JP2010144512A - Structure near intermediate supporting point of continuous i-beam bridge - Google Patents

Structure near intermediate supporting point of continuous i-beam bridge Download PDF

Info

Publication number
JP2010144512A
JP2010144512A JP2010032865A JP2010032865A JP2010144512A JP 2010144512 A JP2010144512 A JP 2010144512A JP 2010032865 A JP2010032865 A JP 2010032865A JP 2010032865 A JP2010032865 A JP 2010032865A JP 2010144512 A JP2010144512 A JP 2010144512A
Authority
JP
Japan
Prior art keywords
girder
lower flange
continuous
flange
web
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
JP2010032865A
Other languages
Japanese (ja)
Other versions
JP4508293B2 (en
Inventor
Atsushi Okada
淳 岡田
Naoyoshi Tsumura
直宜 津村
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
JFE Engineering Corp
Original Assignee
JFE Engineering Corp
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by JFE Engineering Corp filed Critical JFE Engineering Corp
Priority to JP2010032865A priority Critical patent/JP4508293B2/en
Publication of JP2010144512A publication Critical patent/JP2010144512A/en
Application granted granted Critical
Publication of JP4508293B2 publication Critical patent/JP4508293B2/en
Anticipated expiration legal-status Critical
Expired - Lifetime legal-status Critical Current

Links

Images

Landscapes

  • Bridges Or Land Bridges (AREA)

Abstract

【課題】鋼重、工数、工費を低減し、現場でのコンクリート打設作業を減らして急速施工を可能とすると共に、現場までの輸送コストを低減する。
【解決手段】上フランジ32、下フランジ34、ウェブ36、鉛直補剛材38を備えたI桁30と床版によって構成され、1又は複数の中間支点によって支持される連続I桁橋において、中間支点近傍の下フランジ34、ウェブ36、鉛直補剛材38で囲まれる領域の下フランジ34の上に上フランジ32との間に空間を設けてプレキャスト板40を配設し、下フランジ34とプレキャスト板40を上フランジに連結していないずれ止めで一体化させることにより、下フランジ34の局部座屈を防ぎ、横座屈強度を向上させる。
【選択図】図6
[PROBLEMS] To reduce steel weight, man-hours, and construction costs, reduce concrete placement work on site, enable rapid construction, and reduce transportation costs to the site.
In a continuous I-girder bridge composed of an I-girder 30 and a floor slab provided with an upper flange 32, a lower flange 34, a web 36, and a vertical stiffener 38, and supported by one or more intermediate fulcrums. A space is provided between the upper flange 32 and the lower flange 34 in the region surrounded by the lower flange 34, the web 36, and the vertical stiffener 38 in the vicinity of the fulcrum. By integrating the plate 40 with a stopper that is not connected to the upper flange, local buckling of the lower flange 34 is prevented and the lateral buckling strength is improved.
[Selection] Figure 6

Description

本発明は、橋梁等の土木構造物、特に、連続I桁橋の中間支点近傍の構造に関するものである。   The present invention relates to a civil engineering structure such as a bridge, and more particularly to a structure near an intermediate fulcrum of a continuous I-girder bridge.

図10及び図11に例示する如く、連続I桁橋10の中間支点12付近には、大きな負の曲げモーメントMが生じる。この曲げモーメントにより、I桁130の下フランジ134には圧縮力が作用するため、図12及び図13にI桁130の横断面を拡大して示す如く、局部座屈(図12)したり、横座屈(図13)を生じる可能性がある。特に、比較的スパンの長い連続I桁橋において、高強度鋼等を適用する場合には、このような問題が顕著となる。図12及び図13において、116は床版、132は、I桁130の上フランジ、136は、同じくウェブである。   As illustrated in FIGS. 10 and 11, a large negative bending moment M is generated near the intermediate fulcrum 12 of the continuous I girder bridge 10. Due to this bending moment, a compressive force acts on the lower flange 134 of the I girder 130, so that as shown in the enlarged cross section of the I girder 130 in FIGS. 12 and 13, local buckling (FIG. 12), Lateral buckling (FIG. 13) can occur. In particular, when a high-strength steel or the like is applied to a continuous I girder bridge having a relatively long span, such a problem becomes significant. 12 and 13, 116 is a floor slab, 132 is an upper flange of the I-girder 130, and 136 is a web.

これに対する従来技術1として、中間支点付近において、
(1)下フランジ134の肉厚を大きくする、
(2)横桁や横溝等の間隔を小さくして密に配置する、
等の対策がある。
As prior art 1 for this, in the vicinity of the intermediate fulcrum,
(1) Increasing the thickness of the lower flange 134,
(2) The gap between the horizontal beam and the horizontal groove is reduced and arranged closely.
There are measures such as.

