JP2021174541A - Production lead time analysis method and production lead time analysis system - Google Patents

Production lead time analysis method and production lead time analysis system Download PDF

Info

Publication number
JP2021174541A
JP2021174541A JP2021069519A JP2021069519A JP2021174541A JP 2021174541 A JP2021174541 A JP 2021174541A JP 2021069519 A JP2021069519 A JP 2021069519A JP 2021069519 A JP2021069519 A JP 2021069519A JP 2021174541 A JP2021174541 A JP 2021174541A
Authority
JP
Japan
Prior art keywords
time
product
semi
finished product
production lead
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
JP2021069519A
Other languages
Japanese (ja)
Other versions
JP7141487B2 (en
Inventor
左濱
Bin Zuo
誠 米内
Makoto Yoneuchi
晃久 辻部
Akihisa Tsujibe
鉄平 井上
Teppei INOUE
哲朗 足立
Tetsuro Adachi
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Hitachi Ltd
Original Assignee
Hitachi Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Hitachi Ltd filed Critical Hitachi Ltd
Publication of JP2021174541A publication Critical patent/JP2021174541A/en
Application granted granted Critical
Publication of JP7141487B2 publication Critical patent/JP7141487B2/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Classifications

    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06QINFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
    • G06Q10/00Administration; Management
    • G06Q10/06Resources, workflows, human or project management; Enterprise or organisation planning; Enterprise or organisation modelling
    • G06Q10/063Operations research, analysis or management
    • G06Q10/0633Workflow analysis
    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06QINFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
    • G06Q50/00Information and communication technology [ICT] specially adapted for implementation of business processes of specific business sectors, e.g. utilities or tourism
    • G06Q50/04Manufacturing
    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02PCLIMATE CHANGE MITIGATION TECHNOLOGIES IN THE PRODUCTION OR PROCESSING OF GOODS
    • Y02P90/00Enabling technologies with a potential contribution to greenhouse gas [GHG] emissions mitigation
    • Y02P90/30Computing systems specially adapted for manufacturing

Landscapes

  • Business, Economics & Management (AREA)
  • Human Resources & Organizations (AREA)
  • Engineering & Computer Science (AREA)
  • Economics (AREA)
  • Strategic Management (AREA)
  • Tourism & Hospitality (AREA)
  • Theoretical Computer Science (AREA)
  • Entrepreneurship & Innovation (AREA)
  • General Physics & Mathematics (AREA)
  • Marketing (AREA)
  • General Business, Economics & Management (AREA)
  • Physics & Mathematics (AREA)
  • Educational Administration (AREA)
  • Quality & Reliability (AREA)
  • Operations Research (AREA)
  • Game Theory and Decision Science (AREA)
  • Development Economics (AREA)
  • Manufacturing & Machinery (AREA)
  • Health & Medical Sciences (AREA)
  • General Health & Medical Sciences (AREA)
  • Primary Health Care (AREA)
  • Management, Administration, Business Operations System, And Electronic Commerce (AREA)
  • General Factory Administration (AREA)

Abstract

To provide a production lead time analysis method and a production lead time analysis system that can quickly identify a problem which prolongs a production lead time.SOLUTION: A production lead time analysis system in question is comprised of: a work record information collection unit that collects work record information of each related process for each product, the work record information including a work start time and a work end time of the process; a process work time calculation unit that calculates a process work time based on the work record information for each process of each product, the process work time being a time difference between the work start time and the work end time of the process; a process standard work time acquisition unit that acquires a corresponding process standard work time for each process of the product; and a process delay time calculation unit that, for each process of each product, calculates a delay time of the process work time with respect to the corresponding process standard work time in the process and sets the delay time as a process delay time of the process.SELECTED DRAWING: Figure 1

Description

本発明は、製品の生産リードタイムを分析する生産リードタイム分析方法及び生産リードタイム分析システムに関する。 The present invention relates to a production lead time analysis method and a production lead time analysis system for analyzing the production lead time of a product.

商取引において、顧客ニーズが多様化し、企業間競争が熾烈化するなかで、生産企業にとっては、顧客の求める生産リードタイムを満たす必要がある。発注段階で、商品の価格と品質が理想的であっても、納品までに長い時間がかかる場合、注文が競合会社に流れてしまうこともあり得る。企業は生産リードタイムを短縮するために、各種IT技術を用いてその時点の生産リードタイムを収集しているが、データの利用はまだ十分ではなく、問題の分析と現場の改善に対して、主に用いられているのは人の経験や知識であるため、信頼性と汎用性に欠ける。 In commercial transactions, as customer needs diversify and competition between companies intensifies, it is necessary for production companies to meet the production lead times required by customers. Even if the price and quality of the goods are ideal at the ordering stage, if it takes a long time to deliver, the order may flow to the competitors. Companies use various IT technologies to collect production lead times at that time in order to shorten production lead times, but the use of data is not yet sufficient, and for problem analysis and on-site improvement, Since human experience and knowledge are mainly used, it lacks reliability and versatility.

特許文献1には、回路を製造し搭載するために、複数の工程を順次経て、各工程で特定の設備を用いることが記載されている。一般的な設備では、工程の違いや単位時間内に処理される製品の数、処理速度および作業時間によって変化が生じるため、製品の生産リードタイムは、理論上の作業時間を考慮する以外に、工程間の待機時間も考慮に入れる必要がある。生産計画を遵守するためには、生産ラインに投入される一単位である生産ロットの目標リードタイムを正確に測定する必要があるが、現時点では主に人の経験によって対処されており、こうした技術課題に対し、特許文献1では、半導体やICのメーカーを対象に、目標リードタイムの測定方法が記載され、それは、各工程設備の性能データ及び製品の理論作業時間に基づいて、各工程設備の利用率を算出するとともに、各工程設備の利用率を用いて、各工程における待機時間を算出し、最後に、各工程待機時間の合計値と製品の理論作業時間を加算して、目標リードタイムを算出するように構成されている。 Patent Document 1 describes that in order to manufacture and mount a circuit, a plurality of steps are sequentially performed, and a specific facility is used in each step. In general equipment, the production lead time of a product is not limited to considering the theoretical working time, because it changes depending on the process difference, the number of products processed in a unit time, the processing speed and the working time. The waiting time between processes also needs to be taken into account. In order to comply with the production plan, it is necessary to accurately measure the target lead time of the production lot, which is a unit put into the production line, but at present, it is mainly dealt with by human experience, and such technology In response to the problem, Patent Document 1 describes a method for measuring the target lead time for semiconductor and IC manufacturers, which is based on the performance data of each process equipment and the theoretical working time of the product of each process equipment. In addition to calculating the utilization rate, the waiting time in each process is calculated using the utilization rate of each process equipment, and finally, the total value of the waiting time in each process and the theoretical working time of the product are added to obtain the target lead time. Is configured to calculate.

中国特許出願公開第101727098号明細書Chinese Patent Application Publication No. 101727098

しかしながら、特許文献1に係る半導体やICメーカーのようなロット生産や生産ライン生産方式及び設備は、生産ラインに適用される技術でしかなく、汎用性に欠ける。また特許文献1は、目標リードタイムを正確に測定することで生産計画の最適化を行って、生産リードタイムの短縮を図っているが、生産リードタイム自体に対する分析は行われていないため、生産リードタイムの内部のどの段階で待機が発生したかを知ることはできず、そのため生産現場をピンポイントで改善して生産リードタイムを短縮させるということはできない。 However, lot production and production line production methods and equipment such as semiconductor and IC manufacturers according to Patent Document 1 are only technologies applied to production lines and lack versatility. Further, Patent Document 1 optimizes the production plan by accurately measuring the target lead time to shorten the production lead time, but the production lead time itself is not analyzed, so that the production is produced. It is not possible to know at what stage inside the lead time the standby occurred, so it is not possible to pinpoint the production site and shorten the production lead time.

本発明は、上記技術課題を解決するためになされたもので、1又は複数の製品の生産リードタイムを分析する生産リードタイム分析方法を提供しており、前記製品は、1又は複数の半製品により1又は複数の工程を経て加工されてなり、前記半製品は、1又は複数の工程を経て加工形成され、前記生産リードタイム分析方法は、下記ステップを含むことを特徴とする。即ち、前記各製品に対し、関係する各工程の作業実績情報を収集する作業実績情報収集ステップであって、前記作業実績情報は工程の作業開始時刻及び作業終了時刻を含むステップと、前記各製品の各工程に対し、前記作業実績情報に基づいて工程作業時間を算出する工程作業時間算出ステップであって、前記工程作業時間は該工程の作業開始時刻と作業終了時刻との時間差であるステップと、前記製品の各種工程に対し、対応する工程標準作業時間を取得する工程標準作業時間取得ステップと、前記各製品の各工程に対し、当該工程における対応する工程標準作業時間に対する前記工程作業時間の遅延時間を算出し、当該工程の工程遅延時間とする工程遅延時間算出ステップ。 The present invention has been made to solve the above technical problems, and provides a production lead time analysis method for analyzing the production lead time of one or more products, and the product is one or more semi-finished products. The semi-finished product is processed and formed through one or a plurality of steps, and the production lead time analysis method includes the following steps. That is, it is a work record information collection step for collecting work record information of each related process for each product, and the work record information includes a step including a work start time and a work end time of the process, and each product. For each process, the process work time calculation step of calculating the process work time based on the work record information, and the process work time is the time difference between the work start time and the work end time of the process. , The process standard work time acquisition step for acquiring the corresponding process standard work time for various processes of the product, and the process work time for each process of the product with respect to the corresponding process standard work time in the process. A process delay time calculation step that calculates the delay time and uses it as the process delay time of the process.

上記生産リードタイム分析方法はまた、次のように構成されてもよい。即ち、前記各製品における、各半製品の前記加工形成に用いる工程のうち最遅の工程及び当該製品における最遅の工程を除く各工程に対し、当該工程の工程停滞時間を算出する工程停滞時間算出ステップをさらに含み、前記工程停滞時間は、当該工程の作業終了時刻と、当該工程の次の工程の作業開始時刻との時間差である。 The production lead time analysis method may also be configured as follows. That is, the process stagnation time for calculating the process stagnation time of the process for each process excluding the slowest process and the slowest process in the product among the processes used for the processing formation of each semi-finished product in each product. Further including a calculation step, the process stagnation time is a time difference between the work end time of the process and the work start time of the next process of the process.

上記生産リードタイム分析方法はまた、以下のように構成されてもよい。即ち、前記工程遅延時間が予め設定した工程遅延閾値を超えた工程を異常遅延工程であると判定し、かつ前記工程停滞時間が予め設定した工程停滞閾値を超えた工程を異常停滞工程であると判定する異常判定ステップと、各工程の前記工程作業時間、各種工程の前記工程標準作業時間、及び工程異常情報のうちの少なくとも1つを表示するステップであって、前記工程異常情報は、各工程の前記工程遅延時間、各工程の前記工程停滞時間、工程の異常遅延率、工程の異常停滞率、前記異常遅延工程の識別情報、及び前記異常停滞工程の識別情報のうちの少なくとも1つを含む表示ステップと、をさらに含む。 The production lead time analysis method may also be configured as follows. That is, a process in which the process delay time exceeds the preset process delay threshold is determined to be an abnormal delay process, and a process in which the process stagnation time exceeds the preset process stagnation threshold is regarded as an abnormal stagnation process. An abnormality determination step for determination, a step for displaying at least one of the process work time of each process, the process standard work time of various processes, and process abnormality information, and the process abnormality information is a step of displaying each process. Includes at least one of the process delay time, the process stagnation time of each process, the abnormal delay rate of the process, the abnormal stagnation rate of the process, the identification information of the abnormal delay process, and the identification information of the abnormal stagnation process. Also includes display steps and.

これにより、製品の生産リードタイムを短縮するために、インテリジェント、視覚的かつ迅速に、生産リードタイムを長引かせる問題工程を特定し、ピンポイントに措置を講じて不要な待機時間を回避し、製品の生産リードタイムの短縮を図ることができる。 This allows you to intelligently, visually and quickly identify problem processes that prolong production lead time, take pinpoint measures to avoid unnecessary waiting time, and reduce product production lead time. Production lead time can be shortened.

上記生産リードタイム分析方法はまた、以下のように構成されてもよい。即ち、前記各製品に対し、前記作業実績情報に基づいて製品生産リードタイムを算出する製品生産リードタイム算出ステップであって、前記製品生産リードタイムは、前記作業実績情報収集ステップで収集した各工程のうち最早の工程の作業開始時刻と、最遅の工程の作業終了時刻との時間差であるステップと、前記製品に対応する製品標準生産リードタイムを取得する製品標準生産リードタイム取得ステップと、前記各製品に対し、当該製品における前記製品標準生産リードタイムに対する前記製品生産リードタイムの遅延時間を算出し、当該製品の製品遅延時間とする製品遅延時間算出ステップと、をさらに含み、前記異常判定ステップにおいて、前記製品遅延時間が予め設定した製品遅延閾値を超えた製品を異常遅延製品であるとさらに判定し、前記表示ステップにおいて、各製品の前記製品生産リードタイム、前記製品標準生産リードタイム、及び製品異常情報のうちの少なくとも1つをさらに表示し、前記製品異常情報は、各製品の前記製品遅延時間、製品の異常遅延率、平均遅延時間、及び前記異常遅延製品の識別情報のうちの少なくとも1つを含む。 The production lead time analysis method may also be configured as follows. That is, it is a product production lead time calculation step for calculating the product production lead time based on the work record information for each product, and the product production lead time is each step collected in the work record information collection step. Among the steps, the step that is the time difference between the work start time of the earliest process and the work end time of the latest process, the product standard production lead time acquisition step for acquiring the product standard production lead time corresponding to the product, and the above-mentioned For each product, the abnormality determination step further includes a product delay time calculation step of calculating the delay time of the product production lead time with respect to the product standard production lead time of the product and using it as the product delay time of the product. In the above, a product whose product delay time exceeds a preset product delay threshold is further determined to be an abnormally delayed product, and in the display step, the product production lead time, the product standard production lead time, and the product standard production lead time of each product are determined. At least one of the product abnormality information is further displayed, and the product abnormality information is at least one of the product delay time, the product abnormality delay rate, the average delay time, and the identification information of the abnormality delay product of each product. Including one.

