JP2010001634A - Concrete foundation laying device and foundation laying method for equipment for substation for power distribution - Google Patents

Concrete foundation laying device and foundation laying method for equipment for substation for power distribution Download PDF

Info

Publication number
JP2010001634A
JP2010001634A JP2008160419A JP2008160419A JP2010001634A JP 2010001634 A JP2010001634 A JP 2010001634A JP 2008160419 A JP2008160419 A JP 2008160419A JP 2008160419 A JP2008160419 A JP 2008160419A JP 2010001634 A JP2010001634 A JP 2010001634A
Authority
JP
Japan
Prior art keywords
mortar
precast concrete
hole
laying
sealing material
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
JP2008160419A
Other languages
Japanese (ja)
Other versions
JP5110652B2 (en
Inventor
Sadaaki Nakamura
定明 中村
Takashi Kobayashi
崇 小林
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
PC Bridge Co Ltd
Original Assignee
PC Bridge Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by PC Bridge Co Ltd filed Critical PC Bridge Co Ltd
Priority to JP2008160419A priority Critical patent/JP5110652B2/en
Publication of JP2010001634A publication Critical patent/JP2010001634A/en
Application granted granted Critical
Publication of JP5110652B2 publication Critical patent/JP5110652B2/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Foundations (AREA)

Abstract

<P>PROBLEM TO BE SOLVED: To provide a device and method for laying a foundation of equipment for a substation for power distribution, such as a transformer, which can shorten its construction period so as to shorten a power supply stop period for the reinstallation of the transformer and the like, by using a precast concrete slab for the foundation of the equipment for the substation for power distribution, such as the transformer, and which can enhance power supply reliability. <P>SOLUTION: This device includes: a sealant which has an air vent hole also serving as a mortar filling checking hole, and which is arranged on leveling concrete; a precast concrete slab placed on the sealant; and mortar which is infilled between the levelling concrete and a bottom surface of the precast concrete slab. The precast concrete slab is provided with a box release portion which also serves as a mortar charging hole, the air vent hole which also serves as the mortar filling checking hole, and a working hole for a height adjusting member. Filling conditions can be checked through the air vent hole which also serves as the mortar filling checking hole, and the equipment for the substation for the power distribution is installed and fixed on the precast concrete slab. <P>COPYRIGHT: (C)2010,JPO&INPIT

Description

本発明は、配電用変電所用設備、例えば変圧器のコンクリート基礎となるコンクリート版の敷設装置及びその敷設工法に関するものである。
The present invention relates to a distribution substation equipment, for example, a concrete plate laying apparatus which becomes a concrete foundation of a transformer, and a laying method thereof.

電力の屋外変圧器とは、一般に電力発電所から送電される電気を変圧し、住宅地へと供給する装置を指標する。
一般的には、1施設当たり2〜3基の変圧器によって電力を供給しているのが現状である。
ここで、変圧器の寿命は、一般に30年乃至40年と言われており、もって定期的な変圧器の交換が必要となっている。しかして、通常、その交換の際には、屋外変圧器は、工場で製造された後、現地(屋外)の敷設現場に設置されるものとなる。
An electric power outdoor transformer generally refers to a device that transforms electricity transmitted from a power plant and supplies it to a residential area.
In general, power is supplied by 2 to 3 transformers per facility.
Here, it is generally said that the lifetime of a transformer is 30 to 40 years, and therefore it is necessary to replace the transformer regularly. Therefore, normally, when the replacement is performed, the outdoor transformer is manufactured at a factory and then installed at a local (outdoor) laying site.

そして、当該変圧器の設置については、住宅地の近傍位置に設置しなければならず、しかも非常に狭い場所に設置されている場合が多いなどの設置に関する制約条件が多々ある。
さらに、構造の安定性をはかる上でコンクリート基礎などの剛性の高い構造物上に設置する必要があり、もって、前記変圧器の取り替えに際しても、従来このコンクリート基礎の張り替え作業が必須条件となっている。
And about the installation of the said transformer, there are many restrictions on installation, such as having to install in the vicinity of a residential area, and being installed in a very narrow place in many cases.
Furthermore, it is necessary to install on a rigid structure such as a concrete foundation in order to ensure the stability of the structure. Therefore, when replacing the transformer, it is necessary to replace the concrete foundation in the past. Yes.

よって、従来では、前記屋外に設置される変圧器の取り替えおよび新設(又は増設)工事においては、必ず前記のコンクリート基礎についても張り替え作業あるいは新設作業を現場打ちして行わざるを得ないものであった。
すなわち、例えば、前記変圧器の取り替え作業に際しては、現場打ちした既設コンクリート基礎の強度が経年変化により、現在の所定基準を満たしていないことなどが考えられ、新たにコンクリート基礎を製作しなければならないのが現状だったのである。
Therefore, conventionally, in the replacement and new construction (or expansion) of the transformer installed outdoors, the above-mentioned concrete foundation must be reworked or newly constructed on site. It was.
That is, for example, when replacing the transformer, it is considered that the strength of the existing concrete foundation cast on site does not meet the current predetermined standards due to secular change, and a new concrete foundation must be manufactured. That was the current situation.

また、変圧器は、前述の通り、住宅地の近傍位置で、しかも非常に狭い場所に設置されている場合が多いなどの制約条件が多々あるため、別の位置に変圧器を設置することが困難であり、元の位置での撤去作業や据付作業を行わざるを得ず、少なくとも約2ヶ月間の電力停止期間を設けなければならなかった。
一方、スムーズで正確な電力供給を図るとの観点からは、変圧器の取り替え中は、残された変圧器で当該地域の電力供給をまかなわなくてはならないとの課題もある。
In addition, as mentioned above, there are many restrictions such as the fact that the transformer is often located in a very narrow place in the vicinity of the residential area, so it is possible to install the transformer in another position. It was difficult, and it was necessary to carry out removal work and installation work at the original position, and had to provide a power outage period of at least about two months.
On the other hand, from the viewpoint of providing a smooth and accurate power supply, there is also a problem that during the replacement of the transformer, the remaining power supply must cover the power supply in the area.

そして、取り替え中のバックアップシステムの確保や当該地域の停電に対するリスク回避システムの要請から鑑みて、いわゆる変圧器の取替期間はできるだけ短くしたいのが実情である。
よって、これらのことから、変圧器基礎の取替工事には、工期短縮および施工性を考慮した施工法の開発が要望されていた。
In view of securing a backup system during replacement and a request for a risk avoidance system for a power outage in the area, it is actually desirable to make the so-called transformer replacement period as short as possible.
Therefore, for the replacement work of the transformer foundation, there has been a demand for the development of a construction method in consideration of shortening the construction period and workability.

前述のように、現場打ちの従来工法では、場所打ちRC工法が主流であったが、当該現場打ち工法では、型枠の設置作業に1日を要し、鉄筋の組立に2日を要し、コンクリート打設に1日を要し、コンクリートの養生作業に7日を要する工程であるため、全体として少なくとも約12日間の作業期間が必要とされている。
一方、いわゆるプレキャスト工法では、現場での施工とは切り離して版の製作が可能なため、あらかじめ工場で製作したコンクリート製プレキャスト版の現場への搬入、そして、搬入したプレキャスト版の据付け作業、及びモルタルの充填作業、さらには養生作業を含め約1日で完了するものとなっている。
その結果、従来の場所打ちRC工法に比べて、約10日以上の工期短縮が可能なのである。
As mentioned above, the cast-in-place RC method was the mainstream in the conventional on-site method, but in this on-site method, it took 1 day to install the formwork and 2 days to assemble the rebar. In addition, since it takes 1 day for concrete placement and 7 days for concrete curing work, a work period of at least about 12 days is required as a whole.
On the other hand, with the so-called precast method, it is possible to produce plates separately from on-site construction, so the concrete precast plate produced in the factory in advance, the installation work of the precast plate carried in, and mortar It can be completed in about one day including filling work and curing work.
As a result, the construction period can be shortened by about 10 days or more compared with the conventional cast-in-place RC method.