又、従来技術2として、特許文献1が挙げられる。この特許文献1に記載された橋梁用連続桁は、上下のフランジとウェブとを有して橋軸方向に延び、1又は複数の中間支点で支持される鋼製の桁本体を備え、この桁本体の上記中間支点の周辺には、垂直、水平鉄筋の全て若しくは一部を埋設してなる鉄筋コンクリートが、上記ウェブに添うようにして打設されており、上記垂直鉄筋が、垂直に延びると共に上下端が上下のフランジにそれぞれ連結され、上記水平鉄筋が、上記橋軸方向に延び上記垂直鉄筋と直交されて、中間支点周辺の被支持領域が、上下フランジとウェブと垂直補剛材とで画成された凹部内に、ウェブと平行に格子状に配設された鉄筋と、これを覆うよう打設充填されたコンクリートで補強されている。   Further, Patent Document 1 is cited as the prior art 2. The bridge continuous girder described in Patent Document 1 includes a steel girder body that has upper and lower flanges and a web, extends in the bridge axis direction, and is supported by one or more intermediate fulcrums. Around the intermediate fulcrum of the main body, reinforced concrete in which all or part of vertical and horizontal reinforcing bars are embedded is placed so as to follow the web, and the vertical reinforcing bars extend vertically and vertically Ends are respectively connected to the upper and lower flanges, the horizontal rebar extends in the direction of the bridge axis and perpendicular to the vertical rebar, and the supported area around the intermediate fulcrum is defined by the upper and lower flanges, the web and the vertical stiffener. In the formed recess, the reinforcing bars are reinforced with reinforcing bars arranged in a lattice pattern parallel to the web and concrete filled and filled to cover the reinforcing bars.

又、平行する一対のI桁を用いた連続桁橋の桁構造として、特許文献2や特許文献3には、支点近くの下フランジ間に補強板(特許文献2)やコンクリート版(特許文献3)を架設固定し、箱形断面として補強することが記載されている。   Further, as a girder structure of a continuous girder bridge using a pair of parallel I-girder, Patent Document 2 and Patent Document 3 include a reinforcing plate (Patent Document 2) and a concrete plate (Patent Document 3) between lower flanges near a fulcrum. ) Is fixed and reinforced as a box-shaped cross section.

又、箱桁橋梁の構造として、特許文献4には、中間支点周辺の領域の鋼箱桁の内部空間全体をコンクリートで埋め尽くして補強することが記載されている。   Moreover, as a structure of the box girder bridge, Patent Document 4 describes that the entire internal space of the steel box girder in the area around the intermediate fulcrum is filled with concrete and reinforced.

特開2002−266317号公報JP 2002-266317 A 特開平11−81240号公報JP-A-11-81240 特開平11−148110号公報Japanese Patent Laid-Open No. 11-148110 特開2004−176344号公報JP 2004-176344 A

しかしながら、従来技術1には、次のような問題点がある。   However, the prior art 1 has the following problems.

(1)下フランジの板厚を大きくする場合には、鋼重が大幅に増え、又、断面毎の溶接接合やボルト接合による作業が大変になるため、工数が増え、工費が増大することになる。   (1) When the plate thickness of the lower flange is increased, the steel weight will increase significantly, and the work by welding and bolting for each cross section will become difficult, resulting in an increase in man-hours and cost. Become.

(2)横桁や横溝等の間隔を小さくして密に配置する場合には、横桁や横溝等の個数が増えるため、鋼重及び工数が増え、工費が増大することになる。   (2) In the case where the gaps such as the cross beams and the horizontal grooves are arranged closely and densely arranged, the number of the cross beams, the horizontal grooves and the like increases, so that the steel weight and the man-hour increase, and the construction cost increases.

又、従来技術2には、次のような問題点がある。   The prior art 2 has the following problems.

従来技術2は、垂直鉄筋の上下端を上下のフランジにそれぞれ直接、あるいは、短鉄筋とカプラーを介して溶接等により連結する必要がある。一般に、桁橋の上下フランジ間は2〜3m程度となるため、垂直鉄筋も2〜3m程度の長さとなる。2〜3mの長さの長い鉄筋を上下のフランジへ直接溶接する作業は、煩雑且つ困難であり、精度確保も難しい。又、短鉄筋とカプラーを介して連結する場合も、短鉄筋を溶接して、更に長い鉄筋をカプラーを介して連結する必要があるため、工数が増えるばかりか、短鉄筋の取付位置や角度等に高い精度が要求される。更に、現場での複雑なコンクリート打設作業及び長い養生期間が必要である。又、仮に工場でコンクリート打設まで行う場合には、現場までの輸送が困難となる。   In the prior art 2, it is necessary to connect the upper and lower ends of the vertical reinforcing bar to the upper and lower flanges directly or by welding or the like via a short reinforcing bar and a coupler. In general, since the gap between the upper and lower flanges of the girder bridge is about 2 to 3 m, the vertical rebar also has a length of about 2 to 3 m. The operation of directly welding long reinforcing bars of 2 to 3 m to the upper and lower flanges is complicated and difficult, and it is difficult to ensure accuracy. Also, when connecting short rebars via couplers, it is necessary to weld short rebars and connect longer rebars via couplers, which not only increases the number of man-hours, but also the positions and angles of short rebars. High accuracy is required. Furthermore, complex concrete placement work on site and a long curing period are required. In addition, if the concrete is to be placed in a factory, transportation to the site becomes difficult.