これにより、製品の生産リードタイムを短縮するために、インテリジェント、視覚的かつ迅速に、生産リードタイムを長引かせる問題製品を特定することで、ピンポイントに措置を講じて不要な待機時間を回避し、製品の生産リードタイムの短縮を図ることができる。 This allows you to pinpoint and avoid unnecessary wait times by identifying problem products that intelligently, visually and quickly prolong production lead times in order to reduce product production lead times. , The production lead time of the product can be shortened.

上記生産リードタイム分析方法はまた、以下のように構成されてもよい。即ち、前記各製品の各半製品に対し、前記作業実績情報に基づいて半製品生産リードタイムを算出する半製品生産リードタイム算出ステップであって、前記半製品生産リードタイムは、当該半製品の前記加工形成に用いる工程のうち最早の工程の作業開始時刻と、最遅の工程の作業終了時刻との時間差であるステップと、前記製品の各種半製品に対し、対応する半製品標準生産リードタイムを取得する半製品標準生産リードタイム取得ステップと、前記各製品の各半製品に対し、当該半製品における対応する半製品標準生産リードタイムに対する前記半製品生産リードタイムの遅延時間を算出し、当該半製品の半製品遅延時間とする半製品遅延時間算出ステップと、相互組付に用いる複数の半製品の各々に対し、当該半製品の半製品停滞時間を算出する半製品停滞時間算出ステップであって、前記半製品停滞時間は、当該半製品の前記加工形成に用いる工程のうち最遅の工程の作業終了時刻と、前記相互組付に係る工程のうち最早の工程の作業開始時刻との時間差であるステップと、をさらに含み、前記異常判定ステップにおいてさらに、前記半製品遅延時間が予め設定した半製品遅延閾値を超えた半製品を異常遅延半製品であると判定し、かつ前記半製品停滞時間が予め設定した半製品停滞閾値を超えた半製品を異常停滞半製品であると判定し、前記表示ステップにおいて、各半製品の前記半製品生産リードタイム、各半製品の前記半製品標準生産リードタイム、及び半製品異常情報のうちの少なくとも1つをさらに表示し、前記半製品異常情報は、各半製品の前記半製品遅延時間、各半製品の前記半製品停滞時間、半製品の異常遅延率、半製品の異常停滞率、前記異常遅延半製品の識別情報、及び前記異常停滞半製品の識別情報のうちの少なくとも1つを含む。 The production lead time analysis method may also be configured as follows. That is, it is a semi-finished product production lead time calculation step for calculating the semi-finished product production lead time based on the work record information for each semi-finished product of the said semi-finished product, and the semi-finished product production lead time is the semi-finished product. A step that is the time difference between the work start time of the earliest process and the work end time of the latest process among the processes used for the processing formation, and the corresponding semi-finished product standard production lead time for various semi-finished products of the product. For each semi-finished product of the semi-finished product, the delay time of the semi-finished product production lead time with respect to the corresponding semi-finished product standard production lead time of the semi-finished product is calculated. The semi-product delay time calculation step is the semi-product delay time of the semi-finished product, and the semi-product stagnation time calculation step is to calculate the semi-product stagnation time of the semi-finished product for each of the plurality of semi-products used for mutual assembly. The semi-finished product stagnation time is the time difference between the work end time of the latest step of the process used for the processing formation of the semi-finished product and the work start time of the earliest step of the step related to mutual assembly. In the abnormality determination step, a semi-product whose semi-product delay time exceeds a preset semi-product delay threshold is determined to be an abnormal delay semi-product, and the semi-product stagnation A semi-finished product whose time exceeds a preset semi-finished product stagnation threshold is determined to be an abnormally stagnant semi-finished product, and in the display step, the semi-finished product production lead time of each semi-finished product and the semi-finished product standard production of each semi-finished product The lead time and at least one of the semi-product abnormality information are further displayed, and the semi-product abnormality information includes the semi-product delay time of each semi-product, the semi-product stagnation time of each semi-product, and the semi-product abnormality. It includes at least one of a delay rate, an abnormal stagnation rate of a semi-finished product, an identification information of the abnormally delayed semi-product, and an identification information of the abnormally stagnant semi-product.

これにより、製品の生産リードタイムを短縮するために、インテリジェント、視覚的かつ迅速に、生産リードタイムを長引かせる問題半製品を特定することで、ピンポイントに措置を講じて不要な待機時間を回避し、製品の生産リードタイムの短縮を図ることができる。 This allows you to pinpoint and avoid unnecessary wait times by identifying problematic semi-finished products that intelligently, visually and quickly prolong production lead times in order to reduce product lead times. However, the production lead time of the product can be shortened.

上記生産リードタイム分析方法はまた、以下のように構成されてもよい。即ち、前記工程標準作業時間取得ステップにおいて、前記製品の各種工程に対し、前記各製品の当該工程の前記工程作業時間から異常値を除去して、前記工程標準作業時間を算出する。 The production lead time analysis method may also be configured as follows. That is, in the process standard work time acquisition step, for various processes of the product, the process standard work time is calculated by removing an abnormal value from the process work time of the process of each product.

これにより、工程標準作業時間をより正確に取得することができる。 As a result, the process standard working time can be obtained more accurately.

本発明はさらに、1又は複数の製品の生産リードタイムを分析する生産リードタイム分析システムを提供しており、前記製品は、1又は複数の半製品により1又は複数の工程を経て加工されてなり、前記半製品は、1又は複数の工程を経て加工形成され、前記生産リードタイム分析システムは下記を含むことを特徴とする。即ち、前記各製品に対し、関係する各工程の作業実績情報を収集する作業実績情報収集部であって、前記作業実績情報は工程の作業開始時刻及び作業終了時刻を含むものと、前記各製品の各工程に対し、前記作業実績情報に基づいて工程作業時間を算出する工程作業時間算出部であって、前記工程作業時間は該工程の作業開始時刻と作業終了時刻との時間差であるものと、前記製品の各種工程に対し、対応する工程標準作業時間を取得する工程標準作業時間取得部と、前記各製品の各工程に対し、当該工程における対応する工程標準作業時間に対する前記工程作業時間の遅延時間を算出し、当該工程の工程遅延時間とする工程遅延時間算出部。 The present invention further provides a production lead time analysis system that analyzes the production lead time of one or more products, wherein the product is processed by one or more semi-finished products through one or more steps. The semi-finished product is processed and formed through one or a plurality of steps, and the production lead time analysis system includes the following. That is, it is a work record information collecting unit that collects work record information of each related process for each product, and the work record information includes a work start time and a work end time of the process, and each product. The process work time calculation unit calculates the process work time based on the work record information for each process, and the process work time is the time difference between the work start time and the work end time of the process. , The process standard work time acquisition unit that acquires the corresponding process standard work time for various processes of the product, and the process work time for each process of the product with respect to the corresponding process standard work time in the process. A process delay time calculation unit that calculates the delay time and uses it as the process delay time of the process.

上記生産リードタイム分析システムはまた、以下のように構成されてもよい。即ち、前記各製品における、各半製品の前記加工形成に用いる工程のうち最遅の工程及び当該製品における最遅の工程を除く各工程に対し、当該工程の工程停滞時間を算出する工程停滞時間算出部であって、前記工程停滞時間は、当該工程の作業終了時刻と当該工程の次の工程の作業開始時刻との時間差であるものをさらに含む。 The production lead time analysis system may also be configured as follows. That is, the process stagnation time for calculating the process stagnation time of the process for each process excluding the slowest process and the slowest process in the product among the processes used for the processing formation of each semi-finished product in each product. In the calculation unit, the process stagnation time further includes a time difference between the work end time of the process and the work start time of the next process of the process.

上記生産リードタイム分析システムはまた、以下のように構成されてもよい。即ち、前記工程遅延時間が予め設定した工程遅延閾値を超えた工程を異常遅延工程であると判定し、かつ前記工程停滞時間が予め設定した工程停滞閾値を超えた工程を異常停滞工程であると判定する異常判定部と、各工程の前記工程作業時間、各種工程の前記工程標準作業時間、及び工程異常情報のうちの少なくとも1つを表示する表示部であって、前記工程異常情報は、各工程の前記工程遅延時間、各工程の前記工程停滞時間、工程の異常遅延率、工程の異常停滞率、前記異常遅延工程の識別情報、及び前記異常停滞工程の識別情報のうちの少なくとも1つを含むものと、をさらに含む。 The production lead time analysis system may also be configured as follows. That is, a process in which the process delay time exceeds the preset process delay threshold is determined to be an abnormal delay process, and a process in which the process stagnation time exceeds the preset process stagnation threshold is regarded as an abnormal stagnation process. An abnormality determination unit for determining, a display unit for displaying at least one of the process work time of each process, the process standard work time of various processes, and process abnormality information, and the process abnormality information is each. At least one of the process delay time of the process, the process stagnation time of each process, the abnormal delay rate of the process, the abnormal stagnation rate of the process, the identification information of the abnormal delay process, and the identification information of the abnormal stagnation process. Including and further including.

これにより、製品の生産リードタイムを短縮するために、インテリジェント、視覚的かつ迅速に、生産リードタイムを長引かせる問題工程を特定することで、ピンポイントに措置を講じて不要な待機時間を回避し、製品の生産リードタイムの短縮を図ることができる。 This allows you to pinpoint and avoid unnecessary wait times by identifying problem processes that intelligently, visually and quickly prolong production lead times in order to reduce product production lead times. , The production lead time of the product can be shortened.

上記生産リードタイム分析システムはまた、以下のように構成されてもよい。即ち、前記各製品に対し、前記作業実績情報に基づいて製品生産リードタイムを算出する製品生産リードタイム算出部であって、前記製品生産リードタイムは、前記作業実績情報収集部で収集された各工程のうち最早の工程の作業開始時刻と、最遅の工程の作業終了時刻との時間差であるものと、前記製品に対応する製品標準生産リードタイムを取得する製品標準生産リードタイム取得部と、前記各製品に対し、当該製品における前記製品標準生産リードタイムに対する前記製品生産リードタイムの遅延時間を算出し、当該製品の製品遅延時間とする製品遅延時間算出部と、をさらに含み、前記異常判定部は、前記製品遅延時間が予め設定した製品遅延閾値を超えた製品を異常遅延製品であるとさらに判定し、前記表示部は、各製品の前記製品生産リードタイム、前記製品標準生産リードタイム、及び製品異常情報のうちの少なくとも1つをさらに表示し、前記製品異常情報は、各製品の前記製品遅延時間、製品の異常遅延率、平均遅延時間、及び前記異常遅延製品の識別情報のうちの少なくとも1つを含む。 The production lead time analysis system may also be configured as follows. That is, it is a product production lead time calculation unit that calculates a product production lead time based on the work record information for each of the products, and the product production lead time is each collected by the work record information collection unit. The time difference between the work start time of the earliest process and the work end time of the latest process, the product standard production lead time acquisition unit that acquires the product standard production lead time corresponding to the product, and the product standard production lead time acquisition unit. For each of the products, the abnormality determination includes a product delay time calculation unit that calculates the delay time of the product production lead time with respect to the product standard production lead time of the product and sets it as the product delay time of the product. The unit further determines that the product whose product delay time exceeds the preset product delay threshold is an abnormally delayed product, and the display unit indicates the product production lead time, the product standard production lead time, and the product standard production lead time of each product. And at least one of the product abnormality information is further displayed, and the product abnormality information includes the product delay time of each product, the product abnormality delay rate, the average delay time, and the identification information of the abnormality delay product. Includes at least one.

これにより、製品の生産リードタイムを短縮するために、インテリジェント、視覚的かつ迅速に、生産リードタイムを長引かせる問題製品を特定することで、ピンポイントに措置を講じて不要な待機時間を回避し、製品の生産リードタイムの短縮を図ることができる。 This allows you to pinpoint and avoid unnecessary wait times by identifying problem products that intelligently, visually and quickly prolong production lead times in order to reduce product production lead times. , The production lead time of the product can be shortened.

