JP2010112081A - Method of placing time-curable material - Google Patents
Method of placing time-curable material Download PDFInfo
- Publication number
- JP2010112081A JP2010112081A JP2008285852A JP2008285852A JP2010112081A JP 2010112081 A JP2010112081 A JP 2010112081A JP 2008285852 A JP2008285852 A JP 2008285852A JP 2008285852 A JP2008285852 A JP 2008285852A JP 2010112081 A JP2010112081 A JP 2010112081A
- Authority
- JP
- Japan
- Prior art keywords
- time
- curable material
- foundation
- hardening material
- curable
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Granted
Links
Images
Landscapes
- On-Site Construction Work That Accompanies The Preparation And Application Of Concrete (AREA)
Abstract
Description
本発明は、基礎部分に対する経時性硬化材料の打設方法に関する。 The present invention relates to a method for placing a time-hardening material on a base portion.
一般に、設備基礎上面における設備設置面の施工方法は、基礎部分を所定の高さで仕上げた後、基礎部分表面の粗面化処理と設備設置面のレベル出し用のパッドグラウト打設を行い、その後、基礎部分上方に設備を設置するための設備取合い金物を設置して、設備取合い金物と設備基礎上面の空隙に流動性の高いグラウトを充填するという方法がとられている。しかし、この方法は、施工が何段階にもなり、施工手間および施工時間を要すという課題があった。 In general, the installation method of the installation surface on the upper surface of the facility foundation is to finish the foundation part at a predetermined height, then perform roughening treatment of the surface of the foundation part and pad grout placement for leveling the installation installation surface, Then, the method of installing the equipment fitting metal for installing an installation above a foundation part, and filling the grout with high fluidity into the space | gap of an equipment fitting metal and an equipment foundation upper surface is taken. However, this method has a problem that the number of stages of construction is required, and it takes time and time for construction.
そこで、以下に説明するような設備基礎における設備設置面の施工方法が行われることとなった。図1は、従来一般的に行われている設備基礎における設備設置面の施工方法の説明図である。図1に示すように、基礎部分100の上部に基礎金物101および基礎用鉄筋102が設置され、また、基礎部分100の側方には、基礎部分100の側面を囲むように型枠103が配置される。このとき、型枠103の上端部は、基礎金物101および基礎用鉄筋102が設置された位置より上方とされる。また、基礎部分100の側面は必ずしも平滑ではないため、型枠103と基礎部分100の側面の間には、基礎部分100の側面の凹凸によって生ずる隙間を埋めるシール材104が設けられる。このように型枠103と基礎部分100の側面の間を埋めるシール材104の一例として、特許文献1では、発泡性分解性プラスチックからなる経時性硬化材料が提案されている。
Then, the construction method of the equipment installation surface in the equipment foundation which is demonstrated below was performed. FIG. 1 is an explanatory diagram of a construction method for a facility installation surface in a facility foundation that is generally performed conventionally. As shown in FIG. 1, a
そして、基礎部分100に基礎金物101および基礎用鉄筋102と、型枠103を設置した後、型枠103内に、例えばコンクリートやグラウト等の経時性硬化材料Aが充填される。この場合、経時性硬化材料Aは、基礎用鉄筋102を埋設させ、基礎金物101の高さまで充填され、基礎金物101の上面は、経時性硬化材料Aの上面に沿うように配置される。
Then, after the
しかしながら、基礎部分の側面は必ずしも平滑ではなく、複雑な形状である場合もある。また、長期間使用したコンクリート構造物等からなる基礎部分の側面には、凹凸が生じている場合もある。このため、シール材によって隙間を完全に塞ぐことは困難である。加えて、基礎部分の側面全周に渡ってシール材を設ける作業は手間がかかり、施工コストと作業時間を要してしまう。 However, the side surface of the base portion is not necessarily smooth and may have a complicated shape. Moreover, the unevenness | corrugation may arise in the side surface of the base part which consists of a concrete structure etc. which were used for a long period of time. For this reason, it is difficult to completely close the gap with the sealing material. In addition, the work of providing the sealing material over the entire circumference of the side surface of the foundation portion takes time and requires construction costs and work time.
