JP2012525519A - Shield plate installation structure at construction site - Google Patents

Shield plate installation structure at construction site Download PDF

Info

Publication number
JP2012525519A
JP2012525519A JP2012508390A JP2012508390A JP2012525519A JP 2012525519 A JP2012525519 A JP 2012525519A JP 2012508390 A JP2012508390 A JP 2012508390A JP 2012508390 A JP2012508390 A JP 2012508390A JP 2012525519 A JP2012525519 A JP 2012525519A
Authority
JP
Japan
Prior art keywords
panel
clamp
assembly
construction site
installation structure
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
JP2012508390A
Other languages
Japanese (ja)
Other versions
JP5465780B2 (en
Inventor
リー,デヨン
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
SEOK KANG CO Ltd
Original Assignee
SEOK KANG CO Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by SEOK KANG CO Ltd filed Critical SEOK KANG CO Ltd
Publication of JP2012525519A publication Critical patent/JP2012525519A/en
Application granted granted Critical
Publication of JP5465780B2 publication Critical patent/JP5465780B2/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G21/00Preparing, conveying, or working-up building materials or building elements in situ; Other devices or measures for constructional work
    • E04G21/32Safety or protective measures for persons during the construction of buildings
    • FMECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
    • F16ENGINEERING ELEMENTS AND UNITS; GENERAL MEASURES FOR PRODUCING AND MAINTAINING EFFECTIVE FUNCTIONING OF MACHINES OR INSTALLATIONS; THERMAL INSULATION IN GENERAL
    • F16LPIPES; JOINTS OR FITTINGS FOR PIPES; SUPPORTS FOR PIPES, CABLES OR PROTECTIVE TUBING; MEANS FOR THERMAL INSULATION IN GENERAL
    • F16L3/00Supports for pipes, cables or protective tubing, e.g. hangers, holders, clamps, cleats, clips, brackets
    • F16L3/24Supports for pipes, cables or protective tubing, e.g. hangers, holders, clamps, cleats, clips, brackets with a special member for attachment to profiled girders
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G21/00Preparing, conveying, or working-up building materials or building elements in situ; Other devices or measures for constructional work
    • E04G21/24Safety or protective measures preventing damage to building parts or finishing work during construction
    • E04G21/30Safety or protective measures preventing damage to building parts or finishing work during construction against mechanical damage or dirt, e.g. guard covers of stairs
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G21/00Preparing, conveying, or working-up building materials or building elements in situ; Other devices or measures for constructional work
    • E04G21/32Safety or protective measures for persons during the construction of buildings
    • E04G21/3204Safety or protective measures for persons during the construction of buildings against falling down
    • E04G21/3209Temporary tunnels specially adapted against falling objects
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G5/00Component parts or accessories for scaffolds
    • E04G5/12Canopies
    • FMECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
    • F16ENGINEERING ELEMENTS AND UNITS; GENERAL MEASURES FOR PRODUCING AND MAINTAINING EFFECTIVE FUNCTIONING OF MACHINES OR INSTALLATIONS; THERMAL INSULATION IN GENERAL
    • F16BDEVICES FOR FASTENING OR SECURING CONSTRUCTIONAL ELEMENTS OR MACHINE PARTS TOGETHER, e.g. NAILS, BOLTS, CIRCLIPS, CLAMPS, CLIPS OR WEDGES; JOINTS OR JOINTING
    • F16B2/00Friction-grip releasable fastenings
    • F16B2/02Clamps, i.e. with gripping action effected by positive means other than the inherent resistance to deformation of the material of the fastening
    • F16B2/06Clamps, i.e. with gripping action effected by positive means other than the inherent resistance to deformation of the material of the fastening external, i.e. with contracting action
    • FMECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
    • F16ENGINEERING ELEMENTS AND UNITS; GENERAL MEASURES FOR PRODUCING AND MAINTAINING EFFECTIVE FUNCTIONING OF MACHINES OR INSTALLATIONS; THERMAL INSULATION IN GENERAL
    • F16BDEVICES FOR FASTENING OR SECURING CONSTRUCTIONAL ELEMENTS OR MACHINE PARTS TOGETHER, e.g. NAILS, BOLTS, CIRCLIPS, CLAMPS, CLIPS OR WEDGES; JOINTS OR JOINTING
    • F16B5/00Joining sheets or plates, e.g. panels, to one another or to strips or bars parallel to them
    • F16B5/06Joining sheets or plates, e.g. panels, to one another or to strips or bars parallel to them by means of clamps or clips
    • FMECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
    • F16ENGINEERING ELEMENTS AND UNITS; GENERAL MEASURES FOR PRODUCING AND MAINTAINING EFFECTIVE FUNCTIONING OF MACHINES OR INSTALLATIONS; THERMAL INSULATION IN GENERAL
    • F16BDEVICES FOR FASTENING OR SECURING CONSTRUCTIONAL ELEMENTS OR MACHINE PARTS TOGETHER, e.g. NAILS, BOLTS, CIRCLIPS, CLAMPS, CLIPS OR WEDGES; JOINTS OR JOINTING
    • F16B5/00Joining sheets or plates, e.g. panels, to one another or to strips or bars parallel to them
    • F16B5/12Fastening strips or bars to sheets or plates, e.g. rubber strips, decorative strips for motor vehicles, by means of clips
    • FMECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
    • F16ENGINEERING ELEMENTS AND UNITS; GENERAL MEASURES FOR PRODUCING AND MAINTAINING EFFECTIVE FUNCTIONING OF MACHINES OR INSTALLATIONS; THERMAL INSULATION IN GENERAL
    • F16LPIPES; JOINTS OR FITTINGS FOR PIPES; SUPPORTS FOR PIPES, CABLES OR PROTECTIVE TUBING; MEANS FOR THERMAL INSULATION IN GENERAL
    • F16L3/00Supports for pipes, cables or protective tubing, e.g. hangers, holders, clamps, cleats, clips, brackets
    • F16L3/08Supports for pipes, cables or protective tubing, e.g. hangers, holders, clamps, cleats, clips, brackets substantially surrounding the pipe, cable or protective tubing
    • F16L3/12Supports for pipes, cables or protective tubing, e.g. hangers, holders, clamps, cleats, clips, brackets substantially surrounding the pipe, cable or protective tubing comprising a member substantially surrounding the pipe, cable or protective tubing
    • F16L3/1211Supports for pipes, cables or protective tubing, e.g. hangers, holders, clamps, cleats, clips, brackets substantially surrounding the pipe, cable or protective tubing comprising a member substantially surrounding the pipe, cable or protective tubing with a substantially-radial tightening or securing member