上記生産リードタイム分析システムはまた、以下のように構成されてもよい。即ち、前記各製品の各半製品に対し、前記作業実績情報に基づいて半製品生産リードタイムを算出する半製品生産リードタイム算出部であって、前記半製品生産リードタイムは、当該半製品の前記加工形成に用いる工程のうち最早の工程の作業開始時刻と、最遅の工程の作業終了時刻との時間差であるものと、前記製品の各種半製品に対し、対応する半製品標準生産リードタイムを取得する半製品標準生産リードタイム取得部と、前記各製品の各半製品に対し、当該半製品における対応する半製品標準生産リードタイムに対する前記半製品生産リードタイムの遅延時間を算出し、当該半製品の半製品遅延時間とする半製品遅延時間算出部と、相互組付に用いる複数の半製品の各々に対し、当該半製品の半製品停滞時間を算出する半製品停滞時間算出部であって、前記半製品停滞時間は、当該半製品の前記加工形成に用いる工程のうち最遅の工程の作業終了時刻と、前記相互組付に係る工程のうち最早の工程の作業開始時刻との時間差であるものと、をさらに含み、前記異常判定部はさらに、前記半製品遅延時間が予め設定した半製品遅延閾値を超えた半製品を異常遅延半製品であると判定し、かつ前記半製品停滞時間が予め設定した半製品停滞閾値を超えた半製品を異常停滞半製品であると判定し、前記表示部はさらに、各半製品の前記半製品生産リードタイム、各半製品の前記半製品標準生産リードタイム、及び半製品異常情報のうちの少なくとも1つを表示し、前記半製品異常情報は、各半製品の前記半製品遅延時間、各半製品の前記半製品停滞時間、半製品の異常遅延率、半製品の異常停滞率、前記異常遅延半製品の識別情報、及び前記異常停滞半製品の識別情報のうちの少なくとも1つを含む。 The production lead time analysis system may also be configured as follows. That is, it is a semi-finished product production lead time calculation unit that calculates a semi-finished product production lead time based on the work record information for each semi-finished product of the said semi-finished product, and the semi-finished product production lead time is the semi-finished product. The time difference between the work start time of the earliest process and the work end time of the latest process among the processes used for the processing formation, and the corresponding semi-finished product standard production lead time for various semi-finished products of the product. For each semi-finished product of the semi-finished product and the semi-finished product, the delay time of the semi-finished product production lead time with respect to the corresponding semi-finished product standard production lead time of the semi-finished product is calculated. A semi-product delay time calculation unit that calculates the semi-product delay time of a semi-product, and a semi-product stagnation time calculation unit that calculates the semi-product stagnation time of the semi-product for each of a plurality of semi-products used for mutual assembly. The semi-finished product stagnation time is the time difference between the work end time of the latest step of the process used for the processing formation of the semi-finished product and the work start time of the earliest step of the step related to mutual assembly. Further, the abnormality determination unit further determines that the semi-product whose semi-product delay time exceeds the preset semi-product delay threshold is an abnormal delay semi-product, and the semi-product stagnation. A semi-finished product whose time exceeds a preset semi-finished product stagnation threshold is determined to be an abnormally stagnant semi-finished product. At least one of the production lead time and the semi-finished product abnormality information is displayed, and the semi-finished product abnormality information includes the semi-finished product delay time of each semi-finished product, the semi-finished product stagnation time of each semi-finished product, and the semi-finished product abnormality. It includes at least one of a delay rate, an abnormal stagnation rate of a semi-finished product, identification information of the abnormally delayed semi-product, and identification information of the abnormally stagnant semi-product.

これにより、製品の生産リードタイムを短縮するために、インテリジェント、視覚的かつ迅速に、生産リードタイムを長引かせる問題半製品を特定することで、ピンポイントに措置を講じて不要な待機時間を回避し、製品の生産リードタイムの短縮を図ることができる。 This allows you to pinpoint and avoid unnecessary wait times by identifying problematic semi-finished products that intelligently, visually and quickly prolong production lead times in order to reduce product lead times. However, the production lead time of the product can be shortened.

上記生産リードタイム分析システムはまた、以下のように構成されてもよい。即ち、前記工程標準作業時間取得部は、前記製品の各種工程に対し、前記各製品の当該工程の前記工程作業時間から異常値を除去して、前記工程標準作業時間を算出する。 The production lead time analysis system may also be configured as follows. That is, the process standard work time acquisition unit calculates the process standard work time by removing an abnormal value from the process work time of the process of each product for various processes of the product.

これにより、工程標準作業時間をより正確に取得することができる。 As a result, the process standard working time can be obtained more accurately.

本発明によれば、製品の生産リードタイムを短縮するために、インテリジェント、視覚的かつ迅速に、生産リードタイムを長引かせる問題点を特定することで、ピンポイントに措置を講じて不要な待機時間を回避し、製品の生産リードタイムの短縮を図ることができる。 According to the present invention, in order to shorten the production lead time of a product, by identifying the problem of prolonging the production lead time intelligently, visually and quickly, pinpoint measures are taken to eliminate unnecessary waiting time. This can be avoided and the production lead time of the product can be shortened.

実施例1の生産リードタイム分析システム100の構成を示したブロック図である。It is a block diagram which showed the structure of the production lead time analysis system 100 of Example 1. FIG. (a)は、作業実績情報収集部101で収集された作業実績情報の例を示しており、(b)は、製品PRD01における製品シリアル番号P0000001の製品に組付けられる半製品SM00001〜SM00004の、横軸の時間に対するガントチャートを示しており、(c)は、半製品SM00002における半製品シリアル番号BD9AD01の半製品の加工形成のための4工程の、時間に対するガントチャートを示している。(A) shows an example of the work record information collected by the work record information collecting unit 101, and (b) shows the semi-finished products SM00001 to SM00004 to be assembled to the product of the product serial number P0000001 in the product PRD01. The Gantt chart for time on the horizontal axis is shown, and (c) shows the Gantt chart for time of four steps for processing and forming the semi-finished product of the semi-finished product serial number BD9AD01 in the semi-finished product SM00002. 実施例1における表示部105に表示された工程分析部103の分析結果を示すグラフである。It is a graph which shows the analysis result of the process analysis unit 103 displayed on the display unit 105 in Example 1. FIG. 実施例2の生産リードタイム分析システム200の構成を示すブロック図である。It is a block diagram which shows the structure of the production lead time analysis system 200 of Example 2. 実施例2における表示部105に表示された製品分析部201の分析結果を示すグラフである。It is a graph which shows the analysis result of the product analysis unit 201 displayed on the display unit 105 in Example 2. FIG. 実施例3の生産リードタイム分析システム300の構成を示すブロック図である。It is a block diagram which shows the structure of the production lead time analysis system 300 of Example 3. FIG. 実施例3の4つの半製品の生産リードタイムの状況を例示したグラフである。It is a graph which illustrated the situation of the production lead time of four semi-finished products of Example 3. 実施例3における表示部105に表示された半製品分析部301の分析結果を示すグラフである。It is a graph which shows the analysis result of the semi-finished product analysis unit 301 displayed on the display unit 105 in Example 3. FIG. 実施例4の生産リードタイム分析方法を示すフロー図である。It is a flow chart which shows the production lead time analysis method of Example 4. 処理工程が前後する2工程間に停滞時間が発生する原理を説明するためのグラフである。It is a graph for demonstrating the principle that the stagnation time occurs between two processes before and after a processing process. 同じ製品に組付けられる各半製品間に停滞時間が発生する原理を説明するためのグラフである。It is a graph for demonstrating the principle that the stagnation time occurs between each semi-finished product assembled in the same product. 工程の実際の作業時間と工程標準作業時間との比較を説明するためのグラフである。It is a graph for demonstrating the comparison between the actual working time of a process, and the standard working time of a process.

以下、本発明を実施するための形態について説明する。人手による製造及び機械製造を含む製造業の分野において、製品の注文から納入までに要する時間には通常、加工作業時間、運搬時間及び停滞時間が含まれる。このうち、比率が最も高くかつ削減が最も実現可能である時間は停滞時間である。停滞が発生する原因は主に2つあり、第一には、順次実行される工程間のシームレスな繋がりがないということである。例えば図10に示すように、用紙の水平方向を時間軸とするとき、2つの順次実行される工程において前の工程の作業終了時刻と後の工程の作業開始時刻との間に時間差が存在する場合、不要な停滞時間が発生する。 Hereinafter, modes for carrying out the present invention will be described. In the field of manufacturing, including manual manufacturing and machine manufacturing, the time required from ordering to delivery of a product usually includes processing work time, transportation time and stagnation time. Of these, the time when the ratio is the highest and the reduction is most feasible is the stagnation time. There are two main causes of stagnation, the first is that there is no seamless connection between the processes that are executed sequentially. For example, as shown in FIG. 10, when the horizontal direction of the paper is set as the time axis, there is a time difference between the work end time of the previous process and the work start time of the subsequent process in the two sequentially executed processes. In that case, unnecessary stagnation time occurs.

第二には、同じ製品に組付けられる各半製品が同時生産されていないことである。例えば図11に示すように、用紙の水平方向を時間軸とするとき、ある製品は3つの半製品を組付けて形成され、また3つの半製品は製作完了後に組付工程が行われると仮定した場合、図示された3つの半製品の製作完了時刻は同時ではないため、半製品1及び半製品2には、不要な停滞時間が発生する。 Second, each semi-finished product that can be assembled into the same product is not produced at the same time. For example, as shown in FIG. 11, when the horizontal direction of the paper is the time axis, it is assumed that a certain product is formed by assembling three semi-finished products, and that the three semi-finished products are assembled after the production is completed. In this case, since the production completion times of the three semi-finished products shown in the figure are not the same, unnecessary stagnation time occurs in the semi-finished products 1 and the semi-finished products 2.

上記停滞時間を可能な限り取り除くためには、停滞が発生する部位が、どの工程又はどの半製品であるのかを明確にしなければ、製作フローをピンポイントに改善して、全製品の生産リードタイムの短縮効果を実現することはできない。 In order to eliminate the above stagnation time as much as possible, unless it is clarified which process or which semi-finished product the stagnation occurs, the production flow can be improved pinpointly and the production lead time of all products. It is not possible to realize the shortening effect of.

さらに、加工作業時間及び運搬時間の短縮が検討される。手作業を中心とする工程では、作業の標準化が十分でないことが多いため、同一工程の実施であっても、或いは同一の製品や半製品の生産であっても、要する時間はまちまちである。これについては、標準作業を確立することで、工程作業、製品の生産、半製品の生産のピンポイントな改善を実現することができる。例えば図12に示すように、ある工程に対し工程標準作業時間を設定し、その工程の実際の作業時間と当該工程標準作業時間とを比較した時間差を工程遅延時間とすることで、工程遅延時間が長い工程を、改善を要する工程として認識する(例えば工程遅延閾値を設定して判定してもよい)。これにより、全製品の生産リードタイムをより確実に短縮することができる。 Further, shortening of processing work time and transportation time is considered. In processes centered on manual work, standardization of work is often insufficient, so the time required varies even if the same process is carried out or the same product or semi-finished product is produced. In this regard, by establishing standard work, it is possible to realize pinpoint improvements in process work, product production, and semi-finished product production. For example, as shown in FIG. 12, a process standard work time is set for a certain process, and the time difference between the actual work time of the process and the process standard work time is set as the process delay time. A process with a long time is recognized as a process requiring improvement (for example, a process delay threshold may be set for determination). As a result, the production lead time of all products can be shortened more reliably.

上記技術的思想に基づき、本発明は、製造業における製品の生産リードタイムの短縮を図るため、現場で収集した工程作業実績情報を用いて、1又は複数の製品の生産リードタイムを分析する生産リードタイム分析方法及びシステムを提供する。 Based on the above technical idea, the present invention analyzes the production lead time of one or more products by using the process work record information collected at the site in order to shorten the production lead time of the product in the manufacturing industry. A lead time analysis method and system are provided.

次に具体的な実施例を例に挙げて、本発明の生産リードタイム分析方法及びシステムを説明する。 Next, the production lead time analysis method and system of the present invention will be described with reference to specific examples.

本実施例の生産リードタイム分析システムでは、ある製品PRD01の生産リードタイムに対する分析を行い、当該製品PRD01の各々は、複数の半製品により複数の工程を経て加工されてなり、各半製品はそれぞれ複数の工程を経て加工形成されている。 In the production lead time analysis system of this embodiment, the production lead time of a certain product PRD01 is analyzed, and each of the product PRD01 is processed by a plurality of semi-finished products through a plurality of steps, and each semi-finished product is processed. It is processed and formed through a plurality of steps.

当該生産リードタイム分析システム100の構成は図1に示すように、作業実績情報収集部101、記憶部102、工程分析部103、異常判定部104、及び表示部105を含む。 As shown in FIG. 1, the configuration of the production lead time analysis system 100 includes a work record information collecting unit 101, a storage unit 102, a process analysis unit 103, an abnormality determination unit 104, and a display unit 105.

ここで、作業実績情報収集部101は製品PRD01の各々に対し、関係する各工程の作業実績情報を収集する。当該作業実績情報は、例えば図2(a)に示すように、各工程の作業開始時刻及び作業終了時刻を含み、データ源は製造現場でリアルタイムに収集されてもよいし、他のデータベースから導入されてもよい。製品PRD01の各々は、半製品SM00001〜SM00010を組付けて加工されてなり、各半製品はそれぞれ複数の工程を経て加工形成され、例えば半製品SM00002は、工程コードL3−DDL−01〜L3−DDL−04の4つの工程により加工形成される。一例であるが、図2(b)は、製品PRD01における製品シリアル番号P0000001の製品に組付けられる半製品SM00001〜SM00004の、時間に対する説明図を示しており、図2(c)は、半製品SM00002におけるシリアル番号BD9AD01の半製品の加工形成のための4工程の、時間に対するガントチャートを示している。 Here, the work record information collecting unit 101 collects the work record information of each related process for each of the product PRD01. As shown in FIG. 2A, for example, the work record information includes the work start time and work end time of each process, and the data source may be collected in real time at the manufacturing site or introduced from another database. May be done. Each of the product PRD01 is processed by assembling the semi-finished products SM00001 to SM000010, and each semi-finished product is processed and formed through a plurality of steps. It is processed and formed by the four steps of DDL-04. As an example, FIG. 2 (b) shows explanatory views for time of the semi-finished products SM00001 to SM00004 attached to the product with the product serial number P0000001 in the product PRD01, and FIG. 2 (c) shows the semi-finished product. Shown is a Gantt chart for time of four steps for processing and forming a semi-finished product of serial number BD9AD01 in SM00002.

記憶部102は、作業実績情報収集部101で収集された作業実績情報を記憶し、作業実績情報の記憶部102内での記憶形式は図2(a)に限定されることはなく、他の形式であってもよい。 The storage unit 102 stores the work record information collected by the work record information collection unit 101, and the storage format of the work record information in the storage unit 102 is not limited to FIG. 2A, and other It may be in the form.

工程分析部103は、各工程の作業時間の分析に用いられ、工程作業時間算出部106、工程標準作業時間取得部107、工程遅延時間算出部108、及び工程停滞時間算出部109を含む。 The process analysis unit 103 is used for analyzing the work time of each process, and includes a process work time calculation unit 106, a process standard work time acquisition unit 107, a process delay time calculation unit 108, and a process stagnation time calculation unit 109.

