JP2014173368A - Construction method of foundation structure - Google Patents
Construction method of foundation structure Download PDFInfo
- Publication number
- JP2014173368A JP2014173368A JP2013048633A JP2013048633A JP2014173368A JP 2014173368 A JP2014173368 A JP 2014173368A JP 2013048633 A JP2013048633 A JP 2013048633A JP 2013048633 A JP2013048633 A JP 2013048633A JP 2014173368 A JP2014173368 A JP 2014173368A
- Authority
- JP
- Japan
- Prior art keywords
- insulating material
- heat insulating
- concrete layer
- foundation
- concrete
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Granted
Links
Images
Landscapes
- Building Environments (AREA)
Abstract
Description
本発明は、基礎構造の施工方法に関する。 The present invention relates to a construction method for a foundation structure.
建物の基礎構造としては断熱材を敷設した構造が知られている。断熱材は居住部分の床下以外、例えば玄関などの土間部分にも敷設されることもある(例えば特許文献1参照)。
図10は、従来の建物の基礎構造の概略構成を示す断面図である。図10に示すように、基礎構造100には、基礎101間に対して下から順に防湿用コンクリート102、断熱材103、土間コンクリート104が敷設されている。また、土間コンクリート104と基礎101との間には土間コンクリート104を囲むように断熱材105が配置されている。
ここで、基礎101と防湿用コンクリート102との間に隙間があると蟻が床下内に侵入してしまうので、防蟻用のシール剤でその隙間を埋める防蟻処理が施されている。
As a basic structure of a building, a structure in which a heat insulating material is laid is known. The heat insulating material may be laid on a soil portion such as an entrance other than under the floor of the living portion (see, for example, Patent Document 1).
FIG. 10 is a cross-sectional view showing a schematic configuration of a conventional building foundation structure. As shown in FIG. 10, moisture-
Here, if there is a gap between the
ところで、防蟻品質の確実性を高めるためには、防蟻処理を防湿用コンクリート102の硬化後に行うことが望まれている。このため、防湿用コンクリート102を硬化させてから防蟻処理を施し、防湿用コンクリート102上に断熱材103を敷設した後に土間コンクリート104を打設することになる。このため、防湿用コンクリート102と土間コンクリート104とがそれぞれ硬化する時間が必要となり、作業時間が長期化してしまうのが実状であった。
このため、本発明の課題は、防蟻処理を施す場合であっても作業時間の短縮化を図ることである。
By the way, in order to increase the certainty of the ant-proof quality, it is desired to perform the ant-proofing treatment after the moisture-
For this reason, the subject of this invention is aiming at shortening of working time, even when it is a case where an ant protection process is performed.
請求項1記載の発明に係る基礎構造1の施工方法は、例えば図1,図4に示すように、
基礎2の側面に対して密着するように第一コンクリート層3を打設する第一コンクリート打設工程と、
前記基礎2の側面に対して間隔Hが空くように、前記第一コンクリート層3の硬化前に当該第一コンクリート層3上に断熱材4を敷設する断熱材敷設工程と、
前記断熱材敷設工程の前若しくは前記断熱材敷設工程の後に、前記間隔Hを保持するための型枠10を設置する型枠設置工程と、
前記断熱材4上に重なるように前記型枠10内に第二コンクリート層5を打設する第二コンクリート打設工程と、
前記第一コンクリート層3及び前記第二コンクリート層5を硬化させる硬化工程と、
前記型枠10を取り外して、前記基礎2と前記第一コンクリート層3との境界に防蟻シール剤6を塗布する防蟻工程と、
前記間隔Hに対して副断熱材7を設置する副断熱材設置工程と、
を含むことを特徴としている。
As shown in FIGS. 1 and 4, for example, the construction method of the
A first concrete placing step for placing the
A heat insulating material laying step of laying a
Before the heat insulating material laying step or after the heat insulating material laying step, a mold installing step for installing the
A second concrete placing step for placing the
A curing step of curing the
Removing the
A sub-insulator installation step of installing the
It is characterized by including.