又、特許文献2乃至4に記載された技術は、いずれも箱桁断面を構成する必要があり、I桁断面よりも、工数が増え、工費が増大する。   In addition, all of the techniques described in Patent Documents 2 to 4 need to form a box girder cross section, which requires more man-hours and costs than the I girder cross section.

本発明は、前記従来の問題点を解決するべくなされたもので、鋼重、工数、工費を低減し、現場でのコンクリート打設作業を減らして急速施工を可能とすると共に、現場までの輸送コストを低減することを課題とする。   The present invention has been made to solve the above-mentioned conventional problems, and can reduce the steel weight, man-hours and cost, reduce the concrete placing work on site, enable rapid construction, and transport to the site. The object is to reduce costs.

本発明の請求項1に係る発明は、上フランジ、下フランジ、ウェブ、鉛直補剛材を備えたI桁と床版によって構成され、1又は複数の中間支点によって支持される連続I桁橋において、中間支点近傍の下フランジ、ウェブ、鉛直補剛材で囲まれる領域の下フランジの上に上フランジとの間に空間を設けてプレキャスト板を配設し、下フランジとプレキャスト板を上フランジに連結していないずれ止めで一体化させることにより、下フランジの局部座屈を防ぎ、横座屈強度を向上させることを特徴とする連続I桁橋における中間支点近傍のI桁の構造により、前記課題を解決したものである。   The invention according to claim 1 of the present invention is a continuous I-girder bridge constituted by an I-girder and a floor slab provided with an upper flange, a lower flange, a web, and a vertical stiffener, and supported by one or more intermediate fulcrums. A space is provided between the upper flange and the lower flange near the intermediate fulcrum, the web, and the lower flange in the area surrounded by the vertical stiffener, and the precast plate is placed on the upper flange. By the structure of the I-girder in the vicinity of the intermediate fulcrum in the continuous I-girder bridge, which is integrated with a non-displacement stopper to prevent local buckling of the lower flange and improve lateral buckling strength, Is a solution.

又、本発明の請求項2に係る発明は、前記プレキャスト板に箱抜き部が設けられており、該箱抜き部が設けられたプレキャスト板を、中間支点近傍の下フランジ、ウェブ、鉛直補剛材で囲まれる領域の下フランジの上に配設し、ずれ止めを箱抜き部の中となるように下フランジに配設し、箱抜き部へ充填材を打設して、下フランジとプレキャスト板を一体化させるようにしたものである。   In the invention according to claim 2 of the present invention, the precast plate is provided with a box cutting portion, and the precast plate provided with the box cutting portion is connected to a lower flange, a web, a vertical stiffening member near the intermediate fulcrum. Place on the lower flange of the area surrounded by the material, place the stopper on the lower flange so as to be in the boxed part, and place the filling material on the boxed part, preload with the lower flange The plates are integrated.

本発明では、I桁の下フランジとプレキャスト板が一体化された合成構造となる。これにより、連続I桁橋の中間支点付近において大きな負の曲げモーメントが生じ、下フランジに大きな圧縮力が作用する場合でも、下フランジの局部座屈や横座屈を効果的に防ぎ、耐荷力を大幅に向上させることができる。従って、従来技術1のように、下フランジの板厚を大きくしたり、横桁や横溝等の間隔を小さくして密に配置する必要がないため、従来技術1より鋼重、工数、工費を低減できる。   In the present invention, the lower structure of the I girder and the precast plate are integrated. As a result, even when a large negative bending moment is generated near the middle fulcrum of the continuous I-girder bridge and a large compressive force acts on the lower flange, local buckling and lateral buckling of the lower flange are effectively prevented, and the load bearing capacity is reduced. It can be greatly improved. Therefore, unlike the prior art 1, it is not necessary to increase the plate thickness of the lower flange or to reduce the spacing between the cross beams and the lateral grooves and arrange them densely. Can be reduced.