さらに、高強度コンクリートとPC構造の最適な組合せにより、いわゆるプレキャスト化された版を用いることが出来、もって工期短縮・高品質・高耐久性を有する変圧器用基礎を提供できるものである。
また、変圧器基礎プレキャストPC版は、電力停止期間を大幅に短縮でき、電力供給信頼度の向上を図ることができる。
特開平7−54354号公報
Furthermore, by using an optimal combination of high-strength concrete and PC structure, a so-called precast plate can be used, thereby providing a transformer foundation having a shortened construction period, high quality, and high durability.
In addition, the transformer basic precast PC version can greatly shorten the power outage period and improve the power supply reliability.
Japanese Unexamined Patent Publication No. 7-54354

かくして本発明は、前記従来の課題を解消するために創案されたものであって、いわゆる高強度のコンクリートとPC構造の組合せによりプレキャスト化されたコンクリート版を変圧器などの配電用変電所用設備基礎に用いることで前記基礎の高品質及び高耐久性を保証し、かつ、基礎形成に際し、その工期短縮が大幅に行え、もって変圧器再設置などによる電力停止期間を大幅に短縮でき、かつ、電力供給信頼度の向上が図れる、例えば変圧器など配電用変電所用設備基礎の敷設装置及びその敷設工法を提供することを目的とするものである。
Thus, the present invention was devised in order to solve the above-described conventional problems, and a concrete plate precasted by a combination of so-called high-strength concrete and a PC structure is used as a facility base for distribution substations such as transformers. It can be used to guarantee the high quality and high durability of the foundation, and when the foundation is formed, the construction period can be greatly shortened. An object of the present invention is to provide a laying apparatus for a distribution substation equipment base such as a transformer and a laying method thereof, which can improve supply reliability.

かくして、本発明は、
配電用変電所用設備の設置箇所に形成された均しコンクリートと、
該均しコンクリート上に、枠状に配置して取り付けられ、前記枠状に配置された際の枠内及び枠外に貫通するモルタル充填確認孔兼空気抜き孔を有するシール材と、
前記枠状に配置して取り付けられたシール材上に、裏面外周端部が密着して載置されるプレキャストコンクリート版と、
前記均しコンクリートと、前記シール材上に載置されたプレキャストコンクリート版の底面との間に充填されるモルタルと、
を備え、
前記プレキャストコンクリート版は、上下面に向けて貫通する前記モルタルの投入口兼箱抜け部、モルタル充填確認孔兼空気抜き孔、及びプレキャストコンクリート版の敷設高さ調整部材用作業孔、を有し、
前記モルタルの投入口兼箱抜け部より前記モルタルが充填可能とされると共に、該充填状況を前記シール材及びプレキャストコンクリート版のモルタル充填確認孔兼空気抜き孔より確認可能とされ、前記プレキャストコンクリート版の敷設高さ調整部材用作業孔に取り付けた高さ調整部材を操作して敷設高さが調節可能とされ、
前記高さ調節とモルタル充填終了後に、前記モルタル充填確認孔兼空気抜き孔を塞ぎ、前記投入口兼箱抜け部の凹部を利用して配電用変電所用設備の前記プレキャストコンクリート版への設置固定を行う、
ことを特徴とし、
または、
工場で予め製造した配電用変電所用設備の基礎となるプレキャストコンクリート版を、予め均しコンクリートが打設された敷設現場に運搬し、
前記プレキャストコンクリート版は、上下面に貫通する投入口兼箱抜け部、上下面に貫通するモルタル充填確認孔兼空気抜き孔、上下面に貫通するプレキャストコンクリート版の敷設高さ調整部材用作業孔を有し、
前記均しコンクリート上に、前記プレキャストコンクリート版の外周端と当接する様枠状にシール材を取り付け、
前記シール材には、複数個所において前記枠状に配置された際の枠内及び枠外に貫通するモルタル充填確認孔兼空気抜き孔を設けてなり、
次いで、前記枠状に取り付けたシール材上に前記プレキャストコンクリート版を載置し、
前記敷設高さ調整部材用作業孔に取り付けた高さ調整部材を操作して敷設高さを調整すると共に、前記投入口兼箱抜け部からモルタルを投入して、前記シール材及びコンクリート版のモルタル充填確認孔兼空気抜き孔から充填状態を確認しつつ、前記枠状をなすシール材内にモルタルを充填し、
充填後、モルタルの養生を行った後、プレキャストコンクリート版上に配電用変電所用設備を設置する、
ことを特徴とし、
または、
前記モルタルは、超速硬性高強度無収縮モルタルである、
ことを特徴とし、
または、
前記プレキャストコンクリート版は、複数に分割された版ユニットを前記敷設現場で接合し、最終形成した、
ことを特徴とするものである。
Thus, the present invention
Leveling concrete formed at the installation site of distribution substation equipment,
A sealing material having a mortar filling confirmation hole and an air vent hole penetrating into and out of the frame when arranged in a frame shape and attached on the leveled concrete,
On the sealing material arranged and attached in the frame shape, a precast concrete plate on which the outer peripheral end of the back surface is placed in close contact, and
Mortar filled between the leveled concrete and the bottom surface of the precast concrete plate placed on the sealing material,
With
The precast concrete slab has a mortar inlet / box opening, a mortar filling confirmation hole / air vent hole, and a working hole for a laying height adjusting member of the precast concrete slab penetrating toward the top and bottom surfaces,
The mortar can be filled from the mortar inlet / box exit, and the filling state can be confirmed from the mortar filling confirmation hole / air vent hole of the sealing material and the precast concrete plate. The laying height can be adjusted by operating the height adjusting member attached to the working hole for the laying height adjusting member,
After completion of the height adjustment and mortar filling, the mortar filling confirmation hole / air vent hole is closed, and the installation / fixing of the distribution substation equipment to the precast concrete plate is performed using the recess of the inlet / box removal part. ,
It is characterized by
Or
Transport the precast concrete slab, which is the foundation of the distribution substation equipment manufactured in advance at the factory, to the laying site where the leveled concrete is cast in advance.
The precast concrete slab has an inlet / box opening that penetrates the top and bottom surfaces, a mortar filling confirmation hole and air vent that penetrates the top and bottom surfaces, and a work hole for the laying height adjustment member of the precast concrete slab that penetrates the top and bottom surfaces. And
On the leveled concrete, a sealing material is attached in a frame shape so as to come into contact with the outer peripheral edge of the precast concrete plate,
The sealing material is provided with mortar filling confirmation holes and air vent holes penetrating into and out of the frame when arranged in the frame shape at a plurality of locations,
Next, the precast concrete plate is placed on the sealing material attached in the frame shape,
The height adjusting member attached to the working hole for the laying height adjusting member is operated to adjust the laying height, and mortar is thrown from the insertion port / box removal part, and the mortar for the sealing material and the concrete plate While confirming the filling state from the filling confirmation hole and air vent hole, filling the mortar into the frame-shaped sealing material,
After filling, after curing the mortar, install the substation equipment for distribution on the precast concrete plate.
It is characterized by
Or
The mortar is a super fast hard high strength non-shrink mortar,
It is characterized by
Or
The precast concrete plate is a final unit formed by joining a plurality of divided plate units at the laying site,
It is characterized by this.

発明による例えば変圧器など配電用変電所用設備基礎の敷設装置及びその敷設工法であれば、いわゆる高強度のコンクリートとPC構造の組合せによりプレキャスト化されたコンクリート版を変圧器などの配電用変電所用設備基礎に用いることで前記基礎の高品質及び高耐久性を保証し、かつ、基礎形成に際し、その工期短縮が大幅に行え、もって変圧器再設置などによる電力停止期間を大幅に短縮でき、かつ、電力供給信頼度の向上が図れるとの優れた効果を奏する。
According to the invention, for example, a transformer laying equipment for a distribution substation, such as a transformer, and its laying method, a so-called high strength concrete and PC structure precast cast concrete plate is used for a transformer substation for a distribution substation. By using it as a foundation, it guarantees the high quality and durability of the foundation, and at the time of foundation formation, the construction period can be greatly shortened, so that the power outage period due to transformer re-installation etc. can be greatly shortened, and There is an excellent effect that the power supply reliability can be improved.