請求項1記載の発明によれば、基礎2と第一コンクリート層3との境界が前記間隔Hによって露出されているので、第一コンクリート層3及び第二コンクリート層5の硬化後に防蟻工程を施すことができる。
そして、第一コンクリート層3の硬化と第二コンクリート層5の硬化が同時に行われているために作業時間の短縮化を図ることができる。
According to invention of
And since hardening of the
請求項2記載の発明は、請求項1に記載の基礎構造1の施工方法において、例えば図1に示すように、
前記副断熱材7は、前記間隔Hよりも幅が小さい第一副断熱材71と、第二副断熱材72とを備え、
前記第一副断熱材71は、断熱材4の端面に当接し、
前記第二副断熱材72は、前記第一副断熱材71の上に重ねられているとともに、前記基礎2の側面に当接していることを特徴としている。
Invention of
The sub
Said 1st sub
The second sub
断熱性の観点から考えると、副断熱材7が断熱材4の端面及び基礎2の側面に接して、基礎2の内側に連続した断熱材4,7のラインが形成されていることが好ましい。しかしながら副断熱材7が単体であると前記間隔H内に嵌合させなければ断熱材4の端面及び基礎2の側面の両者に当接させることは困難である。つまり、単体の副断熱材7に対してはある程度の精度が要求されることになる。
しかしながら、請求項2記載の発明のように、断熱材4の端面に当接する第一副断熱材71と、第一副断熱材71の上に重ねられているとともに基礎2の側面に当接する第二副断熱材72とを副断熱材7が備えていると、断熱性を確保しつつも副断熱材7の形状の自由度を高めることができる。
From the viewpoint of heat insulation, it is preferable that the sub
However, as in the invention described in
請求項3記載の発明は、請求項1記載の基礎構造1の施工方法において、例えば図9に示すように、
前記副断熱材7Aが前記型枠として用いられることを特徴としている。
The invention according to
The sub heat insulating material 7A is used as the mold.
請求項3記載の発明によれば、副断熱材7Aが型枠として用いられているので、型枠専用の部材が不要となり、施工時に用いられる部材を削減することができる。
According to the invention described in
請求項4記載の発明は、請求項1〜3のいずれか一項に記載の基礎構造1の施工方法において、例えば図1に示すように、
前記第二コンクリート層5上にモルタル8を敷設するモルタル敷設工程をさらに含むことを特徴としている。
Invention of
The method further includes a mortar laying step of laying the
請求項4記載の発明によれば、第二コンクリート層5上にモルタル8が敷設されるので、モルタル8を介してタイル9を設置することができ、見栄えをよくすることが可能である。
According to invention of
請求項5記載の発明は、請求項4記載の基礎構造1の施工方法において、例えば図1に示すように、
前記モルタル8は、前記第二コンクリート層5と前記副断熱材7との隙間S1を埋めていることを特徴としている。
Invention of
The
請求項5記載の発明によれば、第二コンクリート層5と副断熱材7との隙間S1をモルタル8が埋めているので、副断熱材7の位置ズレを防止することができるとともに断熱性も高めることができる。
According to the invention described in
本発明によれば、防蟻処理を施す場合であっても作業時間の短縮化を図ることができる。 According to the present invention, the working time can be shortened even when the ant protection treatment is performed.