Landscapes

  • Engineering & Computer Science (AREA)
  • General Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Mechanical Engineering (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Refuge Islands, Traffic Blockers, Or Guard Fence (AREA)
  • Road Paving Structures (AREA)

Abstract

本発明は、都市の美観及び建設現場からの歩行者保護のために、建設現場と歩道の間に設置される遮蔽板設置構造に関する。本発明は、Hビーム10に連結固定される足場棒12に、クランプ30を用いて、それぞれ隣接する左右パネル20をクランプ固定するように構成するにあたり、各パネル20は、前面部21に補強リブ22を設けており、左右の側面部における中央部には、左右方向に対して傾斜して延びる組付凹部23及び組付凸部24を有し、これらにより左右に互いに組み付けられる。このようにして、緊密で堅固な組付けができる。クランプ30は、パネル20との係合のための係合片35が、ボディー31と連結片34とを連結する軸ピン33を軸として回転できる。傾斜した地面に設置する際、足場棒12を地面と同じ傾斜角にしても、クランプ30によるパネル20のクランプが可能なようにして、最小個数の足場棒12で設置できる。
【選択図】図1
The present invention relates to a shielding plate installation structure installed between a construction site and a sidewalk for the beauty of a city and the protection of pedestrians from the construction site. In the present invention, when the left and right panels 20 adjacent to each other are clamped and fixed to the scaffolding rod 12 connected and fixed to the H beam 10 by using the clamps 30, each panel 20 is provided with a reinforcing rib on the front portion 21. 22 is provided at the center of the left and right side portions, and has an assembly recess 23 and an assembly projection 24 that extend obliquely with respect to the left-right direction, and are assembled to each other by these. In this way, a tight and firm assembly is possible. In the clamp 30, the engagement piece 35 for engagement with the panel 20 can rotate around the shaft pin 33 that connects the body 31 and the connection piece 34. When installing on the inclined ground, even if the scaffold bar 12 has the same inclination angle as the ground, the panel 20 can be clamped by the clamp 30 so that the minimum number of scaffold bars 12 can be installed.
[Selection] Figure 1

Description

本発明は、建設現場と歩道との間に設置される建設現場の遮蔽板設置構造に関する。   The present invention relates to a shielding plate installation structure for a construction site installed between a construction site and a sidewalk.

一般に、各種建設工事時には建設現場と歩道との間に、都市の美観及び歩行者らの安全のために、遮蔽板が設置される。このような遮蔽板は、やはり組立式に構成して、設置費用の節減及び再使用が可能なようにしている。   Generally, during various construction works, a shielding plate is installed between the construction site and the sidewalk for the beauty of the city and the safety of pedestrians. Such a shielding plate is also constructed in an assembling manner so that installation costs can be reduced and reused.

図1は、今まで使われてきた建設現場の遮蔽板を示したものである。地面に適正な間隔を置いてHビーム100を垂直固定する。前記Hビーム100には横方向に複数個の足場棒102を連結形成する。パネル112には、足場棒102の前方に、図2におけるように、それぞれ前面部103の両側部における前方部分に係止凹部104及び係止凸部106が形成される。また、パネル112には、係止凹部及び係止凸部の後方に、それぞれパネル内側へと折れ曲がった支持片108、110が備えられる。このような複数枚のパネル112は、横方向に互いに組み付けられ、それぞれが足場棒102に組み付けられる。図3におけるようなクランプ116の上下の係合片118,120が、左右のパネル112の支持片108,110に係合する。この状態で、締め付けボルト122の締め付けによりクランプ116が後退することによって、パネル112が足場棒102に密着固定される。   FIG. 1 shows a shield at a construction site that has been used so far. The H beam 100 is fixed vertically with an appropriate distance from the ground. A plurality of scaffolding bars 102 are connected to the H beam 100 in the lateral direction. In the panel 112, a locking recess 104 and a locking protrusion 106 are formed in front of the scaffolding rod 102 and in front portions on both sides of the front surface portion 103, respectively, as shown in FIG. 2. Further, the panel 112 is provided with support pieces 108 and 110 that are bent inwardly of the panel behind the locking recess and the locking protrusion, respectively. Such a plurality of panels 112 are assembled to each other in the lateral direction, and each is assembled to the scaffold bar 102. The upper and lower engagement pieces 118 and 120 of the clamp 116 as shown in FIG. 3 engage with the support pieces 108 and 110 of the left and right panels 112. In this state, the clamp 116 is retracted by tightening the tightening bolt 122, whereby the panel 112 is tightly fixed to the scaffold bar 102.