以下本発明を図に示す実施例に基づいて説明する。
まず、図1を参照して、本発明による変圧器など配電用変電所用設備基礎の敷設装置1の構成につき説明する。
当該変圧器2など配電用変電所用設備基礎の敷設装置1は、配電用変電所用設備の設置箇所3に形成された均しコンクリート4を有する。
なお、当該均しコンクリート4の仕上げ状況(形成範囲など)により、後述するモルタル5の充填量が決定される。
Hereinafter, the present invention will be described based on embodiments shown in the drawings.
First, with reference to FIG. 1, it demonstrates per structure of the installation apparatus 1 of the equipment foundation for distribution substations, such as a transformer by this invention.
A distribution base 1 for distribution substation equipment such as the transformer 2 has leveling concrete 4 formed at the installation location 3 of the distribution substation equipment.
In addition, the filling amount of the mortar 5 mentioned later is determined by the finishing condition (formation range etc.) of the said leveling concrete 4. FIG.

すなわち、図1から理解されるように、例えば、均しコンクリート4の第1施工側(図1に示す均しコンクリート4上に取り付けられた枠状シール材6の手前側エリア)で、(内寸2.490m×2.620m×0.0235m(厚さ)=0.153m3=153リットル<13.5リットル×12袋)にロス分を考慮した1.1倍の170リットル(13袋)が消費され、第2施工側(図1で示す均しコンクリート4上に取り付けられた枠状シール材6の向こう側エリア)で[内寸2.490m×2.620m×0.026m(厚さ)=0.170m3=170リットル<13.5リットル×13袋]にロス分を考慮した1.1倍の190リットル(14袋)が消費されるものととなり、これを基準にモルタル充填量など充填状況の確認が行える。 That is, as understood from FIG. 1, for example, on the first construction side of the leveled concrete 4 (the front side area of the frame-shaped sealing material 6 attached on the leveled concrete 4 shown in FIG. 1), 2.490m x 2.620m x 0.0235m (thickness) = 0.153m 3 = 153 liters <13.5 liters x 12 bags) 1.1 times 170 liters (13 bags) taking into account the loss is consumed and the second construction side (Inside area of frame-shaped sealing material 6 mounted on leveled concrete 4 shown in FIG. 1) [Inner dimensions 2.490m x 2.620m x 0.026m (thickness) = 0.170m 3 = 170 liters <13.5 liters × 13 bags] consumes 1.1 times 190 liters (14 bags) considering the loss, and based on this, the filling status such as the mortar filling amount can be confirmed.

次に、図において符号6はシール材であり、前記のように、当該シール材6は、均しコンクリート4上に、例えば後述する方形状をなすプレキャストコンクリート版7にあわせて、そのプレキャストコンクリート版7の裏面外周端部に当接するよう略方形枠状に配置して取り付けられている。
ここで、シール材6の材質については、何ら制限されるものではないが、耐久性のある樹脂材料で構成するのが好ましい。
また、当該シール材6には、図に示すよう均しコンクリート4上に、略方形枠状に配置される際、枠内及び枠外に貫通するモルタル充填確認孔兼空気抜き孔8・・を複数有している。
Next, in the figure, reference numeral 6 denotes a sealing material. As described above, the sealing material 6 is placed on the leveled concrete 4 in accordance with, for example, a precast concrete plate 7 having a rectangular shape to be described later. 7 is arranged and attached in a substantially rectangular frame shape so as to contact the outer peripheral end of the back surface.
Here, the material of the sealing material 6 is not limited at all, but it is preferable that the sealing material 6 is made of a durable resin material.
Further, the seal material 6 has a plurality of mortar filling confirmation holes and air vent holes 8... Penetrating into and out of the frame when arranged in a substantially rectangular frame shape on the leveling concrete 4 as shown in the figure. is doing.

略方形枠状に配置して取り付けられたシール材6の上に、裏面外周端部が密着して、予め工場で製造されたプレキャストコンクリート版7が載置される。
ところで、本発明で何故プレキャストのコンクリート版7を使用するに至ったかであるが、該プレキャストコンクリート版7は、品質管理の行き届いたJIS工場で製作され、もって、高強度・高耐久性を有する非常に品質の高い安定した製品を連続的に、大量に供給することができるのである。
A precast concrete plate 7 manufactured in advance in a factory is placed on the sealing material 6 arranged and attached in a substantially square frame shape, with the outer peripheral end of the back surface being in close contact therewith.
By the way, the reason why the precast concrete slab 7 was used in the present invention was manufactured at a JIS factory with a good quality control, and thus has high strength and high durability. It is possible to continuously supply a large quantity of stable products with high quality.

すなわち、プレキャストのコンクリート版7としてプレストレスを与えたプレストレストコンクリートのコンクリート版7を使用する。このようにプレストレストコンクリートのコンクリート版7を使用することで、プレキャストのコンクリート版7が荷重を受けたとき、コンクリートに引張応力が発生しないか、または引張応力が制御されるため、一般の鉄筋(RC)コンクリート版より、引張応力によるひび割れ等を防ぐことができるのである。
また、輸送、据付時の振動により、プレキャストコンクリート版7自体が割れてしまうことがない。
このように、プレストレスを与えたプレキャストコンクリート版7を使用することにより、コンクリート版7について、高品質及び高耐久性が保証され、かつ、変圧器などの基礎形成に際して大幅な工期短縮が期待できるものとなる。
That is, a prestressed concrete concrete plate 7 prestressed is used as the precast concrete plate 7. By using the prestressed concrete slab 7 in this way, when the precast concrete slab 7 receives a load, tensile stress is not generated in the concrete or the tensile stress is controlled, so that a general rebar (RC ) Cracks due to tensile stress can be prevented from the concrete plate.
Moreover, the precast concrete plate 7 itself is not broken by vibration during transportation and installation.
Thus, by using the prestressed concrete plate 7 to which prestress is applied, high quality and high durability are assured for the concrete plate 7, and it can be expected that the construction period will be greatly shortened when forming a foundation such as a transformer. It will be a thing.

しかして該プレキャストコンクリート版7は、図から理解されるように、そのプレキャストコンクリート版7の四隅において、上下面に向けて貫通するモルタルの投入口兼箱抜け部9・・・が4つ設けられている。
また、プレキャストコンクリート版7の両端部側等にもモルタル充填確認孔兼空気抜き孔10・・・が複数設けられている。
さらに、例えば、モルタルの投入口兼箱抜け部9・・・の近傍位置には、プレキャストコンクリート版の敷設高さを調節するために使用される敷設高さ調整部材用作業孔11・・・が設けられている。
Thus, as can be understood from the figure, the precast concrete plate 7 is provided with four mortar insertion ports and box dropout portions 9... That penetrate through the precast concrete plate 7 toward the upper and lower surfaces. ing.
Also, a plurality of mortar filling confirmation holes / air vent holes 10... Are provided on both ends of the precast concrete plate 7.
Further, for example, in the vicinity of the mortar inlet / box opening 9 ..., there are laying height adjusting member working holes 11 ... used for adjusting the laying height of the precast concrete plate. Is provided.