以下、図面を参照して本発明の実施の形態について説明する。図1は本実施形態に係る建物の基礎構造1を示す断面図である。図1に示すように、基礎構造1には、地中に埋設された基礎2と、基礎2の立ち上がり部21の側面に対して密着するように地面に設けられた第一コンクリート層3とが設けられている。第一コンクリート層3は防湿土間コンクリートとして機能する。
また、第一コンクリート層3上には、基礎2の立ち上がり部21の側面に対して間隔Hを空けるように、例えば防蟻断熱材などの断熱材4が敷設されている。断熱材4上には、当該断熱材4とともに間隔Hを形成するように第二コンクリート層5が重ねて配置されている。第二コンクリート層5は下地土間コンクリートとして機能する。
Embodiments of the present invention will be described below with reference to the drawings. FIG. 1 is a sectional view showing a
Further, on the
間隔H内においては、立ち上がり部21と第一コンクリート層3との境界に塗布された防蟻シール剤6と、例えば防蟻断熱材などの副断熱材7とが設けられている。
副断熱材7は、間隔Hよりも幅が小さい第一副断熱材71と、第二副断熱材72とを備えている。第一副断熱材71は断熱材4の端面に当接している。第一副断熱材71と基礎2の立ち上がり部21との間には隙間S1が設けられていて、この隙間S1内に防蟻シール剤6が配置されている。
第二副断熱材72は、第一副断熱材71の上に重ねられているとともに立ち上がり部21の側面に当接している。このため、第一副断熱材71と第二コンクリート層5との間には隙間S2が形成されることになる。また、第二副断熱材72の上面と立ち上がり部21の上面とは面一となっている。
Within the interval H, an ant-
The sub
The second sub
そして、隙間S2を埋めるように第二コンクリート層5の上面及び第二副断熱材72の側面には例えばバサモルタルなどのモルタル8が重ねられている。このモルタル8に対してはタイル9が貼付されている。
Then, a
次に、基礎構造1の施工方法について説明する。図2〜図8は基礎構造1の施工方法の各工程を示す断面図である。
まず、基礎2の設置後においては、図2に示すように、基礎2の立ち上がり部21の側面に対して密着するように第一コンクリート層3を打設する(第一コンクリート打設工程)。
Next, the construction method of the
First, after the
その後、図3に示すように、基礎2の立ち上がり部21の側面に対して間隔Hが空くように、第一コンクリート層3の硬化前、つまり湿潤状態である場合に当該第一コンクリート層3上に断熱材4を敷設する(断熱材敷設工程)。
そして、図4に示すように、断熱材敷設工程の後に間隔Hを保持するための型枠10を設置する(型枠設置工程)。型枠10には、コンクリートと直接接する堰板11と、当該堰板11を所定の位置に固定する支保工12とが設けられている。堰板11が断熱材4の端面に当接した状態で垂直となるように支保工12で堰板11の位置を固定する。なお、図示はしていないが、第二コンクリート層5を打設する領域が型枠10により囲まれている。
Thereafter, as shown in FIG. 3, the first
And as shown in FIG. 4, the
次いで、図5に示すように、断熱材4上に重なるように型枠10内に第二コンクリート層5を打設する(第二コンクリート打設工程)。
このままの状態で所定時間待機して、第一コンクリート層3及び第二コンクリート層5を同時に硬化させる(硬化工程)。
Next, as shown in FIG. 5, the second
In this state, the first
硬化後においては、図6に示すように、型枠10を取り外して、基礎2の立ち上がり部21と第一コンクリート層3との境界に防蟻シール剤6を塗布する(防蟻工程)。境界に隙間がある場合はその隙間を埋めるように防蟻シール剤6を塗布する。
そして、図7に示すように、間隔Hに対して副断熱材7を設置する(副断熱材設置工程)。このとき、断熱材4の端面に当接するように第一副断熱材71を第一コンクリート層3上に載置し、隙間S1を形成する。次いで、第一副断熱材71の上に第二副断熱材72を重ねて、基礎2の立ち上がり部21の側面に当接させる。
After the curing, as shown in FIG. 6, the
Then, as shown in FIG. 7, the auxiliary
副断熱材7の設置が完了すると、図8に示すように、第二コンクリート層5上にモルタル8を敷設する(モルタル敷設工程)。このとき、第二コンクリート層5と第二副断熱材72との隙間S2をモルタル8で埋めるとともに、第二副断熱材72の側面もモルタル8で覆う。
そして、モルタル8上にタイル9を貼付することで、図1に示した基礎構造1が形成される。
When the installation of the auxiliary
And the
以上のように、基礎2と第一コンクリート層3との境界が間隔Hによって露出されているので、第一コンクリート層3及び第二コンクリート層5の硬化後に防蟻工程を施すことができる。
そして、第一コンクリート層3の硬化と第二コンクリート層5の硬化が同時に行われているために作業時間の短縮化を図ることができる。
As described above, since the boundary between the
And since hardening of the 1st
また、断熱材4の端面に当接する第一副断熱材71と、第一副断熱材71の上に重ねられているとともに基礎2の立ち上がり部21の側面に当接する第二副断熱材72とを副断熱材7が備えているので、断熱性を確保しつつも副断熱材7の形状の自由度を高めることができる。
Moreover, the 1st sub
また、第二コンクリート層5上にモルタル8が敷設されるので、モルタル8を介してタイル9を設置することができ、見栄えをよくすることが可能である。これに加えて防汚性、防水性、保温性等の効果を持つ種々のタイルを選択して適用すれば住環境の一層の向上が可能となる。
また、第二コンクリート層5と副断熱材7との隙間S2をモルタル8が埋めているので、副断熱材7の位置ズレを防止することができるとともに断熱性も高めることができる。
Moreover, since the
In addition, since the
なお、本発明は上記実施形態に限らず適宜変更可能である。以下、変形例について説明するが、上記実施形態と同一の部分においては同一の符号を付しその説明を省略する。 Note that the present invention is not limited to the above embodiment, and can be modified as appropriate. Hereinafter, although a modification is demonstrated, the same code | symbol is attached | subjected in the part same as the said embodiment, and the description is abbreviate | omitted.
