A JP2014010683 A JP 2014010683A JP 2012147518 A JP2012147518 A JP 2012147518A JP 2012147518 A JP2012147518 A JP 2012147518A JP 2014010683 A JP2014010683 A JP 2014010683A
- Authority
- JP
- Japan
- Prior art keywords
- load amount
- prediction
- time
- history data
- load
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Granted
Links
- 238000000034 method Methods 0.000 title claims description 16
- 238000005259 measurement Methods 0.000 claims abstract description 41
- XLYOFNOQVPJJNP-UHFFFAOYSA-N water Substances O XLYOFNOQVPJJNP-UHFFFAOYSA-N 0.000 description 12
- 230000006870 function Effects 0.000 description 7
- 238000010586 diagram Methods 0.000 description 6
- 230000007704 transition Effects 0.000 description 6
- 238000013139 quantization Methods 0.000 description 4
- 238000012986 modification Methods 0.000 description 3
- 230000004048 modification Effects 0.000 description 3
- 238000004378 air conditioning Methods 0.000 description 2
- 230000008569 process Effects 0.000 description 2
- 238000012545 processing Methods 0.000 description 2
- 238000012935 Averaging Methods 0.000 description 1
- 238000004364 calculation method Methods 0.000 description 1
- 230000008859 change Effects 0.000 description 1
- 238000002474 experimental method Methods 0.000 description 1
- 238000000746 purification Methods 0.000 description 1
- 230000009467 reduction Effects 0.000 description 1
- 230000004044 response Effects 0.000 description 1
Classifications
-
- G—PHYSICS
- G06—COMPUTING; CALCULATING OR COUNTING
- G06Q—INFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
- G06Q50/00—Information and communication technology [ICT] specially adapted for implementation of business processes of specific business sectors, e.g. utilities or tourism
- G06Q50/06—Energy or water supply
-
- H—ELECTRICITY
- H02—GENERATION; CONVERSION OR DISTRIBUTION OF ELECTRIC POWER
- H02J—CIRCUIT ARRANGEMENTS OR SYSTEMS FOR SUPPLYING OR DISTRIBUTING ELECTRIC POWER; SYSTEMS FOR STORING ELECTRIC ENERGY
- H02J3/00—Circuit arrangements for ac mains or ac distribution networks
- H02J3/003—Load forecast, e.g. methods or systems for forecasting future load demand
-
- Y—GENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
- Y04—INFORMATION OR COMMUNICATION TECHNOLOGIES HAVING AN IMPACT ON OTHER TECHNOLOGY AREAS
- Y04S—SYSTEMS INTEGRATING TECHNOLOGIES RELATED TO POWER NETWORK OPERATION, COMMUNICATION OR INFORMATION TECHNOLOGIES FOR IMPROVING THE ELECTRICAL POWER GENERATION, TRANSMISSION, DISTRIBUTION, MANAGEMENT OR USAGE, i.e. SMART GRIDS
- Y04S10/00—Systems supporting electrical power generation, transmission or distribution
- Y04S10/50—Systems or methods supporting the power network operation or management, involving a certain degree of interaction with the load-side end user applications
Landscapes
- Business, Economics & Management (AREA)
- Engineering & Computer Science (AREA)
- Economics (AREA)
- Health & Medical Sciences (AREA)
- Human Resources & Organizations (AREA)
