JP2010128819A - Support process determination system and support process determination method - Google Patents

Support process determination system and support process determination method Download PDF

Info

Publication number
JP2010128819A
JP2010128819A JP2008303207A JP2008303207A JP2010128819A JP 2010128819 A JP2010128819 A JP 2010128819A JP 2008303207 A JP2008303207 A JP 2008303207A JP 2008303207 A JP2008303207 A JP 2008303207A JP 2010128819 A JP2010128819 A JP 2010128819A
Authority
JP
Japan
Prior art keywords
work
support
time
delay time
production line
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
JP2008303207A
Other languages
Japanese (ja)
Inventor
Soichi Mitani
聡一 三谷
Takeshi Yasui
毅 安井
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Nissan Motor Co Ltd
Original Assignee
Nissan Motor Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Nissan Motor Co Ltd filed Critical Nissan Motor Co Ltd
Priority to JP2008303207A priority Critical patent/JP2010128819A/en
Publication of JP2010128819A publication Critical patent/JP2010128819A/en
Pending legal-status Critical Current

Links

Images

Classifications

    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02PCLIMATE CHANGE MITIGATION TECHNOLOGIES IN THE PRODUCTION OR PROCESSING OF GOODS
    • Y02P90/00Enabling technologies with a potential contribution to greenhouse gas [GHG] emissions mitigation
    • Y02P90/02Total factory control, e.g. smart factories, flexible manufacturing systems [FMS] or integrated manufacturing systems [IMS]
    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02PCLIMATE CHANGE MITIGATION TECHNOLOGIES IN THE PRODUCTION OR PROCESSING OF GOODS
    • Y02P90/00Enabling technologies with a potential contribution to greenhouse gas [GHG] emissions mitigation
    • Y02P90/30Computing systems specially adapted for manufacturing

Landscapes

  • General Factory Administration (AREA)
  • Management, Administration, Business Operations System, And Electronic Commerce (AREA)

Abstract

<P>PROBLEM TO BE SOLVED: To provide a support process determination method capable of automatically determining which process is required to be supported by an instructor to advance a line most smoothly. <P>SOLUTION: The support process determination method which is a procedure to be performed in a support process determination system installed in a production line includes: a step of storing operation delay time obtained by subtracting the standard operation time of each product from real operation time practically required for a worker to perform the operation of each product at any time as an operation result in each process included in the production line; a step (step S12) of calculating future accumulative operation delay time when products are sequentially charged into respective processes in future based on operation results and a production plan indicating the order of products allowed to flow into the production line; steps (steps S14, S15) of specifying a process that the calculated accumulative operation delay time is not less than reference time to be a reference for determining the delay of the production line; and steps (steps S17 to S19) of determining the specified process as a process requiring support. <P>COPYRIGHT: (C)2010,JPO&INPIT

Description

本発明は、生産ラインの工程において、支援が必要な工程を判断する支援工程判断システムおよび支援工程判断方法に関する。   The present invention relates to a support process determination system and a support process determination method for determining a process that needs support in a production line process.

生産ラインにおいて、工程替え直後など、習熟が充分ではない工程に作業者が新たに配置される場合、該工程には、作業者の作業手順を指示する作業指示装置が配置される(たとえば、特許文献1参照)。作業指示装置は、工程の作業項目を順に表示する。作業項目が全て終了すると、作業者によって工程終了が入力される。   In the production line, when a worker is newly arranged in a process that is not sufficiently learned, such as immediately after a process change, a work instruction device that instructs the work procedure of the worker is arranged in the process (for example, a patent Reference 1). The work instruction device displays work items of the process in order. When all work items are completed, the end of the process is input by the worker.

ところで、生産ラインには、作業の遅れや作業ミスを挽回するために、ベテランの指導員(支援者)が配置されている。指導員は、複数工程、たとえば、15工程前後を担当して、作業者が作業遅れや作業ミスした場合に、作業者の呼出に応じて、該作業者の工程に駆けつけ、作業を支援する。ここで、作業員は、生産ラインに配設されている紐を引っ張ることによって、指導員に作業遅れ等を知らせる。   By the way, in order to make up for work delays and work mistakes, experienced instructors (supporters) are arranged on the production line. The instructor is in charge of a plurality of processes, for example, around 15 processes, and when the worker is late or misses the work, he or she rushes to the worker's process and supports the work. Here, the worker informs the instructor of the work delay or the like by pulling the string arranged on the production line.

しかし、上記システムでは、指導員を支援のために呼ぶかどうかの判断は、作業者の判断に任されている。したがって、その判断が適切であるかどうかは不明である。特に、作業者は、過去の作業時間の実績や、今後流れてくる製品の種類や作業量もわからないので、作業者が適切に指導員を呼び出せているとは限らない。指導員が呼び出された時には、既にライン停止がやむを得ない場合もある。作業者は、ライン停止を確信するまで、指導員を呼ばない傾向がある。
特開2002−304210号公報
However, in the above system, it is up to the operator to determine whether to call an instructor for support. Therefore, it is unclear whether the judgment is appropriate. In particular, since the worker does not know the past work time record, the type of product that will flow in the future, and the amount of work, the worker is not always able to call the instructor appropriately. When an instructor is called, there may be unavoidable line stops. Workers tend not to call instructors until they are sure that the line will stop.
JP 2002-304210 A

本発明は上記事情に鑑みてなされたものであり、どの工程に対して指導員を支援させれば最もラインが円滑に進行するかを自動で判断できる支援工程判断システムおよび支援工程判断方法を提供することを目的とする。   The present invention has been made in view of the above circumstances, and provides a support process determination system and a support process determination method capable of automatically determining which process is most smoothly performed when an instructor is supported for which process. For the purpose.

本発明の支援工程判断システムは、第1記憶部と、第2記憶部と、第3記憶部と、算出部と、判断部とを有する。第1記憶部は、生産ラインに含まれる工程毎に、各製品の標準作業時間と、該生産ラインの遅れを判断するための基準となる基準時間とを記憶する。第2記憶部は、工程毎に、各製品の作業に作業者が実際に要した実作業時間から、各製品の標準作業時間を減算して得られた作業遅れ時間を、作業実績として随時記憶する。第3記憶部は、生産ラインに流す製品の種類および順番を示す生産計画を記憶する。算出部は、作業実績および生産計画に基づいて、今後各工程に製品が順に投入されたときの将来の累積的な作業遅れ時間を算出する。判断部は、算出した累積的な作業遅れ時間が基準時間以上の工程を特定し、支援が必要な工程と判断する。   The support process determination system of the present invention includes a first storage unit, a second storage unit, a third storage unit, a calculation unit, and a determination unit. A 1st memory | storage part memorize | stores the standard operation time of each product and the reference | standard time used as the reference | standard for judging the delay of this production line for every process included in a production line. The second storage unit stores the work delay time obtained by subtracting the standard work time of each product from the actual work time actually required for the work of each product for each process as work results. To do. A 3rd memory | storage part memorize | stores the production plan which shows the kind and order of the product sent to a production line. The calculation unit calculates a future cumulative work delay time when products are sequentially introduced into each process in the future based on the work results and the production plan. The determination unit identifies a process in which the calculated cumulative work delay time is equal to or longer than a reference time, and determines that the process needs support.