ここで、工程作業時間算出部106は、製品PRD01の各々の各工程に対し、図2(a)に示す作業実績情報に基づいて工程作業時間を算出して記憶部102に記憶し、当該工程作業時間とは、当該工程の作業開始時刻と作業終了時刻との時間差、即ち当該工程を完成するための処理時間を意味する。これにより、製品PRD01の各工程はいずれも、対応する工程作業時間が記憶される。 Here, the process work time calculation unit 106 calculates the process work time for each process of the product PRD01 based on the work record information shown in FIG. 2A and stores it in the storage unit 102, and stores the process in the storage unit 102. The work time means the time difference between the work start time and the work end time of the process, that is, the processing time for completing the process. As a result, the corresponding process working time is stored in each process of the product PRD01.

工程標準作業時間取得部107は、製品PRD01の各工程に対し、対応する工程標準作業時間を取得して記憶部102に記憶する。ここでの工程標準作業時間の概念は上述の図12に示したように、製品PRD01の各々の当該工程の工程作業時間と比較して、対応する工程遅延時間を決定するためのものである。工程標準作業時間の取得方法の検討では、例えば工程コードL1−ASM−01の工程の工程標準作業時間について、記憶部102に記憶された作業実績情報のうち、製品PRD01の各々の工程L1−ASM−01の工程作業時間に対し、スミルノフ=グラブス検定を用いてその中から異常値を除去するとともに残りのデータの平均をとり、当該平均値を工程L1−ASM−01の工程標準作業時間としてもよい。これにより、製品PRD01の各工程はいずれも工程標準作業時間が対応的に記憶される。 The process standard work time acquisition unit 107 acquires the corresponding process standard work time for each process of the product PRD01 and stores it in the storage unit 102. As shown in FIG. 12 above, the concept of the process standard working time here is for determining the corresponding process delay time in comparison with the process working time of each relevant process of the product PRD01. In the examination of the process standard work time acquisition method, for example, regarding the process standard work time of the process of the process code L1-ASM-01, among the work record information stored in the storage unit 102, each process L1-ASM of the product PRD01 For the process work time of -01, the Smirnov-Grabs test is used to remove abnormal values from it and the remaining data are averaged, and the average value is also used as the process standard work time of process L1-ASM-01. good. As a result, the process standard working time is correspondingly stored in each process of the product PRD01.

工程遅延時間算出部108は、製品PRD01の各々の各工程に対し、当該工程における対応する工程標準作業時間に対する工程作業時間の遅延時間を算出し、当該工程の工程遅延時間として記憶部102に記憶する。これにより、製品PRD01の各々の各工程はいずれも、工程遅延時間が対応的に記憶される。 The process delay time calculation unit 108 calculates the delay time of the process work time with respect to the corresponding process standard work time in the process for each process of the product PRD01, and stores it in the storage unit 102 as the process delay time of the process. do. As a result, the process delay time is correspondingly stored in each process of the product PRD01.

工程停滞時間算出部109は、製品PRD01の各々及び各半製品SM00001〜SM00010の加工形成に用いる工程のうち、最遅の工程を除く各工程に対し、当該工程の工程停滞時間を算出して記憶部102に記憶する。即ち、工程停滞時間算出部109は、製品PRD01の各々における、各半製品の加工形成に用いる工程のうち最遅の工程及び全製品における最遅の工程を除く各工程に対し、当該工程の工程停滞時間を算出して記憶部102に記憶し、ここでの工程停滞時間は、当該工程の作業終了時刻と当該工程の次の工程の作業開始時刻との時間差である。 The process stagnation time calculation unit 109 calculates and stores the process stagnation time of each process other than the latest process among the processes used for processing and forming each of the product PRD01 and each of the semi-finished products SM00001 to SM000010. Store in unit 102. That is, the process stagnation time calculation unit 109 refers to each process of the product PRD01 except for the latest process of the processes used for processing and forming each semi-finished product and the latest process of all products. The stagnation time is calculated and stored in the storage unit 102, and the process stagnation time here is the time difference between the work end time of the process and the work start time of the next process of the process.

ここで、まず、製品における最遅の工程はそもそも最後の一工程であるため、その工程停滞時間は算出されない。さらに「半製品の加工形成に用いる工程」とは、当該半製品を形成するための各工程を意味し、例えば当該半製品が、複数の別の半製品を組付ければ完成するのであれば、当該半製品の「加工形成に用いる工程のうち最遅の工程」とは即ち、これら別の半製品を相互組付するその組付工程(組付工程が複数であるときは、最遅の一組付工程)を意味する。当該半製品が複数の別の半製品の組付後、さらに若干の工程を経て加工されて完成する場合、或いは複数の別の半製品の組付によって完成されるものではない場合は、当該半製品の「加工形成に用いる工程のうち最遅の工程」とは即ち、当該半製品を生産する複数の工程のうちの最後の一工程を意味する。これにより、製品PRD01の各々における、半製品の加工形成用の最遅の工程及び当該製品における最遅の工程を除く各工程はいずれも、対応する工程停滞時間が記憶される。 Here, first, since the slowest process in the product is the last process in the first place, the process stagnation time is not calculated. Further, the "process used for processing and forming a semi-finished product" means each step for forming the semi-finished product, for example, if the semi-finished product is completed by assembling a plurality of other semi-finished products. The "latest process among the processes used for processing and forming" of the semi-finished product is the assembling process of mutually assembling these other semi-finished products (when there are a plurality of assembling steps, the slowest one). Assembling process). If the semi-finished product is completed by assembling a plurality of other semi-finished products and then processed through a few steps, or if it is not completed by assembling a plurality of other semi-finished products, the semi-finished product is said. The "latest step among the steps used for processing and forming" of a product means the last step of a plurality of steps for producing the semi-finished product. As a result, the corresponding process stagnation time is stored in each of the products PRD01 except for the latest process for processing and forming the semi-finished product and the latest process in the product.

各工程の工程遅延時間及び工程停滞時間に対し、異常判定部104は、記憶部102に記憶されている予め設定した閾値を用いて判定する。具体的には、異常判定部104は、製品PRD01の各々の各工程のうち、工程遅延時間が予め設定した工程遅延閾値を超えた工程を異常遅延工程であると判定し、かつ製品PRD01の各々の各工程のうち、工程停滞時間が予め設定した工程停滞閾値を超えた工程を異常停滞工程であると判定する。 The abnormality determination unit 104 determines the process delay time and process stagnation time of each process using a preset threshold value stored in the storage unit 102. Specifically, the abnormality determination unit 104 determines that, among the respective processes of the product PRD01, the process whose process delay time exceeds the preset process delay threshold is the abnormal delay process, and each of the product PRD01. Of the above steps, a step in which the step stagnation time exceeds a preset process stagnation threshold is determined to be an abnormal stagnation step.

表示部105は、本実施例の生産リードタイム分析システム100における工程分析部103の分析結果を外部に向けて表示する。図3に示すように、一定期間に生産された複数の製品PRD01における各工程の異常遅延率及び異常停滞率を、グラフ形式で表示してもよい。工程の異常遅延率及び異常停滞率はそれぞれ工程異常情報として、図示しない演算部により前記各項データに基づいて演算されて記憶部102に記憶され、ユーザはまた、コンピュータ表示インタフェース上で、当該グラフの様々な部位をクリックすることで、各工程の工程標準作業時間や、ある工程の工程作業時間、及びその他の工程異常情報(例えば各工程の工程遅延時間、各工程の工程停滞時間、異常遅延工程であると判定された工程コード及び他の識別情報、異常停滞工程であると判定された工程コード及び他の識別情報等)を、それぞれ取得することもできる。工程分析部103の分析結果は図3で例示的に示されているが、図示の形式はこれに限定されるものではない。 The display unit 105 displays the analysis result of the process analysis unit 103 in the production lead time analysis system 100 of this embodiment to the outside. As shown in FIG. 3, the abnormal delay rate and the abnormal stagnation rate of each process in the plurality of products PRD01 produced in a certain period may be displayed in a graph format. The abnormal delay rate and the abnormal stagnation rate of the process are calculated as process abnormality information by a calculation unit (not shown) based on the data of each item and stored in the storage unit 102, and the user can also use the graph on the computer display interface. By clicking various parts of, the process standard work time of each process, the process work time of a certain process, and other process abnormality information (for example, process delay time of each process, process stagnation time of each process, abnormal delay) It is also possible to acquire the process code and other identification information determined to be a process, the process code determined to be an abnormally stagnant process and other identification information, etc.). The analysis result of the process analysis unit 103 is shown as an example in FIG. 3, but the illustrated format is not limited to this.

このように、本実施例によれば、製品の生産リードタイムを短縮するために、インテリジェント、視覚的かつ迅速に、生産リードタイムを長引かせる問題工程の位置を特定することで、ピンポイントに措置を講じて不要な待機時間を回避し、製品の生産リードタイムの短縮を図ることができる。 Thus, according to this embodiment, in order to shorten the production lead time of the product, pinpoint measures are taken by locating the problematic process that prolongs the production lead time intelligently, visually and quickly. It is possible to avoid unnecessary waiting time and shorten the production lead time of the product.

本実施例の生産リードタイム分析システム200の構成は図4に示すように、実施例1の生産リードタイム分析システム100と同一の構成のほか、さらに製品分析部201を含み、それは各製品の生産リードタイムの分析に用いられ、製品生産リードタイム算出部202、製品標準生産リードタイム取得部203、及び製品遅延時間算出部204を含む。 As shown in FIG. 4, the configuration of the production lead time analysis system 200 of this embodiment has the same configuration as the production lead time analysis system 100 of the first embodiment, and further includes a product analysis unit 201, which is the production of each product. It is used for lead time analysis and includes a product production lead time calculation unit 202, a product standard production lead time acquisition unit 203, and a product delay time calculation unit 204.

ここで、製品生産リードタイム算出部202は、製品PRD01の各々(即ち製品番号が同じで製品シリアル番号が異なる製品)に対し、上述した作業実績情報に基づいて製品生産リードタイムを算出して記憶部102に記憶し、この製品生産リードタイムとは、記憶部102に記憶された、作業実績情報収集部101で収集された各工程のうち最早の工程の作業開始時刻と最遅の工程の作業終了時刻との時間差である、当該製品を生産するための処理時間を意味する。これにより、製品PRD01の各々はいずれも、対応する製品生産リードタイムが記憶される。 Here, the product production lead time calculation unit 202 calculates and stores the product production lead time for each of the product PRD01 (that is, products having the same product number but different product serial numbers) based on the above-mentioned work record information. The product production lead time stored in the unit 102 is the work start time of the earliest process and the work of the latest process among the processes collected by the work record information collecting unit 101 stored in the storage unit 102. It means the processing time for producing the product, which is the time difference from the end time. As a result, each of the product PRD01 stores the corresponding product production lead time.

製品標準生産リードタイム取得部203は、製品PRD01に対応する製品標準生産リードタイムを取得して記憶部102に記憶する。ここでの製品標準生産リードタイムの定義は、上述した工程標準作業時間に類似し、製品PRD01の各々の製品生産リードタイムと比較して、対応する製品遅延時間を決定するために用いられる。当該製品標準生産リードタイムの取得方法も前記工程標準作業時間に類似し、例えば記憶部102に記憶されている各製品生産リードタイムにおいて、スミルノフ=グラブス検定を用いて異常値を除去するとともに残りのデータの平均をとり、当該平均値を製品PRD01の製品標準生産リードタイムとしてもよい。これにより、記憶部102内に製品PRD01に対して製品標準生産リードタイムが記憶される。 The product standard production lead time acquisition unit 203 acquires the product standard production lead time corresponding to the product PRD 01 and stores it in the storage unit 102. The definition of product standard production lead time here is similar to the process standard working time described above and is used to determine the corresponding product delay time as compared to each product production lead time of product PRD01. The method of acquiring the product standard production lead time is also similar to the process standard working time. For example, in each product production lead time stored in the storage unit 102, an abnormal value is removed by using the Smirnov-Grabs test, and the remaining value is removed. The data may be averaged and the average value may be used as the product standard production lead time of the product PRD01. As a result, the product standard production lead time is stored in the storage unit 102 for the product PRD01.

製品遅延時間算出部は、製品PRD01の各々に対し、製品標準生産リードタイムに対する当該製品の製品生産リードタイムの遅延時間を算出し、当該製品の製品遅延時間として記憶部102に記憶する。これにより、製品PRD01の各々はいずれも、製品遅延時間が対応的に記憶される。 The product delay time calculation unit calculates the delay time of the product production lead time of the product with respect to the product standard production lead time for each of the product PRD01, and stores it in the storage unit 102 as the product delay time of the product. As a result, each of the product PRD01 is correspondingly stored in the product delay time.

本実施例において、製品PRD01の各々の製品遅延時間に対し、異常判定部104もまた記憶部102に記憶されている予め設定した閾値を用いて判定する。具体的には、異常判定部104は、製品PRD01の各々のうち製品遅延時間が予め設定した製品遅延閾値を超えた製品を、異常遅延製品であると判定する。 In this embodiment, each product delay time of the product PRD01 is determined by the abnormality determination unit 104 also using a preset threshold value stored in the storage unit 102. Specifically, the abnormality determination unit 104 determines that each of the product PRD01 products whose product delay time exceeds the preset product delay threshold value is an abnormality delay product.