- General Business, Economics & Management (AREA)
- Water Supply & Treatment (AREA)
- General Health & Medical Sciences (AREA)
- Theoretical Computer Science (AREA)
- Marketing (AREA)
- Primary Health Care (AREA)
- Strategic Management (AREA)
- Tourism & Hospitality (AREA)
- Physics & Mathematics (AREA)
- Public Health (AREA)
- General Physics & Mathematics (AREA)
- Power Engineering (AREA)
- Management, Administration, Business Operations System, And Electronic Commerce (AREA)
- Supply And Distribution Of Alternating Current (AREA)
Abstract
【解決手段】測定した負荷量の測定時刻と同時刻であり測定日よりも過去の異なる二つの日に測定された負荷量、測定時刻に測定されたエンタルピおよび負荷量を一組にして一つのデータを構成する履歴データを登録する登録部11と、予測時刻と同時刻であり予測日よりも過去の異なる二つの日に測定された負荷量、および予測時刻に予想されるエンタルピである予想エンタルピを、予測用パラメータとして取得する取得部12と、取得された予測用パラメータに基づいて、登録された履歴データから、予測用パラメータに類似する履歴データを選定する選定部13と、選定された履歴データを用い、代表となる履歴データを算出し、代表となる履歴データに含まれる、測定時刻に測定された負荷量に対応する負荷量を、予測時刻における負荷量とする予測部14と、を備える。
【選択図】図1
Description
外気エンタルピ=1.006×乾球温度+(1.805×乾球温度+2501)×絶対温度 … (1)
上記式(1)の絶対湿度[kg/kg(DA)]は、下記式(2)で求めることができる。
絶対湿度=18.015×水蒸気圧÷(29.064×(大気圧−水蒸気圧)) … (2)
上記式(2)の水蒸気圧[hPa]は、下記式(3)で求めることができる。
水蒸気圧=飽和水蒸気圧×相対湿度 … (3)
上記式(3)の飽和水蒸気圧[hPa]は、下記式(4)で求めることができる。
飽和水蒸気圧=6.11×10(7.5×T/(T+237.3)) … (4)
上記式(4)のTは乾球温度である。
(2)予測日、予測日の前日、予測日の7日前が、休日、平日、平日である場合、前日および直近の土曜日の同時刻における電力消費量を用いる。
(3)予測日、予測日の前日、予測日の7日前が、平日、休日、平日である場合、前日および直近の月曜日の同時刻における電力消費量を用いる。
(4)予測日、予測日の前日、予測日の7日前が、休日、休日、平日である場合、直近の土曜日および直近の日曜日の同時刻における電力消費量を用いる。
(6)予測日、予測日の前日、予測日の7日前が、休日、平日、休日である場合、前日および直近の土曜日の同時刻における電力消費量を用いる。
(7)予測日、予測日の前日、予測日の7日前が、平日、休日、休日である場合、前日および直近の月曜日の同時刻における電力消費量を用いる。
(8)予測日、予測日の前日、予測日の7日前が、ともに休日である場合、直近の土曜日および直近の日曜日の同時刻における電力消費量を用いる。
3 事例モデルDB
11 登録部
12 取得部
13 選定部
14 予測部
Claims (4)
- 予測時刻における負荷量を予測する負荷量予測装置であって、
測定した負荷量である第1負荷量の測定時刻と同時刻であり測定日よりも過去の異なる二つの日に測定された負荷量である第2負荷量および第3負荷量、ならびに、前記測定時刻に測定されたエンタルピおよび前記第1負荷量を一組にして一つのデータを構成する履歴データを登録する登録部と、
前記予測時刻と同時刻であり予測日よりも過去の異なる二つの日に測定された負荷量である第4負荷量および第5負荷量、ならびに、前記予測時刻に予想されるエンタルピである予想エンタルピを、予測用パラメータとして取得する取得部と、
前記取得部により取得された前記予測用パラメータに基づいて、前記登録部により登録された前記履歴データの中から、前記予測用パラメータに類似する一つまたは複数の前記履歴データを選定する選定部と、
前記選定部により選定された前記履歴データを用い、代表となる前記履歴データを算出し、当該代表となる前記履歴データに含まれる前記第1負荷量に対応する負荷量を、前記予測時刻における負荷量とする予測部と、
を備えることを特徴とする負荷量予測装置。 - 前記過去の異なる二つの日は、前記測定日または前記予測日の前日、および前記測定日または前記予測日の7日前の日である、
ことを特徴とする請求項1記載の負荷量予測装置。 - 予測時刻における負荷量を予測する負荷量予測方法であって、
測定した負荷量である第1負荷量の測定時刻と同時刻であり測定日よりも過去の異なる二つの日に測定された負荷量である第2負荷量および第3負荷量、ならびに、前記測定時刻に測定されたエンタルピおよび前記第1負荷量を一組にして一つのデータを構成する履歴データを登録する登録ステップと、
前記予測時刻と同時刻であり予測日よりも過去の異なる二つの日に測定された負荷量である第4負荷量および第5負荷量、ならびに、前記予測時刻に予想されるエンタルピである予想エンタルピを、予測用パラメータとして取得する取得ステップと、
前記取得ステップにおいて取得された前記予測用パラメータに基づいて、前記登録ステップにおいて登録された前記履歴データの中から、前記予測用パラメータに類似する一つまたは複数の前記履歴データを選定する選定ステップと、
前記選定ステップにおいて選定された前記履歴データを用い、代表となる前記履歴データを算出し、当該代表となる前記履歴データに含まれる前記第1負荷量に対応する負荷量を、前記予測時刻における負荷量とする予測ステップと、
を含むことを特徴とする負荷量予測方法。 - 前記過去の異なる二つの日は、前記測定日または前記予測日の前日、および前記測定日または前記予測日の7日前の日である、
ことを特徴とする請求項3記載の負荷量予測方法。
Priority Applications (3)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP2012147518A JP5902055B2 (ja) | 2012-06-29 | 2012-06-29 | 負荷量予測装置および負荷量予測方法 |