本発明の支援工程判断方法は、生産ラインに設けられた支援工程判断システムによって実行される手順であって、次のステップを実行する。生産ラインに含まれる工程毎に、各製品の作業に作業者が実際に要した実作業時間から、各製品の標準作業時間を減算して得られた作業遅れ時間を、作業実績として随時記憶する。作業実績とこれから生産ラインに流す製品の順番を示す生産計画とに基づいて、今後各工程に製品が順に投入されたときの将来の累積的な作業遅れ時間を算出する。算出した累積的な作業遅れ時間が、生産ラインの遅れを判断するための基準となる基準時間以上の工程を特定し、支援が必要な工程と判断する。   The support process determination method of the present invention is a procedure executed by a support process determination system provided in a production line, and executes the following steps. For each process included in the production line, the work delay time obtained by subtracting the standard work time of each product from the actual work time actually required for the work of each product is stored as work results as needed. . Based on the actual work and a production plan indicating the order of products to be sent to the production line, a future cumulative work delay time when products are sequentially introduced into each process in the future is calculated. A process in which the calculated cumulative work delay time is equal to or longer than a reference time serving as a reference for determining a delay in the production line is determined and determined as a process requiring support.

本発明の支援工程判断システムによれば、作業実績および生産計画に基づいて、累積的な作業遅れ時間を予測算出するので、将来的に支援が必要となりそうな工程を、事前に自動で判断できる。したがって、作業者が自身で作業遅れを判断する必要がない。また、工程を支援する指導員などの支援者にとっても、作業者の主観的な判断ではなく、客観的に支援が必要な工程を得られうる。将来的に生産ラインを停止させる虞がある工程を、支援が必要な工程として特定して、生産ラインの停止を予防できる。   According to the support process determination system of the present invention, since the cumulative work delay time is predicted and calculated based on the work results and the production plan, it is possible to automatically determine in advance a process that is likely to require support in the future. . Therefore, it is not necessary for the worker to determine the work delay by himself. Also, for a supporter such as an instructor supporting the process, a process that requires objective support can be obtained instead of the subjective judgment of the worker. It is possible to prevent a production line from being stopped by identifying a process that may cause the production line to be stopped in the future as a process requiring assistance.

本発明の支援工程判断方法によれば、作業実績および生産計画に基づいて、累積的な作業遅れ時間を予測算出するので、将来的に支援が必要となりそうな工程を、事前に自動で判断できる。したがって、作業者が自身で作業遅れを判断する必要がない。また、工程を支援する指導員などの支援者にとっても、作業者の主観的な判断ではなく、客観的に支援が必要な工程を得られうる。将来的に生産ラインを停止させる虞がある工程を、支援が必要な工程として特定して、生産ラインの停止を予防できる。   According to the support process determination method of the present invention, the cumulative work delay time is predicted and calculated based on the work results and the production plan, so that a process that may be required in the future can be automatically determined in advance. . Therefore, it is not necessary for the worker to determine the work delay by himself. Also, for a supporter such as an instructor supporting the process, a process that requires objective support can be obtained instead of the subjective judgment of the worker. It is possible to prevent a production line from being stopped by identifying a process that may cause the production line to be stopped in the future as a process requiring assistance.

以下、図面を参照して、本発明の実施の形態を説明する。以下では、生産ラインに商品として車両が流れて、部品が取り付けられる等して、組み立てられる場合について説明する。   Embodiments of the present invention will be described below with reference to the drawings. Hereinafter, a case where a vehicle flows as a product on a production line and parts are attached and assembled will be described.

(第1実施形態)
図1は支援工程判断システムを示す概略図、図2はデータ処理装置の概略構成を示す図、図3は生産ラインに作業ナビゲーション装置が設置された様子を示す図、図4はモニターに示される作業内容の例を示す図である。
(First embodiment)
FIG. 1 is a schematic diagram showing a support process determination system, FIG. 2 is a diagram showing a schematic configuration of a data processing device, FIG. 3 is a diagram showing a work navigation device installed on a production line, and FIG. 4 is shown on a monitor. It is a figure which shows the example of work content.

図1に示すように、支援工程判断システムは、生産ラインに設置されるシステムであって、データ処理装置10と、複数の作業指示装置(以下、作業ナビという)20とを有する。データ処理装置10には、複数の作業ナビ20が接続されており、どの製品を順に加工するか等の今後の生産計画を含む作業指示が入力される。データ処理装置10は、必要な情報を各作業ナビ20a〜dに展開する。   As shown in FIG. 1, the support process determination system is a system installed on a production line, and includes a data processing device 10 and a plurality of work instruction devices (hereinafter referred to as work navigation) 20. A plurality of work navigators 20 are connected to the data processing apparatus 10, and work instructions including future production plans such as which products are to be processed in order are input. The data processing device 10 develops necessary information in each of the work navigations 20a to 20d.

データ処理装置10は、図2に示すように、記憶部12、表示部14および制御部16を有する。記憶部12は、第1記憶部、第2記憶部および第3記憶部としての機能を果たす。第1記憶部として、記憶部12は、生産ラインに含まれる工程毎に、各製品の標準作業時間と、該生産ラインの遅れを判断するための基準となる基準時間とを記憶する。第2記憶部として、記憶部12は、生産ラインの工程毎に、各製品の作業に作業者が実際に要した実作業時間から、各製品の前記標準作業時間を減算して得られた作業遅れ時間を、作業実績として随時記憶する。第3記憶部として、記憶部12は、生産ラインに流す製品の種類および順番を示す生産計画を記憶する。   As illustrated in FIG. 2, the data processing device 10 includes a storage unit 12, a display unit 14, and a control unit 16. The storage unit 12 functions as a first storage unit, a second storage unit, and a third storage unit. As the first storage unit, the storage unit 12 stores, for each process included in the production line, a standard work time of each product and a reference time serving as a reference for determining the delay of the production line. As the second storage unit, the storage unit 12 is a work obtained by subtracting the standard work time of each product from the actual work time actually required for the work of each product for each process of the production line. The delay time is stored as a work record at any time. As the third storage unit, the storage unit 12 stores a production plan indicating the type and order of products to be sent to the production line.

表示部14は、ユーザインターフェースであり、各種情報を表示する。たとえば、表示部14は、記憶部12に記憶されている内容を表示する。また、表示部14には、作業実績や作業遅れ時間などの作業ナビ20に蓄積された情報を表示することもできる。   The display unit 14 is a user interface and displays various types of information. For example, the display unit 14 displays the contents stored in the storage unit 12. The display unit 14 can also display information accumulated in the work navigation 20 such as work results and work delay times.