しかし、用いられる各パネル112は、製造原価の節減及び軽量化のために、約0.5〜1.2mmの厚さの金属板材で折曲形成されるものである。単純に何らの補強のない前面部103の両側に、係止凹部104及び係止凸部106並びに支持片108、110が折曲形成される。そのため、パネル112の前面部103は、反りや衝撃に非常に弱く、施工過程で、または施工後において、弱い衝撃でも変形しやすい。そのため、寿命が非常に短く、再使用率が低いので、それだけ、購入費用の負担が増大する。   However, each panel 112 used is formed by bending a metal plate having a thickness of about 0.5 to 1.2 mm in order to reduce manufacturing costs and reduce weight. The locking recess 104, the locking projection 106, and the support pieces 108 and 110 are bent on both sides of the front surface portion 103 without any reinforcement. Therefore, the front surface portion 103 of the panel 112 is very weak against warping and impact, and is easily deformed even during weak construction or after construction. Therefore, since the lifetime is very short and the reuse rate is low, the burden of the purchase cost increases accordingly.

また、左右のパネル112同士が、それぞれ左右の側部における前方部分に露出形成される係止凹部104及び係止凸部106によって組み合わさるようにする。そのため、クランプ116のクランプ時に、各パネル112は、単純に足場棒102と密着されるだけで、パネル間には引っ張り力または結束力が全く与えられず、その間に隙間が発生してしまう。したがって、外観が美麗でないだけでなく、手抜き施工の誤解を招く恐れがある。また、強風または強い衝撃などにより、一部のクランプの係止が解除されたときには、当該パネルが、隣接パネルから歩道側へと突出し、完全に分離されるので、安全対策不備による事故に直結する。   Further, the left and right panels 112 are combined with each other by a locking concave portion 104 and a locking convex portion 106 that are exposed at the front portions of the left and right sides. Therefore, when the clamp 116 is clamped, each panel 112 is simply brought into close contact with the scaffolding rod 102, and no pulling force or binding force is given between the panels, and a gap is generated between them. Therefore, not only the appearance is not beautiful, but there is a risk of misunderstanding of hand-cutting construction. Also, when some of the clamps are released due to strong winds or strong impacts, the panel protrudes from the adjacent panel to the sidewalk and is completely separated, leading directly to an accident due to inadequate safety measures. .

特に、各パネル112をクランプ固定する各クランプ116は、足場棒102を組付けるボディーと、パネル112に引っ掛けられる係合片118、120とが互いに直角をなすように固定されている。図4におけるように、地面が傾斜した傾斜面124に設置する際にも、クランプを組付ける足場棒102は、地面が有する傾斜角と無関係に、パネル112が持つ支持片108、110と直角をなすように固定形成してこそ、クランプ116によるクランプを行うことができる。そのため、足場棒102の必要個数が増えて、遮蔽板の設置作業時に人力と時間が多く必要となる。これにより、施工費用が上昇することになるなどの多くの問題点がある。   In particular, each clamp 116 that clamps and fixes each panel 112 is fixed so that the body to which the scaffolding rod 102 is assembled and the engagement pieces 118 and 120 that are hooked on the panel 112 are perpendicular to each other. As shown in FIG. 4, also when installing on the inclined surface 124 where the ground is inclined, the scaffold bar 102 for assembling the clamp is perpendicular to the support pieces 108, 110 of the panel 112 regardless of the inclination angle of the ground. Clamping with the clamp 116 can be performed only by fixing as it is made. Therefore, the required number of scaffolding bars 102 increases, and a lot of manpower and time are required during the installation work of the shielding plate. This causes many problems such as an increase in construction costs.

特開平06-158870JP 06-158870 特開平06-136965JP 06-136965 韓国特許10-0536825Korean patent 10-0536825 韓国特許出願公開10-2008-0113476Korean Patent Application Publication 10-2008-0113476

本発明は、以下のことを可能にする建設現場の遮蔽板設置構造を提供することにその目的がある。用いられる板材の厚さに比べて、パネルの強度を向上させることができる。また、クランプによりパネルを締付保持する際、左右のパネル同士が緊密に密着され得るようにする。一部のクランプが本来の機能を喪失することになっても、左右のパネル間の堅固な結合力によって、一部のパネルが前方に突出する恐れが全くないことから、安全に利用することができる。また、傾斜面への設置時には、足場棒が傾斜面と同じ傾斜角を有していても、クランプによりパネルを堅固に締付保持できるので、足場棒の必要個数を節減することができる、   An object of the present invention is to provide a shield plate installation structure at a construction site that enables the following. The strength of the panel can be improved compared to the thickness of the plate material used. In addition, when the panels are clamped and held by the clamp, the left and right panels can be brought into close contact with each other. Even if some clamps lose their original function, there is no possibility that some panels will protrude forward due to the firm coupling force between the left and right panels. it can. In addition, when installing on an inclined surface, even if the scaffold bar has the same inclination angle as the inclined surface, the panel can be firmly tightened and held by the clamp, so the necessary number of scaffold bars can be reduced.

