JP2010236311A - Method for constructing pile foundation, and the pile foundation for use in the same - Google Patents

Method for constructing pile foundation, and the pile foundation for use in the same Download PDF

Info

Publication number
JP2010236311A
JP2010236311A JP2009087046A JP2009087046A JP2010236311A JP 2010236311 A JP2010236311 A JP 2010236311A JP 2009087046 A JP2009087046 A JP 2009087046A JP 2009087046 A JP2009087046 A JP 2009087046A JP 2010236311 A JP2010236311 A JP 2010236311A
Authority
JP
Japan
Prior art keywords
ready
filler
pile foundation
pile
excavation
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
JP2009087046A
Other languages
Japanese (ja)
Inventor
Kenji Takano
謙二 高野
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Mitani Sekisan Co Ltd
Original Assignee
Mitani Sekisan Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Mitani Sekisan Co Ltd filed Critical Mitani Sekisan Co Ltd
Priority to JP2009087046A priority Critical patent/JP2010236311A/en
Publication of JP2010236311A publication Critical patent/JP2010236311A/en
Pending legal-status Critical Current

Links

Images

Landscapes

  • Piles And Underground Anchors (AREA)
  • Placing Or Removing Of Piles Or Sheet Piles, Or Accessories Thereof (AREA)

Abstract

<P>PROBLEM TO BE SOLVED: To provide a method for constructing a pile foundation, which can downsize a shape of a footing attached to an upper portion of each prefabricated pile, and the pile foundation for use in the method. <P>SOLUTION: In the method for constructing the pile foundation, two drilled holes 2 are drilled in such a manner as to communicate with each other; each of the drilled holes 2 communicating with each other is filled with cement milk (filler) 3; the prefabricated concrete pile 1 is erected in each of the drilled holes 2 filled with the cement milk (filler) 3; and the two prefabricated concrete piles 1 are integrated together by means of the cement milk (filler) 3 in a gap between each of the drilled holes 2 and the prefabricated concrete pile 1. In the pile foundation, the prefabricated concrete pile 1 is erected in each 2 of the two drilled holes 2 communicating with each other; and the two prefabricated concrete piles 1 are integrated together by means of the cement milk (filler) 3 which is infilled into the gap between each of the drilled holes 2 and the prefabricated concrete pile 1. <P>COPYRIGHT: (C)2011,JPO&INPIT

Description

本発明は、複数本の既製杭から構成される杭基礎の施工方法及びその杭基礎に関する。   The present invention relates to a method for constructing a pile foundation composed of a plurality of ready-made piles and the pile foundation.

大型の構造物の建設においては、大径の杭が使用されることがあり、大径の現場打ち杭に限らず、大径の既製杭が使用される。   In the construction of a large structure, a large-diameter pile may be used, and a large-diameter ready-made pile is used, not limited to a large-diameter field pile.

しかし、既製杭の直径は、技術開発の進展により拡大されてきているが、未だ製造技術と規格上の制約から最大直径に上限がある。
そのため、柱荷重が大きく1本の既製杭の支持力では十分でない場合には、1個の柱に対してフーチングを介して数本の既製杭で柱荷重を支持する必要がある。
その場合、構造物を支持する既製杭は、一本ごとにある間隔を保って施工されている。
そして、杭の最小間隔について、例えば、「建築基礎構造設計指針」(社団法人日本建築学会発行、2002年4月15日、第2版第2刷)の第199頁第6〜24行(非特許文献1参照)に記載があり、この記載によれば、杭の最小間隔の目安値として、埋込み杭の場合は、杭径の2倍以上としている。
However, the diameter of ready-made piles has been expanded due to the progress of technological development, but there is still an upper limit on the maximum diameter due to restrictions in manufacturing technology and standards.
Therefore, when the column load is large and the supporting force of one ready-made pile is not sufficient, it is necessary to support the column load with several ready-made piles via a footing for one column.
In that case, the ready-made pile which supports a structure is constructed with a certain space | interval maintained for every one.
And about the minimum space | interval of a pile, for example, "Architectural foundation structure design guideline" (The Architectural Institute of Japan, April 15, 2002, the 2nd edition 2nd printing), 199 pages 6-24 lines (non-) According to this description, in the case of an embedded pile, the value is at least twice the diameter of the pile.