一方、基礎部分の上面に流動性の低い経時性硬化材料を充填することにより、型枠と基礎部分側面との間における経時性硬化材料の漏出を妨げることも考えられる。しかし、流動性の低い経時性硬化材料を用いた場合、基礎金物や基礎用鉄筋が設置された状態で基礎部分の上面全体に経時性硬化材料を充填することが困難となり、充填むらが発生してしまう。また、経時性硬化材料の表面平坦性を確保することも困難である。特に、高炉のような大型設備の改修工事を行う場合にはこれらの問題が顕著となる。 On the other hand, it is also conceivable to prevent leakage of the time-hardening material between the mold and the side face of the base portion by filling the upper surface of the base portion with the time-hardening material having low fluidity. However, when a time-hardening material with low fluidity is used, it becomes difficult to fill the upper surface of the base part with the time-hardening material in a state where the base hardware and reinforcing bars are installed, resulting in uneven filling. End up. It is also difficult to ensure the surface flatness of the time-hardening material. In particular, when renovation of large equipment such as a blast furnace is performed, these problems become significant.
本発明の目的は、型枠と基礎部分側面との間における経時性硬化材料の漏出を容易に防止できる打設方法を提供することにある。 An object of the present invention is to provide a placing method that can easily prevent leakage of a time-hardening material between a mold and a side surface of a base portion.
本発明によれば、基礎部分の上面に経時性硬化材料を平坦に打設する方法であって、側面が型枠で囲まれた前記基礎部分の上面に第1の経時性硬化材料を打設し、前記第1の経時性硬化材料の上面に、前記第1の経時性硬化材料の硬化前に連続して、前記第1の経時性硬化材料よりスランプフローの高い第2の経時性硬化材料を打設する、経時性硬化材料の打設方法が提供される。かかる本発明にあっては、基礎部分の上面に先ずスランプフローの低い第1の経時性硬化材料を打設することによって、型枠と基礎部分側面との間における経時性硬化材料の漏出を回避する。そして、このように経時性硬化材料の漏出を回避した状態で、第1の経時性硬化材料よりスランプフローの高い第2の経時性硬化材料を打設することにより、基礎金物や基礎用鉄筋が設置された基礎部分の上面全体に経時性硬化材料をむらなく充填させる。 According to the present invention, there is provided a method for placing a time-hardening material flat on the upper surface of a base portion, wherein the first time-hardening material is placed on the upper surface of the base portion whose side surface is surrounded by a mold. And a second time curable material having a higher slump flow than the first time curable material continuously on the upper surface of the first time curable material before the first time curable material is cured. There is provided a method for casting a time-hardening material. In the present invention, by first placing the first time-hardening material having a low slump flow on the upper surface of the base portion, leakage of the time-hardening material between the mold and the side surface of the base portion is avoided. To do. And in the state which avoided the leakage of the time-hardening material in this way, by placing the second time-hardening material having a higher slump flow than the first time-hardening material, The entire upper surface of the installed base portion is uniformly filled with the time-hardening material.
この打設方法において、例えば、前記第1の経時性硬化材料は、スランプフロー(JIS A1150)が300mm〜750mmであり、ブリーディング量(JIS A1123)は0.3cm3/cm2以下であり、また、前記第2の経時性硬化材料のスランプフロー(JIS R5201)は250mm〜400mmであり、20℃におけるJ14漏斗(JSCE−F541)は10sec〜25secであり、ブリーディング量(JSCE−F522)は0.3cm3/cm2以下である。また、例えば、前記第1の経時性硬化材料はコンクリートであり、前記第2の経時性硬化材料はモルタルまたはグラウトである。 In this placing method, for example, the first time-hardening material has a slump flow (JIS A1150) of 300 mm to 750 mm, a bleeding amount (JIS A1123) of 0.3 cm 3 / cm 2 or less, The slump flow (JIS R5201) of the second aging curing material is 250 mm to 400 mm, the J14 funnel (JSCE-F541) at 20 ° C. is 10 sec to 25 sec, and the bleeding amount (JSCE-F522) is 0.00. 3 cm 3 / cm 2 or less. For example, the first time-hardening material is concrete, and the second time-hardening material is mortar or grout.