例えば、上記実施形態においては、型枠設置工程が断熱材敷設工程の後に行った場合を例示して説明したが、型枠設置工程は断熱材敷設工程の前に行うことも可能である。
また、上記実施形態では、堰板11と支保工12とを備える型枠10を用いた型枠設置工程を例示して説明したが、例えば図9に示すように、型枠10の代わりに副断熱材7Aを用いることも可能である。この場合、第一コンクリート層3及び第二コンクリート層5が硬化した後に副断熱材7Aを一時的に取り外して、基礎2と第一コンクリート層3との境界を露出させてから当該境界に防蟻シール剤6を塗布する。その後、再度副断熱材7Aを間隔H内に配置する。
このように、副断熱材7Aが型枠として用いられていれば、型枠専用の部材が不要となり、施工時に用いられる部材を削減することができる。
For example, in the above-described embodiment, the case where the mold installation process is performed after the heat insulating material laying process has been described as an example. However, the mold frame installation process can be performed before the heat insulating material laying process.
Moreover, in the said embodiment, although the mold installation process using the
In this way, if the auxiliary heat insulating material 7A is used as a mold, a member dedicated to the mold becomes unnecessary, and the number of members used during construction can be reduced.
1 基礎構造
2 基礎
3 第一コンクリート層
4 断熱材
5 第二コンクリート層
6 防蟻シール剤
7,7A 副断熱材
8 モルタル
9 タイル
10 型枠
71 第一副断熱材
72 第二副断熱材
H 間隔
S1 隙間
S2 隙間
DESCRIPTION OF
Claims (5)
前記基礎の側面に対して間隔が空くように、前記第一コンクリート層の硬化前に当該第一コンクリート層上に断熱材を敷設する断熱材敷設工程と、
前記断熱材敷設工程の前若しくは前記断熱材敷設工程の後に、前記間隔を保持するための型枠を設置する型枠設置工程と、
前記断熱材上に重なるように前記型枠内に第二コンクリート層を打設する第二コンクリート打設工程と、
前記第一コンクリート層及び前記第二コンクリート層を硬化させる硬化工程と、
前記型枠を取り外して、前記基礎と前記第一コンクリート層との境界に防蟻シール剤を塗布する防蟻工程と、
前記間隔に対して副断熱材を設置する副断熱材設置工程と、
を含むことを特徴とする基礎構造の施工方法。 A first concrete placing process for placing the first concrete layer so as to adhere to the side surface of the foundation;
A heat insulating material laying step of laying a heat insulating material on the first concrete layer before the first concrete layer is hardened so as to be spaced from the side surface of the foundation;
Before the heat insulating material laying step or after the heat insulating material laying step, a mold installing step for installing a mold for maintaining the spacing;
A second concrete placing step for placing a second concrete layer in the mold so as to overlap the heat insulating material;
A curing step of curing the first concrete layer and the second concrete layer;
Removing the mold and applying an ant-proof sealant to the boundary between the foundation and the first concrete layer;
A sub-insulation material installation step of installing a sub-insulation material with respect to the spacing;
A method of constructing a foundation structure characterized by including:
前記副断熱材は、前記間隔よりも幅が小さい第一副断熱材と、第二副断熱材とを備え、
前記第一副断熱材は、断熱材の端面に当接し、
前記第二副断熱材は、前記第一副断熱材の上に重ねられているとともに、前記基礎の側面に当接していることを特徴とする基礎構造の施工方法。 In the construction method of the foundation structure according to claim 1,
The sub heat insulating material includes a first sub heat insulating material having a width smaller than the interval, and a second sub heat insulating material,
The first auxiliary heat insulating material is in contact with the end face of the heat insulating material,
The construction method of a foundation structure, wherein the second sub heat insulating material is overlaid on the first sub heat insulating material and is in contact with a side surface of the foundation.