本発明の目的は、次のように構成される建設現場の遮蔽板設置構造によって達成される。パネルの前面部に少なくとも一つ以上の補強リブが形成されるようにする。左右の側面部の中央部には、一側前方へと傾斜した組付凹部と組付凸部が形成されるようにして、パネル間にて左右方向から相互の組付けが行われるようにする。クランプは、足場棒を組付けるボディーに対して、係合片を連結支持する連結片が回転するようにして、パネルに対して足場棒が傾斜した場合にも締付保持を可能にする。   The object of the present invention is achieved by a shielding plate installation structure at a construction site configured as follows. At least one reinforcing rib is formed on the front surface of the panel. In the center part of the left and right side parts, an assembling concave part and an assembling convex part that are inclined forward one side are formed so that mutual assembling is performed between the panels from the left and right directions. . The clamp allows the coupling piece for coupling and supporting the rotating piece to rotate with respect to the body to which the scaffold bar is assembled, so that the clamp can be held even when the scaffold bar is inclined with respect to the panel.

本発明に用いられる各パネル20は、その前面部に備えられる補強リブ22によって強度が補強されるので、使用寿命を延長することができることから、その分だけ施工費用を節減することができる。   Since each panel 20 used in the present invention has its strength reinforced by the reinforcing ribs 22 provided on the front surface portion thereof, the service life can be extended, so that the construction cost can be reduced accordingly.

また、左右のパネル20は、それぞれ左右の側面部における中央部にて、左右方向に対して傾斜して延びるように形成される組付凹部23及び組付凸部24により、左右方向に対し傾斜して組み付けられる。このようにすることで、クランプ30を用いた締付保持の際、左右のパネル20は、組付凹部23及び組付凸部24に備えられる傾斜面27、28の案内により、より緊密に密着される。したがって、左右のパネル20の間に隙間が発生する恐れがなく、滑らかで小ぎれいな外観を維持できるのはもちろんのこと、手抜き施工に対する誤解を招く恐れがない。また、強風や強い衝撃などにより一部のクランプ30の締付保持機能が喪失された際にも、当該パネルは、組付凹部23と組付凸部24との組付けにより、前方へと分離される恐れが全くない。そのため、左右のパネル間の堅固な組付け力を維持することができ、施工後、パネルの分離によって、安全対策不備による事故が発生する危険性をなくすことができる。   In addition, the left and right panels 20 are inclined with respect to the left and right directions by the assembling concave portions 23 and the assembling convex portions 24 formed so as to be inclined and extend with respect to the left and right directions at the center portions of the left and right side surfaces, respectively. And assembled. By doing so, the left and right panels 20 are more closely adhered to each other by the guide of the inclined surfaces 27 and 28 provided in the assembling concave portion 23 and the assembling convex portion 24 at the time of tightening and holding using the clamp 30. Is done. Therefore, there is no possibility that a gap is generated between the left and right panels 20, and a smooth and neat appearance can be maintained. Further, even when the tightening and holding function of some clamps 30 is lost due to strong winds or strong impacts, the panel is separated forward by the assembly of the assembly recesses 23 and the assembly projections 24. There is no fear of being done. Therefore, a firm assembly force between the left and right panels can be maintained, and the risk of an accident due to inadequate safety measures can be eliminated by separating the panels after construction.

さらに、パネル20を足場棒12にクランプ固定するクランプ30の、上下の係合片35は、ボディー31に対し、軸ピン33によって連結されている。足場棒12がパネル20と直角をなさない場合にも、クランプ30によるパネル20の締付保持が可能なようにするのである。これにより、傾斜面に設置する際、足場棒12を、傾斜面と同じ傾斜角を有するように固定設置すれば、足場棒12の必要個数を減らすことができる。そのため、施工時の時間及び人力を節減できるのはもちろんのこと、これによって施工費用を節減できるなど多くの効果がある。   Further, the upper and lower engaging pieces 35 of the clamp 30 that clamps and fixes the panel 20 to the scaffolding rod 12 are connected to the body 31 by the shaft pin 33. Even when the scaffolding bar 12 does not form a right angle with the panel 20, the clamp 20 can be clamped and held by the clamp 30. Thereby, when installing on the inclined surface, if the scaffolding bar 12 is fixedly installed so as to have the same inclination angle as the inclined surface, the necessary number of scaffolding bars 12 can be reduced. Therefore, not only can the time and manpower during construction be saved, but there are many effects such as saving construction costs.