図9は、従来の基礎構造を示すもので、2本の既製コンクリート杭の上部にフーチングを取り付けた状態を示す基礎構造で、(a)はその平面図、(b)はその断面図である。
図9に示す従来の基礎構造における2本の既製コンクリート杭の間の間隔は前記の非特許文献1の記載に基づいて、既製コンクリート杭の径の2倍以上となっている。
FIG. 9 shows a conventional foundation structure, which is a foundation structure in which a footing is attached to the upper part of two ready-made concrete piles, (a) is a plan view thereof, and (b) is a sectional view thereof. .
The distance between the two ready-made concrete piles in the conventional foundation structure shown in FIG. 9 is at least twice the diameter of the ready-made concrete pile based on the description of Non-Patent Document 1.

この場合、2本の既製コンクリート杭の間の間隔は、既製コンクリート杭の径の2.5倍以上離れているから、柱にかかる荷重は柱から既製コンクリート杭へとフーチングによって分散されて伝達されることになる。
そのため、フーチングは2本の既製コンクリート杭の間の間隔を覆う必要があるので、相応の大きさのものになる。
In this case, since the distance between the two ready-made concrete piles is more than 2.5 times the diameter of the ready-made concrete piles, the load applied to the pillars is distributed and transmitted from the pillars to the ready-made concrete piles by footing. Will be.
Therefore, since the footing needs to cover the space between the two ready-made concrete piles, the footing has a corresponding size.

また、柱からの荷重を分散して2本の既製コンクリート杭に伝達するので、フーチングはせん断力及び曲げ応力等に耐えるものとしなければならない。
したがって、フーチングは構造的に相応の大きさのものとなり、これには所要のコンクリート強度及び鉄筋量等の材料および型枠が必要となる。
また、このようなフーチング施工をするには時間と人手も要することになる。
さらに、このフーチングのための地面掘削が余分に必要となることも多く、これにも仮設材料や時間及び人手を要する。
In addition, since the load from the column is distributed and transmitted to two ready-made concrete piles, the footing must withstand shearing force and bending stress.
Therefore, the footing has a structurally appropriate size, and this requires materials and formwork such as the required concrete strength and the amount of reinforcing bars.
In addition, such footing construction requires time and manpower.
Furthermore, extra ground excavation for the footing is often required, which also requires temporary materials, time and manpower.

建築基礎構造設計指針(社団法人日本建築学会発行、2002年4月15日、第2版第2刷の第199頁第6〜24行参照)Guidelines for Designing Basic Building Structures (published by the Architectural Institute of Japan, April 15, 2002, second edition, second print, page 199, lines 6-24)

そこで、本発明は、各既製杭の上部に取り付けられるフーチングの形状を小さくできる杭基礎の施工方法及びその杭基礎を提供することを目的とするものである。   Then, an object of this invention is to provide the construction method of the pile foundation which can make the shape of the footing attached to the upper part of each ready-made pile small, and its pile foundation.

すなわち、本発明は、(1)、杭基礎の施工方法であって、複数の掘削孔を相互に連通するように掘削し、連通する前記各掘削孔に充填材を充填し、前記充填材を充填した前記各掘削孔にそれぞれ既製杭を建込み、前記各掘削孔と前記既製杭の隙間の前記充填材により前記複数本の既製杭を一体化する杭基礎の施工方法である。   That is, the present invention is (1) a method for constructing a pile foundation, wherein a plurality of excavation holes are excavated so as to communicate with each other, the communicating excavation holes are filled with a filler, and the filler is used. It is a construction method of a pile foundation in which a ready-made pile is installed in each filled excavation hole, and the plurality of ready-made piles are integrated by the filler in a gap between each excavation hole and the ready-made pile.

また、本発明は、(2)、杭基礎の施工方法であって、所定直径の1個の掘削孔を掘削し、前記掘削孔に充填材を充填し、前記充填材を充填した前記掘削孔の中心部に複数本の既製杭をまとめて建込み、前記掘削孔と前記複数本の既製杭の隙間の前記充填材により前記複数本の既製杭を一体化する杭基礎の施工方法である。   Further, the present invention is (2) a method for constructing a pile foundation, wherein one excavation hole having a predetermined diameter is excavated, the excavation hole is filled with a filler, and the excavation hole filled with the filler is used. Is a construction method of a pile foundation in which a plurality of ready-made piles are installed together in the center of the pile, and the plurality of ready-made piles are integrated by the filler in a gap between the excavation hole and the plurality of ready-made piles.

請求また、本発明は、(3)、前記充填材はセメントミルクである上記(1)または(2)記載の杭基礎の施工方法である。   Further, the present invention is (3) the pile foundation construction method according to (1) or (2) above, wherein the filler is cement milk.