制御部16は、記憶部12および表示部14に接続されており、データ処理装置10の全体を制御する。制御部16は、算出部および判断部の機能を果たし、各工程の将来の作業遅れ時間を算出したり、支援が必要な工程を判断したりする。詳細な制御部16の作用については、後述する。   The control unit 16 is connected to the storage unit 12 and the display unit 14 and controls the entire data processing apparatus 10. The control unit 16 functions as a calculation unit and a determination unit, and calculates a future work delay time for each process or determines a process that needs support. The detailed operation of the control unit 16 will be described later.

作業ナビ20は、生産ラインの各工程に配置される。作業ナビ20は、指示装置として、データ処理装置10からの生産計画に基づいて、配置された工程に流れる製品に対する作業内容を作業者に指示する。作業ナビ20は、たとえば、図3に示すように、作業者A、B、Dの工程に設置される。この場合、作業者A、B、Dは、比較的、不慣れな作業者であり、作業ナビから教示された作業内容を確認しながら、作業を実行する。一方、作業者Cは、作業手順を熟知しており、作業ナビによって作業の工程を指示される必要がないベテラン作業員である。このように、比較的不慣れな作業者の工程に、作業ナビ20が配置されることが好ましい。生産ラインには、不慣れな作業者A、B、Dの作業が遅れたときに、遅れた工程に向かい作業を支援する指導員Xが配置されている。指導員Xは、複数工程を担当して、作業遅延に備えて待機している。   The work navigation 20 is arranged in each process of the production line. The work navigator 20 instructs the worker as to the work content for the product flowing in the arranged process based on the production plan from the data processing device 10 as an instruction device. The work navigation 20 is installed in the processes of workers A, B, and D, for example, as shown in FIG. In this case, the workers A, B, and D are relatively unskilled workers, and perform the work while confirming the work content taught from the work navigation. On the other hand, the worker C is a veteran worker who is familiar with the work procedure and does not need to be instructed in the work process by the work navigation. Thus, it is preferable that the work navigation 20 is arranged in a process of a relatively unfamiliar worker. In the production line, when the work of unfamiliar workers A, B, and D is delayed, an instructor X is arranged to assist the work toward the delayed process. The instructor X is in charge of a plurality of processes and stands by in preparation for work delays.

各作業ナビ20には、モニター22が接続されている。モニター22は、作業内容を表示し、各工程の作業者に必要な作業を示す。たとえば、製品である車両に、部品であるサスペンションを取り付ける場合、モニター22には、図4に示すように、部品番号や、部品の写真が示される。特に、同種の他の部品と間違えないように、付されている印の色などの特徴が示される。   A monitor 22 is connected to each work navigation 20. The monitor 22 displays the work content and indicates the work necessary for the worker in each process. For example, when a suspension that is a part is attached to a vehicle that is a product, a part number and a picture of the part are displayed on the monitor 22 as shown in FIG. In particular, features such as the color of the mark attached are shown so as not to be mistaken for other parts of the same type.

作業ナビ20は、次のように動作する。   The work navigation 20 operates as follows.

図5は作業ナビの動作の流れを示すフローチャートである。図5では、複数の作業ナビ20のうち、ある工程に配置されている1つの動作を示す。   FIG. 5 is a flowchart showing a flow of operations of the work navigation. FIG. 5 shows one operation arranged in a certain process among the plurality of work navigations 20.

まず、作業ナビ20は、担当工程に新たな製品が流れてきて、作業が開始になったかを確認する(ステップS1)。たとえば、作業ナビ20は、コンベアを流れる製品が担当工程に入ったことをセンサで確認し、作業が開始になったと判断する。ここでは、作業ナビ20は、確認部として機能する。作業が開始されない場合(ステップS1:NO)、作業開始まで作業ナビ20は待機する。作業が開始された場合(ステップS1:YES)、作業ナビ20は、処理される製品に対する作業内容をモニター22に表示して、作業者に指示する(ステップS2)。ここでは、作業ナビ20は、指示部として機能する。   First, the work navigation 20 confirms whether a new product has flowed into the process in charge and the work has started (step S1). For example, the work navigation 20 confirms with a sensor that the product flowing through the conveyor has entered the process in charge, and determines that the work has started. Here, the work navigation 20 functions as a confirmation unit. If the work is not started (step S1: NO), the work navigation 20 waits until the work starts. When the work is started (step S1: YES), the work navigation 20 displays the work content for the product to be processed on the monitor 22 and instructs the worker (step S2). Here, the work navigation 20 functions as an instruction unit.

そして、作業ナビ20は、表示した作業内容が完了したかどうかを判断する(ステップS3)。作業内容が完了したかどうかは、作業者が作業ナビ20に設けられたボタンを押したり、モニター22のタッチパネルに触れたりすることによって確認される。ここでは、作業ナビ20は、入力部として機能する。   Then, the work navigation 20 determines whether or not the displayed work content is completed (step S3). Whether the work content is completed is confirmed by the operator pressing a button provided on the work navigation 20 or touching the touch panel of the monitor 22. Here, the work navigation 20 functions as an input unit.

作業項目の完了が確認されない場合(ステップS3:NO)、作業ナビ20は、作業項目が完了されるまで、作業内容を表示する。作業内容の完了が確認された場合(ステップS3:YES)、作業ナビ20は、該作業内容について作業開始から作業完了までの実作業時間を計測し、データ処理装置10に送信する(ステップS4)。ここでは、作業ナビ20は、計測部として機能する。   If the completion of the work item is not confirmed (step S3: NO), the work navigation 20 displays the work content until the work item is completed. When the completion of the work content is confirmed (step S3: YES), the work navigation 20 measures the actual work time from the work start to the work completion for the work content, and transmits it to the data processing device 10 (step S4). . Here, the work navigation 20 functions as a measurement unit.

作業ナビ20は、全ての作業が終了したか否かを判断する(ステップS5)。全ての作業が終了していない場合(ステップS5:NO)、すなわち、生産計画により次の製品がある場合、作業ナビ20は、ステップS1の動作に戻り、次の製品が流れてくるまで待機する。作業が終了した場合(ステップS5:YES)、作業ナビ20は、動作を終了する。   The work navigation 20 determines whether or not all work has been completed (step S5). When all the operations are not completed (step S5: NO), that is, when there is a next product according to the production plan, the work navigation 20 returns to the operation of step S1 and waits until the next product flows. . When the work is finished (step S5: YES), the work navigation 20 finishes the operation.

図6は記憶部に記憶される各種設定時間を示す図、図7はデータ処理装置10に蓄積される作業実績のデータの例を示す図である。   FIG. 6 is a diagram illustrating various set times stored in the storage unit, and FIG. 7 is a diagram illustrating an example of work performance data stored in the data processing apparatus 10.

データ処理装置10は、作業ナビ20から実作業時間を受信すると、対応する工程の対応する車種に対する標準的な作業時間(標準作業時間)を記憶部12から読み出す。そして、図6に示すように、実作業時間から標準作業時間を減算して、作業遅れ時間を算出する。   When the data processing apparatus 10 receives the actual work time from the work navigation 20, the data processing apparatus 10 reads the standard work time (standard work time) for the corresponding vehicle type in the corresponding process from the storage unit 12. Then, as shown in FIG. 6, the work delay time is calculated by subtracting the standard work time from the actual work time.