従来発明の要部の斜視図である。It is a perspective view of the principal part of conventional invention. 従来発明のパネルの分解斜視図である。It is a disassembled perspective view of the panel of conventional invention. 従来発明のクランプの斜視図である。It is a perspective view of the clamp of conventional invention. 従来発明についての、傾斜面に設置する際の一部背面構成図である。It is a partial back block diagram at the time of installing in an inclined surface about conventional invention. 本発明の要部の斜視図である。It is a perspective view of the principal part of this invention. 本発明の要部の平面構成図である。It is a plane block diagram of the principal part of this invention. 本発明の要部の側面構成図である。It is a side block diagram of the principal part of this invention. 本発明に用いられるパネルの斜視図である。It is a perspective view of the panel used for this invention. 本発明に用いられるパネルの一部分解図である。It is a partial exploded view of the panel used for this invention. 本発明に用いられるパネルの組立図である。It is an assembly drawing of the panel used for this invention. 本発明に用いられるクランプの斜視図である。It is a perspective view of the clamp used for this invention. 本発明に用いられるクランプの断面構成図である。It is a section lineblock diagram of a clamp used for the present invention. 本発明を傾斜面に設置する際の一部背面構成図である。It is a partial back surface block diagram at the time of installing this invention in an inclined surface.

以下、本発明の好ましい実施例を添付の図面に基づいて詳細に説明する。ただし、図面中に同一の構成要素には可能なかぎり同一の図面符号を付し、関連した公知技術や機能に対する具体的な説明は、本発明の要旨が曖昧になることを避けるために省略することにする。   Hereinafter, preferred embodiments of the present invention will be described in detail with reference to the accompanying drawings. However, in the drawings, the same components are denoted by the same reference numerals as much as possible, and specific descriptions of related known techniques and functions are omitted to avoid obscuring the gist of the present invention. I will decide.

図5は、本発明の要部の斜視図である。本発明においては、建設現場と歩道との間にて、適正な間隔を置いて垂直固定されるHビーム10に、複数個の足場棒12が、上下に適正な間隔を有するようにして、横方向に連結固定される。前記足場棒12の前方には、金属板材でもって折曲形成される複数個のパネル20を、左右に並べて結合形成する。そして、それぞれが足場棒12に組付けられる複数個のクランプ30を用い、これらそれぞれが、隣接している左右のパネル20を、同時にクランプ固定するように構成される。   FIG. 5 is a perspective view of a main part of the present invention. In the present invention, a plurality of scaffolding rods 12 are arranged on the H beam 10 that is vertically fixed at an appropriate interval between the construction site and the sidewalk so that the plurality of scaffolding bars 12 have an appropriate interval in the vertical direction. Connected and fixed in the direction. In front of the scaffolding rod 12, a plurality of panels 20 bent with a metal plate are arranged side by side and joined together. And each using the some clamp 30 assembled | attached to the scaffolding rod 12, each of these is comprised so that the left and right panels 20 which adjoin may be clamp-fixed simultaneously.

本発明に用いられるHビーム10と足場棒12は、建設工事の際によく利用されている一般的なものである。Hビーム10は、建設現場を取り囲むように、複数個が地面に垂直に固定される。また、足場棒12は、Hビーム10の間に、上下に適正な間隔を維持するように横方向に連結固定される。   The H beam 10 and the scaffold bar 12 used in the present invention are general ones that are often used during construction work. A plurality of H beams 10 are fixed vertically to the ground so as to surround the construction site. In addition, the scaffold bar 12 is connected and fixed in the horizontal direction between the H beams 10 so as to maintain an appropriate vertical distance.

図8乃至図10には、本発明に用いられるパネルを示す。パネル20は、総じて左右の幅が狭く上下に長い形態であり、その前面部21に一つ以上の補強リブ22が上下に長く形成される。前面部21から折曲形成される左右の側面部の中央部には、隣接するパネル20間の結合のために、それぞれが左右方向に対して傾斜して延びる組付凹部23及び組付凸部24が形成される。また、左右の側面部の後端には、それぞれ前方へと折れ曲がってクランプ30に係合される支持片25、26が形成される。   8 to 10 show a panel used in the present invention. The panel 20 generally has a narrow left and right width and is vertically long, and one or more reinforcing ribs 22 are formed vertically on the front surface portion 21 thereof. In the central part of the left and right side parts bent from the front part 21, an assembling recess 23 and an assembling protrusion each extend obliquely with respect to the left-right direction for coupling between adjacent panels 20. 24 is formed. In addition, support pieces 25 and 26 that are bent forward and engaged with the clamp 30 are formed at the rear ends of the left and right side portions.

さらに、パネル20の両側部に備えられる組付凹部23及び組付凸部24は、雄雌結合のためのものである。組付凹部23は、組付凸部24が余裕を持って組み付けられるようにするならば、クランプ30によるクランプ時に、傾斜面27,28の案内によって、より深くまた安全に結合される。のみならず、左右のパネル20間の緊密な密着が可能となる。   Furthermore, the assembly recess 23 and the assembly projection 24 provided on both sides of the panel 20 are for male-female coupling. If the assembly convex portion 24 is assembled with a margin, the assembly concave portion 23 is more deeply and safely coupled by the guide of the inclined surfaces 27 and 28 when clamped by the clamp 30. In addition, close contact between the left and right panels 20 is possible.

図11及び図12には、本発明に用いられるクランプを示す。各パネル20を足場棒12にクランプ固定するクランプ30においては、足場棒12を組付けるU状のボディー31の後方に、締め付けボルト32がねじ結合される。ボディーの上下端部には、それぞれ軸ピン33を介して、連結片34が回転可能に連結される。前記連結片34には、それぞれ一対の係合片35が、それぞれピン36によって回転可能なように連結構成される。   11 and 12 show a clamp used in the present invention. In the clamp 30 that clamps and fixes each panel 20 to the scaffolding rod 12, a fastening bolt 32 is screwed to the rear of the U-shaped body 31 to which the scaffolding rod 12 is assembled. A connecting piece 34 is rotatably connected to the upper and lower ends of the body via shaft pins 33. A pair of engaging pieces 35 are connected to the connecting pieces 34 so as to be rotatable by pins 36, respectively.