また、本発明は、(4)、相互に連通する複数の掘削孔の各掘削孔にそれぞれ既製杭を建込み、前記各掘削孔と前記既製杭の隙間に充填された充填材により前記複数本の既製杭を一体化した杭基礎である。   Further, the present invention provides (4) a plurality of prefabricated piles built in the respective excavation holes of the plural excavation holes communicating with each other, and the plural pieces are filled with a filler filled in the gaps between the respective excavation holes and the prefabricated piles. It is a pile foundation that integrates ready-made piles.

また、本発明は、(5)、所定直径の1個の掘削孔の中心部に複数本の既製杭をまとめて建込み、前記掘削孔と前記複数本の既製杭の隙間に充填された充填材により前記複数本の既製杭を一体化した杭基礎である。   Further, the present invention is (5), filling a plurality of ready-made piles together at the center of one excavation hole having a predetermined diameter, and filling a gap between the excavation holes and the plurality of pre-made piles It is a pile foundation in which the plurality of ready-made piles are integrated with a material.

また、本発明は、(6)、前記充填材はセメントミルクである上記(4)または(5)記載の杭基礎である。   Moreover, this invention is a pile foundation of the said (4) or (5) description whose said filler is cement milk (6).

なお、本発明の目的に添ったものであれば上記(1)から(6)を適宜組み合わせた構成も採用可能である。   Note that a configuration in which the above (1) to (6) are appropriately combined can be adopted as long as the object of the present invention is met.

本発明の杭基礎の施工方法及びその杭基礎によれば、従来例(図9に示すもの)に比較して、フーチングの形状寸法を小さくすることができる。
そのため、フーチングの断面性能の低減も可能となる。さらに、フーチングの形状寸法を小さくすることによって、全体的な資材の低減および施工工期・人手の低減が可能である。
According to the pile foundation construction method and the pile foundation of the present invention, the shape dimensions of the footing can be reduced as compared with the conventional example (shown in FIG. 9).
Therefore, the cross-sectional performance of the footing can be reduced. Furthermore, by reducing the shape dimensions of the footing, it is possible to reduce the overall material, construction period and manpower.

図1は、本発明の実施の形態に係る施工方法における相互に連通する2個の掘削孔を二軸オーガーで掘削する工程を示す断面図である。FIG. 1 is a cross-sectional view showing a process of excavating two excavation holes communicating with each other in a construction method according to an embodiment of the present invention with a biaxial auger. 図2は、図1に示す相互に連通する2個の各掘削孔にセメントミルクを充填する工程を示し、(a)は相互に連通する2個の各掘削孔の平面図、(b)はその断面図である。FIG. 2 shows a step of filling cement milk in each of the two drilling holes communicating with each other shown in FIG. 1, (a) is a plan view of the two drilling holes communicating with each other, and (b) is a plan view. FIG. 図3は、図2に示すセメントミルクを充填した相互に連通する2個の各掘削孔に既製コンクリート杭を建込んだ状態を示す断面図である。FIG. 3 is a cross-sectional view showing a state in which a ready-made concrete pile is built in each of two communicating holes filled with cement milk shown in FIG. 図4は、図3に示す2本の既製コンクリート杭の上部にフーチングを取り付けた状態を示す基礎構造で、(a)はその平面図、(b)はその断面図である。FIG. 4 is a basic structure showing a state in which a footing is attached to the upper part of the two ready-made concrete piles shown in FIG. 3, wherein (a) is a plan view thereof and (b) is a sectional view thereof. 図5は、相互に連通する3個の掘削孔を直線状に掘削した掘削孔の平面図で、図2(a)に相当する平面図である。FIG. 5 is a plan view of an excavation hole obtained by excavating three excavation holes communicating with each other in a straight line, and is a plan view corresponding to FIG. 図6は、相互に連通する3個の掘削孔を略三角形状に掘削した掘削孔の平面図で、図2(a)に相当する平面図である。FIG. 6 is a plan view of an excavation hole obtained by excavating three excavation holes communicating with each other in a substantially triangular shape, and is a plan view corresponding to FIG. 図7は、相互に連通する4個の掘削孔を略四角形状に掘削した掘削孔の平面図で、図2(a)に相当する平面図である。FIG. 7 is a plan view of an excavation hole obtained by excavating four excavation holes communicating with each other into a substantially square shape, and is a plan view corresponding to FIG. 図8は、本発明の他の実施の形態に係るものの平面図である。FIG. 8 is a plan view of another embodiment of the present invention. 図9は、従来の基礎構造を示すもので、2本の既製コンクリート杭の上部にフーチングを取り付けた状態を示す基礎構造で、(a)はその平面図、(b)はその断面図である。FIG. 9 shows a conventional foundation structure, which is a foundation structure in which a footing is attached to the upper part of two ready-made concrete piles, (a) is a plan view thereof, and (b) is a sectional view thereof. .