又、本発明では、現場でのコンクリート打設は、箱抜き部への無収縮モルタル等の充填材の打設のみとなるため、従来技術2のような現場打ちコンクリート打設工法と比較して、現場での作業が大幅軽減され、クリープや乾燥収縮の影響も小さくなる。又、コンクリートの養生期間も少なくなるため、急速施工が可能となり、工費と工期の低減効果が得られる。仮に従来技術2を工場でコンクリート打設まで行なう場合には、現場までの輸送が困難となる。本発明では、I桁とプレキャスト板を別々に現場まで輸送できるため、従来技術2と比較して現場までの輸送コストが軽減される。   Further, in the present invention, since the concrete placement on site is only placement of a filler such as non-shrink mortar into the box opening part, it is compared with the on-site concrete placement method as in prior art 2. Work on site is greatly reduced and the effects of creep and drying shrinkage are reduced. Moreover, since the curing period of concrete also decreases, rapid construction becomes possible, and the effect of reducing construction cost and construction period can be obtained. If the prior art 2 is performed up to the concrete placement in the factory, the transportation to the site becomes difficult. In the present invention, since the I girder and the precast plate can be separately transported to the site, the transportation cost to the site is reduced as compared with the conventional technique 2.

本発明に関する第1参考例に係る中間支点近傍のI桁の構造を示す斜視図The perspective view which shows the structure of the I girder near the intermediate fulcrum concerning the 1st reference example regarding this invention 同じく側面図Same side view 同じく施工例を示す側面図Side view showing another example of construction 箱抜き部の形状・配置の例を示す平面図A plan view showing an example of the shape and arrangement of the box opening part 本発明に関する第2参考例に係る中間支点近傍のI桁の構造の側面図Side view of I-girder structure near intermediate fulcrum according to second reference example of the present invention 本発明の第1実施形態に係る中間支点近傍のI桁の構造を示す斜視図The perspective view which shows the structure of the I girder near the intermediate fulcrum according to the first embodiment of the present invention. 同じく側面図Same side view 同じく施工例を示す側面図Side view showing another example of construction 本発明の第2実施形態に係る中間支点近傍のI桁の構造の側面図Side view of the structure of the I-girder near the intermediate fulcrum according to the second embodiment of the present invention 第1、第2参考例を連続I桁橋に配置した例を示す側面図Side view showing an example where the first and second reference examples are arranged on a continuous I girder bridge 第1、第2実施形態を連続I桁橋に配置した例を示す側面図Side view showing an example in which the first and second embodiments are arranged on a continuous I girder bridge 連続I桁橋の中間支点近傍における下フランジの局部座屈を示した正面図Front view showing local buckling of the lower flange near the intermediate fulcrum of a continuous I-girder bridge 連続I桁橋の中間支点近傍における横座屈を示した正面図Front view showing lateral buckling near intermediate fulcrum of continuous I-girder bridge

以下、図面を参照して、本発明に関する参考例および本発明の実施形態を詳細に説明する。   DETAILED DESCRIPTION Reference examples and embodiments of the present invention will be described below in detail with reference to the drawings.

本発明に関する第1参考例を、図1(斜視図)及び図2(側面図)に示す。図1(A)及び図2は、連続I桁橋10(図10参照)における中間支点12近傍のI桁30の構造を示し、I桁30は、上フランジ32、下フランジ34、ウェブ36から構成されている。図1(B)に詳細に示すプレキャスト板40は、例えば、プレキャストRC板、プレキャストPC板、プレキャストFRP板等であるが、所定の性能を満たすものであれば、他の材料を用いたものでも構わない。以下、箱抜き部42を設けたプレキャスト板40を例に説明する。   A first reference example relating to the present invention is shown in FIG. 1 (perspective view) and FIG. 2 (side view). FIGS. 1A and 2 show the structure of the I-girder 30 near the intermediate fulcrum 12 in the continuous I-girder bridge 10 (see FIG. 10). The I-girder 30 is composed of an upper flange 32, a lower flange 34, and a web 36. It is configured. The precast board 40 shown in detail in FIG. 1 (B) is, for example, a precast RC board, a precast PC board, a precast FRP board, or the like, but other materials may be used as long as they satisfy predetermined performance. I do not care. Hereinafter, the precast board 40 provided with the box opening part 42 will be described as an example.

第1参考例の現場での施工例を図3に示す。   A construction example of the first reference example on site is shown in FIG.

(1)図3(A)に示す如く、I桁30を下フランジ34の下面を上向きにして仮置し、I桁30の下フランジ34にずれ止め用のスタッド50を設置する。   (1) As shown in FIG. 3A, the I girder 30 is temporarily placed with the lower surface of the lower flange 34 facing upward, and a stud 50 for slippage prevention is installed on the lower flange 34 of the I girder 30.

(2)図3(B)に示す如く、I桁30の下フランジ34に設置したスタッド50の所に、プレキャスト板40の箱抜き部42が合うように設置する。   (2) As shown in FIG. 3 (B), the pre-cast plate 40 is installed so that the box opening portion 42 is aligned with the stud 50 installed on the lower flange 34 of the I girder 30.