なお、本発明の打設方法は、例えば高炉の設備基礎を対象とする。 In addition, the placement method of the present invention is directed to, for example, the equipment foundation of a blast furnace.
本発明によれば、型枠と基礎部分側面との間における経時性硬化材料の漏出を容易に防止でき、シール材の施工作業を低減できる。また、高炉のような大型設備であっても、基礎部分の上面全体に経時性硬化材料をむらなく、かつ表面を平坦に充填できるようになる。 According to the present invention, it is possible to easily prevent leakage of the time-hardening material between the mold and the base portion side surface, and to reduce the construction work of the sealing material. Further, even in a large facility such as a blast furnace, the entire upper surface of the base portion can be uniformly filled with the time-hardening material and the surface can be filled flat.
以下、本発明の実施の形態の一例を、高炉の設備基礎1の改修に適用した場合について、図面を参照にして説明する。 Hereinafter, a case where an example of an embodiment of the present invention is applied to refurbishment of a blast furnace equipment foundation 1 will be described with reference to the drawings.
図2(a)〜(c)は、高炉の設備基礎1の改修手順の説明図であり、(a)は、基礎部分10の上方に、設備取合い金物11および基礎用鉄筋12を設置した状態を示し、(b)は、基礎部分10の上面に第1の経時性硬化材料B1を打設した状態を示し、(c)は、第1の経時性硬化材料B1の上面に第2の経時性硬化材料B2を打設した状態を示している。なお、本明細書及び図面において、実質的に同一の機能構成を有する構成要素については、同一の符号を付することにより重複説明を省略する。
2 (a) to 2 (c) are explanatory diagrams of the repair procedure of the blast furnace equipment foundation 1, and (a) is a state in which the equipment fitting 11 and the
基礎部分10は、例えば、長年使用された高炉における既設の設備基礎1、あるいは、既設の設備基礎の上部を切断したものである。例えば、高炉の改修工事では、既設の設備基礎上部を切断し、設備基礎1の高さを低くして炉容を下方に拡張させることが行われている。
The
先ず、図2(a)に示されるように、基礎部分10の上方において、設備取合い金物11および基礎用鉄筋12が所定の位置に配置される。
First, as shown in FIG. 2 (a), the equipment fitting 11 and the
また一方で、図2(a)に示されるように、基礎部分10の側面に沿って、型枠15が設置される。こうして、基礎部分10の上面が型枠15で囲まれ、型枠15の内方に、設備取合い金物11と基礎用鉄筋12が設置された状態となる。
On the other hand, as shown in FIG. 2A, the
次に、図2(b)に示されるように、型枠15の内方において、基礎部分10の上面に第1の経時性硬化材料B1が打設される。この場合、第1の経時性硬化材料B1は、設備取合い金物11(アンカー13)と基礎用鉄筋12の下部を埋める位置まで、型枠15の内方に充填される。これにより、基礎部分10の上面全体が第1の経時性硬化材料B1で覆われ、充填された第1の経時性硬化材料B1の上方に、設備取合い金物11と基礎用鉄筋12の上部が突出した状態となる。
Next, as shown in FIG. 2B, the first time-hardening material B <b> 1 is placed on the upper surface of the
ここで、第1の経時性硬化材料B1は、基礎部分10の上面において、設備取合い金物11(アンカー13)と基礎用鉄筋12の下部の周りに隙間なく充填されるように、十分な自己充填性を備えている必要があり、第1の経時性硬化材料B1には、ある水準以上の流動性が求められる。一方で、基礎部分10と型枠15の間に生じた空隙等から第1の経時性硬化材料B1が漏洩しないように、第1の経時性硬化材料B1には、一定水準以上の非漏洩性が求められる。そのため、第1の経時性硬化材料B1は、スランプフロー(JIS A1150)が300mm〜750mmであるコンクリートが望ましい。また、第1の経時性硬化材料B1の表面強度低下の防止と第2の経時性硬化材料との打ち継ぎ面の一体性を確保するために、ブリーディング量(JIS A1123)は0.3cm3/cm2以下であることが望ましい。