本発明の実施の形態に係る杭基礎の施工方法及びその杭基礎について以下に図1〜7を参照して説明する。   A construction method of a pile foundation according to an embodiment of the present invention and the pile foundation will be described below with reference to FIGS.

図1は、本発明の実施の形態に係る施工方法における相互に連通する2個の掘削孔を二軸オーガーで掘削する工程を示す断面図である。   FIG. 1 is a cross-sectional view showing a process of excavating two excavation holes communicating with each other in a construction method according to an embodiment of the present invention with a biaxial auger.

図2は、図1に示す相互に連通する2個の各掘削孔にセメントミルクを充填する工程を示し、図2(a)は相互に連通する2個の各掘削孔の平面図、図2(b)はその断面図である。   FIG. 2 shows a process of filling cement milk in each of the two drilling holes communicating with each other shown in FIG. 1, and FIG. 2 (a) is a plan view of the two drilling holes communicating with each other. (B) is a sectional view thereof.

図3は、図2に示すセメントミルクを充填した相互に連通する2個の各掘削孔に既製コンクリート杭を建込んだ状態を示す断面図である。   FIG. 3 is a cross-sectional view showing a state in which a ready-made concrete pile is built in each of two communicating holes filled with cement milk shown in FIG.

図4は、図3に示す2本の既製コンクリート杭の上部にフーチングを取り付けた状態を示す基礎構造で、 図4(a)はその平面図、 図4(b)はその断面図である。   FIG. 4 is a basic structure showing a state in which a footing is attached to the upper part of two ready-made concrete piles shown in FIG. 3, FIG. 4 (a) is a plan view thereof, and FIG. 4 (b) is a sectional view thereof.

図5は、相互に連通する3個の掘削孔を直線状に掘削した掘削孔の平面図で、図2(a)に相当する平面図である。   FIG. 5 is a plan view of an excavation hole obtained by excavating three excavation holes communicating with each other in a straight line, and is a plan view corresponding to FIG.

図6は、相互に連通する3個の掘削孔を略三角形状に掘削した掘削孔の平面図で、図2(a)に相当する平面図である。   FIG. 6 is a plan view of an excavation hole obtained by excavating three excavation holes communicating with each other in a substantially triangular shape, and is a plan view corresponding to FIG.

図7は、相互に連通する4個の掘削孔を略四角形状に掘削した掘削孔の平面図で、図2(a)に相当する平面図である。   FIG. 7 is a plan view of an excavation hole obtained by excavating four excavation holes communicating with each other into a substantially square shape, and is a plan view corresponding to FIG.

本発明の実施の形態に係る施工方法について以下に説明する。
まず、2本の既製コンクリート杭(既製杭)を埋込み工法について説明する。
図1に示すように、二軸オーガー8によって地盤(支持層)6及び中間地盤7に掘削孔2を掘削する。
二軸オーガー8によって掘削された掘削孔2は、図2(a)に示すように、略ひょうたん状に形成され、2個の掘削孔2は相互に連通している。
The construction method according to the embodiment of the present invention will be described below.
First, the method of embedding two ready-made concrete piles (ready-made piles) will be described.
As shown in FIG. 1, the excavation hole 2 is excavated in the ground (support layer) 6 and the intermediate ground 7 by a biaxial auger 8.
As shown in FIG. 2A, the excavation hole 2 excavated by the biaxial auger 8 is formed in a substantially gourd shape, and the two excavation holes 2 communicate with each other.

次に、図2(a),図2(b)に示すように、2個の掘削孔2にセメントミルク(充填材)3を充填する。
その際、地盤(支持層)6の部分には、セメント量を多くしたセメントミルク(充填材)3を根固め液として注入し、その上にセメントミルク(充填材)3を周辺固定液として充填する。
Next, as shown in FIGS. 2A and 2B, cement milk (filler) 3 is filled in the two excavation holes 2.
At that time, cement milk (filler) 3 having a large amount of cement is poured into the ground (support layer) 6 as a root-setting liquid, and cement milk (filler) 3 is filled thereon as a peripheral fixative. To do.