しかして、前記均しコンクリート4と、前記シール材6上に載置されたプレキャストコンクリート版7の底面との間には、前記モルタル投入口兼箱抜け部9からモルタル5が充填されるものとなる。
そして、モルタル5の充填状況は前記シール材6及びプレキャストコンクリート版7のモルタル充填確認孔兼空気抜き孔8、10より確認でき、前記プレキャストコンクリート版7の敷設高さ調整部材用作業孔11に取り付けた高さ調整部材13を操作して、プレキャストコンクリート版7の敷設高さが調節される。
Thus, between the leveled concrete 4 and the bottom surface of the precast concrete plate 7 placed on the sealing material 6, the mortar 5 is filled from the mortar inlet / box exit 9. Become.
And the filling condition of the mortar 5 can be confirmed from the mortar filling confirmation hole / air venting holes 8 and 10 of the sealing material 6 and the precast concrete plate 7, and the mortar 5 is attached to the laying height adjusting member working hole 11 of the precast concrete plate 7. The height adjusting member 13 is operated to adjust the laying height of the precast concrete plate 7.

前記高さ調節とモルタル充填終了後、養生後に、前記モルタル充填確認孔兼空気抜き孔8,10が塞がれ、前記投入口兼箱抜け部9の凹部が利用されて配電用変電所用設備、例えば変圧器2の前記プレキャストコンクリート版7への設置固定が行われるのである。
以上において、次に本発明による敷設工法の構成の詳細を説明すると、まず、配電用変電所用設備、例えば変圧器2の基礎を形成する部材となる工場で予め製造されたプレキャストコンクリート版7を、予め均しコンクリート4が打設されてなる敷設現場に運搬する。
運搬の方法に関しては何ら限定されないが、一般的には、例えばトレーラ等の専用運搬車両によって工場から現場へ運搬され、当該トレーラからはクレーンなどによって、プレキャストコンクリート版7が現場の敷設箇所に載置される。
After completion of the height adjustment and mortar filling, after curing, the mortar filling confirmation hole / air vent holes 8, 10 are closed, and the recess of the inlet / box exit 9 is utilized to provide power distribution substation equipment, for example, The installation and fixing of the transformer 2 to the precast concrete plate 7 is performed.
In the above, the details of the construction of the laying method according to the present invention will be described next. First, the precast concrete plate 7 pre-manufactured in the factory that will be a member forming the foundation of the transformer 2 for distribution substation equipment, for example, It is transported to the laying site where the leveled concrete 4 is cast in advance.
The method of transportation is not limited at all, but in general, it is transported from the factory to the site by a dedicated transport vehicle such as a trailer, and the precast concrete plate 7 is placed on the site laying site by a crane or the like. Is done.

このプレキャストコンクリート版7には、予め、上下面に貫通する投入口兼箱抜け部9、上下面に貫通するモルタル充填確認孔兼空気抜き孔10、上下面に貫通するプレキャストコンクリート版7の敷設高さ調整部材用作業孔11が設けられていることはすでに説明した。 The precast concrete plate 7 is preliminarily provided with an inlet / box removal portion 9 penetrating the upper and lower surfaces, a mortar filling confirmation hole / air vent hole 10 penetrating the upper and lower surfaces, and a laying height of the precast concrete plate 7 penetrating the upper and lower surfaces. As described above, the adjustment member working hole 11 is provided.

ところで、前記敷設現場には、あらかじめ均しコンクリート4が打設されており、その上には方形枠状にシール材6が取り付けられている(図4参照)。
このシール材6についても、長手方向の複数個所において前記方形枠状に配置された際の枠内及び枠外に貫通するモルタル充填確認孔兼空気抜き孔8が複数個を設けられていることすでに説明した通りである。
そして、このシール材6は、前記プレキャストコンクリート版7の外周端と当接する様方形枠状に取り付けるものとする。
この様に取り付けられたシール材6上に前記プレキャストコンクリート版7を載置する(図5参照)。この載置方法についてもなんら限定されないが、通常重機のクレーンを使用して行われる。
By the way, the leveling concrete 4 is cast in advance at the laying site, and the sealing material 6 is attached in a rectangular frame shape thereon (see FIG. 4).
As described above, the sealing material 6 is also provided with a plurality of mortar filling confirmation holes and air vent holes 8 penetrating into and out of the frame when arranged in the rectangular frame shape at a plurality of locations in the longitudinal direction. Street.
The sealing material 6 is attached in a rectangular frame shape so as to come into contact with the outer peripheral end of the precast concrete plate 7.
The precast concrete plate 7 is placed on the sealing material 6 attached in this way (see FIG. 5). The mounting method is not limited at all, but is usually performed using a heavy-duty crane.

そして、このプレキャストコンクリート版7の載置において、あらかじめ設けられた敷設高さ調整部材用作業孔11に高さ調整部材13、例えば長尺ボルトで構成された部材などを操作し、プレキャストコンクリート版7の敷設高さや水平度などを調整する(図6参照)。
その後、投入口兼箱抜け部9からモルタル5を投入するのであるが、前記シール材6及びコンクリート版7のモルタル充填確認孔兼空気抜き孔8,10からモルタルの充填状態を確認しつつ、方形枠状をなすシール材6内の空間にモルタル5を充填する(図7参照)。
When the precast concrete plate 7 is placed, the precast concrete plate 7 is operated by operating a height adjusting member 13, for example, a member made of a long bolt, in the work hole 11 for a laying height adjusting member provided in advance. Adjust the laying height, levelness, etc. (see Fig. 6).
Thereafter, the mortar 5 is introduced from the inlet / box exit 9, while the mortar filling confirmation holes and air vent holes 8, 10 of the sealing material 6 and the concrete plate 7 are being confirmed while checking the mortar filling state. A mortar 5 is filled into a space in the sealing material 6 having a shape (see FIG. 7).

ここで、充填確認の方法につき詳しく説明する。
ここで、前記したように、シール材6は略長方形をなす枠状に取り付けられている。なお、該長方形をなす枠の長手方向略中間位置など、長手方向の一定間隔をあけた位置に、前記長方形の枠内を細かく仕切るように、シール材6を取り付けることもある。これは充填を良好に行うためでもある。
そして、例えば、この中間に位置するシール材6を境にして、一応、図8において下側を最初にモルタル5を充填する第1施工部、上側を次にモルタル5を充填する第2施工部とする。
Here, a method for confirming filling will be described in detail.
Here, as described above, the sealing material 6 is attached in a frame shape having a substantially rectangular shape. In addition, the sealing material 6 may be attached so that the inside of the rectangular frame is finely divided at a position spaced apart in the longitudinal direction, such as a substantially intermediate position in the longitudinal direction of the rectangular frame. This is also for good filling.
Then, for example, with the sealing material 6 located in the middle as a boundary, in FIG. 8, the first construction portion that first fills the mortar 5 on the lower side, and the second construction portion that fills the mortar 5 on the upper side. And

まず、下側に位置するプレキャストコンクリート版7に設けられたモルタル5の投入口兼箱抜け部9−1からモルタル5を投入する。
ここで、モルタル5の累積投入量が例えば、約27.0リットルに達したところで、シール材6に形成されたモルタル充填確認孔兼空気抜き孔8−1からモルタル5が漏れだす(図8参照)。よって、この漏れだしを確認することにより、隅部の充填が確認できる。そして、この部分も充填確認後は、モルタル充填確認孔兼空気抜き孔8−1を閉塞する。
First, the mortar 5 is thrown from the mortar 5 charging opening / box removal part 9-1 provided in the precast concrete plate 7 located on the lower side.
Here, when the cumulative input amount of the mortar 5 reaches, for example, about 27.0 liters, the mortar 5 leaks from the mortar filling confirmation hole / air vent hole 8-1 formed in the sealing material 6 (see FIG. 8). Therefore, the filling of the corner can be confirmed by confirming this leakage. And after this part also confirms filling, the mortar filling confirmation hole / air vent hole 8-1 is closed.