表示部105は、本実施例の生産リードタイム分析システム200における製品分析部201の分析結果を外部に向けて表示する。本実施例の生産リードタイム分析システム200を用いて、一定期間に生産された複数の製品PRD01〜PRD10のそれぞれを分析した場合において、図5に示すように、各製品の異常遅延率及び平均遅延日数をグラフ形式で表示してもよい。製品の異常遅延率及び平均遅延日数はそれぞれ製品異常情報として、図示しない演算部により前記各項データに基づいて演算されて記憶部102に記憶され、ユーザはまた、コンピュータ表示インタフェース上で、当該グラフの様々な部位をクリックすることで、各製品の製品標準生産リードタイムや、ある製品の製品生産リードタイム、及びその他の製品異常情報(例えば各製品の製品遅延時間、異常遅延製品であると判定された製品番号及び序列番号等)をそれぞれ取得することもできる。製品分析部201の分析結果は図5において例示的に示されているが、図示の形式はこれに限定されるものではない。 The display unit 105 displays the analysis result of the product analysis unit 201 in the production lead time analysis system 200 of this embodiment to the outside. When each of the plurality of products PRD01 to PRD10 produced in a certain period of time is analyzed using the production lead time analysis system 200 of this embodiment, as shown in FIG. 5, the abnormal delay rate and the average delay of each product are analyzed. The number of days may be displayed in a graph format. The product abnormality delay rate and the average delay days are calculated as product abnormality information by a calculation unit (not shown) based on the data of each item and stored in the storage unit 102, and the user can also use the graph on the computer display interface. By clicking various parts of, the product standard production lead time of each product, the product production lead time of a certain product, and other product abnormality information (for example, the product delay time of each product, the abnormality delay product is determined). It is also possible to obtain the product number and the order number, etc.). The analysis result of the product analysis unit 201 is shown as an example in FIG. 5, but the illustrated format is not limited to this.

これにより、本実施例によれば、製品の生産リードタイムを短縮するために、インテリジェント、視覚的かつ迅速に、生産リードタイムを長引かせる問題製品を特定することで、ピンポイントに措置を講じて不要な待機時間を回避し、製品の生産リードタイムの短縮を図ることができる。 Thereby, according to this embodiment, in order to shorten the production lead time of the product, pinpoint measures are taken by identifying the problem product that prolongs the production lead time intelligently, visually and quickly. It is possible to avoid unnecessary waiting time and shorten the production lead time of the product.

本実施例の生産リードタイム分析システム300の構成は、図6に示したように、実施例1の生産リードタイム分析システム100と同一の構成のほか、さらに半製品分析部301を含み、それは各半製品の生産リードタイムの分析に用いられ、半製品生産リードタイム算出部302、半製品標準生産リードタイム取得部303、半製品遅延時間算出部304、及び半製品停滞時間算出部305を含む。 As shown in FIG. 6, the configuration of the production lead time analysis system 300 of this embodiment has the same configuration as that of the production lead time analysis system 100 of the first embodiment, and further includes a semi-finished product analysis unit 301. It is used for the analysis of the production lead time of the semi-finished product, and includes the semi-finished product production lead time calculation unit 302, the semi-product standard production lead time acquisition unit 303, the semi-product delay time calculation unit 304, and the semi-product stagnation time calculation unit 305.

ここで、半製品生産リードタイム算出部302は、製品PRD01の各々の各半製品に対し、上述した作業実績情報に基づいて半製品生産リードタイムを算出して記憶部102に記憶し、この半製品生産リードタイムとは、記憶部102に記憶された、当該半製品の加工形成に用いる工程のうち最早の工程の作業開始時刻と最遅の工程の作業終了時刻との時間差である、当該半製品を加工形成するための処理時間を意味する。これにより、各々の半製品はいずれも、半製品生産リードタイムが対応的に記憶される。 Here, the semi-finished product production lead time calculation unit 302 calculates the semi-finished product production lead time for each semi-finished product of the product PRD01 based on the above-mentioned work record information and stores the semi-finished product production lead time in the storage unit 102. The product production lead time is the time difference between the work start time of the earliest process and the work end time of the latest process among the processes used for processing and forming the semi-finished product, which is stored in the storage unit 102. It means the processing time for processing and forming a product. As a result, the semi-finished product production lead time is correspondingly stored in each semi-finished product.

半製品標準生産リードタイム取得部303は、製品PRD01の各半製品に対し、対応する半製品標準生産リードタイムを取得して記憶部102に記憶する。ここでの半製品標準生産リードタイムの定義は、上述した工程標準作業時間に類似し、製品PRD01の各々の該半製品の半製品生産リードタイムと比較して、対応する半製品遅延時間を決定するために用いられる。当該半製品標準生産リードタイムの取得方法も、前記工程標準作業時間に類似し、例えば記憶部102に記憶されている製品PRD01の各々の該半製品の半製品生産リードタイムにおいて、スミルノフ=グラブス検定を用いて異常値を除去するとともに残りのデータの平均をとり、当該平均値を製品PRD01のその半製品の半製品標準生産リードタイムとしてもよい。これにより、記憶部102に製品PRD01のその半製品に対する半製品標準生産リードタイムが記憶される。 The semi-finished product standard production lead time acquisition unit 303 acquires the corresponding semi-finished product standard production lead time for each semi-finished product of the product PRD01 and stores it in the storage unit 102. The definition of the semi-finished product standard production lead time here is similar to the process standard working time described above, and the corresponding semi-finished product delay time is determined by comparing with the semi-finished product production lead time of each of the semi-finished products of the product PRD01. Used to do. The method for acquiring the semi-finished product standard production lead time is also similar to the process standard working time. For example, in the semi-finished product production lead time of each semi-finished product stored in the storage unit 102, the Smirnov-Grabs test is performed. The abnormal value may be removed and the remaining data may be averaged, and the average value may be used as the semi-finished product standard production lead time of the semi-finished product of the product PRD01. As a result, the storage unit 102 stores the semi-finished product standard production lead time for the semi-finished product of the product PRD01.

半製品遅延時間算出部304は、製品PRD01の各々の各半製品に対し、対応する半製品標準生産リードタイムに対する当該半製品の半製品生産リードタイムの遅延時間を算出し、当該半製品の半製品遅延時間として記憶部102に記憶する。これにより、製品PRD01の各々の半製品はいずれも、対応する半製品遅延時間が記憶される。 The semi-finished product delay time calculation unit 304 calculates the delay time of the semi-finished product production lead time for each semi-finished product of the product PRD01 with respect to the corresponding semi-finished product standard production lead time, and calculates the delay time of the semi-finished product production lead time. It is stored in the storage unit 102 as the product delay time. As a result, each semi-finished product of the product PRD01 stores the corresponding semi-finished product delay time.

半製品停滞時間算出部305は、同じ製品に組付けられる複数の半製品の各々に対し、当該半製品の半製品停滞時間を算出し、ここでの半製品停滞時間は、当該半製品の加工形成に用いる工程のうち最遅の工程の作業終了時刻と、当該相互組付に係る工程のうち最早の工程の作業開始時刻との時間差である。 The semi-finished product stagnation time calculation unit 305 calculates the semi-finished product stagnation time of the semi-finished product for each of a plurality of semi-finished products assembled in the same product, and the semi-finished product stagnation time here is the processing of the semi-finished product. This is the time difference between the work end time of the latest step of the steps used for forming and the work start time of the earliest step of the steps related to the mutual assembly.

ここでの「相互組付」に関して、例えば半製品Cは、半製品Aと半製品Bの組付後に加工形成され、また最終製品は、半製品Cと半製品Dを組付けて形成されるとすれば、半製品A及び半製品Bは「相互組付に用いる2つの半製品」であり、半製品C及び半製品Dは「相互組付に用いる2つの半製品」である。 Regarding "mutual assembly" here, for example, the semi-finished product C is processed and formed after the semi-finished product A and the semi-finished product B are assembled, and the final product is formed by assembling the semi-finished product C and the semi-finished product D. If so, the semi-finished product A and the semi-finished product B are "two semi-finished products used for mutual assembly", and the semi-finished product C and the semi-finished product D are "two semi-finished products used for mutual assembly".

説明を簡略化するため、上記4つの半製品の生産リードタイムの状況を図7に示した。半製品Aは時刻t0から生産を開始し、時刻t1で生産が完了し、半製品Bは時刻t2で生産が完了する。時刻t2からt3の間は、半製品AとBはいずれも停滞している。t3からt4までは半製品Aと半製品Bの組付工程、即ち「半製品Aと半製品Bの相互組付に係る工程」であり、一工程であっても、複数の工程の組み合わせであってもよく、時刻t4で当該組付工程は終了し、組付が完了する。その後、一定時間(時刻t4からt6まで)の加工工程を経て、半製品Cは時刻t6に生産が完了する。半製品Dは時刻t5に生産が完了し、時刻t6からt7の間は、半製品CとDはいずれも停滞している。t7からt8までは半製品Cと半製品Dの組付工程、即ち「半製品Cと半製品Dの相互組付に係る工程」であり、時刻t8で当該組付工程は終了し、組付が完了して、製品が得られる。この例において、上記定義からわかるように、半製品Aの半製品停滞時間は(t3−t1)、半製品Bの半製品停滞時間は(t3−t2)、半製品Cの半製品停滞時間は(t7−t6)、半製品Dの半製品停滞時間は(t7−t5)である。 In order to simplify the explanation, FIG. 7 shows the production lead times of the above four semi-finished products. The production of the semi-finished product A starts at time t0, the production is completed at time t1, and the production of the semi-finished product B is completed at time t2. From time t2 to t3, both semi-finished products A and B are stagnant. From t3 to t4 are the assembly process of the semi-finished product A and the semi-finished product B, that is, the "process related to the mutual assembly of the semi-finished product A and the semi-finished product B". The assembly process is completed at time t4, and the assembly is completed. Then, after a processing process for a certain period of time (time t4 to t6), the production of the semi-finished product C is completed at time t6. Production of the semi-finished product D was completed at time t5, and between the time t6 and t7, both the semi-finished products C and D were stagnant. From t7 to t8 are the assembly process of the semi-finished product C and the semi-finished product D, that is, the "process related to the mutual assembly of the semi-finished product C and the semi-finished product D". Is completed and the product is obtained. In this example, as can be seen from the above definition, the semi-product stagnation time of semi-product A is (t3-t1), the semi-product stagnation time of semi-product B is (t3-t2), and the semi-product stagnation time of semi-product C is. (T7-t6), the semi-finished product stagnation time of the semi-finished product D is (t7-t5).

これにより、製品PRD01の各々における各半製品はいずれも、対応する半製品停滞時間が記憶される。 As a result, each semi-finished product in each of the product PRD01 stores the corresponding semi-finished product stagnation time.

本実施例において、製品PRD01の各々の各半製品の半製品遅延時間に対し、異常判定部104も、記憶部102に記憶されている予め設定された閾値を用いて判定する。具体的には、異常判定部104は、製品PRD01の各々における半製品遅延時間が予め設定した半製品遅延閾値を超えた半製品を異常遅延半製品であると判定し、製品PRD01の各々における半製品停滞時間が予め設定した半製品停滞閾値を超えた半製品を異常停滞半製品であると判定する。 In this embodiment, the abnormality determination unit 104 also determines the semi-product delay time of each semi-finished product of the product PRD01 by using a preset threshold value stored in the storage unit 102. Specifically, the abnormality determination unit 104 determines that a semi-finished product having a semi-finished product delay time exceeding a preset semi-finished product delay threshold value in each of the product PRD01 is an abnormal delay semi-finished product, and semi-finished in each of the product PRD01. A semi-finished product whose product stagnation time exceeds a preset semi-finished product stagnation threshold is determined to be an abnormally stagnant semi-finished product.

表示部105は、本実施例の生産リードタイム分析システム300における半製品分析部301の分析結果を外部に向けて表示する。図8に示したように、一定期間に生産された複数の製品PRD01における各半製品の異常遅延率及び異常停滞率を、グラフ形式で表示してもよい。半製品の異常遅延率及び異常停滞率はそれぞれ半製品異常情報として、図示しない演算部により前記各項データに基づいて演算されて記憶部102に記憶され、ユーザはまた、コンピュータ表示インタフェース上で、当該グラフの様々な部位をクリックすることで、各半製品の半製品標準生産リードタイムや、ある半製品の半製品生産リードタイム、及びその他の半製品異常情報(例えば各半製品の半製品遅延時間、各半製品の半製品停滞時間、異常遅延半製品であると判定された半製品番号及び序列番号、異常停滞半製品であると判定された半製品番号及び序列番号等)をそれぞれ取得することができる。半製品分析部301の分析結果は図8において例示的に示されているが、図示の形式はこれに限定されるものではない。 The display unit 105 displays the analysis result of the semi-finished product analysis unit 301 in the production lead time analysis system 300 of this embodiment to the outside. As shown in FIG. 8, the abnormal delay rate and the abnormal stagnation rate of each semi-finished product in the plurality of products PRD01 produced in a certain period may be displayed in a graph format. The abnormal delay rate and the abnormal stagnation rate of the semi-finished products are calculated as semi-finished product abnormality information by a calculation unit (not shown) based on the data of each item and stored in the storage unit 102, and the user can also use the computer display interface. By clicking various parts of the graph, the semi-finished product standard production lead time of each semi-finished product, the semi-finished product production lead time of one semi-finished product, and other semi-finished product abnormality information (for example, the semi-finished product delay of each semi-finished product) Obtain time, semi-product stagnation time of each semi-finished product, semi-product number and rank number determined to be abnormally delayed semi-finished product, semi-product number and rank number determined to be abnormally stagnant semi-finished product, etc.) be able to. The analysis result of the semi-finished product analysis unit 301 is shown exemplary in FIG. 8, but the illustrated format is not limited to this.

これにより、本実施例によれば、製品の生産リードタイムを短縮するために、インテリジェント、視覚的かつ迅速に、生産リードタイムを長引かせる問題半製品を特定することで、ピンポイントに措置を講じて不要な待機時間を回避し、製品の生産リードタイムの短縮を図ることができる。 Thereby, according to this embodiment, in order to shorten the production lead time of the product, pinpoint measures are taken by identifying the problematic semi-finished product that prolongs the production lead time intelligently, visually and quickly. It is possible to avoid unnecessary waiting time and shorten the production lead time of the product.

本実施例は生産リードタイム分析方法に関し、当該生産リードタイム分析方法のフロー図を図9に示した。 In this embodiment, regarding the production lead time analysis method, a flow chart of the production lead time analysis method is shown in FIG.