そして、作業遅れ時間が、作業実績として記憶部12に蓄積される。ここで、図7に示す例では、作業ナビ20毎に、車種と作業者のデータが蓄積される。作業ナビ20aが設置された工程には、これまで、作業員A、作業員B、作業員Cが配属され、車種a〜eの組立作業を実施したことが示される。   Then, the work delay time is accumulated in the storage unit 12 as work results. Here, in the example illustrated in FIG. 7, the data of the vehicle type and the worker is accumulated for each work navigation 20. In the process in which the work navigation 20a is installed, the worker A, the worker B, and the worker C have been assigned so far, and the assembly work of the vehicle types a to e has been performed.

図7によると、作業員Aは、作業ナビ20aが設置される工程では、車両aについて遅れ時間の平均が−5秒で、最小遅れ時間(Min)が−15秒、最大遅れ時間(Max)が10秒であったことがわかる。ここで−5秒とは、標準作業時間よりも5秒余ることを意味する。同様に、作業員Bは、作業ナビ20aが設置される工程では、車両aについて遅れ時間の平均が−5秒で、最小遅れ時間が−15秒、最大遅れ時間が0秒であったことがわかる。   According to FIG. 7, in the process in which the work navigation 20a is installed, the worker A has an average delay time of −5 seconds, a minimum delay time (Min) of −15 seconds, and a maximum delay time (Max). Is 10 seconds. Here, −5 seconds means that 5 seconds are left after the standard work time. Similarly, in the process in which the work navigation 20a is installed, the worker B has an average delay time of -5 seconds, a minimum delay time of -15 seconds, and a maximum delay time of 0 seconds for the vehicle a. Recognize.

このように、作業者および車種毎の作業遅れ時間の最小値、平均値、最大値が随時更新され記憶される。本実施形態では、同じ作業ナビ20a担当の工程で、同時に作業員A、作業員B、作業員Cが作業することはないので、たとえば、作業ナビ20aの車種aについての作業遅れ時間のデータは、異なる日時に収集されたものである。作業ナビ20bや他の作業ナビ20についても同様に作業遅れ時間のデータが蓄積される。   Thus, the minimum value, average value, and maximum value of the work delay time for each worker and vehicle type are updated and stored as needed. In this embodiment, since the worker A, the worker B, and the worker C do not work at the same time in the process of the same work navigation 20a, for example, the work delay time data for the vehicle type a of the work navigation 20a is , Collected at different dates and times. The work delay time data is similarly accumulated for the work navigation 20b and other work navigations 20.

なお、図6に示す許容時間は、それ以上遅れると生産ラインを停止しなくてはいけない限界時間である。基準時間は、許容時間よりも短く設定されており、工程において、作業者を支援する指導員を呼ぶかどうかを判断するための基準である。詳細については、次述のデータ処理装置10の作用として説明する。   Note that the permissible time shown in FIG. 6 is a limit time that the production line must be stopped if it is delayed further. The reference time is set shorter than the allowable time, and is a reference for determining whether or not to call an instructor supporting the worker in the process. Details will be described as an operation of the data processing apparatus 10 described below.

図8はデータ処理装置の動作の流れを示すフローチャート、図9はデータ処理装置により予測される作業遅延の具体例を示す図である。   FIG. 8 is a flowchart showing the operation flow of the data processing apparatus, and FIG. 9 is a diagram showing a specific example of work delay predicted by the data processing apparatus.

データ処理装置10は、上記のように収集した作業実績を用いて、将来的な作業遅れを予測して、指導員による支援が必要な工程を判断する。データ処理装置10の作用は、制御部16によって実行される。   The data processing apparatus 10 predicts a future work delay using the work results collected as described above, and determines a process that needs assistance from the instructor. The operation of the data processing apparatus 10 is executed by the control unit 16.

制御部16は、各工程の作業遅れ時間を参照する(ステップS10)。この参照は、図9に示すテーブルの「進捗」の行を参照する。この行には、現在の作業遅れ時間が示されている。図9に示す例では、作業員A、作業員B、作業員C共に現在10秒の作業遅れが発生しているのがわかる。   The control unit 16 refers to the work delay time of each process (step S10). This reference refers to the “progress” line in the table shown in FIG. This line shows the current work delay time. In the example shown in FIG. 9, it can be seen that the worker A, the worker B, and the worker C all have a work delay of 10 seconds.

続けて、制御部16は、記憶部12に記憶されている作業実績および生産計画を参照し(ステップS11)、将来の累積的な作業遅れを算出する(ステップS12)。ここでは、制御部16は、生産計画に基づいて、今後作業予定の車種を10台分特定する。そして、各車種の作業に作業者がかかる時間を、図7の作業実績データから特定する。最小作業遅れ時間、平均作業遅れ時間、最大作業遅れ時間をそれぞれ累積して、10台後の累積的な作業遅れ時間を演算する。図9の作業員Aでは、10台後の最小作業遅れ時間が5秒、平均作業遅れ時間が75秒、最大作業遅れ時間が195秒である。   Subsequently, the control unit 16 refers to the work results and the production plan stored in the storage unit 12 (step S11), and calculates a future cumulative work delay (step S12). Here, the control unit 16 specifies 10 types of vehicles scheduled to be worked on in the future based on the production plan. And the time which an operator takes in the operation | work of each vehicle type is specified from the work performance data of FIG. The minimum work delay time, the average work delay time, and the maximum work delay time are accumulated to calculate a cumulative work delay time after 10 units. For worker A in FIG. 9, the minimum work delay time after 10 units is 5 seconds, the average work delay time is 75 seconds, and the maximum work delay time is 195 seconds.

制御部16は、10台後の累積的な平均作業遅れ時間を、基準時間と比較する(ステップS13)。基準時間は、製品および工程ごとに異なる。したがって、制御部16は、該当する工程の10台後の製品の作業に対する基準時間と、平均作業遅れ時間を比較する。図9の作業員Aの場合、工程−1で10台後の製品は車種bであるので、工程−1での車種bを作業するときの基準時間を、平均作業遅れ時間75秒と比較する。基準時間は、たとえば、図6に示すように、許容時間の2/3程度である。許容時間は、たとえば、標準作業時間の半分として設定されている。   The control unit 16 compares the cumulative average work delay time after 10 units with the reference time (step S13). The reference time is different for each product and process. Therefore, the control unit 16 compares the reference time for the work of the product after 10 units in the corresponding process with the average work delay time. In the case of the worker A in FIG. 9, the product after 10 units in the process-1 is the vehicle type b. Therefore, the reference time when working the vehicle type b in the process-1 is compared with the average work delay time 75 seconds. . The reference time is, for example, about 2/3 of the allowable time, as shown in FIG. The allowable time is set as, for example, half of the standard work time.