(3)図3(C)に示す如く、箱抜き部42へ無収縮モルタルあるいは硬化剤等の充填材52を打設して、I桁30の下フランジ34とプレキャスト板40を一体化し、合成させる。   (3) As shown in FIG. 3C, a filler 52 such as a non-shrink mortar or a curing agent is placed on the box opening portion 42, and the lower flange 34 of the I-girder 30 and the precast plate 40 are integrated and synthesized. Let

(4)所定の期間、養生を行なった後、図3(D)に示す如く、上下を反転させて、I桁30を架設する。   (4) After curing for a predetermined period, as shown in FIG. 3 (D), the I girder 30 is installed upside down.

なお、本参考例では、箱抜き部42は、図4(A)に示す如く、矩形形状としているが、スタッド50のずれ止めが中に配置できればよく、図4(B)(C)(D)に変形例を例示する如く、任意の形状が適用できる。   In this reference example, the box opening portion 42 has a rectangular shape as shown in FIG. 4 (A). However, it is sufficient that the stopper 50 can be disposed in the inside, and FIGS. 4 (B), (C) and (D). An arbitrary shape can be applied as illustrated in the modification example.

又、スタッド50の設置順序は、施工性等を考慮して変更しても構わない。例えば、予め工場で設置しておいても良いし、I桁30の下フランジ34にプレキャスト板40を設置した後で、箱抜き部42に設置しても構わない。   Further, the installation order of the studs 50 may be changed in consideration of workability and the like. For example, it may be installed in a factory in advance, or after the precast plate 40 is installed on the lower flange 34 of the I girder 30, it may be installed in the box opening portion 42.

一方、箱抜き部42を設けないプレキャスト板40を用いる場合は、図5に示す第2参考例のように、中間支点12近傍の下フランジ34の下にプレキャスト板40を配設し、高力ボルト56等により一体化させても良い。   On the other hand, when using the precast plate 40 without the box opening 42, the precast plate 40 is disposed under the lower flange 34 in the vicinity of the intermediate fulcrum 12 as in the second reference example shown in FIG. You may make it integrate with the volt | bolt 56 grade | etc.,.

以上より、I桁30の下フランジ34とプレキャスト板40が一体化された合成構造となる。これにより、連続I桁橋10の中間支点12付近において大きな負の曲げモーメントが生じ、下フランジ34に大きな圧縮力が作用する場合でも、下フランジ34の局部座屈や横座屈を効果的に防ぎ、耐荷力を大幅に向上させることができる。   From the above, a composite structure in which the lower flange 34 of the I girder 30 and the precast plate 40 are integrated is obtained. As a result, a large negative bending moment is generated in the vicinity of the intermediate fulcrum 12 of the continuous I-girder bridge 10, and even when a large compressive force acts on the lower flange 34, local buckling and lateral buckling of the lower flange 34 are effectively prevented. The load bearing capacity can be greatly improved.

又、現場でのコンクリート打設は、箱抜き部42への充填材52等の打設のみとなるため、現場打ちコンクリート打設工法と比較して、現場での作業が大幅に軽減され、クリープや乾燥収縮の影響も小さくなる。又、現場打ちコンクリート打設工法と比較して、コンクリートの養生期間も少なくなるため、急速施工が可能となる。   In addition, since the concrete placement on site is only the placement of the filler 52 or the like into the box opening portion 42, the work on site is greatly reduced as compared with the on-site concrete placement method, and creep. And the effect of drying shrinkage is reduced. In addition, the concrete curing period is reduced as compared with the on-site concrete placing method, so that rapid construction is possible.

次に、本発明の第1実施形態を図6(斜視図)及び図7(側面図)に示す。図6(A)及び図7は、連続I桁橋10(図11参照)における中間支点12近傍のI桁30の構造を示し、I桁30は、上フランジ32、下フランジ34、ウェブ36、鉛直補剛材38から構成されている。図6(B)に詳細に示すプレキャスト板40は、例えば、プレキャストRC板、プレキャストPC板、プレキャストFRP板等であるが、所定の性能を満たすものであれば、他の材料を用いたものでも構わない。以下、箱抜き部42を設けたプレキャスト板40を例に説明する。   Next, a first embodiment of the present invention is shown in FIG. 6 (perspective view) and FIG. 7 (side view). 6 (A) and 7 show the structure of the I-girder 30 near the intermediate fulcrum 12 in the continuous I-girder bridge 10 (see FIG. 11). The I-girder 30 includes an upper flange 32, a lower flange 34, a web 36, It consists of a vertical stiffener 38. The precast board 40 shown in detail in FIG. 6B is, for example, a precast RC board, a precast PC board, a precast FRP board, or the like, but other materials may be used as long as they satisfy predetermined performance. I do not care. Hereinafter, the precast board 40 provided with the box opening part 42 will be described as an example.

第1実施形態の現場での施工例を図8に示す。   The construction example in the field of 1st Embodiment is shown in FIG.