当該生産リードタイム分析方法では、ある製品PRD01の生産リードタイムを分析しており、当該製品PRD01の各々は、複数の半製品により複数の工程を経て加工されてなり、各半製品はそれぞれ複数の工程を経て加工形成される。 In the production lead time analysis method, the production lead time of a certain product PRD01 is analyzed, and each of the product PRD01 is processed by a plurality of semi-finished products through a plurality of steps, and each semi-finished product has a plurality of semi-finished products. It is processed and formed through a process.

まず、ステップS901において、製品PRD01の各々に対し、関係する各工程の作業実績情報を収集し、当該作業実績情報は工程の作業開始時刻及び作業終了時刻を含むが、具体的な形態は実施例1と同じであるため、その説明は省略する。 First, in step S901, the work record information of each related process is collected for each of the products PRD01, and the work record information includes the work start time and the work end time of the process. Since it is the same as 1, the description thereof will be omitted.

次に、ステップS902において、製品PRD01の各々の各工程に対し、上記作業実績情報に基づいて工程作業時間を算出し、工程作業時間とは当該工程の作業開始時刻と作業終了時刻との時間差を意味する。 Next, in step S902, for each process of the product PRD01, the process work time is calculated based on the above work record information, and the process work time is the time difference between the work start time and the work end time of the process. means.

次に、ステップS903において、製品PRD01の各工程に対し、対応する工程標準作業時間を取得する。工程標準作業時間の定義に関しては、実施例1と同じであるため、その説明は省略する。 Next, in step S903, the corresponding process standard working time is acquired for each process of the product PRD01. Since the definition of the process standard working time is the same as that in the first embodiment, the description thereof will be omitted.

次に、ステップS904において、製品PRD01の各々の各工程に対し、対応する工程標準作業時間に対する当該工程の工程作業時間の遅延時間を算出し、当該工程の工程遅延時間とする。工程遅延時間の具体的な定義に関しては、実施例1と同じであるため、その説明は省略する。 Next, in step S904, for each process of the product PRD01, the delay time of the process work time of the process with respect to the corresponding process standard work time is calculated and used as the process delay time of the process. Since the specific definition of the process delay time is the same as that of the first embodiment, the description thereof will be omitted.

次に、ステップS905において、製品PRD01の各々における、各半製品の加工形成に用いる工程のうち最遅の工程及び当該製品における最遅の工程を除く各工程に対し、当該工程の工程停滞時間を算出し、工程停滞時間は、当該工程の作業終了時刻と、当該工程の次の工程の作業開始時刻との時間差である。工程停滞時間の具体的な定義に関しては、実施例1と同じであるため、その説明は省略する。 Next, in step S905, the process stagnation time of the process is set for each process excluding the latest process and the slowest process in the product among the processes used for processing and forming each semi-finished product in each product PRD01. The calculated process stagnation time is the time difference between the work end time of the process and the work start time of the next process of the process. Since the specific definition of the process stagnation time is the same as that of the first embodiment, the description thereof will be omitted.

次に、ステップS906において、製品PRD01の各々に対し、前記作業実績情報に基づいて製品の生産リードタイムを算出し、当該製品生産リードタイムは、前記作業実績情報収集ステップで収集された各工程のうち最早の工程の作業開始時刻と、最遅の工程の作業終了時刻との時間差である。 Next, in step S906, the production lead time of the product is calculated for each of the products PRD01 based on the work record information, and the product production lead time is the product production lead time of each process collected in the work record information collection step. This is the time difference between the work start time of the earliest process and the work end time of the latest process.

次に、ステップS907において、製品PRD01に対応する製品標準生産リードタイムを取得し、製品標準生産リードタイムの定義に関しては、実施例2と一致するため、その説明は省略する。 Next, in step S907, the product standard production lead time corresponding to the product PRD01 is acquired, and the definition of the product standard production lead time is the same as that of the second embodiment, and thus the description thereof will be omitted.

次に、ステップS908において、製品PRD01の各々に対し、製品標準生産リードタイムに対する当該製品の製品生産リードタイムの遅延時間を算出し、当該製品の製品遅延時間とする。製品遅延時間の具体的な定義に関しては、実施例2と一致するため、その説明は省略する。 Next, in step S908, for each of the products PRD01, the delay time of the product production lead time of the product with respect to the product standard production lead time is calculated and used as the product delay time of the product. Since the specific definition of the product delay time is the same as that of the second embodiment, the description thereof will be omitted.

次に、ステップS909において、製品PRD01の各々の各半製品に対し、作業実績情報に基づいて半製品生産リードタイムを算出し、半製品生産リードタイムは、当該半製品の加工形成に用いる工程のうち最早の工程の作業開始時刻と、最遅の工程の作業終了時刻との時間差である。「加工形成に用いる工程」に関しては、実施例1と一致するため、その説明は省略する。 Next, in step S909, the semi-finished product production lead time is calculated for each semi-finished product of the product PRD01 based on the work record information, and the semi-finished product production lead time is the step used for processing and forming the semi-finished product. This is the time difference between the work start time of the earliest process and the work end time of the latest process. Since the "step used for processing and forming" is the same as that of the first embodiment, the description thereof will be omitted.

次に、ステップS910において、製品PRD01の各半製品に対し、対応する半製品標準生産リードタイムを取得する。半製品標準生産リードタイムの定義に関しては、実施例3と一致するため、その説明は省略する。 Next, in step S910, the corresponding semi-finished product standard production lead time is acquired for each semi-finished product of the product PRD01. Since the definition of the semi-finished product standard production lead time is the same as that of the third embodiment, the description thereof will be omitted.

次に、ステップS911において、製品PRD01の各々の各半製品に対し、対応する半製品標準生産リードタイムに対する当該半製品の半製品生産リードタイムの遅延時間を算出し、当該半製品の半製品遅延時間とする。半製品遅延時間の具体的な定義に関しては、実施例3と一致するため、その説明は省略する。 Next, in step S911, for each semi-finished product of the product PRD01, the delay time of the semi-finished product production lead time of the semi-finished product with respect to the corresponding semi-finished product standard production lead time is calculated, and the semi-finished product delay of the semi-finished product is calculated. Let it be time. Since the specific definition of the semi-finished product delay time is the same as that of the third embodiment, the description thereof will be omitted.

次に、ステップS912において、相互組付に用いる複数の半製品の各々に対し、当該半製品の半製品停滞時間を算出し、半製品停滞時間は、当該半製品の加工形成に用いる工程のうち最遅の工程の作業終了時刻と、相互組付に係る工程のうち最早の工程の作業開始時刻との時間差である。半製品停滞時間の具体的な定義に関しては、実施例3と一致するため、その説明は省略する。 Next, in step S912, the semi-finished product stagnation time of the semi-finished product is calculated for each of the plurality of semi-finished products used for mutual assembly, and the semi-finished product stagnation time is included in the process used for processing and forming the semi-finished product. This is the time difference between the work end time of the latest process and the work start time of the earliest process among the processes related to mutual assembly. Since the specific definition of the semi-product stagnation time is the same as that of the third embodiment, the description thereof will be omitted.

次に、ステップS913において、異常判定を行い、具体的には、工程遅延時間が予め設定した工程遅延閾値を超えた工程を異常遅延工程であると判定するとともに、工程停滞時間が予め設定した工程停滞閾値を超えた工程を異常停滞工程であると判定し、製品遅延時間が予め設定した製品遅延閾値を超えた製品を異常遅延製品であると判定し、半製品遅延時間が予め設定した半製品遅延閾値を超えた半製品を異常遅延半製品であると判定するとともに、半製品停滞時間が予め設定した半製品停滞閾値を超えた半製品を異常停滞半製品であると判定する。 Next, in step S913, an abnormality determination is performed, and specifically, a process in which the process delay time exceeds the preset process delay threshold is determined to be an abnormal delay process, and the process stagnation time is preset. A process that exceeds the stagnation threshold is determined to be an abnormal stagnation process, a product that exceeds the product delay threshold with a preset product delay threshold is determined to be an abnormal delay product, and a semi-product delay time is preset. A semi-finished product that exceeds the delay threshold is determined to be an abnormally delayed semi-finished product, and a semi-finished product that exceeds the preset semi-product stagnation threshold is determined to be an abnormally stagnant semi-finished product.

次に、ステップS914において、表示を行う。具体的には、工程に関連する分析結果、製品に関連する分析結果、及び半製品に関連する分析結果を表示する。具体的な表示内容は実施例1から実施例3と一致するため、その説明は省略する。ここで、フローは終了する。 Next, in step S914, the display is performed. Specifically, the analysis result related to the process, the analysis result related to the product, and the analysis result related to the semi-finished product are displayed. Since the specific display contents are the same as those in the first to third embodiments, the description thereof will be omitted. At this point, the flow ends.

これにより、本実施例によれば、製品の生産リードタイムを短縮するために、インテリジェント、視覚的かつ迅速に、生産リードタイムを長引かせる問題点を特定することで、ピンポイントに措置を講じて不要な待機時間を回避し、製品の生産リードタイムの短縮を図ることができる。
<変形例>
Thereby, according to this embodiment, in order to shorten the production lead time of the product, measures are taken pinpointly by identifying the problem of prolonging the production lead time intelligently, visually and quickly. It is possible to avoid unnecessary waiting time and shorten the production lead time of the product.
<Modification example>

以上、本発明の各実施例を図示して説明したが、当業者には明らかなように、本発明は必ずしも説明された全ての構成を備えた各実施例に限定されるわけではなく、本発明の技術的思想を逸脱しない範囲において、ある実施例の構成に別の実施例の構成を加えることができ、また、各実施例の構成の一部に対し別の構成の追加、削除、置換を行うことができる。このような変形例について、以下説明する。 Although each embodiment of the present invention has been illustrated and described above, as will be apparent to those skilled in the art, the present invention is not necessarily limited to each embodiment having all the configurations described. The configuration of another embodiment can be added to the configuration of one embodiment without departing from the technical idea of the invention, and another configuration can be added, deleted, or replaced with respect to a part of the configuration of each embodiment. It can be performed. An example of such a modification will be described below.

例えば、生産リードタイム分析システムは、実施例2の製品分析部201と実施例3の半製品分析部301を同時に含んでもよく、また、実施例1の工程分析部103は含まずに、実施例2の製品分析部201又は実施例3の半製品分析部301のみを含んでもよい。 For example, the production lead time analysis system may include the product analysis unit 201 of the second embodiment and the semi-product analysis unit 301 of the third embodiment at the same time, and may not include the process analysis unit 103 of the first embodiment. Only the product analysis unit 201 of 2 or the semi-product analysis unit 301 of Example 3 may be included.

さらに、実施例1の工程分析部103において、工程停滞時間算出部109は含まずに、工程遅延時間のみを算出することもでき、同様に、実施例3の半製品分析部301において、半製品停滞時間算出部305は含まずに、半製品遅延時間のみを算出することもできる。 Further, the process analysis unit 103 of the first embodiment can calculate only the process delay time without including the process stagnation time calculation unit 109. Similarly, the semi-finished product analysis unit 301 of the third embodiment can calculate the semi-finished product. It is also possible to calculate only the semi-finished product delay time without including the stagnation time calculation unit 305.

さらに、上記の各実施例では、複数の半製品で加工されてなる複数の製品PRD01の分析について説明しているが、製品は1つの半製品のみで加工されていてもよく、この場合、半製品間の相互組付は存在しないため、当該半製品の「加工形成に用いる工程のうち最遅の工程」とは、全製品における最遅の工程となる。さらに、各半製品は、1種の工程のみを経て加工形成されてもよく、また、ある一製品のみに対し分析を行ってもよい。 Further, in each of the above embodiments, the analysis of a plurality of product PRD01 processed by a plurality of semi-finished products is described, but the product may be processed by only one semi-finished product, and in this case, the semi-finished product is used. Since there is no mutual assembly between products, the "latest process among the processes used for processing and forming" of the semi-finished product is the slowest process in all products. Further, each semi-finished product may be processed and formed through only one type of process, or only one product may be analyzed.

さらに、上記の各実施例において、ある工程の工程標準作業時間は、スミルノフ=グラブス検定を用いて各製品のその工程の複数の工程作業時間から異常値を除去した後、平均をとって算出されているが、当該算出方法はこれに限定されるものではなく、スミルノフ=グラブス検定以外の別のデータ処理方法であってもよい。また、当該工程標準作業時間の取得は、既存データに基づく計算により取得されてもよく、或いは人為的に事前に設定されてもよく、例えば業界標準を用いた工程作業時間を用いることもできる。製品標準生産リードタイム及び半製品標準生産リードタイムについても、上記と同じ理由で、別の計算方法により取得されるか又は事前に設定されてもよい。 Further, in each of the above examples, the process standard working time of a certain process is calculated by averaging after removing abnormal values from a plurality of process working times of the process of each product using the Smirnov-Grabs test. However, the calculation method is not limited to this, and may be another data processing method other than the Smirnov-Grabs test. Further, the process standard work time may be acquired by calculation based on existing data, or may be artificially set in advance. For example, the process work time using an industry standard may be used. The product standard production lead time and the semi-finished product standard production lead time may also be acquired or preset by another calculation method for the same reason as described above.

さらに、実施例4の生産リードタイム分析方法は、工程分析に係るステップS902〜S905、製品分析に係るステップS906〜S908、及び半製品分析に係るステップS909〜S912を含むが、これらの間の実行順序は上記に限定されるものではなく、別の実行順序により順次実行するか又は同時に実行してもよい。また、当該生産リードタイム分析方法は、工程分析に係るステップのみを含む、又は製品分析に係るステップのみを含む、又は半製品分析に係るステップのみを含むとしてもよく、この場合には、ステップS913の異常判定ステップ及びステップS914の表示ステップにおいて、対応するターゲットのみを判定して表示する。 Further, the production lead time analysis method of Example 4 includes steps S902 to S905 relating to process analysis, steps S906 to S908 relating to product analysis, and steps S909 to S912 relating to semi-finished product analysis, which are executed between them. The order is not limited to the above, and may be executed sequentially or simultaneously according to another execution order. Further, the production lead time analysis method may include only steps related to process analysis, only steps related to product analysis, or only steps related to semi-finished product analysis. In this case, step S913 may be included. In the abnormality determination step and the display step of step S914, only the corresponding target is determined and displayed.