前記副断熱材が前記型枠として用いられることを特徴とする基礎構造の施工方法。 In the construction method of the foundation structure according to claim 1,
A construction method of a foundation structure, wherein the sub-insulating material is used as the formwork.
前記第二コンクリート層上にモルタルを敷設するモルタル敷設工程をさらに含むことを特徴とする基礎構造の施工方法。 In the construction method of the foundation structure as described in any one of Claims 1-3,
A construction method for a foundation structure, further comprising a mortar laying step of laying mortar on the second concrete layer.
前記モルタルは、前記第二コンクリート層と前記副断熱材との隙間を埋めていることを特徴とする基礎構造の施工方法。 In the construction method of the foundation structure according to claim 4,
The construction method of a foundation structure, wherein the mortar fills a gap between the second concrete layer and the auxiliary heat insulating material.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP2013048633A JP5893579B2 (en) | 2013-03-12 | 2013-03-12 | Construction method of foundation structure |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP2013048633A JP5893579B2 (en) | 2013-03-12 | 2013-03-12 | Construction method of foundation structure |
Publications (2)
Publication Number | Publication Date |
---|---|
JP2014173368A true JP2014173368A (en) | 2014-09-22 |
JP5893579B2 JP5893579B2 (en) | 2016-03-23 |
Family
ID=51694893
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
JP2013048633A Active JP5893579B2 (en) | 2013-03-12 | 2013-03-12 | Construction method of foundation structure |
Country Status (1)
Country | Link |
---|---|
JP (1) | JP5893579B2 (en) |
Cited By (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JP2016166489A (en) * | 2015-03-10 | 2016-09-15 | フクビ化学工業株式会社 | Floor structure of building |
JP2018003267A (en) * | 2016-06-27 | 2018-01-11 | 積水ハウス株式会社 | Termite prevention structure for building foundation part and method for constructing the same |
CN108571162A (en) * | 2017-03-10 | 2018-09-25 | 天津市华利杰科技发展有限公司 | A kind of compound heat preservation die plate used for building exterior wall and its construction method |
Citations (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JP2002294889A (en) * | 2001-03-27 | 2002-10-09 | Kanegafuchi Chem Ind Co Ltd | Termite prevention structure of building and the building |
US20020174595A1 (en) * | 1998-07-02 | 2002-11-28 | Tom Hoshall | Subsurface pesticide injection and fluid extraction system |
JP2005290764A (en) * | 2004-03-31 | 2005-10-20 | Panahome Corp | Termite-proof structure and termite-proofing method for underfloor space |
JP2012246720A (en) * | 2011-05-31 | 2012-12-13 | Misawa Homes Co Ltd | Heat insulation structure of wooden building |
-
2013
- 2013-03-12 JP JP2013048633A patent/JP5893579B2/en active Active
Patent Citations (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
US20020174595A1 (en) * | 1998-07-02 | 2002-11-28 | Tom Hoshall | Subsurface pesticide injection and fluid extraction system |
JP2002294889A (en) * | 2001-03-27 | 2002-10-09 | Kanegafuchi Chem Ind Co Ltd | Termite prevention structure of building and the building |
JP2005290764A (en) * | 2004-03-31 | 2005-10-20 | Panahome Corp | Termite-proof structure and termite-proofing method for underfloor space |
JP2012246720A (en) * | 2011-05-31 | 2012-12-13 | Misawa Homes Co Ltd | Heat insulation structure of wooden building |
Cited By (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JP2016166489A (en) * | 2015-03-10 | 2016-09-15 | フクビ化学工業株式会社 | Floor structure of building |
JP2018003267A (en) * | 2016-06-27 | 2018-01-11 | 積水ハウス株式会社 | Termite prevention structure for building foundation part and method for constructing the same |