PCT/JP2013/063844 WO2014002645A1 (ja) | 2012-06-29 | 2013-05-17 | 負荷量予測装置および負荷量予測方法 |
TW102123150A TW201407530A (zh) | 2012-06-29 | 2013-06-28 | 負載量預測裝置及負載量預測方法 |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP2012147518A JP5902055B2 (ja) | 2012-06-29 | 2012-06-29 | 負荷量予測装置および負荷量予測方法 |
Publications (2)
Publication Number | Publication Date |
---|---|
JP2014010683A true JP2014010683A (ja) | 2014-01-20 |
JP5902055B2 JP5902055B2 (ja) | 2016-04-13 |
Family
ID=49782816
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
JP2012147518A Active JP5902055B2 (ja) | 2012-06-29 | 2012-06-29 | 負荷量予測装置および負荷量予測方法 |
Country Status (3)
Country | Link |
---|---|
JP (1) | JP5902055B2 (ja) |
TW (1) | TW201407530A (ja) |
WO (1) | WO2014002645A1 (ja) |
Cited By (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JP2017078925A (ja) * | 2015-10-20 | 2017-04-27 | 国際航業株式会社 | 電気料金情報予測システム |
WO2017104237A1 (ja) * | 2015-12-14 | 2017-06-22 | 日本電気株式会社 | 情報処理装置、その情報処理方法、およびプログラム |
JP2018063574A (ja) * | 2016-10-13 | 2018-04-19 | アズビル株式会社 | トレンド予測装置および負荷予測装置 |
JP2020205692A (ja) * | 2019-06-17 | 2020-12-24 | 大和ハウス工業株式会社 | 電力需要予測システム |
Families Citing this family (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JP6029901B2 (ja) * | 2012-09-13 | 2016-11-24 | アズビル株式会社 | 負荷量予測装置および負荷量予測方法 |
CN108090663B (zh) * | 2017-12-11 | 2020-06-26 | 囯网河北省电力有限公司电力科学研究院 | 供热机组深度调峰最低出力的评估方法及系统 |
CN111553529B (zh) * | 2020-04-27 | 2023-02-17 | 新奥数能科技有限公司 | 负荷预测方法、装置、计算机可读存储介质及电子设备 |
CN114330902A (zh) * | 2021-12-31 | 2022-04-12 | 河北工业大学 | 一种基于解耦机制的配电线路负荷预测方法 |
Citations (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JPH0695880A (ja) * | 1992-09-14 | 1994-04-08 | Yamatake Honeywell Co Ltd | 事例ベース推論装置 |
JP2002119956A (ja) * | 2000-10-17 | 2002-04-23 | Yamatake Corp | 濁度予測システム、濁度制御システムおよび濁度管理システム |
JP2009189085A (ja) * | 2008-02-04 | 2009-08-20 | Meidensha Corp | 電力・熱負荷の予測システム |
-
2012
- 2012-06-29 JP JP2012147518A patent/JP5902055B2/ja active Active
-
2013
- 2013-05-17 WO PCT/JP2013/063844 patent/WO2014002645A1/ja active Application Filing
- 2013-06-28 TW TW102123150A patent/TW201407530A/zh unknown
Patent Citations (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JPH0695880A (ja) * | 1992-09-14 | 1994-04-08 | Yamatake Honeywell Co Ltd | 事例ベース推論装置 |
JP2002119956A (ja) * | 2000-10-17 | 2002-04-23 | Yamatake Corp | 濁度予測システム、濁度制御システムおよび濁度管理システム |
JP2009189085A (ja) * | 2008-02-04 | 2009-08-20 | Meidensha Corp | 電力・熱負荷の予測システム |
Cited By (6)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JP2017078925A (ja) * | 2015-10-20 | 2017-04-27 | 国際航業株式会社 | 電気料金情報予測システム |
WO2017104237A1 (ja) * | 2015-12-14 | 2017-06-22 | 日本電気株式会社 | 情報処理装置、その情報処理方法、およびプログラム |
JPWO2017104237A1 (ja) * | 2015-12-14 | 2018-10-04 | 日本電気株式会社 | 情報処理装置、その情報処理方法、およびプログラム |
JP2018063574A (ja) * | 2016-10-13 | 2018-04-19 | アズビル株式会社 | トレンド予測装置および負荷予測装置 |
JP2020205692A (ja) * | 2019-06-17 | 2020-12-24 | 大和ハウス工業株式会社 | 電力需要予測システム |
JP7286428B2 (ja) | 2019-06-17 | 2023-06-05 | 大和ハウス工業株式会社 | 電力需要予測システム |
Also Published As