次に、図3に示すように、セメントミルク(充填材)3を充填した各掘削孔2にそれぞれ既製コンクリート杭1を建込む。
セメントミルク(充填材)3が硬化することにより2本の既製コンクリート杭1は一体化されて杭基礎となる。
Next, as shown in FIG. 3, ready-made concrete piles 1 are installed in the respective excavation holes 2 filled with cement milk (filler) 3.
When the cement milk (filler) 3 is hardened, the two ready-made concrete piles 1 are integrated into a pile foundation.

以上のような施工方法によって、図3に示すように、相互に連通する2個の掘削孔2の各掘削孔2にそれぞれ既製コンクリート杭1を建込み、各掘削孔2と既製コンクリート杭1の隙間に充填されたセメントミルク(充填材)3により2本の既製コンクリート杭1を一体化した杭基礎を構成することができる。
なお、図3において、9は捨てコンクリート、10は砕石を示す。
With the construction method as described above, as shown in FIG. 3, the ready-made concrete piles 1 are respectively built in the two excavation holes 2 of the two excavation holes 2 communicating with each other. A pile foundation in which two ready-made concrete piles 1 are integrated by cement milk (filler) 3 filled in the gap can be formed.
In FIG. 3, 9 indicates discarded concrete and 10 indicates crushed stone.

そして、図4(a),図4(b)に示すように、2本の既製コンクリート杭1の上部にフーチングを取り付けることにより基礎構造が形成される。   And as shown to Fig.4 (a) and FIG.4 (b), a foundation structure is formed by attaching a footing to the upper part of the two ready-made concrete piles 1. FIG.

次に、3本の既製コンクリート杭1を建込むための掘削孔2の例について説明する。
図5に示すものは、相互に連通する3個の掘削孔2を直線状に掘削した掘削孔2の平面図で、図2(a)に相当する平面図である。
3個の掘削孔2を直線状に掘削するには、図5において左側と中央の掘削孔2を二軸オーガー8により掘削し、続いて中央と右側の掘削孔2をもう一度、二軸オーガー8により掘削する。
すなわち、二軸オーガー8の二度掘りにより3個の掘削孔2を直線状に掘削する。
その後、相互に連通する3個の掘削孔2にセメントミルク(充填材)3を充填する。
Next, the example of the excavation hole 2 for constructing the three ready-made concrete piles 1 is demonstrated.
FIG. 5 is a plan view of the excavation hole 2 obtained by excavating the three excavation holes 2 communicating with each other in a straight line, and is a plan view corresponding to FIG.
In order to excavate the three excavation holes 2 in a straight line, the left and central excavation holes 2 are excavated by the biaxial auger 8 in FIG. Drill by.
That is, three excavation holes 2 are excavated linearly by digging twice by the biaxial auger 8.
Then, cement milk (filler) 3 is filled in the three excavation holes 2 communicating with each other.

次に、図示はしないが、セメントミルク(充填材)3を充填した各掘削孔2にそれぞれ既製コンクリート杭1を建込む。
セメントミルク(充填材)3が硬化することにより3本の既製コンクリート杭1は一体化されて杭基礎となる。
そして、図示はしないが、3本の既製コンクリート杭1の上部にフーチングを取り付けることにより基礎構造が形成される。
Next, although not shown, the ready-made concrete piles 1 are installed in the respective excavation holes 2 filled with cement milk (filler) 3.
When the cement milk (filler) 3 is hardened, the three ready-made concrete piles 1 are integrated into a pile foundation.
And although not shown in figure, a foundation structure is formed by attaching a footing to the upper part of the three ready-made concrete piles 1. FIG.

図6に示すものは、相互に連通する3個の掘削孔2を略三角形状に掘削した掘削孔2の平面図で、図2(a)に相当する平面図である。
3個の掘削孔2を略三角形状に掘削するには、図6において下側の2個の掘削孔2を二軸オーガー8により掘削し、続いて上側の掘削孔2を一軸オーガーにより掘削する。
その後、相互に連通する3個の掘削孔2にセメントミルク(充填材)3を充填する。
6 is a plan view of the excavation hole 2 obtained by excavating the three excavation holes 2 communicating with each other in a substantially triangular shape, and is a plan view corresponding to FIG.
In order to excavate the three excavation holes 2 into a substantially triangular shape, the lower two excavation holes 2 in FIG. 6 are excavated by the biaxial auger 8, and then the upper excavation hole 2 is excavated by the single axial auger. .
Then, cement milk (filler) 3 is filled in the three excavation holes 2 communicating with each other.