制御部16は、基準時間以上の工程があるかを判断する(ステップS14)。基準時間以上の工程がない場合(ステップS14:NO)、生産ライン停止となる虞がないので、ステップS10に戻り、処理を繰り返す。基準時間以上の工程がある場合(ステップS14:YES)、制御部16は、該当する工程を特定する(ステップS15)。   The control unit 16 determines whether there is a step longer than the reference time (step S14). If there is no process longer than the reference time (step S14: NO), there is no possibility of the production line being stopped, so the process returns to step S10 and the process is repeated. When there is a process longer than the reference time (step S14: YES), the control unit 16 specifies the corresponding process (step S15).

制御部16は、特定した工程が複数工程か判断する(ステップS16)。複数工程でない場合(ステップS16:NO)、制御部16は、特定した工程を、指導員Xにより支援が必要な工程と判断する(ステップS17)。   The control unit 16 determines whether the identified process is a plurality of processes (step S16). When it is not a plurality of processes (step S16: NO), the control unit 16 determines that the identified process is a process that needs assistance from the instructor X (step S17).

複数工程がある場合(ステップS16:YES)、制御部16は、特定した工程の作業遅れ時間に重み付けする(ステップS18)。たとえば、制御部16は、複数の工程について、より上流にある工程により大きな係数をかける。一番上流の工程の遅れ時間を1.5倍、その次を1.3倍、その次を1.1倍…というように係数をかける。   When there are a plurality of processes (step S16: YES), the control unit 16 weights the work delay time of the identified process (step S18). For example, the control unit 16 applies a larger coefficient to the processes upstream of the plurality of processes. The delay time of the most upstream process is multiplied by 1.5, the next is multiplied by 1.3, the next is multiplied by 1.1, and so on.

制御部16は、工程ごとに、標準作業時間に対する、重み付けられた累積的な作業遅れ時間の割合を算出し、該割合が最大の工程を、支援が必要な工程と判断する(ステップS19)。   For each process, the control unit 16 calculates a ratio of the weighted cumulative work delay time to the standard work time, and determines a process having the maximum ratio as a process requiring support (step S19).

制御部16は、表示部14およびモニター22に、支援が必要と判断した工程を表示する(ステップS20)。これにより、今後の生産計画に基づいて、客観的に支援が必要な工程がわかる。好ましくは、特定した工程は、実際に作業の支援を行う指導員Xに直接通知される。この場合、指導員が携帯するPDAや携帯電話等の携帯端末に工程が通知される。これにより指導員は、即座に支援が必要な工程を知ることができる。あるいは、支援が必要と判断された工程に配置されたモニター22にのみ、支援が必要な旨が通知されてもよい。   The control unit 16 displays the process determined to require support on the display unit 14 and the monitor 22 (step S20). As a result, it is possible to know a process that requires objective support based on a future production plan. Preferably, the specified process is directly notified to the instructor X who actually supports the work. In this case, the process is notified to a portable terminal such as a PDA or a mobile phone carried by the instructor. As a result, the instructor can immediately know the process that needs assistance. Alternatively, only the monitor 22 arranged in the process determined to require support may be notified that support is required.

制御部16は、作業が終了したかどうかを判断する(ステップS21)。作業の終了とは、たとえば、本日の生産計画が終了した場合である。作業が終了していない場合(ステップS21:NO)、制御部16は、ステップS10からの処理を繰り返す。作業が終了した場合(ステップS21:YES)、制御部16は動作を停止する。   The control unit 16 determines whether or not the work is finished (step S21). The end of work is, for example, a case where today's production plan is finished. When the work is not finished (step S21: NO), the control unit 16 repeats the processing from step S10. When the work is finished (step S21: YES), the control unit 16 stops its operation.

上記実施形態の支援工程判断システムによれば、作業実績および生産計画に基づいて、累積的な作業遅れ時間を予測算出するので、将来的に支援が必要となりそうな工程を、事前に自動で判断できる。したがって、作業者が自身で作業遅れを判断する必要がない。また、工程を支援する指導員にとっても、作業者の主観的な判断ではなく、客観的に支援が必要な工程を得られうる。結果として、将来的に生産ラインを停止させる虞がある工程を指導員Xが支援して、生産ラインの停止を予防できる。   According to the support process determination system of the above-described embodiment, the cumulative work delay time is predicted and calculated based on the work results and the production plan. Therefore, processes that are likely to require support in the future are automatically determined in advance. it can. Therefore, it is not necessary for the worker to determine the work delay by himself. In addition, for the instructor who supports the process, it is possible to obtain a process that requires objective support instead of the subjective judgment of the operator. As a result, the instructor X supports a process that may cause the production line to be stopped in the future, and can prevent the production line from being stopped.

特に、支援が必要と判断された工程を通知するので、工程を支援する指導員Xに通知された場合には指導員Xが直ちにその工程に駆けつけることができる。また、作業ナビ20のモニター22を通じて、支援が必要な工程が作業者に通知された場合には、作業者が自己の判断によらず直ちに支援者に応援を頼むことができる。   In particular, since the process for which support is determined to be required is notified, when the instructor X supporting the process is notified, the instructor X can immediately reach the process. In addition, when a process requiring assistance is notified to the worker through the monitor 22 of the work navigation 20, the worker can immediately ask the supporter for support regardless of his / her own judgment.

また、複数の工程が特定された場合でも、重み付けして将来的に最も支援が必要な工程を自動で判断できる。   Even when a plurality of processes are specified, it is possible to automatically determine a process that needs the most support in the future by weighting.

標準時間に対する、重み付けられた累積的な作業遅れ時間の割合が最大の工程を、支援が必要な工程を判断している。これにより、工程ごと製品ごとに異なる標準作業時間が異なっても、標準化して、最も作業遅れの度合いが高い工程を判断できる。   The process in which the ratio of the weighted cumulative work delay time with respect to the standard time is the largest is determined as the process requiring support. Thereby, even if the standard work time which differs for every product differs for every process, it can standardize and the process with the highest degree of work delay can be judged.

上流にある工程を重み付けて補正した上で、最も支援が必要な工程を判断する。したがって、上流の工程の方が生産ラインへの影響力が高いことを考慮して、支援が必要な工程を判断できる。   The process that needs the most support is judged after weighting and correcting the process in the upstream. Therefore, it is possible to determine a process that needs support in consideration of the fact that the upstream process has a higher influence on the production line.

また、上記実施形態によれば、図5に示す通り、作業ナビ20によって、作業者に作業内容が指示された上で、作業者によって作業の終了が入力されるので、適切に作業が終了したことを前提として、精度良く、作業者の作業実績を蓄積できる。   Further, according to the embodiment, as shown in FIG. 5, the work navigation 20 instructs the work content to the worker, and the worker finishes the work, so the work is finished properly. As a result, it is possible to accumulate the work results of the worker with high accuracy.