Publication number | Publication date |
---|---|
TW201407530A (zh) | 2014-02-16 |
JP5902055B2 (ja) | 2016-04-13 |
WO2014002645A1 (ja) | 2014-01-03 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
JP5902055B2 (ja) | 負荷量予測装置および負荷量予測方法 | |
Jain et al. | Data-driven model predictive control with regression trees—an application to building energy management | |
JP6292076B2 (ja) | 時系列予測アンサンブル | |
US20120095608A1 (en) | Demand prediction apparatus, and computer readable, non-transitory storage medium | |
US9559549B2 (en) | Energy management server, energy management method, and program | |
US9753477B2 (en) | Load forecasting for residential sector demand response | |
WO2021108224A1 (en) | Building control system with smart edge devices having embedded model predictive control | |
Wang et al. | Evaluation of operation performance of a multi-chiller system using a data-based chiller model | |
JP2015041379A (ja) | ビルエネルギ管理最適化 | |
JP2013005465A (ja) | 負荷量予測装置、負荷量予測方法および負荷量予測プログラム | |
JP4512074B2 (ja) | エネルギー需要予測方法、予測装置、プログラム及び記録媒体 | |
US9810443B2 (en) | Devices, methods, and systems for data-driven acceleration of deployed services | |
US20140278699A1 (en) | Modeling energy conversion in systems | |
Wang et al. | Event-driven optimal control of central air-conditioning systems: Event-space establishment | |
JP2014157457A (ja) | 予測装置および予測方法 | |
JP6029901B2 (ja) | 負荷量予測装置および負荷量予測方法 | |
JP5622698B2 (ja) | 目標電力設定システム、目標電力設定方法及びプログラム | |
JP6239901B2 (ja) | 制御装置および制御方法 | |
CN113225994B (zh) | 一种面向数据中心的智能空调控制方法 | |
Weber et al. | Realistic modeling of a combined heat and power plant in the context of mixed integer linear programming | |
US20140365023A1 (en) | Systems and Methods for Computer Implemented Energy Management | |
JP2018061314A (ja) | デマンドレスポンス計画システム、デマンドレスポンス計画方法、及びデマンドレスポンス計画プログラム | |
EP4083723B1 (en) | Evaluation apparatus, evaluation method, evaluation program, and control apparatus | |
WO2017073544A1 (ja) | 計画装置、計画方法およびプログラム | |
TWI578244B (zh) | 穩態製造效率產生方法、穩態製造效率產生系統及非暫態電腦可讀取記錄媒體 |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
A621 | Written request for application examination |
Free format text: JAPANESE INTERMEDIATE CODE: A621 Effective date: 20150325 |
|
A131 | Notification of reasons for refusal |
Free format text: JAPANESE INTERMEDIATE CODE: A131 Effective date: 20151203 |
|
A521 | Request for written amendment filed |
Free format text: JAPANESE INTERMEDIATE CODE: A523 Effective date: 20160126 |
|
TRDD | Decision of grant or rejection written | ||
A01 | Written decision to grant a patent or to grant a registration (utility model) |
Free format text: JAPANESE INTERMEDIATE CODE: A01 Effective date: 20160212 |
|
A61 | First payment of annual fees (during grant procedure) |
Free format text: JAPANESE INTERMEDIATE CODE: A61 Effective date: 20160309 |
|
R150 | Certificate of patent or registration of utility model |
Ref document number: 5902055 Country of ref document: JP Free format text: JAPANESE INTERMEDIATE CODE: R150 |