(1)図8(A)に示す如く、現場でI桁30を架設し、I桁30の下フランジ34にずれ止め用のスタッド50を設置する。   (1) As shown in FIG. 8 (A), an I-girder 30 is installed on site, and a stud 50 for preventing slippage is installed on the lower flange 34 of the I-girder 30.

(2)図8(B)に示す如く、I桁30の下フランジ34に配列したスタッド50の所に、プレキャスト板40の箱抜き部42が合うように設置する。   (2) As shown in FIG. 8 (B), the pre-cast plate 40 is installed so that the box opening portion 42 is aligned with the stud 50 arranged on the lower flange 34 of the I-girder 30.

(3)図8(C)に示す如く、箱抜き部42へ無収縮モルタルあるいは硬化剤等の充填材52を打設して、I桁30の下フランジ34とプレキャスト板40を一体化し、合成させる。   (3) As shown in FIG. 8C, a filler 52 such as a non-shrink mortar or a curing agent is placed in the box opening portion 42, and the lower flange 34 of the I-girder 30 and the precast plate 40 are integrated and synthesized. Let

なお、本実施形態では、箱抜き部42は、第1参考例と同様に矩形形状としているが、スタッド50のずれ止めが中に配置できれば良く、任意の形状が適用できる。   In the present embodiment, the box opening portion 42 has a rectangular shape as in the first reference example. However, any shape can be applied as long as the stud 50 can be disposed therein.

又、スタッド50の設置順序は、施工性等を考慮して変更しても構わない。例えば、予め工場で設置しておいても良いし、I桁30の下フランジ34にプレキャスト板40を設置した後で、箱抜き部42に設置しても構わない。   Further, the installation order of the studs 50 may be changed in consideration of workability and the like. For example, it may be installed in a factory in advance, or after the precast plate 40 is installed on the lower flange 34 of the I girder 30, it may be installed in the box opening portion 42.

一方、箱抜き部42を設けないプレキャスト板40を用いる場合は、図9に示す第2実施形態のように、中間支点12近傍の下フランジ34の上にプレキャスト板40を配設し、高力ボルト56等により一体化させてもよい。   On the other hand, when using the precast plate 40 without the box opening 42, the precast plate 40 is disposed on the lower flange 34 in the vicinity of the intermediate fulcrum 12 as in the second embodiment shown in FIG. You may integrate with the volt | bolt 56 grade | etc.,.

以上より、I桁30の下フランジ34とプレキャスト板40が一体化された合成構造となる。これにより、連続I桁橋10の中間支点12付近において大きな負の曲げモーメントが生じ、下フランジ34に大きな圧縮力が作用する場合でも、下フランジ34の局部座屈や横座屈を効果的に防ぎ、耐荷力を大幅に向上させることができる。   From the above, a composite structure in which the lower flange 34 of the I girder 30 and the precast plate 40 are integrated is obtained. As a result, a large negative bending moment is generated in the vicinity of the intermediate fulcrum 12 of the continuous I-girder bridge 10, and even when a large compressive force acts on the lower flange 34, local buckling and lateral buckling of the lower flange 34 are effectively prevented. The load bearing capacity can be greatly improved.

又、現場でのコンクリート打設は、箱抜き部42への充填材52等の打設のみとなるため、現場打ちコンクリート打設工法と比較して、現場での作業が大幅に軽減され、クリープや乾燥収縮の影響も小さくなる。又、現場打ちコンクリート打設工法と比較して、コンクリートの養生期間も少なくなるため、急速施工が可能となる。   In addition, since the concrete placement on site is only the placement of the filler 52 or the like into the box opening portion 42, the work on site is greatly reduced as compared with the on-site concrete placement method, and creep. And the effect of drying shrinkage is reduced. In addition, the concrete curing period is reduced as compared with the on-site concrete placing method, so that rapid construction is possible.

図10に、連続I桁橋10に関する中間支点12近傍の構造の第1、第2参考例60の配置例を、図11に、同じく第1、第2実施形態62の配置例を示す。本発明に係る中間支点12近傍のI桁30の構造は、図11(A)に示すように、負曲げ域の全般に渡り配置しても良い。あるいは、図11(B)に示すように、負曲げ域の厳しい部分にのみ配置してもよい。図において、14は端支点、16は床版、Mは曲げモーメント分布である。   FIG. 10 shows an arrangement example of the first and second reference examples 60 in the vicinity of the intermediate fulcrum 12 regarding the continuous I girder bridge 10, and FIG. 11 shows an arrangement example of the first and second embodiments 62. The structure of the I girder 30 in the vicinity of the intermediate fulcrum 12 according to the present invention may be arranged over the entire negative bending region as shown in FIG. Alternatively, as shown in FIG. 11 (B), it may be arranged only in a severe part of the negative bending region. In the figure, 14 is an end fulcrum, 16 is a floor slab, and M is a bending moment distribution.