次いで、モルタルの累積投入量が例えば、約40.5リットルに達したところで、シール材6に形成されたモルタル充填確認孔兼空気抜き孔8−2からモルタル5が漏れだす。そして、この漏れだしが確認されると、かかる周辺箇所の充填が確認できるものとなる。そして、この充填確認後は、モルタル充填確認孔兼空気抜き孔8−2を閉塞する。
次に、モルタルの累積投入量が例えば、約54.0リットルに達したところで、シール材6に形成されたモルタル充填確認孔兼空気抜き孔8−3、8−4からモルタル5が漏れだす。
Next, when the accumulated amount of mortar reaches, for example, about 40.5 liters, the mortar 5 leaks from the mortar filling confirmation hole / air vent hole 8-2 formed in the sealing material 6. And if this leak is confirmed, filling of this peripheral part can be confirmed. Then, after this filling confirmation, the mortar filling confirmation hole / air vent hole 8-2 is closed.
Next, when the accumulated amount of mortar reaches, for example, about 54.0 liters, the mortar 5 leaks from the mortar filling confirmation holes / air vent holes 8-3 and 8-4 formed in the sealing material 6.

そして、この箇所から漏れだしたことにより、かかるところまでモルタル5が充填したことを確認できる。なお、充填確認後は、モルタル充填確認孔兼空気抜き孔8−3、8−4をやはり閉塞する。
さらに、モルタル5の累積投入量が例えば、約108.0リットルに達したところで、シール材6の反対側隅部に形成されたモルタル充填確認孔兼空気抜き孔8−5からモルタルが漏れだす。
And since it leaked from this location, it can confirm that the mortar 5 was filled to such a place. In addition, after filling confirmation, the mortar filling confirmation hole and air vent holes 8-3 and 8-4 are also closed.
Furthermore, when the cumulative input amount of the mortar 5 reaches, for example, about 108.0 liters, the mortar leaks from the mortar filling confirmation hole / air vent hole 8-5 formed at the opposite corner of the sealing material 6.

そして、かかる箇所から漏れだしたことにより、さらにはモルタルの投入口兼箱抜け部9−2からもモルタル5が視認できたことにより、モルタルの投入口兼箱抜け部9−2の箇所からモルタル充填確認孔兼空気抜き孔8−5の箇所に至るまでのモルタル充填が確認できる。そして、充填確認後は、モルタル充填確認孔兼空気抜き孔8−5を閉塞する。 When the mortar 5 is visible from the mortar inlet / box exit 9-2 due to leakage from the location, the mortar is inserted from the mortar inlet / box exit 9-2. The mortar filling up to the location of the filling confirmation hole / air vent hole 8-5 can be confirmed. And after filling confirmation, the mortar filling confirmation hole and air vent hole 8-5 is obstruct | occluded.

次に、モルタルの投入口を、モルタルの投入口兼箱抜け部9−1からモルタルの投入口兼箱抜け部9−2に変更する。
そして、モルタルの累積投入量が例えば、約121.5リットルに達したところで、今度はモルタル充填確認孔兼空気抜き孔8−6、8−7からモルタルが漏れだす。そして、この箇所から漏れだしたことにより、かかる周辺箇所にモルタルが充填したことを確認するものとなる。なお、やはり充填確認後は、モルタル充填確認孔兼空気抜き孔8−6、8−7を閉塞する。
Next, the mortar inlet is changed from the mortar inlet / box exit 9-1 to the mortar inlet / box exit 9-2.
Then, when the accumulated amount of mortar reaches, for example, about 121.5 liters, the mortar leaks from the mortar filling confirmation holes and air vent holes 8-6 and 8-7. And since it leaked from this location, it will confirm that the mortar filled the peripheral location. After filling is confirmed, the mortar filling confirmation hole / air vent holes 8-6 and 8-7 are closed.

さらに、モルタルの累積投入量が例えば約135.0リットルに達したところで、モルタル充填確認孔兼空気抜き孔8−8からモルタルが漏れだす。かかる漏れだしが確認されたことにより、ここまでのモルタル充填が確認できる。そして、充填確認後は、モルタル充填確認孔兼空気抜き孔8−8を閉塞する。
次いで、モルタルの累積投入量が例えば約148.5リットルに達したところで、モルタル充填確認孔兼空気抜き孔8−9からモルタルが漏れだし、該漏れだしが確認されると、この隅部までモルタル5が充填されたことが確認できる。
そして、充填確認後は、モルタル充填確認孔兼空気抜き孔8−9を閉塞する。
Further, when the accumulated amount of mortar reaches, for example, about 135.0 liters, the mortar leaks from the mortar filling confirmation hole / air vent hole 8-8. By confirming such leakage, mortar filling so far can be confirmed. Then, after the filling confirmation, the mortar filling confirmation hole / air vent hole 8-8 is closed.
Next, when the accumulated amount of mortar reaches, for example, about 148.5 liters, the mortar leaks from the mortar filling confirmation hole / air vent hole 8-9. When the leakage is confirmed, the mortar 5 is filled up to this corner. It can be confirmed.
Then, after the filling confirmation, the mortar filling confirmation hole / air vent hole 8-9 is closed.

また、最終的に、プレキャストコンクリート版7の上面より各モルタル充填確認孔兼空気抜き孔10―1、10−2、10−3からモルタル充填状況を確認して、第1施工側の充填が完了する。
次に、第2施工側についても同様の手順によりモルタル充填の確認を行い、モルタル充填を完了するものとなる。
Finally, the mortar filling confirmation hole is confirmed from the top surface of the precast concrete plate 7 through the mortar filling confirmation / air vent holes 10-1, 10-2, 10-3, and the filling on the first construction side is completed. .
Next, the mortar filling is confirmed on the second construction side by the same procedure, and the mortar filling is completed.

ところで、モルタル充填確認孔兼空気抜き孔8,10は、モルタル投入口兼箱抜き部9からモルタル5が投入された際に、前記したモルタル9の充填状況を確認するとの役割のほか、プレキャストコンクリート版7とシール材6との間の空気を外部に逃すとの役割をも果たすものとなる。
この様に、充填した後、モルタルの養生が短期間で行われ、その後、プレキャストコンクリート版7上に配電用変電所用設備、すなわち変圧器2が設置されることとなる。
By the way, the mortar filling confirmation hole / air venting holes 8, 10 have a role of confirming the filling state of the mortar 9 when the mortar 5 is introduced from the mortar inlet / box removal part 9. It also plays the role of letting the air between 7 and the sealing material 6 escape to the outside.
Thus, after filling, the curing of the mortar is performed in a short period of time, and then the distribution substation equipment, that is, the transformer 2 is installed on the precast concrete plate 7.

ここで、本発明で使用されるモルタル5につき説明する。
本発明に使用するモルタル5は、いわゆる超速硬性無収縮モルタルであることが望ましい。超速硬性無収縮モルタルは,短時間での強度発現が可能であるため、本発明における配電用変電所用変圧器基礎の敷設に際し、大幅な工期短縮を図ることができる。また,プレキャスト版とベースコンクリートの間の狭小部分に充填するため優れた流動性と保持時間の確保も必要となる。本発明における超速硬性無収縮モルタルは、優れた流動性を約30分間確保できるように改良を行ったことで確実な施工性が得られるのである。
ここで、前述した超速硬性無収縮モルタルは、その強度発現性から可使時間が短く、実施工において可使時間を考慮した工程、器具・人員の配置を行う必要がある。
Here, the mortar 5 used in the present invention will be described.
It is desirable that the mortar 5 used in the present invention is a so-called super fast hard non-shrink mortar. Since the super-hard hard non-shrink mortar can develop strength in a short time, the construction period can be greatly shortened when laying the transformer foundation for distribution substation in the present invention. In addition, it is necessary to secure excellent fluidity and holding time in order to fill the narrow part between the precast plate and the base concrete. The ultrafast hard non-shrinking mortar according to the present invention can provide reliable workability by improving so that excellent fluidity can be secured for about 30 minutes.
Here, the ultrafast hard non-shrinkable mortar described above has a short pot life due to its strength development, and it is necessary to perform a process, arrangement of equipment and personnel in consideration of the pot life in the construction work.