Here, the first time-hardening material B1 is sufficiently self-filled so as to be filled around the lower part of the equipment fitting 11 (anchor 13) and the
次に、図2(c)に示されるように、第1の経時性硬化材料B1の上面に、第2の経時性硬化材料B2が充填される。この場合、第2の経時性硬化材料B2は、基礎用鉄筋12が完全に埋設され、設備取合い金物11の上面が第2の経時性硬化材料B2の上面と同じ高さとなるまで充填される。これにより、充填された第2の経時性硬化材料B2の上面に設備取合い金物11の上面が露出し、設備取合い金物11の下部(アンカー13)と基礎用鉄筋12が、第1の経時性硬化材料B1および第2の経時性硬化材料B2の内部に埋め込まれた状態となる。
Next, as shown in FIG. 2C, the second time-curable material B2 is filled on the upper surface of the first time-curable material B1. In this case, the second aging hardening material B2 is filled until the
ここで、第2の経時性硬化材料B2は、先に充填された第1の経時性硬化材料B1の上面全体に広がって、設備取合い金物11の下部(アンカー13)と基礎用鉄筋12の周りに隙間なく充填されなければならない。また、充填された第2の経時性硬化材料B2の上面と設備取合い金物11の上面とが同一な水平面となるように、第2の経時性硬化材料B2には、優れた流動性が求められる。このため、第2の経時性硬化材料B2には、第1の経時性硬化材料B1よりも流動性の高いコンクリート等が用いられる。第2の経時性硬化材料B2は、例えばスランプフロー(JIS R5201)が250mm〜400mmであり、20℃におけるJ14漏斗(JSCE−F541)が10sec〜25secであり、ブリーディング量(JSCE−F522)は0.3cm3/cm2以下であるコンクリート等が望ましい。また、第2の経時性硬化材料B2には、流動性が高い例えばモルタルやグラウト等が用いられる。なお、このように第2の経時性硬化材料B2には、第1の経時性硬化材料B1よりも流動性の高いコンクリート等が用いられるが、第2の経時性硬化材料B2の下方には第1の経時性硬化材料B1が既に充填されているため、第2の経時性硬化材料B2については、基礎部分10と型枠15の間からの漏洩は問題とはならない。
Here, the second time-hardening material B2 spreads over the entire top surface of the first time-hardening material B1 filled in advance, and around the lower part (anchor 13) of the equipment fitting 11 and the reinforcing
そして、第1の経時性硬化材料B1および第2の経時性硬化材料B2が硬化すると、基礎部分10の側面に設置されていた型枠15が除去される。こうして、基礎用鉄筋12によって補強された上面に設備取合い金物11が設置された設備基礎1が得られる。これらの工程によれば、基礎部分10と型枠15の間から第1の経時性硬化材料B1が漏洩することなく、また、上面にむらなく第2の経時性硬化材料B2をさせた設備基礎1を得ることができる。
Then, when the first time curable material B1 and the second time curable material B2 are cured, the
また、基礎部分10の上面に打設する充填材料を流動性の低いもの(第1の経時性硬化材料B1)と流動性の高いもの(第2の経時性硬化材料B2)に分けることで、高価である流動性の高い硬化材料の使用量が削減される。このため、施工コストを低く抑えることができる。
Further, by dividing the filling material to be cast on the upper surface of the
以上、本発明の実施の形態の一例を説明したが、本発明は図示の形態に限定されない。当業者であれば、特許請求の範囲に記載された思想の範疇内において、各種の変更例または修正例に想到し得ることは明らかであり、それらについても当然に本発明の技術的範囲に属するものと了解される。 As mentioned above, although an example of embodiment of this invention was demonstrated, this invention is not limited to the form of illustration. It is obvious for those skilled in the art that various modifications or modifications can be conceived within the scope of the idea described in the claims, and these naturally belong to the technical scope of the present invention. It is understood.