本発明において、従来のように、建設現場と歩道との境界線に、複数個のHビーム10を、適正な間隔を置いて垂直に固定する。前記各Hビーム10の間ごとにて、上下に適正な間隔を有するように足場棒12を横方向に連結固定する。また、足場棒12の前方には規格化された複数枚のパネル20を左右に結合形成する。そして、それぞれが足場棒12に結合されるクランプ30の上下係合片35が、隣接している左右パネル20の支持片25、26と係合されるようにした状態で、締め付けボルト32を締め付けて足場棒12からクランプ30を後退させる。すると、各パネル20が足場棒12に密着固定されて遮蔽板Aを形成することになる。   In the present invention, as in the prior art, a plurality of H beams 10 are fixed vertically at appropriate intervals at the boundary between the construction site and the sidewalk. The scaffolding rods 12 are connected and fixed in the lateral direction so as to have an appropriate space in the vertical direction between the H beams 10. In addition, a plurality of standardized panels 20 are coupled to the front of the scaffold bar 12 on the left and right. Then, the fastening bolts 32 are tightened with the upper and lower engaging pieces 35 of the clamps 30 that are respectively coupled to the scaffolding bars 12 engaged with the supporting pieces 25 and 26 of the adjacent left and right panels 20. Then, the clamp 30 is retracted from the scaffold bar 12. Then, each panel 20 is closely fixed to the scaffolding rod 12 to form the shielding plate A.

ここで、各パネル20は、その前面部21に少なくとも一つ以上の補強リブ22が折曲形成されて、パネル20の製作時に用いられる板材の厚さに比べて、遥かに強い曲げ力と強度を有することになる。そのため、取り扱いが容易で、また、外部の衝撃にも変形を受ける恐れが少なく、使用寿命を延長させることができる。   Here, each panel 20 has at least one or more reinforcing ribs 22 formed at the front surface portion 21 so that the bending force and strength are much stronger than the thickness of the plate material used when the panel 20 is manufactured. Will have. Therefore, it is easy to handle and is less likely to be deformed by an external impact, and the service life can be extended.

また、各パネル20の結合手段である組付凹部23と組付凸部24は、左右の側面部の中央部に形成されており、左右方向に結合される。そのため、左右のパネル20同士を組みつけた後、クランプ30によるクランプ固定の際、一部のクランプ30が本来の機能を果たせなくても、当該パネルが、隣接の他のパネルとの結合力により、前方に分離される恐れが全くなく、本来の機能を果たすことができる。   Further, the assembly recess 23 and the assembly projection 24 which are the coupling means of each panel 20 are formed at the center of the left and right side surfaces, and are coupled in the left-right direction. For this reason, after the left and right panels 20 are assembled together, even when some clamps 30 cannot perform their original functions when the clamps 30 are fixed by the clamps 30, the panels are affected by the bonding force with other adjacent panels. There is no fear of being separated forward, and the original function can be achieved.

さらに、各パネル20の左右の側面部に備えられる組付凹部23及び組付凸部24は、それぞれ左右方向に対して傾斜して延びるように形成されている。クランプ30を用いた締付保持の際、引っ張り力が作用すればするほど、この組付凸部24は組付凹部23に、より深く結合されて、完全な結合ができる。また、このとき、左右のパネル20は、組付凹部23及び組付凸部24が有する傾斜面27、28によって、相互間に引っ張り力が作用することになる。そのため、左右のパネル20の間に隙間が発生する恐れが全くない。したがって、安定感があり、且つ堅固な施工が可能になる。   Furthermore, the assembly recesses 23 and the assembly projections 24 provided on the left and right side portions of each panel 20 are formed so as to extend while being inclined with respect to the left-right direction. The more the pulling force is applied at the time of clamping and holding using the clamp 30, the deeper the assembling convex part 24 is coupled to the assembling concave part 23, and the complete coupling can be achieved. At this time, the left and right panels 20 are subjected to a tensile force between the inclined surfaces 27 and 28 of the assembly concave portion 23 and the assembly convex portion 24. Therefore, there is no possibility that a gap is generated between the left and right panels 20. Therefore, there is a sense of stability and a solid construction is possible.