Claims (12)

1又は複数の製品の生産リードタイムを分析する生産リードタイム分析方法であって、前記製品は、1又は複数の半製品により1又は複数の工程を経て加工されてなり、前記半製品は、1又は複数の工程を経て加工形成される、前記生産リードタイム分析方法において、
前記各製品に対し、関係する各工程の作業実績情報を収集する作業実績情報収集ステップであって、前記作業実績情報は工程の作業開始時刻及び作業終了時刻を含むステップと、
前記各製品の各工程に対し、前記作業実績情報に基づいて工程作業時間を算出する工程作業時間算出ステップであって、前記工程作業時間は該工程の作業開始時刻と作業終了時刻との時間差であるステップと、
前記製品の各種工程に対し、対応する工程標準作業時間を取得する工程標準作業時間取得ステップと、
前記各製品の各工程に対し、当該工程における対応する工程標準作業時間に対する前記工程作業時間の遅延時間を算出し、当該工程の工程遅延時間とする工程遅延時間算出ステップと、
を含むことを特徴とする生産リードタイム分析方法。
A production lead time analysis method for analyzing the production lead time of one or more products, wherein the product is processed by one or more semi-finished products through one or more steps, and the semi-finished product is one. Alternatively, in the production lead time analysis method, which is processed and formed through a plurality of steps.
It is a work record information collection step for collecting work record information of each related process for each product, and the work record information includes a step including a work start time and a work end time of the process.
It is a process work time calculation step for calculating the process work time based on the work record information for each process of each product, and the process work time is the time difference between the work start time and the work end time of the process. With a certain step
A process standard work time acquisition step for acquiring the corresponding process standard work time for various processes of the product, and a process standard work time acquisition step.
For each process of each product, a process delay time calculation step of calculating the delay time of the process work time with respect to the corresponding process standard work time in the process and using the process delay time of the process as the process delay time,
A production lead time analysis method characterized by including.
前記各製品における、各半製品の前記加工形成に用いる工程のうち最遅の工程及び当該製品における最遅の工程を除く各工程に対し、当該工程の工程停滞時間を算出する工程停滞時間算出ステップをさらに含み、前記工程停滞時間は、当該工程の作業終了時刻と当該工程の次の工程の作業開始時刻との時間差である
ことを特徴とする請求項1に記載の生産リードタイム分析方法。
A process stagnation time calculation step for calculating the process stagnation time of the process for each process excluding the latest process and the slowest process in the product among the processes used for the processing formation of each semi-finished product in each product. The production lead time analysis method according to claim 1, wherein the process stagnation time is a time difference between a work end time of the process and a work start time of the next process of the process.
前記工程遅延時間が予め設定した工程遅延閾値を超えた工程を異常遅延工程であると判定し、かつ前記工程停滞時間が予め設定した工程停滞閾値を超えた工程を異常停滞工程であると判定する異常判定ステップと、
各工程の前記工程作業時間、各種工程の前記工程標準作業時間、及び工程異常情報のうちの少なくとも1つを表示するステップであって、前記工程異常情報は、各工程の前記工程遅延時間、各工程の前記工程停滞時間、工程の異常遅延率、工程の異常停滞率、前記異常遅延工程の識別情報、及び前記異常停滞工程の識別情報のうちの少なくとも1つを含む表示ステップと、
をさらに含むことを特徴とする請求項2に記載の生産リードタイム分析方法。
A process having a process delay time exceeding a preset process delay threshold is determined to be an abnormal delay process, and a process having a process stagnation time exceeding a preset process stagnation threshold is determined to be an abnormal stagnation process. Abnormality judgment step and
It is a step of displaying at least one of the process work time of each process, the process standard work time of various processes, and process abnormality information, and the process abnormality information is the process delay time of each process. A display step including at least one of the process stagnation time of the process, the abnormal delay rate of the process, the abnormal stagnation rate of the process, the identification information of the abnormal delay process, and the identification information of the abnormal stagnation process.
The production lead time analysis method according to claim 2, further comprising.
前記各製品に対し、前記作業実績情報に基づいて製品生産リードタイムを算出するステップであって、前記製品生産リードタイムは、前記作業実績情報収集ステップで収集される各工程のうち最早の工程の作業開始時刻と、最遅の工程の作業終了時刻との時間差である、製品生産リードタイム算出ステップと、
前記製品に対応する製品標準生産リードタイムを取得する製品標準生産リードタイム取得ステップと、
前記各製品に対し、当該製品における前記製品標準生産リードタイムに対する前記製品生産リードタイムの遅延時間を算出し、当該製品の製品遅延時間とする製品遅延時間算出ステップと、をさらに含み、
前記異常判定ステップにおいて、前記製品遅延時間が予め設定した製品遅延閾値を超えた製品を異常遅延製品であるとさらに判定し、
前記表示ステップにおいて、各製品の前記製品生産リードタイム、前記製品標準生産リードタイム、及び製品異常情報のうちの少なくとも1つをさらに表示し、前記製品異常情報は、各製品の前記製品遅延時間、製品の異常遅延率、平均遅延時間、及び前記異常遅延製品の識別情報のうちの少なくとも1つを含む
ことを特徴とする請求項3に記載の生産リードタイム分析方法。
It is a step of calculating the product production lead time for each product based on the work record information, and the product production lead time is the earliest step among the steps collected in the work record information collection step. The product production lead time calculation step, which is the time difference between the work start time and the work end time of the latest process,
The product standard production lead time acquisition step for acquiring the product standard production lead time corresponding to the product, and
For each product, the product delay time calculation step of calculating the delay time of the product production lead time with respect to the product standard production lead time of the product and using it as the product delay time of the product is further included.
In the abnormality determination step, a product whose product delay time exceeds a preset product delay threshold value is further determined to be an abnormality delay product.
In the display step, at least one of the product production lead time, the product standard production lead time, and the product abnormality information of each product is further displayed, and the product abnormality information is the product delay time of each product. The production lead time analysis method according to claim 3, wherein the product includes at least one of an abnormal delay rate, an average delay time, and identification information of the abnormally delayed product.
前記各製品の各半製品に対し、前記作業実績情報に基づいて半製品生産リードタイムを算出するステップであって、前記半製品生産リードタイムは、当該半製品における前記加工形成に用いる工程のうち最早の工程の作業開始時刻と最遅の工程の作業終了時刻との時間差である、半製品生産リードタイム算出ステップと、
前記製品の各種半製品に対し、対応する半製品標準生産リードタイムを取得する半製品標準生産リードタイム取得ステップと、
前記各製品の各半製品に対し、当該半製品における対応する半製品標準生産リードタイムに対する前記半製品生産リードタイムの遅延時間を算出し、当該半製品の半製品遅延時間とする半製品遅延時間算出ステップと、
相互組付に用いる複数の半製品の各々に対し、当該半製品の半製品停滞時間を算出するステップであって、前記半製品停滞時間は、当該半製品の前記加工形成に用いる工程のうち最遅の工程の作業終了時刻と前記相互組付に係る工程のうち最早の工程の作業開始時刻との時間差である、半製品停滞時間算出ステップと、
をさらに含み、
前記異常判定ステップにおいて、前記半製品遅延時間が予め設定した半製品遅延閾値を超えた半製品を異常遅延半製品であるとさらに判定し、かつ前記半製品停滞時間が予め設定した半製品停滞閾値を超えた半製品を異常停滞半製品であると判定し、
前記表示ステップにおいて、各半製品の前記半製品生産リードタイム、各半製品の前記半製品標準生産リードタイム、及び半製品異常情報のうちの少なくとも1つをさらに表示し、前記半製品異常情報は、各半製品の前記半製品遅延時間、各半製品の前記半製品停滞時間、半製品の異常遅延率、半製品の異常停滞率、前記異常遅延半製品の識別情報、及び前記異常停滞半製品の識別情報のうちの少なくとも1つを含む
ことを特徴とする請求項3に記載の生産リードタイム分析方法。
For each semi-finished product of the semi-finished product, the step of calculating the semi-finished product production lead time based on the work record information, and the semi-finished product production lead time is one of the steps used for the processing formation in the semi-finished product. The semi-finished product production lead time calculation step, which is the time difference between the work start time of the earliest process and the work end time of the latest process,
For each of the semi-finished products of the above products, a semi-finished product standard production lead time acquisition step for acquiring the corresponding semi-finished product standard production lead time, and
For each semi-finished product of the semi-finished product, the delay time of the semi-finished product production lead time with respect to the corresponding semi-finished product standard production lead time of the semi-finished product is calculated, and the semi-finished product delay time is set as the semi-finished product delay time of the semi-finished product. Calculation steps and
It is a step of calculating the semi-finished product stagnation time of the semi-finished product for each of the plurality of semi-finished products used for mutual assembly, and the semi-finished product stagnation time is the most of the steps used for the processing formation of the semi-finished product. The semi-finished product stagnation time calculation step, which is the time difference between the work end time of the late process and the work start time of the earliest process among the processes related to the mutual assembly,
Including
In the abnormality determination step, a semi-product whose semi-product delay time exceeds the preset semi-product delay threshold is further determined to be an abnormal delay semi-product, and the semi-product stagnation time is preset. A semi-finished product that exceeds the above value is judged to be an abnormally stagnant semi-finished product.
In the display step, at least one of the semi-finished product production lead time of each semi-finished product, the semi-finished product standard production lead time of each semi-finished product, and the semi-finished product abnormality information is further displayed, and the semi-finished product abnormality information is displayed. , The semi-finished product delay time of each semi-finished product, the semi-finished product stagnation time of each semi-finished product, the abnormal delay rate of the semi-finished product, the abnormal stagnation rate of the semi-finished product, the identification information of the abnormally delayed semi-finished product, and the abnormal stagnant semi-finished product. The production lead time analysis method according to claim 3, wherein the production lead time analysis method includes at least one of the identification information of the above.
前記工程標準作業時間取得ステップにおいて、前記製品の各種工程に対し、前記各製品の当該工程の前記工程作業時間から異常値を除去して前記工程標準作業時間を算出する
ことを特徴とする請求項1〜5のいずれか1項に記載の生産リードタイム分析方法。
A claim characterized in that, in the process standard work time acquisition step, for various processes of the product, the process standard work time is calculated by removing an abnormal value from the process work time of the process of each product. The production lead time analysis method according to any one of 1 to 5.
1又は複数の製品の生産リードタイムを分析する生産リードタイム分析システムであって、前記製品は、1又は複数の半製品により1又は複数の工程を経て加工されてなり、前記半製品は、1又は複数の工程を経て加工形成される、前記生産リードタイム分析システムにおいて、
前記各製品に対し、関係する各工程の作業実績情報を収集する作業実績情報収集部であって、前記作業実績情報は工程の作業開始時刻及び作業終了時刻を含む、作業実績情報収集部と、
前記各製品の各工程に対し、前記作業実績情報に基づいて工程作業時間を算出する工程作業時間算出部であって、前記工程作業時間は該工程の作業開始時刻と作業終了時刻との時間差である、工程作業時間算出部と、
前記製品の各種工程に対し、対応する工程標準作業時間を取得する工程標準作業時間取得部と、
前記各製品の各工程に対し、当該工程における対応する工程標準作業時間に対する前記工程作業時間の遅延時間を算出し、当該工程の工程遅延時間とする工程遅延時間算出部と、
を含むことを特徴とする生産リードタイム分析システム。
A production lead time analysis system that analyzes the production lead time of one or more products, wherein the product is processed by one or more semi-finished products through one or more steps, and the semi-finished product is one. Alternatively, in the production lead time analysis system, which is processed and formed through a plurality of steps.
A work record information collection unit that collects work record information of each related process for each product, and the work record information includes a work start time and a work end time of the process, and a work record information collection unit.
It is a process work time calculation unit that calculates the process work time based on the work record information for each process of each product, and the process work time is the time difference between the work start time and the work end time of the process. There is a process work time calculation unit and
A process standard work time acquisition unit that acquires the corresponding process standard work time for various processes of the product, and a process standard work time acquisition unit.
For each process of each product, a process delay time calculation unit that calculates the delay time of the process work time with respect to the corresponding process standard work time in the process and sets it as the process delay time of the process.
A production lead time analysis system characterized by including.
前記各製品における、各半製品の前記加工形成に用いる工程のうち最遅の工程及び当該製品における最遅の工程を除く各工程に対し、当該工程の工程停滞時間を算出する工程停滞時間算出部をさらに含み、前記工程停滞時間は、当該工程の作業終了時刻と当該工程の次の工程の作業開始時刻との時間差である
ことを特徴とする請求項7に記載の生産リードタイム分析システム。
Process stagnation time calculation unit that calculates the process stagnation time of the process for each process excluding the slowest process and the slowest process in the product among the processes used for the processing formation of each semi-finished product in each product. The production lead time analysis system according to claim 7, wherein the process stagnation time is a time difference between a work end time of the process and a work start time of the next process of the process.
前記工程遅延時間が予め設定した工程遅延閾値を超えた工程を異常遅延工程であると判定し、かつ前記工程停滞時間が予め設定した工程停滞閾値を超えた工程を異常停滞工程であると判定する異常判定部と、
各工程の前記工程作業時間、各種工程の前記工程標準作業時間、及び工程異常情報のうちの少なくとも1つを表示する表示部であって、前記工程異常情報は、各工程の前記工程遅延時間、各工程の前記工程停滞時間、工程の異常遅延率、工程の異常停滞率、前記異常遅延工程の識別情報、及び前記異常停滞工程の識別情報のうちの少なくとも1つを含む、表示部と、
をさらに含むことを特徴とする請求項8に記載の生産リードタイム分析システム。
A process having a process delay time exceeding a preset process delay threshold is determined to be an abnormal delay process, and a process having a process stagnation time exceeding a preset process stagnation threshold is determined to be an abnormal stagnation process. Abnormality judgment unit and
A display unit that displays at least one of the process work time of each process, the process standard work time of various processes, and process abnormality information, and the process abnormality information is the process delay time of each process. A display unit including at least one of the process stagnation time of each process, the abnormal delay rate of the process, the abnormal stagnation rate of the process, the identification information of the abnormal delay process, and the identification information of the abnormal stagnation process.
The production lead time analysis system according to claim 8, further comprising.
前記各製品に対し、前記作業実績情報に基づいて製品生産リードタイムを算出する製品生産リードタイム算出部であって、前記製品生産リードタイムは、前記作業実績情報収集部で収集された各工程のうち最早の工程の作業開始時刻と最遅の工程の作業終了時刻との時間差である、製品生産リードタイム算出部と、
前記製品に対応する製品標準生産リードタイムを取得する製品標準生産リードタイム取得部と、
前記各製品に対し、当該製品における前記製品標準生産リードタイムに対する前記製品生産リードタイムの遅延時間を算出し、当該製品の製品遅延時間とする製品遅延時間算出部と、
をさらに含み、
前記異常判定部は、前記製品遅延時間が予め設定した製品遅延閾値を超えた製品を異常遅延製品であるとさらに判定し、
前記表示部は、各製品の前記製品生産リードタイム、前記製品標準生産リードタイム、及び製品異常情報のうちの少なくとも1つをさらに表示し、前記製品異常情報は、各製品の前記製品遅延時間、製品の異常遅延率、平均遅延時間、及び前記異常遅延製品の識別情報のうちの少なくとも1つを含む
ことを特徴とする請求項9に記載の生産リードタイム分析システム。
A product production lead time calculation unit that calculates a product production lead time based on the work record information for each product, and the product production lead time is the product production lead time of each process collected by the work record information collection unit. The product production lead time calculation unit, which is the time difference between the work start time of the earliest process and the work end time of the latest process,
The product standard production lead time acquisition unit that acquires the product standard production lead time corresponding to the product, and the product standard production lead time acquisition unit.
For each of the products, a product delay time calculation unit that calculates the delay time of the product production lead time with respect to the product standard production lead time of the product and uses it as the product delay time of the product.
Including
The abnormality determination unit further determines that the product whose product delay time exceeds the preset product delay threshold value is an abnormality delay product, and further determines that the product is an abnormality delay product.
The display unit further displays at least one of the product production lead time, the product standard production lead time, and the product abnormality information of each product, and the product abnormality information is the product delay time of each product. The production lead time analysis system according to claim 9, wherein the product includes at least one of an abnormal delay rate, an average delay time, and identification information of the abnormally delayed product.
前記各製品の各半製品に対し、前記作業実績情報に基づいて半製品生産リードタイムを算出する半製品生産リードタイム算出部であって、前記半製品生産リードタイムは、当該半製品における前記加工形成に用いる工程のうち最早の工程の作業開始時刻と最遅の工程の作業終了時刻との時間差である、半製品生産リードタイム算出部と、
前記製品の各種半製品に対し、対応する半製品標準生産リードタイムを取得する半製品標準生産リードタイム取得部と、
前記各製品の各半製品に対し、当該半製品における対応する半製品標準生産リードタイムに対する前記半製品生産リードタイムの遅延時間を算出し、当該半製品の半製品遅延時間とする半製品遅延時間算出部と、
相互組付に用いる複数の半製品の各々に対し、当該半製品の半製品停滞時間を算出する半製品停滞時間算出部であって、前記半製品停滞時間は、当該半製品の前記加工形成に用いる工程のうち最遅の工程の作業終了時刻と前記相互組付に係る工程のうち最早の工程の作業開始時刻との時間差である、半製品停滞時間算出部と、をさらに含み、
前記異常判定部はさらに、前記半製品遅延時間が予め設定した半製品遅延閾値を超えた半製品を異常遅延半製品であると判定し、かつ前記半製品停滞時間が予め設定した半製品停滞閾値を超えた半製品を異常停滞半製品であると判定し、
前記表示部は、各半製品の前記半製品生産リードタイム、各半製品の前記半製品標準生産リードタイム、及び半製品異常情報のうちの少なくとも1つをさらに表示し、前記半製品異常情報は、各半製品の前記半製品遅延時間、各半製品の前記半製品停滞時間、半製品の異常遅延率、半製品の異常停滞率、前記異常遅延半製品の識別情報、及び前記異常停滞半製品の識別情報のうちの少なくとも1つを含む
ことを特徴とする請求項9に記載の生産リードタイム分析システム。
A semi-finished product production lead time calculation unit that calculates a semi-finished product production lead time based on the work record information for each semi-finished product of each product, and the semi-finished product production lead time is the processing of the semi-finished product. The semi-finished product production lead time calculation unit, which is the time difference between the work start time of the earliest process and the work end time of the latest process among the processes used for formation,
A semi-finished product standard production lead time acquisition unit that acquires the corresponding semi-finished product standard production lead time for various semi-finished products of the above products.
For each semi-finished product of the semi-finished product, the delay time of the semi-finished product production lead time with respect to the corresponding semi-finished product standard production lead time of the semi-finished product is calculated, and the semi-finished product delay time is set as the semi-finished product delay time of the semi-finished product. Calculation part and
A semi-finished product stagnation time calculation unit that calculates the semi-finished product stagnation time of the semi-finished product for each of the plurality of semi-finished products used for mutual assembly. It further includes a semi-finished product stagnation time calculation unit, which is a time difference between the work end time of the latest process among the processes to be used and the work start time of the earliest process among the processes related to the mutual assembly.
The abnormality determination unit further determines that a semi-finished product having a semi-product delay time exceeding the preset semi-product delay threshold value is an abnormal delay semi-finished product, and the semi-product stagnation time is preset to a semi-product stagnation threshold value. A semi-finished product that exceeds the above value is judged to be an abnormally stagnant semi-finished product.
The display unit further displays at least one of the semi-finished product production lead time of each semi-finished product, the semi-finished product standard production lead time of each semi-finished product, and the semi-finished product abnormality information. , The semi-finished product delay time of each semi-finished product, the semi-finished product stagnation time of each semi-finished product, the abnormal delay rate of the semi-finished product, the abnormal stagnation rate of the semi-finished product, the identification information of the abnormally delayed semi-finished product, and the abnormal stagnant semi-finished product. The production lead time analysis system according to claim 9, wherein the production lead time analysis system includes at least one of the identification information of the above.
前記工程標準作業時間取得部は前記製品の各種工程に対し、前記各製品の当該工程の前記工程作業時間から異常値を除去して前記工程標準作業時間を算出する
ことを特徴とする請求項7〜11のいずれか1項に記載の生産リードタイム分析システム。
7. The process standard working time acquisition unit calculates the process standard working time by removing an abnormal value from the process working time of the process of each product for various processes of the product. The production lead time analysis system according to any one of 1 to 11.
JP2021069519A 2020-04-22 2021-04-16 Production lead time analysis method and production lead time analysis system Active JP7141487B2 (en)