上記実施の形態においては、本発明を高炉の設備基礎1の改修に適用した場合について説明したが、本発明はこれに限られるものではなく、例えば圧延機等の種々の大型装置の設備基礎において、基礎部分の上方に経時性硬化材料を打設する場合等にも同様に適用することができる。なお、前記第1の経時性硬化材料と第2の経時性硬化材料の流動性は、基礎部分の上面の面積や設備取合い金物および基礎用鉄筋の配置などに応じて適宜変更することが好ましい。また、施工面積が小さい場合や強度が要求されない場合などには、基礎用鉄筋12あるいは設備取合い金物11を省略することも考えられる。
In the said embodiment, although the case where this invention was applied to repair of the blast furnace equipment foundation 1 was demonstrated, this invention is not restricted to this, For example, in the equipment foundation of various large sized apparatuses, such as a rolling mill The present invention can also be applied to the case where a time-hardening material is placed above the base portion. In addition, it is preferable to change suitably the fluidity | liquidity of a said 1st aging hardening material and a 2nd aging hardening material according to the area of the upper surface of a base part, arrangement | positioning of an equipment fitting metal fitting, and a reinforcing bar for foundations. Further, when the construction area is small or when the strength is not required, it may be considered that the
また、打設材料として、主にコンクリートを挙げて説明したが、本発明においては異なる流動性を有する経時性硬化材料を、下層に流動性が比較的低い経時性硬化材料を充填し、上層に流動性が比較的高い経時性硬化材料を充填すれば足り、コンクリートに限定されるものではない。例えば、モルタルといったコンクリートより流動性の高い経時性硬化材料を用いる場合にも本発明は適用される。 In addition, although concrete has been mainly described as the casting material, in the present invention, a time-hardening material having different fluidity is filled with a time-hardening material having a relatively low fluidity in the lower layer, and the upper layer is filled. It is sufficient to fill a time-hardening material having a relatively high fluidity, and the material is not limited to concrete. For example, the present invention is also applied to the case of using a time-hardening material having higher fluidity than concrete such as mortar.
本発明者らは、経時性硬化材料の流動性の違いにより、その充填性にどれほどの違いが発生し、また、異なる流動性を持つ経時性硬化材料のそれぞれがどの程度の充填性を有するのかについて調べる流動試験を行った。以下に図面を参照して実施例を説明する。 The inventors have determined how much the filling property varies due to the difference in fluidity of the time-hardening materials, and how much filling property each of the time-hardening materials having different fluidity has. A flow test was conducted to investigate the above. Embodiments will be described below with reference to the drawings.
図3(a)、(b)は、流動試験を行った試験体20の平面図および断面図である。試験体20の内部は空洞になっており、試験体20の天井面には、3箇所に試験体20の上面から垂直に支持される堰22が設けられている。各堰22は、いずれも試験体20の高さより短い板形状となっており、各堰22の下方において、試験体20の内部が連通した状態になっている。試験体20の上面には2つの打設口21a、21bが設けられており、これら打設口21a、21bのうち、試験体20の端部近傍に設置された一方の打設口21aから経時性硬化材料を打設した。また、他方の打設口21bは予備とした。試験体20は、図3(b)に示すように、基礎コンクリート構造体25の上に支持されており、試験体20の大きさは、幅1.8m、長さ7.0m、深さ(高さ)0.4mであり、3箇所の堰22は等間隔に配置されている。
3A and 3B are a plan view and a cross-sectional view of the
経時性硬化材料は、試験例1として高流動モルタル、試験例2として高流動コンクリート、試験例3として高流動コンクリートおよび超高流動モルタルを用いた。試験例1および試験例2では、一種類の経時性硬化材料によって、試験体20の深さ0.4mまで充填を行った。試験例3では、高流動コンクリートを深さ25cm、超高流動モルタルを深さ15cmの割合で充填を行った。
As the time-hardening material, high fluid mortar was used as Test Example 1, high fluid concrete as Test Example 2, high fluid concrete and ultra high fluid mortar as Test Example 3. In Test Example 1 and Test Example 2, the
図4〜6は、試験例1〜3の時間経過と充填状況の関係を示す説明図である。経過時間ごとの充填度合いを図中の試験体20内部に線グラフとして示した。図4に示すように、試験例1の場合、打設口21aから試験体20中央部付近の堰22の近傍までは、ほぼ均一に高流動モルタルの充填が行われたが、それよりも遠い部分については十分に充填がされず、途中で経時性硬化材料(高流動モルタル)が硬化してしまった(図4中の21分のグラフ線参照)。また、図5に示すように、高流動コンクリートを使用した試験例2についても、試験例1と同様に十分な経時性硬化材料の充填が行われない部分が存在した。
4-6 is explanatory drawing which shows the relationship between the time passage of the test examples 1-3, and a filling condition. The degree of filling for each elapsed time is shown as a line graph inside the
一方、図6に示すように、試験例3として、先に高さ25cm程度まで高流動コンクリートを充填させ、その上方空間に超高流動モルタルを充填させた場合、試験体20内部全体に超高流動モルタルをほぼ均一に充填させることができた。 On the other hand, as shown in FIG. 6, as Test Example 3, when the high-fluidity concrete was first filled to a height of about 25 cm and the upper space was filled with ultrahigh-fluidity mortar, The fluid mortar could be filled almost uniformly.