次に、図示はしないが、セメントミルク(充填材)3を充填した各掘削孔2にそれぞれ既製コンクリート杭1を建込む。
セメントミルク(充填材)3が硬化することにより3本の既製コンクリート杭1は一体化されて杭基礎となる。
そして、図示はしないが、3本の既製コンクリート杭1の上部にフーチングを取り付けることにより基礎構造が形成される。
Next, although not shown, the ready-made concrete piles 1 are installed in the respective excavation holes 2 filled with cement milk (filler) 3.
When the cement milk (filler) 3 is hardened, the three ready-made concrete piles 1 are integrated into a pile foundation.
And although not shown in figure, a foundation structure is formed by attaching a footing to the upper part of the three ready-made concrete piles 1. FIG.

次に、4本の既製コンクリート杭1を建込むための掘削孔2の例をついて説明する。
図7に示すものは、相互に連通する4個の掘削孔2を略四角形状に掘削した掘削孔2の平面図で、図2(a)に相当する平面図である。
4個の掘削孔2を略四角形状に掘削するには、図7において下側の2個の掘削孔2を二軸オーガー8により掘削し、続いて上側の2個の掘削孔2を二軸オーガー8により掘削する。
その後、相互に連通する4個の掘削孔2にセメントミルク(充填材)3を充填する。
Next, the example of the excavation hole 2 for constructing the four ready-made concrete piles 1 is demonstrated.
7 is a plan view of the excavation hole 2 obtained by excavating the four excavation holes 2 communicating with each other into a substantially square shape, and is a plan view corresponding to FIG.
In order to excavate the four excavation holes 2 into a substantially square shape, the lower two excavation holes 2 in FIG. 7 are excavated by the biaxial auger 8, and then the upper two excavation holes 2 are biaxial. Drilling with Auger 8.
Thereafter, cement milk (filler) 3 is filled into the four excavation holes 2 communicating with each other.

次に、図示はしないが、セメントミルク(充填材)3を充填した各掘削孔2にそれぞれ既製コンクリート杭1を建込む。
セメントミルク(充填材)3が硬化することにより4本の既製コンクリート杭1は一体化されて杭基礎となる。
そして、図示はしないが、4本の既製コンクリート杭1の上部にフーチングを取り付けることにより基礎構造が形成される。
Next, although not shown, the ready-made concrete piles 1 are installed in the respective excavation holes 2 filled with cement milk (filler) 3.
When the cement milk (filler) 3 is hardened, the four ready-made concrete piles 1 are integrated into a pile foundation.
And although not shown in figure, a foundation structure is formed by attaching a footing to the upper part of the four ready-made concrete piles 1. FIG.

次に、本発明の他の実施の形態に係る杭基礎の施工方法及びその杭基礎について以下に図8を参照して説明する。
図8に示すように、図示しない大口径掘削機により、所定直径(大口径)の1個の掘削孔2’を掘削する。
その後、掘削孔2’にセメントミルク(充填材)3を充填する。
Next, a pile foundation construction method and pile foundation according to another embodiment of the present invention will be described below with reference to FIG.
As shown in FIG. 8, one excavation hole 2 'having a predetermined diameter (large diameter) is excavated by a large-diameter excavator (not shown).
Then, cement milk (filler) 3 is filled in the excavation hole 2 ′.

次に、セメントミルク(充填材)3を充填した掘削孔2’の中心部に3本の既製コンクリート杭(既製杭)1’をまとめて建込む。
セメントミルク(充填材)3が硬化することにより3本の既製コンクリート杭1’は一体化されて杭基礎となる。
そして、図示はしないが、3本の既製コンクリート杭1’の上部にフーチングを取り付けることにより基礎構造が形成される。
Next, three ready-made concrete piles (ready-made piles) 1 ′ are built together in the center of the excavation hole 2 ′ filled with cement milk (filler) 3.
When the cement milk (filler) 3 is hardened, the three ready-made concrete piles 1 'are integrated into a pile foundation.
And although not shown in figure, a foundation structure is formed by attaching a footing to the upper part of three ready-made concrete piles 1 '.

本発明の実施の形態及び他の実施の形態に係る杭基礎の施工方法及びその杭基礎によれば、従来例(図9に示すもの)に比較して、フーチング4の形状寸法を小さくすることができる。
そのため、フーチング4の断面性能の低減も可能となる。さらに、フーチング4の形状寸法を小さくすることによって、全体的な資材の低減および施工工期・人手の低減が可能である。
According to the pile foundation construction method and the pile foundation according to the embodiment of the present invention and the other embodiments, the shape dimension of the footing 4 is reduced as compared with the conventional example (shown in FIG. 9). Can do.
Therefore, the cross-sectional performance of the footing 4 can be reduced. Furthermore, by reducing the size of the footing 4, it is possible to reduce the overall material, construction period, and manpower.