CN108571162A (en) * | 2017-03-10 | 2018-09-25 | 天津市华利杰科技发展有限公司 | A kind of compound heat preservation die plate used for building exterior wall and its construction method |
Also Published As
Publication number | Publication date |
---|---|
JP5893579B2 (en) | 2016-03-23 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
JP5576207B2 (en) | Installation foundation and its construction method | |
CN103669402A (en) | Pile and wall integrated structure combining outer wall of basement body and guard pile | |
KR100787178B1 (en) | Light weight steel frame foundation flooring material and method for construction | |
JP5893579B2 (en) | Construction method of foundation structure | |
JP5179344B2 (en) | Building basic structure and building foundation | |
JP2011074754A (en) | Method for manufacturing floor slab of steel-concrete composite using precast concrete panel | |
JP5835390B2 (en) | Foundation structure | |
KR20110124476A (en) | Assembly trench and trench structure using the same | |
KR101928041B1 (en) | Construction method of building structure using exterior insulation material wall module | |
JP6933916B2 (en) | Embankment raising structure | |
JP2015078495A (en) | Construction method of reinforcement structure | |
JP5875951B2 (en) | Girder and floor slab joint structure and method | |
KR101826094B1 (en) | Construction method for transfer mat and transfer mat using the same | |
JP6632792B2 (en) | Ground improvement method | |
KR102594640B1 (en) | An Extendable Bracket for Foundation of a House and a Foundation Construction Method Using the Same | |
KR20170000255A (en) | Construction method for bathroom and Bathroom using the same | |
JP2010189972A5 (en) | ||
KR101481810B1 (en) | Method for construction of constinuous overlap pile wall using the double casing for construction of constinuous overlap pile wall | |
KR20120091934A (en) | Method for connecting between precast concrete columns in construction layer using headed reinforcement | |
JP2010240905A (en) | Method for manufacturing ribbed cement panel, ribbed cement panel, and method for manufacturing structure | |
KR102108862B1 (en) | Corner-waterproofing apparatus for concrete structure | |
JPH0995955A (en) | External wall construction method of underground structure, external wall construction, waterproof panel for external wall of underground structure, and manufacture thereof | |
KR102279927B1 (en) | Construction method for underground culvert | |
JP7201453B2 (en) | building foundation structure | |
JP2007284980A (en) | Precast concrete slab with step height strengthened in step height part |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
A621 | Written request for application examination |
Free format text: JAPANESE INTERMEDIATE CODE: A621 Effective date: 20140917 |
|
A977 | Report on retrieval |
Free format text: JAPANESE INTERMEDIATE CODE: A971007 Effective date: 20150710 |
|
A131 | Notification of reasons for refusal |
Free format text: JAPANESE INTERMEDIATE CODE: A131 Effective date: 20150721 |
|
A521 | Written amendment |
Free format text: JAPANESE INTERMEDIATE CODE: A523 Effective date: 20150914 |
|
TRDD | Decision of grant or rejection written | ||
A01 | Written decision to grant a patent or to grant a registration (utility model) |
Free format text: JAPANESE INTERMEDIATE CODE: A01 Effective date: 20160223 |
|
A61 | First payment of annual fees (during grant procedure) |
Free format text: JAPANESE INTERMEDIATE CODE: A61 Effective date: 20160224 |
|
R150 | Certificate of patent or registration of utility model |
Ref document number: 5893579 Country of ref document: JP Free format text: JAPANESE INTERMEDIATE CODE: R150 |