Applications Claiming Priority (2)

Application Number Priority Date Filing Date Title
CN202010321226.7 2020-04-22
CN202010321226.7A CN113537683A (en) 2020-04-22 2020-04-22 Production cycle analysis method and production cycle analysis system

Publications (2)

Publication Number Publication Date
JP2021174541A true JP2021174541A (en) 2021-11-01
JP7141487B2 JP7141487B2 (en) 2022-09-22

Family

ID=78094087

Family Applications (1)

Application Number Title Priority Date Filing Date
JP2021069519A Active JP7141487B2 (en) 2020-04-22 2021-04-16 Production lead time analysis method and production lead time analysis system

Country Status (2)

Country Link
JP (1) JP7141487B2 (en)
CN (1) CN113537683A (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2023072469A (en) * 2021-11-12 2023-05-24 株式会社名張ホールディングス Production facility management device and production facility management program

Families Citing this family (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN114637264B (en) * 2022-03-15 2024-05-17 广州明珞装备股份有限公司 Motion stability analysis method, system, device and storage medium
CN116663868B (en) * 2023-08-01 2024-04-19 江门市科能电子有限公司 PCB assembly progress monitoring system

Citations (10)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH04240059A (en) * 1991-01-21 1992-08-27 Nec Corp Control device for production tray
JPH0772921A (en) * 1993-09-03 1995-03-17 Misawa Homes Co Ltd Production control system
JPH1080842A (en) * 1996-09-05 1998-03-31 Toyota Motor Corp Production plan preparing device
JP2003067033A (en) * 2001-08-29 2003-03-07 Trinity Ind Corp Continuous processing stage display system
JP2005071136A (en) * 2003-08-26 2005-03-17 Matsushita Electric Works Ltd Delivery time management support system, its program, recording medium recording its program and delivery time management method for product
JP2010128819A (en) * 2008-11-27 2010-06-10 Nissan Motor Co Ltd Support process determination system and support process determination method
CN103345209A (en) * 2013-06-04 2013-10-09 张舒 Method and system for production monitoring
JP2014225068A (en) * 2013-05-15 2014-12-04 株式会社日立製作所 Production index extraction apparatus and program
JP2016018241A (en) * 2014-07-04 2016-02-01 オムロン株式会社 Production process analysis system
JP2017162044A (en) * 2016-03-08 2017-09-14 株式会社日立ソリューションズ東日本 Production planning device, production planning method and production planning program

Patent Citations (10)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH04240059A (en) * 1991-01-21 1992-08-27 Nec Corp Control device for production tray
JPH0772921A (en) * 1993-09-03 1995-03-17 Misawa Homes Co Ltd Production control system
JPH1080842A (en) * 1996-09-05 1998-03-31 Toyota Motor Corp Production plan preparing device
JP2003067033A (en) * 2001-08-29 2003-03-07 Trinity Ind Corp Continuous processing stage display system
JP2005071136A (en) * 2003-08-26 2005-03-17 Matsushita Electric Works Ltd Delivery time management support system, its program, recording medium recording its program and delivery time management method for product
JP2010128819A (en) * 2008-11-27 2010-06-10 Nissan Motor Co Ltd Support process determination system and support process determination method
JP2014225068A (en) * 2013-05-15 2014-12-04 株式会社日立製作所 Production index extraction apparatus and program
CN103345209A (en) * 2013-06-04 2013-10-09 张舒 Method and system for production monitoring
JP2016018241A (en) * 2014-07-04 2016-02-01 オムロン株式会社 Production process analysis system
JP2017162044A (en) * 2016-03-08 2017-09-14 株式会社日立ソリューションズ東日本 Production planning device, production planning method and production planning program

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2023072469A (en) * 2021-11-12 2023-05-24 株式会社名張ホールディングス Production facility management device and production facility management program
JP7289555B2 (en) 2021-11-12 2023-06-12 株式会社名張ホールディングス Production equipment management device and production equipment management program

Also Published As

Publication number Publication date
JP7141487B2 (en) 2022-09-22
CN113537683A (en) 2021-10-22

Similar Documents

Publication Publication Date Title
JP2021174541A (en) Production lead time analysis method and production lead time analysis system
CN107850889A (en) Management system and management method
CN108780312B (en) Method and system for root cause analysis for assembly lines using path tracing
US11157821B2 (en) Traceability system and method for traceability
CN107908548A (en) A kind of method and apparatus for generating test case
CN110060087A (en) Detection method, device and the server of abnormal data
CN110889684A (en) Method and device for identifying upstream and downstream customers, electronic equipment and storage medium
JP6802122B2 (en) Cause estimation method and program
US20100228510A1 (en) Quality Information Control Analysis System
Kang et al. A methodology for production analysis based on the RFID-collected manufacturing big data
JP7474303B2 (en) Management System
JP6531820B2 (en) Estimator Visualization System
CN113780744B (en) Goods combination method and device and electronic equipment
JP6556387B2 (en) Information technology utilization evaluation device and information technology utilization evaluation method
JP2021179981A (en) Information processing system, information processing device, and program
CN115619358A (en) Building engineering progress management system and method based on BIM technology
US11823111B2 (en) Work instruction system and work instruction method
US11656613B2 (en) Information processing device and information processing method
CN115081921A (en) ERP e-commerce management system based on big data
CN115204572A (en) Improved space-time alignment-based Castrip digital portrait generation and construction method
JP4801512B2 (en) Rework measurement system and measurement method thereof
US20170068927A1 (en) Warehouse profit simulation device
CN112446626A (en) Application tool for monitoring manufacturing data abnormity in real time
US20190384272A1 (en) System section data management device and method thereof
WO2020221656A1 (en) Method, apparatus and system for acquiring digitized data of factory

Legal Events

Date Code Title Description
A621 Written request for application examination

Free format text: JAPANESE INTERMEDIATE CODE: A621

Effective date: 20210416

A131 Notification of reasons for refusal

Free format text: JAPANESE INTERMEDIATE CODE: A131

Effective date: 20220222

A977 Report on retrieval

Free format text: JAPANESE INTERMEDIATE CODE: A971007

Effective date: 20220224

A521 Request for written amendment filed

Free format text: JAPANESE INTERMEDIATE CODE: A523

Effective date: 20220420

TRDD Decision of grant or rejection written
A01 Written decision to grant a patent or to grant a registration (utility model)

Free format text: JAPANESE INTERMEDIATE CODE: A01

Effective date: 20220906

A61 First payment of annual fees (during grant procedure)

Free format text: JAPANESE INTERMEDIATE CODE: A61

Effective date: 20220909

R150 Certificate of patent or registration of utility model

Ref document number: 7141487

Country of ref document: JP

Free format text: JAPANESE INTERMEDIATE CODE: R150