しかして、超速硬性無収縮モルタルの充填についての人員配置及び作業時間について概略的に説明すると、現場における外気温10℃を想定した状況において、超速硬性無収縮モルタルの練り混ぜに例えば4名、材料投入に例えば4名、該超速硬性無収縮モルタルの投入に例えば2名、計10名の人員を配置することが考えられる。そして、作業時間は15分以内であることが、該超速硬性無収縮モルタルの流動性試験結果から望ましいものとなる。
ところで、例えば大型の変圧器2など設備の場合、これに合わせた大型の基礎の形成が必要となるが、かかる場合は、プレキャストコンクリート版7をあらかじめ工場において分割した複数の版ユニット14・・・として形成しておき、これらを前記敷設現場で接合し、最終形成することも出来る。
The outline of the personnel allocation and working time for filling the super fast hard non-shrink mortar will be described. In the situation assuming an outside air temperature of 10 ° C., for example, 4 people are mixed in the super fast hard non-shrink mortar. For example, it is conceivable to arrange a total of 10 people, for example, 4 people for the introduction and 2 people for the introduction of the super-hard hard non-shrink mortar. The working time is preferably within 15 minutes from the results of the fluidity test of the ultrafast hard no-shrink mortar.
By the way, for example, in the case of equipment such as a large transformer 2, it is necessary to form a large foundation corresponding to this. In such a case, a plurality of plate units 14 in which the precast concrete plate 7 is divided in advance in the factory. It is possible to form these as follows, and join these at the laying site to form a final product.

すなわち、分割した状態のコンクリート版ユニット14を各々小分けした状態で前記敷設現場に搬入し、それらを敷設現場にて、例えばポストテンション工法などを採用し、一体化させるのである。 That is, the divided concrete plate units 14 are carried into the laying site in a state of being divided into small portions, and they are integrated at the laying site by using, for example, a post-tension method.

その具体例を図10、図11に基づいて説明する。
施工性条件(敷設条件)から,プレキャストコンクリート版7には、重量および寸法制限が生じることがある。
例えば、運搬上の制限からは,プレキャストコンクリート版7の幅は2.5m以下に制限される。
敷設の条件にもよるが,一般的な敷設箇所では、大型クレーン車を据えて敷設することはきわめて困難な場合が多いと考えられる。
そのような場合には,コンクリート版7を2分割あるいは3分割にして,敷設現場の現地で接合する方法が考えられるのである。
Specific examples thereof will be described with reference to FIGS.
Due to workability conditions (laying conditions), the precast concrete slab 7 may have weight and size restrictions.
For example, due to transportation restrictions, the width of the precast concrete slab 7 is limited to 2.5 m or less.
Although it depends on the laying conditions, it is considered that it is often very difficult to lay a large crane vehicle at a general laying location.
In such a case, it is possible to divide the concrete plate 7 into two or three parts and join them at the site of the installation site.

ここで、プレキャストコンクリート版7の接合方法には,プレストレスを用いたポストテンション方式による接合が工程・耐力・耐久性の点から優れている。
しかして、接合方法としては,図10に示すように、分割したプレキャスト版ユニット14・・・を仮支持点15・・・上でレベリングし,予めダクト(シース)などでプレキャスト版ユニット14・・・に穴16を開けておき,その穴16の中にPC鋼材(例えば、PC鋼棒)17を挿入する。
その作業中に、図11に示すようにプレキャスト版ユニット14,14の間を超速硬無収縮のモルタル5で充填し、養生させる。
Here, as a method for joining the precast concrete slab 7, joining by a post-tension method using prestress is excellent from the viewpoint of process, proof stress, and durability.
As a joining method, as shown in FIG. 10, the divided precast plate units 14... Are leveled on the temporary support points 15..., And the precast plate units 14. A hole 16 is made in the hole 16 and a PC steel material (for example, a PC steel rod) 17 is inserted into the hole 16.
During the operation, as shown in FIG. 11, the space between the precast plate units 14 and 14 is filled with a mortar 5 which is ultrafast and non-shrinkable and cured.

その後,両端にねじ切りしたPC鋼棒17に支圧板18とナット19を挿入する。そして、PC鋼棒17の片側に緊張ジャッキ(図示せず)をセットし,ポンプ(図示せず)にて緊張を行う。
所定の緊張力に達したのを確認し,PC鋼棒17に伸びが生じた状態で,ナット19を締め込んでPC鋼棒17を定着する。それによって,分割したプレキャスト版ユニット14・・・にプレストレス(圧縮応力)を導入でき、一枚のプレキャストコンクリート版7を形成できる。
Thereafter, a support plate 18 and a nut 19 are inserted into the PC steel rod 17 threaded at both ends. Then, a tension jack (not shown) is set on one side of the PC steel rod 17, and tension is performed by a pump (not shown).
After confirming that the predetermined tension force has been reached, the PC steel rod 17 is fixed by tightening the nut 19 with the PC steel rod 17 stretched. Thereby, prestress (compression stress) can be introduced into the divided precast plate units 14..., And a single precast concrete plate 7 can be formed.

ここで、前記分割したコンクリート版ユニット14の現場組立、現場結合の施工手順は,(1)複数のプレキャスト版14・・・の現場搬入、(2)複数枚のプレキャスト版ユニット14の設置(所定位置に仮置き,位置・高さ調整:約2時間)、(3)PC鋼棒17の挿入(約30分)、(4)版ユニット14・・・の間に超速硬無収縮モルタル5の充填(約30分)、(5)超速硬無収縮モルタル5の養生(3時間)、(6)PC鋼棒17の緊張(2時間)、(7)組み立てたプレキャストコンクリート版7と均しコンクリート4との間を超速硬無収縮モルタル5で充填(約1時間)、(8)超速硬無収縮モルタル5の養生(3時間)となり,施工時間は合計で約12時間となり,前記のように分割版とした場合でも約1日足らずで施工完了することが出来るのである。
Here, the construction procedures for the on-site assembly and on-site coupling of the divided concrete plate units 14 are as follows: (1) On-site delivery of a plurality of precast plates 14... (2) Installation of a plurality of precast plate units 14 (predetermined Temporary placement at position, position / height adjustment: about 2 hours), (3) insertion of PC steel rod 17 (about 30 minutes), (4) super fast hard non-shrink mortar 5 between plate units 14. Filling (approx. 30 minutes), (5) Curing of super fast hard non-shrink mortar 5 (3 hours), (6) Tension of PC steel rod 17 (2 hours), (7) Precast concrete plate 7 assembled and leveled concrete 4 is filled with super fast hard non-shrink mortar 5 (about 1 hour), (8) super fast hard non-shrink mortar 5 is cured (3 hours), and the total construction time is about 12 hours. Construction in less than a day even when divided versions Ryosuru it is that can be.

本発明による配電用変電所用設備のコンクリート基礎敷設装置の概略構成を説明する説明図(その1)である。It is explanatory drawing (the 1) explaining schematic structure of the concrete foundation laying apparatus of the equipment for distribution substations by this invention. 本発明によって設置された配電用変電所用変圧器を示す説明図である。It is explanatory drawing which shows the transformer for distribution substations installed by this invention. 本発明による配電用変電所用設備のコンクリート基礎敷設装置の概略構成を説明する説明図(その2)である。It is explanatory drawing (the 2) explaining schematic structure of the concrete foundation laying apparatus of the equipment for distribution substations by this invention. 本発明による配電用変電所用設備のコンクリート基礎敷設工法の工程を説明する説明図(その1)である。It is explanatory drawing (the 1) explaining the process of the concrete foundation laying construction method of the equipment for distribution substations by this invention. 本発明による配電用変電所用設備のコンクリート基礎敷設工法の工程を説明する説明図(その2)である。It is explanatory drawing (the 2) explaining the process of the concrete foundation laying method of the distribution substation equipment by this invention. 本発明による配電用変電所用設備のコンクリート基礎敷設工法の工程を説明する説明図(その3)である。It is explanatory drawing (the 3) explaining the process of the concrete foundation laying construction method of the equipment for distribution substations by this invention. 本発明による配電用変電所用設備のコンクリート基礎敷設工法の工程を説明する説明図(その4)である。It is explanatory drawing (the 4) explaining the process of the concrete foundation laying construction method of the equipment for distribution substations by this invention. 本発明による配電用変電所用設備のコンクリート基礎敷設工法の工程を説明する説明図(その5)である。It is explanatory drawing (the 5) explaining the process of the concrete foundation laying construction method of the equipment for distribution substations by this invention. 本発明による配電用変電所用設備のコンクリート基礎敷設工法の工程を説明する説明図(その6)である。It is explanatory drawing (the 6) explaining the process of the concrete foundation laying method of the distribution substation equipment by this invention. 分割した版ユニットを接合してプレキャストコンクリート版を形成する状態を説明する説明図(その1)である。It is explanatory drawing (the 1) explaining the state which joins the divided | segmented plate unit and forms a precast concrete plate. 分割した版ユニットを接合してプレキャストコンクリート版を形成する状態を説明する説明図(その2)である。It is explanatory drawing (the 2) explaining the state which joins the divided plate unit and forms a precast concrete plate.