以上で説明した本発明の実施の形態及び他の実施の形態に係る杭基礎の施工方法及びその杭基礎においては、既製杭として既製コンクリート杭を使用した場合について説明したが、本発明はこれに限定されるものではなく、例えば、既製コンクリート杭に代えて既製鋼製杭を使用することもできる。
また、既製コンクリート杭及び既製鋼製杭は中実のものでも、中空のものでもよい。
In the construction method of the pile foundation and the pile foundation according to the embodiment of the present invention and the other embodiments described above, the case where the ready-made concrete pile is used as the ready-made pile has been described. It is not limited, For example, it can replace with a ready-made concrete pile and can use a ready-made steel pile.
The ready-made concrete pile and the ready-made steel pile may be solid or hollow.

1…既製コンクリート杭(既製杭)
2,2’ …掘削孔
3…セメントミルク(充填材)
4…フーチング
5…柱
6…地盤(支持層)
7…中間地盤
8…二軸オーガー
9…捨てコンクリート
10…砕石

1 ... Ready-made concrete pile (ready-made pile)
2, 2 '... Drilling hole 3 ... Cement milk (filler)
4 ... Footing 5 ... Pillar 6 ... Ground (support layer)
7 ... Intermediate ground 8 ... Biaxial auger 9 ... Discarded concrete 10 ... Crushed stone

Claims (6)

杭基礎の施工方法であって、複数の掘削孔を相互に連通するように掘削し、連通する前記各掘削孔に充填材を充填し、前記充填材を充填した前記各掘削孔にそれぞれ既製杭を建込み、前記各掘削孔と前記既製杭の隙間の前記充填材により前記複数本の既製杭を一体化することを特徴とする杭基礎の施工方法。   A pile foundation construction method, in which a plurality of excavation holes are excavated so as to communicate with each other, a filling material is filled in the communicating excavation holes, and the excavation holes filled with the filling material are respectively ready-made piles The pile foundation construction method is characterized in that the plurality of ready-made piles are integrated with the filler in the gaps between the excavation holes and the ready-made piles. 杭基礎の施工方法であって、所定直径の1個の掘削孔を掘削し、前記掘削孔に充填材を充填し、前記充填材を充填した前記掘削孔の中心部に複数本の既製杭をまとめて建込み、前記掘削孔と前記複数本の既製杭の隙間の前記充填材により前記複数本の既製杭を一体化することを特徴とする杭基礎の施工方法。   A method for constructing a pile foundation, wherein one excavation hole having a predetermined diameter is excavated, the excavation hole is filled with a filler, and a plurality of ready-made piles are provided at the center of the excavation hole filled with the filler. A construction method for a pile foundation characterized in that the plurality of ready-made piles are integrated by using the filler in the gap between the excavation hole and the plurality of ready-made piles. 前記充填材はセメントミルクであることを特徴とする請求項1または2記載の杭基礎の施工方法。   3. The pile foundation construction method according to claim 1, wherein the filler is cement milk. 相互に連通する複数の掘削孔の各掘削孔にそれぞれ既製杭を建込み、前記各掘削孔と前記既製杭の隙間に充填された充填材により前記複数本の既製杭を一体化したことを特徴とする杭基礎。   A prefabricated pile is built in each excavation hole of a plurality of excavation holes communicating with each other, and the plural prefabricated piles are integrated by a filler filled in a gap between each excavation hole and the prefabricated pile And pile foundation. 所定直径の1個の掘削孔の中心部に複数本の既製杭をまとめて建込み、前記掘削孔と前記複数本の既製杭の隙間に充填された充填材により前記複数本の既製杭を一体化したことを特徴とする杭基礎。   A plurality of ready-made piles are built together in the center of one excavation hole having a predetermined diameter, and the plurality of ready-made piles are integrated by a filler filled in a gap between the excavation hole and the plurality of ready-made piles. Pile foundation characterized by having become. 前記充填材はセメントミルクであることを特徴とする請求項4または5記載の杭基礎。

The pile foundation according to claim 4 or 5, wherein the filler is cement milk.