本発明は、例えば、高炉の設備基礎や種々の大型装置の設備基礎の改修などにおける経時性硬化材料の打設方法に適用できる。 The present invention can be applied to a method for placing a time-hardening material in, for example, refurbishing the equipment foundation of a blast furnace or the equipment foundation of various large apparatuses.
1…設備基礎
10…基礎部分
11…設備取合い金物
12…基礎用鉄筋
13…アンカー
15…型枠
16…境界面
20…試験体
21…打設口
22…堰
25…基礎コンクリート構造体
100…基礎部分
101…基礎金物
102…基礎用鉄筋
103…型枠
104…シール材
DESCRIPTION OF SYMBOLS 1 ...
Claims (4)
側面が型枠で囲まれた前記基礎部分の上面に第1の経時性硬化材料を打設し、
前記第1の経時性硬化材料の上面に、前記第1の経時性硬化材料の硬化前に連続して、前記第1の経時性硬化材料よりスランプフローの高い第2の経時性硬化材料を打設する、経時性硬化材料の打設方法。 A method of placing a time-hardening material flat on the upper surface of a base part,
Placing a first time-hardening material on the upper surface of the foundation part whose side is surrounded by a formwork;
A second time curable material having a higher slump flow than the first time curable material is applied to the upper surface of the first time curable material continuously before the first time curable material is cured. A method for placing a time-curable curable material.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP2008285852A JP5544704B2 (en) | 2008-11-06 | 2008-11-06 | Method for placing age-hardening material |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP2008285852A JP5544704B2 (en) | 2008-11-06 | 2008-11-06 | Method for placing age-hardening material |
Publications (2)
Publication Number | Publication Date |
---|---|
JP2010112081A true JP2010112081A (en) | 2010-05-20 |
JP5544704B2 JP5544704B2 (en) | 2014-07-09 |
Family
ID=42300839
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
JP2008285852A Active JP5544704B2 (en) | 2008-11-06 | 2008-11-06 | Method for placing age-hardening material |
Country Status (1)
Country | Link |
---|---|
JP (1) | JP5544704B2 (en) |
Citations (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JPH11293933A (en) * | 1998-04-07 | 1999-10-26 | Toda Constr Co Ltd | Concrete filling method under base plate |
JP2002037651A (en) * | 2000-07-28 | 2002-02-06 | Denki Kagaku Kogyo Kk | Admixture and cement composition for heavy weight grout mortar and heavy weight grout mortar |
JP2009228357A (en) * | 2008-03-25 | 2009-10-08 | Kumagai Gumi Co Ltd | Grouting tool |
JP2010013828A (en) * | 2008-07-02 | 2010-01-21 | Kumagai Gumi Co Ltd | Method of manufacturing lower part of base isolating foundation |
-
2008
- 2008-11-06 JP JP2008285852A patent/JP5544704B2/en active Active
Patent Citations (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JPH11293933A (en) * | 1998-04-07 | 1999-10-26 | Toda Constr Co Ltd | Concrete filling method under base plate |
JP2002037651A (en) * | 2000-07-28 | 2002-02-06 | Denki Kagaku Kogyo Kk | Admixture and cement composition for heavy weight grout mortar and heavy weight grout mortar |
JP2009228357A (en) * | 2008-03-25 | 2009-10-08 | Kumagai Gumi Co Ltd | Grouting tool |
JP2010013828A (en) * | 2008-07-02 | 2010-01-21 | Kumagai Gumi Co Ltd | Method of manufacturing lower part of base isolating foundation |
Also Published As
Publication number | Publication date |
---|---|
JP5544704B2 (en) | 2014-07-09 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
JP5576207B2 (en) | Installation foundation and its construction method | |
US8348555B2 (en) | Formwork element for bounding a trench wall section, formwork part and method for producing a trench wall in the ground | |
KR20140047118A (en) | Foundation system for bridges | |