符号の説明Explanation of symbols

1 敷設装置
2 変圧器
3 設置箇所
4 均しコンクリート
5 モルタル
6 シール材
7 プレキャストコンクリート版
8 モルタル充填確認孔兼空気抜き孔
9 モルタル投入口兼箱抜け部
10 モルタル充填確認孔兼空気抜き孔
11 敷設高さ調整部材用作業孔
12 クレーン
13 高さ調整部材
14 版ユニット
15 仮支点
16 穴
17 PC鋼材
18 支圧板
19 ナット
DESCRIPTION OF SYMBOLS 1 Laying apparatus 2 Transformer 3 Installation place 4 Leveling concrete 5 Mortar 6 Sealing material 7 Precast concrete plate 8 Mortar filling confirmation hole and air vent hole 9 Mortar inlet and box opening part 10 Mortar filling confirmation hole and air vent hole 11 Installation height Working hole for adjusting member 12 Crane 13 Height adjusting member 14 Plate unit 15 Temporary fulcrum 16 Hole 17 PC steel 18 Bearing plate 19 Nut

Claims (5)

配電用変電所用設備の設置箇所に形成された均しコンクリートと、
該均しコンクリート上に、枠状に配置して取り付けられ、前記枠状に配置された際の枠内及び枠外に貫通するモルタル充填確認孔兼空気抜き孔を有するシール材と、
前記枠状に配置して取り付けられたシール材上に、裏面外周端部が密着して載置されるプレキャストコンクリート版と、
前記均しコンクリートと、前記シール材上に載置されたプレキャストコンクリート版の底面との間に充填されるモルタルと、
を備え、
前記プレキャストコンクリート板は、上下面に向けて貫通する前記モルタルの投入口兼箱抜け部、モルタル充填確認孔兼空気抜き孔、及びプレキャストコンクリート版の敷設高さ調整部材用作業孔、を有し、
前記モルタルの投入口兼箱抜け部より前記モルタルが充填可能とされると共に、該充填状況を前記シール材及びプレキャストコンクリート版のモルタル充填確認孔兼空気抜き孔より確認可能とされ、前記プレキャストコンクリート版の敷設高さ調整部材用作業孔に取り付けた高さ調整部材を操作して敷設高さが調節可能とされ、
前記高さ調節とモルタル充填終了後に、前記モルタル充填確認孔兼空気抜き孔を塞ぎ、前記投入口兼箱抜け部の凹部を利用して配電用変電所用設備の前記プレキャストコンクリート版への設置固定を行う、
ことを特徴とする配電用変電所用設備の敷設装置。
Leveling concrete formed at the installation site of distribution substation equipment,
A sealing material having a mortar filling confirmation hole and an air vent hole penetrating into and out of the frame when arranged in a frame shape and attached on the leveled concrete,
On the sealing material arranged and attached in the frame shape, a precast concrete plate on which the outer peripheral end of the back surface is placed in close contact, and
Mortar filled between the leveled concrete and the bottom surface of the precast concrete plate placed on the sealing material,
With
The precast concrete plate has a mortar inlet and box drop-out portion penetrating toward the upper and lower surfaces, a mortar filling confirmation hole and air vent hole, and a precast concrete plate laying height adjustment member working hole,
The mortar can be filled from the mortar inlet / box removal part, and the filling state can be confirmed from the mortar filling confirmation hole and air vent hole of the sealing material and the precast concrete plate. The laying height can be adjusted by operating the height adjusting member attached to the working hole for the laying height adjusting member,
After completion of the height adjustment and mortar filling, the mortar filling confirmation hole / air vent hole is closed, and the installation / fixing of the distribution substation equipment to the precast concrete plate is performed using the recess of the inlet / box removal part. ,
A facility for laying equipment for distribution substations.
工場で予め製造した配電用変電所用設備の基礎となるプレキャストコンクリート版を、予め均しコンクリートが打設された敷設現場に運搬し、
前記プレキャストコンクリート版は、上下面に貫通する投入口兼箱抜け部、上下面に貫通するモルタル充填確認孔兼空気抜き孔、上下面に貫通するプレキャストコンクリート版の敷設高さ調整部材用作業孔を有し、
前記均しコンクリート上に、前記プレキャストコンクリート版の外周端と当接する様枠状にシール材を取り付け、
前記シール材には、複数個所において前記枠状に配置された際の枠内及び枠外に貫通するモルタル充填確認孔兼空気抜き孔を設けてなり、
次いで、前記枠状に取り付けたシール材上に前記プレキャストコンクリート版を載置し、
前記敷設高さ調整部材用作業孔に取り付けた高さ調整部材を操作して敷設高さを調整すると共に、前記投入口兼箱抜け部からモルタルを投入して、前記シール材及びコンクリート版のモルタル充填確認孔兼空気抜き孔から充填状態を確認しつつ、前記枠状をなすシール材内にモルタルを充填し、
充填後、モルタルの養生を行った後、プレキャストコンクリート版上に配電用変電所用設備を設置する、
ことを特徴とする配電用変電所用設備の基礎敷設工法。
Transport the precast concrete slab, which is the foundation of the distribution substation equipment manufactured in advance at the factory, to the laying site where the leveled concrete is cast in advance.
The precast concrete slab has an inlet / box opening that penetrates the top and bottom surfaces, a mortar filling confirmation hole and air vent that penetrates the top and bottom surfaces, and a work hole for the laying height adjustment member of the precast concrete slab that penetrates the top and bottom surfaces. And
On the leveled concrete, a sealing material is attached in a frame shape so as to come into contact with the outer peripheral edge of the precast concrete plate,
The sealing material is provided with mortar filling confirmation holes and air vent holes penetrating into and out of the frame when arranged in the frame shape at a plurality of locations,
Next, the precast concrete plate is placed on the sealing material attached in the frame shape,
The height adjusting member attached to the working hole for the laying height adjusting member is operated to adjust the laying height, and the mortar is introduced from the insertion port / box removal part, and the mortar for the sealing material and the concrete plate While confirming the filling state from the filling confirmation hole and air vent hole, filling the mortar into the frame-shaped sealing material,
After filling, after curing the mortar, install the substation equipment for distribution on the precast concrete plate.
A basic laying method for distribution substation equipment.
前記モルタルは、超速硬性高強度無収縮モルタルである、
ことを特徴とする請求項1記載の配電用変電所用設備の基礎敷設装置。
The mortar is a super fast hard high strength non-shrink mortar,
The basic laying apparatus for distribution substation equipment according to claim 1.
前記モルタルは、超速硬性高強度無収縮モルタルである、
ことを特徴とする請求項2記載の配電用変電所用設備の基礎敷設工法。
The mortar is a super fast hard high strength non-shrink mortar,
The foundation laying method of the equipment for distribution substations of Claim 2 characterized by the above-mentioned.
前記プレキャストコンクリート版は、複数に分割された版ユニットを前記敷設現場で接合し、最終形成した、
ことを特徴とする請求項2または請求項4記載の配電用変電所用設備の基礎敷設工法。

The precast concrete plate is a final unit formed by joining a plurality of divided plate units at the laying site,
The foundation laying method of the equipment for distribution substations of Claim 2 or Claim 4 characterized by the above-mentioned.