JP2009087046A 2009-03-31 2009-03-31 Method for constructing pile foundation, and the pile foundation for use in the same Pending JP2010236311A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP2009087046A JP2010236311A (en) 2009-03-31 2009-03-31 Method for constructing pile foundation, and the pile foundation for use in the same

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP2009087046A JP2010236311A (en) 2009-03-31 2009-03-31 Method for constructing pile foundation, and the pile foundation for use in the same

Publications (1)

Publication Number Publication Date
JP2010236311A true JP2010236311A (en) 2010-10-21

Family

ID=43090895

Family Applications (1)

Application Number Title Priority Date Filing Date
JP2009087046A Pending JP2010236311A (en) 2009-03-31 2009-03-31 Method for constructing pile foundation, and the pile foundation for use in the same

Country Status (1)

Country Link
JP (1) JP2010236311A (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN113152450A (en) * 2021-04-22 2021-07-23 广东际安工程管理有限公司 Application of prestressed concrete pipe pile planting technology in complex foundation

Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS6319340A (en) * 1986-07-14 1988-01-27 Kajima Corp Collecting pile
JPH116147A (en) * 1997-06-18 1999-01-12 Mitani Sekisan Co Ltd Constructing method for pile group, structure of pile group and pile holding device
JP2000027180A (en) * 1998-07-07 2000-01-25 Kajima Corp Construction method of large-caliber concrete pile
JP2004162348A (en) * 2002-11-12 2004-06-10 Geotop Corp Work-execution method for pile

Patent Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS6319340A (en) * 1986-07-14 1988-01-27 Kajima Corp Collecting pile
JPH116147A (en) * 1997-06-18 1999-01-12 Mitani Sekisan Co Ltd Constructing method for pile group, structure of pile group and pile holding device
JP2000027180A (en) * 1998-07-07 2000-01-25 Kajima Corp Construction method of large-caliber concrete pile
JP2004162348A (en) * 2002-11-12 2004-06-10 Geotop Corp Work-execution method for pile

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN113152450A (en) * 2021-04-22 2021-07-23 广东际安工程管理有限公司 Application of prestressed concrete pipe pile planting technology in complex foundation

Similar Documents

Publication Publication Date Title
KR101014796B1 (en) Top-down underground construction method using prefabricated concrete column member as temporary bridge column
KR101241566B1 (en) Method for Constructing Cap Beam Combined Wale For Retaining Wall
JP5274145B2 (en) Cast-in-place pile and its construction method
KR101005780B1 (en) Underground constructure form system for preventing concretes of underground slab and girder from crack
JP2009167660A (en) Tower crane foundation structure and method of constructing the same
JP5330874B2 (en) Soil cement column mountain wall
JP2008231816A (en) Construction method of pile foundation structure
JP6855665B2 (en) Pile foundation structure and how to reinforce existing piles
JP6143068B2 (en) Underground structure of building
KR20120030493A (en) Method of reinforcing existing concrete footing structure using micropile and structure thereof
KR101072958B1 (en) Foundation structure using the micropile and truss, and construction method thereof in a surrounding structure and the places that it is adjacent to
JP5228862B2 (en) Underground structure, construction method of underground structure
JP2010236311A (en) Method for constructing pile foundation, and the pile foundation for use in the same
JP2019218795A (en) Joint structure of foundation pile and foundation slab
JP4228308B2 (en) Reinforcement method for existing floors and seismic isolation method for existing buildings
JP2005002671A (en) Underpinning method and viaduct
KR101047257B1 (en) Construction method of earth wall using composite sheet pile
JP2016199915A (en) Foundation structure and foundation construction method
JP2006188862A (en) Construction method of structure, and foundation structure used for the same
JP7019905B2 (en) Pile foundation structure and reinforcement method for existing piles
KR101255610B1 (en) Structure construction method and structure of use it
KR20050011111A (en) The site other opinion picket spatial-temporal method which applies the meritorious metal tubing
KR20110029418A (en) Pile for reducing negative skin friction, foundation structure using the same and construction method thereof
KR102264595B1 (en) Self supporting type phc pile and construction method for the same
KR102108622B1 (en) Support structure of temporary strut for construction period reduction

Legal Events

Date Code Title Description
A621 Written request for application examination

Effective date: 20120217

Free format text: JAPANESE INTERMEDIATE CODE: A621

A977 Report on retrieval

Effective date: 20121115

Free format text: JAPANESE INTERMEDIATE CODE: A971007

A131 Notification of reasons for refusal

Free format text: JAPANESE INTERMEDIATE CODE: A131

Effective date: 20121120

A02 Decision of refusal

Free format text: JAPANESE INTERMEDIATE CODE: A02

Effective date: 20130402