10…連続I桁橋
12…中間支点
14…端支点
16…床版
30…I桁
32…上フランジ
34…下フランジ
36…ウェブ
38…鉛直補剛材
40…プレキャスト板
42…箱抜き部
50…スタッド(ずれ止め)
52…充填材
54…固着材
56…高力ボルト
60…第1、第2参考例の中間支点近傍の構造
62…第1、第2実施形態の中間支点近傍の構造
M…曲げモーメント
DESCRIPTION OF SYMBOLS 10 ... Continuous I girder 12 ... Intermediate fulcrum 14 ... End fulcrum 16 ... Floor slab 30 ... I girder 32 ... Upper flange 34 ... Lower flange 36 ... Web 38 ... Vertical stiffener 40 ... Precast board 42 ... Box opening part 50 ... Stud (stop)
52 ... Filler 54 ... Adhering material 56 ... High strength bolt 60 ... Structure near the intermediate fulcrum of the first and second reference examples 62 ... Structure near the intermediate fulcrum of the first and second embodiments M ... Bending moment

Claims (3)

上フランジ、下フランジ、ウェブ、鉛直補剛材を備えたI桁と床版によって構成され、1又は複数の中間支点によって支持される連続I桁橋において、
中間支点近傍の下フランジ、ウェブ、鉛直補剛材で囲まれる領域の下フランジの上に上フランジとの間に空間を設けてプレキャスト板を配設し、
下フランジとプレキャスト板を上フランジに連結していないずれ止めで一体化させることにより、
下フランジの局部座屈を防ぎ、横座屈強度を向上させることを特徴とする連続I桁橋における中間支点近傍のI桁の構造。
In a continuous I-girder bridge composed of I-girder and floor slab with upper flange, lower flange, web, vertical stiffener, and supported by one or more intermediate fulcrums,
A space is provided between the upper flange and the lower flange in the vicinity of the intermediate fulcrum, the web, and the lower flange in the region surrounded by the vertical stiffener, and the precast plate is disposed.
By integrating the lower flange and precast plate with a stopper that is not connected to the upper flange,
An I-girder structure in the vicinity of an intermediate fulcrum in a continuous I-girder bridge characterized by preventing local buckling of the lower flange and improving lateral buckling strength.
前記プレキャスト板に箱抜き部が設けられており、該箱抜き部が設けられたプレキャスト板を、中間支点近傍の下フランジ、ウェブ、鉛直補剛材で囲まれる領域の下フランジの上に配設し、ずれ止めを箱抜き部の中となるように下フランジに配設し、箱抜き部へ充填材を打設して、下フランジとプレキャスト板を一体化させることを特徴とする請求項1記載の連続I桁橋における中間支点近傍のI桁の構造。   The precast plate is provided with a boxing portion, and the precast plate provided with the boxing portion is arranged on the lower flange in the vicinity of the intermediate fulcrum, the web, and the lower flange surrounded by the vertical stiffener. The stopper is disposed on the lower flange so as to be in the box-cutting portion, and a filler is placed on the box-cutting portion to integrate the lower flange and the precast plate. Structure of the I-girder near the intermediate fulcrum in the described continuous I-girder bridge. 請求項1又は2に記載の中間支点近傍のI桁の構造を有する連続I桁橋。   A continuous I-girder bridge having an I-girder structure near an intermediate fulcrum according to claim 1 or 2.
JP2010032865A 2010-02-17 2010-02-17 Structure near the intermediate support of a continuous I-girder bridge Expired - Lifetime JP4508293B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP2010032865A JP4508293B2 (en) 2010-02-17 2010-02-17 Structure near the intermediate support of a continuous I-girder bridge

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP2010032865A JP4508293B2 (en) 2010-02-17 2010-02-17 Structure near the intermediate support of a continuous I-girder bridge

Related Parent Applications (1)

Application Number Title Priority Date Filing Date
JP2005119619A Division JP4492422B2 (en) 2005-04-18 2005-04-18 Structure near the intermediate support of a continuous I-girder bridge

Publications (2)

Publication Number Publication Date
JP2010144512A true JP2010144512A (en) 2010-07-01
JP4508293B2 JP4508293B2 (en) 2010-07-21

Family

ID=42565207

Family Applications (1)

Application Number Title Priority Date Filing Date
JP2010032865A Expired - Lifetime JP4508293B2 (en) 2010-02-17 2010-02-17 Structure near the intermediate support of a continuous I-girder bridge

Country Status (1)

Country Link
JP (1) JP4508293B2 (en)

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107309844A (en) * 2017-06-20 2017-11-03 邯郸市恒工冶金机械有限公司 One kind is used for moveable cutting frame on single current cutting equipment
US10190936B2 (en) 2015-01-05 2019-01-29 Bae Systems Plc Mobile bridge apparatus
US10202729B2 (en) * 2015-01-05 2019-02-12 Bae Systems Plc Mobile bridge module