また、地面が傾斜した傾斜面に設置する際には、図13におけるように、Hビーム10に連結固定される足場棒12は、パネル20との間において有する傾斜角に関係なく、その地面と同じ傾斜角を有するようにHビーム10に連結固定する。そして、左右パネル20の支持片25、26と出会う地点にて、クランプ30を組付ける。前記クランプ30のボディー31が有する傾斜角に関係なく、そのボディー31から係合片35を連結する連結片34について、軸ピン33を軸として回転させて、係合片35の係止部が、パネル20が有する支持片25、26と直角をなすようにする。このようにした状態で、支持片25、26と係合されるようにした後、締め付けボルト32を締め付けると、各パネル20がクランプ30の締付によって足場棒12に密着固定されて、クランプされる。そのため、足場棒12の必要個数を節減できる分だけ、遮蔽板Aの設置時間と人力及び費用を節減することができる。   In addition, when installing on an inclined surface where the ground is inclined, as shown in FIG. 13, the scaffolding rod 12 connected and fixed to the H beam 10 is connected to the ground regardless of the inclination angle with the panel 20. The H beam 10 is connected and fixed so as to have the same inclination angle. And the clamp 30 is assembled | attached in the point which meets the support pieces 25 and 26 of the left-right panel 20. FIG. Regardless of the inclination angle of the body 31 of the clamp 30, the connecting piece 34 that connects the engaging piece 35 from the body 31 is rotated about the shaft pin 33, and the engaging portion of the engaging piece 35 is The panel 20 is perpendicular to the support pieces 25 and 26 of the panel 20. In this state, after engaging with the support pieces 25 and 26 and then tightening the tightening bolt 32, each panel 20 is tightly fixed to the scaffold bar 12 by the clamp 30 and clamped. The Therefore, the installation time, manpower, and cost of the shielding plate A can be reduced by the amount that can reduce the required number of scaffolding bars 12.

A…遮蔽板; 10…Hビーム; 12…足場棒; 20…パネル;
21…前面部; 22…補強リブ; 23…組付凹部; 24…組付凸部;
25、26…支持片; 27、28…傾斜面;
30…クランプ; 31…ボディー; 32…締め付けボルト; 33…軸ピン;
34…連結片; 35…係合片; 36…ピン
A ... Shield plate; 10 ... H beam; 12 ... Scaffolding bar; 20 ... Panel;
21 ... Front part; 22 ... Reinforcing rib; 23 ... Assembly concave part; 24 ... Assembly convex part;
25, 26 ... support pieces; 27, 28 ... inclined surfaces;
30 ... Clamp; 31 ... Body; 32 ... Tightening bolt; 33 ... Shaft pin;
34 ... Connecting piece; 35 ... Engagement piece; 36 ... Pin

Claims (2)

地面に固定されるHビームを介して足場棒が連結され、足場棒に組み付けられるクランプの上下の係合片は、隣接する左右のパネルの支持片と係合され、締め付けボルトの締め付けによってパネルをクランプするように構成された建設現場の遮蔽板設置構造において、
前記各パネル(20)における、その前面部(21)には、一つ以上の補強リブ(22)が形成され、また、支持片(25、26)を有する左右の側面部の中央部には、組付凹部(23)及び組付凸部(24)が形成され、これにより、パネル(20)間での左右方向の組み付けが行われ、
クランプ(30)が有する係合片(35)は、足場棒(12)を組付けるボディー(31)に対して、軸ピン(33)により連結される連結片(34)を介して、回転可能に連結されていることを特徴とする、建設現場の遮蔽板設置構造。
The scaffolding rod is connected via an H beam fixed to the ground, and the upper and lower engagement pieces of the clamp assembled to the scaffolding rod are engaged with the support pieces of the adjacent left and right panels, and the panel is removed by tightening the fastening bolts. In the construction site shielding plate installation structure configured to clamp,
One or more reinforcing ribs (22) are formed on the front surface (21) of each panel (20), and at the center of the left and right side surfaces having support pieces (25, 26). , An assembly recess (23) and an assembly projection (24) are formed, whereby assembly in the left-right direction between the panels (20) is performed,
The engagement piece (35) of the clamp (30) is rotatable via a connecting piece (34) connected to the body (31) for assembling the scaffolding rod (12) by the shaft pin (33). A shield plate installation structure at a construction site, characterized in that it is connected to.
前記各パネル(20)が有する組付凹部(23)及び組付凸部(24)は、いずれも、左右方向に対して傾斜して延びるように設けられたことを特徴とする、請求項1に記載の建設現場の遮蔽板設置構造。   The assembly recesses (23) and the assembly projections (24) of each panel (20) are both provided to be inclined and extend with respect to the left-right direction. Construction site shielding plate installation structure described in 1.
JP2012508390A 2009-05-01 2010-04-22 Shield plate installation structure at construction site Expired - Fee Related JP5465780B2 (en)

Applications Claiming Priority (3)

Application Number Priority Date Filing Date Title
KR10-2009-0038760 2009-05-01
KR1020090038760A KR101077823B1 (en) 2009-05-01 2009-05-01 Installation structure of screening panel for construction site
PCT/KR2010/002515 WO2010126250A2 (en) 2009-05-01 2010-04-22 Cover board installation structure for a construction site

Publications (2)

Publication Number Publication Date
JP2012525519A true JP2012525519A (en) 2012-10-22
JP5465780B2 JP5465780B2 (en) 2014-04-09

Family

ID=43032656

Family Applications (1)

Application Number Title Priority Date Filing Date
JP2012508390A Expired - Fee Related JP5465780B2 (en) 2009-05-01 2010-04-22 Shield plate installation structure at construction site

Country Status (4)

Country Link
JP (1) JP5465780B2 (en)
KR (1) KR101077823B1 (en)
CN (1) CN102428239B (en)
WO (1) WO2010126250A2 (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN114482124A (en) * 2020-11-11 2022-05-13 金岭 Piping lane support and have piping lane of this piping lane support