なお、上記実施形態では、生産ライン中の1つの工程に1人の作業者が配置されている場合について説明したが、これに限定されない。1つの工程に複数の作業者が配置されてもよい。この場合、データ処理装置10の記憶部12には、1つの工程内の作業者毎に、遅れ時間が蓄積される。   In addition, although the said embodiment demonstrated the case where one worker was arrange | positioned at one process in a production line, it is not limited to this. A plurality of workers may be arranged in one process. In this case, the storage unit 12 of the data processing apparatus 10 accumulates a delay time for each worker in one process.

また、上記実施形態では、現在処理している製品から10台後の製品を処理したときの累積的な作業遅れ時間を予測して、作業遅れを判断している。しかし、10台後を予測することに限定されない。1台後や100台後などいかなる台数後の作業遅れを予測してもよい。   Further, in the above embodiment, the work delay is determined by predicting the cumulative work delay time when a product after 10 units is processed from the currently processed product. However, it is not limited to predicting after 10 vehicles. Work delays after any number of units such as after one unit or after 100 units may be predicted.

また、上記実施形態では、平均作業遅れ時間の累積を予測して、基準時間と比較している。しかし、最小作業遅れ時間の累積や、最大作業遅れ時間の累積を基準時間と比較してもよい。たとえば、3台後の最大作業遅れ時間や20台後の最小作業遅れ時間の累積を、基準時間と比較してもよい。   In the above embodiment, the accumulation of the average work delay time is predicted and compared with the reference time. However, the accumulation of the minimum work delay time or the accumulation of the maximum work delay time may be compared with the reference time. For example, the accumulation of the maximum work delay time after 3 units or the minimum work delay time after 20 units may be compared with the reference time.

上記実施形態によれば、支援が必要な工程はデータ処理装置10によって自動で判断され、支援が必要だと作業者自身で判断する場合についての説明は省略している。しかし、図3に示すように、生産ラインのベルトコンベアに沿って、支援要請用の紐30を配置しておくことが好ましい。作業者A〜Dは、紐30を引っ張ることによって、自分の工程のランプを点灯させ、指導員Xを呼ぶことができる。通常、作業者自身が紐30をひくときは、緊急を要する場合なので、指導員Xは、上記データ処理装置10よりも紐30による応援要請を優先する。   According to the above-described embodiment, the process for which assistance is required is automatically determined by the data processing apparatus 10, and the description of the case where the operator himself determines that assistance is required is omitted. However, as shown in FIG. 3, it is preferable to arrange the support request string 30 along the belt conveyor of the production line. The workers A to D can call the instructor X by pulling the string 30 to turn on the lamp of their process. Usually, when the operator himself pulls the string 30, an emergency is required, so the instructor X gives priority to the support request by the string 30 over the data processing device 10.

(第2実施形態)
第1実施形態では、作業遅れ時間が基準時間以上の工程がある場合のみ、支援が必要な工程と判断している。これに対し、第2実施形態では、作業遅れ時間が基準時間以上の工程がない場合にも、最も作業遅れ時間が大きい工程を支援が必要な工程と判断する。
(Second Embodiment)
In the first embodiment, only when there is a process whose work delay time is equal to or longer than the reference time, it is determined that the process needs assistance. On the other hand, in the second embodiment, even when there is no process whose work delay time is equal to or longer than the reference time, a process having the longest work delay time is determined as a process requiring assistance.

図10は第2実施形態に係るデータ処理装置の動作の流れを示すフローチャートである。以下では、図8に示す第1実施形態のフローチャートと重複する工程については、同じステップ番号を付して、その具体的な説明は省略する。   FIG. 10 is a flowchart showing an operation flow of the data processing apparatus according to the second embodiment. Below, the same step number is attached | subjected about the process which overlaps with the flowchart of 1st Embodiment shown in FIG. 8, and the specific description is abbreviate | omitted.

データ処理装置10の制御部16は、ステップS10〜13を実行する。制御部16は、10台後の累積的な作業遅れ時間が基準時間以上の工程があるかを判断する(ステップS14)。基準時間以上の工程がある場合(ステップS14:YES)は、制御部16は、第1実施形態のステップS15〜19の処理を実行する。   The control part 16 of the data processing apparatus 10 performs step S10-13. The control unit 16 determines whether there is a process in which the cumulative work delay time after 10 units is longer than the reference time (step S14). When there is a process longer than the reference time (step S14: YES), the control unit 16 executes the processes of steps S15 to S19 of the first embodiment.

基準時間以上の工程がない場合(ステップS14:NO)、制御部16は、指導員Xが手すきかどうかを判断する(ステップS30)。指導員Xが手すきかどうかは、指導員Xが持っている携帯端末からの信号を受信することによって判断する。指導員Xの携帯端末には、作業者が支援可能な状態であるかどうかを設定する支援可能設定部が設けられている。指導員Xは、工程を支援しておらず、他に作業がない場合には、自分が手すきであることを知らせるために、携帯端末において、支援可能であることを設定する。たとえば、携帯端末の特定のボタンを押すことによって、支援可能である旨が設定される。   When there is no process longer than the reference time (step S14: NO), the control unit 16 determines whether the instructor X is a hand (step S30). Whether or not the instructor X is a hand is determined by receiving a signal from the mobile terminal held by the instructor X. The portable terminal of the instructor X is provided with a supportable setting unit that sets whether or not the worker is in a supportable state. If the instructor X does not support the process and there is no other work, the instructor X sets that support is possible in the portable terminal in order to notify that he is a handrail. For example, it is set that support is possible by pressing a specific button of the mobile terminal.

指導員Xが手すきでない場合(ステップS30:NO)、制御部16、ステップS10の処理に戻る。指導員Xが手すきである場合(ステップS30:YES)、制御部16は、各工程の平均作業遅れ時間に重み付けする(ステップS31)。重み付けは、ステップS18と同様である。上流の工程ほど大きな係数をかける。   If the instructor X is not a handrail (step S30: NO), the process returns to the control unit 16 and step S10. When the instructor X is a handrail (step S30: YES), the control unit 16 weights the average work delay time of each process (step S31). The weighting is the same as in step S18. A higher factor is applied to the upstream process.

制御部16は、工程ごとに、標準作業時間に対する、重み付けられた累積的な平均作業遅れ時間の割合を算出し、該割合が最大の工程を、支援が必要な工程と判断する(ステップS32)。   For each process, the control unit 16 calculates the weighted cumulative average work delay time ratio with respect to the standard work time, and determines the process having the maximum ratio as a process requiring support (step S32). .

制御部16は、表示部14およびモニター22に、支援が必要と判断した工程を表示する(ステップS20)。   The control unit 16 displays the process determined to require support on the display unit 14 and the monitor 22 (step S20).

以上のように、第2実施形態では、指導員Xの手が空いている場合に、携帯端末によって支援可能であると設定することによって、基準時間以上遅れていない工程でも支援が必要な工程と判断できる。したがって、指導員Xの手が空く時間を短くして、稼働率を向上できる。さらに、基準時間以上遅れていない工程を、指導員Xの空き時間を利用して予備的に支援できるので、ライン停止に至る作業遅れの発生をより確実に防止できる。   As described above, in the second embodiment, when the instructor X is free, by setting that support is possible with the mobile terminal, it is determined that the process requires support even in a process that is not delayed more than the reference time. it can. Therefore, it is possible to shorten the time when the instructor X is free and improve the operating rate. Furthermore, since a process that is not delayed more than the reference time can be preliminarily supported using the free time of the instructor X, it is possible to more reliably prevent an operation delay leading to a line stop.