DK2488338T3 (en) | Process for the preparation of tower segment-concrete finished parts of a wind power installation tower and formwork unit for production of concrete finished parts | |
KR20150057581A (en) | Level adjusting apparatus for precast slab and precast slab construction method using therewith | |
CN109812621B (en) | Concrete encapsulated pipeline structure and construction method thereof | |
JP2017214722A (en) | Construction method of base structure, and base structure | |
JP5544704B2 (en) | Method for placing age-hardening material | |
CN207959249U (en) | Cushion cap and its foundation pit cushion construction structure | |
JP5961470B2 (en) | Concrete jointing method | |
CN105003088A (en) | Construction method for omitting embedded parts during steel structure construction | |
JP2019002140A (en) | Steel form for constructing base mortar and construction method of base mortar using the same | |
JP2014173368A (en) | Construction method of foundation structure | |
CN209960000U (en) | Concrete-encapsulated pipeline structure | |
JP2012241351A (en) | Base isolation structure and construction method of the same | |
JP2017025696A (en) | Dam corridor construction method | |
JP2017025607A (en) | Dam corridor construction method, corridor cell of dam corridor, and formwork used for manufacturing corridor cell | |
JP2016037768A (en) | Repair method for existing concrete, construction method for new installation foundation | |
JP2002213194A (en) | Method for reinforcing/repairing lining concrete | |
KR101512031B1 (en) | Method for reinforcing ground using grouting | |
KR100379187B1 (en) | delay-joint method of constructuction for underground structure | |
CN221030721U (en) | Antiseep structure for junction of new and old building | |
JP2013011160A (en) | Tunnel structure and its construction method | |
JP6323773B2 (en) | Anchor member fixing method for existing concrete structure | |
JP5470195B2 (en) | How to install the structure |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
A621 | Written request for application examination |
Free format text: JAPANESE INTERMEDIATE CODE: A621 Effective date: 20110215 |
|
A977 | Report on retrieval |
Free format text: JAPANESE INTERMEDIATE CODE: A971007 Effective date: 20120926 |
|
A131 | Notification of reasons for refusal |
Free format text: JAPANESE INTERMEDIATE CODE: A131 Effective date: 20121002 |
|
A521 | Written amendment |
Free format text: JAPANESE INTERMEDIATE CODE: A523 Effective date: 20121128 |
|
A131 | Notification of reasons for refusal |
Free format text: JAPANESE INTERMEDIATE CODE: A131 Effective date: 20130709 |
|
A521 | Written amendment |
Free format text: JAPANESE INTERMEDIATE CODE: A523 Effective date: 20130906 |
|
TRDD | Decision of grant or rejection written | ||
A01 | Written decision to grant a patent or to grant a registration (utility model) |
Free format text: JAPANESE INTERMEDIATE CODE: A01 Effective date: 20140415 |
|
A61 | First payment of annual fees (during grant procedure) |
Free format text: JAPANESE INTERMEDIATE CODE: A61 Effective date: 20140428 |
|
R151 | Written notification of patent or utility model registration |
Ref document number: 5544704 Country of ref document: JP Free format text: JAPANESE INTERMEDIATE CODE: R151 |
|
S533 | Written request for registration of change of name |
Free format text: JAPANESE INTERMEDIATE CODE: R313533 |
|
R350 | Written notification of registration of transfer |
Free format text: JAPANESE INTERMEDIATE CODE: R350 |