JP2008160419A 2008-06-19 2008-06-19 Concrete foundation laying equipment for distribution substation equipment and foundation laying method for distribution substation equipment Expired - Fee Related JP5110652B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP2008160419A JP5110652B2 (en) 2008-06-19 2008-06-19 Concrete foundation laying equipment for distribution substation equipment and foundation laying method for distribution substation equipment

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP2008160419A JP5110652B2 (en) 2008-06-19 2008-06-19 Concrete foundation laying equipment for distribution substation equipment and foundation laying method for distribution substation equipment

Publications (2)

Publication Number Publication Date
JP2010001634A true JP2010001634A (en) 2010-01-07
JP5110652B2 JP5110652B2 (en) 2012-12-26

Family

ID=41583564

Family Applications (1)

Application Number Title Priority Date Filing Date
JP2008160419A Expired - Fee Related JP5110652B2 (en) 2008-06-19 2008-06-19 Concrete foundation laying equipment for distribution substation equipment and foundation laying method for distribution substation equipment

Country Status (1)

Country Link
JP (1) JP5110652B2 (en)

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN104153610A (en) * 2014-08-22 2014-11-19 福建省电力勘测设计院 Modularization box type integral integrated electric control device for fuel gas power plant and installing method of modularization box type integral integrated electric control device
CN104631487A (en) * 2013-11-14 2015-05-20 宁夏中远天晟科技有限公司 Prefabricated foundation of combination box transformer substation with reactive compensation function
CN107268670A (en) * 2017-08-15 2017-10-20 中国能源建设集团江苏省电力设计院有限公司 A kind of 1000kV transforming plant main transformers basis
CN110952584A (en) * 2019-12-23 2020-04-03 广东顺德电力设计院有限公司 Transformer substation building structure with main transformer foundation connected with building foundation

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH0485418A (en) * 1990-07-26 1992-03-18 Tategu Sogo Shosha Futaba:Kk Construction panel
JPH0754354A (en) * 1993-08-20 1995-02-28 Nakamura Kensetsu Kk Precast concrete slab for foundation and construction method of foundation using this precast concrete slab
JPH07166558A (en) * 1993-12-13 1995-06-27 Shigeru Tsukahara Foundation member made of precast concrete
JPH09158216A (en) * 1995-12-07 1997-06-17 Toshiba Eng & Constr Co Ltd Construction method for installing large-sized machine
JPH11173107A (en) * 1997-12-08 1999-06-29 Toshiba Corp Soleplate of steam turbine, installation structure of steam turbine and uniaxial combined cycle plant

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH0485418A (en) * 1990-07-26 1992-03-18 Tategu Sogo Shosha Futaba:Kk Construction panel
JPH0754354A (en) * 1993-08-20 1995-02-28 Nakamura Kensetsu Kk Precast concrete slab for foundation and construction method of foundation using this precast concrete slab
JPH07166558A (en) * 1993-12-13 1995-06-27 Shigeru Tsukahara Foundation member made of precast concrete
JPH09158216A (en) * 1995-12-07 1997-06-17 Toshiba Eng & Constr Co Ltd Construction method for installing large-sized machine
JPH11173107A (en) * 1997-12-08 1999-06-29 Toshiba Corp Soleplate of steam turbine, installation structure of steam turbine and uniaxial combined cycle plant

Cited By (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN104631487A (en) * 2013-11-14 2015-05-20 宁夏中远天晟科技有限公司 Prefabricated foundation of combination box transformer substation with reactive compensation function
CN104153610A (en) * 2014-08-22 2014-11-19 福建省电力勘测设计院 Modularization box type integral integrated electric control device for fuel gas power plant and installing method of modularization box type integral integrated electric control device
CN107268670A (en) * 2017-08-15 2017-10-20 中国能源建设集团江苏省电力设计院有限公司 A kind of 1000kV transforming plant main transformers basis
CN110952584A (en) * 2019-12-23 2020-04-03 广东顺德电力设计院有限公司 Transformer substation building structure with main transformer foundation connected with building foundation
CN110952584B (en) * 2019-12-23 2021-04-16 广东顺德电力设计院有限公司 Transformer substation building structure with main transformer foundation connected with building foundation

Also Published As

Publication number Publication date
JP5110652B2 (en) 2012-12-26

Similar Documents

Publication Publication Date Title
DK2488338T3 (en) Process for the preparation of tower segment-concrete finished parts of a wind power installation tower and formwork unit for production of concrete finished parts
JP6041485B2 (en) Installation base
US9068320B2 (en) Mounting base
JP5110652B2 (en) Concrete foundation laying equipment for distribution substation equipment and foundation laying method for distribution substation equipment
JP4934779B2 (en) Boarding / exit structure and boarding / exiting method
WO2012081653A1 (en) Method of installing a mounting base
CN111733873A (en) Construction method of assembled subway station
WO2014189031A1 (en) Storage tank construction method
CN110656657A (en) Compressor foundation bolt installation method
KR101800790B1 (en) Echo replacing method of bearings without vibration, waste, noise, deformation
CZ190096A3 (en) Wall element for high-rise buildings and process for producing thereof
US20060248847A1 (en) Method for providing a pad to support heavy equipment
CN106436746A (en) Prefabricated box-type substation cement foundation
JP2014080824A (en) Method for constructing foundation structure by utilizing skeleton of existing structure, and foundation structure
JP2019078065A (en) Laying method of cantilever-type retaining wall
JP2018100488A (en) Base-isolation construction, base plate and method for construction of lower foundation member
CN205242695U (en) Take superimposed shear wall of keyway that shears
CN105442729A (en) Superimposed shear wall with shear-resistant key grooves and construction and manufacture method thereof
KR102570578B1 (en) A fast bridge bearing replacement method without safety accident dangerousness, civil complaints and structural damage
CN114808663B (en) Bridge widening structure and construction method thereof
JP4690590B2 (en) Foundation concrete board, tank support equipment and installation method
JP5544704B2 (en) Method for placing age-hardening material
Cunningham et al. Self-Aligning Structural Connection for Precast Concrete Wall Panels
Canto et al. Practical Assessment of Mass Concrete Construction for Wind Farm Projects in Remote Sites
JP2001182013A (en) Precast concrete reaction wall body for bridge and bridge support device using this wall body and installing method therefor

Legal Events

Date Code Title Description
A621 Written request for application examination

Free format text: JAPANESE INTERMEDIATE CODE: A621

Effective date: 20110304

A711 Notification of change in applicant

Free format text: JAPANESE INTERMEDIATE CODE: A711

Effective date: 20111129

A521 Written amendment

Free format text: JAPANESE INTERMEDIATE CODE: A821

Effective date: 20111129

A521 Written amendment

Free format text: JAPANESE INTERMEDIATE CODE: A523

Effective date: 20111222

A977 Report on retrieval

Free format text: JAPANESE INTERMEDIATE CODE: A971007

Effective date: 20120521

TRDD Decision of grant or rejection written
A01 Written decision to grant a patent or to grant a registration (utility model)

Free format text: JAPANESE INTERMEDIATE CODE: A01

Effective date: 20121004

A01 Written decision to grant a patent or to grant a registration (utility model)

Free format text: JAPANESE INTERMEDIATE CODE: A01

A61 First payment of annual fees (during grant procedure)

Free format text: JAPANESE INTERMEDIATE CODE: A61

Effective date: 20121004

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20151019

Year of fee payment: 3

R150 Certificate of patent or registration of utility model

Free format text: JAPANESE INTERMEDIATE CODE: R150

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

LAPS Cancellation because of no payment of annual fees