は支援工程判断システムを示す概略図である。FIG. 1 is a schematic diagram showing a support process determination system. データ処理装置の概略構成を示す図である。It is a figure which shows schematic structure of a data processor. 生産ラインに作業ナビゲーション装置が設置された様子を示す図である。It is a figure which shows a mode that the work navigation apparatus was installed in the production line. モニターに示される作業内容の例を示す図である。It is a figure which shows the example of the work content shown on a monitor. 作業ナビの動作の流れを示すフローチャートである。It is a flowchart which shows the flow of operation | movement of work navigation. 記憶部に記憶される各種設定時間を示す図である。It is a figure which shows the various setting time memorize | stored in a memory | storage part. データ処理装置10に蓄積される作業実績のデータの例を示す図である。3 is a diagram illustrating an example of work performance data stored in the data processing apparatus 10. FIG. データ処理装置の動作の流れを示すフローチャートである。It is a flowchart which shows the flow of operation | movement of a data processor. データ処理装置により予測される作業遅延の具体例を示す図である。It is a figure which shows the specific example of the work delay estimated by a data processor. 第2実施形態に係るデータ処理装置の動作の流れを示すフローチャートである。It is a flowchart which shows the flow of operation | movement of the data processor which concerns on 2nd Embodiment.

符号の説明Explanation of symbols

10 データ処理装置、
12 記憶部、
14 表示部、
16 制御部、
20 各作業ナビ、
22 モニター、
30 紐。
10 data processing device,
12 storage unit,
14 Display section,
16 control unit,
20 Each work navigation,
22 Monitor,
30 strings.

Claims (12)

生産ラインに含まれる工程毎に、各製品の標準作業時間と、該生産ラインの遅れを判断するための基準となる基準時間とを記憶する第1記憶部と、
前記工程毎に、各製品の作業に作業者が実際に要した実作業時間から、各製品の前記標準作業時間を減算して得られた作業遅れ時間を、作業実績として随時記憶する第2記憶部と、
前記生産ラインに流す製品の種類および順番を示す生産計画を記憶する第3記憶部と、
前記作業実績および前記生産計画に基づいて、今後各工程に製品が順に投入されたときの将来の累積的な作業遅れ時間を算出する算出部と、
算出した累積的な作業遅れ時間が前記基準時間以上の工程を特定し、支援が必要な工程と判断する判断部と、
を有する支援工程判断システム。
For each process included in the production line, a first storage unit that stores a standard work time of each product and a reference time serving as a reference for determining the delay of the production line;
Second memory for storing the work delay time obtained by subtracting the standard work time of each product from the actual work time actually required for the work of each product for each process as work results. And
A third storage unit for storing a production plan indicating the type and order of products to be sent to the production line;
Based on the work results and the production plan, a calculation unit for calculating a future cumulative work delay time when products are sequentially introduced into each process in the future;
A determination unit that identifies a process in which the calculated cumulative work delay time is equal to or greater than the reference time, and determines that the process needs support;
A support process determination system.
前記工程に設置される指示装置をさらに有し、
前記指示装置は、
該工程の作業の開始を確認する確認部と、
該工程の作業内容を前記作業者に指示する指示部と、
前記作業を終了した前記作業者が作業終了を入力する入力部と、
作業の開始から、前記入力部への入力までの時間を実作業時間として計測する計測部と、
を有する請求項2に記載の支援工程判断システム。
It further has an indicating device installed in the process,
The pointing device is
A confirmation unit for confirming the start of work in the process;
An instruction unit for instructing the worker about the work content of the process;
An input unit for inputting the end of work by the worker who has finished the work;
A measurement unit that measures the time from the start of work to the input to the input unit as an actual work time;
The support process determination system according to claim 2, comprising:
前記判断部によって支援が必要と判断された工程を通知する通知装置をさらに有する請求項1または請求項2に記載の支援工程判断システム。   The support process determination system according to claim 1, further comprising a notification device that notifies a process determined to require support by the determination unit. 前記通知装置は、携帯端末であり、
前記携帯端末には、各工程の作業を支援する支援者が支援可能か否かを設定する支援可否設定部が設けられ、
前記支援可否設定部において、支援者が支援可能であると設定されている場合、前記判断部は、前記作業遅れ時間が前記基準時間以上の工程が特定されていなくても、前記標準作業時間に対する前記作業遅れ時間の割合が最も大きい工程を、支援が必要な工程と判断する請求項3に記載の支援工程判断システム。
The notification device is a mobile terminal,
The portable terminal is provided with a support availability setting unit that sets whether or not a supporter supporting the work of each process can support,
In the support availability setting unit, when the supporter is set to be able to support, the determination unit is configured for the standard work time even if a process with the work delay time equal to or longer than the reference time is not specified. The support process determination system according to claim 3, wherein the process having the largest work delay time ratio is determined as a process requiring support.
前記判断部は、特定した工程が複数ある場合、該特定された工程のうち、前記標準作業時間に対する前記累積的な作業遅れ時間の割合が最も大きい工程を、支援が必要な工程と判断する請求項1〜4のいずれか一項に記載の支援工程判断システム。   When there are a plurality of specified processes, the determination unit determines that a process having the largest ratio of the cumulative work delay time to the standard work time among the specified processes is a process requiring assistance. Item 5. The support process determination system according to any one of Items 1 to 4. 前記判断部は、特定した工程が複数ある場合、上流にある工程の前記累積的な作業遅れ時間を、下流にある工程よりも重み付けて補正した上で、前記標準作業時間に対する割合が最も大きい工程を、支援が必要な工程と判断する請求項5記載の支援工程判断システム。   When there are a plurality of specified processes, the determination unit corrects the cumulative work delay time of the upstream process by weighting more than the downstream process, and then has the largest ratio to the standard work time. 6. The support process determination system according to claim 5, wherein the process is determined to be a process that requires support. 生産ラインに設けられた支援工程判断システムによって実行される手順であって、
生産ラインに含まれる工程毎に、各製品の作業に作業者が実際に要した実作業時間から、各製品の標準作業時間を減算して得られた作業遅れ時間を、作業実績として随時記憶するステップと、
前記作業実績とこれから前記生産ラインに流す製品の順番を示す生産計画とに基づいて、今後各工程に製品が順に投入されたときの将来の累積的な作業遅れ時間を算出するステップと、
算出した累積的な作業遅れ時間が、生産ラインの遅れを判断するための基準となる基準時間以上の工程を特定し、支援が必要な工程と判断するステップと、
を有する支援工程判断方法。
A procedure executed by a support process determination system provided in the production line,
For each process included in the production line, the work delay time obtained by subtracting the standard work time of each product from the actual work time actually required for the work of each product is stored as work results as needed. Steps,
Based on the work results and a production plan indicating the order of products to be sent to the production line from now on, calculating a future cumulative work delay time when products are sequentially inserted into each process in the future;
A step in which the calculated cumulative work delay time is greater than a reference time that is a reference for determining a delay in the production line, and a step that determines that the process needs support;
A method for determining a support process.
工程毎に、作業の開始を確認するステップと、
該工程の作業者に作業内容を指示するステップと、
前記作業を終了した前記作業者による作業終了の入力を受け付けるステップと、
作業の開始から、前記作業終了の受け付けまでの時間を実作業時間として計測するステップと、
をさらに有する請求項7記載の支援工程判断方法。
For each process, confirming the start of work,
Instructing the operator of the process of the work content;
Receiving an input of work completion by the worker who finished the work;
Measuring the time from the start of the work to the acceptance of the end of the work as the actual work time;
The support process determination method according to claim 7, further comprising:
前記判断部によって支援が必要と判断された工程を通知する通知ステップをさらに有する請求項7または8に記載の支援工程判断方法。   The support process determination method according to claim 7, further comprising a notification step of notifying a process determined to require support by the determination unit. 前記通知ステップでは、各工程の作業を支援する支援者が保持する携帯端末に、支援が必要な工程を通知し、
前記携帯端末において、前記支援者が支援可能か否かの入力を受け付けるステップをさらに有し、
前記支援者が支援可能であると入力されている場合、前記判断ステップでは、前記特定ステップにおいて工程が特定されていなくても、前記標準作業時間に対する前記作業遅れ時間の割合が最も大きい工程を、支援が必要な工程と判断する請求項9に記載の支援工程判断方法。
In the notification step, a portable terminal held by a supporter who supports the work of each process is notified of a process that needs support,
The portable terminal further includes a step of accepting an input as to whether or not the supporter can support,
When it is input that the supporter can support, in the determination step, even if the process is not specified in the specifying step, a process in which the ratio of the work delay time to the standard work time is the largest, The method of determining a support process according to claim 9, wherein the process is determined to require a support.
前記判断ステップにおいて、特定した工程が複数ある場合、該特定された工程のうち、前記標準作業時間に対する前記累積的な作業遅れ時間の割合が最も大きい工程を、支援が必要な工程と判断する請求項7〜10のいずれか一項に記載の支援工程判断方法。   In the determining step, when there are a plurality of specified processes, a process in which a ratio of the cumulative work delay time to the standard work time is the largest among the specified processes is determined as a process requiring assistance. The support process determination method according to any one of Items 7 to 10. 前記判断ステップにおいて、特定した工程が複数ある場合、上流にある工程の前記累積的な作業遅れ時間を、下流にある工程よりも重み付けて補正した上で、前記標準作業時間に対する割合が最も大きい工程を、支援が必要な工程と判断する請求項11記載の支援工程判断方法。   In the determination step, when there are a plurality of specified processes, the cumulative work delay time of the upstream process is corrected by weighting more than the downstream process, and the process having the largest ratio to the standard work time 12. The support process determination method according to claim 11, wherein the process is determined to be a process requiring support.
JP2008303207A 2008-11-27 2008-11-27 Support process determination system and support process determination method Pending JP2010128819A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP2008303207A JP2010128819A (en) 2008-11-27 2008-11-27 Support process determination system and support process determination method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP2008303207A JP2010128819A (en) 2008-11-27 2008-11-27 Support process determination system and support process determination method