Families Citing this family (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR101127138B1 (en) * 2011-05-25 2012-03-20 김영택 Clamp for fixing safety fence panel
CN103680315B (en) * 2013-12-10 2016-01-06 京东方科技集团股份有限公司 A kind of mosaic screen and display device
CN111927129A (en) * 2020-07-23 2020-11-13 界首市天瓴建筑工程有限公司 Door and window isolated column for high-rise building construction

Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH06136964A (en) * 1992-10-23 1994-05-17 Nippon Kiden Kk Temporary shroud
JPH06136965A (en) * 1992-10-23 1994-05-17 Nippon Kiden Kk Support frame bracket for temporary shroud
JPH0643172U (en) * 1992-11-10 1994-06-07 昭和アルミニウム株式会社 Panel mounting device used for enclosures at construction sites
JPH06158870A (en) * 1992-11-27 1994-06-07 Nippon Kiden Kk Temporary shroud
JPH0710301U (en) * 1993-07-19 1995-02-14 株式会社三共 Temporary enclosure panel
JP2000064625A (en) * 1998-08-21 2000-02-29 Kawatetsu Galvanizing Co Ltd Fitting for temporary enclosure panel

Family Cites Families (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN2069449U (en) * 1990-06-11 1991-01-16 蒋明 Safety net fastener
PL332966A1 (en) * 1996-10-25 1999-10-25 Partek Paroc Oy Ab Construction of a joint for panels and method of using same
US6324809B1 (en) * 1997-11-25 2001-12-04 Premark Rwp Holdings, Inc. Article with interlocking edges and covering product prepared therefrom
KR100536825B1 (en) * 2005-10-17 2005-12-14 주식회사 누리플랜 Construction and dismantle method of soundproofed wall apparatus for construction
KR20080113476A (en) * 2007-06-25 2008-12-31 (주)삼정스틸 Sound proofing wall pipe clamp

Patent Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH06136964A (en) * 1992-10-23 1994-05-17 Nippon Kiden Kk Temporary shroud
JPH06136965A (en) * 1992-10-23 1994-05-17 Nippon Kiden Kk Support frame bracket for temporary shroud
JPH0643172U (en) * 1992-11-10 1994-06-07 昭和アルミニウム株式会社 Panel mounting device used for enclosures at construction sites
JPH06158870A (en) * 1992-11-27 1994-06-07 Nippon Kiden Kk Temporary shroud
JPH0710301U (en) * 1993-07-19 1995-02-14 株式会社三共 Temporary enclosure panel
JP2000064625A (en) * 1998-08-21 2000-02-29 Kawatetsu Galvanizing Co Ltd Fitting for temporary enclosure panel

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN114482124A (en) * 2020-11-11 2022-05-13 金岭 Piping lane support and have piping lane of this piping lane support

Also Published As

Publication number Publication date
JP5465780B2 (en) 2014-04-09
KR101077823B1 (en) 2011-10-28
WO2010126250A2 (en) 2010-11-04
CN102428239A (en) 2012-04-25
CN102428239B (en) 2014-10-15
KR20100119690A (en) 2010-11-10
WO2010126250A3 (en) 2011-03-10

Similar Documents

Publication Publication Date Title
JP5465780B2 (en) Shield plate installation structure at construction site
KR100511681B1 (en) Soundproof plate coupled structure for soundproofed wall
JPH08270207A (en) Main rope post
JP2015045162A (en) Guard fence
KR101712851B1 (en) Interior and exterior of the building panel fasteners
JP5559102B2 (en) Shaft assembly joining equipment
JP5004918B2 (en) Formwork structure for decorative plate member
KR101087737B1 (en) Wall for building
JP7201171B2 (en) Mounting bracket for extruded cement board flooring and flooring mounting structure using it
KR101938974B1 (en) Joint unit for forms
JP3162329U (en) Grating connection structure
JP6723882B2 (en) Width of temporary scaffolding timber
JP6782887B2 (en) Aperture reinforcement unit
JP5723477B2 (en)
JP6389405B2 (en) Guard fence construction method and construction jig
JP6220528B2 (en) Building structures and unit buildings
KR101876141B1 (en) Recycling utility for beam installation
KR200466569Y1 (en) Safety guard rail for mounting beam
KR20130004588U (en) A temporary structure for construction
KR101187965B1 (en) A lattice girder for tunnel construction
JP4160537B2 (en) Connector
JP2004183307A (en) Scaffold bridge member and its fitting structure
KR101612083B1 (en) Aluminum form panel For connection Clip device
JP5284730B2 (en) Fence strut member and fence having the strut member
JP5767191B2 (en)

Legal Events

Date Code Title Description
A131 Notification of reasons for refusal

Free format text: JAPANESE INTERMEDIATE CODE: A131

Effective date: 20130108

A521 Request for written amendment filed

Free format text: JAPANESE INTERMEDIATE CODE: A523

Effective date: 20130404

TRDD Decision of grant or rejection written
A01 Written decision to grant a patent or to grant a registration (utility model)

Free format text: JAPANESE INTERMEDIATE CODE: A01

Effective date: 20131224

A61 First payment of annual fees (during grant procedure)

Free format text: JAPANESE INTERMEDIATE CODE: A61

Effective date: 20140122

R150 Certificate of patent or registration of utility model

Ref document number: 5465780

Country of ref document: JP

Free format text: JAPANESE INTERMEDIATE CODE: R150

Free format text: JAPANESE INTERMEDIATE CODE: R150

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

LAPS Cancellation because of no payment of annual fees