Families Citing this family (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102330408A (en) * 2011-08-05 2012-01-25 中国神华能源股份有限公司 Bridge

Citations (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2002266317A (en) * 2001-03-12 2002-09-18 Topy Ind Ltd Continuous girder for bridge

Patent Citations (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2002266317A (en) * 2001-03-12 2002-09-18 Topy Ind Ltd Continuous girder for bridge

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US10190936B2 (en) 2015-01-05 2019-01-29 Bae Systems Plc Mobile bridge apparatus
US10202729B2 (en) * 2015-01-05 2019-02-12 Bae Systems Plc Mobile bridge module
CN107309844A (en) * 2017-06-20 2017-11-03 邯郸市恒工冶金机械有限公司 One kind is used for moveable cutting frame on single current cutting equipment

Also Published As

Publication number Publication date
JP4508293B2 (en) 2010-07-21

Similar Documents

Publication Publication Date Title
JP3660826B2 (en) Rigid structure of upper and lower composite members
KR20200008726A (en) Steel-concrete hybrid box-type girders with incrementally-cast bottom concrete flange and its constructional method
KR20130090709A (en) Construction method for corrugated steel plate web-psc composite beam
JP2010144512A (en) Structure near intermediate supporting point of continuous i-beam bridge
JP3830767B2 (en) Continuous girder for bridge
KR101243777B1 (en) Rahmen bridge using composite structure of corrugated steel web and concrete member and constructing method thereof
KR101426155B1 (en) The hybrid rahmen structure which can add prestress on steel girder of horizontal member by gap difference of connection face between vertical member and steel girder of horizontal member
KR101329372B1 (en) Deflection control structure of deck plate of slim floor with demountable tendon and construction method thereof
KR101752285B1 (en) Hybrid beam with wide PSC lower flange and enlarged section upper flange and structure frame using the same
JP2006299554A (en) Structure near the intermediate fulcrum of continuous I-girder bridge
JP7123870B2 (en) Girder reinforcement structure
JP5029271B2 (en) Structure of a continuous I-girder bridge and its I-girder near its intermediate support
KR100550241B1 (en) Girder bridge
JP3996043B2 (en) Joint structure of bridge corrugated steel web composite girder
JP4644146B2 (en) PC box girder bridge
JP6325286B2 (en) Bridge reinforcement structure and bridge reinforcement method
JP2008088634A (en) Steel concrete composite slab
JP2000008325A (en) Floor slab composite girder structure
KR100767145B1 (en) Construction method of prestressed concrete temporary bridge that can be assembled and dismantled using lateral steel wire
JP5105016B2 (en) Structure of a continuous I-girder bridge and its I-girder near its intermediate support
JP4967972B2 (en) Continuous I-girder bridge, structure of I-girder near its intermediate support and method of construction
JP3950748B2 (en) Bridge girder
JP5738111B2 (en) Bridge girder
JP5295198B2 (en) Composite floor slab and continuous girder bridge
KR102561925B1 (en) Composite girder and manufacturing method thereof

Legal Events

Date Code Title Description
A975 Report on accelerated examination

Free format text: JAPANESE INTERMEDIATE CODE: A971005

Effective date: 20100401

TRDD Decision of grant or rejection written
A01 Written decision to grant a patent or to grant a registration (utility model)

Free format text: JAPANESE INTERMEDIATE CODE: A01

Effective date: 20100413

A01 Written decision to grant a patent or to grant a registration (utility model)

Free format text: JAPANESE INTERMEDIATE CODE: A01

A61 First payment of annual fees (during grant procedure)

Free format text: JAPANESE INTERMEDIATE CODE: A61

Effective date: 20100426

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20130514

Year of fee payment: 3

R150 Certificate of patent or registration of utility model

Ref document number: 4508293

Country of ref document: JP

Free format text: JAPANESE INTERMEDIATE CODE: R150

Free format text: JAPANESE INTERMEDIATE CODE: R150

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20140514

Year of fee payment: 4

S531 Written request for registration of change of domicile

Free format text: JAPANESE INTERMEDIATE CODE: R313531

R370 Written measure of declining of transfer procedure

Free format text: JAPANESE INTERMEDIATE CODE: R370

R370 Written measure of declining of transfer procedure

Free format text: JAPANESE INTERMEDIATE CODE: R370

S531 Written request for registration of change of domicile

Free format text: JAPANESE INTERMEDIATE CODE: R313531

R371 Transfer withdrawn

Free format text: JAPANESE INTERMEDIATE CODE: R371

S531 Written request for registration of change of domicile

Free format text: JAPANESE INTERMEDIATE CODE: R313531

R350 Written notification of registration of transfer

Free format text: JAPANESE INTERMEDIATE CODE: R350

EXPY Cancellation because of completion of term