Publications (1)

Publication Number Publication Date
JP2010128819A true JP2010128819A (en) 2010-06-10

Family

ID=42329162

Family Applications (1)

Application Number Title Priority Date Filing Date
JP2008303207A Pending JP2010128819A (en) 2008-11-27 2008-11-27 Support process determination system and support process determination method

Country Status (1)

Country Link
JP (1) JP2010128819A (en)

Cited By (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2014081813A (en) * 2012-10-17 2014-05-08 Kobe Steel Ltd Operator support system, operator support method, and computer program
JP2014132393A (en) * 2013-01-04 2014-07-17 Fujitsu Ltd Production management device and production management method
JP2015099429A (en) * 2013-11-18 2015-05-28 富士通株式会社 Production management method and production management device
JP2018036918A (en) * 2016-08-31 2018-03-08 株式会社日立ソリューションズ Data analyzer and data analysis method
JP2020057341A (en) * 2018-09-28 2020-04-09 フジキンソフト株式会社 Production management device and production management method
JP2021174541A (en) * 2020-04-22 2021-11-01 株式会社日立製作所 Production lead time analysis method and production lead time analysis system

Cited By (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2014081813A (en) * 2012-10-17 2014-05-08 Kobe Steel Ltd Operator support system, operator support method, and computer program
JP2014132393A (en) * 2013-01-04 2014-07-17 Fujitsu Ltd Production management device and production management method
JP2015099429A (en) * 2013-11-18 2015-05-28 富士通株式会社 Production management method and production management device
JP2018036918A (en) * 2016-08-31 2018-03-08 株式会社日立ソリューションズ Data analyzer and data analysis method
JP2020057341A (en) * 2018-09-28 2020-04-09 フジキンソフト株式会社 Production management device and production management method
JP2021174541A (en) * 2020-04-22 2021-11-01 株式会社日立製作所 Production lead time analysis method and production lead time analysis system
JP7141487B2 (en) 2020-04-22 2022-09-22 株式会社日立製作所 Production lead time analysis method and production lead time analysis system

Similar Documents

Publication Publication Date Title
JP2010128819A (en) Support process determination system and support process determination method
US8527315B2 (en) Operation support apparatus, operation support method, and computer program
JP5852546B2 (en) Worker support system and worker support method
US20120219140A1 (en) Conference progress supporting apparatus
JP2003015723A (en) Work distribution planning supporting device using visual display screen
JP2019175209A (en) Vehicle remote support system and method
EP3657412A1 (en) System for managing maintenance work
JP6381810B2 (en) Elevator control device and elevator notification timing control method
CN106395515B (en) The group management system of elevator
JP2007163413A (en) Arrival time information notification device, navigation device, and program
JP2004221890A (en) On-vehicle information terminal
JP5470694B2 (en) Facility search system
JP5731999B2 (en) Navigation device, navigation method, and program
AU2019415992B2 (en) Method and apparatus for commissioning a passenger transportation system
JP4747144B2 (en) Program and simulation device
JP7334796B2 (en) Optimization device, optimization method, program
EP3139234A1 (en) Device system, information processing device, and operation proposal method
KR102265559B1 (en) Operator selection system, operator selection method and operator selection computer program
CN113298332A (en) Information processing method and device and electronic equipment
JP2003050630A (en) Plant operation supporting system
JP5474740B2 (en) Blast furnace charge distribution setting support device and blast furnace charge distribution setting support method
JP2018194914A (en) System, method, and program
JP2018194918A (en) System, method, and program
US6782092B2 (en) Reservation system and method
JP2000198050A (en) Buffer control device and processing system